6                          WASTE MANAGEMENT Implications

6.1                    Introduction

6.1.1               Waste management issues associated with the dredging works for the proposed cruise terminal would be related to dredged marine sediment generated from dredging of the seabed to provide the manoeuvring basin of adequate draught for the cruise vessels and construction and demolition (C&D) material generated from dredging of the existing seawall at the southern tip of the former Kai Tak Airport runway for construction of the quay deck structure.  Potential environmental impacts that may result from these identified wastes arisings are evaluated, and mitigation measures on the handling, transportation and disposal of these wastes are recommended with reference to the applicable waste legislation and guidelines.

6.2                    Environmental Legislation, Policies, Plans, Standards and Criteria

6.2.1               The criteria and guidelines for assessing waste management implications are set out in Annex 7 and Annex 15 of the Technical Memorandum on Environmental Impact Assessment Ordinance (EIAO-TM), respectively.

6.2.2               The following legislation relates to the handling, treatment and disposal of wastes in the Hong Kong SAR and has been used in assessing potential impacts:

l              Waste Disposal Ordinance (Cap. 354C)

l              Waste Disposal (Chemical Waste) (General) Regulation (Cap. 354C)

l              Land (Miscellaneous Provisions) Ordinance (Cap. 28)

l              Public Health and Municipal Services Ordinance (Cap. 132) - Public Cleansing and Prevention of Nuisances Regulation

l              Waste Disposal (Charges for Disposal of Construction Waste) Regulation (Cap. 354N)

Waste Management

6.2.3               The Waste Disposal Ordinance (WDO) prohibits the unauthorised disposal of wastes.  Construction waste is defined as any substance, matter or thing that is generated from construction work and abandoned, whether or not it has been processed or stockpiled before being abandoned, but does not include any sludge, screenings or matter removed in or generated from any desludging, desilting or dredging works.  Under the WDO, wastes can be disposed of only at designated waste disposal facilities.

6.2.4               Under the WDO, the Chemical Waste (General) Regulation 1992 provides regulations for chemical waste control, and administers the possession, storage, collection, transport and disposal of chemical wastes.  The Environmental Protection Department (EPD) has also issued a guideline document, the Code of Practice on the Packaging, Labelling and Storage of Chemical Wastes (1992), which details how the Contractor should comply with the regulations on chemical wastes.

6.2.5               The Public Cleansing and Prevention of Nuisances Regulation provides control on illegal tipping of wastes on unauthorised (unlicensed) sites.

Dredged Marine Sediment

6.2.6               The ETWB TCW No. 34/2002 sets out the procedure for seeking approval to dredge / excavate sediment and the management framework for marine disposal of dredged / excavated sediment.  This Technical Circular outlines the requirements to be followed in assessing and classifying the sediment and explains the marine disposal arrangement for the classified material.  The sediment quality criteria for the classification of sediment are presented in Table 6.1.

6.2.7               Dumping permits from EPD are required for marine disposal of dredged materials.

Chemical Waste

6.2.8               Under the Waste Disposal (Chemical Waste) (General) Regulations, all producers of chemical waste must register with EPD and treat their wastes, either utilising on-site plant licensed by EPD, or arranging for a licensed collector to transport the wastes to a licensed facility.  The regulation also prescribes the storage facilities to be provided on site, including labelling and warning signs, and requires the preparation of written procedures and training to deal with emergencies such as spillages, leakages or accidents arising from the storage of chemical wastes.

Construction and Demolition (C&D) Materials

6.2.9               The current policy related to the disposal of C&D material is documented in the Works Branch Technical Circular No. 2/93, ‘Public Dumps’.  Construction and demolition materials that are wholly inert, namely public fill, should not be disposed of to landfill, but taken to public filling areas, which usually form part of reclamation schemes.  The Land (Miscellaneous Provisions) Ordinance requires that dumping licences be obtained by individuals or companies who deliver public fill to public filling areas.  The Civil Engineering and Development Department (CEDD) issues the licences under delegated powers from the Director of Lands.

6.2.10           Under the Waste Disposal (Charges for Disposal of Construction Waste) Regulation, enacted in January 2006, construction waste delivered to a landfill for disposal must not contain more than 50% by weight of inert material.  Construction waste delivered to a sorting facility for disposal must contain more than 50% by weight of inert material, and construction waste delivered to a public fill reception facility for disposal must consist entirely of inert material. The Environment, Transport and Works Bureau (ETWB) TCW No. 31/2004, “Trip Ticket System for Disposal of Construction & Demolition Materials” provides measures to track the disposal of C&D materials.  Details of the ETWB TCW No. 31/2004 are given in Appendix 6.1a.

6.2.11           Measures have been introduced under ETWB TCW No. 33/2002, “Management of Construction and Demolition Material Including Rock” to enhance the management of construction and demolition material, and to minimize its generation at source.  The enhancement measures include: (i) drawing up a Construction and Demolition Material Management Plan (C&DMMP) at the feasibility study or preliminary design stage to minimize C&D material generation and encourage proper management of such material; (ii) vetting of the C&DMMP prior to upgrading of the project to Category A in the Public Works Programme; and (iii) providing the contractor with information from the C&DMMP in order to facilitate him in the preparation of the Waste Management Plan (WMP) and to minimize C&D material generation during construction.  Projects generating C&D material less than 50,000m3 or importing fill material less than 50,000m3 are exempt from the C&DMMP.  The new ETWB TCW No. 19/2005 “Environmental Management on Construction Sites” includes procedures on waste management requiring contractors to reduce the C&D material to be disposed of during the course of construction.  Under ETWB TCW No. 19/2005, the contractor is required to prepare and implement an Environmental Management Plan (EMP) and the WMP becomes part of the EMP. Reference should also be made to the ETWB TCW No. 31/2004 “Trip Ticket System for Disposal of Construction and Demolition Materials” as attached in Appendix 6.1a.

6.3                    Assessment Methodology

General

6.3.1               The criteria for assessing waste management implications are outlined in Annex 7 of the EIAO-TM.  The methods for assessing potential waste management impacts during the construction phase of the Project follow those presented in Annex 15 of the EIAO-TM and include the following:

l            Estimation of the types and quantities of the wastes generated.

l            Assessment of potential impacts from the management of solid waste with respect to potential hazards, air and odour emissions, noise, wastewater discharge and transport.

l            Assessment of impacts on the capacity of waste collection, transfer and disposal facilities.

Dredged Marine Sediment

6.3.2               A Sediment Sampling Proposal (SSP) was originally prepared by “Meinhardt Infrastructure and Environmental Limited” in accordance with the technical circular Management of Dredge / Excavated Sediment (ETWB TCW No. 34/2002) and it is intended that the sampling and the testing results will be needed for supporting future dumping permit application for the dredged spoil for the proposed Cruise Terminal at Kai Tak.  The SSP was submitted and agreed with the Marine Dumpling Section of the EPD on 14 September 2006 on the scope of works and testing requirements with respect to ETWB TCW No. 34/2002.

6.3.3               In order to fulfil the requirements of EIA Study Brief for the feasibility study of Kai Tak Development, the scope of the sampling and testing services was expanded and the Revised Sediment Sampling Proposal (RSSP) was submitted.  The Revised Sediment Sampling Proposal (RSSP Rev 2) was endorsed by EPD as partially fulfilled the requirements stipulated in Sections 3.4.7.6(k) and 3.4.9.2(iii) of the EIA Study Brief for the feasibility study of Kai Tak Development on 28 December 2006.  The endorsed RSSP Rev 2 is included in Appendix 6.1 of this report.

6.3.4               Marine site investigation (SI) to determine the contamination level of the seabed to be dredged for the manoeuvring basin of the cruise terminal has been conducted by CEDD under Agreement No. KDO 01/2006 in two phases for Sub-area A and Sub-area B respectively (i.e. Phase A and Phase B respectively as stated in the Sediment Quality Report (SQR) attached in Appendix 6.2).  The first phase of the marine SI (for Sub-area A) commenced on 15 January 2007 and was completed on 23 January 2007 and comprised 30 sampling stations (stations A01-A30) (refer to Figure 6.1).  The second phase of the marine SI (for Sub-area B) commenced on 23 February 2007 and was completed on 10 March 2007 and comprised 43 sampling stations (stations B01-B43) (refer to Figure 6.1).  The marine SI comprised grab sampling and vibrocoring to obtain sediment samples for chemical testing.

6.3.5               In January 2007, Maunsell Consultants Asia Limited (MCAL) was commissioned by CEDD to undertake Agreement No. CE35/2006 (CE) – Kai Tak Development Engineering Study cum Design and Construction of Advance Works – Investigation, Design and Construction. The dredging extent for the proposed Cruise Terminal has been revised and is shown in Figure 2.4a.  The RSSP Rev 2 has been reviewed in relation to the revised dredging extent and it is consider that the sediment sampling locations of RSSP Rev 2 are applicable and adequate for the revised dredging extent.  The RSSP Rev 2 was accepted by EPD as partially fulfilled the requirements stipulated in Sections 3.4.7.6(k) and 3.4.9.2 (iii) of EIA Study Brief for the feasibility study of Kai Tak Development and Sections 3.4.7.5(viii) and 3.4.8.2(iii)(a) of EIA Study Brief No. ESB-159/2006 (for Dredging Works for Proposed Cruise Terminal at Kai Tak) for the revised dredging extent on 12 June 2007.

Chemical Testing

6.3.6               Each sub-sample recovered from the marine SI was tested in the laboratory for the following parameters:

(i)             Metal and metalloid concentrations including chromium (Cr), copper (Cu), mercury (Hg), lead (Pb), cadmium (Cd), nickel (Ni), zinc (Zn), silver (Ag) and arsenic (As);

(ii)           Concentrations of organic compounds including total polychlorinated biphenyls (PCBs), polyaromatic hydrocarbons (PAHs); and

(iii)          Concentration of tributyltin (TBT) in interstitial water.

6.3.7               Elutriate tests were conducted to assess the likelihood of release of contaminants from sediment to the water, when the seabed is disturbed during dredging.  If the contaminant levels are higher in the elutriates in comparison with the sample of marine water from the same site, it can be concluded that the contaminants are likely to be released into the open waters during dredging activities.  The potential water quality impacts associated with the dredging of sediment are discussed in Section 5 of this Report.

6.3.8               Under the management and classification system, dredged sediments destined for marine disposal are classified according to their level of contamination by 13 contaminants (Table 6.1).

Table 6.1                        SedimentQuality Criteria for the Classification of Sediment

Contaminants

LCEL

UCEL

Heavy Metal (mg/kg dry weight)

Cadmium (Cd)

1.5

4

Chromium (Cr)

80

160

Copper (Cu)

65

110

Mercury (Hg)

0.5

1

Nickel (Ni)

40

40

Lead (Pb)

75

110

Silver (Ag)

1

2

Zinc (Zn)

200

270

Metalloid (mg/kg dry weight)

Arsenic

12

42

Organic-PAHs (µg/kg dry weight)

PAHs (Low Molecular Weight)

550

3160

PAHs (High Molecular Weight)

1700

9600

Organic-non-PAHs (µg/kg dry weight)

Total PCBs

23

180

Organometallics (µg-TBT L-1 in interstitial water)

Tributyltin

0.15

0.15

Source:  Appendix A of ETWB TCW No. 34/2002 Management of Dredged / Excavated Sediment

Note:     LCEL   Lower Chemical Exceedance Level

                       UCEL              Upper Chemical Exceedance Level

6.3.9               Sediments are categorised with reference to the LCEL and UCEL, as follows:

Category L      Sediment with all contaminant levels not exceeding the LCEL.  The material must be dredged, transported and disposed of in a manner that minimises the loss of contaminants either into solution or by suspension.

Category M     Sediment with any one or more contaminant levels exceeding the LCEL and none exceeding the UCEL.  The material must be dredged and transported with care, and must be effectively isolated from the environment upon final disposal unless appropriate biological tests demonstrate that the material will not adversely affect the marine environment.

Category H      Sediment with any one or more contaminant levels exceeding the UCEL.  The material must be dredged and transported with great care, and must be effectively isolated from the environment upon final disposal.

6.3.10           In the case of Category M and Category H contamination, the final determination of appropriate disposal options, routing and the allocation of a permit to dispose of material at a designated site will be made by EPD and the Marine Fill Committee (MFC) in accordance with the ETWB TCW No. 34/2002.

Biological Testing

6.3.11           For Category M sediment, Tier III biological screening was carried out to determine the appropriate disposal methods in accordance with the requirements of ETWB TCW No. 34/2002:

(i)             a 10‑day burrowing amphipod toxicity test;

(ii)           a 20‑day burrowing polychaete toxicity test; and

(iii)          a 48‑96 hour larvae (bivalve) toxicity test.

6.3.12           The species used for each type of biological test and the test conditions are listed in Table 6.2 below.

Table 6.2                        TestSpecies for Biological Testing

           Test Types          

Species

Reference Test Conditions*

10‑day  burrowing amphipod toxicity test

Leptocheirus plumulosus

U.S.EPA (1994)

20‑day  burrowing polychaete toxicity test

Neanthes arenaceodentata

PSEP (1995)

48‑96 hour bivalve larvae toxicity test

Mytilus spp. or Crassostrea gigas

PSEP (1995)

Notes:*

(i)     U.S.EPA (U.S. Environmental Protection Agency) 1994.  Methods for assessing the toxicity of sediment-associated contaminants with estuarine and marine amphipods.  Office of Research and Development. U.S. Environmental Protection Agency, Cincinnati, OH. EPA/600/R94/025.

(ii)        PSEP (Puget Sound Estuary Program) 1995. Recommended guidelines for conducting laboratory bioassays on Puget Sound sediments.

6.3.13           Sediment samples were characterized by the testing laboratory for ancillary testing parameters such as pore water salinity, ammonia, TOC, grain size and moisture content.  This provided necessary information on the general characteristics of the sediment.  The test endpoints and decision criteria are summarized in Table 6.3.  The sediment was deemed to have failed the biological testing if it failed in any one of the three toxicity tests.

Table 6.3                        TestEndpoints and Decision Criteria for Biological Testing 

Toxicity test

Endpoints measured

Failure criteria

10-day amphipod

Survival

Mean survival in test sediment is significantly different (p £ 0.05)1 from mean survival in reference sediment and mean survival in test sediment < 80% of mean survival in reference sediment.

20-day polychaete

Dry Weight2

Mean dry weight in test sediment is significantly different (p £ 0.05)1 from mean dry weight in reference sediment and mean dry weight in test sediment < 90% of mean dry weight in reference sediment.

48-96 hour bivalve larvae

 

Normality Survival3

Mean normality survival in test sediment is significantly different (p £ 0.05)1 from mean normality survival in reference sediment and mean normality survival in test sediment < 80% of mean normality survival in reference sediment.

1        Statistically significant differences should be determined using appropriate two-sample comparisons (e.g., t-tests) at a probability of  p £  0.05.

2        Dry weight means total dry weight after deducting dead and missing worms.

3    Normality survival integrates the normality and survival end points, and measures survival of only the normal larvae relative to the starting number.

6.4                    Baseline Conditions

Existing Sediment Characteristics

6.4.1               A review of the sediment testing results for the samples collected from Sub-area A during the first phase of the marine SI (i.e. Phase A as stated in the SQR) indicates that Category H sediment was found at sampling stations A01 to A05, A10 and A26 due to high contaminant levels of Cu, Ni, Hg and Ag that exceeded the UCEL of these four metals.  Category M sediment was found at sampling stations A04, A07 to A9, A11, A15 and A25 due to the contaminants of Hg and PCBs.  Out of a total of ninety-eight samples collected from Sub-area A, seven samples were classified as Category M and seven samples were classified as Category H, indicating that the sediment samples were mostly classified as Category L.  The results of the sediment quality analysis, as compared with the sediment quality criteria for the classification of sediment, are presented in Table 6.4 for those samples with contaminant levels exceeding the LCEL or UCEL.  Please refer to Appendix B of the Sediment Quality Report as attached in Appendix 6.2 of this EIA report for a complete and comprehensive summary of sediment chemical screening/ results.

6.4.2               A review of the sediment testing results for the samples collected from Sub-area B during the second phase of the marine SI (i.e. Phase B as stated in the SQR) indicates that Category H sediment was found at sampling stations B02, B03, B21 and B33 due to high contaminant levels of Ag that exceeded the UCEL of this metal.  Category M sediment was found at sampling stations B01, B23, B26, B31, B37 and B39 due to the contaminants of Cu, Hg, Ag and PCBs.  Out of a total of sixty-nine samples collected from Sub-area B, six samples were classified as Category M and five samples were classified as Category H, indicating that the sediment samples were mostly classified as Category L.  The results of the sediment quality analysis, as compared with the sediment quality criteria for the classification of sediment, are presented in Table 6.5 for those samples with contaminant levels exceeding the LCEL or UCEL.  Details of the marine site investigation and laboratory testing results are provided in Appendix 6.2.

6.4.3               Based on the results of chemical screening under Agreement No. KDO 01/2006, approximately 15% of the sediment samples were classified as Category M or H.


Table 6.4                        SedimentChemistry Results Showing Exceedances (from Sub-area A of Marine SI)

Station

Sample Depth (m)

Cd

mg/kg

Cr

mg/kg

Cu

mg/kg

Ni

Mg/kg

Pb

mg/kg

Zn

mg/kg

Hg

mg/kg

As

mg/kg

Ag

mg/kg

TBT

µgTBT/L

LPAH

µg/kg

HPAH

µg/kg

PCBs

µg/kg

Category

Disposal Option

From

To

 

 

UCEL

4

160

110

40

110

270

1

42

2

0.15

3160

9600

180

-

-

 

 

LCEL

1.5

80

65

40

75

200

0.5

12

1

0.15

550

1700

23

-

-

A05

0.0

0.9

<0.2

26

29

20

110

120

2.6

7.8

0.27

<0.015

110

790

<3.0

H

Type 2

A01

4.9

5.9

0.23

72

22

52

84

160

0.28

20

0.1

<0.015

<55

<170

<3.0

H

Type 2

A03

0.0

0.9

0.5

48

160

18

63

130

0.78

6.9

2.4

<0.015

140

1400

6.8

H

Type 2

A04

0.0

0.9

0.4

48

140

20

54

150

0.58

7.4

2.8

<0.015

90

630

110

H

Type 2

A04

0.9

1.9

<0.2

25

16

18

74

82

1.0

7.4

0.16

<0.015

81

450

<3.0

M

*

A08

0.0

0.9

0.23

28

62

14

61

80

0.89

6.6

0.61

<0.015

<55

<170

6

M

*

A07

0.0

0.9

<0.2

18

18

11

54

63

0.74

5.7

0.21

<0.015

<55

360

20

M

*

A11

0.0

0.9

0.36

37

110

17

52

93

0.47

6.3

1.0

<0.015

99

640

89

M

*

A02

0.0

0.9

<0.2

24

34

18

88

130

1.7

7.8

0.32

<0.015

<55

260

<3.0

H

Type 2

A26

0.9

1.9

<0.2

21

<7.0

43

15

39

<0.05

3.9

<0.1

<0.015

<55

<170

<3.0

H

Type 2

A10

0.0

0.9

0.94

54

270

23

50

140

0.68

6.9

2.5

<0.015

<55

640

7.5

H

Type 2

A09

0.0

0.9

<0.2

24

34

14

55

78

0.68

7

0.34

<0.015

120

1300

9.4

M

*

A15

0.0

0.9

<0.2

14

13

10

50

53

0.59

5.9

<0.1

<0.015

<55

290

<3.0

M

*

A25

0.0

0.9

<0.2

16

21

8.6

37

62

0.62

4.4

0.24

<0.015

69

760

3.6

M

*

Notes:

Shaded Cell = Value exceeded UCEL; Underlined Cell = Value exceeded LCEL; “<” = below reporting limit

               “*” = to be determined upon completion of biological screening

Category and disposal option follows ETWB TCW No. 34/2002 (Annex B)

Table 6.5                        SedimentChemistry Results Showing Exceedances (fromSub-area B of Marine SI)

Station

Sample Depth (m)

Cd

mg/kg

Cr

mg/kg

Cu

mg/kg

Ni

Mg/kg

Pb

mg/kg

Zn

mg/kg

Hg

mg/kg

As

mg/kg

Ag

mg/kg

TBT

µgTBT/L

LPAH

µg/kg

HPAH

µg/kg

PCBs

µg/kg

Category

Disposal Option

From

To

 

 

UCEL

4

160

110

40

110

270

1

42

2

0.15

3160

9600

180

-

-

 

 

LCEL

1.5

80

65

40

75

200

0.5

12

1

0.15

550

1700

23

-

-

B01

0.0

0.9

<0.2

21

30

12

66

71

1.0

6.3

0.28

<0.015

140

840

6.8

M

*

B02

0.0

0.7

0.26

40

100

14

65

110

0.78

6.4

2.2

<0.015

<55

470

120

H

Type 2

B03

0.0

0.5

0.25

39

99

13

37

110

0.42

6.4

2.1

<0.015

100

960

21

H

Type 2

B21

0.9

1.9

<0.2

21

<7

14

17

43

<0.05

3.4

4.6

<0.015

<55

<170

<3

H

Type 2

B23

0.0

0.9

<0.2

22

51

8.4

27

72

0.19

3.9

1.6

<0.015

<55

<170

32

M

*

B26

0.0

0.4

<0.2

22

64

8.6

26

63

0.26

3.4

1.2

<0.015

<55

<170

<3

M

*

B31

0.9

1.9

<0.2

12

<7

7.7

16

24

0.05

4.2

2.0

<0.015

<55

<170

<3

M

*

B33

0.0

0.9

<0.2

15

<7

9.6

15

30

0.10

3.5

2.2

<0.015

<55

<170

<3

H

Type 2

B33

0.9

1.9

<0.2

15

<7

9.5

16

27

<0.05

3.4

2.6

<0.015

<55

<170

<3

H

Type 2

B37

0.0

0.3

<0.2

26

66

11

32

75

0.21

6.9

1.7

<0.015

<55

<170

<3

M

 

B39

0.0

0.3

<0.2

10

31

4.1

37

43

0.71

2.3

0.65

<0.015

<55

<170

<3

M

*

Notes:

Shaded Cell = Value exceeded UCEL; Underlined Cell = Value exceeded LCEL; “<” = below reporting limit

               “*” = to be determined upon completion of biological screening

Category and disposal option follows ETWB TCW No. 34/2002 (Annex B)


6.4.4               Tier III biological screening was conducted for the Category M sediment samples as described above.  The results of the biological screening are summarized in Table 6.6 below.   A composite test sample was prepared from samples A08 and A11 since these two samples are continuous in horizontal profile and of similar depth.  The other Category M samples collected from Sub-area A during the first phase of marine SI were tested individually.  As the Category M samples collected from Sub-area B during the second phase of marine SI are discrete (i.e. not being continuous in either horizontal or vertical profile), no composing was arranged and each sample was tested individually.

Table 6.6                        Resultsof Biological Screening of Category M Samples

Vibrocore No. / Depth

Amphipod Test

Polychaete Test

Bivalve Test

Result of Biological Screening

A04

0.9 – 1.9m

Ö

Ö

Ö

Pass

A07

0 – 0.9m

Ö

Ö

Ö

Pass

A08 & A11

0 – 0.9m

Ö

Ö

Ö

Pass

A09

0 – 0.9m

Ö

Ö

X

Fail

A15

0 – 0.9m

Ö

X

X

Fail

A25

0 – 0.9m

Ö

Ö

Ö

Pass

B01

0 – 0.9m

Ö

X

X

Fail

B23

0 - 0.9m

Ö

Ö

X

Fail

B26

0 - 0.4m

Ö

Ö

X

Fail

 

B31

0.9 - 1.9m

Ö

Ö

Ö

Pass

B37

0 - 0.3m

Ö

Ö

Ö

Pass

B39

0 - 0.3m

Ö

Ö

X

Fail

Notes:

X = fail biological test

Ö = pass biological test

 

6.5                    Identification of Potential Sources of Environmental Impact

6.5.1               The construction phase activities to be carried out for the proposed Project would generate a variety of wastes that can be divided into distinct categories based on their composition and ultimate method of disposal.  The identified waste types include: 

l            Marine dredged sediment

l            C&D material

l            Chemical waste

l            General refuse

6.5.2               Each type of waste arising is described below, together with an evaluation of the potential environmental impacts associated with the generation, handling, storage and transport of the waste.

6.6                    Prediction and Evaluation of Environmental Impacts

Dredged Marine Sediment

Capital Dredging During Construction Phase

6.6.1               The initial capital dredging for the manoeuvring basin for operation of the Phase I Berth and the Phase II Berth of the proposed cruise terminal should allow for dredging to -12mCD.  The existing seabed levels within the dredging area are based on the bathymetric survey carried out under Agreement No. KDO 01/2006 “Site Investigation and Contaminated Assessment at Remaining Area of Former Kai Tak Airport and Proposed Cruise Terminal Geophysical Survey Work”.  The total in-situ volume of dredging required for the manoeuvring basin of the Phase I Berth and the Phase II Berth is estimated to be 1,380,000 m3 (700,000 m3 for the manoeuvring basin of the Phase I Berth and 680,000 m3 for the manoeuvring basin of the Phase II Berth).

6.6.2               The chemical and biological screening results presented in Section 6.4 above identified the locations and the corresponding depths of the contaminated sediment.  The disposal options for the identified contaminated sediment as determined in accordance with ETWB TCW No. 34/2002 are summarised in Table 6.7 below.

Table 6.7                        DisposalOptions for the Identified Contaminated Sediment

Station

Depth

Sediment Category

Disposal Option

From

To

A05

0.0

0.9

H

Type 2 – Confined Marine Disposal

A01

4.9

5.9

H

Type 2 – Confined Marine Disposal

A03

0.0

0.9

H

Type 2 – Confined Marine Disposal

A04

0.0

0.9

H

Type 2 – Confined Marine Disposal

A04

0.9

1.9

M

Type 1 – Open Sea Disposal (Dedicated Sites)

A08

0.0

0.9

M

Type 1 – Open Sea Disposal (Dedicated Sites)

A07

0.0

0.9

M

Type 1 – Open Sea Disposal (Dedicated Sites)

A11

0.0

0.9

M

Type 1 – Open Sea Disposal (Dedicated Sites)

A02

0.0

0.9

H

Type 2 – Confined Marine Disposal

A26

0.9

1.9

H

Type 2 – Confined Marine Disposal

A10

0.0

0.9

H

Type 2 – Confined Marine Disposal

A09

0.0

0.9

M

Type 2 – Confined Marine Disposal

A15

0.0

0.9

M

Type 2 – Confined Marine Disposal

A25

0.0

0.9

M

Type 1 – Open Sea Disposal (Dedicated Sites)

B01

0.0

0.9

M

Type 2 – Confined Marine Disposal

B02

0.0

0.7

H

Type 2 – Confined Marine Disposal

B03

0.0

0.5

H

Type 2 – Confined Marine Disposal

B21

0.9

1.9

H

Type 2 – Confined Marine Disposal

B23

0.0

0.9

M

Type 2 – Confined Marine Disposal

B26

0.0

0.4

M

Type 2 – Confined Marine Disposal

B31

0.9

1.9

M

Type 1 – Open Sea Disposal (Dedicated Sites)

B33

0.0

0.9

H

Type 2 – Confined Marine Disposal

B33

0.9

1.9

H

Type 2 – Confined Marine Disposal

B37

0.0

0.3

M

Type 1 – Open Sea Disposal (Dedicated Sites)

B39

0.0

0.3

M

Type 2 – Confined Marine Disposal

 

6.6.3               The volume of contaminated sediment within the dredging area for the manoeuvring basin of the Phase I Berth and the Phase II Berth is estimated based on the sediment testing results summarized above in Table 6.7.  The locations of contaminated sediment are represented by grab or vibrocore sampling stations.  The estimation is undertaken to determine the volume of contaminated sediment to be dredged taking into account the proposed dredging area and the dredging depth profile.

6.6.4               The potential extent of the identified contaminated sediment are shown in Figure 6.1.  The volume of sediment requiring different disposal options in accordance ETWB TCW No. 34/2002 are summarised in Table 6.8 below.

Table 6.8                        Volumeof Sediment Requiring Different Disposal Options (in m3)

Disposal Option

Stage 1 Dredging

Stage 2 Dredging

Type 1 – Open Sea Disposal

490,000

460,000

Type 1 – Open Sea Disposal (Dedicated Sites)

25,000

90,000

Type 2 – Confined Marine Disposal

185,000

130,000

Sub-total

700,000

680,000

Total

1,380,000

Note:             All materials to be generated from the removal of the existing seawall for berth construction are expected to be C&D material (i.e. no sediment would be generated from the removal of the existing seawall).

 

Maintenance Dredging During Operational Phase of the Proposed Cruise Terminal

6.6.5               It is assumed that the siltation rate will be in the order of 100mm per year (refer to Section 2.7).  As such up to 500mm of sediment will need to be dredged every 5 to 10 years.  Given that the area needed for manoeuvring of vessels is approximately 700,000 m2, then this represents a dredged volume of approximately 350,000 m3 every 5 to 10 years.

6.6.6               As discussed in Section 2.7, there would be a long term improvement in the sediment quality of the manoeuvring area.  In any case, maintenance dredging would require sediment sampling and testing in accordance with the requirements of the ETWB TCW No. 34/2002 for proper disposal of the uncontaminated and contaminated dredged sediment.  Marine Fill Committee (MFC) would determine the most appropriate open sea or confined marine disposal site on the basis of the chemical and biological test results and formally allocate marine disposal space in accordance with the ETWB TCW No. 34/2002. Therefore, no adverse waste impact from maintenance dredging would be expected.

Dredging, Transportation and Disposal

6.6.7               To minimise any potential adverse impacts arising from the dredged marine sediment, the sediment should be dredged, transported and disposed of in a manner that would minimise the loss of contaminants either into solution or by resuspension.

6.6.8               As discussed in Section 3, the dredging activities are marine based activities and negligible dust impacts on nearby air sensitive receivers would be expected.  Besides, it is expected that the potential odour emissions from the sediments within the dredging area of the proposed cruise terminal would be minimal and adverse odour impact from the capital and maintenance dredging activities and the associated transportation and disposal would not be anticipated.

6.6.9               The findings of the noise impact assessment presented in Section 4 of this report indicated that adverse noise impact would not be expected during the course of the capital and maintenance dredging activities.

6.6.10           Mitigation measures to minimise potential environmental impacts are recommended in Section 6.7.  With the implementation of the recommended mitigation measures, no unacceptable impacts would be expected from the dredging, transportation and disposal of the dredged sediment.

Construction and Demolition Material

6.6.11           C&D material would be generated from the removal of a section of the existing seawall by dredging at the southern tip of the former Kai Tak Airport runway to facilitate construction of a quay deck structure for the two berths of the cruise terminal.  The estimated volume of C&D material to be removed from the existing seawall by dredging is approximately 322,300 m3. The C&D material would comprise rockfill, general fill and rock armour.  Approximately 20,000 m3 of pell mell rubble would be generated from the removal of the existing abandoned Kai Tak Runway submarine outfall. No C&D material would be generated from the maintenance dredging.

6.6.12           It is assumed all the C&D material generated from the Project would require off-site disposal. Seawall construction relies very heavily on the grading of materials. If the materials are not graded properly then there is the risk that the reclamation will wash out through the seawall and the seawall will collapse. Whilst the as-built drawings of the existing runway seawalls and reclamations have been obtained they do not give any information as to the grading of the existing materials. As such it is not possible with the information available to make any accurate assessment as to which materials may be suitable for reuse. As such a conservative estimate has been made for the purpose of the EIA.

6.6.13           Nevertheless, the contractor for capital dredging should investigate the potential for reusing the C&D materials on site. If practical, the C&D material generated from the Project should be sorted and any unsuitable material removed to achieve the correct grading for seawall construction. In other words, it may be possible that the existing material could be blended with other new material to achieve the required grading for seawall construction.

6.6.14            The C&D material to be disposed off-site should be transported and handled in a manner that would minimise the disturbance to the environment.  Mitigation measures to minimise potential environmental impacts are recommended in Section 6.7.  With the implementation of the recommended mitigation measures, no unacceptable impacts would be expected from the transportation and disposal of the C&D material.

6.6.15           With regard to the material to be generated from the removal of the abandoned Kai Tak Runway submarine outfall, much of the material will be removed by grab dredger, using marine plant, with no clear view of what is being picked up the grab underwater. As such the material being loaded into the barge will be a mixture of rubble and marine mud. It is not practical to assume that these materials can be separated during the dredging process. Dredging works for removal of the abandoned Kai Tak Runway submarine outfall will be incorporated into the Stage 1 dredging works and all material generated from the outfall removal would be disposed off-site as marine sediments.

 

Chemical Waste

6.6.16           The maintenance and servicing of construction plant and equipment may generate some chemical wastes such as cleaning fluids, solvents, lubrication oil and fuel.  It is difficult to quantify the amount of chemical waste that will arise from the construction activities since it will be dependent on the contractor’s maintenance requirements and the amount of plant utilised.  However, it is anticipated that the quantity of chemical waste, such as lubricating oil and solvent produced from plant maintenance, would be small and in the order of a few cubic metres per month during both capital and maintenance dredging.  The amount of chemical waste to be generated will be quantified in the site Waste Management Plan to be prepared by the contractor.

6.6.17           Chemical wastes arising during the construction phase may pose environmental, health and safety hazards if not stored and disposed of in an appropriate manner as stipulated in the Waste Disposal (Chemical Waste) (General) Regulations.  The potential hazards include:

l            Toxic effects to workers

l            Adverse impacts on water quality from spills

l            Fire hazards

6.6.18           Materials classified as chemical wastes will require special handling and storage arrangements before removal for appropriate treatment at the Chemical Waste Treatment Facility (CWTF) or other licensed facility.  Wherever possible, opportunities should be taken to reuse and recycle materials.  Mitigation and control requirements for chemical wastes are detailed in Section 6.7.  Provided that the handling, storage and disposal of chemical wastes are in accordance with these requirements, adverse environmental impacts would not be expected to result.

General Refuse

6.6.19           The workforce to be involved in the capital and maintenance dredging would generate general refuse comprising food scraps, waste paper, empty containers, etc.  Release of general refuse into the marine water or surface channel should not be permitted as introduction of these wastes is likely to have detrimental effects on water quality in the area.  Rapid and effective collection of site wastes would be required to prevent waste materials being blown around by wind, flushed or leached into the aquatic environment, and odour nuisance.  The work sites may also attract pests and vermin if the waste storage area is not well maintained and cleaned regularly.  Disposal of refuse at sites other than approved waste transfer or disposal facilities can also result in similar impacts.

6.6.20           With the implementation of the recommended waste management practices at the site, adverse environmental impacts are not expected to arise from the storage, handling and transportation of refuse.

6.7                    Mitigation of Environmental Impacts

Good Site Practices

6.7.1               It is not anticipated that adverse waste management related impacts would arise, provided that good site practices are adhered to.  Recommendations for good site practices during the dredging activities include:

Ÿ               Nomination of an approved person, such as a site manager, to be responsible for good site practices, arrangements for collection and effective disposal to an appropriate facility, of all wastes generated at the site.

Ÿ               Training of site personnel in proper waste management and chemical waste handling procedures.

Ÿ               Provision of sufficient waste disposal points and regular collection for disposal.

Ÿ               Appropriate measures to minimise windblown litter and dust during transportation of waste by either covering trucks or by transporting wastes in enclosed containers.

Ÿ               A recording system for the amount of wastes generated, recycled and disposed of (including the disposal sites).

Waste Reduction Measures

6.7.2               As discussed in Section 2.6 of this EIA report, the proposed location for the cruise terminal at the runway tip has the deepest seabed along the former runway and larger manoeuvring space for receiving mega cruise vessels.  The access from and to the main fairway is also a very direct one.  The proposed location for the cruise terminal has thus minimised the extent seabed dredging and hence reduce the volume of dredge sediment generated from the Project.

6.7.3               Besides, the proposed size and configuration of the manoeuvring areas for the cruise terminal was reviewed using real time vessel simulations to be the minimum essential to provide space needed for safe manoeuvring of cruise vessels clear of the fairway and cruise berth. 

6.7.4               With regards to the berth structure, also discussed in Section 2.6, amongst the three feasible options namely Option 1 (Piled Quay Deck), Option 2 (Precast Reinforced Concrete Caisson) and Option 3 (Precast Concrete Blockwork Seawall), the piled quay deck (Option 1) would require the least amount of dredging at the existing seawall during construction.  In environmental terms the main difference between Options 1, 2, and 3 is the volume of dredging from the existing seawall.  It should be noted that the volume of dredging from the existing seawall is comparatively less in the case of Option 1, therefore the allowance for Options 2 and 3 in this EIA represents a worst case assumption (refer to Table 2.2).

6.7.5               On dredging method, closed grab dredgers are considered as the most suitable dredgers for relatively small volumes and contaminated mud.  It is feasible to use small trailer suction dredgers but these will give less control over handling of contaminated mud and produce more marine sediment by volume (due to high water content) when compared with grab dredging.  Whilst larger equipment has been adopted for major reclamation projects such as the Penny’s Bay reclamation and Container Terminals in Kwai Chung, in this case, given that dredging is not on the critical programme path, it is assumed that the most cost effective construction method with the least environmental impact including the production of least dredge sediment will be adopted for the cruise terminal i.e. closed grab dredgers.

6.7.6               Apart from the planning and design measures on waste reduction described above, good management and control can also prevent the generation of a significant amount of waste.  Waste reduction is best achieved at the planning and design stage, as well as by ensuring the implementation of good site practices.  Recommendations to achieve waste reduction include:

Ÿ               Segregation and storage of different types of waste in different containers, skips or stockpiles to enhance reuse or recycling of materials and their proper disposal.

Ÿ               Encourage collection of aluminium cans, PET bottles and paper by providing separate labelled bins to enable these wastes to be segregated from other general refuse generated by the work force.

Ÿ               Any unused chemicals or those with remaining functional capacity shall be recycled.

6.7.7               In addition to the above measures, specific mitigation measures are recommended below for the identified waste arisings to minimise environmental impacts during handling, transportation and disposal of these wastes.

Dredged Marine Sediment

6.7.8               The basic requirements and procedures for dredged mud disposal are specified under the ETWB TCW No. 34/2002.  The management of the dredging, use and disposal of marine mud is monitored by the MFC, while the licensing of marine dumping is required under the Dumping at Sea Ordinance and is the responsibility of the Director of Environmental Protection (DEP).

6.7.9               The dredged marine sediments would be loaded onto barges and transported to the designated disposal sites allocated by the MFC depending on their level of contamination.  Sediment classified as Category L would be suitable for Type 1 - Open Sea Disposal.  Contaminated sediment would require either Type 1 – Open Sea Disposal (Dedicated Sites) or Type 2 - Confined Marine Disposal and must be dredged and transported with great care in accordance with ETWB TCW No. 34/2002.  Subject to the final allocation of the disposal sites by MFC, the dredged contaminated sediment must be effectively isolated from the environment upon final disposal and shall be disposed of at the East Sha Chau Contaminated Mud Pits that are designated for the disposal of contaminated mud in Hong Kong. 

6.7.10           It will be the responsibility of the contractor to satisfy the appropriate authorities that the contamination levels of the marine sediment to be dredged have been analysed and recorded.  According to the ETWB TCW No. 34/2002, this will involve the submission of a formal Sediment Quality Report to the DEP, prior to the dredging contract being tendered. The contractor for the dredging works shall apply for allocation of marine disposal sites and all necessary permits from relevant authorities for the disposal of dredged sediment.During transportation and disposal of the dredged marine sediments requiring Type 1 and Type 2 disposal, the following measures should be taken to minimise potential impacts on water quality:

l            Bottom opening of barges shall be fitted with tight fitting seals to prevent leakage of material.  Excess material shall be cleaned from the decks and exposed fittings of barges and hopper dredgers before the vessel is moved.

l            Monitoring of the barge loading shall be conducted to ensure that loss of material does not take place during transportation.  Transport barges or vessels shall be equipped with automatic self-monitoring devices as required under the Dumping at Sea Ordinance and as specified by the DEP.

l            Barges or hopper barges shall not be filled to a level that would cause the overflow of materials or sediment laden water during loading or transportation.

6.7.11           Negligible dust impacts would be expected from dredging activities.  In order to further ensure compliance with the Air Quality Objectives at the air sensitive receivers, requirements of the Air Pollution Control (Construction Dust) Regulation, where relevant, shall be adhered to during the construction period of the Project.  The dredged sediment placed on barge should be properly covered as far as practicable to minimise the potential odour emissions during the dredging operation and transportation of the dredged sediment.   

6.7.12           In order to further ameliorate the noise impacts associated with the capital and maintenance dredging activities, good site practices listed below should be adopted by all the contractors as far as practicable:

l            Only well-maintained plant should be operated on-site and plant should be serviced regularly during the construction program.

l            Mobile plant, if any, should be sited as far away from nearby noise sensitive receivers as possible.

l            Machines and plant (such as trucks) that may be in intermittent use should be shut down between works periods or should be throttled down to a minimum.

l            Plant known to emit noise strongly in one direction should, wherever possible, be orientated so that the noise is directed away from nearby noise sensitive receivers.

l            Material stockpiles and other structures should be effectively utilised, wherever practicable, in screening noise from on-site construction activities.

Construction and Demolition Material

6.7.13           It is recommended that the extent of dredging of the existing seawall should be kept to a minimum in the detailed design of the new cruise terminal to minimize generation of C&D material.  Mitigation measures and good site practices should be incorporated in the contract document to control potential environmental impact from handling and transportation of C&D material.  The mitigation measures include:

Ÿ               Where it is unavoidable to have transient stockpiles of C&D material within the Project work site pending collection for disposal, the transient stockpiles shall be located away from waterfront or storm drains as far as possible.

Ÿ               Open stockpiles of construction materials or construction wastes on-site should be covered with tarpaulin or similar fabric.

Ÿ               Skip hoist for material transport should be totally enclosed by impervious sheeting.

Ÿ               Every vehicle should be washed to remove any dusty materials from its body and wheels before leaving a construction site.

Ÿ               The area where vehicle washing takes place and the section of the road between the washing facilities and the exit point should be paved with concrete, bituminous materials or hardcores.

Ÿ               The load of dusty materials carried by vehicle leaving a construction site should be covered entirely by clean impervious sheeting to ensure dust materials do not leak from the vehicle.

Ÿ               All dusty materials should be sprayed with water prior to any loading, unloading or transfer operation so as to maintain the dusty materials wet.

Ÿ               The height from which excavated materials are dropped should be controlled to a minimum practical height to limit fugitive dust generation from unloading.

6.7.14           When delivering inert C&D material to public fill reception facilities, the material shall consist entirely of inert construction waste and of size less than 250mm or other sizes as agreed with the Secretary of the Public Fill Committee.  In order to monitor the disposal of the surplus C&D material at the designed public fill reception facility and to control fly tipping, a trip-ticket system as stipulated in the ETWB TCW No. 31/2004 “Trip Ticket System for Disposal of Construction and Demolition Materials” should be included as one of the contractual requirements and implemented by an Environmental Team undertaking the Environmental Monitoring and Audit work.  An Independent Environmental Checker should be responsible for auditing the results of the system.

Chemical Waste

6.7.15           After use, chemical wastes (for example, cleaning fluids, solvents, lubrication oil and fuel) should be handled according to the Code of Practice on the Packaging, Labelling and Storage of Chemical Wastes.  Spent chemicals should be collected by a licensed collector for disposal at the CWTF or other licensed facility, in accordance with the Waste Disposal (Chemical Waste) (General) Regulation.

General Refuse

6.7.16           General refuse should be stored in enclosed bins or compaction units separate from C&D material.  A reputable waste collector should be employed by the contractor to remove general refuse from the site, separately from C&D material.  An enclosed and covered area is preferred to reduce the occurrence of 'wind blown' light material.

6.7.17           Table 6.9 provides a summary of the various waste types likely to be generated during the construction phase, together with the recommended handling and disposal methods.

 

Table 6.9                        Summaryof Waste Handling Procedures and Disposal Routes

Waste Type

Generated from Works Item

Total Quantity Generated

Quantity to be disposed off-site / re-used

Handling

Disposal

Capital Dredging

C&D Material 

 

Removal of existing seawall by dredging

 

 

322,300 m3  rock fill / rock armour / general fill

 

322,300 m3  of C&D material to be disposed off-site

C&D material should be reused as far as practicable

Dust and water quality mitigation measures

(Sections 6.7.14 – 6.7.15)

Inert C&D material to be disposed off-site to the designated public fill reception facility

C&D material should be reused as far as practicable

Dredged Sediment

Dredging of seabed in the proposed manoeuvring basin (Category H and Category M sediment)

430,000 m3

Stage 1: 210,000 m3 & Stage 2: 220,000m3

430,000 m3

(Stage 1: 210,000m3 & Stage 2: 220,000m3)

Dust, odour, noise , water quality mitigation measures

(Sections 6.7.8 – 6.7.13)

Type 1 – Open Sea Disposal (Dedicated Sites) or Type 2 - Confined Marine Disposal at disposal site(s) to be allocated by MFC

Dredging of seabed in the proposed manoeuvring basin (Category L sediment)

950,000 m3

Stage 1: 490,000m3 (including 20,000m3 from removal of the Kai Tak Runway submarine outfall) &

Stage 2: 460,000m3

950,000 m3

(Stage 1: 490,000m3 & Stage 2: 460,000m3)

Type 1 - Open Sea Disposal - gazetted marine disposal ground allocated by MFC

Removal of existing seawall by dredging

None

None

-

-

Chemical Wastes

Cleansing fluids, solvent, lubrication oil and fuel from construction plant and equipment

Few cubic metres per month (preliminary estimate)

Few cubic metres per month (preliminary estimate)

Recycle by licensed companies

Stored on-site within suitably designed containers

(Section 6.7.16)

Chemical Waste Treatment Facility or other licensed facility

General Refuse

Waste paper, discarded containers, etc. generated from workforce

Approx. 13 kg per day (preliminary estimate based on workforce of 20)

Approx. 13 kg per day

Provide on-site refuse collection points (Section 6.7.17)

Refuse station for compaction and containerisation and then to landfill

Maintenance Dredging

Dredged Sediment

Sediment quality to be determined by sediment sampling and testing under the requirements of the ETWB TCW No. 34/2002 

Approx. 350,000 m3 every 5 to 10 years

Approx. 350,000 m3 every 5 to 10 years

Dust, odour, noise , water quality mitigation measures

(Sections 6.7.8 – 6.7.13)

 

MFC would formally allocate marine disposal space in accordance with ETWB TCW No. 34/2002.

Chemical Wastes

Cleansing fluids, solvent, lubrication oil and fuel from construction plant and equipment

Few cubic metres per month (preliminary estimate)

Few cubic metres per month (preliminary estimate)

Recycle by licensed companies

Stored on-site within suitably designed containers

(Section 6.7.16)

Chemical Waste Treatment Facility or other licensed facility

General Refuse

Waste paper, discarded containers, etc. generated from workforce

Approx. 13 kg per day (preliminary estimate based on workforce of 20)

Approx. 13 kg per day

Provide on-site refuse collection points (Section 6.7.17)

Refuse station for compaction and containerisation and then to landfill

 

 

6.8                    Evaluation of Residual Environmental Impacts

6.8.1               With the implementation of the recommended mitigation measures for the handling, transportation and disposal of the identified waste arisings, no residual impact is expected to arise during the proposed capital dredging during construction stage and maintenance dredging during operational stage of the proposed cruise terminal.

6.9                    Environmental Audit

6.9.1               Waste management will be the contractor’s responsibility to ensure that all wastes produced during the dredging operation are handled and disposed of in accordance with the recommended mitigation measures and EPD’s regulations and requirements.  The mitigation measures recommended in Section 6.7 above should form the basis of the site Waste Management Plan to be developed by the contractor in the construction and operational stages of the propose cruise terminal.

6.10                 Summary

6.10.1           The total volume of dredged sediment generated from the dredging of the seabed to provide the manoeuvring basin for the cruise terminal is estimated to be approximately 1.38 Mm3 during construction phase.  Based on the results of the chemical and biological screening, approximately 430,000 m3 was classified as contaminated dredged sediment (Category M and H) requiring Type 1 – Open Sea Disposal (Dedicated Sites) or Type 2 - Confined Marine Disposal, and approximately 950,000 m3 was classified as Category L sediment suitable for Type 1 - Open Sea Disposal in accordance with ETWB TCW No. 34/2002.

6.10.2           The total volume of dredged sediment generated from maintenance dredging during operational phase is estimated to be approximately 350,000 m3 every 5 to 10 years.  Prior to any maintenance dredging, sediment sampling and testing will be carried out in accordance with the ETWB TCW No. 34/2002 to determine the contamination level of the dredged sediment.  The most appropriate open sea or confined marine disposal site will be allocated for proper disposal of the dredged sediment on the basis of the chemical and biological test results in accordance with the ETWB TCW No. 34/2002. 

6.10.3           The total volume of C&D material generated from the removal of the existing seawall by dredging for the berth construction is estimated to be approximately 322,300 m3 during construction phase.  No C&D material would be generated from maintenance dredging during operational stage of the proposed cruise terminal.  Other wastes generated from the capital and maintenance dredging are likely to include chemical waste from the maintenance of construction plant and equipment and general refuse from the construction workforce. 

6.10.4           Mitigation measures are recommended in this EIA to minimise potential environmental impacts associated with handling and disposal of different wastes arising from the Project.  Provided that the recommended mitigation measures are properly followed, adverse environmental impacts would not be expected from the capital and maintenance dredging.