Table F2.1 Construction Dust Monitoring Locations
Identification No. |
ASR ID in EIA Report |
Location |
CMA1 |
A93 |
North Point – |
CMA2 |
A63 |
North Point – Victoria Centre |
CMA3 |
A50 |
|
CMA4 |
A38 |
Wanchai – Wanchai Sports Ground |
CMA5 |
A32 |
Wanchai – Hong Kong Convention & Exhibition Centre |
a)
be at the site boundary or
such locations close to the major dust emission source;
b)
be close to the sensitive
receptors; and
c)
take into account the
prevailing meteorological conditions.
a)
a horizontal platform with
appropriate support to secure the samplers against gusty wind should be
provided;
b)
no two samplers should be
placed less than 2 meters apart;
c)
the distance between the
sampler and an obstacle, such as buildings, must be at least twice the height
that the obstacle protrudes above the sampler;
d)
a minimum of 2 meters of
separation from walls, parapets and penthouses is required for rooftop
samplers;
e)
a minimum of 2 meters
separation from any supporting structure, measured horizontally is required;
f)
no furnace or incinerator
flue is nearby;
g)
airflow around the sampler
is unrestricted;
h)
the sampler is more than 20
meters from the dripline;
i)
any wire fence and gate, to
protect the sampler, should not cause any obstruction during monitoring;
j)
permission must be obtained
to set up the samplers and to obtain access to the monitoring stations; and
k)
a secured supply of
electricity is needed to operate the samplers.
·
Strictly
limit the truck speed on site to below
·
Watering
during excavation and material handling;
·
Provision
of vehicle wheel and body washing facilities at the exit points of the site,
combined with cleaning of public roads where necessary; and
·
Tarpaulin
covering of all dusty vehicle loads transported to, from and between site
locations.
Table F3.1 Construction Noise Monitoring Stations
Noise Monitoring Station |
NSR ID (Based on EIA Report) |
Noise Monitoring Location |
M1 |
N2 |
Causeway Centre |
M2 |
N8 |
|
M3 |
N11 |
|
M4 |
N17 |
|
M5 |
N18 |
Block 10, |
M6 |
N20 |
|
(i)
at locations close to the major site activities which
are likely to have noise impacts;
(ii)
close to the noise sensitive receivers; and
(iii)
for monitoring locations located in the vicinity of
the sensitive receivers, care shall be taken to cause minimal disturbance to
the occupants during monitoring.
(i) The
instrument should be a portable and weatherproof dissolved oxygen (DO)
measuring instrument complete with cable and sensor, and use a DC power
source. The equipment should be
capable of measuring:
·
a DO level in the range of 0 ‑ 20 mg L-1
and 0 ‑ 200% saturation; and
·
a temperature of 0 ‑ 45 degree Celsius.
(ii) It
should have a membrane electrode with automatic temperature compensation
complete with a cable.
(iii) Should
salinity compensation not be built-in to the DO equipment, in-situ salinity should be measured to calibrate the DO equipment prior
to each DO measurement.
Table F4.1 Analytical
Methods to be applied to Marine Water Quality Samples
Determinant |
Standard Method |
Detection Limit |
Suspended solids (mg L-1) |
APHA 2540 D |
0.1 mg L-1 |
Table F4.2 Proposed
Marine Water Quality Monitoring Stations
Station |
Description |
Easting |
Northing |
Remark |
WSD
Salt Water Intake |
||||
WSD7 |
|
833789.2 |
818076.2 |
- |
WSD9 |
Tai Wan |
838026.1 |
818209.7 |
- |
WSD10 |
Cha Kwo
Ling |
841386.4 |
817728.4 |
- |
WSD11 |
Yau Tong |
842110.3 |
816861.7 |
- |
WSD15 |
Sai Wan
Ho |
841039.6 |
816473.0 |
- |
WSD17 |
|
839740.4 |
817032.2 |
- |
WSD19 |
Sheung
Wan |
832359.4 |
816868.8 |
- |
WSD20 |
|
830783.7 |
816070.2 |
- |
WSD21 |
Wan Chai |
836188.8 |
815911.1 |
Impact
monitoring should be ended after decommission of the intake |
RW1 |
Wan Chai
(Reprovision) |
836232.0 |
816020.9 |
Impact
monitoring should be began after commission of the intake |
Cooling
Water Intake |
||||
C1 |
HKCEC
Extension |
835885.6 |
816223.0 |
- |
C2 |
Telecom
House |
835647.9 |
815864.4 |
Impact
monitoring should be ended after decommission of the intake |
C3 |
HKCEC
Phase I |
835836.3 |
815910.0 |
Impact monitoring
should be ended after decommission of the intake |
C4 |
Wan |
835932.8 |
815888.2 |
Impact
monitoring should be ended after decommission of the intake |
C5 |
Sun Hung
Kai Centre |
836250.1 |
815932.2 |
Impact monitoring
should be ended after decommission of the intake |
C6 |
World
Trade Centre |
837009.6 |
815999.3 |
- |
C7 |
|
837193.7 |
816150.0 |
Impact
monitoring should be suspended during the period of dilution of the intake |
C8 |
|
837970.6 |
816957.3 |
- |
C9 |
Provident
Centre |
838355.0 |
817116.6 |
- |
RC1 |
Proposed
HKAPA Extension |
835487.7 |
815987.7 |
Impact
monitoring should be began after commission of the intake |
RC5 |
Sun Hung
Kai Centre (Reprovision) |
836291.4 |
816029.7 |
Impact
monitoring should be began after commission of the intake |
RC7 |
|
837245.2 |
816156.6 |
Impact
monitoring should be hold during the period of dilution of the intake |
Table F4.3 Proposed
Marine Water Quality Monitoring Frequency and Parameters
Activities |
Monitoring Frequency Note 1 |
Key
Parameters Note 2 |
During the 4-week baseline monitoring period |
Three days per week, at mid-flood and mid-ebb tides |
Turbidity, Suspended
Solids (SS), Dissolved Oxygen (DO), pH, temperature, salinity |
During marine construction works |
Three days per week, at mid-flood and mid-ebb tides |
Turbidity, Suspended
Solids (SS), Dissolved Oxygen (DO), pH, temperature, salinity |
After completion of marine construction works |
Three days per week, at mid-flood and mid-ebb tides |
Turbidity, Suspended Solids
(SS), Dissolved Oxygen (DO), pH, temperature, salinity |
1.
For
selection of tides for in-situ measurement and water sampling, tidal range of
individual flood and ebb tides should be not less than
2.
Turbidity
should be measured in situ whereas SS should be determined by laboratory.
·
Record the problems and investigate the causes;
·
Issue action notes to the Contractor who is
responsible for the works;
·
Implement remedial and corrective actions
immediately;
·
Re-inspect the site conditions upon completion of
the remedial and corrective actions; and
·
Record the event and discuss with the Contractor
for preventive actions.
·
Notify the site management on the
non-compliance;
·
Identify the sources of pollution;
·
Check the implementation status of the
recommended mitigation measures;
·
Investigate the operating conditions of the
on-site treatment systems;
·
Implement corrective and remedial actions to
improve the effluent quality;
·
Increase monitoring frequency until the effluent
quality is in compliance with the discharge licence requirements; and
·
Record the non-compliance and propose preventive
measures.
Table F4.4 Action and Limit Levels for Marine Water Quality at Seawater Intakes
Parameters |
Action |
Limit |
WSD Salt Water Intake |
||
SS in mg L-1 |
95 percentile of baseline data or >9.5 mg/l |
99 percentile of baseline data or
>10mg/l |
Turbidity in NTU |
95 percentile of
baseline data or >9.5 NTU |
99 percentile of
baseline data or >10NTU |
DO in mg/L |
95 percentile of
baseline data or <2.1 mg/l |
99 percentile of
baseline data or <2mg/l |
Cooling Water Intake |
||
SS in mg L-1
|
95 percentile of baseline data |
99 percentile of
baseline data |
Turbidity in NTU |
95 percentile of
baseline data |
99 percentile of
baseline data |
DO in mg/L |
95 percentile of baseline data |
99 percentile of
baseline data |
Notes:
1.
It is recommended to conduct the monitoring behind the silt screens and
at the appropriate vertical levels of the abstraction points of these intakes
2.
For
turbidity and SS, non-compliance of the water quality limits occurs when
monitoring result is higher than the limits.
3.
All
the figures given in the table are used for reference only and the EPD may
amend the figures whenever it is considered as necessary.
Table F4.5 Event and Action Plan for Marine Water Quality
EVENT |
ACTION |
|||
|
ET |
IC(E) |
ER |
CONTRACTOR |
Action level being exceeded by one sampling day |
Repeat in-situ measurement to confirm findings; Identify source(s) of impact; Inform IC(E) and Contractor; Check monitoring data, all plant, equipment and Contractor's working
methods; Discuss mitigation measures with IC(E) and Contractor; (The above actions should be taken within 1 working day after the
exceedance is identified) Repeat measurement on next day of exceedance. |
Discuss with ET and Contractor on the mitigation measures; Review proposals on mitigation measures submitted by Contractor and
advise the ER accordingly; Assess the effectiveness of the implemented mitigation measures. (The above actions should be taken within 1 working day after the
exceedance is identified) |
Discuss with IC(E) on the proposed mitigation measures; Make agreement on the mitigation measures to be implemented. (The above actions should be taken within 1 working day after the exceedance
is identified) |
Inform the ER and confirm notification of the non-compliance in
writing; Rectify unacceptable practice; Check all plant and equipment; Consider changes of working methods; Discuss with ET and IC(E) and propose mitigation measures to IC(E) and
ER; Implement the agreed mitigation measures. (The above actions should be taken within 1 working day after the
exceedance is identified) |
Action level being exceeded by more than one consecutive sampling days |
Identify source(s) of impact; Inform IC(E) and Contractor; Check monitoring data, all plant, equipment and Contractor's working
methods; Discuss mitigation measures with IC(E) and Contractor; Ensure mitigation measures are implemented; Prepare to increase the monitoring frequency to daily; (The above actions should be taken within 1 working day after the
exceedance is identified) Repeat measurement on next working day of exceedance. |
Discuss with ET and Contractor on the mitigation measures; Review proposals on mitigation measures submitted by Contractor and
advise the ER accordingly; Assess the effectiveness of the implemented mitigation measures. (The above actions should be taken within 1 working day after the
exceedance is identified) |
Discuss with IC(E) on the proposed mitigation measures; Make agreement on the mitigation measures to be implemented; Assess the effectiveness of the implemented mitigation measures. (The above actions should be taken within 1 working day after the
exceedance is identified) |
Inform the Engineer and confirm notification of the non-compliance in
writing; Rectify unacceptable practice; Check all plant and equipment; Consider changes of working methods; Discuss with ET and IC(E) and propose mitigation measures to IC(E) and
ER within 3 working days; Implement the agreed mitigation measures. (The above actions should
be taken within 1 working day after the exceedance is identified) |
Limit level being exceeded by one sampling day |
Repeat in-situ measurement to confirm findings; Identify source(s) of impact; Inform IC(E), contractor and EPD; Check monitoring data, all plant, equipment and Contractor's working
methods; Discuss mitigation measures with IC(E), ER and Contractor; Ensure mitigation measures are implemented; Increase the monitoring frequency to daily until noexceedance of Limit
level. (The above actions should
be taken within 1 working day after the exceedance is identified) |
Discuss with ET and Contractor on the mitigation measures; Review proposals on mitigation measures submitted by Contractor and
advise the ER accordingly; Assess the effectiveness of the implemented mitigation measures. (The above actions should be taken within 1 working day after the
exceedance is identified) |
Discuss with IC(E), ET and Contractor on the proposed mitigation
measures; Request Contractor to critically review the working methods; Make agreement on the mitigation measures to be implemented; Assess the effectiveness of the implemented mitigation measures. (The above actions should be taken within 1 working day after the
exceedance is identified) |
Inform the Engineer and confirm notification of the non-compliance in
writing; Rectify unacceptable practice; Check all plant and equipment; Consider changes of working methods; Discuss with ET , IC(E) and ER and propose mitigation measures to
IC(E) and ER within 3 working days; Implement the agreed mitigation measures. (The above actions should
be taken within 1 working day after the exceedance is identified) |
Limit level being exceeded by more than one consecutive sampling days |
Identify source(s) of impact; Inform IC(E), contractor and EPD; Check monitoring data, all plant, equipment and Contractor's working
methods; Discuss mitigation measures with IC(E), ER and Contractor; Ensure mitigation measures are implemented; Increase the monitoring frequency to daily until no exceedance of
Limit level for two consecutive days. (The above actions should
be taken within 1 working day after the exceedance is identified) |
Discuss with ET and Contractor on the mitigation measures; Review proposals on mitigation measures submitted by Contractor and
advise the ER accordingly; Assess the effectiveness of the implemented mitigation measures. (The above actions should be taken within 1 working day after the
exceedance is identified) |
Discuss with IC(E), ET and
Contractor on the proposed mitigation measures; Request Contractor to
critically review the working methods; Make agreement on the
mitigation measures to be implemented; Assess the effectiveness of the implemented
mitigation measures; Consider and instruct, if
necessary, the Contractor to slow down or to stop all or part of the marine
work until no exceedance of Limit level. (The above actions should
be taken within 1 working day after the exceedance is identified) |
Inform the ER and confirm
notification of the non-compliance in writing; Rectify unacceptable
practice; Check all plant and
equipment; Consider changes of working
methods; Discuss with ET , IC(E) and
ER and propose mitigation measures to IC(E) and ER within 3working days; Implement the agreed
mitigation measures; As directed by the Engineer,
to slow down or to stop all or part of the marine work or construction
activities. (The above actions should
be taken within 1 working day after the exceedance is identified) |
·
Bottom opening of barges shall be fitted with tight
fitting seals to prevent leakage of material.
·
Monitoring of the barge loading shall be conducted to
ensure that loss of material does not take place during transportation. Transport barges or vessels shall be
equipped with automatic self-monitoring devices as specified by the DEP.
·
Nomination of an approved person, such as a site
manager, to be responsible for good site practices, arrangements for collection
and effective disposal to an appropriate facility, of all wastes generated at the
site.
·
Training of site personnel in proper waste management
and chemical waste handling procedures.
·
Provision of sufficient waste disposal points and
regular collection for disposal.
·
Appropriate measures to minimise windblown litter and
dust during transportation of waste by either covering trucks or by
transporting wastes in enclosed containers.
·
Regular cleaning and maintenance programme for
drainage systems, sumps and oil interceptors.
·
A recording system for the amount of wastes generated,
recycled and disposed of (including the disposal sites).
·
Sort C&D waste from demolition of the existing
waterfront structures to recover recyclable portions such as metals.
·
Segregation and storage of different types of waste in
different containers, skips or stockpiles to enhance reuse or recycling of
materials and their proper disposal.
·
Encourage collection of aluminium cans, PET bottles
and paper by providing separate labelled bins to enable these wastes to be
segregated from other general refuse generated by the work force.
·
Any unused chemicals or those with remaining
functional capacity shall be recycled.
·
Use of reusable non-timber formwork, such as in
casting the tunnel box sections, to reduce the amount of C&D material.
·
Proper storage and site practices to minimise the
potential for damage or contamination of construction materials.
·
Plan and stock construction materials carefully to
minimise amount of waste generated and avoid unnecessary generation of waste.
l
Locate
a suitable recipient site for transplanted corals before commencement of coral
translocation works;
l
Collect
baseline information (e.g. total number of coral colonies to be translocated,
health status, attached boulder size, etc.) of transplanted coral colonies in
pre-translocation survey before commencement of coral translocation works;
l
Tag
the transplanted coral colonies one by one in the pre-translocation survey;
l
Record
the size, depth and orientation of each tagged coral colonies in the
pre-translocation survey;
l
Move
boulders with translocated coral colonies from sea bottom to ship/boat with
lifting bag;
l
Submerge
translocated coral colonies in large plastic bucket filled with seawater with
aeration onboard;
l
Transport
coral colonies to recipient site as quick as possible;
l
Place
the transplanted coral colonies in the recipient site in similar depth and
orientation as the existing coral site;
l
Record
information (e.g. health status, translocated location of tagged coral, etc) of
transplanted coral colonies upon the completion of translocation works; and
l
Carry
out post-translocation monitoring on transplanted coral colonies every three
months for a year after completion of coral translocation works.
Baseline Survey
l
Bleached (i.e. bleached white)
Coral monitoring
after transplantation
Table F8.1 Monitoring
Programme
Stage |
Monitoring Task |
Monitoring Report |
Form of Approval |
Frequency |
Design |
Monitoring of design works
against the recommendations of the landscape and visual impact assessments
within the EIA should be undertaken during detailed design and tender stages,
to ensure that they fulfil the intentions of the mitigation measures. Any changes to the design, including
design changes on site should also be checked. |
Report by ER
confirming that the design conforms to requirements of EP |
Approved by
Client |
At Completion of
Design Stage |
Construction |
Monitoring of the
contractor’s operations during the construction period. |
Report on
Contractor's compliance, by ET |
Counter-signature
of report by IC(E) |
Weekly |
Design
Construction & Establishment Period
Table F8.2 Construction
& Establishment Periods
EVENT ACTION LEVEL |
ACTION |
|||
ET |
IC(E) |
ER |
CONTRACTOR |
|
Design Check |
·
Check final design conforms
to the requirements of EP and prepare report. |
·
Check report. ·
Recommend remedial design
if necessary |
·
Undertake remedial design
if necessary |
|
Non-conformity on one occasion |
·
Identify Source ·
Inform IC(E) and ER ·
Discuss remedial actions with
IC(E), ER and Contractor ·
Monitor remedial actions
until rectification has been completed |
·
Check report ·
Check Contractor's working
method ·
Discuss with ET and
Contractor on possible remedial measures ·
Advise ER on effectiveness
of proposed remedial measures. ·
Check implementation of
remedial measures. |
·
Notify Contractor ·
Ensure remedial measures
are properly implemented |
·
Amend working methods ·
Rectify damage and
undertake any necessary replacement |
Repeated Non-conformity |
·
Identify Source ·
Inform IC(E) and ER ·
Increase monitoring
frequency ·
Discuss remedial actions
with IC(E), ER and Contractor ·
Monitor remedial actions
until rectification has been completed ·
If non-conformity stops, cease additional monitoring |
·
Check monitoring report ·
Check Contractor's working
method ·
Discuss with ET and
Contractor on possible remedial measures ·
Advise ER on effectiveness
of proposed remedial measures ·
Supervise implementation
of remedial measures. |
·
Notify Contractor ·
Ensure remedial measures
are properly implemented |
·
Amend working methods ·
Rectify damage and
undertake any necessary replacement |
|
|
|
|
|
Landscape and Visual Mitigation Measures during Construction
Phase
·
Control night-time lighting (CM5);
·
Erection of decorative hoardings (CM6).
Landscape and Visual Mitigation Measures during Operation
Phase
·
Aesthetic
design of proposed waterfront promenade (OM4).
Table F9.1 Implementation Schedule for Air Quality Control
EIA Ref |
Environmental Protection Measures / Mitigation Measures |
Location / Timing |
Implementation Agent |
Implementation Stages* |
Relevant Legislation and Guidelines |
|||
Des |
C |
O |
Dec |
|||||
Construction Phase |
||||||||
S |
Four times a day watering of the
work site with active operations. |
Work
site / during construction |
Contractor |
|
Ö |
|
|
EIAO-TM |
S |
Implementation of dust suppression
measures stipulated in Air Pollution Control (Construction Dust)
Regulation. The following mitigation
measures, good site practices and a comprehensive dust monitoring and audit
programme are recommended to minimise cumulative dust impacts. ·
Strictly
limit the truck speed on site to below ·
Watering
during excavation and material handling; ·
Provision
of vehicle wheel and body washing facilities at the exit points of the site,
combined with cleaning of public roads where necessary; and |
Work
site / during construction |
Contractor |
|
Ö |
|
|
|
|
·
Tarpaulin
covering of all dusty vehicle loads transported to, from and between site
locations. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
S |
For the dredging activities carried out in the vicinity
of Police Officers’ Club, the dredging operation will be restricted to only 1
small close grab dredger to minimise the odour impact during the dredging
activity. The dredging rate
should be reduced as much as practicable for the area in close proximity to
the Police Officers’ Club. The
sediments contain highly contaminated mud which may be disposed with the use
of geosynthetic containers (details shall refer to Section 6), grab dredger
has to be used for filling up the geosynthetic containers on barges. the dredging rate for the removal of
the sediments at the south-west corner of the typhoon shelter shall be slowed
down or restricted to specific non-popular hours in weekdays when it is
necessary during construction. |
Corner of
CBTS/implementation of harbour-front enhancement |
CEDD[4] |
|
Ö |
|
|
EIAO-TM |
* Des - Design, C - Construction, O
– Operation, and Dec - Decommissioning
Table F9.2 Implementation
Schedule for Noise Control
EIA Ref |
Environmental Protection Measures / Mitigation Measures |
Location / Timing |
Implementation Agent |
Implementation Stages* |
Relevant Legislation and Guidelines |
|||
Des |
C |
O |
Dec |
|||||
Construction Phase |
|
|
|
|
|
|
|
|
S |
Good Site
Practice:
Only
well-maintained plant shall be operated on-site and plant shall be serviced
regularly during the construction program.
Silencers
or mufflers on construction equipment shall be utilized and shall be properly
maintained during the construction program.
Mobile
plant, if any, shall be sited as far away from NSRs as possible.
Machines
and plant (such as trucks) that may be in intermittent use shall be shut down
between works periods or shall be throttled down to a minimum.
Plant
known to emit noise strongly in one direction shall, wherever possible, be
orientated so that the noise is directed away from the nearby NSRs.
Material
stockpiles and other structures shall be effectively utilized, wherever
practicable, in screening noise from |
Work Sites / During Construction |
Contractor |
|
Ö |
|
|
EIAO-TM, NCO |
S |
Use of quiet powered mechanical
equipment for the following task: ·
Filling behind seawall ·
Seawall construction |
Work Sites / During Construction |
Contractor |
|
Ö |
|
|
EIAO-TM, NCO |
* Des - Design, C - Construction, O
– Operation, and Dec - Decommissioning
Table F9.3 Implementation Schedule for Water Quality Control
EIA Ref |
Environmental Protection Measures / Mitigation Measures |
Location / Timing |
Implementation Agent |
Implementation Stages* |
Relevant Legislation and Guidelines |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Des |
C |
O |
Dec |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Construction Phase |
|
|
|
|
|
|
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||
S5.8 |
A phased reclamation approach is planned for
the WDII. Containment of fill within each of the reclamation phases by
seawalls is proposed, with the seawall constructed first (above high water
mark) with filling carried out behind the completed seawalls. Any gaps that may need to be provided
for marine access will be shielded by silt curtains to control sediment plume
dispersion away from the site.
Filling for seawall construction should be carried out behind the silt
curtain |
Work site
/ During the construction period |
Contractor |
|
Ö |
|
|
EIAO-TM, WPCO |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||
S5.8 |
Dredging shall be carried out by closed grab dredger for the following works: · Seawall construction in all the reclamation areas; · Construction of the CWB Tunnel · Construction of the proposed WSD water mains; and · Construction of the proposed Wan Chai East sewage outfall pipelines. |
Work site
/ During the construction period |
Contractor |
|
Ö |
|
|
EIAO-TM, WPCO |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||
S5.8,
Figure 5.3 |
Dredging for the Wan Chai East sewage outfall pipelines shall not be carried out concurrently with the following activities: · Dredging along the proposed WSD water mains; · Dredging along the seawall in the Wan Chai Reclamation (WCR) zone (area between HKCEC Extension and PCWA). |
Work site
/ During the construction period |
Contractor |
|
Ö |
|
|
EIAO-TM, WPCO |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||
S5.8 |
The water body behind the temporary reclamations
within the
|
Work site
/ During the construction period |
Contractor |
|
Ö |
|
|
EIAO-TM, WPCO |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||
S5.8 |
As a mitigation measure, to avoid the accumulation
of water borne pollutants within the temporary embayment between CRIII and HKCEC1,
an impermeable barrier, suspended from a floating boom on the water surface
and extending down to the seabed, will be erected by the contractor before
the HKCEC1 commences. The barrier
will channel the stormwater discharge flows from Culvert L to the outside of
the embayment. The contractor
will maintain this barrier until the reclamation works in HKCEC2W are carried
out and the new Culvert L extension is constructed.
|
Work site
/ During the construction period |
Contractor |
|
Ö |
|
|
EIAO-TM, WPCO |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||
S5.8,
Figure 5.3 |
The total dredging rates in each of the marine works zones shall not be more than the maximum production rates stated in the table below. These are the production rates without considering the effect of silt curtain.
Note: |
Work site
/ During the construction period |
Contractor |
|
Ö |
|
|
EIAO-TM, WPCO |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||
S5.8,
Figure 5.3 |
Dredging
along the seawall at WCR1 shall be undertaken initially at |
Work site
/ During the construction period |
Contractor |
|
Ö |
|
|
EIAO-TM, WPCO |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||
S5.8,
Figure 5.3 |
For dredging within the |
Work site
/ During the construction period |
Contractor |
|
Ö |
|
|
EIAO-TM, WPCO |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||
S5.8,
Figure 5.3 |
Silt curtains shall be deployed around the closed grab dredgers during seawall dredging and seawall trench filling in the areas of HKCEC, WCR, TCBR and NP. |
Work site
/ During the construction period |
Contractor |
|
Ö |
|
|
EIAO-TM, WPCO |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||
S5.8, Figure
5.3 |
Silt screens shall be applied to seawater intakes at interim construction stages as stated below:
|
Work site
/ During the construction period |
Contractor |
|
Ö |
|
|
EIAO-TM, WPCO |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||
S5.8 |
Other mitigation measures include: · mechanical grabs, if used, shall be designed and maintained to avoid spillage and sealed tightly while being lifted. For dredging of any contaminated mud, closed watertight grabs must be used; |
Work site
/ During the construction period |
Contractor |
|
Ö |
|
|
ProPECC PN 1/94; WPCO (TM-DSS) |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
· all vessels shall be sized so that adequate clearance is maintained between vessels and the seabed in all tide conditions, to ensure that undue turbidity is not generated by turbulence from vessel movement or propeller wash; |
|
|
|
|
|
|
|
|||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
· all hopper barges and dredgers shall be fitted with tight fitting seals to their bottom openings to prevent leakage of material; |
|
|
|
|
|
|
|
|||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
· construction activities shall not cause foam, oil, grease, scum, litter or other objectionable matter to be present on the water within the site or dumping grounds; |
|
|
|
|
|
|
|
|||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
· loading of barges and hoppers shall be controlled to prevent splashing of dredged material into the surrounding water. Barges or hoppers shall not be filled to a level that will cause the overflow of materials or polluted water during loading or transportation; and |
|
|
|
|
|
|
|
|||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
· before commencement of the reclamation works, the holder of Environmental Permit has to submit plans showing the phased construction of the reclamation, design and operation of the silt curtain. |
|
|
|
|
|
|
|
|||||||||||||||||||||||||||||||||||||||||||||||||||||||
S5.8 |
Silt screens are recommended to be deployed at the seawater intakes during the reclamation works period. Installation of silt screens at the seawater intake points may cause a potential for accumulation and trapping of pollutants, floating debris and refuse behind the silt screens and may lead to potential water quality deterioration at the seawater intake points. Major sources of pollutants and floating refuse include the runoff and storm water discharges from the nearby coastal areas. As a mitigation measure to avoid the pollutant and refuse entrapment problems and to ensure that the impact monitoring results are representative, regular maintenance of the silt screens and refuse collection shall be performed at the monitoring stations at regular intervals on a daily basis. The Contractor shall be responsible for keeping the water behind the silt screen free from floating rubbish and debris during the impact monitoring period. |
Work site
/ During the construction period |
Contractor |
|
Ö |
|
|
EIAO-TM, WPCO |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||
S5.8 |
Dredging of contaminated mud is recommended as a mitigation
measures for control of operational odour impact from the |
|
CEDD[5] |
|
Ö |
|
|
WPCO |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||
S5.8 |
Construction Runoff and Drainage Exposed soil areas should be minimised to reduce
the potential for increased siltation, contamination of runoff, and
erosion. Construction runoff
related impacts associated with the above ground construction activities can
be readily controlled through the use of sediment traps and adequate maintenance
of drainage systems to prevent flooding and overflow. Construction site should be provided with adequately designed perimeter channel and pre-treatment facilities and proper maintenance. The boundaries of critical areas of earthworks should be marked and surrounded by dykes or embankments for flood protection. Temporary ditches should be provided to facilitate runoff discharge into the appropriate watercourses, via a silt retention pond. Permanent drainage channels should incorporate sediment basins or traps and baffles to enhance deposition rates. The design of efficient silt removal facilities should be based on the guidelines in Appendix A1 of ProPECC PN 1/94. Ideally, construction works should be programmed to minimise surface excavation works during the rainy season (April to September). All exposed earth areas should be completed as soon as possible after earthworks have been completed, or alternatively, within 14 days of the cessation of earthworks where practicable. If excavation of soil cannot be avoided during the rainy season, or at any time of year when rainstorms are likely, exposed slope surfaces should be covered by tarpaulin or other means. A sediment tank constructed from pre-formed individual cells of
approximately 6 ‑ Open stockpiles of construction materials (for examples,
aggregates, sand and fill material) of more than |
Work
site / During the construction period |
Contractor |
|
Ö |
|
|
ProPECC PN 1/94; WPCO (TM-DSS) |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||
S5.8 |
Manholes (including newly constructed ones) should always be adequately covered and temporarily sealed so as to prevent silt, construction materials or debris being washed into the drainage system and storm runoff being directed into foul sewers. Precautions to be taken at any time of year when rainstorms are likely, actions to be taken when a rainstorm is imminent or forecast, and actions to be taken during or after rainstorms are summarised in Appendix A2 of ProPECC PN 1/94. Particular attention should be paid to the control of silty surface runoff during storm events. Oil interceptors should be provided in the drainage system and regularly cleaned to prevent the release of oils and grease into the storm water drainage system after accidental spillages. The interceptor should have a bypass to prevent flushing during periods of heavy rain. All vehicles and plant should be cleaned before leaving a
construction site to ensure no earth, mud, debris and the like is deposited
by them on roads. An adequately designed
and located wheel washing bay should be provided at every site exit, and
wash-water should have sand and silt settled out and removed at least on a
weekly basis to ensure the continued efficiency of the process. The section of access road leading to,
and exiting from, the wheel-wash bay to the public road should be paved with
sufficient backfall toward the wheel-wash bay to prevent vehicle tracking of
soil and silty water to public roads and drains. |
Work
site / During the construction period |
Contractor |
|
Ö |
|
|
ProPECC PN 1/94; WPCO (TM-DSS) |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||
S5.8 |
It is recommended that on-site drainage system should be installed prior to the commencement of other construction activities. Sediment traps should be installed in order to minimise the sediment loading of the effluent prior to discharge into foul sewers. There shall be no direct discharge of effluent from the site into the sea. |
Work
site / During the construction period |
Contractor |
|
Ö |
|
|
ProPECC PN 1/94; WPCO (TM-DSS) |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
All temporary and permanent drainage pipes and culverts provided to facilitate runoff discharge shall be adequately designed for the controlled release of storm flows. All sediment control measures shall be regularly inspected and maintained to ensure proper and efficient operation at all times and particularly following rain storms. The temporarily diverted drainage shall be reinstated to its original condition when the construction work is finished or the temporary diversion is no longer required. |
|
|
|
|
|
|
|
|||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
All fuel tanks and store areas shall be provided with locks and be
sited on sealed areas, within bunds of a capacity equal to 110% of the
storage capacity. |
|
|
|
|
|
|
|
|||||||||||||||||||||||||||||||||||||||||||||||||||||||
S5.8 |
Sewage from Construction Work Force Construction
work force sewage discharges on site shall be connected to the existing trunk
sewer or sewage treatment facilities.
The construction sewage shall be handled by portable chemical toilets
prior to the commission of the on-site sewer system. Appropriate numbers of portable
toilets shall be provided by a licensed contractor to serve the large number
of construction workers over the construction site. The Contractor shall also be
responsible for waste disposal and maintenance practices. |
Work
site / During the construction period |
Contractor |
|
Ö |
|
|
ProPECC PN 1/94; WPCO (TM-DSS) |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||
S5.8 |
Floating Debris and Refuse Collection and
removal of floating refuse shall be performed at regular intervals on a daily
basis. The contractor shall be
responsible for keeping the water within the site boundary and the
neighbouring water free from rubbish. |
Work
site and adjacent water / During the construction period. |
Contractor |
|
Ö |
|
|
WPCO |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||
S5.8 |
Storm Water
Discharges Minimum
distances of |
Work
site and adjacent water / During the design and construction period. |
Contractor |
Ö |
Ö |
|
|
WPCO |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||
Operational Phase |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
S5.8 |
Existing
practices currently adopted by Marine Department for collection of floating refuse
at the Project site should be continued during the operational phase of the
Project. |
Project
site and adjacent water /During operational phase |
Marine Department |
|
|
Ö |
|
WPCO, WDO |
* Des - Design, C - Construction, O
– Operation, and Dec - Decommissioning
3 if employ Management, Operation and
Maintenance (MOM) Contract
Table F9.4 Implementation Schedule for Waste Management
EIA Ref |
Environmental Protection Measures / Mitigation Measures |
Location / Timing |
Implementation Agent |
Implementation Stages* |
Relevant Legislation and Guidelines |
||||
Des |
C |
O |
Dec |
||||||
Construction Phase |
|
|
|
|
|
|
|
||
S |
Marine
Sediments
The dredged marine sediments would
be loaded onto barges, transported to and disposed of at the designated
disposal sites at South of Cheung Chau, East of Ninepin, East of Tung Lung
Chau, South of Tsing Yi or East of Sha Chau to be allocated by the MFC
depending on their level of contamination or at other disposal sites after
consultation with the MFC and EPD. In accordance with the ETWB TCW No. 34/2002, the contaminated material must be dredged and transported with
great care. The mitigation
measures recommended in Section 5, Volume 1 of the EIA Report shall be
incorporated. The dredged contaminated sediment must be effectively isolated
from the environment upon final disposal and shall be disposed of at the Type
2 confined marine disposal contaminated mud pit. |
Work site
/ During the construction period |
Contractor |
|
Ö |
|
|
ETWB TCW No. 34/2002 |
|
S |
Based on the biological screening
results, the Category H (>10xLCEL) sediment which failed the biological
testing would require Type 3 special disposal. The volume of Category H sediment from
the |
|
|
|
|
|
|
|
|
S |
It will be the responsibility of the
Contractor to satisfy the appropriate authorities that the contamination
levels of the marine sediment to be dredged have been analysed and
recorded. According to the ETWB
TCW No. 34/2002, this will involve the submission of a formal Sediment
Quality Report to the DEP, at least 3 months prior to the dredging contract
being tendered |
|
|
|
|
|
|
|
|
S |
During transportation and disposal
of the dredged marine sediments requiring Type 1 and Type 2 disposal, the following
measures shall be taken to minimise potential impacts on water quality: |
|
|
|
|
|
|
|
|
|
·
Bottom opening of barges shall be fitted with tight fitting seals to
prevent leakage of material.
Excess material shall be cleaned from the decks and exposed fittings
of barges and hopper dredgers before the vessel is moved. |
|
|
|
|
|
|
|
|
|
·
Monitoring of the barge loading shall be conducted to ensure that loss
of material does not take place during transportation. Transport barges or vessels shall be
equipped with automatic self-monitoring devices as specified by the DEP. ·
Barges or hopper barges shall not be filled to a level that would
cause the overflow of materials or sediment laden water during loading or
transportation. |
|
|
|
|
|
|
|
|
S |
Floating Refuse During the construction phase, the
project proponent’s contractor will be responsible for the collection of any
refuse within their works area. Floating booms will be provided on the water
surface to confine the refuse from the working barges as well as to avoid the
accumulation of pollutants within temporary embayment as mentioned in Table
F9.3. |
Work site
/ During the construction period |
Contractor |
|
Ö |
|
|
|
|
S |
Good Site Practices Recommendations for good site
practices during the construction activities include:
·
nomination of an approved person, such as a site
manager, to be responsible for good site practices, arrangements for
collection and effective disposal to an appropriate facility, of all wastes
generated at the site; ·
training of site personnel in proper waste
management and chemical waste handling procedures; ·
provision of sufficient waste disposal points and
regular collection for disposal; ·
appropriate measures to minimise windblown litter
and dust during transportation of waste by either covering trucks or by
transporting wastes in enclosed containers; ·
regular cleaning and maintenance programme for
drainage systems, sumps and oil interceptors; and ·
a recording system for the amount of wastes
generated, recycled and disposed of (including the disposal sites). |
Work site
/ During the construction period |
Contractor |
|
Ö |
|
|
Waste Disposal Ordinance (Cap.354) |
|
S |
Waste Reduction Measures Waste reduction is best achieved at the planning and design stage, as
well as by ensuring the implementation of good site practices. Recommendations to achieve waste
reduction include: |
Work site
/ During planning and design stage, and construction stage |
Contractor |
Ö |
Ö |
|
|
|
|
|
·
Sort C&D waste from demolition of the existing
waterfront structures to recover recyclable portions such as metals. |
|
|
|
|
|
|
|
|
|
·
Segregation and storage of
different types of waste in different containers, skips or stockpiles to
enhance reuse or recycling of materials and their proper disposal. |
|
|
|
|
|
|
|
|
|
·
Encourage collection of aluminium cans, PET bottles
and paper by providing separate labelled bins to enable these wastes to be
segregated from other general refuse generated by the work force. ·
Any unused chemicals or those with remaining
functional capacity shall be recycled. ·
Use of reusable non-timber formwork to reduce the
amount of C&D material. ·
Proper storage and site practices to minimise the
potential for damage or contamination of construction materials. ·
Plan and stock construction materials carefully to
minimise amount of waste generated and avoid unnecessary generation of waste. |
|
|
|
|
|
|
|
|
S |
General Refuse
General refuse shall be stored in enclosed bins
or compaction units separate from C&D material. A licensed waste collector shall be
employed by the contractor to remove general refuse from the site, separately
from C&D material. A collection area shall be provided where
wastes can be stored and loaded prior to removal from site. An enclosed and covered area is
recommended to reduce the occurrence of 'wind blow' light material. |
Work site
/ During the construction period |
Contractor |
|
Ö |
|
|
Public Health
and Municipal Services Ordinance (Cap. 132) |
|
S |
Chemical Wastes
After use, chemical wastes (for example,
cleaning fluids, solvents, lubrication oil and fuel) shall be handled
according to the Code of Practice on the Packaging, Labelling and Storage of
Chemical Wastes. Spent chemicals
shall be collected by a licensed collector for disposal at the CWTF or other
licensed facility in accordance with the Waste Disposal (Chemical Waste)
(General) Regulation. |
Work site
/ During the construction period |
Contractor |
|
Ö |
|
|
Waste
Disposal (Chemical Waste) (General) Regulation Code of
Practice on the Packaging, Labelling and Storage of Chemical Wastes |
|
S |
Construction and Demolition Material
C&D material shall be sorted on-site into
inert C&D material (that is, public fill) and C&D waste. All the
suitable inert C&D material shall be broken down to |
Work site
/ During the construction period |
Contractor |
|
Ö |
|
|
ETWB TCW
No. 33/2002, 31/2004, 19/2005 |
|
S |
In order to monitor the disposal
of public fill and C&D waste at public fill reception facilities and
landfills, respectively, and to control fly tipping, a trip-ticket system
shall be included as one of the contractual requirements and implemented by
the Environmental Team undertaking the environmental monitoring and audit
work. An Independent Environment
Checker shall be responsible for auditing the results of the system. |
Work site
/ During the construction period |
Contractor and Independent Environmental
Checker |
|
Ö |
|
|
ETWB TCW
No. 31/2004 |
|
* Des - Design, C - Construction, O
– Operation, and Dec - Decommissioning
Table F9.5 Implementation Schedule for Land Contamination
EIA Ref |
Environmental Protection Measures / Mitigation Measures |
Location / Timing |
Implementation Agent |
Implementation Stages* |
Relevant Legislation and Guidelines |
||||
Des |
C |
O |
Dec |
||||||
Construction and Operation Phase |
|||||||||
S. |
As no potential contaminative land
uses were identified within the Study Area, adverse land contamination
impacts associated with the construction and operation of the Project is not
expected. As such, environmental
protection and mitigation measures are considered not necessary. |
- |
- |
|
|
|
|
- |
|
* Des - Design, C - Construction, O
– Operation, and Dec - Decommissioning
Table
F9.6 Implementation
Schedule for Marine Ecology
EIA Ref |
Environmental Protection Measures
/ Mitigation Measures |
Location / Timing |
Implementation Agent |
Implementation Stages* |
Relevant Legislation and
Guidelines |
||||
Des |
C |
O |
Dec |
||||||
Construction & Operation
Phases |
|
|
|
|
|
|
|
||
S. |
Alternative design of the
Trunk Road constructed in tunnel should be adopted to avoid permanent
reclamation in CBTS and |
- |
CEDD/HyD |
Ö |
|
|
|
EIAO TM Annex 16 (Section 8.4) & EIAO Guidance Note No. 3/2002. |
|
S. |
Translocation of those
potentially affected coral colonies to the nearby suitable habitats such as |
Ex- |
CEDD/HyD |
Ö |
|
|
|
EIAO TM Annex 16 (Section 8.4) & EIAO Guidance Note No. 3/2002. |
|
S. |
During
dredging and filling operations, a number of mitigation measures to control
water quality should be adopted to confine sediment plume within
reclamation area and protect
marine fauna in proximity to the reclamation. The mitigation measures include
the following:
·
Installation
of silt curtains during dredging activities
·
Use of
tightly-closed grab dredger
·
Reduction
of dredging rate
|
Work site / during construction phase |
Contractor |
|
Ö |
|
|
EIAO TM Annex 16 (Section 8.4) & EIAO Guidance Note No. 3/2002. |
|
|
·
Control of
grab descending speed
|
|
|
|
|
|
|
|
|
|
·
Construction of leading edges of
seawall in the early stages of the reclamation works
· Adoption of multiple-phase construction schedule
|
|
|
|
|
|
|
|
|
S. |
To minimize potential disturbance impacts on the
foraging ardeid population in the CBTS, particularly in the area near the A
King Shipyard, appropriate mitigation measures should be adopted particularly
during the construction phase. The following measures are recommended:
·
Use of Quiet Mechanical Plant
during the construction phase should be adopted wherever possible.
·
Adoption
of multiple-phase construction schedule.
General
measures to reduce noise generated during the construction phase (see noise
impact assessment) should be effectively implemented.
|
Work site / during construction phase |
Contractor |
|
Ö |
|
|
EIAO TM Annex 16 (Section 8.4) & EIAO Guidance Note No. 3/2002. |
|
S. |
Seawalls should be
constructed in advance around the reclamation areas within the area of the
CBTS to screen adjacent feeding ground from construction phase activities,
reduce noise disturbance to the associated seabirds and also to restrict
access to this habitat adjacent to works areas by ship traffic. |
Work site / during construction phase |
Contractor |
|
Ö |
|
|
EIAO TM Annex 16 (Section 8.4) & EIAO Guidance Note No. 3/2002. |
|
S. |
Loss of artificial seawall habitats should be
reinstated by the construction of about |
Work site / during construction phase |
Contractor |
|
Ö |
|
|
EIAO TM Annex 16 (Section 8.4) & EIAO Guidance Note No. 3/2002. |
|
*Des - Design, C - Construction, O – Operation, and Dec - Decommissioning
Table F9.7 Implementation
Schedule for Landscape and Visual
EIA Ref |
Environmental Protection Measures / Mitigation Measures |
Location / Timing |
Implementation Agent |
Implementation Stages* |
Relevant Legislation and Guidelines |
||||
Des |
C |
O |
Dec |
||||||
Construction Phase |
|
|
|
|
|
|
|
||
Table
10.5 |
CM5 Control of night-time lighting. |
Work site
/ During Construction Phase |
Contractor |
|
Ö |
|
|
EIAO TM |
|
Table 10.5 |
CM6 Erection of decorative screen hoarding
compatible with the surrounding setting. |
Work site
/ During Construction Phase |
Contractor |
|
Ö |
|
|
EIAO TM |
|
Operation Phase |
|||||||||
Table
10.6, Figure |
OM4 Aesthetic design
of proposed waterfront promenade. |
Work site
/ During Design Stage and Operation Phases |
CEDD[6] |
Ö |
Ö |
Ö |
|
ETWB TCW 2/2004 |
|
*Des - Design, C - Construction, O –
Operation, and Dec - Decommissioning
(ii) Fleischer, P., Bowles, F. A. “Turbidity currents generated by seafloor impact of geotextile fabric containers”. Applied Ocean Research, 21 (1999) 215-217;
(iii) Valent, P. J. et al. “Engineering concepts for the placement of wastes on the abyssal seafloor”. Journal of Marine Systems, 14 (1998) 273-288.
[4] CEDD will identify an implementation agent.
[5] CEDD will identify an implementation agent.
[6] CEDD will identify an implementation agent