7.1.1
The
EIA has recommended landscape and visual mitigation measures to be undertaken
during construction and operation phases of the Project. This section defines
the EM&A requirements to ensure the proposed landscape and visual impact
mitigation measures are effectively implemented.
7.1.2
The
construction phase EM&A of the landscape and visual environment and
mitigation works shall be carried out as part of the site audit programme. Specific
EM&A during operation phase of the Project is not required as long as the
proposed mitigation measures in the EIA and as depicted in the Landscape
Mitigation Plan are fully implemented.
7.2.1
Baseline
changes with respect to the landscape and visual environments should be carried
out in reference to the recorded baseline conditions of the site as described
in the EIA. The monitoring should in particular record changes of each
landscape resource, landscape character area and the view conditions of each
visually sensitive receiver. Parameters used to describe changes in each of the
above should be the same as in the EIA.
7.2.2
The
baseline monitoring should be conducted as a one-off site survey prior to
commencement of any construction works.
7.3.1
Monitoring
and audit should be undertaken during the construction and operation phases of
the Project to ensure and check that the implementation and maintenance of
landscape and visual mitigation measures are carried out. Site inspections
should be undertaken at least once every two weeks through the construction
period.
7.3.2
A landscape
auditor (as a member of the ET) shall be employed to review contractor’s
submission and proposals and to monitor and audit the contractor’s landscape
works in particular to ensure the existing trees retained on-site are being
well preserved, tree transplanting and felling operations are being undertaken
in accordance with the requirements, procedures and specifications as
stipulated in the contract and the approvals granted by concerned authorities,
and all the newly planted vegetations are being maintained properly during the
establishment period.
7.3.3
In
particular, the extent of the agreed works areas should be regularly checked
during the construction phase. Any trespass by the contractor outside the limit
of the works, including any damage to existing trees, woodland and vegetation
should be noted.
7.3.4
The
landscape auditor should also audit the proposed operation phase mitigation
measures in the EIA to ensure they are fully implemented within the Project
design and construction.
7.4.1
Should non-compliance of the
landscape and visual impacts occur, actions in accordance with the action plan
stated in Table 7.1 should be carried out.
Event and
Action Plan for Landscape and Visual Impact - Construction Phase
Action
Level |
Environmental
Team (ET) Leader |
Independent
Environmental Checker (IEC) |
Engineer’s Representative
(ER) |
Contractor |
Non-conformity on one occasion |
1.
Identify source 2.
Inform the IEC and the ER 3.
Discuss remedial actions with the
IEC, the ER and the Contractor 4.
Monitor remedial actions until
rectification has been completed |
1.
Check report 2.
Check the Contractor’s working
method 3.
Discuss with the ER and the
Contractor on possible remedial measures 4.
Advise the ER on effectiveness of
proposed remedial measures |
1.
Notify the Contractor 2.
Ensure remedial measures are
properly implemented |
1.
Amend working methods 2.
Rectify damage and undertake
remedial measures or any necessary replacement |
Repeated Non-conformity |
1.
Identify source 2.
Inform the IEC and the ER 3.
Increase monitoring (site audit)
frequency 4.
Discuss remedial actions with the
IEC, the ER and the Contractor 5.
Monitor remedial actions until
rectification has been completed 6.
If exceedance stops, cease
additional monitoring (site audit) |
1.
Check report 2.
Check the Contractor’s working
method 3.
Discuss with the ER and the
Contractor on possible remedial measures 4.
Advise the ER on effectiveness of
proposed remedial measures 5.
Supervise implementation of
remedial measures |
1.
Notify the Contractor 2.
Ensure remedial measures are
properly implemented |
1.
Amend working methods 2.
Rectify damage and undertake
remedial measures or any necessary replacement |
7.5
Landscape and Visual Impact
Mitigation Measures
7.5.1
The proposed works would unlikely be acceptable in landscape
and visual terms if these mitigation measures are not incorporated. The
landscape mitigation measures would need to be monitored as follows:
·
LMM 1 (Landscape Mitigation Measure 1): Gabions / Gabion
Mattress for Riparian Vegetation
Gabion/
Gabion Mattress, a wire mesh cage filled with loose stone - provide flexible
structure for bank & bed protection and with the gaps in between the loose
stone, suitable plants can be introduced. A sufficient planting medium
(compacted clay and topsoil) is needed to cover the gabion / gabion mattress to
accommodate roots of the proposed plants. Since the water level for the channel
will rise during wet season and drop during dry season, plants that are
proposed should be able to adapt the alternate wet and dry condition and must
have the ability to regenerate in the next season. These may include but not
limited to the following species (which are also species present in the area): Alocais macrorrhiza, Alopecurus aequalis, Bacopa monniera, Colocasia esculenta, Commelina
diffusa, Cyperus pilosus, Ludwigia adscendens, Polygonum barbatum, Polygonum chinense, and Ranunculus
scleratus. Further suggested species are listed in DSD Practice Note No.
1/2005 “Guidelines on Environmental Considerations for River Channel Design,
Section 9.2.2 - Proposed plant list in channel bed and toe-zone”. The areas to
receive LMM1 – Gabions / Gabion Mattress for Riparian Vegetation are as
follows:
- MUP 03, 04A, 04B & 05 = approx. 4,170 m2
- LMH01 = approx. 705 m2
·
LMM 2 (Landscape Mitigation Measure 2): Existing natural
river bed to be retained or widened, using natural substrate
(example rip-rap bedding) & Existing natural riverbank to be
retained or reinforced using gabions/ gabion mattress for riparian
vegetation (refer to different type of two-stage channel detail)
This measure has
an emphasis on retaining or widening the existing natural riverbed and
retaining or reinforcing the existing natural riverbank. Riprap bedding
comprises of a layer of different sized, angular rocks or boulders to simulate
the condition of natural pebble or stone stream/ riverbed. The space between
the rocks provide good habitat for establishment of the ecosystem for flora and
fauna.
Similar
to LMM 1 above, further suggested species of plants are those that can adapt to
dry and wet conditions are listed in DSD’s “Guidelines on Environmental
Considerations for River Channel Design, Section 9.2.2 - Proposed plant list
for channel bed and toe-zone”. The areas to receive LMM2 are as follows:
- MUP 03, 04A, 04B & 05 = approx. 14,390 m2
- LMH01 = N/A
·
LMM 3 (Landscape Mitigation Measure 3): Compensatory tree
planting along channel side
The
1 meter wide verge at one side or both sides of the channel are proposed for
compensatory tree planting. Compensatory tree planting is intended to replace
trees that cannot be retained or transplanted and will serve dual purpose of
landscape impact mitigation as well as mitigating the loss of riparian trees in
terms of ecological impact. More species are listed in DSD’s “Guidelines on
Environmental Considerations for River Channel Design, Section 9.2.3 Proposed
plant list along channel side”. Suggested
percentage mixture of trees can be found in Table 8.8 of the EIA Report. Recommended plant
species that are known to be of high value to wildlife as described in the
Ecology chapter of the EIA should also be included.
The areas to receive LMM3 – Compensatory Tree Planting (Heavy Standard Trees) are as follows:
- MUP 03, 04A, 04B & 05 = 740 nos. of trees, approx. 1,100 m2
- LMH01 = 11 nos. of trees, approx. 16 m2
·
LMM 4 (Landscape Mitigation Measure 4): Maintenance
access ramps with grasscrete finish and planting with channel bed/ toe zone
vegetation
Similar to LMM 1
& 2 above, plants species for LMM 4 should be plants that are able to adapt
the alternate wet and dry conditions and have the ability to regenerate in the
next season. Suggested species are listed in DSD’s “Guidelines on Environmental
Considerations for River Channel Design, Section 9.2.2 - Proposed plant list in
channel bed and toe-zone”.
Mitigation measures involve the establishing of plant communities from wild grass/flower seed mixes instead of turf. This would require a reduction in regular cutting. The areas to receive LMM 4 – Maintenance Access Ramps with Grasscrete Finish and Planting are as follows:
- MUP 05 = approx. 2,180 m2
- MUP 03, 04A&B, LMH01 = N/A
·
LMM 5 (Landscape Mitigation Measure 5): Mitigation
planting along embankments
Proposed plants that are adapted to the area between the average high water level and top of the embankment. As this area is close to water table, the moisture content in soil is relative high during the wet season. These may include but not limited to the following species (some of which are also species present in the area): Ficus hispida, Ficus viriolosa, Ilex pubescens, Ligustrum sinense, Rhododendron simsii, and Schefflera heptaphylla. Suggested species are listed in DSD’s “Guidelines on Environmental Considerations for River Channel Design, Section 9.2.3 Proposed plant list for planting at embankment”. The areas to receive LMM 5 – Mitigation Planting along Embankments are as follows:
- MUP 05 = approx. 590 m2
- MUP 03, 04A&B, LMH01 = N/A
Tree Preservation
7.5.2
The tree vegetation in MUP05
area is dominated by the roadside planting (nearly
300 trees) of mainly exotic tree species
along
Measures for Preservation
and Protection of Trees
7.5.3
To ensure the preserved trees
are not adversely affected during construction, the Contractor should submit a
Tree Preservation and Protection Plan to the ET for review and Engineer for
approval before commencing any works on site.
7.5.4
In addition, the Contractor
should exercise the greatest care to avoid any damage to the preserved trees
and should comply with the following in respect of all the preserved trees:
(i) No nails or other fixings shall be driven into the trees.
(ii) No fencing, services, or signs other than the identification labels or markings shall be attached to any part of the trees.
(iii) No trees shall be used as anchorages for ropes or chains used in guying or pulling or for equipment used for removing stumps, roots or other trees, or for any other purposes.
(iv) No soil, materials, equipment or machinery shall be stockpiled or stored within the tree protection zones[1].
(v) No site offices, workshops, canteens, containers or similar structures shall be installed within the tree protection zones.
(vi) Excessive water shall be drained away from the tree protection zones to prevent damage to tree roots by asphyxiation.
(vii) No passage or parking of vehicles and no operation of equipment or machinery shall take place within the tree protection zones unless otherwise agreed by the Engineer.
(viii) No stripping of surface vegetation or top layer of soil shall be carried out within the tree protection zones unless otherwise agreed by the Engineer.
7.5.5
The Contractor should erect,
secure and maintain in good condition temporary protective fencing to protect
the preserved trees before commencement of any works within the site. The
temporary protective fencing should be erected along or beyond the perimeter of
the tree protection zone of each individual tree. If erection of temporary
protective fencing is not practicable, temporary hessian armouring (or hessian
and plank armouring) should be provided around tree trunks to protect the
preserved trees. The Contractor should submit method statements including
proposed design details of the temporary protective fencing or armouring to the
ET for review and to the Engineer for approval.
7.5.6
Notwithstanding the above
measures, the Contractor should also follow all the requirements listed in the
General Specification for Civil Engineering Works: Section 26 – Preservation
and Protection of Trees.
7.5.7
To enhance the health and the
appearance of the preserved trees, advance tree surgery or pruning works may be
necessary. The Contractor should provide detailed proposals and method
statements to the ET for review and to the Engineer for approval before
commencement of any tree surgery or pruning works. Pruning should be conducted
in accordance with good arboriculture and horticultural practices.
7.5.8
The Contractor should assign a
competent member of the site supervisory staff to oversee and supervise tree
works related to horticultural operations and preservation of trees within the
site, including, but without limitation to, planting, transplanting, tree
surgery work, pruning and control of pest and disease affecting trees on the
site.
Tree
Transplanting
7.5.9
Selection criteria for determining tree suitable for
transplanting are summarized below:
1. Health - determine if the tree is healthy, free of
disease, infestation, is undamaged in any way.
2. Species - is the tree of a species worth retaining in
some way - if really rare then a more sensible approach would be to revise the
alignment. However, no registered tree or tree of conservation importance or
rare/protected species was found in the Project area. A good specimen even if
not rare then it could be a good candidate for transplanting. Invasive species,
introduced species of no amenity value or very common, quick growing species
and species that tend not to respond well to transplanting (e.g. many conifers)
would be best avoided as candidates for transplanting also.
3. Size - Large trees, 500mm girth or larger
(measured at 1m above ground level), which require specialized methods to
transplant, have a lower survival rate than that of smaller trees and are also
likely to be considerably damaged to their form using conventional
transplanting techniques. Budget constraints may be a consideration in
assessing the possibility of very large trees as only in the case of
significant trees (or old or valuable trees) are the costs likely to be an
acceptable proposition. The transplanting of large trees is therefore likely to
be considered only when all other factors justify the attempt.
4. Form - Trees of poor shape (even
though they may be healthy) and multi-stem trees which are difficult to
transplant.
5. Location - Certain trees may be
situated in positions that are difficult to transplant from due to their
location next to surfaces, utilities, structures etc that makes careful
excavation and protection of the root difficult or impossible.
Compensatory Tree
Planting (LMM3)
7.5.10
Where trees cannot be retained or transplanted and have to be
felled, compensatory tree planting (LMM3) is proposed as shown in Figures 8.6A I-V to 8.6B I-III (of the
EIA). In addition, existing retained
and new slopes should be planted with suitable tree planting mixes for
screening to mitigate views and other purposes. Based on the current available
information, the approximate numbers of trees to be felled and compensated are
summarized below.
|
Felled |
Compensated |
Ratio |
MUPs |
117 nos. |
740 nos. |
1 : 6.3 |
LMH01 |
1 no. |
11 nos. |
1 : 11 |
Landscape Plan
7.5.11
As details of the proposed
planting cannot be ascertain at the EIA stage, the preliminary design stage of
the Project, it is recommended that a detailed Landscape Plan be submitted
before commencement of the planting or landscape works of the Project. The
Landscape Plan should include the locations, size, number and species of
plantings, design details, implementation programme, maintenance and management
schedules, and drawings in scale of 1:1000 showing the landscape and visual
mitigation measures. The Landscape Plan should also take into account the plant
species recommended in the Ecology chapter. The Landscape Plan should be
certified by the ET Leader and verified by the IEC as conforming to the
information, requirements and recommendations set out in the approved EIA
Report before submission to the relevant authorities.
7.5.12
The
implementation schedule for the recommended mitigation measures is presented in
Appendix A.
7.5.13
If
the above measures are not sufficient to restore the impacts to acceptable
levels upon the advice of ET Leader, the Contractor shall liaise with the ET
Leader on some other mitigation measures, endorsed by IEC and propose to ER for
approval, and implement the mitigation measures.
[1] “Tree protection zone” means an area the perimeter of which is defined by the dripline of the tree. “Dripline” of a tree means the imaginary vertical plumb line that extends downward from the tips of the outer most tree branches and intersects the ground.