Environmental
Protection Department
Agreement No.
CE20/2004 (EP)
North East New Territories (NENT) Landfill Extension
Environmental Monitoring
& Audit Manual
May 2007
1.2 Purpose and Scope of this
Manual
1.3 Description of the Project
2.1 Objectives of EM&A
Programme
2.2 Organisation for EM&A
Programme
2.3 Environmental Management Plan
2.7 Compliance with Action and
Limit Levels
2.11 Cessation of EM&A Programme
3.3 Precautionary Measures During
Operational, Restoration and Aftercare Phases
4.9 Environmental Mitigation
Measures
5.2 Precautionary / Mitigation
Measures during Construction and Operation Phases
6.2 Waste Control and Mitigation
Measures
8 Landscape
and Visual Monitoring
9 Cultural
Heritage Monitoring
9.3 Ngong Tong (North and West of
Shek Tsai Ha Road: Western & Central Section)
9.4 Tong To Shan (North of Shek
Tsai Ha Road: east section)
9.5 AMO requirements for Survey and
Preservation
10.2 Ecological Mitigation Measures
10.3 Monitoring and Audit for Ecology
11.2 Compliance with Environmental Requirements
12.2 Baseline Monitoring Report
12.5 Interim Notification of
Environmental Exceedances
APPENDICES
Appendix A Tentative Outline Programme
Appendix B Project Organisation
Appendix C Environmental Mitigation Implementation Schedule
Appendix D A Sample List of VOC Monitoring Parameters
DRAWINGS
24315/01/107 Landfill
Extension Layout Option 4
24315/13/151 Air
Monitoring Location
24315/13/251 Noise
Monitoring Location
24315/13/504 Existing
Landfill and Landfill Extension Monitoring Plan
24315/13/606 Archaeological
Findings
24315/13/702 Habitat Map Location of Species of
Conservation interest overlaid with Option 4
Currently, around 6 million tonnes of waste are disposed each year at the three strategic landfills in Hong Kong, including the West New Territories (WENT) Landfill, the South East New Territories (SENT) Landfill, and the North East New Territories (NENT) Landfill.
At time of commissioning, the three landfills with a total capacity
in the order of
To tackle the problem, further efforts have been taken to reduce and
recycle waste. Also, the HKSAR
Government has planned to develop Integrated Waste Management Facilities (IWMF)
to substantially reduce the volume of waste requiring landfill disposal. Yet these measures could not obviate totally
the need for new landfill capacity in
The Environmental Protection Department (EPD) of the HKSAR
Government therefore commissioned a study in Year 2000 on the Extension of
Existing Landfills and Identification of Potential New Waste Disposal
Sites. Amongst the potential sites
recommended in this territory-wide study is the extension of the existing NENT
Landfill, with a target capacity of about
In February 2005, EPD appointed Ove Arup & Partners Hong Kong Ltd. To undertake a detailed feasibility study for the NENT Landfill Extension (hereafter referred to “the Project”), with the following key tasks: formulation and evaluation of layout options for the landfill extension; EIA study; and conceptual design of landfill facilities.
Environmental Monitoring and Audit (EM&A) is an important aspect in the EIA process which specifies the timeframe and responsibilities for the implementation of environmental mitigation measures. The requirements on environmental monitoring (including baseline and impact monitoring) are given in the EM&A Manual (the Manual) which is a supplementary document to the EIA Study for the Project and prepared in accordance with the requirements in the EIA Study Brief and Technical Memorandum on Environmental Impact Assessment Process (TM-EIAO).
The purpose of this EM&A Manual is to guide the establishment of an EM&A programme to ensure compliance with the EIA recommendations, to assess the effectiveness of recommended mitigation measures, and to identify further need for additional mitigation measures or remedial action.
This Manual outlines the monitoring and audit requirements for the construction, operation, restoration and aftercare stages of the NENT Landfill Extension. It aims to provide systematic procedures for monitoring, auditing and minimising environmental impacts associated with construction works and operational activities.
This Manual contains the following information:
·
Organisation,
hierarchy and responsibilities of the DBO Contractor, Environmental Team (ET),
Independent Environmental Checker (IEC), and Independent Consultant (IC), with
respect to the EM&A requirements during the construction, operation,
restoration and aftercare phases of landfill extension;
·
Information
on project organisation and programming of construction activities;
·
Requirements
with respect to the construction schedule and necessary EM&A programme to
track the varying environmental impacts;
·
Full
details of methodologies to be adopted, including all field, laboratory and
analytical procedures, and details on quality assurance;
·
Procedure
for undertaking on-site environmental audits;
·
Definition
of Action and Limit Levels;
·
Establishment
of Event and Action Plans;
·
Requirements
of reviewing pollution sources and working procedures required in the event of
non-compliance of environmental criteria and complaints;
·
Requirements
for reviewing the EIA predictions, implementation of mitigation measures, and
effectiveness of environmental protection and pollution control measures
adopted; and
·
Presentation
of requirements for EM&A data and appropriate reporting procedures.
1.3.1 General Description of the Project
The development of the NENT Landfill Extension will involve the following works:
·
Site
formation, drainage diversion and preparation;
·
Installation
of liner system;
·
Installation
of leachate collection, treatment and disposal facilities;
·
Installation
of gas collection, utilization and management facilities;
·
Operation
and environmental monitoring of landfill;
·
Restoration
and aftercare.
1.3.2 Key Project Requirements
The
key project requirements for the NENT Landfill Extension are:
·
Development
of sanitary landfill that covers an area of about
·
Provision
of liner system for the landfill to prevent contamination of land and water
resources;
·
Provision
of leachate collection, treatment and disposal facilities with sufficient
capacity for handling the leachate arising from the new landfill;
·
Provision
of landfill gas (LFG) collection, utilisation and management facilities;
·
Provision
of utilities, drainage and road network necessary for the proper operation of
the Project;
·
Provision
of facilities (both civil works and electrical and mechanical equipment) for
waste reception, inspection, charging, handling and compaction, and plant
maintenance;
·
Provision
of facilities for site administration;
·
Operation
of landfill in compliance with all relevant engineering, geotechnical and
environmental standards;
·
Restoration
of landfill in compliance with all relevant engineering, geotechnical and
environmental standards;
·
Provision
of aftercare for the landfill for a period of about 30 years
·
Carrying
out environmental monitoring and audits throughout construction, operation,
restoration and aftercare of the landfill; and
·
Implementation
of environmental measures necessary for the protection of the surrounding
environment.
1.3.3 Size, Scale, Shape and Design of the Project
The landfill extension site will be a
bowl-shape area with a large void space in the middle for waste filling. The
northwestern and southeastern boundaries of the landfill extension site follow
the ridgelines to maximise the landfill
capacity. Some set back of the northern
boundary is included to minimise the impact to
woodland and Lin Ma Hang Catchment. The total site
area is
·
Bottom
liner system – separate rubbish and leachate from groundwater;
·
Landfill
cells – store waste within the unit;
·
Storm
water drainage system – collect rain water run off on the landfill;
·
Leachate
collection system – collect liquid leaching from the waste mass and convey it
to a leachate treatment plant prior to discharging to Shek Wu Hui Sewage
Treatment Works;
·
Gas
collection system – collect gases formed during the decompositon of waste.
These gases will be treated and utilised for production of electricity on site;
and
·
Covering
and capping – seal off the top of the landfill with a gas venting layer, an
impermeable mineral layer, a drainage layer of at least
1.3.4 Construction Phase Activities
Simple excavation and slope formation works will be carried out during the construction stage. The permanent works comprise cut and fill earthworks, slope formation and earth wall construction. The temporary works will involve the formations of temporary ditches along the sides of excavations and associated drainage works, and material storage areas. During site formation, sediment will be contained in permanent detention ponds/silt traps that will be constructed according to landfill phasing. Final design and location of sediment traps are yet to be decided, but are likely to be down gradient of each landfill phase or in the downstream valleys near the existing waste reception area. Where possible they will be maintained during the operation of each phase to ensure the effective control of operational soil erosion problem.
1.3.5 Operation Phase Activities
During operation, waste will be disposed of at individual landfill
cells. Deposited waste will be compacted
to thin layers of up to two metres in thickness. The works will be maintained at a gradient of
not greater than
·
Heavy duty reusable and biodegradable sheets;
·
Biodegradable, non-reusable plastic
films;
·
Geotextiles;
and
·
Foams
and sprays.
Advantages of using alternative daily cover over traditional methods may include preservation of void space and soil material; biodegradable and less permeable to water and gas (reduce water infiltration, odour and dust emission).
1.3.6 Restoration Phase Activities
Restoration is a process to restore a landfill site to a condition suitable for afteruse. After completion of waste filling, final capping will be applied to minimise infiltration of rainwater into the waste body thus reducing the amount of leachate generated. The capping system normally includes a number of components including topsoil, subsoil, drainage layer and barrier layer.
1.3.7 Aftercare Phase Activities
Aftercare is the work done after the replacement of the soil and includes cultivations, fertilisation, planting, construction of pathways, access points, vegetation maintenance and an ongoing long term commitment to the restored landfill. Landscaped berms will be created and tree planting will be provided during the aftercare period for aesthetic purpose.
The Landfill Extension will start receiving waste only when the Existing NENT Landfill has ceased operation. The timing of this has yet to be determined as it depends on the rate of waste deliveries in the forthcoming period. Based on current predictions, the capacity of the Existing Landfill will probably run out by early-to-mid next decade, by which time the Landfill Extension shall start operation.
Taking into account of the time needed for mobilization and preparatory works prior to commencement of receipt of waste, it may be necessary to award the Landfill Extension contract towards the end of this decade, this should talling with Project Programme anywhere else in the EIA. In order to ensure that new landfill space will be available before the capacity of the existing landfill runs out.
It is anticipated that the DBO (Design-Build-Operate) contract form, which has hitherto worked well for the existing waste management contracts (notably the three strategic landfill contracts and the refuse transfer station contracts), will be adopted for NENT Landfill Extension. Detailed design and formulation of technical details for the construction, operation, restoration and aftercare of the NENT Landfill Extension will be carried out by the DBO Contractor, in accordance with requirements stipulated in the Specification and other documents of the DBO Contract.
A tentative outline programme for implementation of the NENT Landfill Extension is shown in Appendix A. As pointed out above, the exact timing of the various activities may vary, depending on actual volume of waste to be delivered in the forthcoming years.
The requirements of EM&A programme should include the
recommendations from the EIA study and with reference to EPD’s
“Environmental Monitoring and Audit Guidelines for Development Projects in
The EM&A requirements recommended in the EIA Report will ensure compliance with the specified mitigation measures. An EM&A programme should be designed based on these requirements to achieve the following key objectives:
·
Establishment
of existing environmental setting of the site to assist the development of
landfill design and to establish a baseline against which any adverse
environmental impacts can be evaluated;
·
Provision
of a database against which any short- or long-term environmental impacts of
the Project can be determined against the Project compliance with regulatory
requirements, standards and Government policies;
·
Verification
of environmental impacts predicted in the EIA study and provision of an early
indication of any failure of environmental control measures or practices to
achieve the acceptable standards;
·
Evaluation
of environmental impacts during site preparation works and operational phases
of the landfill extension project to assist the determination of effectiveness
of the mitigation measures to be implemented, ensure compliance with the
relevant environmental regulations, and design of any additional mitigation
measures requirements;
·
Provision
of information to enable environmental audit of Project activities during
construction, operation, restoration and aftercare phases, and taking remedial
action if unexpected problems or unacceptable impacts arise; and
·
Provision
of a basis for long-term monitoring programme folllowing the completion of
works during the aftercare phase.
The proposed project organisation and lines of responsibilities with respect to the EM&A programme are shown in Appendix B, which consists of the Project Proponent (EPD/WFG), DBO Contractor, Environmental Team (ET), Independent Environmental Checker (IEC), and Independent Consultant (IC), etc. It should be established to take the responsibilities for environmental protection for this landfill extension project. The IEC will be appointed by the Project Proponent as part of the IC to conduct independent auditing of the overall EM&A programme including environmental and operation monitoring, implementation of mitigation measures, EM&A submissions, and any other submissions required under the Environmental Permit (EP). The individual responsibilities are:
DBO Contractor
·
Employment
of an ET to carry out environmental monitoring, laboratory analysis and
reporting of environmental monitoring and audit;
·
Provision
of assistance to ET in carrying out monitoring and auditing;
·
Submission
of proposals of mitigation measures in case of exceedances of Action and Limit (A/L)
Levels in accordance with the Event and Action Plan (EAP);
·
Implementation
of mitigation measures to reduce the impacts where A/L Levels are exceeded; and
·
Adherence
to the agreed procedures for carrying out complaint investigation.
ET
·
Setting
up of all the required environmental monitoring stations;
·
Monitoring
of various environmental parameters as required;
·
Analysis
of monitoring and audit data and review the success of EM&A programme to
cost-effectively confirm the adequacy of mitigation measures implemented and
the validity of the EIA predictions and to identify any adverse environmental
impacts arising;
·
Carrying
out site inspections to investigate and audit the DBO Contractor’s site
practices, equipment and work methodologies with respect to pollution control
and environmental mitigation, and take proactive actions to pre-empt problems;
·
Auditing
and preparation of audit reports on environmental monitoring data and site
conditions;
·
Reporting
of environmental monitoring and audit results to the IEC, DBO Contractor, IC
and Project Proponent or its delegated representative;
·
Recommendation
of suitable mitigation measures to the DBO Contractor in case exceedance of A/L
Levels in accordance with the EAP; and
·
Undertaking
of regular on-site audits/ inspections and reporting to the DBO Contractor and
IC of any potential non-compliance; and
·
Following
up and closing out of non-compliance actions.
IEC
·
Review
of EM&A programme by the ET (at not less than monthly intervals);
·
Auditing
of monitoring activities and results (at not less than monthly intervals);
·
Reporting
of audit results to the IC and Project Proponent in parallel;
·
Reviewing
of EM&A reports (monthly, quarterly and annual summary reports) submitted
by the ET;
·
Reviewing
of proposal of mitigation measures submitted by the DBO Contractor in
accordance with the EAP;
·
Checking
of mitigation measures recommended in the EIA Report and EM&A Manual, and
ensuring they are properly implemented in timely manner when required; and
·
Reporting
of findings of site inspections and other environmental performance reviews to
IC and Project Proponent.
IC
·
Verification
and checking DBO Contractor’s activities and ensure that the requirements in
the EM&A Manual are fully complied with;
·
Informing
DBO Contractor when action is required to reduce impacts in accordance with the
EAP;
·
Ensure
compliance with the agreed Event Action Plan in case any exceedance.
Sufficient and suitably qualified professional and technical staff should be employed by the respective parties to ensure full compliance with their duties and responsibilities, as required under the EM&A programme for the duration of the Project.
A systematic Environmental Management Plan (EMP) should be developed and implemented by the DBO Contractor in accordance with the ETWB TC(W) 19/2005 Environmental Management on Construction Sites to ensure effective implementation of the mitigation measures, monitoring and remedial requirements presented in the EIA, EM&A and environmental mitigation implementation schedule (EMIS) (Appendix C). The IEC should audit the implementation status of EMP and advise the necessary remedial action as required. Such remedial actions should be enforced through contractual requirements. The EMP should be certified by the ET and verified by the IEC.
The EMP should require the DBO Contractor (and sub-contractors) and
ET to define in details how to implement the recommended mitigation measures in
order to achieve the environmental performance stipulated in the
The EMP should summarise the requirements for the DBO Contractor to submit a Landfill Monitoring Plan (LMP) and an Emergency Response Plan (ERP) for approval. The LMP should describe the procedures and provide details of the environmental monitoring programme for the DBO Contractor to carry out throughout the construction, operation, restoration and aftercare phases of the Project. The ERP should address various scenarios within NENT Landfill Extension, in particular in the event of leakage of LFG/ leachate, failure of LFG/ leachate treatment operation, fire, chemical/ DG spillage, etc.
If the DBO Contractor would adopt alternative construction methods or implementation schedules, the detailed modifications of methodology and equipment should be submitted to the IEC for approval prior to the commencement of works. Any changes in construction methods should be indicated in the revised EMP. The DBO Contractor should review the EMIS with respect to the design developments and construction methodology. All necessary mitigation measures identified and recommended in the EIA study are summarised in the EMIS, which specifies the extent, locations, time frame and responsibilities for the implementation of the environmental mitigation measures identified.
The DBO Contractor should develop the waste management requirements as part of the EMP in Section 2.3 above for the construction phase of the Project. The DBO Contractor should also prepare a Waste Management Plan (WMP) for the Project during the operational, restoration and aftercare phases. Where waste generation is unavoidable, any opportunities for recycling or reuse of the wastes should be maximised. If the wastes cannot be recycled, recommendations for appropriate disposal routes should be provided in the WMP. A method statement for stockpiling and transportation of the excavated materials and other construction wastes should also be included in the WMP and approved before the commencement of construction. All mitigation measures arising from the approved WMP should be fully implemented. The WMP should be certified by the ET and verified by IEC.
It is not anticipated that any significant quantities of excavated C&D materials would require off-site disposal, as most will be reused on-site. Notwithstanding this, a trip-ticket system should be put in place in accordance with ETWB TC(W) No 31/2004. Copies/ counterfoils from trip-tickets (showing the quantities of C&D Materials taken off-site) should be kept for record purposes.
For the purpose of enhancing the management of Construction and Demolition (C&D) materials including rock, and minimising its generation at source, construction would be undertaken in accordance with the Environment, Transport and Works Bureau Technical Circular (Works) No 33/2002 – Management of Construction and Demolition Material Including Rock, or its latest versions. The management measures stipulated in the Technical Circular should be incorporated.
Prior to the commencement of construction works, the baseline
conditions of environmental parameters should be established at designated
monitoring locations to determine the nature and ranges of natural variation
and to demonstrate the suitability of the proposed impact, control and
reference monitoring locations in the EM&A programme. The baseline conditions of the following
environmental parameters should be established by the ET, including air quality
(dust, organic emissions, odour), noise, water quality (groundwater and surface water),
ecology (vegetation and biodiversity), landscape and visual, and cultural
heritage.
During the implementation of the Project, environmental monitoring should be conducted at designated monitoring locations to detect the changes of environmental parameters attributed to the Project. Impact monitoring should be conducted during all phases of the Project. The environmental monitoring parameters during construction phase should include air quality (dust, organic emissions, odour), noise, water quality (groundwater and surface water), ecology (vegetation and biodiversity), landscape and visual, and cultural heritage. The monitoring during operational, restoration and aftercare phases should include all parameters of construction phase, in addition to leachate and LFG.
The A/L Levels should be defined for environmental monitoring at designated monitoring locations exceeding which a prescribed response should be required. Individual A/L Levels should be quantitatively defined for the respective environmental monitoring parameters according to the following basic principles:
2.7.1 Action Level
Action Levels indicate deteriorating ambient environmental quality potentially due to the Project implementation. It acts as a sign to trigger appropriate remedial actions in order to rectify any mal-practices or non-conformance of Project activities thereby preventing the deterioration of environmental quality and to resume the ambient environmental quality back to normal levels.
2.7.2 Limit Level
Limit Levels are the statutory and/or contractual levels below which environmental conditions are considered unacceptable. If Limit Levels were exceeded, the relevant part of the works should not be continued without implementation of immediate remedial action, including a critical review of plant and working methods.
The EAP should lay down the systematic procedures for implementation in case exceedances of A/L Levels and environmental complaints in order to timely address, investigate and resolve such incidents and minimise their recurrence. The EAP should define the action under specific conditions, i.e. exceedances of A/L Levels, and trigger the relevant parties in the EM&A programme to take the action.
Environmental audit should include the following components:
·
Regular
inspection of site practices should be conducted to assess and ensure the
environmental protection and pollution control measures to be in accordance
with the EIA recommendations and complied with contract specifications.
·
Examination
of all available information related to the investigation of the nature and
cause of actual, potential and cumulative environmental impacts and complaints/
queries;
·
Proposal
for remedial measures for resolution of impacts, effective implementation of
proposed mitigation measures, documentation and summary of audit findings, and
liaison and consultation with the public and concerned parties on the effects
of such remedial works; and
·
Enquiries
and complaints related to the environmental performance of the Project should be
anticipated from individuals and organisations, which should be referred to the
ET Leader for investigation and action.
Systematic procedures for environmental complaints should be established
and followed. During the complaint
investigation, the DBO Contractor and IEC should facilitate the ET by providing
all necessary information.
2.10.1 Baseline Monitoring
Baseline Monitoring Report should be prepared by the ET and submitted within 4 weeks of completion of baseline monitoring to include all the baseline monitoring data and findings. The Report should be certified by the ET and verified by the IEC prior to submission to the EPD.
2.10.2 Impact Monitoring
Monthly EM&A Reports should be prepared by the ET and submitted within 21 days of each reporting month during construction, operational, restoration and aftercare phases to include all the impact monitoring data, findings and recommendations. Quarterly Summary, Annual Review and Final Review EM&A Reports should be prepared by the ET and submitted within 10 days of each reporting quarter, reporting year and cessation of project phase, respectively, during construction and operational, restoration, and aftercare phases to include all the summary of monitoring trends, findings and recommendations. These reports should be certified by the ET and verified by the IEC prior to formal submission to the EPD.
To implement the EM&A programme according to the Construction and Operational Phases, Restoration Phase and Aftercare Phase in which different EM&A requirements should be imposed, the ET and IEC should notify the EPD the completion of EM&A programme for the specific Project phases and request for agreement to cease the EM&A programme.
Monitoring of the Total Suspended Particulate (TSP) levels shall be
carried out by the ET to ensure that any deteriorating air quality could be
readily detected and timely action be taken to rectify the situation. 1-hour and 24-hour TSP levels should be
measured to indicate the impacts of construction dust on air quality. The TSP levels shall be measured by following
the standard high volume sampling method as set out in the Title 40 of the Code
of Federal Regulations,
All relevant data including temperature, pressure, weather conditions, elapsed-time meter reading for the start and stop of the sampler, identification and weight of the filter paper, and other special phenomena and work progress of the concerned site etc. shall be recorded down in details.
High volume sampler (HVS) in compliance with the following specifications shall be used for carrying out the 1-hr and 24-hr TSP monitoring:
·
0.6
· equipped with a timing/control device with +/- 5 minutes accuracy for 24 hours operation;
· installed with elapsed-time meter with +/- 2 minutes accuracy for 24 hours operation;
·
capable of providing a minimum
exposed area of
· flow control accuracy: +/- 2.5% deviation over 24-hr sampling period;
· equipped with a shelter to protect the filter and sampler;
· incorporated with an electronic mass flow rate controller or other equivalent devices;
· equipped with a flow recorder for continuous monitoring;
· provided with a peaked roof inlet;
· incorporated with a manometer;
· able to hold and seal the filter paper to the sampler housing at horizontal position;
· easy to change the filter; and
· capable of operating continuously for 24-hr period.
The ET Leader is responsible for provision of the monitoring equipment. He shall ensure that sufficient number of HVSs with an appropriate calibration kit are available for carrying out the baseline monitoring, regular impact monitoring and ad hoc monitoring. The HVSs shall be equipped with an electronic mass flow controller and be calibrated against a traceable standard at regular intervals. All the equipment, calibration kit, filter papers, etc. shall be clearly labeled.
Initial calibration of dust monitoring equipment shall be conducted upon installation and thereafter at bi-monthly intervals. The transfer standard shall be traceable to the internationally recognised primary standard and be calibrated annually. The calibration data shall be properly documented for future reference. All the data should be converted into standard temperature and pressure condition. The flow-rate of the sampler before and after the sampling exercise with the filter in position shall be verified to be constant and be recorded down in the data sheet.
If the ET Leader proposes to use a direct reading dust meter to measure 1-hr TSP levels, he shall submit sufficient information to the IC and IEC to prove that the instrument is capable of achieving a comparable result as that of the HVS and may be used for the 1-hr sampling. The instrument should also be calibrated regularly, and the 1-hr sampling shall be determined periodically by HVS to check the validity and accuracy of the results measured by direct reading method.
Wind data monitoring equipment shall also be provided and set up at conspicuous locations for logging wind speed and wind direction near to the dust monitoring locations. The equipment installation location shall be proposed by the ET Leader and agreed with the ER. For installation and operation of wind data monitoring equipment, the following points shall be observed:
·
the wind sensors should be
installed on masts at an elevated level
· the wind data should be captured by a data logger and to be downloaded for processing at least once a month;
· the wind data monitoring equipment should be re-calibrated at least once every six months; and
· wind direction should be divided into 16 sectors of 22.5 degrees each.
In exceptional situations, the ET Leader may propose alternative methods to obtain representative wind data upon approval from the IC and IEC, and agreement from EPD.
3.1.3 Laboratory Measurement/Analysis
A clean laboratory with constant temperature and humidity control, and equipped with necessary measuring and conditioning instruments, to handle the dust samples collected, shall be available for sample analysis, and equipment calibration and maintenance. The laboratory should be HOKLAS accredited.
If a site laboratory is set up or a non-HOKLAS accredited laboratory is hired for carrying out the laboratory analysis, the laboratory equipment shall be approved by the IC and IEC and the measurement procedures (first measurement) shall be witnessed by the IC and IEC. The ET Leader shall provide the IC and IEC with one copy of the Title 40 of the Code of Federal Regulations, Chapter 1 (Part 50), Appendix B for his reference.
Filter paper of size 8"x10" shall be labeled before sampling. It shall be a clean filter paper with no pin holes, and shall be conditioned in a humidity controlled chamber for over 24-hr and be pre-weighed before use for the sampling.
After sampling, the filter paper loaded with dust shall be kept in a clean and tightly sealed plastic bag. The filter paper is then returned to the laboratory for reconditioning in the humidity controlled chamber followed by accurate weighing by an electronic balance with a readout down to 0.1 mg. The balance shall be regularly calibrated against a traceable standard. All the collected samples shall be kept in a good condition for 6 months before disposal.
The dust monitoring locations are shown in Table 3.1. The status and locations of dust sensitive receivers may change after issuing this manual. If such cases exist, the ET Leader shall propose updated monitoring locations and seek approval from IC and IEC and agreement from EPD on the proposal.
The ET shall also write to the relevant private owners or owner’s incorporation for their agreement to install the HVS at suitable location at least 3 months before construction works. The purpose of monitoring (to minimize potential impact and to safeguard the residential) should be clearly stipulated. The specification, wiring, fixing, maintenance, communication and payment of electricity cost shall be detailed in the letter. If there is objection from the owner, alternative monitoring location at premises in the vicinity shall be identified and agreed with EPD, IEC and IC. The monitoring location is illustrated in Drawing No. 24315/13/151.
Table 3.1 Description
of dust monitoring locations
AML ID |
EIA ASR Ref |
Location |
Land Uses |
Monitoring Parameters |
AM(D)1 |
ASR11 |
Tung Lo Hang |
Residential/ Pig Farm |
1-hr and 24-hour TSP |
AM(D)2 |
ASR7 |
Heung Yuen Wai |
Residential |
1-hr and 24-hour TSP |
AM(D)3 |
ASR1 |
Wo Keng Shan Tsuen |
Residential |
1-hr and 24-hour TSP |
When alternative monitoring locations are proposed, the following criteria, as far as practicable, should be followed:
· At the site boundary or such locations close to the major dust emission source;
· Close to the sensitive receptors; and
· Account for the prevailing meteorological conditions.
The ET Leader shall agree with the IC and IEC on the position of the HVS for installation of the monitoring equipment. When positioning the samplers, the following points shall be noted:
· a horizontal platform with appropriate support to secure the samplers against gusty wind should be provided;
· no two samplers should be placed less than 2 meter apart;
· the distance between the sampler and an obstacle, such as buildings, must be at least twice the height that the obstacle protrudes above the sampler;
· a minimum of 2 metres separation from walls, parapets and penthouses is required for rooftop samplers;
· a minimum of 2 metres separation from any supporting structure, measured horizontally is required;
· no furnace or incinerator flue is nearby;
· airflow around the sampler is unrestricted;
· the sampler is more than 20 metres from the drip-line;
· any wire fence and gate, to protect the sampler, should not cause any obstruction during monitoring;
· permission must be obtained to set up the samplers and to obtain access to the monitoring stations; and
· a secured supply of electricity is needed to operate the samplers.
The ET Leader shall carry out baseline monitoring at all of the designated monitoring locations for at least 14 consecutive days prior to the commencement of the construction works to obtain daily 24-hr TSP samples. 1-hour sampling shall also be done at least 3 times per day while the highest dust impact is expected. During the baseline monitoring, there should not be any construction or dust generation activities in the vicinity of the monitoring stations.
In case the baseline monitoring cannot be carried out at the designated monitoring locations during the baseline monitoring period, the ET Leader shall carry out the monitoring at alternative locations which can effectively represent the baseline conditions at the impact monitoring locations. The alternative baseline monitoring locations shall be approved by the IC and IEC and agreed with EPD.
In exceptional case, when insufficient baseline monitoring data or questionable results are obtained, the ET Leader shall liaise with EPD to agree on an appropriate set of data to be used as a baseline reference and submit to IC and IEC for approval.
If the baseline level for air quality exceeds the limit level, the ET shall carry out an investigation to determine the cause of the exceedance in consultation with EPD. Regardless of whether the exceedance was caused by poor weather condition (e.g. high API) or as a result of inadequate control measures on construction activities being carried out on other nearby construction sites, a second set of baseline monitoring shall be conducted by the ET to determine an appropriate baseline level for the EM&A programme in agreement with EPD.
Ambient conditions may vary seasonally and shall be reviewed at every three months. If the ET Leader considers that the ambient conditions have been changed and a repeat of the baseline monitoring is required to be carried out for obtaining the updated baseline levels, the monitoring should be at times when the DBO Contractor's activities are not generating dust, at least in the proximity of the monitoring stations. Should change in ambient conditions be determined, the baseline levels and, in turn, the air quality criteria, should be revised. The revised baseline levels and air quality criteria should be agreed with EPD.
The ET Leader shall carry out impact monitoring during the course of the Works. For regular impact monitoring, the sampling frequency of at least once in every six-days, shall be strictly observed at all the monitoring stations for 24-hr TSP monitoring. For 1-hr TSP monitoring, the sampling frequency of at least three times in every six-days should be undertaken when the highest dust impact occurs. The specific time to start and stop the 24-hr TSP monitoring shall be clearly defined for each location and be strictly followed by the DBO Contractor.
In case of non-compliance with the dust criteria, more frequent
monitoring exercise, as specified in the Action Plan in Section
The baseline monitoring results form the basis for determining the air quality criteria for the impact monitoring. The ET Leader shall compare the impact monitoring results with air quality criteria set up for 24-hour TSP and 1-hour TSP. Table 3.2 shows the dust criteria, namely Action and Limit levels to be used. Should non-compliance of the air quality criteria occur, the ET, the IC/IEC and the DBO Contractor shall undertake the relevant action in accordance with the Action Plan in Table 3.3.
Table 3.2 Action and limit levels for dust impact
Parameters |
Action |
Limit |
24-hour TSP Level in µg/m³ |
For baseline level 200 µg/m³,
Action level = (130% of baseline level + Limit level)/2 For baseline level > 200
µg/m³, Action level = Limit level |
260 |
1-hour TSP Level in µg/m³ |
For baseline level 384 µg/m³,
Action level = (130% of baseline level + Limit level)/2 For baseline level > 384
µg/m³, Action level = Limit level |
500 |
Table 3.3 Event/Action plan for dust impact
Event |
ET |
IEC |
IC |
DBO Contractor |
Exceedance of Action Level |
||||
1. Exceedance for one sample |
· Identify
source · Inform IEC and
DBO Contractor · Repeat
measurement to confirm findings · Increase monitoring
frequency to daily |
· Check
monitoring data and DBO Contractor's working methods |
· Notify DBO
Contractor for the identification of cause |
· Rectify any
unacceptable practice · Amend working
methods if appropriate |
2. Exceedance for two or more consecutive
samples |
· Identify
source · Notify IEC and
DBO Contractor · Repeat
measurements to confirm findings · Increase
monitoring frequency to daily · Discuss with
IEC/IC for remedial actions required · If exceedance continues, arrange meeting with IEC · If exceedance stops, cease additional monitoring |
· Review with
analysed results submitted by ET · Review the
proposed remedial measures by DBO Contractor and advise IC accordingly · Supervise the
implementation of remedial measures |
· Confirm
receipt of notification of exceedance in writing · Notify DBO
Contractor · Require DBO
Contractor to propose remedial measures for the analysed dust problem · Ensure
remedial measures are properly implemented |
· Submit
proposals for remedial actions to IEC within 3 working days of notification · Implement the
agreed proposals · Amend proposal
if appropriate |
Exceedance of Limit Level |
||||
1.Exceedance for one sample |
· Identify
source · Inform IEC and
DBO Contractor · Repeat
measurement to confirm findings · Increase monitoring
frequency to daily · Assess
effectiveness of DBO Contractor's remedial actions and keep EPD and IEC/IC
informed of the results |
· Check
monitoring data and DBO Contractor's working methods · Discuss with
ET Leader and DBO Contractor potential remedial actions · Supervise the
implementation of remedial measures |
· Confirm
receipt of notification of exceedance in writing · Notify DBO
Contractor · Require DBO
Contractor to propose remedial measures for the analysed dust problem · Ensure remedial
measures are properly implemented |
· Take immediate
action to avoid further exceedance · Submit
proposals for remedial actions to IEC within 3 working days of notification · Implement the
agreed proposals · Amend proposal
if appropriate |
2.Exceedance for two or more consecutive samples |
· Identify
source · Inform IEC,
IC, and EPD the causes and actions
taken for the exceedances · Increase
monitoring frequency to confirm findings · Carry out analysis
of DBO Contractor’s working procedures to determine possible mitigation to be
implemented · Assess
effectiveness of DBO Contractor’s remedial actions and keep IEC, EPD and IC
informed of the results · If exceedance stops, cease additional monitoring |
· Discuss
amongst IC, ET Leader and DBO Contractor on the potential remedial actions. · Review DBO
Contractor’s remedial actions whenever necessary to assure their
effectiveness and advise IC accordingly · Supervise the
implementation of remedial measures |
· Confirm
receipt of notification of exceedance in writing · Notify DBO
Contractor · Require DBO
Contractor to propose remedial measures for the analysed dust problem · Ensure
remedial measures are properly implemented · If exceedance continues, consider what activity of the work
is responsible and instruct DBO Contractor to stop that activity of work
until the exceedance is abated |
· Take immediate
action to avoid further exceedance · Submit
proposals for remedial actions to IEC within 3 working days of notification · Implement the
agreed proposals · Resubmit
proposals if problem still not under control · Stop the
relevant activity of works as determined by the IC until the exceedance is abated |
3.1.8 Dust Mitigation Measures
The EIA report has recommended dust control and mitigation measures. The DBO Contractor shall be responsible for the design and implementation of these measures:
· Dust emission from construction vehicle movement are confined within the worksites area.
· Watering facilities will be provided at every designated vehicular exit point.
· Good site practice is recommended during construction phase. Covering with impermeable sheet should be provided for the inactive tipping area.
If the above measures are not sufficient to restore the air quality to acceptable levels upon the advice of ET Leader, the DBO Contractor shall liaise with the ET Leader on some other mitigation measures, propose to IC and IEC for approval, and implement the mitigation measures.
3.2.1 Odour Intensity Analysis
Odour Intensity Analysis is conducted by independent trained personnel / competent persons patrolling and sniffing around the Air Sensitive Receiver to detect any odour at the concerned hours.
The independent trained personnel / competent persons shall :
· have their individual odour threshold of n-butanol in nitrogen gas in the range of 20 to 80 ppb/v required by the European Standard Method (EN 13725).
· be at least 16 years of age and willing and able to follow instructions.
· be free from any respiratory diseases.
· be engaged for a sufficient period to build up and monitor/detect at several monitoring location;
· not be allowed to smoke, eat, drink (except water) or use chewing gum or sweets 30 min before and during odour intensity analysis;
· take great care not to cause any interference with their own perception or that of others by lack of personal hygiene or the use of perfumes, deodorants, body lotions or cosmetics;
· not communicate with each other about the results of their choices.
At least three independent trained personnel / competent persons shall be selected to form a patrol team to conduct the odour intensity analysis, who should participated in a set of screening tests.
Subject to the prevailing weather forecast condition, odour intensity analysis shall be conducted by independent trained personnel / competent persons at the downwind locations. During the analysis, the sequence should start from less odorous locations to stronger odorous locations.
The independent trained personnel / competent persons shall use their nose (olfactory sensors) to sniff odours at different locations. The main odour emission sources and the areas to be affected by the odour nuisance shall be identified.
The perceived odour intensity is to be divided into 5 levels which are ranked in the descending order as follows:
· 0 - Not detected. No odour perceived or an odour so weak that it can not be easily characterised or described;
· 1 - Slight Identifiable odour, and slight chance to have odour nuisance;
· 2 - Moderate Identifiable odour, and moderate chance to have odour nuisance;
· 3 - Strong Identifiable, likely to have odour nuisance;
· 4 - Extreme Severe odour, and unacceptable odour level.
The independent trained personnel / competent persons shall record the findings including odour intensity, odour nature and possible odour sources, and also the local wind speed and direction at each location. In addition, some relevant meteorological data such as daily average temperature, and daily average humidity, on that surveyed day shall be obtained from the Hong Kong Observatory Station for reference.
3.2.2 Odour Patrol
Apart from odour intensity analysis, routine odour patrol by competent persons shall also be conducted to detect odour nuisance.
3.2.3 Odour Intensity Analysis / Odour Patrol Locations
The odour intensity analysis and odour patrol locations are shown in Table 3.4. The status and locations of air sensitive receivers may change after issuing this manual. If such cases exist, the ET Leader shall propose updated monitoring locations and seek approval from IC and IEC and agreement from EPD on the proposal. The monitoring location is illustrated in Drawing No. 24315/13/151.
Table 3.4 Description
of odour monitoring locations
AML ID |
EIA ASR Ref |
Location [1] |
Land Uses |
Monitoring Parameters |
AM(O)1 |
ASR1 |
Wo Keng Shan Tsuen |
Residential |
Odour Intensity |
AM(O)2 |
ASR2 |
Village houses at Junction
of Ng Chow Road and |
Residential |
Odour Intensity |
AM(O)3 |
ASR13 |
Nga Yiu Ha |
Residential |
Odour Intensity |
AM(O)4 |
ASR14 |
Ping Yeung |
Residential |
Odour Intensity |
AM(O)5 |
ASR10 |
Lin Ma Hang |
Residential |
Odour Intensity |
AM(O)6 |
ASR27 |
Tong To Shan Tsuen [2] |
Only if it is occupied by
residents |
Odour Intensity |
Remark:
[1] Odour odour intensity analysis and odour patrol shall only be conduced for the downwind monitoring locations.
[2] Tong To Shan Tsuen is currently a derelict isolated single house.
3.2.4 Event and Action
Table 3.5 shows the Action and Limit levels to be used, and the patrol frequency is listed in Table 3.6. Should non-compliance of the air quality criteria occur, the ET, the IC/IEC and the DBO Contractor shall undertake the relevant action in accordance with the Action Plan in Table 3.7.
Table 3.5 Action and limit levels for odour nuisance
Parameters |
Action |
Limit |
Odour Nuisance (from odour
intensity analysis or odour patrol) |
· When two documented complaint are received; or · Odour Intensity of 2 is measured from odour
intensity analysis. |
· Five or more consecutive geninue documented
complaints within a week; or · Odour Intensity of 3 or above is measured from odour
intensity analysis. |
Table 3.6 Odour Intensity Analysis and Odour Patrol Frequency
Routine Mode |
Action Level |
Limit Level |
Odour
Patrol : Once every six days during the following period: ·
early morning;
and ·
peak tipping
hour (e.g. 11:00am), Odour
Intensity Analysis : Quarterly during the following period: ·
early morning;
and ·
peak tipping
hour (e.g. 11:00am), |
Daily odour patrol. Weekly odour intensity analysis for 2 period during: · early morning; and · peak tipping hour (e.g. 11:00am) |
Daily odour patrol. Daily odour intensity analysis for 2 period during: · early morning; and · peak tipping hour (e.g. 11:00am) |
Table 3.7 Event/Action plan for odour nuisance
Event |
ET |
IEC |
IC |
DBO Contractor |
Action Level |
· Identify
source · Inform IEC and
DBO Contractor · If nuisance
stops or external source has been identified, resume monitoring to routine
mode · Recommend
precautionary measures |
· Review
submissions and reports from ET |
· Notify DBO
Contractor · Ensure
implementation of precautionary measures |
· Rectify any
unacceptable practice · Review the
operation of odour enhancement facilities at leachate
treatment plants · Amend working
methods if appropriate · Carry out
precautionary measures |
Limit Level |
· Identify
source · Inform IEC, and
IC, the causes and actions taken for the nuisance · Carry out
analysis of DBO Contractor’s working procedures to determine possible
mitigation to be implemented · Assess
effectiveness of DBO Contractor’s remedial actions and keep IEC, EPD and IC
informed of the results · If nuisance
stops or external source has been identified, resume monitoring to routine
mode |
· Discuss
amongst IC, ET Leader and DBO Contractor on the potential remedial actions. · Review DBO
Contractor’s remedial actions whenever necessary to assure their
effectiveness and advise IC accordingly · Supervise the
implementation of remedial measures |
· Confirm
receipt of notification of exceedance in writing · Notify DBO
Contractor · Require DBO
Contractor to propose remedial measures for the analysed odour nuisance · Ensure
remedial measures are properly implemented · If nuisance
continues, instruct DBO Contractor to stop that activity of work suspected to
be the origin of the nuisance source until the nuisance is abated |
· Take immediate
action to avoid further nuisance · Submit
proposals for remedial actions to IEC within 3 working days of notification · Proposals
include tipping at the far end of the upwind location; thicker daily cover
can be arranged in case odour patrol identify potential odour nuisance; and
use of immediate soil cover for sewage sludge, animal waste · Implement the
agreed proposals · Resubmit
proposals if problem still not under control |
3.3.1 Stack Discharge from ASP, Flare and LFG Power Generator
· The maximum allowable discharge limit for ASP, flare and LFG power generator should be specified in the design specification.
· Owing to the requirement for the installation of stack, the design requirement shall be submitted to IEC and IC for vetting by the DBO Contractor under the Air Pollution Control (Furnaces, Ovens and Chimneys) (Installation and Alternation) Regulations.
· Subject to the subsequent EPD’s requirement on chimney installation, once every 3 months regular stack monitoring of vinyl chloride, benzene, TOC, NOx and SO2 shall be carried out to demonstrate compliance during the operations.
· A monthly monitoring report should be prepared by ET and submitted to IEC and IC for approval.
3.3.2 Odour from Leachate Treatment Facilities
For the
proposed leachate treatment plant in NENT Landfill
Extension, the overall leachate treatment facilities
include:
· Adopted updated treatment method such as Sequencing Batch Reactor for future leachate treatment. Provision of ventilated cover for the leachate storage lagoons / tanks and emissions extracted to suitable odour removal filters with odour removal efficiency of 99%.
· Ferric nitrate or sodium hypochlorite can be added to oxidise the odourous chemical in the leachate. The pH value of leachate can be controlled to a suitable value from future on-site experiment such that the generation of any odourous H2S and ammonia can be optimised.
· For the gaseous extraction system, the wind speed immediately above the leachate surface should be kept to minimal (in the order of 1E-3 m/s) such that the odour emission strength from lagoon can be minimised. Suitable treatment system should be provided for odour removal. The ventilated gaseous emission from lagoons should be provided with 5-10 air change per hour for further dilution before discharge.
· The notional centre of the future discharge point (e.g. stack) shall be located at a location with maximum setback distance from the ASRs and further away from the notional centre of the lagoons. The location of discharge point and discharge height should be determined at the detailed design stage to ensure that the odour criterion at the ASRs will not be exceeded.
· The overall arrangement should be investigated in details by the DBO Contractor and agreed with IEC and EPD. As such, the odour emission from the future leachate treatment facilities will be insignificant.
3.3.3 Odour from Waste Transfer Activities
The following are some odour precautionary measures that shall be considered by EPD and FEHD:
· As an improvement measure to enhance to environmental standard for waste transfer, EPD could take the initiative to recommend others to use enclosed type RCVs (dominantly government vehicles and sludge vehicles).
· Clearing / watering of the surface and clearing of the waste water receptor of government RCV is recommended before leaving refuse transfer station or government Refuse Collection Point (FEHD).
3.3.4 Precautionary Odour from Waste Tipping Activities
· The use of alternative daily cover (less permeable layer) instead of inert material should be considered under worst-case weather condition, subject to EM&A Programme.
· The use of immediate daily cover for odorous waste such as sewage sludge, animal waste etc. under critical condition should also be considered, subject to EM&A Programme.
· For the time being, there is no population in the derelict Tong To Shan Tsuen. If there is new residents moving in, thicker daily cover / alternative daily cover should be applied at phase 3 of the extension site such that the emission strength for the night time can be reduced (similar performance as that in the inactive tipping area). Odour patrol at Tong To Shan Tsuen should be arranged during night time / early morning in order to ensure the effectiveness of the measures.
·
In accordance with some
reference from
· During stable and calm weather condition and subject to EM&A programme, tipping could be arranged to further increase the setback distance.
3.3.5 VOC Surface Emission
· The VOC monitoring requirements are discussed in Section 7. Details will be further established in the Landfill Monitoring Plan (LMP) to be developed by the future DBO Contractor based on EM&A Manual for landfill gas monitoring.
· Subject to future engineering design, the arrangement of the landfill gas collection system and surface covering material for inactive tipping area shall be reviewed by DBO Contractor every 5 year to identify any modern technology/arrangement (covering material, LFG well spacing and locations) and the latest WHO/USEPA health-risk criteria. A working team shall be formulated to review all processes, control practice and extraction system in order to maximise the efficiency of the system. A review report should be prepared by the DBO Contractor for the submission to IC and IEC on the implementation/arrangement of LFG extraction system. The first review report should be submitted to IC and IEC for agreement before commencement. With a good system to collect LFG (high extraction efficiency), surface release of VOC to the nearby environment can be much reduced or utilised.
· Maintain a slightly negative pressure within the entire tipping area (by suction). Minimise any potential leakage of LFG to the surrounding by increase the number of gas-extraction wells. Improve the extraction efficiency by checking/reinstate gas wells with abnormally low extraction rate due to blockage/soil movement or sedimentation.
· Increase the coverage of inactive tipping area with HDPE/plastic sheet which can enhance the anaerobic decomposition (reduce air getting in and VOC leaking out).
· EM&A will be conducted at ASR to establish the future VOC ambient level one year before (as baseline) and one year after the commissioning of NENT extension. This monitoring work should be carried out in a frequency once every 3 month during the period when the ASP and flare are not in operation (only have the contribution from surface emission). Benzene and vinyl chloride are the key monitoring parameters. By comparing the monitoring data at the boundary and at ASR, the cause of VOC and the general downwind dispersion effect (dilution effect) from the boundary to the ASR can be identified. This monitoring should be repeated by the DBO Contractor once every 5 year and the findings should be incorporated into the landfill gas collection system review report as mentioned above.
· The monitoring location is listed in Table 3.4 and illustrated in Drawing No. 24315/13/151. This off-site VOC monitoring report shall be submitted to IC and IEC for vetting.
Table 3.8 Off-site
Surface gas monitoring locations at ASRs
AML ID |
EIA ASR Ref |
Location |
Land Uses |
Monitoring Indicator |
AM(V)1 |
ASR1 |
Wo Keng Shan Tsuen (West of NENT Extension) |
Residential |
Benzene and Vinyl Chloride |
AM(V)2 |
ASR3 |
Cheung Shan Monastery (South of NENT Extension) |
Religions |
Benzene and Vinyl Chloride |
AM(V)3 |
ASR10 |
Lin Ma Hang (North of NENT Extension) |
Residential |
Benzene and Vinyl Chloride |
AM(V)4 |
ASR27 |
Tong To Shan Tsuen (North-east of NENT Extension) |
Only if it is occupied by residents |
Benzene and Vinyl Chloride |
4.1 Monitoring Parameters
Construction noise level shall be measured in
terms of the A-weighted equivalent continuous sound pressure level (Leq). Leq30min
shall be used as the monitoring parameter for the time period between 0700 and
1900 hours on normal weekdays. For all
other time periods, Leq5min shall be employed for comparison with
the Noise Control Ordinance (NCO) criteria.
As supplementary information for data auditing, statistical results such
as L10 and L90 shall also be obtained for reference.
4.1.2 Operational and Traffic Noise
The noise level shall be measured in terms of
the A-weighted equivalent continuous sound pressure level over a period of 30
minutes (LAeq, 30mins) and
A-weighted 10% of time over a period of one hour (LA10, 1hr) for operational noise and operational traffic
noise, respectively. As supplementary information for data auditing,
statistical results such as LA10, LAeq and LA90 shall
also be obtained for reference.
In accordance with the Technical Memorandum (TM)
issued under the Noise Control Ordinance (NCO), sound level meters in
compliance with the International Electrotechnical
Commission Publications 651: 1979 (Type 1) and 804: 1985 (Type 1)
specifications shall be used for carrying out the noise monitoring. Immediately prior to and following each noise
measurement, the accuracy of the sound level meter shall be checked using an
acoustic calibrator generating a known sound pressure level at a known
frequency. Measurements may be accepted
as valid only if the calibration level from before and after the noise
measurement agree to within 1.0dB.
The ET Leader shall be responsible for the
provision, installation and maintenance of the monitoring equipment. He shall ensure that sufficient noise
monitoring equipment and associated instrumentation are available for carrying
out the baseline monitoring, regular impact monitoring and ad hoc
monitoring. All the equipment and
associated instrumentation shall be clearly labelled. The location of equipment installation should
be proposed by the ET Leader and agreed with the IC and EPD in consultation
with the IEC.
Noise measurements should not be made in the
presence of fog, rain, wind with a steady speed exceeding 5m/s or wind with
gusts exceeding 10m/s. The wind speed shall
be checked with a portable wind speed meter capable of measuring the wind speed
in m/s.
The ET shall carry out noise monitoring during the construction and
operational phases at 3 monitoring stations as shown in Table 4.1 and Drawing No. 24315/13/251. The status and
locations of NSRs may change after issuing this
EM&A Manual. In such cases, the ET
Leader should propose updated monitoring locations and seek approval from EPD.
Table 4.1 Noise monitoring locations
Monitoring ID |
Location |
Type of Monitoring
|
Monitoring
Parameters |
Supplementary
Information |
NM1 |
Wo Keng Shan Tsuen |
Construction
& Operation |
LAeq, 30mins |
LA10 and LA90 |
NM2 |
Lin Ma Hang |
Construction
& Operation |
LAeq, 30mins |
LA10 and LA90 |
NM3 |
Cheung
Shan Monastery |
Traffic
Noise |
LA10, 1hr |
LAeq and LA90 |
When alternative monitoring locations are
proposed, the monitoring locations should be chosen based on the following criteria:
· At locations close to the major site activities which are likely to have noise impacts;
· Close to the noise sensitive receivers;
· For monitoring locations in the vicinity of the sensitive receivers, care should be taken to avoid disturbance to the occupants during monitoring.
The monitoring station shall normally be at a
point 1m from the exterior of the sensitive receivers building facade and be at
a position 1.2m above the ground. If
there is problem with access to the normal monitoring position, an alternative
position may be chosen, and a correction to the measurements shall be
made. For reference, a correction of
+3dB(A) shall be made to the free field measurements. The ET Leader shall agree with the IEC on the
monitoring positions and the corrections adopted. Once the positions for the monitoring
stations are chosen, the baseline monitoring and the impact monitoring shall be
carried out at the same positions.
4.4 Baseline Monitoring
The ET shall carry out baseline noise monitoring
prior to the commencement of the operation of landfill. The continuous
baseline monitoring shall be carried out daily for a period of at least two
weeks in a sample period of 5 minutes or 30 minutes. A schedule on the
baseline monitoring shall be submitted to the IC and IEC for approval before
the monitoring starts.
In exceptional case, when insufficient baseline
monitoring data or questionable results are obtained, the ET Leader shall
liaise with the IC, IEC and EPD to agree on an appropriate set of data to be
used as a baseline reference and submit to ER for approval.
During normal construction working hour
(0700-1900 Monday to Saturday), monitoring of Leq30min noise levels
(as 6 consecutive Leq5min readings) shall be carried out at the
agreed monitoring locations once every week.
If a school exists near the construction
activity, noise monitoring shall be carried out at the monitoring stations for
the schools during the school examination periods. The ET Leader shall liaise with the school’s
personnel and the Examination Authority to ascertain the exact dates and times
of all examination periods during the course of the contract.
In case of non-compliance with the construction
noise criteria, more frequent monitoring as specified in the Event and Action
Plan shall be carried out. This
additional monitoring shall be continued until the recorded noise levels are
rectified or proved to be irrelevant to the construction activities.
A schedule on the compliance monitoring shall be
submitted to the IEC and IC for approval before the monitoring starts. Sample data sheet for construction noise
measurements is given in Appendix
C2.
During normal operational working hours,
monitoring of LAeq, 30min noise
levels (as six consecutive LAeq, 5min
readings) shall be carried out at the agreed monitoring locations once
every week in accordance with the methodology in the TM.
Other noise sources such as road traffic and
construction activities may make a significant contribution to the overall
noise environment. Therefore, the
results of noise monitoring activities shall take into account such influencing
factors, which may not be present during the baseline monitoring period.
In case of non-compliance with the operational
noise criteria, more frequent monitoring as specified in the Event and Action
Plan shall be carried out. This
additional monitoring shall be continued until the recorded noise levels are
rectified or proved to be irrelevant to the operational activities.
During normal operational working hours,
monitoring of LA10, 1hr noise levels shall be carried out at the
agreed monitoring locations once every week in accordance with the methodology
in the Section III of the “Calculation of Road Traffic Noise, 1998”.
The operational traffic noise monitoring will be
measured in term of the A-weighted L10 within the peak traffic hour for each designated noise
monitoring location. Measurements were
paused if noise detected from other non-traffic activities became dominant.
In case of non-compliance with the traffic noise
criteria, more frequent monitoring as specified in the Event and Action Plan
shall be carried out. This additional
monitoring shall be continued until the recorded noise levels are rectified or
proved to be irrelevant to the operational activities.
The Action and Limit levels for construction,
operational and traffic noise are defined in Tables 4.2-4.4. Should
non-compliance of the criteria occur, actions in accordance with the Event and
Action Plan in Tables 4.5-4.6 shall
be carried out.
Table 4.2 Action and limit
levels for construction noise
Time Period |
Action
Level |
Limit
Level |
0700 - 1900 hours on normal weekdays |
When one documented complaint is received |
75 dB(A)* |
If
works are to be carried out during restricted hours, the conditions stipulated
in the construction noise permit issued by the Noise Control Authority have to
be followed.
* Reduce to 70dB(A) for schools and 65dB(A) during
school examination periods.
Table 4.3 Action and
limit levels for operational noise
Time Period |
Action
Level |
Limit
Level |
0700-1900 on all days |
When one documented complaint is received |
60 dB(A) * |
1900-2300 on all days |
60 dB(A) * |
|
2300-0700 on all days |
50 dB(A) * |
* Only apply to operational noise without road traffic and construction
activities noise.
Table 4.4 Action and
limit levels for traffic noise
Time Period |
Action
Level |
Limit
Level |
Hotel, hostels & All domestic premises including
temporary housing accommodation |
When one documented complaint is received |
70 dB(A) |
Schools & Place of public Worship |
65 dB(A) |
Table 4.5 Event and
action plan for construction noise
Event |
ET |
IEC |
IC |
DBO Contractor |
Exceedance of Action
Level |
· Identify
source, investigate the causes of exceedance and propose
remedial measures; · Notify IEC and
DBO Contractor; · Report the
results of investigation to IEC, IC and DBO Contractor; · Discuss with
DBO Contractor and formulate remedial measures; · Increase
monitoring frequency to check mitigation effectiveness. |
· Review the
analysed results submitted by ET; · Review the
proposed remedial measures by DBO Contractor and advise IC accordingly; · Supervise the
implementation of remedial measures. |
· Confirm
receipt of notification of failure in writing; · Notify DBO
Contractor; · Require DBO
Contractor to propose remedial measures for the analysed noise problem; · Ensure
remedial measures are properly implemented. |
· Submit noise
mitigation proposals to IEC; · Implement
noise mitigation proposals. |
Exceedance of Limit
Level |
· Identify
source; · Inform IEC,
IC, EPD and DBO Contractor; · Repeat
measurements to confirm findings; · Increase
monitoring frequency; · Carry out
analysis of Contractor’s working procedures to determine possible mitigation
to be implemented; · Inform IEC, IC
and EPD the causes and actions taken for exceedances; · Assess
effectiveness of DBO Contractor’s remedial actions and keep IEC, EPD and IC
informed of the results; · If exceedance stops, cease additional monitoring. |
· Discuss
amongst IC, ET, and DBO Contractor on the potential remedial actions; · Review DBO
Contractors remedial actions whenever necessary to assure their effectiveness
and advise IC accordingly; · Supervise
implementation of remedial measures. |
· Confirm
receipt of notification of failure in writing; · Notify DBO
Contractor; · Require DBO
Contractor to propose remedial measures for the analysed noise problem; · Ensure
remedial measures properly implemented; · If exceedance continues, consider what portion of the work
is responsible and instruct DBO Contractor to stop that portion of works
until the exceedance is abated. |
· Take immediate
action to avoid further exceedance; · Submit
proposals for remedial actions to IEC
within 3 working days of notification; · Implement the
agreed proposals; · Resubmit proposals
if problem still not under control; · Stop the
relevant portion of works as determined by IC until the exceedance
is abated. |
Table 4.6 Event and
action plan for operational and traffic noise
Event |
ET |
IEC |
IC |
DBO Contractor |
Exceedance of Action
Level |
· Notify IEC and
DBO Contractor · Carry out
investigation · Report the
results of investigation to IEC and the DBO Contractor · Discuss with
the DBO Contractor and formulate remedial measures · Increase monitoring
frequency to check mitigation measures |
· Review with
analysed results submitted by ET · Review the
proposed remedial measures by DBO Contractor and advise IC accordingly · Supervise the
implementation of remedial measures |
· Confirm
receipt of notification of exceedance in writing · Notify DBO
Contractor · Require DBO
Contractor to propose remedial measures for the analysed noise problem · Ensure
remedial measures are properly implemented |
· Submit noise
mitigation proposals to IEC · Implement
noise mitigation proposals |
Exceedance of Limit
Level |
· Identify
source · Notify IEC,
IC, EPD and DBO Contractor · Repeat
measurement to confirm findings · Increase
monitoring frequency · Carry out
analysis of DBO Contractor’s working procedures to determine possible mitigation
to be implemented · Inform IEC,
IC, and EPD the causes and actions taken for the exceedances · Assess
effectiveness of DBO Contractor’s remedial actions and keep IEC, EPD and IC
informed of the results · If exceedance stops, cease additional monitoring |
· Discuss
amongst IC, ET Leader and DBO Contractor on the potential remedial actions. · Review DBO
Contractor’s remedial actions whenever necessary to assure their
effectiveness and advise IC accordingly · Supervise the
implementation of remedial measures |
· Confirm
receipt of notification of exceedance in writing · Notify DBO
Contractor · Require DBO
Contractor to propose remedial measures for the analysed noise problem · Ensure
remedial measures are properly implemented · If exceedance continues, consider what activity of the work
is responsible and instruct DBO Contractor to stop that activity of work
until the exceedance is abated |
· Take immediate
action to avoid further exceedance · Submit
proposals for remedial actions to IEC within 3 working days of notification · Implement the
agreed proposals · Resubmit
proposals if problem still not under control · Stop the
relevant activity of works as determined by the IC until the exceedance is abated |
The DBO Contractor shall
be responsible for implementation of the noise control and mitigation measures
during operational phase, which shall include, but not limited to, the
following:
· Quiet equipment and construction method should be employed;
· Only well-maintained plant shall be operated on site and plant shall be serviced regularly during the construction work;
· Machines and plant that may be in intermittent use (such as breakers) shall be shut down between work periods or should be throttled down to a minimum;
· Mobile plant shall be sited as far away from NSRs as possible;
· Material stockpiles and other structures shall be effectively utilised, where practicable, to screen noise from on-site construction activities;
· Silencers or mufflers on construction equipment should be properly fitted and maintained during the construction works.
Potential water pollution sources arising from construction activities include sources mainly from land-based activities, such as construction site runoff; sewage effluent due to workforce on site; accidental spillage of chemical; drainage diversion; and groundwater seepage.
Potential water pollution sources arising from operational include sources mainly from land-based activities, such as seepage of leachate, accidental Leakage of leachate and erosion.
The EIA Report has assessed the water quality impacts caused
by the construction and operation of NENT Landfill Extension. Mitigation measures have been recommended in
the EIA to ensure compliance with the relevant legislative requirements. These mitigation measures are summarised in
following sections. An implementation schedule of the recommended mitigation
measures is presented in Appendix
C3.
5.2.1 Construction Phase
5.2.1.1 Construction Site Runoff
In accordance with the Practice Note for Professional Persons on Construction Site Drainage, Environmental Protection Department, 1994 (ProPECC PN 1/94), and DSD Technical Circular TC14/2000, construction phase precautionary measures as presented in Appendix C3 shall be implemented where necessary. By adopting the above precautionary measures with Best Management Practices (BMPs) it is anticipated that the impacts of runoff from the construction site will be reduced to satisfactory levels before discharges.
The construction runoff discharged from the landfill site shall fully comply with the standards stated in Section 5.2 of the EIA report, otherwise the discharge shall be collected and conveyed to the on-site leachate treatment plant.
5.2.1.2 Sewage from Workforce
Portable chemical toilets and sewage holding tanks will be provided for handling the sewage generated by the workforce. A licensed contractor will be employed to provide appropriate and adequate portable toilets and be responsible for appropriate disposal and maintenance.
5.2.1.3 Accidental Spillage of Chemical
Any service workshops and maintenance facilities will be located within a bunding area, and sumps and oil interceptors will be provided. Maintenance of equipment involving activities with potential for leakage and spillage will only be undertaken within the areas appropriately equipped to control these discharges.
5.2.2 Operational Phase
5.2.2.1 Contingency Plan on Accidental Leakage of Leachate
Existing
Contingency Plan for Groundwater Contamination
The existing Contingency Plan is comprehensive and well-developed and will be used as basis for developing the Contingency Plan for the extension site. The parameters to be monitored include groundwater level and groundwater quality. The objective of the monitoring programme is to ensure that the trigger levels below are not exceeded.
Ammonia Nitrogen : 5 mg/L
COD : 30 mg/L
In the event that the above trigger levels are exceeded, the DBO Contractor will implement a Corrective Action Programme, which shall include:
· groundwater interception and diversion; and
· groundwater extraction (by active pumping of leachate from leachate and groundwater collection layers) and treatment prior to discharge.
Proposed Modifications to Contingency Plan for Groundwater
Contamination
Potential actions to be taken in case of identification of groundwater contamination should also include:
· Installation of additional ground-water monitoring well;
· Increased frequency of ground-water quality testing;
· Installation of ground-water extraction wells to remove contaminated groundwater for treatment;
· Installation of subsurface barriers, such as bentonite;
· Detailed investigation of the potential impact to be performed within six months of the first detection of the justified impact.
Contingency Plan for Surface Water Contamination
Surface water monitoring will be conducted to keep the ammonia-nitrogen and COD below the following trigger levels:
Ammonia Nitrogen : 0.5 mg/L
COD : 30 mg/L
Suspended Solid : 20 mg/L.
In the event that any one of the above parameters was exceeded, the landfill operation should implement a Corrective Action Programme. The key elements shall include:
· Surface water interception and temporary storage of the contaminated surface water;
· Installation of surface barriers, such as sand bund along the surface water channel / site boundary to avoid overflow off-site.
· Active pumping of the contaminated surface water to the leachate lagoons / leachate recirculation system / on-site leachate treatment plant;
· Additional monitoring locations will be selected to determine the pollution source;
· Installation of surface barriers, such as intercepting bund to separate the active and inactive tipping area.
· Change of working methods to prevent surface water contamination; and
· Implementation of diversionary works.
5.2.2.2 Erosion Control
The DBO Contractor shall devise a soil erosion control plan during the detailed design stage so as to define the site-specific measures and procedures (including the specific operation plan, implementation frequency, monitoring procedures, maintenance schedules, etc). Such requirement shall be specified in contract documents. Appendix C3 summarizes the most popular erosion control methods for reference.
5.2.2.3 Surface Water Drainage System
A temporary surface water drainage system to manage runoff will be adopted during construction and operation. It consists of perimeter channels around the site perimeter. It will collect surface water from higher elevations to lower elevations and ultimately to the discharge point. Details of surface water drainage system are included in Appendix C3.
The surface flow discharge from the landfill site shall fully comply with the standards stated in Section 5.2 of the EIA report, otherwise the contaminated surface flow shall be collected and disposed of to the on-site leachate treatment plant.
5.3 Leachate Monitoring
The DBO Contractor shall develop and operate a programme of monitoring which shall record the progressive generation of leachate at the NENT Landfill Extension in accordance with the following objectives:
· To determine the level of leachate within the landfill;
· To determine the quality of leachate arising from the landfill;
· To determine the quantity of leachate arising from the landfill and being treated;
· To monitor the quantity and quality of treated leachate from the leachate treatment works before discharging into leachate pipeline connecting to Shek Wu Hui Sewage Treatment Plant;
· To ascertain the landfill characteristics and effectiveness of the leachate treatment works.
The leachate monitoring programme shall commence at the start of landfill operations and continue until the issue of the Aftercare Certificate. The programme shall be developed with in-built flexibility to allow for modification during the development of the leachate treatment works and any modifications to the monitoring of the quality and quantity of leachate generated.
5.3.1 Equipment
Routine sampling and on-site measurements of leachate quality shall be carried out with appropriate equipment which include:
· Portable thermometer, pH and electrical conductivity (EC) meter
· Sample bottle of glass or PET of volume not less than 1 litre
· Flowmeters
At the leachate collection point, the submersible pump shall be used to discharge leachate flow from the leachate removal chamber. Level sensors shall be incorporated into the side slope riser pipe for pump control and measurement of leachate level. In addition, a dipstick and measuring tape shall be used to determine (in-situ) normal leachate levels if the level sensor is not operative.
5.3.2 Calibration and Maintenance
The DBO Contractor shall ensure that all equipment are calibrated and maintained according to manufacturer’s instructions. Routine maintenance shall be carried out in strict accordance with the manufacturer’s requirements. Where calibration intervals are not specified by the equipment manufacturer, the length of time between calibration periods shall not be greater than 6 months.
An inspection procedure shall be established to ensure that the frequency of maintenance is regularised for each equipment. Results from the monitoring programme shall be used to assist in the ongoing operation of the leachate treatment works to ensure that the facility is being operated under the optimum conditions, and that the leachate discharge complies with the trigger levels specified in Section 5.3.8.
5.3.3 Procedures
The DBO Contractor shall monitor leachate levels within the landfill using calibrated submersible level sensors incorporated into the side slope riser pipe.
Quantity of raw leachate shall be monitored using in-line flow meters installed in the pipe. The flow meters shall be designed and constructed to determine the volume and rate of leachate leaving the landfill site to an accuracy and precision of within +/- 1%.
At the same locations, the leachate shall also be monitored periodically to assess leachate quality produced within operational areas and after treatment. This shall be achieved using in-line sampling valves/taps. The design and construction of these valves/taps shall be such that samples of leachate of between 1 and 25 litres can be readily and easily obtained without sampling rates being too high resulting in unacceptably-high levels of splashing or too low making the duration of sampling unacceptably long.
The DBO Contractor shall use the groundwater drainage layer to detect any leachate escaping through the liner system. The detection system shall involve daily sampling at the groundwater discharge point (shown as Leachate Leakage Detector) and the groundwater monitoring boreholes.
All leachate samples shall be collected and transported to a HOKLAS accredited laboratory as soon after sampling as possible. Appropriate pre-treatment of samples shall be prepared in respect of the analytical parameters, with due regard to its holding times.
Leachate quality shall be monitored as a feedback to the operation for optimisation of the leachate treatment works and to establish its trend over the life of the landfill. The programmes shall generate data to support the establishment of a procedure for the necessary treatment and safe disposal of effluent from NENT Landfill Extension.
The following parameters shall be measured in accordance with the standards contained within the Specification:
Table 5.1
Programme A |
Programme B |
||||
Parameters |
Detection
Limit |
Frequency |
Parameters |
Detection
Limit |
Frequency |
Temperature * |
0.1°C |
Weekly basis initially and then
monthly when settled values are obtained for the first 3 years of NENT
Landfill Extension operation |
Mg |
50 mg/L |
Monthly basis initially and then 3
monthly Intervals when settled values are obtained for the first 3 years of
NENT Landfill Extension operation |
pH * |
0.1 |
Ca |
50 mg/L |
||
Electrical conductivity * |
1 mS/cm |
K |
50 mg/L |
||
COD |
10 mg/L |
Fe |
50 mg/L |
||
BOD5 |
3 mg/L |
Ni |
1 mg/L |
||
TOC |
1 mg/L |
Zn |
10 mg/L |
||
SS |
0.1 mg/L |
Mn |
1 mg/L |
||
Ammonia-nitrogen |
0.2 mg/L |
Cu |
1 mg/L |
||
Nitrate |
0.5 mg/L |
Pb |
1 mg/L |
||
Nitrite |
0.5 mg/L |
Cd |
0.2 mg/L |
||
Total Nitrogen |
0.4 mg/L |
|
|
||
Sulphate |
5 mg/L |
|
|
||
Phosphate |
0.01 mg/L |
|
|
||
Chloride |
0.5 mg/L |
|
|
||
Sodium |
50 mg/L |
|
|
||
Alkalinity |
1 mg/L |
|
|
||
Volatile fatty Acids |
2 mg/L |
|
|
*
On-site measurement
Table 52
Parameters |
Detection Limit |
Parameters |
Detection Limit |
Frequency |
Temperature |
0.1°C |
Phosphate |
0.01 mg/L |
Quarterly Basis after the first 3
years of NENT Landfill Extension operation |
pH |
0.1 |
Chloride |
0.5 mg/L |
|
COD |
10 mg/L |
Sodium |
50 mg/L |
|
BOD5 |
3 mg/L |
Alkalinity |
1 mg/L |
|
SS |
0.1 mg/L |
Fe |
50 mg/L |
|
Ammonia-nitrogen |
0.2 mg/L |
Zn |
10 mg/L |
|
Nitrate |
0.5 mg/L |
Cu |
1 mg/L |
|
Total Nitrogen |
0.4 mg/L |
Cd |
0.2 mg/L |
|
Sulphate |
5 mg/L |
|
|
|
Suite 1 (Programme A and Programme B) shall be used to
establish the quality of leachate from each
collection point (i.e., before and after treatment) for the first 3 years of
NENT Landfill Extension operation, and
For leachate leakage detection, the DBO Contractor shall analyse the samples taken at the groundwater discharge point for ammonia-nitrogen, pH and conductivity. If necessary, COD shall be tested when high ammonia-nitrogen is detected at the groundwater discharge point. Samples shall be stored and preserved according to the guidelines of the approved accredited laboratory.
5.3.5 Frequency and Locations of Sampling
The DBO Contractor shall take raw leachate samples and treated leachate samples. The frequency and sampling locations summarized in Table 5.3.
Table 5.3 Frequency and
Locations of Sampling
Program |
Frequency |
Location |
|
Weekly
intervals initially and then monthly when settled values are obtained |
At new leachate
Collection Points (i.e prior to discharging points
at raw leachate lagoon for raw leachate
monitoring and final effluent holding lagoon for partially treated leachate monitoring) |
|
At monthly
intervals and then three monthly intervals when settled values are obtained
for the first three years of NENT Landfill Extension operation |
|
|
At
quarterly intervals after |
The DBO Contractor shall monitor levels of leachate continuously using calibrated submersible pressure transducers via data retrieving equipment. Daily records of leachate production shall be maintained via data logging flow meters for all abstraction of liquid from the site and leachate quantities leaving the site.
The DBO Contractor shall determine the locations of leachate monitoring points and submit the proposed plan to the Independent Consultant for approval.
5.3.6 Results
All sample containers shall be clearly marked, and identified with relevant sampling information. In addition, all monitoring results and observations made at time of sampling shall be recorded in a field data sheet specifically allocated to that sampling task. The following information shall be recorded on each sampling visit:
· Sampling point;
· Data and time of sample collection;
· Name of technician carrying out the sampling;
· Weather conditions and ambient temperature;
· General appearance, condition and temperature of the water body;
· Sampling device and method used;
· Sample preservation used;
· Storage requirements adopted;
· Space for listing analytical determinations.
5.3.7 Leachate Leakage Detection
Facilities to detect leakage within a 24-hr period shall be placed in the manner and positions specified and be monitored daily for the presence of leachate or contaminated water.
The DBO Contractor shall operate a programme of monitoring with the following objectives:
· Determine the level of leachate within the landfill;
· Determine the quality of leachate from the landfill;
· Determine the quantity of leachate from the landfill.
The DBO Contractor shall monitor the levels of leachate continuously at the leachate collection point through the use of calibrated submersible level sensors via data retrieving equipment. The level of leachate at any point within the landfill shall not exceed 1m height above the top of the primary barrier of the landfill liner system.
The standards for discharge of treated leachate from the leachate treatment works into the pipeline leading into Shek Wu Hui Sewage Treatment Works (SWHSTW) are given in Table 1 of the Water Pollution Control Ordinance (WPCO) Technical Memorandum – Standards for Effluent Discharged into Drainage and Sewerage System, Inland and Coastal Waters prepared by the EPD, with the exception for the following discharge limits.
Total Nitrogen : |
200 mg/L |
COD : |
2000 mg/L |
BOD : |
400 mg/L |
Ammonia-nitrogen : |
5 mg/L |
SS : |
400 mg/L |
|
|
Treated leachate shall be discharged to the leachate pipeline leading to the SWHSTW. The leachate generated by the NENT Landfill Extension has been estimated. Under normal meteorological condition (i.e. with an average annual rainfall of 1,875 mm, data taken from Ta Kwu Ling Station from 1999 to 2005), the peak leachate flow rate from restored NENT Landfill and NENT Landfill Extension (under fully operation in Year 10) is estimated to be (265+860 =) 1,105 m3 /day in wet season, which is within the design capacity of the existing leachate treatment plant (i.e. 1,200 m3 /day). Nevertheless, daily records shall also be made for the quantity of leachate production.
5.3.9 Corrective Action
If the trigger levels in Section 5.3.8 are exceeded, the DBO Contractor shall implement a Corrective Action Programme, which shall include:
· Leachate extraction;
· Phased development and closure to minimise the active area footprint;
· Temporary geosynthetic covers to minimize infiltration in active cells;
· Run-on and runoff control systems for active and closed areas;
· Low permeability final cover system to minimise infiltration during post-closure;
In event that the DBO Contractor detects leachate leakage (i.e. the trigger level is exceeded at the groundwater discharge point), the liquid shall be treated at the leachate treatment plant prior to discharge to the leachate pipeline leading to SWHSTW.
Groundwater Level
5.4.1 Introduction
Groundwater levels shall be monitored over the working life of the site to determine the following information:
· Natural seasonal variation in groundwater levels;
· Effects of any ground water abstraction;
· Identification of hydraulic gradients;
· Variation caused by the construction, operation or aftercare.
5.4.2 Equipment
A portable dip meter, not affected by condensation, shall be used to measure water depth and checked before use. The dip meter shall comprise a graduated tape and sonic indicator of water level.
5.4.3 Procedures
Water level measurements shall be carried out prior to any purging or sampling from monitoring holes.
The DBO Contractor shall take groundwater level measurements relative to a permanent fixed datum at a measured elevation at each location, situated and marked on the monitoring borehole casing or cover. Recorded levels shall be expressed as metres relative to Principal Datum, and the levels checked 3 times prior to recording the measurements.
5.4.4 Frequency and Locations of Sampling
All manual groundwater level measurements shall be carried out at least once a month.
In the event that automatic measuring equipment is installed, the associated data loggers shall be interrogated / downloaded at least on a monthly basis. The automatic monitoring equipment shall be calibrated monthly and periodic manual water level measurements shall be carried out to corroborate the measurements.
Monthly groundwater monitoring shall be carried out at specified points ED1-ED35 in accordance with Drawing No. 24315/13/504 unless otherwise approved by the IC.
5.4.5 Results
All manual water level measurements shall be recorded relative to both monitoring borehole datum and Principal Datum. All automatic monitoring equipment shall be in a form that can be input to computer and displayed in numerical or graphical form. Results shall include site name; unique monitoring borehole reference or location code; date and water level in metres below monitoring borehole datum and to Principal Datum.
Groundwater Quality
5.4.6 Equipment
The criteria for selection of appropriate equipment shall depend upon the purpose of the sampling exercise, the site characterisation and the parameters that are to be analysed. This shall be assessed using the following criteria:
· Required sampling accuracy and precision
· Sampling frequency;
· Sampler construction material;
· Required head;
· Required discharge rate;
· Reliability and ease of maintenance, including availability of spares.
Teflon and/or stainless steel samplers (e.g. bailers) shall be used to sample groundwater.
Where sampling relies on the sample being pumped to the surface via tubing, the tubing used shall be Teflon, Teflon lined, or polypropylene. Bladder pumps shall be used to purge and to sample. Groundwater may be pumped from depths in excess of 100m below ground level, due to the depth to groundwater and the topographic level of the site.
5.4.7 Calibration and maintenance
Before each purging process, field meters shall be calibrated according to manufacturer specifications and the calibration results recorded in a calibration log file. All sampling equipment shall be thoroughly decontaminated as per standard sampling protocol prior to use.
5.4.8 Procedures
The DBO Contractor shall purge a monitoring borehole before a sample is taken in order that representative groundwater is sampled. This process shall be combined with field monitoring of determinants such as electrical conductivity, pH and temperature, so that stable sampling conditions can be achieved. If the water is contaminated it shall be contained and treated as leachate, otherwise abstracted groundwater shall be discharged to the surface water drainage system.
Samples shall be stored and preserved according to the guideline of approved accredited laboratory. Representative groundwater sample shall be collected, in approved receptacles as follows:
· Sampling containers shall be pre-rinsed with the water being collected, except in the case where specific determinations require preservatives in pre-prepared bottles;
· Glass containers shall be used for receipt of samples for organic analysis;
· Polyethylene containers shall be used for other determinants, except trace metals determinants such as mercury;
· Water shall be poured into sampling bottles carefully until filled completely, unless a specific volume is required by the analytical laboratory;
· A minimum of one litre sample shall be taken, unless otherwise specified;
· On-site measurement of EC, pH and temperature shall be carried out;
· On completion of sampling, portable equipment shall be removed from the borehole, and cleaned prior to use at next installation.
All sample bottles shall be labelled, samples shall be kept at for degrees centigrade and sent to the laboratory within specified holding times for the analytical methods. Samples shall be sent to the laboratory with appropriate chain-of-custody documentation.
Analysis of samples shall be carried out in accordance with methods described in American Society for Testing and Material (ASTM) or American Public Health Association (APHA) – American Water Works Association (AWWA) – Water Pollution Control Federation (WPCF).
5.4.9 Results
All sample containers shall be clearly marked to show the site name, location and date of sample collection. All results shall be presented as following:
· Site name;
· Unique sampling location reference;
· Time and date of the sampling;
· Name of the sampling technician;
· Weather conditions and air temperature;
· Appearance, condition and temperature of the water body;
· Sampling device used;
· On-site measurements of EC, pH and temperature;
· Volume of water purged prior to sampling;
· Physical description of the sample.
5.4.10 Analysis Parameters
The DBO Contractor shall measure the parameters according to the Table 5.4 in monthly basis. In the event of contamination being detected in the monthly monitoring programme, additional groundwater monitoring shall be carried out in weekly basis.
Table 5.4 Groundwater Monitoring
Parameters |
Detection
Limit |
Normal
Frequency |
Additional
Frequency |
Temperature |
0.1°C |
Monthly basis |
|
pH |
0.1 |
Monthly basis |
Weekly Basis |
Electrical conductivity |
1 mS/cm |
Monthly basis |
Weekly Basis |
COD |
10 mg/L |
Monthly basis |
Weekly Basis |
BOD5 |
3 mg/L |
Monthly basis |
Weekly Basis |
SS |
0.1 mg/L |
Monthly basis |
Weekly Basis |
Ammonia-nitrogen |
0.2 mg/L |
Monthly basis |
Weekly Basis |
Nitrate |
0.5 mg/L |
Monthly basis |
- |
TKN |
0.4 mg/L |
Monthly basis |
- |
Sulphate |
5 mg/L |
Monthly basis |
- |
Sulphite |
2 mg/L |
Monthly basis |
- |
Phosphate |
0.01 mg/L |
Monthly basis |
- |
Chloride |
0.5 mg/L |
- |
Weekly Basis |
Iron |
50 mg/L |
- |
Weekly Basis |
Zinc |
10 mg/L |
- |
Weekly Basis |
Coliform Count |
1 cfu/
100mL |
Monthly basis |
Weekly Basis |
5.4.11 Trigger Levels
The DBO Contractor shall propose a permanent monitoring network at the site to include the following:
· Detailed information on the hydrogeological regime;
· Details on seasonal groundwater level fluctuations and short-term variations in certain areas;
· Detailed baseline groundwater quality information;
· Detailed pumping test data for areas down gradient of the site where contaminants are likely to migrate.
The DBO Contractor shall monitor groundwater around the site to ensure that the following trigger levels are not exceeded Table 5.1.
5.4.12 Corrective Action
In the event that the above trigger levels are exceeded, the DBO Contractor shall implement a Corrective Action Programme, which shall include:
· Groundwater extraction and, if necessary, treatment prior to discharge;
· Groundwater interception and diversion.
5.5.1 Introduction
The DBO
Contractor shall carry out surface water monitoring from the commencement of
the works until the issue of the Aftercare Certificate in accordance with the
following objectives:
· To assess the performance of the
registered design, where: surface water leaves the site and/or the landfill
boundary; surface water leaves an operational area; and surface water leaves
areas of potential contamination e.g., waste reception area, vehicle and wheel
washing, haul route, vehicle servicing, etc.
· To ensure no long-term
deterioration in surface water quality adjacent to the site;
· To provide data for the design
and to monitor the effectiveness of any remedial measures which may be
necessary in the event of excessive leachate
migration or liner failure.
Surface
water monitoring stations shall be established in and around the site as part
of the monitoring programme.
5.5.2
Equipment
For monitoring surface water quality, the
DBO Contractor shall use the following sampling and measuring equipment:
· Varying water sample containers,
as appropriate to the type of analysis being determined, fabricated from
polyethylene, polypropylene, polycarbonate, aluminium, stainless steel or glass
o
Glass containers for organic constituents, but where major constituents
of glass are to be analysed (e.g. sodium, potassium, boron, silicon and trace
metallic impurities), glass containers shall not be used.
o
Polyethylene containers shall not be used for trace metallic impurities
such as mercury.
· Silicon sieve/disposable filters
for removal of suspended solids
· Thermometer with a range of 0-50°C
· Digital pH meter
· Electrical conductivity meter
A clamp, pole or string shall be attached to the bottle if the water poses
a threat to the sampling technician or if direct contact is likely to be made
with skin. However, in all situations, gloves shall be worn as a matter of
routine when sampling potentially-contaminated water.
The following equipment or the approved equivalents shall be provided
for monitoring flow:
· IS32 flow monitor complete with Druck transducer capable of measuring parameters of depth
and velocity at specified intervals, with trip mode built-in.
· Velocity calibrator – Montec 3013 portable Doppler measurement for in-situ
calibrations of velocity. A 1.25m logging wand shall be used for recording
in-situ measurements.
· Monitoring software –
specifically designed for use with IS32 and Montec
3013, to produce depth, velocity and discharge graphs, as well as tabulated
data.
5.5.3
Calibration and Maintenance
Clean,
pre-conditioned/washed sample containers shall be used during the sampling
programme. Sample containers shall be used only once with the exception of
glass containers appropriately decontaminated at the analytical laboratory
prior to use. All sampling equipment including open-mouthed collection vessels
(buckets and cans) and sieves shall be decontaminated prior to use between
sample points to prevent cross contamination. Decontamination procedures
involve the use of laboratory grade detergent and rinsing in de-ionized water.
Sample bottles that contain chemical preservatives shall not be rinsed or
cleansed in any way.
Thermometers
shall be rinsed with de-ionized water and then wiped with disposable towels immediately
after use before being replaced in the carrying case.
All flow measuring equipment shall be calibrated according to the
manufacturer’s specifications.
5.5.4
Procedures
The DBO
Contractor shall undertake sampling of surface water quality with reference to
the following documents:
· British Standard Institution
(BSI) BS6068: 1981 Water Quality Sampling Section 6.1. Guidance on the Design
of Sampling Programmes
· International Standard
Organisation (SO) ISO 5667-6 1990 Guidance on Sampling of Rivers and Streams
· BSI, BS 6068 1983 Water Quality
Section 6.2 Guidance on Sampling Techniques. Health and Safety Executive
· BSI, BS 6068: 1986 Water Quality
Section 6.3 Guidance on the Preservation and Handling of Samples (International
Standards Organisation ISO 5667/3 – 1985 Water quality – Sampling – Part 3:
Guidance on the Preservation and Handling of Samples).
Before sampling, the
flow rate of the stream/river shall be determined and the water and air
temperature, pH and electrical conductivity shall be measured and recorded.
All the precautions
outlined in the Specification for avoiding contamination during sampling shall
be taken, for example, pre-rinsing sampling containers (excluding those
containers which are preserved by certain type of chemicals) with the surface
water to be collected. In addition, appropriate health and safety precautions
including the wearing of protective waterproof gloves shall be followed.
In general, samples
shall be collected from within 500mm of the water surface. Samples shall be
collected within an open mouthed vessel with the lip pointing upstream. The
sample shall be filtered as appropriate. Alternatively the sample shall be
collected directly into the sample container. Sampling of the surface film
layer shall be avoided during the sampling programme.
During sample
collection, care shall be taken so that air is not introduced into the samples
thereby altering the relative compositions of the determinants. Once the sample
bottle is filled to the top with no remaining air space the lid shall be
securely screwed on. Where samples are to be preserved with acid or alkalis
prior to transport to the laboratory, the sample bottles shall be filled to the
level specified by the analytical laboratory.
Samples shall be
transported to the laboratory for analysis as soon as possible after the sample
is collected, since the longevity of some of the sample determinants is
limited. All samples shall be stored at 4°C and
transported to the laboratory within 48 hours from sampling.
Analyses shall be carried out in accordance with methods described in
ASTM or APHA – AWWA – WPCF Standard.
Flow measurements shall also be taken continuously using automatic
logging equipment.
The DBO Contractor shall measure the all parameters according to Table 5.5 in monthly basis. In the event of contamination being detected in the monthly monitoring programme, additional surface water monitoring shall be carried out in weekly basis.
Table 5.5 Surface Water Monitoring
Parameters |
Detection Limit |
Normal Frequency |
Additional Frequency |
pH |
0.1 |
Monthly
basis |
Weekly Basis |
Electrical conductivity |
1 mS/cm |
Monthly basis |
Weekly Basis |
Alkalinity |
1
mg/L |
Monthly basis |
- |
COD |
10
mg/L |
Monthly basis |
Weekly Basis |
BOD5 |
3
mg/L |
Monthly basis |
Weekly Basis |
TOC |
1
mg/L |
Monthly basis |
Weekly Basis |
SS |
0.1
mg/L |
Monthly basis |
Weekly Basis |
Ammonia-nitrogen |
0.2
mg/L |
Monthly basis |
Weekly Basis |
TKN |
0.4
mg/L |
Monthly basis |
- |
Nitrate |
0.5
mg/L |
Monthly basis |
- |
Sulphate |
5
mg/L |
Monthly basis |
- |
Sulphite |
2
mg/L |
Monthly basis |
- |
Phosphate |
0.01
mg/L |
Monthly basis |
- |
Chloride |
0.5
mg/L |
Monthly basis |
- |
Sodium |
50 mg/L |
Monthly basis |
- |
Mg |
50 mg/L |
Monthly basis |
- |
Ca |
50 mg/L |
Monthly basis |
- |
K |
50 mg/L |
Monthly basis |
- |
Fe |
50 mg/L |
Monthly basis |
Weekly Basis |
Ni |
1 mg/L |
Monthly basis |
- |
Zn |
10 mg/L |
Monthly basis |
Weekly Basis |
Mn |
1 mg/L |
Monthly basis |
- |
Cu |
1 mg/L |
Monthly basis |
- |
Pb |
1 mg/L |
Monthly basis |
- |
Cd |
0.2
mg/L |
Monthly basis |
- |
Coliform Count |
1 cfu/ 100mL |
Monthly basis |
Weekly Basis |
Oil and Gease |
5
mg/L |
Monthly basis |
- |
Surface water flow shall be monitored continuously using automatic data
logging equipment. Following periods of heavy rainfall, flow shall be monitored
weekly and more frequently to determine peak discharge rates.
5.5.6
Locations of Sampling
Monthly surface water
monitoring shall be carried out at specified points WM1 (Upstream of Lin Ma
Hang) and WM2 (
5.5.7
Results
Upon completion of each sampling exercise,
the sample containers shall be clearly labelled with site name; sampling
location reference; date and time of collection and sample number.
In addition, the
sampling technician shall record any abnormality which may affect water quality
in their record notebooks. The sampling
record shall include the following details:
· Sampling site and sampling point;
· Date and time of collection;
· Name of sampling technician;
· Weather conditions and air
temperature;
· Appearance, condition and
temperature of the water body;
· Sampling method and sampling
device used;
· Sample preservation;
· Storage requirements;
· List of parameters (with space
for the analytical results).
The DBO
Contractor shall conduct the surface water monitoring programme in order to
keep ammonia-nitrogen and COD below the following trigger levels:
Ammonia-nitrogen
: 0.5mg/L
COD : 30 mg/L
In addition, suspended solids
concentrations for surface waters leaving the site shall not exceed
20mg/L.
5.5.9
Corrective Action
In the event that these trigger
levels are exceeded, the DBO Contractor shall implement a Corrective Action
Programme, which shall include:
· Sampling upstream into landfill
to trace the source;
· Surface water interception and
treatment prior to discharge;
· Changes to working methods to
prevent surface water contamination;
· Diversionary works.
Where
analytical results indicate the presence of contamination, additional
monitoring locations shall be selected to determine the pollution source. The
DBO Contractor shall implement procedures in accordance with the corrective
action plan to mitigate any contamination sources identified, or discharge the
surface water to the leachate treatment plant.
The Action and Limit levels for surface and ground water quality are defined in Table 5.6 and Table 5.7. Should non-compliance of the criteria occur, action in accordance with the Action Plan in Table 5.8 shall be carried out.
Table 5.6 Action and Limit Levels for Surface Water
Quality
Parameters |
Action |
Limit |
|
Construction |
DO in mg L-1 (Surface, Middle & Bottom) |
Surface and Middle 5 percentile of baseline data for surface and middle layer Bottom 5 percentile of baseline data for bottom layer |
Surface and Middle 4 mg L-1 or 1%-ile of baseline data for surface and middle layer Bottom 2 mg L-1 or 1%-ile of baseline data for bottom
layer |
pH (depth averaged), Turbidity in
NTU (depth-averaged), SS in mg L-1 (depth-averaged) |
95 percentile of baseline data or 120% of
upstream control station's pH, Turbidity, SS at the same tide of the same day |
99 percentile of baseline or 130% of upstream
control station's pH, Turbidity, SS at the same tide of the same day |
|
Operation |
COD, Ammonia-nitrogen |
--- |
Ammonia-nitrogen:
0.5mg/L COD: 30
mg/L |
SS in mg L-1 |
--- |
20mg/L |
Notes: 1. "depth-averaged" is calculated by
taking the arithmetic means of reading of all three depths.
2. For DO, non-compliance of the water quality
limits occurs when monitoring result is lower than the limits.
3. For turbidity, SS, Ammonia-nitrogen, COD, non-compliance
of the water quality limits occurs when monitoring result is higher than the
limits.
4. For pH, non-compliance of the water quality
limits occurs when monitoring result is outside the specified range.
5. All the figures given in the table are used
for reference only and the EPD may amend the figures whenever it is considered
as necessary.
Table 5.8 Action and Limit Levels for Ground Water
Quality
Parameters |
Action |
Limit |
Remark |
COD, Ammonia-nitrogen |
--- |
COD: 30 mg/L Ammonia-nitrogen: 5mg/L |
For
COD, Ammonia-nitrogen, non-compliance of the water quality limits occurs when
monitoring result is higher than the limits.
|
Table 5.9 Event and Action Plan for Water Quality
Event |
ET |
IEC |
IC |
DBO Contractor |
Action
level being exceeded by one sampling day |
Identify
source(s) of impact; Inform IEC, DBO contractor; Check monitoring data, all
plant, equipment and DBO Contractor's working methods. Repeat measurement on next day
of exceedance. |
Check monitoring data and DBO
Contractor’s working methods. |
Confirm receipt of
notification of non-compliance in writing; Notify Contractor. |
Rectify unacceptable practice; Amend working methods if
appropriate. |
Action level being exceeded by
two or more consecutive sampling days |
Identify source(s) of impact; Inform IEC, DBO contractor; Check monitoring data, all
plant, equipment and Contractor's working methods; Discuss mitigation measures with IEC, IC and Contractor; Ensure mitigation measures are
implemented; Increase the monitoring
frequency to daily until no exceedance of Action
level; Repeat measurement on next day
of exceedance. |
Check monitoring data and DBO
Contractor’s working method; Discuss with ET and DBO Contractor
on possible remedial actions; Review the proposed mitigation
measures; Supervise the implementation
of mitigation measures. |
Discuss with IEC on the
proposed mitigation measures; Ensure mitigation measures are
properly implemented; Assess the effectiveness of
the implemented mitigation measures. |
Rectify unacceptable practice; Check all plant and equipment
and consider changes of working methods; Submit proposal of additional
mitigation measures to IEC within 3 working days of notification; Implement the agreed
mitigation measures. |
Limit level being exceeded by one sampling day |
Identify
source(s) of impact; Inform IEC, IC and DBO
contractor; Check
monitoring data, all plant, equipment and Contractor's working methods; Discuss
mitigation measures with IEC, IC and Contractor; Ensure
mitigation measures are implemented; Increase the monitoring frequency to
daily until no exceedance of Limit level; |
Check monitoring data
submitted by ET and Contractor’s working method; Discuss with ET and Contractor
on possible remedial actions; Review the proposed mitigation
measures submitted by Contractor and advise the IC accordingly. |
Confirm receipt of
notification of failure in writing; Discuss with IEC, ET and
Contractor on the proposed mitigation measures; Request Contractor to review
the working methods. |
Take immediate corrective
actions to avoid further exceedance; Submit proposal of mitigation
measures to IEC within 3 working days; Implement the agreed
mitigation measures; Submit further mitigation
measures if problem still not under control; |
Limit
level being exceeded by two or more consecutive sampling days |
Identify source(s) of impact; Inform IEC, IC, EPD Check
monitoring data, all plant, equipment and Contractor's working methods; Discuss
mitigation measures with IEC, ICR and
Contractor; Ensure mitigation measures are implemented; Ensure
mitigation measures are implemented; Increase the monitoring frequency to
daily until no exceedance of Limit level for two
consecutive days; |
Check monitoring data
submitted by ET and Contractor’s working method; Discuss with ET and Contractor
on possible remedial actions; Review the Contractor’s
mitigation measures whenever necessary to assure their effectiveness; Supervise the implementation
of mitigation measures. |
Discuss
with IEC, ET and Contractor on the proposed mitigation measures; Request Contractor to
critically review the working methods; Make agreement on the mitigation measures and ensure
mitigation measures are properly implemented; Consider and instruct, if
necessary, to slow down or stop that
activity of work until exceedance is abated. |
Take immediate corrective
actions to avoid further exceedance; Submit proposal of mitigation
measures to IEC within 3 working days; Implement the agreed
mitigation measures; Resubmit proposals if problem
still not under control; Slow down or to stop relevant
activity until exceedance is abated. |
It will be the DBO Contractor’s responsibility to
ensure that all wastes produced during the NENT Landfill Extension are handled,
stored and disposed of in accordance with good waste management practices and
EPD’s regulations and requirements.
The major waste material generated during construction
activities has been identified to be construction and demolition (C&D)
material and recommended to be audited at regular intervals (at least weekly)
to ensure that proper storage, transportation and disposal practices will be
implemented.
Monitoring of waste management practices will ensure
that these solid wastes generated during construction will not be disposed into
the nearby coastal waters. The DBO Contractor will be responsible for the
implementation of any mitigation measures to minimise waste or redress problems
arising from the waste materials.
Construction Phase
Mitigation measures for waste management are summarised
below. With the appropriate handling, storage and removal of waste arisings
during the construction phase as defined below, the potential to cause adverse
environmental impacts would be minimised. The EMIS of the recommended
mitigation measures is presented in Appendix
C.
Good Site Practices and Waste Reduction Measures
It is expected that adverse impacts from waste
management would not arise, provided that good site practices are strictly
followed. Recommendations for good site practices during construction include:
·
Nomination
of approved personnel to be responsible for good site practices and making
arrangements for collection of all wastes generated on-site and effective
disposal;
·
Training
of site personnel for cleanliness, proper waste management procedures including
chemical waste handling, and waste reduction, reuse and recycling concepts;
·
Provision
of sufficient waste collection points and regular collection for disposal;
·
Appropriate
measures to minimise windblown litter and dust during transportation of waste
by either covering trucks or by transporting wastes in enclosed containers;
·
Regular
cleaning and maintenance programme for drainage systems, sumps and oil
interceptors;
·
Appropriate
waste management should be implemented in accordance with the ETWB TC(W) No
19/2005; and
·
Recording
system for the amount of wastes generated, recycled and disposed (including the
disposal sites) should be proposed.
A trip-ticket system should be implemented in accordance
with WBTC No 31/2004 for proper record of the quantity of C&D material
generated on-site. Construction Waste
Disposal Charging Scheme under the Waste Disposal Ordinance also applies to
control the disposal of construction waste.
Good management and control will prevent the generation of significant
amounts of waste.
Waste reduction is best achieved at the planning and
design stage, as well as by ensuring the implementation of good site
practices. Recommendations include:
·
Segregation
and storage of different types of waste in different containers, skips or
stockpiles to enhance reuse or recycling of materials and their proper
disposal;
·
Separate
labelled bins should be provided to segregate aluminium cans from other general
refuse generated by the work force and to encourage collection of aluminium
cans by individual collectors;
·
Any
unused chemicals or those with remaining functional capacity should be
recycled;
·
Maximising
the use of reusable steel formwork to reduce the amount of C&D material;
·
Prior
to disposal of C&D waste, it is recommended that wood, steel and other
metals should be separated for re-use and/or recycling to minimise the quantity
of waste to be disposed of to landfill;
·
Proper
storage and site practices should be implemented to minimise the potential for
damage or contamination of construction materials;
·
Plan
and stock construction materials carefully to minimise amount of waste
generated and avoid unnecessary generation of waste; and
·
Minimise
excessive ordering of concrete, mortars and cement grout by doing careful check
before ordering.
In addition, specific mitigation measures are
recommended below for the identified waste arisings to minimise environmental
impacts during handling, transportation and disposal of these wastes.
C&D Material
As the design has adopted a C&D material balance
approach, the impact on the handling, collection, transportation and disposal
of C&D material is insignificant.
Excavated slope, stockpiled material and bund walls will be covered
(e.g. by a tarpaulin) until used in order to prevent wind-blown dust during dry
weather, and to reduce muddy runoff during wet weather. If any topsoil-like materials need to be
stockpiled for any length of time, consideration should be given to
hydroseeding of the topsoil on the stockpile to improve its visual appearance
and prevent soil erosion.
Chemical Wastes
Plant/ equipment maintenance schedule should be designed to
optimise maintenance effectiveness and to minimise the generation of chemical
wastes. Chemical waste should be
properly stored and transported off-site for treatment by a licensed
collector. The DBO Contractor should
register with EPD as a chemical waste producer.
Where possible, chemical wastes (e.g. waste lube oil) should be recycled
by licensed treatment facilities.
General Refuse
All recyclable materials (separated from the general waste)
should be stored on-site in appropriate containers with cover prior to
collection by a local recycler for subsequent reuse and recycling. Residual, non-recyclable, general waste
should be stored in appropriate containers to avoid odour. Regular collection should be arranged by an
approved waste collector in purpose-built vehicles that minimise environmental
impacts during transportation.
Sludge
Sludge should be collected by a licensed collector at regular
intervals, to suit the operation schedule of the leachate treatment plant. The use of purpose-built sludge tankers can
minimise the potential of environmental impacts during transportation. Co-disposal of this sludge in designated
trenches should be considered to reduce its hazardous impact.
The qualitative risk assessment for landfill gas (LFG) hazards associated with the construction, operation, restoration and aftercare phases indicated that the overall risks to the receivers within the NENT Landfill Extension site was categorised as ‘High’ and that to the receivers outside the NENT Landfill Extension site was ‘Medium’.
The sensitive receivers falling within the newly proposed 250m Consultation Zone may be prone to LFG potential risk and appropriate protective and precautionary measures including engineering design and monitoring programme have been proposed to reduce such risk to acceptable levels. With these measures in place, no adverse impact is anticipated. LFG monitoring should be conducted throughout various phases of NENT Landfill Extension with the following key objectives:
·
To
ensure the safety and health of workers during the construction stage of
landfill extension;
·
To
determine the performance and effectiveness of LFG mitigation measures and
control systems for preventing uncontrolled LFG migration, with respect to the
LFG risk on properties, residents and vegetation;
·
To
establish a system for assessment and monitoring of any potential ecological
stress in the vicinities of the site;
·
To
establish a monitoring regime for buildings within the site services routes and
other enclosed areas providing a warning system for detection of potential build-up
of hazardous LFG; and
·
To
ascertain the characteristics of the landfill and estimate the quantity and
quality of the LFG production in order to assess the potential for future
utilisation.
This EM&A Manual
specifies the basic requirements for LFG monitoring in NENT Landfill Extension,
including the monitoring locations, parameters, equipment, procedures,
frequency, reporting format, Action and Limit (A/L) Levels, Event and Action
Plan (EAP), and Emergency and Contingency Plan (ECP), etc. Further details of LFG monitoring
requirements should be established in the Landfill Monitoring Plan (LMP) to be
developed by the future DBO Contractor based on this EM&A Manual.
The LFG monitoring programme
should include on-site and off-site monitoring at the agreed period of time and
frequency. On-site and off-site LFG
monitoring during different phases of landfill development should cover:
·
Quantity and quality of
extracted LFG at individual gas well heads;
·
Quantity of LFG automatically
monitored at LFG pumping station;
·
Fixed surface and borehole
locations along the landfill site boundary and at potential sources of
concern;
·
Monitoring safe level of LFG
concentration, and implementation of sufficient mitigation measures when
entering confined spaces within the landfill site; and
·
Off-site monitoring for
LFG.
LFG monitoring should be
conducted in monthly basis at designated monitoring locations and gas
monitoring boreholes, supplemented by monthly site surveys of the surrounding
environment including natural cracks and fissures, service drains and ducts,
area with sign of vegetation death, and any below ground enclosed spaces, which
include normal bulk gas using portable instrument verified by gas sampling and
laboratory analyses. If the monitoring
results indicate evidence of gas migration, the monitoring frequency should be
increased accordingly, with the implementation of appropriate mitigation
measures under the EAP.
LFG monitoring should commence at
the start of construction works through the operation, restoration and until
completion of aftercare phases. The
measured LFG results should be checked for compliance against pre-defined A/L
Levels in this EM&A Manual and the LMP.
In case exceedance of compliance level was
detected at any locations, the EAP should be triggered for necessary action to
be taken.
If abnormally high LFG levels are
detected at off-site sensitive receivers, the ECP should be strictly followed
to timely trigger the listed action without delay, which includes evacuation of
occupants, provision of forced ventilation to the concerned sensitive receiver,
investigation of potential source of LFG, increase LFG extraction rate on-site
for minimise leakage etc. Details of the
procedures will be documented in the ECP.
7.3 Monitoring Parameters
A suite of LFG monitoring parameters include:
·
Monitoring borehole: |
Methane (CH4), carbon dioxide (CO2), oxygen (O2), flammable gas |
·
Surface gas location: |
CH4,
CO2, O2 |
·
Gas well head: |
CH4,
CO2, O2, flammable
gas, volatile organic compounds (VOC) |
·
Off-site location: |
VOC |
Monitoring for Construction
Works
Intrinsically safe portable gas detectors should be used
during excavation or when working in any confined spaces, which have the
potential for presence of LFG and risk of explosion or asphyxiation. The monitoring equipment should alarm, both
audibly and visually, when the concentrations of the following gases were
exceeded:
·
CH4:
>10% Lower Explosion Limit (LEL);
·
CO2:
>0.5%; and
·
O2:
<18% by volume.
Monitoring at Designated Locations
Pre-entry and routine monitoring should be conducted at
boreholes, gas well heads, utilities’ manholes and chambers throughout the
landfill extension development. The LFG
monitoring should be conducted regularly.
The LFG monitoring instrument should:
·
Comply
with EPD’s Landfill Gas Hazard Assessment – Guidance Note as intrinsically
safe;
·
Be
capable of continuous monitoring of CH4, CO2, O2,
barometric pressure and gas pressure measurement;
·
Normally
operate in diffusion mode unless required for spot sampling, when it should be capable of operating by means of
an aspirator or pump;
·
Have
low battery, fault and over range indication incorporated;
·
Store
monitoring date and be capable of being down-loaded directly; and
·
Measure
within these ranges: methane 0-100% LEL & 0-100% v/v; oxygen 0-25% v/v;
carbon dioxide 0-100% v/v; barometric pressure mBar (absolute); gas pressure
(relative to atmosphere) pascals; and temperature 0-100°C.
Proper gas sampling
devices such as stainless steel gas cylinders or Tedlar bags should be used for
collection of ambient gas samples at specified surface and off-site locations
and delivered to laboratory for testing using gas chromatography analysis.
All buildings within the NENT Landfill Extension site
should be monitored for the presence of LFG with a permenant detection system with
the following features:
·
Detector heads to be located within buildings;
·
Main control box which houses individual control
devices for each detector head;
·
Central control panel to alert site personnel,
audibly and visually, when gas concentration reached or exceeded threshold
levels; and
·
Dial-out facility to enable appropriate personnel
to be alerted if detectors are triggered outside operation hours.
Calibration
and Maintenance
All portable instrument should be calibrated and
serviced according to the manufacturer’s instructions. Calibration gases should be used for checking
portable instrument for methane and carbon dioxide detection before and after
use. Instrument for monitoring oxygen
should be calibrated against normal expected air concentrations. Any significant variations in instrument
performance outside that expected theough normal drift should be noted with the
instrument calibration timely corrected.
During the construction works within the NENT Landfill
Extension site with excavation of 1m deep or more, LFG concentrations should be
monitored before entry and periodically during the progress of works. If drilling is required, the procedures for
safety management and working procedures as stipulated in EPD’s Landfill Gas
Hazard Assessment – Guidance Note should be strictly adopted.
Throughout the landfill extension development, when
service voids, manholes or inspection chambers within the project site are
entered for maintenance, monitoring and a checklist system of safety
requirements should be performed before entry in accordance with the Code of
Practice on Safety and Health at Work in Confined Spaces.
The proposed LFG monitoring
locations including designated boreholes and surface locations, gas wells, and
off-site locations for NENT Landfill Extension development are shown in Drawing No. 24315/13/504,
which are subject to changes depending on the design and modification by the
future DBO Contractor. Detailed requirements of LFG monitoring should be
established in the LMP by the DBO Contractor.
7.6 Monitoring Frequency
LFG monitoring should be
conducted in monthly basis at designated monitoring locations and gas
monitoring boreholes, supplemented by monthly site surveys of the surrounding
environment including natural cracks and fissures, service drains and ducts,
area with sign of vegetation death, and any below ground enclosed spaces.
If the monitoring results
indicate evidence of gas migration, the monitoring frequency should be
increased accordingly, with the implementation of appropriate mitigation
measures under the EAP.
The monitoring frequency should be reviewed throughout
the on-going development of NENT Landfill Extension and revised as necessary
based on the LFG monitoring data.
Detailed requirements of LFG monitoring frequency should be established
in the LMP by the DBO Contractor.
7.7 Monitoring Procedures
Surface Gas Emission
·
Walkover survey for the whole site area should be undertaken at a slow pace with the
inlet tube of the probe only a few centimeters above ground level.
·
Measurements
will be taken in areas off-site and/or beyond the landfill boundary where there is visible
vegetation stress or die-back which may be caused by depletion of soil oxygen
and accumulation of toxic gases or vapors in the root zone.
·
Survey of the capping, focusing upon cracks or areas of settlement,
surface drains, sub-surface service entries to buildings and any other enclosed
spaces should be taken.
Monitoring Borehole
·
The sampling port should be connected to the gas
monitoring probe.
·
The gas analyser should be turned on to sample the
gas for about one minute.
·
The sampling port should be removed and the
temperature probe should be inserted into the gas monitoring probe to record
the temperature.
·
Results should be recorded on a log sheet.
·
Pressure (within installations, relative to
atmospheric pressure) should be monitored at any monitoring probe where methane
was detected on the previous monitoring occasion. The order of monitoring
should be pressure, followed by flammable gas (CH4), O2,
CO2 and temperature.
·
Bulk samples of LFG should be drawn from gas
monitoring probes with tubing connected directly to a 10L Tedlar bag and sent
for laboratory analysis.
Well Head
·
Proper hoses should be connected from the GEM-500
to the wellhead.
·
Black striped Tygon hose with the external
filter/water trap assembly should be attached to the static port on the
GEM-500.
·
Almond-coloured male quick connect should be placed
on the end of this tubing to read the static pressure on the Accu-Flo wellhead.
·
Clear Tygon hose should be connected to the impact
port of the GEM-500. A chrome plated brass male fitting should be placed on the
end of the clear tubing. This chrome
fitting should be used to measure the impact pressure at the wellhead.
·
Gas analyser should be turned on and gas should be
sampled for 60 seconds.
·
Results should be recorded on a log sheet.
·
Pressure (within installations, relative to
atmospheric pressure) should be monitored at any monitoring probe where CH4
was present on the previous monitoring occasion. The order of monitoring will be pressure,
followed by flammable gas (CH4), O2, CO2 and
temperature.
·
Bulk samples of LFG should be drawn from gas
monitoring probes with tubing connected directly to a 10L Tedlar bag and sent
for laboratory analysis.
·
Permanent gas detection system should be installed at each on-site
building for the continuous and automatic monitoring of gas ingress into the
building.
·
The effectiveness of the system will
further be monitored by inspection of main gas detector panel every 4 hours;
inspection of air inlets to ensure no blockages, daily; and monitoring of all
maintenance holes, ducts and confined spaces both inside and within close
proximity to the Landfill Site Boundary for flammable gas and carbon dioxide,
monthly.
·
The
gas detection system will be set for alarm (audible and visual) if
* CH4 rises to 20% LEL; or
* CO2 rises to 1.5% by volume; or
* O2 falls to 18% by volume.
Off-site
Location
VOCs
·
A
sample list of VOC monitoring parameter is listed in Appendix D.
·
Prior
to sampling, the sampler should be attached to the canister by tubing.
·
The
canister valve should be opened and the canister pressure gauge should be
recorded.
·
Ambient
air should be pumped
into the canister by the sampler’s diaphragm pump. The flow rate should be
maintained at about 67mL/min
for 3 hours in order to fill the 6L canister to 2 atm. The system timer should be programmed to activate and
deactivate the sample collection.
·
After
sampling, the
canister valve should be closed and the final sample pressure should be
recorded on the
sampling data sheet.
·
Monitoring
for VOCs should not be
carried out if it is raining.
CH4
·
A
sample-collecting air bag should be situated within an airtight drum. The bag should be opened to the atmosphere and a
vacuum should be applied
to the inside of the drum by means of a vacuum pump. The negative pressure causes the air bag to
inflate, drawing in an atmospheric air sample.
The bag should then be sealed immediately.
·
Sample
containers should be
labeled and delivered to the accredited laboratory as soon as is practicable.
7.8 A/L Levels and EAP
The A/L Levels and relevant EAP for LFG detected in
excavation, utilities and enclosed on-site areas are summarised in Table 7.1.
Table 7.1 A/L Levels and
EAP for LFG
Parameter |
Level |
Action |
Oxygen (O2) |
Action
Level <19% O2 |
Ventilate
trench/void to restore O2 to >19% |
Limit
Level <18% O2 |
Stop works Evacuate personnel/prohibit entry Increase
ventilation to restore O2 to >19% |
|
Methane
(CH4) |
Action
Level >10% LEL* |
Prohibit hot works Increase
ventilation to restore CH4 to <10% LEL |
Limit
Level >20% LEL |
Stop works Evacuate personnel/prohibit entry Increase
ventilation to restore CH4 to<10% LEL |
|
Carbon
dioxide (CO2) |
Action
Level** >0.5%** CO2 |
Ventilate
to restore CO2 to < 0.5% |
Limit
Level >1.5% CO2 |
Stop works Evacuate personnel / prohibit
entry Increase
ventilation to restore CO2 to <0.5% |
* LEL: Lower Explosive Limit – concentrations
in air below which there is not enough fuel to continue an explosion.
**
This Action Level of CO2
at 0.5% is set for reference only, assuming no CO2 emission from a
particular location. Depending on
the baseline CO2 levels, the Action Level at a particular location
will be changed.
The protection and precautionary measures to minimise LFG hazards
for the areas within and outside the landfill extension site during
construction, operation, restoration and aftercare phases are summarised in the
EMIS in Appendix C.
Due to the close proximity to the existing NENT Landfill site, the mitigation measures within landfill extension site generally encompass specific protection against hazards of exposure to LFG e.g. ignition, explosion, asphyxiation, toxicity, etc when undertaking construction activities including excavation and trenching.
During operation, restoration and aftercare phases, due care for strict implementation protection measures should be taken when operations within service voids, manholes and inspection chambers need to be exercised within the landfill extension site. All new-built permanent building structures within the landfill extension site should be installed with specific gas protection measures.
For new developments outside the landfill extension site but within
the
· Carry out an LFG hazard assessment to evaluate the degree of risk associated with the proposed development;
· Design suitable precautionary/ protection measures to render the proposed development as safe as reasonably practicable;
· Ensure that the precautionary/ protection measures to be fully implemented according to the design; and
· Establish a maintenance and monitoring programme to ensure the continued performance of implemented protection measures.
8 Landscape and Visual Monitoring
The EIA study has recommended landscape and visual
mitigation measures to be undertaken during the construction and operational
phases, as well as the restoration and aftercare phases of the project. This section outlines the EM&A
requirements of these measures to mitigate the landscape and visual
impacts.
The design, implementation and maintenance of landscape
mitigation measures should be checked to ensure that they are fully implemented
and that potential conflicts between the proposed landscape measures and other
works and operational requirements are timely resolved without compromise to
the intention of the proposed mitigation measures.
Baseline Monitoring
Photographic records of the project site should be
taken at the time when the DBO Contractor take over the site, which should be
approved by the IC. The approved
photographic records should be submitted to the Project Proponent, ET, IEC and
EPD.
Monitoring Locations and Frequency
In order to monitor the landscape and visual impact
after providing mitigation measures effectively, all the specified and affected
LCAs, LRs and VSRs should be monitored.
Photographical records should be taken for the monitoring locations
monthly from the commencement of works.
Those records are recommended to be stated in the Specification and DBO
Contractor’s monthly progress report.
Design
Phase
The mitigation measures proposed in the EIA study to
mitigate the landscape and visual impacts should be embodied into the detailed
engineering design and landscape design drawings and contract documents. Designs should be checked to ensure that the
mitigation measures are fully incorporated and that potential conflicts with
civil, geo-technical, structural, drainage, underground utilities and
operational requirements are resolved prior to construction and operation of
the project. The Project Proponent
should develop a detailded management programme to mitigate the landscape and
visual impacts.
Construction
and Operational Phases
Measures to mitigate the landscape and visual impacts
during the construction and operational phases should be checked to ensure
compliance with the intended aims of the measures. The progress of the engineering works should
be regularly reviewed on site to identify the earliest practical opportunities
for the landscape works to be undertaken.
The event and action plan for landscape and visual monitoring during the
construction and operational phases is summarised in Table 7.1.
Restoration
and Aftercare Phases
Measures to mitigate landscape and visual impacts
during the restoration and aftercare phases should be checked to ensure
compliance with the intended aims of the measures. The success of all planting works intended to
mitigate the visual and landscape impact should be monitored, including
long-term maintenance of the restoration planting works under the detailed
management programme. The event and
action plan for landscape and visual monitoring during the restoration and
aftercare phases is summarised in Table 7.2.
Table 8.1 Summary of event and action plan for landscape and visual monitoring during construction and operational phases
|
ET |
IEC |
IC |
DBO Contractor |
Design checking |
· Check final
design conforms to the requirements of EP and prepare report |
· Check report. · Recommend
remedial design if necessary |
· Undertake
remedial design if necessary |
· Ensure
compliance with EP requirements |
Exceedance on one occasion |
· Identify
source of impact · Inform IEC and
IC · ·Discuss
remedial actions with IEC, IC and DBO Contractor · Monitor
remedial actions until rectification has been completed |
· Check report · Check DBO
Contractor's working method · Discuss with
ET and DBO Contractor on possible remedial measures · Advise IC on
effectiveness of proposed remedial measures · Check
implementation of remedial measures |
· Notify DBO
Contractor · Ensure
remedial measures are properly implemented |
· Amend working
methods · Rectify damage
and undertake any necessary replacement |
Repeated Exceedance(s) |
· Identify
source of impact · Inform IEC and
IC · Increase
monitoring frequency · Discuss
remedial actions with IEC, IC and DBO Contractor · Monitor remedial
actions until rectification has been completed · If exceedance stops, cease additional monitoring |
· Check
monitoring report · Check DBO
Contractor's working method · Discuss with
ET and DBO Contractor on possible remedial measures · Advise IC on
effectiveness of proposed remedial measures · Supervise
implementation of remedial measures |
· Notify DBO
Contractor · Ensure
remedial measures are properly implemented |
· Amend working
methods · Rectify damage
and undertake any necessary replacement |
Table 8.2 Summary of event and action plan for landscape and visual monitoring during restoration and aftercare phases
|
Maintenance
Agency |
Management Agency |
Exceedance |
· Identify
source of impact · Discuss
remedial actions with Management Agency. · Monitor remedial
actions until rectification has been completed. |
· Check report. · Discuss with
Maintenance Agency possible remedial measures. · Supervise
implementation of remedial measures. |
9 Cultural Heritage Monitoring
The EIA study has recommended the built heritage
mitigation measures arising from the NENT Landfill Extension project. This section outlines the specific EM&A
requirements of these measures.
Details of the EM&A programme for impacted cultural
heritage resources will be provided in this section, with the full methodology
for the recording and preparation of the archives for both the cultural
landscape features (boulder paths and boulder terraces) and the graves being
summarised (Drawing No.
24315/13/606). The resources
listed below should be preserved by detailed record. It is the responsibility
of the DBO Contractor that all mitigation recommendations are fully implemented
and the results approved by the Antiquities and Monuments Office (AMO) of the
Leisure and Cultural Services Department (LCSD) prior to any construction
works.
It should be noted that site of abandoned graves will
require no mitigation measures and that the study area is extremely overgrown
with dense ground covering vegetation and the potential for the presence of
more historical graves exists. As a
result, it is recommended that whenever a grave is found during the construction
phase, the AMO should be contacted immediately and the works in the immediate
vicinity of the grave should be stopped until it is inspected by the AMO.
9.3 Ngong Tong (North and West of Shek Tsai Ha Road: Western & Central Section)
The southern section of the path should be surveyed and
mapped to determine if any sections of the path will fall within the extension
boundary of the finalised layout plan.
If any sections are found to be within the extension boundary then
preservation by detailed record should be undertaken and fulfill the AMO
requirements.
G2, G4, G5, G6, G7, G8, G14, G15, G25, G26, G27, G28
and G31 should be preserved by detailed record to fulfill the AMO requirements.
9.4 Tong To Shan (North of Shek Tsai Ha Road: east section)
The southern section of the path should be surveyed and
mapped to determine if any sections of the path fall within the extension
boundary of the finalised layout plan.
If any sections are found to be within the extension boundary then
preservation by detailed record should be undertaken to fulfill the AMO
requirements.
1. The requirement for the recording of grave inscriptions should include rubbing of grave inscriptions to be conducted, the inscriptions to be rewritten in a tabular format with proper cross-referencing (e.g. item numbers, photos).
2. The
requirements for the cartographic survey of historic graves should include:
·
The
following plans are required:
-
Site
plans showing the relative locations of the graves and their associated
cultural/ fung shui landscape (if any) concerned to 1:100 or as appropriate;
-
Plan(s)
showing all structural walls and built-in fittings to 1:50;
-
Elevations
of each face of the graves to 1:50;
-
At
least two cross sections through the graves showing the architectural
characters of the graves to 1:50;
-
Architectural
details including decorations on the “stone head”, spirit stone tablet,
chimneys, inscriptions and couplets, plaster decoration and ornamental
features, mouldings, brick construction patterns and any other items of
historical or conservation interest to scale 1:10 or 1:5;
-
Plan,
elevation and cross section of any important fittings within/ surrounding the
graves, particularly relating to its ceremonial use, to appropriate scale;
-
Construction
details should be noted such as types of brick bonding, joints in granite
features, etc, to scale 1:10 or as appropriate;
-
The
number of courses of brickwork to each wall should be recorded on the
appropriate drawings;
-
All
the plans (apart from details) should have North point.
·
Drawings
should be annotated with descriptions of the building materials used in the
construction of the principal elements.
·
A
full set of the cartographic records has to be submitted to the AMO on or
before the date mutually agreed.
3. The
requirements for photographic survey of historic graves should include:
·
All
the photographic recording should be done in both colour slides and negatives.
The following recordings are required:
-
The
historic grave, its associated structures and their immediate surrounding
environment including important trees, types of paving, and villages concerned
etc. Aerial-photos in oblique angles showing the characteristics of the site such
as the associated cultural/ fung shui landscape are required.
-
Details
of the graves with the following shots:
(a) Identification picture including the
surrounding area;
(b) General views of the graves from all sides,
including the top;
(c) Oblique view of the graves;
(d) Close up of the important details including
calligraphy, e.g. decorations on the stone head, spirit stone tablet, paving,
inscriptions and couplets, plaster decoration and ornamented features,
mouldings, brick construction patterns, and any other items of historical or
conservation interest.
·
All
the photos (size in 5” x 7”) and slides should be properly captioned in both
Chinese and English, and easily referenced to their location on key drawings
and should be numbered and cross-referenced for easy retrieval and duplication.
·
A
full set of photographic records should be submitted to the AMO on or before
the date mutually agreed for inclusion in the photographic archive of the AMO.
4. Format
of the detailed survey of graves to be agreed with AMO before the commencement
of the recording.
Cultural Landscape Features
1. The
requirements for cartographic survey of section of boulder paths to be directly
impacted by project should included:
·
The
following plans are required:
-
Site
plans showing the relative locations of the path to 1:1000 or as appropriate;
-
Plan(s)
showing all structural elements to 1:50;
-
All
the plans (apart from details) should have North point.
·
Drawings
should be annotated with written descriptions of the recorded features
·
A
full set of cartographic records should be submitted to the AMO on or before
the date mutually agreed.
2. The
requirements for photographic
survey of boulder paths should include:
·
All
the photographic recording should be done in both colour photographs and
negatives. The following recordings are required:
-
General
views of the boulder path, including its immediate surrounding environment.
-
Details
of the boulder path with the following shots:
(a) Identification picture;
(b) Views of the boulder path from all sides,
including the top.
·
All
the photos (size in 5” x 7”) and slides should be properly captioned in both
Chinese and English, and easily referenced to their location on key drawings
and should be numbered and cross-referenced for easy retrieval and duplication.
·
A
full set of the photographic records should be submitted to the AMO on or
before the date mutually agreed for inclusion in the photographic archive of
the AMO.
The EIA stipulated that ecological monitoring should be
undertaken throughout the design, construction, operation, restoration and
aftercare phases of NENT Landfill Extension to ensure that all mitigation
measures should be fully complied with.
The objectives of design audit for ecology are to ensure that the design
for ecological mitigation specified in the EIA Report will be conducted to
ensure that such designs are ecologically feasible and effective.
The EM&A objectives for ecology during the construction,
operation, restorarshould be to ensure that the ecological contract works and
construction mitigation procedures recommended are carried out as specified and
are effective. The construction and
operational phase ecological EM&A should be carried out as part of the
overall EM&A programme.
The purposes of ecological monitoring and audit are:
·
To
verify the accuracy of the predictions of the ecological assessment study;
·
To
detect unpredicted ecological impacts arising from the proposed project;
·
To
monitor the effectiveness of the mitigation measures; and
·
To
recommend action plans in response to unpredicted impacts, and/ or failed
mitigation
The performance of monitoring and audit from an
ecological prospective should be integrated with the overall monitoring and
audit plan for the project as a whole.
The information on the commencement and programme of the engineering
works should enable the ecological monitoring to be prepared with
considerations of seasonality factors.
Mitigation measures required for the Project to
minimise ecological impacts and to preserve ecological resources will be
specified in the Environmental Permit.
Ecological mitigation measures to be implemented during the construction
phase and operation phase include the following:
·
Transplantation
of four plant species of conservation interest within the project area prior to site clearance. They are Aquilaria
sinensis, Rhododendron simsii, Endospermum chinense, and Arundina
graminifolia. Their locations are
shown in Drawing No. 24315/13/702.
·
Regular
site audit and good site practices to avoid encroachment onto the nearby
natural habitats and disturbance to wildlife.
These are listed in various sections (including air, water, noise, waste
sections) of the EIA and the other sections of this EM&A Manual.
Ecological mitigation measures to be implemented during
the restoration and aftercare phases should include woodland compensatory
planting and monitoring. The objective
of compensatory planting is to mitigate for vegetation loss. The ratio of compensation, species
composition, and schedule of planting should follow the mitigation measures
specified in Section 8 of the EIA Report.
To ensure the survival and establishment of the
compensatory planting, a 10 year ecological monitoring extending to the
aftercare phase, i.e. year 2021-2031, is proposed. Apart from the standard practices and regular
maintenance covered by the landscape contract, monitoring of survival, height,
health condition of species planted will be monitored.
Good site practices should be implemented to avoid
encroachment onto the nearby natural habitats and disturbance to wildlife. Examples are detailed in various sections of
the EIA report and include:
·
Placement
of equipment or stockpile in designated works areas and access routes selected
on existing disturbed land to minimise disturbance to natural habitats.
·
Restriction
of construction activities to the work areas that would be clearly demarcated.
·
Resinstatment
of the work areas immediately after completion of the works.
·
Only
well-maintained plant should be operated on-site and plant should be serviced
regularly during the construction programme;
·
Machines
and plant (such as trucks, cranes) that may be in intermittent use should be
shut down between work periods or should be throttled down to a minimum;
·
Plant
known to emit noise strongly in one direction, where possible, be orientated so
that the noise is directed away from nearby NSRs;
·
Silencers
or mufflers on construction equipment should be properly fitted and maintained
during the construction works;
·
Mobile
plant should be sited as far away from NSRs as possible and practicable;
·
Material stockpiles, site office and other
structures should be effectively utilised, where practicable, to screen noise
from on-site construction activities;
·
Use
of “quiet” plant and working methods
·
Construction
phase mitigation measures in the Practice Note for Professional Persons on
Construction Site Drainage.
·
Design
and set up of the temporary on-site drainage system will be undertaken by the
DBO Contractor prior to the commencement of construction.
·
Design
and incorporation of silt/sediment traps in the permanent drainage channels to
enhance deposition rates and regular removal of reposited silt and grit.
·
Minimization
of surface excavation works during the rainy seasons (April to September), and
in partiocular, control of silty surface
runoff during storm events, especially for areas located near steep slopes.
·
Regular
inspectsion and maintainence of all drainage facilities and erosion and
sediment control structures to ensure proper and efficient operation at all
times and particularly following rainstorms.
·
Provision
of oil interceptors in the drainage system downstream of any oil/fuel pollution
sources.
The ecological monitoring and audit programme should be
implemented as set out in this EM&A Manual.
Two major components should be included and samples and measurements
should be taken as summarised in Table 10.1:
·
Survey
and transplantation of the four plant species of conservation interest before
site clearance; and
·
10-year
ecological monitoring of compensatory woodland planting during the restoration
and after-care phases.
Table 10.1 Ecological monitoring and audit requirements
Monitoring parameter |
Frequency, Duration and Response |
Transplantation
of plant species of conservation interest before commencement of works |
|
Survey of plant species of conservation interest within the
Project Area |
Once a month during March – June prior to Site Clearance to
locate and mark the individuals. Site
preparation work for tree transplantation at least ½ year before
transplantation. Select sites for
transplantation. |
Transplantation of tree, shrubs and herbs |
During
early wet season to enhance survival (April to June) |
Monitoring of survival and growth of transplanted species |
Monitoring should be conducted at least twice a month during
the first three months and once a month in the following nine months to
ensure survival. The
need of any further monitoring will be reviewed according to the monitoring
results after the 12-month monitoring. |
Ecological monitoring of woodland compensatory
planting during restoration and aftercare phases |
|
Monitoring of survival, growth and health conditions of
planted trees |
A total
of 10 years. Quarterly
during the first two years and every six months during the following three
years of Phase 1 on exotic trees. Quarterly
during the first two years and every six months during the following three
years of Phase 2 on native trees. The need
of any further monitoring will be reviewed according to the monitoring
results after the 10-year monitoring. |
Survey and Transplantation of Plant Species
Preparation work for
transplantation of trees and shrubs should be conducted in accordance to ETWB TC(W)
No. 3/2006 – Tree Preservation, which specifies that when tree transplantation
is reauired, the project office should allow at least 12 months in advance for
consultation to obtain approval, sourcing of receptor location, and preparation
works for transplanting operation.
The
surveys conducted under this EIA identified at least four plant species of
conservation interest within the Project area that would have been directly
impacted by the proposed landfill extension. The group tree surveys recorded 2
no. of Aquilaria sinensis and
3 no. of Endospermum chinense,
while the ecological surveys recorded 2 no. of Rhododendron simsii and about 10 no. of Arundina graminifolia. To minimise the ecological impacts, the affected
individuals would be transplanted to suitable nearby habitats prior to the
construction phase as far as practicable. A detailed vegetation survey covered
the affected habitats would be conducted prior to the commencement of site
clearance works by a suitably qualified botanist /ecologist. The aim of the survey is to update, identify
and record the location and number, health condition and suitability for
transplantation of the affected individuals in order to provide details for the
transplantation scheme. Locations of the species of conservation interest
should be referred to but not be limited to those as shown in Drawing No. 24315/13/702. The vegetation survey should be conducted
once per month during the flowering seasons of the orchid and shrub (March to
June) for easy identification of monitoring locations. Each identified individual should be tagged. The requirements of detailed
vegetation survey will be specified in the NENT Landfill Extension Contract.
According
to the LVIA, due to the fact that the habitats are located to slopes
inaccessible to vehicles and machineries, the majority of them may not be
likely to be preserved by transplanting. However, it is recommended to preserve
among them, some which are of rare and precious species (e.g. Aquilaria sinensis, Endospermum chinense) by
transplanting as far as technically and financially feasible. Feasibility and
suitability of transplanting the affected plant species of conservation
interest would be carefully studied and suitable receptor sites would be
identified by the transplantation scheme.
Examples of the potential receptor sites for Aquilaria sinensis and Endospermum chinese will be fringe of Ling Ma Hang
Woodland immediately to the north of the Project Area, while potential receptor
site for Rhododendron simsii
and Arundina chinensis
will be grassland habitat along the southeast boundary of the Project
Area. Proximity of the receptor sites to
the Project Area will allow access for transplantation and monitoring while
avoiding potential disturbance inside the Project Site due to earth work.
To ensure
good preparation of the transplantation work, the transplantation scheme should
be formulated during the detailed design stage for this Project based on the
information collected during the detailed vegetation survey. It should include
careful selection of receptor sites, detailed transplantation methodology, and
should be implemented and supervised by a suitably qualified botanist/ horticulturist. A monitoring programme should be set out to
monitor the survival and evaluate the successfulness of transplantation. The health and condition of individuals of the
transplanted plant species of conservation interest should be monitored during
the first 12 months after transplantation.
Monitoring should be conducted at least twice a month during the first
three months and once a month in the following nine months to ensure survival.
During construction,
operation, restoration and aftercare phases, routine site inspection should be
conducted on a weekly basis to audit the mitigation measures on disturbance on
habitats adjacent to the work areas. Monitoring of transplantation should be
audited as part of the site audit programme.
Ecological Monitoring of Compensatory
A qualified
botanist/ecologist who forms a member of ET should review the detailed design
of the compensatory planting in order to provide details for ecological
monitoring scheme. He/she should oversee the planting work and conduct
subsequent monitoring. The survival and
health conditions of individuals of the selected plant species should be
monitored over the 10-year period. Since
planting will be conducted in phases in 5 years where native species will be
planted in Years 3 to 5, ecological monitoring should be conducted by phases to
ensure the survival of native species.
The Trigger and Action
Levels and Event Action Plan for monitoring of compensatory woodland planting
are defined in Table 10.2.
The implementation of
mitigation measures and ecological works, DBO Contractor’s compliance with
environmental requirements, and effectiveness of site mitigation measures
during construction, operation, restoration and aftercare phases should be
monitored and audited as detailed in the EM&A programme. The details of the ecological monitoring
plans should be developed by the ecologist of the ET and agreed by EPD and AFCD
prior to commencement of construction works.
Table 10.2 Trigger and Action Levels and Event Action Plan
for monitoring of compensatory woodland planting
Parameter |
Trigger and Action level |
Event Action Plan |
Mortality* |
Trigger Level: > 20%
of mortality of any sampled planted species or overall survival. |
If the Trigger Level is exceeded the ET Leader should inform
DBO Contractor and IEC) immediately.
Frequency of monitoring should increase to closely monitor the
survival and results reported to the DBO Contractor. |
|
Action
Level: > 30%
of mortality of any of each transplanted species. |
If the Trigger Level is exceeded the ET Leader should inform
all parties (DBO Contractor, EPD, AFCD and IEC) immediately. The DBO Contractor should propose
alternative plan and work out the solution (e.g. replacement planting)
according to the requirements of EPD and AFCD. Once the solution has been identified and
agreed with all parties the DBO Contractor should implement the solution. |
* Total defoliation with
no evidence of regeneration (such as presence of leaf buds, stem buds
11 Environmental Audit
Site inspection provides a direct means to initiate and
enforce the specified environmental protection and pollution control
measures. These should be undertaken
routinely to inspect construction activities to ensure these measures are
implemented properly. Site inspection is
one of the most effective tools to enforce the environmental requirements
on-site.
The ET Leader should be responsible to formulate the
environmental site inspection requirements, deficiency and action reporting
system, and to conduct the site inspection works. Within 21 days of the commencement of
construction works, the ET Leader should submit a proposal for site inspection
and deficiency and action reporting procedures to the DBO Contractor for
agreement and the IEC and IC for approval.
The ET’s proposal for rectification should be made known to the IEC.
Regular site inspections should be carried out at least
once per week. The areas of inspection
should not be limited to the environmental situation, pollution control and
mitigation measures within the site. The
inspection should also include a review of the environmental situations outside
the works area which would likely to be affected, directly or indirectly, by
the works activities. The ET Leader
should make reference to the following information when conducting site
inspection:
·
Recommendations
in EIA Report on the environmental protection and pollution control mitigation
measures;
·
Works
progress and programme;
·
Individual
works methodology and proposals, including proposal on the associated pollution
control measures;
·
DBO
Contract specifications on environmental protection requirements;
·
Relevant
environmental protection and pollution control legislation; and
·
Previous
site inspection results.
The DBO Contractor should keep the ET Leader updated
with all relevant information on the construction contract necessary to carry
out the site inspections. All inspection
findings and associated recommendations for improvements to the environmental
protection and pollution control works should be submitted to the IEC and DBO
Contractor within 24 hours after inspection.
The DBO Contractor should follow the procedures and time-frame as
recommended in the site inspection and the deficiency and action reporting
system formulated by the ET Leader to report on any remedial measures
implemented subsequently. Ad-hoc site
inspections should be carried out if significant environmental problems were
identified. Inspections may also be
required subsequent to receipt of environmental complaints or as part of the
investigation work as specified in the EAP for the EM&A programme.
11.2 Compliance with Environmental Requirements
There are contractual environmental protection and
pollution control requirements as well as environmental protection and
pollution control legislation in
The ET Leader should review the progress and programme
of the project works to check that relevant environmental legilsation has not
been violated and that any foreseeable potential for violating the laws should
be avoided. The DBO Contractor should
regularly copy the relevant documents to the ET Leader so that proper audit and
checking should be conducted. Such
documents should at least include the updated works progress reports, works
programme, correspondences for application of different environmental
licenses/permits under the environmental protection legislation, and copies of
all valid environmental licenses/permits.
Site diary should be available for ET Leader's inspection upon request.
The ET Leader should advise the IEC and DBO Contractor
of any non-compliance and non-conformance with the contractual and legislative
requirements on environmental protection and pollution control for follow-up
action. If the ET Leader's review
concluded that the current status on environmental license/permit application
and environmental protection and pollution control preparation works may result
in potential violation of the specified requirements, the ET Leader should
advise immediately inform the DBO Contractor and IC accordingly. Upon receipt of such advice, the DBO
Contractor should take immediate action to rectify the situation. The IC should follow up with the cases to
ensure that appropriate action has been taken to satisfy contractual and legal
requirements.
All environmental complaints should be referred to the
ET Leader for further action. The ET
Leader should undertake the following procedures upon receipt of any
complaints:
·
Log
the complaint and date of receipt into the complaint database and inform the
IEC immediately;
·
Investigate
the complaint to determine its validity and assess whether the source of
problem would be due to the project works activities;
·
Identify
the mitigation measures in consultation with the IEC if the complaint was valid
and due to the project works;
·
Advise
the DBO Contractor if further mitigation measures were required;
·
Review
the DBO Contractor's response to the identified complaint, mitigation measures
and updated situation;
·
If
the complaint was transferred from the EPD, submit the interim report to the
EPD on the status of the complaint investigation and follow-up action within
the time frame as assigned by the EPD;
·
Conduct
additional monitoring and audit to verify the situation if necessary and review
the circumstances leading to the complaint to avoid no recurrence;
·
Report
the investigation findings and subsequent action to the complainant. If the source of complaint was originated
from the EPD, the findings should be reported within the timeframe as assigned
by the EPD; and
·
Record
the environmental complaint, investigation, subsequent action taken and
investigation findings in the monthly EM&A reports.
Reports should be provided in an
electronic medium upon agreement of the format for submission to
the EPD. All the monitoring data (baseline and impact)
should also be submitted on diskettes or other agreed media. The formats of monitoring data to be
submitted should be separately agreed.
The types of reports that the ET Leader should prepare and submit
include Baseline Monitoring Report, Monthly EM&A Reports, Quarterly
EM&A Summary Report, Annual
EM&A Review Report, and Final EM&A Review Report during the
completion and cessation of each project phases.
The ET Leader should prepare and
submit a Baseline Environmental Monitoring Report within 10 working days of
completion of the baseline monitoring.
Copies of the Baseline Environmental Monitoring Report should be
submitted to the DBO Contractor, IEC, IC, Project Proponent and EPD. The ET Leader should liaise with the relevant
parties on the exact number of copies they require. The report format and baseline monitoring
data format should be agreed with the EPD prior to submission. The Baseline Monitoring Report should include
at least the following:
·
Up to half a page executive summary;
·
Brief project background;
·
Drawings showing baseline monitoring locations;
·
Monitoring results (both hard and soft copies)
together with: monitoring methodology, name of laboratory and types of
equipment used and calibration details, parameters monitored, monitoring
locations, date, time, frequency and duration, and quality assurance (QA) /
quality control (QC) results and detection limits;
·
Details of influencing factors including major activities
being carried out on-site, weather conditions and other
factors during the monitoring period which might affect results;
·
Determination of the Action and Limit Levels for each
monitoring parameter and statistical analysis of the baseline data, the analysis
should conclude if there is any significant difference between control and
impact stations for the parameters monitored;
·
Revisions for inclusion in the EM&A Manual; and
·
Comments, recommendations and conclusions.
The results and findings of all
phases of EM&A programme should be recorded in the Monthly, Quarterly, Annual and Final EM&A Reports prepared by the
ET. The EM&A reports should be
submitted within 10 working days of the end of each reporting month, with the
first Monthly EM&A Report due the month after commencement of construction
works. Each EM&A report should be
submitted to the DBO Contractor, IEC, IC, Project Proponent and EPD. Prior to submission of the first Monthly
EM&A Report, the ET Leader should liaise with all parties for the required
number of copies and format of the report in both hard copy and electronic
medium. The ET leader should also review
the number, parameter and location for impact monitoring on six-monthly basis,
or as needed, so as to cater any changes in the baseline condition and
surrounding environment.
First Monthly EM&A Report
The first Monthly EM&A Report
should include at least the following:
·
Executive summary (1-2 pages): Exceedances
of A/L Levels, complaint log, notifications of summons and successful
prosecutions, reporting changes, and future key issues;
·
Brief project information: Project
organisation e.g. key personnel, their contact names and telephone numbers,
project programme, management structure, and works undertaken during the month;
·
Environmental performance status: Works undertaken during the
month with illustrations (e.g. location of works, daily excavation rate, etc)
and drawings showing the project area, environmental sensitive receivers and
impact monitoring and control/ reference
locations (with co-ordinates);
·
Brief summary of EM&A requirements: All
monitoring parameters, environmental quality performance limits (A/L Levels),
EAP, environmental mitigation measures as recommended in the EIA Report, and contractual environmental requirements;
·
Implementation status of mitigation measures: Advice on the
implementation status of environmental protection and pollution
control/mitigation measures as recommended in EIA Report;
·
Monitoring results (in both hard and soft copies) with the
following information: Monitoring methodology, name of laboratory and types of
equipment/instrument deployed and calibration details, parameters monitored,
monitoring locations, date, time, frequency and duration, weather conditions,
other factors affecting the monitoring results, and QA/QC results and detection
limits;
·
Non-compliance, complaints and notifications of summons and
successful prosecutions: Record of all non-compliance or exceedances
of the environmental quality performance limits (A/L Levels), complaints
received (written or verbal) for each media e.g. locations and nature of
complaints investigation, liaison and consultation undertaken, actions and
follow-up procedures taken, results and summary, notification of summons and successful
prosecutions for breaches of current environmental protection/pollution control
legislation, including locations and nature of the breaches, investigation,
follow-up actions taken, results and summary, reasons for and the implications
of non-compliance, complaints, summons and prosecutions including review of
pollution sources and working procedures, and description of the actions taken
in the event of non-compliance and deficiency reporting and any follow-up
procedures related to earlier non-compliance; and
·
Other information: Account of future key issues as reviewed
from the works programme and method statements, advice on waste management
status, and comments on effectiveness and efficiency of mitigation measures, recommendations
on any improvement in the EM&A programme, and conclusion.
Subsequent Monthly EM&A Reports
Subsequent monthly EM&A
reports should include the following:
·
Executive summary (1-2 pages): Breaches of A/L Levels,
complaints log, notifications of summons and successful prosecutions, reporting
changes, and future key issues;
·
Brief project information: Project
organisation e.g. key personnel, their contact names and telephone numbers,
project programme, management structure, and works undertaken during the month;
·
Environmental performance status: Works undertaken during the
month with illustrations (e.g. location of works, daily excavation rate, etc)
and drawings showing the project area, environmental sensitive receivers and
impact monitoring and control/ reference
locations (with co-ordinates);
·
Implementation status of mitigation measures: Advice on the
implementation status of environmental protection and pollution
control/mitigation measures as recommended in EIA Report;
·
Monitoring results (in both hard and soft copies) with the
following information: Monitoring methodology, name of laboratory and types of
equipment/instrument deployed and calibration details, parameters monitored,
monitoring locations, date, time, frequency and duration, weather conditions,
other factors affecting the monitoring results, and QA/QC results and detection
limits;
·
Non-compliance, complaints and notifications of summons and
successful prosecutions: Record of all non-compliance or exceedances
of the environmental quality performance limits (A/L Levels), complaints
received (written or verbal) for each media e.g. locations and nature of
complaints investigation, liaison and consultation undertaken, actions and
follow-up procedures taken, results and summary, notification of summons and
successful prosecutions for breaches of current environmental
protection/pollution control legislation, including locations and nature of the
breaches, investigation, follow-up actions taken, results and summary, reasons
for and the implications of non-compliance, complaints, summons and
prosecutions including review of pollution sources and working procedures, and
description of the actions taken in the event of non-compliance and deficiency
reporting and follow-up procedures related to earlier non-compliance;
·
Other information: Account of future key issues as reviewed
from the works programme and method statements, advice on waste management
status, and comments on effectiveness and efficiency of mitigation measures,
recommendations on any improvement in the EM&A programme, and conclusion of the reporting month; and
·
Appendix: A/L levels, graphical plots of trends of monitored
parameters at key stations over the past 4 reporting periods for representative
monitoring stations annotated against the major activities being carried out on
site during the period, weather conditions during the period, and any other
factors that might affect the monitoring results, monitoring schedule for the
present and next reporting period, cumulative statistics on complaints,
notifications of summons and successful prosecutions, and outstanding issues
and deficiencies.
Quarterly
EM&A Summary Reports
Quarterly EM&A Summary Report of around 5 pages should include
the following
information:
·
Executive summary
(1-2 pages);
·
Brief project
information including a synopsis of the project organisation, works programme,
contacts of key personnel of the EM&A programme, and synopsis of works
undertaken during the reporting quarter;
·
Brief summary of
EM&A requirements e.g. monitoring parameters, environmental quality
performance limits (A/L Levels), and environmental mitigation measures as
recommended in the EIA Report;
·
Advice on
implementation status of environmental protection and pollution
control/mitigation measures as recommended in the EIA Report and summarised in
the updated EMIS;
·
Drawings showing the
project area, environmental sensitive receivers and the monitoring and control
locations;
·
Graphical plots of
trends in monitored parameters over the past four months (the last month of the
previous quarter and the reporting quarter) for representative monitoring
locations annotated against: major activities being carried out on-site,
weather conditions, and other factors which might affect the monitoring results
during the reporting quarter;
·
Advice on the waste
management status;
·
Summary of
non-compliance or exceedances of the environmental
quality performance limits (A/L Levels);
·
Brief review of the
reasons for and implications of the non-compliance, e.g. review of pollution
sources and working procedures;
·
Summary description
of action taken in the event of non-compliance and follow-up procedures related
to any earlier non-compliances;
·
Summarised records
of all complaints received (written or verbal) for each media, liaison and
consultation undertaken, follow-up action and procedures taken;
·
Comments (e.g. a
review of the effectiveness and efficiency of environmental mitigation measures
and performance of the environmental management system of the overall EM&A
programme), recommendations (e.g. improvement in the EM&A programme) and
conclusion for the reporting quarter; and
·
Project Proponent’s
contacts and any hotline telephone number for the public to make enquiries.
The
Annual EM&A Report should include at least the following information:
·
Executive summary
(1-2 pages);
·
Drawings showing the
project area, environmental sensitive receivers and monitoring and control
locations;
·
Brief project
information including a synopsis of the project organisation, contacts of key
personnel of the EM&A programme, and synopsis of work undertaken during the
past 12 months;
·
Brief summary of
EM&A requirements e.g. environmental mitigation measures as recommended in
the EIA Report, environmental impact hypotheses tested, environmental quality
performance limits (A/L Levels), all monitoring parameters, and EAP;
·
Summary of the
implementation status of environmental protection and pollution
control/mitigation measures as recommended in the project EIA Report and
summarised in the updated EMIS;
·
Graphical plots and
statistical analysis of the trends of monitored parameters annotated against
major activities carried out on-site, weather conditions and other factors
which might affect the monitoring results during the reporting year;
·
Summary of
non-compliance or exceedances of the environmental
quality performance limits (A/L Levels);
·
Review of the
reasons for and implications of non-compliances including the pollution sources
and working procedures as appropriate;
·
Description of
actions taken in the event of non-compliances;
·
Summary record of
all complaints received (written or verbal) for each media, liaison and
consultation undertaken, follow-up action and procedures taken;
·
Summary record of
notifications of summons and successful prosecutions for breaches of the
current environmental protection / pollution control legislation, locations and
nature of the breaches, investigation follow-up actions taken and results;
·
Review of the
validity of EIA predictions and identification of shortcomings in EIA
recommendations, and
·
Comments (e.g. a
review of the effectiveness and efficiency of environmental mitigation measures
and performance of the environmental management system of the overall EM&A
programme); and
·
Recommendations and
conclusions (e.g. review of success of the overall EM&A programme to
cost-effectively identify deterioration and to initiate prompt effective
rectification action when necessary) of the reporting year.
Final
EM&A Review Report
The
Final EM&A Review Reports should be submitted prior to the completion and
cessation of each project phases including the Construction and Operation,
Restoration, and Aftercare Phases. The
report should include at least the following information:
·
Executive summary
(1-2 pages);
·
Drawings showing the
project area, environmental sensitive receivers and monitoring and control
locations;
·
Brief project
information including a synopsis of the project organisation, contacts of key
personnel of the EM&A programme, and synopsis of work undertaken during the
entire reporting project phase;
·
Brief summary of
EM&A requirements e.g. environmental mitigation measures as recommended in
the EIA Report, environmental impact hypotheses tested, environmental quality
performance limits (A/L Levels), all monitoring parameters, and EAP;
·
Summary of the
implementation status of environmental protection and pollution
control/mitigation measures as recommended in the project EIA Report and
summarised in the updated EMIS;
·
Graphical plots and
statistical analysis of the trends of monitored parameters annotated against
major activities carried out on-site, weather conditions and other factors
which might affect the monitoring results during the entire reporting project
phase;
·
Summary of non-compliance
or exceedances of the environmental quality
performance limits (A/L Levels);
·
Review of the
reasons for and implications of non-compliances including the pollution sources
and working procedures as appropriate;
·
Description of
actions taken in the event of non-compliances;
·
Summary record of
all complaints received (written or verbal) for each media, liaison and
consultation undertaken, follow-up action and procedures taken;
·
Summary record of notifications
of summons and successful prosecutions for breaches of the current
environmental protection / pollution control legislation, locations and nature
of the breaches, investigation follow-up actions taken and results;
·
Review of the
validity of EIA predictions and identification of shortcomings in EIA
recommendations, and
·
Comments (e.g. a
review of the effectiveness and efficiency of environmental mitigation measures
and performance of the environmental management system of the overall EM&A
programme); and
·
Recommendations and
conclusions (e.g. review of success of the overall EM&A programme to
cost-effectively identify deterioration and to initiate prompt effective
rectification action when necessary) of the entire reporting project phase.
No
site-based documents such as monitoring field records, laboratory analysis
records, site inspection forms, etc should be required to include in the
monthly EM&A reports. However, any
such documents should be well kept by the ET Leader ready for inspection on
request. All relevant information should
be clearly and systematically recorded.
All monitoring data should also be recorded in magnetic media form, with
the soft copy readily available on request.
The data format should be agreed with the EPD. All documents and data should be kept for at
least 1 year following the project completion.
12.5 Interim Notification of Environmental Exceedances
With reference to the EAP, when the
environmental quality performance limits (i.e. A/L Levels) are exceeded, the ET
Leader should immediately notify the IEC, IC, Project Proponent and EPD, as
appropriate. The notification should be
followed up with advice to the IEC and EPD on the results of the investigation,
proposed action and outcome of action taken, with necessary follow-up
proposals.