Construction Phase
Operation Phase
Construction Phase
Operation Phase
Construction Phase
(a)
one set of measurements
between 0700 and 1900 hours on normal weekdays.
Operation Phase
(i)
one set of measurements at
the morning traffic peak hour on normal weekdays;
(ii)
one set of measurement at the
evening traffic peak hour on normal weekdays;
(iii)
a concurrent census of
traffic flow and percentage heavy vehicles shall be conducted for the far-side
and near-side of the road and the existing road network in the vicinity of each
measurement points;
(iv)
average vehicle speed
estimated for far-side and near-side of the road and the existing road network
in the vicinity of each measuring points; and
(v)
the two sets of monitoring
data shall be obtained within the first year of operation.
Construction Phase
Table 3.1 Action and Limit Levels for Construction Noise
Time Period |
Action Level |
Limit Level |
0700 – 1900 hours on normal weekdays |
When one
documented complaint is received |
75
dB(A) * |
Notes:
If works are to be carried
out during restricted hours, the conditions stipulated in the Construction Noise
Permit (CNP) issued by the Noise Control Authority have to be followed.
Operation Phase
Construction Phase
·
Piling
activity for construction of temporary breakwater at Causeway Bay Typhoon
Shelter
·
Temporary
seawall construction, filling behind seawall, for whole project construction
·
Diaphragm
wall, excavation, construction of slabs and backfilling in CWB tunnel
construction
·
Rock
excavation at CWB tunnel (Cross Harbour Tunnel section)
·
Temporary
diversion of cooling water pipeline at CBTS 4
·
Slip
Road 8 and
·
Substructure
and superstructure for landscape deck, connection of IECL
·
Demolition
of structure
·
Drainage
culverts construction
·
Ferry
pier reprovisioning, including construction of new ferry pier and demolition of
existing structure
·
WSD’s
salt water pumping station construction
·
Construction
of Wan Chai East sewage outfall
·
Road
works construction
·
MTR
Tunnel crossing
·
Cross
harbour watermains
·
Foundation
of
· Excavator |
·
Air
Compressor |
· Bentonite Plants |
·
Concrete
Pump |
· Poker Vibrator |
·
Hand-held
Breaker |
· Diaphragm Wall Rigs |
·
Breaker |
· Generator |
|
·
Only well-maintained plant shall be operated on-site and
plant shall be serviced regularly during the construction program.
·
Silencers or mufflers on construction equipment shall be
utilised and shall be properly maintained during the construction program.
·
Mobile plant, if any, shall be sited as far away from
NSRs as possible.
·
Machines and plant (such as trucks) that may be in
intermittent use shall be shut down between works periods or shall be throttled
down to a minimum.
·
Plant known to emit noise strongly in one direction
shall, wherever possible, be orientated so that the noise is directed away from
the nearby NSRs.
·
Material stockpiles and other structures shall be
effectively utilised, wherever practicable, in screening noise from on-site
construction activities.
Operation
Phase
·
about
·
about
·
about
Table 3.2 Event/Action Plan for Construction Noise
EVENT |
ACTION |
|||
|
ET |
IC(E) |
ER |
CONTRACTOR |
Action Level being exceeded |
1. Notify ER, IC(E) and Contractor; 2. Carry out investigation; 3. Report the results of investigation to the IC(E), ER and Contractor; 4. Discuss with the IC(E) and Contractor on remedial measures required; 5. Increase monitoring frequency to check mitigation effectiveness. (The above actions should be taken within 2 working days after the exceedance is identified) |
1.
Review the investigation results submitted by the
ET; 2.
Review
the proposed remedial measures by the Contractor and advise the ER
accordingly; 3.
Advise
the ER on the effectiveness of the proposed remedial measures. (The
above actions should be taken within 2 working days after the exceedance is
identified) |
1. Confirm receipt
of notification of failure in writing; 2. Notify
Contractor; 3. In consolidation
with the IC(E), agree with the Contractor on the remedial measures to be
implemented; 4. Supervise the
implementation of remedial measures. (The
above actions should be taken within 2 working days after the exceedance is
identified) |
1. Submit noise mitigation proposals to IC(E) and ER; 2. Implement noise mitigation proposals. (The above actions should be taken within 2 working days after the exceedance is identified) |
|
|
|
|
|
Limit Level being exceeded |
1. Inform IC(E), ER, Contractor and EPD; 2. Repeat measurements to confirm findings; 3. Increase monitoring frequency; 4. Identify source and investigate the cause of exceedance; 5. Carry out analysis of Contractor’s working procedures; 6. Discuss with the IC(E), Contractor and ER on remedial measures required; 7. Assess effectiveness of Contractor’s remedial actions and keep IC(E), EPD and ER informed of the results; 8. If exceedance stops, cease additional monitoring. (The above actions should be taken within 2 working days after the exceedance is identified) |
1. Discuss amongst ER, ET, and Contractor on the potential remedial actions; 2. Review Contractor’s remedial actions whenever necessary to assure their effectiveness and advise the ER accordingly. (The above actions should be taken within 2 working days after the exceedance is identified) |
1. Confirm receipt
of notification of failure in writing; 2. Notify
Contractor; 3. In consolidation with
the IC(E), agree with the Contractor on the remedial measures to be
implemented; 4. Supervise the
implementation of remedial measures; 5. If exceedance
continues, consider stopping the Contractor to continue working on that
portion of work which causes the exceedance until the exceedance is abated. (The above actions should be taken within 2 working days after the
exceedance is identified) |
1. Take immediate action to avoid further exceedance; 2. Submit proposals for remedial actions to IC(E) and ER within 3 working days of notification; 3. Implement the agreed proposals; 4. Submit further proposal if problem still not under control; 5. Stop the relevant portion of works as instructed by the ER until the exceedance is abated. (The above actions should be taken within 2 working days after the exceedance is identified) |