Agreement No. CE 35/2006(CE)
Kai Tak Development Engineering Study
cum Design and Construction of Advance Works
– Investigation, Design and Construction
Dredging Works for Proposed Cruise Terminal at Kai Tak
Environmental Impact Assessment Report
Contents
2............ PROJECT DESCRIPTION
2.1 Development of Cruise Terminal and Site Constraints
2.2 The Need of Project and Scenario without the Project
2.5 Project Scope and Programme
2.6 Consideration of Alternatives and Development of
Preferred Option
2.7 Siltation and Maintenance Dredging
2.9 Interaction with Other Projects
Lists of Tables
Table 2.2 ......... Approximate
Volume of Dredging from the Existing Seawall
2.1
Development of Cruise Terminal and Site Constraints
General
2.1.1
Development
of the cruise terminal at Kai Tak would require dredging at the existing
seawall at the southern tip of the former
Phasing of Development
2.1.2
It
is planned to implement the cruise terminal in two phases. Phase I Berth (the southern portion) of
2.1.3
Phase
II Berth (additional
Staged Dredging Requirements
2.1.4
Dredging will be required in the Harbour, in the area
around the former
2.1.5
There is a pair of
2.1.6
In view of the constraint of the existing gas pipelines,
the dredging works have to be implemented in two stages to cover the three
dredging zones, in the areas as indicated in Figure 2.4. Dredging in Zone A required for operation of
the Phase I Berth is currently assumed to be carried out during the period from
later half of 2008 to 2011 as part of the Stage 1 dredging. For dredging in Zone B, it is to tie in
with the Phase II Berth construction and is to complete in 2013. The EIA for Stage 1 dredging has
assessed the cumulative impacts from all known possible activities anticipated
in the period from 2008 to 2011 which should represent the worst-case scenario
during the Stage 1 dredging period.
Dredging for the Phase II Berth within Zone C (Stage 2 dredging) would
need to be carried out at a later stage after decommissioning of the existing
submarine gas pipelines in 2013.
The programme for Stage 2 dredging within Zone C is unconfirmed at this
stage but its completion can be extended up to 2020 and the earliest possible
time for the Stage 2 dredging would be 2013 to 2014 after the Stage 1 dredging
and decommissioning and removal of the existing submarine gas pipelines. The current tentative target programme
is to commence the Stage 2 dredging works in 2013 for completion in 2014 for
the purpose of this EIA only. The actual programme might be deferred due to the
progress of the reprovisioning of the submarine gas pipelines and the need for
additional berths as driven by the cruise market. Based on the currently
available information, the assessment for Stage 2 capital dredging has assumed
all other marine works (except for maintenance dredging for the Phase I Berth)
anticipated in or beyond 2012 up to 2020 that would occur concurrently in the
assessment year of 2013/2014. Maintenance dredging for the Phase I Berth will
not be conducted concurrently with the Stage 2 capital dredging. In other words, the assessment has
covered the impacts arising from the Stage 2 capital dredging to be carried out
anytime between 2012 and 2020.
Government Mooring Buoys
2.1.7
The
existing Government Mooring Buoys (GMB) A17 and A43 (Figure 2.4) covering an area of around
2.1.8
In
the long term, the reconfiguration of the Eastern Quarantine and Immigration
2.1.9
Based
on the current design it has been confirmed that the current water depth at the
proposed relocated GMBs is sufficient without the need for dredging. It should be noted that the method of
securing the GMBs is to place a large concrete block on the seabed. When the
existing GMBs are removed, there will not be any disturbance to the seabed
other than to any silt that may have accumulated on top of the anchor block
since its installation. In this respect the likely volume of disturbed material
is only likely to be in the order of
Eastern Quarantine and Immigration
2.1.10
The
EQIA is adjacent and west of the Phase I Berth with a minimum clear separation
from eastern tip (PHE buoy) and berth copeline of
Kai Tak Runway Submarine Outfall
2.1.11
There
is an abandoned submarine outfall namely KTR outfall (
2.1.12
As
shown in the as-built drawings in Appendix
2.1.13
This
abandoned KTR outfall will need to be removed in order to allow the dredging of
existing seabed to the required level for cruise terminal construction. Removal of the KTR outfall would involve
dredging of the seabed. It is
proposed to remove all sections of the outfall where the crown of the outfall
lies above a level of -13mCD. It is
estimated that
2.1.14
It
is proposed that the sections of submarine outfall and the sections of pipe buried
beneath the former runway are to be removed as part of the Stage 1 dredging
works for cruise terminal construction.
2.2
The Need of Project and
Scenario without the Project
2.2.1
The
proposed dredging works are essential to provide necessary manoeuvring basin
for development of the cruise terminal.
The depth alongside the berth face of the cruise terminal has been
determined to suit the maximum draft of design vessel, plus 10% under keel
clearance and
·
Lowest Astronomical Tide (LAT), 0.0mCD
·
greater draft of the vessel currently in operation
(Queen Mary II),
·
allow 10% of the maximum draft for gross underkeel
clearance according to BS 6349-1:2000
ie.
·
allow
2.2.2
Accordingly, the minimum seabed level should be 0mCD – (
2.3.1
The
Government aims to develop
2.3.2
One
of the key considerations for locating the New Cruise Terminal at Kai Tak is
that it is the only site within the
2.3.3
Upon
completion of the New Cruise Terminal, together with the existing cruise
terminal in Tsim Sha Tsui,
General
2.4.1
A two-berth cruise terminal is proposed at the
southern tip of the former
2.4.2
The cruise terminal development will need to cater for a range of cruise
vessels applicable to the region or expected to operate in the future. The size, sophistication and capacity of
cruise vessels will dictate capital and maintenance dredging (navigation
depths, size of manoeuvring areas), the length and capacity of the cruise
terminal berth structure as well as terminal facilities and supporting
infrastructure, particularly transport facilities.
Manoeuvring Area
2.4.3
The
provision of turning basin of
2.4.4
The
2.4.5
Manoeuvring
space is required adjacent to the Phase II Berth with an area approximately
Dredging
2.4.6
For
overall cost effectiveness, initial navigation dredging for operation of Phases
I and II should allow for dredging to -12mCD as justified above in Section
2.2. The area alongside of the
berth structure is to be dredged to provide a depth alongside of -13mCD to
allow for possible future deepening of the manoeuvring area if future new
vessels entail such water depth. The staged dredging requirements for the
cruise terminal are shown in Figure 2.4.
2.4.7
The
existing seabed levels within the Study area (based on IGGE
geophysical survey report under CEDD Contract GE/2005/26) are shown in Figure 2.5. The total in-situ volume of
dredging required for the vessel approach and manoeuvring area to the Phase I
Berth is estimated to be about
2.4.8
In
addition, removal of the existing seawall by dredging is assumed to be required
for berth construction at the south western edge of the former
2.5
Project Scope and Programme
2.5.1
The
scope of the Project comprises:
l
Dredging
of marine sediment of about
l
Removal of existing seawall of about
2.5.2
The
dredging programme is shown in Appendix
2.1. Breakdown of the
dredging volumes is given in Table 2.1. Estimated volumes of contaminated
sediments are given under Section 6 of this report on Waste Management
Implications.
Stages
(Figure 2.4) |
Volume
of Dredging (m3) |
||||
From
Existing Seabed in the Harbour Area |
From Existing Seawall |
Total |
|||
|
Transitional
Structures |
Total |
|||
Stage 1 Dredging Total: |
700,000 (1) |
258,500 |
63,800 |
322,300 |
1,022,300 |
Stage 2 Dredging Total: |
680,000 |
- |
- |
- |
680,000 |
Total (Stage 1 + Stage 2): |
1,380,000 |
258,500 |
63,800 |
322,300 |
1,702,300 |
Note 1: The
total volume of
2.5.3
The
dredging volume presented in this EIA are the result of a detailed engineering
assessment. The total dredging
volume is estimated to be about
2.5.4
Dredging
required for operation of the Phase I Berth is currently assumed to be carried
out during the period from 2009 to 2011 as the first stage. However, the earliest possible time for
commencing the Stage 1 dredging could be in the later half of 2008. The EIA for Stage 1 dredging has
considered the cumulative impacts from all concurrent activities anticipated in
the period from 2008 to 2011 to allow the possible change of the Stage 1
dredging programme to commence in 2008. As the programme for Stage 2 dredging
is unconfirmed, for the purpose of this EIA, it is assumed that the Stage 2
dredging would be carried out from 2013 to 2014, following the Stage 1 dredging
and decommissioning and removal of the existing submarine gas pipelines. The period of 2013 - 2014 is selected as
the time horizon for Stage 2 dredging for impact assessment only. The selected time horizon is the
earliest possible timing for Stage 2 dredging. Based on the currently available
information, the assessment for Stage 2 capital dredging has assumed all other
marine works (except for maintenance dredging for the Phase I Berth)
anticipated in or beyond 2012 up to 2020 that would occur concurrently in the
assessment year of 2013/2014.
Maintenance dredging for the Phase I Berth will not be conducted
concurrently with the Stage 2 capital dredging. In other words, the assessment has
covered the impacts arising from the Stage 2 capital dredging to be carried out
anytime between 2012 and 2020.
2.5.5
This
EIA has not addressed the environmental implication of the third berth which is
outside the scope of this EIA. Any
possible third berth development in future should be subject to separate study.
2.6
Consideration of Alternatives and Development of Preferred Option
Site Location
2.6.1
According
to the studies conducted by the Tourism Commission, taking into account
different growth scenarios,
2.6.2
Adequate
water depth, turning basin and landside developable space are the three key
requirements in determining the location of cruise terminal. The proposed location at the runway tip
would be best able to meet the above requirements when compared to the rest of
Kai Tak. The PODP has proposed
two-alongside berths configuration comprising a continuous
2.6.3
An
alternative location for the cruise terminal at
Dredging Extent
2.6.4
Dredging
will be carried out in the Harbour area and around the former
(a)
The
real time vessel simulation results indicate that a smaller dredged area than
the manoeuvring areas described in Section 2.4 of this report would not be
acceptable, even if operational restrictions were placed on the access of
vessels in the worst conditions, or the use of tugs was mandated.
(b)
Extreme
strong ebb tide pushes the vessels onto the berth, especially at the south
end. The manoeuvring area to the south of the runway is therefore required
to be dredged in line with the berth cope line.
(c)
The
entrance from the fairway into the turning area caused problems during
departing and arriving. The assessment determined that it would be
necessary to provide a wider fairway entrance that ran to the present fairway
buoy at the southeast tip of the EQIA.
(d)
Stage
1 manoeuvring area is adequate for cruise ships to manoeuvre to/from the Phase
I Berth without requiring the relocation of the existing submarine gas
pipelines.
(e)
The
manoeuvring area adjacent to the Phase II Berth has a width of
2.6.1
The
dredging works will be carried out in two stages as shown in Table 2.1
and Figure 2.4. The
proposed dredging extent is essential to provide space needed for safe
manoeuvring of cruise vessels clear of the fairway and cruise berth.
Dredging Programme
2.6.2
The
programme for Stage 1 dredging is governed by the required commissioning date
of the Phase I Berth. Thus, dredging required for operation of the Phase I
Berth (Zone A) has to be carried out during the period from later half of 2008
to 2011 as the first stage in order to meet the commissioning programme for the
Phase 1 Berth. Due to the
site constraints as discussed in Section 2.1, dredging for the Phase II Berth (Zone C) would
need to be carried out at a later stage after decommissioning and removal of
the existing submarine gas pipelines.
The actual program for Stage 2 dredging would also depend on the future
demand for the cruise terminal. The
current tentative programme is to commence the Stage 2 dredging in 2013 for the
purpose of worst-case impact assessment (refer to Section
2.6.3
The duration of maintenance dredging would be less
than 6 months for each phase. Alternative programme for
the maintenance dredging to be carried out in either dry or wet seasons has been
considered under the water quality impact assessment in Section 5. Based on the
model predictions, maintenance dredging in wet season would contribute larger
water quality impact and is therefore not preferred. It is recommended in this
EIA that the maintenance dredging should not be programmed in wet seasons
(April to September) to avoid the potential water quality impacts.
Dredging Method,
Dredging Rates and Staged Dredging Requirements
2.6.4
Dredging
in the Harbour area required for safe manoeuvring of cruise vessels would be
carried out at a maximum production rate of
2.6.5
Closed
grab dredgers are considered as the most suitable dredgers for relatively small
volumes and contaminated mud. It is
feasible to use small trailer suction dredgers although these will give less
control over handling of contaminated mud and produce more marine sediment by
volume (due to high water content) when compared with grab dredging. Whilst larger equipment has been adopted
for major reclamation projects such as the Penny’s Bay reclamation and
Container Terminals in Kwai Chung, in this case, given that dredging is not on
the critical programme path, it is assumed that the most cost effective
construction method with the least environmental impact will be adopted for the
cruise terminal i.e. closed grab dredgers.
2.6.6
The
dredging rate of
2.6.7
In
addition, removal of the existing seawall by dredging will be required for
berth construction at the south western edge of the former
2.6.8
The water quality modelling assessment has
included the assumption that there may be a number of concurrent dredging
projects nearby to the cruise terminal. These assumptions are conservative in
order to allow all potential projects to proceed without severe constraints. The dredging locations, rates,
timing and phased implementation have been analyzed and confirmed by the
technical assessments performed under this EIA to be environmentally
acceptable. In particular,
modelling assessment has been carried out under this EIA to assess the water
quality impacts of undertaking the dredging in either the dry or wet season and
concluded that the proposed dredging rates, locations and timing would not
cause any unacceptable water quality and marine ecological impact, provided
that all the mitigation measures recommended under this EIA are properly
implemented. Further consideration of alternative dredging rate is not
necessary.
Berth Structure
2.6.9
A
section of the existing seawall at the former
l
Option
1 – Piled Quay Deck;
l
Option
2 – Precast Reinforced Concrete Caisson;
l
Option
3 – Precast Concrete Blockwork Seawall;
l
Option
4 – Bored Pile Retaining Wall with Anchor;
l
Option
5 – Precast Reinforced Concrete
l
Option
6 – Sheet Pile Cofferdam Wall
2.6.10
Based
on the above berth structure options, a qualitative assessment has been
conducted by comparison on environmental benefits and dis-benefits, cost,
programme, engineering and maintenance requirements. The general arrangement of the six types
of berth structures is shown in Figure
2.6 to Figure 2.11
respectively.
Option 1 - Piled Quay Deck
2.6.11
The
open piled quay structure would require relatively less amount of dredging at
the existing seawall as compared to other options (except Option 4). The general arrangement of this option
is shown in Figure 2.6. The piled quay with underlying sloping
seawall revetment would more effectively absorb wave energy with beneficial
effects on vessel operations alongside adjacent berths. The piled structure provides a
conventional, reliable and robust structure on which the cruise terminal
operations can be supported and can be adapted to cater for a wide array of
bunkering facilities that may be required.
2.6.12
For
this option, the piled quay structure can be supported by either bored cast
in-situ reinforced concrete (RC) piles or driven steel tubular piles. The bored cast in-situ RC pile system
consumes a relatively large amount of permanent steel casing and in-situ
reinforced concrete, i.e. a higher capital cost. Accordingly, the driven steel tubular
pile with reinforced concrete infill system is more commonly adopted in
2.6.13
Potential
deterioration of the quay deck from corrosion of the steel reinforcement
especially within the tidal and splash zone with potentially rapid
deterioration in any areas of defective workmanship. In order to prolong the service life of
the pile structure in such circumstances cathodic protection may need to be
implemented.
Option 2 – Precast Reinforced Concrete Caisson
2.6.14
The
precast reinforced concrete (RC) structures (Figure 2.7) are typically more durable
under severe marine environmental conditions than in-situ reinforced concrete
structures. The RC caisson can
achieve fast construction placement rates since the units can be fabricated in
advance, then transported to site and sunk in place in a relatively short
period.
2.6.15
However,
this option would require more dredging as compared to the pile option. In addition, the lead time for the
precasting works may result in an initial delay of the works. Significant time may be required to
locate a suitable casting yard location with practical draft depth for the
proposed caisson units.
Transportation of the caisson from a remote casting area to the site
would be subject to either shipping restrictions through the navigation channel
and weather conditions. There would
be considerable uncertainty regarding the caisson costs because of the
requirements for special off site dry docks or similar provisions for casting
and launching the units and transportation.
Option 3 – Precast Concrete Blockwork Seawall
2.6.16
The
fabrication of precast units is one means of speeding up construction since the
units are prefabricated and placed in quick succession following the seawall
dredging and foundation preparation.
The construction method is comparatively simple and versatile which may
not require large numbers of skilled labourers. The general arrangement of this option
is shown in Figure 2.8.
2.6.17
The
mass concrete block structure is more durable under severe marine and environmental
conditions than reinforced concrete structures or steel structures. Maintenance costs for blockwork walls
are therefore expected to be relative low compared to other options.
2.6.18
However,
this option would require more extensive dredging as compared to the pile
option. Moreover, the weight of the
concrete blockwork are relatively heavy, up to approximately 150 tonnes, which
is likely to make it time consuming and expensive to procure, mobilize and
operate suitable heavy lift construction plant. Any settlement of the foundation could
cause the blockwork wall tilt forwards or backwards. The efficiency and cost of the blockwork
system depends in part on the availability of a suitable casting yard which
needs to be easily accessed by floating plant for delivery of the blocks to
site. It is expected however that
space would be made available on site for such a casting yard.
Option 4 – Bored Pile Retaining Wall with
Anchor
2.6.19
This
scheme involves a series of bored piles (Figure
2.9) constructed consecutively to form a wall to retain the backfill
with a continuous reinforced concrete coping beam to interconnect the tops of
the bored piles. High strength tie
rods are connected near the top of the pile wall at regular intervals and
extend back to an anchor wall on the land side to provide additional support.
2.6.20
Under
this system, the bored pile wall acts as a propped cantilever structure with the
base fixed in rock and the lateral loads such as earth pressure, tidal forces,
berthing force and mooring force resisted in bending of the piles. The anchor system aims to provide
additional support to the bored pile wall and reduce the wall deflection.
2.6.21
The
bored pile retaining wall with anchor would require the least extent of
dredging and would be the most preferred option based on environmental
consideration. The system can be
utilized to minimize excavation and disposal of existing runway material.
2.6.22
Bored
pile construction is widely adopted in
2.6.23
However,
the bored pile retaining wall will not attenuate wave agitation and is
unfavourable for the berthing operation.
The bored pile wall option would not satisfy the general guideline of
ETWB Technical Circular 3/95 about wave reflection control at
Option 5 – Precast Reinforced Concrete
2.6.24
The
reinforced concrete (RC) counterfort wall option (Figure 2.10) can achieve a fast
construction rates provided marine access is not a limiting factor. High standards of workmanship are also
possible because the units can be fabricated at a casting yard on land then
transported to the construction site.
The counterfort wall system is typically a relatively economic
structural system provided that casting yard and heavy lift equipment are
available.
2.6.25
However,
this option would require relatively more amount of dredging at the seawall and
thus not an environmental preferred option. The establishment costs for the
preparation of a floating dock or casting yard with suitable water front access
could also be high. In addition the
mobilisation cost of heavy lifting equipment and floating crane, etc are
comparatively high. Since each
counterfort wall unit may weigh more than 200 tonnes, it is likely that
significant additional costs will arise in securing and utilizing suitable
plant / machinery to handle the units from the market. A wave absorption chamber cannot be
easily incorporated at the front of the counterfont wall hence this structural
system would not comply with ETWB Technical Circular 3/
2.6.26
In
view of the above environmental and engineering disadvantages of the Precast RC
Counterfort Wall option, in particular the extreme difficulties in lifting of
precast units, it is not recommended to consider this option further.
Option 6 – Sheet Pile Cofferdam Wall
2.6.27
The
construction method for the sheet pile cofferdam wall (Figure 2.11) is comparatively simple
and versatile which may not require large numbers of trained / skilled
labourers for the construction works.
2.6.28
However,
potentially significant corrosion of the sheet pile sections would be a major
disadvantage and the sheet piles may therefore need the added cost of cathodic
protection. Moreover, the sheet piled cofferdam option would not satisfy the
general guideline of ETWB Technical Circular 3/95 about wave reflection control
at
2.6.29
In
view of the disadvantages, in particular the corrosion and wave reflection
problems it is not recommended to consider this option further.
Summary
2.6.30
Based
on the review above, Options 4, 5 and 6 are not recommended based on
engineering considerations. All of these
three options would not comply with ETWB Technical Circular 3/95 on wave
reflection control at
2.6.31
Amongst
the three feasible options namely Options 1, 2 and 3, the piled quay deck
(Option 1) would require the least amount of dredging at the existing seawall
during construction. .
2.6.32
In
environmental terms the main difference between Options 1, 2, and 3 is the
volume of dredging from the existing seawall for the
Table 2.2 Approximate
Volume of Dredging from the Existing Seawall
|
Option 1 |
Option 2 |
Option 3 |
Rock armour |
|
|
|
General rockfill |
|
|
|
General fill/ sand |
|
|
|
Alluvium |
- |
|
|
Total Approximate Volume of Dredging |
|
|
|
Notes:
All the material to be dredged from
the existing seawall is expected to be uncontaminated C&D material.
Shaded cell – value assumed in this
EIA for conservative assessment.
2.7
Siltation and Maintenance Dredging
2.7.1
No survey records have been located to suggest
long term siltation rates. However
the rate of siltation has been estimated by comparing sea bed levels adjacent
to the Kai Tak runway in the years 1993 and 2004 based on information on
Navigation Charts. Generally, the average rise of sea bed of
2.7.2
The new manoeuvring basin may reduce
the water currents and enhance the sediment deposition at the basin. In addition, opening a large gap (
2.7.3
A water quality modelling exercise has been conducted
using the modelling tools as described under the water quality impact
assessment in Section 5 of this EIA report. The aim of the modelling exercise was to
provide an indication on the relative change in sedimentation pattern as a
result of the new vessel manoeuvring area and the
2.7.4
The contour plot showing the relative increase in the
sedimentation rate due to the new bathymetry together with the runway opening is given
in Figure
2.7.5
As
mentioned before, the average siltation rates within the navigation area under
the existing condition are expected to be in the range of
Sediment Quality
2.7.6
The sediment quality of the
proposed manoeuvring area has been under the influences of various water
pollution sources in the
2.7.7
Stage
Dredging Rate and
Method
2.7.8
It
is assumed that the siltation rate will be in the order of
2.8.1
The
following definitions of the study areas have been adopted with reference to
the EIA Study Brief (No. ESB-159/2006) registered under the EIAO:
l
Air
Quality Impact: the assessment area should include the area within
l
Noise
Impact Assessment: the assessment area should include the area within
l
Water
Quality Impact Assessment: the assessment area should include the Victoria
Harbour Water Control Zone (WCZ), Eastern Buffer WCZ, Western Buffer WCZ, Junk
Bay WCZ and Port Shelter WCZ as declared under the Water Pollution Control
Ordinance (see Figure 5.1) or the area likely to be impacted by the Project;
l
Waste
Management: the assessment will be focused on areas within the boundary of the
dredging zones (Figure
l
Marine
Ecology and Fisheries: the assessment area for marine ecological impact will be
the same as that for the water quality impact assessment (see Figure
5.1); and
l
Cultural
Heritage Impact: the assessment for cultural heritage impact will focus on the
area within the boundary the proposed dredging zones (Figure
2.9
Interaction with Other Projects
Land-based Works
2.9.1
Air
quality and noise impact assessments have taken into account other concurrent
activities within
Marine Works
2.9.2
In
accordance with the EIA Study Brief (No. ESB-159/2006), the assessment area for
water quality and marine ecology should include the Victoria Harbour Water
Control Zone (WCZ), Eastern Buffer WCZ, Western Buffer WCZ, Junk Bay WCZ and
Port Shelter WCZ.
Kai Tak Development (KTD) Area
2.9.3
Possible
concurrent marine works within or near the KTD area include the following:
l
Submarine
gas pipelines relocation to the west of the former
l
Opening
a
l
Construction
of piled deck to cover the
l
Construction
of the proposed public landing steps cum fireboat berth at the former
l
Decommissioning
of the disused fuel dolphin in
l
Construction
of Central Kowloon Route (CKR) near the corner of inner
l
Construction
of Road T
2.9.4
The
programmes for these possible marine works showing potential overlap with the
proposed dredging works for cruise terminal is given in Appendix 2.1. The locations of these concurrent marine
works are indicated in Figure 2.12.
2.9.5
The
submarine gas pipelines diversion programme and the alignment of the new gas
pipelines are still subject to confirmation by detailed design. The Hong Kong and China Gas Company
Limited (HKCGCL) have indicated two possible alignments for the new gas
pipelines crossing namely an east option (
2.9.6
Also,
in accordance with the advice from HKCGCL, it is assumed that the new pipelines
will be installed and commissioned by 2012 before decommissioning the existing
pipelines in late 2013.
2.9.7
Opening
a
2.9.8
On
the other hand, it is necessary to re-construct a short section of the existing
seawall at the former
2.9.9
There is a disused fuel dolphin at inner
2.9.10
It
should be noted that the
2.9.11
The
construction program for CKR and Road T2 is unavailable at this stage. It is likely that these two concurrent
works cannot commence before 2012.
For the purpose of this EIA, it is assumed that construction of the CKR
and Road T2 would coincide with the cruise terminal Stage 2 dredging for worst
case assessment.
Other External Activities
2.9.12
Based
on the information available from the Wan Chai Development Phase II (WDII)
Planning and Engineering Review, construction of the WDII will commence in 2008
for completion in 2016. Based on
the approved EIA for Further Development of Tseung Kwan O (TKOFS), Phase I
reclamation works at TKO would commence in 2010. Based on the latest
information obtained from CEDD under this EIA, the Phase 1 seawall construction
would commence in early 2012. These marine works could cause
potential cumulative impacts with the proposed dredging works for cruise
terminal.
2.9.13
Construction
of the Western Cross Harbour Main is currently scheduled to complete in 2009
which might cause potential cumulative impacts with the proposed Stage 1
dredging works. Stage
2.9.14
A
new landing facility will be built at Lei Yue Mun under the Lei Yue Mun water
enhancement project. Construction of the landing facility would require
dredging off the landing area and construction of a new breakwater. The Hong Kong offshore wind farm project
involves burying a submarine transmission cable connecting the land point at
the southeast of
2.9.15
Further
elaboration of these external marine works and detailed development of water
quality assessment scenarios are provided in Section 5.6 of this Report.