1.1.1
The “Drainage Improvement in
1.1.2
The proposed drainage improvements to be carried out involve
the construction of the secondary and local drainage channels at Lung Yeuk Tau,
Man Uk Pin and Loi Tung in the
1.1.3
The proposed drainage
improvement works (the Project), which are Designated Projects (DP) under the Environmental
Impact Assessment Ordinance (EIAO), are assessed in an Environmental Impact Assessment
(EIA) Report. The Project is DP under the EIAO by viture of I.1(b) of Schedule
2, Part I of the EIAO with specific Designated Project Elements as listed
below:
(i) Drainage channels at Man Uk Pin (MUP03, MUP04A, MUP04B and MUP05) that discharge into an area within 300m from the nearest boundary of an existing “Conservation Area” land used zoning [Item I.1(b)(vii) of Schedule 2 of EIAO].
(ii) Drainage channel at Lung Yeuk Tau (LYT04) that discharges into an area within 300m of an existing site of cultural heritage, the Entrance Tower of Ma Wat Wai at Ma Wat Wai, Lung Yeuk Tau [Item I.1(b)(ii) of Schedule 2 of EIAO].
(iii) Drainage channel at Lin Ma Hang (LMH01) that discharges into an area within 300m of a planned site of specific scientific interest (SSSI), Lin Ma Hang Stream, at Lin Ma Hang [Item I.1(b](i) of Schedule 2 of EIAO].
1.2.1
The proposed works are
Designated Projects (DP) under Schedule 2 Part I of the EIAO and require an
environmental permit under the EIAO for its construction and operation. An
application for an EIA Study Brief under section 5(1) of the EIAO was submitted
by DSD, the Applicant, on
1.2.2
The purpose of the EIA study is
to provide information on the nature and extent of environmental impacts
arising from the construction and operation of the proposed works and related
activities taking place concurrently, and to contribute to decisions on the
overall environmental acceptability of the Project.
1.2.3
The EIA provided an assessment of the potential environmental
impacts associated with the Project, in relation to the issues specified in the
EIA Study Brief No. ESB-103/2002 including air quality, noise, water quality,
waste management, ecology, landscape & visual and cultural heritage.
1.3
Project Location
and Scope
1.3.1
The drainage improvement works comprise the construction of
drainage channels and associated works to improve the secondary and local
drainage systems in Lung Yeuk Tau, Man Uk Pin, Loi Tung and Lin Ma Hang areas
of the
1.3.2
The original proposed improvement to drainage channel LYT04
in Lung Yeuk Tau involves the construction of an open channel along the
existing drainage box culvert which lies underneath the existing access road.
The proposed open channel is to increase the conveyance of flow from upland catchment
to the tributary of Ma Wat Channel near Ma Wat Wai so as to alleviate local
flooding near Shung Him Tong. During public consultation in early 2006, the
villagers of Shung Him Tong objected the original proposal of an open channel
along private land. The design of LYT04 was changed from an approximately 100m
long open channel to a similar length drainage box culvert underneath the
existing access. Based on the revised scope and design of the LYT04, the
proposed improvement works do not fall within the meaning of ‘drainage
channels’ under Category I in Schedule 2 of the EIAO. Therefore the proposed
works of LYT04 is not regarded as DP under the EIAO.
1.3.3
In summary, the scope of EIA study covers the Designated
Project (MUP03, MUP04A, MUP04B, MUP05 and LMH01) in Man Uk Pin and Lin Ma Hang
areas. The locations the DP channels are shown in Figure 1.
2.1
Description of
the Project
2.1.1
The Project comprises the construction of drainage channels
and associated works to improve the secondary and local drainage systems in the
Man Uk Pin, Loi Tung (MUP03, MUP04A, MUP04B & MUP05) and Lin Ma Hang (LMH01)
areas. The scale of the Project is
shown below.
Table 1
Scale of Proposed Drainage Works
Channel |
Proposed Works |
Extent of Works |
||
Approximate Length |
Approximate Width |
Approximate Depth |
||
MUP03 |
U-channel (Diameter = 0.6m) |
150m |
- |
- |
Drainage pipe (Diameter = 0.6m) |
12m |
- |
- |
|
Box culvert connecting MUP05 |
28m |
3m |
1m |
|
Trapezoidal channel with gabion walls and mattress
lining |
93m |
Top = 2.4m – 2.7m |
1.2m – 1.5m |
|
Re-provision of crossings |
One footbridge |
|||
MUP04A |
Trapezoidal channel with gabion walls and mattress
lining |
163m |
Top = 6.3m |
1.75m |
Drainage pipes (Diameter
= 1.95m) |
21m |
- |
- |
|
Re-provision of crossings |
Two vehicular bridges |
|||
MUP04B |
U-channel (Diameter = 0.9m) |
58m |
- |
- |
Drainage pipes (Diameter = 1.35m) |
138m |
- |
- |
|
MUP05 |
Trapezoidal channel with gabion walls and mattress
lining |
287m |
2m – 3m |
2m – 2.8m |
Trapezoidal channel with gabion walls and mattress
lining |
54m |
Top = 15.4m |
2.5m |
|
Two-stage channel with existing natural river bed
retained |
554m |
Top = 15.4m |
2.5m |
|
Trapezoidal channel with gabion walls and mattress
lining |
69m |
Top = 20.3m |
2.2m |
|
Box culvert |
50m |
3m |
2m |
|
Re-provision of crossings |
Five footbridges, four
vehicular bridges |
|||
LMH01 |
Gabion channel and localised bank improvement |
190m |
5m |
1.5m |
Re-provision of crossings |
Three vehicular bridges |
Notes:
Other ancillary works include provision of inle t/outlet pipes, box
culverts, maintenance ramps & accesses, re-provision of crossings and final
landscaping works.
2.2.1
The proposed alignment generally follows the alignment of
existing watercourses which is in line with the DMP Study to minimize
resumption of private land and disturbance to the adjacent ground.
2.2.2 Reference has been made to the government’s technical circulars on protection of natural streamcourses and DSD Practice Note on Environmental Considerations for River Channel Design. The concept of ‘avoidance’ has been incorporated into the design to protect ecologically important streams such as streamcourse in Lin Ma Hang and upstream part of the streamcourse in Loi Tung. For the other streamcourse with ecological significant, ‘Two-stage channel’ design with natural river banks and beds retained has been proposed. Other environmental friendly design such as the use of gabion banks and mattress lining which will encourage accumulation of sediments and eventually recolonisation of the channel bed by benthic community, are also adopted.
2.2.3 Environmental benefits and dis-benefits of various alternative drainage design options along with various other constraints were carefully evaluated before deriving the proposed design.
2.3
Justifications
and Benefits of the Project
2.3.1
The DMP Study investigated the need to improve secondary and
local drainage systems to alleviate flooding in the study area. The proposed
Project is expected to contribute to the relief of the present drainage
problems that have repeatedly led to severe flooding in the study area
resulting in danger to life, economic loss and disruption to everyday life.
2.3.2
The current standard of protection of the watercourses is
very low, with the majority having a protection standard of 1 year or less.
These watercourses were highlighted in the DMP Study as having insufficient
channel capacity leading to localized flooding. Upon completion of the Project,
the standard of protection will be increased to 1 in 10 years for village development.
2.3.3
The villagers in the Man Uk Pin and Lin Ma Hang areas of the
2.3.4
The layout plans of the proposed DP channels are shown in Figures
2 to 5.
2.4
Continuous Public
Involvement
2.4.1
Public consultation including site meetings with the Green
Groups, Sha Tau Kok Rural Committee, North District Council and village representatives
were undertaken during the course of the EIA study. Overall, there were no
objections to the final design and the relevant village representatives and
Rural Committees supported the proposed Project as it would bring relieve to
the flooding in the area and the proposed works are environmentally acceptable.
2.5.1
The construction programme of the Project will commence in
end 2007 for completion by mid 2011.
3.1.1
The air quality impact
assessment has identified Air Sensitive Receivers (ASRs) within the Study Area.
Potential works that may cause potential construction dust nuisance is also
identified. Mitigation measures, as required by Air Pollution Control
(Construction Dust) Regulation, are also highlighted. Provided that all the
necessary mitigation measures are implemented, residual construction dust impact
at nearby representative sensitive receivers is expected to comply with the Air
Quality Objectives.
3.2.1
The
use of powered mechanical equipment during the construction phase of this
drainage project is expected to create noise nuisance, due to the close
proximity between the works areas and noise sensitive receivers. Assessment
indicates that such noise impacts can be mitigated to acceptable levels by
appropriate measures, including the use of quiet plant, temporary noise
barriers, restricting concurrent usage of equipment and the implementation of
good site practices. The contractor will be required to implement these
measures when powered mechanical equipment is used during the construction
phase. With these mitigation measures in place, adverse residual noise impact would not be expected from the construction
works.
3.3.1 The current condition of the water bodies in the Study Area is relatively poor in the lower stretches with many of the streams receiving a variety of polluting inputs including livestock waste, and domestic wastewater from local villages.
3.3.2 The construction of the channels could adversely impact the water bodies through silt-laden site runoff, disturbance of stream sediment during excavation, concreting works, runoff from workshops & depot and increased sewage and wastewater resulting from the additional workforce on site. These impacts can be readily mitigated through the construction of a suitable drainage system with silt traps, good site management practices, careful working practices during excavation of the stream and proper sewage collection and disposal system. With the implementation of these measures, no adverse residual water quality impact from construction work is expected.
3.3.3
The major operational impacts
are a net increase in pollutant loadings to
3.4.1 Construction and demolition materials will inevitably be produced during the construction phase of the Project. Waste generated during construction works includes site clearance / demolition materials, excavated materials, chemical waste and general works waste. Waste types, quantities and timing have been estimated as far as possible and mitigation measures have been proposed in terms of avoidance-minimisation-reuse-recycling-disposal hierarchy. Potential for reuse of inert construction & demolition material (public fill) within the Project will be rigorously explored in an effort to minimise off-site disposal.
3.4.2 Provided that there is strict control of construction and demolition materials generated from construction works and that all arisings are stored, handled, transported and disposed of in accordance with the recommended mitigation measures, potential impact is not expected. The recommended waste management measures can be enforced by incorporating them into an environmental management plan as part of the contract document.
3.4.3 Waste generated during operational maintenance is expected to be minimal. Proper waste management practices similar to those for construction impacts have been recommended.
3.5.1
The proposed works at MUP03 and MUP04B would have no
significant ecological impacts even in the absence of mitigation measures
because they are existing roadside concrete lined drainage systems.
3.5.2
Proposed works at LMH01 were predicted to have minor
construction phase impacts on fauna of conservation importance in the absence
of mitigation. However, these can be fully mitigated by restricting works to
the dry season between November and March in the coming year and implementing
site management practices. With these measures in place potential impacts are
considered to be very small and acceptable.
3.5.3
Proposed works at MUP04A were predicted to have low to
moderate permanent adverse impacts on a stream and adjacent area of
long-inactive agricultural land. However, all impacts will now be avoided by
not channelising the upper section of this stream.
3.5.4
Proposed works at MUP05 were predicted to have moderate and
adverse impacts on a natural streamcourse with natural bed, banks and riparian
corridor. Substantial design changes in terms of ‘Two-stage channel’ with natural
stream banks and beds retained which are in accordance with the advice
contained in ETWB and DSD Technical Circulars and DSD Practice Note have been
adopted. These environmental friendly channel designs along with site
management measures and tree planting will significantly reduce the predicted
impacts to an acceptable level.
3.5.5
With these avoidance, minimization and mitigation measures in
place, all adverse ecological impacts of the project on MUP05 would be
eliminated or reduced to low and acceptable level. Low adverse impacts on
riparian vegetation are unavoidable but would be fully mitigated in time and
are considered acceptable in the overall context of the project.
3.6
Landscape and
Visual Impact
Landscape Impact
3.6.1 The landscape impacts on the landscape resources and character of MUP03, MUP04A, MUP04B and MUP05 are predicted to range from negligible to moderate, mainly due to the loss of the existing trees separating the existing road and channel sides. The retention of at least one natural riverbank side and the existing riverbed in MUP05 and minimizing the works at MUP04A have reduced the landscape impact largely. The incorporation of landscape mitigation measures through retention of natural riverbed and banks, tree planting alongside channels, the planting of embankment and toe zone plant mixes would lessen the landscape impacts to negligible to slight.
3.6.2
The landscape impacts on the landscape resources and
character of LMH01 are predicted to range from slight to negligible adverse.
The incorporation of landscape mitigation measures through planting of
embankment plant mixes would lessen the landscape impact to negligible overall.
Demolishing and reconstruction of vehicular crossing is expected to have a
slight positive impact on Residential Rural Fringe through the improved access.
Visual Impact
3.6.3 The unmitigated visual impact of the Project on Visual Sensitive Receivers (VSRs) at MUP05 is predicted to be significant adverse, due to the loss of the roadside and drainage channel trees and surrounding vegetation and the partial widening of the existing channel, in close proximity to the residential amenities such as a recreational park. However, in the other areas of MUP05, MUP04A, MUP04B and MUP03, the unmitigated visual impacts are negligible or slight.
3.6.4 The unmitigated visual impact of the Project on VSRs at LMH01 is predicted to be negligible and slight adverse. The demolishing and reconstruction of vehicular crossings may have beneficial visual impacts as the newly constructed crossings are expected to be more visually acceptable.
3.6.5 It is predicted that, through the incorporation of the proposed mitigation measures, adverse visual impacts can be further reduced to negligible to slight in most cases. For MUP05, sufficient screen tree planting alongside the channel and embankment planting are expected to reduce the visual impacts after mitigation to slight adverse impacts.
3.6.6 Overall, the drainage improvement in the Project within a flat disturbed landscape is considered to be acceptable with the implementation of mitigation measures recommended in the EIA.
3.7.1
The
proposed drainage works will have no adverse impact on archaeological resources
in either the construction or operational phases. The majority of built heritage features
recorded in the survey will also not be adversely impacted. Potential impacts to
a stone terrace wall were identified only for the construction phase of the
project in the Lin Ma Hang Study Area and appropriate mitigation measures have
been proposed to negate the identified impacts. No operational phase impact on
the built heritage features is expected.
3.8
Environmental
Monitoring and Audit
3.8.1
Mitigation
measures have been recommended in the EIA Report to mitigate potential adverse
impacts from the construction and operation phases of the Project. Based on
these recommendations, Environmental Monitoring and Audit (EM&A)
requirements have been established.
3.8.2
An EM&A
programme will be setup and implemented to ensure compliance with the
mitigation measures recommended in the EIA Report, to assess the effectiveness
of the recommended mitigation measures, and to identify any further need for additional
mitigation measures or remedial measures.
3.8.3
To ensure that the environmental performance of the works
meet all relevant legal and contractual requirements, the contractor will be
required to prepare and implement an Environmental Management Plan, which
details the approach that the contractor is to adopt in managing and
controlling potential environmental impact from construction activities for
this Project.
4.1.1
Based on the findings of the EIA Study, the Project would not
cause any adverse environmental impacts to the concerned Conservation Area (for
MUP03, MUP04A, MUP04B and MUP05) and the planned SSSI i.e. Lin Ma Hang stream
(for LMH01). The residual impacts during construction are considered
acceptable. Residual operational phase impacts will
also be acceptable.
4.1.2
In summary the EIA concludes
that there are no unacceptable environmental impacts associated with the construction
and operation of the proposed secondary channels (MUP03, MUP04A, MUP04B, MUP05
and LMH01) provided that all the legislation, guidelines and recommended mitigation
measures are followed. The EIA has fully met the requirements of the Technical
Memorandum on EIA Process and the EIA Study Brief.
END OF TEXT