8.                        LANDSCAPE AND VISUAL IMPACT

 

8.1                    Introduction

 

8.1.1             This Chapter outlines the Landscape and Visual Impact Assessment (LVIA) associated with the Drainage Improvement in the Northern New Territories (the Project) which requires a LVIA under the Environmental Impact Assessment Ordinance (EIAO).

 

8.1.2             The LVIA is necessary owing to the landscape and visual impacts that could result from the construction and operation of the Project elements as described in Chapter 2 of this Environmental Impact Assessment (EIA) Report. These impacts need to be identified for both the construction and operational phases of the proposed Project. In addition, the significance and magnitude of the expected impacts will vary between construction and operational phases and also between mitigated and unmitigated conditions. Therefore, the significance and magnitude during different phases and conditions need to be defined.

 

8.2                    Scope and Content of Study

 

               The Study Area

 

8.2.1              The location plans, design considerations and layouts for the Project are presented in Chapters 1 and 2. In summary, the following proposed works are covered in this LVIA:

 

Table 8.1         Proposed Works covered in the LVIA

 

Proposed Drainage Channel ID

Location

Detail of Proposed Channel

Approximate Length

Average Base Width

MUP03

Man Uk Pin area

93m (for trapezoidal channel)

150m (for U-channel)

12m (for 0.6m dia. drainage pipe)

28m (for box culvert)

1.2m

0.6m (for U-channel)

-

3m (W) x 1m (D)

MUP04A

Man Uk Pin area

163m

21m (for 1.95m dia. drainage pipes)

4.5m

-

MUP04B

 

Man Uk Pin area

58m (for U-channel)

138m (for 1.35 dia. drainage pipes)

0.9m (for U-channel)

-

MUP05

Man Uk Pin area

1014m

2-14m

LMH01

Stream in Lin Ma Hang area

190m of gabion channel and localised bank improvement works

5m

Notes:

Other ancillary works include provision of inlet/outlet pipes, maintenance ramps & accesses, re-provision of crossings and final landscaping works.    


Location of the LVIA Study Area

 

8.2.2              For the Landscape Impact Assessment (LIA), the Study Area was all terrestrial and aquatic surface areas that are within 500m of the works area of the Project (refer to Figures 7.2 – 7.3 for Habitat Maps and Figures 8.1A – 8.1B for Landscape Resources (LR) & Character Areas (LCA) in accordance with the EIA Ordinance Guidance Note No. 8/2002, Item 3.3a).

 

8.2.3              The Study Area of the Visual Impact Assessment (VIA) includes all terrestrial and aquatic areas within the visual envelope, or Zone of Visual Influence (ZVI) which is shown in Figures 8.4A – 8.4B Location of Visually Sensitive Receivers and Zone of Visual Influence (ZVI). The ZVI is defined according to the EIA Ordinance Guidance Note No. 8/2002, Item 3.3a. It further indicates that the natural and man-made features (i.e. high rise residential housing, view corridors created by drainage) determine the possibility of views to the proposed drainage improvement area and define the extent of the visual envelope.

 

8.3                    Purpose of LVIA

 

8.3.1             The purpose of this LVIA is to identify the existing landscape and visual quality in the LVIA Study Area and to evaluate the landscape and visual impacts and to propose mitigation measures, if necessary. In detail, this includes a Landscape Proposal as part of the EIA Report.

 

8.3.2             To achieve this purpose, the following goals are set out for this LVIA:

 

·                    To perform landscape and visual baseline studies that describe the existing conditions;

·                    To identify and describe the landscape and visual impacts of the areas;

·                    To define the significance and magnitude of these impacts;

·                    To propose mitigation measures by taking local conditions and experience in consideration and to describe the maintenance and management of these mitigation measures; and

·                    To indicate the residual impacts after mitigation.

 

8.3.3             To achieve these goals, the following objectives are set out for this LVIA:

 

·                    To conduct a baseline study (“Tree Survey Report”) that describes the physical properties of landscape and visual resources and defines the sensitivity to change of these landscape and visual resources;

·                    To describe and define the magnitude of change to the landscape and visual baseline conditions brought about by the Project;

·                    To define the significance of impacts according to the sensitivity to change of landscape and visual resources and the magnitude of change that is caused by the Project;

·                    To identify normative mitigation principles that are applicable to moderate the determined impacts and to select measures that are practical and viable;

·                    To define the residual impacts by comparing the significance of impacts before mitigation to the same impacts after mitigation; and

·                    To prescribe practical maintenance and management measures by taking local conditions into account.

 

8.4                 Environmental Legislation, Policies, Plans, Standards and Criteria

 

8.4.1          The methodology for undertaking the LVIA is in accordance with Annexes 10 and 18 of the Technical Memorandum on Environmental Impact Assessment Process (EIAO-TM) and the EIAO Guidance Note No. 8/2002.

 

8.4.2          The landscape impact assessment shall assess the source and magnitude of developmental effects on the existing landscape elements, character and quality in the context of the site and its environs.

 

8.4.3          The visual impact assessment shall assess the source and magnitude of effects caused by the proposed development on the existing views, visual amenity, character and quality of the visually sensitive receivers within the context of the site and its environs.

 

8.4.4          The significance thresholds for the landscape and visual impacts are assessed for the construction phase and operational phase both with and without mitigation.

 

8.4.5          In order to illustrate these landscape and visual impacts and to demonstrate the effectiveness of the proposed landscape and visual mitigation measures, photomontages at selected representative viewpoints have been prepared to illustrate:

 

·                    existing conditions; 

·                    unmitigated impacts; 

·                    partially mitigated impacts after implementation of the proposed mitigation measures on day 1 of the operational phase; and

·                    residual impact in year 10 of the operational phase.

 

8.4.6             These residual impacts are evaluated in accordance with Annex 10 of the EIAO-TM.

 

 

8.5                    Assessment Methodology & Criteria

 

LVIA Approach

 

8.5.1              The approach to this study has three facets:

 

·                    To be in accordance with the standards and legislation as described in the EIAO;

·                    To follow a sound research ethic; and

·                    To base the assessment methodology on the objectives as set in Section 8.3 for the LIA and VIA studies independently.

 

Project Description

 

8.5.2              For the construction phase, the descriptions are on the following aspects:

 

·                    construction areas; and

·                    temporary buildings and storing areas.

 

8.5.3              For the operation phase, the descriptions are on the following aspects:

 

·                    drainage channels, embankments, maintenance paths; and

·                    landscape areas.

  

Review of Planning and Development Control Framework

 

8.5.4              A review of the existing planning studies and documents was undertaken as part of the assessment to gain an insight into the planned role of the site, its context and to help determine the projects fit into the wider existing and future landscape context.  A review of the existing and development framework of the site and surrounding areas was undertaken in order to identify any issue of conflict with the neighbouring planned land uses and to identify the full extent of the 'visually sensitive receivers' (VSRs). For the purposes of this study, the Outline Zoning Plans (OZPs) for the Study Area were used as a basis to get an accurate picture of the future landscape setting and visual context. This also ensures that the landscape proposals are compatible with the surrounding landscape character context.

 

Landscape Impact Assessment

 

8.5.5              The assessment of the potential impacts of a proposed scheme on the existing landscape comprises two distinct sections:

 

 

·                    baseline survey, in this case comprising mainly of a tree and habitat survey; and

·                    potential landscape impacts assessment.

 

8.5.6              To conduct the landscape baseline study that describes the physical properties of the landscape, surveys were carried out with considerations in both the present and planned future landscape: the first was a desktop survey and the second was a site survey. A baseline survey of the existing landscape character and quality has been undertaken through site inspections and desktop surveys. Landscape elements considered included:

 

·                    local topography;

·                    existing road side planting;

·                    woodland extent and type;

·                    other vegetation types; 

·                    built form;

·                    patterns of settlement;

·                    land use;

·                    scenic spots;

·                    details of local materials, styles, streetscapes, etc.;

·                    prominent watercourses; and

·                    cultural and religious identity.

 

8.5.7              Planned developments either within the study area or adjacent to it were also considered. The baseline survey formed the basis of the landscape context by describing broadly homogenous units of similar character. The individual landscape character areas (LCA) and resources were rated using low, medium or high depending not only on the quality of elements present but also their sensitivity to change and local or regional importance. The quality of the landscape was not only related to its visual amenity. The magnitude of change arising from the implementation of the scheme proposals was rated as negligible, small, intermediate or large.

 

8.5.8              Potential landscape impacts of the proposals were resulted from:

 

·                    identification of the sources of impact, and their magnitude, that would be generated during construction and operation of the scheme; and

·                    identification of the principal landscape impacts, primarily in consideration of the degree of change to the baseline conditions. The impacts are considered systematically in terms of the landscape elements, the site and its context.

 

8.5.9              Factors affecting the evaluation of the magnitude of landscape impacts were:

 

·                    compatibility of the project with the surrounding landscape;

·                    duration of impacts under construction and operational phases;

·                    scale of the development; and

·                    reversibility of change.

 

8.5.10          Factors affecting the evaluation of the sensitivity of landscape character/resources were:

 

·                    quality of landscape characters / resources;

·                    importance and rarity of special landscape elements;

·                    ability of the landscape to accommodate change;

·                    significance of the change in local and regional context, and

·                    maturity of the landscape.

 

8.5.11          The significance threshold for impacts to landscape character and resources was rated as significant, moderate, slight or negligible. The impacts may be either beneficial or adverse.

 

8.5.12          The impact is a product of the magnitude of change which the proposals will cause to the existing landscape context and it's ability to tolerate the change, i.e. its quality and sensitivity. The significance threshold is derived from The Significance Threshold Matrix A as described in Table 8.2.

 

Table 8.2

The Significance Threshold Matrix A

 

               Sensitivity To Change

 

Magnitude of Change    

(Caused by proposed)   

 

Low

 

 

 

Medium

 

High

Large

Moderate Impact

Moderate/Significant Impact

Significant Impact

Intermediate

Slight /

Moderate Impact

Moderate Impact

Moderate/

 Significant Impact

Small

Slight Impact

Slight / Moderate Impact

Moderate Impact

Negligible

Negligible Impact

Negligible Impact

Negligible Impact

 

Tree Survey Methodology

 

8.5.13          To minimise conflicts with existing vegetation, a tree survey was completed based on an agreed methodology, and involved the identification of tree groups and significant individual trees with fung shui importance. The numbers of trees and the range of species and sizes in each tree group, added by health conditions and tree form was given. The location, size and species of the significant individual trees with fung shui importance were also given. This allowed the fine-tuning of the proposed design for the proposed scheme and ensured that any significant trees, where possible, were protected during both the design and construction periods. The figures contained in this report were made reference to the findings of the detailed Tree Survey Report (Annex 2 of Appendix H).

 

Visual Impact Assessment

 

8.5.14          The assessment of the potential visual impact of the scheme comprises three distinct parts:

 

·                    Quality of landscape characters / resources

·                    Baseline survey

·                    Visual impact assessment

 

8.5.15          For the Visual Impact Assessment (VIA), the assessment area is taken to include the visual envelope or Zone of Visual Influence (ZVI), which includes all areas from which the scheme proposals can be seen. This area forms the view shed formed by natural / manmade features such as existing ridgelines, built development and for example areas of woodland / large trees.

 

8.5.16          The baseline survey of all views towards the proposals is undertaken by identifying:

 

·                    The visual envelope as has been described above and may contain both open and partial views of the proposals. This must also include indirect effects such as offsite construction activities; and

·                    The visually sensitive receivers (VSRs) within the visual envelope whose views will be affected by the scheme. The identified VSRs include planned visually sensitive receivers (PVSRs). The potential receivers are considered as four groups:

-               quality of landscape characters / resources;

-               Views from residences - the most sensitive of receivers due to the high potential of intrusion on the visual amenity and quality of life;

-               View from workplaces - less sensitive than above due to visual amenity being less important within the work environment; and

-               Views from public areas - including all areas apart from the above, e.g., public parks, recreation grounds, footpaths, roads, cultural sites, etc. Sensitivity of this group depends on the transitory nature of the receiver, e.g. sitting in a park or traveling on a highway, pedestrian or cycling path. Also considered is the degree of view or glimpsed views.

 

8.5.17          However, the assessment of sensitivity has also been based on the quality and extent of the existing view. Therefore, a view from a residential property which would normally be considered the most sensitive view may be less so if, for example, it is degraded by existing development or partially screened by intervening visual obstacles such as existing vegetation.

 

8.5.18          The location and direction of its view relative to the scheme also influences the sensitivity of each group. Typical viewpoints from within each of the visually sensitive groups are identified and their views described. Both present and future visually sensitive receivers are considered.

 

8.5.19          The baseline survey formed the basis of the visual character and quality of the site. Potential visual impacts were resulted from:

 

·                    identification of the sources of visual impacts, and their magnitude, that would be generated during construction and operation of the scheme; and 

·                    identification of the principal visual impacts primarily in consideration of the degree of change to the baseline conditions.

 

8.5.20          The impact assessment was related to the typical viewpoints within the visual receiver group, as identified previously, and their existing and potential views subsequent to the scheme development. The factors affecting the magnitude of change for assessing the visual impacts included the following:

 

·                    compatibility of the project with the surrounding landscape forming the view;

·                    duration of impacts under construction and operational phases;

·                    scale of the development;

·                    reversibility of change;

·                    viewing distance; and

·                    potential blockage of the view.

 

8.5.21          Factors affecting the sensitivity of receivers for evaluation of visual impacts were:

 

·                    value and quality of existing views;

·                    availability and amenity of alternative views;

·                    type and estimated number of receiver population;

·                    duration or frequency of view; and

·                    degree of visibility.

 

8.5.22          The views available to the identified VSRs were rated according to their sensitivity to change using low, medium or high. Whilst the magnitude of change arising from the implementation of the proposed scheme was rated as negligible, small, intermediate or large. The significance threshold for visual impact was rated in a similar fashion to the landscape impact, i.e. significant, moderate, slight and negligible. The impacts may be either beneficial or adverse.

 

8.5.23          The impact is a product of the magnitude of change which the proposals will cause to the existing landscape context and it's ability to tolerate the change, i.e. its quality and sensitivity. The significance threshold is derived from The Significance Threshold Matrix (Table 8.2).

 

Recommended Landscape & Visual Impact Mitigation Measures

 

8.5.24          The identification of the landscape and visual impacts highlighted those sources of conflict requiring design solutions or modifications to reduce the impacts, and, if possible, blend the development and associated activities with respect to the surrounding landscape. These mitigation measures should take into account factors including:

 

·                    preservation of existing vegetation as far as possible;

·                    woodland, tree and shrub planting of new or disturbed slopes, amenity strips and areas, central reservations and adjacent to any new structures to aid stabilisation;

·                    consideration of the contouring of new slopes in order to visually integrate them into the existing topography, use of vegetated earth mounding or structural solutions for screening;

·                    sensitive treatment of structural forms;

·                    appropriate design of hard landscape, furniture and other elements;

·                    careful consideration of significant landscape elements; and

·                    feasibility of mitigation measures in respect of funding, implementation phasing and maintenance.

 

8.5.25          These objectives resulted in the formation of landscape mitigation proposals alleviated the previously identified landscape and visual impacts as far as possible. The aim is the design of integrated landscape proposals to alleviate the landscape and visual impacts that arise from the final scheme, both during its construction and operational phases, and to ensure that the residual impacts are acceptable. As the scheme proposals, in particular the phasing of the project, develop, a programme for the implementation, management and maintenance of landscape works.

 


Defining the Residual Impacts

 

8.5.26          The residual impacts are those, which remain after the proposed mitigation measures have been successfully implemented. This is assessed both during the construction period and during the design year, which is taken to be 10 years after the proposed scheme has been opened to normal operation. During the design year, the soft landscape mitigation measures are deemed to have reached a level of maturity, which allows them to perform their original design objectives.

 

8.5.27          As described above, the level of impact is a product of the magnitude of change, which the proposals will cause to the landscape character, landscape resource or visual amenity, and their sensitivity to change. It is a comparison of the future landscape modified by the proposals with the landscape, which would have existed during this period if the proposed scheme had not been constructed. This assessment also considers the ability of the landscape character, landscape resource or visual amenity to tolerate change, i.e. its quality and sensitivity taking into account the beneficial effects of the proposed mitigation. The significance threshold is derived from the matrices described separately above for the landscape and visual impacts.

 

8.5.28          In accordance with Annex 10 of the EIAO TM, a final conclusion is also made of the residual landscape and visual impacts attributable to the proposed scheme. The degree of residual impact is considered in accordance with the Residual Impact Significance Threshold Matrix in Table 8.3.

 

Table 8.3

Residual Impact Significance Threshold Matrix

 

Beneficial

Acceptable

Acceptable

with Mitigation

Unacceptable

Undetermined

The project will complement the landscape and visual character of its setting, will follow the relevant planning objectives and will improve overall and visual quality.

There will be no significant effects on the landscape and no significant visual effects caused by the appearance of the project, or no interference with key views.

There are some adverse effects, but these can be eliminated, reduced or offset to a large extent by specific measures.

The adverse affects are considered too excessive and would not be reduced to an acceptable level by mitigation.

Significant adverse effects are likely but the extent to which they may occur or may be mitigated cannot be determined from the study. Further detailed study will be required for the specific effects in question.

 


8.6                    Review of Planning and Development Control Framework

 

8.6.1             A number of outline zoning plans (OZPs) were examined in order to review the planning and development control framework. The following OZPs and were reviewed: Plan No. S/NE-MUP/10 for Man Uk Pin.

 

8.6.2             The landscape-related land use zonings present in the Study Area and relevant to the LVIA are as follows:

 

·                    Green Belt (GB) - the planning function of GB is to limit the encroachment of urban development into the countryside.

·                    Conservation Area (CA) - the planning function of a CA is to retain existing natural characteristic of the area.

 

8.6.3             No part of the improved drainage alignment will be constructed through either GB or CA, therefore the Project is considered not to be in conflict with the landscape zonings in the area.

 

8.7                    Existing Landscape Baseline Conditions

 

8.7.1             The landscape baseline of the Study Area comprises landscape resources and landscape character. The existing landscape resources are shown in Figures 8.1A – 8.1B. Landscape character has been categorized into landscape character areas (LCAs) as per LCA boundaries shown in Figures 8.1A - 8.1B Landscape Resources (LR) & Landscape Character Areas (LCA). Figure 8.2 presents a photographic record of the LCAs.

 

8.7.2             The LCAs identified were LCA1 - Wooded Upland and Shrubland, LCA2 - Active and Inactive Agriculture including plantations, LCA3 - Used and Disused Fishponds, LCA4 - Residential Rural Fringe, LCA5 – Stream / Drainage Cchannel, LCA6 – Public Open Space / Park, LCA7 - High-Rise / Commercial and LCA8 Upland Grassland. These detail descriptions are listed below in Table 8.4.

 

8.7.3             The tree survey report (Annex 2 of Appendix H) conducted for this project included approximately 410 nos. identified trees in total (two locations) with the main species commonly found in Hong Kong and mostly in good or fair condition.

 

 

 


Table 8.4

Landscape Character Areas (Refer to Figures 8.1A to 8.1B)

 

Landscape Character Area (LCA)

Landscape Character Type Description

Location

Sensitivity to change

Ability to Accommodate Change

LCA 1
Wooded Upland / Scrubland

Well-wooded upland and scrubland with lower dispersed vegetation cover.

 

 

MUPs: At southern section (Princess Hill), North (Miu Keng) & East section (Near Shan Tong) of MUP 05 and south eastern section of MUP 04B, 03 (near Loi Tung Village)

Medium

Medium

LMH01: At North-eastern section of LMH 04, (Lin Ma Hang village) southern area (Tong To Shan Tsuen)

Medium

Medium

LCA 2

Active / Inactive Agriculture

Agriculture land characterized mainly by small-scale active and inactive agriculture and plantation plots near residential rural areas

MUPs:At both sides of the drainage channel of MUP 05 & MUP 04A (Loi Tung Village)

Medium

Low

LMH01: At both sides of the Shenzhen River channel and major area at southern section of the project site limit.

Medium

Medium

LCA 3

Used & Disused Fishponds

This is characterized by used and disused fishponds, these areas normally interspersed with agricultural land in the rural landscape matrix. 

MUPs: near Loi Tung Village at MUP04B

Low

High

LMH01: Further from the site limit, Wang Lek area

Low

High

LCA 4 Residential Rural Fringe

Residential Rural Fringe is the essential rural residential mixed zone characterized by typical low storey residential development as well as the amenities associated with village style living in the New Territories. This LCA is interspersed with others LCAs, mainly LCA2

MUPs: Loi Tung Village at MUP03, 04A, 04B, Man Uk Pin area, along Wo Keng Shan Road, Tai Tong Wu area.

High

Low

LMH01: Lin Ma Hang

Medium

Medium

LCA 5

Stream/ Drainage Channel

 

This is characterized by natural stream and engineered drainage channels with variable designs and sizes. Natural streams are generally more closely associated with LCA1 Wooded Upland / Shrubland. The drainage channel of LCA 5 is associated with more disturbed landscapes, for instance LCA 2, LCA 4 and LCA 7.

MUPs: Along Ng Tung River: Ch 1013.04 to Ch 944.39 (MUP05) Ch 944.39 to Ch.0.00 (MUP 05), Ch0.00 to Ch 184.00 (MUP 04A)

High

Medium

LMH01: Along Shenzhen River

Medium

Medium

LCA 6

Public Open Space/ Park

 

This is characterized by typical recreational park/public spaces with jogging track, seating and basic facilities for the users.

MUPs: Intersection location for Wo Keng Shan Road & Sha Tau Kok Road-Wo Hang (MUP05) Ch. 1013.04 to Ch. 944.39

High

Low

LMH01: N/A

N/A

N/A

LCA 7

High Rise/ Commercial

This is characterized by high-rise residential new town development and commercial building

MUPs: N/A

N/A

N/A

LMH01: N/A

N/A

N/A

LCA 8

Upland / Grassland

 

This upland grassland, found on cleared slopes in the hilly terrains.

 

MUPs: N/A

N/A

N/A

LMH01: North, West and South western of project site (Wang Lek, Tong To Shan Tsuen)

Low

High

 

 

 


8.8                    Landscape Impact Assessment

 

Landscape Resources during Construction

 

8.8.1             The landscape impacts on existing landscape resources during construction will be generated by the removal of existing trees and other vegetation and the modification of existing natural terrain. The impact on landscape resources is shown in Figures 8.3A (I-V) and 8.3B (I-III).

 

Impacts on Landscape Resources during Operation

 

8.8.2             The Project will not generate any further changes, activities, movement or alterations to the baseline conditions after completion of the construction activities. Therefore, no increases in the levels of impacts on landscape resources above and beyond those produced during construction are predicted.

 

Impacts on Landscape Character during Construction

 

8.8.3             The presence of the Project elements within the LCAs will change their character. The unmitigated impact on the landscape character is summarized in Tables 8.5A to 8.5B.

 

Impacts on Landscape Character during Operation

 

8.8.4             The Project will not generate any further changes, activities, movement or alterations to the baseline conditions after completion of the construction activities. Therefore, no increases in the levels of impacts on landscape character above and beyond those produced during construction are predicted.

 

 

 

 

 

 

 

 

 

 

 

 

 

 


Table 8.5A

Landscape Impact MUP03, MUP04A, MUP04B & MUP05 – Assuming No Mitigation

 

Landscape Character Area (LCA)

Location Reference

Magnitude of Change

Sensitivity to Change

Significance Threshold – Landscape Impact

LCA 1
Wooded Upland / Scrubland

 

At southern section (Princess Hill), North (Miu Keng) & East section (Near Shan Tong) of MUP05 and south eastern section of MUP04B, MUP03 (near Loi Tung Village)

 

Negligible

High

Negligible Impact

LCA 2

Active / Inactive Agriculture

At both sides of the drainage channel of MUP05 & MUP04A (Loi Tung Village)

 

Intermediate

Medium

Moderate Impact

LCA 3

Used & Disused Fishponds

near Loi Tung Village at MUP04B

 

Negligible

Low

Negligible Impact

 

LCA 4

Residential Rural Fringe

Loi Tung Village at MUP03, MUP04A, MUP04B, Man Uk Pin area, along Wo Keng Shan Road, Tai Tong Wu area.

 

Negligible

High

Negligible Impact

LCA 5

Stream/ Drainage Channel

 

Along Ng Tung River:

Ch 1013.04 to Ch 944.39 (MUP05)

 

Intermediate

High

Moderate / Significant Impact

Along Ng Tung River:

Ch 944.39 to Ch.0.00 (MUP05),

Ch 0.00 to Ch 184.00 (MUP04A)

 

Intermediate

High

Moderate / Significant Impact

LCA 6

Public Open Space/ Park

 

Intersection location for Wo Keng Shan Road & Sha Tau Kok Road - Wo Hang (MUP05)

 

Large

High

Significant

Impact

LCA 7

High Rise/ Commercial

 

 

N/A

 

N/A

 

N/A

 

N/A

LCA 8

Upland / Grassland

 

 

N/A

 

 

N/A

 

N/A

 

N/A

 

 


Table 8.5B

Landscape Impact LMH 01 – Assuming No Mitigation

 

Landscape Character Area (LCA)

Location Reference

Magnitude of Change

Sensitivity to Change

Significance Threshold – Landscape Impact

LCA 1
Wooded Upland / Scrubland

At North-eastern section of LMH01, (Lin Ma Hang village) southern area (Tong To Shan Tsuen)

Small

Medium

Slight / Moderate Impact

LCA 2

Active / Inactive Agriculture

 

At both sides of the Shenzhen River channel and major area at southern section of the project site limit.

Small

Medium

Slight / Moderate Impact

LCA 3

Used & Disused Fishponds

 

Further from the site limit, Wang Lek area

Negligible

Low

Negligible Impact

LCA 4

Residential Rural Fringe

 

Lin Ma Hang

Small

Medium

Slight / Moderate Impact

LCA 5

Stream/ Drainage Channel

 

Along Shenzhen River

Small

Medium

Slight / Moderate Impact

LCA 6

Public Open Space/ Park

 

 

N/A

 

N/A

 

N/A

 

N/A

LCA 7

High Rise/ Commercial

 

 

N/A

 

N/A

 

N/A

 

N/A

LCA 8

Upland / Grassland

 

North, West and South western of project site (Wang Lek, Tong To Shan Tsuen)

Negligible

Low

Negligible Impact

 


8.9                    Existing Visual Baseline Conditions

 

8.9.1             The visual impacts have been assessed in accordance with Sections 8.5.14 - 8.5.23. The Zone of Visual Influence (ZVI) of the Project and the Visually Sensitive Receivers (VSRs) are shown in Figures 8.4A to 8.4B to illustrate the sensitivity and quality of the existing view from each VSR location in plan and Figures 8.4Ai to 8.4Aviii and Figures 8.4Bi to 8.4Biv for the detail understanding for each VSRs.

 

8.9.2             A description of the Visually Sensitive Receivers along with an analysis of the quality of the existing view, distance from the impact source, degree of visibility, frequency of view and sensitivity to change is provided in Table 8.6A to 8.6B as shown below.

 


Table 8.6A

Visually Sensitive Receivers (MUP03, MUP04A, MUP04B & MUP 05)

 

Visually

Sensitive Receivers

(VSR)

Description of Visually Sensitive Receivers

Numbers of Individuals (Many/Fair/ Few/Very Few

Quality of Existing View

(Good /

Fair / Poor)

Minimum Distance between

VSRs & Impact

Source

Degree of Visibility

(Full /

Partial /

Glimpse)

Frequency of View

(Very Frequent/
Frequent /
Occasional /
Rare)

Sensitivity to Change

(High/ Medium/ Low)

VSR 1

Road Users of  Wo Keng Shan Road (bridge)

 

Many

 Good

< 10m

Full

 Very Frequent

High

VSR 2

Park Visitors @  Wo Keng Shan Road Garden

 

Fair

Good

< 15m

Full

 Very Frequent

High

VSR 3

Park Visitors @  Wo Keng Shan Road Garden

 

Fair

Good

< 15m

Full

 Very Frequent

High

VSR 4

 

Road Users of  Sha Tau Kok Road-Wo Hang (Along the road)

Many

Good

< 10m

Glimpse

Occasional

Medium

VSR 5

Residents @ toe of Princess Hill

(Individual Village houses/ Rural Fringe area)

Few

Fair

Approx.

80m

Glimpse

Rare

Low

VSR 6

Residents @ Loi Tung

(Individual Village houses/ Rural Fringe area)

Many

Fair

Approx.

50m

Full

Frequent

Medium

VSR 7

 

Residents @  Loi Tung (Active agricultural land)

Few

Fair

< 10m

Full

Frequent

Medium

VSR 8

 

Residents @ Loi Tung

(Low Rise Housing Development)

Many

Fair

Approx.

140m

Partial

Occasional

Low

VSR 9

 

Residents @ Loi Tung

(Individual Village houses/ Rural Fringe area)

Few

Fair

< 30m

Full

Frequent

Medium

VSR 10

 

Residents @ Loi Tung

(Individual Village houses/ Rural Fringe area)

Very Few

Fair

Approx.

20m

Full

Frequent

Medium

VSR 11

 

Residents @ Loi Tung

(Individual Village houses/ Rural Fringe area)

Few

Good

Approx.

30m

Partial

Frequent

Medium

VSR 12

 

Residents @ Loi Tung

(Individual Village houses/ Rural Fringe area)

Few

Good

Approx.

15m

Partial

Frequent

Medium

VSR 13

 

Road Users of  Sha Tau Kok Road-Wo Hang (Along the road near MUP03)

Many

Fair

< 30m

Full

Very Frequent

Low

VSR 14

 

Residents @ toe of small hill next to MUP01

(Individual Village houses/ Rural Fringe area)

Many

Fair

Approx.

25m

Full

Frequent

Low

VSR 15

 

Residents @ near junction of Sha Tau Kok Road-Wo Hang & local road leading to Man Uk Pin Village

(Individual Village houses/ Rural Fringe area)

Many

Poor

Approx.

20m

Full

Frequent

Low

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Table 8.6B

Visually Sensitive Receivers (LMH01)

 

Visually

Sensitive Receivers

(VSR)

Description of Visually Sensitive Receivers

Numbers of Individuals (Many/Fair/ Few/Very Few

Quality of Existing View

(Good /

Fair / Poor)

Minimum Distance between VSRs & Impact Source

Degree of Visibility

(Full /

Partial /

Glimpse)

Frequency of View

(Very Frequent/
Frequent /
Occasional /
Rare)

Sensitivity to Change

VSR 1

Road Users along access  road

Few

Good

< 15m

Partial

Occasional

Medium

VSR 2

Road Users along Lin Ma Hang Road

Few

Good

< 10m

Partial

Occasional

Medium

VSR 3

Residents @ Lin Ma Hang (Low Rise Housing Development)

Fair

Good

Approx.10m

Partial

Frequent

 High

VSR 4

 

Residents near vehicular bridge @ Lin Ma Hang

(Individual Village houses/ Rural Fringe area)

Fair

Good

< 10m

Partial

Frequent

Medium

VSR 5

Residents near river bank @ Lin Ma Hang

 (Individual Village houses/ Rural Fringe area)

Fair

Good

< 10m

Full

 Very Frequent

High

VSR 6

Residents near ancestral shrine @ Lin Ma Hang

(Individual Village houses/ Rural Fringe area)

Fair

Good

Approx. 20m

Partial

Very Frequent

High

VSR 7

 

Residents near the temple @ Lin Ma Hang

(Low Rise Housing Development)

Fair

Good

Approx. 35m

Partial

Frequent

Medium

 

8.10                Visual Impact Assessment

 

Visual Resources during Construction

 

8.10.1        The visual impacts on existing views during construction will be generated by the removal of existing vegetation, the modification of existing natural terrain, and the activity generally associated with construction works such as machinery, temporary buildings and hoarding.

 

Visual Resources during Operation

 

8.10.2        The Project will not generate any further changes, activities, movement or alterations to the baseline conditions after completion of the construction activities. Therefore, no increases in the levels of impacts on visual resources above and beyond those produced during construction are predicted.

 

8.10.3        As it is not possible to accurately portray the appearance of the Project during construction, visual changes are illustrated in Figures 8.5A to 8.5B by comparing the existing views to those immediately after construction and assuming no mitigation measures in place. A summary is provided in Tables 8.7A to 8.7B.

 

Table 8.7A

Summary of Visual Impact – Assuming No Mitigation (MUP03, MUP04A, MUP04B & MUP 05)

 

Visually

Sensitive Receivers

(VSR)

Description of Visually Sensitive Receivers

Minimum Distance between VSRs & Impact Source

Magnitude of Change

Sensitivity to Change

Significance Threshold – Landscape Impact

 

VSR 1

Road Users of  Wo Keng Shan Road (bridge)

< 10m

Large

High

Significant Impact

VSR 2

Park Visitors @  Wo Keng Shan Road Garden

< 15m

Intermediate

High

Moderate / Significant Impact

VSR 3

Park Visitors @  Wo Keng Shan Road Garden

< 15m

Intermediate

High

Moderate / Significant Impact

VSR 4

 

Road Users of  Sha Tau Kok Road-Wo Hang (Along the road)

< 10m

Small

Medium

Slight /

Moderate Impact

VSR 5

Residents @ toe of Princess Hill

(Individual Village houses / Rural Fringe area)

Approx.

80m

Small

Low

Slight Impact

VSR 6

Residents @ Loi Tung

(Individual Village houses / Rural Fringe area)

Approx.

50m

Small

Medium

Slight /

Moderate Impact

VSR 7

 

Residents @  Loi Tung (Active agricultural land)

< 10m

Intermediate

Medium

Moderate Impact

VSR 8

 

Residents @ Loi Tung

(Low Rise Housing Development)

Approx.

140m

Small

Low

Slight Impact

VSR 9

 

Residents @ Loi Tung

(Individual Village houses / Rural Fringe area)

< 30m

Negligible

Medium

Negligible Impact

VSR 10

 

Residents @ Loi Tung

(Individual Village houses / Rural Fringe area)

Approx.

20m

Small

Medium

Slight /

Moderate Impact

VSR 11

 

Residents @ Loi Tung

(Individual Village houses / Rural Fringe area)

Approx.

30m

Small

Medium

Slight /

Moderate Impact

VSR 12

 

Residents @ Loi Tung

(Individual Village houses / Rural Fringe area)

Approx.

15m

Small

Medium

Slight /

Moderate Impact

VSR 13

 

Road Users of  Sha Tau Kok Road-Wo Hang (Along the road near MUP03)

< 30m

Small

Low

Slight /

Moderate Impact

VSR 14

 

Residents @ toe of small hill next to MUP01

(Individual Village houses / Rural Fringe area)

Approx.

25m

Intermediate

Low

Slight Impact

VSR 15

 

Residents @ near junction of Sha Tau Kok Road - Wo Hang & local road leading to Man Uk Pin Village

(Individual Village houses / Rural Fringe area)

Approx.

20m

Small

Low

Slight Impact

 

 

 


Table 8.7B

Summary of Visual Impact – Assuming No Mitigation (LMH 01)

 

Visually

Sensitive Receivers

(VSR)

Description of Visually Sensitive Receivers

Minimum Distance between VSRs & Impact Source

Magnitude of Change

Sensitivity to Change

Significance Threshold – Landscape Impact

 

VSR 1

Road Users along access  road

< 15m

Intermediate

Medium

Moderate Impact

VSR 2

Road Users along Lin Ma Hang Road

< 10m

Intermediate

Medium

Moderate Impact

VSR 3

Residents @ Lin Ma Hang

(Low Rise Housing Development)

Approx.10m

Small

High

Moderate Impact

VSR 4

 

Residents near vehicular bridge @ Lin Ma Hang

(Individual Village houses/ Rural Fringe area)

< 10m

Small

Medium

Slight /

Moderate Impact

VSR 5

Residents near river bank @ Lin Ma Hang

 (Individual Village houses/ Rural Fringe area)

< 10m

Intermediate

High

Moderate / Significant  Impact

VSR 6

Residents near ancestral shrine @ Lin Ma Hang

(Individual Village houses/ Rural Fringe area)

Approx. 20m

Intermediate

High

Moderate / Significant  Impact

VSR 7

 

Residents near the temple @ Lin Ma Hang

(Low Rise Housing Development)

Approx. 35m

Small

Medium

Slight /

Moderate Impact

 


8.11                Recommended Landscape and Visual Impact Mitigation Measures

 

Introduction

 

8.11.1          Refer to Sections 8.5.24 - 8.5.25 for the rationale behind landscape mitigation measures, these mitigation measures devised took into account the following:

 

·                    consideration of surface finishes within and next to the drainage channel which are visually recessive;

·                    feasibility of mitigation measures in respect of funding, implementation phasing and maintenance.

 

Standards, Legislation and Guidelines

 

8.11.2          New landscape works will be designed in accordance with:

 

·                    Works Branch Technical Circular (WBTC) 17/2000 "Improvement to the Appearance of Slopes" which outlines the principles and procedures recommended for all departments involved in new slope formation and in upgrading and maintenance of existing slopes for improving the aesthetic and environmental impact of slope works.

·                    GEO Publication No 1/2000 "Technical Guidelines on Landscape Treatment and Bio-Engineering for Man-made Slopes and Retaining Walls" which prescribes good practice for the aesthetic landscape design of slopes and retaining walls.

·                    ETWB TC(W) No. 2/2004 “Maintenance of Vegetation and Hard Landscape Features” which defines the management and maintenance responsibilities for natural vegetation and landscape works, including both softworks and hardworks, and the authorities for tree preservation and felling. Minimum 1:1 compensatory ratio will be adopted in designing the planting mitigation works within the site boundary.

·                    ETWB TC(W) No. 29/2004 “Registration of Old and Valuable Trees, and Guidelines for their Preservation”. Removal of registered trees is prohibited.

·                    DSD Practice Note No. 1/2005 “Guidelines on Environmental Considerations on River Channel Design”.

·                    ETWB TC(W) No.11/2004 “Cyber Manual for Greening”.

·                     ETWB TC(W) No.5/2005 “Protection of Natural Streams/Rivers from Adverse Impacts arising from Construction Works”.

·                    ETWB TC(W) No. 3/2006 “Tree Preservation” which sets out the policy on tree preservation, and the procedures for control of tree felling, transplanting and pruning in Government projects.

 

Landscape Mitigation Measures

 

8.11.3          The proposed landscape mitigation proposal and measures and how they would be effective are illustrated in Figures 8.6A (I to V), 8.6B (I to III) and Figure 8.7 and Figure 8.7i (Landscape Mitigation Measures).

 

Summary of the Compensatory Tree Planting & Landscape Mitigation Planting Proposals:

 

The areas to receive LMM3 - Compensatory Tree Planting (Heavy Standard Trees) are as follows:

 

- MUP 03, 04A, 04B & 05              = 740 nos. of trees, approx. 1,100 m2
- LMH 01                                       = 11
nos. of trees, approx.   16 m2

 

Others areas are to receive riparian vegetation with the proposal for landscape mitigation measures 1, 2, 4 and 5 are as follows:

 

- MUP 03, 04A, 04, 04B & 05        = approx. 21,330 m2
- LMH 01                                        =
approx. 705   m2

 

LMM 1 (Landscape Mitigation Measure 1):

Gabions/ Gabion Mattress for Riparian Vegetation

 

Gabion/ Gabion Mattress, a wire mesh cage filled with loose stone - provide flexible structure for bank & bed protection and with the gaps in between the loose stone, suitable plants can be introduced. A sufficient planting medium (compacted clay and topsoil) is needed to cover the gabion / gabion mattress to accommodate roots of the proposed plants. Since the water level for the channel will rise during wet season and drop during dry season, plants that are proposed should be able to adapt the alternate wet and dry condition and must have the ability to regenerate in the next season. These may include but not limited to the following species (which are also species present in the area): Alocais macrorrhiza, Alopecurus aequalis, Bacopa monniera, Colocasia esculenta, Commelina diffusa, Cyperus pilosus, Ludwigia adscendens, Polygonum barbatum, Polygonum chinense, and Ranunculus scleratus. Further suggested species are listed in DSD Practice Note No. 1/2005 “Guidelines on Environmental Considerations for River Channel Design, Section 9.2.2 - Proposed plant list in channel bed and toe-zone”.

 

Areas to receive Gabion / Gabion Mattress and Riparian Vegetation are as follows:

 

- MUP 03, 04A, 04B & 05       :  approx.  4,170 m2               

- LMH 01                                  :  approx.  705 m2         

 


LMM 2 (Landscape Mitigation Measure 2):

Existing natural river bed to be retained or widened, using natural substrate (example rip-rap bedding) & Existing natural riverbank to be retained or reinforced using gabions/ gabion mattress for riparian vegetation (refer to different type of two-stage channel detail)

 

This measure has an emphasis on retaining or widening the existing natural riverbed and retaining or reinforcing the existing natural riverbank. Riprap bedding comprises of a layer of different sized, angular rocks or boulders to simulate the condition of natural pebble or stone stream/ riverbed. The space between the rocks provide good habitat for establishment of the ecosystem for flora and fauna.

 

Similar to LMM 1 above, further suggested species of plants are those that can adapt to dry and wet conditions are listed in DSD’s “Guidelines on Environmental Considerations for River Channel Design, Section 9.2.2 - Proposed plant list for channel bed and toe-zone”. Areas for planting are shown as below:

 

- MUP 03, 04A, 04B & 05       :  approx. 14,390 m2,             

- LMH 01                                  :  N/A        

 

LMM 3 (Landscape Mitigation Measure 3):

Compensatory tree planting along channel side

 

The 1-meter wide verge at one side or both sides of the channel are proposed for compensatory tree planting. Compensatory tree planting is intended to replace trees that cannot be retained or transplanted and will serve dual purpose of landscape impact mitigation as well as mitigating the loss of riparian trees in terms of ecological impact. The species of trees for planting along the channel sides are selected as being appropriate for the habitat of the river bank and are in accordance with DSD’s “Guidelines on Environmental Considerations for River Channel Design, Section 9.2.3 - Proposed plants for use along channel side”. Plant species which are known to be of high value to wildlife as recommended in the Ecology chapter (Section 7.9) should also be considered.

 


Table 8.8

List of Suitable Trees for Single Tree Planting

 

Scientific Name

Common Name

Recommended Size

Remarks

Approximate Percentage

Bischofia javanica

Autumn Maple

Heavy standard

Native / ornamental

5%

Castanopsis fissa

Chestnut Oak

Heavy standard

Small tree. Native

10%

Celtis sinensis

Chinese Hackberry

Heavy standard

Native

20%

Cleistocalyx operculatus

Water Banyan

Heavy standard

Native

35%

Cinnamomum burmannii

Indonesian Cinnamon

Heavy standard

Native

5%

Cinnamomum camphora

Camphor Tree

Heavy standard

Native

5%

Liquidambar formosana

Sweet Gum

Heavy standard

Native, Colour Foliage, Seasonal

10%

Sapium sebiferum

Tallow Tree

Heavy standard

Native

10%

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Notes:

Detailed planting proposals to be provided in the final Landscape Plan.

The final Landscape Plan should also take into account the recommended plant species which are known to be of high value to wildlife (see Section 7.9).

 

LMM 4 (Landscape Mitigation Measure 4):

Maintenance access ramps with grasscrete finish and planting with channel bed/ toe zone vegetation

 

Similar to LMM 1 & 2 above, plants species for LMM 4 should be plants that are able to adapt the alternate wet and dry conditions and have the ability to regenerate in the next season. Suggested species are listed in DSD’s “Guidelines on Environmental Considerations for River Channel Design, Section 9.2.2 - Proposed plant list in channel bed and toe-zone”.

 

These measures will only apply in MUP areas where grasscrete ramps are implemented in an area of approximately 2,180 m2. Mitigation measures could involve the establishing of plant communities from wild grass/flower seed mixes instead of turf. This would require a reduction in regular cutting (see Figure 8.7, LMM 4). Trials have shown that the plant community’s composition will change overtime due to the invasion by established species. However, the more diverse flora including the invading species resulting from the reduced cutting does lead to colonization by more diverse fauna, especially invertebrates (as shown in trial at Lam Tsuen River Channel).

 

LMM 5 (Landscape Mitigation Measure 5):

Mitigation planting along embankments

 

These measures will only apply in MUP05 areas (approximately 590 m2) - downstream portion of Ng Tung River, at the existing Wo Keng Shan Road Park. Proposed plants are those that are adapted to the area between the average high water level and top of the embankment as this area is close to water table, the moisture content in soil is relative high during the wet season. These may include but not limited to the following species (some of which are also species present in the area): Ficus hispida, Ficus viriolosa, Ilex pubescens, Ligustrum sinense, Rhododendron simsii, and Schefflera heptaphylla. Further suggested species are listed in DSD’s “Guidelines on Environmental Considerations for River Channel Design, Section 9.2.2 - Proposed plant list for planting at embankment”.

 

Tree Preservation

 

8.11.4          The Tree Survey Report in Annex 2 of Appendix H contains detailed information about the trees.

 

8.11.5          For trees not covered under ETWB TCW No. 29/2004; i.e. all trees in the Study Area, the following order of priority was adopted for tree removal considerations:

a)                  Retain the trees at their existing locations;

 

b)                  If a) is not possible, transplant the affected trees to other permanent locations within the site, unless the trees affected are of low conservation and amenity value, or have low survival rates or a low chance of recovering normal form after transplanting;

 

c)                  If both a) and b) are not possible, transplant the trees affected to a permanent, local, off site, location. Only trees with high conservation value or high amenity value, including rare and precious species and ‘transplantable’ trees are considered for this option.

 

d)                  Felling of trees to be considered as a last resort under the following circumstances:                 

-        there is no other practical alternative; or

-               the tree(s) has unrecoverable health problems and is in poor      condition; or

-         other justifications are provided by the project proponent.

 

8.11.6          Based on the currently available design information and the drainage layout indicated on the Figure 8.3A (I-V) and 8.3B (I-III), the treatment of the Existing Trees on site is summarized in Table 8.9.

 

8.11.7          The following section presents a qualitative and quantitative assessment of existing trees that can be retained or are suitable for transplanting. A total of 410 existing trees have been recorded within the site limit boundary. Table 8.9 below presents further data and indicates the number of trees required for compensatory tree planting during mitigation of construction impacts.

 


Table 8.9

Details of Tree Preservation

 

Areas

Trees to be Retained

Trees to be Transplanting

Trees to be Felled

Missing Trees

Dead
Trees

MUPs

246

17

117

-

3

LMH 01

30

0

1

-

-

 

8.11.8          A number of trees were found to be in direct conflict with the works due to their position on the widened channel alignment, the ramp and footpath area. In addition to selecting alignments to minimize the number of trees in such conflict with the works, trees suitable for transplanting were identified.

 

8.11.9          Trees suitable for transplanting were selected based on several criteria such as; good health and form; amenity and conservation value; and for good transplant survival rates for that species. Trees identified for Transplanting are to be transplanted within the site boundary to permanent locations identified as least affected by the construction operations.

 

8.11.10      Exotic species and self seeding /invasive/adventives species were given a lower rating for transplanting due to their lower conservation and amenity values and were deemed less suitable for transplanting.

 

8.11.11      Trees may also be considered as unsuitable for transplanting if their proximity to other trees is such that severe root damage is likely to be inadvertently caused (however careful the excavation process) in attempting to separate the trees for transplanting that the trees would be highly unlikely to survive. It should be noted that the rating for survivability in the tree schedule relates to the tree species general ability to survive transplanting only and does not indicate the particular site conditions of the individual tree.

 

8.11.12      Retaining trees in existing locations is the preferred preservation strategy according to the above order. This addresses also found in areas earmarked as verge as much as practical.

 

8.11.13      Native Trees (indigenous species) have generally a higher ecological value than exotic tree species. As part of the natural ecosystem, native trees support more indigenous flora and fauna than exotic trees by providing habitat space, food resources, nesting materials, etc. As data on native and exotic tree species were provided by the tree survey, a ratio of native to exotic tree species was calculated (see Annex 1 of Appendix H). This native-exotic tree ratio allowed a direct comparison of ecological values between different works area. Landscape elements such as tree clusters are not evenly distributed along the drainage corridors. Change would cause more significant impacts if trees were clustered, especially if of higher landscape-ecological value. A few examples are given below for MUP05.

 

MUP05

 

8.11.14      The tree vegetation in this area is dominated by the roadside planting (nearly 300 trees) of mainly exotic tree species along Sha Tau Kok Road. Most trees within the site limit are retained but some in some condition it is necessary to fell or transplant the trees. A few large species, such as Chinese Hackberry Tree (Celtis sinensis) (tree nos. T884, T973, T1001, T1028: 4 trees) including one with a climber, Derris trifoliate growing on it at Loi Tong village, Chinese Banyan (Ficus microcarpa) (tree no. T905: 1 tree) and Chinese Tallow Tree (Sapium sebiferum) (tree no. T1002: 1 tree) located within the channel, are native, in good to fair health condition and medium in amenity value, will be retained (preserved) with special treatment using gabion mattress. An indicative sketch showing the special treatment to preserve these existing trees within the channel is shown in Figure 8.7i.

 

8.11.15      Where the river meanders away from the road, more native trees are found. A private orchard near Loi Tung village features some large uncommon but cultivated trees. The highest tree abundance is present in the recreational park with about 151 trees near the intersection. The overall native-exotic tree ratio is about 0.50.

 

MUP 03, MUP04A and MUP04B

 

8.11.16      The tree conditions of MUP03, MUP04A and MUP04B are very similar and comparable to MUP05. Trees within the site limit are proposed to retained and some required to be felled or transplanted. A low density of trees is found in MUP 03 (24 trees) and MUP04A&B (31 trees). However, MUP 04A&B features more native trees (12 trees) such as Elephant’s Ear Tree (Macaranga tanarius), Ficus hispida & Ficus microcarpa than MUP 03.

 

LMH 01

 

8.11.17      In this are, the majority of trees are native species. 1 number tree, Weeping Willow (Salix babylonica), occurs within the site limit and is affected by the works and required to be felled.

 

Measures for Preservation and Protection of Trees

 

8.11.18      To ensure the preserved trees are not adversely affected during construction, the Contractor should submit a Tree Preservation and Protection Plan to the ET for review and Engineer for approval before commencing any works on site.

 

8.11.19      In addition, the Contractor should exercise the greatest care to avoid any damage to the preserved trees and should comply with the following in respect of all the preserved trees:

 

(i)                  No nails or other fixings shall be driven into the trees.

 

(ii)                No fencing, services, or signs other than the identification labels or markings shall be attached to any part of the trees.

 

(iii)               No trees shall be used as anchorages for ropes or chains used in guying or pulling or for equipment used for removing stumps, roots or other trees, or for any other purposes.

 

(iv)              No soil, materials, equipment or machinery shall be stockpiled or stored within the tree protection zones[1].

 

(v)                No site offices, workshops, canteens, containers or similar structures shall be installed within the tree protection zones.

 

(vi)              Excessive water shall be drained away from the tree protection zones to prevent damage to tree roots by asphyxiation.

 

(vii)             No passage or parking of vehicles and no operation of equipment or machinery shall take place within the tree protection zones unless otherwise agreed by the Engineer.

 

(viii)           No stripping of surface vegetation or top layer of soil shall be carried out within the tree protection zones unless otherwise agreed by the Engineer.

 

8.11.20      The Contractor should erect, secure and maintain in good condition temporary protective fencing to protect the preserved trees before commencement of any works within the site. The temporary protective fencing should be erected along or beyond the perimeter of the tree protection zone of each individual tree. If erection of temporary protective fencing is not practicable, temporary hessian armouring (or hessian and plank armouring) should be provided around tree trunks to protect the preserved trees. The Contractor should submit method statements including proposed design details of the temporary protective fencing or armouring to the ET for review and to the Engineer for approval.

 

8.11.21      Notwithstanding the above measures, the Contractor should also follow all the requirements listed in the General Specification for Civil Engineering Works: Section 26 – Preservation and Protection of Trees.

 

8.11.22      To enhance the health and the appearance of the preserved trees, advance tree surgery or pruning works may be necessary. The Contractor should provide detailed proposals and method statements to the ET for review and to the Engineer for approval before commencement of any tree surgery or pruning works. Pruning should be conducted in accordance with good arboriculture and horticultural practices.

 

8.11.23      The Contractor should assign a competent member of the site supervisory staff to oversee and supervise tree works related to horticultural operations and preservation of trees within the site, including, but without limitation to, planting, transplanting, tree surgery work, pruning and control of pest and disease affecting trees on the site.

 

Tree Transplanting

 

8.11.24      Selection criteria for determining tree suitable for transplanting are summarized below:

 

1. Health - determine if the tree is healthy, free of disease, infestation, is undamaged in any way.

 

2. Species - is the tree of a species worth retaining in some way - if really rare then a more sensible approach would be to revise the alignment. However, no registered tree or tree of conservation importance or rare/protected species was found in the Project area. A good specimen even if not rare then it could be a good candidate for transplanting. Invasive species, introduced species of no amenity value or very common, quick growing species and species that tend not to respond well to transplanting (e.g. many conifers) would be best avoided as candidates for transplanting also.

 

3. Size - Large trees, 500mm girth or larger (measured at 1m above ground level), which require specialized methods to transplant, have a lower survival rate than that of smaller trees and are also likely to be considerably damaged to their form using conventional transplanting techniques. Budget constraints may be a consideration in assessing the possibility of very large trees as only in the case of significant trees (or old or valuable trees) are the costs likely to be an acceptable proposition. The transplanting of large trees is therefore likely to be considered only when all other factors justify the attempt. 

 

4. Form - Trees of poor shape (even though they may be healthy) and multi-stem trees which are difficult to transplant.

 

5. Location - Certain trees may be situated in positions that are difficult to transplant from due to their location next to surfaces, utilities, structures etc that makes careful excavation and protection of the root difficult or impossible.

 

Compensatory Tree Planting (LMM3)

 

8.11.25      Where trees cannot be retained or transplanted and have to be felled, compensatory tree planting (LMM3) is proposed as shown in Figures 8.6A I-V to 8.6B I-III. In addition, existing retained and new slopes should be planted with suitable tree planting mixes for screening to mitigate views and other purposes. Based on the current available information, the approximate numbers of trees to be felled and compensated are summarized below.

 

 

Felled

Compensated

Ratio

MUPs

117 nos.

740 nos.

1 : 6.3

LMH01

1 no.

11 nos.

1 : 11

 

Old & Valuable Trees (OVT) / Trees for Religious Rituals

 

8.11.26      No OVT or trees for religious rituals have been identified.

 

Landscape Plan

 

8.11.27      As details of the proposed planting cannot be ascertain at the EIA stage, the preliminary design stage of the Project, it is recommended that a detailed Landscape Plan be submitted before commencement of planting or landscape works of the Project. The Landscape Plan should include the locations, size, number and species of plantings, design details, implementation programme, maintenance and management schedules, and drawings in scale of 1:1000 showing the landscape and visual mitigation measures. The Landscape Plan should also take into account plant species recommended in the Ecology chapter (see Section 7.9). The Landscape Plan should be certified by the ET Leader and verified by the IEC as conforming to the information, requirements and recommendations set out in the approved EIA Report before submission to the relevant authorities.

 

8.12                Residual Environmental Impact

 

Residual Landscape Impacts

 

8.12.1          The residual landscape impacts are defined and assessed as stipulated in Sections 8.5.26 - 8.5.28. Figures 8.6A to 8.6B and Figure 8.7 and Figure 8.7i illustrate the proposed landscape mitigation measures that would be incorporated into the Project to mitigate landscape impacts. Residual landscape impacts on landscape resources and landscape character are summarized in Tables 8.10A-B.

 


Residual Visual Impacts

 

8.12.2          Figures 8.8A to 8.8B illustrates the improvements that landscape mitigation measures would provide if incorporated into the Project. The residual visual impacts are summarized in Table 8.11. For the purposes of this report, the significance Threshold/ Landscape Impact is reduced by one level by the mitigation measures.

 

Table 8.10A

Landscape Impact MUP03, MUP04A, MUP04B & MUP05 – Assuming Mitigation

 

Landscape Character Area (LCA)

Location Reference

Magnitude of Change - Unmitigated

Sensitivity to Change - Unmitigated

Landscape Mitigation Measures

Significance Threshold – Landscape Impact Mitigated

LCA 1
Wooded Upland / Scrubland

 

At southern section (Princess Hill), North (Miu Keng) & East section (Near Shan Tong) of MUP05 and south eastern section of MUP04B, MUP03 (near Loi Tung Village)

Negligible

High

--

Negligible Impact

LCA 2

Active / Inactive Agriculture

At both sides of the drainage channel of MUP05 & MUP04A (Loi Tung Village)

Intermediate

Medium

LMM 1

LMM 2

LMM 3

Slight Impact

LCA 3

Used & Disused Fishponds

near Loi Tung Village at MUP04B

Negligible

Low

--

Negligible Impact

LCA 4

Residential Rural Fringe

Loi Tung Village at MUP03, MUP04A&B, Man Uk Pin area, along Wo Keng Shan Road, Tai Tong Wu area.

Negligible

High

LMM 1

Negligible Impact

LCA 5

Stream/ Drainage Channel

 

Along Ng Tung River:

Ch 1013.04 to Ch 944.39 (MUP05)

Intermediate

High

LMM 4

LMM 5

Moderate

Impact

Along Ng Tung River:

Ch 944.39 to Ch.0.00 (MUP05),

Ch 0.00 to Ch 184.00 (MUP04A)

Intermediate

High

LMM 2

LMM 4

Moderate

Impact

LCA 6

Public Open Space/ Park

 

Intersection location for Wo Keng Shan Road & Sha Tau Kok Road - Wo Hang (MUP05)

Large

High

LMM 3

LMM 4

LMM 5

Moderate

Impact

LCA 7

High Rise/ Commercial

N/A

N/A

N/A

N/A

 

LCA 8

Upland / Grassland

N/A

N/A

N/A

N/A

 

 

 

Table 8.10B

Landscape Impact LMH01 – Assuming Mitigation

 

Landscape Character Area (LCA)

Location Reference

Magnitude of Change - Unmitigated

Sensitivity to Change - Unmitigated

Landscape Mitigation Measures

Significance Threshold – Landscape Impact Mitigated

LCA 1
Wooded Upland / Scrubland

 

At North-eastern section of LMH 04, (Lin Ma Hang village) southern area (Tong To Shan Tsuen)

Small

Medium

LMM 1

Negligible Impact

LCA 2

Active / Inactive Agriculture

 

At both sides of the Shenzhen River channel and major area at southern section of the project site limit.

Small

Medium

LMM 1

Negligible Impact

LCA 3

Used & Disused Fishponds

Further from the site limit, Wang Lek area

Negligible

Low

--

Negligible Impact

LCA 4

Residential Rural Fringe

Lin Ma Hang

Small

Medium

LMM 1

Negligible Impact

LCA 5

Stream/ Drainage Channel

Along Shenzhen River

Small

Medium

LMM 1

Negligible Impact

LCA 6

Public Open Space/ Park

N/A

N/A

N/A

--

N/A

LCA 7

High Rise/ Commercial

N/A

N/A

N/A

--

N/A

LCA 8

Upland / Grassland

 

North, West and South western of project site (Wang Lek, Tong To Shan Tsuen)

Negligible

Low

--

Negligible Impact

 


Table 8.11A

Summary of Visual Impact - Assuming Mitigation (MUP03, MUP04A, MUP04B & MUP05)

 

Visually Sensitive Receivers (VSR)

Description of Visually Sensitive Receivers

Magnitude of Change -Unmitigated

Sensitivity to Change -Unmitigated

Landscape Mitigation Measures

Significance Threshold – Landscape Impact Mitigated

VSR 1

Road Users of  Wo Keng Shan Road (bridge)

Large

High

LMM 1, LMM 3, LMM 4, LMM 5

Slight Impact

VSR 2

Park Visitors @  Wo Keng Shan Road Garden

Intermediate

High

LMM 1, LMM 3, LMM 4, LMM 5

Slight Impact

VSR 3

Park Visitors @  Wo Keng Shan Road Garden

Intermediate

High

LMM 2, LMM 3, LMM 4, LMM 5

Slight Impact

VSR 4

 

Road Users of  Sha Tau Kok Road-Wo Hang

(Along the road)

Small

Medium

LMM 2, LMM 3,  LMM 5

Slight Impact

VSR 5

Residents @ toe of Princess Hill

(Individual Village houses/ Rural Fringe area)

Small

Low

LMM 1, LMM 3, LMM 5

Negligible Impact

VSR 6

Residents @ Loi Tung

(Individual Village houses/ Rural Fringe area)

Small

Medium

LMM 1, LMM 3

Negligible Impact

VSR 7

 

Residents @  Loi Tung (Active agricultural land)

Intermediate

Medium

LMM 1, LMM 3

Negligible Impact

VSR 8

 

Residents @ Loi Tung

(Low Rise Housing Development)

Small

Low

LMM 1, LMM 3

Negligible Impact

VSR 9

 

Residents @ Loi Tung

(Individual Village houses/ Rural Fringe area)

Negligible

Medium

LMM 3,

Negligible Impact

VSR 10

 

Residents @ Loi Tung

(Individual Village houses/ Rural Fringe area)

Small

Medium

LMM 2, LMM 3

Negligible Impact

VSR 11

 

Residents @ Loi Tung

(Individual Village houses/ Rural Fringe area)

Small

Medium

LMM 2, LMM 4

Negligible Impact

VSR 12

 

Residents @ Loi Tung

(Individual Village houses/ Rural Fringe area)

Small

Medium

LMM 2, LMM 3, LMM 4

Negligible Impact

VSR 13

 

Road Users of  Sha Tau Kok Road-Wo Hang (Along the road near MUP03)

Small

Low

LMM 1, LMM 3, LMM 4

Negligible Impact

VSR 14

 

Residents @ toe of small hill next to MUP01

(Individual Village houses/ Rural Fringe area)

Intermediate

Low

LMM 1, LMM 3

Negligible Impact

VSR 15

 

Residents @ near junction of Sha Tau Kok Road-Wo Hang & local road leading to Man Uk Pin Village

(Individual Village houses/ Rural Fringe area)

Small

Low

LMM 1, LMM 3

Negligible Impact

 


 Table 8.11B

Summary of Visual Impact – Assuming Mitigation (LMH01)

 

Visually Sensitive Receivers

Description of Visually Sensitive Receivers

Magnitude of Change -Unmitigated

Sensitivity to Change -Unmitigated

Landscape Mitigation Measures

Significance Threshold – Landscape Impact Mitigated

VSR 1

Road Users along access  road

Intermediate

Medium

LMM 1

Slight Impact

VSR 2

Road Users along Lin Ma Hang Road

Intermediate

Medium

LMM 1

Slight Impact

VSR 3

Residents @ Lin Ma Hang

(Low Rise Housing Development)

Small

High

LMM 1, LMM 3

Slight Impact

VSR 4

 

Residents near vehicular bridge @ Lin Ma Hang

(Individual Village houses/ Rural Fringe area)

Small

Medium

LMM 1

Negligible Impact

VSR 5

Residents near river bank @ Lin Ma Hang

 (Individual Village houses/ Rural Fringe area)

Intermediate

High

LMM 1

Negligible Impact

VSR 6

Residents near ancestral shrine @ Lin Ma Hang

(Individual Village houses/ Rural Fringe area)

Intermediate

High

LMM 1

Negligible Impact

VSR 7

 

Residents near the temple @ Lin Ma Hang

(Low Rise Housing Development)

Small

Medium

LMM 1

Negligible Impact

 

 

8.13                Environmental Monitoring and Audit Requirements

 

8.13.1          This Section defines the Environmental Monitoring and Audit (EM&A) requirements that have been recommended to ensure that the proposed landscape and visual mitigation measures are effectively implemented.

 

8.13.2          A key landscape design issue during detailed design will be the need for a high level of co-ordination and liaison between the design consultants and government to ensure that all recommended mitigation measures are effectively incorporated into the Project. The proposed works would unlikely be acceptable in landscape and visual terms if these mitigation measures are not incorporated. The landscape mitigation measures would need to be monitored as follows:

 

·                    LMM 1 (Landscape Mitigation Measure 1): Gabions / Gabion Mattress for Riparian Vegetation

A sufficient planting medium (compacted clay and topsoil) is needed to cover the gabion/ gabion mattress to accommodate roots of the proposed plants, plants that are proposed should be able to adapt the alternate wet and dry condition and must have the ability to regenerate in the next season. Suggested species are listed in DSD’s “Guidelines on Environmental Considerations for River Channel Design, Section 9.2.2 Proposed plant list in channel bed and toe zone”.

 

·                    LMM 2 (Landscape Mitigation Measure 2): Existing natural river bed to be retained or widened, using natural substrate (example rip-rap bedding) & Existing natural riverbank to be retained or reinforced using gabions/ gabion mattress for riparian vegetation (refer to different type of two-stage channel detail)

Similar to LMM 1, suggested species of plants are those that can adapt to dry and wet conditions will be proposed. Suggested species for gabion bank and widened river bed with natural substrate are listed in DSD’s “Guidelines on Environmental Considerations for River Channel Design, Section 9.2.2 Proposed plant list in channel bed and toe zone”.

 

·                    LMM 3 (Landscape Mitigation Measure 3): Compensatory tree planting along channel side

The 1 meter wide verge at one side or both sides of the channel are proposed for compensatory tree planting to serve dual purpose of mitigating the loss of riparian trees (ecological impact) as well as landscape impact. More species are listed in DSD’s “Guidelines on Environmental Considerations for River Channel Design, Section 9.2.3 Proposed plant list along channel side”.  Suggested percentage mixture of trees can be found in Table 8.8. Recommended plant species that are known to be of high value to wildlife as described in the Ecology chapter should also be included.

 

·                    LMM 4 (Landscape Mitigation Measure 4): Maintenance access ramps with grasscrete finish and planting with channel bed/ toe zone vegetation

Mitigation measures involve the establishing of plant communities from wild grass/flower seed mixes instead of turf. This would require a reduction in regular cutting. Suggested species are listed in DSD’s “Guidelines on Environmental Considerations for River Channel Design, Section 9.2.2 Proposed plant list in channel bed and toe zone”.

 

·                    LMM 5 (Landscape Mitigation Measure 5): Mitigation planting along embankments

Proposed plants that are adapted to the area between the average high water level and top of the embankment. As this area is close to water table, the moisture content in soil is relative high during the wet season. Suggested species are listed in DSD’s “Guidelines on Environmental Considerations for River Channel Design, Section 9.2.3 Proposed plant list for planting at embankment”.

 

 

 

8.13.3          In addition to the Landscape Mitigation Measures set out above, tree felling operations will be carried out just before commencement of works and tree debris to be removed immediately after felling. In order to speed up the restoration of greenery of the environment, advance compensatory planting will be carried out as far as practicable.

 

8.13.4          The proposed mitigation measures are listed in Table 8.12, together with an indication of funding, implementation, management and maintenance agencies. Generally, all landscape mitigation measures are to be implemented as early as possible.

 

8.13.5          Monitoring and audit should be undertaken during the construction and operation phases of the Project to ensure and check that the implementation and maintenance of landscape and visual mitigation measures are carried out.

 

8.13.6          A landscape auditor (as a member of the ET) shall be employed to review contractor’s submissions and proposals and to monitor and audit the contractor’s landscape works in particular to ensure the existing trees retained on-site are being well preserved, tree transplanting and felling operations are being undertaken in accordance with the requirements, procedures and specifications as stipulated in the contract and the approvals granted by concerned authorities, and all the newly planted vegetations are being maintained properly during the establishment period.

 

8.13.7          It is recommended that a detailed Landscape Plan be submitted before commencement of planting or landscape works of the Project. The Landscape Plan should include the locations, size, number and species of plantings, design details, implementation programme, maintenance and management schedules, and drawings in scale of 1:1000 showing the landscape and visual mitigation measures. The Landscape Plan should also take into account plant species recommended in the Ecology chapter. The Landscape Plan should be certified by the ET Leader and verified by the IEC as conforming to the information, requirements and recommendations set out in the approved EIA Report before submission to the relevant authorities.

 

8.13.8          Details of the monitoring and audit programme are presented in the EM&A Manual.

 


Table 8.12

Proposed Landscape and Visual Impact Mitigation Measures

 

LMM

No.

Mitigation Measures

Funding Agency

Implementation Agency

Maintenance / Management Agency

LMM1

Gabions/ Gabion Mattress for Riparian Vegetation

DSD

Construction Contractor

DSD

LMM2

Existing natural river bed to be retained or widened, using natural substrate (example rip-rap bedding) & Existing natural riverbank to be retained or reinforced using gabions/ gabion mattress for riparian vegetation (refer to different type of two-stage channel detail)

DSD

Construction Contractor

DSD

LMM3

Compensatory tree planting along channel side

DSD

Construction Contractor

DSD

LMM4

Maintenance access ramps with grasscrete finish and planting with channel bed/ toe zone vegetation

DSD

Construction Contractor

DSD

LMM5

Mitigation planting along embankments

DSD

Construction Contractor

DSD

 

Note:  Maintenance agency with reference to WBTC No. 14/2002 and ETWB TCW No. 2/2004.

 

8.14                Conclusions

 

Landscape Impacts

 

               MUP05, MUP04A, MUP04B and MUP03

 

8.14.1          The landscape impacts on the landscape resources and character are predicted to be negligible in LCA1 Wooded Upland/Shrubland, LCA3 Used / Disused Fishponds and LCA4 Residential Rural Fringe, as no or limited activities are carried out in these areas, even without mitigation measures incorporated into the Project. The landscape impacts on the landscape resources and character within LCA2 Active / Inactive Agriculture, LCA5 Stream / Drainage Channel and LCA6 Public Open Space / Park are predicted to be moderate to significant adverse without mitigation measures incorporated into the Project, due mainly to the loss of the highest portion of the existing trees lining the road and channel sides. The section of MUP 05 near the intersection of Sha Tau Kok and Wo Keng Shan Road features a recreational Park with more than 150 trees that are likely to be required to be removed along with loss of a large proportion of the park itself. Within LCA5 Stream / Drainage Channel, the retention of at least one natural riverbank side and the existing riverbed (LMM2) in MUP 05 and MUP 04A has changed the landscape character of park significantly.

 

8.14.2          Trees have been preserved or transplanted as far as practicable. The incorporation of landscape mitigation measures through retention of natural riverbed and banks, tree planting alongside channels, the planting of embankment and toe zone plant mixes would lessen the landscape impacts to moderate.

 

               LMH 01

 

8.14.3          The landscape impacts on the landscape resources and character are predicted to be slight in LCA1 Wooded Upland/Shrubland, LCA2 Active / Inactive Agriculture, LCA4 Residential Rural Fringe and LCA5 Stream / Drainage Channel, as no or limited bank improvement works are carried out in these areas, even without mitigation measures incorporated into the Project. The landscape impacts on the landscape resources and character within LCA3 Used / Disused Fishponds and LCA8 Upland Grassland are predicted to negligible adverse without mitigation measures incorporated into the Project. The incorporation of landscape mitigation measures through planting of embankment plant mixes would lessen the landscape impact to negligible overall. Demolishing and reconstruction of vehicular crossing is expected to have a slight positive impact on LCA4 Residential Rural Fringe through the improved access.

 

               Visual Impacts

 

8.14.4          The unmitigated visual impact of the Project on VSRs at MUP05 is predicted to be significant adverse, due to the loss of the roadside and drainage channel trees and surrounding vegetation and the partial widening of the existing channel, in close proximity to the residential amenities such as a recreational park. However, in the other areas of MUP05, MUP04A, MUP04B and MUP03 the unmitigated visual impacts are negligible or slight.

 

8.14.5          The unmitigated visual impact of the Project on VSRs at LMH01 is predicted to be negligible and slight adverse. The improvement of riverbanks might result in slight adverse impacts when unmitigated. The demolishing and reconstruction of vehicular crossings may have beneficial visual impacts as the newly constructed crossings are expected to be more visually acceptable.

 

8.14.6          It is predicted that, through the incorporation of the proposed mitigation measures, adverse visual impacts can be further reduced to negligible to slight in most cases. For MUP05, sufficient screen tree planting alongside the channel and embankment planting are expected to reduce the visual impacts after mitigation to slight adverse impacts. The use of vegetated gabions and gabions mattress will also reduce the visual impact of the drainage improvements.

 

Conclusion on Significance of Residual Impact

 

8.14.7          The significance of the residual landscape and visual impacts is evaluated as described in Annex 10 of the Technical Memorandum to the EIA Ordnance. There are some adverse effects, mainly due to tree loss and infringement into small plots of landscapes, but these can be eliminated, reduced or offset to a large extent by specific landscape measures. Some slight residual visual impact will remain for some of the viewer groups.

 

8.14.8          Overall, the drainage improvement in the Northern New Territories - Package C (the Project) within a flat disturbed landscape is considered to be acceptable with the implementation of mitigation measures recommended in this LVIA.

                                                                                                                                



[1]               “Tree protection zone” means an area the perimeter of which is defined by the dripline of the tree. “Dripline” of a tree means the imaginary vertical plumb line that extends downward from the tips of the outer most tree branches and intersects the ground.