1                   INTRODUCTION

 

1.1              Purpose of the Manual

 

This Environmental Monitoring and Audit (EM&A) Manual (“the Manual”) is prepared by Halcrow China Limited and ERM-Hong Kong, Limited (ERM) on behalf of the Civil Engineering and Development Department (CEDD).  The Manual is a companion document of the EIA Study of the Development of a Bathing Beach at Lung Mei, Tai Po (hereafter referred to as the Project).

 

The Manual has been prepared in accordance with the EIA Study Brief (No. ESB-138/2006) and the Technical Memorandum of the Environmental Impact Assessment Process (EIAO TM).  The purpose of the Manual is to provide information, guidance and instruction to personnel charged with environmental duties and those responsible for undertaking EM&A work during construction and operation. It provides systematic procedures for monitoring and auditing of potential environmental impacts that may arise from the works.

 

The EM&A Manual comprises descriptions of the key elements of the EM&A programme including:

 

·            Appropriate background information on the construction of the Project with reference to relevant technical reports;  

·            Organisational arrangements, hierarchy and responsibilities with regard to the management of environmental performance during the construction phase. The EM&A team, the Contractor team and the Engineer Representative are included; 

·            A broad construction programme indicating those activities for which specific mitigation is required and providing a schedule for their timely implementation; 

·            Descriptions of the parameters to be monitored and criteria through which performance will be assessed including: monitoring frequency and methodology, monitoring locations (typically, the location of sensitive receivers as listed in the EIA), monitoring equipment lists, event contingency plans for exceedances of established criteria and schedule of mitigation and best practice methods for reduced adverse environmental impacts; 

·            Procedures for undertaking on-site environmental performance audits as a means of ensuring compliance with environmental criteria; and  

·            Reporting procedures.

The EM&A Manual will be a dynamic document which will undergo a series of revisions, as needed, to accommodate the progression of the construction programme.

 

1.2              Project Description

 

1.2.1        Background to the Study

 

The ex-Provisional Regional Council (ex-PRC) considered that one swimming pool complex in Tai Po was insufficient and hence suggested developing a bathing beach at Lung Mei, Tai Po. Therefore, on 12 May 1998, the Culture, Recreation and Sports Committee of ex-PRC approved funding for the Architectural Services Department (ArchSD) to study the feasibility of developing an artificial beach at Lung Mei.  The Feasibility Study, which commenced in December 1999 and completed in mid-2001, concluded that it was technically viable to construct a bathing beach at Lung Mei, Tai Po.

 

There is no beach facility in the east region of the New Territories, except in the Sai Kung District, which is very far from Tai Po District.  Moreover, the existing swimming facility in the Tai Po areas could not satisfy the demand for a bathing beach. Therefore, the public has been requesting repeatedly to the LCSD for a beach development in the Tai Po District.

 

In light of the above, the Tai Po District Council (TPDC) strongly requested for the development of a bathing beach at Lung Mei and members of the TPDC urged for early implementation of the Project.  In a Legislative Council case conference on 20 April 2004, Members requested the Government to accord priority to this Project.

 

Lung Mei is adjacent to a prominent leisure area, Tai Mei Tuk, with well-established facilities for holiday-makers and water-based recreation activities, which has attracted many visitors, in particular during public holidays. It is anticipated that the proposed bathing beach would complement the facilities already provided in the Tai Mei Tuk area.

 

1.2.2        The Proposed Project Site

 

The Project will involve the construction and operation of a bathing beach at Lung Mei, Tai Po.  The beach will provide a facility for visitors for leisure and recreation.  The Project will include the following facilities:

 

·       Construction of a 200m long beach with two groynes, which includes dredging and sandfilling; 

·       Construction of two culverts at the eastern and western side of the beach, to collect and divert surface runoff from upstream locations; and, 

·       Construction of associated beach building facilities, kiosk and a car park for visitors.

 

The Project constitutes a Designated Project by virtue of Items C.2 and C.12 of Part I of Schedule 2 under the EIAO.  The following elements of the Project addressed in this EIA Report are classified as Designated Projects under the Environmental Impact Assessment Ordinance (Cap. 499) (EIAO). 

·       Dredging operation which is less than 500m from the nearest boundary of an existing Site of Special Scientific Interest, Coastal Protection Area, Conservation Area and Country Park. 

1.2.3        Objectives of EM&A 

The objectives of carrying out the EM&A for the Project include:

 

·            Providing baseline information against which any short or long term environmental impacts of the projects can be determined;

·            Providing an early indication should any of the environmental control measures or practices fail to achieve the acceptable standards;

·            Monitoring the performance of the Project and the effectiveness of mitigation measures;

·            Verifying the environmental impacts identified in the EIA;

·            Determining Project compliance with regulatory requirements, standards and government policies;

·            Taking remedial action if unexpected results or unacceptable impacts arise; and

·            Providing data to enable an environmental audit to be undertaken at regular intervals.

 

EM&A procedures are required during the design, construction, post-construction and operational phases of the project implementation and a summary of the requirements for each of the environmental parameters is detailed in Table 1.1 below.

 

Table 1.1 Summary of EM&A Requirements

 

Parameter

EM&A Phase

Design

Phase (1)

Construction Phase

Post-Construction Phase

Operation Phase

Air Quality

-

Yes

-

-

Noise

-

Yes

-

-

Water Quality

-

Yes

Yes

Yes

Waste

-

Yes

-

-

Ecology

- (2)

-

Yes

-

Fisheries

-

-

-

-

Landscape and Visual

Yes

Yes

Yes

Yes

Notes:  

(1) EM&A requirements in the design phase shall include confirmation on the compliance for environmental designs which were specified in the EIA Report and the EP for all parameters.

(2) Although pre- construction monitoring may overlap the design phase, the focus of this monitoring will be to provide additional information on which to assess potential impacts through construction.

 
 

1.3              Scope of EM&A

 

The scope of this EM&A programme is to:

 

·           establish baseline air quality, noise and water quality levels at specified locations;

·           implement monitoring and site audit requirements for air quality, noise, water quality and ecology monitoring programme;

·           liaise with, and provide environmental advice (as requested or when otherwise necessary) to construction site staff on the significance and implications of the environmental monitoring data;

·           identify and resolve environmental issues and other functions as they may arise from the works;

·           check and quantify the Contractor(s)’s overall environmental performance, implementation of Event and Action Plans (EAPs), and remedial actions taken to mitigate adverse environmental effects as they may arise from the works;

·           conduct monthly reviews of monitored impact data as the basis for assessing compliance with the defined criteria and to ensure that necessary mitigation measures are identified and implemented, and to undertake additional ad hoc monitoring and auditing as required by special circumstances;

·           evaluate and interpret environmental monitoring data to provide an early indication should any of the environmental control measures or practices fail to achieve the acceptable standards, and to verify the environmental impacts predicted in the EIA;

·           manage and liaise with other individuals or parties concerning other environmental issues deemed to be relevant to the construction process;

·           conduct regular site inspections of a formal or informal nature to assess:

-       the level of the Contractor(s)’s general environmental awareness;

-       the Contractor(s)’s implementation of the recommendations in the EIA and their contractual obligations;

-       the Contractor(s)’s performance as a measured by the EM&A;

-       the need for specific mitigation measures to be implemented or the continued usage of those previously agreed;

-       to advise the site staff of any identified potential environmental issues; and,

-       submit monthly EM&A reports which summarise project monitoring and auditing data, with full interpretation illustrating the acceptability or otherwise of any environmental impacts and identification or assessment of the implementation status of agreed mitigation measures.


1.4       Works Programme and Works Location

 

The construction works are anticipated to commence in 2008.  The preliminary construction programme is given in Appendix A.  It should be noted that the Tolo Harbour Sewerage of Unsewered Areas Stage I Phase IIC (Agreement No. CE 18/94) will carry out works connecting the unsewered areas from Ting Kok village to Lung Mei village, which are in the vicinity of the bathing beach development. The sewerage construction works is scheduled to be completed prior to the operation of this Proposed Bathing Beach Development project. With the implementation of the sewerage connection (expect to be 60% connection rate) and the gazette of the Tolo Harbour Sewerage of Unsewered Areas Stage I Phase IIC (Agreement No. CE 18/94) including Lung Mei area, as part of the Sewerage Master Plan Works for Tolo Harbour Catchment, the water quality at Lung Mei will be improved and guaranteed, and facilitating the operation of this bathing beach.

 

The locations of works are shown in Figure 1.1.  The Sensitive Receivers in the vicinity of the proposed project are presented in Figure 1.1.

 

1.5      Organisation of the EM&A

 

1.5.1   General

 

The Contractor will appoint an Environmental Team (ET) to conduct the monitoring and auditing works and to provide specialist advice on undertaking and the implementation of environmental responsibilities.

 

The ET will have previous relevant experience with managing similarly sized EM&A programmes and the Environmental Team Leader (ET Leader) will be a recognised environmental professional, preferably with a minimum of seven years relevant experience in impact assessments and impact monitoring programmes.

 

To maintain strict control of the EM&A process, CEDD will appoint independent environmental consultants to act as an Independent Environmental Checker (IEC) to verify and validate the environmental performance of the Contractor(s) and his Environmental Team.  The IEC will have previous relevant experience with checking and auditing similarly sized EM&A programmes and the IEC will be a recognised environmental professional, preferably with a minimum of seven years relevant experience in impact assessments and impact monitoring programmes.

 

1.5.2   Project Organisation

 

The roles and responsibilities of the various parties involved in the EM&A process are further expanded in the following sections and in Figure 1.2.

 

The ET Leader will be responsible for, and in charge of, the Environmental Team; and will be the person responsible for executing the EM&A requirements.

 

Engineer Representative (ER)

 

ER will:

·           monitor the Contractor’s compliance with contract specifications, including the effective implementation and operation of environmental mitigation measures and other aspects of the EM&A programme;

·           instruct the Contractor to follow the agreed protocols or those in the Contract Specifications in the event of exceedances or complaints;

·           comply with the agreed Event and Action Plans in the event of any exceedance;

·           liaise with the IEC and assist as necessary in the implementation of the EM&A program; and

·           participate in joint site inspections undertaken by the ET and IEC. 

The Contractor

 

The Contractor will:

·           work within the scope of the construction contract and other tender conditions;

·           provide assistance to the ET in carrying out monitoring;

·           submit proposals on mitigation measures in case of exceedances of Action and Limit levels in accordance with the Event and Action Plans;

·           implement measures to reduce impact where Action and Limit levels are exceeded;

·           implement the corrective actions instructed by ER/ET/IEC;

·           participate in the site inspections undertaken by the ET and the IEC, as required, and undertake any corrective actions instructed by ER/ET/IEC; and

·           adhere to the procedures for carrying out complaint investigation. 

Environmental Team (ET) 

 

The ET will:

·           monitor various environmental parameters as required in this EM&A Manual;

·           assess the EM&A data and review the success of the EM&A programme determining the adequacy of the mitigation measures implemented and the validity of the EIA predictions as well as identify any adverse environmental impacts before they arise;

·           carry out regular site inspection to investigate and audit the Contractor’s site practice, equipment and work methodologies with respect to pollution control and environmental mitigation, and effect proactive action to pre-empt issues;

·           review the Contractor’s working programme and methodology, and comment as necessary;

·           review and prepare reports on the environmental monitoring data, site environmental conditions and audits;

·           report on the environmental monitoring and audit results and conditions to the IEC, Contractor(s), EPD and ER;

·           recommend suitable mitigation measures to the Contractor in the case of exceedance of Action and Limit levels in accordance with the Event and Action Plans;

·           adhere to the procedures for carrying out complaint investigation; and,

·           the ET Leader will keep a contemporaneous log-book and record each and every instance or circumstance or change of circumstances which may affect the environmental impact assessment and every non-conformance with the recommendations of the EIA Reports or the EPs. 

 

The ET will be led and managed by the ET Leader.  The ET leader will have relevant education, training, knowledge, experience and professional qualifications and the appointment will be subject to the approval of the Director of Environmental Protection and ER.  Suitably qualified staff will be included in the ET, and the ET should not be in any way an associated body of the Contractor or the Independent Environmental Checker (IEC) for the Project.

 

Independent Environmental Checker (IEC)

 

The IEC will:

·           review and monitor the implementation of the EM&A programme and the overall level of environmental performance being achieved;

·           arrange and conduct monthly independent site inspections/audits of the works;

·           validate and confirm the accuracy of monitoring results, monitoring equipment, monitoring stations, monitoring procedures and locations of sensitive receivers;

·           carry out random sample check and audit on monitoring data and sampling procedures, etc;

·           audit the EIA recommendations and requirements against the status of implementation of environmental protection measures on site;

·           on needed basis, audit the Contractor(s)’s construction methodology and agree the appropriate, reduced impact alternative in consultation with ER, the ET and the Contractor;

·           provide specialist advice to ER and the Contractor on environmental matters;

·           check complaint cases and the effectiveness of corrective measures;

·           check that the necessary mitigation measures recommended in the EIA, EP and Contract documents, or as subsequently required, are effectively implemented;

·           review EM&A report submitted by the ET leader and feedback audit results to ET by signing off relevant EM&A proformas;

·           report the findings of site inspections/ audits and other environmental performance reviews to ER, ET, EPD and the Contractor(s); and

Sufficient and suitably qualified professional and technical staff will be employed by the respective parties to ensure full compliance with their duties and responsibilities, as required under the EM&A programme for the duration of the Project. 

1.6              Structure of the EM&A

 

The remainder of the Manual is set out as follows:

·            Section 2 sets out the EM&A general requirements;

·            Section 3 sets out the EM&A requirement for construction phase air quality;

·            Section 4 sets out the EM&A requirement for noise;

·            Section 5 details the requirements for water quality;

·            Section 6 details the requirements for waste management;

·            Section 7 details the requirements for ecology;

·            Section 8 details the requirements for fisheries;

·            Section 9 sets out the EM&A requirements for landscape and visual;

·            Section 10 describes the scope and frequency of site environmental auditing; and

·            Section 11 details the reporting requirements for the EM&A.

Appendix E presents the Implementation Schedule.