This section identifies the potential wastes arising
from the construction and operation of the Proposed Beach Developing at Lung
Mei and assesses the potential environmental impacts associated with waste
handling and disposal. The main issues
are:
· Management
of dredged materials;
·
Handling
and disposal of contaminated soil/sediments;
·
Handling
and disposal of construction and demolition (C&D) materials arising from
the demolition, excavation and construction works; and
·
Management
of chemical waste, sewage, and general refuse.
Waste avoidance, minimisation, reuse and recycling,
storage, collection, transport and disposal schemes have been examined and
appropriate measures for waste reduction and management have been
proposed.
The following
discussion on legislative requirements and evaluation criteria applies to both
the construction and operational phases of the Proposed Beach Development. The criteria and guidelines for evaluating
potential waste management implications are laid out in Annexes 7 and 15 of the
EIAO-TM under the EIAO (Cap 499). The following legislation covers, or has some
bearing upon the handling, treatment and disposal of the wastes generated from
the construction and operation of the Proposed Beach Development.
·
Waste Disposal Ordinance (Cap
354);
· Waste Disposal (Chemical Waste) (General) Regulation (Cap 354C);
·
Land (Miscellaneous Provisions)
Ordinance (Cap 28)
·
Public Health and Municipal
Services Ordinance (Cap 132) - Public Cleansing and Prevention of Nuisances
Regulation; and
·
Dumping at Sea Ordinance (Cap
466).
7.2.1
Waste
Disposal Ordinance (Cap 354)
The Waste
Disposal Ordinance (WDO)
prohibits the unauthorised disposal of wastes, with waste defined as any
substance or article, which is abandoned.
Construction waste is not directly defined in the WDO but is considered to fall within the category of
‘trade waste’. Trade waste is defined as
waste from any trade, manufacturer or business or any wasted building, or civil
engineering materials, but does not include animal waste.
Under the WDO, wastes can only be disposed of at a licensed
site. The WDO provides for the issuing of licences for the
collection and transport of wastes.
Licences are not, however, currently issued for the collection and
transport of construction waste or trade waste.
The Waste
Disposal (Charges for Disposal of Construction Waste) Regulation defined construction waste as any substance, matters
or things that is generated from construction work and abandoned, whether or
not it has been processed or stockpiled before being abandoned.
The Construction
Waste Disposal Charging Scheme entered into operation on 1 December 2005. Starting from 1 December 2005, the main
contractor who undertakes construction work under a contract with value of HK$1
million or above is required to open a billing account solely for the contract
for waste disposal. Application shall be
made within 21 days after the contract is awarded. Under the Scheme, charging for disposal of
construction waste started on 20 January 2006 and therefore will apply to this
Project.
Depending on the
percentage of inert materials in the construction waste, inert construction
waste can be disposed of at public fill reception facilities. However mixed construction waste can be
disposed of at construction waste sorting facilities and landfills which have
different disposal costs. The scheme
encourages reducing, reusing and sorting of construction waste such that the waste
producer can reduce their disposal fee. Table
7.1 summarises the
government construction waste disposal facilities, types of waste accepted and
disposal cost.
Table 7.1: Government
Facilities for Disposal of C&D Materials
Government Waste Disposal Facilities |
Type of Construction Waste Accepted |
Charge (HK$/Tonne) |
Public fill reception facilities |
Consisting
entirely of inert construction waste |
$27 |
Sorting facilities |
Containing more
than 50% by weight of inert construction waste |
$100 |
Landfills |
Containing not
more than 50% by weight of inert construction waste |
$125 |
Outlying |
Containing any
percentage of inert construction waste |
$125 |
Chemical waste as
defined under the Waste Disposal (Chemical Waste) (General) Regulation includes any substance being scrap material, or
unwanted substances specified under Schedule 1 of the Regulation, if the specified substance or chemical occurs in
such a form, quantity or concentration so as to cause pollution or constitute a
danger to health or risk of pollution to the environment.
A person should
not produce, or cause to be produced, chemical wastes without registration with
the EPD. Chemical wastes must either be
treated using on-site facility licensed by EPD or be collected by a licensed
collector for off-site treatment at a licensed facility. Under EPD Regulation, the waste producer, collector and disposal facility
must sign all relevant parts of a computerised trip ticket for each consignment
of waste. The computerized system is
designed to allow the transfer of wastes to be traced from cradle-to-grave.
The EPD Regulation prescribes storage facilities to be provided on-site
which include labelling and warning signs. To reduce the risks of pollution and danger to
human health or life, the waste producer is required to prepare and make
available written emergency procedures for spillage, leakage or accidents
arising from the storage of chemical wastes. They must also provide their
employees with training on such procedures.
7.2.3
Land
(Miscellaneous Provisions) Ordinance (Cap 28)
The inert portion
of C&D materials (also called public fill) may be taken to public fill
reception facilities. Public filling
areas usually form part of land reclamation schemes and are operated by the
Civil Engineering and Development Department (CEDD) and others. The Land
(Miscellaneous Provisions) Ordinance requires that individuals or companies who deliver
public fill to the public fill reception facilities to obtain a Dumping Licence
from the CEDD.
Under the licence conditions,
public fill reception facilities will only accept earth, soil, sand, rubble,
brick, tile, rock, boulder, concrete, asphalt, masonry or used bentonite. In addition, in accordance with paragraph 11
of the ETWB TC(W) No.31.2004, Public Fill Committee will advise on the
acceptance criteria (e.g. no mixing of construction waste, nominal size of the
materials less than 250mm, etc). The
material should, however, be free from marine mud, household refuse, plastic,
metal, industrial and chemical wastes, animal and vegetable matter and any
other materials considered unsuitable by the public fill reception facility
supervisor.
7.2.4
Public
Health and Municipal Services Ordinance (Cap 132) - Public Cleansing and
Prevention of Nuisances Regulation
This Regulation provides a further control on the illegal dumping of wastes on unauthorised (unlicensed) sites.
7.2.5
Dumping
at Sea Ordinance (Cap 466)
This Ordinance came into operation in April 1995 and empowers the
Director of Environmental Protection (DEP) to control the disposal and
incineration of substances and articles at sea for the protection of the marine
environment. Under the Ordinance, a permit from the DEP is required for the disposal
of regulated substances within and outside the waters of the Hong Kong
SAR. The permit contains terms and
conditions that includes the following specifications:
·
Type and quantity of substances
permitted to be dumped;
·
Location of the disposal grounds;
· Requirement of equipment for monitoring the disposal operations; and
·
Environmental monitoring
requirements.
Management of Dredged/Excavated Sediments for Marine
Disposal
Marine disposal of
any dredged/excavated sediment is subject to control under the Dumping
at Sea Ordinance 1995. Dredged/excavated sediment destined for
marine disposal is classified based on its contaminant levels with reference to
the Chemical Exceedance Levels (CEL), as stipulated in ETWBTC No. 34/2002:
Management of Dredged/Excavated Sediment.
This Technical Circular includes a set of sediment quality criteria, as
presented in Table 7.2, which includes heavy metals and metalloids, organic
pollutants and a class of contamination level for highly contaminated sediment
not suitable for marine disposal.
Table
7.2: Dredged/Excavated Sediment Quality Criteria for the Classification under
the ETWBTC No 34/2002
Contaminants |
Lower Chemical Exceedance Level (LCEL) |
Upper Chemical Exceedance Level (UCEL) |
Metals (mg kg-1 dry weight) |
||
Cd |
1.5 |
4 |
Cr |
80 |
160 |
Cu |
65 |
110 |
Hg |
0.5 |
1 |
Ni(a) |
40 |
40 |
Pb |
75 |
110 |
Silver (Ag) |
1 |
2 |
Zinc (Zn) |
200 |
270 |
Metalloid (mg
kg-1
dry weight) |
||
Arsenic (As) |
12 |
42 |
Organic-PAHs (mg
kg-1 dry weight) |
||
Low Molecular
Weight (LMW) PAHs |
550 |
3,160 |
High Molecular
Weight (HMW) PAHs |
1,700 |
9,600 |
Organic-non-PAHs (mg
kg-1 dry weight) |
||
Total PCBs |
23 |
180 |
Organometallics (mgTBT l-1
in interstitial water) |
||
Tributyl-tin (a) |
0.15 |
0.15 |
Note:
(a) The
contaminant level is considered to have exceeded the UCEL if it is greater
than the value shown. |
In
accordance with ETWBTC 34/2002, the sediment is classified into three
categories based on its contamination levels:
Category L: Sediment with all contaminant levels not
exceeding the LCEL. The material must be
dredged, transported and disposed of in a manner which reduces the loss of
contaminants either into solution or by re-suspension.
Category M: Any
one or more contaminants in the sediment exceeding the LCEL with none exceeding
the UCEL. The material must be dredged
and transported with care, and must be effectively isolated from the
environment upon final disposal unless appropriate biological tests demonstrate
that the material will not adversely affect the marine environment.
Category H: Any
one or more contaminants in the sediment exceeding the UCEL. The material must be dredged and transported
with great care, and must be effectively isolated from the environment upon
final disposal.
Figure 7.2 summarises the sediment classification and disposal
arrangements. EPD will use the sediment
and biological test results to determine the most appropriate disposal site
(e.g. open sea or confined marine disposal site).
In
accordance with ETWB TC 34/2002, the allocation of sediment disposal space at
sea will be considered only if the need for removal of the sediment has been
satisfactorily demonstrated. Therefore
it is desirable to demonstrate that any proposed mud dredging has been reduced
as far as reasonably and safely practicable and to obtain, in-principle, an
agreement from the Secretary of the Marine Fill Committee (MFC) of the CEDD at
an early stage. Procedures as stipulated
under ETWB TCW No. 34/2002 should be followed if marine disposal of dredged/
excavated sediments is involved.
7.2.6
Other
Relevant Guidelines
Other guideline documents which detail how the
Contractor will comply with the WDO and its associated regulations include:
·
Waste Disposal Plan for Hong
Kong (December 1989), Planning, Environment and Lands Branch Government
Secretariat,
·
Chapter 9 - Environment (1999),
Hong Kong Planning Standards and Guidelines,
·
New Disposal Arrangements for
Construction Waste (1992), EPD & CED,
·
Code of Practice on the
Packaging, Labelling and Storage of Chemical Wastes (1992), EPD,
·
Works Branch Technical Circular
(WBTC) No. 32/92, The Use of Tropical Hard Wood on Construction Site; Works
Branch,
·
WBTC No. 2/93, Public Dumps.
Works Branch,
·
WBTC No. 2/93B, Public Filling
Facilities, Works Branch,
·
WBTC No. 16/96, Wet Soil in
Public Dumps; Works Branch,
·
WBTC Nos. 4/98 and 4/98A, Use
of Public Fill in Reclamation and Earth Filling Projects; Works Bureau,
· Waste Reduction Framework Plan, 1998 to 2007, Planning, Environment and Lands Bureau, Government Secretariat, 5 November 1998;
·
WBTC Nos. 25/99, 25/99A and
25/99C, Incorporation of Information on Construction and Demolition Material
Management in Public Works Sub-committee Papers; Works Bureau,
·
WBTC No. 12/2000, Fill
Management; Works Bureau,
·
WBTC No. 19/2001, Metallic Site
Hoardings and Signboards; Works Bureau,
·
WBTC Nos. 6/2002 and 6/2002A,
Enhanced Specification for Site Cleanliness and Tidiness. Works Bureau,
·
WBTC No. 11/2002, Control of
Site Crusher. Works Bureau,
·
WBTC No. 12/2002, Specification
Facilitating the Use of Recycled Aggregates. Works Bureau,
·
ETWBTC No. 33/2002, Management
of Construction and Demolition Material Including Rock; Environment, Transport
and Works Bureau,
·
EWBTC No. 34/2002, Management
of Dredged/Excavated Sediment; Environment, Transport and Works Bureau,
· ETWBTC No. 31/2004, Trip Ticket System for Disposal of Construction & Demolition Materials, Environment, Transport and Works Bureau, Hong Kong SAR Government; and
·
ETWBTC No. 19/2005,
Environmental Management of Construction Site, Environment, Transport and Works
Bureau,
7.3.1
Construction Phase
During the
construction phase, the main activities, which will result in generation of
waste, include dredging and excavation, road widening, culvert diversion and
construction and building works. The
Proposed Beach Development was designed to minimize waste generation and
promote reuse and recycling of any waste generated from the construction. Waste avoidance and minimisation will be
considered during the planning and design stages and in the selection of
options for construction methods and programme.
The typical waste
types associated with these activities include:
·
Dredged marine sediment;
·
C&D materials;
·
Chemical waste;
·
Sewage; and
·
General refuse.
7.3.2
Operational Phase
The following wastes will be generated from the operation of the Proposed Beach Development:
·
Sewage; and
·
General refuse.
The potential
environmental impacts associated with the handling and disposal of waste
arising from the construction and operation of the Proposed Beach Development
were assessed in accordance with the criteria presented in Annexes 7 and 15 of
the EIAO-TM and summarised as follows:
· Estimation
of the types and quantities of the wastes to be generated based on information
provided by the engineering design team and the relevant research and studies
on waste arisings;
· Assessment
of the secondary environmental impacts due to the management of waste with
respect to potential hazards, air and odour emissions, noise, wastewater
discharges and traffic; and
· Assessment
of the potential impacts on the capacity of waste collection, transfer and
disposal facilities.
7.5.1
Construction Phase
Dredged Marine Sediments
The
beach development works will involve dredging and filling. Various beach
layouts and construction methods have been examined with respect to the
practicality of constructing the Proposed
Beach Development without dredging.
It is concluded that dredging is unavoidable, however the proposed
dredging works have been kept to minimum.
Dredging will be required for foundation formation of the proposed
groynes and removal of 500mm thick granular soil from the existing beach
areas. Dredging activities will be
conducted within the Project Site as shown in
Figure 1.1. Table
7.3 summarize
the quantity of dredged materials to be generated.
Dredging in the offshore area
will be conducted by Closed Grab Dredger.
The formation of the 200m
Table
7.3: Quantity of Dredging Marine Sediment
Description |
Dredged Marine Sediment (m3) |
Seabed
reformation/ Groyne Construction |
10,500 |
A preliminary marine sediment
sampling programme has been undertaken as part of the EIA Study to provide an
indication of the quality of the sediment and the volumes of different types of
sediment to be dredged. The sediment
sampling programme (including the sampling stations, the chemical analysis
suite and the biological testing programmes) was developed based on the
guidelines described in ETWBTC 34/2002.
The sampling and testing programmes are summarised in Table 7.4 and the sampling locations are
presented in
Figure
7.2.
Table
7.4: Marine Sediment Sampling Locations
Sampling Location |
Coordinates |
Vibrocore Sampling |
Interstitial
Water (for TBT) |
Elutriation and Marine Water Test |
|
Northing (m) |
Easting (m) |
||||
SS1 |
841401.05 |
836818.49 |
P |
P |
P |
SS2 |
841421.86 |
836773.17 |
P |
P |
P |
SS3 |
841459.93 |
836680.53 |
P |
P |
P |
SS4 |
841493.11 |
836857.52 |
P |
P |
P |
SS5 |
841512.75 |
836811.54 |
P |
P |
P |
SS6 |
841551.91 |
836719.80 |
P |
P |
P |
SS7 |
841585.07 |
836896.75 |
P |
P |
P |
SS8 |
841604.72 |
836850.78 |
P |
P |
P |
SS9 |
841628.28 |
836795.60 |
P |
P |
P |
Samples
from the vertical profile of sediments to be dredged were collected using a
vibrocore device to the required dredging depth of 3 m or until further
drilling was not possible, whichever was the shallowest. The vibrocore samples were cut on site at the
proposed sampling depths from the existing seabed surface at -0.9m, -1.9m and
-2.9m. The sediment samples for further
biological testing were also concurrently collected. All vibrocores collected were of depth less
than 3m due to thin layer of marine deposit in the area. It should be noted that the sample taken at
depths of 0.0-0.2m and 0.0-0.5m for virbocores SS1 and SS2, respectively, were
not tested due to its sandy material content.
In addition, a reference sediment sample was collected at the EPD
routine sediment monitoring station PS6 (Hong Kong Metric coordinates: 850234E,
820057N) in the Port Shelter.
The
contaminants tested include all the contaminants stated in Table 1 - Analytical
Methodology in Appendix
B
of ETWBTC No 34/2002 plus PCBs and 12 Chlorinated Pesticides.
Tier
III biological screening was also performed on samples where one or more contaminant
level exceeded the LCEL. The
ecotoxicological-testing programme featured a suite of tests that include three
phylogenetically distinct species (amphipod, polychaete and bivalve larvae)
which interact with marine sediments in different ways. The objective of the bioassays was to
determine if the potential toxicological impacts of marine disposal of the
dredged sediment on the marine biota, and whether there is any difference in
the toxicity of the sediments samples taking from the Project Site and the
reference station (collected from a clean area in Port Shelter,
According to the sediment
classification results shown in Table 7.5, sediment samples from drill
holes SS1, SS2, SS4, SS7 and SS8 required biological testing in order to
determine the disposal arrangements.
Biological testing has been carried out for these samples and analysis
results are shown in Table
7.5.
Table 7.5: Marine Sediment Testing Result
Sample Reference |
Heavy Metals (mg kg-1) |
Sediment Category |
Biological Sample No. |
Failed Biological Tests |
Final Disposal |
|||||||||||
Drill hole No. |
Depth (m) From – To |
Cadmium (Cd) |
Chromium (Cr) |
Copper (Cu) |
Nickel (Ni) |
Lead (Pb) |
Zinc (Zn) |
Mercury
(Hg) |
Arsenic (As) |
Silver (Ag) |
Amphipod |
Bivalve |
Polychaete |
|||
Reporting Limits |
0.2 |
8 |
7 |
4 |
8 |
20 |
0.05 |
1 |
0.1 |
|
|
|
|
|
|
|
LCEL |
1.5 |
80 |
65 |
40 |
75 |
200 |
0.5 |
12 |
1 |
|
|
|
|
|
|
|
UCEL |
4 |
160 |
110 |
40 |
110 |
270 |
1 |
42 |
2 |
|
|
|
|
|
|
|
SS1 |
0.2-0.9m |
<0.2 |
<8 |
<7 |
<4 |
13 |
<20 |
<0.05 |
17 |
<0.1 |
M |
CS1 |
x |
|
|
Type 2 Confined |
SS1 |
0.9-1.2m |
<0.2 |
<8 |
<7 |
<4 |
31 |
26 |
<0.05 |
24 |
<0.1 |
M |
CS1 |
x |
|
|
Type 2 Confined |
SS2 |
0.5-.0.9m |
<0.2 |
<8 |
<7 |
<4 |
17 |
20 |
<0.05 |
17 |
<0.1 |
M |
CS2 |
|
|
|
Type 1 Dedicated |
SS2 |
0.9-1.9m |
<0.2 |
<8 |
<7 |
<4 |
18 |
23 |
<0.05 |
28 |
<0.1 |
M |
CS2 |
|
|
|
Type 1 Dedicated |
SS2 |
1.9-2.5m |
<0.2 |
<8 |
<7 |
<4 |
25 |
<20 |
<0.05 |
42 |
<0.1 |
M |
CS2 |
|
|
|
Type 1 Dedicated |
SS3 |
0.0-0.9m |
<0.2 |
<8 |
<7 |
<4 |
13 |
<20 |
0.07 |
5.8 |
<0.1 |
L |
|
|
|
|
Type 1 |
SS3 |
0.9-1.9m |
<0.2 |
<8 |
<7 |
<4 |
11 |
<20 |
0.05 |
5 |
<0.1 |
L |
|
|
|
|
Type 1 |
SS3 |
1.9-2.8m |
<0.2 |
<8 |
<7 |
<4 |
20 |
<20 |
0.06 |
12 |
<0.1 |
L |
|
|
|
|
Type 1 |
SS4 |
0.0-0.9m |
<0.2 |
<8 |
<7 |
<4 |
12 |
20 |
<0.05 |
6.9 |
<0.1 |
L |
|
|
|
|
Type 1 |
SS4 |
0.9-1.3m |
<0.2 |
<8 |
<7 |
<4 |
12 |
<20 |
<0.05 |
27 |
<0.1 |
M |
CS3 |
|
|
|
Type 1 Dedicated |
SS5 |
0.0-0.9m |
<0.2 |
<8 |
<7 |
7.8 |
19 |
<20 |
<0.05 |
2.5 |
0.12 |
L |
|
|
|
|
Type 1 |
SS6 |
0.0-0.9m |
<0.2 |
<8 |
<7 |
<4 |
8.5 |
<20 |
0.10 |
3.3 |
<0.1 |
L |
|
|
|
|
Type 1 |
SS6 |
0.9-1.6m |
<0.2 |
<8 |
<7 |
<4 |
<8 |
<20 |
0.06 |
4.2 |
<0.1 |
L |
|
|
|
|
Type 1 |
SS7 |
0.0-0.9m |
<0.2 |
<8 |
<7 |
<4 |
13 |
<20 |
<0.05 |
6.1 |
<0.1 |
L |
|
|
|
|
Type 1 |
SS7 |
0.9-1.3m |
<0.2 |
<8 |
<7 |
<4 |
13 |
<20 |
<0.05 |
14 |
<0.1 |
M |
CS3 |
|
|
|
Type 1 Dedicated |
SS8 |
0.0-0.9m |
<0.2 |
<8 |
<7 |
<4 |
12 |
<20 |
0.08 |
10 |
<0.1 |
L |
|
|
|
|
Type 1 |
SS8 |
0.9-1.7m |
<0.2 |
<8 |
<7 |
<4 |
8.8 |
<20 |
0.07 |
16 |
<0.1 |
M |
CS3 |
|
|
|
Type 1 Dedicated |
SS9 |
0.0-0.9m |
<0.2 |
<8 |
<7 |
<4 |
10 |
<20 |
0.07 |
4.0 |
<0.1 |
L |
|
|
|
|
Type 1 |
SS9 |
0.9-1.9m |
<0.2 |
<8 |
<7 |
<4 |
<8 |
<20 |
<0.05 |
2.5 |
<0.1 |
L |
|
|
|
|
Type 1 |
SS9 |
1.9-2.1m |
<0.2 |
<8 |
<7 |
<4 |
<8 |
<20 |
<0.05 |
8.5 |
<0.1 |
L |
|
|
|
|
Type 1 |
Notes:
(a)
Bold and unlined = Exceeding LCEL, classified as
Category M, which requires biological screening to determine the types of
disposal site (ie Type 1 or Type 2 Disposal).
(b)
x = Failed biological testing.
(c)
Type 1 Disposal = disposal at an open sea disposal.
(d)
Type 1 Dedicated Site = disposal at a dedicated open
sea disposal site.
(e)
Type 2 Disposal = disposal at confined marine
disposal site |
Sample Reference |
Total PCBs |
Total PAHs (Low MW) |
Total PAHs (High MW) |
TBT (in interstitial water) |
Chlorinated Pesticides (mg kg-1) |
||||||||||||
Drillhole No. |
Depth (m) From-To |
Alpha BHC |
Beta BHC |
Gamma BHC |
Delta- BHC |
Hepta-chlor |
Aldrin |
Hepta-chlor epoxide |
Endo-sulfan |
p,p’ DDT |
p,p’ DDD |
p,p’ DDE |
Endosulfan sulfate |
||||
Reporting Limits |
3 |
550 |
1700 |
0.015 |
0.01 |
0.01 |
0.01 |
0.01 |
0.01 |
0.01 |
0.01 |
0.01 |
0.01 |
0.01 |
0.01 |
0.01 |
|
LCEL |
23 |
1700 |
550 |
23 |
NA |
NA |
NA |
NA |
NA |
NA |
NA |
NA |
NA |
NA |
NA |
NA |
|
UCEL |
180 |
9600 |
3160 |
180 |
NA |
NA |
NA |
NA |
NA |
NA |
NA |
NA |
NA |
NA |
NA |
NA |
|
SS1 |
0.2-0.9m |
<3 |
<550 |
<1700 |
<0.015 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
SS1 |
0.9-1.2m |
<3 |
<550 |
<1700 |
<0.015 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
SS2 |
0.5-.0.9m |
<3 |
<550 |
<1700 |
<0.015 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
SS2 |
0.9-1.9m |
<3 |
<550 |
<1700 |
<0.015 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
SS2 |
1.9-2.5m |
<3 |
<550 |
<1700 |
<0.015 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
SS3 |
0.0-0.9m |
<3 |
<550 |
<1700 |
<0.015 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
SS3 |
0.9-1.9m |
<3 |
<550 |
<1700 |
<0.015 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
SS3 |
1.9-2.8m |
<3 |
<550 |
<1700 |
<0.015 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
SS4 |
0.0-0.9m |
<3 |
<550 |
<1700 |
<0.015 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
SS4 |
0.9-1.3m |
<3 |
<550 |
<1700 |
<0.015 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
SS5 |
0.0-0.9m |
<3 |
<550 |
<1700 |
<0.015 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
SS6 |
0.0-0.9m |
<3 |
<550 |
<1700 |
<0.015 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
SS6 |
0.9-1.6m |
<3 |
<550 |
<1700 |
<0.015 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
SS7 |
0.0-0.9m |
<3 |
<550 |
<1700 |
<0.015 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
SS7 |
0.9-1.3m |
<3 |
<550 |
<1700 |
<0.015 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
SS8 |
0.0-0.9m |
<3 |
<550 |
<1700 |
<0.015 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
SS8 |
0.9-1.7m |
<3 |
<550 |
<1700 |
<0.015 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
SS9 |
0.0-0.9m |
<3 |
<550 |
<1700 |
<0.015 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
SS9 |
0.9-1.9m |
<3 |
<550 |
<1700 |
<0.015 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
SS9 |
1.9-2.1m |
<3 |
<550 |
<1700 |
<0.015 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
<0.01 |
Note:
NA = Not Available |
According to the
ETWB TC(W) No. 34/2002, sediment is deemed to have failed the biological test
if it fails in any one of the three toxicity tests. Due to the failure on the 20-Day Polychaete
Test, the sediment to be dredged represented by sample collected at location
SS1 must be dredged with great care and transported to the confined mud pits at
East Sha Chau for disposal (ie Type 2 – Confined Marine Disposal).
The latest engineering review suggested that dredging depth will generally be limited to 0.5 - 1m below seabed level, and will not be greater than 3m. The estimated in-situ quantities of contaminated and uncontaminated sediment to be dredged for different work activities are summarized in Table 7.6 and the Sediment Disposal Requirement Plan is shown in Figure 7.3 and 7.4.
Table 7.6: Estimated
Quantity of Different Types of Marine Sediment to be Dredged (m3)
Disposal
Options |
Seabed |
% |
Type 1 |
6,380 |
60.76% |
Type 1 Dedicated |
2,620 |
24.95% |
Type 2 Confined Marine Disposal Site |
1,500 |
14.28% |
Total |
10,500 |
100% |
Note:
(a)
The quantity of contaminated
sediment was estimated based on locations where sediment samples were
classified as Category L and Category M within the proposed dredged
areas. The estimated dredging
depth would generally in the range of 0.5m to 1m and not greater than 3m.
|
It is
estimated that a total of 17 barge trips will be required to transport the
dredged sediments during the dredging period ([1]). The dredged marine sediments will be loaded
onto barges using closed grabs and transported to the appropriate disposal
sites depending on their level of contamination. In accordance with the requirements of ETWBTC
No 34/2002, the Category M sediments will be dredged and transported with great
care in order to avoid leakage of contaminated sediment into the sea. With the implementation of the mitigation
measures recommended in Section 7.6, sediment disposal at the designated disposal
sites will not cause adverse environmental impacts.
The Sediment Quality Report (SQR) has been
prepared in accordance with the requirements of ETWBTC 34/2002 for approval as
required under the Dumping at Sea Ordinance and attached in
Appendix F.
The final disposal site will be determined by the MFC and a dumping licence will be obtained from the DEP prior to the commencement of the dredging works. The potential water quality impacts due to the dredging and disposal of these sediments have been assessed and are presented in Section 6, Water Quality Impact Assessment. The assessment concluded that the dredging works and proper disposal of the sediment will meet the relevant water quality impact assessment criteria in the EIAO-TM with the implementation of the recommended mitigation measures.
Demolition
Waste
Demolition
for existing structures and site clearance (450 m3) and for building
& landscaping works and western drainage channel (20 m3) will produce
approximately 470 m3 of demolition waste consist of a mixture of vegetable
matter and inert materials. The
demolition works will be completed within 7 months (i.e. tentatively from
December 2008 to July 2009). Sequential
demolition method will be used to facilitate the separation of inert and
non-inert materials as far as possible to enable the beneficial use of the
inert materials and to minimise waste disposal costs. Assuming a bulking factor of 1.4, it is
estimated that about 1 truck trips will be required each day to dispose of the
demolition waste ([2]). Construction and demolition (C&D)
materials generated will be separated/ sorted into inert and non-inert portions
on site. Inert C&D materials will be
reused on site (e.g. as filing materials) as far as possible. The surplus inert C&D materials
should be delivered to public fill for re-use purpose. The delivery of the C&D materials to
public fill reception facilities and landfills will be monitored using trip
ticket system in accordance with ETWB TCW No. 31/2004..
Excavated Materials
Excavation and
backfilling will be required to form a small piece of land to accommodate the
future beach facilities/buildings, road and footpath, car park, drainage and
sewerage facilities. The site formation
works will last for 7 months, tentatively from December 2008 to June 2009.
A review
of old and recent aerial photographs has indicated that changes of the Project
Site in the past 2 decades are due to natural changes or by village development
(see
Figure 7.5). The area was used as agriculture land in
1940's to 1970's and left naturally in early 1980's. The existing hard standing area at the
western side of the site was formed in late 1980's, but no structure was built
on top of that area. No industrial development
has ever been established near to the area.
All connections to the existing box culverts are road drains and stream
courses and the discharge is mainly surface run-off. It is unlikely that the effluent from box
culverts contains high level of contaminations.
Therefore
no contamination issue is expected on the Project Site and the excavated
soil/material would be free of contaminants and can be re-used on site or
disposed of at public fill.
The
excavation works will mainly be carried out in the first 5 months and will
generate approximately 13,800 m3 of excavated materials (mainly soil). The estimated quantities of excavated
materials are presented in Table
7.7. Excavated soil will be reused as fill
material within the Project Site as far as is practicable. It is estimated that 60% (i.e. 8,280 m3) of excavated
soil can be reused for backfilling and the remaining 5,520 m3 will require
off-site disposal. The location of the
temporary stockpiling area for the construction of the Proposed Beach Development is shown in
Figure 4.2 and
Figure
7.6 shows the
locations of soil excavation and backfilling. Assuming a bulking factor of 1.1 for soil and
a truck capacity of 6 m3, about 9 truck trips ([3]) will be required
each day to dispose the surplus excavated soil off-site. The excavated soil could be used as fill for
reclamation and land formation projects.
However, if the soil could not be accepted by other projects, it will be
delivered to the public fill reception facilities.
Table 7.7: Summary of Quantity of Excavated Materials
Construction Works |
Excavation Materials (m3) |
Building &
Landscaping |
800 |
Roadworks (road
& footpath) |
600 |
Car Park |
4,000 |
Vertical Seawall
/ Retaining Wall |
2,000 |
Western Drainage
Channel |
4,500 |
Eastern Box
Culvert |
1,900 |
Total |
13,800 |
Quantity to be
reused on-site |
8,280 |
Quantity
for off-site disposal |
5,520 |
Construction
Waste
C&D materials (consisting
of waste concrete, packing materials, plastics, metal, concrete, wood, etc)
will be generated from the new building construction. The total gross floor area (GFA) to be constructed
at the Project Site is approximately 2,245 m2. Based on a generation rate of 0.1 m3
per m2 of GFA constructed ([4]),
it is estimated that a total of about 225 m3 of C&D materials
will be generated. These materials will
be sorted on-site for public fill (inert portion) (about 180 m3) and
construction waste (about 45 m3) in order to reduce the amount
of construction waste to be disposed of at landfills. The public fill will be reused on-site as
much as practical and the surplus will be reused at other concurrent
reclamation/land formation projects or disposed of at Government public filling
reception facilities.
With the proper implementation of good construction
site practice and the mitigation measures, the handling and disposal of a small
amount of C&D materials to be generated from the new building construction
works will not cause adverse dust, noise or water quality impacts.
Chemical Wastes
Chemical waste, as defined under the Waste Disposal
(Chemical Waste) (General) Regulation, includes any substance being scrap
material, or unwanted substances specified under Schedule 1 of the
Regulation. A complete list of such
substances is provided under the Regulation; however, substances likely to be
generated from the construction of the Proposed Beach Development will, for the
most part, arise from the maintenance of construction plant and equipment. These may include, but not limited to the
following:
·
Scrap batteries or spent
acid/alkali from their maintenance;
·
Used paint, engine oils,
hydraulic fluids and waste fuel;
·
Spent mineral oils/cleaning
fluids from mechanical machinery; and
·
Spent solvents/solutions from
equipment cleaning activities.
Chemical wastes may pose environmental, health and
safety hazards if not stored and disposed of in an appropriate manner as
outlined in the Waste Disposal (Chemical Waste) (General) Regulation and the
Code of Practice on the Packaging, Labelling and Storage of Chemical
Wastes. These hazards may include:
·
Toxic effects to workers;
·
Adverse effects on air, water
and land from spills; and
·
Fire hazards.
The amount of chemical waste that will arise from the
construction activities will be highly dependent on the Contractor’s on-site
maintenance activities and the quantity of plant and equipment utilized. All barges and marine vessel
will comply with the standard operational procedure and design for prevention
of oil pollution. With respect to the nature of construction works and
the number of construction plant and equipment to be used on site, it is estimated
that the quantity of chemical waste to be generated will be small (in the order
of few hundreds litre for the whole construction phase).
With the incorporation of suitable arrangements for
the storage, handling, transportation and disposal of chemical wastes under the
requirements stated in the Code of Practice on the Packaging, Labelling and
Storage of Chemical Waste, no adverse environmental and health impacts, and
hazards will result from the handling, transportation and disposal of chemical
waste arising from the Proposed Beach Development.
Sewage
Sewage will be generated from the construction
workforce, site office’s sanitary facilities and from portable toilets. If not properly managed, these wastes could
cause adverse water quality impacts, odour and potential health risks to the
workforce by attracting pests and other disease vectors.
It is estimated that a maximum
of 100 workers will be working on site at any one time during the construction
period and maximum 0.1 m3 of sewage will be generated per day ([5]). An adequate number of portable toilets
will be provided at the Project Site to ensure that sewage from site staff is
properly collected. No adverse
environmental impacts are envisaged provided that the portable toilets are
properly maintained by a licensed contractor and the collected sewage is
disposed at the designated Sewage Treatment Works (eg Tai Po Sewage Treatment
Works).
General Refuse
The presence of a construction site with workers and
associated site office will result in the generation of general refuse (mainly
consist of food waste, aluminium cans and waste paper) which requires off-site
disposal. The storage of general refuse
has the potential to give rise to adverse environmental impacts. These include odour if the waste is not
collected frequently (for example, daily), windblown litter, water quality
impacts if waste enters water bodies, and visual impact.
Assuming up to 100 construction
workers will be working on site at any one time, with a general refuse generation
rate of 0.65 kg per worker per day ([6]),
the amount of general refuse to be generated will be about 65 kg per day.
Recyclable materials such as paper and aluminium cans
will be separated and delivered to the local recyclers. An adequate number of waste containers will
be provided to avoid spillage of waste.
The non-recyclable waste will be collected and disposed of at the North
East New Territories Landfill (NENT) on a daily basis. With respect to the small quantity of general
refuse to be transferred, it is not anticipated that it will cause adverse
operational impact to these facilities.
Provided that the mitigation measures recommended in Section 7.6 are adopted, no adverse
environmental impacts are expected to arise from the storage, handling,
transport and disposal of general refuse.
7.5.2
Operational Phase
Dredged Materials &
Chemical Waste
The Project has been designed with a view to reduce
disposal arising. No maintenance
dredging is required and no dredged materials will be produced during
operational phase.
In case oil dispersants will be
use, approval from EPD will be sought and will comply with all requirements to
minimize potential water quality impacts.
Sewage
Sewage will mainly arise from
the visitors to the Proposed Beach Development.
It is estimated that the peak numbers of visit during summer time would
be approximate 4,000 visitors per day.
Taking into account the estimated time spent on the beach and the
associated activities, the average daily sewage generation rate from beach
visitor is estimated to be 10 m3 per day with a peak flow rate of 30
litres per second ([7]). The sewer system for the Proposed Beach
Development will be designed with an adequate capacity and connected to public
sewerage conveying to the Tai Po Sewage Treatment Works for treatment. Therefore, no adverse water quality impacts
are envisaged.
General Refuse
General refuse will arise from
the visitors to the Proposed Beach Development.
General refuse may consist of food waste, plastic, aluminium can and
waste paper. A general refuse generation
rate of 0.38 kg per visitor per day was assumed ([8])
and it is estimated that the amount of general refuse to be generated will be
about 1,520 kg per day.
A waste recycling and collection system using 3-coloured
waste separation bins will be provided at the Proposed Beach Development. Recyclable materials (i.e. paper, plastic
bottle and aluminium can) will be separated and delivered to recyclers in order
to reduce the amount of general refuse to be disposed of at landfill. The non-recyclable general refuse will be
disposed of by refuse collecting vehicles transporting the wastes directly to
landfill on a daily basis. With respect
to the small quantity of general refuse to be disposed of, no adverse environmental
impact associated with the handling and disposal of the refuse is anticipated.
7.6
Mitigation
Measures and Residual Impacts
This section recommends the mitigation measures and
good site practices to avoid or reduce potential adverse environmental impacts
associated with handling, collection and disposal of waste arising from the
construction and operation of the Proposed Beach Development.
The Contractor should incorporate these
recommendations into a Waste Management Plan for the construction works. The Contractor should submit the plan to
Project Proponent’s Engineer Representative for endorsement prior to the
commencement of the construction works.
The plan should incorporate site-specific factors, such as the
designation of areas for the segregation and temporary storage of reusable and
recyclable materials.
It will be the Contractor’s responsibility to ensure
that only reputable licensed waste collectors are used and that appropriate
measures to reduce adverse impacts, including windblown litter and dust from
the transportation of these wastes, are employed. In addition, the Contractor must ensure that
all the necessary permits or licences required under the Waste Disposal
Ordinance are obtained for the construction phase.
Waste
Management Hierarchy
The various waste management options are categorised
in terms of preference from an environmental viewpoint. The options considered to be most preferable
have the least environmental impacts and are more sustainable in the long
term. The hierarchy is as follows:
·
Avoidance and reduction;
·
Reuse of materials;
·
Recovery and recycling; and
·
Treatment and disposal.
The above hierarchy has been used to evaluate and
select waste management options. The aim
has been to reduce waste generation and reduce waste handling and disposal
costs.
The Contractor should consult the EPD for the final
disposal of wastes and implement the following good site practices and
mitigation measures:
· Nomination of approved
personnel to be responsible for good site practices, arrangements for
collection and effective disposal to an appropriate facility of all wastes
generated at the site;
· Training of site personnel in
proper waste management and chemical handling procedures;
· Provision of sufficient waste
disposal points and regular collection for
disposal;
· Appropriate measures to reduce
windblown litter and dust transportation of waste by either covering trucks or
by transporting wastes in enclosed containers;
·
Separation of chemical wastes
for special handling and appropriate treatment at the Chemical Waste Treatment
Centre;
· Regular cleaning and
maintenance programme for drainage systems, sumps and oil interceptors; and
·
A recording system for the
amount of wastes generated/recycled and disposal sites.
Waste
Reduction Measures
Good management and control can prevent generation of
significant amount of waste. Waste
reduction is best achieved at the planning and design stage, as well as by
ensuring the implementation of good site practices. Recommendations to achieve waste reduction
include:
· Segregation and storage of
different types of waste in different containers, skips or stockpiles to
enhance reuse or recycling of material and their proper disposal;
· Encourage collection of
aluminium cans and waste paper by individual collectors during construction
with separate labelled bins being provided to allow the segregation of these
wastes from other general refuse generated by the workforce;
·
Any unused chemicals and those
with remaining functional capacity be recycled as far as possible;
·
Use of reusable non-timber
formwork to reduce the amount of C&D materials;
·
Prior to disposal of
construction waste, wood, steel and other metals should be separated, to the
extent practical for re-use and/or recycling to reduce the quantity of waste to
be disposed at landfills;
·
Proper storage and site
practices to reduce the potential for damage or contamination of construction
materials; and
·
Plan and stock construction
materials carefully to reduce amount of waste generated and avoid unnecessary
generation of waste.
7.6.1
Dredging Materials
The final disposal site for the dredged sediments
should be determined by the MFC and a dumping licence should be obtained from
EPD prior to the commencement of the dredging works. Uncontaminated sediments should be disposed
of at open sea disposal sites designated by the MFC. For contaminated sediments requiring Type 2
confined marine disposal, relevant contract documents should specify the
allocation conditions of the MFC and EPD.
7.6.2
Excavated Materials and C&D
Waste
Management of Waste Disposal
The contractor should open a billing account with EPD in accordance with the Waste Disposal (Charges for Disposal of Construction Waste) Regulation for the payment of disposal charges. Every waste load transferred to Government waste disposal facilities such as public fill, sorting facilities, or landfills should require a valid “chit” which contains the information of the account holder to facilitate waste transaction recording and billing to the waste producer. A trip-ticket system should be established in accordance with ETWBTC No. 31/2004 to monitor the reuse of surplus excavated materials off-site and disposal of construction waste and general refuse at transfer stations/landfills, and to control fly-tipping. The billing “chit” and trip-ticket system should be included as one of the contractual requirements and implemented by the contractor. Regular audits of the waste management measures implemented on-site as described in the Waste Management Plan should be conducted.
A
recording system (similar to summary table as shown in Annex 5 and Annex 6 of Appendix G of ETWBTC No. 19/2005) for
the amount of waste generated, recycled and disposed of (including the disposal
sites) will be established during the construction phase.
Measures for the Reduction of
C&D Materials Generation
Public fill and construction waste should be
segregated and stored in different containers or skips to facilitate reuse or
recycling of the public fill and proper disposal of the construction
waste. Specific areas of the work site
should be designated for such segregation and storage if immediate use is not
practicable.
To reduce the potential dust and water quality impacts
of site formation works, C&D materials should be wetted as quickly as
possible to the extent practicable after excavation/filling.
7.6.3
Chemical Waste
The Contractor should register as a chemical waste
producer with the EPD. Chemical waste,
as defined by Schedule 1 of the Waste Disposal (Chemical Waste) (General)
Regulation, should be handled in accordance with the Code of Practice on the
Packaging, Handling and Storage of Chemical Wastes. Containers used for the storage of chemical
wastes should:
·
Be suitable for the substance
they are holding, resistant to corrosion, maintained in a good condition, and
securely closed;
·
Have a capacity of less than
450 L unless the specifications have been approved by the EPD; and
·
Display a label in English and
Chinese in accordance with instructions prescribed in Schedule 2 of the
Regulations.
The
storage area for chemical wastes will:
·
Be clearly labelled and used
solely for the storage of chemical waste;
·
Be enclosed on at least 3
sides;
· Have an impermeable floor and
bunding, of capacity to accommodate 110% of the volume of the largest container
or 20% by volume of the chemical waste stored in that area, whichever is the
greatest;
· Have adequate ventilation;
·
Be covered to prevent rainfall
entering (water collected within the bund must be tested and disposed of as chemical
waste, if necessary); and
·
Be arranged so that
incompatible materials are appropriately separated.
Chemical waste should be collected by a licensed chemical waste collector to a facility licensed to receive chemical waste, such as the Chemical Waste Treatment Facility.
7.6.4
Sewage
An adequate number of portable toilets should be provided
for the on-site construction workforce during construction phase. All portable toilets should be maintained in
a state that will not deter the users from using them. Night soil should be regularly collected by a
licensed collector for disposal. The
sewage generated from the visitors during operation of the Proposed Beach
Development should be discharged to the adjacent foul sewer conveying to Tai Po
Sewage Treatment Works for treatment.
7.6.5 General
Refuse
General refuse should be stored in enclosed bins or
compaction units separately from construction and chemical wastes. A reputable waste collector should be
employed to remove general refuse from the site, separately from construction
and chemical wastes, on a daily basis to reduce odour, pest and litter
impacts. The burning of refuse on
construction sites is prohibited by law.
Recycling bins should be provided at strategic locations to
facilitate recovery of aluminium cans and waste paper from the Project
Site. Materials recovered should be sold
for recycling.
7.6.6
Staff Training
Training
should be provided to workers on the concept of site cleanliness and
appropriate waste management procedures, including waste reduction, reuse and
recycling at the beginning of the construction works.
7.6.7
Residual Impacts
There
will be no residual impact due to the Proposed Beach Development if the
recommended mitigation measures are properly implemented.
7.7
Environmental
Monitoring and Audit Requirements
7.7.1
Construction Phase
To
facilitate monitoring and control over the contractors’ performance on waste
management, a waste monitoring and audit programme should be implemented
throughout the construction phase. The
aims of the monitoring and audit programme are:
· To review the Contractor’s WMP
including the quantities and types of C&D materials generated, reused and
disposed of off-site; the amount of fill materials exported from/imported to
the site and the quantity of timber used in temporary works construction for
each process/activity;
· To monitor the implementation
and achievement of the WMP on site to assess its effectiveness; and
· To monitor the follow-up action
on deficiencies identified.
Joint
site audits by the Environmental Team and the Contractor should be undertaken
on a weekly basis. Particular attention
should be given to the Contractor’s provision of sufficient spaces, adequacy of
resources and facilities for on-site sorting and temporary storage of C&D
materials. The C&D materials to be
disposed of from the Project Site should be visually inspected. The public fill for delivery to the off-site
stockpiling area should contain no observable non-inert materials (e.g.,
general refuse, timber, etc).
Furthermore, the waste to be disposed of at refuse transfer stations or
landfills should as far as possible contains no observable inert or
reusable/recyclable C&D materials (e.g., soil, broken rock, metal, and
paper/cardboard packaging, etc). Any
irregularities observed during the weekly site audits should be raised promptly
to the Contractor for rectification.
To
facilitate assessment of the effectiveness of the waste management measures,
the WMP should state the performance targets to be achieved in reducing
generation of C&D materials taking account the site constraints. The performance targets should cover the
following items and should be agreed with the Project Proponent at the
beginning of the contract.
· The percentage of excavated
materials to be sorted to recover the soil and broken rock for reuse on site or
deliver to the off-site stockpiling area;
·
The percentage of metal to be
recovered for collection by recycling contractors; and
· The percentage of cardboard and
paper packaging (for plant, equipment and materials) to be recovered. The recovered materials will be properly
stockpiled in dry and covered condition to prevent cross contamination by other
wastes.
The
findings of the waste audits should be reported in the Environmental Monitoring
and Audit Reports.
7.7.2
Operation Phase
As it
is not expected that large quantities of waste will be generated from the
operation of the bathing beach and no adverse environmental impacts will arise
with the implementation of good waste management practices. Waste monitoring and audit programme for the
operational phase of the Proposed Beach Development will not be required.
The
key potential impacts during the construction phase are related to wastes
generated from dredging, demolition works, seawall and groyne construction,
culvert diversion and construction and new building construction.
It is estimated
that a total of approximate10,500 m3 of marine sediment will be
dredged. About 6,380 m3 of
the sediments are uncontaminated and can be disposed of at the open sea
disposal sites and about 2,620 m3 of the Category M sediment (which
passed the biological screening) will be disposed of at dedicated open sea
disposal sites. The remaining 1,500 m3
of the Category M (which failed the biological screening) will have to be
disposed of at the confined marine disposal site at East Sha Chau. The final disposal site for the dredging
sediments will be determined by the MFC and a dumping licence will be obtained
from EPD prior to the commencement of the dredging works.
About 13,800 m3
of excavated materials will be generated during construction phase and
8,280 m3 (about 60%) of which will be reuse on-site. The surplus excavated soil will be reused in
other concurrent construction projects in
About
470 m3 of demolition waste consist of inert and non-inert port (e.g.
vegetable matters) will be generated during construction phase. Approximately 225 m3 of C&D
materials will be generated from new building construction. A maximum of 0.1m3 of sewage and
65kg of general refuse will be generated by workers each day. A small quantity of chemical waste (mainly
used lube oil from maintenance of heavy machinery) will be generated. In view of the small quantity of various
wastes to be generated, the handling and disposal of these wastes at the
licensed waste disposal facilities will not cause adverse environmental
impacts.
During
the operational phase, it is estimated that of 10 m3 of sewage and
1,520 kg of general refuse will be produced each day by visitors during peak
season. In view of the small quantity of
sewage and general refuse to be generated and their proper disposal to foul
sewer or transfer station/landfill, no adverse environmental impact associated
with the management of these wastes is anticipated during the operation of the
Proposed Beach Development.
With the implementation
of the recommendations in Section 7.6,
the potential environmental impacts arising from storage, handling, collection,
transport and disposal of wastes will meet the criteria specified in the EIAO-TM.
No adverse waste management impact is anticipated. No residual and cumulative environmental
impacts and hazards associated with handling and disposal of wastes arising
from the construction of Proposed Beach Development are anticipated.
A Waste Management Plan
should be prepared by the Contractor and should be audited through the
environmental monitoring and auditing (EM&A) programme recommended in Section 7.7 to minimize the potential
environmental impacts arising from waste management.
([1])
Number of trips required for
transportation of dredged sediment from dredging area(s) to disposal site(s)
was calculated using a rate of 700m3 per barge – 4 barge trip for Type 1 open sea
disposal, 10 barge trip for Type 1 dedicated disposal and 3 barge trips for
Type 2 confined disposal.
([2])
Trucks per day = 470 m3 of excavated soil to
be disposed offsite x bulk factor 1.4 / 7 months / 24 days per month / 6 m3 per
truck = 1
([3])Trucks per day = 5,520 m3
of excavated soil to be disposed offsite x
bulk factor 1.1/ 5 months / 24 days per month / 6 m3 per truck = 9