5.
WATER
QUALITY IMPACT ASSESSMENT
5.1.1
This Chapter details the current condition of the water
bodies within and around the Study Area, and describes the potential impacts
on water quality during the construction and operation stages of the proposed secondary
channels: MUP03, MUP04A, MUP04B, MUP05 and LMH01 (the Project). Mitigation
measures are proposed and the residual impacts after implementation of these
measures are evaluated.
5.2
Environmental Legislation, Policies, Standards and
Criteria
5.2.1
The Water Pollution Control
Ordinance (WPCO) (Cap.358) enacted in 1980 is the principal legislation controlling water
quality in Hong Kong along with Annexes 6 and 14 of the Technical Memorandum on
EIA Process (TM-EIA). Under the WPCO,
5.2.2 The other relevant guideline is the Practice Note for Professional Persons (ProPECC Note) PN 1/94 on Construction Site Drainage which provide guidelines for the handling and disposal of construction discharges. This ProPECC Note is generally applicable for control of site runoff and wastewater generated during the construction phase of the Project.
5.2.3
The Technical Memorandum on Standards for Effluents Discharged into Drainage
and Sewerage Systems, Inland and Coastal Waters under the WPCO defines
acceptable discharge limits to different types of receiving water in
5.3
Baseline Water Quality Conditions
Field
Observations
5.3.1
The direction of flow of all of the
watercourses except Lin Ma Hang stream is
towards River Indus, ultimately towards
5.3.2
Site visits took place over a
number of days between February, July and October 2004. Observations are
detailed in Table 5.1 below.
Field Observations at
Watercourses in the Study Area
Stream Number |
Stream Description |
Water Quality Observations |
MUP03 |
A small road side
concrete drain next to |
No water flow observed
during site visit. |
MUP04 |
Flows through
agricultural lands and nurseries. Small sections have been dammed with water
being pumped to nearby agricultural land for irrigation. The stream section
close to |
Clean, free flowing and
relatively undisturbed at the upstream portion, middle portion potentially
nutrient rich from surrounding agricultural lands, downstream portion (close
to road) is adversely impacted by construction waste dumping and domestic
discharge. |
MUP05 |
The upstream portion
(about 300 m) runs parallel to At the middle portion, where
the river meanders about 40 m away from the road, some patches
of mostly disturbed riparian vegetation can be found. The stream banks
consist of natural and concrete materials, while the stream bed is rocky or
muddy. Rubbish can be seen where stream passes near village or industrial
development. Near the western
downstream end, the banks are formed with concrete, between 8 m
to 20 m wide, with rocky / muddy bottom. Construction activities
on the channel across |
At the upstream portion,
water is stagnant at some locations and has a greyish colour but has no bad
odour. Water quality at the
middle portion appears better with the appearance of small fishes. Clear flowing water at
the western end, fishes (tilapia) can be seen. |
LMH01 |
Natural stream with
riparian vegetation. Rocky / sandy / muddy bottom at different locations.
Rubbish tipping at the stream banks adjacent to the main village area. |
Water is clean, free
flowing and relatively undisturbed at most location. Algae and small fish can
be observed at several locations. |
Baseline
Conditions
5.3.3
A considerable amount of water
quality data is available from EPD for water bodies within the Study Area. A
summary of EPD water quality data from 2002 to 2004 is shown in Table 5.2 for
streams and rivers within the Study Area.
5.3.4
River
5.3.5
In 2004, River Indus attained a WQO
compliance of 63%. The two upstream monitoring stations IN2 and IN3 were less
polluted with a “Good” water quality index and E. coli levels at 2,200 –
4,000 cfu/100mL. However, the water quality at the downstream station IN1 was “Bad”
with a much higher E. coli (190,000
cfu/100mL). This may be related to the pollution from unsewered villages and
livestock farms in the lower River Indus, as well as runoff from the Sheung
Shui and Fanling Town Centres (EPD 2005).
5.3.6
In order to further reduce
pollution in the River Indus, new public sewers would be constructed for two
villages in the River Indus catchment by 2005 under the North District Sewerage
Master Plan (SMP).
5.3.7
Sewers for some 16 villages in the
Ta Kwu Ling area would also be provided under the North East New Territories
(NENT) Landfill Village Sewerage Plan by 2007. Improvement of river water
quality is expected with continuous enforcement of pollution control
legislation and gradual provision of sewer facilities to the unsewered villages.
Summary of
Parameters |
IN1 |
IN2 |
IN3 |
||||||
2002 |
2003 |
2004 |
2002 |
2003 |
2004 |
2002 |
2003 |
2004 |
|
DO (mg/l) |
3.1 (1.8 – 6.3) |
5.2 (2.5 – 11.8) |
3.9 (1.4 – 7.2) |
7.4 (3.3 – 9.1) |
10.1 (7.7 – 16.1) |
8.8 (6.0 – 15.6) |
8.3 (7.7 – 10.2) |
8.3 (7.1 – 10.5) |
8.0 (5.5 – 9.1) |
pH |
7.2 (6.9 – 7.4) |
7.2 (6.9 – 7.9) |
7.1 (6.7 – 7.3) |
7.2 (6.6 – 7.7) |
7.8 (7.0 – 9.4) |
7.4 (6.7 – 8.8) |
7.4 (7.1 – 8.5) |
7.3 (6.9 – 8.2) |
7.3 (6.7 – 7.9) |
SS (mg/l) |
31 (13 – 110) |
34 (9 – 77) |
37 (8 – 440) |
67 (22 – 330) |
19 (7 – 150) |
7 (1 – 41) |
5 (3 – 32) |
11 (1 – 210) |
6 (2
– 92) |
BOD5 (mg/l) |
15 (4 – 39) |
5 (4 – 20) |
15 (5 – 32) |
3 (1 – 15) |
4 (1 – 6) |
3 (3 – 21) |
3 (2 – 9) |
3 (1 – 14) |
3 (2 – 10) |
(mg/l) |
33 (15 – 63) |
24 (12 – 44) |
30 (17 – 78) |
16 (5 – 29) |
13 (8 – 22) |
11 (7 – 42) |
17 (8 – 32) |
12 (7 – 17) |
10 (5 – 36) |
E.coli (cfu/100ml) |
390,000 (5,000 – 4,100,000) |
78,000 (11,000 – 3,000,000) |
190,000 (25,000 – 2,900,000) |
16,000 (1,600 – 90,000) |
1,800 (120 – 16,000) |
4,000 (170 – 48,000) |
4,700 (800 – 100,000) |
2,700 (200 – 16,000) |
2,200 (130 – 13,000) |
NH3-N (mg/l) |
7.75 (1.20 – 17.00) |
2.45 (0.41 – 11.00) |
5.85 (0.98 – 18.00) |
1.05 (0.29 – 4.10) |
0.41 (0.20 – 1.10) |
0.82 (0.40 – 1.70) |
0.82 (0.23 – 7.30) |
0.46 (0.16 – 1.30) |
0.82 (0.31 – 2.90) |
Source:
EPD (2004) River Water Quality Monitoring in
EPD (2005) River Water Quality Monitoring in
5.3.8
The ultimate receiving water body
for water from these streams is
5.3.9
In addition to data available from
5.3.10 An
updated baseline water quality should
be established before the commencement of the construction phase of the Project
to allow appropriate action and limit levels to be determined for impact monitoring
and audit.
5.4.1
The Water Sensitive Receivers (WSRs) include the stream course immediate
downstream of the proposed channel, River Indus and
5.5
Potential
Impacts During Construction Phase
Site Preparation
/ Clearance
5.5.1
Preparation of the land for
construction of the drainage channels will involve removal of surface
vegetation and excavations, removal and import of construction materials.
Construction of some temporary infrastructure may also be necessary such as drainage,
bunds and access roads.
5.5.2
The permeability characteristics of
the sites may change, reducing infiltration into surface layer. This may lead
to increased surface runoff with high suspended solids loadings during the wet
season. Erosion of soil enriched in organic matter may also release nutrients
into the nearby watercourses.
De-Watering
of Streams and Sediment Removal
5.5.3
During
excavation, the water in the streams will be temporarily
diverted to provide a dry working stream
bed prior to the channel works. This may lead to disturbance of organic rich
bottom sediments which will release nutrients and suspended solids into the
water.
5.5.4
A
sediment characterisation survey was conducted in January 2005 to determine
whether there are any contaminants in the sediments. The results indicated that
the sediments are “uncontaminated” (Category L). Details of the sediment
testing and its recommended disposal route can be found in Chapter 6 – Waste
Management.
5.5.5
Excavation of the sediments in the
channels will be required for channel formation. Excavated sediments may have
to be stored on-site before being sorted, reused or transported to disposal
sites. If stored as open air stockpiles and left uncovered during rainfall,
there is a potential risk of the excavated sediments being washed away, back
into the stream water, thereby causing sudden increase of oxygen demand and
turbidity during rainy condition.
Concreting Work
5.5.6
Concreting work will be required
for part of the channel formation and other ancillary infrastructure. If
concrete spillage, washdown or concrete curing water is inadvertently
introduced into the water course, the pH level will be raised and may result in
contamination of the water or creation of toxic conditions for the aquatic
life. Turbidity and suspended solids levels will also increase if contaminated by
runoff containing waste concrete. Other possible sources of concrete enriched
waste water include water from wheel wash facilities, and washout from concrete
lorries/pumps.
5.5.7
With the
use of gabion linings and retention of natural stream bed, the use of concrete
will be substantially reduced. The small scale bank improvement works at LMH01
would not require the use of concrete.
Site
Workshop or Depot
5.5.8
Works areas and site offices will
be provided for site staff and contractors, which may include workshop or depot
to provide maintenance and repair services for the equipment on site. The
workshop may store engine oil, lubricants, chemicals and waste oil/materials which may create impacts if accidental spillage
occurs. Waste oil may infiltrate the surface topsoil and contaminate the
ground. Stormwater runoff from the site may wash the oil spillage into adjacent
waterbodies.
Presence
of Additional Population (Workers)
5.5.9
The presence of site staff and
construction workers will generate sewage and domestic refuse. Impacts include
waste and wastewater generated from eating areas, temporary sanitary facilities
and waste disposal areas. Sewage arising from on-site construction workforce
would have the potential to cause water pollution if it is discharged directly
into adjacent water bodies without any appropriate treatment.
General
Construction Works
5.5.10 The
channel construction works are scheduled to start in end 2007 for completion in
mid 2011. General construction works will be continuous throughout both wet and
dry seasons. During the wet
season, silty runoff from the sites will be generated from areas cleared of
vegetation. If the site runoff is not adequately managed, it may enter the streams and increase the
suspended solids and turbidity levels of these water bodies.
5.5.11 The
various construction
activities and their associated impact on water quality described in the above
sections are summarised in Table 5.3
Summary of Impacts from
Construction Activities
Construction Activities |
Possible Impacts |
Site preparation /
clearance |
Increase of site runoff
from exposed surfaces. Increase in suspended
solids, nutrient levels and turbidity in watercourses leading to a decrease
in dissolved oxygen level. |
De-watering of streams
and sediment removal |
Runoff during dewatering works into local streams or channels, resulting in an increase in suspended solids, turbidity and nutrient loading. |
Concreting work |
Generation of concrete
washings, increase in pH value, leading to elevated un-ionised ammonia levels
(potentially ecotoxic). Increase in suspended solids
and turbidity levels. |
Site workshop or depot |
Accidental spillage of chemicals and waste oils into watercourses and groundwater. Stormwater runoff containing
oil and grease into watercourses. |
Additional population
from workforce |
Generation of rubbish and
additional sewage. |
General construction works |
Silty site runoff
resulting in increase in suspended solids and turbidity levels
during wet season. |
5.6
Mitigation
Measures for Construction Phase
5.6.1
The main potential impacts from the
construction stage of the Project include an increase in suspended solids, pH
value, oil & grease and general site effluent entering adjacent water
bodies. The following sections discuss the proposed mitigation measures for the
potential water quality impacts identified above.
General
5.6.2
The contractor shall observe and comply with the Water
Pollution Control Ordinance (WPCO) and its subsidiary regulations. The contractor shall carry out the works
in such a manner as to minimise adverse impacts on the water quality during
execution of the works. In particular the contractor shall arrange his method of working to
minimise the effects on the water quality within and outside the site and on
the transport routes.
5.6.3
The contractor shall follow the practices, and be
responsible for the design, construction, operation and maintenance of all the
mitigation measures below and as specified in ProPECC PN 1/94 – Construction
Site Drainage. In particular, the contractor shall submit and implement an
Erosion Control Plan (as part of the Environmental Management Plan[1]) which shall incorporate
details of the mitigation measures recommended below to reduce water quality
impacts arising from construction works. The design of the mitigation measures and
the Plan shall be submitted by the contractor
to the Engineer for approval.
Site
Surface Runoff
5.6.4
Proper construction site drainage
management measures shall be implemented to control site
runoff and drainage, and thereby prevent high sediment loadings from reaching
downstream sections of the river and adjacent agricultural land.
5.6.5
Turbid water from construction
sites must be treated to minimise the solids content before being discharged. Advice
on the handling and disposal of site discharge is given in the ProPECC Note PN
1/94 - Construction Site Drainage.
5.6.6
In general, surface run-off from
construction sites should be discharged into waterbodies via adequately
designed sand/silt removal facilities such as sand traps, silt traps and
sediment basins. Channels or earth bunds or sand bag barriers should be
provided on site to properly direct stormwater to such silt removal facilities.
Perimeter channels at site boundaries should be provided to intercept storm
run-off from outside the site so that it will not wash across the site (or into
the proposed channel works area). Catchpits and perimeter channels should be
constructed in advance of earthworks.
5.6.7
Silt removal facilities, channels
should be maintained and the deposited silt and grit should be removed
regularly, at the onset of and after each rainstorm to ensure proper
functioning of these facilities at all times.
5.6.8
Measures should be taken to prevent
the washing away of construction materials, soil, silt or debris into the
nearby waterbodies. Open stockpiles susceptible to erosion should be covered with
tarpaulin or similar fabric and provided with containment such as bunds, sand
bag barriers or equivalent measures,
especially during the wet season (April
– September) or when heavy rainstorm is predicted. Runoff to
watercourses should be reduced by minimising flat exposed areas of permeable
soil, and by forming pits or diversion channels into which runoff can flow to
suitable treatment facilities before discharge.
De-watering
/ Excavation of Streams and Removal of Sediment
5.6.9
The use of containment structures such as earth bund or sand bag barriers wrapped
with goetextile fabric or similar material or
diversion channels is recommended to facilitate a dry or at least confined
excavation within watercourses. Schematic
diagram of typical temporary drainage measures during construction is shown in
Figure 5.1.
5.6.10 Excavation
works at the existing stream section of MUP05 should be programmed
to be carried out during periods of low flow (dry season from 1st
October to 31st March) to minimise impacts on downstream water
quality and sensitive receivers. For the ecologically sensitive stream of
LMH01, the restriction period should be further extended for an additional month
(i.e. excavation works allowed from 1st November to 31st
March) to protect the aquatic fauna from silty runoff due to possible heavy
rain during the transitional period of the wet / dry seasons.
5.6.11 In
addition, the excavation works should be carried out in sections to reduce the
area of exposed surfaces as described below. For MUP05, the first 300m upstream
portion will have no restriction as the works involve small scale
reconstruction of existing concrete drains/channel. The associated area of
excavation is expected to be small. For the remaining sections of MUP05 (within
existing stream course), the length of excavation would be restricted to 300m
at any one time. For MUP04A, a 100m restriction should be imposed for the
entire stream works area to cater for potential cumulative impact on MUP05.
5.6.12 As
for LMH01, given its relatively small scale works but sensitive nature of the
stream, it is recommended that only either one portion of bank improvement
works or one vehicular crossing reconstruction should be carried out at any one
time.
5.6.13 No
restriction is necessary for MUP03 and MUP04B as works involve small scale
reconstruction of existing culvert and roadside concrete drains.
5.6.14 After
dewatering of the streams, the sediments should be allowed to dry before excavation
(yet still maintain a moist state to avoid dust nuisance). This will facilitate
excavation of the sediments
and also minimise the risk of drained water flowing back into watercourses as
the sediment is
handled. Where time or weather constraints require handling of wet sediment, care should be taken in
the removal of sediment
and the storage area should be bunded to prevent silty runoff entering watercourses. Given its small quantity, all
excavated sediment should be reused on-site as backfilling material.
5.6.15 Excavated
sediment will likely be temporarily stored on-site for reuse as backfilling
material. This should be stored in a bunded area and covered during wet season
or when rainstorm is forecasted to avoid inadvertent release of silts and suspended solids to
nearby water bodies.
5.6.16 Regular
monitoring of suspended solids and turbidity
should be conducted during excavation works. Any exceedance of water quality in
the nearby water bodies caused by inadvertent release of site runoff should be
rectified in accordance with EM&A programme for this Project.
Concreting
Work
5.6.17 Runoff
should be carefully channelled to prevent concrete-contaminated water from
entering watercourses. Adjustment of pH can be achieved by adding a suitable
neutralising reagent to wastewater prior to discharge. Re-use of the
supernatant from the sediment pits for washing out of concrete lorries should
be practised.
5.6.18 Any
exceedance of acceptable range of pH levels in the nearby water bodies caused
by inadvertent release of site runoff containing concrete should be monitored
and rectified under the EM&A programme for this Project.
5.6.19 To
protect the sensitive stream of Lin Ma Hang, no concrete should be used during
bank improvement works at LMH01.
Site
Workshop or Depot
5.6.20 Any
contractor generating
waste oil or other chemicals as a result of his activities should register as a
chemical waste producer and provide a safe designated storage area for chemicals on site. The storage site
should be located away from
existing water courses.
5.6.21 All compounds in works areas should be located on
areas of hard standing with provision of drainage channels and settlement ponds
where necessary to allow interception and controlled release of settled/treated
water; and provision of bunding for all potentially hazardous materials on site
including fuels. Hard
standing compounds should drain via an oil interceptor. The oil interceptor should be regularly inspected and cleaned to avoid wash-out
of oil during storm conditions. A bypass should be provided to avoid overload
of the interceptor's capacity. To prevent spillage of fuels or other chemicals
to water courses, all fuel tanks and storage areas should be sited on sealed
areas within a bund of a capacity equal to 110% of the storage capacity of the
largest tank. Where temporary storage of
chemicals or fuel drums outside the storage area is necessary, drip tray should
be provided. Disposal of the waste oil should be done by a licensed
collector. Good housekeeping practices should be implemented to minimise careless spillage and to keep the storage and the work space
in a tidy and clean condition. Appropriate training including safety codes and
relevant manuals should be given to the personnel who regularly handle the
chemicals on site.
5.6.22 The contractor should prepare an emergency
contingency plan (spill action plan) for the Project to contain and remove all
accidental spillage of chemicals and all hazardous materials on-site including
fuels at short notice and to prevent or to minimize the quantities of
contaminants entering the stream water and affecting the habitats. The
contractor should submit the emergency contingency plan to the ET for review
& comment and the Engineer for approval. The Plan should include, but not
limited to, the following:
(i)
potential
emergency situations
(ii)
chemicals
or hazardous materials used on-site (and their location)
(iii)
emergency
response team
(iv)
emergency
response procedures
(v)
list of emergency
telephone hotlines
(vi)
locations
and types of emergency response equipment
(vii)
training
plan & testing for effectiveness.
General Guidance for Handling of Spillage / Leakage
5.6.23 In the event that accidental spillage or leakage of
hazardous substances / chemical wastes takes place, the response procedures as
listed below should be followed. It should be noted that the procedures below
are not exhaustive and the contractor should propose other response procedures
in the emergency contingency plan based on the particular types and quantities
of chemicals or hazardous substances used, handled and stored on-site.
·
Oil
leakage or spillage should be contained and cleaned up immediately. Waste oil
should be collected and stored for recycling or disposal in accordance with the
Waste Disposal Ordinance.
·
Instruct
untrained personnel to keep at a safe distance well away from the spillage
area.
·
If the
spillage / leakage involves high toxic, volatile or hazardous waste, initiate emergency
evacuation and call the emergency service.
·
Only
trained persons equipped with suitable protective clothing and equipment should
be allowed to enter and clean up the waste spillage / leakage area.
·
Where
the spillage/ leakage is contained in the enclosed storage area, the waste can
be transferred back into suitable containers by suitable handheld equipment,
such as hand operated pumps, scoops or shovels. If the spillage / leakage
quantity is small, it can be covered and mixed with suitable absorbing
materials such as tissue paper, dry soft sand or vermiculite. The resultant
slurry should be treated as chemical waste and transferred to suitable containers
for disposal.
·
For
spillage / leakage in other areas, immediate action is required to contain the
spillage / leakage. Suitable liquid absorbing materials such as tissue paper,
dry soft sand or vermiculite should be used to cover the spill. The resultant
slurry should be treated as chemical waste and transferred to suitable
containers for disposal.
·
Areas
that have been contaminated by chemical waste spillage / leakage should be
cleaned. While water is a soluble solvent for aqueous chemical wastes and water
soluble organic waste, kerosene or turpentine should be used for organic
chemical wastes that are not soluble in water. The waste from the cleanup
operation should be treated and disposed of as chemical waste.
·
In
incidents where the spillage / leakage may result in significant contamination
of an area or risk of pollution, the Environmental Protection Department should
be informed immediately.
Presence
of Additional Population (Workers)
5.6.24 Sewage
arising from the additional population of workers on site should be collected
in a suitable storage facility, such as portable chemical
toilets. An adequate number of portable toilets should be
provided for the construction workforce. The portable toilets should be
maintained in a state that will not deter the workers from using them. The
collected wastewater from sewage facilities and also from eating areas or
washing facilities must be disposed of properly, in accordance with the WPCO
requirements. Wastewater collected should be discharged into foul sewers and
collected by licensed collectors.
5.6.25 Either
chemical toilets or other types of sewage treatment facilities without local
discharge of wastewater shall be used to handle the foul water effluent arising
from the project sites.
Summary
of Mitigation Measures for Construction Phase
5.6.26 The
potential impacts on water quality during the construction phase of the Project
and the associated recommendation of mitigation measures are summarised in
Table 5.4.
Summary of Mitigation
Measures for Construction Impacts
Impacts from Construction |
Mitigation Measures |
Increase of suspended
solids and turbidity from silty site run-off. |
Reduction of site run-off by diversion into temporary sedimentation or other silt removal facilities. Site management practices in accordance with ProPECC PN 1/94. Carry out works in dry
season. Construction of bunds or
barriers where there is potential for runoff to enter watercourses. |
Release of nutrients/
silts into runoff during excavation of stream
sediment. |
Carry out works in sections
and during dry season. Drying of sediment before excavation. Careful handling of sediment being excavated. Storage of sediment in
bunded area and properly covered. Sediments to be reuse
on-site as backfilling material to minimize off-site disposal. Avoid stockpiling, if
unavoidable stockpile for the shortest duration possible. Ability to confine flow
of water (using bunds, diversion channels, etc). Monitor suspended solids
and turbidity in water courses. |
Elevation of pH in water
courses from concrete washings. |
Close monitoring of pH
in watercourses. Construction of bunds
around the concreting work to collect spilt cement and concrete washings. Adjustment of pH in any
water which has become contaminated with concrete. Restrict the use of
concrete for bank improvement works at LMH01. |
Release of waste oil or
other chemicals used in the site workshop or depot. |
Registration of contractor
as a chemical waste producer. Provide a safe designated
storage area for chemicals on-site. Removal of waste oil by
licensed collectors. Siting the workshop away
from water bodies. Installation and
maintenance of oil interceptor in hard standing compound. Oil interceptor
should have a bypass installed and be regularly maintained. Good housekeeping
practices to minimise careless spillage. Prepare an emergency contingency plan to contain and remove all
accidental spillage. Appropriate training
given to the personnel to handle chemicals. |
Increase of sewage and
other wastewater from additional workers. |
Provision of portable chemical toilets and proper collection and disposal of sewage and
wastewater. |
5.7
Potential Impacts During Operational Phase
Identification, Prediction and Evaluation of Impacts
5.7.1
Potential
water quality impacts during operational phase of the proposed channels include:
•
pollution
loads entering the channels (from polluted upstream water, runoff from adjacent
land and flood waters; and
•
increase in
suspended solids during maintenance of the proposed channels.
5.7.2
The operation
of the proposed secondary channels, however, does not in itself generate any
new pollution load to the catchment.
5.7.3
As the
proposed channels are well over 15 km from
5.7.4
Long term
reduction of pollution load into the channels is required to improve the water
quality in the channel. The first step would be the continuous enforcement of
Livestock Waste Control Scheme by the relevant authority. The stream currently
receives some domestic waste discharges and industrial effluent which will continue even after the Project is complete. The level of impact will be similar to the
current situation and the long term solution will be to provide sewers
connecting to village households to treatment works. Provision of public sewers
to the unsewered villages is currently being implemented under the North
District Sewerage Master Plan.
5.7.5
Vegetation
removes dissolved and particulate pollution through absorptive, filtration and
biological mechanisms. As concrete drainage environment will not provide such
functions, gabion lined channel with existing bed retained is adopted. In
line with the recommendations under the ecological assessment, gabions linings will be installed instead
of concrete channel. Vegetations will be allowed to re-established along the
banks. Natural stream bed will be retained where feasible.
5.7.6
Another potential impact is the temporary
release of odour from polluted water and sediments in the channel during low
flow conditions. A combination of removing sediments during construction and
maintenance of the channel, and long term reduction of pollution loading to the
channels, will lead to a reduction of this nuisance.
5.7.7
Maintenance would be necessary for the proposed gabion
channels to remove excessive silts, vegetation, debris and obstructions in
order to maintain its hydraulic performance and structural integrity. Siltation
will generally be allowed to accumulate and removal of excess silt would be
carried out at locations where it would impede water flow. Little or no
maintenance will be necessary for the ‘two-stage’ channel at MUP05 and the
natural stream sections of LMH01. The potential temporary impacts include an
increase of suspended solids during removal of the accumulated sediments and
disturbance to the aquatic communities from workers and equipment. The impacts
associated with the maintenance works are not expected to create adverse water quality
impacts.
5.7.8
There would be no chemicals or
hazardous materials stored / used on-site during operation, as such the
likelihood of accidental spillage is not expected. Emergency contingency plan
for operation phase is therefore considered not necessary.
5.8
Mitigation Measures for Operational Phase
5.8.1
The most important feature of the
proposed channels is the prospect of suitable re-vegetation of the gabion side
slopes replicating existing riparian vegetation. The vegetation is not expected
to be detrimental in any way to the structure. However, seasonal cutting and
clearance of vegetation, particularly in advance of the wet season will be
required. This mitigation measure has additional benefits of aesthetic and
ecological value.
5.8.2
In addition, the use of gabion or
rock fill base for the bed of the channel has the benefit of providing uneven
surfaces and cavities for sediment to accumulate. Ultimately a sediment layer
will build up on the gabion floor, forming a natural layer for development of
the benthic community. Removal of the upper layer of this sediment will only be
necessary once the layer thickness has built up to around 300 mm thick, and
sediment is likely to be washed downstream in heavy storms. A minimum of 75mm
thick sediment would be allowed to accumulate at the channel bed to permit recolonizing
of benthic communities. Growth of vegetation within the gabion sections will
inhibit washout of sediment and sediment removal can be carried out at the same
time as vegetation harvesting during the dry season when flows are minimal.
5.8.3
The main disadvantage in the use of
gabions in the channel is the increase of hydraulic resistance. This will cause
a slightly wider hydraulic section to be adopted in the channel design to
maintain the same capacity for flood control.
5.8.4
Certain wetland plant species such
as ‘sedges’ which have high flexibility and are easily deformed during flood
conditions and present minimum drag to flow can be used without significantly
compromising the flood capacity of the channel. Species such as vetiver are well documented as being
hardy and able to grow under seasonally flooded conditions and are ideally
suited for channel bank stabilisation and re-vegetation.
5.8.5
Maintenance of grass species in the
channel bottoms is relatively simple and they can be cut prior to the rainy
season to prevent washing into River Indus. The recommended vegetation will
take up both nutrients and pollutants and should be disposed to landfill. At
the same time as grass cutting, excessive sediment may be removed to prevent
this being washed into River Indus. As the volume of excess sediment is
expected to be minimal, this can be disposed to landfill along with the excess
vegetation. The excess sediment should be allowed to drained and dried before
disposal.
5.8.6
Odour reduction can be achieved
through regular sediment removal during low flow (dry season).
Environmental
Considerations for Maintenance of the Proposed Channels
5.8.7
Maintenance may be necessary for
the proposed gabion channel at regular intervals to remove excessive silts,
vegetation, debris and obstruction. Little or no maintenance will be
necessary for the natural streams (e.g. Lin Ma Hang and ‘two-stage’ channel of
MUP05). Good
practice guides for the planning and execution of desilting and maintenance
works on environmentally sensitive watercourses are
recommended in
the following sections.
5.8.8
Before proceeding with any desilting or maintenance works,
except for emergency works, the maintenance engineer should check to ascertain
if any of the proposed works will be located in or near an environmentally
sensitive and/or ecologically important watercourses. In case of doubt, advice
from
5.8.9
If the proposed works will be located inside or near one of
the environmentally sensitive and/or ecologically important watercourses,
careful consideration should be given to the proposed method of implementation
so as to minimise any adverse environmental impact. Depending on the extent of
the maintenance works,
5.8.10
The following considerations should be included in planning
for the maintenance works for the proposed gabion channels:
(a)
Maintenance of the channels should be restricted to annual
silt removal when the accumulated silt will adversely affect the hydraulic
capacity of the channel (except during emergency situations where flooding risk
is imminent). Desilting should be carried out by hand or light machinery during
the dry season (October to March) when water flow is low.
(b)
The management of woody / emergent vegetation should be limited
to manual cutting, to be carried out during dry season and only when unchecked
growth of such vegetation is very likely to impede channel flow.
(c)
A minimum of 75mm thick sediment should be allowed to
accumulate on the channel bed to permit recolonization of benthic communities.
(d)
Phasing of the works should be considered to better control
and minimize any impacts caused, and to provide refuges for aquatic organisms.
Where possible, works should be carried out along half width of the watercourse
in short sections. A free passage along the watercourse is necessary to avoid
forming stagnant water in any phase of the works and to maintain the integrity
of aquatic communities.
(e)
Containment structures (such as sand bags barrier) should be
provided for the active desilting works area to facilitate a dry or at least
confined working area within the watercourses.
(f)
Where no maintenance access is available
for the channel, temporary access to the works site should be carefully planned and located
to minimize disturbance caused to the watercourse, adjacent vegetation and
nearby sensitive receivers by construction plants.
(g)
The use of lesser or smaller construction plants should be
considered to reduce disturbance to the channel bed where fish habitats are
located and to the nearby sensitive receivers. Quiet construction plants should
be used.
(h)
The use of concrete or the like should be avoided or
minimized.
(i)
The locations for the disposal of the removed materials
should be identified and agreement sought with the relevant departments before
commencement of the maintenance works. Temporary stockpile of waste materials
should be located away from the channel and properly covered. These
waste materials should be disposed of in a timely and appropriate manner.
5.8.11 A
summary of the mitigation measures proposed is shown in Table 5.5.
Summary of Mitigation
Measures for Operational Impacts
Impacts from Operation |
Mitigation Measures |
Reduction in water
quality of downstream water courses from introduction of pollutants upstream. |
Pollutants present in
run-off during operation can be reduced through an increase in permeable
areas in sections where the run-off occurs to reduce the volume of pollutants
entering the channels. Grasscrete and gabions can be used to achieve this. |
Removal of permeable
area presently covered in vegetation. |
Use of gabions in
sections of the channels mitigates this impact through allowing vegetative
growth. Infiltration of water into the ground and passage through vegetation
will provide partial treatment of the water in terms of trapping suspended
solids and removal of BOD through aeration. |
Increased sediment
transport to River Indus and ultimately to |
Sediment will be carried
to River Indus and ultimately to |
Temporary release of
odour from polluted water and sediments in the channel during low flow
condition. |
Odour reduction can be
achieved through regular sediment removal during dry season. |
Temporary release of
suspended solids and waste during maintenance process, minor disturbance from
maintenance equipment. |
Implement good practice
guides for the planning and execution of desilting and maintenance works such
as works during dry season, phasing of the works, use of containment
structures, sensitive use of construction plant to reduce disturbance,
minimise the use of concrete, and proper storage and disposal of waste. |
5.9
Residual
and Cumulative Impacts
5.9.1
With the
effective implementation of mitigation measures as described, residual impacts
on water quality of the receiving water bodies due to the implementation of
this Project are expected to be negligible.
5.9.2
A number of other
secondary channels will be constructed within the Study Area. The Non-DP
channels, MUP01 and MUP02, will be connected to MUP05. Only short sections of
bank stabilisation / improvement works are proposed for MUP01 and MUP02. The
main potential cumulative impact would be silty site runoff during construction
phase. With the implementation of proper site drainage system as stipulated in
ProPECC PN 1/94, cumulative impact is not expected.
5.9.3
In general, excavation in all the
proposed secondary channels under this Project is to be executed in the dry
season within a containment structure (see Figure 5.1 for typical example) and
any groundwater outflow from the containment is pumped out by way of a settling
basin. Any water courses or outfalls that would normally be served by the area
of channel under improvement will bypass the works either in a piped system or
a temporary mortar lined peripheral channel.
5.9.4
The implementation of a water
quality monitoring and audit programme during the construction phase can ensure
early detection of deteriorating water quality and timely action to rectify the
situation as well as to ensure the proper implementation of the mitigation
measures and to verify its effectiveness.
5.9.5
Based on the above justification, adverse
cumulative works related water quality impacts are thus not expected.
5.10
Monitoring
and Audit Requirement
5.10.1 Further information
regarding water quality monitoring and audit are described in Chapter 10 of
this Report. Key points are summarized below.
5.10.2
A water quality monitoring and audit
programme will be formulated to check for compliance with permissible effluent standards, to
ensure the proper implementation of the mitigation measures and to verify the
effectiveness of the recommended mitigation measures. Monitoring
locations will be proposed where the works are close to sensitive water bodies
or different projects interface with each other (i.e. where cumulative impacts
may occur). Monitoring should be provided
at both downstream (as impact station) and upstream (as control station).
5.10.3
Baseline
monitoring will be required prior to construction, to determine the appropriate
action and limit levels for impact monitoring.
5.10.4
Monitoring of
pH value, dissolved oxygen, suspended solids and turbidity will need to be carried out to ensure that any deteriorating
water quality could be readily detected and timely action be taken to rectify
the situation.
5.11.1 The
current condition of the water bodies in the Study Area is relatively poor in
the lower stretches with many of the streams receiving a variety of polluting
inputs including livestock waste,
industrial effluent, domestic wastewater and construction waste from local
villages.
5.11.2 The
construction of the channels could adversely impact the water bodies through
silt-laden site runoff, disturbance of stream sediment during excavation,
concreting works, runoff from workshops & depot and increased sewage and wastewater
resulting from the additional workforce on site. These impacts can be readily
mitigated through the construction of a suitable drainage system with silt
traps, good site management practices, careful working practices when
excavating sediments and proper sewage collection and disposal system.
5.11.3 The
major operational impacts are a net increase in pollutant loadings to
5.11.4
With the implementation of the recommended mitigation
measures, no adverse residual water quality impact is expected during
construction and operation phases of the Project.
EPD (2003) River Water Quality Monitoring in
EPD (2004) River Water
Quality Monitoring in
EPD (2005) River Water Quality Monitoring in