Laying of
Environmental Impact Assessment Report
April 2007
Mott Connell Ltd
40th floor, Hopewell Centre
183 Queen’s Road East
Wanchai
Tel: 2828 5757
Fax: 2827 1823
Chapters
1.2 The Environmental Impact
Assessment Study
1.4 Environmental Impact Assessment
Ordinance
2 CONSIDERATION OF
ALTERNATIVES
2.2 Tentative Construction Programme
2.3 Consideration of Alternative
Alignment Options
2.3.1 Physical Constraints to the Alignment
2.3.2 Routing Constraints of the Alignment
2.4 Consideration of Alternative
Construction Methods and Works Sequences
2.4.2 Submarine Pipeline Installation
2.4.4 Horizontal Directional Drilling
2.5 Selection of the Preferred Option
3 WATER QUALITY
IMPACT ASSESSMENT
3.2 Environmental Legislation,
Standards, Guidelines and Criteria
3.2.1 Environmental Impact Assessment
Ordinance (EIAO)
3.2.2 Water Quality Objectives (WQOs)
3.2.4 Hong Kong Planning Standards and
Guidelines (HKPSG)
3.2.5 Water Supplies Department (WSD) Water
Quality Criteria
3.2.7 Suspended Solids Criterion for Fish
Culture Zone
3.2.8 Suspended Solids Criterion for
Benthic Organisms
3.3 Description of the Environment
3.3.1 Marine Water Quality Monitored by EPD
3.3.3 Trend of Water Quality in Victoria
Harbour
3.5.1 Hydrodynamic and Water Quality Models
3.5.2 Sediment Plume Modelling
3.5.3 Effluent, Sewage and Surface runoff
3.6 Identification of Environmental
Impact
3.7 Prediction and Evaluation of
Environmental Impacts
3.7.2 Dissolved Oxygen, Total Inorganic
Nitrogen and Unionised Ammonia
3.7.3 Potential Contaminant Release During
Dredging
3.7.4 Hydrostatic Tests of the Water Mains
System
3.7.5 Surface Runoff, Sewage and Wastewater
from Construction Activities
3.8 Mitigation of Adverse
Environmental Impact
3.9 Evaluation of Residual Impacts
3.10 Environmental Monitoring and Audit
3.11 Conclusions and Recommendations
4 MARINE ECOLOGICAL
IMPACT ASSESSMENT
4.2 Environmental Legislation, Standards, Guidelines and Criteria
4.4 Baseline Conditions & Marine
Ecological Sensitive Receivers
4.4.1 Existing Condition of Victoria
Harbour
4.6 Identification and Prediction of
Environmental Impacts
4.7 Evaluation of Environmental
Impacts
4.8 Mitigation of Adverse
Environmental Impact
4.9 Evaluation of Residual Impacts
4.10 Environmental Monitoring and Audit
4.11 Conclusions and Recommendations
5.2 Environmental Legislation,
Standards, Guidelines and Criteria
5.2.2 Area Sensitivity Ratings
5.4.2 Area Sensitive Ratings (ASRs)
5.4.3 Assessment for the Project
5.5 Identification, Prediction and
Evaluation of Environmental Impacts
5.5.3 Evaluation of Noise Impact
5.6 Mitigation of Adverse
Environmental Impacts
5.6.1 Work Schedule Rearrangement
5.7 Evaluation of Residual Impacts
5.8 Environmental Monitoring and
Audit
5.9 Conclusions and Recommendations
6.2 Environmental Legislation,
Standards, Guidelines and Criteria
6.2.3 Construction and Demolition (C&D)
Materials
6.3.2 Marine Site Investigation
6.4 Baseline Condition of Marine
Dredged Sediment
6.5 Identification and Evaluation of
Environmental Impacts
6.6 Mitigation of Adverse
Environmental Impacts
6.6.2 Waste Reduction Measures
6.7 Evaluation of Residual Impacts
6.8 Environmental Monitoring and
Audit
6.9 Conclusions and Recommendations
7 AIR QUALITY IMPACT
ASSESSMENT
7.2 Environmental Legislation,
Standards, Guidelines and Criteria
7.2.1 Hong Kong Air Pollution Control
Ordinance
7.2.2 Air Pollution Control (Construction
Dust) Regulation
7.2.3 Technical Memorandum on EIA Process
(EIAO-TM), Annex 4 and 12
7.3 Baseline Conditions & Air
Sensitive Receivers
7.4 Identification and Evaluation of
Air Quality Impacts
7.5 Mitigation of Adverse
Environmental Impacts
7.6 Evaluation of Residual Air
Quality Impacts
7.7 Environmental Monitoring and
Audit
7.8 Conclusions and Recommendations
8 CULTURAL HERITAGE
IMPACT ASSESSMENT
8.2 Environmental Legislation,
Standards, Guidelines and Criteria
8.2.1 Technical Memorandum on the EIA
Process, Annex 10 and 19
8.2.2 Antiquities and Monuments Ordinance
(Cap.53)
8.2.3 Hong Kong Planning Standards and
Guidelines
8.2.4 Marine Archaeological Guidelines
8.3 Cultural Heritage Impact
Assessment Methodology
8.3.3 Establishing Archaeological Potential
8.5 Identification of Cultural
Heritage Impact
8.6 Assessment of Cultural Heritage
Impact
8.7 Mitigation of Adverse
Environmental Impact
8.8 Evaluation of Residual Cultural
Heritage Impact
8.9 Environmental Monitoring and
Audit
8.10 Conclusions and Recommendations
9.2 Environmental Legislation,
Standards, Guidelines and Criteria
9.3 Fisheries Impact Assessment
Methodology
9.5 Identification of Fisheries
Impacts
9.6 Assessment of Fisheries Impacts
9.7 Mitigation of Adverse
Environmental Impacts
9.8 Evaluation of Residual Fisheries
Impacts
9.9 Environmental Monitoring &
Audit
9.10 Conclusions and Recommendations
10 SUMMARY OF
ENVIRONMENTAL OUTCOMES
10.1 Population and Environmental
Sensitive Areas Protected
10.2 Environmental Friendly Designs
Recommended and Problems Avoided
10.3 Environmental Benefits of the
Project
11 ENVIRONMENTAL
MONITORING AND AUDIT (EM&A) REQUIREMENTS
12 CONCLUSIONS AND
RECOMMENDATIONS
List of Tables
Table 3‑1.... Summary of Water Quality Objectives for the Victoria
Harbour WCZ
Table 3‑2.... Summary of Water Quality Objectives for the Western
Buffer WCZ
Table 3‑3.... WSD’s Water Quality Criteria for Flushing Water at Sea
Water Intakes
Table 3‑5.... Water Quality Indicator Points
Table 3‑6.... Summary of Parameters for Sediment Plume Model
(Delft3D-WAQ)
Table 3‑7.... Sediment Quality near the Dredging Area
Table 3‑8.... Specifications for General Fill Material and Granular
Fill Material
Table 3‑9.... Depth-averaged and Surface SS levels near the Dredging
Area
Table 3‑10.. DO, TIN and NH3-N levels near
the Dredging Area
Table 3‑11.. Predicted Suspended Solids Elevations at Marine
Ecology Sensitive Receivers
Table 3‑12.. Predicted Suspended Solids Concentrations at Marine
Ecology Sensitive Receivers
Table 3‑13.. Predicted Suspended Solids Elevations at Cooling and
Sea Water Intakes
Table 3‑14.. Predicted Suspended Solids Concentrations at Cooling
and Sea Water Intakes
Table 3‑15.. Predicted Dissolved Oxygen, Total Inorganic Nitrogen
and Unionised Ammonia Elevations
Table 3‑17.. Comparison of Marine Sediment Elutriate Test Results
with Water Quality Standards
Table 4‑3.... Benthic Epifauna Recorded around Green Island (Source:
ERM, 1995)
Table 4‑5.... Evaluation of the Ecological Importance of the
Inter-tidal Habitats
Table 4‑6.... Evaluation of the Ecological Importance of the
Sub-tidal Habitats
Table 4‑7.... Evaluation of the Significance of Ecological Impact
Table 5‑2.... Basic Noise Levels (BNL, Leq.30 min dB(A))
Table 5‑3.... Representative Noise Sensitive Receivers
Table 5‑4.... Noise Emission Inventory (Sai Ying Pun)
Table 5‑5.... Noise Emission Inventory (West Kowloon)
Table 5‑6.... Selected NSRs for Noise Assessment
Table 5‑7.... Summary of Unmitigated Construction Noise Levels during
Normal Daytime Working Hours
Table 5‑8.... Summary of Unmitigated Construction Noise Levels from
dredging during Restricted Hours
Table 6‑1.... Coordinates, Type and Depth of Vibrocores
Table 6‑2.... Sample Arrangement for Chemical Testing
Table 6‑3.... Testing Methods and Reporting Limits for Metals and
Metalloids Analysis
Table 6‑4.... Testing Methods and Reporting Limits for TBT, PAHs and
PCBs Analysis
Table 6‑5.... Sediment Quality Criteria for the Classification of
Sediment
Table 6‑6.... Composite Sample Arrangement for Biological Testing
Table 6‑7.... Test Species for Biological Testing
Table 6‑8.... Test endpoints and decision criteria for biological
testing
Table 6‑9.... Contaminant Levels of Vibrocore Samples and Their
Categories
Table 6‑10.. Summary of Classification of Vibrocore Samples
Table 6‑11.. Summary of Ancillary Tests Results
Table 6‑12.. Summary of Toxicity Test Failure
Table 6‑13.. Summary of Waste Handling Procedures and Disposal
Routes
Table 7‑1.... Hong Kong Air Quality Objectives (mg/m3)(i)
Table 7‑2.... Background Air Quality (2001 – 2005)
Table 7‑3.... Representative Air Sensitive Receivers
Table 9‑2.... Fisheries Production Values from each AFCD Fishing
Zone within the Study Area
List of Figures
Figure 1.1 Indicative Route of the Proposed Watermains
Figure 2.1 Physical Constraints to the Proposed Submarine Watermain
Figure 2.2 Selected Route of Proposed Submarine Watermain
Figure 2.3 Plan View, Profile and Cross Section of Proposed Submarine Watermain
Figure 2.4 Bottom Pull Method
Figure 2.5 Lay Barge Method
Figure 2.6 Float and Sink Method
Figure 2.7 Horizontal Directional Drilling (HDD) Method
Figure 3.2 Locations of Water Sensitive Receivers and Stormwater Outfalls at Western Harbour
Figure 3.3 Extent of the Western Harbour Model Grid
Figure 3.4 Details of the Western Harbour Model Grid in the Project Area
Figure 3.5 Resolution of the Western Harbour Model Grid
Figure 3.6 Grid Refinement of the Western Harbour Model Grid
Figure 3.7a Coastline Configuration in the Project Area
Figure 3.7b Coastline Configuration in the Victoria Harbour
Figure 3.7c Coastline Configuration in the vicinity of the Alignment
Figure 3.8a Bathymetry in the Project Area
Figure 3.8b Bathymetry in the Victoria Harbour
Figure 3.8c Bathymetry in the vicinity of the Alignment
Figure 3.9 Typical Configuration of Silt Curtain and Silt Screen
Figure 4.1 Study Area and Sampling Locations for Marine Ecological Impact Assessment
Figure 4.2 Intertidal Habitats within the Study Area
Figure 5.1 Locations of Noise Sensitive Receivers in Sai Ying Pun
Figure 5.2 Locations of Noise Sensitive Receivers in West Kowloon
Figure 5.3 Works Area – Sai Ying Pun
Figure 5.4 Works Area – West Kowloon
Figure 5.5 Location of Night-time Dredging Zone
Figure 6.1 Longitudinal Geological Profile of Proposed Submarine Watermain Alignment
Figure 6.2 Locations of Vibrocores
Figure 6.3 Sediment Classification Plan
Figure 7.1 Locations of Air Quality Sensitive Receivers in Sai Ying Pun
Figure 8.1 Geophysical Survey Area and Seabed Features with Side Scan Sonar Track
Figure 9.1 Location of AFCD Fishing Zones in the vicinity of the Proposed Watermains
Figure 9.2 Fishing Grids within the Study Area
List of Appendices
Appendix A EIA Study Brief No. ESB-132/2005
Appendix B Tentative Project Programme
Appendix C1 Water Quality Modelling Results
Appendix C2 Laboratory Test Report on Elutriate Tests
Appendix D Not Used
Appendix E Detailed Calculations of Construction Noise Levels
Appendix F2 Laboratory Test Report on Chemical Screening
Appendix F3 Laboratory Test Report on Biological Screening
Appendix F4 Approval Letter from MFC on Dredging Rationale
Appendix G Not Used
Appendix H Marine Archaeological Investigation Report
In February 2006,
Mott Connell Limited (MCL) was commissioned by Water Supplies Department under
Agreement No. CE 42/2005(WS) to carry out the investigation and preliminary
design for the “Laying of Western Cross Harbour Main and Associated Land Mains
from West Kowloon to Sai Ying Pun” (The Project).
The need for the
project has evolved from the requirement to provide security of water supply
between
As cross-harbour
pipelines are strategically important, it is necessary to lay a new
cross-harbour pipeline on the western part of the harbour for maintaining the
reliability of cross-harbour water transfer to
The primary
objective of this Assignment is to study the feasibility of providing laying of
this additional submarine watermain and associated land mains. The Project and
the Environmental Impact Assessment (EIA) is charged with identifying
alternative sites and alignments if necessary as part of the EIA study for the
Project, and obtaining an Environmental Permit (EP). This Assignment requires
preliminary designs, contract strategy, programmes and cost estimates to be
prepared to enable the detailed design to proceed. This Environmental Impact
Assessment (EIA) Report is a key milestone of the Assignment and has been
prepared in conjunction with other design teams.
The route of the proposed watermains is shown in Figure 1.1. The proposed Project is to construct and operate a new western cross harbour main and associated land mains.
The scope of the
proposed Project comprises the following:
(i) approximately 2100-metre section of
1200mm nominal diameter of submarine watermain across Victoria Harbour from its
connection at Lin Cheung Road in West Kowloon to the existing Sai Ying Pun
Fresh Water Pumping Station in Sheung Wan (a designated project under EIA
Ordinance);
(ii)
approximately
2200-metre section of 1200mm nominal diameter of associated land watermains
(Not a designated project under EIA Ordinance).
1.2 The Environmental Impact Assessment Study
The submarine watermain component (referred in Section 1.1(i) above) of
the Project is a Designated Project under Schedule 2, Part 1(E3) of the
Environmental Impact Assessment Ordinance (EIAO) (Cap. 499) and an
Environmental Permit (EP) issued under the EIAO is required for the
construction and operation of the designated project. An application
(No. ESB-132/2005) for a EIA study brief under section 5(7)(a) of the EIAO was
submitted by Water Supplies Department on
The purpose of the EIA study is to provide information on the nature and extent of environmental impacts arising from the construction of the proposed designated project and related activities taking place concurrently, ultimately providing information on the following:
(i) the overall acceptability of any adverse
environmental consequences that are likely to arise as a result of the proposed
project;
(ii) the conditions and requirements for the
detailed design, construction and operation of the proposed project to
mitigate against adverse environmental consequences wherever practicable; and
(iii) the acceptability of residual impacts after the proposed
mitigation measures are implemented.
The scope of the EIA covers the Project proposed in the Project Profile and the works and facilities mentioned in Section 1.1 above. The EIA study addresses the key issues described below, together with any other key issues identified during the course of the EIA study and the cumulative environmental impacts of the Project, through interaction or in combination with other existing, committed, and planned and known potential developments in the vicinity of the Project:
(i) the potential water quality and marine
ecology impacts arising from the dredging, laying of pipe and backfilling works
for the construction of the submarine watermain.
(ii) the potential noise and dust impacts
arising from the construction works of the Project.
(iii) the potential impacts on sites of cultural
heritage of marine archaeological deposit likely to be affected by the
construction works of the Project.
(iv) the potential fisheries impact arising from the
Project.
The EIA study addressed all environmental aspects of the activities and has been based on the best and latest information available during the course of the EIA study. The cumulative environmental impacts from the Project with other interacting projects were assessed, including details of the construction programme and methodologies.
Previously approved studies or EIA reports which are relevant to the Project were reviewed and relevant information extracted for the purpose of this EIA study. The following study or EIA report has been referred to:
·
Proposed Submarine Gas Pipelines from Cheng Tou
Jiao Liquefied Natural Gas Production Plant,
The proposed Project covers three main areas, namely:
The works for
The works in
In Sai Ying Pun (Not
a designated project under EIA Ordinance), the works comprise Sai Ying
Pun area adjacent to Western Wholesale Food Market and is bounded by the
approaches of Western Harbour Crossing Interchange. The proposed 1200mm diameter fresh watermain
will be laid in this portion for connection to the existing Sai Ying Pun Fresh
Water Pumping Station situated at the junction of
This EIA report covers the designated project component of the Project.
1.4 Environmental Impact Assessment Ordinance
As detailed in
Section 1.2, the proposed submarine watermain is a Designated Project under
Schedule 2, Part1(E3) of the EIAO (Cap. 499) and an EP issued under the EIAO is
required for the construction and operation of the designated project.
To apply for an
EP, an EIA must be undertaken in accordance with the requirements of the Study
Brief issued by EPD on 13 October 2005, under reference No. ESB-132/2005.
Reference can be made to the full requirements of the Study Brief which is contained
in Appendix A.
The EIA has been
conducted in accordance with the Study Brief, the Project Profile (No.
PP-258/2005) and the criteria in the relevant sections of the Technical
Memorandum on the EIA Process (Environmental Impact Assessment Ordinance)
(EIAO-TM). The EIA has identified, described, predicted and evaluated potential
environmental impacts, mitigation measures and will consider the impacts of any
feasible alternatives.
The EIA Study
assessed and discussed the alternative alignments and landing points of the
proposed submarine watermain, alternative construction methods and sequences,
and to compare their environmental benefits and dis-benefits with the view of
selecting the preferred options from the environmental perspective.
The
objectives of the EIA Study as detailed in the EIA Study Brief are as follows:
(i) to describe the Project and associated works
together with the requirements for carrying out the Project;
(ii) to identify if there are other types of
Designated Projects under Part I Schedule 2 of the EIAO to be covered in the
Project;
(iii) to consider alternative alignment(s) and
landing points of the submarine watermain, alternative construction method(s)
and sequence(s), and to compare their environmental benefits and dis-benefits
with the view of selecting the preferred options from the environmental
perspective;
(iv) to identify and describe the elements of the
community and environment likely to be affected by the proposed project and/or
likely to cause adverse impacts to the proposed project, including both the
natural and man-made environment;
(v) to identify and quantify emission sources
and determine the significance of impacts on sensitive receivers and potential
affected uses;
(vi) to identify and quantify any potential losses
or damage to flora, fauna and natural habitats and to propose measures to
mitigate these impacts;
(vii) to identify any negative impacts on fisheries
and to propose measures to mitigate these impacts;
(viii) to identify any negative impacts on sites of
cultural heritage and to propose measures to mitigate these impacts;
(ix) to propose the provision of infrastructure or
mitigation measures so as to minimize pollution, visually intrusive sediment
plume dispersion, environmental disturbance and nuisance during construction of
the project;
(x) to investigate the feasibility,
practicability, effectiveness of the proposed mitigation measures.
(xi) to identify, predict and evaluate the
residual (i.e. after practicable mitigation) environmental impacts and the
cumulative effects expected to arise during the construction phase of the
project in relation to the sensitive receivers and potential affected uses;
(xii) to identify, assess and specify methods,
measures and standards, to be included in the detailed design and construction
of the project which are necessary to mitigate these environmental impacts and
reducing them to acceptable levels;
(xiii)
to investigate the extent of secondary
environmental impacts that may arise from the proposed mitigation measures and
to identify constraints associated with the mitigation measures recommended in
the EIA study as well as subsequent provision of necessary modifications;
(xiv) to design and specify the environmental
monitoring and audit requirements, if required, to ensure the implementation
and the effectiveness of the environmental protection and pollution control
measures adopted.
Particular attention has been given to the following document when undertaking this EIA Study:
·
Final EIA Report, Proposed Submarine Gas
Pipelines from Cheng Tou Jiao Liquefied Natural Gas Production Plant,
The need for the
project has evolved from the requirement to provide security of water supply
between
As cross-harbour
pipelines are strategically important, it is necessary to lay a new
cross-harbour pipeline on the western part of the harbour for maintaining the
reliability of cross-harbour water transfer to
2.2 Tentative Construction Programme
The construction of the proposed Project is scheduled to commence in September 2008 for completion by May 2011. The tentative project programme is given in Appendix B.
2.3 Consideration of Alternative Alignment Options
2.3.1 Physical Constraints to the Alignment
There are several major installations and underground structures within the study area which are considered to be physical constraints to the alignment of the proposed submarine watermain. These include:
l Kowloon South Salt Water Pumping Station and associated existing seawater intake culvert;
l
Tunnel structure and
l DSD's drainage culvert next to Sai Ying Pun Fresh Water Pumping Station; and
l
Proposed submarine gas main between
The choice of landing points of the submarine watermain is
limited by the locations of connection point to the existing water supply
network in
As shown on the Figure
2.1, the proposed submarine watermain is bounded by the Western Cross
Harbour Tunnel and the proposed submarine gas main to the east. The existing
seawater intake culvert for Kowloon South Salt Water Pumping Station, Yau Ma
Tei Typhoon Shelter and proposed Western Kowloon Culture District development
at
2.3.2 Routing Constraints of the Alignment
The submarine watermain is proposed to be laid across the
2.4 Consideration of Alternative Construction Methods and Works Sequences
The methods commonly used to install submarine watermain include dredging to form the trench followed by “bottom pull”, “lay barge” or “float and sink” followed by backfilling to protect the pipeline or, “horizontal directional drilling”.
For submarine watermain installations, dredging involves the removal of marine sediments from the seabed to form the trench, into which the submarine watermain are laid by possible methods including Bottom Pull, Lay Barge or the Float and Sink Method. Backfill material will be placed on top to protect the pipeline and minimize the cross section of dredging and backfilling works. The longitudinal profile and a typical cross section of the submarine watermain are provided in Figure 2.3. Design of the cross section and the resulting amount of marine sediments to be dredged from the seabed to form the trench will be the same no matter the Bottom Pull, Lay Barge or the Float and Sink Method is adopted for submarine watermain laying. Horizontal directional drilling involves taking the pipeline directly from the start to end point by underground drilling with no surface disturbance being necessary.
An analysis of different construction methods and techniques to minimise impacts on water quality, marine ecology, fisheries and waste was carried out. Details of the analysis are presented below.
Dredging
Many dredging techniques, such as grab dredging, cutter suction and trailer suction dredging are available and chosen depending on the engineering, environmental and risks conditions e.g. shear strength of marine deposits, marine traffic impact etc.. As the submarine watermain will be located across the Yau Ma Tei, Central and Southern Fairway, grab dredging is selected, as cutter suction and trailer suction dredging which requires a working area of over 150m in width will result in unacceptable impact on marine traffic and are thus not feasible. Dredging by suction dredging will also produce more marine sediment by volume (due to high water content) when compared with grab dredging. Grab dredging is therefore the best practicable and feasible method to minimize dredging and dumping requirements and demand for fill sources.
Dredging can be a comparatively fast way to construct a submarine watermain and is necessary in areas where extra watermain protection is required e.g. rock armour protection. However, the potential for impacts to water quality is higher than horizontal directional drilling (HDD). The excavated sediments would require disposal off-site at a designated disposal ground.
2.4.2 Submarine Pipeline Installation
Bottom Pull
Method
In the bottom pull method (Figure 2.4), pipes are joined to form pipe strings which are progressively pulled from a landfall site into a pre-dredged trench underwater by a winch set up at the landfall site at the other side of the waters until the crossing is complete. Temporary structures are to be erected on both landfall points for launching the pipe strings in a vertical S-curve to avoid overstressing the pipe strings, and for accommodating the winch system throughout the pulling operation. This method is one of the most common method for installation of medium to large diameter pipelines.
Lay Barge Method
In the lay barge method (Figure 2.5), while the work barge moves along the pipeline, the pipes are progressively added to form a string, which are hung in a catenary from at the back of the barge, and are gradually lowered into the pre-dredged trench. Due to limited capacity of work barge, additional marine plants are required to transport pipes from the shore to the work barge throughout the mainlaying operation. As the lay barge method will introduce intolerable marine traffic impact due to its long suspended pipeline at sea during the installation, this method is considered not a feasible option.
Float and Sink
Method
In the float and sink method (Figure 2.6), lengths of pipe are made up into strings at a fabrication yard and these strings are launched to seabed from one of the landfall sites. These prefabricated pipe strings are temporarily stored on the seabed before towed by work barge at or below the water surface to the pre-dredged trench. By removing or filling water to the supporting buoyancy tanks, the pipe strings are sunk to its final position. Underwater welding and bolting are required under this method. This method is one of the most common method for installation of medium to large diameter pipelines.
Cover of pipeline is required to provide adequate anchor protection and to satisfy the maintenance dredging requirements of CEDD. To satisfy the above criterion, the following backfilling material can be used for the submarine pipeline trench:-
l Marine deposit 8 m or deeper or;
l Sand filling 5 m or deeper or;
l Armour rock layer 4.5 m thick with a 0.3 m thick grade 75 bedding.
Pre-dredged trench is required for the pipe laying works, storage of dredged marine deposit for trench backfilling is considered not practicable. Moreover, the overall trench depth for marine deposit backfilling will be up to 9.5 m, this will also significantly increase the quantity of contaminated mud (>30% in volume) when compared with the armour rock option. Backfilling the trench with sand will induce significant disturbance on the existing marine environment and is considered environmentally unacceptable. Armour rock option is recommended as it can provide a strong protection to the pipeline away from the anchoring damage. This option also requires the smallest pre-dredged trench which can minimize the disposal of both contaminated and uncontaminated dredged marine mud.
2.4.4 Horizontal Directional Drilling
Horizontal Directional Drilling (HDD) (Figure 2.7) is a method which takes the pipeline directly from start to end point by underground drilling with no surface disturbance being necessary. A pilot hole will be drilled with fluid pumping down the drill pipes for lubricating and stabilising the walls of the drillhole. After the full length pilot hole is complete, the drill is replaced with a reamer which is pulled back or pushed forward in several passes to enlarge the pilot hole to the required size. On completion of reaming, lengths of pipe are joined and pulled from one side of the landing point to the other using a bonded pull. Finally, the gap between the enlarged hole and the pipe string is grouted for fixing the pipe in position. The potential for impacts to water quality from HDD is lower than dredging as sediments on the seabed would not be disturbed. However, the drilling fluid would require treatment prior to discharge. As the risk and difficulty for recovery in the event of jamming is considered to be very high and HDD has not been used for constructing submarine watermain with size above 1200mm in diameter, this method is considered not a feasible option.
Figure 2.4 Bottom
Pull Method
Figure 2.5 Lay
Barge Method
Figure 2.6 Float
and Sink Method
Figure 2.7 Horizontal
Directional Drilling (HDD) Method
By comparing the pros and cons of
the various construction methods as mentioned in Section 2.4.1 to 2.4.4, grab
dredging and “bottom pull” method followed by protection of the submarine
pipeline by backfilling with 4.5m thick armour rock layer with a 0.3m thick
grade 75 bedding layer are the most practical construction method for the
installation of the proposed submarine watermain. The assessment results, recommendations and
conclusions have been addressed in this EIA report based on the proposed
construction techniques or methods.
The issue of timing and sequencing has been analysed as part of the water quality impact assessment in Section 3. Modelling has examined the impacts on water quality of undertaking the work in either the dry or wet season. For the proposed dredging works, both seasons have been examined to be acceptable in the sense that water quality, marine ecology and fisheries criteria are complied with.
2.5
Selection
of the Preferred Option
The discussions
presented in Sections 2.3 and 2.4 have examined the rationale behind the
selection of the preferred alignment, the preferred construction method and the
issue of timing. The environmental and physical constraints have been presented
along with the preferred alignment for the submarine watermain in Figure 2.2. As can be seen from the figure the submarine
watermain alignment avoids direct impacts to the coral areas. The alignment
presented on Figure 2.2, therefore,
represents the preferred alignment for the submarine watermain taking into
account ecological, water quality and marine traffic constraints. Taking into
account the examination of different alignment options a preferred alignment is
presented in Figure 2.2. By comparing the pros and cons of the various
construction methods, grab
dredging and “bottom pull” method followed by protection of the submarine
pipeline by backfilling with 4.5m thick armour rock layer with a 0.3m thick
grade 75 bedding layer are the most practical construction method for the
installation of the proposed submarine watermain. This proposed alignment and construction
methods for the submarine watermain have been studied in detail as part of this
EIA Report. The selection of this
position was taken after a holistic review of the environmental constraints
(corals), physical constraints (navigation channel) and the results of the
water quality modelling exercise.
The submarine watermain component of the
Project across Victoria Harbour is a Designated Project under Schedule 2, Part
1I(E3) of the Environmental Impact Assessment Ordinance (EIAO) (Cap. 499) and
an Environmental Permit (EP) issued under the EIAO is required for the construction
and operation of the designated project.
In accordance with the EIA Study Brief No. ESB-132/2005,
construction and operation water quality impact arising from the dredging,
laying of pipe and backfilling works for the construction of the submarine
watermain were assessed.
This section presents the findings of the assessment of potential water quality impacts associated with the construction and operation of the proposed submarine watermain specifically in terms of the effects in the vicinity of sensitive receivers in accordance with the requirements of the Study Brief and Annexes 6 and 14 of the Technical Memorandum on the Environmental Impact Assessment Process. Suitable mitigation measures have been recommended to minimise potential adverse impacts and to ensure the acceptability of any residual impact (that is, after mitigation).
3.2 Environmental Legislation, Standards, Guidelines and Criteria
The criteria for evaluating water quality impacts in this EIA Study include:
· Technical Memorandum on Environmental Impact Assessment Process (Environmental Impact Assessment Ordinance) (EIAO-TM);
· Water Pollution Control Ordinance (WPCO);
· Technical Memorandum on Standards for Effluents Discharged into Drainage and Sewerage Systems, Inland and Coastal Waters (TM-DSS);
·
· Water Supplies Department (WSD) Water Quality Criteria; and
· Practice Note for Professional Persons (ProPECC), Construction Site Drainage (PN 1/94).
3.2.1 Environmental Impact Assessment Ordinance (EIAO)
The proposed submarine watermain is a Designated Project under Schedule 2, Part 1 (E3) of the EIAO (Cap.499). The EIAO-TM was issued by the EPD under Section 16 of the EIAO. It specifies the assessment method and criteria that have been followed in this EIA Study. Reference sections in the EIAO-TM provide the details of the assessment criteria and guidelines that are relevant to the water quality impact assessment, including:
· Annex 6 Criteria for Evaluating Water Pollution; and
· Annex 14 Guidelines for Assessment of Water Pollution.
3.2.2 Water Quality Objectives (WQOs)
The
Water Pollution Control Ordinance (Cap. 358) provides the statutory framework
for the protection and control of water quality in
Table 3‑1 Summary of Water Quality Objectives for the
Parameters |
Objectives |
Sub-Zone |
Offensive Odour, Tints |
Not to be present |
Whole zone |
Colour |
Not to exceed 50 Hazen
units, due to human activity |
Inland waters |
Visible foam, oil
scum, litter |
Not to be present |
Whole zone |
E. coli |
Not to exceed 1000 per
100 mL, calculated as the geometric mean of the most recent 5 consecutive
samples taken at intervals between 7 and 21 days |
Inland waters |
Dissolved Oxygen (DO)
within 2 m of the seabed |
Not less than 2.0
mg L-1 for 90% of samples |
Marine waters |
Depth-averaged DO |
Not less than 4.0
mg L-1 for 90% of samples |
Marine waters |
Dissolved Oxygen |
Not less than 4.0
mg L-1 |
Inland waters |
pH |
To be in the range of
6.5 - 8.5, change due to human activity not to exceed 0.2 |
Marine waters |
|
Not to exceed the
range of 6.0 - 9.0 due to human activity |
Inland waters |
Salinity |
Change due to human
activity not to exceed 10% of ambient |
Whole zone |
Temperature |
Change due to human
activity not to exceed 2 oC |
Whole zone |
Suspended solids |
Not to raise the
ambient level by 30% caused by human activity |
Marine waters |
|
Annual median not to
exceed 25 mg L-1 due to human activity |
Inland waters |
Ammonia |
Annual mean not to
exceed 0.021 mg L-1 as unionised form |
Whole zone |
Nutrients |
Shall not cause
excessive algal growth |
Marine waters |
|
Annual mean
depth-averaged inorganic nitrogen not to exceed 0.4 mg L-1 |
Marine waters |
BOD5 |
Not to exceed 5
mg L-1 |
Inland waters |
Chemical Oxygen Demand |
Not to exceed 30
mg L-1 |
Inland waters |
Toxic substances |
Should not attain such
levels as to produce significant toxic, carcinogenic, mutagenic or
teratogenic effects in humans, fish or any other aquatic organisms. |
Whole zone |
|
Human activity should
not cause a risk to any beneficial use of the aquatic environment. |
Whole zone |
Source: Statement of Water Quality Objectives (
Table 3‑2 Summary of Water Quality Objectives for the Western Buffer WCZ
Parameters |
Objectives |
Sub-Zone |
Offensive Odour,
Tints |
Not to be present |
Whole zone |
Colour |
Not to exceed 30 Hazen units, due to human activity |
Water gathering ground subzones |
|
Not to exceed 50 Hazen units, due to human activity |
Inland waters |
Visible foam, oil scum, litter |
Not to be present |
Whole zone |
E. coli |
Not to exceed 610 per 100 mL, calculated as the geometric
mean of all samples collected in a calendar year |
Secondary contact recreation subzones and Fish culture
subzones |
|
Not to exceed 180 per 100 mL, calculated as the geometric
mean of all samples collected from March to October inclusive in 1 calendar
year. Samples should be taken at least 3 times in 1 calendar month at
intervals of between 3 and 14 days. |
Recreation subzones |
|
Less than 1 per 100 mL, calculated as the geometric mean
of the most recent 5 consecutive samples taken at intervals between 7 and 21
days |
Water gathering ground subzones |
|
Not to exceed 1000 per 100 mL, calculated as the geometric
mean of the most recent 5 consecutive samples taken at intervals between 7
and 21 days |
Other Inland waters |
Depth-averaged DO |
Not less than 4.0 mg L-1 for 90% of
samples |
Marine waters except Fish culture subzones |
Dissolved Oxygen (DO) within 2 m of the seabed |
Not less than 2.0 mg L-1 for 90% of
samples |
Marine waters except Fish culture subzones |
Depth-averaged DO |
Not less than 5.0 mg L-1 for 90% of
samples |
Fish culture subzones |
Dissolved Oxygen (DO) within 2 m of the seabed |
Not less than 2.0 mg L-1 for 90% of
samples |
Fish culture subzones |
Dissolved Oxygen |
Not less than 4.0 mg L-1 |
Water gathering ground subzones and other inland waters |
pH |
To be in the range of 6.5 - 8.5, change due to human
activity not to exceed 0.2 |
Marine waters |
|
Not to exceed the range of 6.0 – 8.5 due to human activity |
Water gathering ground subzones |
|
Not to exceed the range of 6.0 - 9.0 due to human activity |
Inland waters |
Salinity |
Change due to human activity not to exceed 10% of ambient |
Whole zone |
Temperature |
Change due to human activity not to exceed 2 oC |
Whole zone |
Suspended solids |
Not to raise the ambient level by 30% caused by human
activity |
Marine waters |
|
Annual median not to exceed 20 mg L-1 due
to human activity |
Water gathering ground subzones |
|
Annual median not to exceed 25 mg L-1 due
to human activity |
Inland waters |
Ammonia |
Annual mean not to exceed 0.021 mg L-1 as
unionised form |
Whole zone |
Nutrients |
Shall not cause excessive algal growth |
Marine waters |
|
Annual mean depth-averaged inorganic nitrogen not to
exceed 0.4 mg L-1 |
Marine waters |
BOD5 |
Not to exceed 3 mg L-1 |
Water gathering ground subzones |
|
Not to exceed 5 mg L-1 |
Inland waters |
Chemical Oxygen Demand |
Not to exceed 15 mg L-1 |
Water gathering ground subzones |
|
Not to exceed 30 mg L-1 |
Inland waters |
Toxic substances |
Should not attain such levels as to produce significant
toxic, carcinogenic, mutagenic or teratogenic effects in humans, fish or any
other aquatic organisms. |
Whole zone |
|
Human activity should not cause a risk to any beneficial
use of the aquatic environment. |
Whole zone |
Source: Statement of Water Quality Objectives (Western
Buffer Water Control Zone).
Besides setting the WQOs, the WPCO controls effluent discharging into the WCZ through a licensing system. A Technical Memorandum on Standards for Effluents Discharged into Drainage and Sewerage Systems, Inland and Coastal Waters (TM-DSS) was issued under Section 21 of the WPCO that gives guidance on the permissible effluent discharges based on the type of receiving waters (foul sewers, storm water drains, inland and coastal waters). The limits control the physical, chemical and microbial quality of effluents. Sewage from the proposed construction activities should comply with the standards for effluent discharged into the foul sewers, inshore waters or marine waters of the Victoria Harbour WCZ, as shown in Table 1, Table 9a and Table 9b, respectively, of the TM-DSS.
3.2.4
The HKPSG, Chapter 9 (Environment), provides additional guidelines against water pollution for sensitive uses such as aquaculture and fisheries zones, bathing waters and other contact recreational waters.
3.2.5 Water Supplies Department (WSD) Water Quality Criteria
Besides the WQOs set under the WPCO, WSD have also specified a set of water quality criteria for flushing water at seawater intakes shown in Table 3-3.
Table
3‑3 WSD’s Water
Quality Criteria for
Parameter
(in mg/L unless otherwise stated) |
Target Limit |
Colour (HU) |
< 20 |
Turbidity (NTU) |
< 10 |
Threshold Odour Number (odour unit) |
< 100 |
Ammonia Nitrogen (NH3-N) |
< 1 |
Suspended Solids (SS) |
< 10 |
Dissolved Oxygen (DO) |
> 2 |
5-day Biochemical Oxygen Demand (BOD5) |
< 10 |
Synthetic Detergents |
< 5 |
E. coli (no. per
100 mL) |
< 20,000 |
A practice note for professional persons was issued by the EPD to provide guidelines for handling and disposal of construction site discharges. The ProPECC PN 1/94 “Construction Site Drainage” provides good practice guidelines for dealing with ten types of discharge from a construction site. These include surface runoff, groundwater, boring and drilling water, bentonite slurry, water for testing and sterilisation of water retaining structures and water pipes, wastewater from building construction, acid cleaning, etching and pickling wastewater, and wastewater from site facilities. Practices given in the ProPECC PN 1/94 should be followed as far as possible during construction to minimise the water quality impact due to construction site drainage.
3.2.7 Suspended Solids Criterion for Fish Culture Zone
A general water quality protection guideline for suspended solids (SS) has been proposed by AFCD(1). The guideline requires maximum SS levels remain below 50mgL-1. This criterion has been adopted in the previous approved EIA(2).
3.2.8 Suspended Solids Criterion for Benthic Organisms
Benthic organisms, including corals, may be damaged by sediment deposition that blocks the respiratory and feeding organs of the corals. According to Hawker and Connell (3), the sedimentation rate higher than 0.1 kg m-2 per day would introduce moderate to severe impact upon corals. This was adopted as the assessment criterion for protecting the marine ecological sensitive receivers in this study. There are no established legislative criteria for water quality for corals. An elevation criterion of 10 mgL-1 in SS has been adopted as the critical value above which impacts to the habitat may occur, same as the previous approved EIA (4).
Dredged
sediments destined for marine disposal are classified according to a set of
regulatory guidelines with sediment quality criteria, which include organic
pollutants and other toxic substances, for designation of sediments (Management
of Dredged/Excavated Sediment, ETWB TCW No. 34/2002). Details on marine dredged
sediment quality are presented in Section 6.
The
requirements for the marine disposal of sediment is specified in the ETWB TCW
No. 34/2002. Marine disposal of dredged
materials is controlled under the Dumping at Sea Ordinance.
3.3 Description of the Environment
3.3.1 Marine Water Quality Monitored by EPD
For the purpose of this EIA, the EPD marine water quality monitoring data routinely collected in the vicinity of the site, which document the water quality in the Victoria Harbour WCZ were used. The EPD monitoring stations of most relevance (that is, in the vicinity of the location of the proposed submarine watermain) include VM5, 6, 7 and 8 as shown in Figure 3.1. A summary of the published marine water quality monitoring data from EPD in 2005 collected at these stations is presented in Table 3-4 (5).
Determinand |
VM6 |
VM7 |
VM5 |
VM8 |
WPCO
WQOs (in marine waters) |
Temperature
(oC) |
23.0 (15.9 – 27.9) |
23.1 (15.8 – 28.0) |
23.0 (15.9 – 27.9) |
23.1 (15.6 – 27.9) |
natural daily level ±
2 oC |
Salinity
(psu) |
31.3 (22.2 – 32.9) |
30.9 (24.4 – 32.8) |
31.4 (22.4 – 32.9) |
31.1 (24.8 – 33.6) |
natural ambient level ±
10 % |
Dissolved
Oxygen (mg/L) |
5.5 (3.2 – 6.6) |
5.6 (3.8 – 6.8) |
5.5 (3.3 – 6.7) |
5.8 (2.5 – 7.3) |
³ 4 mg L-1 |
Dissolved
Oxygen Bottom (mg/L) |
5.3 (3.2 – 6.5) |
5.4 (3.8 – 6.5) |
5.3 (3.3 – 6.6) |
5.6 (2.5 – 7.1) |
³ 2 mg L-1 |
Dissolved
Oxygen (% Saturation) |
77 (45 – 97) |
78 (54 – 104) |
76 (46 – 99) |
80 (35 – 110) |
N/A |
Dissolved
Oxygen Bottom (%
Saturation) |
73 (45 – 94) |
75 (54 – 94) |
74 (46 – 99) |
78 (35 – 108) |
N/A |
pH |
8.0 (7.6 – 8.3) |
8.0 (7.6 – 8.2) |
8.0 (7.6 – 8.3) |
8.1 (7.7 – 8.2) |
6.5 - 8.5 (±
0.2 from natural range) |
Secchi
Disc Depth (m) |
2.1 (1.2 – 3.3) |
1.8 (0.9 – 3.2) |
2.1 (1.3 – 3.1) |
1.9 (1.2 – 2.5) |
N/A |
Turbidity
(NTU) |
9.8 (4.7 – 15.8) |
10.8 (5.6 – 19.1) |
9.8 (4.8 – 16.0) |
11.9 (5.3 – 27.9) |
N/A |
Suspended
Solids (mg/L) |
3.7 (0.8 – 11.0) |
4.1 (1.6 – 9.8) |
3.4 (0.7 – 6.6) |
5.2 (1.4 – 25.0) |
£ natural ambient level + 30% |
5-day
Biochemical Oxygen Demand (mg/L) |
0.9 (0.3 – 1.6) |
1.0 (0.6 – 1.9) |
1.1 (0.6 – 2.4) |
0.8 (0.4 – 1.7) |
not applicable to marine waters |
Ammonia
Nitrogen (mg/L) |
0.19 (0.05 – 0.27) |
0.21 (0.10 – 0.41) |
0.19 (0.06 – 0.30) |
0.18 (0.06 – 0.56) |
N/A |
Unionized
Ammonia (mg/L) |
0.007 (0.003–0.014) |
0.009 (0.004–0.023) |
0.008 (0.003–0.015) |
0.009 (0.002 – 0.040) |
£ 0.021 mg L-1 |
Nitrite
Nitrogen (mg/L) |
0.03 (0.01 – 0.06) |
0.03 (0.01 – 0.07) |
0.03 (0.01 – 0.05) |
0.04 (0.01 – 0.07) |
N/A |
Nitrate
Nitrogen (mg/L) |
0.16 (0.05 – 0.39) |
0.19 (0.08 – 0.50) |
0.15 (0.04 – 0.36) |
0.18 (0.07 – 0.52) |
N/A |
Total
Inorganic Nitrogen (mg/L) |
0.38 (0.11 – 0.68) |
0.43 (0.28 – 0.93) |
0.37 (0.11 – 0.65) |
0.34 (0.18 – 0.92) |
£
0.4 mg L-1 |
Total Kjeldahl Nitrogen (mg/L) |
0.36 (0.21 – 0.48) |
0.36 (0.23 – 0.51) |
0.37 (0.22 – 0.63) |
0.38 (0.15 – 1.40) |
N/A |
Total
Nitrogen (mg/L) |
0.55 (0.27 – 0.83) |
0.58 (0.40 – 1.03) |
0.55 (0.27 – 0.82) |
0.59 (0.25 – 1.56) |
N/A |
Ortho-phosphate
(mg/L) |
0.04 (0.01 – 0.05) |
0.04 (0.01 – 0.05) |
0.04 (0.01 – 0.06) |
0.03 (0.01 – 0.07) |
N/A |
Total-Phosphorus
(mg/L) |
0.05 (0.03 – 0.07) |
0.05 (0.03 – 0.07) |
0.05 (0.03 – 0.09) |
0.05 (0.02 – 0.23) |
N/A |
Silica
(as SiO2) (mg/L) |
0.9 (0.2 – 2.4) |
1.0 (0.6 – 2.1) |
0.9 (0.1 – 2.1) |
1.0 (0.6 – 2.0) |
N/A |
Chlorophyll-a
(mg/L) |
2.7 (0.6 – 10.0) |
2.2 (0.8 – 11.0) |
2.8 (0.6 – 9.4) |
2.0 (0.8 – 8.0) |
N/A |
E.coli
(cfu/100mL) |
5700 (840 – 38000) |
9100 (800 – 49000) |
7700 (360–57000) |
4900 (220 – 190000) |
not applicable to marine waters |
Faecal
Coliforms (cfu/100mL) |
12500 (1700–91000) |
20900 (2000–180000) |
17000 (1100–90000) |
12100 (930–730000) |
N/A |
Note:
1. Except
as specified, data presented are depth-averaged results.
2. Depth-averaged results at each
station are calculated as arithmetic means of measurements at all available
depths (i.e. S, M, B) except for E.coli and faecal coliforms which are
geometric means.
3. Data presented are annual
arithmetic means except for E.coli and faecal coliforms which are annual
geometric means.
4. Data enclosed in brackets
indicate the ranges.
5. Shaded cells indicate
non-compliance with the WQOs.
(Source: Adopted from EPD Marine Water Quality
Full compliance with the WQO for depth-averaged (DA) and bottom dissolved oxygen (DO) and depth-averaged (DA) unionised ammonia (NH3-N) was achieved at VM5, 6, 7 and 8 in 2005. VM5, 6 and 8 also achieved 100% compliance with the depth-averaged total inorganic nitrogen (TIN) of WQO.
The results of marine sediment quality analysis from the marine site investigation along the alignment of the proposed submarine watermain were presented in Section 6. The results indicated that Category H sediment was found at 9 out of 15 vibrocoring locations due to the high contaminant levels of copper (Cu), lead (Pb), mercury (Hg) and silver (Ag) that exceed the Upper Chemical Exceedance Level (UCEL) under the current sediment classification system (ETWB TCW No. 34/2002, Management of Dredged / Excavated Sediment).
3.3.3
Trend of Water Quality in
As reported in the “Marine Water Quality in Hong Kong in 2004” issued by EPD, significant decline in Total Kjeldahl Nitrogen (TKN) and Total Nitrogen (TN) was generally observed, except at the two stations VM5 and 8. On the other hand, an increase of nitrate nitrogen (NO3-N) was detected in the western part of the harbour. An increase in DO, decreases in nutrients (TN, Total Phosphorus (TP)) and organics (5-day Biochemical Oxygen Demand (BOD5)) were also evident in the north Rambler Channel (VM14).
Indicator
points were selected within the
Water sensitive receivers that are potentially affected by the proposed Project are listed below:
· New Yau Ma Tei Typhoon Shelter
·
Coral communities at
·
17 seawater intakes at the waterfront of
Locations
of water sensitive receivers and stormwater outfalls at the
All the sensitive receivers and stormwater outfalls were defined as water quality monitoring points in the model to output the key water quality parameters for determination of water quality changes as a result of the construction and operation phase activities. The modelling results are presented in terms of contour plot, time series plot and table for both the dry and wet seasons in this section.
The
indicator points with brief description are provided in Table 3-5.
Table 3‑5 Water Quality Indicator Points
Location |
Type |
Assessment Point |
Easting |
Northing |
New Yau Ma Tei Typhoon
Shelter |
Typhoon Shelter |
R1 |
834 527.857 |
819 102.182 |
|
Sensitive Receiver of Marine Ecology |
R2 |
829 398.155 |
816 298.432 |
|
Sensitive Receiver of Marine Ecology |
R3 |
829 449.070 |
815 952.418 |
|
Sensitive Receiver of Marine Ecology |
R4 |
830 023.685 |
816 169.040 |
|
Sensitive Receiver of Marine Ecology |
R5 |
830 175.979 |
816 179.217 |
|
Seawater Intake |
R6 |
833 437.625 |
816 747.640 |
|
Seawater Intake |
R7 |
833 461.092 |
816 744.773 |
|
Seawater Intake |
R8 |
833 786.796 |
816 663.359 |
|
Seawater Intake |
R9 |
833 910.436 |
816 507.645 |
|
Seawater Intake |
R10 |
834 094.788 |
816 610.502 |
Reprovisioned Prince’s
Building Group at CRIII |
Cooling Water Intake |
R11 |
834 704.000 |
816 447.288 |
Reprovisioned Hong Kong
Shanghai Bank at CRIII |
Cooling Water Intake |
R12 |
835 142.292 |
816 076.399 |
Reprovisioned Queensway
Government Offices, Admiralty and Police Headquarters at CRIII |
Cooling Water Intake |
R13 |
835 212.354 |
816 057.961 |
WSD Cheung Sha Wan Salt
Water Pumping Station |
Seawater Intake |
R14 |
833 545.427 |
820 678.020 |
WSD |
Seawater Intake |
R15‡ |
833 982.630 |
818 282.101 |
|
Seawater Intake |
R16 |
834 335.800 |
817 769.145 |
|
Seawater Intake |
R17 |
834 364.658 |
817 802.847 |
MTRC Cooling Mains |
Seawater Intake |
R18 |
834 443.154 |
817 864.202 |
|
Seawater Intake |
R19 |
835 227.714 |
817 832.283 |
|
Seawater Intake |
R20 |
835 599.125 |
817 115.536 |
|
Existing Stormwater Outfall |
R21‡ |
833 941.469 |
817 988.659 |
|
Existing Stormwater Outfall |
R22 |
834 123.935 |
817 742.368 |
Sai Ying Pun Outfall |
Existing Stormwater Outfall |
R23‡ |
832 647.357 |
816 865.168 |
Sai Ying Pun Outfall |
Existing Stormwater Outfall |
R24‡ |
832 724.197 |
816 863.893 |
Sai Ying Pun Outfall |
Existing Stormwater Outfall |
R25‡ |
832 786.137 |
816 855.415 |
Sai Ying Pun Outfall |
Existing Stormwater Outfall |
R26 |
832 978.593 |
816 850.883 |
Shek Tong Tsui |
Existing Stormwater Outfall |
R27 |
831 581.898 |
816 516.015 |
|
Seawater Intake |
R28 |
830 707 |
815 983 |
WSD Sheung Wan Salt Water
Pumping Station |
Seawater Intake |
R29 |
833 414 |
816 745 |
Note: ‡ These Assessment
Points fall inside an area within 100m of the proposed water main.
All other Assessment Points fall outside this area.
The
To assess the potential water quality impact arising from the dredging, laying of pipe and backfilling works for the construction of the submarine watermain, the sources and natures of effluent to be generated during construction were identified and their impacts were quantified where practicable.
3.5.1 Hydrodynamic and Water Quality Models
Set-up
of Hydrodynamic Model
Computer
modelling was employed to assess the potential impact on water quality in
In
the present study, the basis for modelling of the harbour waters is the
existing, validated Western Harbour Model. This model covers the relevant part
of the
Coastlines and Bathymetry
The coastline configuration and bathymetry set up for the construction phase of the Project were shown in Figures 3.7 and 3.8, taking account of completed reclamation and the latest progress of the concurrent coastal developments.
Simulation Periods
The simulated periods cover a complete spring-neap tidal cycle. The actual simulation period is preceded by a spin-up period. Both the actual simulation period and the spin-up period originate from the Update Study and represent average tidal conditions. The simulation periods are specified below:
spin-up
dry season: 2 February
dry
season: 9 February
spin-up
wet season: 19 July
wet
season: 26 July
Boundary Conditions for Water Quality
Models
The initial and boundary conditions are set to zero as the excess suspended solids concentrations are modelled.
3.5.2 Sediment Plume Modelling
General
Water quality impacts would arise from dredging activities of the proposed submarine watermain that would disturb the marine bottom sediment, elevate the SS concentrations of the water column and generate sediment plume along the tidal flows. The impact of sediment plume dispersion during the marine works was simulated by a three-dimensional Delft3D-WAQ Model. The WAQ model simulated suspended solids (SS, in mg/L), optionally subdivided over different fractions representing different sediment sources. The simulated SS represented the project related discharges only. The calculated concentrations were interpreted as excess concentrations on top of the background concentrations.
The Delft3D-WAQ model takes into account the sedimentation process by means of a settling velocity, while erosion of bed sediment, causing resuspension of sediment, is governed by a function of the bed shear stress. The parameters adopted in the present study are summarised in Table 3-6.
Table 3‑6 Summary of Parameters for Sediment Plume Model (Delft3D-WAQ)
Sediment
Plume Model Parameters |
|
Settling velocity |
0.5mm/s |
Critical shear stress for deposition |
0.2N/m2 |
Critical shear stress for erosion |
0.3N/m2 |
Minimum depth where deposition allowed |
0.1m |
Resuspension rate |
30g/m2/d |
The impacts in terms of DO depletion, unionised ammonia (NH3-N) and total inorganic nitrogen (TIN) would not be modelled explicitly, but estimated on the basis of the calculated sediment concentrations. This would lead to an estimated increase relative to the background of the concentrations of different contaminants, dependent on the quality of the released sediments. For TIN, it is assumed that the total nitrogen content, being ammonia content and Kjedahl-N of the sediment is transformed to TIN. For NH3-N, it is assumed that the entire nitrogen content of the bottom is transformed to ammonium and unionised ammonia. The percentage unionised ammonia is estimated on the basis of temperature, salinity and pH on the basis of the formulations used in Delft3D-WAQ (Delft3D-WAQ Technical Reference Manual, September 2005, WL | Delft Hydraulics). The estimation of the factor is worst case and different for wet and dry season. Analogously, this would lead to an estimated decrease relative to the background of the concentrations of DO, dependent on the quality of the released sediments. For DO it is assumed that the entire COD content of the sediment is transformed to DO decrease. This can be expressed as follows:
where
TIN |
concentration of Total Inorganic Nitrogen (mgN/L) |
SS |
concentration of suspended solids (mg/L) |
CSS,NH4 |
concentration of ammonium in suspended matter (gN/gSS) |
CSS,Kj-N |
concentration of Kjedahl-N in suspended matter (gN/gSS) |
f(sal,temp,pH) |
factor unionised ammonia (gNH3/(gNH4+gNH3) |
sal |
salinity (ppt) |
T |
temperature (Celsius) |
pH |
pH |
DO |
concentration of dissolved oxygen (mg/L) |
CSS,COD |
concentration of COD in suspended matter (gO/gSS) |
This approach relies on worst case assumptions. Any removal of pollutants from the water phase with the sedimentation of SS and any replenishment of DO from the atmosphere is neglected.
The values used in this assessment are based on the highest EPD routine marine sediment quality monitoring data recorded at VS5 in 2005 near the dredging area and are summarised in Table 3-7.
Table 3‑7 Sediment Quality near the Dredging Area
Parameters |
Dry season |
Wet season |
CSS,NH4 |
41E-6 |
41E-6 |
CSS,Kj-N |
760E-6 |
760E-6 |
f(sal,temp,pH) |
0.03 |
0.05 |
sal |
28 |
28 |
T |
20 |
27 |
pH |
7.9 |
7.9 |
CSS,COD |
27E-3 |
27E-3 |
Modelling Scenario
The
construction of the proposed submarine watermain from
Dredging works of the Project would be undertaken by a grab dredger. The assumptions made with regards to modelling grab dredging are as follows:
One grab dredger with a maximum production
rate of 4,000 m3 per day, 7 days per week, 24 hours per day equate
to a maximum rate of 0.0463 m3 s-1 during dredging
operations.
For the dredging operation, a dry density of 1,300 kgm-3 has been assumed for the dredged material in deriving the figures. This figure was adopted in the Central Reclamation Phase III - Studies, Site Investigation, Design and Construction EIA study.
Spill loss during sediment dredging by a closed grab dredger was assumed to be continuous, 24 hours a day, 7 days per week.
With respect to the rate of sediment loss during dredging, the Contaminated Spoil Management Study (6) reviewed relevant literature and concluded that losses from closed-grab dredgers were estimated at 11 to 20 kg m-3 of mud removed. Taking the upper figure of 20 kg m-3 to be conservative, the loss rate in kg s-1 was calculated based on the daily volume rate of dredging. (Assuming a dry density for marine sediment of 1,300 kg m-3, the sediment loss during dredging is equivalent to a spill amount of approximately 1.54%).
Spilling rates for sediment dredging by a closed grab dredger were assumed to take place uniformly over the water column.
Dredging of contaminated and uncontaminated sediment was assumed be carried out at the same rate.
Granular fill (either decomposed granite or armour rock) would be used as backfilling material after the cross harbour main laying works. As the granular fill does not contain fines material, there would be no sediment plume generation during the backfilling process and the marine water quality would not be affected. The contractor would follow the General Specification for Civil Engineering Works and the particle size distribution of fill material specified in Clause 6.07. The specifications for general fill material and granular fill material are reproduced in Table 3-8.
Table 3‑8 Specifications for General Fill Material and Granular Fill Material
Type of
fill material |
Percentage
by mass passing |
||
Size |
BS test
sieve |
|
|
200 mm |
75 mm |
600 mm |
|
General fill material |
100 |
75 – 100 |
N/A |
Granular fill material |
N/A |
100 |
0 – 5 |
During dredging, a quantity of fine sediment will be lost to suspension that may be transported away from the works area, forming suspended sediment plumes. The formation and transport of sediment plumes from dredging are modelled in this Assignment.
To assess the water quality impact on the sensitive receivers during the entire duration of dredging works and along the entire alignment, load locations which represent the position of the dredger for one day was defined along the proposed alignment of the submarine watermain. The locations follow each other with a distance of 24m (with a working speed of 1m per hour) which result in 84 discharge locations along the alignment. Each location was active for one day. A simulation period of 90 days was thus given. Modelling was conducted for the complete simulation period for the dry and wet season and the spring neap cycle was repeated after every 14 days. This represents the worst case scenario as water quality impact on the sensitive receivers during the entire duration of dredging works and along the entire alignment was simulated with the maximum possible instantaneous working rate of 0.0463m3s-1. As a result, the highest possible elevation of suspended solids were predicted. This is a very conservative assumption as a grab dredger may, depending on the actual grab dredger and the sediment condition at the time of dredging, fill with water. A conservative assumption of loss rate for grab dredger of 20kgm-3 mud dredged with a corresponding sediment loss rate of 0.93kgs-1 was also adopted.
Potential Cumulative Impact
There may be other concurrent external dredging and filling projects that may impact the same areas. An analysis of external projects, which could occur at the same time as the installation of the Western Cross Harbour Main, has found that there will be three projects that could potentially contribute to cumulative impacts. These include reclamation for Central Reclamation Phase III, dredging works for proposed Cruise Terminal at Kai Tak and reclamation for Wan Chai Development Phase II and Central Wan Chai Bypass.
Reclamation
for Central Reclamation Phase III would be constructed prior to the dredging
works for the submarine watermain. Dredging works for proposed Cruise Terminal
at Kai Tak is remote from the Western Cross Harbour Main and will be
constructed after the dredging works for the submarine watermain. Reclamation
for Wan Chai Development Phase II and Central Wan Chai Bypass at North Point is
remote (over 5km away) from the Western Cross Harbour Main and thus is not
anticipated to cause a cumulative impact. Reclamation for Wan Chai Development
Phase II and Central Wan Chai Bypass at Wan Chai and
Conservative
Assumptions in Assessment Methodology
Quantitative uncertainties in the sediment dispersion modelling should be considered when making an evaluation of the modelling predictions. Worst case conditions were adopted as model input to indicate the maximum extent of the potential environmental impacts. The input data tended to be conservative to provide a margin of tolerance. Some examples of the conservative nature of the input parameters are given below:
The dredging rate adopted for the sediment plume modelling represents the maximum production rate that could be achieved during construction. The actual dredging rate would be less as the shallow dredge option would be adopted and lesser quantity of mud would be dredged.
A conservative assumption of sediment loss from a closed grab dredger (that is, 20 kg m-3) was adopted to generate the sediment loss rate for modelling. This loss rate would, however, be higher than the real situation.
Contaminant
Release during Dredging
The loss of sediment to suspension during dredging may have chemical effects on the receiving waters. This is because the sediment would contain organic and chemical pollutants. As part of the marine site investigation works for this Project, laboratory testing of sediment samples was undertaken. A full description of the sediment quality testing and the classification of the sediment according to levels of contaminants are contained in Section 6.
An indication of the likelihood of release of heavy metals from the sediment during dredging is given by the results of the elutriate tests from the marine site investigation works. If the contaminant levels are higher in the elutriates in comparison with the blanks (marine water from the same site), it can be concluded that the contaminants are likely to be released into the marine waters during dredging activities. As there is no existing legislative standard or guideline for individual heavy metal contents in marine waters, the UK Water Quality Standards for Coastal Surface Water (7) were adopted as the assessment criteria.
3.5.3 Effluent, Sewage and Surface runoff
To assess the impact of the effluent from hydrostatic tests of the water mains system and sewage, wastewater and surface runoff from construction activities upon the nearby water bodies, the extent of hydrostatic tests and construction works associated with the proposed submarine watermain were reviewed and identified. Practical water pollution control measures or mitigation proposals were subsequently recommended to ensure effluent discharged from the construction site would comply with the WPCO criteria.
3.6 Identification of Environmental Impact
Dredging
General
Dredging of marine sediment would be undertaken along the alignment of the proposed submarine watermain. The in-situ volume of dredged sediment for the Project was estimated to be approximately 362,000 m3 (with a bulking factor of 1.5, bulked volume of dredged sediment was estimated to be approximately 543,000 m3). The estimated volume of contaminated dredged sediment is approximately 141,333 m3 (with a bulking factor of 1.5, bulked volume of dredged sediment was estimated to be approximately 212,000 m3) (about 39% of the total dredged sediment).
Key water quality concerns during dredging include (i) dredging works that would disturb the marine bottom sediment, causing an increase in SS concentrations in the water column and forming sediment plume along the tidal flows and (ii) construction runoff and drainage, with effluents potentially contaminated with silt, oil and grease.
Potential impacts on water quality from dredging include:
· increased suspension of sediment in the water column during dredging activities, with possible consequence of reducing DO levels and increasing nutrient levels;
· release of previously bound organic and inorganic constituents such as heavy metals, PAHs, polychlorinated biphenyls (PCBs) and nutrients into the water column, either via suspension or by disturbance as a result of dredging activities; and
· release of the same contaminants due to leakage and spillage as a result of poor handling and overflow from barges during dredging and transport.
Impacts would vary depending on the quantities and level of sediment contamination and the nature and locations of the WSRs. All of the above would result in deterioration of the receiving marine water quality and would have adverse effects on WSRs.
Impact
of Suspended Sediment
As a result of dredging activities during the construction phase, fine sediment (less than 63 µm) would be lost to suspension. The suspended sediment would be transported by currents to form sediment plumes, which would gradually resettle. The impact from sediment plumes was to increase the suspended sediment concentrations, and caused non-compliance in WQO and other criteria for particular sensitive receivers.
The extent of elevation of ambient suspended sediment concentrations would determine whether or not the impact is adverse or not. The determination of the acceptability of any elevation is based on the WQOs. The WQO of SS is defined as being an allowable elevation of 30% above the background. As directed in a previous study of the environmental impacts of released SS (8), the ambient value is represented by the 90th percentile of reported concentrations.
The depth-averaged and surface SS levels in
90 percentiles during dry and wet seasons are summarised in Table 3-9. These values are derived
from the marine water quality monitoring results of the four EPD’s routine
monitoring stations VM5, 6, 7 and 8 located near the dredging area. The SS
levels recorded from 2003 to 2005 were used in this Assignment. As stipulated
by the WQOs for the Victoria Harbour WCZ, the 30% allowable elevations of
depth-averaged SS above the ambient were 2.6mgL-1
and 2.5mgL-1 for
the dry and wet seasons, respectively. For surface SS, however, the allowable
elevations were 2.6mgL-1 and
2.0mgL-1 for
the dry and wet seasons, respectively. Since seawater intakes are generally
located near the water surface, the ambient surface SS level of 8.6mgL-1
for dry season and 6.7 mgL-1
for wet season were added to the predicted SS
elevations at these sensitive receivers for comparison against the relevant
water quality criteria.
Table 3‑9 Depth-averaged and Surface SS levels near the Dredging Area
Stations |
Dry Season |
Wet Season |
||
VM5, 6, 7
and 8 |
Depth-averaged |
Surface |
Depth-averaged |
Surface |
Average SS (mg L-1) |
5.3 |
4.7 |
5.0 |
4.1 |
90 percentile (ambient level) |
8.8 |
8.6 |
8.4 |
6.7 |
30% increase above the ambient level |
2.6 |
2.6 |
2.5 |
2.0 |
Impact
of Dissolved Oxygen, Total Inorganic Nitrogen and Unionised Ammonia
The extent of depletion of ambient DO concentration and elevation of ambient TIN and NH3-N would determine or not the impact is adverse or not. The determination of the acceptability of any depletion or elevation is based on the WQOs. The WQO of DO, DO bottom, TIN and NH3-N are defined as being larger than or equal to 4 mgL-1, larger than or equal to 2 mgL-1, less than or equal to 0.4 mgL-1 and less than or equal to 0.021 mgL-1 respectively.
An assessment of dissolved oxygen depletion and nutrient release during dredging was made in relation to the results of the sediment plume modelling of dredging activities and the sediment quality data of the Study Area. The predicted maximum elevations in tidal and depth-averaged SS concentrations at the construction site were used to estimate the effects of increased SS concentrations on DO, TIN and NH3-N. The area in the vicinity of alignment of the proposed submarine pipeline was of particular concern. In the water quality model, it was assumed that all COD was exerted and that all TIN and NH3-N in the sediment were released to the water. These were conservative assumptions and would likely result in an over-prediction of the potential impacts.
The depth-averaged DO, TIN and NH3-N and bottom layer DO levels during dry and wet seasons are summarised in Table 3-10. To determine compliance with the water quality criteria, background water quality data were required. The average DO, TIN and NH3-N values derived from the EPD’s routine marine water quality monitoring data recorded from 2003 to 2005 at VM5, 6, 7 and 8 near the dredging area were used in the assessment. As presented in Table 3-10, the depth-averaged TIN concentration recorded during wet season does not comply with the WQO for TIN (≧0.4 mgL-1).
Table 3‑10 DO, TIN and NH3-N levels near the Dredging Area
Stations |
Dry Season |
Wet Season |
||
VM5, 6, 7
and 8 |
Depth-averaged |
Bottom |
Depth-averaged |
Bottom |
Dissolved Oxygen (mg L-1) |
6.0 |
6.0 |
5.0 |
4.1 |
Total Inorganic Nitrogen (mg L-1) |
0.31 |
- |
0.43 |
- |
Unionised Ammonia (mg L-1) |
0.006 |
- |
0.010 |
- |
Hydrostatic Tests of the Water Mains
System
Hydrostatic tests would be undertaken in accordance with Section 23.73 and 23.77 of the General Specification for Civil Engineering Works Volume 3, 1992 Edition for sterilisation of pipeline and pressure pipeline test for the submarine watermain to check for leaks or flaws. For sterilisation of pipeline, the pipeline would be completely filled with water that has been dosed with a homogeneous solution of sterilising chemicals such that the final concentration of free chlorine in the water is at least 30ppm. The water will be left in the pipeline for at least 24 hours. After the 24 hour period, the pipeline will be drained down. For pressure pipeline testing, the pipeline would be filled with potable water or seawater (a nearly incompressible liquid) and examined for leaks or permanent changes in shape with a specified test pressure. The pipeline would be tested in sections. Pressure tests would not be carried out until the fill material has been deposited and compacted over the complete length of the pipeline to be tested. Effluent from the hydrostatic test of water supply pipeworks which the volume of discharge would be 2,500m3 would be subjected to pre-treatment including dechlorination such as by physical process e.g. adsorption by activated carbon filter, or chemical process e.g. neutralisation by dechlorination agent dosing to ensure compliance with the discharge requirements stipulated in TM-DSS. Local and coastal waters may be impacted if the water for testing is allowed to discharge into the inshore waters or marine waters of the Victoria Harbour WCZ without mitigation.
Surface Runoff, Sewage and Wastewater
from Construction Activities
Surface runoff from construction site may contain considerable loads of SS and contaminants during construction activities. Local and coastal waters may be impacted if the construction site run-off is allowed to discharge into the storm drains or natural drainage without mitigation. Potential water quality impact includes run-off and erosion of exposed bare soil and earth, and stockpiles.
Accumulation
of solid and liquid waste such as packaging and construction materials, sewage
effluent from the construction workforce, and spillage of oil, diesel or
solvents by vessels and vehicles involved with the construction, if
uncontrolled, would lead to deterioration in water quality. Increased nutrient level from contaminated
discharges and sewage effluent would also lead to secondary water quality
impacts including decrease in DO concentrations and localised increase in NH3-N
concentrations which would stimulate algal growth.
Sewage
would arise from sanitary facilities provided for the on-site construction work
force which would be characterised by high levels of BOD, NH3-N and E. coli.
No
maintenance dredging is required for the future operation of the proposed
submarine watermain. There would be no hydrodynamic impact as the operation of
the submarine watermain would not involve reclamation or filling that would
affect the flow volume within
There would also be no water quality impact during the operation phase of the submarine watermain as no effluent would be discharged due to operation of the submarine watermain.
3.7 Prediction and Evaluation of Environmental Impacts
Water quality impact on the
sensitive receivers during the entire duration of dredging works and along the
entire alignment was simulated with the maximum possible instantaneous
working rate of 0.0463m3s-1for
two typical spring neap tidal cycles during dry and wet seasons in
The predicted suspended solids elevations and concentrations for all scenarios in dry and wet seasons at marine ecology sensitive receivers and the cooling and seawater intakes are presented in Tables 3-11 to 3-14 respectively. The results indicated exceedance of WSD water quality (SS) criterion at WSD Seawater Intake at Kowloon South Salt Water Pumping Station. Mitigation measure is therefore required to minimise the impact.
The
contours presented in FiguresC3.1b and 3.1c in Appendix C showed the extent of tidal averaged surface SS
elevations over the complete simulation period during dry and wet seasons,
respectively. As shown in these figures, the extent of SS impact appeared to be
confined near the dredging location at
The
contours presented in FigureC3.1d in Appendix C showed the predicted net
sedimentation per metre square per day during dry and wet seasons,
respectively. Both figures indicated that the sedimentation rates were highest
at waters along the coast of
Table 3‑11 Predicted Suspended Solids Elevations at Marine Ecology Sensitive Receivers
Sensitive
Receivers |
Assessment |
SS
Criterion |
Maximum SS
Elevation |
|||
|
Point |
(mgL-1) |
Dry Season |
|
Wet Season |
|
|
|
|
Depth
averaged (mgL-1) |
Surface
layer (mgL-1) |
Depth
averaged (mgL-1) |
Surface
layer (mgL-1) |
Typhoon
Shelter |
|
|
|
|
|
|
New Yau Ma Tei Typhoon Shelter |
R1 |
- |
0 |
0 |
0.1 |
0 |
Marine
Ecology Sensitive Receivers |
|
|
|
|
|
|
|
R2 |
Elevation <10 |
0.1 |
0.1 |
0 |
0 |
|
R3 |
Elevation <10 |
0.1 |
0.1 |
0 |
0 |
|
R4 |
Elevation <10 |
0.2 |
0.2 |
0 |
0 |
|
R5 |
Elevation <10 |
0.2 |
0.2 |
0 |
0 |
-
Values in Bold indicates exceedance of relevant
criteria
Table 3‑12 Predicted Suspended Solids Concentrations at Marine Ecology Sensitive Receivers
Sensitive
Receivers |
Assessment |
SS
Criterion |
Maximum(1) SS Concentration |
|||
|
Point |
(mgL-1) |
Dry Season |
|
Wet Season |
|
|
|
|
Depth
averaged (mgL-1) |
Surface
layer (mgL-1) |
Depth
averaged (mgL-1) |
Surface
layer (mgL-1) |
Typhoon
Shelter |
|
|
|
|
|
|
New Yau Ma Tei Typhoon Shelter |
R1 |
- |
8.8 |
8.6 |
8.5 |
6.8 |
Marine
Ecology Sensitive Receivers |
|
|
|
|
|
|
|
R2 |
- |
8.9 |
8.7 |
8.4 |
6.7 |
|
R3 |
- |
8.9 |
8.7 |
8.4 |
6.7 |
|
R4 |
- |
9.0 |
8.8 |
8.4 |
6.7 |
|
R5 |
- |
9.0 |
8.7 |
8.4 |
6.7 |
-
Values in Bold indicates exceedance of relevant
criteria
(1) SS concentration include the ambient SS levels presented
in Table 3.9 plus the SS elevation predicted in Table 3.11.
Table 3‑13 Predicted Suspended Solids Elevations at Cooling and Sea Water Intakes
Sensitive
Receivers |
Maximum SS
elevation in surface layer (mgL-1) |
|||
|
Assessment
Point |
SS
Criterion (mgL-1) |
Dry Season |
Wet Season |
Cooling Water Intakes |
|
|
|
|
Reprovisioned
Prince’s Building Group at CRIII |
R11 |
- |
0.8 |
0.4 |
Reprovisioned
Hong Kong Shanghai Bank at CRIII |
R12 |
- |
0.2 |
0.1 |
Reprovisioned
Queensway Government Offices, Admiralty and Police Headquarters at CRIII |
R13 |
- |
0.3 |
0.1 |
WSD Seawater Intakes |
|
|
|
|
Cheung Sha
Wan Salt Water Pumping Station |
R14 |
- |
0 |
0 |
|
R15 |
- |
13.0 |
9.1 |
|
R28 |
- |
0 |
0 |
Sheung Wan
Salt Water Pumping Station |
R29 |
- |
1.2 |
1.4 |
|
||||
|
R6 |
- |
1.2 |
1.4 |
|
R7 |
- |
1.2 |
1.4 |
|
R8 |
- |
1.1 |
1.1 |
|
R9 |
- |
1.0 |
0.7 |
|
R10 |
- |
0.9 |
0.6 |
|
R16 |
- |
1.2 |
0.4 |
|
R17 |
- |
1.0 |
0.3 |
MTRC Cooling
Mains |
R18 |
- |
0.6 |
0.1 |
|
R19 |
- |
0 |
0 |
|
R20 |
- |
0.6 |
0.3 |
- Values in Bold indicates exceedance of relevant
criteria.
Table 3‑14 Predicted Suspended Solids Concentrations at Cooling and Sea Water Intakes
Sensitive
Receivers |
Maximum (1) SS concentration in surface layer (mgL-1) |
|||
|
Assessment
Point |
SS
Criterion (mgL-1) |
Dry
Season |
Wet Season |
Cooling Water Intakes |
|
|
|
|
Reprovisioned
Prince’s Building Group at CRIII |
R11 |
- |
9.4 |
7.1 |
Reprovisioned
Hong Kong Shanghai Bank at CRIII |
R12 |
- |
8.8 |
6.8 |
Reprovisioned
Queensway Government Offices, Admiralty and Police Headquarters at CRIII |
R13 |
<40 |
8.9 |
6.8 |
WSD Seawater Intakes |
|
|
|
|
Cheung Sha
Wan Salt Water Pumping Station |
R14 |
<10 |
8.6 |
6.7 |
|
R15 |
<10 |
21.6 |
15.8 |
|
R28 |
<10 |
8.6 |
6.7 |
Sheung Wan
Salt Water Pumping Station |
R29 |
<10 |
9.8 |
8.1 |
|
||||
|
R6 |
<10 |
9.8 |
8.1 |
|
R7 |
<10 |
9.8 |
8.1 |
|
R8 |
<10 |
9.7 |
7.8 |
|
R9 |
<10 |
9.6 |
7.4 |
|
R10 |
<10 |
9.5 |
7.3 |
|
R16 |
<10 |
9.8 |
7.1 |
|
R17 |
<10 |
9.6 |
7.0 |
MTRC Cooling
Mains |
R18 |
<10 |
9.2 |
6.8 |
|
R19 |
<10 |
8.6 |
6.7 |
|
R20 |
<10 |
9.2 |
7.0 |
- Values in Bold indicates exceedance of relevant
criteria.
(1) Absolute
value of SS includes the ambient SS level presented in Table 3.9 plus the SS
elevations predicted in Table 3.13.
3.7.2 Dissolved Oxygen, Total Inorganic Nitrogen and Unionised Ammonia
The predicted depth-averaged and bottom layer dissolved oxygen, total inorganic nitrogen and unionised ammonia elevations and concentrations for all scenarios in dry and wet seasons at marine ecology sensitive receivers and the cooling and seawater intakes are presented in Tables 3-15 and 3-16. The results in Table 3-16 indicated that TIN exceedance was recorded at all assessment points during wet season. As discussed previously, the ambient TIN level near the dredging area during wet season did not comply with the WQO for TIN.
The
contours presented in FiguresC3.2a, b and c, 3.3a and, 3.4a in Appendix C showed the extent of tidal
and depth-averaged DO depletion, DO depletion at bottom layer and TIN and NH3-N
elevations over a spring-neap cycle during dry and wet seasons, respectively.
As shown in these figures, the extent of DO, TIN and NH3-N
impact appeared to be confined near the dredging location at
As presented in Table 3-15, with the maximum decrease in DO predicted to be 0.696mgL-1 at R15 during dry season and maximum increase in TIN and NH3-N predicted to be 0.0166mgL-1 and 0.0017mgL-1 respectively at R15 during dry season, the impact of decrease in DO and increase in TIN and NH3-N is considered trivial, Implication of algal bloom and red tide is therefore minimal and mitigation measure is therefore not required.
Table 3‑15 Predicted Dissolved Oxygen, Total Inorganic Nitrogen and Unionised Ammonia Elevations
Sensitive
Receivers |
Assessment
Point |
Maximum
Depth-averaged DO depletion (mgL-1) |
Maximum
DO depletion at bottom layer (mgL-1) |
Maximum
TIN elevation (mgL-1) |
Maximum
NH3-N elevation (mgL-1) |
||||
|
|
Dry Season |
Wet Season |
Dry Season |
Wet Season |
Dry Season |
Wet Season |
Dry Season |
Wet Season |
Typhoon Shelter |
|
|
|
|
|
|
|
|
|
New Yau Ma
Tei Typhoon Shelter |
R1 |
0 |
0 |
0 |
0.01 |
0 |
0.0001 |
0 |
0 |
Marine Ecology Sensitive Receivers |
|
|
|
|
|
|
|
|
|
|
R2 |
0 |
0 |
0.01 |
0 |
0.0001 |
0 |
0 |
0 |
|
R3 |
0 |
0 |
0 |
0 |
0.0001 |
0 |
0 |
0 |
|
R4 |
0 |
0 |
0.01 |
0 |
0.0001 |
0 |
0 |
0 |
|
R5 |
0.01 |
0 |
0.01 |
0 |
0.0002 |
0 |
0 |
0 |
Cooling Water Intakes |
|
|
|
|
|
|
|
|
|
Reprovisioned
Prince’s Building Group at CRIII |
R11 |
0.03 |
0.02 |
0.04 |
0.03 |
0.0008 |
0.0005 |
0.0001 |
0 |
Reprovisioned
Hong Kong Shanghai Bank at CRIII |
R12 |
0.01 |
0.01 |
0.01 |
0.02 |
0.0003 |
0.0002 |
0 |
0 |
Reprovisioned
Queensway Government Offices, Admiralty and Police Headquarters at CRIII |
R13 |
0.01 |
0.01 |
0.01 |
0.02 |
0.0003 |
0.0002 |
0 |
0 |
WSD Seawater Intakes |
|
|
|
|
|
|
|
|
|
Cheung Sha
Wan Salt Water Pumping Station |
R14 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
R15 |
0.56 |
0.33 |
0.69 |
0.61 |
0.0166 |
0.0099 |
0.0017 |
0.0005 |
|
R28 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
Sheung Wan
Salt Water Pumping Station |
R29 |
0.06 |
0.05 |
0.12 |
0.10 |
0.0019 |
0.0015 |
0.0002 |
0.0001 |
Other Seawater Intakes |
|
|
|
|
|
|
|
|
|
|
R6 |
0.06 |
0.05 |
0.12 |
0.10 |
0.0019 |
0.0015 |
0.0002 |
0.0001 |
|
R7 |
0.06 |
0.05 |
0.12 |
0.10 |
0.0019 |
0.0015 |
0.0002 |
0.0001 |
|
R8 |
0.05 |
0.04 |
0.10 |
0.09 |
0.0016 |
0.0012 |
0.0002 |
0.0001 |
|
R9 |
0.04 |
0.03 |
0.05 |
0.05 |
0.0011 |
0.0009 |
0.0001 |
0 |
|
R10 |
0.04 |
0.03 |
0.06 |
0.06 |
0.0011 |
0.0010 |
0.0001 |
0 |
|
R16 |
0.05 |
0.01 |
0.06 |
0.05 |
0.0014 |
0.0004 |
0.0001 |
0 |
|
R17 |
0.04 |
0.01 |
0.05 |
0.03 |
0.0012 |
0.0003 |
0.0001 |
0 |
MTRC Cooling
Mains |
R18 |
0.03 |
0.01 |
0.04 |
0.02 |
0.0008 |
0.0003 |
0.0001 |
0 |
|
R19 |
0 |
0 |
0.01 |
0.01 |
0.0001 |
0.0001 |
0 |
0 |
|
R20 |
0.02 |
0.02 |
0.03 |
0.04 |
0.0007 |
0.0005 |
0.0001 |
0 |
- Values in Bold indicates exceedance of relevant
criteria.
Table 3‑16 Predicted Dissolved Oxygen, Total Inorganic Nitrogen and Unionised Ammonia Concentrations
Sensitive
Receivers |
Assessment
Point |
Minimum
Depth-averaged DO level (mgL-1) |
Minimum
DO level at bottom layer (mgL-1) |
Maximum
TIN concentration (mgL-1) |
Maximum
NH3-N concentration (mgL-1) |
||||
|
|
Dry Season |
Wet Season |
Dry Season |
Wet Season |
Dry Season |
Wet Season |
Dry Season |
Wet Season |
Typhoon Shelter |
|
|
|
|
|
|
|
|
|
New Yau Ma
Tei Typhoon Shelter |
R1 |
6.00 |
5.10 |
6.00 |
4.69 |
0.3100 |
0.4301 |
0.0060 |
0.0100 |
Marine Ecology Sensitive Receivers |
|
|
|
|
|
|
|
|
|
|
R2 |
6.00 |
5.10 |
5.99 |
4.70 |
0.3101 |
0.4300 |
0.0060 |
0.0100 |
|
R3 |
6.00 |
5.10 |
6.00 |
4.70 |
0.3101 |
0.4300 |
0.0060 |
0.0100 |
|
R4 |
6.00 |
5.10 |
5.99 |
4.70 |
0.3101 |
0.4300 |
0.0060 |
0.0100 |
|
R5 |
5.99 |
5.10 |
5.99 |
4.70 |
0.3102 |
0.4300 |
0.0060 |
0.0100 |
Cooling Water Intakes |
|
|
|
|
|
|
|
|
|
Reprovisioned
Prince’s Building Group at CRIII |
R11 |
5.97 |
5.08 |
5.96 |
4.67 |
0.3108 |
0.4305 |
0.0061 |
0.0100 |
Reprovisioned
Hong Kong Shanghai Bank at CRIII |
R12 |
5.99 |
5.09 |
5.99 |
4.68 |
0.3103 |
0.4302 |
0.0060 |
0.0100 |
Reprovisioned
Queensway Government Offices, Admiralty and Police Headquarters at CRIII |
R13 |
5.99 |
5.09 |
5.99 |
4.68 |
0.3103 |
0.4302 |
0.0060 |
0.0100 |
WSD Seawater Intakes |
|
|
|
|
|
|
|
|
|
Cheung Sha
Wan Salt Water Pumping Station |
R14 |
6.00 |
5.10 |
6.00 |
4.70 |
0.3100 |
0.4300 |
0.0060 |
0.0100 |
|
R15 |
5.44 |
4.77 |
5.31 |
4.09 |
0.3266 |
0.4399 |
0.0077 |
0.0105 |
|
R28 |
6.00 |
5.10 |
6.00 |
4.70 |
0.3100 |
0.4300 |
0.0060 |
0.0100 |
Sheung Wan
Salt Water Pumping Station |
R29 |
5.94 |
5.05 |
5.88 |
4.60 |
0.3119 |
0.4315 |
0.0062 |
0.0101 |
Other Seawater Intakes |
|
|
|
|
|
|
|
|
|
|
R6 |
5.94 |
5.05 |
5.88 |
4.60 |
0.3119 |
0.4315 |
0.0062 |
0.0101 |
|
R7 |
5.94 |
5.05 |
5.88 |
4.60 |
0.3119 |
0.4315 |
0.0062 |
0.0101 |
|
R8 |
5.95 |
5.06 |
5.90 |
4.61 |
0.3116 |
0.4312 |
0.0062 |
0.0101 |
|
R9 |
5.96 |
5.07 |
5.95 |
4.65 |
0.3111 |
0.4309 |
0.0061 |
0.0100 |
|
R10 |
5.96 |
5.07 |
5.94 |
4.64 |
0.3111 |
0.4310 |
0.0061 |
0.0100 |
|
R16 |
5.95 |
5.09 |
5.94 |
4.65 |
0.3114 |
0.4304 |
0.0061 |
0.0100 |
|
R17 |
5.96 |
5.09 |
5.95 |
4.67 |
0.3112 |
0.4303 |
0.0061 |
0.0100 |
MTRC Cooling
Mains |
R18 |
5.97 |
5.09 |
5.96 |
4.68 |
0.3108 |
0.4303 |
0.0061 |
0.0100 |
|
R19 |
6.00 |
5.10 |
5.99 |
4.69 |
0.3101 |
0.4301 |
0.0060 |
0.0100 |
|
R20 |
5.98 |
5.08 |
5.97 |
4.66 |
0.3107 |
0.4305 |
0.0061 |
0.0100 |
- Values in Bold indicate exceedance of relevant criteria.
(1) DO, TIN and NH3-N concentrations
include the ambient levels presented in Table 3.10 plus the DO and TIN and NH3-N
elevations predicted in Table 3.15.
3.7.3 Potential Contaminant Release During Dredging
The extent of marine sediment contamination along the alignment of the proposed cross harbour main was reported in Section 6. Fifteen vibrocore samples as shown in Figure 6.1 were collected during the marine site investigation conducted in September 2006. The contaminant levels of vibrocore samples and their classifications under the definitions of ETWB TCW No. 34/2002 are presented in Table 6-9. The results indicated that high level of contamination in terms of arsenic (As), copper (Cu), lead (Pb), mercury (Hg), silver (Ag), polyaromatic hydrocarbons (PAHs) and polychlorinated biphenols (PCBs) were found essentially at a number of vibrocore samples.
These contaminants pose a higher risk of water quality impact as they would be released into the marine water when the sediment was disturbed during dredging. Thus, the elutriate tests of these parameters with sediment samples collected at all vibrocores were conducted. The tests provided an indication of the likelihood of release of heavy metals from the marine mud during dredging. The elutriate tests result was considered as rough estimation of the contaminant release at the point of dredging (9). The results are summarised in Table 3-17.
Table 3‑17 Comparison of Marine Sediment Elutriate Test Results with Water Quality Standards
Vibrocore No. |
Metal
Content (µgL-1) |
LMW PAHs (µgL-1) |
HMW PAHs (µgL-1) |
Total PCBs (µgL-1) |
||||
|
As |
Cu |
Pb |
Hg |
Ag |
|
|
|
VC1a |
71 |
<1 |
8.1 |
<0.1 |
<1 |
<0.2 |
<0.2 |
<0.01 |
VC2a |
15 |
<1 |
1.1 |
<0.1 |
<1 |
<0.2 |
<0.2 |
<0.01 |
VC3a |
33 |
1.1 |
1 |
<0.1 |
<1 |
<0.2 |
<0.2 |
<0.01 |
VC4a |
1.1 |
2.9 |
<1 |
<0.1 |
<1 |
<0.2 |
<0.2 |
<0.01 |
VC5a |
9.6 |
2.7 |
<1 |
<0.1 |
<1 |
<0.2 |
<0.2 |
<0.01 |
VC6a |
<1 |
1 |
<1 |
<0.1 |
<1 |
<0.2 |
<0.2 |
<0.01 |
VC7a |
15 |
1.6 |
1.9 |
<0.1 |
<1 |
<0.2 |
<0.2 |
<0.01 |
VC8a |
4.1 |
1.2 |
<1 |
<0.1 |
<1 |
<0.2 |
<0.2 |
<0.01 |
VC9a |
2.4 |
1.7 |
<1 |
<0.1 |
<1 |
<0.2 |
<0.2 |
<0.01 |
VC10a |
1.7 |
3.1 |
<1 |
<0.1 |
<1 |
<0.2 |
<0.2 |
<0.01 |
VC11a |
<1 |
1.1 |
<1 |
<0.1 |
<1 |
<0.2 |
<0.2 |
<0.01 |
VC12a |
<1 |
<1 |
<1 |
<0.1 |
<1 |
<0.2 |
<0.2 |
<0.01 |
VC13a |
1.6 |
4.9 |
1.8 |
<0.1 |
<1 |
<0.2 |
<0.2 |
<0.01 |
VC14a |
3.9 |
<1 |
<1 |
<0.1 |
<1 |
<0.2 |
<0.2 |
<0.01 |
VC15a |
6.3 |
<1 |
1.1 |
<0.1 |
2.7 |
<0.2 |
<0.2 |
<0.01 |
Water
Quality Standard |
25(3) |
5(1) |
25(1) |
0.3(1) |
2.3(1) |
3.0(2) |
3.0(2) |
0.03(4) |
Note: Values in
bold indicates exceedance of Water
Quality Standard
(1)
(2)
Australian and
(3)
Environmental
Economic and BPEO Assessment Principals for Integrated Pollution Control
(4)
USEPA Salt Water
Criterion
As shown in Table 3-17, the As, Cu, Pb, Hg, Ag, PAHs and PCBs content in the elutriate samples fall within the UK Water Quality Standard, Australian and New Zealand Guidelines for Fresh and Marine Waters, Environmental Economic and BPEO Assessment Principals for Integrated Pollution Control and USEPA Salt Water Criterion respectively except for As at VC1a and 3a and Ag at VC15a.
Based on the detected highest concentrations for As, the required dilution to meet the relevant water quality standard was calculated to be 2.8. To estimate the extent of the mixing zone, conservative estimation of the required dilution factor was conducted. Although elevation of suspended solids in bottom layer is not a hundred percent representative of contaminant release, suspended solids in bottom layer represents a very conservative estimation of contaminant release. As shown in Figures C3.1b and c in Appendix C where the predicted maximum elevation of suspended solids in dry and wet seasons at the bottom layer were presented, about 3 times dilution could be achieved in a mixing zone of approximately 400m. As water quality sensitive receivers were not identified within the mixing zone of 400m, adverse water quality impacts are therefore not anticipated. Moreover, it is expected that any release of heavy metals during dredging will be quickly diluted by the large volume of marine water within the construction site. The release of pollutants will also be minimised by the use of closed grab dredger and the dispersion of pollutants will be confined within the construction site by the silt curtains (Section 3.8.1). Thus, it is considered that long-term off-site water quality impact is unlikely and any local water quality impact will be transient and localised.
3.7.4 Hydrostatic Tests of the Water Mains System
Effluent from the hydrostatic tests of water supply pipeworks which the volume of discharge would be 2,500m3 would be subjected to pre-treatment including dechlorination such as by physical process e.g. adsorption by activated carbon filter, or chemical process e.g. neutralisation by dechlorination agent dosing to ensure compliance with the discharge requirements stipulated in TM-DSS . High SS concentration in marine water would lead to associated reduction in DO levels. Proper practice and good management should be strictly followed to prevent water with high level SS from entering the surrounding waters. With the implementation of appropriate measures to control water discharge from hydrostatic test, disturbance of water bodies would be localised and deterioration in water quality would be minimal. Effluent from hydrostatic tests would comply with the standards for effluent discharged into the inshore waters or marine waters of the Victoria Harbour WCZ as shown in Tables 9a and 9b of the TM-DSS and Sections 23.73 and 23.77 of the General Specification for Civil Engineering Works Volume 3, 1992 Edition provided the recommended mitigation measures detailed in Section 3.8 were properly implemented.
3.7.5 Surface Runoff, Sewage and Wastewater from Construction Activities
Construction run-off would cause physical, chemical and biological effects. The physical effects would arise from any increase in SS from the construction site that blocks drainage channels and causes local flooding when heavy rainfall occurs. High SS concentrations in marine water would also lead to associated reduction in DO levels.
Proper
site practice and good site management should be strictly followed to prevent
run-off water with high level of SS from entering the surrounding waters. With the implementation of appropriate
measures to control run-off from the construction site, disturbance of water
bodies would be localised and deterioration in water quality would be
minimal. Unacceptable impacts on the
water quality were not expected provided that the recommended measures
described in Sections 3.8 were properly implemented.
Provided that good construction practices are observed to ensure that litter, fuels, and solvents are managed, stored and handled properly, effects on water quality from general construction activities would be minimal.
Based on the Sewerage Manual, Part I, 1995 of the Drainage Services Department (DSD), the global unit flow factor for employed population of 0.06 m3 per worker per day and commercial activities in year 2012 of 0.29 m3 per worker per day were used to estimate the sewage generation from the construction site. The total sewage production rate was estimated at 0.35 m3 per worker per day. With every 100 construction workers working simultaneously at the construction site, a total of about 35 m3 of sewage would be generated per day. The sewage should not be allowed to discharge directly into the surrounding water body without treatment. Chemical toilets and subsequently on-site sewer should be deployed at the construction site to collect and handle sewage from workers.
3.8 Mitigation of Adverse Environmental Impact
Specific Mitigation Measures for
dredging
Exceedances
of WSD Seawater Intake criterion (10 mg L-1) at Kowloon South Salt
Water Pumping Station was predicted during both dry and wet seasons if dredging
was undertaken near
·
Dredging should be undertaken using one grab
dredger only with a maximum production rate of 4,000m3 per day;
·
Deployment of frame type silt curtain to fully
enclose the grab while dredging works are in progress;
·
Deployment of silt screen at the sea water intake at
Kowloon South Salt Water Pumping Station while dredging works are in
progress.
The frame type silt curtain should be designed to enclose local pollution caused by the grab dredger and suspended by a steel frame mounted on the grab dredger and floating on water. This frame type silt curtain should be fabricated from permeable, durable, abrasion resistant membrane like geotextiles and be mounted on a floating boom structure. The frame type silt curtain should also extend to the seabed to cover the entire water column. Steel chain or ballast should be attached to the bottom of the silt curtain. Mid-ballast may be added as necessary. The structure of the silt curtain should be maintained by metal grids. The frame type silt curtain should be capable or reducing sediment loss to outside by a factor of 4 (or about 75% (10). Silt screen is recommended for dredging near the seawater intake at Kowloon South Salt Water Pumping Station. The implementation of silt screen at the intake could reduce the SS level by a factor of 2.5 (or about 60%) (10). These SS reduction factors have been adopted in the Wan Chai Development Phase II Environmental Impact Assessment Study in 2001. An illustration of a typical configuration of frame type silt curtain and silt screen at seawater intake is shown in Figure 3.9.
Table 3‑18 Predicted SS concentration at the WSD Seawater Intake after implementation of frame type silt curtain and silt screen at the intake
|
SS
Criterion (mgL-1) |
SS
elevation in surface layer (mgL-1) |
SS
concentration in surface layer (mgL-1) (1) |
||
Dry Season |
Wet Season |
Dry Season |
Wet Season |
||
|
<10 |
1.3 |
0.9 |
9.9 |
7.6 |
(1) SS
concentration includes the ambient SS level (8.6 mg L-1 for dry
season and 6.7 mg L-1 for wet season) in the surface layer of water
column
Table 3-18 summarises the predicted SS concentration at WSD Sea Water Intake at Kowloon South Salt Water Pumping Station after implementation of frame type silt curtain and silt screen at the sea water intake at Kowloon South Salt Water Pumping Station. With the implementation of frame type silt curtain and silt screen at sea water intake at Kowloon South Salt Water Pumping Station, the impacted WSD Seawater Intake at Kowloon South Salt Water Pumping Station will comply with the relevant SS criterion (10 mg L-1) during both the dry and wet season. Further mitigation measures were considered not necessary.
Other Mitigation Measures for dredging
Good site practice that should be undertaken during dredging includes:
·
Tight-closing grabs should be used to minimize the
loss of sediment to suspension during dredging works. For dredging of any contaminated mud, closed
watertight grabs must be used;
·
all vessels should be sized so that adequate
clearance is maintained between vessels and the seabed in all tide conditions,
to ensure that undue turbidity is not generated by turbulence from vessel
movement or propeller wash;
·
the decks of all vessels should be kept tidy and
free of oil or other substances that might be accidentally or otherwise washed
overboard;
·
adequate free board shall be maintained on barges to
ensure that decks are not washed by wave action;
·
all barges used for the transport of dredged materials
should be fitted with tight bottom seals to prevent leakage of material during
loading and transport;
·
construction activities should not cause foam, oil,
grease, scum, litter or other objectionable matter to be present in the water
within the site or dumping grounds;
·
loading of barges should be controlled to prevent
splashing of material into the surrounding waters. Barges should not be filled to a level that
would cause the overflow of materials or sediment laden water during loading or
transportation;
·
the speed of vessels should be controlled within the
works area to prevent propeller wash from stirring up the seabed sediments; and
·
before commencement of dredging works, the holder of
the Environmental Permit should submit detailed proposal of the design and
arrangement of the frame type silt curtain to EPD for approval.
Effluent from Hydrostatic Tests of the
Water Mains System
To ensure compliance with the standards for effluent discharged into the inshore waters or marine waters of Victoria Harbour WCZ as shown in Tables 9a and 9b of the TM-DSS and Section 23.73 and 23.77 of the General Specification for Civil Engineering Works Volume 3, 1992 Edition, sedimentation tanks with sufficient capacity, constructed from pre-formed individual cells of approximately 6 to 8 m3 capacities, are recommended as a general mitigation measure which can be used for settling the effluent prior to disposal. The system capacity should be flexible and suited to applications where the influent is pumped. Pre-treatment including dechlorination such as by physical process e.g. adsorption by activated carbon filter, or chemical process e.g. neutralisation by dechlorination agent dosing should be carried out to ensure compliance with the discharge requirements stipulated in TM-DSS.
Surface Runoff, Sewage and Wastewater
from Construction Activities
Appropriate measures should be implemented to control runoff and prevent high loads of SS from entering the marine environment. Proper site management is essential to minimise surface runoff and sewage effluents.
Construction site runoff should be prevented or minimised in accordance with the guidelines stipulated in the EPD's Practice Note for Professional Persons, Construction Site Drainage (ProPECC PN 1/94). All discharges from the construction site should be controlled to comply with the standards for effluents discharged into the Victoria Harbour WCZ under the TM-DSS. Good housekeeping and stormwater best management practices, as detailed below, should be implemented to ensure all construction runoff complies with WPCO standards and no unacceptable impact on the WSRs as a result of construction of the proposed submarine watermain.
Sedimentation tanks with sufficient capacity, constructed from pre-formed individual cells of approximately 6 to 8 m3 capacities, are recommended as a general mitigation measure which can be used for settling surface runoff prior to disposal. The system capacity should be flexible and able to handle multiple inputs from a variety of sources and suited to applications where the influent is pumped.
Manholes (including newly constructed ones) should always be adequately covered and temporarily sealed so as to prevent silt, construction materials or debris being washed into the storm runoff being directed into foul sewers.
All vehicles and plant should be cleaned before leaving a construction site to ensure no earth, mud, debris and the like is deposited by them on roads. An adequately designed and located wheel washing bay should be provided at every site exit, and wash-water should have sand and silt settled out and removed at least on a weekly basis to ensure the continued efficiency of the process. The section of access road leading to, and exiting from, the wheel-wash bay to the public road should be paved with sufficient backfill toward the wheel-wash bay to prevent vehicle tracking of soil and silty water to public roads and drains.
Precautions should be taken at any time of year when rainstorms are likely. Actions should be taken when a rainstorm is imminent or forecast. Actions to be taken during or after rainstorms are summarised in Appendix A2 of ProPECC PN 1/94. Particular attention should be paid to the control of silty surface runoff during storm events, particularly for areas located near steep slopes.
Fuel
tanks and storage areas should be provided with locks and be located on sealed
areas, within bunds of a capacity equal to 110% of the storage capacity of the
largest tank, to prevent spilled fuel oils from reaching the coastal waters of
the
Portable chemical toilets would be used to handle construction workforce sewage prior to discharge to the existing trunk sewer. Sufficient numbers of portable toilets shall be provided by a licensed contractor to serve the construction workers. The Contractor shall also be responsible for waste disposal and maintenance practices.
3.9 Evaluation of Residual Impacts
Major water quality impact associated with dredging activities is the elevation of SS within the marine water column. Provided the recommended mitigation measures including the use of one grab dredger only with a maximum production rate of 4,000m3 per day for dredging, deployment of frame type silt curtain to fully enclose the grab while dredging works are in progress and deployment of silt screen at the seawater intake at Kowloon South Salt Water Pumping Station while dredging works are in progress are implemented, no unacceptable residual cumulative water quality impact due to construction of the cross harbour main as well as the other concurrent marine works is expected.
Hydrostatic test of the water mains system would lead to effluent containing elevated concentrations of SS that would enter into the surrounding water. It was however expected that the above water quality impact would be temporary and localised during construction only. Provided the recommended mitigation measure is implemented and the effluent discharge complied with the TM-DSS standards, no unacceptable residual water quality impact due to effluent arising from hydrostatic test is expected.
General construction activities associated with the construction of the submarine watermain would lead to construction site runoff containing elevated concentrations of SS and associated contaminants that would enter into the marine water. It was however expected that the above water quality impacts would be temporary and localised during construction only. Provided the recommended mitigation measures are implemented and all construction site/works area discharges complied with the TM-DSS standards, no unacceptable residual water quality impact due to construction of the submarine watermain is expected.
3.10 Environmental Monitoring and Audit
Based on the above assessment of the water quality impact, an environmental monitoring and audit (EM&A) programme was considered necessary to obtain a robust, defensible database of baseline information of water quality before construction, and thereafter, to monitor any variation of water quality from the baseline conditions and exceedances of WQOs at sensitive receivers during construction. Details of the EM&A were presented in a stand-alone EM&A Manual.
3.11 Conclusions and Recommendations
Water
quality impact during the dredging works of the submarine watermain was
quantitatively assessed using the Delft3D Model. Suspended sediment was identified as the key
water quality parameter during dredging.
Water quality impact on the sensitive receivers during the entire
duration of the dredging works and along the entire alignment with the maximum
possible instantaneous working rate of 0.0463m3s-1.
(i.e. one grab dredger with
a maximum production rate of 4,000m3 per
day, 7 days per week, 24 hours per day) for the complete simulation period for
the dry and wet seasons was assessed and it was predicted that potential water
quality impact would occur at the WSD Sea Water Intake at Kowloon South Salt
Water Pumping Station. With the implementation of the proposed mitigation
measures including the use of one grab dredger only with a maximum production
rate of 4,000m3 per day for dredging,
deployment of frame type silt curtain to fully enclose the grab while dredging
works are in progress and deployment of silt screen at the sea water intake at
Kowloon South Salt Water Pumping Station while dredging works are in progress,
the potential water quality impact upon the sea water intake would be
effectively minimised and there would be no unacceptable residual cumulative
water quality impact due to the dredging works of the submarine watermain as
well as the other concurrent marine works.
The assessment predicted that the dredging works would have negligible
impact upon the coral communities near
Minor potential water quality impacts from hydrostatic tests of the water mains systems and construction activities associated with the construction of the proposed submarine watermain were associated with effluent, sewage, wastewater and surface runoff. Impacts could be controlled to comply with the WPCO standards by implementing the recommended mitigation measure. No unacceptable residual impact on water quality was expected.
No
maintenance dredging is required for the future operation of the proposed
submarine watermain. There would be no hydrodynamic impact as the operation of
the submarine watermain would not involve reclamation or filling that affects
the flow volume within the
There would also be no water quality impact during the operation of the submarine watermain as no effluent would be discharged due to the operation of the submarine watermain.
The submarine
watermain component of the Project across Victoria Harbour is a Designated
Project under Schedule 2, Part 1I(E3) of the Environmental Impact Assessment
Ordinance (EIAO) (Cap. 499) and an Environmental Permit (EP) issued under the
EIAO is required for the construction and operation of the designated project.
In accordance with the EIA Study
Brief No. ESB-132/2005, construction and operation marine ecological impact
arising from the dredging, laying of pipe and backfilling works for the construction
of the submarine watermain were assessed.
This
section presents the results of the assessment of ecological value of the
habitat and marine resources of the Study Area for the proposed submarine
watermain according to the EIA Study Brief No. ESB-132/2005. The potential
impacts from the construction and operation of the Project on the
existing ecological resources
in the Study Area were assessed and evaluated according to the EIAO-TM Annex 8
and 16.
4.2
Environmental
Legislation, Standards, Guidelines and Criteria
A number of international conventions, local legislations and guidelines provide the framework for the protection of species and habitats of ecological importance. Those related to the Project are:
· Wild Animals Protection Ordinance (Cap 170);
· Protection of Endangered Species of Animals and Plants (Ordinance (Cap 586);
· Town Planning Ordinance (Cap 131);
·
· The Technical Memorandum on Environmental Impact Assessment Process under the Environmental Impact Assessment Ordinance (EIAO TM);
·
EIAO
Guidance Note No. 11/2004 Methodologies for Marine Ecological Baseline Surveys;
· United Nations Convention on Biodiversity (1992);
·
Convention
on International Trade in Endangered Species of Wild Flora and Fauna (CITES);
·
Convention
on the Conservation of Migratory Species of Wild Animals (the
·
IUCN Red Data Books; and
· PRC Regulations and Guidelines.
Under the Wild Animals Protection Ordinance, designated wild animals are protected from being hunted, whilst their nests and eggs are protected from destruction and removal. All birds and most mammals including all cetaceans are protected under this Ordinance, as well as certain reptiles, amphibians and invertebrates. The Second Schedule of the Ordinance that lists all the animals protected was last revised in June 1992.
The Protection of Endangered Species
of Animals and Plants Ordinance was
gazetted on
The Town Planning Ordinance provides for the designation of areas such as “Coastal Protection Areas”, “Sites of Special Scientific Interest (SSSIs)”, “Green Belt” and "Conservation Area” to promote conservation or protection or protect significant habitat.
Chapter 10 of the HKPSG covers planning considerations relevant to
conservation. This chapter details the
principles of conservation, the conservation of natural landscape and habitats,
historic buildings, archaeological sites and other antiquities. It also addresses the issue of
enforcement. The appendices list the
legislation and administrative controls for conservation, other conservation
related measures in
Annex 16 of the EIAO TM sets out the general approach and methodology for assessment of ecological impacts arising from a project or proposal, to allow a complete and objective identification, prediction and evaluation of the potential ecological impacts. Annex 8 recommends the criteria that can be used for evaluating ecological impacts.
EIAO Guidance Note No. 11/2004 Methodologies for Marine Ecological Baseline Surveys elaborates on Annex 16 of the TM to provide information on the requirements of marine ecological baseline study. The note provides general guidelines for conducting a marine ecological baseline survey in order to fulfil the requirements stipulated in the TM in respect of marine ecological assessment for a proposed development.
The Peoples’ Republic of China (PRC) is a Contracting Party to the United Nations Convention on Biological Diversity of 1992. The Convention requires signatories to make active efforts to protect and manage their biodiversity resources. The Government of the Hong Kong Special Administrative Region has stated that it will be “committed to meeting the environmental objectives” of the Convention (PELB 1996).
CITES (the Convention on International Trade in Endangered Species of Wild Fauna and Flora) is an international agreement between Governments. Its aim is to ensure that international trade in specimens of wild animals and plants does not threaten their survival.
The Convention on Migratory Species of Wild
Animals (
The PRC in 1988 ratified the Wild Animal Protection Law of the PRC, which lays down basic principles for protecting wild animals. The Law prohibits killing of protecting animals, controls hunting, and protects the habitats of wild animals, both protected and non-protected. The Law also provides for the creation of lists of animals protected at the state level, under Class I and Class II. There are 96 animal species in Class I and 156 in Class II. Class I provides a higher level of protection for animals considered to be more threatened.
The Study Area was defined as the assessment area for
Water Quality Impact Assessment, which is within 500 m from the site boundary,
the
The baseline information was gathered base on but not limited to the following publications and information:
·
Environmental Resources Management (1998). Environmental Impact Assessment: Dredging an
Area of Kellett Bank for Reprovisioning of Six Government Mooring Buoys. Civil
·
Scott Wilson Kirpatrick Consulting Engineering
(1995).
· Atkins China Ltd. (2001). Central Reclamation, Phase III – Studies, Site Investigation, Design and Construction Environmental Impact Assessment Report. Territory Development Department.
· Maunsell (2001). Wan Chai Development Phase II Comprehensive Feasibility Study Environmental Impact Assessment. Territory Development Department.
·
Maunsell Consultants Asia Limited (2002).
·
Morton, B.S. and Morton, J. (1983). The
·
Environmental Protection Department (2005). Marine Water Quality in
·
Tsim Sha Tsui Arial Photo date
·
Sai Wan and Green Island Arial Photos date
4.4 Baseline Conditions & Marine Ecological Sensitive Receivers
The Study Area consists of several habitats, including the
habitats in the intertidal zone (artificial seawalls and rocky shores),
sub-tidal zone (soft-bottom and hard-bottom habitats) and the open sea (
4.4.1
Existing Condition of
The location of the proposed submarine watermain is at the
west of
Intertidal Zone
Artificial Seawalls
The intertidal zone of the Project area consists of
breakwaters and sloping artificial seawall formed by large boulders and rock
armour during reclamation along West Kowloon Reclamation area (Figure 4.2). Vertical artificial
seawalls along Sai Ying Pun shoreline and concrete embanked wharf piles close
to the Western Wholesale Food Market are common habitats along the
Table 4‑1 Typical Members of the Macrofauling Community in Wharf Piles of
Zonation
Commonly Recorded |
Group |
Species |
Eulittoral
zone Eulittoral
zone Sub-littoral
fringe Sub-littoral
fringe Sub-littoral
zone Sub-littoral
zone |
Bivalve Barnacles Algae Ascidians Polychaete Polyzoa |
Perna
viridis Barbatia
virescens Trapezium
liratum Musculista senhausia Modiolus agripetus Ryenella cuprea Electroma japonica Saccostrea cucullata Chama spp. Striarca afra Claudiconcha japonica Balanus amphitrite Modiolus agripetus Ryenella cuprea Electroma japonica Balanus amphitrite Balanus reticulates Balanus variegates Balanus trigonus Ulva conglobata Enteromorpha prolifera Rhizoclonium riparium Codium cylindricum Colpomenia sinuosa Ascidia sydneiensis Ciona intestinalis Styela plicata Styela Herdmania momus Pomatoceros triqueter Hydroides elegans Spirorbis foraminosus Pedicellina (Genera) Barentsia (Genera) Loxosomella (Genera) |
Natural Rocky
Shores
Literature review showed that the species diversity at the
intertidal zone of Green
Baseline surveys of the coastal communities of Green Island, Little Green Island and a reference site in Hong Kong Island have been conducted by ERM in 1997 (23). In total 22 species of fauna and 8 species of algae were recorded, abstract of the most abundant species are listed in Table 4-2 below.
The results showed that the most abundant species were grazing gastropods including Chiton and Limpets at the low shore, and Periwinkles at the high shore. Predatory gastropods such as the Dogwhelks Thais clavigera and T. luteostoma were also recorded in low density at the low shore. Sessile organisms including Stalked Barnacles and Acorn Barnacles were recorded in high abundances. Algae were sparsely distributed along the shore during summer, with Cyanobacteria Pseudoulvella spp. having the highest percentage cover (24).
By comparing the three survey locations, the overall species abundance and species diversity were highest at the reference Hong Kong sites, followed by the Little Green Island and Green Island. The findings displayed the intertidal community to be typical of semi-exposed rocky shores. No rare species or species of conservation value were recorded during the survey.
Table 4‑2 Abstract of
Coastal Flora and Fauna recorded in
Zonation
Recorded |
Group |
Species |
Not
Mentioned Not
Mentioned |
Herbivorous
Molluscs Predatory
Gastropods Filter-feeding
Barnacles Cyanobacteria |
Chiton
(Acanthopleura japonica) Limpets
(Cellana grata,C. toreuma, Patelloida
pygmaea and P. saccharina) Periwinkles (Nodilittorina
trochoides, N. radiate and N. vidua) Dogwhelks
(Thais clavigera and T. luteostoma) Stalked
Barnacles (Capitulum mitella) Acorn
Barnacles (Tetraclita sp.) Pseudoulvella spp. |
Sub-tidal Zone
Soft-bottom Benthos Assemblages
The sea bed sediment of
In view of the similar composition of the sediment recorded between the literatures and this study, and low species diversity were recorded in the local region with references to difference studies, no benthic fauna survey was conducted. Benthic infauna and epifauna communities recorded within the Study Area and in vicinity have been reviewed, and the findings are summarised below.
Benthic Infauna
Benthic infauna can be studied by grab sampling, vibrocore
survey and the use of sediment profile photography method named Remote
Ecological Monitoring of the Seafloor (REMOTS). Grab sampling results showed
that the particle size distribution of the benthos between
Grab samples along the Sulphur Channel between Green
Island and Kennedy Town conducted in 1993 (Figure
4.1) showed that 92 macrobenthic organisms of 32 taxa were recorded, in
which 69% of the total number of individuals were polychaetes, others include
the molluscs and crustaceans (32).
The most abundant polychaetes comprised Prionospio
saccifera, Tharyx multifilis, Nephtys
polybranchia, Sternespis sculata and Sigambra
hanaokai.
Sediment sampling results in 1995 around the Central waterfront (Figure 4.1) recorded that no live benthic invertebrates were sampled (33). Only empty gastropod shells were collected. The malodorous and anoxic sediment suggested that the marine lives were subject to pollution stress by the long term sewage discharge into the region.
Remote Ecological Monitoring of the Seafloor Studies
(REMOTS) showed that benthic eutrophication occurs as a result of organic
enrichment from the harbour (sampling locations see Figure 4.1) (34).
Only the pollution tolerant polychaetes species (Spionidae and Capitellidae)
and crustaceans (crab larvae and small amphipods) in small size and low density
were recorded on the near surface sediment. CityU (2002) (35) also indicated that the
benthic fauna recorded in
Benthic Epifauna
Trawl surveys were conducted by ERM in 1995 (36) (see Figure 4.1 for trawling location). There are total 15 species and
44 individuals recorded close to the
Table 4‑3 Benthic Epifauna
Recorded around
Species |
Abundance |
Sponge Sclerobelemnon burgeri Pteroides esperi Virgularia gustaviana Gorgonacea sp. Anemones Unidentified
anemones Hydrozoa Unidentified
hydroids Bryozoan Unidentified
bryozoan Molluscs Callanailis hirascana Shrimps & Mantis shrimp Oratosquilla oratoria Crabs Portunus hastatoides Thalamita picta Fish Paralichthys olivaceus Oxyurichthys tentacularis Unidentified
Clupeidae Total no. of species Total no. of individuals |
6 2 2 1 16 1 2 1 5 3 1 1 1 1 1 15 44 |
Hard-bottom Coral Assemblages
Remotely Operated Vehicle (ROV) was used to conduct coral
survey around Green Island, Little Green Island and the Sulphur Channel close
to the western Hong Kong Island (reference site) by ERM as part of the
ecological surveys for the Green Island Development Studies in 1997 (38). Video were taken along
three 10m wide belt transects at depths of -5, -10 and -15 mPD. Four species of
soft coral and gorgonians were recorded in this study at
The seabed profile at the sub-tidal zone around
Table 4‑4 Frequency of Soft
Coral and Gorgonian Colonies Recorded around
Survey
Area and Transect No. |
Level (-mPD |
Species |
|||
Dendronephthya sp. |
Echinogorgia
complexa |
Euplexaura
curvata |
Ellisella
gracilis |
||
Little T1.1 T1.2 T1.3 T2.1 T2.2 T2.3 T3.1 T3.2 T3.3 T4.1 T4.2 T4.3 T5.1 T5.2 T5.3 T6.1 T6.2 T6.3 |
5 10 15 5 10 15 5 10 15 5 10 15 5 10 15 5 10 15 |
20 18 11 17 2 11 8 3 0 20 4 18 0 0 0 0 0 0 |
10 9 10 4 0 2 1 0 0 0 0 0 0 0 0 0 0 0 |
11 15 24 5 9 8 20 57 17 0 2 13 0 0 0 0 0 0 |
0 0 0 2 0 0 0 0 0 0 0 0 0 0 0 0 0 0 |
The most frequently encountered (more than 40 colonies per
transect) species in the Green Island was the White Sea Whip Euplexaura curvata, especially at the
western side of the Green Island at depth -10 mPD, followed by the Pink Soft
Coral Dendronephthya sp. which was
common in both the Green Island and Little Green Island waters. The Orange Sea
Fan Echinogorgia complexa was
considered as rare in the
Marine Mammals
All the marine mammals in
The Chinese White Dolphin has limited distribution in
Marine
Ecological Sensitive Receiver
There are no SSSIs, Fish Culture Zones,
Based on the literatures review of the baseline conditions
discussed above, the ecological assessment show that the marine ecological
resources within the Study Area for the proposed marine cross harbour main are
considered to be of low ecological value, due to their low species diversity
and the present of pollution tolerant indicator species. Except for the
sub-tidal and intertidal zone at
Table 4‑5 Evaluation of the Ecological Importance of the Inter-tidal Habitats
Criteria |
|
|
Naturalness |
Mainly
composed of artificial seawall receiving extensive disturbance through high
pollution load and wave action produced by marine traffic. |
Natural
rocky shores with little human disturbance. |
Size |
Approximate
660m of artificial shoreline was being studied. |
The
natural intertidal shoreline is approximately 2,000m. |
Diversity |
The
species diversity is low. |
The
species diversity is low. |
Rarity |
The
species recorded are commonly found on artificial seawalls in |
The
species recorded are typical of other semi-exposed rocky shores in |
Re-creatability |
The
artificial seawall is recreatable. |
The
natural rocky shores cannot be recreated. |
Fragmentation |
Not
applicable. |
Not
applicable. |
Ecological
Linkage |
The
existing habitats are not functionally linked to high ecological value
habitats. |
The
rocky shores ecologically link with the sub-tidal habitats in the surrounding
waters. |
Potential
Value |
Unlikely
to develop a nature conservation interest habitat. |
Moderate
potential to develop nature conservation interest habitat if water pollution
and other human disturbances remove. |
Nursery/Breeding
Ground |
Not
identified. |
Not
identified. |
Age |
Not
applicable. |
Not
applicable. |
Abundance/Richness
of Wildlife |
The
species abundance was low at vertical smooth structures but medium at wharf
piles. |
Compare
to reference site at |
Summary |
The
inter-tidal assemblages along shoreline of |
The
inter-tidal assemblages along the natural rocky shores at |
Table 4‑6 Evaluation of the Ecological Importance of the Sub-tidal Habitats
Criteria |
|
|
Naturalness |
The
sub-tidal zone is composed of marine sediments receiving continuous
disturbances. |
The
sub-tidal zone is composed of natural rocky seabed with scattered boulders
and become sandy offshore. |
Size |
Approximate
7,000m² of sub-tidal zone was studied. |
The
study area of the sub-tidal zone is small. |
Diversity |
The
species diversity of soft benthos is low. |
The
species diversity of benthic fauna and coral communities is moderate. |
Rarity |
The
species recorded are common in |
The
species recorded are not rare to |
Re-creatability |
The
disturbed seabed is recreatable. |
The
natural seabed can hardly recreate. |
Fragmentation |
Not
applicable. |
Not
applicable. |
Ecological
Linkage |
The
existing habitats are not functionally linked to high ecological value
habitats. |
The
sub-tidal habitats are ecologically link with the inter-tidal habitats in the
surrounding waters. |
Potential
Value |
Low
potential to develop a nature conservation interest habitat. |
Moderate
potential to develop nature conservation interest habitat if water pollution
and other human disturbances remove. |
Nursery/Breeding
Ground |
Not
identified. |
Not
identified. |
Age |
Not
applicable. |
Not
applicable. |
Abundance/Richness
of Wildlife |
The
soft benthos species abundance is low. |
Compare
to reference site at |
Summary |
The
sub-tidal assemblages in |
The
sub-tidal assemblages at |
4.6 Identification and Prediction of Environmental Impacts
The proposed submarine watermain will be constructed approximately 6 m below the existing seabed level. The major impacts on the marine ecological resources will be the direct impacts of habitats loss from dredging and backfilling activities at the seabed and installation of submarine pipeline by “bottom pull” method during construction phase. There may be indirect impacts through the changes to water flow regime, and perturbations of the surrounding water quality. The potential marine ecological impacts arising from construction and operational phases are detailed below.
Habitat Loss and
Disturbances
The direct impacts from construction activities include the permanent loss of approximately 9.2ha of natural seabed resulting from dredging activities for the installation of the proposed submarine watermain and temporary disturbance of approximate 51.2ha of works area in the marine environment. Less than 90m of artificial shore at Yau Ma Tei Typhoon Shelter will be disturbed by the construction of temporary platform and approximate 2m² on either side of the pipeline landing shores will be lost due to the installation of pipeline.
Direct and
Indirect Impacts on Marine Fauna
The dredging activities will also directly remove the less mobile wildlife inhabiting the affected area and surrounding habitats, and indirectly affect the marine wildlife through associated impacts including, degradation of habitat quality, reduce sunlight penetrating the water column due to increase turbidity and reduce the food production ability of the photosynthesizing animals, as well as behaviour changing due to change in physical environment.
The dredging and backfilling activities will also increase the suspended solids (SS) concentration, decrease in dissolved oxygen (DO) level and the increase in nutrient levels in the water column. The high concentration of SS may cause clogging of gills or filaments of the marine organisms, increase energy consumption to expel the sediments by the filter feeding animals, and the reduction in DO level for consumption may eventually cause the marine organisms suffocate to die. The high concentration or deposition rate of SS may also form a blanket that smother the corals and reduce the ability of the associated photosynthesising zooxanthellae to undertake photosynthesis; coral bleaching may occur or even die if the corals cannot tolerate the stresses.
Release of previously bound organic and inorganic constituents such as heavy metals, PAHs and polychlorinated biphenyls (PCBs) into the water column via suspension or disturbance of seabed as a result of dredging may also cause lethal or sub-lethal effect to the marine fauna.
The physical disturbances to the surrounding waters by the construction activities include the increase in human activities, inappropriate storage or dumping of construction materials, increase in marine traffic and change in water flow regime may indirectly affect the marine wildlife at the local region.
No post maintenance work is necessary for the proposed submarine watermain, and the potential impacts in operational phase are mainly the change in seabed profile and substrates along the 44m width alignment. The existing soft marine deposit with silt, sand and gravel will change to armour rock backfill with marine sediment naturally.
4.7 Evaluation of Environmental Impacts
Habitat Loss and
Disturbances
Habitat loss will occur at the sub-tidal zone and
artificial seawalls at the inter-tidal zone along the
The permanent loss of artificial seawalls sections are
very common structures along the seafronts in
In view of the paucity of marine wildlife and low ecological value of the affected seabed and artificial seawalls, the direct impacts on permanent loss of approximately 9.2ha of natural seabed along Victoria Harbour and less than 90m of artificial shores at Yau Ma Tei Typhoon Shelter resulting from dredging activities for the installation of the proposed pipeline, the impacts are considered to be of low significant. Species are expected to recolonize after construction.
Direct and
Indirect Impacts on Marine Fauna
From the baseline marine ecology results show that the marine benthos recorded within the construction area and in vicinity are of low ecological value and in low abundances. The impacts of the direct removal or indirect disturbances of these low importance species will be of low significance.
The potential impacts on the medium ecological value
habitats (the sub-tidal and inter-tidal habitats with coral communities and
natural rocky shores at Green Island) are the increase in SS concentration and
the associated deterioration of water quality at the Green Island waters due to
the dredging and backfilling activities. According to the water modelling
results presented in Section 3 Table
3-11, the predicted suspended solids concentrations for dredging undertaken
near West Kowloon and near Sai Ying Pun in dry and wet seasons at marine
ecological sensitive receivers (assessment points refer to Table 3-5 in Section 3 and location refer to R2, R3, R4 and R5 in Figure 3.2) show that the predicted
elevation of SS concentration during both dry and wet seasons at Green Island,
will be less than 0.1 mgL-1
at depth average, top layer and bottom layer of the water column (Figure C3.1a
to C3.1c in Appendix C1), and the
net sedimentation rate is less than 0.001 kg m-2 per day (Figure C3.3e in Appendix C1). These results are much lower than the SS elevation
limit and sedimentation rate set in Section 3.2.8 of 10mgL-1 and 0.1 kg m-2
per day respectively. Thus,
dredging works near
The extent of marine sediment contamination along the alignment of the proposed submarine main was reported in Section 6. The results indicated that high level of contamination in terms of arsenic (As), copper (Cu), lead (Pb), mercury (Hg), silver (Ag) and polyaromatic hydrocarbons (PAHs) and polychlorinated biphenols (PCBs) were found essentially at a number of vibrocore samples. However, the elutriate tests results reported in Section 3 estimated that the release of the above contaminants to the water column at the point of dredging fall within the UK Water Quality Standard and no exceedances of standard was predicted. Therefore, long-term off-site marine ecological impact due to release of marine sediment with high contamination is negligible.
The physical disturbances to the surrounding waters by the construction activities include the increase in human activities, inappropriate storage or dumping of construction materials, increase in marine traffic and change in water flow regime may have negligible impact on the marine wildlife when good site practices and control of marine traffic speed are implemented during the construction phase.
The significance of impacts arising from this proposed works on the marine ecological resources mentioned above are evaluated using the criteria set in the EIAO-TM Annex 8 Table 1 and presented in Table 4-7 below.
Table 4‑7 Evaluation of the Significance of Ecological Impact
Criteria |
|
|
Habitat
Quality |
The
sub-tidal zone and artificial seawalls at inter-tidal zone being affected are
of low ecological values. |
No
significant impact is anticipated to the moderate ecological valued natural
rocky shores and soft bottom seabed. |
Species |
The
species recorded in the dredging area are common and pollution tolerant. |
No
rare species were recorded within the study area, and coral communities of
moderate conservation interest are not expected to be impacted by the
construction at approximate 2.8km away from |
Size/Abundance |
Approx.
9.2ha of low ecological value benthic assemblages will be loss, and approx.
51.2ha of works area may be temporary disturbed by construction activities.
Around 2m² of artificial seawall at both landing points will also be loss
permanently. The species abundance of the soft benthos and inter-tidal
fouling organisms at vertical seawall is low. |
No
direct impact is anticipated on the moderate abundance inter-tidal and
sub-tidal region at |
Duration |
The
lost of approx. 9.2ha of seabed and 2m² of artificial wall is permanent. The
temporary affected area will last for approximate 1 year. The change in water
quality in the water column around the dredging area is temporary and within
environmental acceptable levels. Benthic communities within the dredging area
are expected to recolonize after the backfilling of the seabed. |
Change
in water quality around the soft coral assemblages are expected to be
temporary and short term. |
Reversibility |
Impacts
to the benthic fauna within the working area will be long term. The seabed
will be backfilled with armour rock and by natural sedimentation. Benthic
fauna is expected to recolonize to the seabed after construction. |
Soft
coral assemblages are reversible if the stress is short term and in low
magnitude. The change in water quality in the vicinity is anticipated to be
in very low magnitude. |
Magnitude |
The
impact to the habitats identified will be of low magnitude. |
The
impact to the habitats identified will be of very low magnitude. |
Summary |
The
impacts to the low ecological valued marine benthos and artificial habitats
within the dredging and works area are predicted to be of low significant. |
The
impacts to the coral communities and coastal communities at intertidal zone
are predicted to be of negligible significant due to no works will be
constructed in the vicinity, remote (2.8km) from the works boundary and the
prediction of low elevation of SS concentration at the region. |
In summary, the impacts of
permanent habitat loss and temporary disturbances to marine ecological
resources will be of low to negligible significance, due to no rare species
recorded within the affected area and in vicinity and the low ecological value
of the marine benthos and the re-creatable artificial structures along the
4.8 Mitigation of Adverse Environmental Impact
The proposed dredging works will be confined in the works area within 25m at either side of the proposed alignment and the use of closed type grab dredger will reduce sediment and contaminants runoff to the water column. The trench will be backfilled with armour rock or decomposed granite and allow natural sedimentation on the substrates to provide protection of the pipeline from damage by ship anchors. Benthic fauna is expected to be recolonized to the seabed after construction. Other mitigation measures suggested in the water quality impacts assessment such as the use of one grab dredger only with a maximum production rate of 4,000m3 per day for dredging, deployment of frame type silt curtain to fully enclose the grab while dredging works are in progress, deployment of silt screen at the sea water intake at Kowloon South Salt Water Pumping Station while dredging works are in progress. and good site practices to avoid silt runoff from construction works associated with the construction of the submarine watermain could also further reduce the impact on the marine ecology. No other specific mitigation measures for marine ecology are considered necessary, as no adverse impact was identified.
4.9 Evaluation of Residual Impacts
There will be loss of approximately 4m² of artificial seawall and change in approximately 9.2ha of seabed substrates along the alignment. Benthic fauna is expected to be recolonized to the seabed after construction. No adverse residual impact due to the construction and operation of the submarine watermain is expected after the implementation of the proposed mitigation measures.
4.10 Environmental Monitoring and Audit
The implementation of the ecological mitigation measures stated in Section 4.8 and water quality mitigation measures in Section 3 should be checked as part of the environmental monitoring and audit procedures during the construction period as presented in the separate Environmental Monitoring and Audit Manual. No other marine ecology-specific measures are considered necessary.
4.11 Conclusions and Recommendations
A review of the existing information showed that the
marine ecological resources within the dredging area consist of pollution
tolerant soft benthos in low diversity and typical to benthos recorded in poor
quality sediments. Inter-tidal species along
In conclusion, the construction of the proposed submarine
watermain along
A noise impact assessment has
been undertaken to define the nature and scale of the potential noise impact to
sensitive receivers associated with the proposed submarine watermain. The
construction noise levels associated were predicted based on the plants to be
used and the phasing of the construction programme was also considered.
The submarine
watermain component of the Project across Victoria Harbour is a Designated
Project under Schedule 2, Part 1I(E3) of the Environmental Impact Assessment
Ordinance (EIAO) (Cap. 499) and an Environmental Permit (EP) issued under the
EIAO is required for the construction and operation of the designated project.
In accordance with the EIA Study
Brief No. ESB-132/2005, construction noise impact arising from the dredging,
laying of pipe and backfilling works for the construction of the submarine
watermain were assessed.
No noise impact is envisaged to
arise from the operation phase of the proposed submarine watermain.
5.2 Environmental Legislation, Standards, Guidelines and Criteria
Noise impacts were assessed in accordance with the criteria and methodology given in the Technical Memoranda (TMs) issued under the Noise Control Ordinance (NCO) and the Technical Memorandum on Environmental Impact Assessment Process (EIAO-TM).
The Noise Control Ordinance provides the statutory framework for noise control. Assessment procedures and standards are set out in the following Technical Memoranda:
· Technical Memorandum on Noise from Construction Work other than Percussive Piling (GW-TM);
· Technical Memorandum on Noise from Construction Work in Designated Areas (DA-TM); and
· Technical Memorandum on Environmental Impact Assessment Process (EIAO-TM) Annexes 5 and 13.
Noise impacts arise from construction works other than percussive piling using items of powered mechanical equipment (PME) during normal working hours (i.e. 0700 to 1900 hours on any day not being a Sunday or public holiday) to the noise sensitive buildings are assessed with reference to the NCO. The recommended noise standards in EIAO-TM are presented in Table 5-1 below.
Table 5‑1 EIAO-TM Daytime Construction Noise Standards
(0700 to 1900 hours on any day not being a Sunday or public holiday) (Leq.30
min dB(A))
Uses |
Acceptable Noise Standards |
Domestic Premises Educational institutions (normal
periods) Educational institutions (during
examination periods) |
75 70* 65* |
Note: *For reference only, not used in this study.
The NCO also provides statutory controls on general construction works during the restricted hours (i.e. 1900-0700 hours Monday to Saturday and at any time on Sundays and public holidays). The use of items of powered mechanical equipment (PME) for carrying out construction works during the restricted hours would require a Construction Noise Permit (CNP). A CNP may be granted provided that the Acceptable Noise Level (ANL) for the noise sensitive receivers (NSRs) can be complied with. The Corrected Noise Levels CNLs (after accounting for factors such as barrier effects and reflections) associated with the proposed operations of items of PME are then compared to ANL. A CNP will be issued if the CNL is equal to or less than the ANL. The Noise Control Authority is guided by the GW-TM when assessing such an application.
The steps to determine the ANL for the sensitive receivers include determining the Basic Noise Level (BNL) and make correction according to the procedures stipulated in the GW-TM. The corresponding Basic Noise Levels (BNLs) for evening and night time periods are given in Table 5-2.
Table 5‑2 Basic
Noise Levels (BNL, Leq.30 min dB(A))
Time
Period |
Area Sensitivity Rating |
||
A |
B |
C |
|
All days during the evening (1900 – 2300 hours) and
general holidays (including Sundays) during the day and evening (0700 – 2300)
hours |
60 |
65 |
70 |
All days during the night-time (2300 – 0700 hours) |
45 |
50 |
55 |
5.2.2 Area Sensitivity Ratings
The Area Sensitivity Ratings assumed in this EIA Report
(in Section 5.4 below) are for
indicative assessment only. Despite any description or assessment made in this
EIA Report on construction noise aspects, there is no guarantee that a
Construction Noise Permit (CNP) will be issued for the project construction.
The Noise Control Authority will consider a well-justified CNP application,
once filed, for construction works within restricted hours as guided by the
relevant Technical Memoranda issued under the Noise Control Ordinance. The
Noise Control Authority will take into account of contemporary conditions/
situations of adjoining land uses and any previous complaints against construction
activities at the site before making his decision in granting a CNP. Nothing in
this EIA Report shall bind the Noise Control Authority in making his
decision. If a CNP is to be issued, the
Noise Control Authority shall include in it any condition he thinks fit.
Failure to comply with any such conditions will lead to cancellation of the CNP
and prosecution action under the NCO.
In
addition to the general controls on the use of items of PME during the
restricted hours, the Noise Control Authority has implemented more stringent
control mechanisms via the DA-TM. The
DA-TM regulates the use of five types of Specified Powered Mechanical Equipment
(SPME) and three types of Prescribed Construction Work (PCW), which are non-PME
activities, in primarily densely populated neighbourhoods called Designated
Areas (DAs). The SPME and PCW are:
Specified Powered Mechanical Equipment:
· Hand-held breaker
· Bulldozer
· Concrete lorry mixer
· Dump truck
· Hand-held vibratory poker
Prescribed Construction Work:
· Erection or dismantling of formwork or scaffolding
· Loading, unloading or handling or rubble, wooden boards, steel bars, wood or scaffolding material
· Hammering
In
an attempt to provide environmental additional protection carrying out of PCW
is generally banned inside a DA. As for the use of SPME, it would be necessary
to comply with DA-TM noise level requirements that are 15 dB(A) more stringent
than those listed in the GW-TM before a CNP would be issued.
It is worth noticing that the above SPME and PCW suggested will not be used during the construction of this Project (refer to the plant inventory listed in Table 5-4). Therefore, the above mentioned regulation in DA-TM would only serve as a reference only.
Representative
Noise Sensitive Receivers (NSRs) within 300m of the Project limit have been
identified according to the criteria set out in the EIAO-TM and through site
inspections and a review of land use plans. However, no NSR within 300m was
found in
The
landfall site at Sai Ying Pun is situated at the seafront area east of the
Western Wholesale Food Market and next to the entrance of Western Harbour
Crossing. Figures 5.1 and 5.3
indicate the proposed works area for the landfall site at Sai Ying Pun with the
extent of seawall construction works. The works in this area include pipe
pulling by winch and seawall reinstatement. The nearest residential buildings
along
The
landfall site at
The Separation Distances (m) between the notional noise source and the NSRs are determined in accordance with the TM on Noise from Construction Work other than Percussive Piling. All items of PME are assumed to be located at a single notional source position. Since the items of PME will be close to the site of seawall reinstatement, the access roads are not considered when determining the geographical centre of the construction site. The Separation Distances established are shown in the Table 5-3.
Table 5‑3 Representative Noise Sensitive Receivers
NSR ID |
Description |
Type of Use |
Separation Distance (m) |
|
|||
WF1 |
The Waterfront |
Residential |
750 |
WF2 |
|
|
790 |
WF3a |
|
|
830 |
KS2 |
|
|
760 |
KS3b |
The Arch |
|
810 |
KS4 |
The Harbourside |
|
670 |
KS6 |
|
|
580 |
Sai Ying Pun |
|||
FSB |
|
Residential |
360 |
VC |
|
|
320 |
CLM |
|
|
310 |
KY2 |
|
|
400 |
KY3a |
|
|
245 |
KY3b |
|
|
225 |
RWM |
|
|
215 |
CG1 |
|
|
220 |
CG2 |
|
|
230 |
CG3 |
|
|
245 |
GB |
|
|
270 |
Note: Noise Sensitive Receivers are representative and will be used in prediction calculations.
A methodology for assessing construction noise other than percussive piling has followed the guidelines set out in the Technical Memorandum on Noise from Construction Work other than Percussive Piling (GW-TM). The methodology is as follows:
· identify the likely type, sequence and duration of principal noisy construction activities required for the implementation of the proposed project;
· identify a list of plant inventory likely to be required for each construction activity;
· calculate the maximum total sound power level (SWL) for each construction activity using the plant list and SWL data given for each plant in the technical memorandum.
· representative NSRs as defined by the EIAO-TM have been identified, based on existing and committed land uses in the study area that may be affected by the worksite.
· calculate the distance attenuation and barrier corrections to NSRs from worksite notional noise source point;
· predict construction noise levels at NSRs in the absence of any mitigation measures; and
· include the +3 dB(A) facade correction to account for the facade effect at each NSR.
If the predicted noise levels at the NSRs exceed the noise assessment criteria, mitigation measures must be considered. A re-evaluation of the total SWL for each construction activity will be made assuming the use of practical mitigation measure such as quiet equipment and movable noise barriers. If the predicted noise levels still exceed the noise criteria, further mitigation measures such as reduction in noisy plant working simultaneously would be considered.
5.4.2 Area Sensitive Ratings (ASRs)
Determination of the Area Sensitivity Ratings for the NSRs
in this study has been made with reference to relevant TMs.
Sai Ying Pun
The NSRs are residential developments located in urban area of Sai Ying Pun with an annual average daily traffic flow of 43,490 and 40,460 running through the nearby Connaught Road West and Western Harbour Crossing respectively (Source: Station no. 1006 and 1026, Annual Traffic Census 2005 published by Transport Department). As the NSRs are located in urban area and are directly affected by this influencing factor, an Area Sensitivity Rating (ASR) of “C” is applied according to the GW-TM.
In West Kowloon, the southwest facade of closest NSRs (KS4 & KS6) facing the landfall site is directly influenced by the traffic noise from the West Kowloon Highway with an annual average daily traffic flow of more than 38,410 (Source: Station no. 3502, Annual Traffic Census 2005 published by Transport Department). As the NSRs are residential developments located in urban area with high-rise buildings and are directly affected by this influencing factor, an Area Sensitivity Rating (ASR) of “C” is applied according to the GW-TM.
Accordingly, the ANL would be 70 dB(A) in the evening and
55 dB(A) at night as detailed in Table
5.2 for both Sai Ying Pun and
5.4.3 Assessment for the Project
Using the
methodology outlined in the TM, notional noise sources for different
construction areas were assumed. All the items of powered mechanical equipment
(PME) listed in Table 5-4 and Table 5-5 for Sai Ying Pun and
Sound power levels
(SWLs) of PME items are adopted from Table 3 of the GW-TM (No percussive
piling is required for this Project).
When no SWL is suggested in the TM, reference was made with BS 5228: Part 1:1997 Noise Control on
Construction and Open Sites. Details of the items of PME and the total SWLs
for various construction activities are listed in Table 5-4 and Table 5-5.
The major tasks in the laying of the
watermain are
· Trench dredging
· Laying of submarine watermain
· Backfilling
From the context of the programming of
construction works, it is suggested that night-time dredging work could be
required. The necessity of night-time dredging will depend on the progress of
the project. For any construction works planned during restricted hours, it
will be the responsibility of the Contractor to ensure compliance with the NCO
and the relevant TMs. In such case, the Contractor will be required to submit
CNP application to the Noise Control Authority and abide any condition stated
in the CNP if it can be issued. An indicative assessment is undertaken at
representative NSRs to identify any potential adverse noise impacts.
The construction programme in Appendix B sets out the time frame for the various tasks in the construction phase. It can be seen that the three major tasks mentioned will be performed consecutively (i.e. they are not concurrent). This important fact was noted in the assessment when the cumulative construction noise impact is considered.
A +3 dB(A)
facade correction would be required to account for the facade effect at each
NSR according to the GW-TM. It would be applicable to all PME items required
for the construction activities in this Project.
5.5 Identification, Prediction and Evaluation of Environmental Impacts
From the tentative project programme in Appendix B, the three major tasks in the construction of the proposed submarine watermain are expected to be carried out consecutively while other works including pipe preparation and seawall reinstatement will be concurrent with the other activities as shown.
Trench
dredging will be carried out along the proposed alignment of the submarine
watermain while the temporary platform is located at the seafront of
Table 5‑4 Noise Emission Inventory (Sai Ying Pun)
Powered
Mechanical Equipment |
CNP Ref |
No. of
Plants |
SWL/Unit,
dB(A) |
SWL,
dB(A) |
|
Trench Dredging |
Grab dredgers+ |
CNP 063 |
2 |
112 |
115 |
Hopper barges # |
- |
2 |
- |
- |
|
Tug boats |
CNP 221 |
2 |
110 |
113 |
|
Crane, barge mounted |
CNP 048 |
2 |
112 |
115 |
|
|
|
|
|
Sub-SWL |
119 |
|
|
|
|
|
|
Pipe laying |
Generator |
CNP 102 |
1 |
100 |
100 |
|
Winch (pneumatic) |
CNP 261 |
1 |
110 |
110 |
|
Water pump (electric) |
CNP 281 |
2 |
88 |
91 |
|
|
|
|
Sub-SWL |
110 |
|
|
|
|
|
|
Backfilling |
Crane, barge mounted |
CNP 048 |
2 |
112 |
115 |
|
Hopper barges # |
- |
2 |
- |
- |
|
Tug boats |
CNP 221 |
2 |
110 |
113 |
|
|
|
|
Sub-SWL |
117 |
|
|
|
|
|
|
Seawall reinstatement |
Crane, mobile/barge mounted |
CNP 048 |
1 |
112 |
112 |
|
Truck / lorry |
CNP 141 |
2 |
112 |
115 |
|
Piling machine |
CNP 163 |
1 |
90 |
90 |
|
|
|
|
Sub-SWL |
117 |
|
|
|
|
|
|
Note: + One grab dredger will be used
for dredging; while the other grab dredger will be used for trimming. Trimming
will be carried out at the seawall at
# No noise
would be emitted from hopper barges.
* The marine
piling vessel is assumed to be an oscillator piling plant.
Table 5‑5 Noise Emission Inventory (
Activity |
Powered
Mechanical Equipment |
CNP Ref |
No. of
Plants |
SWL/Unit,
dB(A) |
SWL,
dB(A) |
Trench |
Grab dredgers+ |
CNP 063 |
2 |
112 |
115 |
Dredging |
Hopper barges # |
- |
2 |
- |
- |
|
Tug boats |
CNP 221 |
2 |
110 |
113 |
|
Crane, barge mounted |
CNP 048 |
2 |
112 |
115 |
|
|
|
|
Sub-SWL |
119 |
|
|
|
|
|
|
Setting up of |
Marine piling vessel |
CNP 165* |
2 |
115 |
118 |
Temporary |
Hopper barges # |
- |
4 |
- |
- |
Platform |
Tug boats |
CNP 221 |
2 |
110 |
113 |
|
Crane, barge mounted |
CNP 048 |
2 |
112 |
115 |
|
|
|
|
Sub-SWL |
121 |
|
|
|
|
|
|
Pipe preparation |
Truck/ lorry |
CNP 141 |
2 |
112 |
115 |
Crane, mobile/barge mounted (diesel) |
CNP 048 |
2 |
112 |
115 |
|
|
|
|
|
Sub-SWL |
118 |
|
|
|
|
|
|
Pipe laying |
Crane, mobile |
CNP 048 |
1 |
112 |
112 |
|
Generator |
CNP 102 |
1 |
100 |
100 |
|
|
|
|
Sub-SWL |
112 |
|
|
|
|
|
|
Backfilling |
Crane, barge mounted |
CNP 048 |
2 |
112 |
115 |
|
Hopper barges # |
- |
2 |
- |
- |
|
Tug boats |
CNP 221 |
2 |
110 |
113 |
|
|
|
|
Sub-SWL |
117 |
|
|
|
|
|
|
Seawall reinstatement |
Crane, mobile/barge mounted |
CNP 048 |
1 |
112 |
112 |
|
Truck / lorry |
CNP 141 |
2 |
112 |
115 |
|
Piling machine |
CNP 163 |
1 |
90 |
90 |
|
|
|
|
Sub-SWL |
117 |
|
|
|
|
|
|
Note: +
One grab dredger will be used for dredging; while the other grab dredger will
be used for trimming. Trimming will be carried out at the seawall at
# No noise would be emitted from hopper barges.
* The marine piling vessel is assumed to be an
oscillator piling plant.
Representative NSRs are chosen for
assessment in both Sai Ying Pun and
Table 5‑6 Selected
NSRs for Noise Assessment
|
Sai Ying Pun |
|
Representative Noise
Sensitive Receivers (NSRs) |
RWM |
KS6 |
Separation distance
of Representative NSRs to landfall sites |
215m |
580m |
Detailed calculations are
provided in Table E2 and E5 of Appendix
E. Dredging work in the
The noise impact from the possible night-time dredging is assessed. The construction noise level associated with the dredging is calculated and shown in Table E3 and E7 of Appendix E. Note that the noise levels assessed during Restricted Hours only include the proposed trench dredging work and are for indicative purpose only. It should be understood that despite any description or assessment made in this EIA Report on construction noise aspects, there is no guarantee that a Construction Noise Permit (CNP) will be granted for the proposed night-time works. Section 5.3 and 5.4 should be referred to for information on the proposed night-time work and relevant regulations. The predicted noise levels are summarized in Tables 5-7 and 5-8.
Table 5‑7 Summary
of Unmitigated Construction Noise Levels during
Representative NSRs |
Predicted Unmitigated
Construction Noise Levels during |
Noise Criteria (dB(A)) |
RWM (Sai Ying Pun) |
59 – 68 |
75 |
KS6 ( |
52 – 64 |
75 |
Table 5‑8 Summary of Unmitigated Construction Noise Levels from dredging during Restricted Hours
Representative NSRs |
Predicted Maximum Construction Noise Levels (dB(A)) |
“Noise
Criteria - All days during the evening (1900 to 2300 hours), and general
holidays (including Sundays) during the daytime and evening (0700 to 2300
hours)”. (dB(A)) |
Noise Criteria – All days during Night time (2300 to 0700 hours) (dB(A)) |
RWM (Sai Ying Pun) |
68 |
70 |
55 |
KS6 ( |
59 |
70 |
55 |
5.5.3 Evaluation of Noise Impact
During normal daytime working
hours, noise generated from the
construction works fully comply with the Noise Criteria set in the TM. Without
mitigation, it can be concluded that there will not be any adverse noise impact
from the marine construction work during daytime, the evening (1900 to 2300
hours) of all normal days and of general holidays (including Sundays).
The calculation is conservative in view of the close separation
distance to the NSRs assumed for dredging work. Most of the dredging work will
be carried out within the harbour and will be far from the landfall sites at
most of the time.
However, the predicted noise level exceeds the Noise Criteria at night
time for dredging work carried out close to the landfall sites. If the
night-time work (2300 to 0700 hours) is carried out, there will possibly be
certain level of noise nuisance at a short period of time.
5.6 Mitigation of Adverse Environmental Impacts
As shown in Table
5-7, the Noise Criteria at Daytime can be complied with at both Sai Ying
Pun and
The predicted noise level exceeds the Noise Criteria at night time for both Noise Sensitive Receivers KS6 and RWM but the Noise Criteria at evening time was complied with. It is therefore recommended that the dredging work should not be carried out as far as possible during night-time from the noise perspective. However, it is understood that due to the work programme and other constraints (e.g. the disturbance to the marine traffic during daytime), night-time dredging might be necessary. In case where night-time dredging is required and a Construction Noise Permit (CNP) can be granted, the noise at night time should be mitigated. The Contractor shall take into consideration the below recommendations prior to application of CNP and commencement of night-time work.
5.6.1 Work Schedule Rearrangement
Concurrent works should be such that necessary noisy works should be carried out at different time slots or spread around the construction sites. This will help to reduce the cumulative noise effect produced in the construction process.
If night-time (2300 to 0700 hours) dredging is required, the work shall be scheduled to carry out at a distance as far as possible to the NSRs. It is determined that the dredging work should be carried out at a location 750m away from the Sai Ying Pun landfall site and 450m from the West Kowloon landfall site along the trench as shown in the Figure 5.5. Under such condition, the separation distances to the NSRs (RWM & KS6) are increased to more than 900m. The night-time criteria of GW-TM can be complied because of the sufficient distance attenuation in noise level. The calculation is shown in the Table E4 and E8 in Appendix E while the results are summarised in the Table 5-9 below. It is noteworthy that the resulting noise levels should be smaller during the dredging since the separation distance would be larger than 900m in the dredging zone. The contractor will be required to adhere to the restricted locations of dredging work at night-time to comply with relevant noise standard.
Table 5‑9 Summary of Mitigated Construction Noise Levels from dredging during Night time (2300 to 0700 hours)
Representative NSRs |
Predicted Maximum Construction Noise Levels (dB(A)) |
Noise Criteria – Night time (2300 to 0700 hours) (dB(A)) |
RWM (Sai Ying Pun) |
55 |
55 |
KS6 ( |
55 |
55 |
The use of Quality PME recognized by the Noise Control Authority for the purpose of CNP application can effectively reduce the noise generated from the construction plants. Quality PME are construction plants and equipments that are notably quieter, more environmental friendly and efficiently. The noise level reduction ranges from 5 – 10 dB(A) depending on the type of equipment used. The Contractor shall note the required procedures involved in application of the QPME.
Mobile or movable noise barriers to be erected near to the construction plants would reduce the noise levels for commonly 5 – 10 dB(A) depending on the types of items of PME and materials of the barriers. It is recommended that the Contractor shall screen noisy works and noise from stationary items of PME whenever practicable.
Good site practice and noise management can significantly reduce the impact of construction site activities on nearby NSRs. The following package of measures should be followed during construction:
· only well-maintained plant should be operated on-site and plant should be serviced regularly during the construction works;
· machines and plant that may be in intermittent use should be shut down between work periods or should be throttled down to a minimum;
· plant known to emit noise strongly in one direction, should, where possible, be orientated to direct noise away from the NSRs;
· mobile plant should be sited as far away from NSRs as possible; and
· material stockpiles and other structures should be effectively utilised, where practicable, to screen noise from on-site construction activities.
5.7 Evaluation of Residual Impacts
No residual impacts are predicted for the construction or operation of the Project.
5.8 Environmental Monitoring and Audit
Full compliance with the noise criteria will be achieved at all NSRs with the implementation of mitigation measures. Environmental monitoring and audit is recommended to ensure that the noise levels do not exceed the criteria during the construction phase as discussed in the EM&A Manual.
5.9 Conclusions and Recommendations
Construction noise impact to the NSRs has been assessed. It is predicted that major construction activities including dredging, laying of pipe and backfilling works would comply with the noise criteria stipulated in the EIAO-TM and NCO during daytime and evening (1900 to 2300 hours).
If night-time works (2300 to 0700 hours) are carried out, the location of dredging works should be restricted while there should be no work within the prohibited zones. With this measure being taken place, the night-time criteria during the dredging period can be complied with.
Work schedule rearrangement, quiet plants and mobile noise barriers are recommended to further suppress noise emissions from construction activities. Good site practices will be necessary to further reduce any potential impact to the noise sensitive receivers.
The submarine
watermain component of the Project across Victoria Harbour is a Designated
Project under Schedule 2, Part 1I(E3) of the Environmental Impact Assessment
Ordinance (EIAO) (Cap. 499) and an Environmental Permit (EP) issued under the
EIAO is required for the construction and operation of the designated project.
In accordance with the EIA Study
Brief No. ESB-132/2005, construction and operation waste management impact
arising from the dredging, laying of pipe and backfilling works for the
construction of the submarine watermain were assessed.
This section identifies the types of solid wastes that are likely to be generated during the construction of the submarine watermain and evaluates the potential environmental impacts that may result from these wastes. The major solid waste would be dredged marine sediment from the construction of the proposed submarine watermain. Mitigation measures and good site practices, including waste handling, storage and disposal, are recommended with reference to the applicable waste legislation and guidelines.
6.2 Environmental Legislation, Standards, Guidelines and Criteria
The criteria and
guidelines for assessing waste management implications are outlined in Annex 7
and Annex 15 of the Technical Memorandum on Environmental Impact Assessment
Process (EIAO-TM), respectively.
The following
legislation relates to the handling, treatment and disposal of wastes in the
Hong Kong SAR and has been used in assessing potential impacts:
·
Waste Disposal
Ordinance (Cap. 354)
·
Waste Disposal
(Chemical Waste) (General) Regulation (Cap. 354)
·
Public Health and
Municipal Services Ordinance (Cap. 132) - Public Cleansing and Prevention of
Nuisances Regulation
·
Land
(Miscellaneous Provisions) Ordinance (Cap. 28)
·
Dumping at Sea
Ordinance (Cap. 466)
Under the WDO, the Chemical Waste (General) Regulation 1992 provides regulations for chemical waste control, and administers the possession, storage, collection, transport and disposal of chemical wastes. The Environmental Protection Department (EPD) has also issued a ‘guideline’ document, the Code of Practice on the Packaging, Labelling and Storage of Chemical Wastes (1992), which details how the Contractor should comply with the regulations on chemical wastes.
The Public Cleansing and Prevention of Nuisances Regulation provides control on illegal tipping of wastes on unauthorised (unlicensed) sites.
6.2.3 Construction and Demolition (C&D) Materials
The current policy related to the dumping of C&D material is documented in the Works Branch Technical Circular No. 2/93, ‘Public Dumps’. Construction and demolition materials that are wholly inert, namely public fill, should not be disposed of to landfill, but taken to public filling areas, which usually form part of reclamation schemes. The Land (Miscellaneous Provisions) Ordinance requires that dumping licences be obtained by individuals or companies who deliver public fill to public filling areas. The Civil Engineering & Development Department (CEDD) issues the licences under delegated powers from the Director of Lands.
Under the Waste Disposal (Charges for Disposal of Construction Waste) Regulation, enacted in January 2006, construction waste delivered to a landfill for disposal must not contain more than 50% by weight of inert material. Construction waste delivered to a sorting facility for disposal must contain more than 50% by weight of inert material, and construction waste delivered to a public fill reception facility for disposal must consist entirely of inert material.
Measures have been
introduced under Environment, Transport and Works Bureau (ETWB) TCW No.
33/2002, “Management of Construction and Demolition Material Including Rock” to
enhance the management of construction and demolition material, and to minimize
its generation at source. The
enhancement measures include: (i) drawing up a Construction and Demolition
Material Management Plan (C&DMMP) at the feasibility study or preliminary
design stage to minimize C&D material generation and encourage proper
management of such material; and (ii) providing the contractor with information
from the C&DMMP in order to facilitate him in the preparation of the Waste
Management Plan (WMP) and to minimize C&D material generation during
construction. Projects generating
C&D material less than 50,000m3 or importing fill material less
than 50,000m3 are exempt from the C&DMMP. The new ETWB TCW No.
19/2005 “Environmental Management on Construction Sites” includes procedures on
waste management requiring contractors to reduce the C&D material to be
disposed of during the course of construction.
A Waste Management Plan should be submitted by the contractor prior to
the commencement of construction works.
ETWB TCW No.
34/2002, “Management of Dredged/Excavated Sediment” sets out the procedures for
seeking approval to dredge/excavate sediment and the management framework for
marine disposal of such sediment.
Dredged marine sediment arising from the Project will be managed in
accordance with the requirements of ETWB TCW No. 34/2002. The sediment quality criteria for the
classification of sediment are presented in Table 6-5.
In accordance with the Dumping at Sea Ordinance, application for dumping permits from EPD are required for marine disposal of dredged materials.
The criteria for assessing waste management implications
are outlined in Annex 7 of the EIAO-TM.
The methods for assessing potential waste management impacts during the
construction phase follow those presented in Annex 15 of the EIAO-TM and
include the following:
·
Estimation of the types and quantities of the wastes
generated.
·
Assessment of potential impacts from the management of
solid waste with respect to potential hazards, air and odour emissions, noise,
wastewater discharges and transport.
·
Assessment of impacts on the capacity of waste
collection, transfer and disposal facilities.
6.3.2 Marine Site Investigation
The chemical characteristics of the dredged material within the dredged
trench area as shown in Figure 2.3
include contaminated mud as indicated in the laboratory test results in the
following reports
·
Agreement No. GEO 01/2000, Environmental
Chemical & Biological Testing for the New Sediment Classification Framework
- Maintenance Dredging for Central Fairway Phases 1, 2 & 3 - Sediment
Quality Report (Mouchel Asia Ltd, March 2002) - Phase I (West Area) - sampling
location points a18 to g19 inclusive on which Tier II & III tests (as per
ETWBTC (W) No. 34/2002) were undertaken; and
·
CED Memo Ref. (35) in TS DF/NFYO/08 Pt.3 dated
In this respect and with reference to ETWB TCW No. 34/2002, the marine
investigations consist of vibrocore sampling on a 100m by 100m grid spacing
with 100mm subsamples taken at seabed, 0.9m down, 1.9m down, 2.9m down, 5.9m
down, 8.9m down and 11.9m down. As site investigation works are not permitted
within the designated Fairways due to potential detrimental effects to marine
traffic, the vibrocores are designed to be at an approximately 100m spacing
taking into consideration offsets from areas outside the Fairways.
A total of 15 vibrocore pairs were taken at designated locations along
the submarine watermain alignment to determine the vertical profile of sediment
quality. Coordinates, type and depth of the vibrocores are summarised in Table 6-1. Locations of the vibrocore
sampling points (given an ‘a’ suffix) are presented in Figure 6.2. Immediately adjacent to the ‘a’ vibrocores a second
vibrocore denoted with a ‘b’ suffix was also taken. These vibrocores were used for
logging purposes.
Table 6‑1 Coordinates, Type and Depth of Vibrocores
Vibrocore |
Coordinates |
Material |
Seabed
level |
Length |
|
No. |
Easting |
Northing |
Type |
mPD |
Recovered
(m) |
VC1a/b |
832652 |
816956 |
Marine mud |
-9.3 |
12.0 |
VC2a/b |
833170 |
817533 |
Marine mud |
-12.1 |
11.4 |
VC3a/b |
833349 |
817640 |
Marine mud |
-12.9 |
3.2 |
VC4a/b |
833504 |
817790 |
Marine mud |
-11.9 |
12.0 |
VC5a/b |
833870 |
818135 |
Marine mud |
-8.7 |
12.0 |
VC6a/b |
833420 |
817709 |
Marine mud |
-12.4 |
9.0 |
VC7a/b |
833270 |
817569 |
Marine mud |
-12.5 |
10.4 |
VC8a/b |
832875 |
817045 |
Marine mud |
-11.1 |
12.0 |
VC9a/b |
832557 |
816917 |
Marine mud |
-10.0 |
12.0 |
VC10a/b |
832770 |
816999 |
Marine mud |
-10.9 |
12.0 |
VC11a/b |
832755 |
817329 |
Marine mud |
-12.3 |
12.0 |
VC12a/b |
833148 |
817065 |
Marine mud |
-13.0 |
12.0 |
VC13a/b |
833569 |
817850 |
Marine mud |
-11.0 |
7.8 |
VC14a/b |
833935 |
818214 |
Marine mud |
-7.2 |
12.0 |
VC15a/b |
833642 |
817911 |
Marine mud |
-9.3 |
12.0 |
Note:
Vibrocores denoted ’a’ & ’b’ were carried out in close proximity to each
other, where ‘a’ vibrocores were laboratory testing samples while ‘b’
vibrocores were split for logging purposes.
General
Marine site investigation works of the Project were carried out in September 2006. Longitudinal geological profile of marine sediment along the proposed alignment of the submarine watermain is presented in Figure 6.1. Vibrocore records are presented in Appendix F1. The records indicated that the material along the proposed alignment of the submarine watermain consists mainly of marine deposits which are very soft, grey, sandy, silty clay with some gravel size shell fragments.
Laboratory testing of contaminants was included in the marine site investigation works to determine the level of contamination in the marine sediments at the existing seabed. The works included vibrocoring at 15 locations distributed along the proposed submarine watermain alignment as detailed in Table 6-1. Locations of the vibrocore sampling points (given an ‘a’ suffix) are presented in Figure 6.2
Chemical Testing
Sample Arrangement
Tier II chemical
screening was carried out to determine whether the sediment is suitable for
open sea disposal without further testing in accordance with the requirements
of ETWB TCW No. 34/2002. Sediment samples collected for chemical testing are
presented in Table 6-2.
Table 6‑2 Sample Arrangement for Chemical Testing
Vibrocore |
Coordinates |
Sample
Depth |
||
No. |
Easting |
Northing |
From (m) |
To (m) |
VC1a |
832652 |
816956 |
0 |
0.9 |
|
|
|
0.9 |
1.9 |
|
|
|
1.9 |
2.9 |
|
|
|
4.9 |
5.9 |
|
|
|
7.9 |
8.9 |
|
|
|
10.9 |
11.9 |
VC2a |
833170 |
817533 |
0 |
0.9 |
|
|
|
0.9 |
1.9 |
|
|
|
1.9 |
2.9 |
|
|
|
4.9 |
5.9 |
|
|
|
7.9 |
8.9 |
|
|
|
10.9 |
11.3 |
VC3a |
833349 |
817640 |
0 |
0.9 |
|
|
|
0.9 |
1.9 |
|
|
|
1.9 |
2.9 |
VC4a |
833504 |
817790 |
0 |
0.9 |
|
|
|
0.9 |
1.9 |
|
|
|
1.9 |
2.9 |
|
|
|
4.9 |
5.9 |
|
|
|
7.9 |
8.9 |
|
|
|
10.9 |
11.9 |
VC5a |
833870 |
818135 |
0 |
0.9 |
|
|
|
0.9 |
1.9 |
|
|
|
1.9 |
2.9 |
|
|
|
4.9 |
5.9 |
|
|
|
7.9 |
8.9 |
|
|
|
10.9 |
11.9 |
VC6a |
833420 |
817709 |
0 |
0.9 |
|
|
|
0.9 |
1.9 |
|
|
|
1.9 |
2.9 |
|
|
|
4.9 |
5.9 |
|
|
|
7.9 |
8.9 |
VC7a |
833270 |
817569 |
0 |
0.9 |
|
|
|
0.9 |
1.9 |
|
|
|
1.9 |
2.9 |
|
|
|
4.9 |
5.9 |
|
|
|
7.9 |
8.9 |
VC8a |
832875 |
817045 |
0 |
0.9 |
|
|
|
0.9 |
1.9 |
|
|
|
1.9 |
2.9 |
|
|
|
4.9 |
5.9 |
|
|
|
7.9 |
8.9 |
|
|
|
10.9 |
11.9 |
VC9a |
832557 |
816917 |
0 |
0.9 |
|
|
|
0.9 |
1.9 |
|
|
|
1.9 |
2.9 |
|
|
|
4.9 |
5.9 |
|
|
|
7.9 |
8.9 |
|
|
|
10.9 |
11.9 |
VC10a |
832770 |
816999 |
0 |
0.9 |
|
|
|
0.9 |
1.9 |
|
|
|
1.9 |
2.9 |
|
|
|
4.9 |
5.9 |
|
|
|
7.9 |
8.9 |
|
|
|
10.9 |
11.9 |
VC11a |
832755 |
817329 |
0 |
0.9 |
|
|
|
0.9 |
1.9 |
|
|
|
1.9 |
2.9 |
|
|
|
4.9 |
5.9 |
|
|
|
7.9 |
8.9 |
|
|
|
10.9 |
11.9 |
VC12a |
833148 |
817065 |
0 |
0.9 |
|
|
|
0.9 |
1.9 |
|
|
|
1.9 |
2.9 |
|
|
|
4.9 |
5.9 |
|
|
|
7.9 |
8.9 |
|
|
|
10.9 |
11.9 |
VC13a |
833569 |
817850 |
0 |
0.9 |
|
|
|
0.9 |
1.9 |
|
|
|
1.9 |
2.9 |
|
|
|
4.9 |
5.9 |
|
|
|
7.7 |
8.7 |
VC14a |
833935 |
818214 |
0 |
0.9 |
|
|
|
0.9 |
1.9 |
|
|
|
1.9 |
2.9 |
|
|
|
4.9 |
5.9 |
|
|
|
7.9 |
8.9 |
|
|
|
10.9 |
11.9 |
VC15a |
833642 |
817911 |
0 |
0.9 |
|
|
|
0.9 |
1.9 |
|
|
|
1.9 |
2.9 |
|
|
|
4.9 |
5.9 |
|
|
|
7.9 |
8.9 |
|
|
|
10.9 |
11.9 |
Sample Preparation
Continuous samples were
taken vertically from seabed down to the bottom of the proposed dredged layers.
Vibrocoring was terminated in the alluvium layer below the marine mud deposit.
On recovery, each vibrocore was cut into sub-samples. The top level of the
sub-samples were at seabed, 0.9m down, 1.9m down, 2.9m down, 5.9m down, 8.9m
down and 11.9m down or to the termination depth of the vibrocore.
Sections of
vibrocore tube were cut, sealed and capped, labelled, stored in a dark
environment in a cool box below 40C immediately after collection on
site. On transfer from site to
laboratory, samples were kept at below 40C, by regularly replacing
the ice packs.
Determination
Method and Reporting Limits
Chemical Testing was carried out for all vibrocores taken from the 15 locations. Each sub-sample recovered from vibrocoring was tested in the laboratory for the following parameters:
(i)
Metals
concentrations including cadmium (Cd), chromium (Cr), copper (Cu), nickel (Ni),
lead (Pb), zinc (Zn), mercury (Hg), arsenic (As) and silver (Ag).
(ii) Concentrations
of organic compounds including total polychlorinated biphenyls (PCBs), polyaromatic
hydrocarbons (PAHs), and tributyltin (TBT).
Details of the determination methods and reporting limits are provided in Tables 6-3 and 6-4 respectively.
Table 6‑3 Testing Methods and Reporting Limits for Metals and Metalloids Analysis
Code |
Test
Parameter |
Preparation
Method USEPA
Method |
Determination
Method USEPA
Method |
Reporting
limits (mg/kg) |
Cd |
Cadmium |
3050B |
6020A |
0.20 |
Cr |
Chromium |
3050B |
6010C |
8.0 |
Cu |
Copper |
3050B |
6010C |
7.0 |
Ni |
Nickel |
3050B |
6010C |
4.0 |
Pb |
Lead |
3050B |
6010C |
8.0 |
Zn |
Zinc |
3050B |
6010C |
20 |
Hg |
Mercury |
7471A |
7471A |
0.05 |
As |
Arsenic |
3050B |
6020A |
1.0 |
Ag |
Silver |
3050B |
6020A |
0.10 |
Table 6‑4 Testing Methods and Reporting Limits for TBT, PAHs and PCBs Analysis
Parameter |
Method Reference |
Reporting limits |
Total PCB |
USEPA 3550B & 8082 |
3 µg/kg |
PAHs |
USEPA 3550B, 3630C &
8270C |
55 ug/kg for LMW PAHs 170 ug/kg for HMW PAHs |
TBT in interstitial water |
UNEP/IOC/IAEA |
15 ng TBT/L |
Sediment Classification
Dredged sediment destined for marine disposal are classified according to their level of contamination by 13 contaminants as detailed in Table 6-5:
Table 6‑5 Sediment Quality Criteria for the Classification of Sediment
Contaminants |
LCEL |
UCEL |
Heavy Metal (mg/kg dry weight) |
||
Cadmium
(Cd) |
1.5 |
4 |
Chromium
(Cr) |
80 |
160 |
Copper (Cu) |
65 |
110 |
Mercury (Hg) |
0.5 |
1 |
Nickel
(Ni) |
40 |
40 |
Lead
(Pb) |
75 |
110 |
Silver
(Ag) |
1 |
2 |
Zinc
(Zn) |
200 |
270 |
Metalloid (mg/kg dry
weight) |
||
Arsenic |
12 |
42 |
Organic-PAHs (µg/kg dry
weight) |
||
PAHs
(Low Molecular Weight) |
550 |
3160 |
PAHs
(High Molecular Weight) |
1700 |
9600 |
Organic-non-PAHs (µg/kg
dry weight) |
||
Total
PCBs |
23 |
180 |
Organometallics (µg-TBT L-1
in interstitial water) |
||
Tributyltin |
0.15 |
0.15 |
Source: Appendix A of ETWB
TCW No. 34/2002 Management of Dredged / Excavated Sediment
Note: LCEL – Lower Chemical
Exceedance Level
UCEL – Upper Chemical Exceedance Level
Sediments are categorised with reference to the LCEL and UCEL, as follows:
Category L |
Sediment with all contaminant levels not exceeding the LCEL. The material must be dredged, transported and disposed of in a manner that minimises the loss of contaminants either into solution or by suspension. |
Category M |
Sediment with any one or more contaminant levels exceeding the LCEL and none exceeding the UCEL. The material must be dredged and transported with care, and must be effectively isolated from the environment upon final disposal unless appropriate biological tests demonstrate that the material will not adversely affect the marine environment |
Category H |
Sediment with any one or more contaminant levels exceeding the UCEL. The material must be dredged and transported with great care, and must be effectively isolated from the environment upon final disposal. |
In case of Category M and Category H contamination, the final determination of appropriate disposal options, routing and the allocation of a permit to dispose of material at a designated site will be made by EPD and the Marine Fill Committee (MFC) in accordance with the ETWB TCW No. 34/2002.
Biological
Testing
For Category M sediment and Category H sediment with contaminant levels exceeding 10 times the LCEL, Tier III biological screening was carried out to determine the appropriate disposal methods in accordance with the requirements of ETWB TCW No. 34/2002.
Based on the results of the chemical testing and the estimated dredging depth of -8m for formation of the trench, the sediment samples presented in Table 6-6 were subjected to biological testing, with a total of six test samples:
Table 6‑6 Composite Sample Arrangement for Biological Testing
Composite Sample No. |
Vibrocore No. |
Coordinates |
Sample Depth |
|
|
|
Easting |
Northing |
|
2 |
VC7a |
833270 |
817569 |
-0.9 to - 1.9m |
4 |
VC11a |
832755 |
817329 |
-0.9 to - 1.9m |
5 |
VC12a |
833148 |
817065 |
0.0 to - 0.9m |
6 |
VC13a |
833569 |
817850 |
0.0 to - 0.9m |
7 |
VC13a |
833569 |
817850 |
-4.9 to – 5.9m |
8 |
VC14a |
833935 |
818214 |
0.0 to - 0.9m |
The following three toxicity tests (to be considered as one set) were conducted on each sample:
·
a 10‑day
burrowing amphipod toxicity test ; and
·
a 20‑day
burrowing polychaete toxicity test; and
·
a 48‑96
hour larvae (bivalve or echinoderm) toxicity test.
The species used for each type of biological test and the test conditions are listed in Table 6-7 below.
Table 6‑7 Test Species for Biological Testing
Test Types |
Species |
Reference Test Conditions* |
10‑day
burrowing amphipod toxicity test |
Leptocheirus
plumulosus |
USEPA (1994) |
20‑day
burrowing polychaete toxicity test |
Neanthes
arenaceodentata |
PSEP (1995) |
48‑96 hour bivalve larvae toxicity test
|
Crassostrea
gigas |
PSEP (1995) |
Notes:*
(i) U.S.EPA (
(ii) PSEP (
Sediment samples were characterized by the testing laboratory for ancillary testing parameters such as porewater salinity, ammonia, TOC, grain size and moisture content. This provided necessary information on the general characteristics of the sediment.
The test endpoints and decision criteria are summarized in Table 6-8. The sediment was deemed to have failed the biological testing if it failed in any one of the three toxicity tests.
Table 6‑8 Test endpoints and decision criteria for biological testing
Toxicity
test |
Endpoints
measured |
Failure
criteria |
10-day amphipod |
Survival |
Mean survival in test sediment is significantly different (p £ 0.05)1 from mean survival in reference sediment and mean survival in test sediment
< 80% of mean survival in reference sediment. |
20-day polychaete |
Dry Weight2 |
Mean dry weight in test sediment is significantly different (p £ 0.05)1 from mean dry weight in reference sediment and mean dry weight in test sediment
< 90% of mean dry weight in reference sediment. |
48-96 hour bivalve larvae |
Normality Survival3 |
Mean normality survival in test sediment is significantly different
(p £ 0.05)1 from mean normality survival in
reference sediment and mean
normality survival in test sediment < 80% of mean normality survival in
reference sediment. |
1 Statistically significant
differences should be determined using appropriate two-sample comparisons
(e.g., t-tests) at a probability
of p£ 0.05.
2 Dry weight means total
dry weight after deducting dead and missing worms.
3 Normality survival
integrates the normality and survival end points, and measures survival of only
the normal larvae relative to the starting number.
6.4
Baseline Condition of Marine Dredged Sediment
The marine sediment quality analysis results of chemical screening from the marine site investigation works are included as Appendix F2, as compared with the sediment quality criteria for the classification of sediment, are presented in Table 6-9.
The sediment chemical testing results indicate that Category L sediments were found at all depths at vibrocores VC2a and 3a. Category M sediment was found at vibrocores VC4a, 7a, 8a, 11a, 12a, 13a, 14a and 15a in terms of Cd, Cu, Pb, Zn, Hg, As, Ag, low molecular weight PAHs and high molecular weight PAHs. Category H sediment was found at vibrocores VC1a, 4a, 5a, 6a, 8a, 9a, 10a, 11a and 13a. The contamination is high in terms of Cu, Pb, Hg, and Ag. Sediment samples VC4a, 7a, 8a, 11a, 12a, 13a, 14a and 15a were required to proceed to Tier III biological screening.
Table 6‑9 Contaminant Levels of Vibrocore Samples and Their Categories
Vibrocore No. |
From (m) |
To (m) |
Material |
LMW |
HMW |
Total PCBs |
Metals |
TBT |
Overall Category |
Disposal Type |
||||||||
Type |
PAHs |
PAHs |
mg/kg |
ng/L |
||||||||||||||
|
ug/kg |
ug/kg |
ug/kg |
Cd |
Cr |
Cu |
Ni |
Pb |
Zn |
Hg |
As |
Ag |
|
|||||
VC1a |
0 |
0.9 |
Clay |
<55 |
<170 |
<3 |
<0.20 |
21 |
9.8 |
18 |
39 |
61 |
1.2 |
4.5 |
0.10 |
<0.015 |
H |
2 |
VC1a |
0.9 |
1.9 |
Clay |
<55 |
<170 |
<3 |
<0.20 |
24 |
<7.0 |
19 |
18 |
52 |
0.06 |
3.3 |
<0.10 |
<0.015 |
L |
1 |
VC1a |
1.9 |
2.9 |
Clay |
<55 |
<170 |
<3 |
<0.20 |
26 |
7.9 |
20 |
24 |
62 |
0.08 |
4.7 |
<0.10 |
<0.015 |
L |
1 |
VC1a |
4.9 |
5.9 |
Clay |
<55 |
<170 |
<3 |
<0.20 |
27 |
10 |
19 |
30 |
59 |
0.09 |
7.1 |
<0.10 |
<0.015 |
L |
1 |
VC1a |
7.9 |
8.9 |
Clay |
<55 |
<170 |
<3 |
<0.20 |
21 |
7.5 |
16 |
26 |
48 |
0.07 |
5.3 |
<0.10 |
<0.015 |
L |
1 |
VC1a |
10.9 |
11.9 |
Clay |
<55 |
<170 |
<3 |
<0.20 |
27 |
12 |
20 |
37 |
63 |
0.08 |
10 |
<0.10 |
<0.015 |
L |
1 |
VC2a |
0 |
0.9 |
Clay |
<55 |
<170 |
<3 |
<0.20 |
19 |
8.5 |
17 |
20 |
47 |
0.16 |
2.5 |
<0.10 |
<0.015 |
L |
1 |
VC2a |
0.9 |
1.9 |
Clay |
<55 |
<170 |
<3 |
<0.20 |
16 |
<7.0 |
12 |
18 |
39 |
0.06 |
3.7 |
<0.10 |
<0.015 |
L |
1 |
VC2a |
1.9 |
2.9 |
Clay |
<55 |
<170 |
<3 |
<0.20 |
22 |
7.4 |
18 |
20 |
50 |
0.07 |
3.9 |
<0.10 |
<0.015 |
L |
1 |
VC2a |
4.9 |
5.9 |
Clay |
<55 |
<170 |
<3 |
<0.20 |
33 |
13 |
26 |
34 |
68 |
0.06 |
7.8 |
<0.10 |
<0.015 |
L |
1 |
VC2a |
7.9 |
8.9 |
Clay |
<55 |
<170 |
<3 |
<0.20 |
28 |
11 |
17 |
30 |
51 |
0.08 |
11 |
<0.10 |
<0.015 |
L |
1 |
VC2a |
10.9 |
11.3 |
Clay |
<55 |
<170 |
<3 |
<0.20 |
18 |
7.7 |
<4.0 |
48 |
37 |
0.05 |
7.4 |
<0.10 |
<0.015 |
L |
1 |
VC3a |
0 |
0.9 |
Clay |
<55 |
<170 |
<3 |
<0.20 |
17 |
<7.0 |
14 |
17 |
45 |
0.07 |
4.2 |
<0.10 |
<0.015 |
L |
1 |
VC3a |
0.9 |
1.9 |
Clay |
<55 |
<170 |
<3 |
<0.20 |
29 |
10 |
23 |
37 |
78 |
0.13 |
6.2 |
<0.10 |
<0.015 |
L |
1 |
VC3a |
1.9 |
2.9 |
Silt |
<55 |
<170 |
<3 |
<0.20 |
29 |
12 |
25 |
33 |
68 |
0.09 |
10 |
0.11 |
<0.015 |
L |
1 |
VC4a |
0 |
0.9 |
Clay |
<55 |
1000 |
<3 |
0.36 |
26 |
77 |
13 |
130 |
190 |
0.28 |
5.5 |
2.1 |
<0.015 |
H |
2 |
VC4a |
0.9 |
1.9 |
Clay |
<55 |
<170 |
<3 |
<0.20 |
22 |
9.4 |
18 |
22 |
54 |
0.08 |
5.6 |
<0.10 |
<0.015 |
L |
1 |
VC4a |
1.9 |
2.9 |
Clay |
<55 |
<170 |
<3 |
<0.20 |
18 |
<7.0 |
15 |
20 |
44 |
<0.05 |
3.4 |
<0.10 |
<0.015 |
L |
1 |
VC4a |
4.9 |
5.9 |
Clay |
<55 |
<170 |
<3 |
<0.20 |
33 |
13 |
26 |
35 |
75 |
0.07 |
6.8 |
<0.10 |
<0.015 |
L |
1 |
VC4a |
7.9 |
8.9 |
Clay |
<55 |
<170 |
<3 |
<0.20 |
21 |
10 |
15 |
26 |
50 |
0.14 |
7.2 |
<0.10 |
<0.015 |
L |
1 |
VC4a |
10.9 |
11.9 |
Clay |
<55 |
<170 |
<3 |
<0.20 |
<8.0 |
<7.0 |
<4.0 |
62 |
<20 |
0.62 |
5.0 |
<0.10 |
<0.015 |
M |
1D |
VC5a |
0 |
0.9 |
Clay |
<55 |
<170 |
<3 |
0.38 |
45 |
140 |
22 |
38 |
110 |
0.30 |
7.3 |
1.4 |
<0.015 |
H |
2 |
VC5a |
0.9 |
1.9 |
Clay |
<55 |
<170 |
<3 |
<0.20 |
25 |
8.3 |
18 |
46 |
54 |
0.09 |
4.4 |
<0.10 |
<0.015 |
L |
1 |
VC5a |
1.9 |
2.9 |
Clay |
<55 |
<170 |
<3 |
<0.20 |
33 |
9.4 |
23 |
24 |
63 |
0.08 |
5.2 |
0.16 |
<0.015 |
L |
1 |
VC5a |
4.9 |
5.9 |
Clay |
<55 |
<170 |
<3 |
<0.20 |
29 |
9.4 |
20 |
28 |
57 |
0.06 |
5.1 |
<0.10 |
<0.015 |
L |
1 |
VC5a |
7.9 |
8.9 |
Clay |
<55 |
<170 |
<3 |
<0.20 |
21 |
7.6 |
15 |
22 |
49 |
0.08 |
3.7 |
<0.10 |
<0.015 |
L |
1 |
VC5a |
10.9 |
11.9 |
Clay |
<55 |
<170 |
<3 |
<0.20 |
23 |
8.3 |
17 |
31 |
52 |
0.28 |
6.1 |
<0.10 |
<0.015 |
L |
1 |
VC6a |
0 |
0.9 |
Clay |
690 |
<170 |
41 |
0.45 |
23 |
360 |
13 |
69 |
250 |
0.63 |
6.3 |
1.7 |
<0.015 |
H |
2 |
VC6a |
0.9 |
1.9 |
Clay |
<55 |
<170 |
<3 |
<0.20 |
23 |
10 |
19 |
25 |
64 |
0.23 |
2.7 |
<0.10 |
<0.015 |
L |
1 |
VC6a |
1.9 |
2.9 |
Clay |
<55 |
<170 |
<3 |
<0.20 |
26 |
10 |
21 |
30 |
56 |
0.11 |
5.4 |
<0.10 |
<0.015 |
L |
1 |
VC6a |
4.9 |
5.9 |
Clay |
<55 |
<170 |
<3 |
<0.20 |
27 |
12 |
23 |
28 |
56 |
0.10 |
6.4 |
<0.10 |
<0.015 |
L |
1 |
VC6a |
7.9 |
8.9 |
Clay |
<55 |
<170 |
<3 |
<0.20 |
29 |
17 |
22 |
40 |
68 |
0.15 |
7.6 |
0.11 |
<0.015 |
L |
1 |
VC7a |
0 |
0.9 |
Clay |
<55 |
<170 |
<3 |
<0.2 |
16 |
11 |
13 |
38 |
46 |
0.17 |
4.2 |
0.15 |
<0.015 |
L |
1 |
VC7a |
0.9 |
1.9 |
Clay |
780 |
9200 |
<3 |
<0.2 |
20 |
<7.0 |
17 |
17 |
42 |
0.08 |
3.0 |
<0.10 |
<0.015 |
M |
2 |
VC7a |
1.9 |
2.9 |
Clay |
<55 |
<170 |
<3 |
<0.2 |
20 |
<7.0 |
18 |
17 |
49 |
0.09 |
3.9 |
<0.10 |
<0.015 |
L |
1 |
VC7a |
4.9 |
5.9 |
Clay |
<55 |
<170 |
<3 |
<0.20 |
31 |
14 |
23 |
40 |
70 |
0.09 |
9.1 |
<0.10 |
<0.015 |
L |
1 |
VC7a |
7.9 |
8.9 |
Clay |
<55 |
<170 |
<3 |
<0.20 |
12 |
<7.0 |
<4.0 |
10 |
<20 |
<0.05 |
2.3 |
<0.10 |
<0.015 |
L |
1 |
VC8a |
0 |
0.9 |
Silt |
<55 |
<170 |
<3 |
0.69 |
55 |
190 |
22 |
84 |
180 |
0.92 |
7.6 |
3.1 |
<0.015 |
H |
2 |
VC8a |
0.9 |
1.9 |
Silt |
<55 |
<170 |
<3 |
<0.20 |
24 |
9.0 |
19 |
33 |
62 |
0.26 |
3.8 |
<0.10 |
<0.015 |
L |
1 |
VC8a |
1.9 |
2.9 |
Clay |
<55 |
<170 |
<3 |
<0.20 |
22 |
<7.0 |
17 |
19 |
52 |
0.07 |
4.4 |
<0.10 |
<0.015 |
L |
1 |
VC8a |
4.9 |
5.9 |
Clay |
<55 |
<170 |
<3 |
<0.20 |
26 |
12 |
20 |
32 |
60 |
0.10 |
8.5 |
<0.10 |
<0.015 |
L |
1 |
VC8a |
7.9 |
8.9 |
Clay |
<55 |
<170 |
<3 |
<0.20 |
26 |
12 |
19 |
38 |
60 |
0.11 |
9.4 |
<0.10 |
<0.015 |
L |
1 |
VC8a |
10.9 |
11.9 |
Clay |
<55 |
<170 |
<3 |
<0.20 |
24 |
12 |
17 |
38 |
58 |
0.09 |
13 |
<0.10 |
<0.015 |
M |
1D |
VC9a |
0 |
0.9 |
Clay |
130 |
1100 |
5.2 |
0.40 |
26 |
65 |
15 |
100 |
120 |
1.1 |
8.2 |
1.8 |
<0.015 |
H |
2 |
VC9a |
0.9 |
1.9 |
Clay |
<55 |
<170 |
<3 |
<0.20 |
22 |
<7.0 |
19 |
20 |
57 |
0.12 |
3.7 |
<0.10 |
<0.015 |
L |
1 |
VC9a |
1.9 |
2.9 |
Clay |
<55 |
<170 |
18 |
<0.20 |
25 |
7.4 |
19 |
22 |
61 |
0.06 |
4.2 |
<0.10 |
<0.015 |
L |
1 |
VC9a |
4.9 |
5.9 |
Clay |
<55 |
<170 |
<3 |
<0.20 |
28 |
12 |
20 |
30 |
60 |
0.08 |
8.0 |
<0.10 |
<0.015 |
L |
1 |
VC9a |
7.9 |
8.9 |
Clay |
<55 |
<170 |
<3 |
<0.20 |
22 |
7.8 |
17 |
26 |
48 |
0.09 |
5.2 |
<0.10 |
<0.015 |
L |
1 |
VC9a |
10.9 |
11.9 |
Clay |
<55 |
<170 |
<3 |
<0.20 |
23 |
11 |
17 |
30 |
56 |
0.07 |
9.4 |
<0.10 |
<0.015 |
L |
1 |
VC10a |
0 |
0.9 |
Clay |
<55 |
420 |
6.0 |
0.69 |
52 |
170 |
21 |
78 |
190 |
0.99 |
7.3 |
2.9 |
<0.015 |
H |
2 |
VC10a |
0.9 |
1.9 |
Clay |
<55 |
<170 |
<3 |
<0.20 |
23 |
7.6 |
17 |
20 |
50 |
0.10 |
5.0 |
<0.10 |
<0.015 |
L |
1 |
VC10a |
1.9 |
2.9 |
Clay |
<55 |
<170 |
<3 |
<0.20 |
22 |
<7.0 |
16 |
20 |
46 |
0.07 |
4.9 |
<0.10 |
<0.015 |
L |
1 |
VC10a |
4.9 |
5.9 |
Clay |
<55 |
<170 |
<3 |
<0.20 |
27 |
9.8 |
20 |
35 |
58 |
0.10 |
7.2 |
<0.10 |
<0.015 |
L |
1 |
VC10a |
7.9 |
8.9 |
Clay |
<55 |
<170 |
<3 |
<0.20 |
27 |
10 |
20 |
28 |
59 |
0.10 |
7.4 |
<0.10 |
<0.015 |
L |
1 |
VC10a |
10.9 |
11.9 |
Clay |
<55 |
<170 |
<3 |
<0.20 |
27 |
12 |
18 |
32 |
58 |
0.08 |
10 |
<0.10 |
<0.015 |
L |
1 |
VC11a |
0 |
0.9 |
Anthropogenic Deposit |
<55 |
<170 |
<3 |
0.39 |
24 |
61 |
11 |
46 |
120 |
0.58 |
7.6 |
2.4 |
<0.015 |
H |
2 |
VC11a |
0.9 |
1.9 |
Clay |
<55 |
<170 |
6.3 |
0.29 |
36 |
50 |
18 |
78 |
130 |
0.62 |
7.2 |
1.1 |
<0.015 |
M |
1D |
VC11a |
1.9 |
2.9 |
Clay |
<55 |
<170 |
<3 |
<0.20 |
23 |
7.1 |
19 |
18 |
53 |
0.06 |
5.6 |
<0.10 |
<0.015 |
L |
1 |
VC11a |
4.9 |
5.9 |
Clay |
<55 |
<170 |
<3 |
<0.20 |
29 |
11 |
20 |
31 |
60 |
0.14 |
8.9 |
0.45 |
<0.015 |
L |
1 |
VC11a |
7.9 |
8.9 |
Clay |
<55 |
<170 |
<3 |
<0.20 |
28 |
13 |
20 |
31 |
68 |
0.09 |
11 |
<0.10 |
<0.015 |
L |
1 |
VC11a |
10.9 |
11.9 |
Clay |
<55 |
<170 |
<3 |
<0.20 |
18 |
8.5 |
10 |
24 |
37 |
0.06 |
12 |
<0.10 |
<0.015 |
L |
1 |
VC12a |
0 |
0.9 |
Anthropogenic Deposit |
<55 |
<170 |
<3 |
<0.20 |
15 |
58 |
7.3 |
28 |
65 |
0.28 |
7.3 |
1.3 |
<0.015 |
M |
2 |
VC12a |
0.9 |
1.9 |
Gravel |
<55 |
<170 |
<3 |
<0.20 |
32 |
14 |
23 |
38 |
69 |
0.19 |
10 |
0.14 |
<0.015 |
L |
1 |
VC12a |
1.9 |
2.9 |
Clay |
<55 |
<170 |
<3 |
<0.20 |
20 |
7.2 |
15 |
23 |
43 |
0.12 |
4.3 |
<0.10 |
<0.015 |
L |
1 |
VC12a |
4.9 |
5.9 |
Clay |
<55 |
<170 |
<3 |
<0.20 |
29 |
12 |
18 |
35 |
61 |
0.24 |
10 |
<0.10 |
<0.015 |
L |
1 |
VC12a |
7.9 |
8.9 |
Clay |
<55 |
<170 |
<3 |
<0.20 |
28 |
12 |
18 |
38 |
60 |
0.12 |
9.4 |
<0.10 |
<0.015 |
L |
1 |
VC12a |
10.9 |
11.9 |
Silt |
<55 |
<170 |
<3 |
<0.20 |
10 |
<7.0 |
6.1 |
16 |
22 |
0.07 |
4.9 |
<0.10 |
<0.015 |
L |
1 |
VC13a |
0 |
0.9 |
Clay |
140 |
2600 |
<3 |
0.25 |
21 |
55 |
9.2 |
55 |
98 |
0.25 |
4.8 |
1.7 |
<0.015 |
M |
1D |
VC13a |
0.9 |
1.9 |
Clay |
180 |
1300 |
7.5 |
0.84 |
60 |
270 |
22 |
110 |
190 |
0.89 |
6.6 |
2.4 |
<0.015 |
H |
2 |
VC13a |
1.9 |
2.9 |
Clay |
<55 |
<170 |
<3 |
<0.20 |
21 |
7.2 |
21 |
21 |
50 |
0.09 |
4.8 |
<0.10 |
<0.015 |
L |
1 |
VC13a |
4.9 |
5.9 |
Clay |
<55 |
<170 |
<3 |
2.8 |
29 |
12 |
23 |
34 |
70 |
0.15 |
6.6 |
<0.10 |
<0.015 |
M |
1D |
VC13a |
7.7 |
8.7 |
Clay |
<55 |
<170 |
<3 |
<0.20 |
20 |
7.1 |
12 |
20 |
38 |
0.05 |
4.7 |
<0.10 |
<0.015 |
L |
1 |
VC14a |
0 |
0.9 |
Silt |
<55 |
<170 |
<3 |
0.28 |
33 |
80 |
16 |
28 |
81 |
0.25 |
5.4 |
1.4 |
<0.015 |
M |
2 |
VC14a |
0.9 |
1.9 |
Silt |
<55 |
<170 |
<3 |
<0.20 |
23 |
16 |
15 |
18 |
50 |
0.10 |
4.5 |
0.10 |
<0.015 |
L |
1 |
VC14a |
1.9 |
2.9 |
Clay |
<55 |
<170 |
<3 |
<0.20 |
33 |
10 |
22 |
46 |
63 |
0.11 |
5.5 |
<0.10 |
<0.015 |
L |
1 |
VC14a |
4.9 |
5.9 |
Clay |
<55 |
<170 |
<3 |
<0.20 |
32 |
9.0 |
21 |
30 |
59 |
0.09 |
4.6 |
<0.10 |
<0.015 |
L |
1 |
VC14a |
7.9 |
8.9 |
Clay |
<55 |
<170 |
<3 |
<0.20 |
31 |
10 |
21 |
27 |
58 |
0.08 |
4.0 |
<0.10 |
<0.015 |
L |
1 |
VC14a |
10.9 |
11.9 |
Clay |
<55 |
<170 |
<3 |
<0.20 |
36 |
13 |
21 |
44 |
63 |
0.28 |
8.9 |
<0.10 |
<0.015 |
L |
1 |
VC15a |
0 |
0.9 |
Clay |
<55 |
<170 |
<3 |
<0.20 |
26 |
36 |
16 |
21 |
62 |
0.11 |
4.6 |
0.40 |
<0.015 |
L |
1 |
VC15a |
0.9 |
1.9 |
Clay |
<55 |
<170 |
<3 |
<0.20 |
28 |
7.5 |
22 |
17 |
59 |
0.06 |
3.8 |
<0.10 |
<0.015 |
L |
1 |
VC15a |
1.9 |
2.9 |
Clay |
<55 |
<170 |
<3 |
<0.20 |
27 |
7.7 |
20 |
19 |
59 |
0.06 |
4.7 |
<0.10 |
<0.015 |
L |
1 |
VC15a |
4.9 |
5.9 |
Clay |
<55 |
<170 |
<3 |
<0.20 |
30 |
10 |
20 |
28 |
55 |
0.10 |
5.2 |
<0.10 |
<0.015 |
L |
1 |
VC15a |
7.9 |
8.9 |
Clay |
<55 |
<170 |
<3 |
<0.20 |
30 |
10 |
20 |
32 |
57 |
0.06 |
6.2 |
0.10 |
<0.015 |
L |
1 |
VC15a |
10.9 |
11.9 |
Clay |
<55 |
<170 |
<3 |
<0.20 |
29 |
11 |
15 |
27 |
50 |
0.07 |
15 |
<0.10 |
<0.015 |
M |
2 |
Notes:
1.
LMW = Low
molecular weight PAHs, that is, acenaphthene, acenaphthylene, anthracene,
fluorene, naphthalene and phenanthrene.
2.
HMW = High
molecular weight PAHs, that is, benzo[a]anthracene, benzo[a]pyrene, chrysene,
dibenzo[a,h]anthracene, fluoranthene, pyrene, benzo[b]fluoranthene,
benzo[k]fluoranthene, indeno[1,2,3-c,d]pyrene and benzo[g,h,i]perylene.
3.
Values underlined
indicate Category M sediment under ETWB TCW No. 34/2002.
4.
Values in bold indicate Category H sediment under
ETWB TCW No. 34/2002.
5.
Values in bold and underlined indicate
Category H sediment under ETWB TCW No. 34/2002 and that the contaminant level
exceeded the LCEL by 10 times.
6.
Disposal Type 1 =
Type 1 -
A summary of classification of the vibrocore samples is provided in Table 6-10. The majority of the sediment samples (78%) were classified as Category L.
Table 6‑10 Summary of Classification of Vibrocore Samples
Category |
Number of
Vibrocore Samples |
Category L |
66 |
Category M |
9 |
Category H |
9 |
Category H (10 x > LCEL) |
0 |
The marine sediment quality analysis results of biological screening from the site investigation works were presented in a comprehensive laboratory testing report and is provided in Appendix F3.
The general characteristics of the marine sediment is
provided in the ancillary tests results summarised in Table 6-11.
Table 6‑11 Summary of Ancillary Tests Results
Composite Sample
No. |
Vibrocore No. |
Interstitial ammonia (mgNH3/L) |
Interstitial
salinity (ppt) |
Grain Size
< 63mm (%) |
Mositure Content (%) |
TOC (%
Wet Weight) |
TOC (%
Dry Weight) |
2 |
VC7a |
See Note 1 |
29 |
44 |
51 |
0.49 |
0.74 |
4 |
VC11a |
9.2 |
33 |
62 |
53 |
0.66 |
1.01 |
5 |
VC12a |
16.4 |
33 |
18 |
40 |
0.40 |
0.56 |
6 & 7 |
VC13a |
14.8 |
35 |
40 |
59 |
0.62 |
0.99 |
8 |
VC14a |
4.3 |
30 |
83 |
93 |
0.70 |
1.35 |
Note: 1. Analysis was not performed due to
insufficient amount of porewater obtained.
The sediment biological screening results indicated that composite sample no. 2, 5 and 8 failed the toxicity tests. The sediment was deemed to have failed the biological test if it fails in any one of the three toxicity tests. A summary of toxicity tests failure is provided in Table 6-12.
Table 6‑12 Summary of Toxicity Test Failure
Toxicity
Test |
Test
Failure (Composite Sample No.) |
10-day amphipod |
Nil |
20-day polychaete |
Nil |
48-96 hour bivalve larvae |
2, 5 and 8 |
6.5 Identification and Evaluation of Environmental Impacts
The construction activities to be carried out for construction of the proposed submarine watermain would generate a variety of wastes that can be divided into distinct categories based on their composition and ultimate method of disposal. The identified waste types include:
·
Construction and demolition (C&D) materials
·
General refuse; and
·
Chemical waste
·
Marine dredged sediment
Each type of waste arising is described below, together with an evaluation of the potential environmental impacts associated with generation, handling, storage and transport of the waste.
Construction and
Demolition (C&D) Materials
Excavated materials would arise from the excavation works for the landing points of the submarine watermain. It is anticipated that the volume of excavated material to be generated would be small and in the order of a few hundred cubic metres. In order to minimise the impact resulting from collection and transportation of C&D material for off-site disposal, the excavated material which comprise of reclamation fill material that could be reused on-site as fill material should be reused on-site as backfilling material for the construction of the associated landmains as far as practicable. The amount of C&D material to be generated would be quantified in the site Waste Management Plan to be prepared by the Contractor.
General Refuse
The construction workforce will generate refuse comprising food scraps, waste paper, empty containers, etc. Such refuse should be properly managed so intentional or accidental release to the surrounding environment does not occur. Disposal of refuse at sites other than approved waste transfer or disposal facilities shall be prohibited. Effective collection of site wastes will be required to prevent waste materials being blown around by wind, flushed or leached into the marine environment, or creating an odour nuisance or pest and vermin problem. Waste storage areas shall be well maintained and cleaned regularly. With the implementation of good waste management practices at the site, adverse environmental impacts are not expected to arise from the storage, handling and transportation of workforce wastes. The maximum number of construction workers to be employed is estimated to be about 100 workers. Based on a generation rate of 0.65 kg per worker per day, the maximum daily arising of general refuse during the construction period would be approximately 65 kg and this waste can be effectively controlled by normal measures.
Chemical Waste
The maintenance and servicing of construction plant and equipment may generate some chemical wastes such as cleaning fluids, solvents, lubrication oil and fuel. Maintenance of vehicles may also involve the use of a variety of chemicals, oil and lubricants. It is difficult to quantify the amount of chemical waste that will arise from the construction activities since it will be dependent on the Contractor’s on-site maintenance requirements and the amount of plant utilised. However, it is anticipated that the quantity of chemical waste, such as lubricating oil and solvent produced from plant maintenance, would be small and in the order of a few cubic metres per month. The amount of chemical waste to be generated will be quantified in the site Waste Management Plan to be prepared by the Contractor.
Chemical wastes arising during the construction phase may pose environmental, health and safety hazards if not stored and disposed of in an appropriate manner as stipulated in the Waste Disposal (Chemical Waste) (General) Regulations. The potential hazards include:
·
Toxic effects to workers
·
Adverse impacts on water quality from spills and
associated adverse impacts on marine biota; and
·
Fire hazards.
Materials classified as chemical wastes would require special handling and storage arrangements before removal for appropriate treatment at the approved Chemical Waste Treatment Facility. Wherever possible opportunities should be taken to reuse and recycle materials. Mitigation and control requirements for chemical wastes are detailed in Section 6.6.5. Provided that the handling, storage and disposal of chemical wastes are in accordance with these requirements, adverse environmental impacts are not expected.
Marine Dredged
Sediment
In accordance with ETWB TC(W) No. 34/2002 - Managmeent of Dredged/Excavated Sediment, review of existing information for site contamination assessment (Tier I), chemical screening (Tier II) and biological screening (Tier III) were conducted along the trench to be dredged for submarine watermain installation to determine the sediment quality. Sediments were classified into Category L, M and H based on its contaminant levels identified from chemical screening. Sediment classified as Category M was then subjected to biological screening. The corresponding types of disposal required were thus identified and presented numerically in Table 6-9 and graphically in Figure 6.3.
The existing seabed area would be dredged to lay the submarine watermain. According to Figure 6.3, the total volume of dredged sediment was estimated to be approximately 543,000 m3. The estimated volume of contaminated dredged sediment was approximately 212,000 m3. The potential environmental effects of the removal of these sediments on water quality have been assessed and presented in Section 3 of this Report.
To minimize any potential adverse impacts arising from the
dredged marine sediment, the sediment shall be dredged, transported and
disposed of in a manner that will minimise the loss of contaminants either into
solution or by resuspension. Mitigation
measures to minimise potential environmental impacts are described in Section
6.6.6. With the implementation of
mitigation measures, no unacceptable impacts would be expected from the
transportation and disposal of the dredged sediment.
No solid wastes are anticipated to be generated during operation except for minor quantities of material collected during maintenance inspections.
6.6 Mitigation of Adverse Environmental Impacts
Adverse impacts related to waste management are not expected to arise, provided that good site practices are strictly followed. Recommendations for good site practices during the construction activities include:
·
Nomination of an approved person, such as a site
manager, to be responsible for good site practices, arrangements for collection
and effective disposal to an appropriate facility, of all wastes generated at
the site
·
Training of site personnel in proper waste
management and chemical handling procedures
·
Provision of sufficient waste disposal points and
regular collection of waste
· Appropriate measures to minimise windblown litter and dust during transportation of waste by either covering trucks or by transporting wastes in enclosed containers
6.6.2 Waste Reduction Measures
Good management and control can prevent the generation of a significant amount of waste. Waste reduction is best achieved at the planning and design stage, as well as by ensuring the implementation of good site practices. Recommendations to achieve waste reduction include:
· Sort C&D material from demolition and decommissioning of the existing facilities to recover recyclable portions such as metals
·
Segregation and storage of different types of waste
in different containers, skips or stockpiles to enhance reuse or recycling of
materials and their proper disposal
·
Encourage collection of aluminium cans by providing
separate labelled bins to enable this waste to be segregated from other general
refuse generated by the work force
·
Proper storage and site practices to minimise the
potential for damage or contamination of construction materials
· Plan and stock construction materials carefully to minimise amount of waste generated and avoid unnecessary generation of waste.
In addition to the above measures, specific mitigation measures are recommended below for the identified waste arising to minimise environmental impacts during handling, transportation and disposal of these wastes.
In order to minimise impacts resulting from collection and transportation of C&D material for off-site disposal, the excavated materials should be reused on-site as backfilling material and for landscaping works for the associated land mains as far as practicable. In addition, C&D material generated from excavation works should be disposed of at public fill reception facilities for other beneficial uses. Other mitigation requirements are listed below:
·
A Waste Management Plan should be prepared.
·
A recording system for the amount of wastes
generated, recycled and disposed (including the disposal sites) should be
proposed.
·
In order to monitor the disposal of C&D
material and solid wastes at public filling facilities and landfills, and to
control fly-tipping, a trip-ticket system (e.g. ETWB TCW No. 31/2004) should be
included.
General refuse should be stored in enclosed bins or compaction units separate from C&D material. A reputable waste collector should be employed by the contractor to remove general refuse from the site, separately from C&D material. Preferably an enclosed and covered area should be provided to reduce the occurrence of 'wind blown' light material.
If chemical wastes are produced at the construction site, the Contractor would be required to register with the EPD as a chemical waste producer and to follow the guidelines stated in the Code of Practice on the Packaging, Labelling and Storage of Chemical Wastes. Good quality containers compatible with the chemical wastes should be used, and incompatible chemicals should be stored separately. Appropriate labels should be securely attached on each chemical waste container indicating the corresponding chemical characteristics of the chemical waste, such as explosive, flammable, oxidizing, irritant, toxic, harmful, corrosive, etc. The Contractor shall use a licensed collector to transport and dispose of the chemical wastes, to either the approved Chemical Waste Treatment Centre, or another licensed facility, in accordance with the Waste Disposal (Chemical Waste) (General) Regulation.
The basic requirements and procedures for dredged mud disposal are specified under the ETWB TCW No. 34/2002. The management of the dredging, use and disposal of marine mud is monitored by the MFC, while the licensing of marine dumping is the responsibility of the Director of Environmental Protection (DEP).
The dredged marine sediments would be loaded
onto barges and transported to designated disposal sites depending on their
level of contamination. Based on the
chemical and biological screening results and subsequently the corresponding
types of disposal required as presented in Table
6-9 and Figure 6.3, it was
estimated that some 326,000m3 of sediments would be suitable for
open sea disposal (Type 1), some 5,000 m3 of sediments would be
suitable for open sea disposal (dedicated sites) (Type 1) and 212,000m3
of sediments would require confined marine disposal (Type 2). Agreement from Marine Fill Committee for the
dredging rationale was obtained as presented in Appendix F4. Moreover, Marine Fill Committee has no comment on the
proposed disposal arrangements. In accordance with the ETWB TCW No. 34/2002, the contaminated material must be dredged and transported with
great care, and the mitigation measures recommended in Section 3 of this Report
should be strictly followed.
Furthermore, the dredged contaminated sediment must be effectively
isolated from the environment upon final disposal and shall be disposed of at
the East Sha Chau Contaminated Mud Pits that is designated for the disposal of
contaminated mud in
During transportation and disposal of the dredged marine sediments, the following measures should be taken to minimise potential impacts on water quality:
·
Bottom opening of barges shall be fitted with tight
fitting seals to prevent leakage of material. Excess material shall be cleaned
from the decks and exposed fittings of barges and dredgers before the vessel is
moved.
·
Monitoring of the barge loading shall be conducted
to ensure that loss of material does not take place during transportation. Transport barges or vessels shall be equipped
with automatic self-monitoring devices as specified by the EPD.
· Barges or hopper barges shall not be filled to a level that would cause the overflow of materials or sediment laden water during loading or transportation.
Table 6-13 provides a summary of the various waste types likely to be generated during the construction activities for the proposed submarine watermain, together with the recommended handling and disposal methods.
Table 6‑13 Summary of Waste Handling Procedures and Disposal Routes
Waste
Material Type |
Generated from works item |
Timing to be Generated |
Total Quantity Generated |
Quantity to be disposed off-site |
Disposal |
Handling |
Marine Dredged Sediment (Uncontaminated) |
Trench excavation |
Sep 08 to Aug 09 |
331,000 m3 |
331,000 m3 |
MFC gazetted marine disposal ground – open
sea disposal site |
Minimise resuspension by use of closed
grab, controlled loading and transfer |
Marine Dredged Sediment (Contaminated) |
Trench excavation |
Sep 08 to Aug 09 |
212,000 m3 |
212,000m3 |
East Sha Chau contaminated mud pit |
Minimise resuspension by use of closed
grab, tight seal on barges, controlled loading and transfer |
C&D Material |
Excavation works |
Sep 08 to May 11 |
Few hundred cubic meters (preliminary
estimate) |
Few hundred cubic meters (preliminary
estimate) |
To be reused on-site for construction of
the associated landmains or To be disposed to public fill reception
points for other beneficial uses or To be disposed to landfill |
Segregate inert C&D material to avoid
contamination from other waste arisings |
General Refuse |
Waste paper, discarded containers, etc.
generated from workforce |
Sep 08 to May 11 |
65 kg per day
(preliminary estimate based on workforce of 100) |
65 kg per day |
Refuse station for compaction and
containerisation and then to landfill |
Provide on-site refuse collection points |
Chemical Waste |
Cleansing fluids, solvent, lubrication oil
and fuel from construction plant and equipment |
Sep 08 to May 11 |
Few cubic metres
per month (preliminary
estimate) |
Few cubic metres per
month (preliminary
estimate) |
Chemical Waste Treatment Centre |
Recycle on-site or by licensed companies. Stored on-site within suitably designed
containers |
6.7 Evaluation of Residual Impacts
With the implementation of the recommended mitigation measures for the handling, transportation and disposal of the identified waste arising, no residual impact is expected to arise during the construction and operation of the proposed submarine watermain.
6.8 Environmental Monitoring and Audit
Waste management would be the contractor’s responsibility
to ensure that all wastes produced during the construction of the submarine
watermain are handled, stored and disposed of in accordance with good waste
management practices and EPD’s regulations and requirements. The recommended mitigation measures shall
form the basis of the site Waste Management Plan to be developed by the
Contractor in the construction stage.
Auditing of each waste stream should be carried out periodically to determine if wastes are being managed in accordance with approved procedures and the site Waste Management Plan. The audits should look at all aspects of waste management including waste generation, storage, recycling, treatment, transport and disposal. An appropriate audit programme would be to undertake a first audit at the commencement of the construction works, and then to audit weekly thereafter.
6.9 Conclusions and Recommendations
A review of the sediment quality data from the marine site investigation indicated that the majority of the marine sediments to be dredged along the proposed submarine watermain were classified as Category L. The total dredged volume for the Project was estimated as 543,000 m3, of which 212,000 m3 of sediment was classified as requiring confined marine disposal. With the implementation of the recommended mitigation measures and management procedures in accordance with the requirements of ETWB TCW No. 34/2002, no residual impact was predicted.
Waste types generated by the construction activities are likely to include C&D material (from minor excavation works), general refuse from the workforce, and chemical waste from the maintenance of construction plant and equipment. Provided that these wastes are handled, transported and disposed of using approved methods and that the recommended good site practices are strictly followed, adverse environmental impacts is not expected during the construction phase.
The submarine
watermain component of the Project across Victoria Harbour is a Designated
Project under Schedule 2, Part 1I(E3) of the Environmental Impact Assessment
Ordinance (EIAO) (Cap. 499) and an Environmental Permit (EP) issued under the
EIAO is required for the construction and operation of the designated project.
In accordance with the EIA Study
Brief No. ESB-132/2005, construction air quality impact arising from the
dredging, laying of pipe and backfilling works for the construction of the
submarine watermain was assessed.
An air quality impact assessment has been undertaken to define the nature and scale of potential environmental impacts associated with the construction of the submarine watermain specifically in terms of the effects of construction dust. Construction phase impacts have been assessed and mitigation measures have been identified to reduce any impact to acceptable levels.
7.2 Environmental Legislation, Standards, Guidelines and Criteria
Legislation, Standards, Guidelines and Criteria relevant to the consideration of air quality impacts under this Study include the following:
·
Hong Kong Air Pollution Control Ordinance;
·
Air Pollution Control (Construction Dust)
Regulation; and
· Technical Memorandum on Environmental Impact Assessment Process.
7.2.1 Hong Kong Air Pollution Control Ordinance
The principal legislation for the management of air quality is the Air Pollution Control Ordinance (APCO) (Cap 311). The whole of the Hong Kong Special Administrative Region (HKSAR) is covered by the Hong Kong Air Quality Objectives (AQOs) which stipulate the statutory limits of some typical air pollutants and the maximum allowable number of exceedance over specific periods (refer to Table 7-1).
Table
7‑1 Hong Kong Air Quality Objectives (mg/m3)(i)
Pollutant |
1 Hour (ii) |
8 Hours (iii) |
24 Hours (iii) |
3 Months (iv) |
1 Year (iv) |
|
800 |
|
350 |
|
80 |
Total Suspended Particulates |
500(vii) |
|
260 |
|
80 |
Respirable Suspended Particulates (v) |
|
|
180 |
|
55 |
Carbon Monoxide |
30,000 |
10,000 |
|
|
|
Nitrogen Dioxide |
300 |
|
150 |
|
80 |
Photochemical Oxidants (as ozone) (vi) |
240 |
|
|
|
|
Lead |
|
|
|
1.5 |
|
Notes:
(i) Measured at 298K(25 oC) and 101.325 kPa (one
atmosphere).
(ii) Not to be exceeded more than three
times per year.
(iii) Not to be exceeded more than once per
year.
(iv) Yearly and three monthly figures
calculated as arithmetic means.
(v) Respirable suspended particulates means suspended particles
in air with nominal aerodynamic diameter of 10 micrometres and smaller.
(vi) Photochemical oxidants are determined by
measurement of ozone only.
Air Pollution Control (Construction
Dust) Regulation
(vii) This is not an AQO but a criterion for
construction dust impact assessment under Annex 4 of the Technical Memorandum
on Environmental Impact Assessment Process.
7.2.2 Air Pollution Control (Construction Dust) Regulation
Air Pollution Control (Construction Dust) Regulation stipulates the construction dust control requirements for both notifiable (e.g. site formation) and regulatory (e.g. road opening) Works to be carried out by the Contractor. The requirements for various notifiable and regulatory works are given in Parts 1 and 2 of the Regulation respectively. Part 3 of the Regulation stipulates the general control requirements (e.g. site boundary and entrance) for construction dust. The control requirements for individual activities (e.g. stockpiling of dusty material) are given in Part 4 of the Regulation.
7.2.3 Technical Memorandum on EIA Process (EIAO-TM), Annex 4 and 12
Criteria and guidelines for evaluating and assessing air quality impact as stated in Section 1 of Annex 4 and Annex 12 of the EIAO-TM are followed respectively. The EIAO-TM states that the hourly Total Suspended Particulate (TSP) level should not exceed 500mg/m3 (measured at 25oC and 1 atm.) for construction dust impact assessment.
7.3 Baseline Conditions & Air Sensitive Receivers
The
proposed landing point at
The
proposed landing point at Sai Ying Pun is adjacent to the Western Wholesale
Food Market. The existing air quality at Sai Ying Pun is mainly affected by
emissions from vehicular traffic on
The nearest EPD air quality monitoring stations (AQMS) are located at Sham Shui Po and Central/Western. The annual average air quality data monitored at these stations for the year 2004 are presented in Table 7-2.
Table 7‑2 Background Air Quality (2001 – 2005)
Air
Pollutant |
Annual
Average Concentration in ugm-3 (Average
of year 2001 to 2005) |
|
|
Sham Shui Po |
Central/Western |
Total Suspended Particulates (TSP) |
79 |
73 |
Respirable Suspended Particulates (RSP) |
55 |
52 |
|
23 |
21 |
Nitrogen Dioxide (NO2) |
67 |
54 |
Source: Air
Quality in
The annual average concentrations presented in Table 7-2 have been used as the background air quality data for the following assessment.
Air
Sensitive Receivers (ASRs) within 500m of the proposed submarine watermain
alignment have been identified in accordance with the criteria set out in Annex
12 of the EIAO-TM by means of site inspections and reviews of land use plans.
No ASR was identified within 500m of the proposed submarine watermain alignment
at
Table 7‑3 Representative Air Sensitive Receivers
ASR ID |
Description |
Type of Use |
Separation Distance (m) |
|
|||
Nil |
|||
Sai
Ying Pun |
|||
FSB |
|
Residential |
360 |
VC |
|
|
320 |
CLM |
|
|
310 |
KY2 |
|
|
400 |
KY3a |
|
|
245 |
KY3b |
|
|
225 |
RWM |
|
|
215 |
CG1 |
|
|
220 |
CG2 |
|
|
230 |
CG3 |
|
|
245 |
GB |
|
|
270 |
TJB |
|
Office |
360 |
CMG |
China
Merchants Group, the Westpoint |
Office |
280 |
IPH |
Island
Pacific Hotel |
Hotel
and hostels |
300 |
SCB |
|
Office |
310 |
AFCDMO |
AFCD
Market Office |
GIC |
220 |
WWFM |
Western
Wholesale Food Market |
GIC |
340 |
7.4 Identification and Evaluation of Air Quality Impacts
The likely air quality impacts arising from the construction of the proposed submarine watermain are dust nuisance and gaseous emission from construction plant, vehicles and barges. It is anticipated that dust would be generated from excavation, material handling and wind erosion from the site.
The construction of the cross harbour main would involve the following construction plants:
- two grab dredgers (one for dredging and one for trimming)
- four hopper barges
- two tug boats
- one winch
- one marine piling vessel
- two lorries
- two cranes
The submarine watermain laying activities such as trench dredging and pipe pulling as detailed in the construction programme are not dust generating and the gaseous emissions of SO2 and NO2 from one barge at anytime on site would be limited. Exceedance of AQOs from their operation is not anticipated.
The construction activities associated with the landing point would involve dust generating activities such as site clearance, minimal ground excavation, material handling and vehicle movements on haul roads. As the number of plants required on site would be limited, dust impact and SO2 and NO2 emissions from plants and site vehicles would be minimal. With the implementation of appropriate dust suppression measures stipulated in the Air Pollution Control (Construction Dust) Regulation, together with proper maintenance of equipment, adverse air quality impacts are not anticipated.
There will not be any operational phase emissions.
7.5 Mitigation of Adverse Environmental Impacts
Construction dust impacts should be controlled within the 1-hour TSP criterion of 500 mg/m3 and 24-hour TSP AQO of 260 mg/m3. Therefore, effective control measures and good site practices should be implemented to meet the requirements of the Air Pollution Control (Construction Dust) Regulation and minimize construction dust impact.
During construction phase, the Contractor shall make reference, but not limit himself, to the following measures:
·
any excavated dusty materials or stockpile of dusty
materials should be covered entirely by impervious sheeting or sprayed with
water so as to maintain the entire surface wet, and recovered or backfilled or
reinstated within 24 hours of the excavation or unloading;
·
the working area of excavation should be sprayed
with water immediately before, during and immediately after the operations so
as to maintain the entire surface wet;
·
the load of dusty materials carried by vehicle
leaving a construction site should be covered entirely by clean impervious
sheeting to ensure that the dusty materials do not leak from the vehicle;
·
where a site boundary adjoins a road, streets or
other area accessible to the public, hoarding of not less than 2.4m high from
ground level should be provided along the entire length except for a site entrance
or exit;
·
the area where vehicle washing takes place and the
section of the road between the washing facilities and the exit point should be
paved with concrete, bituminous materials or hardcores;
·
every main haul road should be scaled with concrete
and kept clear of dusty materials or sprayed with water so as to maintain the
entire road surface wet;
·
the portion of road leading only to a construction
site that is within 30m of a designated vehicle entrance or exit should be kept
clear of dusty materials;
·
all dusty materials should be sprayed with water
prior to any loading, unloading or transfer operation so as to maintain the
dusty material wet;
·
vehicle speed should be limited to 10 kph except on
completed access roads; and
· every vehicle should be washed to remove any dusty materials from its body and wheels before leaving the construction sites.
As impact from operation activities of the submarine watermain is not anticipated, air quality mitigation measures are not required.
7.6 Evaluation of Residual Air Quality Impacts
With the implementation of proposed dust suppression measures and good site practices, no residual air quality impacts associated with the construction and operation of the proposed submarine watermain is anticipated.
7.7 Environmental Monitoring and Audit
Dust monitoring during the construction of the submarine watermain is considered not necessary. Auditing on at least weekly basis during construction of the submarine watermain is required to ensure the proposed dust control measures are properly implemented.
7.8 Conclusions and Recommendations
Potential air quality impacts arising from the construction and operation of the submarine watermain have been evaluated.
As the number of construction plants involved in the submarine watermain laying activities at anytime on site would be limited, exceedance of AQOs emissions of gaseous pollutants from these construction plants is not anticipated. The number of plants required on site for the construction of the landing points would also be limited. Dust impact and SO2 and NO2 emissions from plants and site vehicles would be minimal. With the implementation of appropriate dust suppression measures stipulated in the Air Pollution Control (Construction Dust) Regulation, together with proper maintenance of equipment, adverse air quality impact is not anticipated.
No air quality impact is
anticipated at the operational phase since there will not have any operational
phase emissions.
The submarine watermain
component of the Project across Victoria Harbour is a Designated Project under
Schedule 2, Part 1I(E3) of the Environmental Impact Assessment Ordinance (EIAO)
(Cap. 499) and an Environmental Permit (EP) issued under the EIAO is required
for the construction and operation of the designated project.
In accordance with the EIA Study
Brief No. ESB-132/2005, cultural heritage impact arising from the dredging,
laying of pipe and backfilling works for the construction of the submarine
watermain was assessed.
A cultural heritage impact assessment has been undertaken to define the nature and scale of the potential impacts on cultural heritage resources associated with the construction of the submarine watermain, with a specific focus on the effects in the vicinity of sensitive receivers within the seabed that will be affected by the construction of the submarine watermain. Measures required to mitigate identified impacts are recommended, where appropriate, to reduce residual impacts to acceptable levels.
8.2 Environmental Legislation, Standards, Guidelines and Criteria
The following legislation and guidelines are applicable to
the cultural heritage assessment in
·
Technical Memorandum on the EIA Process, Annex 10
and 19 (EIAO TM);
·
Antiquities and Monuments Ordinance (Cap. 53);
·
· Marine Archaeological Investigation Guidelines.
8.2.1 Technical Memorandum on the EIA Process, Annex 10 and 19
The EIAO-TM outlines the approaches required in investigating and criteria for assessing the impacts on cultural heritage sites. The following Sections are applicable:
Annex 10 - "The criteria for evaluating impact on sites of cultural heritage includes: (a) The general presumption in favour of the protection and conservation of all sites of cultural heritage because they provide an essential, finite and irreplaceable link between the past and the future and are points of reference and identity for culture and tradition; (b) Adverse impacts on sites of cultural heritage shall be kept to the absolute minimum."
Annex 19 - "There is no quantitative standard in deciding the relative importance of these sites, but in general, sites of unique archaeological, historical or architectural value will be considered as highly significant. A baseline study shall be conducted: (a) to compile a comprehensive inventory of places, buildings, sites and structures of architectural, archaeological and historical value within the proposed project area; and (b) to identify possible threats of, and their physical extent, destruction in whole or in part of sites of cultural heritage arising from the proposed project."
The Memorandum also outlines the approach in regard to the preservation in totality, in part, and not at all of cultural resources:
Annex 19 - "Preservation in totality will be a beneficial impact and will enhance the cultural and socio-economical environment if suitable measures to integrate the sites of cultural heritage into the proposed project are carried out. If, due to site constraints and other factors, only preservation in part is possible, this must be fully justified with alternative proposals or layout designs, which confirm the impracticability of total preservation."
8.2.2 Antiquities and Monuments Ordinance (Cap.53)
The Antiquities and Monuments Ordinance (Cap. 53), provides power for the designation of Antiquities and Monuments Sites or Declared Monuments in Hong Kong, and provides statutory protection against the threat of development for declared monuments, historic buildings and archaeological sites on land and underwater which have been recommended by the Antiquities Advisory Board (AAB), approved by the Chief Executive and gazetted in the government gazette to enable their preservation for posterity.
The Antiquities Authority may, after consultation with the Antiquities Advisory Board (AAB) and with Government approval, gazette and protect any place, building, site or structure considered to be of public interest by reason of its historical, archaeological or palaentological significance. Once declared a site of public interest, no person may undertake acts that are prohibited under the Ordinance, such as demolishing or carrying out construction or other works, unless a permit is obtained from the Antiquities Authority.
For archaeological sites, all relics dated prior to 1800 AD belong to the Hong Kong Government. Archaeological sites are generally classified into two categories, as follows:
·
Designated Monuments - those that have been
gazetted in accordance with Cap. 53 by the Antiquities Authority; and
·
Recorded Archaeological Sites – those which have
not been declared but recorded by the AMO under administrative protection
The Legislation also sets out the procedures for the issuing of Licences to Excavate and Search for Antiquities, the effect of which is to forbid all such activities being undertaken without such a licence. It also provides for the penalties exacted for infringement of the Ordinance, including fines and imprisonment.
Although there are no statutory provisions for the
protection of Sites of Cultural Heritage, Deemed Monuments and Graded Buildings
in
Section 11 of the Antiquities and Monuments Ordinance requires any person who discovers an antiquity, or supposed antiquity, to report the discovery to the Antiquities Authority. Nevertheless it is prudent to ensure that procedures and mechanisms which ensure the preservation or formal notification of previously unknown archaeological resources that may be revealed or discovered during a project assessment or during construction are identified at an early stage in project planning.
8.2.3
The HKPSG, Chapter 10 – Conservation covers planning considerations relevant to general guidelines and measures for conservation of historical buildings, archaeological sites and other antiquities.
8.2.4 Marine Archaeological Guidelines
The AMO have issued Guidelines for Marine Archaeological
Investigation (MAI) which details the standard practice, procedures and
methodology which must be undertaken in determining the marine archaeological
potential, presence of archaeological artefacts and defining suitable
mitigation measures.
8.3 Cultural Heritage Impact Assessment Methodology
A baseline review was undertaken to compile a comprehensive inventory of cultural heritage resources of the Study Area. The Review established the historical profile and potential for cultural heritage sites and included:
·
Marine charts records held in British Library and
National Maritime Museum Library in
·
Information held by the Antiquities and Monuments
Office;
·
Publications on local historical, architectural,
anthropological, archaeological and other cultural studies;
· Unpublished papers, records, archival and historical documents held in local libraries and other government departments.
The Geophysical Survey was undertaken to define the areas of greatest archaeological potential, assess the depth and nature of the seabed sediments to define which areas consist of suitable material to bury and preserve archaeological material and to map anomalies on the seabed which may be of archaeological potential.
IGGE (HK) Engineering Geophysical Company Limited undertook the Survey in August 2006, which covered a 200m corridor (100 m either side of the proposed centreline) along the length of the proposed submarine watermain route. This survey allowed for a comprehensive investigation of the seabed, and below the seabed.
8.3.3 Establishing Archaeological Potential
The data examined during the Baseline Review and Geophysical Survey were analysed to provide an indication of the likely character and extent of archaeological resources within the Study Area. The results are presented in the Marine Archaeological Investigation Report in Appendix H and summarised in Section 8.4.
The submarine watermain is proposed to be
located across
IGGE (HK) Engineering Geophysical Company Limited undertook a Geophysical Survey in August 2006 which covered a 200m submarine watermain corridor to identify all forms of submerged marine archaeological deposits and objects. There are evidence of trawl marks, debris and dumped materials. The submarine watermain corridor and surrounds have been greatly affected by fishing trawlers and anchors and this will have resulted in impacts to the type and state of preservation of any submerged marine archaeological deposits. The seabed within the study area consists of mud or fine sand. Generally more than 10 m in thickness of marine deposits covered the study area. This would create a preservation environment for archaeological resources. Interpretation of the digital side scan sonar data revealed that there were no seabed anomalies within the dredging area of the Project as shown in Figure 8.1.
Although archaeological resources could be present on the seabed within the study area, the seabed has been subjected to previous substantial disturbance associated with dredging works for the construction of the western harbour crossing and new reclamation construction at Hong Kong Island and West Kowloon, construction of mooring buoys to the north of the Central Fairway and maintenance dredging of navigation channels within Victoria Harbour. These disturbed seabed areas cover most of the proposed dredging area for the submarine watermain. Further investigation was therefore not recommended.
8.5 Identification of Cultural Heritage Impact
The potential sources of impact may arise due to trench excavation by dredging and installation of the submarine pipeline by “bottom-pull” method.
8.6 Assessment of Cultural Heritage Impact
Preservation in totality is taken as the first priority and the assessment has taken into account the requirements as specified in the Section 2.1 of Annex 10 and Sections 2.6 to 2.14 of Annex 19 of the EIAO-TM.
As no land based cultural heritage resources were identified, no impacts are expected.
No indication of marine archaeological material was identified. As such, no impacts are expected from the installation of the cross harbour main.
8.7 Mitigation of Adverse Environmental Impact
No cultural heritage resources are identified within the Study Area and therefore, no mitigation measures are considered necessary.
8.8 Evaluation of Residual Cultural Heritage Impact
No cultural heritage resources are identified within the Study Area and therefore, no residual impacts are expected.
8.9 Environmental Monitoring and Audit
No cultural heritage resources are identified within the Study Area and therefore, no environmental monitoring and audit programme are recommended.
8.10 Conclusions and Recommendations
A comprehensive baseline review identified no land based or submerged cultural heritage resources within the Study Area.
A Geophysical Survey which covered a 200m submarine watermain corridor was conducted and no indication of marine archaeological material was identified. Therefore, no impacts are expected from the installation of the cross harbour main.
The
submarine watermain component of the Project across Victoria Harbour is a
Designated Project under Schedule 2, Part 1I(E3) of the Environmental Impact
Assessment Ordinance (EIAO) (Cap. 499) and an Environmental Permit (EP) issued
under the EIAO is required for the construction and operation of the designated
project.
In accordance with
the EIA Study Brief No. ESB-132/2005, fisheries impact arising from the
dredging, laying of pipe and backfilling works for the construction of the
submarine watermain was assessed.
This Section of the EIA Report presents the results of an assessment of the impact of construction and operation of the submarine watermain of the Project on existing fisheries resources, fishing operations and fish culture activities based on the findings of the Water Quality Impact Assessment.
9.2 Environmental Legislation, Standards, Guidelines and Criteria
The following legislations and guidelines are
applicable to the fisheries impact assessment in
·
Technical Memorandum on the EIA Process, Annex 9
and 17 (EIAO-TM). Annex 17 of the EIAO-TM prescribes the general approach and
methodology for the assessment of fisheries impacts arising from a project or
proposal, to allow a complete and objective identification, prediction and
evaluation of the potential impacts.
EIAO-TM Annex 9 recommends the criteria that are to be used for
evaluating fisheries impacts.
·
Fisheries Protection Ordinance (Cap 171). This
Ordinance provides for the conservation of fish and other aquatic life and
regulates fishing practices.
·
Marine Fish Culture Ordinance (Cap 353). This
Ordinance regulates and protects marine fish culture and other related
activities
· Water Pollution Control Ordinance (Cap 358). This Ordinance set limits to water quality parameters in various water control zones.
9.3 Fisheries Impact Assessment Methodology
A desktop literature review was conducted in
order to establish the baseline conditions of the physical environment and fisheries
importance of the area. Information from the water quality assessment was used
to determine the size of the Study Area as that potentially affected by
perturbations to water quality parameters. The importance of fisheries
resources and fishing operations identified within the Study Area and the
potential impacts due to the construction and operation of the cross harbour
main were assessed following the criteria and guidelines for evaluating and
assessing fisheries impact as stated in Annexes 9 and 17 of the EIAO-TM, respectively.
This assessment of fisheries impacts focussed on the fisheries resources and fishing operations within the project area.
The availability of literature on the fisheries resources of the Study Area comes mainly from the AFCD 1996-1997 (48) and 2001-2002 (49) Port Survey. Other relevant reports from the Study Area have been reviewed. Updated mariculture information was obtained from the Agriculture, Fisheries and Conservation Department (AFCD).
In
General
The findings of fisheries surveys, fishermen’s interviews and accompanying literature reviews (50) conducted for AFCD’s Fisheries Resources and Fishing Operations in Hong Kong Waters Study have determined that commercial fish species reproduce throughout the year, though spawning for the majority of species appears to be concentrated during the period from June to September. The marine waters within the Study Area were not identified as a primary nursery ground for commercial fisheries as fish fry production density was less than or equal to 50 tails per hectare with reference to the AFCD’s Port Survey 2001/2002.
In 2005, the estimated fisheries production
in
Based on the AFCD Port Survey 2001/2002 data,
the highest range of fisheries production (i.e. 600 – 1000 kg ha-1)
was recorded near Cheung Chau, Penny’s Bay, Kau Yi Chau, Po Toi, Ninepin Group
and Tap Mun. The top 10 families
captured in
Up-to-date information from AFCD is available
for use in this EIA and can be collated to allow an assessment be made of the
importance of Fishing Zones in the Study Area to the
The Study Area interfaces with 5 Fishing Areas as identified in the AFCD Port Survey 1996/1997 Report (Figure 9.1). These Fishing Areas are identified as follows:
·
·
Sai Ying Pun
·
Central
·
Yau Ma Tei
· Tsim Sha Tsui
Findings
from Port Survey 1996/1997
The area and number of vessels operating during 1996-1997 in each of the Fishing Zones is presented in Table 9-1.
Code |
Fishery Area |
Area (Ha) |
Vessels < 15m |
Vessels > 15m |
All Vessels |
089 |
|
595.86 |
16.6 |
8.9 |
25.5 |
0151 |
Sai Ying Pun |
655.76 |
5.0 |
0 |
5.0 |
0152 |
Central |
265.10 |
6.1 |
0 |
6.1 |
0162 |
Yau Ma Tei |
287.75 |
14.9 |
0 |
14.9 |
0163 |
Tsim Sha Tsui |
181.76 |
2.6 |
0 |
2.6 |
Total |
1,986.23 |
* |
* |
* |
|
Total of all Fishing Zones in Hong Kong |
181,790.97 |
2,352.2 |
266.4 |
2,618.5 |
|
Percentage of Hong Kong Total |
1.1 % |
* |
* |
* |
*No values can be calculated for these parameters from the information
provided, as it cannot be determined whether the vessels reported as operating
within one zone are the same vessels that are reported for another zone.
The total number of vessels varies widely from 2.6 in Tsim Sha Tsui Fishing Area to 25.5 in Green Island Fishing Area. According to the AFCD Port Survey 1996/1997, the total fishing production in those fishing areas is mainly from vessels not exceeding 15m. Vessels exceeding 15m are only operated in the Green Island Fishing Area.
The overall fisheries production (adult fish
and fish fry) ranged widely from approximately 4.96 kg ha-1 (Sai
Ying Pun) to 134.3 kg ha-1 (
Table 9‑2 Fisheries
Production Values from each AFCD Fishing Zone within the Study Area
Code |
0089 |
0151 |
0152 |
0162 |
0163 |
Fishing Areas |
|
Sai Ying Pun |
Central |
Yau Ma Tei |
Tsim Sha Tsui |
Total Production |
|||||
Adult Fish (kg) |
80,026.26 |
3,255.84 |
18,230.83 |
20,268.29 |
1,041.98 |
Fry (Tails) |
- |
- |
- |
- |
- |
Value (HKD) |
760,154.46 |
106,666.67 |
400,357.14 |
719,309.53 |
30,857.14 |
Production (ha-1) |
|||||
Adult Fish (kg) |
134.30 |
4.96 |
68.77 |
70.44 |
5.73 |
Fry (Tails) |
- |
- |
- |
, |
- |
Value (HKD) |
1,275.74 |
162.66 |
1,510.22 |
2,499.77 |
169.77 |
Rank Production (Production, ha-1) |
|||||
Adult Fish (kg) |
76 |
170 |
112 |
111 |
168 |
Fry (Tails) |
- |
- |
- |
- |
- |
Value (HKD) |
130 |
169 |
124 |
96 |
168 |
Of the 5 fishing areas identified, one of the
fishing zone recorded medium rank adult fish production (
According to the AFCD Port Survey data, the top five adult fish species caught in the sector Victoria Harbour (SE01) included the Siganus Oramin (Rabbitfish), Leiognathus Brevirostris (Pony Fish), Mixed Species (Mixed Fish), Mixed Crab Species (Crab) and Argyrosomus Spp. (Croaker). The main fish species reported in catches from the Study Area are of low commercial value (<HK$15/kg) including mixed species (juveniles of trash fish species such as Caranx Kalla, Siganus canaliculatus and Leiognathus brevirostris) (Table 9-3). Croaker and Flathead is regarded as of high commercial value (>HK $20/kg).
Code |
Fishing Area |
Top Five Fish Caught (by weight) |
|
|
|
Species |
Common Name |
0089 |
|
Mixed Species |
Mixed Fish |
|
|
Mixed Prawn |
Prawn |
|
|
Mixed Crab Species |
Crab |
|
|
Leiognathus Brevirostris |
Pony Fish |
|
|
Platycephalus Indicus |
Flathead |
0151 |
Sai Ying Pun |
Mixed Species |
Mixed Fish |
|
|
Mixed Prawn |
Prawn |
|
|
Platycephalus Indicus |
Flathead |
|
|
Oratosquilla
Spp. |
Mantis Shrimp |
|
|
Cynoglossus Spp. |
Tongue Sole |
0152 |
Central |
Caranx Kalla |
Shrimp Scad |
|
|
Siganus Oramin |
Rabbitfish |
|
|
Stolephorus Spp. |
Anchovy |
|
|
Mixed Crab Species |
Crab |
|
|
Argyrosomus Spp. |
Croaker |
0162 |
Yau Ma Tei |
Siganus Oramin |
Rabbitfish |
|
|
Argyrosomus Spp. |
Croaker |
|
|
Mixed Crab Species |
Crab |
|
|
Clupanodon Punctatus |
Gizzard Shad |
|
|
Leiognathus Brevirostris |
Pony Fish |
0163 |
Tsim Sha Tsui |
Leiognathus Brevirostris |
Pony Fish |
|
|
Siganus Oramin |
Rabbitfish |
|
|
Argyrosomus Spp. |
Croaker |
|
|
Mixed Crab Species |
Crab |
|
|
Mixed Species |
Mixed Fish |
Findings from Port Survey 2001/2002
More
recent data were extracted from the AFCD’s Port Survey 2001/2002. In this Port Survey,
a uniform grid of 720 ha cell size overlaid on
The results of Port Survey 2001/2002 shows that the waters within the Study Area are having low to medium adult fish production (>0 to 200kg/ha).
The
catches from the direct impact grid cells as shown in Figure 9.2 were at medium price in
Fishing vessels operated in this grid cell include shrimp trawler, gill netter, long liner, hand liner, miscellaneous craft and sampan. All fish vessels are less than 15m in length.
There is no fish fry collected within the direct impact grid cells.
Among the 10 species of major fisheries products in Port Survey 2001/2002, the most abundant species in the direct impact grid cells are crab and seabream with production of 20-40kg/ha and 10-20kg/ha respectively.
For
the value of production, the direct impact grid cells are of low importance to
capture fishing operations in
The closest AFCD designated Fish Culture Zone (FCZ) to the Study Area is located at Ma Wan which is approximately 10km away from the proposed cross harbour main. As of 30 September 2006, updated information from AFCD indicates that the Ma Wan FCZ consists of 108 licensed rafts with a total licensed area of 14,554m2 (total gazetted area = 46,300m2) (52). The main species cultured are the spotted grouper (Epinephelus chlorostigma), gold-lined seabream (Rhabdosargus sarba), mangrove snapper (Lutjanus argentimaculatus) and the pompano (Trachinotus blochii). No figure is available for production at this FCZ, although the estimated production of marine culture fish in 2004 was about 1,540 tonnes valued at approximately $79 million (49).
The importance of the fisheries within the Study Area is addressed based on the baseline information provided above. The Fishing Zones within the Study Area are characterised as mainly of medium to low value. The catches from these zones were composed of juvenile mixed fish species, which are used as fish feed in mariculture.
Based on the preceding review of the available information on the capture and culture fisheries of the waters of the Study Area and its immediate vicinity, no particular sensitive receiver may be affected by the proposed works associated with the Project.
9.5 Identification of Fisheries Impacts
The cross harbour main with a length of approximately 2,100 metres will be submerged and embedded in a 6m deep trench in the seabed. The entire cross harbour main will be armoured with rockfill cover matching the original seabed level as shown in Figure 2.3.
Impact on future fishing operation is not anticipated as the armour rock will not protrude above the original seabed level. Impacts to fishing operations are expected to occur only during the installation of the cross harbour main. These impacts are predicted to be localised and small scale and may occur through the following mechanisms:
Direct
Impact
Long term direct impacts are not expected to occur through the installation of the cross harbour main. Short term direct impacts are predicted to occur along the submarine pipeline trench with a length of approximately 2,100 metres and a width of approximately 44 metres to be formed at the seabed as shown in Figure 2.3 as a result of the “bottom-pull” and dredging operations associated with the installation of the cross harbour main. Once these operations have ceased fisheries resources dependent on the affected area of seabed are expected to return due to recolonisation of the seabed by the supporting benthic fauna. The affected area of seabed will be reinstated in the following manner:
·
Install the submarine pipeline by bottom-pull
method upon completion of trench excavation;
·
Cover the pipeline by a thin layer of grade 75
bedding (minimum 0.3m above the top of the pipeline) by hopper or crane barge;
·
Backfill the submarine pipeline by armour rock
(approximately 4.5m) by hopper or crane barge;
·
Monitor the armour rock level by chain or echo
sounding during the course of rock placement. Trim the backfilled trench by
crane barge to ensure the backfilled level match with the original seabed level
without any rock armour protruding above the original seabed level; and
·
Gaps between the backfilled armour rock and the
edge of the submarine pipeline trench will be filled by marine sediment within
the sea volume from natural movement of the top soft soil of existing seabed.
Indirect
Impact
Indirect
impacts to fisheries resources and fishing operations during the construction
phase include sediment release associated with “bottom-pull” or dredging works.
Potential impacts on water quality from sediment release are listed below:
·
Increase concentrations of suspended solids (SS);
·
A resulting decrease in dissolved oxygen (DO)
concentrations; and
·
An increase in nutrient concentrations in the water column.
Suspended
Solids
Suspended sediment (SS) fluxes occur naturally in the marine
environment, consequently fish have evolved behavioural adaptations to tolerate
increased SS load (e.g., clearing their gills by flushing water over them).
Where SS levels become excessive, fish will move to clearer waters. This level is defined as the tolerance
threshold, which varies from species to species and at different stages of the
life cycle. If SS levels exceed
tolerance thresholds, fish are likely to become stressed, injured and may
ultimately die. Susceptibility generally
decreases with age, with eggs the most vulnerable and adults the least
sensitive to effects from sediments. The
rate, season and duration of SS elevations will influence the type and extent
of impacts upon fish.
It is noted that, despite the very conservative nature of the
assessment, the predicted increases in suspended solids concentrations did not
exceed the guideline value recommended by AFCD which was identified for
fisheries and selected marine ecological sensitive receivers that have been
based on international marine water quality guidelines for the protection of
ecosystems under the Consultancy Study on Fisheries and Marine Ecological
Criteria for Impact Assessment (CSFMEC) (53). The AFCD study recommends a
maximum concentration of 50 mg L-1 (based on half of the no
observable effect concentrations).
Dissolved
Oxygen
The relationships between SS and DO are complex, with increased SS in the water column combining with a number of other effects to reduce DO concentrations. Elevated SS (and turbidity) reduces light penetration, lowers the rate of photosynthesis by phytoplankton (primary productivity) and thus lowers the rate of oxygen production in the water column. Elevated SS can also cause increased energy retention from sunlight, resulting in higher temperatures, and thus the potential for lower oxygen levels as oxygen is more soluble in cold water. This has a particularly adverse effect on the eggs and larvae of fish, as at these stages of development high levels of oxygen in the water are required for growth to support high metabolic rates.
The assessment results of dissolved oxygen concentrations have shown that the predicted maximum decrease in dissolved oxygen concentrations are localised to within and around the submarine pipeline and restricted to the lower layers of the water column (i.e. close to the seabed). It is expected that the concentrations within the Study Area as a whole will be maintained at environmentally acceptable levels (i.e. compliant with the Water Quality Objectives as detailed in Section 3).
Nutrients
High levels of nutrients in seawater can cause rapid increases in
phytoplankton, on occasions to the point where an algal bloom occurs. An intense bloom of algae can lead to sharp
decreases in the levels of dissolved oxygen.
This decrease will initially occur in the surface water, and then deepen
as dead algae fall through the water column and decompose on the bottom. Anoxic conditions may result if DO
concentrations are already low or are not replenished. This may result in mortality to fish,
especially juveniles, due to oxygen deprivation.
The results of the water quality assessment sediment concentrations have
shown that the predicted maximum sediment concentrations are localised to
within and around the submarine pipeline and restricted to the lower layers of
the water column (i.e. close to the seabed).
It is expected that the concentrations within the Study Area as a whole
will be maintained at environmentally acceptable levels (i.e. compliant with
the Water Quality Objectives as detailed in Section 3).
Impacts to the sensitive receivers listed above are predicted, as a
result of the construction of Project, to be within environmentally acceptable
levels (as defined by compliance with the Water Quality Objectives).
The
only operation impacts from the submarine watermain would be if repair works
were required. This includes maintenance and repairing work for any accidental
damage of the pipeline. Since a
protective armour rock layer has been provided to prevent or minimize the
accidental damage, the repair works will not be significant during the design
life of the submarine watermain. The
impacts from this would be of reduced severity than those during the
construction phase as the work would take place in a specific and confined
small area. Therefore, unacceptable impacts to fisheries resources during the
operation of the submarine watermain are not envisaged.
9.6 Assessment of Fisheries Impacts
From the information presented above, the fisheries impact associated with construction of the proposed submarine watermain is considered to be low. An evaluation of the impact in accordance with Annex 9 of the EIAO-TM is presented below.
· Nature of Impact: Temporary, small scale and localised impact will occur to fisheries resources along submarine pipeline trench to be formed at the seabed as a result of the “bottom-pull” and dredging operations.
· Size of Affected Area: Although the submarine pipeline trench to be formed at the seabed as shown in Figure 2.3 is long (approximately 2,100 metres in length), the affected area of fisheries resources is predicted to be very small and localised to the works involved in installation of the cross harbour main.
· Size of fisheries resources/production: The fisheries resources and production rates of the Study Area range from low to medium in terms of catch weight and value.
· Destruction and disturbance of nursery and spawning grounds: The marine waters within the Study Area were not identified as a primary nursery and spawning grounds for commercial fisheries. No destruction and disturbance of areas of fisheries importance is therefore expected due to the project works.
· Impact on fishing activity: The submarine pipeline pass through areas with low to medium fisheries production and activities. Impact to fishing activities in the area are not expected to be of concern due to the small area physically disrupted during the installation of the submarine pipeline and the short time frame of disturbance. Impact on future fishing operation is not anticipated as the armour rock will not protrude above the original seabed level.
· Impact on aquaculture activity: Based on the Water Quality Objectives and AFCD criteria, the closest AFCD gazetted Fish Culture Zone (FCZ) to the Study Area which is located at Ma Wan and is approximately 10km away from the proposed cross harbour main is not predicted to be impacted by either suspended solid elevation, dissolved oxygen depletion or nutrient elevation as a result of the Project.
9.7 Mitigation of Adverse Environmental Impacts
In accordance with the guidelines in the EIAO-TM on fisheries impact assessment the general policy for mitigating impacts to fisheries, in order of priority are avoidance, minimization and compensation.
Impacts to fisheries resources and fishing operations have largely been avoided during construction through constraints on the works operations for installation of the submarine watermain. Good construction practice and associated measures were recommended in Water Quality Assessment in Section 3 to control water quality impacts to within acceptable levels and are also expected to control impacts to fisheries resources. Hence, no fisheries-specific mitigation measures are required during construction of the proposed submarine watermain.
9.8 Evaluation of Residual Fisheries Impacts
No adverse residual impact due to the construction and operation of the submarine watermain is expected after the implementation of the proposed mitigation measures to control water quality impacts.
9.9 Environmental Monitoring & Audit
The
implementation of the water quality mitigation measures stated in the Section 3 (Water Quality Impact
Assessment) should be checked as part of the environmental monitoring and audit
procedures during the construction phase as presented in the separate Environmental Monitoring and Audit
Manual.
The
dredging and “bottom pull” operations include constraints which act as
appropriate mitigation measures to control environmental impacts to within
acceptable levels. Actual water quality impacts from these activities will be
monitored. Monitoring and audit activities designed to detect and mitigate any
unacceptable impacts to water quality will serve to protect against
unacceptable impacts to fisheries resources.
The
water quality monitoring programme will provide management actions and
supplemental mitigation measures to be employed should impacts arise, thereby
ensuring the environmental acceptability of the project. No other
fisheries-specific measures are considered necessary.
9.10 Conclusions and Recommendations
Review of existing information on fisheries resources and fishing operations located within the Study Area have been undertaken. Although the submarine pipeline trench to be formed at the seabed is relatively long, the affected area of fisheries resources is predicted to be temporary, small scale and localised to the works associated with formation of submarine pipeline trench at the seabed as a result of the “bottom-pull” and dredging operations. Although the submarine pipeline passes through areas with low to medium fisheries production and activities, impact to fishing activities in the area are not expected to be of concern due to the small area physically disrupted during the installation of the submarine pipeline and the short time frame of disturbance. Impact on future fishing operation is not anticipated as the armour rock will not protrude above the original seabed level. Ma Wan Fish Culture Zone which is the closest AFCD gazetted Fish Culture Zone to the Study Area is not predicted to be impacted by either suspended solids elevation, dissolved oxygen depletion or nutrient elevation as a result of the Project.
As potential impacts to fisheries resources and fishing operations arising from formation of the submarine pipeline trench at the seabed are predicted to be temporary, small scale and localised, they are not expected to cause adverse impacts to any fishing grounds or species of importance to the fishery. While no special mitigation measures are required for fisheries resources and fishing activities, mitigation measures recommended to control impacts to water quality to within acceptable levels are also expected to mitigate impacts to fisheries resources and fishing activities.
10.1 Population and Environmental Sensitive Areas Protected
The EIA process has facilitated integration of environmental considerations into the design process for the Project. The principal measures identified are those achieved through careful routing of the watermain and the installation methodology or watermain design. Moreover, a number of mitigation measures have been identified to minimise the potential for adverse environmental impacts to occur. The mitigation measures are detailed in full in the Environmental Mitigation Implementation Schedule in Section 13. These measures will be implemented by WSD and, if appropriate, enforced by EPD by means of the EIAO.
One of the key
environmental outcomes has been the ability to plan, design and ultimately
construct the Project so that direct impacts to sensitive receivers are
avoided, as far as practically possible. A detailed assessment of alternatives
for routing the watermain was undertaken. A number of alternative watermain
routes were studied and the preferred alignment avoids direct impacts to
ecologically sensitive habitats and species such as corals fringing
10.2 Environmental Friendly Designs Recommended and Problems Avoided
In preparing the design and installation
method for the watermain, a key concern was to take steps so that indirect
impacts to water quality sensitive receivers, through disturbance to the
seabed, were avoided or minimised. Consequently, the following approaches were
taken to achieve the above.
·
Reduction in Indirect Impacts - The alignment
chosen for the submarine watermain was located at a sufficient distance from
ecological sensitive receivers so that the temporary dispersion of sediment
from the installation works was not predicted to affect the receivers at levels
of concern (as defined by the WQO and tolerance criteria).
·
Installation Equipment - The use of grab dredging
and “bottom-pull” along the entire route has minimised the severity of
perturbations to water quality and hence allowed compliance with the WQOs at
the sensitive receivers. This careful
selection of installation equipment has helped avoid impacts to sensitive
ecological receivers.
·
Adoption of Acceptable Working Rates - The
modelling work has demonstrated that the selected working
rates for the dredging and “bottom-pull” works will not cause unacceptable
impacts to water quality. Consequently,
unacceptable indirect impacts to marine ecological resources have been avoided.
10.3 Environmental Benefits of the Project
The primary objective of this Project is to lay a new cross harbour main on the western part of the harbour for maintaining the reliability of cross harbour water transfer to Hong Kong Island as it was determined that 10 years’ time, two of the existing four cross harbour mains transferring portable supplies to Hong Kong Island will reach their design life of 50 years.
The new cross harbour main will reduce the risk of insufficient cross harbour transfer capacity in times of emergency in the next decade. With the proposed new cross harbour main, the risk of having one cross harbour main under maintenance while another watermain has to be taken out of service without warning. It will minimise the requirement of constructing new reservoirs and fresh water pumping stations in the highly congested urban areas with heavy traffic and congested underground utilities, and hence prevents associated environmental impacts arisen from those works.
A marine water quality monitoring and audit programme is recommended during the dredging works to verify whether or not impact predictions are representative, and to ensure that the dredging works along the alignment of the proposed submarine watermain do not result in unacceptable impacts and the seawater quality at WSD’s seawater intakes comply with the WSD’s Water Quality Objectives (WQOs) of seawater for flushing supply. If monitoring shows unacceptable water quality impact, appropriate mitigation measures, such as changes in the operation of dredging works should be introduced.
Details of the environmental monitoring and audit programme are presented in the EM&A Manual. Water quality monitoring would be carried out at selected potentially affected sensitive receivers. The Manual includes site-specific monitoring and auditing protocols for baseline and impact monitoring of marine water quality. Such protocols include but are not limited to the locations of monitoring stations, parameters and frequencies for monitoring, monitoring equipment, and reporting of monitoring results.
As no adverse water quality impact was predicted from the operation of the Project, operational water quality monitoring and audit was not considered necessary.
The implementation of the ecological mitigation measures stated in Section 4.8 and water quality mitigation measures in Section 3 should be checked as part of the environmental monitoring and audit procedures during the construction period as presented in the EM&A Manual. No other marine ecology-specific measures are considered necessary.
Full compliance with the noise criteria will be achieved at all NSRs with the implementation of mitigation measures. Environmental monitoring and audit is recommended to ensure that the noise levels do not exceed the criteria during the construction phase as discussed in the EM&A Manual.
It is recommended that auditing of each waste stream should be carried out periodically to determine if wastes are being managed in accordance with approved procedures and the site waste management plan. The audits should look at all aspects of waste management including waste generation, storage, recycling, treatment, transport and disposal. An appropriate audit programme would be to undertake a first audit at the commencement of the construction works, and to audit weekly thereafter.
Full compliance with the air quality criteria will be achieved at all ASRs with the implementation of mitigation measures. Dust monitoring is considered not necessary but weekly site audits are required to ensure that the dust control measures are properly implemented.
As discussed in Section 8, no indication of marine archaeological material was identified and no further investigation activities were recommended. As such, there would be no need for a cultural heritage monitoring programme during the construction phase of the submarine watermain.
The implementation of the water quality mitigation measures stated in the Section 3 (Water Quality Impact Assessment) should be checked as part of the environmental monitoring and audit procedures during the construction period as presented in the separate Environmental Monitoring and Audit Manual. No other fisheries-specific measures are considered necessary.
The dredging and
“bottom pull” operations include constraints which act as appropriate
mitigation measures to control environmental impacts to within acceptable
levels. Actual water quality impacts from these activities will be monitored.
Monitoring and audit activities designed to detect and mitigate any
unacceptable impacts to water quality will serve to protect against
unacceptable impacts to fisheries resources.
The water quality
monitoring programme will provide management actions and supplemental
mitigation measures to be employed should impacts arise, thereby ensuring the
environmental acceptability of the project. No other fisheries-specific
measures are considered necessary.
12.1 Water Quality
Water quality impact during the dredging works of the
submarine watermain was quantitatively assessed using the Delft3D Model. Suspended sediment was identified as the key
water quality parameter during dredging.
Water quality impact on the sensitive receivers during the entire duration
of the dredging works and along the entire alignment with the maximum possible
instantaneous working rate of 0.0463m3s-1. (i.e. one grab dredger with a maximum
production rate of 4,000m3
per day, 7 days per week, 24 hours per day) for the complete simulation period
for the dry and wet seasons was assessed and it was predicted that potential
water quality impact would occur at the WSD Sea Water Intake at Kowloon South
Salt Water Pumping Station. With the implementation of the proposed mitigation measures
including the use of one grab dredger only with a maximum production rate of
4,000m3 per day for
dredging, deployment of frame type silt curtain
to fully enclose the grab while dredging works are in progress and
deployment of silt screen at the sea water intake at Kowloon South Salt Water
Pumping Station while dredging works are in progress (in a configuration as
shown in Figure 3.9), the potential
water quality impact upon the sea water intake would be effectively minimised
and there would be no unacceptable residual cumulative water quality impact due
to the dredging works of the submarine watermain as well as the other
concurrent marine works. The assessment
predicted that the dredging works would have negligible impact upon the coral
communities near
Minor potential water quality impacts from hydrostatic tests of the water mains systems and construction activities associated with the construction of the proposed submarine watermain were associated with effluent, sewage, wastewater and surface runoff. Impacts could be controlled to comply with the WPCO standards by implementing the recommended mitigation measure. No unacceptable residual impact on water quality was expected.
No maintenance dredging is required for the future
operation of the proposed submarine watermain. There would be no hydrodynamic
impact as the operation of the submarine watermain would not involve
reclamation or filling that affect the flow volume within the
There would also be no water quality impact during the operation of the submarine watermain as no effluent would be discharged due to the operation of the submarine watermain.
A review of the existing information showed that the
marine ecological resources within the dredging area consist of pollution
tolerant soft benthos in low diversity and typical to benthos recorded in poor
quality sediments. Inter-tidal species along
In conclusion, the construction of the proposed submarine
watermain along
Construction noise impact to the NSRs has been assessed. It is predicted that major construction activities including dredging, laying of pipe and backfilling works would comply with the noise criteria stipulated in the EIAO-TM and NCO during daytime and evening (1900 to 2300 hours).
If night-time works (2300 to 0700 hours) are carried out, the location of dredging works should be restricted while there should be no work within the prohibited zones. With this measure being taken place, the night-time criteria during the dredging period can be complied with.
Work schedule rearrangement, quiet plants and mobile noise barriers are recommended to further suppress noise emissions from construction activities. Good site practices will be necessary to further reduce any potential impact to the noise sensitive receivers.
A review of the sediment quality data from the marine site investigation indicated that the majority of the marine sediments to be dredged along the proposed submarine watermain were classified as Category L. The total dredged volume for the Project was estimated as 543,000 m3, of which 212,000 m3 of sediment was classified as requiring confined marine disposal. With the implementation of the recommended mitigation measures and management procedures in accordance with the requirements of ETWB TCW No. 34/2002, no residual impact was predicted.
Waste types generated by the construction activities are likely to include C&D material (from minor excavation works), general refuse from the workforce, and chemical waste from the maintenance of construction plant and equipment. Provided that these wastes are handled, transported and disposed of using approved methods and that the recommended good site practices are strictly followed, adverse environmental impacts is not expected during the construction phase.
Potential air quality impacts arising from the construction and operation of the submarine watermain have been evaluated.
As the number of construction plants involved in the submarine watermain laying activities at anytime on site would be limited, exceedance of AQOs emissions of gaseous pollutants from these construction plants is not anticipated. The number of plants required on site for the construction of the landing points would also be limited. Dust impact and SO2 and NO2 emissions from plants and site vehicles would be minimal. With the implementation of appropriate dust suppression measures stipulated in the Air Pollution Control (Construction Dust) Regulation, together with proper maintenance of equipment, adverse air quality impact is not anticipated.
No air quality impact is
anticipated at the operational phase since there will not have any operational
phase emissions.
A comprehensive baseline review identified no land based or submerged cultural heritage resources within the Study Area.
A Geophysical Survey which covered a 200m submarine watermain corridor was conducted and no indication of marine archaeological material was identified. Therefore, no impacts are expected from the installation of the cross harbour main.
Review of existing information on fisheries resources and fishing operations located within the Study Area have been undertaken. Although the submarine pipeline trench to be formed at the seabed is long, the affected area of fisheries resources is predicted to be temporary, small scale and localised to the works associated with formation of submarine pipeline trench at the seabed as a result of the “bottom-pull” and dredging operations. Although the submarine pipeline pass through areas with low to medium fisheries production and activities, impact to fishing activities in the area are not expected to be of concern due to the small area physically disrupted during the installation of the submarine pipeline and the short time frame of disturbance. Impact on future fishing operation is not anticipated as the armour rock will not protrude above the original seabed level. Ma Wan Fish Culture Zone which is the closest AFCD gazetted Fish Culture Zone to the Study Area is not predicted to be impacted by either suspended solids elevation, dissolved oxygen depletion or nutrient elevation as a result of the Project.
As potential impacts to fisheries resources and fishing operations arising from formation of the submarine pipeline trench at the seabed are predicted to be temporary, small scale and localised, they are not expected to cause adverse impacts to any fishing grounds or species of importance to the fishery. While no special mitigation measures are required for fisheries resources and fishing activities, mitigation measures recommended to control impacts to water quality to within acceptable levels are also expected to mitigate impacts to fisheries resources and fishing activities.
EIA Ref. |
EM&A Ref. |
Recommended Mitigation Measures |
Who to implement
the measure? |
Location
of the measure |
When to
implement the measure? |
What
requirements or standards for the measure to
achieve? |
Water Quality |
||||||
3.8.1 |
2.9 |
Specific Mitigation Measures for Dredging Exceedances of WSD Seawater
Intake criterion (10 mg L-1) at Kowloon South Salt Water Pumping
Station was predicted during both dry and wet seasons if dredging was
undertaken near -
Dredging should
be undertaken using one grab dredger only with a maximum production rate of
4,000m3 per day; -
Deployment of
frame type silt curtain to fully enclose the grab while dredging work are in
progress. -
Deployment of
silt screen at the sea water intake at Kowloon South Salt Water Pumping
Station while dredging works are in progress. The frame type silt curtain
should be designed to enclose local pollution caused by the grab dredger and
suspended by a steel frame mounted on the grab dredger and floating on water.
This frame type silt curtain should be fabricated from permeable, durable,
abrasion resistant membrane like geotextiles and be mounted on a floating
boom structure. The frame type silt curtain should also extend to the seabed
to cover the entire water column. Steel chain or ballast should be attached
to the bottom of the silt curtain. Mid-ballast may be added as necessary. The
structure of the silt curtain should be maintained by metal grids. The frame
type silt curtain should be capable or reducing sediment loss to outside by a
factor of 4 (or about 75%). Silt screen is recommended for dredging near the
seawater intake at Kowloon South Salt Water Pumping Station. The
implementation of silt screen at the intake could reduce the SS level by a
factor of 2.5 (or about 60%). These SS reduction factors have been adopted in
the Wan Chai Development Phase II Environmental Impact Assessment Study in
2001. An illustration of a typical
configuration of frame type silt curtain and silt screen at seawater intake
is shown in Figure 3.9. |
WSD’s Contractor |
Construction Work Sites
(Along the alignment of dredging) |
During Marine Construction
works |
Practice Note for
Professional Persons with regard to site drainage (ProPECC PN 1/94) and WQO |
3.8.1 |
2.9 |
Other Mitigation
Measures for Dredging Good Site Practices are
recommended to further reduce the potential water quality impacts from the
construction works, especially during dredging. |
|
|
|
|
|
|
·
Tight-closing
grabs should be used to minimize the loss of sediment to suspension during
dredging works. For dredging of any
contaminated mud, closed watertight grabs must be used; |
|
|
|
|
|
|
·
all vessels should
be sized so that adequate clearance is maintained between vessels and the
seabed in all tide conditions, to ensure that undue turbidity is not
generated by turbulence from vessel movement or propeller wash; |
|
|
|
|
|
|
·
the decks of all
vessels should be kept tidy and free of oil or other substances that might be
accidentally or otherwise washed overboard; |
|
|
|
|
|
|
·
adequate free
board shall be maintained on barges to ensure that decks are not washed by
wave action; |
|
|
|
|
|
|
·
all barges used
for the transport of dredged materials should be fitted with tight bottom
seals to prevent leakage of material during loading and transport; |
|
|
|
|
|
|
·
construction activities
should not cause foam, oil, grease, scum, litter or other objectionable
matter to be present in the water within the site or dumping grounds; |
|
|
|
|
|
|
·
loading of
barges should be controlled to prevent splashing of material into the surrounding
waters. Barges should not be filled to
a level that would cause the overflow of materials or sediment laden water
during loading or transportation; |
|
|
|
|
|
|
·
the speed of vessels
should be controlled within the works area to prevent propeller wash from
stirring up the seabed sediments; and |
|
|
|
|
|
|
·
before
commencement of dredging works, the holder of the Environmental Permit should
submit detailed proposal of the design and arrangement of the frame type silt
curtain to EPD for approval. |
|
|
|
|
3.8.1 |
2.9 |
Effluent from Hydrostatic Tests of the Water Mains
System To ensure compliance with the
standards for effluent discharged into the inshore waters or marine waters of
Victoria Harbour WCZ as shown in Tables 9a and 9b of the TM-DSS and Section
23.73 and 23.77 of the General Specification for Civil Engineering Works
Volume 3, 1992 Edition, sedimentation tanks with sufficient capacity,
constructed from pre-formed individual cells of approximately 6 to 8 m3
capacities, are recommended as a general mitigation measure which can be used
for settling surface runoff prior to disposal. The system capacity should be flexible and
suited to applications where the influent is pumped. Pre-treatment including
dechlorination such as by physical process e.g. adsorption by activated
carbon filter, or chemical process e.g. neutralisation by dechlorination agent
dosing should be carried out to ensure compliance with the discharge
requirements stipulated in TM-DSS. |
WSD’s Contractor |
Construction Work Sites
(General) |
During Hydrostatic Tests |
Practice Note for Professional
Persons with regard to site drainage (ProPECC PN 1/94) and WQO |
3.8.1 |
2.9 |
Surface Runoff, Sewage and Wastewater from
Construction Activities Appropriate measures should
be implemented to control runoff and prevent high loads of SS from entering
the marine environment. Proper site
management is essential to minimise surface runoff and sewage effluents. ·
Construction
site runoff should be prevented or minimised in accordance with the
guidelines stipulated in the EPD's Practice Note for Professional Persons,
Construction Site Drainage (ProPECC PN 1/94). All discharges from the
construction site should be controlled to comply with the standards for
effluents discharged into the Victoria Harbour WCZ under the TM-DSS. Good
housekeeping and stormwater best management practices, as detailed below,
should be implemented to ensure all construction runoff complies with WPCO
standards and no unacceptable impact on the WSRs as a result of construction
of the proposed submarine watermain; |
WSD’s Contractor |
Construction Work Sites
(General) |
During Construction works |
Practice Note for
Professional Persons with regard to site drainage (ProPECC PN 1/94) and WQO |
|
|
·
Sedimentation tanks
with sufficient capacity, constructed from pre-formed individual cells of
approximately 6 to 8 m3 capacities, are recommended as a general
mitigation measure which can be used for settling surface runoff prior to
disposal. The system capacity should
be flexible and able to handle multiple inputs from a variety of sources and
suited to applications where the influent is pumped; |
|
|
|
|
|
|
·
Manholes
(including newly constructed ones) should always be adequately covered and temporarily
sealed so as to prevent silt, construction materials or debris being washed
into the storm runoff being directed into foul sewers; |
|
|
|
|
|
|
·
All vehicles and
plant should be cleaned before leaving a construction site to ensure no earth,
mud, debris and the like is deposited by them on roads. An adequately designed and located wheel
washing bay should be provided at every site exit, and wash-water should have
sand and silt settled out and removed at least on a weekly basis to ensure
the continued efficiency of the process.
The section of access road leading to, and exiting from, the
wheel-wash bay to the public road should be paved with sufficient backfill
toward the wheel-wash bay to prevent vehicle tracking of soil and silty water
to public roads and drains; |
|
|
|
|
|
|
·
Precautions
should be taken at any time of year when rainstorms are likely. Actions
should be taken when a rainstorm is imminent or forecast. Actions to be taken
during or after rainstorms are summarised in Appendix A2 of ProPECC PN
1/94. Particular attention should be
paid to the control of silty surface runoff during storm events, particularly
for areas located near steep slopes; |
|
|
|
|
|
|
·
Fuel tanks and
storage areas should be provided with locks and be located on sealed areas,
within bunds of a capacity equal to 110% of the storage capacity of the
largest tank, to prevent spilled fuel oils from reaching the coastal waters
of the Victoria Harbour and Western Harbour WCZs; |
|
|
|
|
|
|
·
Portable
chemical toilets should be used to handle construction workforce sewage prior
to discharge to the existing trunk sewer. Sufficient numbers of portable toilets
shall be provided by a licensed contractor to serve the construction
workers. The Contractor shall also be
responsible for waste disposal and maintenance practices. |
|
|
|
|
Ecology |
||||||
4.8 |
3 |
Other mitigation measures suggested
in the water quality impacts assessment such as the use of one grab dredger
only with a maximum production rate of 4,000m3 per day for
dredging, deployment of frame type silt curtain to fully enclose the grab
while dredging works are in progress, deployment of silt screen at the sea
water intake at Kowloon South Salt Water Pumping Station while dredging works
are in progress and good site practices to avoid silt runoff from
construction works associated with the construction of the submarine watermain
should be implemented to further reduce the impact on the marine ecology. |
WSD’s Contractor |
Construction Work Sites
(Along the alignment of dredging) |
During Marine Construction
works |
EIAO |
Noise |
||||||
5.6.1 |
4.8 |
Work Schedule Rearrangement Concurrent works should be
such that necessary noisy works should be carried out at different time slots
or spread around the construction sites. This will help to reduce the
cumulative noise effect produced in the construction process. If night-time (2300 to 0700
hours) dredging is required, the work shall be scheduled to carry out at a
distance as far as possible to the NSRs. It is determined that the dredging
work should be carried out at a location 750m away from the Sai Ying Pun
landfall site and 450m from the West Kowloon landfall site along the trench
as shown in the Figure 5.5 of the EIA Report. The Contractor shall adhere to
the restricted locations of dredging work at night-time to comply with
relevant noise standard. |
WSD’s Contractor |
Construction Work Sites
(Along the alignment of dredging) |
During Marine Construction
works |
PN 2/93 Noise from
Construction Activities & EIAO |
5.6.2 |
4.8 |
Using Quality PME The use of Quality PME recognized
by the Noise Control Authority for the purpose of CNP application can
effectively reduce the noise generated from the construction plants. Quality
PME are construction plants and equipments that are notably quieter, more
environmental friendly and efficiently. The noise level reduction ranges from
5 – 10 dB(A) depending on the type of equipment used. The Contractor shall
note the required procedures involved in application of the QPME. |
|
|
|
|
5.6.3 |
4.8 |
Using Noise Barriers Mobile or movable noise
barriers to be erected near to the construction plants would reduce the noise
levels for commonly 5 – 10 dB(A) depending on the types of items of PME and
materials of the barriers. It is recommended that the Contractor shall screen
noisy works and noise from stationary items of PME whenever practicable. |
|
|
|
|
5.6.4 |
4.8 |
Good Site Practices Good site practice and
noise management can significantly reduce the impact of construction site
activities on nearby NSRs. The following
package of measures should be followed during construction: |
|
|
|
|
|
|
·
only
well-maintained plant should be operated on-site and plant should be serviced
regularly during the construction works; |
|
|
|
|
|
|
·
machines and plant
that may be in intermittent use should be shut down between work periods or
should be throttled down to a minimum; |
|
|
|
|
|
|
·
plant known to
emit noise strongly in one direction, should, where possible, be orientated to
direct noise away from the NSRs; |
|
|
|
|
|
|
·
mobile plant
should be sited as far away from NSRs as possible; and |
|
|
|
|
|
|
·
material
stockpiles and other structures should be effectively utilised, where practicable,
to screen noise from on-site construction activities. |
|
|
|
|
Waste Management |
||||||
6.6.1 |
5.3 |
Good Site Practices Adverse impacts related to
waste management are not expected to arise, provided that good site practices
are strictly followed. Recommendations for good site practices during the
construction activities include: |
WSD’s Contractor |
Construction Work Sites
(General) |
During Construction works |
Waste Disposal Ordinance (Cap.354);
Waste Disposal (Chemical Wastes) (General) Regulation |
|
|
·
Nomination of an approved person, such as a site manager, to be
responsible for good site practices, arrangements for collection and effective
disposal to an appropriate facility, of all wastes generated at the site; |
|
|
|
(Cap 354) and ETWBTC No.
15/2003, Waste |
|
|
·
Training of site personnel in proper waste management and chemical
handling procedures; |
|
|
|
Management on |
|
|
·
Provision of sufficient waste disposal points and regular collection of
waste; |
|
|
|
Construction Site |
|
|
· Appropriate measures to
minimise windblown litter and dust during transportation of waste by either
covering trucks or by transporting wastes in enclosed containers. |
|
|
|
|
6.6.2 |
5.3 |
Waste Reduction Measures Good management and control
can prevent the generation of a significant amount of waste. Waste reduction is best achieved at the
planning and design stage, as well as by ensuring the implementation of good
site practices. Recommendations to achieve waste reduction include: |
WSD’s Contractor |
Construction Work Sites
(General) |
During Construction works |
|
|
|
· Sort C&D material from
demolition and decommissioning of the existing facilities to recover
recyclable portions such as metals; |
|
|
|
|
|
|
· Segregation and storage of different
types of waste in different containers, skips or stockpiles to enhance reuse
or recycling of materials and their proper disposal; |
|
|
|
|
|
|
o
Encourage collection of aluminium cans by providing separate labelled bins
to enable this waste to be segregated from other general refuse generated by
the work force; |
|
|
|
|
|
|
o
Proper storage
and site practices to minimise the potential for damage or contamination of
construction materials; and |
|
|
|
|
|
|
o
Plan and stock
construction materials carefully to minimise amount of waste generated and
avoid unnecessary generation of waste. |
|
|
|
|
6.6.3 |
5.3 |
C&D
Material In order
to minimise impacts resulting from collection and transportation of C&D material
for off-site disposal, the excavated materials should be reused on-site as
backfilling material and for landscaping works as far as practicable. In addition, C&D material generated
from excavation works should be disposed of at public fill reception
facilities for other beneficial uses. Other mitigation requirements are
listed below: |
WSD’s Contractor |
Construction Work Sites
(General) |
During Construction works |
ETWB TCW No. 31/2004 |
|
|
· A Waste Management Plan should be prepared; |
|
|
|
|
|
|
· A recording system for the amount of wastes
generated, recycled and disposed (including the disposal sites) should be
proposed; and |
|
|
|
|
|
|
· In order to monitor the disposal of C&D material and
solid wastes at public filling facilities and landfills, and to control
fly-tipping, a trip-ticket system (e.g. ETWB TCW No. 31/2004) should be
included. |
|
|
|
|
6.6.4 |
5.3 |
General
Refuse General refuse should be stored in enclosed
bins or compaction units separate from C&D material. A reputable waste collector should be
employed by the contractor to remove general refuse from the site, separately
from C&D material. Preferably an
enclosed and covered area should be provided to reduce the occurrence of
'wind blown' light material. |
WSD’s Contractor |
Construction Work Sites
(General) |
During Construction works |
|
6.6.5 |
5.3 |
Chemical Waste Good quality containers compatible
with the chemical wastes should be used, and incompatible chemicals should be
stored separately. Appropriate labels
should be securely attached on each chemical waste container indicating the
corresponding chemical characteristics of the chemical waste, such as
explosive, flammable, oxidizing, irritant, toxic, harmful, corrosive,
etc. The Contractor shall use a
licensed collector to transport and dispose of the chemical wastes, to either
the approved Chemical Waste Treatment Centre, or another licensed facility. |
WSD’s Contractor |
Construction Work Sites
(General) |
During Construction works |
Code of Practice on the
Packaging, Labelling and Storage of Chemical Wastes, Waste Disposal (Chemical
Waste) (General) Regulation |
6.6.6 |
5.3 |
Marine
Dredged Sediment During transportation and disposal of
the dredged marine sediments, the following measures should be taken to
minimise potential impacts on water quality: |
WSD’s Contractor |
Construction Work Sites
(Along the alignment of dredging) |
During Marine Construction
works |
ETWB TCW No. 34/2002 |
|
|
· Bottom opening of barges shall be fitted with tight
fitting seals to prevent leakage of material. Excess material shall be cleaned
from the decks and exposed fittings of barges and dredgers before the vessel
is moved; |
|
|
|
|
|
|
· Monitoring of the barge loading shall be conducted to
ensure that loss of material does not take place during transportation. Transport barges or vessels shall be
equipped with automatic self-monitoring devices as specified by the EPD; and |
|
|
|
|
|
|
· Barges or hopper barges shall not be filled to a
level that would cause the overflow of materials or sediment laden water
during loading or transportation. |
|
|
|
|
Air Quality |
||||||
7.5.1 |
6.30 |
Dust Control Construction dust impacts
should be controlled within the 1-hour TSP criterion of 500 g/m3
and 24-hour TSP AQO of 260 g/m3.
Therefore, effective control measures and good site practices should
be implemented : |
WSD’s Contractor |
Construction Work Sites
(General |
During Construction works |
EIAO-TM and Air Pollution
Control (Construction Dust) Regulation |
|
|
·
Any excavated
dusty materials or stockpile of dusty materials should be covered entirely by
impervious sheeting or sprayed with water so as to maintain the entire
surface wet, and recovered or backfilled or reinstated within 24 hours of the
excavation or unloading; |
|
|
|
|
|
|
·
The working area
of excavation should be sprayed with water immediately before, during and
immediately after the operations so as to maintain the entire surface wet; |
|
|
|
|
|
|
· The load of dusty materials carried by vehicle
leaving a construction site should be covered entirely by clean impervious
sheeting to ensure that the dusty materials do not leak from the vehicle; |
|
|
|
|
|
|
· Where a site boundary adjoins a road, streets or
other area accessible to the public, hoarding of not less than 2.4m high from
ground level should be provided along the entire length except for a site
entrance or exit; |
|
|
|
|
|
|
· The area where vehicle washing takes place and the
section of the road between the washing facilities and the exit point should
be paved with concrete, bituminous materials or hardcores; |
|
|
|
|
|
|
· Every main haul road should be scaled with concrete
and kept clear of dusty materials or sprayed with water so as to maintain the
entire road surface wet; |
|
|
|
|
|
|
· The portion of road leading only to a construction site
that is within 30m of a designated vehicle entrance or exit should be kept
clear of dusty materials; |
|
|
|
|
|
|
· All dusty materials should be sprayed with water
prior to any loading, unloading or transfer operation so as to maintain the dusty
material wet; |
|
|
|
|
|
|
· Vehicle speed should be limited to 10 kph except on
completed access roads; and |
|
|
|
|
|
|
·
Every vehicle
should be washed to remove any dusty materials from its body and wheels
before leaving the construction sites. |
|
|
|
|
Cultural Heritage |
||||||
8.7 |
7 |
No cultural heritage
resources are identified within the Study Area and therefore, no mitigation measures
are considered necessary. |
|
|
|
|
Fisheries |
||||||
9.7 |
8 |
Impacts to fisheries
resources and fishing operations have largely been avoided during
construction through constraints on the works operations for installation of the
submarine watermain. Good construction practice and associated measures
recommended for Water Quality to control water quality impacts to within
acceptable levels and are also expected to control impacts to fisheries
resources. |
WSD’s Contractor |
Construction Work Sites
(General) |
During Marine Construction
works |
EIAO-TM |
(1)
(2) Maunsell Consultants Asia Ltd. (2001), Environmental Impact Assessment for Tai Po Sewage Treatment Works – Stage V, Final EIA Report, For Drainage Services Department, Hong Kong SAR Government.
(3) Hawker, D. W. and Connell, D. W. (1992). “Standards and Criteria for Pollution Control in Coral Reef Areas” in Connell, D. W and Hawker, D. W. (eds.), Pollution in Tropical Aquatic Systems, CRC Press, Inc.
(4) ERM Hong Kong Ltd. (2001), Environmental Impact Assessment for the Proposed submarine Gas Pipeline from Cheng Tou Jiao Liquefied Natural Gas Receiving Terminal, Shenzhen to Tai Po Gas Production Plant, Hong Kong, Final EIA Report, For the Hong Kong and China Gas Co., Ltd.
(5) EPD
(2005). Marine Water Quality in
(6) Mott MacDonald (1991). Contaminated Spoil Management Study, Final Report, Volume 1.
(7) Environmental Quality Standards and Assessment Levels for Coastal Surface Water (from HMIP (1994) Environmental Economic and BPEO Assessment Principals for Integrated Pollution Control). (Source: Environmental Impact Assessment Study for Disposal of Contaminated Mud in the East Sha Chau Marine Borrow Pit, by ERM, January 1997).
(8) ERM-Hong
Kong Ltd (1997). Environmental Impact Assessment for the Disposal of Contaminated Mud in
the
(9) Ludwig,
D.D., Sherard, J. H. And Amende, R. A. (1988).
An Evaluation of the Standard Elutriate Test as an Estimator of
Contaminant Release at the Point of Dredging.
Contract Report HL-88-1, prepared by Virginia Polytechnic Institute,
(10) Maunsell Consultants Asia Ltd (2001), Agreement No. CE 74/98, Wan Chai Development Phase II Comprehensive Feasibility Study, Final Environmental Impact Assessment Report, for Territory Development Department.
(11) Morton,
B. and Morton, J. (1983). The
(12) Environmental
Protection Department (2005). Marine Water Quality in
(13) Ibid
(14) ERM (1998). Dredging an Area of Kellett Bank for Reprovisioning of Six Government Mooring Buoys Environmental Impact Assessment. Civil Engineering Department.
(15) Maunsell
Consultants Asia Ltd. (2002).
(16) Morton, B. and Morton, J. (1983). Op cit.
(17) Morton, B. and Morton, J. (1983). Op cit.
(18) Morton, B. and Morton, J. (1983). Op cit.
(19) Environmental Resources Management (1998). Op cit.
(20) Ibid.
(21) Ibid
(22) .Morton, B. and Morton, J. (1983). Op cit.
(23) Ibid.
(24) Environmental Resources Management (1998). Op cit.
(25) Mouchel Asia Limited (2002). Maintenance Dredging for Central Fairway Phases 1, 2 & 3 Sediment Quality Report. Civil Engineering Department, Geotechnical Engineering Office HKSAR.
(26) CityU
Professional Services Limited (2002). Consultancy
Study on Marine Benthic Communities in
(27) ERM (1998). Op cit.
(28) Ibid.
(29) CityU Professional Services Limited (2002). Op cit.
(30) ERM (1998). Op cit.
(31) CityU Professional Services Limited (2002). Op cit.
(32) Binnie Consultants Limited (1994). South Cheung Chau &
(33) ERM (1998). Op cit.
(34) ERM (1998). Op cit.
(35) CityU Professional Services Limited (2002). Op cit.
(36) ERM Hong Kong Ltd (1995). Backfilling of South Tsing Yi and North of Lantau MBAs: Final Environmental Impact Assessment. Civil Engineering Department.
(37) Ibid.
(38) Babtie BMT (1997).
(39) ERM (1998). Op cit.
(40) ERM (1998). Op cit.
(41) IUCN 2006. 2006 IUCN Red List of Threatened Species. <www.iucnredlist.org>. Downloaded on
(42) UNEP-WCMC.
On the World Wide Web : http://www.unep-wcmc.org/isdb/CITES/Taxonomy/country_list.cfm?col=I&country=HK&source=animals&displaylanguage=eng
(43)
(44) AFCD
web page downloaded on
(45) AFCD (2005). Monitoring of Chinese White Dolphins (Sousa chinensis) in Hong Kong Waters.
(46) Ibid.
(47) ERM (1998). Op cit.
(48) Agriculture, Fisheries and Conservation Department (1998) Port Survey 1996/1997.
(49) Agriculture, Fisheries and Conservation Department (2006) Port Survey 2001/2002, Web site www.afcd.gov.hk.
(50) ERM (1998) Fisheries Resources and Fishing Operations in Hong Kong Waters, Final Report, for Agriculture, Fisheries and Conservation Department, March 1998
(51) Agriculture, Fisheries and Conservation Department (2006) Web site www.afcd.gov.hk
(52) ScottWilson (2001) Planning and Engineering Feasibility Study for Sham Tseng Development, EIA Final Report., for Civil Engineering Department.
(53)