Laying of
Environmental
Monitoring & Audit Manual
April 2007
Mott
Connell Ltd
40th
floor, Hopewell Centre
183
Queen’s Road East
Wanchai
Tel:
2828 5757
Fax:
2827
1823
Chapters
1.6 Environmental Monitoring and Audit Requirements
2.3 Sampling Procedures and Monitoring Equipment
2.7 Post-Construction Monitoring
2.8 Event and Action Plan for Water Quality
4.7 Event and Action Plan for Noise
9.2 Compliance with Legal and Contractual Requirements
10.3 Baseline Monitoring Report
10.6 Interim Notifications of Environmental Quality Limit
Exceedances
List of Tables
Table
2‑1.... Water Quality
Monitoring Stations
Table
2‑2.... Typical Action
and Limit Levels for Water Quality
Table
2‑3.... Event and Action
Plan for Water Quality for Construction Phase
Table
4‑1.... Noise Monitoring
Stations
Table
4‑2.... Action and Limit
Levels for Construction Noise
Table
4‑3.... Event and Action
Plan for Construction Noise
List of Figures
Figure 1.2a Location of Sea Water Intakes, Stormwater
Outfalls and Coral Sites in Victoria Harbour
Figure 1.2b Location of Noise Sensitive Receivers in Sai Ying Pun
Figure 1.2c Location of Noise Sensitive Receivers in West Kowloon
Figure 1.2d Location of Air Sensitive Receivers in Sai Ying Pun
Figure
1.3 Project
Organisation and Lines of Communication
Figure 1.4 Tentative Project Programme
Figure 2.1 Proposed Location of Water Quality Monitoring Stations
Figure 2.2 Typical Configuration of Silt Curtain and Silt Screen
Figure 4.1 Proposed Location of Noise Monitoring Stations in Sai Ying Pun
Figure 4.2 Proposed Location of Noise Monitoring Stations in West Kowloon
Figure 4.3 Location of Night-time Dredging Zone
Figure 9.1 Complaint Response Procedures
List
of Annexes
Annex A Environmental Mitigation Implementation Schedule
Annex B Sample
Environmental Monitoring Data Recording Sheets
Annex D Sample Interim Notification of Environmental Quality Limit Exceedances
The purpose of this
Environmental Monitoring and Audit (EM&A) Manual (hereafter referred to as
the Manual) is to guide the setup of an EM&A programme to ensure compliance
with the Environmental Impact Assessment (EIA) study recommendations, to assess
the effectiveness of the recommended mitigation measures and to identify any
further need for additional mitigation measures or remedial action. This Manual
outlines the monitoring and audit programme proposed for the “Laying of Western
Cross Harbour
For the purpose of this
Manual, the "Engineer" shall refer to the Engineer as defined in the
Contract and the Engineer's Representative (ER), in cases where the Engineer's
powers have been delegated to the ER, in accordance with the Contract. The Environmental
Team (ET) Leader, who shall be responsible for and in charge of the ET, shall
refer to the person delegated the role of executing the environmental
monitoring and audit requirements.
It shall be noted that this
EM&A Manual is subject to changes. The Manual shall be reviewed and updated
later, where necessary, near the commencement of construction of the Project.
In February 2006, Mott Connell Ltd was commissioned by Water Supplies Department under Agreement No. CE 42/2005(WS) to carryout the investigation and preliminary design for the “Laying of Western Cross Harbour Main and Associated Land Mains from West Kowloon to Sai Ying Pun” (The Project).
The scope of the proposed Project comprises the following:
·
approximately
2100-metre section of 1200mm nominal diameter of submarine watermain across
Victoria Harbour from its connection at Lin Cheung Road in West Kowloon to the
existing Sai Ying Pun Fresh Water Pumping Station in Sheung Wan (a designated
project under EIA Ordinance); and
·
approximately 2200-metre section of 1200mm
nominal diameter of associated land watermain (Not a designated project under
EIA Ordinance).
The submarine watermain component (referred in first bullet above) of the
Project is a Designated Project under Schedule 2, Part 1(E3) of the Environmental
Impact Assessment Ordinance (EIAO) (Cap. 499) and an Environmental Permit (EP)
issued under the EIAO is required for the construction and operation of the designated
project. An application (No. ESB-132/2005) for a EIA study brief under
section 5(7)(a) of the EIAO was submitted by Water Supplies Department on
From the EIA, the
recommendations for monitoring contained herein, are made.
The proposed Project
covers three main areas, namely:
The works for
The works in
In Sai Ying Pun
(Not a designated project under EIA Ordinance), the works comprise Sai Ying Pun
area adjacent to Western Wholesale Food Market and is bounded by the approaches
of Western Harbour Crossing Interchange.
The proposed 1200mm diameter fresh watermain will be laid in this
portion for connection to the existing Sai Ying Pun Fresh Water Pumping Station
situated at the junction of
The route of the
proposed watermains is illustrated in Figure
1.1.
Sensitive receivers have been identified in the EIA and are
shown on Figures 1.2a-d. Representative Sensitive Receivers (SRs) for
water quality, marine ecology, noise, air quality and fisheries are selected
according to the criteria set out in the Technical Memorandum on Environmental
Impact Assessment Ordinance (EIAO-TM) and listed as follows:
·
New Yau
Ma Tei Typhoon Shelter (WSR);
·
Coral
communities at
·
17 sea water intakes at the waterfront of
·
Marine
habitats in
·
Residential
buildings in West Kowloon including The Waterfront, Sorrento, The Arch, The
Harbourside and the Union Square (NSRs);
·
Residential
buildings in Sai Ying Pun including Fung Shing Building, Viking Court, Cheong
Ling Mansion, Kwan Yik Building Phase 2 & 3, Richwealth Mansion, Connaught
Garden and General Building (ASRs and NSRs);
·
Other
buildings in Sai Ying Pun including Tianjin Building, China Merchants Group,
the Westpoint, Island Pacific Hotel, Singga Commercial Building, AFCD Market
Office and Western Wholesale Food Market (ASRs).
1.6
Environmental Monitoring and Audit Requirements
The EIA study identified the
likely environmental impacts during construction and operation phases. These
impacts can be minimised to acceptable levels with the implementation of
environmental mitigation measures and environmental monitoring and audit
requirements. An Implementation Schedule
of the Environmental Mitigation Measures recommended in the EIA Report is
described in Annex A. To ensure the environmental acceptability of
the proposed Project, monitoring and audit requirements have been identified
and are described in detail in the subsequent sections. A summary of the
EM&A requirements on different environmental aspects studied in the EIA is
provided below:
Water Quality
A marine water quality monitoring and audit programme is
recommended during the dredging works to verify whether or not impact
predictions are representative, and to ensure that the dredging works along the
alignment of the proposed cross harbour main do not result in unacceptable
impacts and the seawater quality at WSD’s seawater intakes comply with the
WSD’s Water Quality Objectives (WQOs) of seawater for flushing supply. If
monitoring shows unacceptable water quality impact, appropriate mitigation
measures, such as changes in the operation of dredging works, should be
introduced.
Marine Ecology
The implementation of the
ecological mitigation measures stated in Section
4.8 and water quality mitigation measures in Section 3 of the EIA report should be checked as part of the
environmental monitoring and audit procedures during the construction period. No
other marine ecology-specific measures are considered necessary.
Noise
Full compliance with the noise
criteria will be achieved at all NSRs with the implementation of mitigation
measures. Environmental monitoring and
audit is recommended to ensure that the noise levels do not exceed the criteria
during the construction phase.
Auditing of each waste stream
is recommended to be carried out periodically to determine if wastes are being
managed in accordance with approved procedures and the site waste management
plan. The audits should look at all aspects of waste management including waste
generation, storage, recycling, treatment, transport and disposal. An
appropriate audit programme would be to undertake a first audit at the
commencement of the construction works, and to audit weekly thereafter.
Air Quality
Full compliance with the air quality
criteria will be achieved at all ASRs with the implementation of mitigation
measures. Dust monitoring is considered not necessary but weekly site audits
are required to ensure that the dust control measures are properly implemented.
Cultural Heritage
As discussed in Section 8 of
the EIA report, no indication of marine archaeological material was identified
and no further investigation activities were recommended. As such, there would be no need for a
cultural heritage monitoring programme during the construction phase of the
submarine watermain.
Fisheries
The implementation of the water quality mitigation
measures stated in Section 3 of the
EIA report should be checked as part of the environmental monitoring and audit
procedures during the construction period. No other fisheries-specific measures are considered necessary.
The proposed project
organisation is shown in Figure 1.3. The responsibilities of respective parties
are:
The Contractor
·
provide assistance to ET in carrying out
monitoring;
·
submit proposals on mitigation measures in case
of exceedances of Action and Limit levels in accordance with the Event and
Action Plans;
· implement measures to reduce impact where Action and Limit levels are exceeded;
·
employ a ET to carryout the EM&A works; and
·
adhere to the procedures for carrying out
complaint investigation in accordance with Section
9.3.
The Engineer or Engineer
Representative (ER)
·
supervise the Contractors activities and ensure
that the requirements in the Manual are fully complied with;
·
inform the Contractor when action is required to
reduce impacts in accordance with the Event and Action Plans;
·
employ an IEC to audit the results of the
EM&A works carried out by the ET; and
·
adhere to the procedures for carrying out complaint
investigation in accordance with Section
9.3.
The Environmental Team (ET)
·
monitor the various environmental parameters as
required in the Manual;
·
analyse the EM&A data and review the success
of EM&A programme to cost effectively confirm the adequacy of mitigation
measures implemented and the validity of the EIA predictions and to identify
any adverse environmental impacts arising;
·
carry out site inspections to investigate and
audit the Contractor’s site practice, equipment and work methodologies with
respect to pollution control and environmental mitigation, and anticipate
environmental issues for proactive action before problems arise;
·
audit and prepare audit reports on the
environmental monitoring data and the site environmental conditions;
·
report on the EM&A results to the IEC,
Contractor, the ER, and the EPD;
·
recommend suitable mitigation measures to the
Contractor in the case of exceedance of Action and Limit levels in accordance
with the Event and Action Plans; and
·
adhere to the procedures for carrying out
complaint investigation in accordance with Section
9.3.
The ET leader shall have relevant professional qualifications
and at least 7 years of experience in environmental monitoring and audit
(EM&A) or environmental management subject to approval of the ER and the
Environmental Protection Department (EPD).
Independent Environmental Checker
(IEC)
·
check, review, verify the EM&A works
performed by the ET;
·
audit the monitoring activities and results;
·
evaluate the EM&A reports submitted by the ET;
·
review the proposals for mitigation measures
submitted by the Contractor in accordance with the Event and Action Plans; and
·
adhere to the procedures for carrying out
complaint investigation in accordance with Section
9.3.
The IEC shall have relevant professional
qualifications and at least 7 years of experience in environmental monitoring
and audit (EM&A) or environmental management subject to approval of the ER
and the EPD.
Sufficient and suitably
qualified professional and technical staff shall be employed by the respective
parties to ensure full compliance with their duties and responsibility, as
required under the EM&A programme for the duration of the project. The ET shall not be in any way an associated
body of the Contractor and the IEC. The IEC shall not be in any an associated
body of the Contractor or the ET.
The construction of the proposed Project is scheduled to commence in September 2008 for completion by May 2011. The tentative project programme is given in Figure 1.4.
As identified in
the EIA Report, a key water quality issue of the construction phase would be
dredging works for the pipeline trench.
Marine water quality monitoring shall be carried out during the dredging
works to ensure that any unacceptable increase in suspended solids/turbidity
and decrease in dissolved oxygen due to dredging activities could be readily
detected and timely action be taken to rectify the situation.
Monitoring for Dissolved Oxygen (DO), Dissolved Oxygen Saturation (DO%), temperature, turbidity, salinity, suspended solid (SS) and water depth shall be undertaken at designated monitoring locations. All parameters should be measured in-situ whereas SS shall be determined by the laboratory. DO shall be presented in mg/L and in % saturation.
Other relevant
data shall also be recorded, including monitoring location / position, time,
tidal stages, weather conditions and any special phenomena or work underway at
the construction site.
2.3
Sampling Procedures and Monitoring Equipment
(N.B. Water
samples for all monitoring parameters shall be collected, stored, preserved and
analysis according to Standard Methods, APHA 19 ed. and/or methods agreed by
the Director of Environmental Protection. In-situ
measurements at monitoring locations including DO, temperature, turbidity,
salinity and water depth shall be collected by equipment with the
characteristics and functions listed in the following sections).
The following
equipment and facilities shall be provided by the ET and used for the
monitoring of water quality impacts:
Dissolved Oxygen and Temperature Measuring
Equipment
DO and water
temperature should be measured in-situ by a DO/ temperature meter. The
instrument should be portable and weatherproof using a DC power source. It
should have a membrane electrode with automatic temperature compensation
complete with a cable. The equipment should be capable of measuring:
·
a DO level in the range of 0-20 mg/1 and 0-200%
saturation; and
·
a temperature of between 0 and 45 degree
Celsius.
Turbidity Measurement Instrument
The instrument
should be portable and weatherproof using a DC power source. It should have a photoelectric sensor capable
of measuring turbidity between 0-1000 NTU, such as a Hach model 2100P or
similar approved.
Salinity
A portable
salinometer with measuring range of 0-40 mg/L (YSI 30 Salinity meter or other
approved instrument) should be used to determine the salinity of the water.
Water Depth Detector
A portable, battery-operated echo sounder (Seafarer 700 or other approved instrument) would be used for the measurement of water depth at each designated monitoring station. The unit would be either handheld or affixed to the bottom of the work boat, if the same vessel is to be used throughout the monitoring programme.
Positioning Device
A digital Global Positioning System (GPS) should be used during monitoring to ensure the monitoring vessel is at the correct location before taking measurements.
Calibration of In-Situ Instruments
All in-situ monitoring instruments would be checked, calibrated and certified by a laboratory accredited under HOKLAS or any other international accreditation scheme before use, and subsequently re-calibrated at 3 monthly intervals throughout all stages of the water quality monitoring programme. Responses of sensors and electrodes should be checked with certified standard solutions before each use.
Wet bulb calibration for a DO probe should be carried out at least once per monitoring day. A zero check in distilled water should be performed with the turbidity probe at least once per monitoring day. The probe should then be calibrated with a solution of known NTU. In addition, the turbidity probe should be calibrated at least twice per month to establish the relationship between turbidity readings (in NTU) and levels of suspended solids (in mgL-1).
For the on-site
calibration of field equipment, the BS 1427: 1993, Guide to Field and On-Site Test Methods for the Analysis of Waters
should be observed. Sufficient stocks of spare parts should be maintained for
replacements when necessary. Backup monitoring equipment should also be made
available so that monitoring could proceed uninterrupted even when some
equipment is under maintenance, calibration etc.
A water sampler comprises a transparent PVC cylinder, with a capacity of not less than 2 litres, and could be effectively sealed with latex cups at both ends should be used. The sampler should have a positive latching system to keep it open and prevent premature closure until released by a messenger when the sampler is at the selected water depth (Kahlsico Water Sampler or an approved similar instrument).
Water samples for suspended solids measurement should be collected in high density polythene bottles, packed in ice (cooled to 4°C without being frozen), and delivered to the laboratory as soon as possible after collection.
Laboratory Measurement/Analysis
Analysis of suspended solids should be carried out in a HOKLAS or other international accredited laboratory. Water samples of about 1L should be collected at the monitoring stations for carrying out the laboratory suspended solids determination. The SS determination work should start within 24 hours after collection of the water samples. The SS analyses should follow the standard method APHA 2540D with a detection limit of 1mg/L as described in APHA Standard Methods for the Examination of Water and Wastewater, 19th Edition, unless otherwise specified.
If in-house or non-standard methods are proposed, details of the method verification should, if required, be submitted to EPD. In any circumstances, the sample testing should have comprehensive quality assurance and quality control programmes. The laboratory should be prepared to demonstrate the quality control programmes to EPD or their representative if and when required.
Additional duplicate samples may be required by EPD for inter laboratory calibration. Remaining samples after analysis should be kept by the laboratory for 3 months in case repeat analysis is required. If in-house or non-standard methods are proposed, details of the method verification may also be required to submit to EPD. In any circumstance, the sample testing should have comprehensive quality assurance and quality control programmes. The laboratory should prepare to demonstrate the programmes to EPD or his representatives when requested.
It is proposed to monitor the water quality in
the vicinity of
·
Dredging should be undertaken using one grab
dredger only with a maximum production rate of 4,000m3 per
day;
·
Deployment of frame type silt curtain to fully
enclose the grab while dredging works are in progress;
·
Deployment of silt screen at the sea water intake at
Kowloon South Salt Water Pumping Station while dredging works are in progress.
It is recommended to conduct the monitoring at the appropriate vertical levels of the abstraction points of the seawater intakes to collect information on the mitigated water quality condition if practicable. Four Control Stations are proposed to represent the project site in its undisturbed condition and their respective positions are also shown in Figure 2.1.
Table 2‑1 Water Quality Monitoring Stations
ID |
Description |
Easting |
Northing |
R5 |
|
830 175.979 |
816 179.217 |
R6 |
|
833 437.625 |
816 747.640 |
R7 |
|
833 461.092 |
816 744.773 |
R8 |
|
833 786.796 |
816 663.359 |
R15 |
|
833 982.630 |
818 282.101 |
R16 |
|
834 335.800 |
817 769.145 |
R17 |
|
834 364.658 |
817 802.847 |
R28 |
|
830 707 |
815 983 |
R29 |
WSD Sheung Wan Salt Water Pumping Station |
833 414 |
816 745 |
C1 |
Control Station |
830 797.729 |
819 163.377 |
C2 |
Control Station |
836 30.628 |
817 135.218 |
C3 |
Control Station |
829 495.126 |
817 228.312 |
C4 |
Control Station |
836 638.773 |
816 686.030 |
When alternative
monitoring locations are proposed, they shall be chosen based on the following
criteria:
(a) at locations close
to and preferably at the boundary of the mixing zone of the major site
activities as indicated in the EIA report, which are likely to have water
quality impacts;
(b) close to the sensitive receptors which are
directly or likely to be affected;
(c) for monitoring
locations located in the vicinity of the sensitive receptors, care shall be
taken to cause minimal disturbance during monitoring;
Measurement shall
be taken at 3 water depths, namely, 1m below water surface, mid-depth and 1m
above sea bed, except where the water depth less that 6m, the mid-depth station
may be omitted. Should the water depth be less than 3m, only the mid-depth
station will be monitored. The ET Leader shall seek approval from the IEC and
EPD on all the monitoring stations.
Replicates in-situ
measurements and samples collected from each independent monitoring event are
required for all parameters to ensure a robust statistically interpretable
dataset.
The purpose of the
baseline monitoring is to establish ambient conditions prior to the
commencement of marine construction works and to demonstrate the suitability of
the proposed monitoring stations. The measurements should be taken at all
designated monitoring stations, 3-days per week, at mid-flood and mid-ebb
tides, for at least 4 consecutive weeks prior to the commencement of marine
construction works.
Two consecutive
measurements of DO concentration (mgL-1), DO saturation (%) and
turbidity (NTU) should be taken in-situ according to the stated sampling
method. Where the difference in value between the first and second measurement
of DO or turbidity parameters is more than 25% of the value of the first
reading, the reading should be discarded and further readings should be taken.
Water samples for SS (mgL-1) measurements should be collected at the
same depths.
In addition to the
above in-situ measurements, water temperature and salinity should be determined
at all monitoring stations at the same depths, as specified above. Note that in
addition to the water depth, monitoring location/position, time, weather
conditions, sea conditions (where appropriate), tidal stage (where
appropriate), and any special phenomena should be recorded.
The baseline
monitoring campaign should be executed prior to commencement of marine
construction works. In exceptional cases, when insufficient baseline monitoring
data or questionable results are obtained, the ET Leader should liaise with the
IEC and EPD to agree on an appropriate set of data to be used as a baseline
reference and submit to ER for approval.
Baseline monitoring
schedule should be submitted to the Contractor, IEC, ER and EPD one week prior
to the commencement of baseline monitoring. The interval between two sets of
monitoring would not be less than 36 hours.
During the course of
the marine construction works, impact monitoring should be undertaken at all
monitoring stations three working days per week, at mid-ebb and mid-flood
tides, with sampling /measurement. The interval between two sets of monitoring
should not be less than 36 hours except where the Action and/or Limit levels
is/are exceeded, in which case the monitoring frequency should be increased.
Two consecutive
measurements of DO concentration (mgL-1), DO saturation (%) and
turbidity (NTU) should be taken in-situ according to the stated sampling
method. Where the difference in value between the first and second measurement
of DO or turbidity parameters is more than 25% of the value of the first
reading, the reading should be discarded and further readings would be taken.
Water samples for SS (mgL-1) measurements should be collected at the
same depths. Duplicate water samples should be taken and analyzed.
In addition to the
above in-situ measurements, water temperature and salinity should be determined
at all monitoring stations at the same depths, as specified above. Note that in
addition to the water depth, monitoring location/position, time, weather
conditions, sea conditions (where appropriate), tidal stage (where
appropriate), and any special phenomena should be recorded.
Proposed water
quality monitoring schedule should be provided to the Contractor, IEC, ER and
EPD on or before the first day of the monitoring month. The Contractor, IEC, ER
and EPD should be notified immediately for any changes in schedule.
2.7
Post-Construction Monitoring
Upon completion of all marine construction activities, a post project water quality monitoring exercise should be carried out for four weeks upon completion of all marine activities, in the same manner as the impact monitoring during construction of the submarine watermain.
2.8
Event and Action Plan for Water Quality
The Action and
Limit (AL) Levels for water quality are defined in Table 2-2. The actions in accordance with the Action Plan in Table 2-3 shall be carried out if the
water quality assessment criteria are exceeded at any designated monitoring
points.
Table 2‑2 Typical Action and Limit Levels for Water
Quality
Parameters |
Action Level |
Limit Level |
DO in mg/l (Surface, Middle & Bottom) |
WSD
Seawater Intakes 2
mg/L Other
Impact Monitoring Stations 5
percentile of baseline data |
Surface and Middle WSD
Seawater Intakes 2
mg/L Other
Impact Monitoring Stations 4
mg/L or 1 percentile of baseline data Bottom 2
mg/L or 1 percentile of baseline data |
SS
in mg/l (depth-averaged) |
WSD
Seawater Intakes 10
mg/L Other
Impact Monitoring Stations 95
percentile of baseline data |
WSD
Seawater Intakes 10
mg/L Other
Impact Monitoring Stations 99
percentile of baseline data |
Turbidity
(depth-averaged) |
WSD
Seawater Intakes 10
NTU Other
Impact Monitoring Stations 95
percentile of baseline data |
WSD
Seawater Intakes 10
NTU Other
Impact Monitoring Stations 99
percentile of baseline data |
Notes: 1. “Depth-averaged” is calculated by taking
the arithmetic means of the readings of the three depths.
2. For DO measurement,
non-compliance occurs when monitoring result is lower than the limits.
3. For SS and turbidity,
non-compliance of water quality results when monitoring results is higher than
the limits.
4. All the figures given in the
table are used for reference only and the EPD may amend the figures whenever
necessary.
Table 2‑3 Event and Action Plan for Water Quality for
Construction Phase
Event |
Action |
|||
ET Leader |
IEC |
ER |
Contractor |
|
Action Level |
|
|
|
|
1. Exceedance for one sample |
1. Repeat in-situ measurement to confirm
finding; 2. Identify source(s) of impact; 3. Inform IEC and Contractor; 4. Check monitoring data, all plant, equipment
and Contractor’s working methods; 5. Discuss mitigation measures with IEC and
Contractor; and 6. Repeat measurement on next day of
exceedance. |
1. Discuss with ET and Contractor on the
mitigation measures; 2. Review proposals on mitigation measures
submitted by Contractor and advise the ER accordingly; and 3. Assess the effectiveness of the implemented
mitigation measures. |
1. Discuss with IEC on the proposed mitigation
measures; and 2. Make agreement on the mitigation measures
to be implemented. |
1. Inform the ER and confirm notification of
the non-compliance in writing; 2. Rectify unacceptable practice; 3. Check all plant and equipment; 4. Consider changes of working methods; 5. Discuss with ET and IEC and propose
mitigation measures to IEC and ER; and 6. Implement the agreed mitigation measures. |
2. Exceedance for two or more consecutive
samples |
1. Repeat in-situ measurement to confirm
finding; 2. Identify source(s) of impact; 3. Inform IEC and Contractor; 4. Check monitoring data, all plant, equipment
and Contractor’s working methods; 5. Discuss mitigation measures with IEC and
Contractor; 6. Ensure mitigation measures are implemented; 7. Prepare to increase the monitoring
frequency to daily; and 8. Repeat measurement on next day of
exceedance. |
1. Discuss with ET and Contractor on the
mitigation measures; 2. Review proposals on mitigation measures
submitted by Contractor and advise the ER accordingly; and 3. Assess the effectiveness of the implemented
mitigation measures. |
1. Discuss with IEC on the proposed mitigation
measures; 2. Make agreement on the mitigation measures
to be implemented; and 3. Assess the effectiveness of the implemented
mitigation measures. |
1. Inform the Engineer and confirm
notification of the non-compliance in writing; 2. Rectify unacceptable practice; 3. Check all plant and equipment; 4. Consider changes of working methods; 5. Discuss with ET and IEC and propose
mitigation measures to IEC and ER within 3 working days; and 6. Implement the agreed mitigation measures. |
Limit Level |
|
|
|
|
1. Exceedance for one sample |
1. Repeat in-situ measurement to confirm
finding; 2. Identify source(s) of impact; 3. Inform IEC, Contractor and EPD; 4. Check monitoring data, all plant, equipment
and Contractor’s working methods; 5. Discuss mitigation measures with IEC, ER
and Contractor; 6. Ensure mitigation measures are implemented;
and 7. Increase the monitoring frequency to daily
until no exceedance of Limit level. |
1. Discuss with ET and Contractor on the
mitigation measures; 2. Review proposals on mitigation measures
submitted by Contractor and advise the ER accordingly; and 3. Assess the effectiveness of the implemented
mitigation measures. |
1. Discuss with IEC, ET and Contractor on the
proposed mitigation measures; and 2. Request Contractor to critically review the
working methods; 3. Make agreement on the mitigation measures
to be implemented; and 4. Assess the effectiveness of the implemented
mitigation measures. |
1. Inform the Engineer and confirm
notification of the non-compliance in writing; 2. Rectify unacceptable practice; 3. Check all plant and equipment; 4. Consider changes of working methods; 5. Discuss with ET and IEC and ER and propose
mitigation measures to IEC and ER within 3 working days; and 6. Implement the agreed mitigation measures. |
2. Exceedance for two or more consecutive
samples |
1. Repeat in-situ measurement to confirm
finding; 2. Identify source(s) of impact; 3. Inform IEC, Contractor and EPD; 4. Check monitoring data, all plant, equipment
and Contractor’s working methods; 5. Discuss mitigation measures with IEC, ER
and Contractor; 6. Ensure mitigation measures are implemented;
and 7. Increase the monitoring frequency to daily
until no exceedance of Limit level for two consecutive days. |
1. Discuss with ET and Contractor on the
mitigation measures; 2. Review proposals on mitigation measures
submitted by Contractor and advise the ER accordingly; and 3. Assess the effectiveness of the implemented
mitigation measures. |
1. Discuss with IEC, ET and Contractor on the
proposed mitigation measures; and 2. Request Contractor to critically review the
working methods; 3. Make agreement on the mitigation measures
to be implemented; 4. Assess the effectiveness of the implemented
mitigation measures; and 5. Consider and instruct, if necessary, the
Contractor to slow down or to stop all or part of the marine work until no
exceedance of Limit Level. |
1. Inform the ER and confirm notification of the
non-compliance in writing; 2. Rectify unacceptable practice; 3. Check all plant and equipment; 4. Consider changes of working methods; 5. Discuss with ET and IEC and ER and propose
mitigation measures to IEC and ER within 3 working days; 6. Implement the agreed mitigation measures;
and 7. As directed by the Engineer, to slow down
or to stop all or part of the marine work or construction activities. |
The mitigation
measures recommended for the construction phase of the submarine watermain are
summarized below. The implementation
schedule of the recommended water quality mitigation measures is presented in Annex A.
Specific Mitigation Measures for dredging
·
Dredging should be undertaken using one grab
dredger only with a maximum production rate of 4,000m3 per
day;
·
Deployment of frame type silt curtain to fully
enclose the grab while dredging works are in progress;
·
Deployment of silt screen at the sea water intake at
Kowloon South Salt Water Pumping Station while dredging works are in progress.
The frame type silt curtain should be designed to enclose local pollution caused by the grab dredger and suspended by a steel frame mounted on the grab dredger and floating on water. This frame type silt curtain should be fabricated from permeable, durable, abrasion resistant membrane like geotextiles and be mounted on a floating boom structure. The frame type silt curtain should also extend to the seabed to cover the entire water column. Steel chain or ballast should be attached to the bottom of the silt curtain. Mid-ballast may be added as necessary. The structure of the silt curtain should be maintained by metal grids. The frame type silt curtain should be capable or reducing sediment loss to outside by a factor of 4 (or about 75%)(1). Silt screen is recommended for dredging near the seawater intake at Kowloon South Salt Water Pumping Station. The implementation of silt screen at the intake could reduce the SS level by a factor of 2.5 (or about 60%)(1). An illustration of a typical configuration of frame type silt curtain and silt screen at seawater intake is shown in Figure 2.2.
Other Mitigation Measures for dredging
Good site practice
that should be undertaken during dredging includes:
·
Tight-closing grabs should be used to minimize the
loss of sediment to suspension during dredging works. For dredging of any contaminated mud, closed
watertight grabs must be used;
·
all vessels should be sized so that adequate
clearance is maintained between vessels and the seabed in all tide conditions,
to ensure that undue turbidity is not generated by turbulence from vessel
movement or propeller wash;
·
the decks of all vessels should be kept tidy and
free of oil or other substances that might be accidentally or otherwise washed
overboard;
·
adequate free board shall be maintained on barges to
ensure that decks are not washed by wave action;
·
all barges used for the transport of dredged
materials should be fitted with tight bottom seals to prevent leakage of
material during loading and transport;
·
construction activities should not cause foam, oil,
grease, scum, litter or other objectionable matter to be present in the water
within the site or dumping grounds;
·
loading of barges should be controlled to prevent
splashing of material into the surrounding waters. Barges should not be filled to a level that
would cause the overflow of materials or sediment laden water during loading or
transportation;
·
the speed of vessels should be controlled within the
works area to prevent propeller wash from stirring up the seabed sediments; and
·
before commencement of dredging works, the holder of
the Environmental Permit should submit detailed proposal of the design and
arrangement of the frame type silt curtain to EPD for approval.
Effluent from Hydrostatic Tests of the
Water Mains System
To ensure compliance with the standards for effluent discharged into the inshore waters or marine waters of Victoria Harbour WCZ as shown in Tables 9a and 9b of the TM-DSS and Section 23.73 and 23.77 of the General Specification for Civil Engineering Works Volume 3, 1992 Edition, sedimentation tanks with sufficient capacity, constructed from pre-formed individual cells of approximately 6 to 8 m3 capacities, are recommended as a general mitigation measure which can be used for settling the effluent prior to disposal. The system capacity should be flexible and suited to applications where the influent is pumped. Pre-treatment including dechlorination such as by physical process e.g. adsorption by activated carbon filter, or chemical process e.g. neutralisation by dechlorination agent dosing should be carried out to ensure compliance with the discharge requirements stipulated in TM-DSS.
Surface Runoff, Sewage and Wastewater from
Construction Activities
Appropriate measures should be implemented to control runoff and prevent high loads of SS from entering the marine environment. Proper site management is essential to minimise surface runoff and sewage effluents.
Construction site runoff should be prevented or minimised in accordance with the guidelines stipulated in the EPD's Practice Note for Professional Persons, Construction Site Drainage (ProPECC PN 1/94). All discharges from the construction site should be controlled to comply with the standards for effluents discharged into the Victoria Harbour WCZ under the TM-DSS. Good housekeeping and stormwater best management practices, as detailed below, should be implemented to ensure all construction runoff complies with WPCO standards and no unacceptable impact on the WSRs as a result of construction of the proposed submarine watermain.
Sedimentation tanks with sufficient capacity, constructed from pre-formed individual cells of approximately 6 to 8 m3 capacities, are recommended as a general mitigation measure which can be used for settling surface runoff prior to disposal. The system capacity should be flexible and able to handle multiple inputs from a variety of sources and suited to applications where the influent is pumped.
Manholes (including newly constructed ones) should always be adequately covered and temporarily sealed so as to prevent silt, construction materials or debris being washed into the storm runoff being directed into foul sewers.
All vehicles and plant should be cleaned before leaving a construction site to ensure no earth, mud, debris and the like is deposited by them on roads. An adequately designed and located wheel washing bay should be provided at every site exit, and wash-water should have sand and silt settled out and removed at least on a weekly basis to ensure the continued efficiency of the process. The section of access road leading to, and exiting from, the wheel-wash bay to the public road should be paved with sufficient backfill toward the wheel-wash bay to prevent vehicle tracking of soil and silty water to public roads and drains.
Precautions should be taken at any time of year when rainstorms are likely. Actions should be taken when a rainstorm is imminent or forecast. Actions to be taken during or after rainstorms are summarised in Appendix A2 of ProPECC PN 1/94. Particular attention should be paid to the control of silty surface runoff during storm events, particularly for areas located near steep slopes.
Fuel tanks and
storage areas should be provided with locks and be located on sealed areas,
within bunds of a capacity equal to 110% of the storage capacity of the largest
tank, to prevent spilled fuel oils from reaching the coastal waters of the
Portable chemical toilets would be used to handle construction workforce sewage prior to discharge to the existing trunk sewer. Sufficient numbers of portable toilets shall be provided by a licensed contractor to serve the construction workers. The Contractor shall also be responsible for waste disposal and maintenance practices.
A review of the
existing information showed that the marine ecological resources within the
dredging area consist of pollution tolerant soft benthos in low diversity and
typical to benthos recorded in poor quality sediments. Inter-tidal species along
The proposed dredging works would be confined in the works area within 25m at either side of the proposed alignment and the use of closed type grab dredger would reduce sediment and contaminants runoff to the water column. The trench would be backfilled with armour rock layer 4.5m thick with a 0.3m thick grade 75 bedding and gaps between the backfilled armour rock and the edge of the submarine pipeline trench would be filled by marine sediment within the sea volume from natural movement of the top soft soil of existing seabed to provide protection of the pipeline from damage by ship anchors. Benthic fauna is expected to be recolonized to the seabed after construction.
Mitigation
measures for water quality impacts as detailed in Section 2 of this EM&A Manual would apply to minimize the potential
impact on marine ecology. No other ecology-specific measures or Environmental
Monitoring and Audit Programme are considered necessary.
The monitoring
programme shall be carried out by the ET to ensure that the noise level of
construction works complies with the 75dB(A) criterion for domestic premises,
with 70 dB(A) for schools and with a further reduction to 65dB(A) during
examination periods.
The construction
noise level shall be measured in terms of the A-weighted equivalent continuous
sound pressure level (Leq). Leq(30
min) shall be used as the monitoring parameter for the time period
between 0700-1900 hours on normal weekdays.
Supplementary
information for data auditing, statistical results such as L10 and L90
shall also be obtained for reference.
A sample data record sheet is shown in Annex B for reference.
As refer to the
Technical Memorandum (TM) issued under the Noise Control Ordinance (NCO), sound
level metres in compliance with the International Electrotechnical Commission
Publications 651: 1979 (Type 1) and 804: 1985 (Type 1) specifications shall be
used for carrying out the noise monitoring.
The calibration of the sound level meters and their respective
calibrators shall be carried out in accordance with the manufacturer’s
requirements.
Noise measurements
shall not be made in the presence of fog, rain, wind with a steady speed
exceeding 5 ms-1 or wind with gusts exceeding 10 ms-1.
The ET Leader is
responsible for the provision and maintenance of the monitoring equipment. He shall ensure that sufficient noise
measuring equipment and associated instrumentation are available for carrying
out the baseline monitoring, regular impact monitoring and ad hoc
monitoring. All the equipment and
associated instrumentation shall be clearly labelled. The location of equipment installation should
be proposed by the ET Leader and agreed with the ER and EPD in consultation
with the IEC.
The noise
monitoring locations (Refer to Figure 4.1
and 4.2) are summarised in Table 4-1. The status and locations of noise sensitive
receivers may change after issuing this manual.
If such cases exist, the ET Leader shall propose updated monitoring
locations and seek agreement from ER, IEC and EPD.
Table 4‑1 Noise Monitoring Stations
ID |
Area |
Description |
KS4 |
|
The Harbourside |
KS6 |
|
|
CG |
Sai Ying Pun |
|
RWM |
Sai Ying Pun |
|
KY3 |
Sai Ying Pun |
|
When alternative
monitoring locations are proposed, the monitoring locations shall be chosen
based on the following criteria:
a)
at locations close to the major site activities
which are likely to have noise impacts;
b)
close to the noise sensitive receivers (any
domestic premises, temporary housing accommodation, educational institution,
place of public worship, shall be considered as a noise sensitive receiver);
and
c)
for monitoring locations located in the vicinity
of the sensitive receivers, care shall be taken to cause minimal disturbance to
the occupants during monitoring.
The monitoring
station shall normally be at a point 1m from the exterior of the sensitive
receivers building facade and be at a position 1.2m above the ground. If there is a problem with access to the
normal monitoring position, an alternative position may be chosen, and a
correction to the measurements shall be made.
For reference, a correction of +3dB(A) shall be made to the free field
measurements. The ET Leader shall agree
with the IEC on the monitoring positions and the correction adopted. Once the positions for the monitoring
stations are chosen, the baseline monitoring and the impact monitoring shall be
carried out at the same positions.
The ET shall carry out baseline noise monitoring prior to the commencement of the construction works. There shall not be any construction activities in the vicinity of the stations during the baseline monitoring. Continuous baseline noise monitoring for the A-weighted levels LAeq, LA10 and LA90 shall be carried out daily for a period of at least two weeks in a sample period of 30 minutes between 0700 and 1900. Baseline monitoring schedule should be submitted to the Contractor, IEC, ER and EPD one week prior to the commencement of the baseline monitoring.
In
exceptional case, when insufficient baseline monitoring data or questionable
results are obtained, the ET Leader shall liaise with IEC and EPD to agree on
an appropriate set of data to be used as a baseline reference and submit to ER
for approval.
During normal
construction working hour (0700-1900 Monday to Saturday), monitoring of LAeq,
30min noise levels (or as six consecutive LAeq, 5min readings)
shall be carried out at the agreed monitoring locations once every week in
accordance with the methodology in the TM.
Other noise
sources such as road traffic may make a significant contribution to the overall
noise environment. Therefore, the
results of noise monitoring activities will take into account such influencing
factors, which may not be presented during the baseline monitoring period.
In case of non-compliance with the construction noise criteria, more frequent monitoring as specified in the Event and Action Plan in Section 4.7 shall be carried out. This additional monitoring shall be continued until the recorded noise levels are rectified or proved to be irrelevant to the construction activities.
Proposed noise
monitoring schedule should be provided to the Contractor, IEC, ER and EPD on or
before the first day of the monitoring month. The Contractor, IEC, ER and EPD
should be notified immediately for any changes in schedule.
4.7
Event and Action Plan for Noise
The Action and
Limit (AL) Levels for construction noise are defined in Table 4-2. Should
non-compliance of the criteria occurs, action in accordance with the Event and
Action Plan in Table 4-3, shall be
carried out.
Table 4‑2 Action and Limit Levels for Construction
Noise
Time Period |
Action |
Limit |
0700-1900
hrs on normal weekdays |
When
one documented complaint is received. |
75*
dB(A) |
1900-2300
hrs on normal weekdays |
When
one documented complaint is received. |
70
dB(A) |
Restricted
hours (2300-0700 hrs) |
When
one documented complaint is received. |
55
dB(A) |
Note:
* 70 dB(A) for schools and 65 dB(A)
during school examination periods.
Table 4‑3 Event and Action Plan for Construction
Noise
Event |
Action |
|||
ET
Leader |
IEC |
ER |
Contractor |
|
Action
Level |
1. Notify
IEC and the Contractor. 2. Carry
out investigation. 3. Report
the results of investigation to IEC and the Contractor. 4. Discuss
with the Contractor and formulate remedial measures. 5. Increase
monitoring frequency to check mitigation measures. |
1. Review
with analysed results submitted by ET. 2. Review
the proposed remedial measures by the Contractor and advise ER accordingly. 3. Supervise
the implement of remedial measures. |
1. Confirm
receipt of notification of exceedance in writing. 2. Notify
the Contractor. 3. Require
the Contractor to propose remedial measures for the analysed noise problem. 4. Ensure
remedial measures are properly implemented. |
1. Submit
noise mitigation proposals to IEC. 2. Implement
noise mitigation proposals. |
Limit
Level |
1. Identify
the source. 2. Notify
IEC, ER, EPD and the Contractor. 3. Repeat
measurement to confirm findings. 4. Increase
monitoring frequency. 5. Carry
out analysis of Contractor’s working procedures to determine possible
mitigation to be implemented. 6. Inform
IEC, ER, and EPD the causes & actions taken for the exceedances. 7. Assess
effectiveness of the Contractor’s remedial actions and keep IEC, EPD and ER
informed of the results. 8. If
exceedance stops, cease additional monitoring. |
1. Discuss
amongst ER, ET Leader and the Contractor on the potential remedial actions. 2. Review
the Contractor’s remedial actions whenever necessary to assure their
effectiveness and advise ER accordingly. 3. Supervise
the implementation of remedial measures. |
1. Confirm
receipt of notification of exceedance in writing. 2. Notify
the Contractor. 3. Require
the Contractor to propose remedial measures for the analysed noise problem. 4. Ensure
remedial measures are properly implemented. 5. If
exceedance continues, consider what activity of the work is responsible and
instruct the Contractor to stop that activity of work until the exceedance is
abated. |
1. Take
immediate action to avoid further exceedance. 2. Submit
proposals for remedial actions to IEC within 3 working days of notification. 3. Implement
the agreed proposals. 4. Resubmit
proposals if problem still not under control. 5. Stop
the relevant activity of works as determined by the ER until the exceedance
is abated. |
The mitigation measures recommended for the construction phase of the submarine watermain are summarised below. The implementation schedule of the recommended noise mitigation measures is presented in Annex A.
Work Schedule Rearrangement
Concurrent works should be such that necessary noisy works should be carried out at different time slots or spread around the construction sites. This will help to reduce the cumulative noise effect produced in the construction process.
If night-time
(2300 to 0700 hours) dredging is required, the work shall be scheduled to carry
out at a distance as far as possible to the NSRs. It is determined that the
dredging work should be carried out at a location 750m away from the Sai Ying
Pun landfall site and 450m from the West Kowloon landfall site along the trench
as shown in Figure 4.3. Under such
condition, the separation distances to the NSRs (e.g.
Using Quality PME
The use of Quality
PME recognized by the Noise Control Authority for the purpose of CNP
application can effectively reduce the noise generated from the construction
plants. Quality PME are construction plants and equipments that are notably
quieter, more environmental friendly and efficiently. The noise level reduction
ranges from 5 – 10 dB(A) depending on the type of equipment used. The
Contractor shall note the required procedures involved in application of the
QPME.
Using Noise Barriers
Mobile or movable
noise barriers to be erected near to the construction plants would reduce the
noise levels for commonly 5 – 10 dB(A) depending on the types of items of PME
and materials of the barriers. It is recommended that the Contractor shall
screen noisy works and noise from stationary items of PME whenever practicable.
Good site practice
and noise management can significantly reduce the impact of construction site
activities on nearby NSRs. The following
package of measures should be followed during construction:
·
only well-maintained plant should be operated
on-site and plant should be serviced regularly during the construction works;
·
machines and plant that may be in intermittent
use should be shut down between work periods or should be throttled down to a
minimum;
·
plant known to emit noise strongly in one
direction, should, where possible, be orientated to direct noise away from the
NSRs;
· mobile plant should be sited as far away from NSRs as possible; and
· material stockpiles and other structures should be effectively utilised, where practicable, to screen noise from on-site construction activities.
The Contractor
shall have a plan in controlling the waste generated from the construction
activities. Besides removal of waste material produced and implementation of
recommended mitigation measures to minimise waste problems arising, a site
waste inventory record should be maintained. The Contractor shall mention good
site practice to ensure that the waste impacts are minimised and shall make
sure that relevant disposal permits are obtained.
For the waste to be disposed appropriately, it is recommended that, if practical, the waste should be separated by category on-site by the Contractor. The following categories shall be adopted:
l
Construction and Demolition (C&D) waste;
l General refuse;
l
Chemical waste; and
l
Marine Dredged Sediment
It is recommended
that auditing of each waste stream should be carried out periodically by the Contractor
to determine if wastes are being managed in accordance with approved procedures
and the site waste management plan. The audits
should look at all aspects of waste management including waste generation,
storage, recycling, treatment, transport and disposal. An appropriate audit programme would be to
undertake the first audit at the commencement of the construction works, and
then to audit weekly thereafter.
Good Site Practices
Adverse impacts
related to waste management are not expected to arise, provided that good site
practices are strictly followed. Recommendations for good site practices during
the construction activities include:
·
Nomination of an approved person, such as a site
manager, to be responsible for good site practices, arrangements for collection
and effective disposal to an appropriate facility, of all wastes generated at
the site
·
Training of site personnel in proper waste
management and chemical handling procedures
·
Provision of sufficient waste disposal points
and regular collection of waste
·
Appropriate measures to minimise windblown
litter and dust during transportation of waste by either covering trucks or by
transporting wastes in enclosed containers
Waste Reduction Measures
Good management
and control can prevent the generation of a significant amount of waste. Waste reduction is best achieved at the
planning and design stage, as well as by ensuring the implementation of good
site practices. Recommendations to
achieve waste reduction include:
·
Sort C&D material from demolition and
decommissioning of the existing facilities to recover recyclable portions such
as metals
·
Segregation and storage of different types of
waste in different containers, skips or stockpiles to enhance reuse or
recycling of materials and their proper disposal
·
Encourage collection of aluminium cans by
providing separate labelled bins to enable this waste to be segregated from
other general refuse generated by the work force
·
Proper storage and site practices to minimise
the potential for damage or contamination of construction materials
·
Plan and stock construction materials carefully
to minimise amount of waste generated and avoid unnecessary generation of
waste.
Construction & Demolition Material
In order to
minimise impacts resulting from collection and transportation of C&D
material for off-site disposal, the excavated materials should be reused on-site
as backfilling material for landscaping works for the associated land mains as
far as practicable. In addition, C&D material generated from the excavation
works should be disposed of at public fill reception facilities for other
beneficial uses. Other mitigation requirements
are listed below:
·
A Waste Management Plan should be prepared.
·
A recording system for the amount of wastes
generated, recycled and disposed (including the disposal sites) should be
proposed.
·
In order to monitor the disposal
of C&D material and solid wastes at public filling facilities and
landfills, and to control fly-tipping, a trip-ticket system (e.g. ETWB TCW No.
31/2004) should be included.
General Refuse
General
refuse should be stored in enclosed bins or compaction units separate from
C&D material. A reputable waste
collector should be employed by the Contractor to remove general refuse from
the site, separately from C&D material.
Preferably an enclosed and covered area should be provided to reduce the
occurrence of 'wind blown' light material.
Chemical Waste
If chemical wastes
are produced at the construction site, the Contractor would be required to
register with the EPD as a chemical waste producer and to follow the guidelines
stated in the Code of Practice on the Packaging, Labelling and Storage of
Chemical Wastes. Good quality containers compatible with the chemical
wastes should be used, and incompatible chemicals should be stored
separately. Appropriate labels should be
securely attached on each chemical waste container indicating the corresponding
chemical characteristics of the chemical waste, such as explosive, flammable,
oxidizing, irritant, toxic, harmful, corrosive, etc. The Contractor shall use a licensed collector
to transport and dispose of the chemical wastes, to either the approved
Chemical Waste Treatment Centre, or another licensed facility, in accordance
with the Waste Disposal (Chemical Waste) (General) Regulation.
Marine Dredged Sediment
The basic
requirements and procedures for dredged mud disposal are specified under the
ETWB TCW No. 34/2002. The management of
the dredging, use and disposal of marine mud is monitored by the MFC, while the
licensing of marine dumping is the responsibility of the Director of
Environmental Protection (DEP).
The dredged marine
sediments would be loaded onto barges and transported to designated disposal
sites depending on their level of contamination. Based on the chemical and
biological screening results and subsequently the corresponding types of
disposal required as evaluated in the EIA report, it was estimated that some 326,000m3
of sediments would be suitable for open sea disposal (Type 1), some 5,000 m3
of sediments would be suitable for open sea disposal (dedicated sites) (Type 1)
and 212,000m3 of sediments would require confined marine disposal
(Type 2). In accordance with the ETWB
TCW No. 34/2002, the contaminated material must be dredged and transported with
great care, and the mitigation measures recommended in Section 3 of the EIA
report should be strictly followed.
Furthermore, the dredged contaminated sediment must be effectively
isolated from the environment upon final disposal and shall be disposed of at
the East Sha Chau Contaminated Mud Pits that is designated for the disposal of
contaminated mud in
During transportation
and disposal of the dredged marine sediments, the following measures should be
taken to minimise potential impacts on water quality:
·
Bottom opening of barges shall be fitted with
tight fitting seals to prevent leakage of material. Excess material shall be
cleaned from the decks and exposed fittings of barges and dredgers before the
vessel is moved.
·
Monitoring of the barge loading shall be
conducted to ensure that loss of material does not take place during
transportation. Transport barges or
vessels shall be equipped with automatic self-monitoring devices as specified
by the EPD.
·
Barges or hopper barges shall not be filled to a
level that would cause the overflow of materials or sediment laden water during
loading or transportation.
Potential air quality impacts arising from the
construction and operation of the Project have been evaluated. As the number of
construction plants involved in the cross harbour main laying activities at
anytime on site would be limited, exceedance of Air Quality Objectives (AQOs)
emissions of gaseous pollutants from these construction plants is not
anticipated. Dust impact and SO2 and NO2 emissions from
plants and site vehicles would be minimal. With the implementation of
appropriate dust suppression measures stipulated in the Air Pollution Control
(Construction Dust) Regulation, adverse air quality impact is not anticipated.
Dust monitoring during the construction of the Project is therefore
considered not necessary but weekly site audits are required to ensure that the
dust control measures are properly implemented. Monitoring during operation
phase is not required.
6.2
Audit Requirement
It is recommended that audits shall be carried out by the
Environmental Team on a weekly basis to ensure that the recommended mitigation
measures are carried out by the Contractor. Special attention shall be paid to
the enforcement of dust control measures during construction process. The ET
should consider the programme and site for construction works in determining the
location to carry out the auditing.
Effective control measures and good site practices should
be implemented to meet the requirements of the Air Pollution Control (Construction Dust) Regulation and minimize
construction dust impact.
During construction phase, the Contractor shall make
reference, but not limit himself, to the following measures:
· any excavated dusty materials or stockpile of dusty materials should be covered entirely by impervious sheeting or sprayed with water so as to maintain the entire surface wet, and recovered or backfilled or reinstated within 24 hours of the excavation or unloading;
· the working area of excavation should be sprayed with water immediately before, during and immediately after the operations so as to maintain the entire surface wet;
· the load of dusty materials carried by vehicle leaving a construction site should be covered entirely by clean impervious sheeting to ensure that the dusty materials do not leak from the vehicle;
· where a site boundary adjoins a road, streets or other area accessible to the public, hoarding of not less than 2.4m high from ground level should be provided along the entire length except for a site entrance or exit;
· the area where vehicle washing takes place and the section of the road between the washing facilities and the exit point should be paved with concrete, bituminous materials or hardcores;
· every main haul road should be scaled with concrete and kept clear of dusty materials or sprayed with water so as to maintain the entire road surface wet;
· the portion of road leading only to a construction site that is within 30m of a designated vehicle entrance or exit should be kept clear of dusty materials;
· all dusty materials should be sprayed with water prior to any loading, unloading or transfer operation so as to maintain the dusty material wet;
· vehicle speed should be limited to 10 kph except on completed access roads; and
· every vehicle should be washed to remove any dusty materials from its body and wheels before leaving the construction sites.
A comprehensive baseline review identified no land based or submerged cultural heritage resources within the Study Area. A Geophysical Survey which covered a 200m submarine watermain corridor was conducted and no indication of marine archaeological material was identified.
No cultural heritage resources are identified within the Study Area and therefore, no environmental monitoring and audit programme and mitigation measures are required.
Impacts to fisheries resources and fishing operations have largely been avoided during construction through constraints on the works operations for installation of the cross harbour main. Good construction practice and associated measures recommended in Section 2 to control water quality impacts to within acceptable levels are also expected to control impacts to fisheries resources.
The implementation of the water quality mitigation measures stated in the Section 2 (Water Quality) should be checked as part of the environmental monitoring and audit procedures during the construction phase. No fisheries-specific mitigation measures during construction of the proposed submarine watermain are considered necessary.
Site Inspections provide a direct means to trigger and
enforce the specified environmental protection and pollution control
measures. They shall be undertaken
routinely by the ET Leader to inspect the construction activities in order to
ensure that appropriate environmental protection and pollution control
mitigation measures are properly implemented.
With well defined pollution control and mitigation specifications and a
well established site inspection, deficiency and action reporting system, the
site inspection is one of the most effective tools to enforce the environmental
protection requirements on the construction site.
The ET Leader is responsible for formulation of the
environmental site inspection, deficiency and action reporting system, and for
carrying out the site inspection works.
He shall submit a proposal on the site inspection, deficiency and action
reporting procedures within 21 days of the construction contract commencement
to the Contractor for agreement and to the ER for approval.
Regular site inspections shall be carried out at least
once per week. The areas of inspection
shall not be limited to the pollution control and mitigation measures within
the site; the environmental situation outside the site area which is likely to
be affected, directly or indirectly, by the site activities shall be reviewed. The ET Leader shall make reference to the
following information when conducting the inspection:
a)
the
EIA recommendations on environmental protection and pollution control
mitigation measures;
b)
works
progress and programme;
c)
individual
works methodology proposals (which shall include proposal on associated
pollution control measures);
d)
the
contract specifications on environmental protection;
e)
the
relevant environmental protection and pollution control laws; and
f)
previous
site inspection results.
The Contractor shall update the ET Leader with all
relevant information of the construction contract for him to carry out the site
inspections. The inspection results and
its associated recommendations on improvements to the environmental protection
and pollution control works shall be submitted to the IEC and the Contractor
within 24 hours, for reference and for taking immediate action. The Contractor shall follow the procedures
and time-frame as stipulated in the environmental site inspection, deficiency
and action reporting system formulated by the ET Leader to report on any
remedial measures subsequent to the site inspections.
Ad hoc site inspections shall also be
carried out if significant environmental problems are identified. Inspections may also be required subsequent
to receipt of an environmental complaint, or as part of the investigation work,
as specified in the Action Plan for environmental monitoring and audit.
9.2
Compliance with Legal and Contractual Requirements
There are contractual environmental protection and
pollution control requirements as well as environmental protection and
pollution control laws in
In order that the works are in compliance with the
contractual requirements, all the works method statements submitted by the
Contractor to the ER for approval shall also be sent to the ET Leader for
vetting to see whether sufficient environmental protection and pollution
control measures have been included. The
implementation schedule of mitigation measures is summarised in Annex A.
The ET Leader shall also review the progress and programme
of the works to check that relevant environmental laws have not been violated,
and that any foreseeable potential for violating the laws can be
prevented.
The Contractor shall regularly copy relevant documents to
the ET Leader so that the checking work can be carried out. The document shall at least include the
updated Work Progress Reports, the updated Works Programme, application letters
for different license/permits under the environmental protection laws, and all
the valid license/permit. The site diary
shall also be available for the ET Leader's inspection upon his request.
After reviewing the document, the ET Leader shall advise
the ER and the Contractor of any non-compliance with the contractual and
legislative requirements on environmental protection and pollution control for
them to take follow-up actions. If the
ET Leader's review concludes that the current status on license/permit
application and any environmental protection and pollution control preparation
works may not cope with the works programme or may result in potential
violation of environmental protection and pollution control requirements by the
works in due course, he shall advise the Contractor and the ER accordingly.
Upon receipt of the advice, the Contractor shall undertake
immediate action to remedy the situation.
The ER shall follow up to ensure that appropriate action has been taken
by the Contractor in order that the environmental protection and pollution
control requirements are fulfilled.
Handling of environmental complaints should
follow the environmental complaint flow diagram and reporting channel as
presented in Figure 9.1.
During the complaint investigation work, the
Contractor and ER shall cooperate with the IEC and ET Leader in providing all
necessary information and assistance for completion of the investigation. If
mitigation measures are identified in the investigation, the Contractor shall
promptly carry out the mitigation works. The ER shall ensure that the measures
have been carried out by the Contractor. Sample of the complaint log is shown
in Annex C.
The reporting requirements of EM&A
information are based upon a paper-documented approach. However, the same information can be provided
in an electronic medium upon agreeing the format with the ER and EPD. This will enable a transition from a paper /
historic and reactive approach to an electronic / real time proactive approach.
Types of reports that the ET Leader shall
prepare and submit include baseline monitoring report, monthly EM&A report,
quarterly EM&A summary report and final EM&A review report. In accordance with Annex 21 of the EIAO-TM, a
copy of the monthly, quarterly summary and final review EM&A reports shall
be made available to the Director of Environmental Protection. The exact
details of the frequency, distribution and time frame for submission shall be
agreed with EPD prior to commencement of works.
To facilitate the public inspection of the
Baseline Monitoring Report and monthly EM&A Reports, via the EIAO Internet
Website and at the EIAO Register Office, electronic copies of these Reports
shall be prepared in Hyper Text Markup Language (HTML) (version 4.0 or later)
and in Portable Document Format (PDF version 4.0 or later), unless otherwise
agreed by EPD and shall be submitted at the same time as the hard copies. For
the HTML version, a content page capable of providing hyperlink to each section
and sub-section of the EM&A Reports shall be included in the beginning of
the document. Hyperlinks to all figures, drawings and tables in the EM&A
Reports shall be provided in the main text from where the respective references
are made. All graphics in the report shall be in interlaced GIF format unless
otherwise agreed by the EPD. The content of the electronic copies of the
EM&A Reports must be the same as the hard copies.
10.3
Baseline Monitoring Report
The ET Leader shall prepare and submit a Baseline
Environmental Monitoring Report within 10 working days of completion of the
baseline monitoring. Copies of the
Baseline Environmental Monitoring Report shall be submitted to all parties: the
Contractor, the IEC, the ER and the EPD.
The ET Leader shall liaise with the relevant parties on the exact number
of copies they want. The format and content of the report, and the
representation of the baseline monitoring data shall be in a format to the
satisfaction of EPD and include, but not be limited to the following:
a)
up
to half a page executive summary;
b)
brief
project background information;
c)
drawings
showing locations of the baseline monitoring stations;
d)
monitoring
results (in both hard and diskette copies) together with the following
information:
·
monitoring
methodology;
·
name
of laboratory and types of equipment used and calibration details;
·
parameters
monitored;
·
monitoring
locations;
·
monitoring
date, time, frequency and duration;
·
QA/QC
results and detection limits;
e)
details
on influencing factors, including
·
major
activities, if any, being carried out on the Site during the period;
·
weather
conditions during the period;
·
other
factors which might affect the results.
f)
determination
of the Action and Limit Levels (AL Levels) for each monitoring parameter and
statistical analysis of the baseline data; the analysis shall conclude if there
is any significant difference between control and impact stations for the
parameters monitored, and the following information shall be recorded:
·
graphical
plots of monitored parameters in the month annotated against;
·
the
major activities being carried out on site during the period;
g)
revisions
for inclusion in the EM&A Manual; and
h)
comments
and conclusions.
The results and findings of all EM&A work required in
the Manual shall be recorded in the monthly EM&A reports prepared by the ET
Leader. The EM&A report shall be
prepared by the ER, endorsed by IEC and submitted within 10 working days of the
end of each reporting month, with the first report due in the month after
construction commences. Before
submission of the first EM&A report, the ET Leader shall liaise with the
parties on the exact number of copies and format of the monthly reports in both
hard copy and electronic medium requirement.
The ET Leader shall review the number and location of monitoring
stations and parameters to monitor every 6 months or on as needed basis in
order to cater for the changes in surrounding environment and nature of works in
progress.
i. First Monthly EM&A Report
The First Monthly EM&A Report shall include at least
the following:
a)
1-2
pages executive summary;
·
Breaches
of
·
Complaints
Log;
·
Notifications
of any summons and successful prosecutions;
·
Reporting
Changes; and
·
Future
key issues.
b)
Basic
Project Information
·
Project
organisations including key personnel contact names and telephone numbers;
·
Programme;
·
Management
structure; and
·
Works
undertaken during the month.
c)
Environmental
Status
·
Work
undertaken during the month with illustrations (such as location of works daily
dredging/filling rates percentage fines in the fill material used); and
·
Drawing
showing the project area, any environmental sensitive receivers and the
locations of the monitoring and control stations.
d)
Summary
of EM&A requirements
·
All
monitoring parameters;
·
·
Event-Action
Plans;
·
Environmental
mitigation measures, as recommended in the project EIA Report; and
·
Environmental
requirements in contract documents.
e)
Implementation
Status
Advice on the implementation status of environmental
protection and pollution control/mitigation measures, as recommended in the
project EIA Report, summarised in the updated implementation schedule (in Annex A).
f)
Monitoring
Results
To provide monitoring results (in both hard and diskette
copies) together with the following information:
·
Monitoring
methodology;
·
Name
of laboratory and types of equipment used and calibration details;
·
Parameters
monitored;
·
Monitoring
locations;
·
Monitoring
date, time, frequency, and duration;
·
Weather
conditions during the period;
·
Any
other factors which might affect the monitoring results; and
·
QA/QC
results and detection limits.
g)
Report
on Non-compliance, Complaints, Notifications of Summons and Successful
Prosecutions
·
Record
of all non-compliance (exceedances) of the environmental quality performance
limits (AL Levels);
·
Record
of all complaints received (written or verbal) for each media, including
locations and nature of complaints investigation, liaison and consultation undertaken,
actions and follow-up procedures taken, results and summary;
·
Record
of all notifications of summons and successful prosecutions for breaches of the
current environmental protection/pollution control legislations, including
locations and nature of the breaches, investigation, follow-up actions taken,
results and summary;
·
Review
of the reasons for and the implications of non-compliance, complaints, summons
and prosecutions including review of pollution sources and working procedures;
and
·
Description
of the actions taken in the event of non-compliance and deficiency reporting
and any follow-up procedures related to earlier non-compliance.
h)
Others
·
An
account of the future key issues as reviewed from the works programme and work
method statements; and
·
Advice
on the solid and liquid waste management status.
ii. Subsequent Monthly EM&A Reports
The subsequent Monthly EM&A Reports shall include the following:
a)
Executive
Summary (1-2 pages)
·
Breaches
of
·
Complaint
Log;
·
Notifications
of any summons and successful prosecutions;
·
Future
key issues.
b)
Environmental
Status
·
Works
undertaken during the month with illustrations including key personnel contact
names and telephone number; and
·
Drawing
showing the project area, any environmental sensitive receivers and the
locations of the monitoring and control stations.
c)
Implementation
Status
Advice on the implementation status of environmental
protection and pollution control/mitigation measures including measures for air,
noise, water quality and ecological impacts etc, as recommended in the EIA
Report, summarised in the updated implementation schedule (see Annex A).
d)
Monitoring
Results
To provide monitoring results (in both hard and diskette
copies) together with the following information:
·
Monitoring
methodology;
·
Name
of laboratory and types of equipment used and calibration details;
·
Parameters
monitored;
·
Monitoring
locations;
·
Monitoring
date, time, frequency, and duration;
·
Weather
conditions during the period;
·
Any
other factors which might affect the monitoring results; and
·
QA/QC
results and detection limits.
e)
Report
on Non-compliance, Complaints, Notifications of Summons and Successful
Prosecutions
·
Record
of all non-compliance (exceedances) of the environmental quality performance
limits (AL Levels);
·
Record
of all complaints received (written or verbal) for each media, including
locations and nature of complaints investigation, liaison and consultation
undertaken, actions and follow-up procedures taken, results and summary;
·
Record
of all notifications of summons and successful prosecutions for breaches of the
current environmental protection/pollution control legislations, including
locations and nature of the breaches, investigation, follow-up actions taken,
results and summary;
·
Review
of the reasons for and the implications of non-compliance, complaints, summons
and prosecutions including review of pollution sources and working procedures;
and
·
A
description of the actions taken in the event of non-compliance and deficiency
reporting and any follow-up procedures related to earlier non-compliance.
f)
Others
·
An
account of the future key issues as reviewed from the works programme and work
method statements; and
·
Advice
on the solid and liquid waste management status.
g)
Appendix
·
·
Graphical
plots of trends of monitored parameters at key stations over the past four
reporting periods for representative monitoring stations annotated against the
following:
i) major activities being carried out on site
during the period;
ii) weather conditions during the period; and
iii) any other factors which might affect the
monitoring results
·
Monitoring
schedule for the present and next reporting period
·
Cumulative
statistics
·
On
complaints, notifications of summons and successful prosecutions
·
Outstanding
issues and deficiencies
iii. Quarterly EM&A Summary Reports
The Quarterly EM&A Summary Report which shall
generally be around 5 pages (including about 3 of text and tables and 2 of
figures) shall contain at least the following information:
a)
up to half a page executive
summary;
b)
basic
project information including a synopsis of the project organisation,
programme, contacts of key management, and a synopsis of work undertaken during
the quarter;
c)
a
brief summary of EM&A requirements including:
·
monitoring
parameters;
·
environmental
quality performance limits (AL Levels); and
·
environmental
mitigation measures, as recommended in the EIA Report;
d)
advice
on the implementation status of environmental protection and pollution
control/mitigation measures, as recommended in the project EIA study report,
summarised in the updated implementation schedule;
e)
drawings
showing the project area, any environmental sensitive receivers and the
locations of the monitoring and control stations;
f)
graphical
plots of the trends of monitored parameters over the past 4 months (the last
month of the previous quarter and the present quarter) for representative
monitoring stations annotated against;
·
the
major activities being carried out on site during the period;
·
weather
conditions during the period; and
·
any
other factors which might affect the monitoring results;
g)
advice
on the solid and liquid waste management status;
h)
a
summary of non-compliance (exceedances) of the environmental quality
performance limits (AL Levels);
i)
an
quarterly assessment of constructional impacts on water quality at the project
site including but not limited to comparison of the difference between the
quarterly mean and 1.3 times of the ambient which is defined as 30% increase of
the baseline data or EPD data of the related parameters by using appropriate
statistical procedures. Suggestion of
appropriate mitigation measures if the quarterly assessment analytical results
demonstrate that the quarterly mean is significantly higher than the liaison
water quality times of the ambient mean (p < 0.05);
j)
a
brief review of the reasons for and the implications of non-compliance
including review of pollution sources and working procedures;
k)
a
summary description of the actions taken in the event of non-compliance and any
follow-up procedures related to earlier non-compliance;
l)
a
summary record of all complaints received (written or verbal) for each media,
liaison and consultation undertaken, actions and follow-up procedures taken;
m) comments (e.g. effectiveness
and efficiency of the mitigation measures), recommendations (e.g. any
improvement in the EM&A programme) and conclusions for the quarter; and
n)
proponents'
contacts and any hotline telephone number for the public to make enquiries.
iv. Final EM&A Review Reports
The Final EM&A Report shall contain at least the
following information:
a)
Executive
Summary (1-2 pages);
b)
drawings
showing the project area, any environmental sensitive receivers and the
locations of the monitoring and control stations;
c)
basic
project information including a synopsis of the project organisation contacts
of key management, and a synopsis of work undertaken during the course of the
project or past twelve months;
d)
a
brief summary of EM&A requirements including:
(i) environmental mitigation measures, as recommended in the
project EIA Report;
(ii) environmental impact hypotheses tested;
(iii) AL Levels;
(iv) all monitoring parameters; and
(v) Event-Action Plans;
e)
a
summary of the implementation status of environmental protection and pollution
control/mitigation measures as recommended in the project EIA study report
summarized in the updated implementation schedule;
f)
graphical
plots and the statistical analysis of the trends of monitored parameters over
the course of the project, including the post project monitoring (for the past
twelve months for annual report) for all monitoring stations against:
·
the
major activities being carried out on site during the period;
·
weather
conditions during the period; and
·
any
other factors which might affect the monitoring results;
g)
a
summary of non-compliance (exceedances) of the environmental quality
performance limits (AL Levels);
h)
a
review of the reasons for and the implications of non-compliance including
review of pollution sources and working procedures as appropriate;
i)
a
description of the actions taken in the event of non-compliance;
j)
a
summary record of all complaints received (written or verbal) for each media
liaison and consultation undertaken, action and follow-up procedures
taken;
k)
a
summary record of notifications of summons and successful prosecutions for
breaches of the current environmental protection pollution control legislations
locations and nature of the breaches, investigation, follow-up actions taken
and results;
l)
a
review of the validity of EIA Report predictions and identification of
shortcomings in EIA Report recommendations;
m) a review of the effectiveness
and efficiency of the mitigation measures; and
n)
a
review of success of the EM&A programme to cost effectively identify
deterioration and to initiate prompt effective mitigatory action when
necessary.
The site document such as the monitoring field records,
laboratory analysis records, site inspection forms, etc. are not required to be
included in the monthly EM&A reports for submission. However, the document shall be well kept by
the ET Leader and be ready for inspection upon request. All relevant information shall be clearly and
systematically recorded in the document.
The monitoring data shall also be recorded in magnetic media form, and
the software copy can be available upon request. The water quality data software format shall
be agreed with EPD. All the documents and data shall be kept for at least one year after completion
of the construction contract.
10.6
Interim Notifications of Environmental Quality
Limit Exceedances
With reference to Event/Action Plans in Tables 2-3 and 4-3, when the environmental quality limits are exceeded, the ET Leader shall immediately notify the ER and EPD, as appropriate. The notification shall be followed up with advice to EPD on the results of the investigation, proposed action and success of the action taken, with any necessary follow-up proposals. A sample template for the interim notifications is shown in Annex D.
(1) Maunsell Consultants Asia Ltd
(2001), Agreement No. CE 74/98, Wan Chai Development Phase II Comprehensive
Feasibility Study, Final Environmental Impact Assessment Report, for Territory
Development Department.