Laying of
– Investigation
合約編號:CE 42/2005(WS)
敷設由西九龍至西營盤之西區過海海底水管
及與其相關的地下喉管
–勘測
Executive
Summary
Document No. 226133/11/C
文件編號:226133/11/C
April 2007
2007年4月
Mott
Connell Ltd
40th
floor, Hopewell Centre
183
Queen’s Road East
Wanchai
Tel:
2828 5757
Fax:
2827
1823
List of Contents
Chapters
1.2 Consideration
of Alternatives
4. ENVIRONMENTAL MONITORING AND AUDIT
List of Figures
Figure 1.1 Indicative Route of the Proposed
Watermains
Figure 1.2 Plan View, Profile and Cross Section
of Proposed Submarine Watermain
Figure 1.3 Location of Night-time Dredging Zone
The need for a new cross-harbour pipeline on the western
part of the harbour has evolved from the requirement to provide security of
water supply between
The Project involves construction and operation of a new
western cross harbour main and associated land mains. The route of the proposed
Project is shown in Figure 1.1. The
scope of the proposed Project comprises the following:
(i)
approximately 2100-metre section of 1200mm
nominal diameter of submarine watermain across Victoria Harbour from its
connection at Lin Cheung Road in West Kowloon to the existing Sai Ying Pun
Fresh Water Pumping Station in Sheung Wan (a designated project under EIA
Ordinance);
(ii)
approximately 2200-metre section of 1200mm
nominal diameter of associated land mains (Not a designated project under EIA
Ordinance).
The submarine watermain component (referred in Section 1.1(i) above) of the Project is a Designated
Project under Schedule 2, Part I(E3) of the Environmental Impact Assessment
Ordinance (EIAO) (Cap. 499) and an Environmental Permit (EP) issued under the
EIAO is required for the construction and operation of the designated project.
An Environmental Impact Assessment (EIA) Study has been
undertaken to provide information on the nature and extent of environmental
impacts arising from the construction of
the proposed designated project and related activities taking place concurrently
and to contribute to decisions on the overall environmental acceptability of
the Project.
This Exercutive Summary provides the key findings of the
EIA Report, including an assessment of potential water quality, marine ecology,
noise, waste, air quality, cutltural heritage and fisheries impacts from the
construction and operation of the Project, and recommendations for mitigation
measures to comply with environmental legislations and guidelines.
1.2 Consideration
of Alternatives
1.2.1
Physical and Routing Constraints to the
Alignment
Major installations and
underground structures within the study area which are considered to be the physical
constraints to the alignment of the proposed submarine watermain include the Kowloon
South Salt Water Pumping Station and associated existing seawater intake
culvert; tunnel structure and toll plaza of the Western Harbour Crossing; DSD’s
drainage culvert next to Sai Ying Pun Fresh Water Pumping Station; and proposed
submarine gas main between West Kowloon and Sai Ying Pun. The choice of landing
points of the submarine watermain is limited by the locations of connection
point to the existing water supply network in
As shown in Figure 1.1, the proposed submarine watermain is bounded by the
Western Cross Harbour Tunnel and the proposed submarine gas main to the east.
The existing seawater intake culvert for Kowloon South Salt Water Pumping
Station, Yau Ma Tei Typhoon Shelter and proposed West Kowloon Cultural District
development at
The submarine watermain is
proposed to be laid across the
1.2.2
Construction Methods
The methods commonly used to
install submarine watermains include dredging to form the trench followed by
“bottom pull”, “lay barge”or “float and sink” followed by backfilling to
protect the pipeline or “horizontal directional drilling”.
For submarine watermain
installations, dredging involves the removal of marine sediments from the
seabed to form the trench, into which the submarine watermain are laid by
possible methods including Bottom Pull, Lay Barge or the Float and Sink Method.
Backfill material will be placed on top to protect the pipeline and minimize
the cross section of dredging and backfilling works. The longitudinal profile
and a typical cross section of the submarine watermain are provided in Figure 1.2. Design of the cross section
and the resulting amount of marine sediments to be dredged from the seabed to
form the trench will be the same no matter the Bottom Pull, Lay Barge or the
Float and Sink Method is adopted for submarine watermain laying. Horizontal
directional drilling involves taking the pipeline directly from the start to
end point by underground drilling with no surface disturbance being necessary.
An analysis of different
construction methods and techniques to minimise impacts on water quality,
marine ecology, fisheries and waste was carried out.
Trench Excavation
Dredging techniques including
grab dredging, cutter suction and trailer suction dredging are considered and
chosen depending on the engineering, environmental and risks conditions. As the
submarine watermain will be located across the Yau Ma Tei, Central and Southern
Fairway, grab dredging is selected, as cutter suction and trailer suction
dredging which requires a working area of over 150m in width, will result in an
unacceptable impact on marine traffic and thus are not feasible. Suction
dredging will also produce more marine sediment by volume when compared with
grab dredging. Grab dredging is therefore the best practicable and feasible
method to minimize dredging and dumping requirements and demand for fill
sources.
Submarine Pipeline Installation
In the bottom pull method, pipes
are joined to form pipe strings which are progressively pulled from a landfall
site into a pre-dredged trench underwater by a winch set up at the landfall
site at the other side of the waters until the crossing is complete. This
method is one of the most common method for installation of medium to large
diameter pipelines.
In the lay barge method, while
the work barge moves along the pipeline, the pipes are progressively added to
form a string, which are hung in a catenary from at the back of the barge, and
are gradually lowered into the pre-dredged trench. As the lay barge method will
introduce intolerable marine traffic impact due to its long suspended pipeline
at sea during the installation, this method is considered not a feasible
option.
In the float and sink method,
lengths of pipe are made up into strings at a fabrication yard and these
strings are launched to seabed from one of the landfall sites. These
prefabricated pipe strings are temporarily stored on the seabed before towed by
work barge at or below the water surface to the pre-dredged trench. By removing
or filling water to the supporting buoyancy tanks, the pipe strings are sunk to
its final position. This method is also one of the most common method for
installation of medium to large diameter pipelines.
Backfilling
Cover of pipeline is required to provide
adequate anchor protection. Backfilling material considered for the submarine
pipeline trench include marine deposit 8 m or deeper or sand filling 5 m or
deeper or armour rock layer 4.5 m thick with a 0.3 m thick grade 75
bedding. Pre-dredged trench is required
for the pipe laying works, storage of dredged marine deposit for trench
backfilling is considered not practicable. Moreover, the overall trench depth
for marine deposit backfilling will be up to 9.5 m, this will also
significantly increase the quantity of contaminated mud when compared with the
armour rock option. Backfilling the trench with sand will induce significant
disturbance on the existing marine environment and is considered
environmentally unacceptable. Armour rock option is recommended as it can
provide a strong protection to the pipeline away from the anchoring damage and requires
the smallest pre-dredged trench which can minimize the disposal of both
contaminated and uncontaminated dredged marine mud.
1.2.3
The Preferred Option
By comparing the pros and cons of
the various construction methods, the preferred option is trench excavation by grab
dredging by one grab dredger and install the submarine watermain by the
“bottom-pull method” followed by protection of the submarine piepeline by backfilling
with 4.5m thick armour rock layer with a 0.3m thick grade 75 bedding layer.
The Project comprises
the following:
(i) approximately
2100-metre section of 1200mm nominal diameter of submarine watermain across
Victoria Harbour from its connection at Lin Cheung Road in West Kowloon to the
existing Sai Ying Pun Fresh Water Pumping Station in Sheung Wan (a designated
project under EIA Ordinance);
(ii) approximately
2200-metre section of 1200mm nominal diameter of associated land watermains
(Not a designated project under EIA Ordinance).
The site boundary of the proposed Project covers three
main areas, namely:
The works for
The works in
In Sai Ying Pun (Not a designated project under EIA
Ordinance), the works comprise Sai Ying Pun area adjacent to Western Wholesale
Food Market and is bounded by the approaches of Western Harbour Crossing Interchange. The proposed 1200mm diameter fresh watermain
will be laid in this portion for connection to the existing Sai Ying Pun Fresh
Water Pumping Station situated at the junction of
This EIA report covers the designated project component of
the Project.
The construction of the proposed Project
is scheduled to commence in September 2008 for completion by May 2012.
The environmental impacts associated with
the construction and operation of the submarine watermain are summarised in the
following sections.
Key water sensitive receivers identified for
construction phase of the submarine watermain include the New Yau Ma Tei Typhoon
Shelter, coral communities at Green Island and Water Supplies Department’s
seawater intakes at the waterfront of Victoria Harbour. Water quality impact
during dredging works for the installation of the submarine watermain was
quantitatively assessed by water quality modelling. Suspended sediment was
identified as the key water quality parameter during dredging. Water quality impact on the sensitive
receivers during the entire duration of the dredging works and along the entire
alignment with the maximum possible instantaneous working rate of 0.0463m3s-1
(i.e. one grab dredger with a maximum production rate of 4,000m3 per
day, 7 days per week, 24 hours per day for the complete simulation period of 90
days) for the dry and wet seasons was assessed and it was predicted that
potential water quality impact would occur at the WSD Sea Water Intake at
Kowloon South Salt Water Pumping Station.
With the implementation of the proposed
mitigation measures in particular, the use of one grab dredger only with a
maximum production rate of 4,000m3 per day for dredging, deployment
of frame type silt curtain to fully enclose the grab while dredging works are
in progress and deployment of silt screen at the sea water intake at Kowloon
South Salt Water Pumping Station while dredging works are in progress and
various good site practices associated with dredging, the potential water
quality impact upon the sea water intake would be effectively minimised and
there would be no unacceptable residual cumulative water quality impact due to
the dredging works of the submarine watermain as well as the other concurrent
marine works. The assessment predicted that the dredging works would have
negligible impact upon the coral communities near
High level of contamination in terms of arsenic
(As), copper (Cu), lead (Pb), mercury (Hg), silver (Ag), polyaromatic
hydrocarbons (PAHs) and polychlorinated biphenols (PCBs) were found at a couple
of vibrocores along the alignment of the proposed submarine watermain. These
contaminants pose a higher risk of water quality impact as they would be
released into the marine water when the sediment was disturbed during dredging.
Elutriate tests were carried out for these parameters and the results indicated
their content fall within the relevant water quality standard except for As for
2 samples and Ag for one sample. As water quality sensitive receivers were not
identified within the mixing zones, adverse water quality impacts are therefore
not anticipated. Moreover, it is expected that any release of heavy metals
during dredging will be quickly diluted by the large volume of marine water
within the construction site. The release of pollutants will also be minimised
by the use of closed grab dredger and the dispersion of pollutants will be
confined within the construction site by the silt curtains. Thus, it is
considered that long-term off-site water quality impact is unlikely and any
local water quality impact will be transient and localised.
Minor potential water quality impacts from
hydrostatic tests of the water mains systems and construction activities
associated with the construction of the proposed submarine watermain were
associated with effluent, sewage, wastewater and surface runoff. Impacts could
be controlled to comply with the WPCO standards by implementing the recommended
mitigation measures. No unacceptable residual impact on water quality was
expected.
No maintenance dredging is required for the
future operation of the proposed submarine watermain. There would be no
hydrodynamic impact as the operation of the submarine watermain would not
involve reclamation or filling that affect the flow volume within the
A desktop literature review was conducted to
establish the baseline conditions and the general ecological profile.
Information from the water quality assessment was also used to identify the
effects of change in water quality on the marine ecology. Habitats including
those in the intertidal zone (artificial seawalls and rocky shores), sub-tidal
zone (soft-bottom and hard-bottom habitats), and the open sea (
The marine
ecological resources within the dredging area consist of pollution tolerant
soft benthos in low diversity and typical to benthos recorded in poor quality
sediments. Inter-tidal species along
Direct
impacts of permanent habitat loss and temporary disturbances to marine
ecological resources from dredging and backfilling activities at the seabed and
installation of pipeline by “bottom pull” method during construction phase will
be of low to negligible significance, due to no rare species recorded within
the affected area and in vicinity and the low ecological value of the marine
benthos and the re-creatable artificial structures along the Victoria Harbour.
Indirect
impacts through the changes to water flow regime, and perturbations of the
surrounding water quality on the medium ecological value habitats at Green
Island are anticipated to be negligible as the results
of water quality modelling showed that the elevation of SS concentration and
sedimentation rate around the Green Island waters is predicted to be less than
0.1mgL-1 and 0.001kgm-2 per day respectively, which are
much lower than the tolerant levels for coral communities. In
addition, due to the remoteness from the works area, the impacts to the marine
environment in vicinity to
The
proposed dredging works will be confined in the works area within 25m at either
side of the proposed alignment and the use of closed type grab dredger will
reduce sediment and contaminants runoff to the water column. The trench will be
backfilled with armour rock or decomposed granite and allow natural
sedimentation on the substrates to provide protection of the pipeline from
damage by ship anchors. Benthic fauna is expected to be recolonized to the
seabed after construction. Other mitigation measures suggested in the water
quality impact assessment such as the use of one grab dredger only with a
maximum production rate of 4,000m3
per day for dredging, deployment of frame type silt curtain to fully enclose
the grab while dredging works are in progress, deployment of silt screen at the
sea water intake at Kowloon South Salt Water Pumping Station while dredging
works are in progress and good site practices to avoid silt runoff from
construction works associated with the construction of the submarine watermain
could also further reduce the impact on the marine ecology. No other specific
mitigation measures for marine ecology are considered necessary, as no adverse
impact was identified.
The
Study Area is not the distribution range of marine mammals and as low
ecological value species are encountered in the region, the implementation of
good site practices and mitigation measures for water quality impact are
considered to be sufficient to minimize the impacts on the marine ecology.
Thus, no specific mitigation measures are necessary for ecological sensitive
receivers.
An
assessment was undertaken to define the nature and scale of the potential noise
impact to sensitive receivers at Sai Ying Pun and
The
assessment predicted that the major construction activities associated with
dredging, laying of watermains and backfilling may cause temporary noise
impacts to the residential buidilngs in the Study Area. During normal daytime
working hours, noise generated from the construction works fully comply with the
noise criteria stipulated in the EIAO-TM and NCO. Without mitigation measures,
it can be concluded that there will not be any adverse noise impact from the
marine construction activities during daytime and evening (1900 to 2300 hours).
No mitigation measure is therefore required but it is recommended that the
Contrtactor shall take initiatives to further reduce the noise generated from
the construction activities, including better management of work schedule, use
of movable noise barriers, quality powered mechanical equipment (PMEs) and good
site practices.
However,
the predicted noise level at noise sensitive receivers including the
An assessment of the dredged marine sediment
was carried out. A review of the sediment quality data from the marine site
investigation indicated that the majority of the marine sediments to be dredged
along the proposed submarine watermain were classified as Category L. The total dredged volume for the Project was
estimated as 543,000m3, of which 212,000m3 of sediment
was classified as requiring confined marine disposal. With the implementation
of the recommended mitigation measures and procedures for management of dredged
or excavated sediment are strictly followed, no residual waste impact was
predicted.
Waste types generated by the construction
activities are likely to include C&D material (from minor excavation
works), general refuse from the workforce, and chemical waste from the
maintenance of construction plant and equipment. Provided that these wastes are handled,
transported and disposed of using approved methods and that the recommended
good site practices are strictly followed, adverse environmental impacts is not
expected.
Potential air quality impacts arising from
the construction and operation of the submarine watermain have been evaluated.
As the number of construction plants involved in the submarine watermain laying
activities at anytime on site would be limited, exceedance of Air Quality
Objectives (AQOs) emissions of gaseous pollutants from these construction
plants is not anticipated. The number of plants required on site for the
construction of the landing points would also be limited. Dust impact and SO2
and NO2 emissions from plants and site vehicles would be minimal.
With the implementation of appropriate dust suppression measures stipulated in
the Air Pollution Control (Construction Dust) Regulation, together with proper
maintenance of equipment and good site practices, adverse air quality impact is
not anticipated.
No air quality impact is anticipated at the
operational phase since there will not have any operational phase emissions.
A comprehensive baseline review was
undertaken to compile a comprehensive inventory of cultural heritage resources
of the Study Area. No land based or a submerged cultural heritage resource was
identified within the Study Area.
A Geophysical Survey which covered a 200m submarine watermain corridor was conducted to define the areas of greatest archaeological potential, assess the depth and nature of the seabed sediments to define which areas consist of suitable material to bury and preserve archaeological material and to map anomalies on the seabed which may be of archaeological potential. No indication of marine archaeological material was identified. Therefore, no impacts are expected from the installation of the cross harbour main and no mitigation measures are considered necessary.
Review of existing information on fisheries
resources and fishing operations located within the Study Area have been
undertaken. For capture fisheries, the results of Port Survey 2001/2002 shows
that the waters within the Study Area are having low to medium adult fish
production (>0 to 200kg/ha). The catches were at medium price in
Although the submarine pipeline trench to be
formed at the seabed is relatively long (approximately 2,100 metres in length),
the affected area of fisheries resources is predicted to be temporary, small
scale and localised to the works associated with formation of submarine
pipeline trench at the seabed as a result of the “bottom-pull” and dredging
operations. Although the submarine pipeline passes through areas with low to
medium fisheries production and activities, impact to fishing activities in the
area are not expected to be of concern due to the small area physically
disrupted during the installation of the submarine pipeline and the short time
frame of disturbance. Impact on future fishing operation is not anticipated as
the armour rock will not protrude above the original seabed level. Ma Wan Fish
Culture Zone which is the closest AFCD gazetted Fish Culture Zone to the Study
Area is not predicted to be impacted by either suspended solids elevation,
dissolved oxygen depletion or nutrient elevation as a result of the Project.
As potential impacts to fisheries resources
and fishing operations arising from formation of the submarine pipeline trench
at the seabed are predicted to be temporary, small scale and localised, they
are not expected to cause adverse impacts to any fishing grounds or species of
importance to the fishery. Impacts to fisheries resources and fishing
operations have largely been avoided during construction through constraints on
the works operations for installation of the submarine watermain. While no
special mitigation measures are required for fisheries resources and fishing
activities, good construction practice and associated measures were recommended
in water quality assessment to control water quality impacts to within
acceptable levels and are also expected to control impacts to fisheries
resources.
An environmental monitoring and audit
(EM&A programme) has been recommended for implementation during
construction of the Project to ensure compliance with environmental legislation
and standards during Project implementation.
Monitoring of construction noise and water
quality is recommended during construction of the Project to verify the
effectiveness of the mitigation measures and to obtain a robust, defensible
database of baseline information of noise and water quality before
construction, and thereafter, to monitor any variation of noise and water
quality from the baseline conditions and exceedances of relevant noise criteria
and water quality objectives (WQOs) at the sensitive receivers during
construction of the Project.
The EIA has provided information
on the nature and extent of environmental impacts likely to arise from the
construction and operation of the proposed submarine watermain of the Project. The EIA has, where required, proposed
mitigation measures to ensure compliance with environmental legislation and
standards.
Overall, the EIA Report concludes
that the Project would be environmentally acceptable with the implementation of
the proposed mitigation measures for construction and operation phases. An environmental monitoring and audit
programme has been recommended to ensure the effectiveness of recommended
mitigation measures.