1.1.1
Wan
Chai Development Phase II (WDII) is the conclusion of a number of planning
studies commissioned by Government, covering transport infrastructure and
development along the shoreline of Central and Wan Chai, that date back to the
early 1980s. The WDII project is
undergoing a process of statutory town planning procedures and public
consultation, in which there has been thorough public discussion on matters
including the scale of reclamation and the usage of the land to be made
available by the project.
1.1.2
The need
for the Central and Wan Chai Reclamation was first identified in the strategic
study on “Harbour Reclamations and Urban Growth” undertaken between March 1982
and October 1983. The need was
further confirmed in various planning studies, including the Territorial
Development Strategy of 1984, the Port and Airport Development Strategy 1989,
Metroplan 1991, and the Territorial Development Strategy Review of 1996. The whole Central and Wan Chai
Reclamation project forms land for the construction of, among other things,
strategic transport links, associated surface road networks, the Airport
Railway and its Hong Kong Station and the Hong Kong Convention and Exhibition
Centre (HKCEC) Extension. The
Central Reclamation Phases I, II and the Wan Chai Reclamation Phase I were
completed in 1997 to 1998. Central
Reclamation Phase III (CRIII) is currently under construction. WDII is the final phase, and an integral
part, of the Central and Wan Chai Reclamation.
1.1.3
The
Wan Chai Development Phase II Comprehensive Feasibility Study (the WDIICFS) was
commissioned by the then Territory Development Department in June 1999. The main purpose of that assignment was
to make provision for key transport infrastructure and facilities along the
north shore of Hong
Kong Island, in Wan Chai and Causeway Bay. Under the WDIICFS, a Trunk Road layout
was derived, comprising the Central-Wan Chai Bypass (CWB) running along the Wan
Chai shoreline in tunnel, and the Island Eastern Corridor Link (IECL) running
behind the Causeway Bay Typhoon Shelter (CBTS) on elevated roadway, connecting
to the existing elevated Island Eastern Corridor (IEC). New land was proposed along the Wan Chai
and Causeway Bay shoreline, primarily for the
construction of the Trunk Road and other key infrastructure, and also to
provide an attractive waterfront with a new public promenade. A total reclamation area of some 28.5 ha along the existing Wan Chai and
Causeway Bay shorelines was envisaged under the WDIICFS, from the interface
with the CRIII project on the west side of the HKCEC Extension, to the east of
the CBTS.
1.1.4
The
Trunk Road and the associated land use proposals for the WDII project were
incorporated in a draft Wan Chai North Outline Zoning Plan No. S/H25/1 (the
draft OZP) which was gazetted under the Town Planning Ordinance on 19 April
2002. At the same time, the road
works and reclamation proposed under the WDII project were gazetted under the
Roads (Works, Use and Compensation) Ordinance and Foreshore and Sea-bed
(Reclamations) Ordinance respectively.
1.1.5
Objections
to the draft OZP were received and considered by the Town Planning Board, which
decided to propose amendments to the draft OZP to meet or partially meet some
of the objections after giving preliminary consideration and further
consideration to the objections on 6 September 2002, and 29 November 2002 and 6
December 2002, respectively; and after giving consideration to further
objections on 14 February 2003.
1.1.6
In
February 2003, the Society for the Protection of the Harbour Limited sought a
judicial review of the decisions of the Town Planning Board made on 6 December
2002 and 14 February 2003 in
connection with the draft Wan Chai North OZP and its compliance with the
Protection of the Harbour Ordinance (PHO).
The High Court handed down its judgment on 8 July 2003, whereby the
decisions of the Town Planning Board made on 6 December 2002 and 14 February 2003 in respect of the draft OZP were
quashed. The Court also ordered the
Town Planning Board to reconsider the draft OZP and the objections
thereto. As this interpretation of
the PHO would apply to all future planning of harbour-front areas which
included reclamation, and due to the great general and public importance of the
case, the Town Planning Board appealed directly to the Court of Final Appeal (CFA).
1.1.7
Objections
were also received for the WDII road works and reclamation schemes gazetted
under the Roads (Works, Use and Compensation) Ordinance and Foreshore and
Sea-bed (Reclamations) Ordinance respectively. In the light of the on-going legal
proceedings, it was considered not appropriate to submit the road works and
reclamation schemes to the Chief Executive in Council for consideration. The above gazettals lapsed on 18 and 19
September 2003 respectively. The
WDII project was re-gazetted under the relevant ordinances in July 2007.
1.1.8
In
October 2003, the Town Planning Board considered the findings of a preliminary
planning assessment on the draft OZP conducted by Planning Department according
to the High Court’s judgment on the judicial review and requested Government to
conduct a comprehensive review of the planning and engineering proposals of the
WDII project and draw up a minimum reclamation option for Wan Chai North that
would comply with the law. The Town
Planning Board is reconsidering the draft OZP and the objections according to
the provisions of the Town Planning Ordinance upon completion of the review.
1.1.9
On 9
January 2004, the CFA handed down its judgment on the judicial review. The CFA ruled that the presumption
against reclamation in the PHO can only be rebutted by establishing an
overriding public need for reclamation (the “Overriding Public Need Test”), and
that there must be cogent and convincing materials available to enable the
decision-maker to be satisfied that the test is fulfilled for rebutting the
presumption against reclamation.
1.1.10
Following
the Town Planning Board request for a review of the WDII proposals and in the
light of the CFA judgment, Government has undertaken to conduct a planning and
engineering review of the development and reclamation proposals for the WDII
project (the WDII Review). The WDII
Review commenced in March 2004.
1.2.1
The
main purpose of the WDII project is to provide land for the construction of the
Trunk Road (comprising the CWB which runs from Central Interchange in Central
Reclamation Phase I through the CRIII and WDII project areas, and the IECL
which provides connection from the eastern portal of the CWB to the IEC), and
other key transport infrastructure including the necessary ground level roads
for connection to the Trunk Road and to cater for through traffic from Central
to Wan Chai and Causeway Bay.
1.2.2
Rail
infrastructure that would be accommodated by the WDII project includes the Hong
Kong Island section of the Shatin to Central Link (SCL) and the future Mass
Transit Railway (MTR) North Hong Kong Island Line (NIL).
1.2.3
The
land formed for the above transport infrastructure will provide opportunities
for the development of an attractive waterfront promenade for the enjoyment of
the public.
1.2.4
The
WDII Review seeks to assess individually the purpose and extent of each
proposed reclamation by reference to the Overriding Public Need Test and, if
needed, to make recommendations on the revised alignment for the Trunk Road and
at-grade roads, extent of reclamation and/or the land uses for the review area
covered by the Assignment.
1.3.1
The
Harbour-front Enhancement Committee (HEC) was established in May 2004 to advise
Government, through the then Secretary for Housing, Planning and Lands, on the
planning, land uses and developments along the existing and new harbour-front
of Victoria Harbour. As guidance for the planning,
development and management of the Victoria
Harbour and the
harbour-front areas, the HEC has established harbour planning principles which
should be followed when examining transport infrastructure, including the Trunk
Road, and harbour-front enhancement schemes. These are:
·
preserving
Victoria Harbour
·
stakeholder
engagement
·
sustainable
development
·
integrated
planning
·
proactive
harbour enhancement
·
vibrant
harbour
·
accessible
harbour
·
public
enjoyment.
1.3.2
The
HEC has set up a Sub-committee, namely the Sub-committee on WDII Review, to
advise on the WDII Review. Government
has accepted the recommendation by the Sub-committee on WDII Review that
enhanced participation should be a key element of the Review. To achieve this, a public engagement
exercise, namely the “Harbour-front Enhancement Review – Wan Chai, Causeway Bay and Adjoining Areas” (HER), has been
carried out under the steer of the Sub-committee on WDII Review. Results of the HER project provide
inputs to the WDII Review.
1.3.3
In
order to achieve a better understanding of the opportunities for waterfront
enhancement and to ensure a high degree of community support for the future
draft OZPs and the draft Recommended Outline Development Plan (RODP), a 3-stage
public engagement strategy has been formulated so as to enable a more
structured approach to be adopted to the HER public engagement activities:
(i) “Envisioning Stage” Public
to provide their visions, wishes and concepts, as well as to compile
Sustainability Principles and Indicators as a basis for the development of the
Concept Plan
(ii) “Realization Stage” Public
to evaluate the Concept Plan to arrive at consensus
(iii) “Detailed Planning Stage” Ensure
draft OZPs and draft RODP reflect the consensus.
1.3.4
The
Envisioning Stage was formally launched on 22 May 2005, with a wide range of
public engagement activities taking place over a two-month public engagement
period. The envisioning exercise
was to engage the public in identifying the key issues and establishing
principles in terms of improving the waterfront. The concept of sustainable development
underpins the whole HER project. A
list of sustainability principles and indicators was prepared and agreed
through the public consultation process; these agreed sustainability principles
and indicators have been used to evaluate the Concept Plan that was developed
in the Realization Stage.
1.3.5
As
part of the public engagement activities, the HEC Sub-committee on WDII Review
convened an “Expert Panel Forum on Sustainable Transport Planning and
Central-Wan Chai Bypass”, to explore sustainable transport along the northern
shore of Hong Kong Island and to deliberate on whether the Central-Wan Chai
Bypass (ie the Trunk Road) is needed – one of the key issues of the project.
1.3.6
The
various issues that were raised by participants during the public engagement
process, particularly in respect of Trunk Road alignments and harbour-front
enhancement ideas, were extensively considered and addressed by the
Sub-committee on WDII Review as part of the process of consolidating
harbour-front and Trunk Road ideas.
The outcomes of this process then formed the basis of the preparation of
the Concept Plan.
1.3.7
In the
Realization Stage, a Concept Plan, for the development and enhancement of the
harbour-front under the ambit of the WDII Review, was prepared for evaluation
and consensus building by the public, using the HEC’s harbour planning
principles and the sustainability principles and indicators developed during
the Envisioning Stage. At a Consensus Building Town Hall
meeting on 16 December 2006, there was general agreement with the proposals put
forward by the Concept Plan, in respect of the Trunk Road proposal and the
envisaged land uses, although there was some discussion on various detailed
aspects of the harbour-front enhancement schemes.
1.3.8
On the
basis of consensus on the Concept Plan, detailed planning, engineering and
environmental assessments have been carried out for the derivation of the draft
OZPs and RODP, which reflect the consensus on the Concept Plan.
1.3.9
A
detailed scheme for the WDII project and the section of Trunk Road (CWB) within
the study area (hereafter referred to as “the Project”) has been developed from
the Concept Plan, with minimum reclamation necessary to meet the overriding
public need, in conformance with the PHO. Figure
1.1
shows the layout plan of the Project.
This scheme has been subject to detailed environmental impact assessment
(EIA) under the WDII Review.
1.4.1
An EIA
for WDII and CWB projects has been undertaken in accordance with the EIA Study
Brief and the Technical Memorandum on Environmental Impact Assessment Process
(EIAO-TM). According to the EIA
Study Brief, the objective of this EIA is to provide information on the nature
and extent of environmental impacts arising from the construction and operation
of the developments proposed under the Project and related works that take
place concurrently. This
information will contribute to decisions on:
(i)
The
overall acceptability of any adverse environmental consequences that are likely
to arise as a result of the Project and associated works, and any related
phased implementation.
(ii)
The
conditions and requirements for the detailed design, construction and operation
of the Project to mitigate against adverse environmental consequences wherever
practicable.
(iii)
The
acceptability of residual impacts after the staged as well as the full
implementation of the Project, the associated works and the related proposed
mitigation measures.
1.5.1
The proposed
Project is an engineering feasibility study of an urban development project
with a study area covering approximately 90 ha
(i.e. more than 20 ha). Under the Environmental Impact
Assessment Ordinance (EIAO), this Project is classified as a Schedule 3
Designated Project (DP) under item 1 of the Schedule 3 “Major Designated
Projects Requiring Environmental Impact Assessment Reports”. A detailed environmental assessment for
approval by the Director of Environmental Protection (DEP) is required.
1.5.2
The Project
also contains various Schedule 2 DPs that, under the EIAO, require
Environmental Permits (EPs) to be granted by the DEP before they may be either
constructed or operated. Table 1.1 summarises the six individual
DPs under this Project. Figure 1.2 shows the locations of these
Schedule 2 DPs.
Table 1.1 Schedule
2 Designated Projects under this Project
Item
|
Designated Project
|
EIAO Reference
|
Reason for inclusion
|
DP1
|
Central-Wanchai
Bypass (CWB) including its road tunnel and slip roads
|
Schedule 2, Part I, A.1 and A.7
|
Trunk Road and road tunnel 800 m in length
|
DP2
|
Road P2 and
other roads which are classified as primary/district distributor roads
|
Schedule 2,
Part I, A.1
|
Primary / district distributor roads
|
DP3
|
Reclamation
works including associated dredging works
|
Schedule 2,
Part I, C.1 and C.12
|
Reclamation more than 5 ha in size and a dredging operation
less than 100 m
from a seawater intake point
|
DP4
|
Temporary
typhoon shelter
|
Schedule 2, Part I, C.5
|
A typhoon shelter designed to provide
moorings for not less than 30 vessels
|
DP5
|
Wan Chai
East Sewage Outfall
|
Schedule 2,
Part I, F.5 and F.6
|
Submarine sewage pipelines with a total
diameter more than 1,200 mm
and include a submarine sewage
outfall
|
DP6
|
Dredging for
the Cross-harbour Water Mains from Wan Chai to Tsim Sha Tsui
|
Schedule 2,
Part I, C.12
|
A dredging operation less than 100 m from a seawater intake point
|
1.5.3
Description
of the six DPs are given below:
·
DP1
- Central-Wanchai Bypass including its road tunnel and slip roads
The Trunk Road is a duel-3 carriageway defined from
the connection with the existing Rumsey Street Flyover in Central, through to a
connection with the existing IEC to the east of the CBTS. At the Rumsey Street Flyover connection,
a Central Interchange will provide connections into the Central area, and then
the Trunk Road will drop down into tunnel and run along the Central shoreline,
through CRIII, to the WDII project area.
In WDII area, the Trunk Road will continue in tunnel until it needs to
rise onto elevated structure to connect with the elevated IEC. Total Trunk Road length is around 4.5km and the total tunnel length is
around 3.5 km. The section of Trunk Road within the
study area is around 3 km and
the tunnel length is around 2.5
km.
In the Wan
Chai North and Causeway Bay
area, the Trunk Road will be connected to the local road system by slip
roads.
As the CWB is a trunk road and road tunnel within the study
area is longer than 800m,
it is classified as DP under Schedule 2 Part I, A1 & A7. The location of this DP1 is shown in Figure 1.2a.
·
DP2
- Road P2 and other roads which are classified as primary/district distributor
roads
The major element of the future ground level road
system is Road P2, which runs east-west from Central to connections with the
existing road network in Wan Chai North.
Road P2 is a dual 2-lane primary distributor that serves both local
east-west movements and the distribution of north-south traffic movements.
The Road P2 alignment has been planned to run over the
top of the Trunk Road tunnel through CRIII and the HKCEC water channel, to the
connection with Fleming Road,
in order to minimise the overall road
“footprint” and area of land sterilised by highway infrastructure. New junctions are formed along Road P2 with
the north-south roads.
Along the Wan Chai shoreline, the existing Hung Hing
Road in front of the Wan Chai North Public Transport Interchange (PTI) is realigned to connect with the new Road P2 /
Fleming Road junction, but the current Hung Hing Road alignment further east in front of the Wan Chai Sports Ground is
retained. The length of the new
Road P2 through WDII is approximately 0.6
km. The new
at-grade road network also provides connections to slip roads of the Trunk Road
in Wan Chai North. The total length of other new primary
and district distributor road connecting to slip road of the Trunk Road is
around 0.7 km.
Since these are primary / district distributor roads,
they are classified as a DP under Schedule 2, Part I, A1. The location of DP2 is shown in Figure 1.2b.
·
DP3
- Reclamation works including associated dredging works
The project is driven by the need for the implementation
of the Trunk Road, which will form an east-west strategic route through Central
and Wan Chai to existing IEC.
Construction of this Trunk Road will, though, require permanent
reclamation in the areas to the west of HKCEC, through the HKCEC water channel,
along the Wan Chai shoreline and along the North Point shoreline. Permanent reclamation is not required in
the ex-Public Cargo working Area
(PCWA) basin or in the CBTS.
During the Trunk Road construction, temporary
reclamation will be required in the ex-PCWA basin and the CBTS to facilitate
cut-and-cover tunnel construction of the Trunk Road. After construction of the Trunk Road,
the temporary reclamation will be removed and the ex-PCWA basin and the CBTS will
be reinstated.
The total volume of sediments to be dredged and
disposed is estimated to be approximately 1.15
Mm3.
The minimum area of permanent reclamation required is summarised as follows:
(i) HKCEC
West: 3.7 ha
(ii) HKCEC
Water Channel: 1.6 ha
(iii) Wan
Chai Shoreline: 4.1 ha
(iv) North
Point Shoreline: 3.3 ha
The total reclamation area is 12.7 ha.
Since the reclamation is more than 5 ha
in size, it is classified as a DP under Schedule 2, Part I, C1.
For the mitigation of odour, dredging to remove the polluted sediments at the south-west corner of the
CBTS will be carried out during the implementation of harbour-front
enhancement and forms part of DP3.
Further, as dredging will be carried out less than 100m from a seawater intake, it would also be classified as a DP under Schedule 2, Part I, C.12.
The location of DP3 is shown in Figure 1.2c.
·
DP4
– Temporary typhoon shelter
The construction of the Trunk Road tunnel beneath the
CBTS will temporarily affect the existing moorings. To maintain the operation of the CBTS
during the construction period, it is necessary to reprovision a temporary
typhoon shelter in the vicinity of the existing one. The Project therefore includes a temporary typhoon shelter with
around 4 ha temporary mooring
area for not less than 30 vessels at the north of the existing typhoon
shelter. It involves the
construction of a 400m
long rubble mound breakwater some 180m
offshore and parallel to the existing CBTS breakwater, together with 120m and 130m lengths of piled wave walls at the eastern and
western ends of the sheltered mooring area respectively. As such, it is classified as DP under
Schedule 2 Part I, C.5. The
location of this DP4 is shown in Figure 1.2d.
·
DP5
– Wan Chai East Sewage Outfall
The Wan Chai West Sewage Screening Plant will be decommissioned
once flows have been diverted to the Wan Chai East Sewage Screening Plant. The Wan Chai East Sewage Screening Plant
will have adequate capacity to handle these flows. However, in the longer term, the
existing sewage outfall will need to be upgraded to handle the future design
flows. A new sewage outfall will be
constructed under the project to replace and upgrade the existing Wan Chai East
sewage outfall. The configuration
of the new sewage outfall will comprise a landfall section of 2,250mm diameter pipe with approximate
length of 180m,
and a marine section of twin 1,600mm
diameter submarine pipelines of about 550m
length. As the twin submarine
sewage pipelines comprise a total
diameter more than 1,200mm
and include submarine sewage outfall, it is classified as DP under Schedule 2
Part I, F.5 and F.6. The location
of this DP5 is shown in Figure 1.2e.
·
DP6
– Dredging for the Cross-harbour Water Mains from Wan Chai to Tsim Sha Tsui
An existing cross harbour fresh water mains of about 1.1 km length and comprising twin 1,000 mm diameter steel submarine
pipelines runs from Tsim Sha Tsui, along the west of the MTR Tsuen Wan Line to
a landfall at the seafrontage north of the Wan Chai West Sewage Screening
Plant, near Lung King Street. The reclamation works could potentially
damage the watermains and diversion
of these mains will be necessary.
The total dredged volume for the construction of the cross-harbour
watermain is estimated to be approximately 0.06Mm3. As dredging for the installation of the
new cross harbour watermains will be carried out less than 100m from a seawater intake, it is
classified as DP under Schedule 2, Part I, C.12. The location of this DP6 is shown in Figure 1.2f.
1.5.4
Apart
from DP4 (temporary typhoon shelter), the original schemes of the Schedule 2
DPs in Table 1.1 have been previously assessed in the approved EIA
Reports for the WDII and/or CWB & IEC.
As the original schemes
for the DP5 (Wan Chai East Sewage Outfall) and DP6 (Dredging for the Cross-harbour Water Mains from Wan Chai to
Tsim Sha Tsui) have not changed materially, the related EIA assessments of the approved EIA Report for these works remain valid. This EIA study therefore focuses mainly on those elements of the Project, including the
Schedule 2 DP’s 1, 2, 3 and 4,
that have changed significantly from the schemes as presented in the approved
EIA Reports. For DP5 and DP6, this EIA Study has
still included the cumulative impact assessment, updated the assessment
assumptions and the corresponding mitigation measures.
1.5.5
The
detailed EIA for the Project (ie the Schedule 3 DP) as well as separate
presentation of the EIAs for individual Schedule 2 DPs (DP1 to DP6 above) are
presented in the EIA Report for WDII and CWB. This Executive Summary presents a
summary of the key findings of the EIA for the Project.
2.1.1
The
Project is located mainly in Wan Chai, Causeway Bay
and North Point, and is demarcated by Gloucester
Road and Victoria
Park Road to the south, Fenwick Pier Street to the west and Tong
Shui Road Interchange to the east, as shown in Figure 1.1.
2.1.2
The
study area encompasses existing developments along the Wan Chai, Causeway Bay and North Point shorelines. Major land
uses include the HKCEC Extension, the Wan Chai Ferry Pier, the ex-Public Cargo
Working Area (ex-PCWA), the Royal Hong Kong Yacht Club (RHKYC), the Police
Officers' Club, the CBTS and commercial and residential developments.
Project
Requirements
2.2.1
The
basis of the WDII project and the core transport infrastructure for which the
project provides is the Trunk Road.
The Trunk Road is defined from the connection with the existing Rumsey
Street Flyover in Central, through to a connection with the existing IEC to the
east of the CBTS. At the Rumsey
Street Flyover connection, a Central Interchange will provide connections into
the Central area, and then the Trunk Road will drop down into tunnel and run
along the Central shoreline, through CRIII, to the WDII project area. In WDII, the Trunk Road will continue in
tunnel until it needs to rise onto elevated flyover structure to connect with
the elevated IEC. The section of
the Trunk Road that runs in tunnel through CRIII and WDII is also known as the
CWB, whilst the section of the Trunk Road on flyover, for the connection with
the IEC, is also known as the IECL.
2.2.2
The
Trunk Road will form an east-west strategic route through Central and Wan
Chai. The Trunk Road is an essential
element of Government’s strategic transport planning for Hong Kong; it is the
“missing link” in the strategic highway running along the northern part of Hong Kong Island. The Trunk Road is required to provide
relief to the existing major east-west route (Connaught Road Central – Harcourt Road – Gloucester Road).
2.2.3
The
Trunk Road was originally proposed under the Central and Wanchai Reclamation
Feasibility Study, completed in 1989, where its feasibility was
established. The need for the Trunk
Road was reaffirmed in the WDIICFS, completed in 2001, which demonstrated an
urgent need for the link to be put in place in order to relieve the existing
and growing congestion along the east-west corridor of Hong Kong Island North. A number of strategic traffic studies
have also confirmed the need to improve the flow of the east-west traffic
through Central and Wan Chai, including the Long Term Road Study completed in
1968 and the First, Second and Third Comprehensive Transport Studies (CTS)
completed in 1976, 1989 and 1999 respectively. A recent rerun of the CTS-3 transport
model also confirmed the need for the CWB despite changes in land use planning
assumptions and population projections.
2.2.4
Following
the 9 January 2004 CFA ruling on compliance with the PHO, the compelling and
present need for the Trunk Road to meet the transport needs of the community
within a reasonable and definite planning time frame, and to meet the social
and economic needs of the community, was established under the CRIII project,
and is presented in “A Review of Central Reclamation Phase III by applying the
Court of Final Appeal’s “Overriding Public Need Test”, April 2004”.
2.2.5
Under
the WDII project, the compelling and present need for the Trunk Road has also
been confirmed. Reference can be
made to the “Report on Cogent and Convincing Materials to demonstrate
Compliance with the Overriding Public Need Test, February 2007”.
2.2.6
Apart
from providing land for key transport infrastructure and reprovisioned
waterfront facilities, the Project can also create a coherent pattern of land
use and provide for the development of an appropriate waterfront ‘edge’ to the
existing urban area.
Project
Scope
2.2.7
The
scope of the Project comprises:
(i)
Land
formation for key transport infrastructure and facilities, including the Trunk
Road (CWB) and the associated slip roads for connection to the Trunk Road and
for through traffic from Central to Wan Chai and Causeway Bay. The land formed for this transport
infrastructure will provide opportunities for the development of an attractive
waterfront promenade for the enjoyment of the public.
(ii)
Reprovisioning / protection of the existing facilities
and structures affected by the land formation works.
(iii)
Extension, modification, reprovisioning or protection of
existing storm water drainage outfalls, sewage outfalls and watermains affected
by the revised land use and land formation works.
(iv)
Upgrading of the hinterland storm water drainage
system and sewerage system, which would be rendered insufficient by the land
formation works.
(v)
Provision of ground level roads, road bridges,
footbridges, necessary transport facilities and associated utility services.
(vi)
Construction of the new waterfront promenade,
landscape works and the associated utility services.
(vii)
The
Trunk Road (i.e. CWB) within the study area and the associated slip roads for
connection to the Trunk Road.
2.3.1
The
Project construction works are anticipated to commence on site in early 2009,
with completion of the project by 2016.
2.4.1
The
following projects are related to the WDII project:
(i)
Civil Engineering and Development Department’s CRIII
project, comprising reclamation along the Central waterfront for transport
infrastructure needs (including CWB) and basic land use requirements. A section of CWB tunnel will also be
constructed under CRIII project.
Construction started in February 2003 and is scheduled for completion in
September 2012.
(ii)
Trade Development Council’s Atrium Link Extension
project, comprising a link bridge spanning across the water channel between the
HKCEC Phase I and HKCEC Extension.
Construction started in May 2006 and is scheduled for completion in
March 2009.
3.1.1
The
following paragraphs summarise the nature and extent of the key environmental
impacts and outcomes arising from the construction and operation of the Project
and related activities taking place concurrently. Details of the environmental impact
assessment of the Project including the recommended mitigation measures, as
well as separately presented findings for the individual Schedule 2 DPs, are
provided in the EIA Report for WDII and CWB. Section 3.12 of this Executive Summary
also provides a summary of key environmental impacts avoided and protection and
benefits afforded to sensitive environmental resources and populations.
Construction
Phase
3.2.1
During
construction, reclamation filling and surcharging have been identified as the
major dust sources. Trunk Road
tunnel works would also generate dust.
Due to the complex sequencing of the construction activities, six worst case scenarios of the construction
schedules have been identified and assessed. The findings of the construction phase
air quality assessment indicate that no exceedences of the 1-hour and 24-hour
total suspended particulates (TSP) criteria are predicted at air sensitive
receivers (ASRs) in the vicinity of the construction sites. In order to ensure compliance with the
TSP criteria at the ASRs at all times, the dust suppression measures and requirements
of the Air Pollution Control (Construction Dust) Regulation shall be adhered to
during the construction period. In
addition, a comprehensive dust monitoring and audit programme are recommended
to ensure
the effective implementation of dust suppression measures.
Operational
Phase
3.2.2
The
cumulative air quality impacts arising
from the background pollutant levels within and adjacent to WDII, vehicle
emissions from open road networks, tunnel portal and ventilation building emissions
from the Trunk Road, tunnel portal emissions from the Cross Harbour Tunnel and portal emissions from existing
underpasses and planned deckovers, have been assessed. Results show that the predicted 1-hour and
24-hour average nitrogen
dioxide (NO2) concentrations and 24-hour average respirable suspended particulates (RSP) concentrations at the ASRs would comply with the AQO
criteria. No mitigation measures
are required. The air quality
inside the tunnel section of Trunk Road and planned deckovers
at the HKCEC Atrium Link, Road P2 and Expo
Drive would also comply with the Environmental
Protection Department’s (EPD’s) in-tunnel air quality standards.
3.2.3
With
the Trunk Road tunnel ventilation system designed for zero portal emission at
the eastern portal, at North Point, potential air quality impacts from the
tunnel portal emission would be avoided.
In addition, the air quality at the eastern portal area would be
enhanced by locating the vent shaft at the end of the eastern breakwater of the
CBTS and by the introduction of an electrostatic precipitator system at the East Ventilation
Building to screen RSPs
from the tunnel emissions.
3.2.4
During
operational phase, this Project will not create any new odour source. However,
odour nuisance associated with the CBTS is an existing environmental
problem. In order to improve the
environment, this Project will take the opportunity to mitigate the potential
sources of odour nuisance within the Project area so as to alleviate this
existing environmental problem, as well as to provide an acceptable environment
for the future land uses within the project area. Enhancement measures have been
formulated to alleviate this existing odour problem. These include rectification of expedient
connections, regular collection of floating debris, dredging to remove the
polluted and odourous sediments at the corner of CBTS and clean up the slime
attached on CBTS seawall. With the
implementation of these enhancement measures, the predicted odour levels in the
vicinity of CBTS would be reduced significantly. In other words, this Project
will alleviate the existing odour problems in the vicinity of CBTS to a large
extent by implementing the proposed enhancement measures. However, some
exceedances of the odour criterion are still predicted at planned ASRs at the
northern breakwater of the CBTS and the marine recreational area at the Wan
Chai waterfront (ex-PCWA basin), under the worst case conditions. Nevertheless, the residual odour impact at
these planned ASRs is not persistent, with a time of exceedance of the odour
criterion expected to be less than 0.2% of time in a year. In view of this
infrequent likelihood of occurrence, no unacceptable adverse odour impact would
be expected at the planned ASRs within the study area.
3.3
Noise
Construction Phase
3.3.1
The construction noise impacts of the Project during
normal daytime working hours have been assessed, taking into account other
concurrent projects including the CRIII and HKCEC Atrium Link Extension
projects.
3.3.2
With the implementation of noise mitigation measures
such as the use of quiet powered mechanical equipment (PME), movable and
temporary noise barriers, PME grouping, together with the implementation of
noise mitigation measures proposed in the CRIII project, the noise levels at the noise sensitive receivers (NSRs), except for some NSRs in North Point, would comply with
the construction noise standards.
3.3.3
In
North Point, it is expected that the predicted noise level at Mayson Garden
would exceed the noise standard of 75 dB(A) for 1 month by 10 dB(A), while at Harbour Heights the predicted noise level would exceed the noise
standard of 75 dB(A) by up to 5 dB(A) for a total of 8 weeks. At City
Garden, the predicted
noise level would exceed the noise standard of 75 dB(A) by up to 9 dB(A) for a
total of 16 weeks. At the Hong Kong Baptist Church
Henrietta Secondary
School, the predicted noise level would exceed
the noise standard for examination periods of 65 dB(A) by up to 12 dB(A) for a
total of 28 weeks in 2009, 2013 and 2015.
Noise levels would exceed the noise standard of 70 dB(A) for normal
teaching periods by 7 dB(A) for 13.5 weeks. However, the school has been noise
insulated with air conditioners and, by keeping the windows closed during
construction activities, noise impacts at the indoor environment can be
avoided. Whilst the impact
assessment does indicate some noise exceedances for limited periods of time,
during the actual construction period as much as practically possible would be
done to reduce construction noise still further, and there will be on-going
liaison with all concerned parties and site monitoring to deal with and
minimise any exceedances.
Operational Phase
3.3.4
The
potential road traffic noise impacts have been assessed based on the worst case
traffic flows in 2031. NSRs in Wan
Chai, Causeway Bay, Tin Hau and North Point are
expected to be affected by exceedances of EIAO-TM traffic noise criteria. Direct mitigation measures have been
proposed for the noise impacts at NSRs in North Point (Victoria Centre, Harbour
Heights, City Garden, Hong Kong Baptist Church Henrietta Secondary School) and
planned NSRs near Oil Street where ‘new’ road noise levels (in this case
arising from the reconstruction of the IEC at the connection with the Trunk
Road) would exceed the relevant noise criteria and ‘new’ road noise
contributions to the overall noise levels would be more than 1.0 dB(A).
3.3.5
With
the proposed noise semi-enclosure, cantilevered noise barrier and vertical
noise barrier in place at these reconstructed sections of the IEC, the
predicted overall noise levels at Harbour Heights, City Garden and planned NSRs
near Oil Street would be in the range of 51 to 66 dB(A) which would comply with
the noise limit of 70 dB(A). For
all other affected NSRs, the ‘new’ road noise contributions to the overall
noise levels would be less than 1.0 dB(A) and the ‘new’ road noise levels would
all be below the relevant noise criteria, although the overall noise criteria
would still be exceeded. However,
it should be noted that such noise exceedances at these NSRs are due to the
existing roads, not the ‘new’ roads.
Nevertheless, there will be an overall reduction of noise brought about
by the Project, which may be considered an environmental benefit.
3.3.6
For
noise mitigation at the proposed site of the reprovisioned floating Tin Hau Temple, at the south-east corner of the CBTS, a 2.5m
high boundary wall along the southern and eastern boundary of re-provisioned Tin Hau
Temple has been examined
for its noise reduction effectiveness.
However, in view of the traditional design of a Tin Hau Temple, it would not be considered
desirable to erect a boundary wall along the western boundary of the temple, as
this would block the seaview. With the southern and eastern boundary wall in
place but without the western boundary wall, the predicted noise levels at the
temple would still exceed EIAO-TM noise limit of 65 dB(A) by 4 dB(A) due to the
existing roads. Instead of a
western boundary wall, the openable windows of the temple should rather be
orientated so as to avoid direct line of sight to the existing Victoria Park Road
as far as practicable. An
indicative layout for the temple has demonstrated that the traffic noise
criterion would be met with proper orientation of the sensitive façade. The project proponent of the temple will
need to take into account such environmental requirements/constraints and
review the mitigation measures during the detailed design of the temple with a
view to eliminating the need for the boundary wall.
3.3.7
No
adverse impacts in respect of the Noise Control Ordinance (NCO) and the EIAO-TM
noise criteria arising from the operation of the proposed permanent helipad and
fixed noise sources including ventilation buildings and the reprovisioned Wan
Chai North Public Transport Interchange (PTI) are anticipated at existing and
planned NSRs.
3.4
Hydrodynamics
and Water Quality
Construction Phase
Marine-based Impact
3.4.1
The
water quality impacts during the reclamation of WDII and CWB have been
quantitatively assessed by numerical modelling. Suspended sediment is identified as the
most significant water quality parameter during the reclamation. The worst-case scenarios during
reclamation, taking into account the anticipated reclamation stages and possible
overlapping dredging and filling activities, have been assessed. The assessment also takes into account
the cumulative effects that arise from other concurrent marine works in the
Harbour. It is predicted that
potential water quality impacts could occur at seawater intakes along the
Central and Wan Chai shorelines and in the CBTS. However, the water quality impacts at
the seawater intakes can be effectively minimised with the implementation of
proposed mitigation measures, which include silt curtains around the dredging
operations, silt screens at the intakes, restricted dredging rates and bulk
filling behind constructed seawalls.
With the implementation of these mitigation measures, there would be no
unacceptable residual water quality impacts due to the WDII and CWB reclamation
and due to the cumulative effects from other concurrent reclamation
activities. A water quality
monitoring and audit programme will be implemented to ensure the effectiveness
of the proposed water quality mitigation measures.
Land-based Impact
3.4.2
Water
quality impacts from land-based construction, including road works, waterfront
facilities and public utilities, are associated with surface runoff and
effluent discharge from the site.
Impacts can be controlled to comply with statutory standards by
implementing mitigation measures such as on-site drainage and sediment traps to
control run-off. No unacceptable
residual impact on water quality is anticipated.
Operational Phase
3.4.3
An
assessment of the hydrodynamic and water quality impacts due to the Project has
been carried out by numerical modelling, taking into consideration all other
concurrent developments and water pollution sources. For both hydrodynamics and water
quality, the baseline (without the WDII and CWB reclamation) and operational
phase (with the WDII reclamation) simulations have been compared. The model results indicate that the WDII
and CWB reclamation would have minimal impact on the hydrodynamic regime of the
study area. The model results also
suggest that the levels of pollutants near Wan Chai and the neighbouring areas
are similar under both baseline and operational scenarios. No unacceptable impacts associated with
the operation of the WDII project upon the water quality in Victoria Harbour
are therefore anticipated.
3.4.4
The
key water quality issue in relation to the operation of the CWB would be the
potential oil-contaminated surface road runoff and tunnel seepage. However, the CWB will be designed with
adequate drainage systems and appropriate oil interceptors, as required, and no
adverse water quality impact is therefore expected.
3.5.1
The
total volume of dredged sediments for the WDII reclamation is estimated to be
approximately 1.15 Mm3. A review of the sediment quality data
from the marine ground investigation works indicates that some 0.75 Mm3 of the marine
sediments to be dredged for the WDII and CWB reclamation would be classified as
Category M and H (i.e. high levels of contaminants). The contaminated marine sediments will
therefore not be suitable for open sea disposal. However, with the implementation of
mitigation measures in accordance with the requirements of Environment and
Transport Works Branch Technical Circular ETWB TCW No. 34/2002, and confined
disposal to the designated contaminated mud pits depending on their levels of
contamination after consultation with the Marine Fill Committee (MFC) and EPD,
where appropriate, no residual adverse impact is predicted. The contaminated marine sediments would
be disposed of at confined marine disposal facilities at East of Sha Chau or
other disposal sites after consultation with the MFC and EPD.
3.5.2
In the
CBTS, dredging of highly contaminated Category H sediment (approximately 0.05 Mm3) will be
required. Containment of these
contaminated sediments in geosynthetic containers before disposal at the
designated contaminated mud pits is proposed to prevent release of contaminants
to the marine environment.
3.5.3
Wastes
generated by construction activities will include construction and demolition
(C&D) materials (including excavated material), general refuse and chemical
waste. The quantity of C&D
materials generated is estimated to be approximately 2.915Mm3 of which around 1.17Mm3 will be reused
on-site and the remaining surplus of around 1.745Mm3 will be disposed
off-site. Provided that these
identified waste arisings are handled, transported and disposed of using
approved methods and that recommended good site practice are strictly followed,
adverse environmental impacts are not anticipated. The C&D materials should be sorted
on-site into inert C&D material (ie public fill), for reuse in the
reclamation, and C&D waste for recycling or disposal.
3.6.1
The
potential land contamination impacts in the study area resulting from the
planned development have been examined.
No land contamination impacts are expected during the operational phase
of the development, however, there would be land contamination concerns
associated with handling contaminated soil by construction workers at A King
Marine shipyard.
3.6.2
A site
investigation has been carried out at the A King Marine shipyard site under
this EIA study. Based on the
analytical results, exceedances in heavy metals and total petroleum
hydrocarbons (TPH) were identified and an estimated 633m3 of contaminated soil (mainly heavy
metals) would require remediation.
A Remediation Action Plan (RAP) has been drawn up to formulate the
necessary remedial measures; cement solidification / stabilisation and landfill
disposal are proposed as the soil remediation methods. Mitigation measures for the remediation
works have been proposed and, with the proper implementation of these
mitigation measures, no adverse land contamination impacts are
anticipated. After the completion
of appropriate remediation actions, contaminated areas at A King Marine shipyard
site would be cleaned up to acceptable standards and no adverse residual impact
is envisaged.
3.7.1
The
impacts on the existing sewerage system in the study area resulting from the planned
development have been assessed.
Findings indicate that the sewage from the planned development would
have no adverse impact on the existing local sewerage system. For the connections to the trunk sewer,
sufficient allowance has been made in the design of existing deep trunk sewer
system and no modification work is required. Reprovisioning of the existing Wan Chai
East Sewage Outfall will be required as a result of the WDII reclamation and
this sewage outfall will be upgraded under the WDII project to cope with the
future design flows.
3.8.1
Literature
reviews of existing information supplemented with the results of recently
undertaken field surveys on marine ecological resources indicate that
identified marine habitats within the study area are of low ecological
value. There are no ecological
sensitive receivers, such as Sites of Special Scientific Interest (SSSIs) and
Marine Parks and / or Reserves or other areas of ecological importance or conservation
interest, in and within the immediate vicinity of the study area.
3.8.2
The
Project will result in the permanent loss of approximately 12.7 ha of soft bottom benthic and
subtidal habitats. Considering that
the benthic, intertidal and subtidal habitats within the affected area are of
very low ecological value, and as direct impacts on some small and isolated
coral colonies attached to movable boulders would be avoided by translocation,
no adverse direct ecological impact is expected.
3.8.3
Indirect
disturbance impact on the associated waterbirds and other avifaunal species of
conservation interest in the CBTS and Victoria Harbour
was expected to occur during the construction and operation phases of the
Project. Considering the existing background of intense human activities in
these areas, the affected avifauna are considered already well adapted to human
disturbance and therefore no adverse indirect impact is expected to occur.
3.8.4
Other
impacts arising from the Project would be temporary and minimised with
implementation of proper mitigation measures. Overall, no adverse ecological impacts on
marine resources are anticipated.
3.9.1
The
proposed development and associated works follow in principle the planning
intentions of the Visions and Goals for Victoria Harbour
prepared by Town Planning Board and the views of the public received during the
engagement exercises of the HER that was carried out under the steer of HEC
Sub-committee on WDII Review. In
response to the CFA judgement on the PHO, the extent of reclamation has been
reduced to the minimum. With the
new waterfront development proposals together with enhanced connectivity to the
waterfront from the hinterland and east-west linkages along the northshore, the
landscape planning framework of the waterfront from Wan Chai to North Point is
strengthened and reinforced by the proposed project.
3.9.2
Approximately
12.7 ha (1.8% of total 700 ha harbour area) of Victoria Harbour
will be permanently lost under the proposed land formed for the construction of
the Trunk Road. CBTS will be
temporarily alienated for the construction of the Trunk Road tunnel. The temporary reclamation will be
removed and sea-bed reinstated after the completion of the tunnel
construction. A temporary typhoon
shelter with mooring area of approximately 4
ha will be constructed in Victoria Harbour
just outside the existing typhoon shelter.
It is considered that the residual landscape impacts on Victoria Harbour are moderate during construction
phase but slight during operation phase with implementation of mitigation
measures.
3.9.3
Under
the proposed development, Fenwick Pier Street Public Open Space will be
temporarily affected during the construction stage. In the longer term, this open space will
be permanently lost for the development of the Hong Kong Academy of Performing
Arts Extension. Approximately 0.24 ha of Victoria Park will be
permanently lost for the construction of Slip Road 8 of the Trunk Road. Alternative schemes of Slip Road 8 and
reprovisioning options of affected facilities in Victoria Park, including a bowling green, have been
examined to minimise the intrusion into the Victoria Park and minimise the
impacts. Construction works will temporarily affect the operations of the
CBTS. During the construction
phase, therefore, there will be substantial negative impacts on the Fenwick
Pier Street Public Open Space landscape character and on the CBTS landscape
character, and moderate residual impact on Victoria Park. Under the proposed development,
approximately 13.8 ha
of new waterfront open space will be provided to strengthen the existing
landscape framework from Central to North Point. It is considered the proposed
development with mitigation measures will not create adverse impact to open space
framework and have positive impact to the waterfront from Central to North
Point.
3.9.4
It is
estimated that approximately 571 trees will be affected by the construction of
Road P2, Slip Road 8, the reprovisioning of bowling green
and the landscaped deck connecting
Victoria Park to the Causeway
Bay waterfront, the HKAPA
Extension, the HK Visual Arts Education Centre and the helipad. None of these are Champion Trees or
Registered Old and Valuable Trees.
There are no rare or endangered species; all trees are common
species. All trees with high
amenity value which are unavoidably affected by the works will be transplanted
where possible. Detailed tree
preservation, transplanting and felling, including compensatory planting
proposals, will be submitted to relevant government departments for
approval. New trees will be planted
along roadside amenity areas and along the new waterfront to compensate for the
loss of existing trees.
3.9.5
The
proposed Trunk Road consists primarily of a road tunnel, administration
building, Central Ventilation Building,
eastern tunnel portal, East
Ventilation Building
and an associated exhaust vent shaft at the eastern breakwater of CBTS. At the eastern end, the Trunk Road rises
on flyover structure to connect with the existing IEC. Most of the Trunk Road is underground or
underneath the CBTS and there will not be significant visual or landscape
impacts. The eastern tunnel portal
will be covered by a landscaped deck with lush planting. The noise barriers/semi-enclosures on
the IEC will mainly compose of transparent noise barrier panels above and green
panels below. Amenity planting will
provided along the eastbound and westbound of IEC with vertical greening of
noise barriers/semi-enclosures for around 3m
above the planter to soften the structures. The location of the administration
building is selected at the least prominent location along the available
waterfront area; it is proposed at a location underneath the elevated IEC and
climbers will be planted on the building façade to soften the structure.
3.9.6
The Central Ventilation
Building, East Ventilation
Building and its
associated exhaust vent shaft will be the main source of impact. These buildings will be structures with
compatible disposition, form and finishing which match with the future harbour
environment to achieve visual conformity.
Tree and shrub planting is proposed to soften the Central
Ventilation Building
and East Ventilation Building. The location of the East Ventilation
Building at the north of the FEHD Whitfield Depot and at the west end of the
North Point reclamation area has been selected in order to increase the
distance to the nearby residents as far as practicable. The building height has been minimised
by placing some E&M equipment in a basement. The overall height of the building will
be lower than the adjacent existing IEC elevated road. The exhaust of the East
Ventilation Building
has been separated from the East
Ventilation Building
and extended to the tip of the eastern breakwater of CBTS to further increase
the distance to the residents. The vent shaft will be a
structure with compatible disposition, form, colour and finishing to create a
harmonious visual relationship with the Harbour. Finishing materials will be sensitively
designed in form, basic color, color/tone variation, micro- and macro-texture,
and reflectivity/light absorbance to avoid glare. The maximum height of the vent shaft will be
restricted to +25mPD.
3.9.7
With
implementation of mitigation measures during construction, there will be some moderate
negative visual impacts on visually sensitive receivers (VSRs) in the front row
of high rise buildings along the waterfront from Central to North Point. Residual impacts on VSRs further away
from Victoria Harbour and in the hinterland will
become slight or insubstantial.
During operation, there will be substantial to moderate positive visual
impact on VSRs along the new waterfront as the landscape and visual amenity are
generally enhanced and strengthened by the proposed project. The visual impacts from the hinterland
and from the harbour will be slight or insubstantial.
3.9.8
Under
the proposed scheme, there will be a significant area of new open space (13.8 ha) and a substantial number of new
trees and other proposed planting (approximately 1500 new trees will be planted
in the new waterfront and along roadside amenity areas after the new open space
is built to compensate the felled trees).
The existing landscape characters along the waterfront will be
enhanced. There will still be
slight residual visual impact due to the provision of noise
barriers/screening/semi-enclosures in North Point. However, there will be significant area
of new waterfront open space from Tin Hau to Oil Street with at-grade pedestrian
connection to North Point. Therefore, overall, it is considered that the
residual landscape and visual impacts of the proposed development and the
associated designated projects are considered acceptable with mitigation
measures during construction, acceptable with mitigation measures during
operation up to10 years and beneficial with mitigation in the long run after 20
to 30 years.
3.10
Cultural
Heritage
3.10.1
A
marine archaeological investigation has been carried out for the seabed that
will be affected by the reclamation under the Project. It is concluded that there are no marine
archaeological resources within the study area. It follows that there are no related
constraints on the proposed development, and there is no need for any further
archaeological investigation or mitigation measures.
3.11.1
Environmental
monitoring and audit are recommended for construction stage dust, noise, water
quality and marine ecology, to check compliance with relevant statutory criteria
and to ensure the effectiveness of the mitigation measures. Site inspection and audit are also
recommended for waste management during construction and for implementation of
landscaping measures during operation.
Details of the recommended mitigation measures, monitoring procedures
and locations are presented in a stand-alone Environmental Monitoring and Audit
(EM&A) Manual. This will enable
the Contractor to have early warning and provide necessary action to reduce
impacts at specific areas if the critical assessment criteria are
approached. The effectiveness of
on-site control measures would also be evaluated through a monitoring
exercise. All the recommended
mitigation measures will be incorporated in an EM&A programme during
implementation.
3.12.1
The
key benefit associated with the Project is that the provision of land required
for the construction of the Trunk Road will provide the opportunity to create
an attractive waterfront for the enjoyment and benefit of the public. Environmental benefits arising from the
Project include:
·
The
Project will take the opportunity to mitigate the potential sources of odour
nuisance within the Project area so as to alleviate this existing environmental
problem as well as to provide an acceptable environment for the future land
uses within the project area. Enhancement measures have been formulated to
alleviate this existing odour problem.
With the implementation of these enhancement measures, the existing
odour impact would be reduced significantly.
·
Landscaped decks, noise semi-enclosures and barriers
will be installed at the reconstructed IEC at the connection with the Trunk
Road. Road traffic noise along the future IEC at North Point area will be
reduced. The landscaped deck over the east tunnel portal area of the Trunk Road
provides both visual and noise screening effect to the nearby sensitive
receivers.
·
Air
quality at the east tunnel portal area would be enhanced by the introduction of
an electrostatic precipitator system into the tunnel ventilation exhaust system
and zero portal emission design of the eastern tunnel portal.
·
There
will be substantial to moderate positive landscape and visual impact along the
new waterfront as the landscape and visual amenity are generally enhanced and
strengthened by the Project.
4.1.1
The
findings of this EIA have provided information on the nature and extent of
environmental impacts arising from the construction and operation of the Project. The EIA has, where appropriate,
identified mitigation measures to ensure compliance with environmental
legislation and standards.
4.1.2
Overall,
the EIA for WDII and CWB has predicted that the Project will generally comply
with environmental standards and legislation after the proposed construction
and operation stage mitigation measures are implemented. This EIA has also demonstrated the
general acceptability of the residual impacts from the Project and the protection
of the population and environmentally sensitive resources. Environmental monitoring and audit
mechanisms have been recommended before and during construction and operation,
where necessary, to verify the accuracy of the EIA predictions and the effectiveness
of recommended mitigation measures.