Agreement No. CE 42/2005(WS)

Laying of Western Cross Harbour Main and Associated Land Mains from West Kowloon to Sai Ying Pun – Investigation

Environmental Impact Assessment Report

Document No. 226133/09/D

April 2007

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Mott Connell Ltd

40th floor, Hopewell Centre

183 Queen’s Road East

Wanchai

Hong Kong

 

Tel: 2828 5757

 

Fax: 2827 1823

 

 

 


List of Contents                                                                                               

Chapters

1          INTRODUCTION   1-1

1.1        Background  1-1

1.2        The Environmental Impact Assessment Study  1-1

1.3        The Project Area  1-3

1.4        Environmental Impact Assessment Ordinance  1-3

1.5        Documents Reviewed  1-5

2          CONSIDERATION OF ALTERNATIVES  2-1

2.1        Need for the Project 2-1

2.2        Tentative Construction Programme  2-1

2.3        Consideration of Alternative Alignment Options  2-1

2.3.1    Physical Constraints to the Alignment 2-1

2.3.2    Routing Constraints of the Alignment 2-2

2.4        Consideration of Alternative Construction Methods and Works Sequences  2-2

2.4.1    Trench Excavation  2-2

2.4.2    Submarine Pipeline Installation  2-3

2.4.3    Backfilling  2-3

2.4.4    Horizontal Directional Drilling  2-4

2.4.5    Best Practical Method  2-6

2.4.6    Sequencing and Timing  2-6

2.5        Selection of the Preferred Option  2-6

3          WATER QUALITY IMPACT ASSESSMENT   3-1

3.1        Introduction  3-1

3.2        Environmental Legislation, Standards, Guidelines and Criteria  3-1

3.2.1    Environmental Impact Assessment Ordinance (EIAO) 3-1

3.2.2    Water Quality Objectives (WQOs) 3-1

3.2.3    Technical Memorandum   3-4

3.2.4    Hong Kong Planning Standards and Guidelines (HKPSG) 3-5

3.2.5    Water Supplies Department (WSD) Water Quality Criteria  3-5

3.2.6    Practice Note  3-5

3.2.7    Suspended Solids Criterion for Fish Culture Zone  3-5

3.2.8    Suspended Solids Criterion for Benthic Organisms  3-6

3.2.9    Sediment Quality  3-6

3.3        Description of the Environment 3-6

3.3.1    Marine Water Quality Monitored by EPD   3-6

3.3.2    Sediment Quality  3-9

3.3.3    Trend of Water Quality in Victoria Harbour 3-9

3.4        Water Sensitive Receivers  3-9

3.5        Assessment Methodology  3-11

3.5.1    Hydrodynamic and Water Quality Models  3-11

3.5.2    Sediment Plume Modelling  3-12

3.5.3    Effluent, Sewage and Surface runoff 3-16

3.6        Identification of Environmental Impact 3-16

3.6.1    Construction Phase  3-16

3.6.2    Operation Phase  3-19

3.7        Prediction and Evaluation of Environmental Impacts  3-20

3.7.1    Suspended Solids  3-20

3.7.2    Dissolved Oxygen, Total Inorganic Nitrogen and Unionised Ammonia  3-23

3.7.3    Potential Contaminant Release During Dredging  3-29

3.7.4    Hydrostatic Tests of the Water Mains System   3-31

3.7.5    Surface Runoff, Sewage and Wastewater from Construction Activities  3-31

3.8        Mitigation of Adverse Environmental Impact 3-32

3.8.1    Construction Phase  3-32

3.9        Evaluation of Residual Impacts  3-35

3.10      Environmental Monitoring and Audit 3-35

3.11      Conclusions and Recommendations  3-36

3.11.1   Construction Phase  3-36

3.11.2   Operation Phase  3-36

4          MARINE ECOLOGICAL IMPACT ASSESSMENT   4-1

4.1        Introduction  4-1

4.2        Environmental Legislation, Standards, Guidelines and Criteria  4-1

4.3        Assessment Methodology  4-3

4.4        Baseline Conditions & Marine Ecological Sensitive Receivers  4-4

4.4.1    Existing Condition of Victoria Harbour 4-4

4.5        Ecological Importance  4-12

4.6        Identification and Prediction of Environmental Impacts  4-14

4.6.1    Construction Phase  4-14

4.6.2    Operational Phase  4-15

4.7        Evaluation of Environmental Impacts  4-15

4.7.1    Construction Phase  4-15

4.8        Mitigation of Adverse Environmental Impact 4-17

4.9        Evaluation of Residual Impacts  4-18

4.10      Environmental Monitoring and Audit 4-18

4.11      Conclusions and Recommendations  4-18

5          NOISE IMPACT ASSESSMENT   5-1

5.1        Introduction  5-1

5.2        Environmental Legislation, Standards, Guidelines and Criteria  5-1

5.2.1    Construction Noise  5-1

5.2.2    Area Sensitivity Ratings  5-2

5.3        Noise Sensitive Receivers  5-3

5.4        Assessment Methodology  5-4

5.4.1    Guidelines in GW-TM   5-4

5.4.2    Area Sensitive Ratings (ASRs) 5-5

5.4.3    Assessment for the Project 5-5

5.5        Identification, Prediction and Evaluation of Environmental Impacts  5-6

5.5.1    Construction Phase  5-6

5.5.2    Representative NSRs  5-8

5.5.3    Evaluation of Noise Impact 5-9

5.6        Mitigation of Adverse Environmental Impacts  5-10

5.6.1    Work Schedule Rearrangement 5-10

5.6.2    Using Quality PME  5-11

5.6.3    Using Noise Barriers  5-11

5.6.4    Good Site Practice  5-11

5.7        Evaluation of Residual Impacts  5-11

5.8        Environmental Monitoring and Audit 5-11

5.9        Conclusions and Recommendations  5-12

6          WASTE IMPACT ASSESSMENT   6-1

6.1        Introduction  6-1

6.2        Environmental Legislation, Standards, Guidelines and Criteria  6-1

6.2.1    General 6-1

6.2.2    Waste Management 6-1

6.2.3    Construction and Demolition (C&D) Materials  6-2

6.2.4    Marine Dredged Sediment 6-2

6.3        Assessment Methodology  6-3

6.3.1    General 6-3

6.3.2    Marine Site Investigation  6-3

6.3.3    Marine Dredged Sediment 6-4

6.4        Baseline Condition of Marine Dredged Sediment 6-10

6.4.1    Chemical Screening  6-10

6.4.2    Biological Screening  6-15

6.5        Identification and Evaluation of Environmental Impacts  6-15

6.5.1    Construction Phase  6-15

6.5.2    Operation Phase  6-17

6.6        Mitigation of Adverse Environmental Impacts  6-18

6.6.1    Good Site Practices  6-18

6.6.2    Waste Reduction Measures  6-18

6.6.3    C&D Material 6-18

6.6.4    General Refuse  6-19

6.6.5    Chemical Waste  6-19

6.6.6    Marine Dredged Sediment 6-19

6.7        Evaluation of Residual Impacts  6-22

6.8        Environmental Monitoring and Audit 6-22

6.9        Conclusions and Recommendations  6-22

7          AIR QUALITY IMPACT ASSESSMENT   7-1

7.1        Introduction  7-1

7.2        Environmental Legislation, Standards, Guidelines and Criteria  7-1

7.2.1    Hong Kong Air Pollution Control Ordinance  7-1

7.2.2    Air Pollution Control (Construction Dust) Regulation  7-2

7.2.3    Technical Memorandum on EIA Process (EIAO-TM), Annex 4 and 12  7-2

7.3        Baseline Conditions & Air Sensitive Receivers  7-2

7.3.1    Baseline Conditions  7-2

7.3.2    Air Sensitive Receivers  7-3

7.4        Identification and Evaluation of Air Quality Impacts  7-4

7.4.1    Construction Phase  7-4

7.4.2    Operation Phase  7-4

7.5        Mitigation of Adverse Environmental Impacts  7-4

7.5.1    Construction Phase  7-4

7.5.2    Operation Phase  7-5

7.6        Evaluation of Residual Air Quality Impacts  7-5

7.7        Environmental Monitoring and Audit 7-5

7.8        Conclusions and Recommendations  7-6

8          CULTURAL HERITAGE IMPACT ASSESSMENT   8-1

8.1        Introduction  8-1

8.2        Environmental Legislation, Standards, Guidelines and Criteria  8-1

8.2.1    Technical Memorandum on the EIA Process, Annex 10 and 19  8-1

8.2.2    Antiquities and Monuments Ordinance (Cap.53) 8-2

8.2.3    Hong Kong Planning Standards and Guidelines  8-3

8.2.4    Marine Archaeological Guidelines  8-3

8.3        Cultural Heritage Impact Assessment Methodology  8-3

8.3.1    Baseline Review   8-3

8.3.2    Geophysical Survey  8-3

8.3.3    Establishing Archaeological Potential 8-3

8.4        Baseline Conditions  8-4

8.5        Identification of Cultural Heritage Impact 8-4

8.6        Assessment of Cultural Heritage Impact 8-4

8.7        Mitigation of Adverse Environmental Impact 8-5

8.8        Evaluation of Residual Cultural Heritage Impact 8-5

8.9        Environmental Monitoring and Audit 8-5

8.10      Conclusions and Recommendations  8-5

9          FISHERIES IMPACT ASSESSMENT   9-1

9.1        Introduction  9-1

9.2        Environmental Legislation, Standards, Guidelines and Criteria  9-1

9.3        Fisheries Impact Assessment Methodology  9-1

9.4        Baseline Conditions  9-2

9.4.1    Capture Fisheries  9-2

9.4.2    Culture Fisheries  9-5

9.4.3    Fisheries Importance  9-6

9.4.4    Sensitive Receivers  9-6

9.5        Identification of Fisheries Impacts  9-6

9.5.1    Construction Phase  9-6

9.5.2    Operation Phase  9-8

9.6        Assessment of Fisheries Impacts  9-9

9.7        Mitigation of Adverse Environmental Impacts  9-9

9.8        Evaluation of Residual Fisheries Impacts  9-10

9.9        Environmental Monitoring & Audit 9-10

9.10      Conclusions and Recommendations  9-10

10        SUMMARY OF ENVIRONMENTAL OUTCOMES  10-1

10.1      Population and Environmental Sensitive Areas Protected  10-1

10.2      Environmental Friendly Designs Recommended and Problems Avoided  10-1

10.3      Environmental Benefits of the Project 10-1

11        ENVIRONMENTAL MONITORING AND AUDIT (EM&A) REQUIREMENTS  11-1

11.1      Water Quality  11-1

11.2      Marine Ecology  11-1

11.3      Noise  11-1

11.4      Waste Management 11-1

11.5      Air Quality  11-2

11.6      Cultural Heritage  11-2

11.7      Fisheries  11-2

12        CONCLUSIONS AND RECOMMENDATIONS  12-1

12.1      Water Quality  12-1

12.1.1   Construction Phase  12-1

12.1.2   Operation Phase  12-1

12.2      Marine Ecology  12-1

12.3      Noise  12-2

12.4      Waste  12-2

12.5      Air Quality  12-3

12.6      Cultural Heritage  12-3

12.7      Fisheries  12-3

13        IMPLEMENTATION SCHEDULE   13-1

 

List of Tables

Table 3‑1.... Summary of Water Quality Objectives for the Victoria Harbour WCZ. 3-2

Table 3‑2.... Summary of Water Quality Objectives for the Western Buffer WCZ. 3-3

Table 3‑3.... WSD’s Water Quality Criteria for Flushing Water at Sea Water Intakes. 3-5

Table 3‑4.... Marine Water Quality in Phases Two and Three of the Victoria Harbour Water Control Zone at Selected Stations in 2005. 3-7

Table 3‑5.... Water Quality Indicator Points. 3-10

Table 3‑6.... Summary of Parameters for Sediment Plume Model (Delft3D-WAQ) 3-12

Table 3‑7.... Sediment Quality near the Dredging Area. 3-13

Table 3‑8.... Specifications for General Fill Material and Granular Fill Material 3-14

Table 3‑9.... Depth-averaged and Surface SS levels near the Dredging Area. 3-18

Table 3‑10.. DO, TIN and NH3-N levels near the Dredging Area. 3-18

Table 3‑11.. Predicted Suspended Solids Elevations at Marine Ecology Sensitive Receivers. 3-21

Table 3‑12.. Predicted Suspended Solids Concentrations at Marine Ecology Sensitive Receivers. 3-21

Table 3‑13.. Predicted Suspended Solids Elevations at Cooling and Sea Water Intakes. 3-22

Table 3‑14.. Predicted Suspended Solids Concentrations at Cooling and Sea Water Intakes. 3-23

Table 3‑15.. Predicted Dissolved Oxygen, Total Inorganic Nitrogen and Unionised Ammonia Elevations. 3-25

Table 3‑16.. Predicted Dissolved Oxygen, Total Inorganic Nitrogen and Unionised Ammonia Concentrations  3-27

Table 3‑17.. Comparison of Marine Sediment Elutriate Test Results with Water Quality Standards. 3-30

Table 4‑1.... Typical Members of the Macrofauling Community in Wharf Piles of Hong Kong (Source: Morton, B. and Morton, J. 1983) 4-5

Table 4‑2.... Abstract of Coastal Flora and Fauna recorded in Green Island, Little Green Island and a reference site in Hong Kong Island. (Source: ERM, 1998) 4-7

Table 4‑3.... Benthic Epifauna Recorded around Green Island (Source: ERM, 1995) 4-9

Table 4‑4.... Frequency of Soft Coral and Gorgonian Colonies Recorded around Green Island (Source: ERM, 1998) 4-11

Table 4‑5.... Evaluation of the Ecological Importance of the Inter-tidal Habitats. 4-13

Table 4‑6.... Evaluation of the Ecological Importance of the Sub-tidal Habitats. 4-13

Table 4‑7.... Evaluation of the Significance of Ecological Impact 4-16

Table 5‑1.... EIAO-TM Daytime Construction Noise Standards (0700 to 1900 hours on any day not being a Sunday or public holiday) (Leq.30 min dB(A)) 5-2

Table 5‑2.... Basic Noise Levels (BNL, Leq.30 min dB(A)) 5-2

Table 5‑3.... Representative Noise Sensitive Receivers. 5-4

Table 5‑4.... Noise Emission Inventory (Sai Ying Pun) 5-7

Table 5‑5.... Noise Emission Inventory (West Kowloon) 5-8

Table 5‑6.... Selected NSRs for Noise Assessment 5-9

Table 5‑7.... Summary of Unmitigated Construction Noise Levels during Normal Daytime Working Hours  5-9

Table 5‑8.... Summary of Unmitigated Construction Noise Levels from dredging during Restricted Hours  5-9

Table 5‑9.... Summary of Mitigated Construction Noise Levels from dredging during Night time (2300 to 0700 hours) 5-11

Table 6‑1.... Coordinates, Type and Depth of Vibrocores. 6-4

Table 6‑2.... Sample Arrangement for Chemical Testing. 6-5

Table 6‑3.... Testing Methods and Reporting Limits for Metals and Metalloids Analysis. 6-7

Table 6‑4.... Testing Methods and Reporting Limits for TBT, PAHs and PCBs Analysis. 6-7

Table 6‑5.... Sediment Quality Criteria for the Classification of Sediment 6-7

Table 6‑6.... Composite Sample Arrangement for Biological Testing. 6-9

Table 6‑7.... Test Species for Biological Testing. 6-9

Table 6‑8.... Test endpoints and decision criteria for biological testing. 6-10

Table 6‑9.... Contaminant Levels of Vibrocore Samples and Their Categories. 6-11

Table 6‑10.. Summary of Classification of Vibrocore Samples. 6-15

Table 6‑11.. Summary of Ancillary Tests Results. 6-15

Table 6‑12.. Summary of Toxicity Test Failure. 6-15

Table 6‑13.. Summary of Waste Handling Procedures and Disposal Routes. 6-21

Table 7‑1.... Hong Kong Air Quality Objectives (mg/m3)(i) 7-1

Table 7‑2.... Background Air Quality (2001 – 2005) 7-3

Table 7‑3.... Representative Air Sensitive Receivers. 7-3

Table 9‑1.... Area (ha) and Number of Vessels Operating During 1996 - 1997 in Each AFCD Fishing Zone within the Study Area. 9-3

Table 9‑2.... Fisheries Production Values from each AFCD Fishing Zone within the Study Area. 9-4

Table 9‑3.... Top Five Adult Fish (by weight) Caught in Each AFCD Fishing Zone within the waters of the Study Area  9-4

List of Figures

Figure 1.1    Indicative Route of the Proposed Watermains

Figure 2.1    Physical Constraints to the Proposed Submarine Watermain

Figure 2.2    Selected Route of Proposed Submarine Watermain

Figure 2.3    Plan View, Profile and Cross Section of Proposed Submarine Watermain

Figure 2.4    Bottom Pull Method

Figure 2.5    Lay Barge Method

Figure 2.6    Float and Sink Method

Figure 2.7    Horizontal Directional Drilling (HDD) Method

Figure 3.1    Locations of EPD’s Marine Water Quality Monitoring Stations in Victoria Harbour and Western Buffer Water Control Zones

Figure 3.2    Locations of Water Sensitive Receivers and Stormwater Outfalls at Western Harbour

Figure 3.3    Extent of the Western Harbour Model Grid

Figure 3.4    Details of the Western Harbour Model Grid in the Project Area

Figure 3.5    Resolution of the Western Harbour Model Grid

Figure 3.6    Grid Refinement of the Western Harbour Model Grid

Figure 3.7a   Coastline Configuration in the Project Area

Figure 3.7b   Coastline Configuration in the Victoria Harbour

Figure 3.7c   Coastline Configuration in the vicinity of the Alignment

Figure 3.8a   Bathymetry in the Project Area

Figure 3.8b   Bathymetry in the Victoria Harbour

Figure 3.8c   Bathymetry in the vicinity of the Alignment

Figure 3.9    Typical Configuration of Silt Curtain and Silt Screen

Figure 4.1    Study Area and Sampling Locations for Marine Ecological Impact Assessment

Figure 4.2    Intertidal Habitats within the Study Area

Figure 5.1    Locations of Noise Sensitive Receivers in Sai Ying Pun

Figure 5.2    Locations of Noise Sensitive Receivers in West Kowloon

Figure 5.3    Works Area – Sai Ying Pun

Figure 5.4    Works Area – West Kowloon

Figure 5.5    Location of Night-time Dredging Zone

Figure 6.1    Longitudinal Geological Profile of Proposed Submarine Watermain Alignment

Figure 6.2    Locations of Vibrocores

Figure 6.3    Sediment Classification Plan

Figure 7.1    Locations of Air Quality Sensitive Receivers in Sai Ying Pun

Figure 8.1    Geophysical Survey Area and Seabed Features with Side Scan Sonar Track

Figure 9.1    Location of AFCD Fishing Zones in the vicinity of the Proposed Watermains

Figure 9.2    Fishing Grids within the Study Area

List of Appendices

Appendix A      EIA Study Brief No. ESB-132/2005

Appendix B      Tentative Project Programme

Appendix C1     Water Quality Modelling Results

Appendix C2     Laboratory Test Report on Elutriate Tests

Appendix D      Not Used

Appendix E       Detailed Calculations of Construction Noise Levels

Appendix F1     Vibrocore Records

Appendix F2     Laboratory Test Report on Chemical Screening

Appendix F3     Laboratory Test Report on Biological Screening

Appendix F4     Approval Letter from MFC on Dredging Rationale

Appendix G      Not Used

Appendix H      Marine Archaeological Investigation Report

 

 


1                        INTRODUCTION

1.1                   Background

In February 2006, Mott Connell Limited (MCL) was commissioned by Water Supplies Department under Agreement No. CE 42/2005(WS) to carry out the investigation and preliminary design for the “Laying of Western Cross Harbour Main and Associated Land Mains from West Kowloon to Sai Ying Pun” (The Project).

The need for the project has evolved from the requirement to provide security of water supply between Hong Kong and Kowloon. Specifically, it has been determined that 10 years’ time, two of the existing four cross-harbour pipelines transferring portable supplies to Hong Kong Island will reach their design life of 50 years. There will be increasing risk of having one cross-harbour pipeline under maintenance while another pipeline has to be taken out of service without warning.

As cross-harbour pipelines are strategically important, it is necessary to lay a new cross-harbour pipeline on the western part of the harbour for maintaining the reliability of cross-harbour water transfer to Hong Kong Island.

The primary objective of this Assignment is to study the feasibility of providing laying of this additional submarine watermain and associated land mains. The Project and the Environmental Impact Assessment (EIA) is charged with identifying alternative sites and alignments if necessary as part of the EIA study for the Project, and obtaining an Environmental Permit (EP). This Assignment requires preliminary designs, contract strategy, programmes and cost estimates to be prepared to enable the detailed design to proceed. This Environmental Impact Assessment (EIA) Report is a key milestone of the Assignment and has been prepared in conjunction with other design teams.

The route of the proposed watermains is shown in Figure 1.1. The proposed Project is to construct and operate a new western cross harbour main and associated land mains.

The scope of the proposed Project comprises the following:

(i)       approximately 2100-metre section of 1200mm nominal diameter of submarine watermain across Victoria Harbour from its connection at Lin Cheung Road in West Kowloon to the existing Sai Ying Pun Fresh Water Pumping Station in Sheung Wan (a designated project under EIA Ordinance);

(ii)           approximately 2200-metre section of 1200mm nominal diameter of associated land watermains (Not a designated project under EIA Ordinance).

1.2                   The Environmental Impact Assessment Study

The submarine watermain component (referred in Section 1.1(i) above) of the Project is a Designated Project under Schedule 2, Part 1(E3) of the Environmental Impact Assessment Ordinance (EIAO) (Cap. 499) and an Environmental Permit (EP) issued under the EIAO is required for the construction and operation of the designated project. An application (No. ESB-132/2005) for a EIA study brief under section 5(7)(a) of the EIAO was submitted by Water Supplies Department on 30 August 2005 with a project profile No. PP-258/2005 (the Project Profile). The EPD issued an EIA Study Brief No. ESB-132/2005 on 13 October 2005, detailing the requirements for carrying out and reporting the EIA study.

The purpose of the EIA study is to provide information on the nature and extent of environmental impacts arising from the construction of the proposed designated project and related activities taking place concurrently, ultimately providing information on the following:

(i)      the overall acceptability of any adverse environmental consequences that are likely to arise as a result of the proposed project;

(ii)      the conditions and requirements for the detailed design, construction and operation of the proposed project to mitigate against adverse environmental consequences wherever practicable; and

(iii)     the acceptability of residual impacts after the proposed mitigation measures are implemented.

The scope of the EIA covers the Project proposed in the Project Profile and the works and facilities mentioned in Section 1.1 above.  The EIA study addresses the key issues described below, together with any other key issues identified during the course of the EIA study and the cumulative environmental impacts of the Project, through interaction or in combination with other existing, committed, and planned and known potential developments in the vicinity of the Project:

(i)      the potential water quality and marine ecology impacts arising from the dredging, laying of pipe and backfilling works for the construction of the submarine watermain.

(ii)     the potential noise and dust impacts arising from the construction works of the Project.

(iii)    the potential impacts on sites of cultural heritage of marine archaeological deposit likely to be affected by the construction works of the Project.

(iv)    the potential fisheries impact arising from the Project.

The EIA study addressed all environmental aspects of the activities and has been based on the best and latest information available during the course of the EIA study.  The cumulative environmental impacts from the Project with other interacting projects were assessed, including details of the construction programme and methodologies.

Previously approved studies or EIA reports which are relevant to the Project were reviewed and relevant information extracted for the purpose of this EIA study.  The following study or EIA report has been referred to:

·         Proposed Submarine Gas Pipelines from Cheng Tou Jiao Liquefied Natural Gas Production Plant, Hong Kong

1.3                   The Project Area

The proposed Project covers three main areas, namely: Victoria Harbour, West Kowloon and Sai Ying Pun.

The works for Victoria Harbour (a designated project under EIA Ordinance) is envisaged to comprise an approximately 50m wide corridor across Victoria Harbour linking West Kowloon with Sai Ying Pun.

The works in West Kowloon (Not a designated project under EIA Ordinance) generally comprise the West Kowloon Reclamation Area adjacent to the Western Harbour Tunnel Toll Plaza, and are bounded by Jordan Road to its north and Lin Cheung Road to its east. The land uses in this portion include the land reserved for the West Kowloon Cultural District, the Kowloon Station Development, the Wui Cheung Road Bus Terminus, the Yau Ma Tei Public Cargo Working Area, and the Western Harbour Tunnel Toll Plaza.  The proposed 1200mm diameter fresh watermain will be laid in this portion for connection to the existing 1200mm diameter fresh watermain at the junction of Lin Cheung Road or Wui Cheung Road.

In Sai Ying Pun (Not a designated project under EIA Ordinance), the works comprise Sai Ying Pun area adjacent to Western Wholesale Food Market and is bounded by the approaches of Western Harbour Crossing Interchange.  The proposed 1200mm diameter fresh watermain will be laid in this portion for connection to the existing Sai Ying Pun Fresh Water Pumping Station situated at the junction of Water Street/Fung Mat Road.

This EIA report covers the designated project component of the Project.

1.4                   Environmental Impact Assessment Ordinance

As detailed in Section 1.2, the proposed submarine watermain is a Designated Project under Schedule 2, Part1(E3) of the EIAO (Cap. 499) and an EP issued under the EIAO is required for the construction and operation of the designated project.

To apply for an EP, an EIA must be undertaken in accordance with the requirements of the Study Brief issued by EPD on 13 October 2005, under reference No. ESB-132/2005. Reference can be made to the full requirements of the Study Brief which is contained in Appendix A. 

The EIA has been conducted in accordance with the Study Brief, the Project Profile (No. PP-258/2005) and the criteria in the relevant sections of the Technical Memorandum on the EIA Process (Environmental Impact Assessment Ordinance) (EIAO-TM). The EIA has identified, described, predicted and evaluated potential environmental impacts, mitigation measures and will consider the impacts of any feasible alternatives.

The EIA Study assessed and discussed the alternative alignments and landing points of the proposed submarine watermain, alternative construction methods and sequences, and to compare their environmental benefits and dis-benefits with the view of selecting the preferred options from the environmental perspective.

The objectives of the EIA Study as detailed in the EIA Study Brief are as follows:

(i)         to describe the Project and associated works together with the requirements for carrying out the Project;

(ii)        to identify if there are other types of Designated Projects under Part I Schedule 2 of the EIAO to be covered in the Project;

(iii)       to consider alternative alignment(s) and landing points of the submarine watermain, alternative construction method(s) and sequence(s), and to compare their environmental benefits and dis-benefits with the view of selecting the preferred options from the environmental perspective;

(iv)       to identify and describe the elements of the community and environment likely to be affected by the proposed project and/or likely to cause adverse impacts to the proposed project, including both the natural and man-made environment;

(v)        to identify and quantify emission sources and determine the significance of impacts on sensitive receivers and potential affected uses;

(vi)       to identify and quantify any potential losses or damage to flora, fauna and natural habitats and to propose measures to mitigate these impacts;

(vii)      to identify any negative impacts on fisheries and to propose measures to mitigate these impacts;

(viii)     to identify any negative impacts on sites of cultural heritage and to propose measures to mitigate these impacts;

(ix)       to propose the provision of infrastructure or mitigation measures so as to minimize pollution, visually intrusive sediment plume dispersion, environmental disturbance and nuisance during construction of the project;

(x)        to investigate the feasibility, practicability, effectiveness of the proposed mitigation measures.

(xi)       to identify, predict and evaluate the residual (i.e. after practicable mitigation) environmental impacts and the cumulative effects expected to arise during the construction phase of the project in relation to the sensitive receivers and potential affected uses;

(xii)      to identify, assess and specify methods, measures and standards, to be included in the detailed design and construction of the project which are necessary to mitigate these environmental impacts and reducing them to acceptable levels;

(xiii)     to investigate the extent of secondary environmental impacts that may arise from the proposed mitigation measures and to identify constraints associated with the mitigation measures recommended in the EIA study as well as subsequent provision of necessary modifications;

(xiv)     to design and specify the environmental monitoring and audit requirements, if required, to ensure the implementation and the effectiveness of the environmental protection and pollution control measures adopted.

1.5                   Documents Reviewed

Particular attention has been given to the following document when undertaking this EIA Study:

·         Final EIA Report, Proposed Submarine Gas Pipelines from Cheng Tou Jiao Liquefied Natural Gas Production Plant, Hong Kong

 


2                        CONSIDERATION OF ALTERNATIVES

2.1                   Need for the Project

The need for the project has evolved from the requirement to provide security of water supply between Hong Kong and Kowloon. Specifically, it has been determined that 10 years’ time, two of the existing four cross-harbour pipelines transferring portable supplies to Hong Kong Island will reach their design life of 50 years. There will be increasing risk of having one cross-harbour pipeline under maintenance while another pipeline has to be taken out of service without warning.

As cross-harbour pipelines are strategically important, it is necessary to lay a new cross-harbour pipeline on the western part of the harbour for maintaining the reliability of cross-harbour water transfer to Hong Kong Island.

2.2                   Tentative Construction Programme

The construction of the proposed Project is scheduled to commence in September 2008 for completion by May 2011. The tentative project programme is given in Appendix B.

2.3                   Consideration of Alternative Alignment Options

2.3.1             Physical Constraints to the Alignment

There are several major installations and underground structures within the study area which are considered to be physical constraints to the alignment of the proposed submarine watermain. These include:

l           Kowloon South Salt Water Pumping Station and associated existing seawater intake culvert;

l           Tunnel structure and Toll Plaza of the Western Harbour Crossing;

l           DSD's drainage culvert next to Sai Ying Pun Fresh Water Pumping Station; and

l           Proposed submarine gas main between West Kowloon and Sai Ying Pun.

The choice of landing points of the submarine watermain is limited by the locations of connection point to the existing water supply network in West Kowloon and the Fresh Water Pumping Station at Sai Ying Pun.

As shown on the Figure 2.1, the proposed submarine watermain is bounded by the Western Cross Harbour Tunnel and the proposed submarine gas main to the east. The existing seawater intake culvert for Kowloon South Salt Water Pumping Station, Yau Ma Tei Typhoon Shelter and proposed Western Kowloon Culture District development at West Kowloon and the Western AFCD Wholesale Food Market at Sai Ying Pun also affect the land availability for the landing point of the submarine watermain.  By considering the physical constraints discussed above, the most feasible landing points are at the waterfront area next to the Kowloon South Salt Water Pumping Station at West Kowloon and the waterfront area next to the existing AFCD Western Wholesale Food Market at Fung Mat Road of Sai Ying Pun, which would lead to the shortest alignment across the Victoria Harbour with the least marine traffic impact.

2.3.2             Routing Constraints of the Alignment

The submarine watermain is proposed to be laid across the Victoria Harbour at a minimum depth of approximately 6m below the dredged seabed level and to interface with land mains at the landing points in West Kowloon and Sai Ying Pun. The proposed horizontal alignment will keep a minimum separation of 50m as far as practicable from the existing or planned marine installations. As the alignment of the submarine watermain is mainly dictated by the locations of the landing points, which constraints has been illustrated and discussed in section 2.3.1, therefore, the shortest and the most feasible route for this portion is straight between the dictated landing points such that the impact on water quality be minimized and impact on marine traffic is minimal.  The alignment of submarine watermain is shown in Figure 2.2.

2.4                   Consideration of Alternative Construction Methods and Works Sequences

The methods commonly used to install submarine watermain include dredging to form the trench followed by “bottom pull”, “lay barge” or “float and sink” followed by backfilling to protect the pipeline or, “horizontal directional drilling”.

For submarine watermain installations, dredging involves the removal of marine sediments from the seabed to form the trench, into which the submarine watermain are laid by possible methods including Bottom Pull, Lay Barge or the Float and Sink Method. Backfill material will be placed on top to protect the pipeline and minimize the cross section of dredging and backfilling works. The longitudinal profile and a typical cross section of the submarine watermain are provided in Figure 2.3. Design of the cross section and the resulting amount of marine sediments to be dredged from the seabed to form the trench will be the same no matter the Bottom Pull, Lay Barge or the Float and Sink Method is adopted for submarine watermain laying. Horizontal directional drilling involves taking the pipeline directly from the start to end point by underground drilling with no surface disturbance being necessary.

An analysis of different construction methods and techniques to minimise impacts on water quality, marine ecology, fisheries and waste was carried out. Details of the analysis are presented below.

2.4.1             Trench Excavation

Dredging

Many dredging techniques, such as grab dredging, cutter suction and trailer suction dredging are available and chosen depending on the engineering, environmental and risks conditions e.g. shear strength of marine deposits, marine traffic impact etc.. As the submarine watermain will be located across the Yau Ma Tei, Central and Southern Fairway, grab dredging is selected, as cutter suction and trailer suction dredging which requires a working area of over 150m in width will result in unacceptable impact on marine traffic and are thus not feasible. Dredging by suction dredging will also produce more marine sediment by volume (due to high water content) when compared with grab dredging. Grab dredging is therefore the best practicable and feasible method to minimize dredging and dumping requirements and demand for fill sources.

Dredging can be a comparatively fast way to construct a submarine watermain and is necessary in areas where extra watermain protection is required e.g. rock armour protection. However, the potential for impacts to water quality is higher than horizontal directional drilling (HDD). The excavated sediments would require disposal off-site at a designated disposal ground.

2.4.2             Submarine Pipeline Installation

Bottom Pull Method

In the bottom pull method (Figure 2.4), pipes are joined to form pipe strings which are progressively pulled from a landfall site into a pre-dredged trench underwater by a winch set up at the landfall site at the other side of the waters until the crossing is complete. Temporary structures are to be erected on both landfall points for launching the pipe strings in a vertical S-curve to avoid overstressing the pipe strings, and for accommodating the winch system throughout the pulling operation. This method is one of the most common method for installation of medium to large diameter pipelines.

Lay Barge Method

In the lay barge method (Figure 2.5), while the work barge moves along the pipeline, the pipes are progressively added to form a string, which are hung in a catenary from at the back of the barge, and are gradually lowered into the pre-dredged trench. Due to limited capacity of work barge, additional marine plants are required to transport pipes from the shore to the work barge throughout the mainlaying operation. As the lay barge method will introduce intolerable marine traffic impact due to its long suspended pipeline at sea during the installation, this method is considered not a feasible option.

Float and Sink Method

In the float and sink method (Figure 2.6), lengths of pipe are made up into strings at a fabrication yard and these strings are launched to seabed from one of the landfall sites. These prefabricated pipe strings are temporarily stored on the seabed before towed by work barge at or below the water surface to the pre-dredged trench. By removing or filling water to the supporting buoyancy tanks, the pipe strings are sunk to its final position. Underwater welding and bolting are required under this method. This method is one of the most common method for installation of medium to large diameter pipelines.

2.4.3             Backfilling

Cover of pipeline is required to provide adequate anchor protection and to satisfy the maintenance dredging requirements of CEDD. To satisfy the above criterion, the following backfilling material can be used for the submarine pipeline trench:-

l           Marine deposit 8 m or deeper or;

l           Sand filling 5 m or deeper or;

l           Armour rock layer 4.5 m thick with a 0.3 m thick grade 75 bedding. 

Pre-dredged trench is required for the pipe laying works, storage of dredged marine deposit for trench backfilling is considered not practicable. Moreover, the overall trench depth for marine deposit backfilling will be up to 9.5 m, this will also significantly increase the quantity of contaminated mud (>30% in volume) when compared with the armour rock option. Backfilling the trench with sand will induce significant disturbance on the existing marine environment and is considered environmentally unacceptable. Armour rock option is recommended as it can provide a strong protection to the pipeline away from the anchoring damage. This option also requires the smallest pre-dredged trench which can minimize the disposal of both contaminated and uncontaminated dredged marine mud.        

2.4.4             Horizontal Directional Drilling

Horizontal Directional Drilling (HDD) (Figure 2.7) is a method which takes the pipeline directly from start to end point by underground drilling with no surface disturbance being necessary. A pilot hole will be drilled with fluid pumping down the drill pipes for lubricating and stabilising the walls of the drillhole. After the full length pilot hole is complete, the drill is replaced with a reamer which is pulled back or pushed forward in several passes to enlarge the pilot hole to the required size.  On completion of reaming, lengths of pipe are joined and pulled from one side of the landing point to the other using a bonded pull. Finally, the gap between the enlarged hole and the pipe string is grouted for fixing the pipe in position. The potential for impacts to water quality from HDD is lower than dredging as sediments on the seabed would not be disturbed. However, the drilling fluid would require treatment prior to discharge. As the risk and difficulty for recovery in the event of jamming is considered to be very high and HDD has not been used for constructing submarine watermain with size above 1200mm in diameter, this method is considered not a feasible option.

Figure 2.4    Bottom Pull Method

 

 

 

 

 

 

 

 



Figure 2.5    Lay Barge Method

 

 

 

 

 

 

 

 


Figure 2.6    Float and Sink Method

 

 

 

 

 

 

 

 


Figure 2.7    Horizontal Directional Drilling (HDD) Method

 

2.4.5             Best Practical Method

By comparing the pros and cons of the various construction methods as mentioned in Section 2.4.1 to 2.4.4, grab dredging and “bottom pull” method followed by protection of the submarine pipeline by backfilling with 4.5m thick armour rock layer with a 0.3m thick grade 75 bedding layer are the most practical construction method for the installation of the proposed submarine watermain.  The assessment results, recommendations and conclusions have been addressed in this EIA report based on the proposed construction techniques or methods.

2.4.6             Sequencing and Timing

The issue of timing and sequencing has been analysed as part of the water quality impact assessment in Section 3. Modelling has examined the impacts on water quality of undertaking the work in either the dry or wet season. For the proposed dredging works, both seasons have been examined to be acceptable in the sense that water quality, marine ecology and fisheries criteria are complied with.

2.5                   Selection of the Preferred Option

The discussions presented in Sections 2.3 and 2.4 have examined the rationale behind the selection of the preferred alignment, the preferred construction method and the issue of timing. The environmental and physical constraints have been presented along with the preferred alignment for the submarine watermain in Figure 2.2.  As can be seen from the figure the submarine watermain alignment avoids direct impacts to the coral areas. The alignment presented on Figure 2.2, therefore, represents the preferred alignment for the submarine watermain taking into account ecological, water quality and marine traffic constraints. Taking into account the examination of different alignment options a preferred alignment is presented in Figure 2.2.  By comparing the pros and cons of the various construction methods, grab dredging and “bottom pull” method followed by protection of the submarine pipeline by backfilling with 4.5m thick armour rock layer with a 0.3m thick grade 75 bedding layer are the most practical construction method for the installation of the proposed submarine watermain. This proposed alignment and construction methods for the submarine watermain have been studied in detail as part of this EIA Report.  The selection of this position was taken after a holistic review of the environmental constraints (corals), physical constraints (navigation channel) and the results of the water quality modelling exercise.

 


3                        WATER QUALITY IMPACT ASSESSMENT

3.1                   Introduction

The submarine watermain component of the Project across Victoria Harbour is a Designated Project under Schedule 2, Part 1I(E3) of the Environmental Impact Assessment Ordinance (EIAO) (Cap. 499) and an Environmental Permit (EP) issued under the EIAO is required for the construction and operation of the designated project.

In accordance with the EIA Study Brief No. ESB-132/2005, construction and operation water quality impact arising from the dredging, laying of pipe and backfilling works for the construction of the submarine watermain were assessed.

This section presents the findings of the assessment of potential water quality impacts associated with the construction and operation of the proposed submarine watermain specifically in terms of the effects in the vicinity of sensitive receivers in accordance with the requirements of the Study Brief and Annexes 6 and 14 of the Technical Memorandum on the Environmental Impact Assessment Process. Suitable mitigation measures have been recommended to minimise potential adverse impacts and to ensure the acceptability of any residual impact (that is, after mitigation).

3.2                   Environmental Legislation, Standards, Guidelines and Criteria

The criteria for evaluating water quality impacts in this EIA Study include:

·         Technical Memorandum on Environmental Impact Assessment Process (Environmental Impact Assessment Ordinance) (EIAO-TM);

·         Water Pollution Control Ordinance (WPCO);

·         Technical Memorandum on Standards for Effluents Discharged into Drainage and Sewerage Systems, Inland and Coastal Waters (TM-DSS);

·         Hong Kong Planning Standards and Guidelines (HKPSG);

·         Water Supplies Department (WSD) Water Quality Criteria; and

·         Practice Note for Professional Persons (ProPECC), Construction Site Drainage (PN 1/94).

3.2.1             Environmental Impact Assessment Ordinance (EIAO)

The proposed submarine watermain is a Designated Project under Schedule 2, Part 1 (E3) of the EIAO (Cap.499). The EIAO-TM was issued by the EPD under Section 16 of the EIAO. It specifies the assessment method and criteria that have been followed in this EIA Study.  Reference sections in the EIAO-TM provide the details of the assessment criteria and guidelines that are relevant to the water quality impact assessment, including:

·         Annex 6 Criteria for Evaluating Water Pollution; and

·         Annex 14 Guidelines for Assessment of Water Pollution.

3.2.2             Water Quality Objectives (WQOs)

The Water Pollution Control Ordinance (Cap. 358) provides the statutory framework for the protection and control of water quality in Hong Kong.  According to the Ordinance and its subsidiary legislation, Hong Kong waters are divided into ten Water Control Zones (WCZs).  Water Quality Objectives (WQOs) are stipulated for different water regimes (marine waters, inland waters, bathing beaches subzones, secondary contact recreation subzones and fish culture subzones) in the WCZs based on their beneficial uses.  The proposed submarine watermain is located within the Victoria Harbour (Phases Two and Three) WCZ. The corresponding WQOs of the assessment area including the Victoria Harbour and Western Buffer WCZs are listed in Tables 3-1 and 3-2 respectively.

Table 31     Summary of Water Quality Objectives for the Victoria Harbour WCZ

Parameters

Objectives

Sub-Zone

Offensive Odour,  Tints

Not to be present

Whole zone

Colour

Not to exceed 50 Hazen units, due to human activity

Inland waters

Visible foam, oil scum, litter

Not to be present

Whole zone

E. coli

Not to exceed 1000 per 100 mL, calculated as the geometric mean of the most recent 5 consecutive samples taken at intervals between 7 and 21 days

Inland waters

Dissolved Oxygen (DO) within 2 m of the seabed

Not less than 2.0 mg L-1 for 90% of samples

Marine waters

Depth-averaged DO

Not less than 4.0 mg L-1 for 90% of samples

Marine waters

Dissolved Oxygen

Not less than 4.0 mg L-1

Inland waters

pH

To be in the range of 6.5 - 8.5, change due to human activity not to exceed 0.2

Marine waters

 

Not to exceed the range of 6.0 - 9.0 due to human activity

Inland waters

Salinity

Change due to human activity not to exceed 10% of ambient

Whole zone

Temperature

Change due to human activity not to exceed 2 oC

Whole zone

Suspended solids

Not to raise the ambient level by 30% caused by human activity

Marine waters

 

Annual median not to exceed 25 mg L-1 due to human activity

Inland waters

Ammonia

Annual mean not to exceed 0.021 mg L-1 as unionised form

Whole zone

Nutrients

Shall not cause excessive algal growth

Marine waters

 

Annual mean depth-averaged inorganic nitrogen not to exceed 0.4 mg L-1

Marine waters

BOD5

Not to exceed 5 mg L-1

Inland waters

Chemical Oxygen Demand

Not to exceed 30 mg L-1

Inland waters

Toxic substances

Should not attain such levels as to produce significant toxic, carcinogenic, mutagenic or teratogenic effects in humans, fish or any other aquatic organisms.

Whole zone

 

Human activity should not cause a risk to any beneficial use of the aquatic environment.

Whole zone

Source: Statement of Water Quality Objectives (Victoria Harbour (Phases One, Two and Three) Water Control Zone).

Table 32     Summary of Water Quality Objectives for the Western Buffer WCZ

Parameters

Objectives

Sub-Zone

Offensive Odour,  Tints

Not to be present

Whole zone

Colour

Not to exceed 30 Hazen units, due to human activity

 

Water gathering ground subzones

 

Not to exceed 50 Hazen units, due to human activity

Inland waters

Visible foam, oil scum, litter

Not to be present

Whole zone

E. coli

Not to exceed 610 per 100 mL, calculated as the geometric mean of all samples collected in a calendar year

 

Secondary contact recreation subzones and Fish culture subzones

 

Not to exceed 180 per 100 mL, calculated as the geometric mean of all samples collected from March to October inclusive in 1 calendar year. Samples should be taken at least 3 times in 1 calendar month at intervals of between 3 and 14 days.

Recreation subzones

 

Less than 1 per 100 mL, calculated as the geometric mean of the most recent 5 consecutive samples taken at intervals between 7 and 21 days

Water gathering ground subzones

 

 

Not to exceed 1000 per 100 mL, calculated as the geometric mean of the most recent 5 consecutive samples taken at intervals between 7 and 21 days

 

Other Inland waters

Depth-averaged DO

Not less than 4.0 mg L-1 for 90% of samples

Marine waters except Fish culture subzones

Dissolved Oxygen (DO) within 2 m of the seabed

Not less than 2.0 mg L-1 for 90% of samples

Marine waters except Fish culture subzones

Depth-averaged DO

Not less than 5.0 mg L-1 for 90% of samples

 

Fish culture subzones

Dissolved Oxygen (DO) within 2 m of the seabed

Not less than 2.0 mg L-1 for 90% of samples

Fish culture subzones

Dissolved Oxygen

Not less than 4.0 mg L-1

Water gathering ground subzones and other inland waters

pH

To be in the range of 6.5 - 8.5, change due to human activity not to exceed 0.2

Marine waters

 

Not to exceed the range of 6.0 – 8.5 due to human activity

Water gathering ground subzones

 

Not to exceed the range of 6.0 - 9.0 due to human activity

Inland waters

Salinity

Change due to human activity not to exceed 10% of ambient

Whole zone

Temperature

Change due to human activity not to exceed 2 oC

Whole zone

Suspended solids

Not to raise the ambient level by 30% caused by human activity

Marine waters

 

Annual median not to exceed 20 mg L-1 due to human activity

Water gathering ground subzones

 

Annual median not to exceed 25 mg L-1 due to human activity

Inland waters

Ammonia

Annual mean not to exceed 0.021 mg L-1 as unionised form

Whole zone

Nutrients

Shall not cause excessive algal growth

Marine waters

 

Annual mean depth-averaged inorganic nitrogen not to exceed 0.4 mg L-1

Marine waters

BOD5

Not to exceed 3 mg L-1

Water gathering ground subzones

 

Not to exceed 5 mg L-1

Inland waters

Chemical Oxygen Demand

Not to exceed 15 mg L-1

Water gathering ground subzones

 

Not to exceed 30 mg L-1

Inland waters

Toxic substances

Should not attain such levels as to produce significant toxic, carcinogenic, mutagenic or teratogenic effects in humans, fish or any other aquatic organisms.

Whole zone

 

Human activity should not cause a risk to any beneficial use of the aquatic environment.

Whole zone

Source: Statement of Water Quality Objectives (Western Buffer Water Control Zone).

3.2.3             Technical Memorandum

Besides setting the WQOs, the WPCO controls effluent discharging into the WCZ through a licensing system.  A Technical Memorandum on Standards for Effluents Discharged into Drainage and Sewerage Systems, Inland and Coastal Waters (TM-DSS) was issued under Section 21 of the WPCO that gives guidance on the permissible effluent discharges based on the type of receiving waters (foul sewers, storm water drains, inland and coastal waters).  The limits control the physical, chemical and microbial quality of effluents. Sewage from the proposed construction activities should comply with the standards for effluent discharged into the foul sewers, inshore waters or marine waters of the Victoria Harbour WCZ, as shown in Table 1, Table 9a and Table 9b, respectively, of the TM-DSS.

3.2.4             Hong Kong Planning Standards and Guidelines (HKPSG)

The HKPSG, Chapter 9 (Environment), provides additional guidelines against water pollution for sensitive uses such as aquaculture and fisheries zones, bathing waters and other contact recreational waters.

3.2.5             Water Supplies Department (WSD) Water Quality Criteria

Besides the WQOs set under the WPCO, WSD have also specified a set of water quality criteria for flushing water at seawater intakes shown in Table 3-3.

Table 33     WSD’s Water Quality Criteria for Flushing Water at Sea Water Intakes

Parameter (in mg/L unless otherwise stated)

Target Limit

Colour (HU)

< 20

Turbidity (NTU)

< 10

Threshold Odour Number (odour unit)

< 100

Ammonia Nitrogen (NH3-N)

< 1

Suspended Solids (SS)

< 10

Dissolved Oxygen (DO)

> 2

5-day Biochemical Oxygen Demand (BOD5)

< 10

Synthetic Detergents

< 5

E. coli (no. per 100 mL)

< 20,000

3.2.6             Practice Note

A practice note for professional persons was issued by the EPD to provide guidelines for handling and disposal of construction site discharges.  The ProPECC PN 1/94 “Construction Site Drainage” provides good practice guidelines for dealing with ten types of discharge from a construction site.  These include surface runoff, groundwater, boring and drilling water, bentonite slurry, water for testing and sterilisation of water retaining structures and water pipes, wastewater from building construction, acid cleaning, etching and pickling wastewater, and wastewater from site facilities.  Practices given in the ProPECC PN 1/94 should be followed as far as possible during construction to minimise the water quality impact due to construction site drainage.

3.2.7             Suspended Solids Criterion for Fish Culture Zone

A general water quality protection guideline for suspended solids (SS) has been proposed by AFCD(1). The guideline requires maximum SS levels remain below 50mgL-1. This criterion has been adopted in the previous approved EIA(2).

3.2.8             Suspended Solids Criterion for Benthic Organisms

Benthic organisms, including corals, may be damaged by sediment deposition that blocks the respiratory and feeding organs of the corals.  According to Hawker and Connell (3), the sedimentation rate higher than 0.1 kg m-2 per day would introduce moderate to severe impact upon corals.  This was adopted as the assessment criterion for protecting the marine ecological sensitive receivers in this study. There are no established legislative criteria for water quality for corals. An elevation criterion of 10 mgL-1 in SS has been adopted as the critical value above which impacts to the habitat may occur, same as the previous approved EIA (4).

3.2.9             Sediment Quality

Dredged sediments destined for marine disposal are classified according to a set of regulatory guidelines with sediment quality criteria, which include organic pollutants and other toxic substances, for designation of sediments (Management of Dredged/Excavated Sediment, ETWB TCW No. 34/2002). Details on marine dredged sediment quality are presented in Section 6.

The requirements for the marine disposal of sediment is specified in the ETWB TCW No. 34/2002. Marine disposal of dredged materials is controlled under the Dumping at Sea Ordinance.

3.3                   Description of the Environment

3.3.1             Marine Water Quality Monitored by EPD

For the purpose of this EIA, the EPD marine water quality monitoring data routinely collected in the vicinity of the site, which document the water quality in the Victoria Harbour WCZ were used.  The EPD monitoring stations of most relevance (that is, in the vicinity of the location of the proposed submarine watermain) include VM5, 6, 7 and 8 as shown in Figure 3.1.  A summary of the published marine water quality monitoring data from EPD in 2005 collected at these stations is presented in Table 3-4 (5).


Table 34     Marine Water Quality in Phases Two and Three of the Victoria Harbour Water Control Zone at Selected Stations in 2005

Determinand

VM6

VM7

VM5

VM8

WPCO WQOs (in marine waters)

Temperature (oC) 

23.0

(15.9 – 27.9)

23.1

(15.8 – 28.0)

23.0

(15.9 – 27.9)

23.1

(15.6 – 27.9)

natural daily level ± 2 oC

Salinity (psu)       

31.3

(22.2 – 32.9)

30.9

(24.4 – 32.8)

31.4

(22.4 – 32.9)

31.1

(24.8 – 33.6)

natural ambient level ± 10 %

Dissolved Oxygen (mg/L)

5.5

(3.2 – 6.6)

5.6

(3.8 – 6.8)

5.5

(3.3 – 6.7)

5.8

(2.5 – 7.3)

³ 4 mg L-1

Dissolved Oxygen Bottom (mg/L)

5.3

(3.2 – 6.5)

5.4

(3.8 – 6.5)

5.3

(3.3 – 6.6)

5.6

(2.5 – 7.1)

³ 2 mg L-1

Dissolved Oxygen (% Saturation)

77

(45 – 97)

78

(54 – 104)

76

(46 – 99)

80

(35 – 110)

N/A

Dissolved Oxygen Bottom

(% Saturation)

73

(45 – 94)

75

(54 – 94)

74

(46 – 99)

78

(35 – 108)

N/A

pH

8.0

(7.6 – 8.3)

8.0

(7.6 – 8.2)

8.0

(7.6 – 8.3)

8.1

(7.7 – 8.2)

6.5 - 8.5

(± 0.2 from natural range)

Secchi Disc Depth (m)

2.1

(1.2 – 3.3)

1.8

(0.9 – 3.2)

2.1

(1.3 – 3.1)

1.9

(1.2 – 2.5)

N/A

Turbidity (NTU)

9.8

(4.7 – 15.8)

10.8

(5.6 – 19.1)

9.8

(4.8 – 16.0)

11.9

(5.3 – 27.9)

N/A

Suspended Solids (mg/L)

3.7

(0.8 – 11.0)

4.1

(1.6 – 9.8)

3.4

(0.7 – 6.6)

5.2

(1.4 – 25.0)

£ natural ambient level + 30%

5-day Biochemical Oxygen Demand (mg/L)

0.9

(0.3 – 1.6)

1.0

(0.6 – 1.9)

1.1

(0.6 – 2.4)

0.8

(0.4 – 1.7)

not applicable to marine waters

Ammonia Nitrogen (mg/L)

0.19

(0.05 – 0.27)

0.21

(0.10 – 0.41)

0.19

(0.06 – 0.30)

0.18

(0.06 – 0.56)

N/A

Unionized Ammonia (mg/L)

0.007

(0.003–0.014)

0.009

(0.004–0.023)

0.008

(0.003–0.015)

0.009

(0.002 – 0.040)

£ 0.021 mg L-1

Nitrite Nitrogen (mg/L)

0.03

(0.01 – 0.06)

0.03

(0.01 – 0.07)

0.03

(0.01 – 0.05)

0.04

(0.01 – 0.07)

N/A

Nitrate Nitrogen (mg/L)

0.16

(0.05 – 0.39)

0.19

(0.08 – 0.50)

0.15

(0.04 – 0.36)

0.18

(0.07 – 0.52)

N/A

Total Inorganic Nitrogen (mg/L)

0.38

(0.11 – 0.68)

0.43

(0.28 – 0.93)

0.37

(0.11 – 0.65)

0.34

(0.18 – 0.92)

£  0.4 mg L-1

Total Kjeldahl Nitrogen (mg/L)

0.36

(0.21 – 0.48)

0.36

(0.23 – 0.51)

0.37

(0.22 – 0.63)

0.38

(0.15 – 1.40)

N/A

Total Nitrogen (mg/L)

0.55

(0.27 – 0.83)

0.58

(0.40 – 1.03)

0.55

(0.27 – 0.82)

0.59

(0.25 – 1.56)

N/A

Ortho-phosphate (mg/L)

0.04

(0.01 – 0.05)

0.04

(0.01 – 0.05)

0.04

(0.01 – 0.06)

0.03

(0.01 – 0.07)

N/A

Total-Phosphorus (mg/L)

0.05

(0.03 – 0.07)

0.05

(0.03 – 0.07)

0.05

(0.03 – 0.09)

0.05

(0.02 – 0.23)

N/A

Silica (as SiO2) (mg/L)

0.9

(0.2 – 2.4)

1.0

(0.6 – 2.1)

0.9

(0.1 – 2.1)

1.0

(0.6 – 2.0)

N/A

Chlorophyll-a (mg/L)

2.7

(0.6 – 10.0)

2.2

(0.8 – 11.0)

2.8

(0.6 – 9.4)

2.0

(0.8 – 8.0)

N/A

E.coli (cfu/100mL)

5700

(840 – 38000)

9100

(800 – 49000)

7700

(360–57000)

4900

(220 – 190000)

not applicable to marine waters

Faecal Coliforms (cfu/100mL)

12500

(1700–91000)

20900

(2000–180000)

17000

(1100–90000)

12100

(930–730000)

N/A

Note:      

1.  Except as specified, data presented are depth-averaged results.

2.   Depth-averaged results at each station are calculated as arithmetic means of measurements at all available depths (i.e. S, M, B) except for E.coli and faecal coliforms which are geometric means.

3.   Data presented are annual arithmetic means except for E.coli and faecal coliforms which are annual geometric means.

4.   Data enclosed in brackets indicate the ranges.

5.   Shaded cells indicate non-compliance with the WQOs.

(Source: Adopted from EPD Marine Water Quality Hong Kong in 2005)


Full compliance with the WQO for depth-averaged (DA) and bottom dissolved oxygen (DO) and depth-averaged (DA) unionised ammonia (NH3-N) was achieved at VM5, 6, 7 and 8 in 2005. VM5, 6 and 8 also achieved 100% compliance with the depth-averaged total inorganic nitrogen (TIN) of WQO.

3.3.2             Sediment Quality

The results of marine sediment quality analysis from the marine site investigation along the alignment of the proposed submarine watermain were presented in Section 6. The results indicated that Category H sediment was found at 9 out of 15 vibrocoring locations due to the high contaminant levels of copper (Cu), lead (Pb), mercury (Hg) and silver (Ag) that exceed the Upper Chemical Exceedance Level (UCEL) under the current sediment classification system (ETWB TCW No. 34/2002, Management of Dredged / Excavated Sediment).

3.3.3             Trend of Water Quality in Victoria Harbour

As reported in the “Marine Water Quality in Hong Kong in 2004” issued by EPD, significant decline in Total Kjeldahl Nitrogen (TKN) and Total Nitrogen (TN) was generally observed, except at the two stations VM5 and 8. On the other hand, an increase of nitrate nitrogen (NO3-N) was detected in the western part of the harbour. An increase in DO, decreases in nutrients (TN, Total Phosphorus (TP)) and organics (5-day Biochemical Oxygen Demand (BOD5)) were also evident in the north Rambler Channel (VM14).

3.4                   Water Sensitive Receivers

Indicator points were selected within the Victoria Harbour and Western Buffer Water Control Zones, and all areas within 500m from the Project boundary to provide hydrodynamic and water quality outputs for evaluation of water quality impacts. The selected indicator points included water quality sensitive receivers and stormwater outfalls at the Western Harbour.

Water sensitive receivers that are potentially affected by the proposed Project are listed below:

·         New Yau Ma Tei Typhoon Shelter

·         Coral communities at Green Island

·         17 seawater intakes at the waterfront of Victoria Harbour

Locations of water sensitive receivers and stormwater outfalls at the Western Harbour are shown in Figure 3.2.

All the sensitive receivers and stormwater outfalls were defined as water quality monitoring points in the model to output the key water quality parameters for determination of water quality changes as a result of the construction and operation phase activities. The modelling results are presented in terms of contour plot, time series plot and table for both the dry and wet seasons in this section.

The indicator points with brief description are provided in Table 3-5.

Table 35     Water Quality Indicator Points

Location

Type

Assessment Point

Easting

Northing

New Yau Ma Tei Typhoon Shelter

Typhoon Shelter

R1

834 527.857

819 102.182

Green Island

Sensitive Receiver of Marine Ecology

R2

829 398.155

816 298.432

Green Island

Sensitive Receiver of Marine Ecology

R3

829 449.070

815 952.418

Green Island

Sensitive Receiver of Marine Ecology

R4

830 023.685

816 169.040

Green Island

Sensitive Receiver of Marine Ecology

R5

830 175.979

816 179.217

Prince Philip Dental Hospital

Seawater Intake

R6

833 437.625

816 747.640

Tsan Yuk Hospital

Seawater Intake

R7

833 461.092

816 744.773

Macau Ferry Terminal

Seawater Intake

R8

833 786.796

816 663.359

Munsey Street

Seawater Intake

R9

833 910.436

816 507.645

Harbour Building

Seawater Intake

R10

834 094.788

816 610.502

Reprovisioned Prince’s Building Group at CRIII

Cooling Water Intake

R11

834 704.000

816 447.288

Reprovisioned Hong Kong Shanghai Bank at CRIII

Cooling Water Intake

R12

835 142.292

816 076.399

Reprovisioned Queensway Government Offices, Admiralty and Police Headquarters at CRIII

Cooling Water Intake

R13

835 212.354

816 057.961

WSD Cheung Sha Wan Salt Water Pumping Station

Seawater Intake

R14

833 545.427

820 678.020

WSD Kowloon South Salt Water Pumping Station

Seawater Intake

R15‡

833 982.630

818 282.101

Kowloon Government Offices Building

Seawater Intake

R16

834 335.800

817 769.145

Canton Road Government Offices Building

Seawater Intake

R17

834 364.658

817 802.847

MTRC Cooling Mains

Seawater Intake

R18

834 443.154

817 864.202

China Ferry Terminal

Seawater Intake

R19

835 227.714

817 832.283

Hong Kong Cultural Centre

Seawater Intake

R20

835 599.125

817 115.536

Western Harbour Crossing West Kowloon Outfall

Existing Stormwater Outfall

R21‡

833 941.469

817 988.659

Western Harbour Crossing West  Kowloon Outfall

Existing Stormwater Outfall

R22

834 123.935

817 742.368

Sai Ying Pun Outfall

Existing Stormwater Outfall

R23‡

832 647.357

816 865.168

Sai Ying Pun Outfall

Existing Stormwater Outfall

R24‡

832 724.197

816 863.893

Sai Ying Pun Outfall

Existing Stormwater Outfall

R25‡

832 786.137

816 855.415

Sai Ying Pun Outfall

Existing Stormwater Outfall

R26

832 978.593

816 850.883

Shek Tong Tsui

Existing Stormwater Outfall

R27

831 581.898

816 516.015

WSD Kennedy Town Salt Water Pumping Station

Seawater Intake

R28

830 707

815 983

WSD Sheung Wan Salt Water Pumping Station

Seawater Intake

R29

833 414

816 745

Note:          These Assessment Points fall inside an area within 100m of the proposed water main.

             All other Assessment Points fall outside this area.

The Green Island coral communities are located about 2.8 km west of the proposed submarine watermain.  The coral communities may be potentially impacted during the construction of the submarine watermain due to the sedimentation of the suspended solids (SS) in the water column.

3.5                   Assessment Methodology

To assess the potential water quality impact arising from the dredging, laying of pipe and backfilling works for the construction of the submarine watermain, the sources and natures of effluent to be generated during construction were identified and their impacts were quantified where practicable. 

3.5.1             Hydrodynamic and Water Quality Models

Set-up of Hydrodynamic Model

Computer modelling was employed to assess the potential impact on water quality in Victoria Harbour and Western Buffer Water Control Zones associated with the construction of the proposed submarine watermain for different tidal conditions.  The hydrodynamic and water quality models were developed by Delft Hydraulics, namely Delft3D-FLOW and Delft3D-WAQ respectively.

In the present study, the basis for modelling of the harbour waters is the existing, validated Western Harbour Model. This model covers the relevant part of the Hong Kong waters, including the Pearl Estuary and the Dangan (Lema) Channel (Figure 3.3). The resolution of the model is between 100 and 200m in the project area (Figure 3.4 and 3.5). A locally refined domain in the project area was inserted to obtain the above-said resolution. The grid mesh was further modified to generate higher resolution (about 50 m x 100 m) in the vicinity of the proposed submarine watermain (Figure 3.6).

Coastlines and Bathymetry

The coastline configuration and bathymetry set up for the construction phase of the Project were shown in Figures 3.7 and 3.8, taking account of completed reclamation and the latest progress of the concurrent coastal developments.

Simulation Periods

The simulated periods cover a complete spring-neap tidal cycle.  The actual simulation period is preceded by a spin-up period.  Both the actual simulation period and the spin-up period originate from the Update Study and represent average tidal conditions.  The simulation periods are specified below:

spin-up dry season:      2 February 13:00 - 9 February 12:00

dry season:                 9 February 12:00 - 23 February 12:00

spin-up wet season:     19 July 04:00 - 26 July 04:00

wet season:                 26 July 04:00 - 9 August 04:00

Boundary Conditions for Water Quality Models

The initial and boundary conditions are set to zero as the excess suspended solids concentrations are modelled.

3.5.2             Sediment Plume Modelling

General

Water quality impacts would arise from dredging activities of the proposed submarine watermain that would disturb the marine bottom sediment, elevate the SS concentrations of the water column and generate sediment plume along the tidal flows.  The impact of sediment plume dispersion during the marine works was simulated by a three-dimensional Delft3D-WAQ Model. The WAQ model simulated suspended solids (SS, in mg/L), optionally subdivided over different fractions representing different sediment sources. The simulated SS represented the project related discharges only. The calculated concentrations were interpreted as excess concentrations on top of the background concentrations.

The Delft3D-WAQ model takes into account the sedimentation process by means of a settling velocity, while erosion of bed sediment, causing resuspension of sediment, is governed by a function of the bed shear stress.  The parameters adopted in the present study are summarised in Table 3-6.

Table 36     Summary of Parameters for Sediment Plume Model (Delft3D-WAQ)

Sediment Plume Model Parameters

Settling velocity

0.5mm/s

Critical shear stress for deposition

0.2N/m2

Critical shear stress for erosion

0.3N/m2

Minimum depth where deposition allowed

0.1m

Resuspension rate

30g/m2/d

The impacts in terms of DO depletion, unionised ammonia (NH3-N) and total inorganic nitrogen (TIN) would not be modelled explicitly, but estimated on the basis of the calculated sediment concentrations. This would lead to an estimated increase relative to the background of the concentrations of different contaminants, dependent on the quality of the released sediments. For TIN, it is assumed that the total nitrogen content, being ammonia content and Kjedahl-N of the sediment is transformed to TIN. For NH3-N, it is assumed that the entire nitrogen content of the bottom is transformed to ammonium and unionised ammonia. The percentage unionised ammonia is estimated on the basis of temperature, salinity and pH on the basis of the formulations used in Delft3D-WAQ (Delft3D-WAQ Technical Reference Manual, September 2005, WL | Delft Hydraulics). The estimation of the factor is worst case and different for wet and dry season. Analogously, this would lead to an estimated decrease relative to the background of the concentrations of DO, dependent on the quality of the released sediments. For DO it is assumed that the entire COD content of the sediment is transformed to DO decrease. This can be expressed as follows:

where

TIN

concentration of Total Inorganic Nitrogen (mgN/L)

SS

concentration of suspended solids (mg/L)

CSS,NH4

concentration of ammonium in suspended matter (gN/gSS)

CSS,Kj-N

concentration of Kjedahl-N in suspended matter (gN/gSS)

f(sal,temp,pH)

factor unionised ammonia (gNH3/(gNH4+gNH3)

sal

salinity (ppt)

T

temperature (Celsius)

pH

pH

DO

concentration of dissolved oxygen (mg/L)

CSS,COD

concentration of COD in suspended matter (gO/gSS)

This approach relies on worst case assumptions. Any removal of pollutants from the water phase with the sedimentation of SS and any replenishment of DO from the atmosphere is neglected.

The values used in this assessment are based on the highest EPD routine marine sediment quality monitoring data recorded at VS5 in 2005 near the dredging area and are summarised in Table 3-7.

Table 37     Sediment Quality near the Dredging Area

Parameters

Dry season

Wet season

CSS,NH4

41E-6

41E-6

CSS,Kj-N

760E-6

760E-6

f(sal,temp,pH)

0.03

0.05

sal

28

28

T

20

27

pH

7.9

7.9

CSS,COD

27E-3

27E-3

Modelling Scenario

The construction of the proposed submarine watermain from West Kowloon to Sai Ying Pun was scheduled to commence in September 2008 and complete in May 2010.  Major marine works include dredging for the submarine watermain which was scheduled to be carried out from January to mid-May 2009, while backfilling was scheduled to be undertaken from December 2009 to February 2010.

Dredging works of the Project would be undertaken by a grab dredger.  The assumptions made with regards to modelling grab dredging are as follows:

One grab dredger with a maximum production rate of 4,000 m3 per day, 7 days per week, 24 hours per day equate to a maximum rate of 0.0463 m3 s-1 during dredging operations.

For the dredging operation, a dry density of 1,300 kgm-3 has been assumed for the dredged material in deriving the figures. This figure was adopted in the Central Reclamation Phase III - Studies, Site Investigation, Design and Construction EIA study.

Spill loss during sediment dredging by a closed grab dredger was assumed to be continuous, 24 hours a day, 7 days per week.

With respect to the rate of sediment loss during dredging, the Contaminated Spoil Management Study (6) reviewed relevant literature and concluded that losses from closed-grab dredgers were estimated at 11 to 20 kg m-3 of mud removed.  Taking the upper figure of 20 kg m-3 to be conservative, the loss rate in kg s-1 was calculated based on the daily volume rate of dredging.  (Assuming a dry density for marine sediment of 1,300 kg m-3, the sediment loss during dredging is equivalent to a spill amount of approximately 1.54%).

Spilling rates for sediment dredging by a closed grab dredger were assumed to take place uniformly over the water column.

Dredging of contaminated and uncontaminated sediment was assumed be carried out at the same rate.

Granular fill (either decomposed granite or armour rock) would be used as backfilling material after the cross harbour main laying works.  As the granular fill does not contain fines material, there would be no sediment plume generation during the backfilling process and the marine water quality would not be affected.  The contractor would follow the General Specification for Civil Engineering Works and the particle size distribution of fill material specified in Clause 6.07.  The specifications for general fill material and granular fill material are reproduced in Table 3-8.

Table 38     Specifications for General Fill Material and Granular Fill Material

Type of fill material

Percentage by mass passing

Size

BS test sieve

 

200 mm

75 mm

600 mm

General fill material

100

75 – 100

N/A

Granular fill material

N/A

100

0 – 5

During dredging, a quantity of fine sediment will be lost to suspension that may be transported away from the works area, forming suspended sediment plumes. The formation and transport of sediment plumes from dredging are modelled in this Assignment.

To assess the water quality impact on the sensitive receivers during the entire duration of dredging works and along the entire alignment, load locations which represent the position of the dredger for one day was defined along the proposed alignment of the submarine watermain. The locations follow each other with a distance of 24m (with a working speed of 1m per hour) which result in 84 discharge locations along the alignment. Each location was active for one day. A simulation period of 90 days was thus given. Modelling was conducted for the complete simulation period for the dry and wet season and the spring neap cycle was repeated after every 14 days. This represents the worst case scenario as water quality impact on the sensitive receivers during the entire duration of dredging works and along the entire alignment was simulated with the maximum possible instantaneous working rate of 0.0463m3s-1. As a result, the highest possible elevation of suspended solids were predicted. This is a very conservative assumption as a grab dredger may, depending on the actual grab dredger and the sediment condition at the time of dredging, fill with water. A conservative assumption of loss rate for grab dredger of 20kgm-3 mud dredged with a corresponding sediment loss rate of 0.93kgs-1 was also adopted.

Potential Cumulative Impact

There may be other concurrent external dredging and filling projects that may impact the same areas.  An analysis of external projects, which could occur at the same time as the installation of the Western Cross Harbour Main, has found that there will be three projects that could potentially contribute to cumulative impacts. These include reclamation for Central Reclamation Phase III, dredging works for proposed Cruise Terminal at Kai Tak and reclamation for Wan Chai Development Phase II and Central Wan Chai Bypass.

Reclamation for Central Reclamation Phase III would be constructed prior to the dredging works for the submarine watermain. Dredging works for proposed Cruise Terminal at Kai Tak is remote from the Western Cross Harbour Main and will be constructed after the dredging works for the submarine watermain. Reclamation for Wan Chai Development Phase II and Central Wan Chai Bypass at North Point is remote (over 5km away) from the Western Cross Harbour Main and thus is not anticipated to cause a cumulative impact. Reclamation for Wan Chai Development Phase II and Central Wan Chai Bypass at Wan Chai and Causeway Bay is scheduled to commence after the dredging works for the submarine watermain and consequently is not expected to overlap with the dredging works of the submarine watermain. At present, therefore, there are no planned marine construction projects that could have cumulative impacts with the installation of the Western Cross Harbour Main.

Conservative Assumptions in Assessment Methodology

Quantitative uncertainties in the sediment dispersion modelling should be considered when making an evaluation of the modelling predictions.  Worst case conditions were adopted as model input to indicate the maximum extent of the potential environmental impacts.  The input data tended to be conservative to provide a margin of tolerance.  Some examples of the conservative nature of the input parameters are given below:

The dredging rate adopted for the sediment plume modelling represents the maximum production rate that could be achieved during construction.  The actual dredging rate would be less as the shallow dredge option would be adopted and lesser quantity of mud would be dredged.

A conservative assumption of sediment loss from a closed grab dredger (that is, 20 kg m-3) was adopted to generate the sediment loss rate for modelling.  This loss rate would, however, be higher than the real situation.

Contaminant Release during Dredging

The loss of sediment to suspension during dredging may have chemical effects on the receiving waters.  This is because the sediment would contain organic and chemical pollutants.  As part of the marine site investigation works for this Project, laboratory testing of sediment samples was undertaken.  A full description of the sediment quality testing and the classification of the sediment according to levels of contaminants are contained in Section 6.

An indication of the likelihood of release of heavy metals from the sediment during dredging is given by the results of the elutriate tests from the marine site investigation works.  If the contaminant levels are higher in the elutriates in comparison with the blanks (marine water from the same site), it can be concluded that the contaminants are likely to be released into the marine waters during dredging activities.  As there is no existing legislative standard or guideline for individual heavy metal contents in marine waters, the UK Water Quality Standards for Coastal Surface Water (7) were adopted as the assessment criteria.

3.5.3             Effluent, Sewage and Surface runoff

To assess the impact of the effluent from hydrostatic tests of the water mains system and sewage, wastewater and surface runoff from construction activities upon the nearby water bodies, the extent of hydrostatic tests and construction works associated with the proposed submarine watermain were reviewed and identified.  Practical water pollution control measures or mitigation proposals were subsequently recommended to ensure effluent discharged from the construction site would comply with the WPCO criteria.

3.6                   Identification of Environmental Impact

3.6.1             Construction Phase

Dredging

General

Dredging of marine sediment would be undertaken along the alignment of the proposed submarine watermain. The in-situ volume of dredged sediment for the Project was estimated to be approximately 362,000 m3 (with a bulking factor of 1.5, bulked volume of dredged sediment was estimated to be approximately 543,000 m3). The estimated volume of contaminated dredged sediment is approximately 141,333 m3 (with a bulking factor of 1.5, bulked volume of dredged sediment was estimated to be approximately 212,000 m3) (about 39% of the total dredged sediment).

Key water quality concerns during dredging include (i) dredging works that would disturb the marine bottom sediment, causing an increase in SS concentrations in the water column and forming sediment plume along the tidal flows and (ii) construction runoff and drainage, with effluents potentially contaminated with silt, oil and grease.

Potential impacts on water quality from dredging include:

·         increased suspension of sediment in the water column during dredging activities, with possible consequence of reducing DO levels and increasing nutrient levels;

·         release of previously bound organic and inorganic constituents such as heavy metals, PAHs, polychlorinated biphenyls (PCBs) and nutrients into the water column, either via suspension or by disturbance as a result of dredging activities; and

·         release of the same contaminants due to leakage and spillage as a result of poor handling and overflow from barges during dredging and transport.

Impacts would vary depending on the quantities and level of sediment contamination and the nature and locations of the WSRs. All of the above would result in deterioration of the receiving marine water quality and would have adverse effects on WSRs.

Impact of Suspended Sediment

As a result of dredging activities during the construction phase, fine sediment (less than 63 µm) would be lost to suspension.  The suspended sediment would be transported by currents to form sediment plumes, which would gradually resettle.  The impact from sediment plumes was to increase the suspended sediment concentrations, and caused non-compliance in WQO and other criteria for particular sensitive receivers.

The extent of elevation of ambient suspended sediment concentrations would determine whether or not the impact is adverse or not.  The determination of the acceptability of any elevation is based on the WQOs.  The WQO of SS is defined as being an allowable elevation of 30% above the background.  As directed in a previous study of the environmental impacts of released SS (8), the ambient value is represented by the 90th percentile of reported concentrations.

The depth-averaged and surface SS levels in 90 percentiles during dry and wet seasons are summarised in Table 3-9. These values are derived from the marine water quality monitoring results of the four EPD’s routine monitoring stations VM5, 6, 7 and 8 located near the dredging area. The SS levels recorded from 2003 to 2005 were used in this Assignment. As stipulated by the WQOs for the Victoria Harbour WCZ, the 30% allowable elevations of depth-averaged SS above the ambient were 2.6mgL-1 and 2.5mgL-1 for the dry and wet seasons, respectively. For surface SS, however, the allowable elevations were 2.6mgL-1 and 2.0mgL-1 for the dry and wet seasons, respectively. Since seawater intakes are generally located near the water surface, the ambient surface SS level of 8.6mgL-1 for dry season and 6.7 mgL-1 for wet season were added to the predicted SS elevations at these sensitive receivers for comparison against the relevant water quality criteria.

Table 39     Depth-averaged and Surface SS levels near the Dredging Area

Stations

Dry Season

Wet Season

VM5, 6, 7 and 8

Depth-averaged

Surface

Depth-averaged

Surface

Average SS (mg L-1)

5.3

4.7

5.0

4.1

90 percentile (ambient level)

8.8

8.6

8.4

6.7

30% increase above the ambient level

2.6

2.6

2.5

2.0

Impact of Dissolved Oxygen, Total Inorganic Nitrogen and Unionised Ammonia

The extent of depletion of ambient DO concentration and elevation of ambient TIN and NH3-N would determine or not the impact is adverse or not. The determination of the acceptability of any depletion or elevation is based on the WQOs. The WQO of DO, DO bottom, TIN and NH3-N are defined as being larger than or equal to 4 mgL-1, larger than or equal to 2 mgL-1, less than or equal to 0.4 mgL-1 and less than or equal to 0.021 mgL-1 respectively.

An assessment of dissolved oxygen depletion and nutrient release during dredging was made in relation to the results of the sediment plume modelling of dredging activities and the sediment quality data of the Study Area. The predicted maximum elevations in tidal and depth-averaged SS concentrations at the construction site were used to estimate the effects of increased SS concentrations on DO, TIN and NH3-N. The area in the vicinity of alignment of the proposed submarine pipeline was of particular concern. In the water quality model, it was assumed that all COD was exerted and that all TIN and NH3-N in the sediment were released to the water. These were conservative assumptions and would likely result in an over-prediction of the potential impacts.

The depth-averaged DO, TIN and NH3-N and bottom layer DO levels during dry and wet seasons are summarised in Table 3-10. To determine compliance with the water quality criteria, background water quality data were required. The average DO, TIN and NH3-N values derived from the EPD’s routine marine water quality monitoring data recorded from 2003 to 2005 at VM5, 6, 7 and 8 near the dredging area were used in the assessment. As presented in Table 3-10, the depth-averaged TIN concentration recorded during wet season does not comply with the WQO for TIN (0.4 mgL-1).

Table 310   DO, TIN and NH3-N levels near the Dredging Area

Stations

Dry Season

Wet Season

VM5, 6, 7 and 8

Depth-averaged

Bottom

Depth-averaged

Bottom

Dissolved Oxygen (mg L-1)

6.0

6.0

5.0

4.1

Total Inorganic Nitrogen (mg L-1)

0.31

-

0.43

-

Unionised Ammonia (mg L-1)

0.006

-

0.010

-

Hydrostatic Tests of the Water Mains System

Hydrostatic tests would be undertaken in accordance with Section 23.73 and 23.77 of the General Specification for Civil Engineering Works Volume 3, 1992 Edition for sterilisation of pipeline and pressure pipeline test for the submarine watermain to check for leaks or flaws. For sterilisation of pipeline, the pipeline would be completely filled with water that has been dosed with a homogeneous solution of sterilising chemicals such that the final concentration of free chlorine in the water is at least 30ppm. The water will be left in the pipeline for at least 24 hours. After the 24 hour period, the pipeline will be drained down. For pressure pipeline testing, the pipeline would be filled with potable water or seawater (a nearly incompressible liquid) and examined for leaks or permanent changes in shape with a specified test pressure. The pipeline would be tested in sections. Pressure tests would not be carried out until the fill material has been deposited and compacted over the complete length of the pipeline to be tested. Effluent from the hydrostatic test of water supply pipeworks which the volume of discharge would be 2,500m3 would be subjected to pre-treatment including dechlorination such as by physical process e.g. adsorption by activated carbon filter, or chemical process e.g. neutralisation by dechlorination agent dosing to ensure compliance with the discharge requirements stipulated in TM-DSS. Local and coastal waters may be impacted if the water for testing is allowed to discharge into the inshore waters or marine waters of the Victoria Harbour WCZ without mitigation.

Surface Runoff, Sewage and Wastewater from Construction Activities

Surface runoff from construction site may contain considerable loads of SS and contaminants during construction activities. Local and coastal waters may be impacted if the construction site run-off is allowed to discharge into the storm drains or natural drainage without mitigation. Potential water quality impact includes run-off and erosion of exposed bare soil and earth, and stockpiles.

Accumulation of solid and liquid waste such as packaging and construction materials, sewage effluent from the construction workforce, and spillage of oil, diesel or solvents by vessels and vehicles involved with the construction, if uncontrolled, would lead to deterioration in water quality.  Increased nutrient level from contaminated discharges and sewage effluent would also lead to secondary water quality impacts including decrease in DO concentrations and localised increase in NH3-N concentrations which would stimulate algal growth.

Sewage would arise from sanitary facilities provided for the on-site construction work force which would be characterised by high levels of BOD, NH3-N and E. coli. 

3.6.2             Operation Phase

No maintenance dredging is required for the future operation of the proposed submarine watermain. There would be no hydrodynamic impact as the operation of the submarine watermain would not involve reclamation or filling that would affect the flow volume within Victoria Harbour.

There would also be no water quality impact during the operation phase of the submarine watermain as no effluent would be discharged due to operation of the submarine watermain.

3.7                   Prediction and Evaluation of Environmental Impacts

3.7.1             Suspended Solids

Water quality impact on the sensitive receivers during the entire duration of dredging works and along the entire alignment was simulated with the maximum possible instantaneous working rate of 0.0463m3s-1for two typical spring neap tidal cycles during dry and wet seasons in Hong Kong. Absolute maximum depth averaged and surface SS concentrations for the complete simulation period at each WSR, taking into account the ambient SS concentration, are presented for all scenarios.

The predicted suspended solids elevations and concentrations for all scenarios in dry and wet seasons at marine ecology sensitive receivers and the cooling and seawater intakes are presented in Tables 3-11 to 3-14 respectively. The results indicated exceedance of WSD water quality (SS) criterion at WSD Seawater Intake at Kowloon South Salt Water Pumping Station. Mitigation measure is therefore required to minimise the impact.

The contours presented in FiguresC3.1b and 3.1c in Appendix C showed the extent of tidal averaged surface SS elevations over the complete simulation period during dry and wet seasons, respectively. As shown in these figures, the extent of SS impact appeared to be confined near the dredging location at West Kowloon and Sai Ying Pun. Temporal variations of surface SS elevations at various WSRs during dry and wet seasons are shown in FiguresC3.1e to t.

The contours presented in FigureC3.1d in Appendix C showed the predicted net sedimentation per metre square per day during dry and wet seasons, respectively. Both figures indicated that the sedimentation rates were highest at waters along the coast of West Kowloon and Sai Ying Pun. The sedimentation rate at Green Island, where coral communities are located, will be much lower than 0.1 kg m-2 per day. Thus, dredging works near West Kowloon and Sai Ying Pun will have negligible impact upon the coral communities at waters near Green Island.


Table 311   Predicted Suspended Solids Elevations at Marine Ecology Sensitive Receivers

Sensitive Receivers

Assessment

SS Criterion

Maximum SS Elevation

 

Point

(mgL-1)

Dry Season

 

Wet Season

 

 

 

 

Depth averaged (mgL-1)

Surface layer (mgL-1)

Depth averaged (mgL-1)

Surface layer (mgL-1)

Typhoon Shelter

 

 

 

 

 

 

New Yau Ma Tei Typhoon Shelter

R1

-

0

0

0.1

0

Marine Ecology Sensitive Receivers

 

 

 

 

 

 

Green Island

R2

Elevation <10

0.1

0.1

0

0

Green Island

R3

Elevation <10

0.1

0.1

0

0

Green Island

R4

Elevation <10

0.2

0.2

0

0

Green Island

R5

Elevation <10

0.2

0.2

0

0

-          Values in Bold indicates exceedance of relevant criteria

Table 312   Predicted Suspended Solids Concentrations at Marine Ecology Sensitive Receivers

Sensitive Receivers

Assessment

SS Criterion

Maximum(1) SS Concentration

 

Point

(mgL-1)

Dry Season

 

Wet Season

 

 

 

 

Depth averaged (mgL-1)

Surface layer (mgL-1)

Depth averaged (mgL-1)

Surface layer (mgL-1)

Typhoon Shelter

 

 

 

 

 

 

New Yau Ma Tei Typhoon Shelter

R1

-

8.8

8.6

8.5

6.8

Marine Ecology Sensitive Receivers

 

 

 

 

 

 

Green Island

R2

-

8.9

8.7

8.4

6.7

Green Island

R3

-

8.9

8.7

8.4

6.7

Green Island

R4

-

9.0

8.8

8.4

6.7

Green Island

R5

-

9.0

8.7

8.4

6.7

-          Values in Bold indicates exceedance of relevant criteria

(1) SS concentration include the ambient SS levels presented in Table 3.9 plus the SS elevation predicted in Table 3.11.


Table 313   Predicted Suspended Solids Elevations at Cooling and Sea Water Intakes

Sensitive Receivers

Maximum SS elevation in surface layer (mgL-1)

 

Assessment Point

SS Criterion (mgL-1)

Dry Season

Wet Season

Cooling Water Intakes

 

 

 

 

Reprovisioned Prince’s Building Group at CRIII

R11

-

0.8

0.4

Reprovisioned Hong Kong Shanghai Bank at CRIII

R12

-

0.2

0.1

Reprovisioned Queensway Government Offices, Admiralty and Police Headquarters at CRIII

R13

-

0.3

0.1

WSD Seawater Intakes

 

 

 

 

Cheung Sha Wan Salt Water Pumping Station

R14

-

0

0

Kowloon South Salt Water Pumping Station

R15

-

13.0

9.1

Kennedy Town Salt Water Pumping Station

R28

-

0

0

Sheung Wan Salt Water Pumping Station

R29

-

1.2

1.4

 

Prince Philip Dental Hospital

R6

-

1.2

1.4

Tsan Yuk Hospital

R7

-

1.2

1.4

Macau Ferry Terminal

R8

-

1.1

1.1

Munsey Street

R9

-

1.0

0.7

Harbour Building

R10

-

0.9

0.6

Kowloon Government Offices Building

R16

-

1.2

0.4

Canton Road Government Offices Building

R17

-

1.0

0.3

MTRC Cooling Mains

R18

-

0.6

0.1

China Ferry Terminal

R19

-

0

0

Hong Kong Cultural Centre

R20

-

0.6

0.3

- Values in Bold indicates exceedance of relevant criteria.

Table 314   Predicted Suspended Solids Concentrations at Cooling and Sea Water Intakes

Sensitive Receivers

Maximum (1) SS concentration in surface layer (mgL-1)

 

Assessment Point

SS Criterion (mgL-1)

Dry Season

Wet Season

Cooling Water Intakes

 

 

 

 

Reprovisioned Prince’s Building Group at CRIII

R11

-

9.4

7.1

Reprovisioned Hong Kong Shanghai Bank at CRIII

R12

-

8.8

6.8

Reprovisioned Queensway Government Offices, Admiralty and Police Headquarters at CRIII

R13

<40

8.9

6.8

WSD Seawater Intakes

 

 

 

 

Cheung Sha Wan Salt Water Pumping Station

R14

<10

8.6

6.7

Kowloon South Salt Water Pumping Station

R15

<10

21.6

15.8

Kennedy Town Salt Water Pumping Station

R28

<10

8.6

6.7

Sheung Wan Salt Water Pumping Station

R29

<10

9.8

8.1

 

Prince Philip Dental Hospital

R6

<10

9.8

8.1

Tsan Yuk Hospital

R7

<10

9.8

8.1

Macau Ferry Terminal

R8

<10

9.7

7.8

Munsey Street

R9

<10

9.6

7.4

Harbour Building

R10

<10

9.5

7.3

Kowloon Government Offices Building

R16

<10

9.8

7.1

Canton Road Government Offices Building

R17

<10

9.6

7.0

MTRC Cooling Mains

R18

<10

9.2

6.8

China Ferry Terminal

R19

<10

8.6

6.7

Hong Kong Cultural Centre

R20

<10

9.2

7.0

- Values in Bold indicates exceedance of relevant criteria.

(1) Absolute value of SS includes the ambient SS level presented in Table 3.9 plus the SS elevations predicted in Table 3.13.

3.7.2             Dissolved Oxygen, Total Inorganic Nitrogen and Unionised Ammonia

The predicted depth-averaged and bottom layer dissolved oxygen, total inorganic nitrogen and unionised ammonia elevations and concentrations for all scenarios in dry and wet seasons at marine ecology sensitive receivers and the cooling and seawater intakes are presented in Tables 3-15 and 3-16. The results in Table 3-16 indicated that TIN exceedance was recorded at all assessment points during wet season. As discussed previously, the ambient TIN level near the dredging area during wet season did not comply with the WQO for TIN.

The contours presented in FiguresC3.2a, b and c, 3.3a and, 3.4a in Appendix C showed the extent of tidal and depth-averaged DO depletion, DO depletion at bottom layer and TIN and NH3-N elevations over a spring-neap cycle during dry and wet seasons, respectively. As shown in these figures, the extent of DO, TIN and NH3-N impact appeared to be confined near the dredging location at West Kowloon and Sai Ying Pun. Temporal variations of DO depletion, TIN and NH3-N elevations at various WSRs during dry and wet seasons are shown in FiguresC3.2d to s, C3.3d to s and C3.4d to s respectively.

As presented in Table 3-15, with the maximum decrease in DO predicted to be 0.696mgL-1 at R15 during dry season and maximum increase in TIN and NH3-N predicted to be 0.0166mgL-1 and 0.0017mgL-1 respectively at R15 during dry season, the impact of decrease in DO and increase in TIN and NH3-N is considered trivial, Implication of algal bloom and red tide is therefore minimal and mitigation measure is therefore not required.


Table 315   Predicted Dissolved Oxygen, Total Inorganic Nitrogen and Unionised Ammonia Elevations

Sensitive Receivers

Assessment Point

Maximum Depth-averaged DO depletion (mgL-1)

Maximum DO depletion at bottom layer   (mgL-1)

Maximum TIN elevation

(mgL-1)

Maximum NH3-N elevation (mgL-1)

 

 

Dry Season

Wet Season

Dry Season

Wet Season

Dry Season

Wet Season

Dry Season

Wet Season

Typhoon Shelter

 

 

 

 

 

 

 

 

 

New Yau Ma Tei Typhoon Shelter

R1

0

0

0

0.01

0

0.0001

0

0

Marine Ecology Sensitive Receivers

 

 

 

 

 

 

 

 

 

Green Island

R2

0

0

0.01

0

0.0001

0

0

0

Green Island

R3

0

0

0

0

0.0001

0

0

0

Green Island

R4

0

0

0.01

0

0.0001

0

0

0

Green Island

R5

0.01

0

0.01

0

0.0002

0

0

0

Cooling Water Intakes

 

 

 

 

 

 

 

 

 

Reprovisioned Prince’s Building Group at CRIII

R11

0.03

0.02

0.04

0.03

0.0008

0.0005

0.0001

0

Reprovisioned Hong Kong Shanghai Bank at CRIII

R12

0.01

0.01

0.01

0.02

0.0003

0.0002

0

0

Reprovisioned Queensway Government Offices, Admiralty and Police Headquarters at CRIII

R13

0.01

0.01

0.01

0.02

0.0003

0.0002

0

0

WSD Seawater Intakes

 

 

 

 

 

 

 

 

 

Cheung Sha Wan Salt Water Pumping Station

R14

0

0

0

0

0

0

0

0

Kowloon South Salt Water Pumping Station

R15

0.56

0.33

0.69

0.61

0.0166

0.0099

0.0017

0.0005

Kennedy Town Salt Water Pumping Station

R28

0

0

0

0

0

0

0

0

Sheung Wan Salt Water Pumping Station

R29

0.06

0.05

0.12

0.10

0.0019

0.0015

0.0002

0.0001

Other Seawater Intakes

 

 

 

 

 

 

 

 

 

Prince Philip Dental Hospital

R6

0.06

0.05

0.12

0.10

0.0019

0.0015

0.0002

0.0001

Tsan Yuk Hospital

R7

0.06

0.05

0.12

0.10

0.0019

0.0015

0.0002

0.0001

Macau Ferry Terminal

R8

0.05

0.04

0.10

0.09

0.0016

0.0012

0.0002

0.0001

Munsey Street

R9

0.04

0.03

0.05

0.05

0.0011

0.0009

0.0001

0

Harbour Building

R10

0.04

0.03

0.06

0.06

0.0011

0.0010

0.0001

0

Kowloon Government Offices Building

R16

0.05

0.01

0.06

0.05

0.0014

0.0004

0.0001

0

Canton Road Government Offices Building

R17

0.04

0.01

0.05

0.03

0.0012

0.0003

0.0001

0

MTRC Cooling Mains

R18

0.03

0.01

0.04

0.02

0.0008

0.0003

0.0001

0

China Ferry Terminal

R19

0

0

0.01

0.01

0.0001

0.0001

0

0

Hong Kong Cultural Centre

R20

0.02

0.02

0.03

0.04

0.0007

0.0005

0.0001

0

- Values in Bold indicates exceedance of relevant criteria.

Table 316   Predicted Dissolved Oxygen, Total Inorganic Nitrogen and Unionised Ammonia Concentrations

Sensitive Receivers

Assessment Point

Minimum Depth-averaged DO level (mgL-1)

Minimum DO level at bottom layer   (mgL-1)

Maximum TIN concentration

(mgL-1)

Maximum NH3-N concentration (mgL-1)

 

 

Dry Season

Wet Season

Dry Season

Wet Season

Dry Season

Wet Season

Dry Season

Wet Season

Typhoon Shelter

 

 

 

 

 

 

 

 

 

New Yau Ma Tei Typhoon Shelter

R1

6.00

5.10

6.00

4.69

0.3100

0.4301

0.0060

0.0100

Marine Ecology Sensitive Receivers

 

 

 

 

 

 

 

 

 

Green Island

R2

6.00

5.10

5.99

4.70

0.3101

0.4300

0.0060

0.0100

Green Island

R3

6.00

5.10

6.00

4.70

0.3101

0.4300

0.0060

0.0100

Green Island

R4

6.00

5.10

5.99

4.70

0.3101

0.4300

0.0060

0.0100

Green Island

R5

5.99

5.10

5.99

4.70

0.3102

0.4300

0.0060

0.0100

Cooling Water Intakes

 

 

 

 

 

 

 

 

 

Reprovisioned Prince’s Building Group at CRIII

R11

5.97

5.08

5.96

4.67

0.3108

0.4305

0.0061

0.0100

Reprovisioned Hong Kong Shanghai Bank at CRIII

R12

5.99

5.09

5.99

4.68

0.3103

0.4302

0.0060

0.0100

Reprovisioned Queensway Government Offices, Admiralty and Police Headquarters at CRIII

R13

5.99

5.09

5.99

4.68

0.3103

0.4302

0.0060

0.0100

WSD Seawater Intakes

 

 

 

 

 

 

 

 

 

Cheung Sha Wan Salt Water Pumping Station

R14

6.00

5.10

6.00

4.70

0.3100

0.4300

0.0060

0.0100

Kowloon South Salt Water Pumping Station

R15

5.44

4.77

5.31

4.09

0.3266

0.4399

0.0077

0.0105

Kennedy Town Salt Water Pumping Station

R28

6.00

5.10

6.00

4.70

0.3100

0.4300

0.0060

0.0100

Sheung Wan Salt Water Pumping Station

R29

5.94

5.05

5.88

4.60

0.3119

0.4315

0.0062

0.0101

Other Seawater Intakes

 

 

 

 

 

 

 

 

 

Prince Philip Dental Hospital

R6

5.94

5.05

5.88

4.60

0.3119

0.4315

0.0062

0.0101

Tsan Yuk Hospital

R7

5.94

5.05

5.88

4.60

0.3119

0.4315

0.0062

0.0101

Macau Ferry Terminal

R8

5.95

5.06

5.90

4.61

0.3116

0.4312

0.0062

0.0101

Munsey Street

R9

5.96

5.07

5.95

4.65

0.3111

0.4309

0.0061

0.0100

Harbour Building

R10

5.96

5.07

5.94

4.64

0.3111

0.4310

0.0061

0.0100

Kowloon Government Offices Building

R16

5.95

5.09

5.94

4.65

0.3114

0.4304

0.0061

0.0100

Canton Road Government Offices Building

R17

5.96

5.09

5.95

4.67

0.3112

0.4303

0.0061

0.0100

MTRC Cooling Mains

R18

5.97

5.09

5.96

4.68

0.3108

0.4303

0.0061

0.0100

China Ferry Terminal

R19

6.00

5.10

5.99

4.69

0.3101

0.4301

0.0060

0.0100

Hong Kong Cultural Centre

R20

5.98

5.08

5.97

4.66

0.3107

0.4305

0.0061

0.0100

- Values in Bold indicate exceedance of relevant criteria.

(1)  DO, TIN and NH3-N concentrations include the ambient levels presented in Table 3.10 plus the DO and TIN and NH3-N elevations predicted in Table 3.15.

 


3.7.3             Potential Contaminant Release During Dredging

The extent of marine sediment contamination along the alignment of the proposed cross harbour main was reported in Section 6.  Fifteen vibrocore samples as shown in Figure 6.1 were collected during the marine site investigation conducted in September 2006.  The contaminant levels of vibrocore samples and their classifications under the definitions of ETWB TCW No. 34/2002 are presented in Table 6-9. The results indicated that high level of contamination in terms of arsenic (As), copper (Cu), lead (Pb), mercury (Hg), silver (Ag), polyaromatic hydrocarbons (PAHs) and polychlorinated biphenols (PCBs) were found essentially at a number of vibrocore samples.

These contaminants pose a higher risk of water quality impact as they would be released into the marine water when the sediment was disturbed during dredging.  Thus, the elutriate tests of these parameters with sediment samples collected at all vibrocores were conducted.  The tests provided an indication of the likelihood of release of heavy metals from the marine mud during dredging.  The elutriate tests result was considered as rough estimation of the contaminant release at the point of dredging (9). The results are summarised in Table 3-17.

Table 317   Comparison of Marine Sediment Elutriate Test Results with Water Quality Standards

Vibrocore No.

Metal Content (µgL-1)

 

LMW PAHs (µgL-1)

HMW PAHs (µgL-1)

Total PCBs (µgL-1)

 

As

Cu

Pb

Hg

Ag

 

 

 

VC1a

71

<1

8.1

<0.1

<1

<0.2

<0.2

<0.01

VC2a

15

<1

1.1

<0.1

<1

<0.2

<0.2

<0.01

VC3a

33

1.1

1

<0.1

<1

<0.2

<0.2

<0.01

VC4a

1.1

2.9

<1

<0.1

<1

<0.2

<0.2

<0.01

VC5a

9.6

2.7

<1

<0.1

<1

<0.2

<0.2

<0.01

VC6a

<1

1

<1

<0.1

<1

<0.2

<0.2

<0.01

VC7a

15

1.6

1.9

<0.1

<1

<0.2

<0.2

<0.01

VC8a

4.1

1.2

<1

<0.1

<1

<0.2

<0.2

<0.01

VC9a

2.4

1.7

<1

<0.1

<1

<0.2

<0.2

<0.01

VC10a

1.7

3.1

<1

<0.1

<1

<0.2

<0.2

<0.01

VC11a

<1

1.1

<1

<0.1

<1

<0.2

<0.2

<0.01

VC12a

<1

<1

<1

<0.1

<1

<0.2

<0.2

<0.01

VC13a

1.6

4.9

1.8

<0.1

<1

<0.2

<0.2

<0.01

VC14a

3.9

<1

<1

<0.1

<1

<0.2

<0.2

<0.01

VC15a

6.3

<1

1.1

<0.1

2.7

<0.2

<0.2

<0.01

Water Quality Standard

25(3)

5(1)

25(1)

0.3(1)

2.3(1)

3.0(2)

3.0(2)

0.03(4)

Note: Values in bold indicates exceedance of Water Quality Standard

(1)     UK Water Quality Standard

(2)     Australian and New Zealand Guidelines for Fresh and Marine Waters

(3)     Environmental Economic and BPEO Assessment Principals for Integrated Pollution Control

(4)     USEPA Salt Water Criterion


As shown in Table 3-17, the As, Cu, Pb, Hg, Ag, PAHs and PCBs content in the elutriate samples fall within the UK Water Quality Standard, Australian and New Zealand Guidelines for Fresh and Marine Waters, Environmental Economic and BPEO Assessment Principals for Integrated Pollution Control and USEPA Salt Water Criterion respectively except for As at VC1a and 3a and Ag at VC15a.

Based on the detected highest concentrations for As, the required dilution to meet the relevant water quality standard was calculated to be 2.8. To estimate the extent of the mixing zone, conservative estimation of the required dilution factor was conducted. Although elevation of suspended solids in bottom layer is not a hundred percent representative of contaminant release, suspended solids in bottom layer represents a very conservative estimation of contaminant release. As shown in Figures C3.1b and c in Appendix C where the predicted maximum elevation of suspended solids in dry and wet seasons at the bottom layer were presented, about 3 times dilution could be achieved in a mixing zone of approximately 400m. As water quality sensitive receivers were not identified within the mixing zone of 400m, adverse water quality impacts are therefore not anticipated. Moreover, it is expected that any release of heavy metals during dredging will be quickly diluted by the large volume of marine water within the construction site. The release of pollutants will also be minimised by the use of closed grab dredger and the dispersion of pollutants will be confined within the construction site by the silt curtains (Section 3.8.1). Thus, it is considered that long-term off-site water quality impact is unlikely and any local water quality impact will be transient and localised.

3.7.4             Hydrostatic Tests of the Water Mains System

Effluent from the hydrostatic tests of water supply pipeworks which the volume of discharge would be 2,500m3 would be subjected to pre-treatment including dechlorination such as by physical process e.g. adsorption by activated carbon filter, or chemical process e.g. neutralisation by dechlorination agent dosing to ensure compliance with the discharge requirements stipulated in TM-DSS . High SS concentration in marine water would lead to associated reduction in DO levels. Proper practice and good management should be strictly followed to prevent water with high level SS from entering the surrounding waters. With the implementation of appropriate measures to control water discharge from hydrostatic test, disturbance of water bodies would be localised and deterioration in water quality would be minimal. Effluent from hydrostatic tests would comply with the standards for effluent discharged into the inshore waters or marine waters of the Victoria Harbour WCZ as shown in Tables 9a and 9b of the TM-DSS and Sections 23.73 and 23.77 of the General Specification for Civil Engineering Works Volume 3, 1992 Edition provided the recommended mitigation measures detailed in Section 3.8 were properly implemented.

3.7.5             Surface Runoff, Sewage and Wastewater from Construction Activities

Construction run-off would cause physical, chemical and biological effects.  The physical effects would arise from any increase in SS from the construction site that blocks drainage channels and causes local flooding when heavy rainfall occurs.  High SS concentrations in marine water would also lead to associated reduction in DO levels.

Proper site practice and good site management should be strictly followed to prevent run-off water with high level of SS from entering the surrounding waters.  With the implementation of appropriate measures to control run-off from the construction site, disturbance of water bodies would be localised and deterioration in water quality would be minimal.  Unacceptable impacts on the water quality were not expected provided that the recommended measures described in Sections 3.8 were properly implemented.

Provided that good construction practices are observed to ensure that litter, fuels, and solvents are managed, stored and handled properly, effects on water quality from general construction activities would be minimal.

Based on the Sewerage Manual, Part I, 1995 of the Drainage Services Department (DSD), the global unit flow factor for employed population of 0.06 m3 per worker per day and commercial activities in year 2012 of 0.29 m3 per worker per day were used to estimate the sewage generation from the construction site. The total sewage production rate was estimated at 0.35 m3 per worker per day. With every 100 construction workers working simultaneously at the construction site, a total of about 35 m3 of sewage would be generated per day.  The sewage should not be allowed to discharge directly into the surrounding water body without treatment. Chemical toilets and subsequently on-site sewer should be deployed at the construction site to collect and handle sewage from workers.

3.8                   Mitigation of Adverse Environmental Impact

3.8.1             Construction Phase

Specific Mitigation Measures for dredging

Exceedances of WSD Seawater Intake criterion (10 mg L-1) at Kowloon South Salt Water Pumping Station was predicted during both dry and wet seasons if dredging was undertaken near West Kowloon. To minimise the potential SS impact, implementation of the following mitigation measures is recommended:

·         Dredging should be undertaken using one grab dredger only with a maximum production rate of 4,000m3 per day;

·         Deployment of frame type silt curtain to fully enclose the grab while dredging works are in progress;

·         Deployment of silt screen at the sea water intake at Kowloon South Salt Water Pumping Station while dredging works are in progress.  

The frame type silt curtain should be designed to enclose local pollution caused by the grab dredger and suspended by a steel frame mounted on the grab dredger and floating on water. This frame type silt curtain should be fabricated from permeable, durable, abrasion resistant membrane like geotextiles and be mounted on a floating boom structure. The frame type silt curtain should also extend to the seabed to cover the entire water column. Steel chain or ballast should be attached to the bottom of the silt curtain. Mid-ballast may be added as necessary. The structure of the silt curtain should be maintained by metal grids. The frame type silt curtain should be capable or reducing sediment loss to outside by a factor of 4 (or about 75% (10). Silt screen is recommended for dredging near the seawater intake at Kowloon South Salt Water Pumping Station. The implementation of silt screen at the intake could reduce the SS level by a factor of 2.5 (or about 60%) (10). These SS reduction factors have been adopted in the Wan Chai Development Phase II Environmental Impact Assessment Study in 2001. An illustration of a typical configuration of frame type silt curtain and silt screen at seawater intake is shown in Figure 3.9.

Table 3‑18   Predicted SS concentration at the WSD Seawater Intake after implementation of frame type silt curtain and silt screen at the intake

WSD Sea Water Intake

SS Criterion (mgL-1)

SS elevation in surface layer (mgL-1)

SS concentration in surface layer (mgL-1) (1)

Dry Season

Wet Season

Dry Season

Wet Season

Kowloon South Salt Water Pumping Station

<10

1.3

0.9

9.9

7.6

(1) SS concentration includes the ambient SS level (8.6 mg L-1 for dry season and 6.7 mg L-1 for wet season) in the surface layer of water column

Table 3-18 summarises the predicted SS concentration at WSD Sea Water Intake at Kowloon South Salt Water Pumping Station after implementation of frame type silt curtain and silt screen at the sea water intake at Kowloon South Salt Water Pumping Station. With the implementation of frame type silt curtain and silt screen at sea water intake at Kowloon South Salt Water Pumping Station, the impacted WSD Seawater Intake at Kowloon South Salt Water Pumping Station will comply with the relevant SS criterion (10 mg L-1) during both the dry and wet season. Further mitigation measures were considered not necessary.

Other Mitigation Measures for dredging

Good site practice that should be undertaken during dredging includes:

·         Tight-closing grabs should be used to minimize the loss of sediment to suspension during dredging works.  For dredging of any contaminated mud, closed watertight grabs must be used;

·         all vessels should be sized so that adequate clearance is maintained between vessels and the seabed in all tide conditions, to ensure that undue turbidity is not generated by turbulence from vessel movement or propeller wash;

·         the decks of all vessels should be kept tidy and free of oil or other substances that might be accidentally or otherwise washed overboard;

·         adequate free board shall be maintained on barges to ensure that decks are not washed by wave action;

·         all barges used for the transport of dredged materials should be fitted with tight bottom seals to prevent leakage of material during loading and transport;

·         construction activities should not cause foam, oil, grease, scum, litter or other objectionable matter to be present in the water within the site or dumping grounds;

·         loading of barges should be controlled to prevent splashing of material into the surrounding waters.  Barges should not be filled to a level that would cause the overflow of materials or sediment laden water during loading or transportation;

·         the speed of vessels should be controlled within the works area to prevent propeller wash from stirring up the seabed sediments; and

·         before commencement of dredging works, the holder of the Environmental Permit should submit detailed proposal of the design and arrangement of the frame type silt curtain to EPD for approval.

Effluent from Hydrostatic Tests of the Water Mains System

To ensure compliance with the standards for effluent discharged into the inshore waters or marine waters of Victoria Harbour WCZ as shown in Tables 9a and 9b of the TM-DSS and Section 23.73 and 23.77 of the General Specification for Civil Engineering Works Volume 3, 1992 Edition, sedimentation tanks with sufficient capacity, constructed from pre-formed individual cells of approximately 6 to 8 m3 capacities, are recommended as a general mitigation measure which can be used for settling the effluent prior to disposal.  The system capacity should be flexible and suited to applications where the influent is pumped. Pre-treatment including dechlorination such as by physical process e.g. adsorption by activated carbon filter, or chemical process e.g. neutralisation by dechlorination agent dosing should be carried out to ensure compliance with the discharge requirements stipulated in TM-DSS.

Surface Runoff, Sewage and Wastewater from Construction Activities

Appropriate measures should be implemented to control runoff and prevent high loads of SS from entering the marine environment.  Proper site management is essential to minimise surface runoff and sewage effluents.

Construction site runoff should be prevented or minimised in accordance with the guidelines stipulated in the EPD's Practice Note for Professional Persons, Construction Site Drainage (ProPECC PN 1/94). All discharges from the construction site should be controlled to comply with the standards for effluents discharged into the Victoria Harbour WCZ under the TM-DSS. Good housekeeping and stormwater best management practices, as detailed below, should be implemented to ensure all construction runoff complies with WPCO standards and no unacceptable impact on the WSRs as a result of construction of the proposed submarine watermain. 

Sedimentation tanks with sufficient capacity, constructed from pre-formed individual cells of approximately 6 to 8 m3 capacities, are recommended as a general mitigation measure which can be used for settling surface runoff prior to disposal.  The system capacity should be flexible and able to handle multiple inputs from a variety of sources and suited to applications where the influent is pumped.

Manholes (including newly constructed ones) should always be adequately covered and temporarily sealed so as to prevent silt, construction materials or debris being washed into the storm runoff being directed into foul sewers.

All vehicles and plant should be cleaned before leaving a construction site to ensure no earth, mud, debris and the like is deposited by them on roads.  An adequately designed and located wheel washing bay should be provided at every site exit, and wash-water should have sand and silt settled out and removed at least on a weekly basis to ensure the continued efficiency of the process.  The section of access road leading to, and exiting from, the wheel-wash bay to the public road should be paved with sufficient backfill toward the wheel-wash bay to prevent vehicle tracking of soil and silty water to public roads and drains.

Precautions should be taken at any time of year when rainstorms are likely. Actions should be taken when a rainstorm is imminent or forecast. Actions to be taken during or after rainstorms are summarised in Appendix A2 of ProPECC PN 1/94.  Particular attention should be paid to the control of silty surface runoff during storm events, particularly for areas located near steep slopes.

Fuel tanks and storage areas should be provided with locks and be located on sealed areas, within bunds of a capacity equal to 110% of the storage capacity of the largest tank, to prevent spilled fuel oils from reaching the coastal waters of the Victoria Harbour and Western Harbour WCZs.

Portable chemical toilets would be used to handle construction workforce sewage prior to discharge to the existing trunk sewer. Sufficient numbers of portable toilets shall be provided by a licensed contractor to serve the construction workers.  The Contractor shall also be responsible for waste disposal and maintenance practices.

3.9                   Evaluation of Residual Impacts

Major water quality impact associated with dredging activities is the elevation of SS within the marine water column. Provided the recommended mitigation measures including the use of one grab dredger only with a maximum production rate of 4,000m3 per day for dredging,  deployment of frame type silt curtain to fully enclose the grab while dredging works are in progress and deployment of silt screen at the seawater intake at Kowloon South Salt Water Pumping Station while dredging works are in progress are implemented, no unacceptable residual cumulative water quality impact due to construction of the cross harbour main as well as the other concurrent marine works is expected.

Hydrostatic test of the water mains system would lead to effluent containing elevated concentrations of SS that would enter into the surrounding water. It was however expected that the above water quality impact would be temporary and localised during construction only. Provided the recommended mitigation measure is implemented and the effluent discharge complied with the TM-DSS standards, no unacceptable residual water quality impact due to effluent arising from hydrostatic test is expected.

General construction activities associated with the construction of the submarine watermain would lead to construction site runoff containing elevated concentrations of SS and associated contaminants that would enter into the marine water. It was however expected that the above water quality impacts would be temporary and localised during construction only. Provided the recommended mitigation measures are implemented and all construction site/works area discharges complied with the TM-DSS standards, no unacceptable residual water quality impact due to construction of the submarine watermain is expected.

3.10               Environmental Monitoring and Audit

Based on the above assessment of the water quality impact, an environmental monitoring and audit (EM&A) programme was considered necessary to obtain a robust, defensible database of baseline information of water quality before construction, and thereafter, to monitor any variation of water quality from the baseline conditions and exceedances of WQOs at sensitive receivers during construction.  Details of the EM&A were presented in a stand-alone EM&A Manual.

3.11               Conclusions and Recommendations

3.11.1         Construction Phase

Water quality impact during the dredging works of the submarine watermain was quantitatively assessed using the Delft3D Model.  Suspended sediment was identified as the key water quality parameter during dredging.  Water quality impact on the sensitive receivers during the entire duration of the dredging works and along the entire alignment with the maximum possible instantaneous working rate of 0.0463m3s-1.  (i.e. one grab dredger with a maximum production rate of 4,000m3 per day, 7 days per week, 24 hours per day) for the complete simulation period for the dry and wet seasons was assessed and it was predicted that potential water quality impact would occur at the WSD Sea Water Intake at Kowloon South Salt Water Pumping Station. With the implementation of the proposed mitigation measures including the use of one grab dredger only with a maximum production rate of 4,000m3 per day for dredging, deployment of frame type silt curtain to fully enclose the grab while dredging works are in progress and deployment of silt screen at the sea water intake at Kowloon South Salt Water Pumping Station while dredging works are in progress, the potential water quality impact upon the sea water intake would be effectively minimised and there would be no unacceptable residual cumulative water quality impact due to the dredging works of the submarine watermain as well as the other concurrent marine works.  The assessment predicted that the dredging works would have negligible impact upon the coral communities near Green Island.  An environmental monitoring and audit programme was recommended to ensure the effectiveness of the proposed water quality mitigation measures.

Minor potential water quality impacts from hydrostatic tests of the water mains systems and construction activities associated with the construction of the proposed submarine watermain were associated with effluent, sewage, wastewater and surface runoff. Impacts could be controlled to comply with the WPCO standards by implementing the recommended mitigation measure.  No unacceptable residual impact on water quality was expected.

3.11.2         Operation Phase

No maintenance dredging is required for the future operation of the proposed submarine watermain. There would be no hydrodynamic impact as the operation of the submarine watermain would not involve reclamation or filling that affects the flow volume within the Victoria Harbour.

There would also be no water quality impact during the operation of the submarine watermain as no effluent would be discharged due to the operation of the submarine watermain.

 


4                        MARINE ECOLOGICAL IMPACT ASSESSMENT

4.1                   Introduction

The submarine watermain component of the Project across Victoria Harbour is a Designated Project under Schedule 2, Part 1I(E3) of the Environmental Impact Assessment Ordinance (EIAO) (Cap. 499) and an Environmental Permit (EP) issued under the EIAO is required for the construction and operation of the designated project.

In accordance with the EIA Study Brief No. ESB-132/2005, construction and operation marine ecological impact arising from the dredging, laying of pipe and backfilling works for the construction of the submarine watermain were assessed.

This section presents the results of the assessment of ecological value of the habitat and marine resources of the Study Area for the proposed submarine watermain according to the EIA Study Brief No. ESB-132/2005. The potential impacts from the construction and operation of the Project on the existing ecological resources in the Study Area were assessed and evaluated according to the EIAO-TM Annex 8 and 16.

4.2                   Environmental Legislation, Standards, Guidelines and Criteria

A number of international conventions, local legislations and guidelines provide the framework for the protection of species and habitats of ecological importance.  Those related to the Project are:

·       Wild Animals Protection Ordinance (Cap 170);

·       Protection of Endangered Species of Animals and Plants (Ordinance (Cap 586);

·       Town Planning Ordinance (Cap 131);

·       Hong Kong Planning Standards and Guidelines Chapter 10 (HKPSG);

·       The Technical Memorandum on Environmental Impact Assessment Process under the Environmental Impact Assessment Ordinance (EIAO TM);

·       EIAO Guidance Note No. 11/2004 Methodologies for Marine Ecological Baseline Surveys;

·       United Nations Convention on Biodiversity (1992);

·       Convention on International Trade in Endangered Species of Wild Flora and Fauna (CITES);

·       Convention on the Conservation of Migratory Species of Wild Animals (the Bonn Convention);

·        IUCN Red Data Books; and

·       PRC Regulations and Guidelines.

Under the Wild Animals Protection Ordinance, designated wild animals are protected from being hunted, whilst their nests and eggs are protected from destruction and removal.  All birds and most mammals including all cetaceans are protected under this Ordinance, as well as certain reptiles, amphibians and invertebrates.  The Second Schedule of the Ordinance that lists all the animals protected was last revised in June 1992.

The Protection of Endangered Species of Animals and Plants Ordinance was gazetted on 10 March 2006 to replace the Animals and Plants (Protection of Endangered Species) Ordinance. The Ordinance will be effective on 1 December 2006, which aims at to regulate the import, introduction from the sea, export, re-export and possession or control of certain endangered species of animals and plants and parts and derivatives of those species; and to provide for incidental and connected matters.

The Town Planning Ordinance provides for the designation of areas such as “Coastal Protection Areas”, “Sites of Special Scientific Interest (SSSIs)”, “Green Belt” and "Conservation Area” to promote conservation or protection or protect significant habitat. 

Chapter 10 of the HKPSG covers planning considerations relevant to conservation.  This chapter details the principles of conservation, the conservation of natural landscape and habitats, historic buildings, archaeological sites and other antiquities.  It also addresses the issue of enforcement.  The appendices list the legislation and administrative controls for conservation, other conservation related measures in Hong Kong, and Government departments involved in conservation.

Annex 16 of the EIAO TM sets out the general approach and methodology for assessment of ecological impacts arising from a project or proposal, to allow a complete and objective identification, prediction and evaluation of the potential ecological impacts.  Annex 8 recommends the criteria that can be used for evaluating ecological impacts.

EIAO Guidance Note No. 11/2004 Methodologies for Marine Ecological Baseline Surveys elaborates on Annex 16 of the TM to provide information on the requirements of marine ecological baseline study. The note provides general guidelines for conducting a marine ecological baseline survey in order to fulfil the requirements stipulated in the TM in respect of marine ecological assessment for a proposed development.

The Peoples’ Republic of China (PRC) is a Contracting Party to the United Nations Convention on Biological Diversity of 1992.  The Convention requires signatories to make active efforts to protect and manage their biodiversity resources.  The Government of the Hong Kong Special Administrative Region has stated that it will be “committed to meeting the environmental objectives” of the Convention (PELB 1996).

CITES (the Convention on International Trade in Endangered Species of Wild Fauna and Flora) is an international agreement between Governments. Its aim is to ensure that international trade in specimens of wild animals and plants does not threaten their survival.

The Convention on Migratory Species of Wild Animals (Bonn Convention) aims at to develop international cooperation with a view to the conservation of migratory species of wild animals. This includes the conserve of terrestrial, marine and avian migratory species throughout their range. Migratory species threatened with extinction are listed as Appendix I of the Convention. Migratory species that needs or would significantly benefit from international cooperation are listed in Appendix II of the Convention. Hong Kong was a Party of this Convention since 1985.

The PRC in 1988 ratified the Wild Animal Protection Law of the PRC, which lays down basic principles for protecting wild animals.  The Law prohibits killing of protecting animals, controls hunting, and protects the habitats of wild animals, both protected and non-protected.  The Law also provides for the creation of lists of animals protected at the state level, under Class I and Class II.  There are 96 animal species in Class I and 156 in Class II.  Class I provides a higher level of protection for animals considered to be more threatened.

4.3                   Assessment Methodology

The Study Area was defined as the assessment area for Water Quality Impact Assessment, which is within 500 m from the site boundary, the Victoria Harbour and Western Buffer Water Control Zones. Area likely to be impacted by the Project including Green Island was also included in this assessment. A desktop literature review was conducted in order to establish the baseline conditions of the physical environment and to establish the general ecological profile for impact assessment. Information from the water quality assessment was also used to identify the effects of the change in water quality parameters on the marine ecology. The importance of marine ecological resources identified within the Study Area and the potential impacts due to the construction and operation of the Cross Harbour Main were assessed following the criteria and guidelines for evaluating and assessing ecological impact as stated in Annexes 8 and 16 of the EIAO-TM respectively.

The baseline information was gathered base on but not limited to the following publications and information:

·         Environmental Resources Management (1998). Environmental Impact Assessment: Dredging an Area of Kellett Bank for Reprovisioning of Six Government Mooring Buoys. Civil Engineering Department Port Works Division.

·         Scott Wilson Kirpatrick Consulting Engineering (1995). Green Island Reclamation (Part) – Public Dump. Environmental and Traffic Impact Assessment, Final Report Vol. I. Environmental Impact Assessment. Civil Engineering Department.

·         Atkins China Ltd. (2001). Central Reclamation, Phase III – Studies, Site Investigation, Design and Construction Environmental Impact Assessment Report. Territory Development Department.

·         Maunsell (2001). Wan Chai Development Phase II Comprehensive Feasibility Study Environmental Impact Assessment. Territory Development Department.

·         Maunsell Consultants Asia Limited (2002). Yau Tong Bay Development Reclamation of Yau Tong Bay Environmental Impact Assessment Study.

·         Morton, B.S. and Morton, J. (1983). The Sea Shore Ecology of Hong Kong, Hong Kong University Press, Hong Kong.

·         Environmental Protection Department (2005). Marine Water Quality in Hong Kong in 2004.

·         Tsim Sha Tsui Arial Photo date 5 October 2004 at 4,000 ft. Survey & Mapping Office, Lands Department HKSAR.

·         Sai Wan and Green Island Arial Photos date 8 March 2005 at 4,000 ft. Survey & Mapping Office, Lands Department HKSAR.

4.4                   Baseline Conditions & Marine Ecological Sensitive Receivers

The Study Area consists of several habitats, including the habitats in the intertidal zone (artificial seawalls and rocky shores), sub-tidal zone (soft-bottom and hard-bottom habitats) and the open sea (Victoria Harbour). The marine ecology around Green Island located approximately 2.8 km away from the proposed submarine watermain was also included in this study. Figure 4.1 shows the Study Area for the marine ecological impact assessment.

4.4.1             Existing Condition of Victoria Harbour

The location of the proposed submarine watermain is at the west of Victoria Harbour, within the gazetted Victoria Harbour Water Control Zone under the Water Pollution Control Ordinance (Cap. 358). Victoria Harbour was described as unclean cesspits receiving effluent and every sort of rubbish (11). The recent marine water quality monitoring results from Environmental Protection Department (2005) (12) showed that the water quality of the Victoria Harbour has been improved significantly after the implementation of the Harbour Area Treatment Scheme (HATS) in 2002. Only the total inorganic nitrogen (TIN) showed non-compliance to the Water Quality Objectives (WQO) in one monitoring station (with annual arithmetic means 0.20-0.57 mg/L) close to the alignment during 2004. Other key parameters such as dissolved oxygen and unionised ammonia were compliant with the WQO in both 2003 and 2004. The marine water quality sampling results at western Victoria Harbour in 2004 (13) showed that the water was generally turbid (8.1 – 14.8 NTU), with increasing trend of nitrate nitrogen concentration (0.05 – 0.30 mg/L), E. coli (540 – 26000 cfu/100mL) and faecal coliforms (16000 – 95000 cfu/100mL) count. The recently conducted water quality monitoring results in August 2006 showed that the turbidity level within the study area has much improved, ranging from 3.71 – 12.02 mg/L. The nitrate nitrogen concentration approximates 0.16 mg/L and the E. coli count range from 2000 to 9000 cfu/100mL.

Intertidal Zone

Artificial Seawalls

The intertidal zone of the Project area consists of breakwaters and sloping artificial seawall formed by large boulders and rock armour during reclamation along West Kowloon Reclamation area (Figure 4.2). Vertical artificial seawalls along Sai Ying Pun shoreline and concrete embanked wharf piles close to the Western Wholesale Food Market are common habitats along the Victoria Harbour (Figure 4.2). Fouling organisms are commonly found in this kind of artificial structures. They include rock oysters, periwinkles and barnacles as well as algae, coelenterates, ascidians, bryozoans, sponges, crustaceans, other molluscs and polychaetes, which were tolerant to pollution (14,15,16). No detail survey for these structures has been conducted, as much of the Harbour is ecologically degraded due to the smooth structures of the artificial seawall reduces the number of niches available for settlement and thus restricts the diversity of the flora and fauna that colonizes it (17). Literatures within the Study Area and in vicinity have been reviewed and summarised in Table 4-1 below.

Table 41    Typical Members of the Macrofauling Community in Wharf Piles of Hong Kong (Source: Morton, B. and Morton, J. 1983)

Zonation Commonly Recorded

Group

Species

Eulittoral zone

 

 

 

 

 

 

 

 

 

 

 

Eulittoral zone

 

 

 

 

 

 

 

 

Sub-littoral fringe

 

 

 

 

 

Sub-littoral fringe

 

 

 

 

 

Sub-littoral zone

 

 

 

Sub-littoral zone

 

 

 

Bivalve

 

 

 

 

 

 

 

 

 

 

 

Barnacles

 

 

 

 

 

 

 

 

Algae

 

 

 

 

 

Ascidians

 

 

 

 

 

Polychaete

 

 

 

Polyzoa

Perna viridis

Barbatia virescens

Trapezium liratum

Musculista senhausia

Modiolus agripetus

Ryenella cuprea

Electroma japonica

Saccostrea cucullata

Chama spp.

Striarca afra

Claudiconcha japonica

 

Balanus amphitrite

Modiolus agripetus

Ryenella cuprea

Electroma japonica

Balanus amphitrite

Balanus reticulates

Balanus variegates

Balanus trigonus

 

Ulva conglobata

Enteromorpha prolifera

Rhizoclonium riparium

Codium cylindricum

Colpomenia sinuosa

 

Ascidia sydneiensis

Ciona intestinalis

Styela plicata

Styela canopus

Herdmania momus

 

Pomatoceros triqueter

Hydroides elegans

Spirorbis foraminosus

 

Pedicellina (Genera)

Barentsia (Genera)

Loxosomella (Genera)

Natural Rocky Shores

Green Island was formed by granitic rocks with natural rocky shores at the coast (18). The northern shores have a greater habitat variety than the southern shores, by having gentler slopes with sand and boulders at the coast (19).

Literature review showed that the species diversity at the intertidal zone of Green Island was similar on both northern and southern shores, but different assemblages of intertidal fauna were recorded. The species recorded in Green Island include the commonly found barnacle Tetraclita squamosa, topshells Monodonta labio, littorinids nodilittorina trochoides, chitons Acanthopleura japonica, the limpets Cellana grata and a rare species of nerite Nerita undata (20). These species were found having a larger body size than the same species recorded at the northwestern shores of Hong Kong Island, which was probably the effect of limited human disturbance with food availability arising from the eutrophic water of the Victoria Harbour (21). Apart from the fauna community, the mid-tidal zone of the rocky shores have an extensive bed of macroalgae Porphyra sp., Ulva sp., Gelidium sp. and encrusting cyanobacteria Kyrtuthrix maculans. The sea-lettuce Ulva sp. was described common upon nearly all shores in Hong Kong (22).  

Baseline surveys of the coastal communities of Green Island, Little Green Island and a reference site in Hong Kong Island have been conducted by ERM in 1997 (23). In total 22 species of fauna and 8 species of algae were recorded, abstract of the most abundant species are listed in Table 4-2 below.

The results showed that the most abundant species were grazing gastropods including Chiton and Limpets at the low shore, and Periwinkles at the high shore. Predatory gastropods such as the Dogwhelks Thais clavigera and T. luteostoma were also recorded in low density at the low shore. Sessile organisms including Stalked Barnacles and Acorn Barnacles were recorded in high abundances. Algae were sparsely distributed along the shore during summer, with Cyanobacteria Pseudoulvella spp. having the highest percentage cover (24).

By comparing the three survey locations, the overall species abundance and species diversity were highest at the reference Hong Kong sites, followed by the Little Green Island and Green Island. The findings displayed the intertidal community to be typical of semi-exposed rocky shores. No rare species or species of conservation value were recorded during the survey.

Table 42     Abstract of Coastal Flora and Fauna recorded in Green Island, Little Green Island and a reference site in Hong Kong Island. (Source: ERM, 1998)

Zonation Recorded

Group

Species

Low Shore

 

 

 

High Shore

 

 

Low Shore

 

 

Not Mentioned

 

 

Not Mentioned

 

Herbivorous Molluscs

 

 

 

Predatory Gastropods

 

 

Filter-feeding Barnacles

 

 

Cyanobacteria

Chiton (Acanthopleura japonica)

Limpets (Cellana grata,C. toreuma, Patelloida pygmaea and P. saccharina)

 

Periwinkles (Nodilittorina trochoides, N. radiate and N. vidua)

 

Dogwhelks (Thais clavigera and T. luteostoma)

 

 

Stalked Barnacles (Capitulum mitella)

Acorn Barnacles (Tetraclita sp.)

 

Pseudoulvella spp.

Sub-tidal Zone

Soft-bottom Benthos Assemblages

The sea bed sediment of Victoria Harbour was described as grey, clayey, very silty and very gravelly sand with shell fragments in 2002 sediment testing (25), which is similar to the recent sediment testing results conducted in September 2006. There were minimal seasonal changes in sediment characteristics for both summer and winter recorded around Victoria Harbour (26). Vibrocore samples were collected in 15 locations (Figure 4.1), samples results showed that the seabed close to the Sai Ying Pun and along the proposed submarine watermain at the central are mainly composed of marine deposit with very soft, grey, silty clay with trace of coarse sand and fine gravel size shell fragments. For the surface sediments close to the Yau Ma Tei New Typhoon Shelter, the marine deposit appeared dark grey, silty, fine sand with occasional coarse sand size shell fragments recorded. Sediments collected close to the central and southern fairway around 200m away from the proposed water main indicated that the surface deposit at around 1m depth from the seabed were anthropogenic, black sediment which oxidize to brown, slightly silty, fine to coarse sand with little subangular, fine to medium gravel of rocks were recorded. The different in sediments composition was the result of continuous seabed disturbance by the marine traffic at the Victoria Harbour.

In view of the similar composition of the sediment recorded between the literatures and this study, and low species diversity were recorded in the local region with references to difference studies, no benthic fauna survey was conducted. Benthic infauna and epifauna communities recorded within the Study Area and in vicinity have been reviewed, and the findings are summarised below.

Benthic Infauna

Benthic infauna can be studied by grab sampling, vibrocore survey and the use of sediment profile photography method named Remote Ecological Monitoring of the Seafloor (REMOTS). Grab sampling results showed that the particle size distribution of the benthos between Stonecutters Island and Kennedy Town had a mean silt content of 77% and an organic content of 2.2% (27). The most abundant benthic fauna recorded is Polychaetes, which comprised of approximate 80% of the total infauna recorded. Other species include molluscs, crustaceans and echinoderms with abundance less than 10% of the total species recorded for each species group. The assemblages of the Victoria Harbour benthic infauna was characterised by low species diversity, evenness and low individual biomass (28, 29). The most abundant polychaete species recorded in the Western Harbour Area include the Aglaophamus lyrochaeta, Nephtys sp., Paraprionospio pinnata, Tharys sp., Marphysa stragulum, Notomastus latericeus and Glycera chiori (30). Paraprionospio pinnata is known to be well adapted to organic pollution and is an indicator of the increase in TOM in sediments (31).

Grab samples along the Sulphur Channel between Green Island and Kennedy Town conducted in 1993 (Figure 4.1) showed that 92 macrobenthic organisms of 32 taxa were recorded, in which 69% of the total number of individuals were polychaetes, others include the molluscs and crustaceans (32). The most abundant polychaetes comprised Prionospio saccifera, Tharyx multifilis, Nephtys polybranchia, Sternespis sculata and Sigambra hanaokai.

Sediment sampling results in 1995 around the Central waterfront (Figure 4.1) recorded that no live benthic invertebrates were sampled (33). Only empty gastropod shells were collected. The malodorous and anoxic sediment suggested that the marine lives were subject to pollution stress by the long term sewage discharge into the region.

Remote Ecological Monitoring of the Seafloor Studies (REMOTS) showed that benthic eutrophication occurs as a result of organic enrichment from the harbour (sampling locations see Figure 4.1) (34). Only the pollution tolerant polychaetes species (Spionidae and Capitellidae) and crustaceans (crab larvae and small amphipods) in small size and low density were recorded on the near surface sediment. CityU (2002) (35) also indicated that the benthic fauna recorded in Victoria Harbour is characterized by species which can adapt to an eutrophic environment. The sediments in the study area appeared dark grey to black, reflecting the anoxic condition with high organic loading of the local region.

Benthic Epifauna

Trawl surveys were conducted by ERM in 1995 (36) (see Figure 4.1 for trawling location). There are total 15 species and 44 individuals recorded close to the Green Island (Table 4-3). The species diversity of the benthic epifauna was diverse, but low in abundance. The dominant species was anemones, which comprises of approximately 36% of the total number of organisms recorded in the region. Apart from the gorgonian soft corals and sea pen (Pteroides esperi) recorded were considered to be of ecological value, the fish diversity and macro-invertebrate communities around the Green Island were considered to be low comparing with other areas in Hong Kong (37).

Table 43     Benthic Epifauna Recorded around Green Island (Source: ERM, 1995)

Species

Abundance

Sponge

Sclerobelemnon burgeri

Pteroides esperi

Virgularia gustaviana

Gorgonacea sp.

 

Anemones

Unidentified anemones

 

Hydrozoa

Unidentified hydroids

 

Bryozoan

Unidentified bryozoan

 

Molluscs

Callanailis hirascana

 

Shrimps & Mantis shrimp

Alpheus bisincisus

Oratosquilla oratoria

 

Crabs

Portunus hastatoides

Thalamita picta

 

 

Fish

Paralichthys olivaceus

Oxyurichthys tentacularis

Unidentified Clupeidae

Total no. of species

Total no. of individuals

 

6

2

2

1

 

 

16

 

 

1

 

 

2

 

 

1

 

 

5

3

 

 

1

1

 

 

 

1

1

1

15

44

Hard-bottom Coral Assemblages

Remotely Operated Vehicle (ROV) was used to conduct coral survey around Green Island, Little Green Island and the Sulphur Channel close to the western Hong Kong Island (reference site) by ERM as part of the ecological surveys for the Green Island Development Studies in 1997 (38). Video were taken along three 10m wide belt transects at depths of -5, -10 and -15 mPD. Four species of soft coral and gorgonians were recorded in this study at Green Island and Little Green Island, including the Pink Soft Coral Dendronnephthya sp., Orange Sea Fan Echinogorgia complexa, White Sea Whip Euplexaura curvata and Purple Sea Whip Ellisella gracilis. No soft coral and gorgonian colonies was recorded in the western Hong Kong Island waters in this study. Table 4-4 shows the frequency of soft coral and gorgonian colonies encountered during the study.

The seabed profile at the sub-tidal zone around Green Island is composed of rocky seabed with scattered boulders at -5 mPD (39), and become sandy offshore. Seabed profile around the western Hong Kong Island is a bit different from the Green Island, with sandy substrates in shallow region and becomes muddy with scattered shell fragments offshore. This may show the different in marine organism distribution among the sites. 

Table 44     Frequency of Soft Coral and Gorgonian Colonies Recorded around Green Island (Source: ERM, 1998) (40)

Survey Area and Transect No.

Level

(-mPD

Species

Dendronephthya sp.

Echinogorgia complexa

Euplexaura curvata

Ellisella gracilis

Little Green Island

T1.1

T1.2

T1.3

T2.1

T2.2

T2.3

 

Green Island

T3.1

T3.2

T3.3

T4.1

T4.2

T4.3

 

Hong Kong Island

T5.1

T5.2

T5.3

T6.1

T6.2

T6.3

 

5

10

15

5

10

15

 

 

5

10

15

5

10

15

 

 

5

10

15

5

10

15

 

20

18

11

17

2

11

 

 

8

3

0

20

4

18

 

 

0

0

0

0

0

0

 

10

9

10

4

0

2

 

 

1

0

0

0

0

0

 

 

0

0

0

0

0

0

 

11

15

24

5

9

8

 

 

20

57

17

0

2

13

 

 

0

0

0

0

0

0

 

0

0

0

2

0

0

 

 

0

0

0

0

0

0

 

 

0

0

0

0

0

0

The most frequently encountered (more than 40 colonies per transect) species in the Green Island was the White Sea Whip Euplexaura curvata, especially at the western side of the Green Island at depth -10 mPD, followed by the Pink Soft Coral Dendronephthya sp. which was common in both the Green Island and Little Green Island waters. The Orange Sea Fan Echinogorgia complexa was considered as rare in the Green Island region, but was common and evenly distributed at the three depths in Little Green Island. The Purple Sea Whip Ellisella gracilis was only encountered at the Little Green Island region at depth -5 mPD and considered as rare as less then 20 colonies were recorded in this transect.

Open Sea

Marine Mammals

All the marine mammals in Hong Kong are protected under the Wild Animals Protection Ordinance (Cap. 170) and the Protection of Endangered Species of Animals and Plants Ordinance (Cap. 586). The Chinese White Dolphin Sousa chinensis and Finless Porpoise Neophocaena phocaenoides are the most common cetaceans recorded in Hong Kong. They are listed as ‘Data Deficient’ in the IUCN Red list (41) and as ‘highest protection’ in CITES Appendix I (42).

The Chinese White Dolphin has limited distribution in Hong Kong waters, due to their preference for shallow, coastal estuarine habitats (43). Their distribution range are mainly in the western waters, including outer Deep Bay, north, south, west and east Lantau, and west Lamma (44). All of the areas with dolphin sightings recorded were influenced by freshwater discharge from the Pearl River (45). While for the Finless Porpoise, they only occur in the southern and eastern waters, but not the northwestern waters which are influenced by the Pearl River (46). The only sighting of the Chinese White Dolphin near the vicinity of the Study Area was in 1994, when the dolphin was sighted swimming towards the Lantau coast, away from the study area (47).

Marine Ecological Sensitive Receiver

There are no SSSIs, Fish Culture Zones, Marine Parks or Marine Reserves in the Study Area. The only marine ecological sensitive receiver is the established coral communities at Green Island, approximately 2.8 km to the west of the proposed cross harbour main. The Study Area is not the distribution range of the Chinese White Dolphin and Finless Porpoise, thus it is not considered to be an important habitat to the cetacean.

4.5                   Ecological Importance

Based on the literatures review of the baseline conditions discussed above, the ecological assessment show that the marine ecological resources within the Study Area for the proposed marine cross harbour main are considered to be of low ecological value, due to their low species diversity and the present of pollution tolerant indicator species. Except for the sub-tidal and intertidal zone at Green Island, which are considered to be of moderate ecological value with the presents of soft corals and gorgonian species and the more diverse coastal communities compare with the species present on the artificial seawalls along the Victoria Harbour. The evaluation of the ecological importance of each habitat was determined on the basis of the criteria set in the EIAO-TM Annex 8 Table 2. Table 4-5 and Table 4-6 summarised the results of habitat evaluation.

Table 45     Evaluation of the Ecological Importance of the Inter-tidal Habitats

Criteria

Victoria Harbour

Green Island

Naturalness

Mainly composed of artificial seawall receiving extensive disturbance through high pollution load and wave action produced by marine traffic.

Natural rocky shores with little human disturbance.

Size

Approximate 660m of artificial shoreline was being studied.

The natural intertidal shoreline is approximately 2,000m.

Diversity

The species diversity is low.

The species diversity is low.

Rarity

The species recorded are commonly found on artificial seawalls in Hong Kong waters.

The species recorded are typical of other semi-exposed rocky shores in Hong Kong.

Re-creatability

The artificial seawall is recreatable.

The natural rocky shores cannot be recreated.

Fragmentation

Not applicable.

Not applicable.

Ecological Linkage

The existing habitats are not functionally linked to high ecological value habitats.

The rocky shores ecologically link with the sub-tidal habitats in the surrounding waters.

Potential Value

Unlikely to develop a nature conservation interest habitat.

Moderate potential to develop nature conservation interest habitat if water pollution and other human disturbances remove.

Nursery/Breeding Ground

Not identified.

Not identified.

Age

Not applicable.

Not applicable.

Abundance/Richness of Wildlife

The species abundance was low at vertical smooth structures but medium at wharf piles.

Compare to reference site at Hong Kong Island, the species abundance was low.

Summary

The inter-tidal assemblages along shoreline of Victoria Harbour are of low ecological value.

The inter-tidal assemblages along the natural rocky shores at Green Island are of low to medium ecological value.

 Table 46    Evaluation of the Ecological Importance of the Sub-tidal Habitats

Criteria

Victoria Harbour

Green Island

Naturalness

The sub-tidal zone is composed of marine sediments receiving continuous disturbances.

The sub-tidal zone is composed of natural rocky seabed with scattered boulders and become sandy offshore.

Size

Approximate 7,000m² of sub-tidal zone was studied.

The study area of the sub-tidal zone is small.

Diversity

The species diversity of soft benthos is low.

The species diversity of benthic fauna and coral communities is moderate.

Rarity

The species recorded are common in Hong Kong.

The species recorded are not rare to Hong Kong.

Re-creatability

The disturbed seabed is recreatable.

The natural seabed can hardly recreate.

Fragmentation

Not applicable.

Not applicable.

Ecological Linkage

The existing habitats are not functionally linked to high ecological value habitats.

The sub-tidal habitats are ecologically link with the inter-tidal habitats in the surrounding waters.

Potential Value

Low potential to develop a nature conservation interest habitat.

Moderate potential to develop nature conservation interest habitat if water pollution and other human disturbances remove.

Nursery/Breeding Ground

Not identified.

Not identified.

Age

Not applicable.

Not applicable.

Abundance/Richness of Wildlife

The soft benthos species abundance is low.

Compare to reference site at Hong Kong Island, the species abundance was higher.

Summary

The sub-tidal assemblages in Victoria Harbour are of low ecological value.

The sub-tidal assemblages at Green Island are of medium ecological value.

4.6                   Identification and Prediction of Environmental Impacts

The proposed submarine watermain will be constructed approximately 6 m below the existing seabed level.  The major impacts on the marine ecological resources will be the direct impacts of habitats loss from dredging and backfilling activities at the seabed and installation of submarine pipeline by “bottom pull” method during construction phase. There may be indirect impacts through the changes to water flow regime, and perturbations of the surrounding water quality. The potential marine ecological impacts arising from construction and operational phases are detailed below.

4.6.1             Construction Phase

Habitat Loss and Disturbances

The direct impacts from construction activities include the permanent loss of approximately 9.2ha of natural seabed resulting from dredging activities for the installation of the proposed submarine watermain and temporary disturbance of approximate 51.2ha of works area in the marine environment. Less than 90m of artificial shore at Yau Ma Tei Typhoon Shelter will be disturbed by the construction of temporary platform and approximate 2m² on either side of the pipeline landing shores will be lost due to the installation of pipeline.

Direct and Indirect Impacts on Marine Fauna

The dredging activities will also directly remove the less mobile wildlife inhabiting the affected area and surrounding habitats, and indirectly affect the marine wildlife through associated impacts including, degradation of habitat quality, reduce sunlight penetrating the water column due to increase turbidity and reduce the food production ability of the photosynthesizing animals, as well as behaviour changing due to change in physical environment.

The dredging and backfilling activities will also increase the suspended solids (SS) concentration, decrease in dissolved oxygen (DO) level and the increase in nutrient levels in the water column. The high concentration of SS may cause clogging of gills or filaments of the marine organisms, increase energy consumption to expel the sediments by the filter feeding animals, and the reduction in DO level for consumption may eventually cause the marine organisms suffocate to die. The high concentration or deposition rate of SS may also form a blanket that smother the corals and reduce the ability of the associated photosynthesising zooxanthellae to undertake photosynthesis; coral bleaching may occur or even die if the corals cannot tolerate the stresses.

Release of previously bound organic and inorganic constituents such as heavy metals, PAHs and polychlorinated biphenyls (PCBs) into the water column via suspension or disturbance of seabed as a result of dredging may also cause lethal or sub-lethal effect to the marine fauna.

The physical disturbances to the surrounding waters by the construction activities include the increase in human activities, inappropriate storage or dumping of construction materials, increase in marine traffic and change in water flow regime may indirectly affect the marine wildlife at the local region.

4.6.2             Operational Phase

No post maintenance work is necessary for the proposed submarine watermain, and the potential impacts in operational phase are mainly the change in seabed profile and substrates along the 44m width alignment. The existing soft marine deposit with silt, sand and gravel will change to armour rock backfill with marine sediment naturally.

4.7                   Evaluation of Environmental Impacts

4.7.1             Construction Phase

Habitat Loss and Disturbances

Habitat loss will occur at the sub-tidal zone and artificial seawalls at the inter-tidal zone along the Victoria Harbour. The seabed substrates are composed of marine sediments that receive continuous disturbances. Species recorded in this region were in low diversity and were dominated by common and pollution tolerant indicator marine benthos. Benthic fauna is expected to recolonize the seabed after the backfilling works and the deposition of sediment by natural process.

The permanent loss of artificial seawalls sections are very common structures along the seafronts in Hong Kong. The vertical surfaces of these structures support low species abundance of fouling organisms.

In view of the paucity of marine wildlife and low ecological value of the affected seabed and artificial seawalls, the direct impacts on permanent loss of approximately 9.2ha of natural seabed along Victoria Harbour and less than 90m of artificial shores at Yau Ma Tei Typhoon Shelter resulting from dredging activities for the installation of the proposed pipeline, the impacts are considered to be of low significant. Species are expected to recolonize after construction.

Direct and Indirect Impacts on Marine Fauna

From the baseline marine ecology results show that the marine benthos recorded within the construction area and in vicinity are of low ecological value and in low abundances. The impacts of the direct removal or indirect disturbances of these low importance species will be of low significance.

The potential impacts on the medium ecological value habitats (the sub-tidal and inter-tidal habitats with coral communities and natural rocky shores at Green Island) are the increase in SS concentration and the associated deterioration of water quality at the Green Island waters due to the dredging and backfilling activities. According to the water modelling results presented in Section 3 Table 3-11, the predicted suspended solids concentrations for dredging undertaken near West Kowloon and near Sai Ying Pun in dry and wet seasons at marine ecological sensitive receivers (assessment points refer to Table 3-5 in Section 3 and location refer to R2, R3, R4 and R5 in Figure 3.2) show that the predicted elevation of SS concentration during both dry and wet seasons at Green Island, will be less than 0.1 mgL-1 at depth average, top layer and bottom layer of the water column (Figure C3.1a to C3.1c in Appendix C1), and the net sedimentation rate is less than 0.001 kg m-2 per day (Figure C3.3e in Appendix C1). These results are much lower than the SS elevation limit and sedimentation rate set in Section 3.2.8 of 10mgL-1 and 0.1 kg m-2 per day respectively. Thus, dredging works near West Kowloon and Sai Ying Pun will have negligible impact upon the coral communities at waters near Green Island.

The extent of marine sediment contamination along the alignment of the proposed submarine main was reported in Section 6. The results indicated that high level of contamination in terms of arsenic (As), copper (Cu), lead (Pb), mercury (Hg), silver (Ag) and polyaromatic hydrocarbons (PAHs) and polychlorinated biphenols (PCBs) were found essentially at a number of vibrocore samples. However, the elutriate tests results reported in Section 3 estimated that the release of the above contaminants to the water column at the point of dredging fall within the UK Water Quality Standard and no exceedances of standard was predicted. Therefore, long-term off-site marine ecological impact due to release of marine sediment with high contamination is negligible.

The physical disturbances to the surrounding waters by the construction activities include the increase in human activities, inappropriate storage or dumping of construction materials, increase in marine traffic and change in water flow regime may have negligible impact on the marine wildlife when good site practices and control of marine traffic speed are implemented during the construction phase.

The significance of impacts arising from this proposed works on the marine ecological resources mentioned above are evaluated using the criteria set in the EIAO-TM Annex 8 Table 1 and presented in Table 4-7 below.

Table 47     Evaluation of the Significance of Ecological Impact

Criteria

Victoria Harbour

Green Island

Habitat Quality

The sub-tidal zone and artificial seawalls at inter-tidal zone being affected are of low ecological values.

No significant impact is anticipated to the moderate ecological valued natural rocky shores and soft bottom seabed.

Species

The species recorded in the dredging area are common and pollution tolerant.

No rare species were recorded within the study area, and coral communities of moderate conservation interest are not expected to be impacted by the construction at approximate 2.8km away from Green Island.

Size/Abundance

Approx. 9.2ha of low ecological value benthic assemblages will be loss, and approx. 51.2ha of works area may be temporary disturbed by construction activities. Around 2m² of artificial seawall at both landing points will also be loss permanently. The species abundance of the soft benthos and inter-tidal fouling organisms at vertical seawall is low.

No direct impact is anticipated on the moderate abundance inter-tidal and sub-tidal region at Green Island.

Duration

The lost of approx. 9.2ha of seabed and 2m² of artificial wall is permanent. The temporary affected area will last for approximate 1 year. The change in water quality in the water column around the dredging area is temporary and within environmental acceptable levels. Benthic communities within the dredging area are expected to recolonize after the backfilling of the seabed.

Change in water quality around the soft coral assemblages are expected to be temporary and short term.

Reversibility

Impacts to the benthic fauna within the working area will be long term. The seabed will be backfilled with armour rock and by natural sedimentation. Benthic fauna is expected to recolonize to the seabed after construction.

Soft coral assemblages are reversible if the stress is short term and in low magnitude. The change in water quality in the vicinity is anticipated to be in very low magnitude.

Magnitude

The impact to the habitats identified will be of low magnitude.

The impact to the habitats identified will be of very low magnitude.

Summary

The impacts to the low ecological valued marine benthos and artificial habitats within the dredging and works area are predicted to be of low significant.

The impacts to the coral communities and coastal communities at intertidal zone are predicted to be of negligible significant due to no works will be constructed in the vicinity, remote (2.8km) from the works boundary and the prediction of low elevation of SS concentration at the region.

In summary, the impacts of permanent habitat loss and temporary disturbances to marine ecological resources will be of low to negligible significance, due to no rare species recorded within the affected area and in vicinity and the low ecological value of the marine benthos and the re-creatable artificial structures along the Victoria Harbour. The indirect impacts on the medium ecological value habitats at Green Island are anticipated to be negligible, due to no works will be constructed in the vicinity, remote from the works boundary, the prediction of low elevation of SS concentration and receiving no effect on the release of contaminant during the dredging process.

4.8                   Mitigation of Adverse Environmental Impact

The proposed dredging works will be confined in the works area within 25m at either side of the proposed alignment and the use of closed type grab dredger will reduce sediment and contaminants runoff to the water column. The trench will be backfilled with armour rock or decomposed granite and allow natural sedimentation on the substrates to provide protection of the pipeline from damage by ship anchors. Benthic fauna is expected to be recolonized to the seabed after construction. Other mitigation measures suggested in the water quality impacts assessment such as the use of one grab dredger only with a maximum production rate of 4,000m3 per day for dredging, deployment of frame type silt curtain to fully enclose the grab while dredging works are in progress, deployment of silt screen at the sea water intake at Kowloon South Salt Water Pumping Station while dredging works are in progress. and good site practices to avoid silt runoff from construction works associated with the construction of the submarine watermain could also further reduce the impact on the marine ecology. No other specific mitigation measures for marine ecology are considered necessary, as no adverse impact was identified.

4.9                   Evaluation of Residual Impacts

There will be loss of approximately 4m² of artificial seawall and change in approximately 9.2ha of seabed substrates along the alignment. Benthic fauna is expected to be recolonized to the seabed after construction. No adverse residual impact due to the construction and operation of the submarine watermain is expected after the implementation of the proposed mitigation measures.

4.10               Environmental Monitoring and Audit

The implementation of the ecological mitigation measures stated in Section 4.8 and water quality mitigation measures in Section 3 should be checked as part of the environmental monitoring and audit procedures during the construction period as presented in the separate Environmental Monitoring and Audit Manual.  No other marine ecology-specific measures are considered necessary.

4.11               Conclusions and Recommendations

A review of the existing information showed that the marine ecological resources within the dredging area consist of pollution tolerant soft benthos in low diversity and typical to benthos recorded in poor quality sediments. Inter-tidal species along Victoria shorelines are common fouling organisms recorded at artificial seawall. Both the species diversity and abundance recorded are lower than those recorded in semi-exposed shore in Hong Kong. The marine ecology in Green Island is of moderate ecological value, with soft coral assemblages and larger size inter-tidal species recorded. However, the results of water quality modelling showed that the elevation of SS concentration and sedimentation rate around the Green Island waters is predicted to be less than 0.1mgL-1 and 0.001 kg m-2 per day respectively, which are much lower than the tolerant levels for corals communities. In addition, due to the remoteness from the works area, the impacts to the marine environment in vicinity to Green Island are anticipated to be negligible. The Study Area is not the distribution range of marine mammals and as low ecological value species are encountered in the region, the implementation of good site practices and mitigation measures for water quality impact are considered to be sufficiently minimize the impacts on the marine ecology. Thus, no special mitigation measures are necessary for ecological sensitive receivers.

In conclusion, the construction of the proposed submarine watermain along Victoria Harbour between Sai Ying Pun and West Kowloon is anticipated to be of low ecological impacts. 


5                        NOISE IMPACT ASSESSMENT

5.1                   Introduction

A noise impact assessment has been undertaken to define the nature and scale of the potential noise impact to sensitive receivers associated with the proposed submarine watermain. The construction noise levels associated were predicted based on the plants to be used and the phasing of the construction programme was also considered.

The submarine watermain component of the Project across Victoria Harbour is a Designated Project under Schedule 2, Part 1I(E3) of the Environmental Impact Assessment Ordinance (EIAO) (Cap. 499) and an Environmental Permit (EP) issued under the EIAO is required for the construction and operation of the designated project.

In accordance with the EIA Study Brief No. ESB-132/2005, construction noise impact arising from the dredging, laying of pipe and backfilling works for the construction of the submarine watermain were assessed.

No noise impact is envisaged to arise from the operation phase of the proposed submarine watermain.

5.2                   Environmental Legislation, Standards, Guidelines and Criteria

Noise impacts were assessed in accordance with the criteria and methodology given in the Technical Memoranda (TMs) issued under the Noise Control Ordinance (NCO) and the Technical Memorandum on Environmental Impact Assessment Process (EIAO-TM).

 

The Noise Control Ordinance provides the statutory framework for noise control. Assessment procedures and standards are set out in the following Technical Memoranda:

 

·     Technical Memorandum on Noise from Construction Work other than Percussive Piling (GW-TM);

·     Technical Memorandum on Noise from Construction Work in Designated Areas (DA-TM); and

·     Technical Memorandum on Environmental Impact Assessment Process (EIAO-TM) Annexes 5 and 13.

5.2.1             Construction Noise

Noise impacts arise from construction works other than percussive piling using items of powered mechanical equipment (PME) during normal working hours (i.e. 0700 to 1900 hours on any day not being a Sunday or public holiday) to the noise sensitive buildings are assessed with reference to the NCO. The recommended noise standards in EIAO-TM are presented in Table 5-1 below.

Table 51     EIAO-TM Daytime Construction Noise Standards (0700 to 1900 hours on any day not being a Sunday or public holiday) (Leq.30 min dB(A))

Uses

Acceptable Noise Standards

Domestic Premises

Educational institutions (normal periods)

Educational institutions (during examination periods)

75

70*

65*

Note:      *For reference only, not used in this study.

The NCO also provides statutory controls on general construction works during the restricted hours (i.e. 1900-0700 hours Monday to Saturday and at any time on Sundays and public holidays). The use of items of powered mechanical equipment (PME) for carrying out construction works during the restricted hours would require a Construction Noise Permit (CNP). A CNP may be granted provided that the Acceptable Noise Level (ANL) for the noise sensitive receivers (NSRs) can be complied with. The Corrected Noise Levels CNLs (after accounting for factors such as barrier effects and reflections) associated with the proposed operations of items of PME are then compared to ANL. A CNP will be issued if the CNL is equal to or less than the ANL. The Noise Control Authority is guided by the GW-TM when assessing such an application.

The steps to determine the ANL for the sensitive receivers include determining the Basic Noise Level (BNL) and make correction according to the procedures stipulated in the GW-TM. The corresponding Basic Noise Levels (BNLs) for evening and night time periods are given in Table 5-2.

Table 52     Basic Noise Levels (BNL, Leq.30 min dB(A))

Time Period

Area Sensitivity Rating

A

B

C

All days during the evening (1900 – 2300 hours) and general holidays (including Sundays) during the day and evening (0700 – 2300) hours

60

65

70

All days during the night-time (2300 – 0700 hours)

45

50

55

5.2.2             Area Sensitivity Ratings

The Area Sensitivity Ratings assumed in this EIA Report (in Section 5.4 below) are for indicative assessment only. Despite any description or assessment made in this EIA Report on construction noise aspects, there is no guarantee that a Construction Noise Permit (CNP) will be issued for the project construction. The Noise Control Authority will consider a well-justified CNP application, once filed, for construction works within restricted hours as guided by the relevant Technical Memoranda issued under the Noise Control Ordinance. The Noise Control Authority will take into account of contemporary conditions/ situations of adjoining land uses and any previous complaints against construction activities at the site before making his decision in granting a CNP. Nothing in this EIA Report shall bind the Noise Control Authority in making his decision.  If a CNP is to be issued, the Noise Control Authority shall include in it any condition he thinks fit. Failure to comply with any such conditions will lead to cancellation of the CNP and prosecution action under the NCO.

In addition to the general controls on the use of items of PME during the restricted hours, the Noise Control Authority has implemented more stringent control mechanisms via the DA-TM.  The DA-TM regulates the use of five types of Specified Powered Mechanical Equipment (SPME) and three types of Prescribed Construction Work (PCW), which are non-PME activities, in primarily densely populated neighbourhoods called Designated Areas (DAs).  The SPME and PCW are:

Specified Powered Mechanical Equipment:

·           Hand-held breaker

·           Bulldozer

·           Concrete lorry mixer

·           Dump truck

·           Hand-held vibratory poker

Prescribed Construction Work:

·           Erection or dismantling of formwork or scaffolding

·           Loading, unloading or handling or rubble, wooden boards, steel bars, wood or scaffolding material

·           Hammering

In an attempt to provide environmental additional protection carrying out of PCW is generally banned inside a DA. As for the use of SPME, it would be necessary to comply with DA-TM noise level requirements that are 15 dB(A) more stringent than those listed in the GW-TM before a CNP would be issued. 

It is worth noticing that the above SPME and PCW suggested will not be used during the construction of this Project (refer to the plant inventory listed in Table 5-4). Therefore, the above mentioned regulation in DA-TM would only serve as a reference only.

5.3                   Noise Sensitive Receivers

Representative Noise Sensitive Receivers (NSRs) within 300m of the Project limit have been identified according to the criteria set out in the EIAO-TM and through site inspections and a review of land use plans. However, no NSR within 300m was found in West Kowloon, so the closest NSRs are considered. NSRs and their separate distance to the respective landfall sites have been obtained and are summarized in Table 5-3. Locations of the NSRs and the assessment area are shown in Figures 5.1 and 5.2 at Sai Ying Pun and West Kowloon respectively. There is no planned development identified within the assessment areas hence no planned NSR was included in this assessment.

The landfall site at Sai Ying Pun is situated at the seafront area east of the Western Wholesale Food Market and next to the entrance of Western Harbour Crossing. Figures 5.1 and 5.3 indicate the proposed works area for the landfall site at Sai Ying Pun with the extent of seawall construction works. The works in this area include pipe pulling by winch and seawall reinstatement. The nearest residential buildings along Connaught Road West are separated from the landfall site by the existing massive transport corridor.

The landfall site at West Kowloon is at the seafront area near the exit of the Western Harbour Crossing. Figures 5.2 and 5.4 shows the works area in West Kowloon. Extent of seawall construction is also shown. The works in this area include construction of the temporary platform, pipe preparation, pipe laying and seawall reinstatement. The closest residential buildings are private developments above the Kowloon Station, including The Union Square (KS6), The Arch (KS3b) and The Harbourside (KS4). These buildings are located far away from the construction site (>300m). They are included in this study for indicative purpose.

The Separation Distances (m) between the notional noise source and the NSRs are determined in accordance with the TM on Noise from Construction Work other than Percussive Piling. All items of PME are assumed to be located at a single notional source position. Since the items of PME will be close to the site of seawall reinstatement, the access roads are not considered when determining the geographical centre of the construction site. The Separation Distances established are shown in the Table 5-3.

Table 53     Representative Noise Sensitive Receivers

NSR ID

Description

Type of Use

Separation Distance (m)

West Kowloon

WF1

The Waterfront

Residential

750

WF2

 

 

790

WF3a

 

 

830

KS2

Sorrento

 

760

KS3b

The Arch

 

810

KS4

The Harbourside

 

670

KS6

Union Square

 

580

Sai Ying Pun

FSB

Fung Shing Building

Residential

360

VC

Viking Court

 

320

CLM

Cheong Ling Mansion

 

310

KY2

Kwan Yik Building Phase 2

 

400

KY3a

Kwan Yik Building Phase 3

 

245

KY3b

 

 

225

RWM

Richwealth Mansion

 

215

CG1

Connaught Garden

 

220

CG2

 

 

230

CG3

 

 

245

GB

General Building

 

270

Note:      Noise Sensitive Receivers are representative and will be used in prediction calculations.

 

5.4                   Assessment Methodology

5.4.1             Guidelines in GW-TM

A methodology for assessing construction noise other than percussive piling has followed the guidelines set out in the Technical Memorandum on Noise from Construction Work other than Percussive Piling (GW-TM).  The methodology is as follows:

·           identify the likely type, sequence and duration of principal noisy construction activities required for the implementation of the proposed project;

·           identify a list of plant inventory likely to be required for each construction activity;

·           calculate the maximum total sound power level (SWL) for each construction activity using the plant list and SWL data given for each plant in the technical memorandum.

·           representative NSRs as defined by the EIAO-TM have been identified, based on existing and committed land uses in the study area that may be affected by the worksite.

·           calculate the distance attenuation and barrier corrections to NSRs from worksite notional noise source point;

·           predict construction noise levels at NSRs in the absence of any mitigation measures; and

·           include the +3 dB(A) facade correction to account for the facade effect at each NSR.

If the predicted noise levels at the NSRs exceed the noise assessment criteria, mitigation measures must be considered.  A re-evaluation of the total SWL for each construction activity will be made assuming the use of practical mitigation measure such as quiet equipment and movable noise barriers. If the predicted noise levels still exceed the noise criteria, further mitigation measures such as reduction in noisy plant working simultaneously would be considered.

5.4.2             Area Sensitive Ratings (ASRs)

Determination of the Area Sensitivity Ratings for the NSRs in this study has been made with reference to relevant TMs.

Sai Ying Pun

The NSRs are residential developments located in urban area of Sai Ying Pun with an annual average daily traffic flow of 43,490 and 40,460 running through the nearby Connaught Road West and Western Harbour Crossing respectively (Source: Station no. 1006 and 1026, Annual Traffic Census 2005 published by Transport Department). As the NSRs are located in urban area and are directly affected by this influencing factor, an Area Sensitivity Rating (ASR) of “C” is applied according to the GW-TM.

West Kowloon

In West Kowloon, the southwest facade of closest NSRs (KS4 & KS6) facing the landfall site is directly influenced by the traffic noise from the West Kowloon Highway with an annual average daily traffic flow of more than 38,410 (Source: Station no. 3502, Annual Traffic Census 2005 published by Transport Department). As the NSRs are residential developments located in urban area with high-rise buildings and are directly affected by this influencing factor, an Area Sensitivity Rating (ASR) of “C” is applied according to the GW-TM.

Accordingly, the ANL would be 70 dB(A) in the evening and 55 dB(A) at night as detailed in Table 5.2 for both Sai Ying Pun and West Kowloon.

5.4.3             Assessment for the Project

Using the methodology outlined in the TM, notional noise sources for different construction areas were assumed. All the items of powered mechanical equipment (PME) listed in Table 5-4 and Table 5-5 for Sai Ying Pun and West Kowloon are assumed to be located at notional source.

Sound power levels (SWLs) of PME items are adopted from Table 3 of the GW-TM (No percussive piling is required for this Project). When no SWL is suggested in the TM, reference was made with BS 5228: Part 1:1997 Noise Control on Construction and Open Sites. Details of the items of PME and the total SWLs for various construction activities are listed in Table 5-4 and Table 5-5.

The major tasks in the laying of the watermain are

·           Trench dredging

·           Laying of submarine watermain

·           Backfilling

From the context of the programming of construction works, it is suggested that night-time dredging work could be required. The necessity of night-time dredging will depend on the progress of the project. For any construction works planned during restricted hours, it will be the responsibility of the Contractor to ensure compliance with the NCO and the relevant TMs. In such case, the Contractor will be required to submit CNP application to the Noise Control Authority and abide any condition stated in the CNP if it can be issued. An indicative assessment is undertaken at representative NSRs to identify any potential adverse noise impacts.

The construction programme in Appendix B sets out the time frame for the various tasks in the construction phase. It can be seen that the three major tasks mentioned will be performed consecutively (i.e. they are not concurrent). This important fact was noted in the assessment when the cumulative construction noise impact is considered.

A +3 dB(A) facade correction would be required to account for the facade effect at each NSR according to the GW-TM. It would be applicable to all PME items required for the construction activities in this Project.

5.5                   Identification, Prediction and Evaluation of Environmental Impacts

5.5.1             Construction Phase

From the tentative project programme in Appendix B, the three major tasks in the construction of the proposed submarine watermain are expected to be carried out consecutively while other works including pipe preparation and seawall reinstatement will be concurrent with the other activities as shown.

Trench dredging will be carried out along the proposed alignment of the submarine watermain while the temporary platform is located at the seafront of West Kowloon. Pipe preparation will therefore be performed at West Kowloon landfall site and pipe laying by bottom pull method will be at Sai Ying Pun landfall site. Since the types and number of plants mobilized in Sai Ying Pun and West Kowloon landfall site are different, the noise emission inventories have been established independently and provided in Tables 5-4 and 5-5. The plant inventories established as shown in Tables 5-4 and 5-5 are realistic, practical and valid for the completion of works within project programme as confirmed by the Project Proponent.

Table 54     Noise Emission Inventory (Sai Ying Pun)

Activity

Powered Mechanical Equipment

CNP Ref

No. of Plants

SWL/Unit, dB(A)

SWL, dB(A)

Trench Dredging

Grab dredgers+

CNP 063

2

112

115

Hopper barges #

-

2

-

-

Tug boats

CNP 221

2

110

113

Crane, barge mounted

CNP 048

2

112

115

 

 

 

 

Sub-SWL

119

 

 

 

 

 

 

Pipe laying

Generator

CNP 102

1

100

100

 

Winch (pneumatic)

CNP 261

1

110

110

 

Water pump (electric)

CNP 281

2

88

91

 

 

 

 

Sub-SWL

110

 

 

 

 

 

 

Backfilling

Crane, barge mounted

CNP 048

2

112

115

 

Hopper barges #

-

2

-

-

 

Tug boats

CNP 221

2

110

113

 

 

 

 

Sub-SWL

117

 

 

 

 

 

 

Seawall reinstatement

Crane, mobile/barge mounted

CNP 048

1

112

112

 

Truck / lorry

CNP 141

2

112

115

 

Piling machine

CNP 163

1

90

90

 

 

 

 

Sub-SWL

117

 

 

 

 

 

 

Note:   + One grab dredger will be used for dredging; while the other grab dredger will be used for trimming. Trimming will be carried out at the seawall at West Kowloon which would involve removal of armour rock for the set up of a temporary platform. Water quality impact arising from trimming activities is therefore not anticipated. Although dredging and trimming might be carried out simultaneously, cumulative water quality impact attributed to trimming activities is thus not anticipated.

# No noise would be emitted from hopper barges.

* The marine piling vessel is assumed to be an oscillator piling plant.

Table 55     Noise Emission Inventory (West Kowloon)

Activity

Powered Mechanical Equipment

CNP Ref

No. of Plants

SWL/Unit, dB(A)

SWL, dB(A)

Trench

Grab dredgers+

CNP 063

2

112

115

Dredging

Hopper barges #

-

2

-

-

 

Tug boats

CNP 221

2

110

113

 

Crane, barge mounted

CNP 048

2

112

115

 

 

 

 

Sub-SWL

119

 

 

 

 

 

 

Setting up of

Marine piling vessel

CNP 165*

2

115

118

Temporary

Hopper barges #

-

4

-

-

Platform

Tug boats

CNP 221

2

110

113

 

Crane, barge mounted

CNP 048

2

112

115

 

 

 

 

Sub-SWL

121

 

 

 

 

 

 

Pipe preparation

Truck/ lorry

CNP 141

2

112

115

Crane, mobile/barge mounted (diesel)

CNP 048

2

112

115

 

 

 

 

Sub-SWL

118

 

 

 

 

 

 

Pipe laying

Crane, mobile

CNP 048

1

112

112

 

Generator

CNP 102

1

100

100

 

 

 

 

Sub-SWL

112

 

 

 

 

 

 

Backfilling

Crane, barge mounted

CNP 048

2

112

115

 

Hopper barges #

-

2

-

-

 

Tug boats

CNP 221

2

110

113

 

 

 

 

Sub-SWL

117

 

 

 

 

 

 

Seawall reinstatement

Crane, mobile/barge mounted

CNP 048

1

112

112

 

Truck / lorry

CNP 141

2

112

115

 

Piling machine

CNP 163

1

90

90

 

 

 

 

Sub-SWL

117

 

 

 

 

 

 

Note:   + One grab dredger will be used for dredging; while the other grab dredger will be used for trimming. Trimming will be carried out at the seawall at West Kowloon which would involve removal of armour rock for the set up of a temporary platform. Water quality impact arising from trimming activities is therefore not anticipated. Although dredging and trimming might be carried out simultaneously, cumulative water quality impact attributed to trimming activities is thus not anticipated.

# No noise would be emitted from hopper barges.

* The marine piling vessel is assumed to be an oscillator piling plant.

5.5.2             Representative NSRs

Representative NSRs are chosen for assessment in both Sai Ying Pun and West Kowloon. In Sai Ying Pun, Richwealth Mansion (RWM) is used as it is closest to the landfall site and the north facade is facing the landfall site; In West Kowloon, the Union Square (KS6) which is closest to the landfall site is selected for indicative assessment although it does not fall into the 300m assessment boundary. With regard to the tentative project programme, noise generated affecting the NSRs were assessed.

Table 56     Selected NSRs for Noise Assessment

 

Sai Ying Pun

West Kowloon

Representative Noise Sensitive Receivers (NSRs)

RWM

KS6

Separation distance of Representative NSRs to landfall sites

215m

580m

Detailed calculations are provided in Table E2 and E5 of Appendix E. Dredging work in the Victoria Harbour will be separated from the NSRs with a distance greater than those in Table 5-3 and Table 5-6. However, to be conservative and to simplify the calculation, the trench dredging work is assumed to be carried out near the landfall site. Therefore, the distances used in Appendix E are taken as the distances in Table 5-6.

The noise impact from the possible night-time dredging is assessed. The construction noise level associated with the dredging is calculated and shown in Table E3 and E7 of Appendix E. Note that the noise levels assessed during Restricted Hours only include the proposed trench dredging work and are for indicative purpose only. It should be understood that despite any description or assessment made in this EIA Report on construction noise aspects, there is no guarantee that a Construction Noise Permit (CNP) will be granted for the proposed night-time works. Section 5.3 and 5.4 should be referred to for information on the proposed night-time work and relevant regulations. The predicted noise levels are summarized in Tables 5-7 and 5-8.

Table 57     Summary of Unmitigated Construction Noise Levels during Normal Daytime Working Hours

Representative NSRs

Predicted Unmitigated Construction Noise Levels during Normal Daytime Working Hour (0700 to 1900 on weekday) (dB(A))

Noise Criteria

(dB(A))

RWM (Sai Ying Pun)

59 – 68

75

KS6 (West Kowloon)

52 – 64

75

Table 58     Summary of Unmitigated Construction Noise Levels from dredging during Restricted Hours

Representative NSRs

Predicted Maximum

Construction Noise Levels

(dB(A))

 “Noise Criteria - All days during the evening (1900 to 2300 hours), and general holidays (including Sundays) during the daytime and evening (0700 to 2300 hours)”. 

 (dB(A))

Noise Criteria –

All days during Night time (2300 to 0700 hours)

(dB(A))

RWM

(Sai Ying Pun)

68

70

55

KS6

(West Kowloon)

59

70

55

5.5.3             Evaluation of Noise Impact

During normal daytime working hours, noise generated from the construction works fully comply with the Noise Criteria set in the TM. Without mitigation, it can be concluded that there will not be any adverse noise impact from the marine construction work during daytime, the evening (1900 to 2300 hours) of all normal days and of general holidays (including Sundays).

The calculation is conservative in view of the close separation distance to the NSRs assumed for dredging work. Most of the dredging work will be carried out within the harbour and will be far from the landfall sites at most of the time.

However, the predicted noise level exceeds the Noise Criteria at night time for dredging work carried out close to the landfall sites. If the night-time work (2300 to 0700 hours) is carried out, there will possibly be certain level of noise nuisance at a short period of time.

5.6                   Mitigation of Adverse Environmental Impacts

As shown in Table 5-7, the Noise Criteria at Daytime can be complied with at both Sai Ying Pun and West Kowloon. No mitigation measure is required but it is recommended that the Contractor shall take initiatives to further reduce the noise generated from the construction activities, including better arrangement of construction programme, the use of movable barriers, Quality PME and good site practices listed below.

The predicted noise level exceeds the Noise Criteria at night time for both Noise Sensitive Receivers KS6 and RWM but the Noise Criteria at evening time was complied with. It is therefore recommended that the dredging work should not be carried out as far as possible during night-time from the noise perspective. However, it is understood that due to the work programme and other constraints (e.g. the disturbance to the marine traffic during daytime), night-time dredging might be necessary. In case where night-time dredging is required and a Construction Noise Permit (CNP) can be granted, the noise at night time should be mitigated. The Contractor shall take into consideration the below recommendations prior to application of CNP and commencement of night-time work.

5.6.1             Work Schedule Rearrangement

Concurrent works should be such that necessary noisy works should be carried out at different time slots or spread around the construction sites. This will help to reduce the cumulative noise effect produced in the construction process.

If night-time (2300 to 0700 hours) dredging is required, the work shall be scheduled to carry out at a distance as far as possible to the NSRs. It is determined that the dredging work should be carried out at a location 750m away from the Sai Ying Pun landfall site and 450m from the West Kowloon landfall site along the trench as shown in the Figure 5.5. Under such condition, the separation distances to the NSRs (RWM & KS6) are increased to more than 900m. The night-time criteria of GW-TM can be complied because of the sufficient distance attenuation in noise level. The calculation is shown in the Table E4 and E8 in Appendix E while the results are summarised in the Table 5-9 below. It is noteworthy that the resulting noise levels should be smaller during the dredging since the separation distance would be larger than 900m in the dredging zone. The contractor will be required to adhere to the restricted locations of dredging work at night-time to comply with relevant noise standard.

Table 59     Summary of Mitigated Construction Noise Levels from dredging during Night time (2300 to 0700 hours)

Representative NSRs

Predicted Maximum

Construction Noise Levels

(dB(A))

Noise Criteria –

Night time (2300 to 0700 hours) (dB(A))

RWM (Sai Ying Pun)

55

55

KS6 (West Kowloon)

55

55

5.6.2             Using Quality PME

The use of Quality PME recognized by the Noise Control Authority for the purpose of CNP application can effectively reduce the noise generated from the construction plants. Quality PME are construction plants and equipments that are notably quieter, more environmental friendly and efficiently. The noise level reduction ranges from 5 – 10 dB(A) depending on the type of equipment used. The Contractor shall note the required procedures involved in application of the QPME.

5.6.3             Using Noise Barriers

Mobile or movable noise barriers to be erected near to the construction plants would reduce the noise levels for commonly 5 – 10 dB(A) depending on the types of items of PME and materials of the barriers. It is recommended that the Contractor shall screen noisy works and noise from stationary items of PME whenever practicable.

5.6.4             Good Site Practice

Good site practice and noise management can significantly reduce the impact of construction site activities on nearby NSRs.  The following package of measures should be followed during construction:

·           only well-maintained plant should be operated on-site and plant should be serviced regularly during the construction works;

·           machines and plant that may be in intermittent use should be shut down between work periods or should be throttled down to a minimum;

·           plant known to emit noise strongly in one direction, should, where possible, be orientated to direct noise away from the NSRs;

·           mobile plant should be sited as far away from NSRs as possible; and

·           material stockpiles and other structures should be effectively utilised, where practicable, to screen noise from on-site construction activities.

5.7                   Evaluation of Residual Impacts

No residual impacts are predicted for the construction or operation of the Project.

5.8                   Environmental Monitoring and Audit

Full compliance with the noise criteria will be achieved at all NSRs with the implementation of mitigation measures.  Environmental monitoring and audit is recommended to ensure that the noise levels do not exceed the criteria during the construction phase as discussed in the EM&A Manual.

5.9                   Conclusions and Recommendations

Construction noise impact to the NSRs has been assessed. It is predicted that major construction activities including dredging, laying of pipe and backfilling works would comply with the noise criteria stipulated in the EIAO-TM and NCO during daytime and evening (1900 to 2300 hours).

If night-time works (2300 to 0700 hours) are carried out, the location of dredging works should be restricted while there should be no work within the prohibited zones. With this measure being taken place, the night-time criteria during the dredging period can be complied with.

Work schedule rearrangement, quiet plants and mobile noise barriers are recommended to further suppress noise emissions from construction activities. Good site practices will be necessary to further reduce any potential impact to the noise sensitive receivers.

 


6                        WASTE IMPACT ASSESSMENT

6.1                   Introduction

The submarine watermain component of the Project across Victoria Harbour is a Designated Project under Schedule 2, Part 1I(E3) of the Environmental Impact Assessment Ordinance (EIAO) (Cap. 499) and an Environmental Permit (EP) issued under the EIAO is required for the construction and operation of the designated project.

In accordance with the EIA Study Brief No. ESB-132/2005, construction and operation waste management impact arising from the dredging, laying of pipe and backfilling works for the construction of the submarine watermain were assessed.

This section identifies the types of solid wastes that are likely to be generated during the construction of the submarine watermain and evaluates the potential environmental impacts that may result from these wastes.  The major solid waste would be dredged marine sediment from the construction of the proposed submarine watermain. Mitigation measures and good site practices, including waste handling, storage and disposal, are recommended with reference to the applicable waste legislation and guidelines.

6.2                   Environmental Legislation, Standards, Guidelines and Criteria

6.2.1             General

The criteria and guidelines for assessing waste management implications are outlined in Annex 7 and Annex 15 of the Technical Memorandum on Environmental Impact Assessment Process (EIAO-TM), respectively.

              The following legislation relates to the handling, treatment and disposal of wastes in the Hong Kong SAR and has been used in assessing potential impacts:

·         Waste Disposal Ordinance (Cap. 354)

·         Waste Disposal (Chemical Waste) (General) Regulation (Cap. 354)

·         Public Health and Municipal Services Ordinance (Cap. 132) - Public Cleansing and Prevention of Nuisances Regulation

·         Land (Miscellaneous Provisions) Ordinance (Cap. 28)

·         Dumping at Sea Ordinance (Cap. 466)

6.2.2             Waste Management

The Waste Disposal Ordinance (WDO) prohibits the unauthorised disposal of wastes.  Construction waste is defined as any substance, matter or thing that is generated from construction work and abandoned, whether or not it has been processed or stockpiled before being abandoned, but does not include any sludge, screenings or matter removed in or generated from any desludging, desilting or dredging works.  Under the WDO, wastes can be disposed of only at designated waste disposal facilities.

Under the WDO, the Chemical Waste (General) Regulation 1992 provides regulations for chemical waste control, and administers the possession, storage, collection, transport and disposal of chemical wastes.  The Environmental Protection Department (EPD) has also issued a ‘guideline’ document, the Code of Practice on the Packaging, Labelling and Storage of Chemical Wastes (1992), which details how the Contractor should comply with the regulations on chemical wastes.

The Public Cleansing and Prevention of Nuisances Regulation provides control on illegal tipping of wastes on unauthorised (unlicensed) sites.

6.2.3             Construction and Demolition (C&D) Materials

The current policy related to the dumping of C&D material is documented in the Works Branch Technical Circular No. 2/93, ‘Public Dumps’. Construction and demolition materials that are wholly inert, namely public fill, should not be disposed of to landfill, but taken to public filling areas, which usually form part of reclamation schemes.  The Land (Miscellaneous Provisions) Ordinance requires that dumping licences be obtained by individuals or companies who deliver public fill to public filling areas.  The Civil Engineering & Development Department (CEDD) issues the licences under delegated powers from the Director of Lands.

Under the Waste Disposal (Charges for Disposal of Construction Waste) Regulation, enacted in January 2006, construction waste delivered to a landfill for disposal must not contain more than 50% by weight of inert material.  Construction waste delivered to a sorting facility for disposal must contain more than 50% by weight of inert material, and construction waste delivered to a public fill reception facility for disposal must consist entirely of inert material.

Measures have been introduced under Environment, Transport and Works Bureau (ETWB) TCW No. 33/2002, “Management of Construction and Demolition Material Including Rock” to enhance the management of construction and demolition material, and to minimize its generation at source.  The enhancement measures include: (i) drawing up a Construction and Demolition Material Management Plan (C&DMMP) at the feasibility study or preliminary design stage to minimize C&D material generation and encourage proper management of such material; and (ii) providing the contractor with information from the C&DMMP in order to facilitate him in the preparation of the Waste Management Plan (WMP) and to minimize C&D material generation during construction.  Projects generating C&D material less than 50,000m3 or importing fill material less than 50,000m3 are exempt from the C&DMMP.  The new ETWB TCW No. 19/2005 “Environmental Management on Construction Sites” includes procedures on waste management requiring contractors to reduce the C&D material to be disposed of during the course of construction.  A Waste Management Plan should be submitted by the contractor prior to the commencement of construction works.

6.2.4             Marine Dredged Sediment

ETWB TCW No. 34/2002, “Management of Dredged/Excavated Sediment” sets out the procedures for seeking approval to dredge/excavate sediment and the management framework for marine disposal of such sediment.  Dredged marine sediment arising from the Project will be managed in accordance with the requirements of ETWB TCW No. 34/2002.  The sediment quality criteria for the classification of sediment are presented in Table 6-5.

In accordance with the Dumping at Sea Ordinance, application for dumping permits from EPD are required for marine disposal of dredged materials.

6.3                   Assessment Methodology

6.3.1             General

The criteria for assessing waste management implications are outlined in Annex 7 of the EIAO-TM.  The methods for assessing potential waste management impacts during the construction phase follow those presented in Annex 15 of the EIAO-TM and include the following:

·         Estimation of the types and quantities of the wastes generated.

·         Assessment of potential impacts from the management of solid waste with respect to potential hazards, air and odour emissions, noise, wastewater discharges and transport.

·         Assessment of impacts on the capacity of waste collection, transfer and disposal facilities.

6.3.2             Marine Site Investigation

The chemical characteristics of the dredged material within the dredged trench area as shown in Figure 2.3 include contaminated mud as indicated in the laboratory test results in the following reports

·           Agreement No. GEO 01/2000, Environmental Chemical & Biological Testing for the New Sediment Classification Framework - Maintenance Dredging for Central Fairway Phases 1, 2 & 3 - Sediment Quality Report (Mouchel Asia Ltd, March 2002) - Phase I (West Area) - sampling location points a18 to g19 inclusive on which Tier II & III tests (as per ETWBTC (W) No. 34/2002) were undertaken; and

·           CED Memo Ref. (35) in TS DF/NFYO/08 Pt.3 dated 16/5/2000 - Maintenance Dredging for Northern Fairway, Sediment Quality Report - Part of Contract No. CV/99/09 - Maintenance Dredging (2000-02) under Works Order No. MD/20/99 - sampling points R, S, T & U over lines 26 to 22. The assessment was based on the former classification system which has now been superseded by ETWBTC(W) No. 34/2002.

In this respect and with reference to ETWB TCW No. 34/2002, the marine investigations consist of vibrocore sampling on a 100m by 100m grid spacing with 100mm subsamples taken at seabed, 0.9m down, 1.9m down, 2.9m down, 5.9m down, 8.9m down and 11.9m down. As site investigation works are not permitted within the designated Fairways due to potential detrimental effects to marine traffic, the vibrocores are designed to be at an approximately 100m spacing taking into consideration offsets from areas outside the Fairways.

A total of 15 vibrocore pairs were taken at designated locations along the submarine watermain alignment to determine the vertical profile of sediment quality. Coordinates, type and depth of the vibrocores are summarised in Table 6-1. Locations of the vibrocore sampling points (given an ‘a’ suffix) are presented in Figure 6.2. Immediately adjacent to the ‘a’ vibrocores a second vibrocore denoted with a ‘b’ suffix was also taken. These vibrocores were used for logging purposes.

Table 61     Coordinates, Type and Depth of Vibrocores

Vibrocore

Coordinates

Material

Seabed level

Length

No.

Easting

Northing

Type

mPD

Recovered (m)

VC1a/b

832652

816956

Marine mud

-9.3

12.0

VC2a/b

833170

817533

Marine mud

-12.1

11.4

VC3a/b

833349

817640

Marine mud

-12.9

3.2

VC4a/b

833504

817790

Marine mud

-11.9

12.0

VC5a/b

833870

818135

Marine mud

-8.7

12.0

VC6a/b

833420

817709

Marine mud

-12.4

9.0

VC7a/b

833270

817569

Marine mud

-12.5

10.4

VC8a/b

832875

817045

Marine mud

-11.1

12.0

VC9a/b

832557

816917

Marine mud

-10.0

12.0

VC10a/b

832770

816999

Marine mud

-10.9

12.0

VC11a/b

832755

817329

Marine mud

-12.3

12.0

VC12a/b

833148

817065

Marine mud

-13.0

12.0

VC13a/b

833569

817850

Marine mud

-11.0

7.8

VC14a/b

833935

818214

Marine mud

-7.2

12.0

VC15a/b

833642

817911

Marine mud

-9.3

12.0

                   Note: Vibrocores denoted ’a’ & ’b’ were carried out in close proximity to each other, where ‘a’ vibrocores were laboratory testing samples while ‘b’ vibrocores were split for logging purposes.

6.3.3             Marine Dredged Sediment

General

Marine site investigation works of the Project were carried out in September 2006. Longitudinal geological profile of marine sediment along the proposed alignment of the submarine watermain is presented in Figure 6.1. Vibrocore records are presented in Appendix F1. The records indicated that the material along the proposed alignment of the submarine watermain consists mainly of marine deposits which are very soft, grey, sandy, silty clay with some gravel size shell fragments.

Laboratory testing of contaminants was included in the marine site investigation works to determine the level of contamination in the marine sediments at the existing seabed.  The works included vibrocoring at 15 locations distributed along the proposed submarine watermain alignment as detailed in Table 6-1. Locations of the vibrocore sampling points (given an ‘a’ suffix) are presented in Figure 6.2

Chemical Testing

Sample Arrangement

Tier II chemical screening was carried out to determine whether the sediment is suitable for open sea disposal without further testing in accordance with the requirements of ETWB TCW No. 34/2002. Sediment samples collected for chemical testing are presented in Table 6-2.

Table 62     Sample Arrangement for Chemical Testing

Vibrocore

Coordinates

Sample Depth

No.

Easting

Northing

From (m)

To (m)

VC1a

832652

816956

0

0.9

 

 

 

0.9

1.9

 

 

 

1.9

2.9

 

 

 

4.9

5.9

 

 

 

7.9

8.9

 

 

 

10.9

11.9

VC2a

833170

817533

0

0.9

 

 

 

0.9

1.9

 

 

 

1.9

2.9

 

 

 

4.9

5.9

 

 

 

7.9

8.9

 

 

 

10.9

11.3

VC3a

833349

817640

0

0.9

 

 

 

0.9

1.9

 

 

 

1.9

2.9

VC4a

833504

817790

0

0.9

 

 

 

0.9

1.9

 

 

 

1.9

2.9

 

 

 

4.9

5.9

 

 

 

7.9

8.9

 

 

 

10.9

11.9

VC5a

833870

818135

0

0.9

 

 

 

0.9

1.9

 

 

 

1.9

2.9

 

 

 

4.9

5.9

 

 

 

7.9

8.9

 

 

 

10.9

11.9

VC6a

833420

817709

0

0.9

 

 

 

0.9

1.9

 

 

 

1.9

2.9

 

 

 

4.9

5.9

 

 

 

7.9

8.9

VC7a

833270

817569

0

0.9

 

 

 

0.9

1.9

 

 

 

1.9

2.9

 

 

 

4.9

5.9

 

 

 

7.9

8.9

VC8a

832875

817045

0

0.9

 

 

 

0.9

1.9

 

 

 

1.9

2.9

 

 

 

4.9

5.9

 

 

 

7.9

8.9

 

 

 

10.9

11.9

VC9a

832557

816917

0

0.9

 

 

 

0.9

1.9

 

 

 

1.9

2.9

 

 

 

4.9

5.9

 

 

 

7.9

8.9

 

 

 

10.9

11.9

VC10a

832770

816999

0

0.9

 

 

 

0.9

1.9

 

 

 

1.9

2.9

 

 

 

4.9

5.9

 

 

 

7.9

8.9

 

 

 

10.9

11.9

VC11a

832755

817329

0

0.9

 

 

 

0.9

1.9

 

 

 

1.9

2.9

 

 

 

4.9

5.9

 

 

 

7.9

8.9

 

 

 

10.9

11.9

VC12a

833148

817065

0

0.9

 

 

 

0.9

1.9

 

 

 

1.9

2.9

 

 

 

4.9

5.9

 

 

 

7.9

8.9

 

 

 

10.9

11.9

VC13a

833569

817850

0

0.9

 

 

 

0.9

1.9

 

 

 

1.9

2.9

 

 

 

4.9

5.9

 

 

 

7.7

8.7

VC14a

833935

818214

0

0.9

 

 

 

0.9

1.9

 

 

 

1.9

2.9

 

 

 

4.9

5.9

 

 

 

7.9

8.9

 

 

 

10.9

11.9

VC15a

833642

817911

0

0.9

 

 

 

0.9

1.9

 

 

 

1.9

2.9

 

 

 

4.9

5.9

 

 

 

7.9

8.9

 

 

 

10.9

11.9

Sample Preparation

Continuous samples were taken vertically from seabed down to the bottom of the proposed dredged layers. Vibrocoring was terminated in the alluvium layer below the marine mud deposit. On recovery, each vibrocore was cut into sub-samples. The top level of the sub-samples were at seabed, 0.9m down, 1.9m down, 2.9m down, 5.9m down, 8.9m down and 11.9m down or to the termination depth of the vibrocore.

Sections of vibrocore tube were cut, sealed and capped, labelled, stored in a dark environment in a cool box below 40C immediately after collection on site.  On transfer from site to laboratory, samples were kept at below 40C, by regularly replacing the ice packs.

Determination Method and Reporting Limits

Chemical Testing was carried out for all vibrocores taken from the 15 locations. Each sub-sample recovered from vibrocoring was tested in the laboratory for the following parameters:

(i)        Metals concentrations including cadmium (Cd), chromium (Cr), copper (Cu), nickel (Ni), lead (Pb), zinc (Zn), mercury (Hg), arsenic (As) and silver (Ag).

(ii)      Concentrations of organic compounds including total polychlorinated biphenyls (PCBs), polyaromatic hydrocarbons (PAHs), and tributyltin (TBT).

Details of the determination methods and reporting limits are provided in Tables 6-3 and 6-4 respectively.

Table 63     Testing Methods and Reporting Limits for Metals and Metalloids Analysis

Code

Test Parameter

Preparation Method

USEPA Method

Determination Method

USEPA Method

Reporting limits (mg/kg)

Cd

Cadmium

3050B

6020A

0.20

Cr

Chromium

3050B

6010C

8.0

Cu

Copper

3050B

6010C

7.0

Ni

Nickel

3050B

6010C

4.0

Pb

Lead

3050B

6010C

8.0

Zn

Zinc

3050B

6010C

20

 

Hg

Mercury

7471A

7471A

0.05

As

Arsenic

3050B

6020A

1.0

 

Ag

Silver

3050B

6020A

0.10

Table 64     Testing Methods and Reporting Limits for TBT, PAHs and PCBs Analysis

Parameter

Method Reference

Reporting limits

Total PCB

USEPA 3550B & 8082

3 µg/kg

PAHs

USEPA 3550B, 3630C & 8270C

55 ug/kg for LMW PAHs

170 ug/kg for HMW PAHs

TBT in interstitial water

UNEP/IOC/IAEA

15 ng TBT/L

Sediment Classification

Dredged sediment destined for marine disposal are classified according to their level of contamination by 13 contaminants as detailed in Table 6-5:

Table 65     Sediment Quality Criteria for the Classification of Sediment

Contaminants

LCEL

UCEL

Heavy Metal (mg/kg dry weight)

Cadmium (Cd)

1.5

4

Chromium (Cr)

80

160

Copper (Cu)

65

110

Mercury (Hg)

0.5

1

Nickel (Ni)

40

40

Lead (Pb)

75

110

Silver (Ag)

1

2

Zinc (Zn)

200

270

Metalloid (mg/kg dry weight)

Arsenic

12

42

Organic-PAHs (µg/kg dry weight)

PAHs (Low Molecular Weight)

550

3160

PAHs (High Molecular Weight)

1700

9600

Organic-non-PAHs (µg/kg dry weight)

Total PCBs

23

180

Organometallics (µg-TBT L-1 in interstitial water)

Tributyltin

0.15

0.15

Source: Appendix A of ETWB TCW No. 34/2002 Management of Dredged / Excavated Sediment

                Note:    LCEL –   Lower Chemical Exceedance Level

                                UCEL –   Upper Chemical Exceedance Level

Sediments are categorised with reference to the LCEL and UCEL, as follows:

Category L

Sediment with all contaminant levels not exceeding the LCEL.  The material must be dredged, transported and disposed of in a manner that minimises the loss of contaminants either into solution or by suspension.

Category M

Sediment with any one or more contaminant levels exceeding the LCEL and none exceeding the UCEL.  The material must be dredged and transported with care, and must be effectively isolated from the environment upon final disposal unless appropriate biological tests demonstrate that the material will not adversely affect the marine environment

Category H

Sediment with any one or more contaminant levels exceeding the UCEL.  The material must be dredged and transported with great care, and must be effectively isolated from the environment upon final disposal.

In case of Category M and Category H contamination, the final determination of appropriate disposal options, routing and the allocation of a permit to dispose of material at a designated site will be made by EPD and the Marine Fill Committee (MFC) in accordance with the ETWB TCW No. 34/2002.

Biological Testing

For Category M sediment and Category H sediment with contaminant levels exceeding 10 times the LCEL, Tier III biological screening was carried out to determine the appropriate disposal methods in accordance with the requirements of ETWB TCW No. 34/2002.

Based on the results of the chemical testing and the estimated dredging depth of -8m for formation of the trench, the sediment samples presented in Table 6-6 were subjected to biological testing, with a total of six test samples:

Table 66     Composite Sample Arrangement for Biological Testing

Composite Sample No.

Vibrocore No.

Coordinates

Sample Depth

 

 

Easting

Northing

 

2

VC7a

833270

817569

-0.9 to - 1.9m

4

VC11a

832755

817329

-0.9 to - 1.9m

5

VC12a

833148

817065

0.0 to - 0.9m

6

VC13a

833569

817850

0.0 to - 0.9m

7

VC13a

833569

817850

-4.9 to – 5.9m

8

VC14a

833935

818214

0.0 to - 0.9m

The following three toxicity tests (to be considered as one set) were conducted on each sample:

·         a 10‑day burrowing amphipod toxicity test ; and

·         a 20‑day burrowing polychaete toxicity test; and

·         a 48‑96 hour larvae (bivalve or echinoderm) toxicity test.

The species used for each type of biological test and the test conditions are listed in Table 6-7 below.

Table 67     Test Species for Biological Testing

Test Types

Species

Reference Test Conditions*

10‑day  burrowing amphipod toxicity test

 

Leptocheirus plumulosus

 

USEPA (1994)

20‑day  burrowing polychaete toxicity test

Neanthes arenaceodentata

PSEP (1995)

 

 

48‑96 hour bivalve larvae

toxicity test 

Crassostrea gigas

 

PSEP (1995)

Notes:*

(i)   U.S.EPA (U.S. Environmental Protection Agency) 1994.  Methods for assessing the toxicity of sediment-associated contaminants with estuarine and marine amphipods.  Office of Research and Development. U.S. Environmental Protection Agency, Cincinnati, OH. EPA/600/R94/025.

(ii)  PSEP (Puget Sound Estuary Program) 1995. Recommended guidelines for conducting laboratory bioassays on Puget Sound sediments.

Sediment samples were characterized by the testing laboratory for ancillary testing parameters such as porewater salinity, ammonia, TOC, grain size and moisture content.  This provided necessary information on the general characteristics of the sediment.

The test endpoints and decision criteria are summarized in Table 6-8. The sediment was deemed to have failed the biological testing if it failed in any one of the three toxicity tests.

Table 68     Test endpoints and decision criteria for biological testing

Toxicity test

 

Endpoints measured

Failure criteria

10-day amphipod

 

 

Survival

 

Mean survival in test sediment is significantly different (p £ 0.05)1 from mean survival in reference sediment and mean survival in test sediment < 80% of mean survival in reference sediment.

20-day polychaete

Dry Weight2

Mean dry weight in test sediment is significantly different (p £ 0.05)1 from mean dry weight in reference sediment and mean dry weight in test sediment < 90% of mean dry weight in reference sediment.

 

48-96 hour bivalve larvae

 

Normality Survival3

Mean normality survival in test sediment is significantly different (p £ 0.05)1 from mean normality survival in reference sediment and mean normality survival in test sediment < 80% of mean normality survival in reference sediment.

 

1 Statistically significant differences should be determined using appropriate two-sample comparisons (e.g., t-tests) at a probability of  p£ 0.05.

2 Dry weight means total dry weight after deducting dead and missing worms.

3 Normality survival integrates the normality and survival end points, and measures survival of only the normal larvae relative to the starting number.

6.4                   Baseline Condition of Marine Dredged Sediment

6.4.1             Chemical Screening

The marine sediment quality analysis results of chemical screening from the marine site investigation works are included as Appendix F2, as compared with the sediment quality criteria for the classification of sediment, are presented in Table 6-9.

The sediment chemical testing results indicate that Category L sediments were found at all depths at vibrocores VC2a and 3a.  Category M sediment was found at vibrocores VC4a, 7a, 8a, 11a, 12a, 13a, 14a and 15a in terms of Cd, Cu, Pb, Zn, Hg, As, Ag, low molecular weight PAHs and high molecular weight PAHs. Category H sediment was found at vibrocores VC1a, 4a, 5a, 6a, 8a, 9a, 10a, 11a and 13a. The contamination is high in terms of Cu, Pb, Hg, and Ag. Sediment samples VC4a, 7a, 8a, 11a, 12a, 13a, 14a and 15a were required to proceed to Tier III biological screening.

Table 69     Contaminant Levels of Vibrocore Samples and Their Categories

Vibrocore No.

From (m)

To

(m)

Material

LMW

HMW

Total PCBs

Metals

TBT

Overall Category

Disposal Type

Type

PAHs

PAHs

mg/kg

ng/L

 

ug/kg

ug/kg

ug/kg

Cd

Cr

Cu

Ni

Pb

Zn

Hg

As

Ag

 

VC1a

0

0.9

Clay

<55

<170

<3

<0.20

21

9.8

18

39

61

1.2

4.5

0.10

<0.015

H

2

VC1a

0.9

1.9

Clay

<55

<170

<3

<0.20

24

<7.0

19

18

52

0.06

3.3

<0.10

<0.015

L

1

VC1a

1.9

2.9

Clay

<55

<170

<3

<0.20

26

7.9

20

24

62

0.08

4.7

<0.10

<0.015

L

1

VC1a

4.9

5.9

Clay

<55

<170

<3

<0.20

27

10

19

30

59

0.09

7.1

<0.10

<0.015

L

1

VC1a

7.9

8.9

Clay

<55

<170

<3

<0.20

21

7.5

16

26

48

0.07

5.3

<0.10

<0.015

L

1

VC1a

10.9

11.9

Clay

<55

<170

<3

<0.20

27

12

20

37

63

0.08

10

<0.10

<0.015

L

1

VC2a

0

0.9

Clay

<55

<170

<3

<0.20

19

8.5

17

20

47

0.16

2.5

<0.10

<0.015

L

1

VC2a

0.9

1.9

Clay

<55

<170

<3

<0.20

16

<7.0

12

18

39

0.06

3.7

<0.10

<0.015

L

1

VC2a

1.9

2.9

Clay

<55

<170

<3

<0.20

22

7.4

18

20

50

0.07

3.9

<0.10

<0.015

L

1

VC2a

4.9

5.9

Clay

<55

<170

<3

<0.20

33

13

26

34

68

0.06

7.8

<0.10

<0.015

L

1

VC2a

7.9

8.9

Clay

<55

<170

<3

<0.20

28

11

17

30

51

0.08

11

<0.10

<0.015

L

1

VC2a

10.9

11.3

Clay

<55

<170

<3

<0.20

18

7.7

<4.0

48

37

0.05

7.4

<0.10

<0.015

L

1

VC3a

0

0.9

Clay

<55

<170

<3

<0.20

17

<7.0

14

17

45

0.07

4.2

<0.10

<0.015

L

1

VC3a

0.9

1.9

Clay

<55

<170

<3

<0.20

29

10

23

37

78

0.13

6.2

<0.10

<0.015

L

1

VC3a

1.9

2.9

Silt

<55

<170

<3

<0.20

29

12

25

33

68

0.09

10

0.11

<0.015

L

1

VC4a

0

0.9

Clay

<55

1000

<3

0.36

26

77

13

130

190

0.28

5.5

2.1

<0.015

H

2

VC4a

0.9

1.9

Clay

<55

<170

<3

<0.20

22

9.4

18

22

54

0.08

5.6

<0.10

<0.015

L

1

VC4a

1.9

2.9

Clay

<55

<170

<3

<0.20

18

<7.0

15

20

44

<0.05

3.4

<0.10

<0.015

L

1

VC4a

4.9

5.9

Clay

<55

<170

<3

<0.20

33

13

26

35

75

0.07

6.8

<0.10

<0.015

L

1

VC4a

7.9

8.9

Clay

<55

<170

<3

<0.20

21

10

15

26

50

0.14

7.2

<0.10

<0.015

L

1

VC4a

10.9

11.9

Clay

<55

<170

<3

<0.20

<8.0

<7.0

<4.0

62

<20

0.62

5.0

<0.10

<0.015

M

1D

VC5a

0

0.9

Clay

<55

<170

<3

0.38

45

140

22

38

110

0.30

7.3

1.4

<0.015

H

2

VC5a

0.9

1.9

Clay

<55

<170

<3

<0.20

25

8.3

18

46

54

0.09

4.4

<0.10

<0.015

L

1

VC5a

1.9

2.9

Clay

<55

<170

<3

<0.20

33

9.4

23

24

63

0.08

5.2

0.16

<0.015

L

1

VC5a

4.9

5.9

Clay

<55

<170

<3

<0.20

29

9.4

20

28

57

0.06

5.1

<0.10

<0.015

L

1

VC5a

7.9

8.9

Clay

<55

<170

<3

<0.20

21

7.6

15

22

49

0.08

3.7

<0.10

<0.015

L

1

VC5a

10.9

11.9

Clay

<55

<170

<3

<0.20

23

8.3

17

31

52

0.28

6.1

<0.10

<0.015

L

1

VC6a

0

0.9

Clay

690

<170

41

0.45

23

360

13

69

250

0.63

6.3

1.7

<0.015

H

2

VC6a

0.9

1.9

Clay

<55

<170

<3

<0.20

23

10

19

25

64

0.23

2.7

<0.10

<0.015

L

1

VC6a

1.9

2.9

Clay

<55

<170

<3

<0.20

26

10

21

30

56

0.11

5.4

<0.10

<0.015

L

1

VC6a

4.9

5.9

Clay

<55

<170

<3

<0.20

27

12

23

28

56

0.10

6.4

<0.10

<0.015

L

1

VC6a

7.9

8.9

Clay

<55

<170

<3

<0.20

29

17

22

40

68

0.15

7.6

0.11

<0.015

L

1

VC7a

0

0.9

Clay

<55

<170

<3

<0.2

16

11

13

38

46

0.17

4.2

0.15

<0.015

L

1

VC7a

0.9

1.9

Clay

780

9200

<3

<0.2

20

<7.0

17

17

42

0.08

3.0

<0.10

<0.015

M

2

VC7a

1.9

2.9

Clay

<55

<170

<3

<0.2

20

<7.0

18

17

49

0.09

3.9

<0.10

<0.015

L

1

VC7a

4.9

5.9

Clay

<55

<170

<3

<0.20

31

14

23

40

70

0.09

9.1

<0.10

<0.015

L

1

VC7a

7.9

8.9

Clay

<55

<170

<3

<0.20

12

<7.0

<4.0

10

<20

<0.05

2.3

<0.10

<0.015

L

1

VC8a

0

0.9

Silt

<55

<170

<3

0.69

55

190

22

84

180

0.92

7.6

3.1

<0.015

H

2

VC8a

0.9

1.9

Silt

<55

<170

<3

<0.20

24

9.0

19

33

62

0.26

3.8

<0.10

<0.015

L

1

VC8a

1.9

2.9

Clay

<55

<170

<3

<0.20

22

<7.0

17

19

52

0.07

4.4

<0.10

<0.015

L

1

VC8a

4.9

5.9

Clay

<55

<170

<3

<0.20

26

12

20

32

60

0.10

8.5

<0.10

<0.015

L

1

VC8a

7.9

8.9

Clay

<55

<170

<3

<0.20

26

12

19

38

60

0.11

9.4

<0.10

<0.015

L

1

VC8a

10.9

11.9

Clay

<55

<170

<3

<0.20

24

12

17

38

58

0.09

13

<0.10

<0.015

M

1D

VC9a

0

0.9

Clay

130

1100

5.2

0.40

26

65

15

100

120

1.1

8.2

1.8

<0.015

H

2

VC9a

0.9

1.9

Clay

<55

<170

<3

<0.20

22

<7.0

19

20

57

0.12

3.7

<0.10

<0.015

L

1

VC9a

1.9

2.9

Clay

<55

<170

18

<0.20

25

7.4

19

22

61

0.06

4.2

<0.10

<0.015

L

1

VC9a

4.9

5.9

Clay

<55

<170

<3

<0.20

28

12

20

30

60

0.08

8.0

<0.10

<0.015

L

1

VC9a

7.9

8.9

Clay

<55

<170

<3

<0.20

22

7.8

17

26

48

0.09

5.2

<0.10

<0.015

L

1

VC9a

10.9

11.9

Clay

<55

<170

<3

<0.20

23

11

17

30

56

0.07

9.4

<0.10

<0.015

L

1

VC10a

0

0.9

Clay

<55

420

6.0

0.69

52

170

21

78

190

0.99

7.3

2.9

<0.015

H

2

VC10a

0.9

1.9

Clay

<55

<170

<3

<0.20

23

7.6

17

20

50

0.10

5.0

<0.10

<0.015

L

1

VC10a

1.9

2.9

Clay

<55

<170

<3

<0.20

22

<7.0

16

20

46

0.07

4.9

<0.10

<0.015

L

1

VC10a

4.9

5.9

Clay

<55

<170

<3

<0.20

27

9.8

20

35

58

0.10

7.2

<0.10

<0.015

L

1

VC10a

7.9

8.9

Clay

<55

<170

<3

<0.20

27

10

20

28

59

0.10

7.4

<0.10

<0.015

L

1

VC10a

10.9

11.9

Clay

<55

<170

<3

<0.20

27

12

18

32

58

0.08

10

<0.10

<0.015

L

1

VC11a

0

0.9

Anthropogenic Deposit

<55

<170

<3

0.39

24

61

11

46

120

0.58

7.6

2.4

<0.015

H

2

VC11a

0.9

1.9

Clay

<55

<170

6.3

0.29

36

50

18

78

130

0.62

7.2

1.1

<0.015

M

1D

VC11a

1.9

2.9

Clay

<55

<170

<3

<0.20

23

7.1

19

18

53

0.06

5.6

<0.10

<0.015

L

1

VC11a

4.9

5.9

Clay

<55

<170

<3

<0.20

29

11

20

31

60

0.14

8.9

0.45

<0.015

L

1

VC11a

7.9

8.9

Clay

<55

<170

<3

<0.20

28

13

20

31

68

0.09

11

<0.10

<0.015

L

1

VC11a

10.9

11.9

Clay

<55

<170

<3

<0.20

18

8.5

10

24

37

0.06

12

<0.10

<0.015

L

1

VC12a

0

0.9

Anthropogenic Deposit

<55

<170

<3

<0.20

15

58

7.3

28

65

0.28

7.3

1.3

<0.015

M

2

VC12a

0.9

1.9

Gravel

<55

<170

<3

<0.20

32

14

23

38

69

0.19

10

0.14

<0.015

L

1

VC12a

1.9

2.9

Clay

<55

<170

<3

<0.20

20

7.2

15

23

43

0.12

4.3

<0.10

<0.015

L

1

VC12a

4.9

5.9

Clay

<55

<170

<3

<0.20

29

12

18

35

61

0.24

10

<0.10

<0.015

L

1

VC12a

7.9

8.9

Clay

<55

<170

<3

<0.20

28

12

18

38

60

0.12

9.4

<0.10

<0.015

L

1

VC12a

10.9

11.9

Silt

<55

<170

<3

<0.20

10

<7.0

6.1

16

22

0.07

4.9

<0.10

<0.015

L

1

VC13a

0

0.9

Clay

140

2600

<3

0.25

21

55

9.2

55

98

0.25

4.8

1.7

<0.015

M

1D

VC13a

0.9

1.9

Clay

180

1300

7.5

0.84

60

270

22

110

190

0.89

6.6

2.4

<0.015

H

2

VC13a

1.9

2.9

Clay

<55

<170

<3

<0.20

21

7.2

21

21

50

0.09

4.8

<0.10

<0.015

L

1

VC13a

4.9

5.9

Clay

<55

<170

<3

2.8

29

12

23

34

70

0.15

6.6

<0.10

<0.015

M

1D

VC13a

7.7

8.7

Clay

<55

<170

<3

<0.20

20

7.1

12

20

38

0.05

4.7

<0.10

<0.015

L

1

VC14a

0

0.9

Silt

<55

<170

<3

0.28

33

80

16

28

81

0.25

5.4

1.4

<0.015

M

2

VC14a

0.9

1.9

Silt

<55

<170

<3

<0.20

23

16

15

18

50

0.10

4.5

0.10

<0.015

L

1

VC14a

1.9

2.9

Clay

<55

<170

<3

<0.20

33

10

22

46

63

0.11

5.5

<0.10

<0.015

L

1

VC14a

4.9

5.9

Clay

<55

<170

<3

<0.20

32

9.0

21

30

59

0.09

4.6

<0.10

<0.015

L

1

VC14a

7.9

8.9

Clay

<55

<170

<3

<0.20

31

10

21

27

58

0.08

4.0

<0.10

<0.015

L

1

VC14a

10.9

11.9

Clay

<55

<170

<3

<0.20

36

13

21

44

63

0.28

8.9

<0.10

<0.015

L

1

VC15a

0

0.9

Clay

<55

<170

<3

<0.20

26

36

16

21

62

0.11

4.6

0.40

<0.015

L

1

VC15a

0.9

1.9

Clay

<55

<170

<3

<0.20

28

7.5

22

17

59

0.06

3.8

<0.10

<0.015

L

1

VC15a

1.9

2.9

Clay

<55

<170

<3

<0.20

27

7.7

20

19

59

0.06

4.7

<0.10

<0.015

L

1

VC15a

4.9

5.9

Clay

<55

<170

<3

<0.20

30

10

20

28

55

0.10

5.2

<0.10

<0.015

L

1

VC15a

7.9

8.9

Clay

<55

<170

<3

<0.20

30

10

20

32

57

0.06

6.2

0.10

<0.015

L

1

VC15a

10.9

11.9

Clay

<55

<170

<3

<0.20

29

11

15

27

50

0.07

15

<0.10

<0.015

M

2

Notes:

1.        LMW = Low molecular weight PAHs, that is, acenaphthene, acenaphthylene, anthracene, fluorene, naphthalene and phenanthrene.

2.        HMW = High molecular weight PAHs, that is, benzo[a]anthracene, benzo[a]pyrene, chrysene, dibenzo[a,h]anthracene, fluoranthene, pyrene, benzo[b]fluoranthene, benzo[k]fluoranthene, indeno[1,2,3-c,d]pyrene and benzo[g,h,i]perylene.

3.        Values underlined indicate Category M sediment under ETWB TCW No. 34/2002.

4.        Values in bold indicate Category H sediment under ETWB TCW No. 34/2002.

5.        Values in bold and underlined indicate Category H sediment under ETWB TCW No. 34/2002 and that the contaminant level exceeded the LCEL by 10 times.

6.        Disposal Type 1 = Type 1 - Open Sea Disposal, Disposal Type 1D = Type 1 - Open Sea Disposal (Dedicated Sites) and Disposal Type 2 = Type 2 – Confined Marine Disposal


 

A summary of classification of the vibrocore samples is provided in Table 6-10. The majority of the sediment samples (78%) were classified as Category L.

Table 610   Summary of Classification of Vibrocore Samples

Category

Number of Vibrocore Samples

Category L

66

Category M

9

Category H

9

Category H (10 x > LCEL)

0

6.4.2             Biological Screening

The marine sediment quality analysis results of biological screening from the site investigation works were presented in a comprehensive laboratory testing report and is provided in Appendix F3.

The general characteristics of the marine sediment is provided in the ancillary tests results summarised in Table 6-11.

Table 611   Summary of Ancillary Tests Results

Composite Sample No.

Vibrocore No.

Interstitial ammonia

(mgNH3/L)

Interstitial salinity

(ppt)

Grain Size < 63mm (%)

Mositure Content (%)

TOC

(% Wet Weight)

TOC

(% Dry Weight)

2

VC7a

See Note 1

29

44

51

0.49

0.74

4

VC11a

9.2

33

62

53

0.66

1.01

5

VC12a

16.4

33

18

40

0.40

0.56

6 & 7

VC13a

14.8

35

40

59

0.62

0.99

8

VC14a

4.3

30

83

93

0.70

1.35

Note: 1. Analysis was not performed due to insufficient amount of porewater obtained.

The sediment biological screening results indicated that composite sample no. 2, 5 and 8 failed the toxicity tests. The sediment was deemed to have failed the biological test if it fails in any one of the three toxicity tests. A summary of toxicity tests failure is provided in Table 6-12.

Table 612   Summary of Toxicity Test Failure

Toxicity Test

Test Failure (Composite Sample No.)

10-day amphipod

Nil

20-day polychaete

Nil

48-96 hour bivalve larvae

2, 5 and 8

6.5                   Identification and Evaluation of Environmental Impacts

6.5.1             Construction Phase

The construction activities to be carried out for construction of the proposed submarine watermain would generate a variety of wastes that can be divided into distinct categories based on their composition and ultimate method of disposal.  The identified waste types include:

·           Construction and demolition (C&D) materials

·           General refuse; and

·           Chemical waste

·           Marine dredged sediment

Each type of waste arising is described below, together with an evaluation of the potential environmental impacts associated with generation, handling, storage and transport of the waste.

Construction and Demolition (C&D) Materials

Excavated materials would arise from the excavation works for the landing points of the submarine watermain. It is anticipated that the volume of excavated material to be generated would be small and in the order of a few hundred cubic metres. In order to minimise the impact resulting from collection and transportation of C&D material for off-site disposal, the excavated material which comprise of reclamation fill material that could be reused on-site as fill material should be reused on-site as backfilling material for the construction of the associated landmains as far as practicable. The amount of C&D material to be generated would be quantified in the site Waste Management Plan to be prepared by the Contractor.

General Refuse

The construction workforce will generate refuse comprising food scraps, waste paper, empty containers, etc.  Such refuse should be properly managed so intentional or accidental release to the surrounding environment does not occur.  Disposal of refuse at sites other than approved waste transfer or disposal facilities shall be prohibited.  Effective collection of site wastes will be required to prevent waste materials being blown around by wind, flushed or leached into the marine environment, or creating an odour nuisance or pest and vermin problem. Waste storage areas shall be well maintained and cleaned regularly.  With the implementation of good waste management practices at the site, adverse environmental impacts are not expected to arise from the storage, handling and transportation of workforce wastes.  The maximum number of construction workers to be employed is estimated to be about 100 workers.  Based on a generation rate of 0.65 kg per worker per day, the maximum daily arising of general refuse during the construction period would be approximately 65 kg and this waste can be effectively controlled by normal measures.

Chemical Waste

The maintenance and servicing of construction plant and equipment may generate some chemical wastes such as cleaning fluids, solvents, lubrication oil and fuel.  Maintenance of vehicles may also involve the use of a variety of chemicals, oil and lubricants.  It is difficult to quantify the amount of chemical waste that will arise from the construction activities since it will be dependent on the Contractor’s on-site maintenance requirements and the amount of plant utilised.  However, it is anticipated that the quantity of chemical waste, such as lubricating oil and solvent produced from plant maintenance, would be small and in the order of a few cubic metres per month.  The amount of chemical waste to be generated will be quantified in the site Waste Management Plan to be prepared by the Contractor.

Chemical wastes arising during the construction phase may pose environmental, health and safety hazards if not stored and disposed of in an appropriate manner as stipulated in the Waste Disposal (Chemical Waste) (General) Regulations. The potential hazards include:

·         Toxic effects to workers

·         Adverse impacts on water quality from spills and associated adverse impacts on marine biota; and

·         Fire hazards.

Materials classified as chemical wastes would require special handling and storage arrangements before removal for appropriate treatment at the approved Chemical Waste Treatment Facility.  Wherever possible opportunities should be taken to reuse and recycle materials.  Mitigation and control requirements for chemical wastes are detailed in Section 6.6.5.  Provided that the handling, storage and disposal of chemical wastes are in accordance with these requirements, adverse environmental impacts are not expected.

Marine Dredged Sediment

In accordance with ETWB TC(W) No. 34/2002 - Managmeent of Dredged/Excavated Sediment, review of existing information for site contamination assessment (Tier I), chemical screening (Tier II) and biological screening (Tier III) were conducted along the trench to be dredged for submarine watermain installation to determine the sediment quality. Sediments were classified into Category L, M and H based on its contaminant levels identified from chemical screening. Sediment classified as Category M was then subjected to biological screening. The corresponding types of disposal required were thus identified and presented numerically in Table 6-9 and graphically in Figure 6.3.

The existing seabed area would be dredged to lay the submarine watermain. According to Figure 6.3, the total volume of dredged sediment was estimated to be approximately 543,000 m3.  The estimated volume of contaminated dredged sediment was approximately 212,000 m3.  The potential environmental effects of the removal of these sediments on water quality have been assessed and presented in Section 3 of this Report.

To minimize any potential adverse impacts arising from the dredged marine sediment, the sediment shall be dredged, transported and disposed of in a manner that will minimise the loss of contaminants either into solution or by resuspension.  Mitigation measures to minimise potential environmental impacts are described in Section 6.6.6.  With the implementation of mitigation measures, no unacceptable impacts would be expected from the transportation and disposal of the dredged sediment.

6.5.2             Operation Phase

No solid wastes are anticipated to be generated during operation except for minor quantities of material collected during maintenance inspections.

6.6                   Mitigation of Adverse Environmental Impacts

6.6.1             Good Site Practices

Adverse impacts related to waste management are not expected to arise, provided that good site practices are strictly followed.  Recommendations for good site practices during the construction activities include:

·         Nomination of an approved person, such as a site manager, to be responsible for good site practices, arrangements for collection and effective disposal to an appropriate facility, of all wastes generated at the site

·         Training of site personnel in proper waste management and chemical handling procedures

·         Provision of sufficient waste disposal points and regular collection of waste

·         Appropriate measures to minimise windblown litter and dust during transportation of waste by either covering trucks or by transporting wastes in enclosed containers

6.6.2             Waste Reduction Measures

Good management and control can prevent the generation of a significant amount of waste.  Waste reduction is best achieved at the planning and design stage, as well as by ensuring the implementation of good site practices.  Recommendations to achieve waste reduction include:

·         Sort C&D material from demolition and decommissioning of the existing facilities to recover recyclable portions such as metals

·         Segregation and storage of different types of waste in different containers, skips or stockpiles to enhance reuse or recycling of materials and their proper disposal

·         Encourage collection of aluminium cans by providing separate labelled bins to enable this waste to be segregated from other general refuse generated by the work force

·         Proper storage and site practices to minimise the potential for damage or contamination of construction materials

·         Plan and stock construction materials carefully to minimise amount of waste generated and avoid unnecessary generation of waste.

In addition to the above measures, specific mitigation measures are recommended below for the identified waste arising to minimise environmental impacts during handling, transportation and disposal of these wastes.

6.6.3             C&D Material

In order to minimise impacts resulting from collection and transportation of C&D material for off-site disposal, the excavated materials should be reused on-site as backfilling material and for landscaping works for the associated land mains as far as practicable.  In addition, C&D material generated from excavation works should be disposed of at public fill reception facilities for other beneficial uses.  Other mitigation requirements are listed below:

·         A Waste Management Plan should be prepared.

·         A recording system for the amount of wastes generated, recycled and disposed (including the disposal sites) should be proposed.

·         In order to monitor the disposal of C&D material and solid wastes at public filling facilities and landfills, and to control fly-tipping, a trip-ticket system (e.g. ETWB TCW No. 31/2004) should be included.

6.6.4             General Refuse

General refuse should be stored in enclosed bins or compaction units separate from C&D material.  A reputable waste collector should be employed by the contractor to remove general refuse from the site, separately from C&D material.  Preferably an enclosed and covered area should be provided to reduce the occurrence of 'wind blown' light material.

6.6.5             Chemical Waste

If chemical wastes are produced at the construction site, the Contractor would be required to register with the EPD as a chemical waste producer and to follow the guidelines stated in the Code of Practice on the Packaging, Labelling and Storage of Chemical Wastes. Good quality containers compatible with the chemical wastes should be used, and incompatible chemicals should be stored separately.  Appropriate labels should be securely attached on each chemical waste container indicating the corresponding chemical characteristics of the chemical waste, such as explosive, flammable, oxidizing, irritant, toxic, harmful, corrosive, etc.  The Contractor shall use a licensed collector to transport and dispose of the chemical wastes, to either the approved Chemical Waste Treatment Centre, or another licensed facility, in accordance with the Waste Disposal (Chemical Waste) (General) Regulation.

6.6.6             Marine Dredged Sediment

The basic requirements and procedures for dredged mud disposal are specified under the ETWB TCW No. 34/2002.  The management of the dredging, use and disposal of marine mud is monitored by the MFC, while the licensing of marine dumping is the responsibility of the Director of Environmental Protection (DEP).

The dredged marine sediments would be loaded onto barges and transported to designated disposal sites depending on their level of contamination.  Based on the chemical and biological screening results and subsequently the corresponding types of disposal required as presented in Table 6-9 and Figure 6.3, it was estimated that some 326,000m3 of sediments would be suitable for open sea disposal (Type 1), some 5,000 m3 of sediments would be suitable for open sea disposal (dedicated sites) (Type 1) and 212,000m3 of sediments would require confined marine disposal (Type 2).  Agreement from Marine Fill Committee for the dredging rationale was obtained as presented in Appendix F4. Moreover, Marine Fill Committee has no comment on the proposed disposal arrangements. In accordance with the ETWB TCW No. 34/2002, the contaminated material must be dredged and transported with great care, and the mitigation measures recommended in Section 3 of this Report should be strictly followed.  Furthermore, the dredged contaminated sediment must be effectively isolated from the environment upon final disposal and shall be disposed of at the East Sha Chau Contaminated Mud Pits that is designated for the disposal of contaminated mud in Hong Kong.

During transportation and disposal of the dredged marine sediments, the following measures should be taken to minimise potential impacts on water quality:

·         Bottom opening of barges shall be fitted with tight fitting seals to prevent leakage of material. Excess material shall be cleaned from the decks and exposed fittings of barges and dredgers before the vessel is moved.

·         Monitoring of the barge loading shall be conducted to ensure that loss of material does not take place during transportation.  Transport barges or vessels shall be equipped with automatic self-monitoring devices as specified by the EPD.

·         Barges or hopper barges shall not be filled to a level that would cause the overflow of materials or sediment laden water during loading or transportation.

Table 6-13 provides a summary of the various waste types likely to be generated during the construction activities for the proposed submarine watermain, together with the recommended handling and disposal methods.


Table 613   Summary of Waste Handling Procedures and Disposal Routes

Waste Material Type

Generated from works item

Timing to be Generated

Total Quantity Generated

Quantity to be disposed off-site

Disposal

Handling

Marine Dredged Sediment (Uncontaminated)

Trench excavation

Sep 08 to Aug 09

331,000 m3

331,000 m3

MFC gazetted marine disposal ground – open sea disposal site

 

Minimise resuspension by use of closed grab, controlled loading and transfer

Marine Dredged Sediment (Contaminated)

Trench excavation

Sep 08 to Aug 09

212,000 m3

212,000m3

East Sha Chau contaminated mud pit

Minimise resuspension by use of closed grab, tight seal on barges, controlled loading and transfer

C&D Material

Excavation works

 

Sep 08 to May 11

Few hundred cubic meters (preliminary estimate)

 

Few hundred cubic meters (preliminary estimate)

To be reused on-site for construction of the associated landmains or

To be disposed to public fill reception points for other beneficial uses  or

To be disposed to landfill

Segregate inert C&D material to avoid contamination from other waste arisings

General Refuse

Waste paper, discarded containers, etc. generated from workforce

Sep 08 to May 11

65 kg per day (preliminary estimate based on workforce of 100)

 

65 kg per day

Refuse station for compaction and containerisation and then to landfill

Provide on-site refuse collection points

Chemical Waste

Cleansing fluids, solvent, lubrication oil and fuel from construction plant and equipment

Sep 08 to May 11

Few cubic metres per month

(preliminary estimate)

 

Few cubic metres per month

(preliminary estimate)

 

Chemical Waste Treatment Centre

Recycle on-site or by licensed companies.

Stored on-site within suitably designed containers

6.7                   Evaluation of Residual Impacts

With the implementation of the recommended mitigation measures for the handling, transportation and disposal of the identified waste arising, no residual impact is expected to arise during the construction and operation of the proposed submarine watermain.

6.8                   Environmental Monitoring and Audit

Waste management would be the contractor’s responsibility to ensure that all wastes produced during the construction of the submarine watermain are handled, stored and disposed of in accordance with good waste management practices and EPD’s regulations and requirements.  The recommended mitigation measures shall form the basis of the site Waste Management Plan to be developed by the Contractor in the construction stage.

Auditing of each waste stream should be carried out periodically to determine if wastes are being managed in accordance with approved procedures and the site Waste Management Plan.  The audits should look at all aspects of waste management including waste generation, storage, recycling, treatment, transport and disposal.  An appropriate audit programme would be to undertake a first audit at the commencement of the construction works, and then to audit weekly thereafter.

6.9                   Conclusions and Recommendations

A review of the sediment quality data from the marine site investigation indicated that the majority of the marine sediments to be dredged along the proposed submarine watermain were classified as Category L.  The total dredged volume for the Project was estimated as 543,000 m3, of which 212,000 m3 of sediment was classified as requiring confined marine disposal. With the implementation of the recommended mitigation measures and management procedures in accordance with the requirements of ETWB TCW No. 34/2002, no residual impact was predicted.

Waste types generated by the construction activities are likely to include C&D material (from minor excavation works), general refuse from the workforce, and chemical waste from the maintenance of construction plant and equipment.  Provided that these wastes are handled, transported and disposed of using approved methods and that the recommended good site practices are strictly followed, adverse environmental impacts is not expected during the construction phase.

 


7                        AIR QUALITY IMPACT ASSESSMENT

7.1                   Introduction

The submarine watermain component of the Project across Victoria Harbour is a Designated Project under Schedule 2, Part 1I(E3) of the Environmental Impact Assessment Ordinance (EIAO) (Cap. 499) and an Environmental Permit (EP) issued under the EIAO is required for the construction and operation of the designated project.

In accordance with the EIA Study Brief No. ESB-132/2005, construction air quality impact arising from the dredging, laying of pipe and backfilling works for the construction of the submarine watermain was assessed.

An air quality impact assessment has been undertaken to define the nature and scale of potential environmental impacts associated with the construction of the submarine watermain specifically in terms of the effects of construction dust. Construction phase impacts have been assessed and mitigation measures have been identified to reduce any impact to acceptable levels.

7.2                   Environmental Legislation, Standards, Guidelines and Criteria

Legislation, Standards, Guidelines and Criteria relevant to the consideration of air quality impacts under this Study include the following:

·         Hong Kong Air Pollution Control Ordinance;

·         Air Pollution Control (Construction Dust) Regulation; and

·         Technical Memorandum on Environmental Impact Assessment Process.

7.2.1             Hong Kong Air Pollution Control Ordinance

The principal legislation for the management of air quality is the Air Pollution Control Ordinance (APCO) (Cap 311).  The whole of the Hong Kong Special Administrative Region (HKSAR) is covered by the Hong Kong Air Quality Objectives (AQOs) which stipulate the statutory limits of some typical air pollutants and the maximum allowable number of exceedance over specific periods (refer to Table 7-1).

Table 71     Hong Kong Air Quality Objectives (mg/m3)(i)

Pollutant

1 Hour

 (ii)

8 Hours (iii)

24 Hours (iii)

3 Months (iv)

1 Year

 (iv)

Sulphur Dioxide

800

 

350

 

80

Total Suspended Particulates

500(vii)

 

260

 

80

Respirable Suspended Particulates (v)

 

 

180

 

55

Carbon Monoxide

30,000

10,000

 

 

 

Nitrogen Dioxide

300

 

150

 

80

Photochemical Oxidants (as ozone) (vi)

240

 

 

 

 

Lead

 

 

 

1.5

 

Notes:

(i)            Measured at 298K(25 oC) and 101.325 kPa (one atmosphere).

(ii)           Not to be exceeded more than three times per year.

(iii)          Not to be exceeded more than once per year.

(iv)          Yearly and three monthly figures calculated as arithmetic means.

(v)          Respirable suspended particulates means suspended particles in air with nominal aerodynamic diameter of 10 micrometres and smaller.

(vi)          Photochemical oxidants are determined by measurement of ozone only.

                Air Pollution Control (Construction Dust) Regulation

(vii)         This is not an AQO but a criterion for construction dust impact assessment under Annex 4 of the Technical Memorandum on Environmental Impact Assessment Process.

7.2.2             Air Pollution Control (Construction Dust) Regulation

Air Pollution Control (Construction Dust) Regulation stipulates the construction dust control requirements for both notifiable (e.g. site formation) and regulatory (e.g. road opening) Works to be carried out by the Contractor.  The requirements for various notifiable and regulatory works are given in Parts 1 and 2 of the Regulation respectively.  Part 3 of the Regulation stipulates the general control requirements (e.g. site boundary and entrance) for construction dust. The control requirements for individual activities (e.g. stockpiling of dusty material) are given in Part 4 of the Regulation. 

7.2.3             Technical Memorandum on EIA Process (EIAO-TM), Annex 4 and 12

Criteria and guidelines for evaluating and assessing air quality impact as stated in Section 1 of Annex 4 and Annex 12 of the EIAO-TM are followed respectively. The EIAO-TM states that the hourly Total Suspended Particulate (TSP) level should not exceed 500mg/m3 (measured at 25oC and 1 atm.) for construction dust impact assessment.

7.3                   Baseline Conditions & Air Sensitive Receivers

7.3.1             Baseline Conditions

The proposed landing point at West Kowloon is adjacent to the Western Harbour Tunnel Toll Plaza. The existing air quality at West Kowloon is mainly affected by vehicular emissions from the West Kowloon Expressway.

The proposed landing point at Sai Ying Pun is adjacent to the Western Wholesale Food Market. The existing air quality at Sai Ying Pun is mainly affected by emissions from vehicular traffic on Connaught Road West and Western Harbour Crossing.

The nearest EPD air quality monitoring stations (AQMS) are located at Sham Shui Po and Central/Western. The annual average air quality data monitored at these stations for the year 2004 are presented in Table 7-2.

Table 72     Background Air Quality (2001 – 2005)

Air Pollutant

Annual Average Concentration in ugm-3

(Average of year 2001 to 2005)

 

Sham Shui Po

Central/Western

Total Suspended Particulates (TSP)

79

73

Respirable Suspended Particulates (RSP)

55

52

Sulphur Dioxide (SO2)

23

21

Nitrogen Dioxide (NO2)

67

54

Source: Air Quality in Hong Kong, EPD

The annual average concentrations presented in Table 7-2 have been used as the background air quality data for the following assessment.

7.3.2             Air Sensitive Receivers

Air Sensitive Receivers (ASRs) within 500m of the proposed submarine watermain alignment have been identified in accordance with the criteria set out in Annex 12 of the EIAO-TM by means of site inspections and reviews of land use plans. No ASR was identified within 500m of the proposed submarine watermain alignment at West Kowloon. ASRs were identified within 500m of the proposed submarine watermain alignment at Sai Ying Pun Identified ASRs with horizontal distances from the proposed watermain alignment are summarised in Table 7-3. The locations of the ASRs which are all located at Sai Ying Pun are shown in Figure 7.1.

Table 73     Representative Air Sensitive Receivers

ASR ID

Description

Type of Use

Separation Distance (m)

West Kowloon

Nil

Sai Ying Pun

FSB

Fung Shing Building

Residential

360

VC

Viking Court

 

320

CLM

Cheong Ling Mansion

 

310

KY2

Kwan Yik Building Phase 2

 

400

KY3a

Kwan Yik Building Phase 3

 

245

KY3b

 

 

225

RWM

Richwealth Mansion

 

215

CG1

Connaught Garden

 

220

CG2

 

 

230

CG3

 

 

245

GB

General Building

 

270

TJB

Tianjin Building

Office

360

CMG

China Merchants Group, the Westpoint

Office

280

IPH

Island Pacific Hotel

Hotel and hostels

300

SCB

Singga Commercial Building

Office

310

AFCDMO

AFCD Market Office

GIC

220

WWFM

Western Wholesale Food Market

GIC           

340

7.4                   Identification and Evaluation of Air Quality Impacts

7.4.1             Construction Phase

The likely air quality impacts arising from the construction of the proposed submarine watermain are dust nuisance and gaseous emission from construction plant, vehicles and barges. It is anticipated that dust would be generated from excavation, material handling and wind erosion from the site.

The construction of the cross harbour main would involve the following construction plants:

-          two grab dredgers (one for dredging and one for trimming)

-          four hopper barges

-          two tug boats

-          one winch

-          one marine piling vessel

-          two lorries

-          two cranes

The submarine watermain laying activities such as trench dredging and pipe pulling as detailed in the construction programme are not dust generating and the gaseous emissions of SO2 and NO2 from one barge at anytime on site would be limited. Exceedance of AQOs from their operation is not anticipated.

The construction activities associated with the landing point would involve dust generating activities such as site clearance, minimal ground excavation, material handling and vehicle movements on haul roads. As the number of plants required on site would be limited, dust impact and SO2 and NO2 emissions from plants and site vehicles would be minimal. With the implementation of appropriate dust suppression measures stipulated in the Air Pollution Control (Construction Dust) Regulation, together with proper maintenance of equipment, adverse air quality impacts are not anticipated.

7.4.2             Operation Phase

There will not be any operational phase emissions.

7.5                   Mitigation of Adverse Environmental Impacts

7.5.1             Construction Phase

Construction dust impacts should be controlled within the 1-hour TSP criterion of 500 mg/m3 and 24-hour TSP AQO of 260 mg/m3.  Therefore, effective control measures and good site practices should be implemented to meet the requirements of the Air Pollution Control (Construction Dust) Regulation and minimize construction dust impact.

During construction phase, the Contractor shall make reference, but not limit himself, to the following measures:

·         any excavated dusty materials or stockpile of dusty materials should be covered entirely by impervious sheeting or sprayed with water so as to maintain the entire surface wet, and recovered or backfilled or reinstated within 24 hours of the excavation or unloading;

·         the working area of excavation should be sprayed with water immediately before, during and immediately after the operations so as to maintain the entire surface wet;

·         the load of dusty materials carried by vehicle leaving a construction site should be covered entirely by clean impervious sheeting to ensure that the dusty materials do not leak from the vehicle;

·         where a site boundary adjoins a road, streets or other area accessible to the public, hoarding of not less than 2.4m high from ground level should be provided along the entire length except for a site entrance or exit;

·         the area where vehicle washing takes place and the section of the road between the washing facilities and the exit point should be paved with concrete, bituminous materials or hardcores;

·         every main haul road should be scaled with concrete and kept clear of dusty materials or sprayed with water so as to maintain the entire road surface wet;

·         the portion of road leading only to a construction site that is within 30m of a designated vehicle entrance or exit should be kept clear of dusty materials;

·         all dusty materials should be sprayed with water prior to any loading, unloading or transfer operation so as to maintain the dusty material wet;

·         vehicle speed should be limited to 10 kph except on completed access roads; and

·         every vehicle should be washed to remove any dusty materials from its body and wheels before leaving the construction sites.

7.5.2             Operation Phase

As impact from operation activities of the submarine watermain is not anticipated, air quality mitigation measures are not required.

7.6                   Evaluation of Residual Air Quality Impacts

With the implementation of proposed dust suppression measures and good site practices, no residual air quality impacts associated with the construction and operation of the proposed submarine watermain is anticipated.

7.7                   Environmental Monitoring and Audit

Dust monitoring during the construction of the submarine watermain is considered not necessary. Auditing on at least weekly basis during construction of the submarine watermain is required to ensure the proposed dust control measures are properly implemented.

7.8                   Conclusions and Recommendations

Potential air quality impacts arising from the construction and operation of the submarine watermain have been evaluated.

As the number of construction plants involved in the submarine watermain laying activities at anytime on site would be limited, exceedance of AQOs emissions of gaseous pollutants from these construction plants is not anticipated. The number of plants required on site for the construction of the landing points would also be limited. Dust impact and SO2 and NO2 emissions from plants and site vehicles would be minimal. With the implementation of appropriate dust suppression measures stipulated in the Air Pollution Control (Construction Dust) Regulation, together with proper maintenance of equipment, adverse air quality impact is not anticipated.

No air quality impact is anticipated at the operational phase since there will not have any operational phase emissions.


8                        CULTURAL HERITAGE IMPACT ASSESSMENT

8.1                   Introduction

The submarine watermain component of the Project across Victoria Harbour is a Designated Project under Schedule 2, Part 1I(E3) of the Environmental Impact Assessment Ordinance (EIAO) (Cap. 499) and an Environmental Permit (EP) issued under the EIAO is required for the construction and operation of the designated project.

In accordance with the EIA Study Brief No. ESB-132/2005, cultural heritage impact arising from the dredging, laying of pipe and backfilling works for the construction of the submarine watermain was assessed.

A cultural heritage impact assessment has been undertaken to define the nature and scale of the potential impacts on cultural heritage resources associated with the construction of the submarine watermain, with a specific focus on the effects in the vicinity of sensitive receivers within the seabed that will be affected by the construction of the submarine watermain. Measures required to mitigate identified impacts are recommended, where appropriate, to reduce residual impacts to acceptable levels.

8.2                   Environmental Legislation, Standards, Guidelines and Criteria

The following legislation and guidelines are applicable to the cultural heritage assessment in Hong Kong:

·         Technical Memorandum on the EIA Process, Annex 10 and 19 (EIAO TM);

·         Antiquities and Monuments Ordinance (Cap. 53);

·         Hong Kong Planning Standards and Guidelines (HKPSG); and

·         Marine Archaeological Investigation Guidelines.

8.2.1             Technical Memorandum on the EIA Process, Annex 10 and 19

The EIAO-TM outlines the approaches required in investigating and criteria for assessing the impacts on cultural heritage sites. The following Sections are applicable:

Annex 10 - "The criteria for evaluating impact on sites of cultural heritage includes:  (a) The general presumption in favour of the protection and conservation of all sites of cultural heritage because they provide an essential, finite and irreplaceable link between the past and the future and are points of reference and identity for culture and tradition; (b) Adverse impacts on sites of cultural heritage shall be kept to the absolute minimum."

Annex 19 - "There is no quantitative standard in deciding the relative importance of these sites, but in general, sites of unique archaeological, historical or architectural value will be considered as highly significant.  A baseline study shall be conducted: (a) to compile a comprehensive inventory of places, buildings, sites and structures of architectural, archaeological and historical value within the proposed project area; and (b) to identify possible threats of, and their physical extent, destruction in whole or in part of sites of cultural heritage arising from the proposed project."

The Memorandum also outlines the approach in regard to the preservation in totality, in part, and not at all of cultural resources:

Annex 19 - "Preservation in totality will be a beneficial impact and will enhance the cultural and socio-economical environment if suitable measures to integrate the sites of cultural heritage into the proposed project are carried out.  If, due to site constraints and other factors, only preservation in part is possible, this must be fully justified with alternative proposals or layout designs, which confirm the impracticability of total preservation."

8.2.2             Antiquities and Monuments Ordinance (Cap.53)

The Antiquities and Monuments Ordinance (Cap. 53), provides power for the designation of Antiquities and Monuments Sites or Declared Monuments in Hong Kong, and provides statutory protection against the threat of development for declared monuments, historic buildings and archaeological sites on land and underwater which have been recommended by the Antiquities Advisory Board (AAB), approved by the Chief Executive and gazetted in the government gazette to enable their preservation for posterity.

The Antiquities Authority may, after consultation with the Antiquities Advisory Board (AAB) and with Government approval, gazette and protect any place, building, site or structure considered to be of public interest by reason of its historical, archaeological or palaentological significance.  Once declared a site of public interest, no person may undertake acts that are prohibited under the Ordinance, such as demolishing or carrying out construction or other works, unless a permit is obtained from the Antiquities Authority.

For archaeological sites, all relics dated prior to 1800 AD belong to the Hong Kong Government.  Archaeological sites are generally classified into two categories, as follows:

·         Designated Monuments - those that have been gazetted in accordance with Cap. 53 by the Antiquities Authority; and

·         Recorded Archaeological Sites – those which have not been declared but recorded by the AMO under administrative protection

The Legislation also sets out the procedures for the issuing of Licences to Excavate and Search for Antiquities, the effect of which is to forbid all such activities being undertaken without such a licence.  It also provides for the penalties exacted for infringement of the Ordinance, including fines and imprisonment.

Although there are no statutory provisions for the protection of Sites of Cultural Heritage, Deemed Monuments and Graded Buildings in Hong Kong, the Government has administrative procedures which state that consideration must be given to protect them.  However, at present, the record of sites of cultural heritage is incomplete as many areas have yet to be surveyed in detail. 

Section 11 of the Antiquities and Monuments Ordinance requires any person who discovers an antiquity, or supposed antiquity, to report the discovery to the Antiquities Authority.  Nevertheless it is prudent to ensure that procedures and mechanisms which ensure the preservation or formal notification of previously unknown archaeological resources that may be revealed or discovered during a project assessment or during construction are identified at an early stage in project planning.

8.2.3             Hong Kong Planning Standards and Guidelines

The HKPSG, Chapter 10 – Conservation covers planning considerations relevant to general guidelines and measures for conservation of historical buildings, archaeological sites and other antiquities.

8.2.4             Marine Archaeological Guidelines

The AMO have issued Guidelines for Marine Archaeological Investigation (MAI) which details the standard practice, procedures and methodology which must be undertaken in determining the marine archaeological potential, presence of archaeological artefacts and defining suitable mitigation measures.

8.3                   Cultural Heritage Impact Assessment Methodology

8.3.1             Baseline Review

A baseline review was undertaken to compile a comprehensive inventory of cultural heritage resources of the Study Area.  The Review established the historical profile and potential for cultural heritage sites and included:

·         Marine charts records held in British Library and National Maritime Museum Library in London focus on cultural heritage features;

·         Information held by the Antiquities and Monuments Office;

·         Publications on local historical, architectural, anthropological, archaeological and other cultural studies;

·         Unpublished papers, records, archival and historical documents held in local libraries and other government departments.

8.3.2             Geophysical Survey

The Geophysical Survey was undertaken to define the areas of greatest archaeological potential, assess the depth and nature of the seabed sediments to define which areas consist of suitable material to bury and preserve archaeological material and to map anomalies on the seabed which may be of archaeological potential.

IGGE (HK) Engineering Geophysical Company Limited undertook the Survey in August 2006, which covered a 200m corridor (100 m either side of the proposed centreline) along the length of the proposed submarine watermain route. This survey allowed for a comprehensive investigation of the seabed, and below the seabed.

8.3.3             Establishing Archaeological Potential

The data examined during the Baseline Review and Geophysical Survey were analysed to provide an indication of the likely character and extent of archaeological resources within the Study Area.  The results are presented in the Marine Archaeological Investigation Report in Appendix H and summarised in Section 8.4.

8.4                   Baseline Conditions

The submarine watermain is proposed to be located across Victoria Harbour from its connection at Lin Cheung Road in West Kowloon to the existing Sai Ying Pun Fresh Water Pumping Station in Sheung Wan. No evidence of any submerged cultural heritage sites including shipwrecks was identified from an examination of AMO records, archaeological and historical academic publications and all archives holding information on shipwrecks in Hong Kong waters. The detailed findings are presented in Appendix H. The associated landing point are proposed to be located at Sai Ying Pun and West Kowloon, which are on reclaimed land. As such, no land-based cultural heritage resources were identified within the Study Area.

IGGE (HK) Engineering Geophysical Company Limited undertook a Geophysical Survey in August 2006 which covered a 200m submarine watermain corridor to identify all forms of submerged marine archaeological deposits and objects. There are evidence of trawl marks, debris and dumped materials. The submarine watermain corridor and surrounds have been greatly affected by fishing trawlers and anchors and this will have resulted in impacts to the type and state of preservation of any submerged marine archaeological deposits. The seabed within the study area consists of mud or fine sand. Generally more than 10 m in thickness of marine deposits covered the study area. This would create a preservation environment for archaeological resources. Interpretation of the digital side scan sonar data revealed that there were no seabed anomalies within the dredging area of the Project as shown in Figure 8.1.

Although archaeological resources could be present on the seabed within the study area, the seabed has been subjected to previous substantial disturbance associated with dredging works for the construction of the western harbour crossing and new reclamation construction at Hong Kong Island and West Kowloon, construction of mooring buoys to the north of the Central Fairway and maintenance dredging of navigation channels within Victoria Harbour. These disturbed seabed areas cover most of the proposed dredging area for the submarine watermain. Further investigation was therefore not recommended.

8.5                   Identification of Cultural Heritage Impact

The potential sources of impact may arise due to trench excavation by dredging and installation of the submarine pipeline by “bottom-pull” method.

8.6                   Assessment of Cultural Heritage Impact

Preservation in totality is taken as the first priority and the assessment has taken into account the requirements as specified in the Section 2.1 of Annex 10 and Sections 2.6 to 2.14 of Annex 19 of the EIAO-TM.

As no land based cultural heritage resources were identified, no impacts are expected. 

No indication of marine archaeological material was identified.  As such, no impacts are expected from the installation of the cross harbour main.

8.7                   Mitigation of Adverse Environmental Impact

No cultural heritage resources are identified within the Study Area and therefore, no mitigation measures are considered necessary. 

8.8                   Evaluation of Residual Cultural Heritage Impact

No cultural heritage resources are identified within the Study Area and therefore, no residual impacts are expected.

8.9                   Environmental Monitoring and Audit

No cultural heritage resources are identified within the Study Area and therefore, no environmental monitoring and audit programme are recommended.

8.10               Conclusions and Recommendations

A comprehensive baseline review identified no land based or submerged cultural heritage resources within the Study Area.

A Geophysical Survey which covered a 200m submarine watermain corridor was conducted and no indication of marine archaeological material was identified. Therefore, no impacts are expected from the installation of the cross harbour main.

 


9                        FISHERIES IMPACT ASSESSMENT

9.1                   Introduction

The submarine watermain component of the Project across Victoria Harbour is a Designated Project under Schedule 2, Part 1I(E3) of the Environmental Impact Assessment Ordinance (EIAO) (Cap. 499) and an Environmental Permit (EP) issued under the EIAO is required for the construction and operation of the designated project.

In accordance with the EIA Study Brief No. ESB-132/2005, fisheries impact arising from the dredging, laying of pipe and backfilling works for the construction of the submarine watermain was assessed.

This Section of the EIA Report presents the results of an assessment of the impact of construction and operation of the submarine watermain of the Project on existing fisheries resources, fishing operations and fish culture activities based on the findings of the Water Quality Impact Assessment.

9.2                   Environmental Legislation, Standards, Guidelines and Criteria

The following legislations and guidelines are applicable to the fisheries impact assessment in Hong Kong:

·         Technical Memorandum on the EIA Process, Annex 9 and 17 (EIAO-TM). Annex 17 of the EIAO-TM prescribes the general approach and methodology for the assessment of fisheries impacts arising from a project or proposal, to allow a complete and objective identification, prediction and evaluation of the potential impacts.  EIAO-TM Annex 9 recommends the criteria that are to be used for evaluating fisheries impacts.

·         Fisheries Protection Ordinance (Cap 171). This Ordinance provides for the conservation of fish and other aquatic life and regulates fishing practices.

·         Marine Fish Culture Ordinance (Cap 353). This Ordinance regulates and protects marine fish culture and other related activities

·         Water Pollution Control Ordinance (Cap 358). This Ordinance set limits to water quality parameters in various water control zones.

9.3                   Fisheries Impact Assessment Methodology

A desktop literature review was conducted in order to establish the baseline conditions of the physical environment and fisheries importance of the area. Information from the water quality assessment was used to determine the size of the Study Area as that potentially affected by perturbations to water quality parameters. The importance of fisheries resources and fishing operations identified within the Study Area and the potential impacts due to the construction and operation of the cross harbour main were assessed following the criteria and guidelines for evaluating and assessing fisheries impact as stated in Annexes 9 and 17 of the EIAO-TM, respectively.

9.4                   Baseline Conditions

This assessment of fisheries impacts focussed on the fisheries resources and fishing operations within the project area.

The availability of literature on the fisheries resources of the Study Area comes mainly from the AFCD 1996-1997 (48) and 2001-2002 (49) Port Survey.  Other relevant reports from the Study Area have been reviewed. Updated mariculture information was obtained from the Agriculture, Fisheries and Conservation Department (AFCD).

In Hong Kong, the commercial marine fishing industry is divided into capture and culture fisheries. To assess the capture fishery within the Study Area, the most up-to-date information on the Hong Kong fishery was consulted.  Information from other relevant studies within the Study Area were also reviewed in order to determine if the areas are important nursery and spawning grounds for commercial fisheries.

9.4.1             Capture Fisheries

General

The findings of fisheries surveys, fishermen’s interviews and accompanying literature reviews (50) conducted for AFCD’s Fisheries Resources and Fishing Operations in Hong Kong Waters Study have determined that commercial fish species reproduce throughout the year, though spawning for the majority of species appears to be concentrated during the period from June to September. The marine waters within the Study Area were not identified as a primary nursery ground for commercial fisheries as fish fry production density was less than or equal to 50 tails per hectare with reference to the AFCD’s Port Survey 2001/2002.

In 2005, the estimated fisheries production in Hong Kong waters from capture fisheries amounted to 162,000 tonnes, valued at HK$1,600 million (51). Within Hong Kong waters, the highest yields for local fisheries within Hong Kong waters were mainly derived from the eastern and northeastern coasts   The five most abundant fish species landed by weight from the capture sector were golden thread (Nemipterus virgatus 14%), lizardfish (Saurida sp 9%), big-eyes (Priacanthus sp 5%), scads (Decapterus sp 5%) and yellow belly (Nemipterus bathybius 4%).

Based on the AFCD Port Survey 2001/2002 data, the highest range of fisheries production (i.e. 600 – 1000 kg ha-1) was recorded near Cheung Chau, Penny’s Bay, Kau Yi Chau, Po Toi, Ninepin Group and Tap Mun.  The top 10 families captured in Hong Kong were rabbitfish (Sigdnidae), sardine (Clupeidae), croaker (Sciaenidae), scad (Carangidae), squid, shrimp, anchovy (Engraulidae), crab, seabream (Sparidae) and threadfin bream (Nemipteridae).

Up-to-date information from AFCD is available for use in this EIA and can be collated to allow an assessment be made of the importance of Fishing Zones in the Study Area to the Hong Kong fishery. The designated Fishing Zones within the Study Area have been identified and the importance of these zones is assessed and discussed below.

The Study Area interfaces with 5 Fishing Areas as identified in the AFCD Port Survey 1996/1997 Report (Figure 9.1).  These Fishing Areas are identified as follows:

·         Green Island

·         Sai Ying Pun

·         Central

·         Yau Ma Tei

·         Tsim Sha Tsui

Findings from Port Survey 1996/1997

The area and number of vessels operating during 1996-1997 in each of the Fishing Zones is presented in Table 9-1. 

Table 91     Area (ha) and Number of Vessels Operating During 1996 - 1997 in Each AFCD Fishing Zone within the Study Area

Code

Fishery Area

Area (Ha)

Vessels < 15m

Vessels > 15m

All Vessels

089

Green Island

595.86

16.6

8.9

25.5

0151

Sai Ying Pun

655.76

5.0

0

5.0

0152

Central

265.10

6.1

0

6.1

0162

Yau Ma Tei

287.75

14.9

0

14.9

0163

Tsim Sha Tsui

181.76

2.6

0

2.6

Total

1,986.23

*

*

*

Total of all Fishing Zones in Hong Kong

181,790.97

2,352.2

266.4

2,618.5

Percentage of Hong Kong Total

1.1 %

*

*

*

*No values can be calculated for these parameters from the information provided, as it cannot be determined whether the vessels reported as operating within one zone are the same vessels that are reported for another zone.

The total number of vessels varies widely from 2.6 in Tsim Sha Tsui Fishing Area to 25.5 in Green Island Fishing Area.  According to the AFCD Port Survey 1996/1997, the total fishing production in those fishing areas is mainly from vessels not exceeding 15m. Vessels exceeding 15m are only operated in the Green Island Fishing Area.

The overall fisheries production (adult fish and fish fry) ranged widely from approximately 4.96 kg ha-1 (Sai Ying Pun) to 134.3 kg ha-1 (Green Island) (Table 9-2). These values are not in the high range for production in Hong Kong.

Table 92     Fisheries Production Values from each AFCD Fishing Zone within the Study Area

Code

0089

0151

0152

0162

0163

Fishing Areas

Green Island

Sai Ying Pun

Central

Yau Ma Tei

Tsim Sha Tsui

Total Production

Adult Fish (kg)

80,026.26

3,255.84

18,230.83

20,268.29

1,041.98

Fry (Tails)

-

-

-

-

-

Value (HKD)

760,154.46

106,666.67

400,357.14

719,309.53

30,857.14

Production (ha-1)

Adult Fish (kg)

134.30

4.96

68.77

70.44

5.73

Fry (Tails)

-

-

-

,

-

Value (HKD)

1,275.74

162.66

1,510.22

2,499.77

169.77

Rank Production (Production, ha-1)

Adult Fish (kg)

76

170

112

111

168

Fry (Tails)

-

-

-

-

-

Value (HKD)

130

169

124

96

168

Of the 5 fishing areas identified, one of the fishing zone recorded medium rank adult fish production (Green Island, 76th out of the 179 zones). Sai Ying Pun, Central, Yau Ma Tei and Tsim Sha Tsui recorded low ranked adult fish production (Sai Ying Pun 170th, Central 112th, Yau Ma Tei 111st and Tsim Sha Tsui 168th). No fish fry capture operations was recorded in the fishing areas within the Study Area.

According to the AFCD Port Survey data, the top five adult fish species caught in the sector Victoria Harbour (SE01) included the Siganus Oramin (Rabbitfish), Leiognathus Brevirostris (Pony Fish), Mixed Species (Mixed Fish), Mixed Crab Species (Crab) and Argyrosomus Spp. (Croaker). The main fish species reported in catches from the Study Area are of low commercial value (<HK$15/kg) including mixed species (juveniles of trash fish species such as Caranx Kalla, Siganus canaliculatus and Leiognathus brevirostris) (Table 9-3).  Croaker and Flathead is regarded as of high commercial value (>HK $20/kg).

Table 93     Top Five Adult Fish (by weight) Caught in Each AFCD Fishing Zone within the waters of the Study Area

Code

Fishing Area

Top Five Fish Caught (by weight)

 

 

Species

Common Name

0089

Green Island

Mixed Species

Mixed Fish

 

 

Mixed Prawn

Prawn

 

 

Mixed Crab Species

Crab

 

 

Leiognathus Brevirostris

Pony Fish

 

 

Platycephalus Indicus

Flathead

0151

Sai Ying Pun

Mixed Species

Mixed Fish

 

 

Mixed Prawn

Prawn

 

 

Platycephalus Indicus

Flathead

 

 

Oratosquilla Spp.

Mantis Shrimp

 

 

Cynoglossus Spp.

Tongue Sole

0152

Central

Caranx Kalla

Shrimp Scad

 

 

Siganus Oramin

Rabbitfish

 

 

Stolephorus Spp.

Anchovy

 

 

Mixed Crab Species

Crab

 

 

Argyrosomus Spp.

Croaker

0162

Yau Ma Tei

Siganus Oramin

Rabbitfish

 

 

Argyrosomus Spp.

Croaker

 

 

Mixed Crab Species

Crab

 

 

Clupanodon Punctatus

Gizzard Shad

 

 

Leiognathus Brevirostris

Pony Fish

0163

Tsim Sha Tsui

Leiognathus Brevirostris

Pony Fish

 

 

Siganus Oramin

Rabbitfish

 

 

Argyrosomus Spp.

Croaker

 

 

Mixed Crab Species

Crab

 

 

Mixed Species

Mixed Fish

Findings from Port Survey 2001/2002

More recent data were extracted from the AFCD’s Port Survey 2001/2002. In this Port Survey, a uniform grid of 720 ha cell size overlaid on Hong Kong waters and the fisheries related information (e.g. production, vessel number and catch value) was presented in the form of categories.

The results of Port Survey 2001/2002 shows that the waters within the Study Area are having low to medium adult fish production (>0 to 200kg/ha).

The catches from the direct impact grid cells as shown in Figure 9.2 were at medium price in Hong Kong (HK$2000-5000/ha) in adult fish production.

Fishing vessels operated in this grid cell include shrimp trawler, gill netter, long liner, hand liner, miscellaneous craft and sampan. All fish vessels are less than 15m in length.

There is no fish fry collected within the direct impact grid cells.

Among the 10 species of major fisheries products in Port Survey 2001/2002, the most abundant species in the direct impact grid cells are crab and seabream with production of 20-40kg/ha and 10-20kg/ha respectively.

For the value of production, the direct impact grid cells are of low importance to capture fishing operations in Hong Kong.

9.4.2             Culture Fisheries

The closest AFCD designated Fish Culture Zone (FCZ) to the Study Area is located at Ma Wan which is approximately 10km away from the proposed cross harbour main. As of 30 September 2006, updated information from AFCD indicates that the Ma Wan FCZ consists of 108 licensed rafts with a total licensed area of 14,554m2 (total gazetted area = 46,300m2) (52). The main species cultured are the spotted grouper (Epinephelus chlorostigma), gold-lined seabream (Rhabdosargus sarba), mangrove snapper (Lutjanus argentimaculatus) and the pompano (Trachinotus blochii). No figure is available for production at this FCZ, although the estimated production of marine culture fish in 2004 was about 1,540 tonnes valued at approximately $79 million (49).

9.4.3             Fisheries Importance

The importance of the fisheries within the Study Area is addressed based on the baseline information provided above.  The Fishing Zones within the Study Area are characterised as mainly of medium to low value.  The catches from these zones were composed of juvenile mixed fish species, which are used as fish feed in mariculture. 

9.4.4             Sensitive Receivers

Based on the preceding review of the available information on the capture and culture fisheries of the waters of the Study Area and its immediate vicinity, no particular sensitive receiver may be affected by the proposed works associated with the Project.

9.5                   Identification of Fisheries Impacts

9.5.1             Construction Phase

The cross harbour main with a length of approximately 2,100 metres will be submerged and embedded in a 6m deep trench in the seabed. The entire cross harbour main will be armoured with rockfill cover matching the original seabed level as shown in Figure 2.3.

Impact on future fishing operation is not anticipated as the armour rock will not protrude above the original seabed level. Impacts to fishing operations are expected to occur only during the installation of the cross harbour main. These impacts are predicted to be localised and small scale and may occur through the following mechanisms:

Direct Impact

Long term direct impacts are not expected to occur through the installation of the cross harbour main. Short term direct impacts are predicted to occur along the submarine pipeline trench with a length of approximately 2,100 metres and a width of approximately 44 metres to be formed at the seabed as shown in Figure 2.3 as a result of the “bottom-pull” and dredging operations associated with the installation of the cross harbour main. Once these operations have ceased fisheries resources dependent on the affected area of seabed are expected to return due to recolonisation of the seabed by the supporting benthic fauna. The affected area of seabed will be reinstated in the following manner:

·         Install the submarine pipeline by bottom-pull method upon completion of trench excavation;

·         Cover the pipeline by a thin layer of grade 75 bedding (minimum 0.3m above the top of the pipeline) by hopper or crane barge;

·         Backfill the submarine pipeline by armour rock (approximately 4.5m) by hopper or crane barge;

·         Monitor the armour rock level by chain or echo sounding during the course of rock placement. Trim the backfilled trench by crane barge to ensure the backfilled level match with the original seabed level without any rock armour protruding above the original seabed level; and

·         Gaps between the backfilled armour rock and the edge of the submarine pipeline trench will be filled by marine sediment within the sea volume from natural movement of the top soft soil of existing seabed.

Indirect Impact

Indirect impacts to fisheries resources and fishing operations during the construction phase include sediment release associated with “bottom-pull” or dredging works. Potential impacts on water quality from sediment release are listed below:

·         Increase concentrations of suspended solids (SS);

·         A resulting decrease in dissolved oxygen (DO) concentrations; and

·         An increase in nutrient concentrations in the water column.

Suspended Solids

Suspended sediment (SS) fluxes occur naturally in the marine environment, consequently fish have evolved behavioural adaptations to tolerate increased SS load (e.g., clearing their gills by flushing water over them). Where SS levels become excessive, fish will move to clearer waters.  This level is defined as the tolerance threshold, which varies from species to species and at different stages of the life cycle.  If SS levels exceed tolerance thresholds, fish are likely to become stressed, injured and may ultimately die.  Susceptibility generally decreases with age, with eggs the most vulnerable and adults the least sensitive to effects from sediments.  The rate, season and duration of SS elevations will influence the type and extent of impacts upon fish.

It is noted that, despite the very conservative nature of the assessment, the predicted increases in suspended solids concentrations did not exceed the guideline value recommended by AFCD which was identified for fisheries and selected marine ecological sensitive receivers that have been based on international marine water quality guidelines for the protection of ecosystems under the Consultancy Study on Fisheries and Marine Ecological Criteria for Impact Assessment (CSFMEC) (53). The AFCD study recommends a maximum concentration of 50 mg L-1 (based on half of the no observable effect concentrations).

Dissolved Oxygen

The relationships between SS and DO are complex, with increased SS in the water column combining with a number of other effects to reduce DO concentrations.  Elevated SS (and turbidity) reduces light penetration, lowers the rate of photosynthesis by phytoplankton (primary productivity) and thus lowers the rate of oxygen production in the water column.  Elevated SS can also cause increased energy retention from sunlight, resulting in higher temperatures, and thus the potential for lower oxygen levels as oxygen is more soluble in cold water.  This has a particularly adverse effect on the eggs and larvae of fish, as at these stages of development high levels of oxygen in the water are required for growth to support high metabolic rates.

The assessment results of dissolved oxygen concentrations have shown that the predicted maximum decrease in dissolved oxygen concentrations are localised to within and around the submarine pipeline and restricted to the lower layers of the water column (i.e. close to the seabed). It is expected that the concentrations within the Study Area as a whole will be maintained at environmentally acceptable levels (i.e. compliant with the Water Quality Objectives as detailed in Section 3).

Nutrients

High levels of nutrients in seawater can cause rapid increases in phytoplankton, on occasions to the point where an algal bloom occurs.  An intense bloom of algae can lead to sharp decreases in the levels of dissolved oxygen.  This decrease will initially occur in the surface water, and then deepen as dead algae fall through the water column and decompose on the bottom.  Anoxic conditions may result if DO concentrations are already low or are not replenished.  This may result in mortality to fish, especially juveniles, due to oxygen deprivation. 

The results of the water quality assessment sediment concentrations have shown that the predicted maximum sediment concentrations are localised to within and around the submarine pipeline and restricted to the lower layers of the water column (i.e. close to the seabed).  It is expected that the concentrations within the Study Area as a whole will be maintained at environmentally acceptable levels (i.e. compliant with the Water Quality Objectives as detailed in Section 3).

Impacts to the sensitive receivers listed above are predicted, as a result of the construction of Project, to be within environmentally acceptable levels (as defined by compliance with the Water Quality Objectives).

9.5.2             Operation Phase

The only operation impacts from the submarine watermain would be if repair works were required. This includes maintenance and repairing work for any accidental damage of the pipeline.  Since a protective armour rock layer has been provided to prevent or minimize the accidental damage, the repair works will not be significant during the design life of the submarine watermain. The impacts from this would be of reduced severity than those during the construction phase as the work would take place in a specific and confined small area. Therefore, unacceptable impacts to fisheries resources during the operation of the submarine watermain are not envisaged.

9.6                   Assessment of Fisheries Impacts

From the information presented above, the fisheries impact associated with construction of the proposed submarine watermain is considered to be low.  An evaluation of the impact in accordance with Annex 9 of the EIAO-TM is presented below.

·         Nature of Impact: Temporary, small scale and localised impact will occur to fisheries resources along submarine pipeline trench to be formed at the seabed as a result of the “bottom-pull” and dredging operations.

·         Size of Affected Area: Although the submarine pipeline trench to be formed at the seabed as shown in Figure 2.3 is long (approximately 2,100 metres in length), the affected area of fisheries resources is predicted to be very small and localised to the works involved in installation of the cross harbour main.

·         Size of fisheries resources/production: The fisheries resources and production rates of the Study Area range from low to medium in terms of catch weight and value.

·         Destruction and disturbance of nursery and spawning grounds: The marine waters within the Study Area were not identified as a primary nursery and spawning grounds for commercial fisheries. No destruction and disturbance of areas of fisheries importance is therefore expected due to the project works.

·         Impact on fishing activity:  The submarine pipeline pass through areas with low to medium fisheries production and activities. Impact to fishing activities in the area are not expected to be of concern due to the small area physically disrupted during the installation of the submarine pipeline and the short time frame of disturbance. Impact on future fishing operation is not anticipated as the armour rock will not protrude above the original seabed level.

·         Impact on aquaculture activity: Based on the Water Quality Objectives and AFCD criteria, the closest AFCD gazetted Fish Culture Zone (FCZ) to the Study Area which is located at Ma Wan and is approximately 10km away from the proposed cross harbour main is not predicted to be impacted by either suspended solid elevation, dissolved oxygen depletion or nutrient elevation as a result of the Project.

9.7                   Mitigation of Adverse Environmental Impacts

In accordance with the guidelines in the EIAO-TM on fisheries impact assessment the general policy for mitigating impacts to fisheries, in order of priority are avoidance, minimization and compensation.

Impacts to fisheries resources and fishing operations have largely been avoided during construction through constraints on the works operations for installation of the submarine watermain. Good construction practice and associated measures were recommended in Water Quality Assessment in Section 3 to control water quality impacts to within acceptable levels and are also expected to control impacts to fisheries resources.  Hence, no fisheries-specific mitigation measures are required during construction of the proposed submarine watermain.

9.8                   Evaluation of Residual Fisheries Impacts

No adverse residual impact due to the construction and operation of the submarine watermain is expected after the implementation of the proposed mitigation measures to control water quality impacts.

9.9                   Environmental Monitoring & Audit

The implementation of the water quality mitigation measures stated in the Section 3 (Water Quality Impact Assessment) should be checked as part of the environmental monitoring and audit procedures during the construction phase as presented in the separate Environmental Monitoring and Audit Manual. 

The dredging and “bottom pull” operations include constraints which act as appropriate mitigation measures to control environmental impacts to within acceptable levels. Actual water quality impacts from these activities will be monitored. Monitoring and audit activities designed to detect and mitigate any unacceptable impacts to water quality will serve to protect against unacceptable impacts to fisheries resources.

The water quality monitoring programme will provide management actions and supplemental mitigation measures to be employed should impacts arise, thereby ensuring the environmental acceptability of the project. No other fisheries-specific measures are considered necessary.

9.10               Conclusions and Recommendations

Review of existing information on fisheries resources and fishing operations located within the Study Area have been undertaken. Although the submarine pipeline trench to be formed at the seabed is relatively long, the affected area of fisheries resources is predicted to be temporary, small scale and localised to the works associated with formation of submarine pipeline trench at the seabed as a result of the “bottom-pull” and dredging operations. Although the submarine pipeline passes through areas with low to medium fisheries production and activities, impact to fishing activities in the area are not expected to be of concern due to the small area physically disrupted during the installation of the submarine pipeline and the short time frame of disturbance. Impact on future fishing operation is not anticipated as the armour rock will not protrude above the original seabed level. Ma Wan Fish Culture Zone which is the closest AFCD gazetted Fish Culture Zone to the Study Area is not predicted to be impacted by either suspended solids elevation, dissolved oxygen depletion or nutrient elevation as a result of the Project.

As potential impacts to fisheries resources and fishing operations arising from formation of the submarine pipeline trench at the seabed are predicted to be temporary, small scale and localised, they are not expected to cause adverse impacts to any fishing grounds or species of importance to the fishery. While no special mitigation measures are required for fisheries resources and fishing activities, mitigation measures recommended to control impacts to water quality to within acceptable levels are also expected to mitigate impacts to fisheries resources and fishing activities.


10                    SUMMARY OF ENVIRONMENTAL OUTCOMES

10.1               Population and Environmental Sensitive Areas Protected

The EIA process has facilitated integration of environmental considerations into the design process for the Project. The principal measures identified are those achieved through careful routing of the watermain and the installation methodology or watermain design. Moreover, a number of mitigation measures have been identified to minimise the potential for adverse environmental impacts to occur.  The mitigation measures are detailed in full in the Environmental Mitigation Implementation Schedule in Section 13.  These measures will be implemented by WSD and, if appropriate, enforced by EPD by means of the EIAO.

One of the key environmental outcomes has been the ability to plan, design and ultimately construct the Project so that direct impacts to sensitive receivers are avoided, as far as practically possible. A detailed assessment of alternatives for routing the watermain was undertaken. A number of alternative watermain routes were studied and the preferred alignment avoids direct impacts to ecologically sensitive habitats and species such as corals fringing Green Island.

10.2               Environmental Friendly Designs Recommended and Problems Avoided

In preparing the design and installation method for the watermain, a key concern was to take steps so that indirect impacts to water quality sensitive receivers, through disturbance to the seabed, were avoided or minimised. Consequently, the following approaches were taken to achieve the above.

·         Reduction in Indirect Impacts - The alignment chosen for the submarine watermain was located at a sufficient distance from ecological sensitive receivers so that the temporary dispersion of sediment from the installation works was not predicted to affect the receivers at levels of concern (as defined by the WQO and tolerance criteria).

·         Installation Equipment - The use of grab dredging and “bottom-pull” along the entire route has minimised the severity of perturbations to water quality and hence allowed compliance with the WQOs at the sensitive receivers.  This careful selection of installation equipment has helped avoid impacts to sensitive ecological receivers.

·         Adoption of Acceptable Working Rates - The modelling work has demonstrated that the selected working rates for the dredging and “bottom-pull” works will not cause unacceptable impacts to water quality.  Consequently, unacceptable indirect impacts to marine ecological resources have been avoided.

10.3               Environmental Benefits of the Project

The primary objective of this Project is to lay a new cross harbour main on the western part of the harbour for maintaining the reliability of cross harbour water transfer to Hong Kong Island as it was determined that 10 years’ time, two of the existing four cross harbour mains transferring portable supplies to Hong Kong Island will reach their design life of 50 years.

The new cross harbour main will reduce the risk of insufficient cross harbour transfer capacity in times of emergency in the next decade. With the proposed new cross harbour main, the risk of having one cross harbour main under maintenance while another watermain has to be taken out of service without warning. It will minimise the requirement of constructing new reservoirs and fresh water pumping stations in the highly congested urban areas with heavy traffic and congested underground utilities, and hence prevents associated environmental impacts arisen from those works.

 


11                    ENVIRONMENTAL MONITORING AND AUDIT (EM&A) REQUIREMENTS

11.1               Water Quality

A marine water quality monitoring and audit programme is recommended during the dredging works to verify whether or not impact predictions are representative, and to ensure that the dredging works along the alignment of the proposed submarine watermain do not result in unacceptable impacts and the seawater quality at WSD’s seawater intakes comply with the WSD’s Water Quality Objectives (WQOs) of seawater for flushing supply.  If monitoring shows unacceptable water quality impact, appropriate mitigation measures, such as changes in the operation of dredging works should be introduced.

Details of the environmental monitoring and audit programme are presented in the EM&A Manual.   Water quality monitoring would be carried out at selected potentially affected sensitive receivers.  The Manual includes site-specific monitoring and auditing protocols for baseline and impact monitoring of marine water quality.  Such protocols include but are not limited to the locations of monitoring stations, parameters and frequencies for monitoring, monitoring equipment, and reporting of monitoring results.

As no adverse water quality impact was predicted from the operation of the Project, operational water quality monitoring and audit was not considered necessary. 

11.2               Marine Ecology

The implementation of the ecological mitigation measures stated in Section 4.8 and water quality mitigation measures in Section 3 should be checked as part of the environmental monitoring and audit procedures during the construction period as presented in the EM&A Manual.  No other marine ecology-specific measures are considered necessary.

11.3               Noise

Full compliance with the noise criteria will be achieved at all NSRs with the implementation of mitigation measures.  Environmental monitoring and audit is recommended to ensure that the noise levels do not exceed the criteria during the construction phase as discussed in the EM&A Manual.

11.4               Waste Management

It is recommended that auditing of each waste stream should be carried out periodically to determine if wastes are being managed in accordance with approved procedures and the site waste management plan.  The audits should look at all aspects of waste management including waste generation, storage, recycling, treatment, transport and disposal.  An appropriate audit programme would be to undertake a first audit at the commencement of the construction works, and to audit weekly thereafter.

11.5               Air Quality

Full compliance with the air quality criteria will be achieved at all ASRs with the implementation of mitigation measures. Dust monitoring is considered not necessary but weekly site audits are required to ensure that the dust control measures are properly implemented.

11.6               Cultural Heritage

As discussed in Section 8, no indication of marine archaeological material was identified and no further investigation activities were recommended.  As such, there would be no need for a cultural heritage monitoring programme during the construction phase of the submarine watermain.

11.7               Fisheries

The implementation of the water quality mitigation measures stated in the Section 3 (Water Quality Impact Assessment) should be checked as part of the environmental monitoring and audit procedures during the construction period as presented in the separate Environmental Monitoring and Audit Manual. No other fisheries-specific measures are considered necessary.

The dredging and “bottom pull” operations include constraints which act as appropriate mitigation measures to control environmental impacts to within acceptable levels. Actual water quality impacts from these activities will be monitored. Monitoring and audit activities designed to detect and mitigate any unacceptable impacts to water quality will serve to protect against unacceptable impacts to fisheries resources.

The water quality monitoring programme will provide management actions and supplemental mitigation measures to be employed should impacts arise, thereby ensuring the environmental acceptability of the project. No other fisheries-specific measures are considered necessary.


12                    CONCLUSIONS AND RECOMMENDATIONS

12.1                Water Quality

12.1.1         Construction Phase

Water quality impact during the dredging works of the submarine watermain was quantitatively assessed using the Delft3D Model.  Suspended sediment was identified as the key water quality parameter during dredging.  Water quality impact on the sensitive receivers during the entire duration of the dredging works and along the entire alignment with the maximum possible instantaneous working rate of 0.0463m3s-1.  (i.e. one grab dredger with a maximum production rate of 4,000m3 per day, 7 days per week, 24 hours per day) for the complete simulation period for the dry and wet seasons was assessed and it was predicted that potential water quality impact would occur at the WSD Sea Water Intake at Kowloon South Salt Water Pumping Station. With the implementation of the proposed mitigation measures including the use of one grab dredger only with a maximum production rate of 4,000m3 per day for dredging, deployment of frame type silt curtain  to fully enclose the grab while dredging works are in progress and deployment of silt screen at the sea water intake at Kowloon South Salt Water Pumping Station while dredging works are in progress (in a configuration as shown in Figure 3.9), the potential water quality impact upon the sea water intake would be effectively minimised and there would be no unacceptable residual cumulative water quality impact due to the dredging works of the submarine watermain as well as the other concurrent marine works.  The assessment predicted that the dredging works would have negligible impact upon the coral communities near Green Island.  An environmental monitoring and audit programme was recommended to ensure the effectiveness of the proposed water quality mitigation measures.

Minor potential water quality impacts from hydrostatic tests of the water mains systems and construction activities associated with the construction of the proposed submarine watermain were associated with effluent, sewage, wastewater and surface runoff. Impacts could be controlled to comply with the WPCO standards by implementing the recommended mitigation measure.  No unacceptable residual impact on water quality was expected.

12.1.2         Operation Phase

No maintenance dredging is required for the future operation of the proposed submarine watermain. There would be no hydrodynamic impact as the operation of the submarine watermain would not involve reclamation or filling that affect the flow volume within the Victoria Harbour.

There would also be no water quality impact during the operation of the submarine watermain as no effluent would be discharged due to the operation of the submarine watermain.

12.2               Marine Ecology

A review of the existing information showed that the marine ecological resources within the dredging area consist of pollution tolerant soft benthos in low diversity and typical to benthos recorded in poor quality sediments. Inter-tidal species along Victoria shorelines are common fouling organisms recorded at artificial seawall. Both the species diversity and abundance recorded are lower than those recorded in semi-exposed shore in Hong Kong. The marine ecology in Green Island is of moderate ecological value, with soft coral assemblages and larger size inter-tidal species recorded. However, the results of water quality modelling showed that the elevation of SS concentration and sedimentation rate around the Green Island waters is predicted to be less than 0.1mgL-1 and 0.001 kg m-2 per day respectively, which are much lower than the tolerant levels for corals communities. In addition, due to the remoteness from the works area, the impacts to the marine environment in vicinity to Green Island are anticipated to be negligible. The Study Area is not the distribution range of marine mammals and as low ecological value species are encountered in the region, the implementation of good site practices and mitigation measures for water quality impact are considered to be sufficiently minimize the impacts on the marine ecology. Thus, no special mitigation measures are necessary for ecological sensitive receivers.

In conclusion, the construction of the proposed submarine watermain along Victoria Harbour between Sai Ying Pun and West Kowloon is anticipated to be of low ecological impacts. 

12.3               Noise

Construction noise impact to the NSRs has been assessed. It is predicted that major construction activities including dredging, laying of pipe and backfilling works would comply with the noise criteria stipulated in the EIAO-TM and NCO during daytime and evening (1900 to 2300 hours).

If night-time works (2300 to 0700 hours) are carried out, the location of dredging works should be restricted while there should be no work within the prohibited zones. With this measure being taken place, the night-time criteria during the dredging period can be complied with.

Work schedule rearrangement, quiet plants and mobile noise barriers are recommended to further suppress noise emissions from construction activities. Good site practices will be necessary to further reduce any potential impact to the noise sensitive receivers.

12.4               Waste

A review of the sediment quality data from the marine site investigation indicated that the majority of the marine sediments to be dredged along the proposed submarine watermain were classified as Category L.  The total dredged volume for the Project was estimated as 543,000 m3, of which 212,000 m3 of sediment was classified as requiring confined marine disposal. With the implementation of the recommended mitigation measures and management procedures in accordance with the requirements of ETWB TCW No. 34/2002, no residual impact was predicted.

Waste types generated by the construction activities are likely to include C&D material (from minor excavation works), general refuse from the workforce, and chemical waste from the maintenance of construction plant and equipment.  Provided that these wastes are handled, transported and disposed of using approved methods and that the recommended good site practices are strictly followed, adverse environmental impacts is not expected during the construction phase.

12.5               Air Quality

Potential air quality impacts arising from the construction and operation of the submarine watermain have been evaluated.

As the number of construction plants involved in the submarine watermain laying activities at anytime on site would be limited, exceedance of AQOs emissions of gaseous pollutants from these construction plants is not anticipated. The number of plants required on site for the construction of the landing points would also be limited. Dust impact and SO2 and NO2 emissions from plants and site vehicles would be minimal. With the implementation of appropriate dust suppression measures stipulated in the Air Pollution Control (Construction Dust) Regulation, together with proper maintenance of equipment, adverse air quality impact is not anticipated.

No air quality impact is anticipated at the operational phase since there will not have any operational phase emissions.

12.6               Cultural Heritage

A comprehensive baseline review identified no land based or submerged cultural heritage resources within the Study Area.

A Geophysical Survey which covered a 200m submarine watermain corridor was conducted and no indication of marine archaeological material was identified. Therefore, no impacts are expected from the installation of the cross harbour main.

12.7               Fisheries

Review of existing information on fisheries resources and fishing operations located within the Study Area have been undertaken. Although the submarine pipeline trench to be formed at the seabed is long, the affected area of fisheries resources is predicted to be temporary, small scale and localised to the works associated with formation of submarine pipeline trench at the seabed as a result of the “bottom-pull” and dredging operations. Although the submarine pipeline pass through areas with low to medium fisheries production and activities, impact to fishing activities in the area are not expected to be of concern due to the small area physically disrupted during the installation of the submarine pipeline and the short time frame of disturbance. Impact on future fishing operation is not anticipated as the armour rock will not protrude above the original seabed level. Ma Wan Fish Culture Zone which is the closest AFCD gazetted Fish Culture Zone to the Study Area is not predicted to be impacted by either suspended solids elevation, dissolved oxygen depletion or nutrient elevation as a result of the Project.

As potential impacts to fisheries resources and fishing operations arising from formation of the submarine pipeline trench at the seabed are predicted to be temporary, small scale and localised, they are not expected to cause adverse impacts to any fishing grounds or species of importance to the fishery. While no special mitigation measures are required for fisheries resources and fishing activities, mitigation measures recommended to control impacts to water quality to within acceptable levels are also expected to mitigate impacts to fisheries resources and fishing activities.

 


13                    IMPLEMENTATION SCHEDULE

 

EIA Ref.

 

EM&A Ref.

Recommended Mitigation Measures

 

Who to implement the measure?

Location of the measure

When to implement the measure?

What requirements or standards for the measure

to achieve?

Water Quality

3.8.1

2.9

Specific Mitigation Measures for Dredging

 

Exceedances of WSD Seawater Intake criterion (10 mg L-1) at Kowloon South Salt Water Pumping Station was predicted during both dry and wet seasons if dredging was undertaken near West Kowloon. To minimise the potential SS impact, implementation of the following mitigation measures is recommended:

 

-          Dredging should be undertaken using one grab dredger only with a maximum production rate of 4,000m3 per day;

-          Deployment of frame type silt curtain to fully enclose the grab while dredging work are in progress.

-          Deployment of silt screen at the sea water intake at Kowloon South Salt Water Pumping Station while dredging works are in progress.

 

The frame type silt curtain should be designed to enclose local pollution caused by the grab dredger and suspended by a steel frame mounted on the grab dredger and floating on water. This frame type silt curtain should be fabricated from permeable, durable, abrasion resistant membrane like geotextiles and be mounted on a floating boom structure. The frame type silt curtain should also extend to the seabed to cover the entire water column. Steel chain or ballast should be attached to the bottom of the silt curtain. Mid-ballast may be added as necessary. The structure of the silt curtain should be maintained by metal grids. The frame type silt curtain should be capable or reducing sediment loss to outside by a factor of 4 (or about 75%). Silt screen is recommended for dredging near the seawater intake at Kowloon South Salt Water Pumping Station. The implementation of silt screen at the intake could reduce the SS level by a factor of 2.5 (or about 60%). These SS reduction factors have been adopted in the Wan Chai Development Phase II Environmental Impact Assessment Study in 2001.  An illustration of a typical configuration of frame type silt curtain and silt screen at seawater intake is shown in Figure 3.9.

 

WSD’s Contractor

Construction Work Sites (Along the alignment of dredging)

During Marine Construction works

Practice Note for Professional Persons with regard to site drainage (ProPECC PN 1/94) and WQO

3.8.1

2.9

Other Mitigation Measures for Dredging

 

Good Site Practices are recommended to further reduce the potential water quality impacts from the construction works, especially during dredging.

 

 

 

 

 

 

·       Tight-closing grabs should be used to minimize the loss of sediment to suspension during dredging works.  For dredging of any contaminated mud, closed watertight grabs must be used;

 

 

 

 

 

 

·       all vessels should be sized so that adequate clearance is maintained between vessels and the seabed in all tide conditions, to ensure that undue turbidity is not generated by turbulence from vessel movement or propeller wash;

 

 

 

 

 

 

·       the decks of all vessels should be kept tidy and free of oil or other substances that might be accidentally or otherwise washed overboard;

 

 

 

 

 

 

·       adequate free board shall be maintained on barges to ensure that decks are not washed by wave action;

 

 

 

 

 

 

·       all barges used for the transport of dredged materials should be fitted with tight bottom seals to prevent leakage of material during loading and transport;

 

 

 

 

 

 

·       construction activities should not cause foam, oil, grease, scum, litter or other objectionable matter to be present in the water within the site or dumping grounds;

 

 

 

 

 

 

·       loading of barges should be controlled to prevent splashing of material into the surrounding waters.  Barges should not be filled to a level that would cause the overflow of materials or sediment laden water during loading or transportation;

 

 

 

 

 

 

·       the speed of vessels should be controlled within the works area to prevent propeller wash from stirring up the seabed sediments; and

 

 

 

 

 

 

·       before commencement of dredging works, the holder of the Environmental Permit should submit detailed proposal of the design and arrangement of the frame type silt curtain to EPD for approval.

 

 

 

 

 

3.8.1

2.9

Effluent from Hydrostatic Tests of the Water Mains System

 

To ensure compliance with the standards for effluent discharged into the inshore waters or marine waters of Victoria Harbour WCZ as shown in Tables 9a and 9b of the TM-DSS and Section 23.73 and 23.77 of the General Specification for Civil Engineering Works Volume 3, 1992 Edition, sedimentation tanks with sufficient capacity, constructed from pre-formed individual cells of approximately 6 to 8 m3 capacities, are recommended as a general mitigation measure which can be used for settling surface runoff prior to disposal.  The system capacity should be flexible and suited to applications where the influent is pumped. Pre-treatment including dechlorination such as by physical process e.g. adsorption by activated carbon filter, or chemical process e.g. neutralisation by dechlorination agent dosing should be carried out to ensure compliance with the discharge requirements stipulated in TM-DSS.

 

WSD’s Contractor

Construction Work Sites (General)

During Hydrostatic Tests

Practice Note for Professional Persons with regard to site drainage (ProPECC PN 1/94) and WQO

3.8.1

2.9

Surface Runoff, Sewage and Wastewater from Construction Activities

 

Appropriate measures should be implemented to control runoff and prevent high loads of SS from entering the marine environment.  Proper site management is essential to minimise surface runoff and sewage effluents.

 

·       Construction site runoff should be prevented or minimised in accordance with the guidelines stipulated in the EPD's Practice Note for Professional Persons, Construction Site Drainage (ProPECC PN 1/94). All discharges from the construction site should be controlled to comply with the standards for effluents discharged into the Victoria Harbour WCZ under the TM-DSS. Good housekeeping and stormwater best management practices, as detailed below, should be implemented to ensure all construction runoff complies with WPCO standards and no unacceptable impact on the WSRs as a result of construction of the proposed submarine watermain;

WSD’s Contractor

Construction Work Sites (General)

During Construction works

Practice Note for Professional Persons with regard to site drainage (ProPECC PN 1/94) and WQO

 

 

·       Sedimentation tanks with sufficient capacity, constructed from pre-formed individual cells of approximately 6 to 8 m3 capacities, are recommended as a general mitigation measure which can be used for settling surface runoff prior to disposal.  The system capacity should be flexible and able to handle multiple inputs from a variety of sources and suited to applications where the influent is pumped;

 

 

 

 

 

 

·       Manholes (including newly constructed ones) should always be adequately covered and temporarily sealed so as to prevent silt, construction materials or debris being washed into the storm runoff being directed into foul sewers;

 

 

 

 

 

 

·       All vehicles and plant should be cleaned before leaving a construction site to ensure no earth, mud, debris and the like is deposited by them on roads.  An adequately designed and located wheel washing bay should be provided at every site exit, and wash-water should have sand and silt settled out and removed at least on a weekly basis to ensure the continued efficiency of the process.  The section of access road leading to, and exiting from, the wheel-wash bay to the public road should be paved with sufficient backfill toward the wheel-wash bay to prevent vehicle tracking of soil and silty water to public roads and drains;

 

 

 

 

 

 

·       Precautions should be taken at any time of year when rainstorms are likely. Actions should be taken when a rainstorm is imminent or forecast. Actions to be taken during or after rainstorms are summarised in Appendix A2 of ProPECC PN 1/94.  Particular attention should be paid to the control of silty surface runoff during storm events, particularly for areas located near steep slopes;

 

 

 

 

 

 

·       Fuel tanks and storage areas should be provided with locks and be located on sealed areas, within bunds of a capacity equal to 110% of the storage capacity of the largest tank, to prevent spilled fuel oils from reaching the coastal waters of the Victoria Harbour and Western Harbour WCZs;

 

 

 

 

 

 

·       Portable chemical toilets should be used to handle construction workforce sewage prior to discharge to the existing trunk sewer. Sufficient numbers of portable toilets shall be provided by a licensed contractor to serve the construction workers.  The Contractor shall also be responsible for waste disposal and maintenance practices.

 

 

 

 

 

Ecology

4.8

3

 

Other mitigation measures suggested in the water quality impacts assessment such as the use of one grab dredger only with a maximum production rate of 4,000m3 per day for dredging, deployment of frame type silt curtain to fully enclose the grab while dredging works are in progress, deployment of silt screen at the sea water intake at Kowloon South Salt Water Pumping Station while dredging works are in progress and good site practices to avoid silt runoff from construction works associated with the construction of the submarine watermain should be implemented to further reduce the impact on the marine ecology.

 

WSD’s Contractor

 

Construction Work Sites (Along the alignment of dredging)

During Marine Construction works

EIAO

Noise

5.6.1

4.8

Work Schedule Rearrangement

 

Concurrent works should be such that necessary noisy works should be carried out at different time slots or spread around the construction sites. This will help to reduce the cumulative noise effect produced in the construction process.

 

If night-time (2300 to 0700 hours) dredging is required, the work shall be scheduled to carry out at a distance as far as possible to the NSRs. It is determined that the dredging work should be carried out at a location 750m away from the Sai Ying Pun landfall site and 450m from the West Kowloon landfall site along the trench as shown in the Figure 5.5 of the EIA Report. The Contractor shall adhere to the restricted locations of dredging work at night-time to comply with relevant noise standard.

 

WSD’s Contractor

 

Construction Work Sites (Along the alignment of dredging)

During Marine Construction works

PN 2/93 Noise from Construction Activities & EIAO

5.6.2

4.8

Using Quality PME

 

The use of Quality PME recognized by the Noise Control Authority for the purpose of CNP application can effectively reduce the noise generated from the construction plants. Quality PME are construction plants and equipments that are notably quieter, more environmental friendly and efficiently. The noise level reduction ranges from 5 – 10 dB(A) depending on the type of equipment used. The Contractor shall note the required procedures involved in application of the QPME.

 

 

 

 

 

5.6.3

4.8

Using Noise Barriers

 

Mobile or movable noise barriers to be erected near to the construction plants would reduce the noise levels for commonly 5 – 10 dB(A) depending on the types of items of PME and materials of the barriers. It is recommended that the Contractor shall screen noisy works and noise from stationary items of PME whenever practicable.

 

 

 

 

 

5.6.4

4.8

Good Site Practices

 

Good site practice and noise management can significantly reduce the impact of construction site activities on nearby NSRs.  The following package of measures should be followed during construction:

 

 

 

 

 

 

·       only well-maintained plant should be operated on-site and plant should be serviced regularly during the construction works;

 

 

 

 

 

 

·       machines and plant that may be in intermittent use should be shut down between work periods or should be throttled down to a minimum;

 

 

 

 

 

 

·       plant known to emit noise strongly in one direction, should, where possible, be orientated to direct noise away from the NSRs;

 

 

 

 

 

 

·       mobile plant should be sited as far away from NSRs as possible; and

 

 

 

 

 

 

·       material stockpiles and other structures should be effectively utilised, where practicable, to screen noise from on-site construction activities.

 

 

 

 

 

Waste Management

6.6.1

5.3

Good Site Practices

 

Adverse impacts related to waste management are not expected to arise, provided that good site practices are strictly followed. Recommendations for good site practices during the construction activities include:

WSD’s Contractor

Construction Work Sites (General)

During Construction works

Waste Disposal Ordinance (Cap.354); Waste Disposal (Chemical Wastes) (General) Regulation

 

 

·       Nomination of an approved person, such as a site manager, to be responsible for good site practices, arrangements for collection and effective disposal to an appropriate facility, of all wastes generated at the site;

 

 

 

(Cap 354) and ETWBTC No. 15/2003, Waste

 

 

·       Training of site personnel in proper waste management and chemical handling procedures;

 

 

 

Management on

 

 

·       Provision of sufficient waste disposal points and regular collection of waste;

 

 

 

Construction Site

 

 

·       Appropriate measures to minimise windblown litter and dust during transportation of waste by either covering trucks or by transporting wastes in enclosed containers.

 

 

 

 

 

6.6.2

5.3

Waste Reduction Measures

 

Good management and control can prevent the generation of a significant amount of waste.  Waste reduction is best achieved at the planning and design stage, as well as by ensuring the implementation of good site practices. Recommendations to achieve waste reduction include:

WSD’s Contractor

Construction Work Sites (General)

During Construction works

 

 

 

·       Sort C&D material from demolition and decommissioning of the existing facilities to recover recyclable portions such as metals;

 

 

 

 

 

·       Segregation and storage of different types of waste in different containers, skips or stockpiles to enhance reuse or recycling of materials and their proper disposal;

 

 

 

 

 

o      Encourage collection of aluminium cans by providing separate labelled bins to enable this waste to be segregated from other general refuse generated by the work force;

 

 

 

 

 

o      Proper storage and site practices to minimise the potential for damage or contamination of construction materials; and

 

 

 

 

 

 

o      Plan and stock construction materials carefully to minimise amount of waste generated and avoid unnecessary generation of waste.

 

 

 

 

 

6.6.3

5.3

C&D Material

 

In order to minimise impacts resulting from collection and transportation of C&D material for off-site disposal, the excavated materials should be reused on-site as backfilling material and for landscaping works as far as practicable.  In addition, C&D material generated from excavation works should be disposed of at public fill reception facilities for other beneficial uses. Other mitigation requirements are listed below:

WSD’s Contractor

Construction Work Sites (General)

During Construction works

ETWB TCW No. 31/2004

 

 

·       A Waste Management Plan should be prepared;

 

 

 

 

 

 

·       A recording system for the amount of wastes generated, recycled and disposed (including the disposal sites) should be proposed; and

 

 

 

 

 

 

·       In order to monitor the disposal of C&D material and solid wastes at public filling facilities and landfills, and to control fly-tipping, a trip-ticket system (e.g. ETWB TCW No. 31/2004) should be included.

 

 

 

 

 

6.6.4

5.3

General Refuse

 

General refuse should be stored in enclosed bins or compaction units separate from C&D material.  A reputable waste collector should be employed by the contractor to remove general refuse from the site, separately from C&D material.  Preferably an enclosed and covered area should be provided to reduce the occurrence of 'wind blown' light material.

 

WSD’s Contractor

Construction Work Sites (General)

During Construction  works

 

6.6.5

5.3

Chemical Waste

 

Good quality containers compatible with the chemical wastes should be used, and incompatible chemicals should be stored separately.  Appropriate labels should be securely attached on each chemical waste container indicating the corresponding chemical characteristics of the chemical waste, such as explosive, flammable, oxidizing, irritant, toxic, harmful, corrosive, etc.  The Contractor shall use a licensed collector to transport and dispose of the chemical wastes, to either the approved Chemical Waste Treatment Centre, or another licensed facility.

WSD’s Contractor

Construction Work Sites (General)

During Construction works

Code of Practice on the Packaging, Labelling and Storage of Chemical Wastes, Waste Disposal (Chemical Waste) (General) Regulation

6.6.6

5.3

Marine Dredged Sediment

 

During transportation and disposal of the dredged marine sediments, the following measures should be taken to minimise potential impacts on water quality:

WSD’s Contractor

Construction Work Sites (Along the alignment of dredging)

During Marine Construction works

ETWB TCW No. 34/2002

 

 

·       Bottom opening of barges shall be fitted with tight fitting seals to prevent leakage of material. Excess material shall be cleaned from the decks and exposed fittings of barges and dredgers before the vessel is moved;

 

 

 

 

 

 

·       Monitoring of the barge loading shall be conducted to ensure that loss of material does not take place during transportation.  Transport barges or vessels shall be equipped with automatic self-monitoring devices as specified by the EPD; and

 

 

 

 

 

 

·       Barges or hopper barges shall not be filled to a level that would cause the overflow of materials or sediment laden water during loading or transportation.

 

 

 

 

 

Air Quality

7.5.1

6.30

Dust Control

 

Construction dust impacts should be controlled within the 1-hour TSP criterion of 500 g/m3 and 24-hour TSP AQO of 260 g/m3.  Therefore, effective control measures and good site practices should be implemented :

WSD’s Contractor

Construction Work Sites (General

During Construction works

EIAO-TM and Air Pollution Control (Construction Dust) Regulation

 

 

·       Any excavated dusty materials or stockpile of dusty materials should be covered entirely by impervious sheeting or sprayed with water so as to maintain the entire surface wet, and recovered or backfilled or reinstated within 24 hours of the excavation or unloading;

 

 

 

 

 

 

·       The working area of excavation should be sprayed with water immediately before, during and immediately after the operations so as to maintain the entire surface wet;

 

 

 

 

 

 

·       The load of dusty materials carried by vehicle leaving a construction site should be covered entirely by clean impervious sheeting to ensure that the dusty materials do not leak from the vehicle;

 

 

 

 

 

 

·       Where a site boundary adjoins a road, streets or other area accessible to the public, hoarding of not less than 2.4m high from ground level should be provided along the entire length except for a site entrance or exit;

 

 

 

 

 

 

·       The area where vehicle washing takes place and the section of the road between the washing facilities and the exit point should be paved with concrete, bituminous materials or hardcores;

 

 

 

 

 

 

·       Every main haul road should be scaled with concrete and kept clear of dusty materials or sprayed with water so as to maintain the entire road surface wet;

 

 

 

 

 

 

·       The portion of road leading only to a construction site that is within 30m of a designated vehicle entrance or exit should be kept clear of dusty materials;

 

 

 

 

 

 

·       All dusty materials should be sprayed with water prior to any loading, unloading or transfer operation so as to maintain the dusty material wet;

 

 

 

 

 

 

·       Vehicle speed should be limited to 10 kph except on completed access roads; and

 

 

 

 

 

 

·       Every vehicle should be washed to remove any dusty materials from its body and wheels before leaving the construction sites.

 

 

 

 

 

Cultural Heritage

8.7

7

 

No cultural heritage resources are identified within the Study Area and therefore, no mitigation measures are considered necessary.

 

 

 

 

 

Fisheries

9.7

8

 

Impacts to fisheries resources and fishing operations have largely been avoided during construction through constraints on the works operations for installation of the submarine watermain. Good construction practice and associated measures recommended for Water Quality to control water quality impacts to within acceptable levels and are also expected to control impacts to fisheries resources.

 

WSD’s Contractor

Construction Work Sites (General)

During Marine Construction works

EIAO-TM

 

 

 

(1)     City University of Hong Kong (2001), Consultancy Study on Fisheries and Marine Ecological Criteria for Impact Assessment, Final Report, For Agriculture, Fisheries and Conservation Department, Hong Kong SAR Government.

(2)     Maunsell Consultants Asia Ltd. (2001), Environmental Impact Assessment for Tai Po Sewage Treatment Works – Stage V, Final EIA Report, For Drainage Services Department, Hong Kong SAR Government.

(3)     Hawker, D. W. and Connell, D. W. (1992).  “Standards and Criteria for Pollution Control in Coral Reef Areas” in Connell, D. W and Hawker, D. W. (eds.), Pollution in Tropical Aquatic Systems, CRC Press, Inc.

(4)     ERM Hong Kong Ltd. (2001), Environmental Impact Assessment for the Proposed submarine Gas Pipeline from Cheng Tou Jiao Liquefied Natural Gas Receiving Terminal, Shenzhen to Tai Po Gas Production Plant, Hong Kong,  Final EIA Report, For the Hong Kong and China Gas Co., Ltd.

(5)     EPD (2005).  Marine Water Quality in Hong Kong in 2004.

(6)     Mott MacDonald (1991).  Contaminated Spoil Management Study, Final Report, Volume 1.

(7)     Environmental Quality Standards and Assessment Levels for Coastal Surface Water (from HMIP (1994) Environmental Economic and BPEO Assessment Principals for Integrated Pollution Control). (Source: Environmental Impact Assessment Study for Disposal of Contaminated Mud in the East Sha Chau Marine Borrow Pit, by ERM, January 1997).

(8)     ERM-Hong Kong Ltd (1997).  Environmental Impact Assessment for the Disposal of Contaminated Mud in the East Sha Chau Marine Borrow Pit.  Final EIA Report, For Civil Engineering Department, Hong Kong SAR Government.

(9)     Ludwig, D.D., Sherard, J. H. And Amende, R. A. (1988).  An Evaluation of the Standard Elutriate Test as an Estimator of Contaminant Release at the Point of Dredging.  Contract Report HL-88-1, prepared by Virginia Polytechnic Institute, Blacksburg VA, for the US Army Engineer Waterways Experiment Station, Vicksburg, MS.

(10)  Maunsell Consultants Asia Ltd (2001), Agreement No. CE 74/98, Wan Chai Development Phase II Comprehensive Feasibility Study, Final Environmental Impact Assessment Report, for Territory Development Department.

(11)  Morton, B. and Morton, J. (1983). The Sea Shore Ecology of Hong Kong. Hong Kong University Press.

(12)  Environmental Protection Department (2005). Marine Water Quality in Hong Kong in 2004.

(13)  Ibid

(14)  ERM (1998). Dredging an Area of Kellett Bank for Reprovisioning of Six Government Mooring Buoys Environmental  Impact Assessment. Civil Engineering Department.

(15)  Maunsell Consultants Asia Ltd. (2002). Yau Tong Bay Development Reclamation of Yau Tong Bay Environmental Impact Assessment Study.

(16)  Morton, B. and Morton, J. (1983). Op cit.

(17)  Morton, B. and Morton, J. (1983). Op cit.

(18)  Morton, B. and Morton, J. (1983). Op cit.

(19)  Environmental Resources Management (1998). Op cit.

(20)  Ibid.

(21)  Ibid

(22)  .Morton, B. and Morton, J. (1983). Op cit.

(23)  Ibid.

(24)  Environmental Resources Management (1998). Op cit.

(25)  Mouchel Asia Limited (2002). Maintenance Dredging for Central Fairway Phases 1, 2 & 3 Sediment Quality Report. Civil Engineering Department, Geotechnical Engineering Office HKSAR.

(26)  CityU Professional Services Limited (2002). Consultancy Study on Marine Benthic Communities in Hong Kong. AFCD.

(27)  ERM (1998). Op cit.

(28)  Ibid.

(29)  CityU Professional Services Limited (2002). Op cit.

(30)  ERM (1998). Op cit.

(31)  CityU Professional Services Limited (2002). Op cit.

(32)  Binnie Consultants Limited (1994). South Cheung Chau & Sulphur Channel Seabed Ecology Pilot Survey by Grab Sample. Civil Engineering Department.

(33)  ERM (1998). Op cit.

(34)  ERM (1998). Op cit.

(35)  CityU Professional Services Limited (2002). Op cit.

(36)  ERM Hong Kong Ltd (1995). Backfilling of South Tsing Yi and North of Lantau MBAs: Final Environmental Impact Assessment. Civil Engineering Department.

(37)  Ibid.

(38)  Babtie BMT (1997). Green Island Development – Studies on Ecological, Water Quality and Marine Traffic Impacts. Initial Ecological and Water Quality Impacts Report. TDD.

(39)  ERM (1998). Op cit.

(40)  ERM (1998). Op cit.

(41)  IUCN 2006. 2006 IUCN Red List of Threatened Species. <www.iucnredlist.org>. Downloaded on 11 October 2006.

(42)  UNEP-WCMC. 11 October, 2006. UNEP-WCMC Species Database: CITES-Listed Species http://www.unep-wcmc.org/isdb/CITES/Taxonomy/index.cfm
On the World Wide Web : http://www.unep-wcmc.org/isdb/CITES/Taxonomy/country_list.cfm?col=I&country=HK&source=animals&displaylanguage=eng

(43)  Clarke, S.C., Jackson, A.P. and Neff, J. (2000). Development of a Risk Assessment Methodology for Evaluating Potential Impacts Associated with Contaminated Mud Disposal in the Marine Environment. Chemosphere 41:69-76.

(44)  AFCD web page downloaded on 11 October 2006: http://www.afcd.gov.hk/english/conservation/con_mar/con_mar_chi/con_mar_chi_chi/con_mar_chi_chi_dis_hk.html

(45)  AFCD (2005). Monitoring of Chinese White Dolphins (Sousa chinensis) in Hong Kong Waters.

(46)  Ibid.

(47)  ERM (1998). Op cit.

(48)  Agriculture, Fisheries and Conservation Department (1998)  Port Survey 1996/1997.

(49)  Agriculture, Fisheries and Conservation Department (2006)  Port Survey 2001/2002, Web site www.afcd.gov.hk.

(50)  ERM (1998)  Fisheries Resources and Fishing Operations in Hong Kong Waters, Final Report, for Agriculture, Fisheries and Conservation Department, March 1998

(51)  Agriculture, Fisheries and Conservation Department (2006) Web site www.afcd.gov.hk

(52)  ScottWilson (2001) Planning and Engineering Feasibility Study for Sham Tseng Development, EIA Final Report., for Civil Engineering Department.

(53)  City University of Hong Kong (2001), Consultancy Study on Fisheries and Marine Ecological Criteria for Impact Assessment, Final Report, For Agriculture, Fisheries and Conservation Department, Hong Kong SAR Government.