Table H3.1 Construction Noise Monitoring Stations
Noise Monitoring Station |
NSR ID (Based on EIA Report) |
Noise Monitoring Location |
M1 |
N2 |
Causeway Centre |
(i)
at locations close to the major site activities which
are likely to have noise impacts;
(ii)
close to the noise sensitive receivers; and
(iii)
for monitoring locations located in the vicinity of the
sensitive receivers, care shall be taken to cause minimal disturbance to the
occupants during monitoring.
(i) The
instrument should be a portable and weatherproof dissolved oxygen (DO)
measuring instrument complete with cable and sensor, and use a DC power
source. The equipment should be
capable of measuring:
·
a DO level in the range of 0 ‑ 20 mg L-1
and 0 ‑ 200% saturation; and
·
a temperature of 0 ‑ 45 degree Celsius.
(ii) It should
have a membrane electrode with automatic temperature compensation complete with
a cable.
(iii) Should salinity
compensation not be built-in to the DO equipment, in-situ salinity should be
measured to calibrate the DO equipment prior to each DO measurement.
Table H4.1 Analytical
Methods to be applied to Marine Water Quality Samples
Determinant |
Standard Method |
Detection Limit |
Suspended solids (mg L-1) |
APHA 2540 D |
0.1 mg L-1 |
Table H4.2 Proposed Marine
Water Quality Monitoring Stations
Station |
Description |
Easting |
Northing |
Remark |
WSD
Salt Water Intake |
||||
WSD7 |
|
833789.2 |
818076.2 |
- |
WSD9 |
Tai Wan |
838026.1 |
818209.7 |
- |
WSD10 |
Cha Kwo
Ling |
841386.4 |
817728.4 |
- |
WSD11 |
Yau Tong |
842110.3 |
816861.7 |
- |
WSD15 |
Sai Wan
Ho |
841039.6 |
816473.0 |
- |
WSD17 |
|
839740.4 |
817032.2 |
- |
WSD19 |
Sheung
Wan |
832359.4 |
816868.8 |
- |
WSD20 |
|
830783.7 |
816070.2 |
- |
WSD21 |
Wan Chai |
836188.8 |
815911.1 |
Impact
monitoring should be ended after decommission of the intake |
RW1 |
Wan Chai
(Reprovision) |
836232.0 |
816020.9 |
Impact
monitoring should be began after commission of the intake |
Cooling
Water Intake |
||||
C1 |
HKCEC
Extension |
835885.6 |
816223.0 |
- |
C2 |
Telecom
House |
835647.9 |
815864.4 |
Impact monitoring
should be ended after decommission of the intake |
C3 |
HKCEC
Phase I |
835836.3 |
815910.0 |
Impact
monitoring should be ended after decommission of the intake |
C4 |
Wan |
835932.8 |
815888.2 |
Impact monitoring
should be ended after decommission of the intake |
C5 |
Sun Hung
Kai Centre |
836250.1 |
815932.2 |
Impact
monitoring should be ended after decommission of the intake |
C6 |
World
Trade Centre |
837009.6 |
815999.3 |
- |
C7 |
|
837193.7 |
816150.0 |
Impact
monitoring should be suspended during the period of dilution of the intake |
C8 |
|
837970.6 |
816957.3 |
- |
C9 |
Provident
Centre |
838355.0 |
817116.6 |
- |
RC1 |
Proposed
HKAPA Extension |
835487.7 |
815987.7 |
Impact
monitoring should be began after commission of the intake |
RC5 |
Sun Hung
Kai Centre (Reprovision) |
836291.4 |
816029.7 |
Impact
monitoring should be began after commission of the intake |
RC7 |
|
837245.2 |
816156.6 |
Impact
monitoring should be hold during the period of dilution of the intake |
Table H4.3 Proposed Marine
Water Quality Monitoring Frequency and Parameters
Activities |
Monitoring Frequency Note 1 |
Key
Parameters Note 2 |
During the 4-week baseline monitoring period |
Three days per week, at mid-flood and mid-ebb tides |
Turbidity, Suspended
Solids (SS), Dissolved Oxygen (DO), pH, temperature, salinity |
During marine construction works |
Three days per week, at mid-flood and mid-ebb tides |
Turbidity, Suspended
Solids (SS), Dissolved Oxygen (DO), pH, temperature, salinity |
After completion of marine construction works |
Three days per week, at mid-flood and mid-ebb tides |
Turbidity, Suspended
Solids (SS), Dissolved Oxygen (DO), pH, temperature, salinity |
1.
For
selection of tides for in-situ measurement and water sampling, tidal range of
individual flood and ebb tides should be not less than
2.
Turbidity
should be measured in situ whereas SS should be determined by laboratory.
·
Record the problems and investigate the causes;
·
Issue action notes to the Contractor who is
responsible for the works;
·
Implement remedial and corrective actions
immediately;
·
Re-inspect the site conditions upon completion
of the remedial and corrective actions; and
·
Record the event and discuss with the Contractor
for preventive actions.
·
Notify the site management on the
non-compliance;
·
Identify the sources of pollution;
·
Check the implementation status of the
recommended mitigation measures;
·
Investigate the operating conditions of the
on-site treatment systems;
·
Implement corrective and remedial actions to
improve the effluent quality;
·
Increase monitoring frequency until the effluent
quality is in compliance with the discharge licence requirements; and
·
Record the non-compliance and propose preventive
measures.
Table H4.4 Action and Limit Levels for Marine Water Quality at Seawater Intakes
Parameters |
Action |
Limit |
WSD Salt Water Intake |
||
SS in mg L-1 |
95 percentile of baseline data or >9.5 mg/l |
99 percentile of baseline data or >10
mg/l |
Turbidity in NTU |
95 percentile of
baseline data or >9.5 NTU |
99 percentile of
baseline data or >10 NTU |
DO in mg/L |
95 percentile of baseline data or <2.1 mg/l |
99 percentile of
baseline data or <2 mg/l |
Cooling Water Intake |
||
SS in mg L-1
|
95 percentile of baseline data |
99 percentile of
baseline data |
Turbidity in NTU |
95 percentile of
baseline data |
99 percentile of
baseline data |
DO in mg/L |
95 percentile of baseline data |
99 percentile of
baseline data |
Notes:
1.
It is recommended to conduct the monitoring behind the silt screens and
at the appropriate vertical levels of the abstraction points of these intakes
2.
For
turbidity and SS, non-compliance of the water quality limits occurs when
monitoring result is higher than the limits.
3.
All
the figures given in the table are used for reference only and the EPD may
amend the figures whenever it is considered as necessary.
Table H4.5 Event and Action Plan for Marine Water Quality
EVENT |
ACTION |
|||
|
ET |
IC(E) |
ER |
CONTRACTOR |
Action level being exceeded by one sampling day |
Repeat in-situ measurement to confirm findings; Identify source(s) of impact; Inform IC(E) and Contractor; Check monitoring data, all plant, equipment and Contractor's working
methods; Discuss mitigation measures with IC(E) and Contractor; (The above actions should be taken within 1 working day after the
exceedance is identified) Repeat measurement on next day of exceedance. |
Discuss with ET and Contractor on the mitigation measures; Review proposals on mitigation measures submitted by Contractor and
advise the ER accordingly; Assess the effectiveness of the implemented mitigation measures. (The above actions should be taken within 1 working day after the
exceedance is identified) |
Discuss with IC(E) on the proposed mitigation measures; Make agreement on the mitigation measures to be implemented. (The above actions should be taken within 1 working day after the exceedance
is identified) |
Inform the ER and confirm notification of the non-compliance in
writing; Rectify unacceptable practice; Check all plant and equipment; Consider changes of working methods; Discuss with ET and IC(E) and propose mitigation measures to IC(E) and
ER; Implement the agreed mitigation measures. (The above actions should be taken within 1 working day after the
exceedance is identified) |
Action level being exceeded by more than one consecutive sampling days |
Identify source(s) of impact; Inform IC(E) and Contractor; Check monitoring data, all plant, equipment and Contractor's working
methods; Discuss mitigation measures with IC(E) and Contractor; Ensure mitigation measures are implemented; Prepare to increase the monitoring frequency to daily; (The above actions should be taken within 1 working day after the
exceedance is identified) Repeat measurement on next working day of exceedance. |
Discuss with ET and Contractor on the mitigation measures; Review proposals on mitigation measures submitted by Contractor and
advise the ER accordingly; Assess the effectiveness of the implemented mitigation measures. (The above actions should be taken within 1 working day after the
exceedance is identified) |
Discuss with IC(E) on the proposed mitigation measures; Make agreement on the mitigation measures to be implemented; Assess the effectiveness of the implemented mitigation measures. (The above actions should be taken within 1 working day after the
exceedance is identified) |
Inform the Engineer and confirm notification of the non-compliance in
writing; Rectify unacceptable practice; Check all plant and equipment; Consider changes of working methods; Discuss with ET and IC(E) and propose mitigation measures to IC(E) and
ER within 3 working days; Implement the agreed mitigation measures. (The above actions should
be taken within 1 working day after the exceedance is identified) |
Limit level being exceeded by one sampling day |
Repeat in-situ measurement to confirm findings; Identify source(s) of impact; Inform IC(E), contractor and EPD; Check monitoring data, all plant, equipment and Contractor's working
methods; Discuss mitigation measures with IC(E), ER and Contractor; Ensure mitigation measures are implemented; Increase the monitoring frequency to daily until noexceedance of Limit
level. (The above actions should
be taken within 1 working day after the exceedance is identified) |
Discuss with ET and Contractor on the mitigation measures; Review proposals on mitigation measures submitted by Contractor and
advise the ER accordingly; Assess the effectiveness of the implemented mitigation measures. (The above actions should be taken within 1 working day after the
exceedance is identified) |
Discuss with IC(E), ET and Contractor on the proposed mitigation
measures; Request Contractor to critically review the working methods; Make agreement on the mitigation measures to be implemented; Assess the effectiveness of the implemented mitigation measures. (The above actions should be taken within 1 working day after the
exceedance is identified) |
Inform the Engineer and confirm notification of the non-compliance in
writing; Rectify unacceptable practice; Check all plant and equipment; Consider changes of working methods; Discuss with ET , IC(E) and ER and propose mitigation measures to
IC(E) and ER within 3 working days; Implement the agreed mitigation measures. (The above actions should
be taken within 1 working day after the exceedance is identified) |
Limit level being exceeded by more than one consecutive sampling days |
Identify source(s) of impact; Inform IC(E), contractor and EPD; Check monitoring data, all plant, equipment and Contractor's working
methods; Discuss mitigation measures with IC(E), ER and Contractor; Ensure mitigation measures are implemented; Increase the monitoring frequency to daily until no exceedance of
Limit level for two consecutive days. (The above actions should
be taken within 1 working day after the exceedance is identified) |
Discuss with ET and Contractor on the mitigation measures; Review proposals on mitigation measures submitted by Contractor and
advise the ER accordingly; Assess the effectiveness of the implemented mitigation measures. (The above actions should be taken within 1 working day after the
exceedance is identified) |
Discuss with IC(E), ET and
Contractor on the proposed mitigation measures; Request Contractor to
critically review the working methods; Make agreement on the
mitigation measures to be implemented; Assess the effectiveness of the implemented
mitigation measures; Consider and instruct, if
necessary, the Contractor to slow down or to stop all or part of the marine
work until no exceedance of Limit level. (The above actions should
be taken within 1 working day after the exceedance is identified) |
Inform the ER and confirm
notification of the non-compliance in writing; Rectify unacceptable
practice; Check all plant and
equipment; Consider changes of working
methods; Discuss with ET , IC(E) and
ER and propose mitigation measures to IC(E) and ER within 3working days; Implement the agreed
mitigation measures; As directed by the Engineer,
to slow down or to stop all or part of the marine work or construction
activities. (The above actions should
be taken within 1 working day after the exceedance is identified) |
·
Bottom opening of barges shall be fitted with tight
fitting seals to prevent leakage of material.
·
Monitoring of the barge loading shall be conducted to
ensure that loss of material does not take place during transportation. Transport barges or vessels shall be equipped
with automatic self-monitoring devices as specified by the DEP.
·
Nomination of an approved person, such as a site manager,
to be responsible for good site practices, arrangements for collection and
effective disposal to an appropriate facility, of all wastes generated at the
site.
·
Training of site personnel in proper waste management
and chemical waste handling procedures.
·
Provision of sufficient waste disposal points and
regular collection for disposal.
·
Appropriate measures to minimise windblown litter and
dust during transportation of waste by either covering trucks or by
transporting wastes in enclosed containers.
·
Regular cleaning and maintenance programme for
drainage systems, sumps and oil interceptors.
·
A recording system for the amount of wastes generated,
recycled and disposed of (including the disposal sites).
·
Sort C&D waste from demolition of the existing
waterfront structures to recover recyclable portions such as metals.
·
Segregation and storage of different types of waste in
different containers, skips or stockpiles to enhance reuse or recycling of materials
and their proper disposal.
·
Encourage collection of aluminium cans, PET bottles
and paper by providing separate labelled bins to enable these wastes to be
segregated from other general refuse generated by the work force.
·
Any unused chemicals or those with remaining
functional capacity shall be recycled.
·
Use of reusable non-timber formwork, such as in
casting the tunnel box sections, to reduce the amount of C&D material.
·
Proper storage and site practices to minimise the
potential for damage or contamination of construction materials.
·
Plan and stock construction materials carefully to
minimise amount of waste generated and avoid unnecessary generation of waste.
Table H8.1 Monitoring Programme
Stage |
Monitoring Task |
Monitoring Report |
Form of Approval |
Frequency |
Design |
Monitoring of design works
against the recommendations of the landscape and visual impact assessments within
the EIA should be undertaken during detailed design and tender stages, to
ensure that they fulfil the intentions of the mitigation measures. Any changes to the design, including
design changes on site should also be checked. |
Report by ER
confirming that the design conforms to requirements of EP |
Approved by
Client |
At Completion of
Design Stage |
Construction |
Monitoring of the
contractor’s operations during the construction period. |
Report on
Contractor's compliance, by ET |
Counter-signature
of report by IC(E) |
Weekly |
Design
Construction & Establishment Period
Table H8.2 Construction &
Establishment Periods
EVENT ACTION LEVEL |
ACTION |
|||
ET |
IC(E) |
ER |
CONTRACTOR |
|
Design Check |
·
Check final design
conforms to the requirements of EP and prepare report. |
·
Check report. ·
Recommend remedial design
if necessary |
·
Undertake remedial design if
necessary |
|
Non-conformity on one occasion |
·
Identify Source ·
Inform IC(E) and ER ·
Discuss remedial actions
with IC(E), ER and Contractor ·
Monitor remedial actions
until rectification has been completed |
·
Check report ·
Check Contractor's working
method ·
Discuss with ET and
Contractor on possible remedial measures ·
Advise ER on effectiveness
of proposed remedial measures. ·
Check implementation of
remedial measures. |
·
Notify Contractor ·
Ensure remedial measures
are properly implemented |
·
Amend working methods ·
Rectify damage and
undertake any necessary replacement |
Repeated Non-conformity |
·
Identify Source ·
Inform IC(E) and ER ·
Increase monitoring
frequency ·
Discuss remedial actions
with IC(E), ER and Contractor ·
Monitor remedial actions
until rectification has been completed ·
If non-conformity stops, cease additional monitoring |
·
Check monitoring report ·
Check Contractor's working
method ·
Discuss with ET and
Contractor on possible remedial measures ·
Advise ER on effectiveness
of proposed remedial measures ·
Supervise implementation
of remedial measures. |
·
Notify Contractor ·
Ensure remedial measures
are properly implemented |
·
Amend working methods ·
Rectify damage and
undertake any necessary replacement |
|
|
|
|
|
Landscape and Visual Mitigation Measures during Construction
Phase
·
Minimisation of works areas (CM2);
·
Erection of decorative hoardings (CM3);
·
Control night-time lighting (CM4);
·
Minimisation of disruption to public by
effective programming of the works (CM5).
Landscape and Visual Mitigation Measures during Operation
Phase
·
There
is no landscape and visual impact due to DP5. Therefore, there will be no
landscape and visual mitigation measures for DP5 during operation.
Table H9.1 Implementation
Schedule for Air Quality Control
EIA Ref |
Environmental Protection Measures / Mitigation Measures |
Location / Timing |
Implementation Agent |
Implementation Stages* |
Relevant Legislation and Guidelines |
|||
Des |
C |
O |
Dec |
|||||
Construction Phase |
||||||||
S |
No adverse air quality impacts at
the ASRs are expected during the construction of this DP. However, the operated dredgers and
equipments should be regularly maintained to minimise emissions during
construction phase. |
Work
site / during construction |
Contractor |
|
Ö |
|
|
EIAO-TM |
* Des - Design, C - Construction, O
– Operation, and Dec - Decommissioning
Table H9.2 Implementation
Schedule for Noise Control
EIA Ref |
Environmental Protection Measures / Mitigation Measures |
Location / Timing |
Implementation Agent |
Implementation Stages* |
Relevant Legislation and Guidelines |
|||
Des |
C |
O |
Dec |
|||||
Construction Phase |
|
|
|
|
|
|
|
|
S |
Good Site
Practice:
Only
well-maintained plant shall be operated on-site and plant shall be serviced
regularly during the construction program.
Silencers
or mufflers on construction equipment shall be utilized and shall be properly
maintained during the construction program.
Mobile
plant, if any, shall be sited as far away from NSRs as possible.
Machines
and plant (such as trucks) that may be in intermittent use shall be shut down
between works periods or shall be throttled down to a minimum.
Plant
known to emit noise strongly in one direction shall, wherever possible, be
orientated so that the noise is directed away from the nearby NSRs.
Material
stockpiles and other structures shall be effectively utilized, wherever
practicable, in screening noise from |
Work Sites / During Construction |
Contractor |
|
Ö |
|
|
EIAO-TM, NCO |
S |
Use of quiet powered mechanical
equipment for the following tasks: ·
Submarine pipelines (marine section) ·
Use of quiet powered mechanical equipment and movable noise barrier
for the following tasks: ·
Installation of a new pipeline (land section) |
Work Sites / During Construction |
Contractor |
|
Ö |
|
|
EIAO-TM, NCO |
* Des - Design, C - Construction, O –
Operation, and Dec - Decommissioning
Table H9.3 Implementation
Schedule for Water Quality Control
EIA Ref |
Environmental Protection Measures
/ Mitigation Measures |
Location / Timing |
Implementation Agent |
Implementation Stages* |
Relevant Legislation and
Guidelines |
|||||||
Des |
C |
O |
Dec |
|||||||||
Construction Phase |
|
|
|
|
|
|
|
|||||
S5.8 |
·
Dredging for construction of
the proposed sewage outfall shall be carried out by closed grab dredger. The corresponding dredging rates shall
not be more than |
Work site / During the
construction period |
Contractor |
|
Ö |
|
|
EIAO-TM, WPCO |
||||
S5.8, Figure 5.3 |
Silt screens shall be applied to seawater intakes at interim WDII construction stages as stated below:
|
Work site / During the
construction period |
Contractor |
|
Ö |
|
|
EIAO-TM, WPCO |
||||
|
|
|
|
|
|
|
|
|
||||
S5.8 |
Other mitigation measures include: · mechanical grabs, if used, shall be designed and maintained to avoid spillage and sealed tightly while being lifted. For dredging of any contaminated mud, closed watertight grabs must be used; · all vessels shall be sized so that adequate clearance is maintained between vessels and the seabed in all tide conditions, to ensure that undue turbidity is not generated by turbulence from vessel movement or propeller wash; ·
all hopper barges and
dredgers shall be fitted with tight fitting seals to their bottom openings to
prevent leakage of material; |
Work site / During the
construction period |
Contractor |
|
Ö |
|
|
ProPECC PN 1/94; WPCO (TM-DSS) |
||||
|
· construction activities shall not cause foam, oil, grease, scum, litter or other objectionable matter to be present on the water within the site or dumping grounds; |
|
|
|
|
|
|
|
||||
|
· loading of barges and hoppers shall be controlled to prevent splashing of dredged material into the surrounding water. Barges or hoppers shall not be filled to a level that will cause the overflow of materials or polluted water during loading or transportation; and |
|
|
|
|
|
|
|
||||
S5.8 |
Silt screens are recommended to be deployed at the seawater intakes during the marine works period. Installation of silt screens at the seawater intake points may cause a potential for accumulation and trapping of pollutants, floating debris and refuse behind the silt screens and may lead to potential water quality deterioration at the seawater intake points. Major sources of pollutants and floating refuse include the runoff and storm water discharges from the nearby coastal areas. As a mitigation measure to avoid the pollutant and refuse entrapment problems and to ensure that the impact monitoring results are representative, regular maintenance of the silt screens and refuse collection shall be performed at the monitoring stations at regular intervals on a daily basis. The Contractor shall be responsible for keeping the water behind the silt screen free from floating rubbish and debris during the impact monitoring period. |
Work site / During the
construction period |
Contractor |
|
Ö |
|
|
EIAO-TM, WPCO |
||||
S5.8 |
The mitigation measures for construction runoff and drainage as listed
below should be implemented where applicable. Construction Runoff and Drainage Exposed soil
areas should be minimised to reduce the potential for increased siltation,
contamination of runoff, and erosion.
Construction runoff related impacts associated with the above ground
construction activities can be readily controlled through the use of sediment
traps and adequate maintenance of drainage systems to prevent flooding and
overflow. Construction site should be provided with adequately designed perimeter channel and pre-treatment facilities and proper maintenance. The boundaries of critical areas of earthworks should be marked and surrounded by dykes or embankments for flood protection. Temporary ditches should be provided to facilitate runoff discharge into the appropriate watercourses, via a silt retention pond. Permanent drainage channels should incorporate sediment basins or traps and baffles to enhance deposition rates. The design of efficient silt removal facilities should be based on the guidelines in Appendix A1 of ProPECC PN 1/94. |
Work site / During the
construction period |
Contractor |
|
Ö |
|
|
ProPECC PN 1/94; WPCO (TM-DSS) |
||||
|
Ideally, construction works should be programmed to minimise surface excavation works during the rainy season (April to September). All exposed earth areas should be completed as soon as possible after earthworks have been completed, or alternatively, within 14 days of the cessation of earthworks where practicable. If excavation of soil cannot be avoided during the rainy season, or at any time of year when rainstorms are likely, exposed slope surfaces should be covered by tarpaulin or other means. |
|
|
|
|
|
|
|
||||
|
A sediment tank constructed from pre-formed individual cells of
approximately 6 ‑ |
|
|
|
|
|
|
|
||||
|
Open stockpiles of construction materials (for examples,
aggregates, sand and fill material) of more than |
|
|
|
|
|
|
|
||||
S5.8 |
Construction Runoff and Drainage
(continued) Manholes (including newly constructed ones) should always be adequately covered and temporarily sealed so as to prevent silt, construction materials or debris being washed into the drainage system and storm runoff being directed into foul sewers; Precautions to be taken at any time of year when rainstorms are likely, actions to be taken when a rainstorm is imminent or forecast, and actions to be taken during or after rainstorms are summarised in Appendix A2 of ProPECC PN 1/94. Particular attention should be paid to the control of silty surface runoff during storm events; Oil interceptors should be provided in the drainage system and regularly cleaned to prevent the release of oils and grease into the storm water drainage system after accidental spillages. The interceptor should have a bypass to prevent flushing during periods of heavy rain. |
Work site / During the
construction period |
Contractor |
|
Ö |
|
|
ProPECC PN 1/94; WPCO (TM-DSS) |
||||
|
All vehicles and plant should be cleaned before leaving a construction site to ensure no earth, mud, debris and the like is deposited by them on roads. An adequately designed and located wheel washing bay should be provided at every site exit, and wash-water should have sand and silt settled out and removed at least on a weekly basis to ensure the continued efficiency of the process. The section of access road leading to, and exiting from, the wheel-wash bay to the public road should be paved with sufficient backfall toward the wheel-wash bay to prevent vehicle tracking of soil and silty water to public roads and drains. |
|
|
|
|
|
|
|
||||
S5.8 |
Construction Runoff and Drainage
(Continued) It is recommended that on-site drainage system should be installed prior to the commencement of other construction activities. Sediment traps should be installed in order to minimise the sediment loading of the effluent prior to discharge into foul sewers. There shall be no direct discharge of effluent from the site into the sea. All temporary and permanent drainage pipes and culverts provided to facilitate runoff discharge shall be adequately designed for the controlled release of storm flows. All sediment control measures shall be regularly inspected and maintained to ensure proper and efficient operation at all times and particularly following rain storms. The temporarily diverted drainage shall be reinstated to its original condition when the construction work is finished or the temporary diversion is no longer required. All fuel tanks and store areas shall be provided with locks and be sited on sealed areas, within bunds of a capacity equal to 110% of the storage capacity. |
Work site / During the
construction period |
Contractor |
|
Ö |
|
|
ProPECC PN 1/94; WPCO (TM-DSS) |
||||
S5.8 |
Sewage from Construction Work
Force Construction work force sewage discharges
on site shall be connected to the existing trunk sewer or sewage treatment
facilities. The construction
sewage shall be handled by portable chemical toilets prior to the commission
of the on-site sewer system.
Appropriate numbers of portable toilets shall be provided by a
licensed contractor to serve the large number of construction workers over
the construction site. The
Contractor shall also be responsible for waste disposal and maintenance
practices. |
Work site / During the
construction period |
Contractor |
|
Ö |
|
|
ProPECC PN 1/94; WPCO (TM-DSS) |
||||
S5.8 |
Floating Debris and Refuse Collection and removal of floating
refuse shall be performed at regular intervals on a daily basis. The contractor shall be responsible for
keeping the water within the site boundary and the neighbouring water free
from rubbish. |
Work site and adjacent water /
During the construction period. |
Contractor |
|
Ö |
|
|
WPCO |
||||
S5.8 |
Storm Water Discharges Minimum distances of |
Work site and adjacent water /
During the design and construction period. |
Contractor |
Ö |
Ö |
|
|
WPCO |
* Des - Design, C - Construction, O – Operation, and Dec -
Decommissioning
Table H9.4 Implementation
Schedule for Waste Management
EIA Ref |
Environmental Protection Measures / Mitigation Measures |
Location / Timing |
Implementation Agent |
Implementation Stages* |
Relevant Legislation and Guidelines |
||||
Des |
C |
O |
Dec |
||||||
Construction Phase |
|
|
|
|
|
|
|
||
S |
Marine Sediments
The dredged marine sediments would
be loaded onto barges, transported to and disposed of at the designated
disposal sites at South of Cheung Chau, East of Ninepin, East of Tung Lung
Chau, South of Tsing Yi and East of Sha Chau to be allocated by the MFC
depending on their level of contamination or at other disposal sites after
consultation with the MFC and EPD. In accordance with the ETWB TCW No. 34/2002, the contaminated material must be dredged and transported with
great care. The mitigation
measures recommended in Section 5 of the EIA Report shall be incorporated.
The dredged contaminated sediment must be effectively isolated from the
environment upon final disposal and shall be disposed of at the Type 2
confined marine disposal contaminated mud pit. |
Work site
/ During the construction period |
Contractor |
|
Ö |
|
|
ETWB TCW No. 34/2002 |
|
S |
It will be the responsibility of
the Contractor to satisfy the appropriate authorities that the contamination levels
of the marine sediment to be dredged have been analysed and recorded. According to the ETWB TCW No. 34/2002,
this will involve the submission of a formal Sediment Quality Report to the
DEP, at least 3 months prior to the dredging contract being tendered. |
|
|
|
|
|
|
|
|
S |
During transportation and disposal
of the dredged marine sediments requiring Type 1 and Type 2 disposal, the
following measures shall be taken to minimise potential impacts on water
quality: |
|
|
|
|
|
|
|
|
|
·
Bottom opening of barges shall be fitted with tight fitting seals to
prevent leakage of material.
Excess material shall be cleaned from the decks and exposed fittings
of barges and hopper dredgers before the vessel is moved. |
|
|
|
|
|
|
|
|
|
·
Monitoring of the barge loading shall be conducted to ensure that loss
of material does not take place during transportation. Transport barges or vessels shall be
equipped with automatic self-monitoring devices as specified by the DEP. ·
Barges or hopper barges shall not be filled to a level that would
cause the overflow of materials or sediment laden water during loading or
transportation. |
|
|
|
|
|
|
|
|
S |
Good Site Practices Recommendations for good site practices during the construction
activities include:
·
nomination of an approved person, such as a site
manager, to be responsible for good site practices, arrangements for collection
and effective disposal to an appropriate facility, of all wastes generated at
the site; |
Work site
/ During the construction period |
Contractor |
|
Ö |
|
|
Waste Disposal Ordinance (Cap.354) |
|
|
·
training of site personnel in proper waste
management and chemical waste handling procedures; |
|
|
|
|
|
|
|
|
|
·
provision of sufficient waste disposal points and
regular collection for disposal; |
|
|
|
|
|
|
|
|
|
·
appropriate measures to minimise windblown litter
and dust during transportation of waste by either covering trucks or by
transporting wastes in enclosed containers; ·
regular cleaning and maintenance programme for
drainage systems, sumps and oil interceptors; and ·
a recording system for the amount of wastes
generated, recycled and disposed of (including the disposal sites). |
|
|
|
|
|
|
|
|
S |
Waste Reduction Measures Waste reduction is best achieved at
the planning and design stage, as well as by ensuring the implementation of
good site practices.
Recommendations to achieve waste reduction include: ·
Sort C&D waste from demolition of the existing
structures to recover recyclable portions such as metals. ·
Segregation and storage of different types of waste
in different containers, skips or stockpiles to enhance reuse or recycling of
materials and their proper disposal. |
Work site
/ During planning and design stage, and construction stage |
Contractor |
Ö |
Ö |
|
|
|
|
|
·
Encourage collection of aluminium cans, PET bottles
and paper by providing separate labelled bins to enable these wastes to be
segregated from other general refuse generated by the work force. ·
Any unused chemicals or those with remaining
functional capacity shall be recycled. ·
Use of reusable non-timber formwork to reduce the
amount of C&D material. |
|
|
|
|
|
|
|
|
|
·
Proper storage and site practices to minimise the potential
for damage or contamination of construction materials. ·
Plan and stock construction materials carefully to minimise amount of
waste generated and avoid unnecessary generation of waste. |
|
|
|
|
|
|
|
|
S |
General Refuse
General refuse shall be stored in enclosed
bins or compaction units separate from C&D material. A licensed waste collector shall be
employed by the contractor to remove general refuse from the site, separately
from C&D material. A collection area shall be provided where
wastes can be stored and loaded prior to removal from site. An enclosed and covered area is
recommended to reduce the occurrence of 'wind blow' light material. |
Work site
/ During the construction period |
Contractor |
|
Ö |
|
|
Public Health
and Municipal Services Ordinance (Cap. 132) |
|
S |
Chemical Wastes
After use, chemical wastes (for example,
cleaning fluids, solvents, lubrication oil and fuel) shall be handled
according to the Code of Practice on the Packaging, Labelling and Storage of
Chemical Wastes. Spent chemicals
shall be collected by a licensed collector for disposal at the CWTF or other
licensed facility in accordance with the Waste Disposal (Chemical Waste) (General)
Regulation. |
Work site
/ During the construction period |
Contractor |
|
Ö |
|
|
Waste
Disposal (Chemical Waste) (General) Regulation Code of
Practice on the Packaging, Labelling and Storage of Chemical Wastes |
|
S |
Construction and Demolition
Material
C&D material shall be sorted on-site into
inert C&D material (that is, public fill) and C&D waste. All the
suitable inert C&D material shall be broken down to |
Work site
/ During the construction period |
Contractor |
|
Ö |
|
|
ETWB TCW
No. 33/2002, 31/2004, 19/2005 |
|
S |
In order to monitor the disposal
of public fill and C&D waste at public fill reception facilities and landfills,
respectively, and to control fly tipping, a trip-ticket system shall be
included as one of the contractual requirements and implemented by the
Environmental Team undertaking the environmental monitoring and audit work. An Independent Environment Checker
shall be responsible for auditing the results of the system. |
Work site
/ During the construction period |
Contractor and Independent Environmental
Checker |
|
Ö |
|
|
ETWB TCW
No. 31/2004 |
|
* Des - Design, C - Construction, O
– Operation, and Dec - Decommissioning
Table H9.5 Implementation Schedule for Land Contamination
EIA Ref |
Environmental Protection Measures / Mitigation Measures |
Location / Timing |
Implementation Agent |
Implementation Stages* |
Relevant Legislation and Guidelines |
||||
Des |
C |
O |
Dec |
||||||
Construction and Operation Phase |
|||||||||
S. |
As no potential contaminative land
uses were identified within the Study Area, adverse land contamination
impacts associated with the construction and operation of the Project is not
expected. As such, environmental
protection and mitigation measures are considered not necessary. |
- |
- |
|
|
|
|
- |
|
* Des - Design, C - Construction, O
– Operation, and Dec - Decommissioning
Table H9.6 Implementation
Schedule for Marine Ecology
EIA Ref |
Environmental Protection Measures
/ Mitigation Measures |
Location / Timing |
Implementation Agent |
Implementation Stages* |
Relevant Legislation and
Guidelines |
||||
Des |
C |
O |
Dec |
||||||
Construction & Operation
Phases |
|
|
|
|
|
|
|
||
S. |
As no adverse ecological impact on marine habitats and associated
wildlife is predicted, no necessary mitigation measure specific for marine
ecology is considered as required in this assessment. The mitigation measures recommended in
the water quality impact assessment to control water quality would also serve
to protect marine ecological resources from indirect impacts and ensure no
adverse impact on marine life would be resulted from this designated project.
|
- |
- |
|
|
|
|
- |
|
*Des - Design, C - Construction, O – Operation, and Dec -
Decommissioning
Table H9.7 Implementation Schedule for Landscape
and Visual
EIA Ref |
Environmental Protection Measures / Mitigation Measures |
Location / Timing |
Implementation Agent |
Implementation Stages* |
Relevant Legislation and Guidelines |
||||
Des |
C |
O |
Dec |
||||||
Construction Phase |
|
|
|
|
|
|
|
||
Refer to EIA-058/2001 Table
10.13 |
CM2 Minimisation of works
areas. |
Work site
/ During Construction Phase |
Contractor |
|
Ö |
|
|
EIAO TM |
|
Refer to EIA-058/2001 Table 10.13 |
CM3 Erection of decorative
hoardings. |
Work site
/ During Construction Phase |
Contractor |
|
Ö |
|
|
EIAO TM |
|
Refer to EIA-058/2001 Table 10.13 |
CM4 Control night-time lighting. |
Work site
/ During Construction Phase |
Contractor |
|
Ö |
|
|
EIAO TM |
|
Refer to EIA-058/2001 Table 10.13 |
CM5 Minimisation of
disruption to public by effective programming of the works. |
Work site
/ During Construction Phase |
Contractor |
|
Ö |
|
|
EIAO TM |
|
*Des - Design, C - Construction, O –
Operation, and Dec - Decommissioning