2.1.1
The
construction activities under the Project would be dredging activities which
are not dusty activities. In view
the construction activities are mostly marine based, negligible dust impacts
would be expected during the dredging works.
2.1.2
Dust
monitoring is not required but regular site audit shall be conducted to ensure
the compliance of requirements of the Air Pollution Control (Construction Dust)
Regulation during the construction stage.
2.1.3
Referring
to the marine site investigation results, the sediments within the dredging
area of the proposed cruise terminal would not be odourous and adverse odour
impact from the dredging activities in the Stage 1 and 2 areas would not be anticipated. Therefore, mitigation measures and
EM&A requirements for odour impact are not required.