TABLE OF CONTENT
Environmental Monitoring and Audit
Requirements
Air Quality Mitigation Measures
Water Quality Mitigation Measures
5. WASTE MANAGEMENT IMPLICATIONS
Waste Control and Mitigation Measures
Ecological Mitigation Measures
Ecological Monitoring and Audit Requirements
Compliance with Legal and Contractual
Requirements
Quarterly EM&A Summary Reports
Interim Notifications of Environmental
Quality Limit Exceedances
Appendices
Appendix
A Implementation Schedule of
Mitigation Measures
Appendix B Construction Stage Noise Monitoring Field Record Sheet
Appendix C Incident Report on Action Level or Limit Level Non-compliance
List of Tables
Table 2.1....... Acceptable Noise Levels (ANLs)
Table 2.2....... Noise Monitoring Stations during
Construction Phase
Table 2.3....... Action and Limit Levels for Construction
Noise
Table 2.4....... Event / Action Plan for Construction Noise
Table 2.5....... Quieter PME
Recommended for Adoption during Construction Phase
Table 2.6....... Plant Inventory for the Low Impact Method
List of Figures
Figure 1.1 Location
Plan for the Proposed Project
Figure 1.2 Project
Organization for Environmental Management
Figure 2.1 Location
of Construction Noise Monitoring Station
Figure 2.2 Typical
Section of Proposed Temporary Barrier
Figure 2.3 Typical
Design of Noise Enclosure
Project Description
1.1
The Sha Tin and Tai Po Drainage Master Plan (DMP) Study, completed in October
1999, indicated that certain stormwater drains and natural
rivers/streamcourses in the Sha Tin and Tai Po areas did not have the required
hydraulic capacity to meet the flow requirements. To minimize the risks of flooding
and to cope with future developments as identified in the DMP Study,
construction of river channels, upgrading of existing stormwater drains,
construction of flood pumping stations in the low-lying areas and other minor
drainage facilities were recommended.
1.2
Upon completion of the DMP Study, Drainage Services
Department (DSD) of Hong Kong SAR Government commissioned Maunsell Consultants
Asia Ltd. (MCAL) to undertake Agreement No. CE50/2001 (DS) Drainage Improvement
in Sha Tin and Tai Po – Design and Construction (hereinafter referred to as
“the Assignment”), for implementing the drainage improvement works at
various locations as recommended by the DMP study to alleviate the
potential flooding problems in Sha Tin and Tai Po districts.
1.3
This manual presents the
environmental monitoring and auditing requirements associated with the proposed drainage improvement
works in Shuen Wan (the Project),
which comprises the following five works items:
§
Construction of a
§
Replacement of existing gates by automatic mechanical gates
at the mouth of Wai Ha River
§
Construction of a
§
Construction of a
§
Construction of a floodwater pumping station at Shuen Wan
1.4
An Environmental Impact
Assessment (EIA) study has been conducted to provide information on the nature
and extent of potential environmental impacts pertinent to the construction and
operation of the Project. The findings
are presented in a separate EIA Report.
1.5
Figure 1.1 shows the location of the
Project.
1.6
As part of the EIA study, the purpose of this Environmental
Monitoring and Audit (EM&A) Manual is to provide
guidelines for the setting up of an EM&A programme to check on compliance with the environmental
protection conditions, EIA Report recommendations, assess the effectiveness of the
recommended mitigation measures, and identify any need for additional
mitigation measures or remedial action.
This Manual also outlines the monitoring and audit
programme for the construction and operation phases of the works
proposed under the Project.
1.7
The EM&A Manual has been prepared
in accordance with the requirements stipulated in Annex 21 of the Technical
Memorandum on the EIA Process (EIAO TM).
1.8
This Manual contains the following information:
§
Responsibilities of the Contractor, the Engineer or
Engineer’s Representative (ER), Environmental Team (ET) and Independent
Environmental Checker (IEC) with respect to the EM&A requirements during
the implementation of the Project.
§
Information on the project organization and programming of
construction activities.
§
Project construction schedule and necessary environmental
monitoring and audit programme to track environmental impacts.
§
Requirements for the review of pollution sources and working
procedures in the event of non-compliance of the project’s environmental
performance criteria.
§
Environmental monitoring protocols and their technical requirements.
§
Environmental auditing procedures.
§
Requirements for the documentation of environmental
monitoring and audit data, and appropriate reporting procedures.
§
Complaint resolution procedures.
1.9
For the purpose of this Manual, the ET leader, who should be
responsible for and in charge of the ET, should refer to the person or
party delegated
the role of executing the respective EM&A requirements.
1.10
The preliminary project programme
for this Project is presented in Table
1.1.
Table 1.1 Preliminary Project Programme
Task Description |
Tentative/Actual Completion Date |
Selection
of the Scheme |
May 2005 |
Detailed
Design of Works |
February 2007 |
Commencement
of Works Contract |
December 2007 |
Completion
of the Contract |
June 2010 |
Environmental Monitoring and Audit Requirements
1.11
The construction and operational
phase environmental impacts of the Project were assessed, and are presented in
the EIA report on Drainage Improvement in Sha Tin and Tai Po – Design and Construction. The EIA report has identified the recommended
environmental mitigation measures to minimize the potential adverse
environmental impacts identified. An
implementation schedule of the recommended mitigation measures is also prepared
as part of the EIA study and is provided in Appendix A of this Manual.
1.12
The proposed project organisation and lines of communication
with respect to environmental protection works are shown in Figure 1.2.
1.13
The general
duties/responsibilities of various parties comprise the following:
Engineer or
Engineer’s Representative (ER)
1.14
The term ER, refers to the organisation
responsible for overseeing the construction works or
operation of
the Project undertaken by various Contractors, and for ensuring that the
construction works are undertaken by the Contractors in accordance with the specification
and requirements in the Contract.
The ER should:
§
Monitor the Contractors’ compliance with contract
specifications, including Environmental Permit (EP) conditions, and the
implementation and operation of the environmental mitigation measures.
§
Follow the requirements in the agreed Event / Action Plan in
the event of any exceedance.
§
Provide assistance to the ET as necessary in the
implementation of the EM&A programme.
§
Engage IEC services to audit EM&A works carried out by
the ET.
§
Require the Contractor to follow the agreed protocols or
those in the contract specifications in the event of exceedance or complaints.
The Contractor
1.15
The term “Contractor” should be taken to mean all
construction contractors and sub-contractors, working on site at any one
time. Besides reporting to the ER, the Contractor should:
§
Work within the scope of the relevant requirements in the
contract and EP.
§
Participate in site inspections undertaken by the ET and
undertake any corrective actions as necessary.
§
Provide information / advice to the ET regarding works
activities which may contribute to the generation of adverse environmental
conditions.
§
Implement measures to reduce impact where Action and Limit
levels are exceeded.
§
Submit proposals on mitigation measures in case of
exceedances of Action and Limit levels in accordance with the Event / Action
Plans.
§
Follow the procedures for carrying out complaint investigation.
Independent
Environmental Checker (IEC)
1.16
The IEC should advise the ER on
environmental issues related to the Project, and should be empowered to audit
the environmental performance of construction.
1.17
The IEC should have at least 7 years’ local experience in
EM&A and ecology, and one year of which should be
relevant to recent ecological survey / monitoring work in the Shuen Wan
area. The IEC should also have relevant
professional qualifications, which should include being an Accredited Monitoring
Professional of the Hong Kong Institute of Environmental Impact Assessment
(HKIEIA), and have relevant project management experience. The appointment of the IEC
is subject to the approval of the ER. The IEC should be
employed prior to the commencement of the construction of the Project.
1.18
The main duty of the IEC is to
carry out environmental audit of the project; this should include, inter alia,
the following:
§
Review and audit all aspects of the EM&A programme.
§
Validate and confirm the accuracy of monitoring results,
monitoring equipment, monitoring locations, monitoring procedures and locations
of sensitive receivers.
§
Carry out random sample check and audit on monitoring data
and sampling procedures.
§
Conduct random site inspection.
§
Audit the EIA recommendations and requirements against the
status of implementation of environmental protection measures on site.
§
Review the effectiveness of environmental mitigation
measures and project environmental performance.
§
On a need basis, verify and certify the environmental
acceptability of the Contractor’s construction methodology (both temporary and
permanent works), relevant design plans and submissions under the EP. Where necessary, the IEC should seek the least
impact alternative in consultation with ET leader and the Contractor.
§
Verify the investigation results of complaint cases and the
effectiveness of corrective measures.
§
Verify EM&A report that has been certified by the ET
leader.
§
Feedback audit results to ET according to Event and Action
Plan in the manual.
§
Conduct a specific monitoring programme of the compensatory
ecological habitats. Details of the
monitoring requirements are set out in Section 6.16 of this Manual.
Environmental Team (ET)
1.19
The ET leader and the ET should be
employed to conduct the EM&A programme and check the Contractor’s
compliance with the Project’s environmental performance requirements during
construction. The ET should be led
and managed by
the ET leader.
1.20
The ET leader should be an independent
party from the Contractor and should possess at least 7 years’ local experience
of EM&A and have relevant professional qualifications, which should include
being an Accredited Monitoring Professional of the Hong Kong Institute of Environmental
Impact Assessment (HKIEIA).
The ET leader should have at least 3 years of experience in ecological
monitoring given ecological impact would be the key environmental issue of this
Project. The appointment of the ET is
subject to the approval of the ER and the Director of Environmental Protection.
1.21
Suitably qualified staff should be included in the ET, and
resources for the implementation of the EM&A programme should be allocated
in time under the Contract, to enable fulfilment of the requirements as
specified in the EM&A Manual during construction and operation of the
Project.
1.22
Duties of the ET
are:
§
Conduct sampling, analysis and statistical evaluation of
monitoring parameters with reference to the EIA study recommendations and
requirements.
§
Conduct environmental site surveillance.
§
Audit of compliance with environmental protection, and
pollution prevention and control regulations.
§
Monitor the implementation of environmental mitigation
measures.
§
Monitor compliance with the environmental protection
clauses/specifications in the Contract.
§
Review construction programme and comment as necessary.
§
Review construction methodology and comment as necessary.
§
Conduct complaint investigation, evaluation and
identification of corrective measures.
§
Liaise with IEC on all environmental performance matters,
and timely submit all relevant EM&A proforma for IEC’s approval.
§
Provide advice to the Contractor on environmental
improvement, awareness, enhancement matters, etc. on site.
§
Submit EM&A report timely to the Project Proponent and
the Director of Environmental Protection.
1.23
Sufficient and suitably qualified professional and technical
staff should be employed by the respective parties to confirm full compliance with
their duties and responsibilities, as required under the EM&A programme for
the duration of the Project.
2.1
In this section, the requirements, methodology, equipment, monitoring
locations, criteria and protocols for the monitoring and audit of noise impacts
during the construction phase of the Project are presented.
2.2
The construction noise level should be measured in terms of
the A-weighted equivalent continuous sound pressure level (Leq). Leq (30 minutes) should
be used as the monitoring parameter for the time period between 0700 and 1900
hours on normal weekdays. For all other
time periods, Leq (5 minutes) should be employed for
comparison with the Noise Control Ordinance (NCO) criteria.
2.3
Supplementary information for data auditing, statistical
results such as L10 and L90 should also be obtained for
reference. A sample data record sheet is
shown in Appendix B for reference.
2.4
Whilst the Noise Control Ordinance (NCO) does not provide
for the statutory control of construction activities occurring on weekdays
during normal working hours (i.e. Monday to Saturday inclusive 0700-1900
hours), a daytime standard of LAeq(30 minute) 75dB stipulated in Annex
5 of the Technical Memorandum on Environmental Impact Assessment Process is
used as the appropriate criterion for all residential dwellings; while a
daytime standard of LAeq(30 minute) 70dB was adopted for all
educational institutions during normal school days and LAeq (30
minute) 65dB during examination periods.
2.5
The NCO provides statutory controls on general construction
works during restricted hours (i.e. 1900-0700 hours Monday to Saturday and at
any time on Sundays and public holidays). The ANLs for evenings and holidays
and for night-time are dependent on the Area Sensitivity Rating at the NSR. The
relevant ANLs are provided in Table 2.1.
Table 2.1 Acceptable
Noise Levels (ANLs)
Time Period |
Area Sensitivity Rating |
||
A |
B |
C |
|
All days during the evening (1900-2300 hours) and
general holidays (including Sundays) during the day and evening (0700-2300
hours) All days during the night-time (2300-0700) |
60 |
65 |
70 |
45 |
50 |
55 |
2.6
As referred to in the Technical Memorandum (TM) issued under
the NCO, sound level meters in compliance with the International
Electrotechnical Commission Publications 651: 1979 (Type 1) and 804: 1985 (Type
1) specifications should be used for carrying out the noise monitoring. Immediately prior to and following each noise
measurement the accuracy of the sound level meter should be checked using an
acoustic calibrator generating a known sound pressure level at a known
frequency. Measurements may be accepted
as valid only if the calibration level from before and after the noise
measurement agree to within 1.0 dB.
2.7
Noise measurements should not be made in the presence of
fog, rain, wind with a steady speed exceeding 5ms-1 or wind with
gusts exceeding 10ms-1. The wind speed should be checked with a
portable wind speed meter capable of measuring the wind speed in m/s.
2.8
The ET is responsible for the provision of the monitoring
equipment. He should confirm that
sufficient noise measuring equipment and associated instrumentation are
available for carrying out the baseline monitoring, regular impact monitoring
and ad hoc monitoring. All the equipment
and associated instrumentation should be clearly labelled.
2.9
Based on the EIA study, four worst affected locations are
designated for construction noise monitoring as listed in Table 2.2 and
illustrated in Figure 2.1. The status and location of noise sensitive
receivers may change after issuing this manual.
If such cases exist, the ET Leader should propose updated monitoring
locations and seek approval from ER and agreement from the IEC and EPD on the
proposal.
Table 2.2 Noise
Monitoring Stations during Construction Phase
Noise Monitoring Station |
Noise Monitoring Location |
M1 |
14, Shuen Wan Chim Uk |
M2 |
150, San Tau Kok |
M3 |
31, Wai Ha |
M4 |
Block 15,
Treasure Spot Garden |
2.10
When alternative monitoring locations are proposed, the
monitoring locations should be chosen based on the following criteria:
§
Monitoring at sensitive receivers close to the major site
activities which are likely to have noise impacts;
§
Monitoring at the noise sensitive receivers as defined in
the Technical Memorandum;
§
Assurance of minimal disturbance to the occupants during
monitoring.
2.11
The monitoring station should normally be at a point
2.12
The ET should carry out baseline noise monitoring prior to
the commencement of the construction works.
The baseline monitoring should be measured for a continuous period of at
least 14 consecutive days at a minimum logging interval of 30 minutes (as six consecutive
LAeq, 5 min readings) for daytime and 15 minutes (as three
consecutive LAeq, 5min readings) for evening time and night
time. The Leq, L10
and L90 should be recorded at the specified interval. A schedule on the baseline monitoring should
be submitted to the IEC and EPD for approval before the monitoring starts.
2.13
There should not be any construction activities in the
vicinity of the stations during the baseline monitoring. Any non-project related construction
activities in the vicinity of the stations during the baseline monitoring
should be noted and the source and location recorded.
2.14
In exceptional cases, when insufficient baseline monitoring
data or questionable results are obtained, the ET should liaise with the EPD to
agree on an appropriate set of data to be used as a baseline reference and
submit to the ER for approval.
2.15
Noise monitoring should be carried out at all the designated
monitoring stations. The monitoring
frequency should depend on the scale of the construction activities. The following is an initial guide on the
regular monitoring frequency for each station on a weekly basis when noise
generating activities are underway:
§
one set of measurements between 0700 and 1900 hours on
normal weekdays.
2.16
In case of non-compliance with the construction noise
criteria, more frequent monitoring, as specified in the Action Plan in Table 2.4, should be carried out. This additional monitoring should be
continued until the recorded noise levels are rectified or proved to be
irrelevant to the construction activities.
2.17
The Action and Limit levels for construction noise are
defined in Table 2.3. Should non-compliance of the criteria occur,
action in accordance with the Action Plan in Table 2.4 should be carried out.
Table 2.3 Action
and Limit Levels for Construction Noise
Time Period |
Action Level |
Limit Level |
0700 – 1900 hours on
normal weekdays |
When one documented complaint
is received |
75
dB(A) |
*Acceptable Noise Levels for Area
Sensitivity Rating of A/B/C.
Table 2.4 Event / Action Plan for Construction
Noise
EVENT |
ACTION |
|||
|
ET Leader |
IEC |
ER |
CONTRACTOR |
Action Level |
1.
Notify IEC and Contractor. 2.
Carry out investigation. 3.
Report the results of investigation to the IEC, ER and
Contractor. 4.
Discuss with the Contractor and formulate remedial
measures. 5.
Increase monitoring frequency to check mitigation
effectiveness. |
1. Review the analysed results submitted by
the ET. 2.
Review the proposed remedial measures by the Contractor
and advise the ER accordingly. 3.
Supervise the implementation of remedial measures. |
1.
Confirm receipt of notification of failure in writing. 2.
Notify Contractor. 3.
Require Contractor to propose remedial measures for the
analysed noise problem; 4. Check remedial measures
are properly implemented. |
1. Submit noise mitigation proposals to IEC. 2. Implement noise mitigation proposals. |
Limit Level |
1.
Notify IEC, ER, EPD and Contractor. 2.
Identify source. 3.
Repeat measurements to confirm findings. 4.
Increase monitoring frequency. 5.
Carry out analysis of Contractor’s working procedures to
determine possible mitigation to be implemented. 6.
Inform IEC, ER and EPD the causes and actions taken for
the exceedances. 7.
Assess effectiveness of Contractor’s remedial actions and
keep IEC, EPD and ER informed of the results. 8.
If exceedance stops, cease additional monitoring. |
1.
Discuss amongst ER, ET, and Contractor on the potential
remedial actions. 2.
Review Contractors remedial actions whenever necessary to
assure their effectiveness and advise the ER accordingly. 3.
Supervise the implementation of remedial measures. |
1.
Confirm receipt of notification of failure in writing. 2.
Notify Contractor. 3.
Require Contractor to propose remedial measures for the
analysed noise problem. 4.
Check remedial measures properly implemented. 5.
If exceedance continues, consider what portion of the work
is responsible and instruct the Contractor to stop that portion of work until
the exceedance is abated. |
1.
Take immediate action to avoid further exceedance. 2.
Submit proposals for remedial actions to IEC within 3 working days of notification. 3.
Implement the agreed proposals. 4.
Resubmit proposals if problem still not under control. 5.
Stop the relevant portion of works as determined by the ER
until the exceedance is abated. |
Mitigation Measures
Good Site Practice
2.18
The following good site practices were
recommended in the EIA study:
§
Only well-maintained plant should be operated on-site and
plant should be serviced regularly during the construction program;
§
Silencers or mufflers on construction equipment should be
utilized and should be properly maintained during the construction program;
§
Mobile plant, if any, should be sited as far from NSRs as possible;
§
Machines and plant (such as trucks) that may be in
intermittent use should be shut down between work periods or should be
throttled down to a minimum;
§
Plant known to emit noise strongly in one direction should,
wherever possible, be orientated so that the noise is directed away from the
nearby NSRs; and
§
Material stockpiles and other structures should be
effectively utilised, wherever practicable, in screening noise from on-site
construction activities.
Adoption of Quieter PME
2.19
The EIA study recommended the use of quieter
plants for the construction tasks proposed for the Project. The quieter plants recommended are listed in
the table below.
Table 2.5 Quieter PME Recommended for Adoption
during Construction Phase
PME |
Reference |
SWL |
Excavator / Loader |
BS C3/97 |
105 |
Dump Truck |
BS C9/39 |
103 |
Concrete Lorry Mixer |
BS C6/23 |
100 |
Vibratory Poker |
BS C6/32 |
100 |
Breaker, Excavator Mounted (Hydraulic) |
BS C8/12 |
106 |
Vibratory Roller |
Noise data
of Quality PME from EPD Website |
101 |
Use of Temporary Noise Barrier
2.20
Temporary noise barriers of about
2.21
Figure
2.2
shows the typical section of the proposed temporary noise barriers. The
barriers should be made of material of surface mass in excess of
Use of Quieter Alternative Construction Method
2.22
Quieter alternative construction method (hereinafter
referred to as “the Low Impact Method”) has been proposed in the EIA study.
This method involves using PMEs with lower impact and generally smaller in
size, making it possible to be enclosed by noise enclosure which can further
reduce the noise emission levels. Table
2.6 presents the proposed PME for the Low Impact Method.
Table 2.6 Plant Inventory for the Low Impact Method
Construction
Sub-task |
PME |
Reference |
SWL |
Pipe
laying at Wai Ha |
|||
Excavation |
Hand-held breaker |
CNP024 |
108 |
|
Air
compressor |
CNP002 |
102 |
|
Mini
backhoe |
CNP082 |
94 |
Pipe
Laying |
Mini
backhoe |
CNP082 |
94 |
|
Vibratory
poker |
BSC6/32 |
100 |
Backfilling |
Vibratory
poker |
BSC6/32 |
100 |
|
Vibratory
roller |
EPD Website:
Quality PME |
101 |
Noise Enclosures and Temporary Noise Barriers
2.23
Noise enclosure has been proposed
in the EIA study to alleviate the construction noise impact. It can be used for
enclosing the PMEs (except mini backhoe) as listed in Table 2.6. For mini backhoe,
the roof panels of the noise enclosure should be removed when it is in use and
the side panels would form a temporary noise barrier (as illustrated in Figure 2.2) along the periphery of the
works area. The conceptual design of the
noise enclosure is shown in Figures 2.3.
2.24
The noise enclosure should be
made of materials with a surface mass of not less than
2.25
The implementation schedule for the recommended mitigation
measures is presented in Appendix A.
3.1
This section
presents the requirements, methodology, equipment, monitoring locations,
criteria and protocols for the audit of air quality impacts during the construction
phase of the Project.
3.2 According to the EIA study, significant dust emission arising from the construction activities would not be expected. With the implementation of mitigation measures as stipulated in the Air Pollution Control (Construction Dust) Regulation, it would be unlikely that the Project would result in adverse air quality impact on the representative ASRs.
3.3
Therefore, no air quality monitoring would be required
during construction of the drainage improvement works. It is recommended that auditing works during
construction phase be carried out to check that the Contractor has implemented
the recommended mitigation measures to minimize the construction dust impact.
Site Inspection
3.4
Weekly site audits should be carried out to inspect the
construction activities and works areas in order to confirm the recommended
dust control mitigation measures are implemented and are working
effectively. The Contractor should be
responsible for the implementation of the Air
Pollution Control (Construction Dust) Regulation and good site practices
Air Quality Mitigation Measures
3.5
Mitigation measures have been proposed in the EIA study,
including the implementation of the Air Pollution
Control (Construction Dust) Regulation and good site practices. The
practical measures are summarized as below:
§
Use of regular watering to reduce dust emissions from
exposed site surfaces and unpaved road, with complete coverage, particularly during
dry weather;
§
Use of frequent watering for particularly dusty static
construction areas and areas close to ASRs;
§
Tarpaulin covering of all dusty vehicle loads transported
to, from and between site location;
§
Establishment and use of vehicle wheel and body washing
facilities at the exit points of the site;
§
Routing of vehicles and positioning of construction plant
should be at the maximum possible distance from ASRs;
§
Stockpiled excavated materials should be covered with
tarpaulin, and should be removed off-site within 24 hours to avoid any odour
nuisance arising.
3.6
Upon receipt of an environmental complaint, or as part of
the environmental audit, the Contractor should liaise with the ET on some other
mitigation measures, propose to ER for approval, and implement the mitigation
measures.
4.1
The water quality assessment in the EIA study
identified
that no adverse impact would occur during the construction
and operation of the Project provided the recommended mitigation measures were
properly implemented. It is recommended
that regular site inspections (at least weekly) be undertaken to audit the
construction activities and works areas in order to check the recommended
mitigation measures are properly implemented.
4.2
Site inspection
should be conducted at least weekly to inspect the construction activities and
works areas in order to check the recommended mitigation measures are properly
implemented
Water Quality Mitigation Measures
4.3
Mitigation measures recommended for the construction and
operation phases of the Project are summarized below. The implementation schedule of the
recommended water quality mitigation measures is presented in Appendix A.
Construction Phase
Construction Run-off and Drainage
4.4
Mitigation measures should be implemented to control
construction site runoff and drainage from the works areas, and to prevent
runoff and drainage water with high levels of suspended solids from entering
the Wai Ha River, fishponds and the receiving water body of Tolo Harbour.
4.5
The site practices outlined in ProPECC PN 1/94 “Construction
Site Drainage” should be followed as far as practicable during the drainage improvement
works in order to minimise surface runoff and to control erosion, and also to
retain and reduce any suspended solids prior to discharge. These practices include the following items
and should be implemented as an erosion control plan during the construction
phase:
§
Before commencing any site formation work, all sewer and
drainage connections should be sealed to prevent debris, soil, sand etc. from
entering public sewers/drains.
§
Temporary ditches should be provided to facilitate run-off discharge
into appropriate watercourses, via a silt retention pond. No site run-off should enter the fishponds at
Shuen Wan.
§
Sand/silt removal facilities such as sand traps, silt traps
and sediment basins should be provided to remove sand/silt particles from
runoff to meet the requirements of the Technical Memorandum standard under the
Water Pollution Control Ordinance. The
design of silt removal facilities should be based on the guidelines provided in
ProPECC PN 1/94. All drainage facilities
and erosion and sediment control structures should be inspected monthly and
maintained to attain proper and efficient operation at all times and
particularly during rainstorms.
§
Water pumped out from excavated pits should be discharged
into silt removal facilities.
§
During rainstorms, exposed slope/soil surfaces should be
covered by a tarpaulin or other means, as far as practicable. Other measures that need to be implemented
before, during, and after rainstorms are summarized in ProPECC PN 1/94.
§
Exposed soil areas should be minimized to reduce potential
for increased siltation and contamination of runoff.
§
Earthwork final surfaces should be well compacted and
subsequent permanent work or surface protection should be immediately performed
to reduce the potential of soil erosion.
§
Open stockpiles of construction materials or construction
wastes on-site of more than
4.6
With standard water pollution control measures set out in
ProPECC PN1/
§
In addition, precautionary measures for controlling
potential water quality impact due to the proposed works close to the Conservation
Area should be required in order to safeguard the known sites of high
ecological value during the construction phase, particularly during the rainy
season as there is a risk that intense rainfall events may result in discharge
of turbid drainage water. The contractor
should implement the following mitigation measures:
§
For the construction of the box culvert next to the existing
channel of the Wai Ha River, sand bags should be deployed around the boundary
of the works trench to prevent muddy water ingress into the adjacent CA or Wai
Ha River. As an effective measure, sand bags should be used to surround the
excavated trench. Generally, the sand
bags will be placed up to a height of
§
Sheet-piles, which would be installed around the works
trench near the Conservation Area, would be extended above ground level for
about
§
Tarpulin sheets would be used to cover the excavation areas
during heavy rainstorms. This would
prevent the ingress of rainwater into the trench minimising the risk of muddy
water getting into Wai Ha River and the adjacent Conservation Area.
§
Any concrete washing water would be contained inside the
works site surrounded by the extended sheet piles. A pump sump at the bottom of the trench would
be provided to pump any excess water during concrete washing.
§
Stockpiling the excavated materials adjacent to the
Conservation Area would not be allowed.
The excavated materials would be either removed off site immediately
after excavation, or stockpile at location(s) away from the Conservation
Area. The stockpile locations should be
approved by the site engineer.
General
Construction Activities
4.7
Debris and refuse generated on-site should be collected,
handled and disposed of properly to avoid entering the Wai Ha River and fish
ponds at Shuen Wan. Stockpiles of cement
and other construction materials should be kept covered when not being
used.
4.8
Oils and fuels should only be used and stored in designated
areas which have pollution prevention facilities. To prevent spillage of fuels and solvents to
nearby water bodies, all fuel tanks and storage areas should be provided with
locks and be sited on sealed areas, within bunds of a capacity equal to 110% of
the storage capacity of the largest tank.
The bund should be drained of rainwater after a rain event.
Sewage from
Construction Workforce
4.9
Temporary sanitary facilities, such as portable chemical
toilets, should be employed on-site. A
licensed contractor would be responsible for appropriate disposal and maintenance
of these facilities.
River Channel
Excavation Works
4.10
The excavation works within the upstream end of the existing
river channel of the Wai Ha River for the construction of the proposed box
culvert should be carried out in dry condition. Containment measures such as bunds and
barriers should be used within the affected length of the river channel and the
excavation works restricted to within an enclosed dry section of the channel.
The excavation works should be restricted to the period from October to
April.
5.1
Waste management should be the contractor’s
responsibility to confirm that all wastes produced during the construction phase
for the drainage improvement works are handled, stored and disposed of in
accordance with good waste management practices and EPD’s regulations and
requirements. The recommended mitigation measures should form the
basis of the Waste Management Plan to be developed by the Contractor.
5.2
Waste materials generated during construction activities,
such as construction and demolition (C&D) material, chemical wastes and
general refuse, are recommended to be audited at regular intervals (at least
quarterly) to check that proper storage, transportation and disposal practices
are being implemented. The Contractor should be responsible for the
implementation of any mitigation measures to minimise waste or redress problems
arising from the waste materials.
Waste
Control and Mitigation Measures
5.3
Mitigation measures for waste management are summarised
below. With the appropriate handling, storage and removal of waste arisings
during the construction works as defined below, the potential to cause adverse
environmental impacts would be minimised. The implementation schedule of the
recommended mitigation measures is presented in Appendix A. During the
site inspections, the ET should pay special attention to the issues relating to
waste management and check whether the Contractor has implemented the
recommended good site practices and other mitigation measures.
Good Site Practices
5.4
Appropriate waste handling, transportation and disposal
methods for all waste arisings generated during the construction works should
be implemented such that construction wastes do not enter the river channels
and coastal waters of Inner Tolo Harbour, and to minimize potential impacts
where works areas are located close to ecological sensitive receivers.
5.5
It is not anticipated that adverse waste management related
impacts would arise, provided that good site practices are strictly
followed. Recommendations for good site
practices during the construction activities include:
§
Nomination of approved personnel, such as a site manager, to
be responsible for good site practices and making arrangements for collection
of all wastes generated at the site and effective disposal to an appropriate
facility.
§
Training of site personnel in proper waste management and
chemical waste handling procedures.
§
Provision of sufficient waste disposal points and regular
collection for disposal.
§
Appropriate measures to minimise windblown litter and dust
during transportation of waste by either covering trucks or by transporting
wastes in enclosed containers.
§
Separation of chemical wastes for special handling and
appropriate treatment at the Chemical Waste Treatment Facility.
§
Regular cleaning and maintenance programme for drainage
systems, sumps and oil interceptors.
§
A recording system for the amount of waste generated,
recycled and disposal (including the disposal sites) should be proposed.
§
A Waste Management Plan should be prepared and submitted to
the Engineer for approval. One may make
reference to ETWB TCW No. 19/2005 for details.
5.6
In order to monitor the disposal of C&D material at
landfills and public filling areas, as appropriate, and to control fly tipping,
a trip-ticket system should be included as one of the contractual
requirements. One may make reference to
ETWB TCW No. 31/2004 for details. The
use of a trip-ticket system should be required to avoid any illegal or
unplanned dumping of waste generated by the Project, particularly at works
areas close to ecological sensitive receivers.
Waste Reduction Measures
5.7
Good management and control can prevent the generation of
significant amounts of waste. Waste
reduction is best achieved at the planning and design stage, as well as by
ensuring the implementation of good site practices. Recommendations to achieve waste reduction
include:
§
Segregation and storage of different types of waste in
different containers, skips or stockpiles to enhance reuse or recycling of
materials and their proper disposal.
§
To encourage collection of aluminium cans by individual collectors,
separate labelled bins should be provided to segregate this waste from other
general refuse generated by the work force.
§
Any unused chemicals or those with remaining functional
capacity should be recycled.
§
Maximising the use of reusable steel formwork to reduce the
amount of C&D material.
§
Prior to disposal of C&D waste, it is recommended that
wood, steel and other metals should be separated for re-use and / or recycling
to minimise the quantity of waste to be disposed of to landfill.
§
Proper storage and site practices to minimise the potential
for damage or contamination of construction materials.
§
Plan and stock construction materials carefully to minimise
amount of waste generated and avoid unnecessary generation of waste.
5.8
In addition to the above good site practices and waste
reduction measures, specific mitigation measures are recommended below for the
identified waste arisings to minimise environmental impacts during handling,
transportation and disposal of these wastes.
Construction and Demolition Material
5.9
To minimize the environmental impacts during the collection
and transportation of C&D material, the following mitigation measures are
recommended:
§
The excavated material with suitable characteristics/size should
be reused on-site as fill material as far as practicable, such as for
backfilling of the box culvert and drainage pipe works, to minimise off-site
disposal of C&D material.
§
Suitable areas should be designated within the works site
boundaries for temporary stockpiling of C&D material.
§
Within stockpile areas, the following measures should be
taken to control potential environmental impacts or nuisance:
-
covering material during heavy rainfall;
-
locating stockpiles to minimse potential visual impacts; and
-
minimizing land intake of stockpile areas as far as possible
§
When disposing C&D material at a public filling area,
the material should only consist of soil, rock, concrete, brick, cement
plaster/mortar, inert building debris, aggregates and asphalt. The material should be free from marine mud,
household refuse, plastic, metals, industrial and chemical waste, animal and
vegetable matter, and other material considered to be unsuitable by the Filling
Supervisor.
Chemical Wastes
5.10
If chemical wastes are produced at the construction site,
the following mitigation measures should be implemented to minimize the
environmental impacts associated with the handling, transportation and disposal
of chemical waste:
§
Contractor should be required to register with the EPD as a
Chemical Waste Producer and to follow the guidelines stated in the Code of
Practice on the Packaging, Labelling and Storage of Chemical Wastes.
§
Good quality containers compatible with the chemical wastes
should be used, and incompatible chemicals should be stored separately.
§
Appropriate labels should be securely attached on each
chemical waste container indicating the corresponding chemical characteristics
of the chemical waste, such as explosives, flammable, oxidizing, irritant,
toxic, harmful, corrosive, etc.
§
The Contractor should use a licensed collector to transport
and dispose of the chemical wastes generated at the Chemical Waste Treatment Centre
at Tsing Yi, or other licensed facility, in accordance with the Waste Disposal
(Chemical Waste) (General) Regulation.
General Refuse
5.11
The recommended mitigation measures for the handling of
general refuse are as below:
§
General refuse should be stored in enclosed bins or
compaction units separate from C&D material.
§
A reputable waste collector should be employed by the
contractor to remove general refuse from the site, separately from C&D
material.
§
An enclosed and covered area is preferred to reduce the
occurrence of 'wind blown' light material.
6.1
The
ecological impact assessment in the EIA Report identified that ecological impacts
resulting from the proposed drainage improvement works are anticipated to be
very minor in scale. Nevertheless, measures were
identified in the EIA Report that would minimise any potential ecological
impact. Ecological mitigation measures are detailed in the following sections.
Ecological Mitigation Measures
6.2
Following EIAOTM Annex
16 guidelines, mitigation measures are proposed in this section to avoid,
minimise and compensate for identified ecological impacts.
Avoidance/ Minimising
6.3
Wherever possible, proposed drainage improvement works have
been designed to avoid or minimise direct impacts to areas of recognised
conservation importance in the Assessment Area including Conservation Area
(CA), Coastal Protection Area (CPA), and Site of Special Scientific Interest
(SSSI).
6.4
The following measures should be implemented to minimise
identified ecological impacts during the construction and operation phase.
Construction
Phase
6.5
The proposed twin cell box-culvert constructed partially
underneath Tung Tsz Road has been designed to reduce the footprint of the
proposed works from
6.6
During the construction of the proposed twin cell
box-culvert, the following measures are recommended to be implemented:
§
Sheet-pilings, which will be installed around the trench of
excavation, should be extended above ground level for ~
§
The trenching works for the construction of the proposed box
culvert should be carried out in phases, with a trench length of not more than
§
The construction of intercept point of twin cell box culvert
at the upstream of Wai Ha River should be confined to only one side of the
river bank.
§
Construction works of box culvert should be conducted in the
existing artificially modified channel as far as practicable which lined with
masonry wall in order to minimised impact to natural stream section.
§
To restore and enhance the ecological value of the stream,
the affected river bank should be reinstated to its original condition or lined
with rock-filled gabion.
§
Planting pits should be provided in the gabion bank to allow
the re-establishment of riparian vegetation.
§
The existing natural riverbed and substrates should be
retained and the natural pool-riffle sequence should be re-created in the new
channel bed.
6.7
Concerning the excavation works, the following measures should
be implemented:
§
All works conducted within or close to water bodies should
be carried out from October to April, with construction by making use of
land-based plant.
§
Works within river/stream channels should be restricted to
an enclosed dry section of the river, with containment measures such as bunds
and barriers used within the river to minimize the impacts upon the downstream
water body.
§
Site runoff should be directed towards regularly cleaned and
maintained silt traps and oil/grease separators to minimise the risk of
sedimentation and pollution of river water. The silt and oil/grease separators
should be appropriately designed for the local drainage and ground conditions.
§
To minimize leakage and loss of sediments during excavation
in narrow channels, tightly sealed closed grab excavators should be deployed
where material to be handled is wet.
6.8
It has been identified in the EIA report that a plant
species of conservation interest (Hong Kong Pavetta, Pavetta hongkongensis) would be potentially affected by the
construction of the proposed box-culvert. In view of this, specific mitigation
measures have been recommended for this species:
§
The affected individuals should be transplanted to a
suitable nearby habitat prior to the construction phase.
§
A detailed vegetation survey of the affected species of
conservation interest should be conducted by a suitably qualified
botanist/ecologist to identify the affected individuals in order to provide
details for transplantation scheme. A detailed transplantation methodology
should be formulated before the commencement of transplantation.
§
Transplantation should be supervised by a suitably qualified
botanist/horticulturalist.
6.9
To minimise disturbance to habitats adjacent to the works
areas, noise mitigation measures as listed below should be implemented:
§
Quieter construction plant should be used during the
construction phase.
§
Temporary noise barriers should be used during the
construction of the box-culvert along Tung Tsz Road, the floodwater pumping
station, the mechanical gate, and drainage pipe to minimise potential
construction phase disturbance to ardeids that may breed in Shuen Wan Egretry
SSSI, and avifauna foraging in marsh habitat.
§
Noise generating construction works near the Shuen Wan
Egretry SSSI should be avoided as far as practicable during the breeding season
(March to June) of the ardeids. Works
near the SSSI (i.e. installation of mechanical gate) could be restricted to be
executed outside the breeding season by provision of special conditions in the
contract document.
§
To further minimise construction noise impact to the
marshland and prevent tipping, storage of construction material and
encroachment of personnel into the marshland area, hoardings with minimum
height of
6.10
Standard good site practice measures should be implemented
throughout the construction phase. The measures should include:
§
Placement of equipment or stockpile in designated works
areas and access routes selected on existing disturbed land to minimise
disturbance to natural or moderate-high ecological value habitats.
§
Construction activities should be restricted to work areas
that should be clearly demarcated. The work areas should be reinstated after
completion of the works.
§
Waste skips should be provided to collect general refuse and
construction wastes. The wastes should be disposed of timely and properly
off-site.
§
General drainage arrangements should include sediment and
oil traps to collect and control construction site run-off.
§
Open burning on works sites is illegal, and should be
strictly prohibited.
Operation
Phase
6.11
Potential operational phase activities in newly box-culvert
would be limited to regular maintenance such as de-silting. Impacts to aquatic
communities in the nearby water channel resulting from these activities are
expected to be minor. Nevertheless, the following measures are recommended to
minimise potential impacts resulting from operational phase activities:
§
To minimise sedimentation, de-silting should be limited to
the dry season.
§
Waste material produced during de-silting should be disposed
of in a timely and appropriate manner.
Compensation
6.12
Compensatory planting as listed below would be required due
to the unavoidable loss of trees and vegetations.
§
Planting of trees should be provided within the project area
to compensate for the unavoidable loss of approximately
§
Planting of trees and other vegetation within project area
along the banks of Wai Ha River and Tung Tsz Road should also provide
compensation for unavoidable tree-felling and loss of riparian vegetation
resulting from the proposed works.
§
The compensatory planting should make use of native plant
species with flowers/fruits attractive to wildlife.
6.13
As there will be loss of a small area of marsh habitat (about
§
The compensation will make use of an existing low ecological
value recreational fishpond on government land adjacent to the marsh.
§
The above-mentioned pond should be enhanced by removing
boardwalks around the existing pond, and restoring vegetation along the pond
bunds. It should also be re-profiled to provide areas of shallow water
(approximately 15
§
Screen planting of shrubs and trees along the south-eastern
bund of the pond should be implemented to minimise disturbance to avifauna and
other wildlife from the adjacent recreational fishpond.
Ecological Monitoring and
Audit Requirements
6.14
The proper implementation of mitigation measures during
construction and operation phase recommended in Section 6.3 to 6.13 should be
monitored and audited.
6.15
Following transplantation, the health and condition of
individuals of the plant species of conservation interest
affected by the proposed works should be monitored by a qualified
botanist/ecologist. Monitoring should
cover 12-month period following transplantation, and be conducted once a week in
the first 3 months and at least once per month in the remaining of monitoring
period.
6.16
A specific monitoring programme of the compensatory habitats is recommended. The
programme should provide data on the establishment of marsh communities, and
allow an assessment of the relative success of mitigation measures to be made.
6.17
The ecological monitoring should be conducted by
qualified local ecologist(s) of the Independent Environmental
Checker (IEC)
with at least 7 years relevant ecology
and EM&A experience. The ecologist(s) should collect baseline data before the
commencement of construction phase, with monitoring conducted during the
construction and operation phases. Information collected should include
the physical and biological parameters of the important habitats such as marsh,
stream and the compensatory habitat. A simple Event and Action Plan for
construction and operation phase is recommended in Table 6.1. Monitoring
programme details should be agreed with the Agriculture, Fisheries and
Conservation Department (AFCD). The IEC should submit reports on the findings
of each monitoring trip, and a final report summarising the monitoring results
over the entire monitoring period to AFCD and Environmental Protection
Department (EPD).
Table 6.1 Event and Action Plan
Event |
Action |
|
Construction Phase |
Operation Phase |
|
Detection
of exceedance of compliance to physical and biological parameters measured |
1.
Identify sources/reasons of exceedance. 2.
Increase frequency of monitoring visits. 3.
Review and identify any changes in construction
activities. 4.
Propose and implement remedial action. 5.
Check the effectiveness of remedial action. |
1.
Identify sources/reasons of exceedance. 2.
Increase frequency of monitoring visits. 3.
Review and identify any changes in the operation of
drainage works. 4.
Propose and implement remedial action. 5.
Check the effectiveness of remedial actions. |
7.1
Landscape and Visual
Impact Assessment in the EIA Report has identified the key issues and the
possible impacts due to the proposed work.
It has also recommended mitigation measures for minimizing the impacts
and for improving overall landscape and visual quality. The Contractor of the Project should be
responsible for the implementation of mitigation measures.
7.2
A Registered
Landscape Architect (RLA) as a member of the ET, with local construction site
experience should be responsible for conducting the baseline review and
monitoring the design, implementation and maintenance of landscape and visual
mitigation measures during construction and operational phases in accordance
with the EIA Report.
Construction Phase
Baseline Review
7.3
A baseline review
should be undertaken at the commencement of the construction contracts. The purpose of the review is:
§
to check the status of the landscape resources within, and
immediately adjacent to, the construction sites and works areas.
§
to determine whether any change has occurred to the status
of the landscape resources since the EIA.
§
to determine whether amendments in the design of the
landscape and visual mitigation measures are required for those changes.
§
to recommend any necessary amendments to the design of the
landscape and visual mitigation measures.
Landscape and
Visual Monitoring
7.4
The design,
implementation and maintenance of landscape and visual mitigation measures
should be checked bi-weekly to check that they are fully realised. Any potential conflicts between the proposed
landscape measures and any other project works or operational requirements
should also be recorded for the Contractor to resolve in early stage, without
compromising the intention of the mitigation measures.
Operational Phase
Landscape and
Visual Monitoring
7.5
All landscape and
visual mitigation measures should be monitored quarterly during the first year of the Operational Phase to check on
the effectiveness of the mitigations.
Construction Phase
7.6
A number of landscape and visual mitigation measures during
the construction phase have been proposed in the EIA report, and are summarized
as below:
§
Use of hoardings as visual screens for the construction in
the works areas.
§
Use of temporary barriers, covers and drainage provision
around the construction works as contaminant / sediment control to prevent the
contaminants and sediments from entering the sensitive water-based habitats.
§
Implementation of pollution control measures to minimise any
adverse environmental impacts to the surrounding habitats.
§
Liaison with the nursery operator as necessary to minimise
any adverse impact to the daily operation and plant holding capacity of the
nursery.
§
Maintenance and protection of the existing trees, especially
their crowns, trunks and roots, within
work sites.
§
Provision of construction light should be controlled at
night to avoid excessive glare to the surrounding villages and to Plover Cove.
Operation Phase
7.7
Landscape and visual mitigation measures during the
operation phase as listed below should be implemented to minimize the potential
impacts:
§
Viewing area formation by planting with shrubs, grasses and
benches along the area.
§
Architectural design of the pump house will help it fit into
the existing suburban, natural to semi-natural surroundings.
§
Landscape design of pump house by providing sufficient
planting around its boundary fence,
§
Enhancement planting along Tung Tsz Road with shrubs / trees
of suitable species to help protect the stream and marshes.
§
Construction of box culvert should be with at least
§
Transplanting of existing affected trees to adjacent
locations should be carried out.
§
Preparation for transplanting is needed to allow sufficient
time for root pruning and rootball preparation prior to transplanting.
§
Reinstatement of affected area should be carried out to
check that the works areas are properly reinstated.
7.8
The implementation
for the recommended landscape and visual impact mitigation measures is
presented in Appendix A.
8.1
Site inspection provides a direct means to assess
and check the project’s environmental protection and pollution control measures
are in compliance with relevant statutory requirements.
Site inspection should be undertaken regularly
and routinely
by the ET to inspect construction activities in order to check that appropriate
environmental protection and pollution control mitigation measures are
implemented in accordance with EIA recommendations. With well defined
pollution control and impact mitigation specifications and an established
efficient and remedial action reporting system, site inspection is an effective tool to verify
the acceptable environmental performance on the construction site.
8.2
The ET leader should be responsible for formulation
of the environmental
site inspection, deficiency and remedial action reporting system, and for
carrying out site inspection works. He
should in consultation with the IEC, prepare a procedure
for the site inspection, deficiency and remedial action reporting requirements,
and submit to
the Contractor for agreement, and to the ER for approval,
within 21 days of commencement of the construction contact.
8.3
Regular site inspections should be carried out at least once
per week for all works areas.
The inspections should cover the environmental situation,
pollution control and mitigation measures within the works
areas; they
should also
review the environmental situation outside the works areas which is likely to be
affected, directly or indirectly, by the site activities. The ET leader should make
reference to the following information in conducting the inspection:
i.
The EIA recommendations and requirements on
environmental protection and pollution control mitigation measures.
ii.
Works progress, programme, site/aerial
photos and site plans.
iii.
Individual works methodology proposals (which should include
proposal on associated pollution control measures).
iv.
Contract specifications on
environmental protection and pollution prevent control.
v.
Relevant environmental protection and pollution control laws,
ProPECC Notes.
vi.
Previous site inspection results.
8.4
The Contractor should update the ET leader with all relevant
information of the construction contract necessary for him to carry out site
inspections. Inspection results and
associated recommendations for improvements in the Project’s
environmental
performance should be submitted to the IEC and the Contractor within
24 hours for reference and for taking immediate remedial action. The Contractor should follow the procedures
and time-frame as stipulated in the environmental site inspection, deficiency
and remedial action reporting system (formulated by the ET
leader), to report on any remedial measures subsequent to the site
inspections.
8.5
The ET and/or IEC should also carry out ad
hoc site inspections if major unacceptable or unforeseen environmental problems
are identified. Inspections may also be
required subsequent to receipt of an environmental complaint, or as part of the
investigation work, as specified in the Action Plan for environmental
monitoring and audit.
Compliance
with Legal and Contractual Requirements
8.6
There are contractual environmental protection and pollution
control requirements as well as environmental protection and pollution control
laws in Hong Kong with which construction activities should comply.
8.7
The ET leader should also review the progress and programme
of the works to check that relevant environmental laws have not been violated,
and that any foreseeable potential for violating laws can be prevented.
8.8
The Contractor should regularly copy relevant documents to
the ET leader so that the checking of the
Project’s environmental performance can be carried out
effectively. Documents to be
submitted by the Contractor should include at least the updated Works Progress Reports,
Works Programme, application for any necessary licence / permits under relevant
environmental
protection laws, and all the valid licence / permits
received to date. The site diary should also be
available for the ET leader's inspection upon his request.
8.9
After reviewing the documents, the ET leader should
advise the Contractor and inform the IEC of any non-compliance with
the project contractual and legislative requirements on environmental protection and
pollution control. The
Contractor should take follow-up and appropriate remedial actions. If the ET leader’s review concludes that the
current status of licence / permit application and any planned environmental
protection and pollution control works may not cope with the works programme,
or potential violation of environmental protection and pollution control
requirements may arise, he should advise the Contractor and ER
accordingly. The review should be copied
to IEC for any follow-up action.
8.10
Upon receipt of the advice, the Contractor should undertake
immediate action to remedy the situation. The ER should follow up to check that
appropriate action has been taken by the Contractor to satisfy Project’s
environmental protection and pollution control requirements
8.11
Complaints should be referred to the ET leader for carrying
out complaint investigation procedures. The ET
leader should undertake the following procedures upon receipt of any complaint:
(i)
Log complaint and date of receipt
onto the complaint database and inform the IEC immediately.
(ii)
Investigate the complaint to determine
its validity, and assess whether the source of the problem is due to works
activities.
(iii)
Identify mitigation measures in
consultation with the IEC if a complaint is valid and due to works.
(iv)
Advise the Contractor accordingly
if mitigation measures are required.
(v)
Review the Contractor's response
to identified and required mitigation measures, and the current situation.
(vi)
If the complaint is transferred
from the EPD, submit interim report to the EPD on the status of the complaint investigation
and follow-up action within the time frame assigned by the EPD.
(vii)
Undertake additional monitoring
and audit to verify the situation if necessary, and check that any valid reason
for complaint does not recur through the proposed amendments to work methods,
procedures, machines and/or equipment, etc.
(viii)
Report investigation results and
subsequent actions to complainant (if the source of complaint is EPD, the
results should be reported within the timeframe assigned by the EPD).
(ix)
Log a record of the compliant,
investigation, the subsequent actions and the results in the monthly EM&A
reports.
8.12
During the complaint
investigation work, the Contractor and ER should cooperate with the ET leader in
providing all necessary information and assistance for completion of the
investigation. If mitigation measures
(in consultation with the IEC) are required following the investigation, the
Contractor should promptly carry out the measures. The ER should check that the measures have
been carried out by the Contractor.
9.1
Reports can be provided in an electronic medium upon
agreeing the format with EPD. This would
enable a transition from a paper / historic and reactive approach to an electronic
/ real time proactive approach. All the
monitoring data (baseline and impact) should also be submitted on
diskettes. The format for noise
monitoring data to be submitted on diskette is shown in Appendix B.
9.2
Types of reports that the ET leader should prepare and
submit include baseline monitoring report, monthly EM&A report, quarterly
EM&A summary report and final EM&A review report. In accordance with Annex 21 of the EIAO-TM, a
copy of the monthly, quarterly summary and final review EM&A reports should
be made available to the Director of Environmental Protection.
9.3
The ET leader should prepare and submit a Baseline
Environmental Monitoring Report within 10 working days of completion of the
baseline monitoring. Copies of the
Baseline Environmental Monitoring Report should be submitted to the Contractor,
the IEC, the ER and the EPD. The ET
leader should liaise with the relevant parties on the exact number of copies
they require. The report format and
baseline monitoring data format should be agreed with the EPD prior to
submission.
9.4
The baseline monitoring report should include at least the
following:
(i) Up to half a page
executive summary.
(ii) Brief
project background information.
(iii) Drawings showing locations of the baseline monitoring stations.
(iv) Monitoring
results (in both hard and diskette copies) together with the following
information:
Monitoring
methodology.
Types of equipment
used and calibration details.
Parameters monitored.
Monitoring locations.
Monitoring date, time,
frequency and duration.
Quality assurance (QA)
/ quality control (QC) results and detection limits.
(v) Details
of influencing factors, including:
Major activities, if any,
being carried out on the site during the period.
Weather conditions
during the period.
Other factors which
might affect results.
(vi) Determination
of the Action and Limit Levels for each monitoring parameter and statistical
analysis of the baseline data, the analysis should conclude if there is any
significant difference between control and impact stations for the parameters
monitored.
(vii) Revisions for inclusion in the EM&A Manual.
(viii) Comments, recommendations and conclusions.
9.5
The results and findings of all EM&A work required in
the Manual should be recorded in the monthly EM&A reports prepared by the
ET leader. The EM&A report should be
prepared and submitted within 10 working days of the end of each reporting
month, with the first report due the month after construction commences. Each monthly EM&A report should be
submitted to the following parties: the Contractor, the IEC, the ER and the
EPD. Before submission of the first
EM&A report, the ET leader should liaise with the parties on the required
number of copies and format of the monthly reports in both hard copy and
electronic medium.
9.6
The ET leader should review the number and location of
monitoring stations and parameters every six months, or on as needed basis, in order
to cater for any changes in the surrounding environment and the nature of works
in progress.
First Monthly EM&A Report
9.7
The first monthly EM&A report should include at least
the following:
(i) Executive summary (1-2
pages):
Breaches of Action and
Limit levels.
Complaint log.
Notifications of any
summons and successful prosecutions.
Reporting changes.
Future key issues.
(ii) Basic project information:
Project organisation
including key personnel contact names and telephone numbers.
Construction programme.
Management structure,
and
Works undertaken
during the month.
(iii) Environmental status:
Works undertaken
during the month with illustrations (such as location of works).
Drawings showing the
project area, any environmental sensitive receivers and the locations of the
monitoring and control stations (with co-ordinates of the monitoring
locations).
(iv) A brief summary of
EM&A requirements including:
All monitoring
parameters.
Environmental quality
performance limits (Action and Limit levels).
Event-Action
Plans.
Environmental
mitigation measures, as recommended in the project EIA study final report.
Environmental
requirements in contract documents.
(v) Implementation status:
Advice on the
implementation status of environmental protection and pollution control /
mitigation measures, as recommended in the project EIA.
(vi) Monitoring results (in
both hard and diskette copies) together with the following information:
Monitoring
methodology.
Name of types of
equipment used and calibration details.
Parameters monitored.
Monitoring locations.
Monitoring date, time,
frequency, and duration.
Weather conditions
during the period.
Any other factors
which might affect the monitoring results.
QA/QC results
and detection limits.
(vii) Report on non-compliance, complaints, and notifications of
summons and successful prosecutions:
Record of all
non-compliance (exceedances) of the environmental quality performance limits
(Action and Limit levels).
Record of all
complaints received (written or verbal) for each media, including locations and
nature of complaints investigation, liaison and consultation undertaken,
actions and follow-up procedures taken, results and summary.
Record of all
notification of summons and successful prosecutions for breaches of current environmental
protection / pollution control legislation, including locations and nature of
the breaches, investigation, follow-up actions taken, results and summary.
Review of the reasons
for and the implications of non-compliance, complaints, summons and prosecutions
including review of pollution sources and working procedures.
Description of the
actions taken in the event of non-compliance and deficiency reporting and any
follow-up procedures related to earlier non-compliance.
(viii) Others
An account of the
future key issues as reviewed from the works programme and work method
statements.
Advice on the solid
and liquid waste management status.
Comments (for
examples, effectiveness and efficiency of the mitigation measures),
recommendations (for example, any improvement in the EM&A programme) and
conclusions.
Subsequent Monthly EM&A Reports
9.8
Subsequent monthly EM&A reports should include the
following:
(i) Executive summary (1 - 2
pages):
Breaches of Action and
Limit levels.
Complaints log.
Notifications of any
summons and successful prosecutions.
Reporting changes.
Future key issues.
(ii) Environmental status:
Works undertaken
during the month with illustrations (such as location of works etc.).
Drawing showing the
project area, any environmental sensitive receivers and the locations of the
monitoring and control stations.
(iii) Implementation status:
Advice on the
implementation status of environmental protection and pollution control /
mitigation measures, as recommended in the project EIA.
(iv) Monitoring results (in
both hard and diskette copies) together with the following information:
Monitoring
methodology.
Name of types of
equipment used and calibration details.
Parameters monitored.
Monitoring locations.
Monitoring date, time,
frequency, and duration.
Weather conditions
during the period.
Any other factors
which might affect the monitoring results.
QA / QC
results and detection limits.
(v) Report on non-compliance,
complaints, and notifications of summons and successful prosecutions:
Record of all
non-compliance (exceedances) of the environmental quality performance limits
(Action and Limit levels).
Record of all
complaints received (written or verbal) for each media, including locations and
nature of complaints investigation, liaison and consultation undertaken,
actions and follow-up procedures taken, results and summary.
Record of all
notification of summons and successful prosecutions for breaches of current
environmental protection / pollution control legislation, including locations
and nature of the breaches, investigation, follow-up actions taken, results and
summary.
Review of the reasons
for and the implications of non-compliance, complaints, summons and
prosecutions including review of pollution sources and working procedures.
Description of the
actions taken in the event of non-compliance and deficiency reporting and any
follow-up procedures related to earlier non-compliance.
(vi) Others
An account of the
future key issues as reviewed from the works programme and work method statements.
Advice on the solid
and liquid waste management status.
Comments (for
examples, effectiveness and efficiency of the mitigation measures),
recommendations (for example, any improvement in the EM&A programme) and
conclusions.
(vii) Appendix
Action and
Limit levels.
Graphical plots of
trends of monitored parameters at key stations over the past four reporting
periods for representative monitoring stations annotated against the following:
major
activities being carried out on site during the period.
weather
conditions during the period.
any other
factors that might affect the monitoring results.
Monitoring schedule
for the present and next reporting period.
Cumulative statistics
on complaints, notifications of summons and successful prosecutions.
Outstanding issues and
deficiencies.
Quarterly EM&A
Summary Reports
9.9
A quarterly EM&A summary report of around five pages
should be produced and should contain at least the following information.
(i) Up to half a page
executive summary.
(ii) Basic project information
including a synopsis of the project organisation, programme, contacts of key
management, and a synopsis of works undertaken during the quarter.
(iii) A brief summary of EM&A requirements including:
Monitoring parameters.
Environmental quality
performance limits (Action and Limit levels).
Environmental
mitigation measures, as recommended in the project EIA Final Report.
(iv) Advice on the
implementation status of environmental protection and pollution control /
mitigation measures, as recommended in the project EIA Final Report, summarised
in the updated implementation schedule.
(v) Drawings showing the
project area, any environmental sensitive receivers and the locations of the
monitoring and control stations.
(vi) Graphical plots of any
trends in monitored parameters over the past four months (the last month of the
previous quarter and the present quarter) for representative monitoring
stations annotated against:
Major activities being
carried out on site during the period.
Weather conditions
during the period.
Any other factors
which might affect the monitoring results.
(vii) Advice on the solid and liquid waste management status.
(viii) A summary of non-compliance (exceedances) of the
environmental quality performance limits (Action and Limit levels).
(ix) A brief review of the
reasons for and the implications of any non-compliance, including a review of pollution sources and working
procedures.
(x) A summary description of
actions taken in the event of non-compliance and any follow-up procedures
related to any earlier non-compliance.
(xi) A summarised record of all
complaints received (written or verbal) for each media, liaison and
consultation undertaken, actions and follow-up procedures taken.
(xii) Comments (for examples, a review of the effectiveness and
efficiency of the mitigation measures), recommendations (for example, any
improvement in the EM&A programme) and conclusions for the quarter.
(xiii) Proponents' contacts and any hotline telephone number for the
public to make enquiries.
9.10
The final EM&A report should include, inter alia, the
following information:
(i) An executive summary.
(ii) Drawings showing the project area, any environmental sensitive receivers and
the locations of the monitoring and control stations.
(iii) Basic project information including a synopsis of the project
organisation, contacts of key management, and a synopsis of work undertaken
during the entire construction period.
(iv) A brief summary
of EM&A requirements including:
Monitoring parameters.
Environmental quality
performance limits (Action and Limit levels).
Environmental
mitigation measures, as recommended in the project EIA study final report.
Event-Action
Plans.
(iv) A summary of the implementation status of environmental protection and
pollution control/mitigation measures, as recommended in the project EIA
Report, summarised in the updated implementation schedule.
(v) Graphical plots of the trends of monitored parameters over
the construction period for representative monitoring stations, including the
post-project monitoring annotated against:
The major activities
being carried out on site during the period.
Weather conditions
during the period.
Any other factors
which might affect the monitoring results.
(vii) A summary
of non-compliance (exceedances) of the environmental quality performance limits
(Action and Limit levels).
(xi) A brief
review of the reasons for and the implications of non-compliance including review
of pollution sources and working procedures as appropriate.
(xii) A summary description of the actions taken in the event of
non-compliance and any follow-up procedures related to earlier non-compliance.
(xiii) A summary record of all complaints received (written or verbal)
for each media, liaison and consultation undertaken, actions and follow-up
procedures taken.
(xiv) A summary record of notifications of summons and successful
prosecutions for breaches of the current environmental protection/pollution
control legislations, locations and nature of the breaches, investigation,
follow-up actions taken and results.
(xii) A
review of the validity of EIA predictions and identification of shortcomings in
EIA recommendations.
(xiii) Comments (for examples, a review of the effectiveness and
efficiency of the mitigation measures and of the performance of the
environmental management system, that is, of the overall EM&A programme).
(xiv) Recommendations and conclusions (for example, a review of
success of the overall EM&A programme to cost-effectively identify
deterioration and to initiate prompt effective mitigatory action when
necessary).
9.11
No site-based documents (such as monitoring field records,
laboratory analysis records, site inspection forms, etc.) are required to be
included in the monthly EM&A reports.
However, any such document should be well kept by the ET leader and be
ready for inspection upon request. All relevant information should be clearly
and systematically recorded in the document.
Monitoring data should also be recorded in magnetic media form, and the
software copy must be available upon request.
Data format should be agreed with EPD.
All documents and data should be kept for at least one year following
completion of the construction contract.
Interim Notifications of
Environmental Quality Limit Exceedances
9.12
With reference to the Event and Action Plan, when the
environmental quality performance limits are exceeded, the ET leader should
immediately notify the IEC and EPD, as appropriate. The notification should be followed up with
advice to IEC and EPD on the results of the investigation, proposed actions and
success of the actions taken, with any necessary follow-up proposals. A sample template for the interim
notifications is presented in Appendix
C.