As stated in
Section 1.1, there are no gazetted beaches provided at the east
region of the
2.2.1
General
As
mentioned above, there is no beach facility in the east region of the
In light of the above, the TPDC strongly requested the development of a bathing beach at Lung Mei and members of the TPDC urged for early implementation of the Project. In a Legislative Council case conference on 20 April 2004, Members requested the Government to accord priority to this Assignment. This project was one of the 25 projects identified for priority implementation in the Chief Executive’s 2005 Policy Address and has the support of Home Affairs Bureau. It is considered that this Proposed Beach Development at Lung Mei will meet the increasing demand for swimming facilities, particularly the site located next to Ting Kok Road which is highly convenient to the public. The site is partly situated on an area zoned for open space use and there is a large piece of hinterland to accommodate various ancillary facilities of the proposed beach development. Moreover, the beach can serve a recreational function even during non-bathing season, ie playing in the sand, sunbathing and other beach activities.
2.2.2
Alternatives to the
Project
The following options have been investigated before arriving
to a conclusion that a bathing beach development should be proposed:
Option 1 – Do Nothing. No extra swimming
facilities in the Tai Po area under this option.
Option 2 – Provision of Swimming
Pool Facilities, such as the construction of a Sports Centre in Area 33, Tai
Po, comprising a public indoor swimming pool with associated facilities. No
engineering works to any coastal area in Tai Po under this option.
Option 3 – Construction of a
The above alternatives have been investigated and evaluated
from different perspectives and the results are presented in
Table 2.1 below.
Table 2.1: Evaluation
of Alternatives to the Project
Options |
Evaluation |
Practicality
of the Option |
Do nothing |
The public and TPDC’s request for beach facilities near Tai Po areas
can not be satisfied. |
Not practicable |
Provision of Swimming Pool Facilities |
It is understood that there will be a Sports Centre in Area 33, Tai Po
proposed to be constructed, currently anticipated to be around mid-2009 to
end-2011, which will comprise a public indoor swimming pool (25m long, 25m
wide) with associated facilities. This project was also one of the 25
projects identified for priority implementation in the Chief Executive’s 2005
Policy Address. Even so, the added swimming pool would not satisfy the
current demand for beach facilities in the Tai Po areas. |
Not practicable |
Provision of
|
The community demand
for beach facilities can be met. The
design criteria and environmental and engineering considerations in site selection
will be further discussed in Section
2.3. |
Practicable |
In the view of the above, only the provision of bathing
beach is considered practicable in satisfying the demand of the public and the
TPDC for a beach facility in Tai Po. In addition to serve swimmers, the beach
can also act all the year round as a recreational ground for non-swimmers, ie
sand playing/sculpture activities, sunbathing and other beach activities etc.
2.2.3
Scenarios with and
without the Project
There are a number of bathing sites considered in the Tai Po
area and they are discussed in Section
2.3 but the preferred proposed Beach Development sited at Lung Mei would
serve many local residents as well as residents from other parts of
However, without this bathing beach, the community demand of
beach swimming would not be met as there are no such facilities at Tai Po. The
opportunity for such an attraction would be lost for the locals, residents’
afar and tourist alike. On top, the prospect to enhance the leisure area of Tai
Mei Tuk area in Tai Po will never be realised. It should also be noted that
Lung Mei is a non-gazetted beach and currently utilised by swimmers. Without
this proposed bathing beach, the swimmers will still insecurely use this
non-gazetted beach. Therefore, we conclude that the bathing beach development
should be supported in light of strong public expectation for such an
attraction and lack of beach facilities in the area.
2.3.1
Site Selection
Consideration
The basic requirements of the
Proposed Beach Development agreed with LCSD are as follows:
·
It should be located
within the Tai Po District;
·
It should have sufficient
area for a development of a 200m long beach with a minimum beach area of 6,000m2,
serving 4,000 bathers during the swimming peak season; and
· The beach should
preferably have no less than 10m wide sand part during very high tide so that
the sufficient sun bathing area can be achieved. Ideally, there should be sufficient space in
its hinterlands to accommodate other beach facilities such as changing room,
toilets, shower area, storerooms, beach office, refreshment kiosk, etc.
From environmental and
engineering points of view, the following criteria are also taken into account
in the preliminary site selection process:
· The new bathing beach
should be located along the shore with acceptable water quality (E. Coli concentration below 180 cfu per
100mL). It is preferable to be sited
away from the industrial areas (ie Tai Po Industrial Estate) due to water
quality concern;
·
It is preferable to be
located within a sheltered area (not subject to wave actions) to avoid sediment
drift during operation and minimize the future maintenance requirement;
·
It is preferred to have a
soft bottom (ie sand, but not muddy bottom such as mudflat) and gentle slope to
minimise dredging and sandfilling requirements during the development;
·
It should be away from
the existing fairway/navigation channel for bathing safety concerns;
·
It is preferable to be
located away from the Fish Culture Zone;
·
It is preferred to have
nearby existing infrastructure (such as road and drainage systems) and
supporting facilities to avoid extensive development works, causing
environmental impacts to the surrounding areas.
Figure 2.1 shows all of the
potential sites located within Tai Po District and geophysically suitable to be
developed as a bathing beach. The
potential bathing beach sites are mainly located in Plover Cove, Tolo Channel,
Hoi Ha Wan and
Therefore, with
consideration of the above criteria, all of the potential bathing beach sites
at the eastern region of Tai Po District including
Table 2.2: Comparison of the
|
Plover Cove |
Tolo Channel |
Hoi Ha Wan |
|
Adjoining to |
No |
Yes |
Yes |
Yes |
Adjacent to |
No |
No |
Yes |
No |
Adjoining to Site of Special
Scientific Interest (1) |
Yes, some of the potential sites |
Yes |
Yes |
No |
Adjacent to Special Area (1) |
Yes, some of the potential sites |
No |
No |
No |
Adjoining to Coastal Protection
Area (1) |
Yes, some of the potential sites |
No |
No |
No |
Adjoining to identified key
mangrove habitat (1) |
Yes, some of the potential sites |
Yes, some of the potential sites |
No |
Yes, some of the potential sites |
Adjacent to Fish Culture Zone (1) |
Yes, some of the potential sites |
Yes, some of the potential sites |
No |
No |
Having nearby existing
infrastructure (such as road and drainage systems) (2) |
Yes |
No |
No |
No |
Shortlisted Sites Identified |
Yes |
No |
No |
No |
Note: (1) Any potential sites locate adjoining to
(2) Only potential sites of nearby existing infrastructure
(such as road and drainage systems) will be considered as those sites can avoid
environmental impacts due to the development of additional infrastructure.
Areas within Plover Cove
are the remaining region in the Tai Po District considered to be suitable for
the Proposed Beach Development (Figure
2.2). There are some potential sites
identified within Plover Cove that avoid environmental sensitive areas,
including Country Park, Marine Park, Site of Special Scientific Interest,
Special Area, Coastal Protection Area, identified key mangrove habitat and Fish
Culture Zone. In addition, those
potential sites within Plover Cove have existing infrastructure which avoid
additional development and associated environmental impacts. Apart from the suitable shore environment,
Plover Cove can also be easy accessed by the public through the existing
·
·
Ma Shi Chau Special Area;
·
Ting Kok Special Site of
Scientific Interest (SSSI); and
·
Yim Tin Tsai (East) Fish
Culture Zones (FCZs).
Further to the review of
the coastal environment along the coastline of Plover Cove, three potential
sites, including Lung Mei, Shuen Wan and Sha Lan, are shortlisted for the
Proposed Beach Development (Figure 2.3). All of the three sites are located in
sheltered bay and therefore substantial sediment drift/ sand loss during
operation would not expect to be anticipated.
2.3.2
Potential Site Examined
i.
Lung Mei
Lung Mei is currently a non-gazetted beach located adjacent
to Tai Mei Tuk which is a popular leisure area, and well away from the Ting Kok
SSSI (about 500 m). From planning
perspective, development of a bathing beach in adjacent to the existing leisure
area can further enhance the recreational functions of the area. Part of the existing government land near the
shore can be utilised and thereby minimise the reclamation area. It is also situated along the existing Ting
Kok road and therefore additional transportation access or extensive associated
infrastructure would not be required.
However, drainage diversion of an existing box culvert and at lower
course of Lo Tsz River is required.
ii.
Shuen Wan
Shuen Wan is located to the north of Shuen Chim
iii.
Sha Lan
Sha Lan is currently a non-gazetted beach and is over 500 m
away from the Ting Kok SSSI towards the northeast. However, there is only one road (
2.3.3
Comparison of the
Environmental Benefits and Dis-benefits of the Potential Sites
i.
Lung Mei
Environmental
benefits
·
The bathing beach location is well sited away from Ting Kok
SSSI, as well as the mangrove habitat, and the existing waterpond at Tai Mei
Tuk, which has been designated as a Conservation Area.
·
It is sited far from the Yim Tin Tsai East FCZ.
·
It has limited dredging and reclamation, and so there is
lower potential for environmental impacts particularly regarding water quality
and waste management.
·
There is an existing piece of land for building the beach
facilities and the area of reclamation required can be minimised.
Environmental
dis-benefits
·
There are potentially more trees to be affected due to the
use of existing private land.
·
Diversion of lower course of Lo Tsz River causing impacts on
the stream (naturalness and ecological significance to be confirmed during
detailed survey) cannot be avoided, but no unacceptable impacts will be
anticipated due to the small scale of the works.
·
Beach facilities are close to village houses causing
potential air, noise and visual impacts, but no unacceptable impacts will be
anticipated due to the small scale of the works.
ii.
Shuen Wan
Environmental benefits
·
It is sited away from the Yim Tin Tsai East FCZ
Environmental
dis-benefits
·
It is sited in the proximity of Ting Kok SSSI and Shuen Wan
Egretry SSSI, as well as the mangrove habitat. The SSSI and mangrove habitats
are potentially affected due to the construction and operation of the Proposed
Beach Development.
·
More reclamation is required, so that there is
greater potential for environmental impacts particularly regarding water
quality and waste management compared with Lung Mei.
·
Diversion of lower course of
·
Beach facilities are close to village houses causing
potential air, noise and visual impacts, but no unacceptable impacts will be
anticipated due to the small scale of the works.
iii.
Sha Lan
Environmental
benefits
·
The bathing beach location is well sited away from the Ting
Kok SSSI, as well as the mangrove habitat.
·
Diversion of stream/ river is not required, therefore no
impacts on natural stream.
Environmental dis-benefits
·
It is close to the Sam Mun Tsai Egretry SSSI, Yim Tin Tsai
& Ma Shi Chau SSSI, Ma Shi Chau Special Area and Yim Tin Tsai East
FCZ. The FCZ is potentially affected due
to the construction and operation of the Proposed Bathing Beach Development.
·
More reclamation is required, so there is
greater potential for environmental impacts particularly regarding water
quality and waste management compared with Lung Mei.
·
Provision of additional or enhancement of transportation
access including road upgrading and provision of longer sewer connection (to
local sewer) would be required. Impacts
on terrestrial ecological resources will be comparatively larger.
·
Beach facilities are close to village houses causing
potential air, noise and visual impacts, but no unacceptable impacts will be
anticipated due to the small scale of the works.
The key environmental concerns of the site comparisons are
the extent of reclamation and dredging which will unavoidable to induce water
quality, marine ecology and fisheries impacts. With consideration of the extent of dredging and
reclamation, proximity of sensitive receivers such as Yim Tin Tsai East FCZ,
provision of additional transport infrastructure and potential impacts
(particularly water quality, waste management, marine and terrestrial ecology,
and fisheries) to the environment, Lung Mei is considered to be the most
suitable site for the proposed beach development in Tai Po (Table 2.3). Although the beach facilities will be located
close to village houses causing potential air, noise and visual impacts, no
unacceptable impacts will be anticipated due to the small scale of the works
and with the implementation of good construction practices.
In summary, Lung Mei is considered to be the best location
for the proposed beach development, which is located next to the existing road
(
Table 2.3: Comparison
of Likely Overall Environmental Impacts on the Three Potential Sites
|
Lung Mei |
Shuen
Wan
|
Sha Lan |
Environmental Benefits and Dis-benefits |
|||
Estimated Reclamation Size |
Approximately 1 ha |
Approximately 2 ha (1) |
Approximately 2 ha
(1) |
Extent of Dredging |
Approximately 5 ha |
Approximately 5 ha |
Approximately 5 ha and 10,000m3 (2) |
Distance to - |
|||
Plover Cove Country Park |
Approximately 350m |
> 2km |
> 2.3km |
Ting Kok SSSI |
Approximately 500m |
< 40m |
Approximately 700m |
Shuen Wan Egretry SSSI |
Approximately 2km |
< 10m |
< 300m |
Sam Mun Tsai Egretry
SSSI
|
Approximately 1.7km |
Approximately 1km |
Approximately 650m |
Yim
Tin Tsai & Ma Shi Chau SSSI |
Approximately
1.2km |
Approximately
1.9km |
Approximately 1.4km |
Mangrove Habitat |
Approximately 500m |
< 40m |
Approximately 700m |
Ma Shi Chau Special
Area |
Approximately 820m |
Approximately 1km |
Approximately 1km |
Yim Tin Tsai East FCZ |
Approximately 1.5km |
Approximately 1.5km |
Approximately 1km |
Conservation Area |
Approximately 400m |
> 2km |
> 2.5km |
Requirement of diversion of stream/ river |
Yes, lower course of Lo Tsz River |
Yes, lower course of
|
No |
Requirement of additional/ enhancement of transportation access
longer sewer connection |
No |
No |
No |
Likely Environmental Impacts |
|||
Air Quality |
Low |
Low |
Low |
Noise |
Low |
Low |
Low |
Waste |
Low |
Moderate |
Moderate |
Water
Quality |
Low |
Moderate |
Moderate |
Terrestrial
Ecology |
Low |
Negligible |
Low |
Marine
Ecology |
Low |
Moderate |
Moderate |
Fisheries |
Low |
Low |
Moderate |
Landscape
and Visual (including tree felling) |
Low to Moderate |
Low |
Low |
Overall Likely Environmental
Impacts |
Low |
Low to Moderate |
Low to Moderate |
Note: (1) Reclamation sizes of Shuen Wan and Shan Lan sites are estimated by provision of same carpak and beach building size as at Lung Mei site, taking into account any available existing land for the development.
(2) Dredging extents and volumes
of Shuen Wan and Sha Lan sites are estimated under an assumption that their
dredging depth and beach size will be very similar as Lung Mei site.
The feasibility of following alternative designs has been
investigated in this Assignment as discussed below for the preferred option at
Lung Mei. In addition, the design and construction of each element of the works
were considered in light of construction methods and sequencing of works:
2.4.1
Option Layout
Option Layout Assessment during Feasibility Study
4 options of the bathing beach configuration at Lung Mei have been
investigated in the Feasibility Study and are shown in
Appendix A. The option
layouts were developed to study different orientations of car park, beach
building, seawall requirements, etc in order to facilitate the beach users,
reduce construction cost and minimise the environmental and engineering
impacts. An option evaluation was also
carried out on each layout and its location, which were based on the following
criteria:
•
Utilisation of beach area
and facilities
• Extent of sand
filling work on the seaward
• Sand stability
control
• Construction cost
• Impacts on
environment
• Air pollution to
beach users
• Traffic circulation
• Channelisation of
natural stream and maintenance.
Considering the various pros and cons of each option as
shown on Table 2.4, it was
recommended that Option 1 would be adopted for further investigation and
development. From Option 1, the car park
site and beach building were shifted eastward to avoid decking over the Lo Tsz
River. The final recommended beach
layout in feasibility study stage is shown on Figure 3.5 of
Appendix A.
Table 2.4:
Evaluation of Beach Option Layouts Proposed during Feasibility Study
Review on |
Option 1 |
Option 2 |
Option 3 |
Option 4 |
Utilisation of beach area and
facilities |
As the car park sets back from the
beach area, a longer waterline is provided, this may be of interest from
recreation point of view. Eastern half of parking area to be
probably occupied first, as it is closer to the facilities house and the
beach area. Longer walk is required
for other users coming late. |
The car park is close to the main
beach area. It is more convenient for
beach users. As compared to Option 1, the
facilities house has a longer distance to the main beach area. Also a shorter waterline is provided. |
The car park is split into two
portions and the facilities house is located at midway between the two
parking areas. It is convenient for
beach users to park their cars and access to the facilities house. The facilities house is close to
the main beach area; however, a shorter waterline is provided as compared to
Option 1. |
Two rows instead of four car pots
are provided. This provides more
usable beach area, and results in a long waterline. Eastern half of parking area to be
probably occupied first. Longer walk
from west of the car park area for other users coming late |
Extent of sand filling work on
seaward |
Approximate 2,000m2 |
Approximate 4,000m2 |
Approximate 4,000m2 |
Approximate 2,000m2 |
Sand stability control |
Better because of presence of
revetment or groyne. |
Wave turbulence likely created at
southeast corner of car park resulting in local scouring and increasing the
loss of sand. A groyne may be required
to overcome this situation. |
Same as Option 2 |
A groyne likely to be required to
prevent the loss of sand. |
Construction cost |
Moderate; groyne construction is
required. |
Expensive because of seawall
construction and either regular replenishment of sand or provision of a
groyne. |
Same as Option 2 |
Cheaper |
Impact on environment |
Construction of car park decking
close to the SSSI and wetland |
A longer distance to the SSSI and
wetland. |
Same as Option 2 |
Same as Option 1 |
Air pollution to beach user due to
traffic at Ting Kok Road |
Poor because sand area close to Ting Kok Road |
Better because of car park area and
the facilities house shifted away the Road. |
Same as Option 2 |
Same as Option 2 |
Traffic control |
Better traffic circulation flow
inside car park. Alternative route
available for diversion traffic flow if one of the routes is blocked. |
Same as Option 1 |
Same as Option 1 but increase in
junctions of car park exit and entrance interface the traffic flow at Ting Kok Road. |
Poor traffic circulation inside car
park. |
Channelisation of natural stream
and maintenance |
A section of some 35m long channel
will be decked. Maintenance of the
decked channel may be of concern. |
Channel will not be decked. |
Same as Option 2 |
Same as Option 1 |
Option Layout Assessment during Investigation Stage
The option layout for this Assignment is developed based on
the recommended option in the Feasibility Study. Although the requirements of
the bathing beach development specified in this Investigation Stage have been
revised, which resulted in the change of configuration for the car park,
building facilities and beach layout, the proposed outcome conclusion is
similar to that expressed in the Feasibility Study.
The current requirements are to provide a minimum beach area
of 6,000m2 above the high water mark for a maximum of 4,000 bathers
at peak period, a parking area for 100 cars, 10 motorcycles and 3 coaches and
beach building facilities. The proposed layout of the beach facilities are
shown on
Figure 2.4.
A review on the location of the proposed bathing beach
layout has been carried out to consider the alternative of locating the
proposed beach further to the west, east and south as follow:
Option A: Shifting the
Option B: Shifting the
Option C: Shifting the
A comparison of the Preferred Options with Options A, B and
C has been carried out and shown on Table
2.5. It shows that the current
layout location is the comparatively preferable in terms of environmental
impact, cost impact and technical viability, whilst meeting the design
requirements. It should be noted that
the lower course of Lo Tsz River has been modified in certain extent (details
refer to Section 8) and subject to
tidal influence. The impacts on the
environment due to reclamation is considered to be more significant compare
with the diversion of lower course of Lo Tsz River, and therefore the Preferred
Option is selected which minimised the reclamation area. Moreover, the current proposed location is
remote from the Fish Culture Zone at Yim Tin Tsai (East), thereby minimising
potential conflicts with fishermen. By selecting the current site at Lung Mei
impacts to these ecologically and conservation sensitive areas have been
minimised.
Table 2.5: Comparison of Layout Options During
Investigation Stage
Considerations |
Preferred Option |
Option A (West) |
Option B (East) |
Option C (South) |
Environmental Issues |
|
|
|
|
Extent of Reclamation |
Approximate
1.02ha |
Similar
to the Preferred Option |
Greater
than the Preferred Option (could be up to around 40% more) |
Greater
reclamation area than the Preferred Option; (could be up to around 50%) Longer
groynes to be required to ensure
shoreline stability |
Extent and Quantity of Dredging |
Approximate
5 ha and 10,000 m3 |
Extent
similar to the Preferred Option; Dredging
quantity to be larger than the Preferred Option due to shallow water at the
west |
Extent
and quantity similar to the Preferred Option |
Extent
and quantity to be more than the
Preferred Option, as there is a sudden level drop further out the sea. |
Sandfilling requirement |
Approximate 37,500m3 |
Slightly
less than the Preferred Option |
Slightly
greater than the Preferred Option due to deeper water at the east |
Greater
than the Preferred Option due to deeper water at the south |
Distances from
Environmental Sensitive Receivers |
About
500m from the Ting Kok SSSI; About
400m from Conservation Area |
Closer
to the Ting Kok SSSI and away from Conservation Area compared with the
Preferred Option |
Away
from the Ting Kok SSSI but closer to Conservation Area compared with the
Preferred Option |
Similar
to the Preferred Option but comparatively closer to the Fish Culture Zone |
Impacts on Trees |
157
trees identified within the Project
site and 119 to be affected |
More
trees to be affected due to occupation of the existing private land |
Affected
trees to be slightly less than the Preferred Option |
Similar
to the Preferred Option |
Impacts on the estuary
of Lo Tsz River |
No
works |
Decking
of the Lo Tsz River required |
No
diversion works of Lo Tsz River |
Similar
to the Preferred Option |
Impacts on the existing infrastructures |
One
existing box culvert to be affected, requiring drainage diversion works; |
Similar
to the Preferred Option |
Extensive
impacts on the existing box culverts, other drainage outlets and the existing
seawall, which will require modification or diversion works |
Similar
to the Preferred Option |
Land Resumption |
Approximately
1ha |
More
private land resumption required |
Slightly
less than the Preferred Option |
Similar
to the Preferred Option |
Impacts on marine facilities and transportation |
12
existing mooring buoys to be affected |
Similar
to the Preferred Option |
Numbers
of the affected existing mooring buoys
similar to the Preferred Option; Conflict
with and limiting the existing leisure activities |
More
existing mooring buoys to be affected; Closer
to the existing activity zone designated by the Tai Mei Tuk Water Sports
Centre |
Overall Construction Cost |
N/A |
Higher than the
Preferred Option |
Higher than the
Preferred Option |
Higher than the
Preferred Option |
Preferability |
Preferred Option to achieve a
balance with different considerations |
Not Preferred due to encroaching
into the Ting Kok SSSI and decking required at Lo Tsz River |
Not Preferred due to involving
greater reclamation, extensive modification/diversion works for the existing
box culverts and seawall with significant potential environmental impacts
during construction |
Not Preferred due to greater
reclamation area required, as well as longer groynes and larger site
boundary. Minimising reclamation is one of the key requirements of this
Project |
Furthermore, several configurations of the proposed beach,
carpark and building layout have been investigated, in order to identify an
optimal solution to fulfil all the environmental and engineering requirements
as listed below:
Several configurations of the proposed beach, carpark and
building layout have been investigated, in order to identify an optimal
solution to fulfil all the environmental and engineering requirements as listed
below:
·
Hydrodynamic Analysis
This was carried out for the proposed groynes and beach
profiles to study their stability and recommend a suitable beach orientation,
which would minimise sand loss, long-term sandfilling maintenance requirements
and optimise the proposed groyne lengths.
·
Optimisation of Land Uses
The studies were carried out to minimize the overall
reclamation requirement with consideration of the following development
scenarios:
-
The level of the car park and ground compound of the
proposed bathing beach facilities and administration building is restricted by
matching in with the existing level of
-
There was an agreed requirement to maintain a buffer zone of
10m between the beach building and the high water mark at extreme storm
conditions of 1 in 100 years, maintaining a beach level at +4.6mPD. However,
this would have meant a larger reclamation area and increased area for the
bathers at high water mark conditions. This requirement was subsequently
reduced to a modelling of a design wave condition for a 1 in 20 years return
period and it was ascertained that under this condition an area of 6,000m2
above the high water mark (HWM) was achieved. This also reduced the length of
the groynes.
-
With the 1 in 20 years return
period, the top level of the beach at equilibrium will be at +3.8mPD while the
mean higher high water level at the project site is +2.0 mPD. Moreover, the
proposed beach will provide an area of 6,000m2 above HWM to
accommodate 4,000 beach goers in the peak season. In addition, the minimum
clearance of 10m between the high water level and beach building will be
maintained at about +3.1mPD, which corresponds to 1 in 4 years return period.
-
A decked car park was proposed, thereby reducing the
footprint of the parking area but this option was not preferred as it would
have an increased visual impact. Conversely, most of the beach buildings are
located towards the beach, away from the
-
The distances between buildings for the Proposed Beach
Development were limited to the requirement of the Fire Services Department for
EVA, which is 6m minimum.
-
Designing the buildings closer together or align them side
by side, such as the gents and ladies changing rooms and toilets. However, this
would limit the circulation movement for the bathers inside the changing rooms
and also limit the movement of bathers on the paved areas going to and fro from
the east side of the beach and the car park. Therefore this was not preferred.
-
The building for the equipment / machinery stores for
catamarans, motorized boats and beach transporters had to be situated close to
the centre of the beach paved area, as this would be the ideal location for
emergencies within the beach area.
·
Minimisation of Dredging
To minimise the environmental impact, the removal of large
quantities of sediment had to be avoided. Therefore, a minimum of 500mm depth
of sediment removal has been proposed, so as to remove all boulders, cobbles,
stones and silty material within the proposed beach area prior to sand filing.
The above materials and debris are required to be removed as they may be
exposed during seasonal changes of the beach profile and platform, which would
be dangerous to the beach users. Moreover, the proposed dredging depth at the
groynes is around 0.5m to 1m for the levelling of the groyne foundation which
is essential for the groyne stability and safety of the beach users.
Therefore, in light of the above, it is considered that the
present arrangement and layout is the most optimal in terms of environmental
impact, cost impact and technical viability, whilst meeting the requirement of
the LCSD and the Brief.
2.4.2
Road Access
Different scenarios of ingress/egress to the proposed car
park have been investigated and it is considered that the current arrangement
best suits the site constraints and requirements. The proposed ingress/egress
is constrained by the requirement of the Transport Planning Design Manual,
where it states that new access should be situated at least 40m away from
existing accesses on the near or far side of the road. Therefore, as there are
two existing accesses leading from Lo Tsz Tin village, the current access
layout is the most preferred.
On the west side, there is the existing Lo Tsz River. The
development has been designed to avoid encroaching into that area as much as
possible for environmental reasons. However, there will be a proposed culvert,
at the upstream end of Lo Tsz River where it meets the
It is envisaged that the construction method for the road
works will be conventional; however, 4 stages of temporary traffic arrangement
are anticipated to complete the roadworks, drainage, sewerage and utilities
works.
2.4.3
Open Channel with
Embankments Baskets at Western End of
To comply with the clause 5.3.2 under Chapter 10 of the Hong
Kong Planning Standards and Guidelines, that no discharge outlets for effluent
disposal should be located within 100m of any gazetted beach, there is the need
to divert the flow from the existing culvert, at the western section of the
bathing beach development. Therefore, different designs for the diversion were
studied, such as a 6.8m rectangular diversion channel that was proposed in the
feasibility study, a culvert and a trapezoidal reinforced concrete channel.
However, in accordance with the Technical Memorandum on EIA process (EPD,
1997), the general policy or approach for mitigating impacts on natural
streams/rivers is in the order of priority, avoidance, minimisation and
compensation, therefore, an open channel with gabion embankments is proposed as
shown on Figure 2.5.
Planters will be provided along the top of the gabion
embankments to mitigate visual impacts from
It is anticipated that the sheet piling as temporary works
for the gabion channel will be carried out using a silent piler, to minimise
the construction noise impact. In addition, the construction of the gabion
baskets for the channel wall and channel bed will be mostly manual and
therefore be more environmentally friendly than the conventional reinforced
concrete open channels.
2.4.4
Culvert at Eastern End of
As discussed in Section 2.4.3, the culvert at the east side
of the beach development had to be diverted as well in order to comply with clause
5.3.2 under Chapter 10 of the Hong Kong Planning Standards and Guidelines. We
have looked at the preliminary design carried out in the feasibility study and
consider that the proposal of constructing a culvert within the carriageway
will slow down the progress of construction. Therefore, we propose to reprofile
the existing culvert at the outlet and divert a new culvert with a right angle
turn to the east by around 90m and parallel with the existing sea wall as shown
on Figure 2.6.
This proposal will not necessitate the digging up of the
existing road and therefore, avoid longer and more extensive temporary traffic
management periods as well as reducing the dust and noise impacts. To ease
construction difficulties and minimize the environmental impacts, we propose
that the box culvert be constructed as pre-cast and cast in-situ segments and
therefore the pre-cast segments can be lifted onto the coast from the
2.4.5
Design of Groynes
The preferred groyne layout option include two rock armour
groynes comprising a western groyne length 100m and an eastern groyne length
120m, both from the building line as shown on
Figure 2.7 to protect the
proposed sandy beach. The design beach to be constructed consists of a 1:12.5
upper slope above +2.0mPD and 1:15 below, with the beach recharge offshore of
the natural step consisting of a 1:25. The crest height of beach at design is
+4.6mPD and the height of groyne at crest is also +4.6mPD for 5m and then
basically falls towards the sea at 1 in 25 as shown on
Figures 2.8 and
2.9. The groynes are designed to retain the beach sand, with the sand profile at construction
as shown on Figures 2.7 to 2.9. During the natural course of events; the beach
will reach an equilibrium profile, also shown on
Figures 2.7 to 2.9.
The proposed groynes will be constructed with a primary rock
armour layer and a rock fill core as shown on
Figure 2.10. To enhance the landscaping areas within the
Project site, a planter is proposed on each groyne with minimum dimensions of
1.5m (H) x 1.5m (W). The proposed
arrangement of the groyne and planter is also depicted on
Figure 2.10.
Apart from the preferred beach layout, other options for
increasing the groyne lengths have also been examined. Two other options were
to have the groynes (both east and west groynes) extended to 135m as well as
180m to the sea, so that the beach material at the toe of the beach slope would
be less susceptible to movement under extreme storm conditions. However, this
would increase the construction quantities, which would not be justified in
consideration of environmental and cost impacts for a longer groyne as well as
more dredging and sand filling required.
In addition, wave and sediment modelling was conducted for
the above scenarios as presented in
Appendix
B and it was demonstrated that the beach material would basically be
retained by the groynes for the preferred layout scheme, due to the current
location of the beach.
Other options for the groyne construction were investigated,
such as concrete blocks and timber. However, rock armour was chosen as it would
be simpler and more natural in appearance. Armour rock will be more ecological
beneficial and require little or no maintenance.
It is anticipated that the groyne construction will commence
prior to the sand filling. The west groyne will most probably be constructed
first. Dredging for the groyne would be carried out by land plants for
locations above the low water mark, whereas a grab dredger will dredge the
seabed for the groyne below the low water mark. The placing of sand is expected
to be carried out using a backfilling barge with a conveyor belt, most probably
from west to east.
2.5.1
The basic construction methods were discussed in
Section 2.4; however, the following
alternative construction methods were also looked into:
·
Silent piler for the
installation of sheet piles as temporary works in the construction of the
gabion channel and for deep excavation for drainage works was proposed to
reduce the noise impact;
·
Pre-cast sections for the
lower half of the culvert at the east end of the beach, to minimise temporary
traffic management as well as noise, dust and material (formwork) on site. The
duration of the construction works could also be reduced;
·
Precast concrete units
for the retaining walls for the boundary of the car park and bathing beach
building to minimise noise, dust and material on site. The duration of the
construction works could also be reduced;
·
Gabion baskets are used
for the channel diversion at the west end of the bathing beach, and therefore
less construction plants will be used for the channel wall and bedding. This
will reduce the construction noise impact as well as material used on site
·
The justifications for
dredging are addressed in Section 2.4.1.
All dredged material is proposed to be disposed by sea (either to South Cheung
Chau dumping ground or East Sha Chau mud pits subject to the results of
sediment testing) and thereby reducing the land transport by trucks; and
·
It is proposed to use the
existing rocks on site for the gabions and groyne construction if the
specifications of the rocks are met.
2.5.2
During the construction phase, the estimated quantities have
generally been reduced since the feasibility stage for the overall construction
works, which was due to alternative construction designs and revising some of
the requirements of the EIA Study Brief,
as shown below:
i. Estimated quantity of land-based excavated
materials is summarised below:
Description for Construction Works |
Volume (m3) |
|
Excavation |
Demolition |
|
Building
& Landscaping |
800 |
10 |
Works
along |
600 |
450 |
Works
at Carpark (including drainage & sewerage works, and carpark formation) |
4,000 |
- |
Vertical
Seawall/Retaining Wall |
2,000 |
- |
Western
Drainage Channel (1) (i.e.
Open channel and box culvert) |
4,500 |
10 |
Eastern
Box Culvert (1) |
1,900 |
- |
Total |
13,800 |
470 |
Note 1: Construction of
the proposed western drainage channel and eastern box culvert will be carried
out above high water mark (HWM) and therefore considered as land-based
construction activities. No dredging
will be required for the proposed drainage diversion works.
It has been
estimated that about 60% of the above land-based excavation can be
reused, that is around 8,280m3.
ii. Estimated Dredging Quantities:
·
Dredged plan area is approximately 5.0ha.
· Dredging volume for the seabed, groynes and seawall is 10,500m3.
iii. Estimated Reclamation Area for the
overall development is about 1.02ha
(or 10,200m2) and
comprises the following:
Description |
Reclamation
Area (m2) |
For bathing beach area |
9,500 |
For groynes |
700 |
Total |
10,200 |
iv. Estimated Rocks and Filling Quantities:
Marine
Works
Description |
Volume (m3) |
|
Rock/Rockfill |
Sand Fill |
|
Beach Construction |
- |
37,500 |
Groyne construction ·
Armour layers ·
Rockfill core |
3,000 1,600 |
- - |
Total |
4,600 |
37,500 |
Land Works
Description |
Volume (m3) |
||
Rock/Rockfill |
Granular Fill /Aggregates |
Soil /Sand Fill |
|
Carpark & Beach Buildings |
|||
·
Backfill of retaining
wall* |
- |
- |
21,000 |
·
Building construction |
- |
- |
100 |
·
Sub-base of carpark |
- |
2,000 |
- |
Western Drainage Channel |
|||
·
Foundation of box
culvert |
40 |
- |
- |
·
Rip-rap bedding of open
channel |
300 |
- |
- |
·
Gabion embankments |
1,400 |
- |
- |
·
Armour layers at outfall |
120 |
- |
- |
·
Rockfill slopes at
outfall |
120 |
- |
- |
·
Backfill of box culvert
and embankments |
- |
- |
1,900 |
Eastern Box Culvert |
|||
·
Foundation |
800 |
- |
- |
·
Backfill of box culvert |
- |
900 |
- |
·
Filling of Planter Wall |
- |
- |
600 |
·
Sandfill for temporary
excavation |
- |
- |
600 |
Works along |
|||
·
Sub-base for local road
widening |
- |
400 |
- |
·
Drainage, sewerage and
utilities |
- |
- |
500 |
Total |
2,800 |
3,300 |
24,700 |
Note: * Land formation for
the proposed carpark and beach building.
v. GFA of new
building/structure according to Building Ordinance = 2,245m2.
2.5.3
The sequences of works for the construction works.
The
comparison of different sequence of works, together with the environmental
benefits and dis-benefits are presented in
Appendix
C1. The following sequences of works
are discussed;
1.
Site Formation for
2.
Road Widening, Roadworks, Utilities, Drainage and Sewerage
Works
3.
Groyne Construction, Dredging and
Sand Filling
The
preferred sequences of works for each element of construction works are
presented in Appendix C2
and
summarised below:
1.
The construction of ramp, staircase,
vertical seawalls, retaining walls and their foundations.
2.
Construction of beach buildings and
their foundations
3.
Construction of paving area for car
park.
4.
Road pavement construction (this
work will be carried out concurrently or in stages with the construction works
for utilities, watermain, drainage and sewerage):
4.1
Construction of new sewage pipeline
and manholes
4.2
Construction of new drainage
pipeline gullies
4.3
Laying of watermains and utilities
5.
Construction of western box culvert.
6.
Construction of western drainage
open channel.
7.
Construction of modification works
on existing box culvert
8.
Construction of 90m long eastern box
culvert.
9.
Groyne construction.
10.
Dredging and sand filling.
The current Project site is situated along the existing
coastline of
The existing site area above high water mark (HWM) is about
8000m2. The beach water is very shallow over a long distance from
the current high water mark. However, based on the Wave and Sediment Modelling
Report, the normal wave condition at Lung Mei area is considered as very mild.
Our study concluded that the proposed bathing beach location and layout would
be less susceptible to erosion due to surge overwash and longshore sediment
transport, such that the sediment transport and siltation under the influence
of environmental forces during the operational phases will be minimal.
Moreover, the present site location (at Lung Mei) is ideal
in consideration of environmental factors as discussed in Section 2.3 (including minimised extent of dredging and reclamation,
and located away from sensitive receivers, including Ting Kok SSSI and FCZ),
and which will complement and be conveniently located to the existing
facilities/activities in the Tai Mei Tuk area.
Given the discussion in Sections
2.4 & 2.5, the proposed construction method and sequences of works,
detailed in Section 3, are the
preferred scenario that will maximise environmental benefits and minimised
adverse environmental effects arising from the Project.