Appendix C

(Implementation Schedule of the Proposed Mitigation Measures)

Agreement No. CE 35/2006(CE) Kai Tak Development Engineering Study Dredging Works for cum Design and Construction of Advance Works Proposed Cruise Terminal at Kai Tak

– Investigation, Design and Construction EM&A Manual

APPENDIX C IMPLEMENTATION SCHEDULE OF THE PROPOSED MITIGATION MEASURES Table C.1 Implementation Schedule for Air Quality Measures

EIA Ref Environmental Protection Measures / Mitigation Measures Location / Timing Implementation Agent Implementation Stages* Relevant Legislation and Guidelines
Des C O Dec
S3.6 Requirements of the Air Pollution Control (Construction Dust) Regulation shall be adhered to during the construction period. Work site / during dredging in the construction stage and maintenance dredging during operation stage Contractor for capital dredging Air Pollution Control (Construction Dust) Regulation
S3.6 In order to minimize the potential odour emissions, if any, the dredged sediment placed on barge should be properly covered as far as practicable to minimise the exposed area and hence the potential odour emissions during the transportation of the dredged sediment. Work site / during dredging in the construction stage and maintenance dredging during operation stage Contractor for capital and maintenance dredging Technical Memorandum on the Environmental Impact Assessment Process (EIAO-TM)

* Des -Design, C -Construction, O – Operation, and Dec -Decommissioning * Des -Design, C -Construction, O – Operation, and Dec -Decommissioning

Table C.2 Implementation Schedule for Noise Measures

EIA Ref Environmental Protection Measures / Mitigation Measures Location / Timing Implementation Agent Implementation Stages* Relevant Legislation and Guidelines
Des C O Dec
S4.8 Good Site Practices: Only well-maintained plant should be operated on-site and plant should be serviced regularly during the construction program. Mobile plant, if any, should be sited as far away from NSRs as possible. Machines and plant (such as trucks) that may be in intermittent use should be shut down between works periods or should be throttled down to a minimum. Plant known to emit noise strongly in one direction should, wherever possible, be orientated so that the noise is directed away from the nearby NSRs. Material stockpiles and other structures should be effectively utilised, wherever practicable, in screening noise from on-site construction activities. Work site / during dredging in the construction stage and maintenance dredging during operation stage Contractor for capital and maintenance dredging Noise Control Ordinance (NCO) EIAO-TM
S4.9 If there is any planned NSRs within 300 m from the work area occupied during the dredging period, an EM&A programme is recommended to be established according to the predicted occurrence of noisy activities. All the recommended mitigation measures for daytime normal working activities should be incorporated into the EM&A programme for implementation during dredging. Representative NSRs at the former Kai Tak Airport runway / Prior and during the capital and maintenance dredging Developer of cruise terminal NCO EIAO-TM

Agreement No. CE 35/2006(CE) Kai Tak Development Engineering Study Dredging Works for cum Design and Construction of Advance Works Proposed Cruise Terminal at Kai Tak

– Investigation, Design and Construction EM&A Manual

Table C.3 Implementation Schedule for Water Quality Measures

EIA Ref Environmental Protection Measures / Mitigation Measures Location / Timing Implementation Agent Implementation Stages* Relevant Legislation and Guidelines
Des C O Dec
S5.9 Dredging will be carried out by closed grab dredger to minimize release of sediment and other contaminants during both capital and maintenance dredging. The maximum production rate for dredging from the seabed to provide necessary manoeuvring area would not be more than 4,000m 3 per day (and no more than 2 closed grab dredgers) during capital dredging and 2,000m 3 per day (and no more than 1 closed grab dredger) during maintenance dredging. The maximum production rate for dredging at or near the seawall area would not be more than 4,000m 3 per day for berth construction. No more than two closed grab dredger would be operated at the same time at or near the seawall for berth construction. Work site/ during dredging in the construction stage and maintenance dredging during operation stage Contractor for capital and maintenance dredging Technical Memorandum on the Environmental Impact Assessment Process (EIAOTM) Water Pollution Control Ordinance (WPCO)
S5.9 The maintenance dredging should not be programmed in wet season (April to September) Work site/ during dredging in the operational stage Contractor for maintenance dredging EIAO-TM, WPCO
S5.9 Silt curtains should be deployed around the closed grab dredgers used for dredging at and near the existing seawall of the former Kai Tak Airport runway for construction of the cruise berth structures. Work site/ during dredging in the construction stage Contractor for capital dredging EEIAO-TM, WPCO
S5.9 Silt screens should be installed at the WSD flushing water intakes at Cha Kwo Ling, Sai Wan Ho, Quarry Bay, Sheung Wan, Wan Chai and Tai Wan for dredging in the manoeuvring basin of the first berth during the capital dredging Seawater intakes in Victoria Harbour/ During the construction of cruise terminal Contractor for capital dredging EIAO-TM, WPCO
EIA Ref Environmental Protection Measures / Mitigation Measures Location / Timing Implementation Agent Implementation Stages* Relevant Legislation and Guidelines
Des C O Dec
S5.9 Silt screens should be installed at the WSD flushing water intakes at Cha Kwo Ling, Quarry Bay and Tai Wan for dredging in the manoeuvring basin of the second berth during the capital dredging. Seawater intakes in Victoria Harbour/ During the construction of cruise terminal Contractor for capital dredging EIAO-TM, WPCO
S5.9 If the opening has been introduced at the northern runway, silt screens should also be installed at the WSD flushing water intake at Sai Wan Ho, Sheung Wan and Wan Chai for dredging in the manoeuvring basin of the second berth during the capital dredging. Seawater intake at Sai Wan Ho, Sheung Wan and Wan Chai/ During the construction of cruise terminal CEDD EIAO-TM, WPCO
S5.9 Other good site practices that should be undertaken during dredging include: all vessels should be sized so that adequate clearance is maintained between vessels and the seabed in all tide conditions, to ensure that undue turbidity is not generated by turbulence from vessel movement or propeller wash; all barges / dredgers should be fitted with tight fitting seals to their bottom openings to prevent leakage of material; construction activities should not cause foam, oil, grease, scum, litter or other objectionable matter to be present on the water within the site or dumping grounds; barges or hoppers should not be filled to a level that will cause the overflow of materials or polluted water during loading or transportation. Work site and adjacent waters / during dredging in the construction stage and maintenance dredging during operation stage Contractor for capital and maintenance dredging EIAO, EIAO-TM, WPCO, Waste Disposal Ordinance (WDO)

Agreement No. CE 35/2006(CE) Kai Tak Development Engineering Study Dredging Works for cum Design and Construction of Advance Works Proposed Cruise Terminal at Kai Tak

– Investigation, Design and Construction EM&A Manual

EIA Ref Environmental Protection Measures / Mitigation Measures Location / Timing Implementation Agent Implementation Stages* Relevant Legislation and Guidelines
Des C O Dec
S5.9 Appropriate numbers of portable chemical toilets shall be provided by a licensed contractor to serve the construction workers over the construction site. The Contractor shall also be responsible for waste disposal and maintenance practices. Work site and adjacent waters / during dredging in the construction stage and maintenance dredging during operation stage Contractor for capital and maintenance dredging EIAO-TM, WPCO, WDO
S5.9 Collection and removal of floating refuse should be performed at regular intervals on a daily basis. The contractor should be responsible for keeping the water within the site boundary and the neighbouring water free from rubbish during the dredging works. Work site and adjacent waters / during dredging in the construction stage and maintenance dredging during operation stage Contractor for capital and maintenance dredging EIAO-TM, WPCO, WDO
S5.9 An environmental monitoring and audit programme should be implemented to verify whether or not impact predictions are representative, and to ensure that all the recommended mitigation measures are implemented properly. If the water quality monitoring data indicate that the proposed dredging works result in unacceptable water quality impacts in the receiving water, appropriate actions should be taken to review the dredging operation and additional measures such as use of frame-type silt curtain, deployment of double silt curtains, slowing down, or rescheduling of works should be implemented as necessary. Selected water receiver points in Victoria Harbour / Prior and during the construction of cruise terminal and maintenance dredging Developer of cruise terminal EIAO-TM, WPCO
EIA Ref Environmental Protection Measures / Mitigation Measures Location / Timing Implementation Agent Implementation Stages* Relevant Legislation and Guidelines
Des C O Dec
S5.9 Silt screens are recommended to be deployed at six selected WSD flushing water intakes during the capital dredging. The contractor for capital dredging shall demonstrate and ensure that the design of the silt screen will not affect the normal operation of flushing water intake. The contractor shall obtain consensus from all relevant parties, including WSD and Marine Department on the design of the silt screen at each of the six selected flushing water intake points before installation of the silt screen and commencement of the proposed dredging works. As a mitigation measure to avoid the pollutant and refuse entrapment problems and to ensure that the impact monitoring results are representative, regular maintenance of the silt screens and refuse collection should be performed at the monitoring stations at regular intervals on a daily basis. The Contractor should be responsible for keeping the water behind the silt screen free from floating rubbish and debris during the impact monitoring period. Selected water receiver points in Victoria Harbour / during dredging in the construction stage Contractor for capital dredging EIAO-TM, WPCO

* Des -Design, C -Construction, O – Operation, and Dec -Decommissioning

Agreement No. CE 35/2006(CE) Kai Tak Development Engineering Study Dredging Works for cum Design and Construction of Advance Works Proposed Cruise Terminal at Kai Tak

– Investigation, Design and Construction EM&A Manual

Table C.4 Implementation Schedule for Waste Management Measures

EIA Ref Environmental Protection Measures / Mitigation Measures Location / Timing Implementation Agent Implementation Stages* Relevant Legislation and Guidelines
Des C O Dec
S6.7 Good Site Practices It is not anticipated that adverse waste management related impacts would arise, provided that good site practices are adhered to. Recommendations for good site practices during the dredging activities include: Nomination of an approved person, such as a site manager, to be responsible for good site practices, arrangements for collection and effective disposal to an appropriate facility, of all wastes generated at the site. Training of site personnel in proper waste management and chemical waste handling procedures. Provision of sufficient waste disposal points and regular collection for disposal. Appropriate measures to minimise windblown litter and dust during transportation of waste by either covering trucks or by transporting wastes in enclosed containers. A recording system for the amount of wastes generated, recycled and disposed of (including the disposal sites). Segregation and storage of different types of waste in different containers, skips or stockpiles to enhance reuse or recycling of materials and their proper disposal. Encourage collection of aluminium cans, PET bottles and paper by providing separate labelled bins to enable these wastes to be segregated from other general refuse generated by the work force. Any unused chemicals or those with remaining functional capacity shall be recycled. Work site / during dredging in the construction stage and maintenance dredging during operation stage Contractor for capital and maintenance dredging EIAO-TM
EIA Ref Environmental Protection Measures / Mitigation Measures Location / Timing Implementation Agent Implementation Stages* Relevant Legislation and Guidelines
Des C O Dec
S6.7 Marine Sediments The dredged marine sediments would be loaded onto barges and transported to the designated disposal sites allocated by the MFC depending on their level of contamination. Sediment classified as Category L would be suitable for Type 1 -Open Sea Disposal. Contaminated sediment would require either Type 1 – Open Sea Disposal (Dedicated Sites) or Type 2 -Confined Marine Disposal and must be dredged and transported with great care in accordance with ETWB TCW No. 34/2002. Subject to the final allocation of the disposal sites by MFC, the dredged contaminated sediment must be effectively isolated from the environment upon final disposal and shall be disposed of at the East Sha Chau Contaminated Mud Pits that are designated for the disposal of contaminated mud in Hong Kong. Work site / during dredging in the construction stage and maintenance dredging during operation stage Contractor for capital and maintenance dredging ETWB TCW No. 34/2002
S6.7 It will be the responsibility of the Contractor to satisfy the appropriate authorities that the contamination levels of the marine sediment to be dredged have been analysed and recorded. According to the ETWB TCW No. 34/2002, this will involve the submission of a formal Sediment Quality Report to the DEP, prior to the dredging contract being tendered. The contractor for the dredging works shall apply for the allocation of marine sediment disposal sites from all relevant authorities. Work site / during dredging in the construction stage and maintenance dredging during operation stage Contractor for capital and maintenance dredging ETWB TCW No. 34/2002

Agreement No. CE 35/2006(CE) Kai Tak Development Engineering Study Dredging Works for cum Design and Construction of Advance Works Proposed Cruise Terminal at Kai Tak

– Investigation, Design and Construction EM&A Manual

EIA Ref Environmental Protection Measures / Mitigation Measures Location / Timing Implementation Agent Implementation Stages* Relevant Legislation and Guidelines
Des C O Dec
S6.7 During transportation and disposal of the dredged marine sediments requiring Type 1 and Type 2 disposal, the following measures shall be taken to minimise potential impacts on water quality: Bottom opening of barges shall be fitted with tight fitting seals to prevent leakage of material. Excess material shall be cleaned from the decks and exposed fittings of barges and hopper dredgers before the vessel is moved. Monitoring of the barge loading shall be conducted to ensure that loss of material does not take place during transportation. Transport barges or vessels shall be equipped with automatic self-monitoring devices as specified by the DEP. Barges or hopper barges shall not be filled to a level that would cause the overflow of materials or sediment laden water during loading or transportation. Work site / during dredging in the construction stage and maintenance dredging during operation stage Contractor for capital and maintenance dredging Waste Disposal Ordinance Water Pollution Control Ordinance Waste Disposal (Chemical Waste) (General) Regulation Code of Practice on the Packaging, Labelling and Storage of Chemical Wastes
S6.7 Chemical Wastes After use, chemical wastes (for example, cleaning fluids, solvents, lubrication oil and fuel) should be handled according to the Code of Practice on the Packaging, Labelling and Storage of Chemical Wastes. Spent chemicals should be collected by a licensed collector for disposal at the CWTF or other licensed facility in accordance with the Waste Disposal (Chemical Waste) (General) Regulation. Work site / during dredging in the construction stage and maintenance dredging during operation stage Contractor for capital and maintenance dredging
EIA Ref Environmental Protection Measures / Mitigation Measures Location / Timing Implementation Agent Implementation Stages* Relevant Legislation and Guidelines
Des C O Dec
S6.7 General Refuse General refuse should be stored in enclosed bins or compaction units separate from C&D material. A reputable waste collector should be employed by the contractor to remove general refuse from the site, separately from C&D material. An enclosed and covered area is preferred to reduce the occurrence of 'wind blown' light material. Work site / during dredging in the construction stage and maintenance dredging during operation stage Contractor for capital and maintenance dredging Waste Disposal Ordinance Water Pollution Control Ordinance
S6.7 Construction and Demolition Material It is recommended that the extent of dredging of the existing seawall should be kept to a minimum in the detailed design of the new cruise terminal to minimize generation of C&D material. Mitigation measures and good site practices should be incorporated in the contract document to control potential environmental impact from handling and transportation of C&D material. The mitigation measures include: Where it is unavoidable to have transient stockpiles of C&D material within the Project work site pending collection for disposal, the transient stockpiles shall be located away from waterfront or storm drains as far as possible. Open stockpiles of construction materials or construction wastes on-site should be covered with tarpaulin or similar fabric. Skip hoist for material transport should be totally enclosed by impervious sheeting. Every vehicle should be washed to remove any dusty materials from its body and wheels before leaving a construction site. The area where vehicle washing takes place and the section of the road between the washing facilities and the exit point should be paved with concrete, Work site / During the construction period Contractor for capital dredging ETWB TCW No. 33/2002, 31/2004, 19/2005

Agreement No. CE 35/2006(CE) Kai Tak Development Engineering Study Dredging Works for cum Design and Construction of Advance Works Proposed Cruise Terminal at Kai Tak

– Investigation, Design and Construction EM&A Manual

EIA Ref Environmental Protection Measures / Mitigation Measures Location / Timing Implementation Agent Implementation Stages* Relevant Legislation and Guidelines
Des C O Dec
bituminous materials or hardcores. The load of dusty materials carried by vehicle leaving a construction site should be covered entirely by clean impervious sheeting to ensure dust materials do not leak from the vehicle. All dusty materials should be sprayed with water prior to any loading, unloading or transfer operation so as to maintain the dusty materials wet. The height from which excavated materials are dropped should be controlled to a minimum practical height to limit fugitive dust generation from unloading.
S6.7 When delivering inert C&D material to public fill reception facilities, the material shall consist entirely of inert construction waste and of size less than 250mm or other sizes as agreed with the Secretary of the Public Fill Committee. In order to monitor the disposal of the surplus C&D material at the designed public fill reception facility and to control fly tipping, a trip-ticket system should be included as one of the contractual requirements and implemented by an Environmental Team undertaking the Environmental Monitoring and Audit work. An Independent Environmental Checker should be responsible for auditing the results of the system. Work site / During the construction period Contractor and Independent Environmental Checker ETWB TCW No. 31/2004

* Des -Design, C -Construction, O – Operation, and Dec -Decommissioning * Des -Design, C -Construction, O – Operation, and Dec -Decommissioning

Table C.5 Implementation Schedule for Cultural Heritage Measures

EIA Ref Environmental Protection Measures / Mitigation Measures Location / Timing Implementation Agent Implementation Stages* Relevant Legislation and Guidelines
Des C O Dec
7.8 The dredging activities of the proposed cruise terminal should ensure that disturbance to the existing seawall masonry outside the Project boundary should be avoided as far as practicable. Work site/ During the design and construction of cruise terminal Developer of cruise terminal Antiquities and Monuments Ordinance Environmental Impact Assessment Ordinance (EIAO) EIAO-TM Guidance Notes on Assessment of Impact on Sites of Cultural Heritage in Environmental Impact Assessment Studies (GN-CH) Hong Kong Planning Standards and Guidelines (HKPSG)
7.10, Appendix 7.1 It is recommended that the dredged spoil should be monitored for the presence of archaeological material. Guidelines for the monitoring brief have been prepared in consultation with the AMO. A qualified marine archaeologist needs to be on standby to provide specialist advice, if required, but the monitoring can be carried out by a member of staff on the dredging barge. Work site / during dredging in the construction stage Developer of cruise terminal /contractor for capital dredging Antiquities and Monuments Ordinance EIAO, EIAO-TM GN-CH HKPSG Marine Archaeological Investigation Guidelines

Agreement No. CE 35/2006(CE) Kai Tak Development Engineering Study Dredging Works for cum Design and Construction of Advance Works Proposed Cruise Terminal at Kai Tak

– Investigation, Design and Construction EM&A Manual

Table C.6 Implementation Schedule for Marine Ecology Measures

EIA Ref Environmental Protection Measures / Mitigation Measures Location / Timing Implementation Agent Implementation Stages* Relevant Legislation and Guidelines
Des C O Dec
8.7 Translocate those existing coral colonies attached on boulders that are manually movable by a diver underwater (possibly longest dimension of less than 50 cm) located within the hard substrata sea area within the dredging site as far as practicable prior to the commencement of the capital dredging activities. The entire translocation exercise include the preparation of a detailed translocation plan, the pre-translocation coral survey, the coral translocation, and the quarterly post-translocation monitoring for one year. Pre-translocation survey would be focused on identifying and mapping of coral colonies that would be directly impacted by the proposed dredging and investigating the translocation feasibility of these coral colonies. A detailed translocation plan (including pre-translocation coral survey, translocation methodology and monitoring of transplanted corals) should be prepared during the detailed design stage of the Project which, together with the ecologist involved in coral translocation, should be approved by AFCD prior to commencement of the translocation exercises. The proposed relocation of the coral colonies should not affect any private/public marine rights at the recipient site. Along the section of the former Kai Tak Airport runway that will be directed affected by the cruise terminal construction / During detailed design stage Developer of cruise terminal EIAO-TM
8.7 New seawalls at the berth structure of the cruise terminal shall be constructed in order to provide large area of hard substrata for settlement and recruitment of intertidal and subtidal assemblages similar to those previously recorded from existing habitats. The section of the former Kai Tak Airport runway that will be directed affected by the cruise terminal construction / During detailed design stage Developer of cruise terminal EIAO-TM

* Des -Design, C -Construction, O – Operation, and Dec -Decommissioning * Des -Design, C -Construction, O – Operation, and Dec -Decommissioning

Table 12.7 Implementation Schedule for Fisheries Measures

EIA Ref Environmental Protection Measures / Mitigation Measures Location / Timing Implementation Agent Implementation Stages* Relevant Legislation and Guidelines
Des C O Dec
9.6 No fisheries-specific mitigation measures would be required - - - - - - -

Agreement No. CE 35/2006(CE) Kai Tak Development Engineering Study Dredging Works for cum Design and Construction of Advance Works Proposed Cruise Terminal at Kai Tak

– Investigation, Design and Construction EM&A Manual