In order to ensure that the construction contractor has
implemented the recommendations of the EIA Report, regular site audits will be
conducted of the waste streams, to determine if wastes are being managed in
accordance with the approved procedures and the site Waste Management Plan.
The audits will look at all aspects of waste management including waste
generation, storage, recycling, transport and disposal.
An appropriate audit programme will be undertaken with the first audit conducted
at the commencement of the construction works. Routine weekly site inspections will also
include waste management.
As it is not expected that large quantities of waste will be generated from the operation of the bathing beach and no adverse environmental impacts will arise with the implementation of good waste management practices. Waste monitoring and audit programme for the operational phase of the proposed beach development will not be required.