14 EIA Findings and Recommendations
14.2 DP1 –Central-Wanchai Bypass including
its road tunnel
14.3 DP2 –WDII major roads (including Road
P2)
14.4 DP3 – Reclamation works including
associated dredging works
14.5 DP4 –Temporary typhoon shelter
14.6 DP5 –Wan Chai East Sewage Outfall
14.7 DP6 –Cross harbour Water Mains from
Wan Chai To Tsim Sha Tsui
List of Tables
Table 14.1 Summary
of EIA Impacts and Recommendations for DP1
Table 14.2 Summary
of EIA Impacts and Recommendations for DP2
Table 14.3 Summary
of EIA Impacts and Recommendations for DP3
Table 14.4 Summary
of EIA Impacts and Recommendations for DP4
Table 14.5 Summary
of EIA Impacts and Recommendations for DP5
Table 14.6 Summary
of EIA Impacts and Recommendations for DP6
·
DP1- Central-Wanchai Bypass including its road
tunnel (Items A.1 and A.7 of Part I of Schedule 2 of the EIAO)
·
DP2 -
WDII major roads (including Road P2) (Item A.1 of Part I of Schedule 2 of the
EIAO)
·
DP3 -
Reclamation works including associated dredging works (Item C.1 of Part I of
Schedule 2 of the EIAO)
·
DP4 - Temporary
typhoon shelter (Item C.5 of Part I, Schedule 2 of the EIAO).
·
DP5 -
Wan Chai East Sewage Outfall (Items F
·
DP6 -
Cross-harbour Water Mains from Wan Chai to Tsim Sha Tsui (Item C.12 of Part I of Schedule 2 of
the EIAO); and
Table 14.1 Summary
of EIA Impacts and Recommendations for DP1
Issue |
Environmental Issues |
Mitigation Measures and Recommendation |
Residual Impact |
||||||||||||||||||||||||||
Air Quality Impact |
Potential air quality impacts are: dust nuisance from wind erosion, construction
of CWB and filling activities during reclamation and gaseous emissions from
the construction plant and vehicles.
|
CWB works inside WDII area Implement the Air Pollution Control (Construction Dust) Regulation
and good site practices by Contractor |
Unacceptable
impacts are not expected
|
||||||||||||||||||||||||||
|
|
Four times daily watering of the works site with active operations by
Contractor. |
|
||||||||||||||||||||||||||
|
|
CWB works at outside WDII area |
|
||||||||||||||||||||||||||
|
|
The mitigation measures and recommendation stated
in the approved CWB&IECL EIA Report remain valid and are restated in
below. |
|
||||||||||||||||||||||||||
|
|
Strictly limit the truck speed on site to
below |
|
||||||||||||||||||||||||||
|
|
Watering during excavation and material handling; |
|
||||||||||||||||||||||||||
|
|
Provision of vehicle wheel and body washing facilities at the exit points of the site, combined with cleaning of public roads where necessary; and |
|
||||||||||||||||||||||||||
|
|
Tarpaulin covering of all dusty vehicle loads transported to, from and between site locations. |
|
||||||||||||||||||||||||||
|
Portal and Ventilation Emission from the CWB tunnel in the WDII area during operation
phase:
Note: #
Electrostatic precipitator will be installed, dust removal efficiency is
80%. The preliminary design of the East and |
No mitigation required. |
Unacceptable impacts are not expected |
||||||||||||||||||||||||||
|
Since there is no increase of
portal emission at the Trunk Road
western portal than that stated in the approved CWB&IECL EIA Report, the predicted impacts stated in
the approved EIA report are still valid.
Adverse impacts due to portal emission at Trunk Road Westbound are not anticipated. |
|
|
||||||||||||||||||||||||||
|
Overall, predicted results
show that no operation air quality impact is expected. |
|
|
||||||||||||||||||||||||||
Noise Impact |
With the implementation of the mitigation measures, the cumulative
construction noise levels at the NSRs selected for construction noise impact assessment except
N11, N17, N18 and N20 are predicted to comply with the noise standards
stipulated in the EIAO-TM. The
on-site survey has revealed that NSR N20 ( |
CWB works inside WDII area |
Residual noise
impact is predicted at N17, N18 and N20 due to demolition of structure,
construction of superstructure and retaining structure
Residual noise
impact is predicted at N20 during examination periods due to demolition of
structure and construction of
substructure
Residual noise impact
is predicted at N11 due to at-grade road construction
|
||||||||||||||||||||||||||
|
Implement good site practice by Contractor. |
||||||||||||||||||||||||||||
|
Use of quiet powered mechanical equipment
(PME), movable noise barrier and/or temporary noise barrier for the following
tasks: |
||||||||||||||||||||||||||||
|
·
Slip road 8 tunnel |
||||||||||||||||||||||||||||
|
·
Diaphragm wall construction |
||||||||||||||||||||||||||||
|
·
Excavation |
||||||||||||||||||||||||||||
|
·
Construction of tunnel top and bottom slabs |
||||||||||||||||||||||||||||
|
·
Backfilling |
||||||||||||||||||||||||||||
|
·
Demolition of structure |
||||||||||||||||||||||||||||
|
·
Construction of IEC (substructure, superstructures and retaining structures) |
||||||||||||||||||||||||||||
|
·
Construction of ventilation buildings (foundation and superstructures) |
||||||||||||||||||||||||||||
|
|
Use of quiet PME grouping
for the following tasks: |
|||||||||||||||||||||||||||
|
|
·
At-grade road construction |
|||||||||||||||||||||||||||
|
|
·
Substructure for IECL connection |
|||||||||||||||||||||||||||
|
|
CWB works outside WDII area |
|||||||||||||||||||||||||||
|
|
The following mitigation measures and
recommendations as stated in the approved CWB&IECL EIA Report would still be
valid: |
|||||||||||||||||||||||||||
|
|
·
Adoption of quiet PME |
|||||||||||||||||||||||||||
|
|
·
Use of movable noise barriers |
|||||||||||||||||||||||||||
|
|
· Reduction in number of PME and PME percentage on-time. |
|
||||||||||||||||||||||||||
|
Unmitigated traffic noise levels are in the range of 60 to 87 dB(A). With implementation of mitigation measures, road traffic noise impact due to new roads is not expected. |
Noise mitigation measures for traffic noise include: ·
about
|
Not
expected |
||||||||||||||||||||||||||
|
|
·
about
|
|
||||||||||||||||||||||||||
|
|
·
about
|
|
||||||||||||||||||||||||||
|
|
·
about
|
|
||||||||||||||||||||||||||
|
|
·
about
|
|
||||||||||||||||||||||||||
|
|
· low noise road surfacing for the trunk road (except tunnel section and beneath the landscaped deck at the eastern portal area) with speed limit of 70 km/hour |
|
||||||||||||||||||||||||||
|
|
·
the openable windows of the
re-provisioned |
|
||||||||||||||||||||||||||
|
Operation of the proposed ventilation buildings
will not impose adverse noise impacts on the existing and planned NSRs. |
No specific noise mitigation measures other than silencers would be required. |
Not expected |
||||||||||||||||||||||||||
Water Quality Impact |
General construction activities associated with the land-based construction works could lead to site runoff containing elevated concentrations of SS and associated contaminants that may enter into the marine water. However, it is anticipated that the water quality impacts will generally be temporary and localised during construction. Therefore, no unacceptable residual water quality impacts are expected during the construction of the proposed infrastructure, provided all of the recommended mitigation measures are implemented and all construction site / works area discharges comply with the TM-DSS standards. |
Mitigation measures outlined in
EPD's Practice Note for Professional Persons, Construction Site Drainage
(ProPECC PN 1/94) should be followed.
|
Not expected
|
||||||||||||||||||||||||||
|
It is considered that impacts resulting from the operation of CWB, in terms of water quality, will be minimal and similar for both the elevated and tunnel sections of the route. Surface runoff from slip-roads and elevated structures may be contaminated by oils leaked from passing vehicles, and tunnel seepage would potentially be contaminated to the same extent. It is considered that impacts upon water quality will be minimal provided that the tunnel and elevated sections of the CWB are designed with adequate drainage systems and appropriate oil interceptors, as required. Adverse water quality impacts associated with the
operation of CWB are not expected.
Thus, there will be no residual impact associated with the operation
of the CWB.
|
The mitigation measures during operation phase
stated in the Approved CWB&IECL EIA Report are still valid. Mitigation measures for this DP are
summarized below. A surface water drainage system would be provided
to collect road runoff. The
following operation stage mitigation measures are recommended to ensure road
runoff would comply with the TM under the WPCO: · The drainage from tunnel sections shall be directed through petrol interceptors to remove oil and grease before being discharged to the nearby foul water manholes. |
Not expected |
||||||||||||||||||||||||||
|
·
Petrol
interceptors shall be regularly cleaned and maintained in good working
condition. |
|
|||||||||||||||||||||||||||
|
·
Oily
contents of the petrol interceptors shall be properly handled and disposed
of, in compliance with the requirements of the Waste Disposal Ordinance. |
|
|||||||||||||||||||||||||||
|
|
·
Sewage
arising from ancillary facilities of CWB & IECL (for example, control
room, ventilation and administration buildings) shall be connected to public
sewerage system. Sufficient
capacity in public sewerage shall be made available to the proposed
facilities. |
|
||||||||||||||||||||||||||
|
|
·
Road
drainage should also be provided with adequately designed silt trap to
minimize discharge of silty runoff. |
|
||||||||||||||||||||||||||
|
|
The design of the
operational stage mitigation measures shall take into account the guidelines published
in ProPECC PN 5/93 “Drainage Plans subject to Comment by the EPD.” All
operational discharges from the CWB into drainage or sewerage systems are
required to be licensed by EPD under the WPCO. |
|
||||||||||||||||||||||||||
Waste Management Implications |
Wastes generated
by construction activities: general refuse from the workforce, chemical waste
from plant and equipment maintenance, and C&D material from modification
of IEC (approx
|
The Contractor should implement the
following mitigation measures: good site practices and waste reduction
measures, good practices to handle general refuse, chemical waste, C&D
material and bentonite slurry. |
Not expected
|
||||||||||||||||||||||||||
Land Contamination Impact |
No land contamination impacts are expected. |
N/A |
Not expected |
||||||||||||||||||||||||||
Marine Ecological Impact |
As no proposed marine works
would be included in DP1, no adverse ecological impact on marine habitats and
associated wildlife is expected and therefore no necessary impact assessment
on marine ecology is required. |
N/A |
Not expected |
||||||||||||||||||||||||||
Landscape and Visual Impact |
Approximately 300 trees
will be affected. None of these are LCSD
Champion Trees, Registered Old and Valuable Trees, rare or
endangered species, but are common species. Trees will be
planted along roadside amenity areas and new waterfront to compensate for the
loss of existing trees. |
The Contractor should implement the following mitigation measures during construction phase · Topsoil, where identified, should be stripped and stored for re-use in the construction of the soft landscape works, where practical. |
Not expected |
||||||||||||||||||||||||||
|
During
construction, substantial negative impacts on the CBTS landscape character, and moderate
residual impact on With
implementation of mitigation measures during construction, there will be some
slight negative visual impact on the VSRs in the front row of high rise
buildings along the waterfront from Central to North Point. Residual impacts on VSRs further away
the |
· Existing trees to be retained on site should be carefully protected during construction · Trees unavoidably affected by the works should be transplanted where practical · Compensatory tree planting should be provided to compensate for felled trees. · Control of night-time lighting. |
|
||||||||||||||||||||||||||
|
During
operation, there will be insubstantial to slight visual impact
on VSRs along the new waterfront due to DP1. |
·
Erection of decorative screen hoarding compatible with the surrounding
setting. |
|
||||||||||||||||||||||||||
|
|
The following measures should be
implemented during operational phase by HyD ·
Aesthetic design of road-related structures, including viaducts, vent
buildings, subways, footbridges and noise barriers and enclosure. ·
Buffer Tree and Shrub Planting to screen proposed roads and associated
structures. ·
Aesthetic streetscape design. |
|
||||||||||||||||||||||||||
|
|
·
Aesthetic design of roadside amenity areas |
|
||||||||||||||||||||||||||
Cultural Heritage Impact |
There are no archaeological resources within the study area. |
N/A |
Not Expected |
Table 14.2 Summary
of EIA Impacts and Recommendations for DP2
Issue |
Environmental Issues |
Mitigation Measures and Recommendation |
Residual Impact |
Air Quality Impact |
Potential air quality impacts are: dust nuisance from wind erosion,
construction of road network and gaseous emissions from the construction
plant and vehicles. |
Implement the Air Pollution Control (Construction Dust) Regulation
and good site practices by Contractor |
Unacceptable impacts
are not
expected
|
|
Four times daily watering of the works site with active operations by
Contractor. |
|
|
No unacceptable operation air quality impact is expected.
|
|
Not expected
|
|
Noise Impact |
With the implementation of the mitigation measures, the cumulative
construction noise levels at all representative NSRs are predicted to comply
with the noise standards stipulated in the EIAO-TM. |
Implement good site practice by Contractor Use of quiet
powered mechanical equipment, movable noise barrier and temporary noise
barrier for the following tasks: |
Not expected |
|
|
·
Temporary road diversion |
|
|
|
·
Resurfacing |
|
|
|
· At-grade roadwork |
|
|
Traffic noise impact due to new roads is not expected. |
|
Not expected
|
|
Fixed plant noise impact is not expected. |
|
Not expected
|
Water Quality Impact |
General construction activities associated with the land-based construction could lead to site runoff containing elevated concentrations of SS and associated contaminants that may enter into the marine water. However, it is anticipated that the water quality impacts will generally be temporary and localised during construction. Therefore, no unacceptable residual water quality impacts are expected during the construction of the proposed infrastructure, provided all of the recommended mitigation measures are implemented and all construction site / works area discharges comply with the TM-DSS standards. |
All mitigation measures should control the following items: ·
Construction Runoff and Drainage ·
Sewage from Construction Work Force ·
Floating Debris and Refuse ·
Storm Water Discharges |
Not expected
|
|
Surface runoff from major roads
may be contaminated by oils leaked from passing vehicles, and road runoff
would potentially be contaminated to the same extent. It is considered that impacts upon
water quality will be minimal provided that the roads are designed with
adequate drainage systems.
|
|
|
Waste Management Implications |
Wastes
generated by construction activities: general refuse from the workforce and
chemical waste from plant and equipment maintenance.
|
The Contractor should implement the
following mitigation measures: good site practices and waste reduction
measures, good practices to handle general refuse, chemical waste and C&D
material. |
Not expected
|
Land Contamination Impact |
No land contamination impacts are expected. |
N/A |
Not expected |
Marine Ecological Impact |
As no proposed marine works
would be included in DP2, no adverse impact on marine habitats and associated
wildlife is expected and therefore no necessary impact assessment on marine
ecology is required. |
N/A |
Not expected |
Landscape and Visual Impact |
Approximately 110 trees
will be affected. None of these are LCSD
Champion Trees, Registered Old and Valuable Trees, rare or
endangered species, but are common species. Trees will be planted
along roadside amenity areas and new waterfront to compensate for the loss of
existing trees. |
The Contractor should implement the following mitigation measures during construction phase · Topsoil, where identified, should be stripped and stored for re-use in the construction of the soft landscape works, where practical. |
|
|
During
operation, with
mitigation measures, there will be slight residual negative impacts on
Victoria Park due to the slight reduction in park area. With
implementation of mitigation measures during construction, there will still be some moderate negative visual impact on the VSRs in the front row
of high rise buildings along the waterfront from Central to North
Point. Residual impacts on VSRs
further away the During
operation, there will be insubstantial to slight visual impact on VSRs due to DP2. |
· Existing trees to be retained on site should be carefully protected during construction |
|
|
· Trees unavoidably affected by the works should be transplanted where practical · Compensatory tree planting should be provided to compensate for felled trees. · Control of night-time lighting. · Erection of decorative screen hoarding compatible with the surrounding setting. |
Not expected |
|
|
|
The following measures should be implemented during operational phase by CEDD/HyD |
|
|
|
· Aesthetic design of road-related structures, including viaducts, vent buildings, subways, footbridges and noise barriers and enclosure. |
|
|
|
·
Buffer Tree and Shrub Planting to screen proposed roads and associated
structures. ·
Aesthetic streetscape design. ·
Aesthetic design of roadside amenity areas. |
|
Cultural Heritage Impact |
No cultural heritage impacts are expected |
N/A |
Not expected |
Table 14.3 Summary
of EIA Impacts and Recommendations for DP3
Issue |
Environmental Issues |
Mitigation Measures and Recommendations |
Residual Impacts |
Air Quality Impact |
Potential
air quality impacts are: dust nuisance from wind erosion, construction of seawall
and filling activities during reclamation, gaseous emissions from the
construction plant and vehicles, and potential odour impact from dredging activities carrying out in the vicinity of Police
Officers’ Club. |
Implement
the Air Pollution Control (Construction Dust) Regulation and good site
practices by Contractor. Four times daily watering of the works site with
active operations by Contractor. The dredging operation in the vicinity of
Police Officers’ Club will be restricted to only 1 small close grab dredger
to minimise the odour impact during the dredging activity. The dredging rate should be reduced as
much as practicable for area in close proximity to the Police Officers’ Club. As there is no programme constraint
for the removal of the sediments at the south-west corner of the typhoon
shelter in the vicinity of Police Officers’ Club for mitigating the existing
odour problem, the dredging rate can be slowed down or restricted to specific
non-popular hours in weekdays when it is necessary during construction. |
Unacceptable impacts are not
expected |
|
During
operational phase, this Project will not create any new odour source. However, odour nuisance associated
with the Causeway Bay Typhoon Shelter is an existing environmental problem. In order to improve the environment,
this Project will take the opportunities to mitigate the potential sources of
odour nuisance within the Project area so as to alleviate this existing
environmental problem as well as to provide an acceptable environment for the
future land uses within the project area. |
Carry out
dredging at the southwest corner of CBTS to remove the polluted sediment and
clean the slime attached on the CBTS shoreline seawall. Implementation of Enhancement Package
for Existing Odour Sources Identified at CBTS |
Based on the modelling results,
residual odour impact is expected at the sensitive use at CBTS Northern Breakwater and
Water Sports Centre (ex-PCWA area) during occassional worst case (extreme
meteorological and tidal) conditions. However, no nuisance
odour is detected
during odour survey at these areas.
A 5-year odour monitoring programme is proposed to monitor residual
impact on the ASRs. |
Noise Impact |
With the
implementation of the mitigation measures, the cumulative construction noise
levels at the NSRs selected for construction noise impact assessment except N20 are predicted to
comply with the noise standards stipulated in the EIAO-TM. The on-site survey has revealed that
NSR N20 (
|
Implement good site practice by Contractor and use of quiet powered
mechanical equipment, moveable / temporary noise barriers and PME
grouping |
Residual noise impact is predicted at N20. However, this is due to
cumulative effects, with the particularly noisy construction activities of
the IEC structure demolition being the major contributor. |
|
No road
traffic and fixed plant noise impact is expected. |
|
Not expected |
Water Quality Impact |
The major water quality impact associated with the reclamation works is the elevation of SS within the marine water column due to dredging and filling activities. Provided the recommended mitigation measures are implemented, including reduction of dredging rates, the deployment of silt curtains at the dredging and filling areas, and installation of silt screens at selected seawater intakes, there will be no unacceptable residual water quality impact due to the proposed reclamation works. |
Mitigation measures should be
implemented to control the following items:
·
Construction runoff and drainage ·
Sewage from construction work force ·
Floating debris and refuse · Storm water discharges |
Not expected |
|
Adverse water quality impacts associated with the operation of WDII
reclamation are not expected. Thus,
there will be no residual impact associated with the operation of the WDII. |
|
Not expected
|
Waste Management Implications |
Main waste: dredged marine sediment with a total volume of approx. Other
wastes generated by construction activities: general refuse from the
workforce, chemical waste from plant and equipment maintenance, and C&D
material from demolition of waterfront structures.
|
In
accordance with the ETWB TCW No. 34/2002, the contaminated material must be
dredged and transported with great care.
The mitigation measures recommended in Section 5 of the EIA Report
shall be incorporated. The dredged contaminated sediment must be effectively
isolated from the environment upon final disposal and shall be disposed of at
the Type 2 confined marine disposal contaminated mud pit. |
Not expected
|
|
|
Based on the
biological screening results, the Category H (>10xLCEL) sediment which
failed the biological testing would require Type 3 special disposal. The volume of Category H sediment from
the |
|
|
|
It will be
the responsibility of the Contractor to satisfy the appropriate authorities
that the contamination levels of the marine sediment to be dredged have been
analysed and recorded. According
to the ETWB TCW No. 34/2002, this will involve the submission of a formal
Sediment Quality Report to the DEP, at least 3 months prior to the dredging
contract being tendered. |
|
|
|
During
transportation and disposal of the dredged marine sediments requiring Type 1
and Type 2 disposal, the following measures shall be taken to minimise
potential impacts on water quality: |
|
|
|
· Bottom opening of barges shall be fitted with tight fitting seals to prevent leakage of material. Excess material shall be cleaned from the decks and exposed fittings of barges and hopper dredgers before the vessel is moved. |
|
|
|
·
Monitoring of the barge loading shall be conducted to ensure that loss
of material does not take place during transportation. Transport barges or vessels shall be
equipped with automatic self-monitoring devices as specified by the DEP. |
|
|
|
·
Barges or hopper barges shall not be filled to a level that would
cause the overflow of materials or sediment laden water during loading or
transportation. |
|
|
|
The Contractor should implement the following mitigation measures: good site practices and waste reduction measures, good practices to handle general refuse, chemical waste, C&D material and bentonite slurry. |
|
Land Contamination Impact |
No land contamination impacts are expected. |
N/A |
Not expected |
Marine Ecological Impact |
Permanent loss of approximately Temporary loss of approximately |
Translocation of all
potentially affected coral colonies to nearby suitable habitats such as |
No adverse residual impact is expected as the loss of 12.7 hectares soft bottom benthic and subtidal habitats due to permanent reclamation works are of very low ecological significance |
|
Potential direct impacts to some small and isolated coral colonies at
ex-PCWA basin and along seawall at North Point will require
translocation of these corals to a nearby suitable habitat. Potential indirect impacts to
subtidal and intertidal habitats and associated marine fauna due to change of
water quality during dredging and filling works. Mobile subtidal fauna would
temporarily avoid the dredged area and recolonise after marine works. Potential impact to
waterbirds and other avifaunal species of conservation interest including
Little Egret, Great Egret, Black-crowned Night Heron, Black Kite and
White-throated Kingfisher, which may suffer from lack of food source during
construction phase of the Project.
The affected birds would temporarily displace to nearby alternative
feeding grounds during construction phase of the project. |
During
dredging and filling operations, a number of mitigation measures to control
water quality should be adopted to confine sediment plume within reclamation
area and protect marine fauna in proximity to the reclamation. The mitigation
measures to be implemented by the Contractor include the following:
·
Installation of silt curtains during
dredging activities ·
Use of tightly-closed grab dredger ·
Limiting maximum dredging rates ·
Control of grab descending speed ·
Construction of leading edges of seawall in
the early stages of the reclamation works · Adoption of multiple-phase construction schedule |
|
|
Waterbirds and other avifaunal
species of conservation interest including Little Egret, Great Egret,
Black-crowned Night Heron, Black Kite and White-throated Kingfisher may be
temporarily disturbed by increased background noise and human activities
during construction phase of the project. |
To minimize potential disturbance impacts on the
foraging avifaunal population in the CBTS, particularly in the area near the
A King Shipyard, appropriate mitigation measures should be adopted
particularly during the construction phase. The following measures are
recommended:
|
|
|
|
·
Use of quiet mechanical plant during the
construction phase should be adopted wherever possible. |
|
|
No ecological imapct due to changes of tidal discharges
and current patterns during operation phase. |
·
General measures to reduce noise generated
during the construction phase (see noise control) should be effectively
implemented. Loss of artificial seawall habitats should be reinstated
by the construction of about |
|
Landscape and Visual Impact |
Under the proposed
development, approximately
|
The Contractor should implement the following mitigation measures during construction phase: ·
Control of night-time lighting. ·
Erection of decorative screen hoarding compatible
with the surrounding setting. |
Not expected |
|
Approximately During
construction,
there will be moderate residual impact on During
operation, slight negative impacts on |
The following measures should be
implemented during operational phase by CEDD* ·
Aesthetic design of proposed waterfront
promenade.* * CEDD will identify an implementation agent. |
|
|
With implementation of mitigation measures
during construction, there will still be some moderate negative visual impact
on the VSRs in the front row of high rise buildings along the
waterfront from Central to North Point.
Residual impacts on VSRs further away the |
|
|
|
During operation, there will be substantial to moderate positive visual impact on VSRs along the new waterfront as the landscape and visual amenity are generally enhanced and strengthened by the Project. Visual impacts from the hinterland and harbour will be insubstantial. |
|
Not expected |
Cultural Heritage Impact |
There are no archaeological resources within the Wan Chai study area |
N/A |
Not expected |
Table 14.4 Summary
of EIA Impacts and Recommendations for DP4
Issue |
Environmental Issues |
Mitigation Measures and Recommendation |
Residual Impact |
Air Quality Impact |
Potential air quality impacts are: dust nuisance
from wind erosion, construction of seawall and gaseous emissions from the
construction plant. |
Implement the Air Pollution Control (Construction Dust) Regulation
and good site practices by Contractor |
Unacceptable impacts are not expected |
|
No unacceptable operation air quality impact is expected. |
|
Not expected
|
Noise Impact |
With the implementation of the mitigation measures, the cumulative
construction noise levels at all representative NSRs are predicted to comply with
the noise standards stipulated in the EIAO-TM. |
Implement good site practice by Contractor Use of quiet powered mechanical equipment for the following tasks: |
Not expected
|
|
|
·
Temporary relocation of typhoon shelter -
Dredging temporary breakwater -
Rock filling, amour placing and bored pile
walls |
|
|
|
-
Removal of the temporary breakwater |
|
|
No road traffic and fixed plant noise impact is expected. |
|
Not expected
|
Water Quality Impact |
The major water quality impact associated
with dredging activities for construction of the temporary typhoon shelter is
the elevation of SS within the marine water column. Provided the recommended mitigation measures
are implemented, including limiting maximum dredging rates, and installation
of silt screens at selected seawater intakes, there will be no unacceptable
residual water quality impact due to the proposed works. |
All mitigation measures should
control the following items:
·
Sewage from Construction Work Force ·
Floating Debris and Refuse |
Not expected |
Waste Management Implications |
Wastes
generated by construction activities: general refuse from the workforce,
chemical waste from plant and equipment maintenance, dredged marine sediment
and C&D material from removal of the temporary
typhoon shelter breakwater (approx |
The Contractor should implement the
following mitigation measures: good site practices and waste reduction measures,
good practices to handle general refuse, chemical waste and C&D material |
Not expected
|
Land Contamination Impact |
No land contamination impacts are expected. |
N/A |
Not expected |
Marine Ecological Impact |
Temporary loss of approximately |
As no adverse ecological impact on marine habitats and associated
wildlife is predicted, no necessary mitigation measure is required. |
Not expected |
|
Potential indirect impacts to
subtidal habitats and associated marine fauna due to change of water quality
during dredging and filling works.
Mobile subtidal fauna would temporarily avoid the dredged area and recolonise
after marine works. |
|
|
|
|
|
|
Landscape and Visual Impact |
|
The Contractor should implement the following mitigation measures during construction phase. |
Not expected |
|
During
construction,
there will be moderate residual impact on |
· Control of night-time lighting. |
|
|
With
implementation of mitigation measures during construction, there will still be some moderate negative visual impact on the VSRs in the front row
of high rise buildings along the waterfront from Central to North
Point. Residual impacts on VSRs
further away the |
|
|
|
During
operation, there will be no visual impact on VSRs due to DP4. |
|
|
Cultural Heritage Impact |
There are no archaeological resources within the study area. |
N/A |
Not expected |
Table 14.5 Summary
of EIA Impacts and Recommendations for DP5
Issue |
Environmental Issues |
Mitigation Measures and Recommendation |
Residual Impact |
Air Quality Impact |
Potential air quality impacts are: dust nuisance from wind erosion,
construction of sewage outfall activities and gaseous emissions from the
construction plant and vehicles. |
Implement the Air Pollution Control (Construction Dust) Regulation
and good site practices by Contractor |
Unacceptable
impacts are not expected
|
|
|
Four times daily watering of the works site with active operations by
Contractor. |
|
|
No unacceptable operation air quality impact is expected. |
|
Not expected
|
Noise Impact |
With the implementation of the mitigation measures, the cumulative construction
noise levels at all representative NSRs are predicted to comply with the
noise standards stipulated in the EIAO-TM. |
Implement good site practice by Contractor Use of
quiet powered mechanical equipment for the following tasks: |
Not expected
|
|
|
·
Submarine pipelines (marine section) |
|
|
|
Use of
quiet powered mechanical equipment and movable noise barrier for the
following tasks: |
|
|
|
·
Installation of a new pipeline (land section) |
|
|
No road traffic and fixed noise impact is expected. |
|
Not expected |
Water Quality Impact |
The major water quality impact associated with dredging activities for construction of the sewage outfall is the elevation of SS within the marine water column. Provided the recommended mitigation measures are implemented, including limiting maximum dredging rates and installation of silt screens at selected seawater intakes, there will be no unacceptable residual water quality impact due to the proposed works. |
All mitigation measures should
control the following items:
·
Construction runoff and drainage ·
Sewage from construction work force ·
Floating debris and refuse · Storm water discharges |
Not expected
|
|
Adverse water quality impacts associated with the operation of new sewage submarine outfall are not expected. Thus, there will be no residual impact associated with the operation of the sewage outfall. |
|
Not expected
|
Waste Management Implications |
Wastes generated
by construction activities: general refuse from the workforce, chemical waste
from plant and equipment maintenance, and dredged marine sediment.
|
The Contractor should implement the
following mitigation measures: good site practices and waste reduction
measures, good practices to handle general refuse, chemical waste, and
C&D material. |
Not expected
|
Land Contamination Impact |
No land contamination impacts are expected. |
N/A |
Not expected
|
Marine Ecological Impact |
No adverse ecological impact would be expected |
N/A |
Not expected
|
Landscape and Visual Impact |
Since
DP5 is under
sea/underground, landscape and visual impact is not
expected. |
The Contractor should implement the following mitigation measures during construction phase |
Not expected |
|
|
· Minimisation of works areas |
|
|
|
·
Erection
of decorative hoardings. |
|
|
|
· Control night-time lighting. |
|
|
|
·
Minimisation of disruption to public by effective programming of the
works. |
|
Cultural Heritage Impact |
There are no archaeological resources within the study area. |
N/A |
Not expected |
Summary of Key Environmental Impacts and
Recommendations
Table 14.6 Summary
of EIA Impacts and Recommendations for DP6
Issue |
Environmental Issues |
Mitigation Measures and Recommendation |
Residual Impact |
Air Quality Impact |
Potential air quality impacts are: dust nuisance from wind erosion,
construction of seawall and filling activities during reclamation and gaseous
emissions from the construction plant and vehicles. |
Implement the Air Pollution Control (Construction Dust) Regulation
and good site practices by Contractor |
Unacceptable
impacts are not
expected
|
|
|
Four times daily watering of the works site with active operations by
Contractor. |
|
|
No unacceptable operation air quality impact is expected. |
|
Not
expected |
Noise Impact |
With the implementation of the mitigation measures, the cumulative construction noise levels at all representative NSRs are predicted to comply with the noise standards stipulated in the EIAO-TM. |
·
Implement good site practice by Contractor ·
Use of quiet powered mechanical equipment
for the following tasks: -
Submarine pipelines (marine section) |
Not expected
|
|
|
·
Use of quiet powered mechanical equipment
and movable noise barrier for the following tasks: |
|
|
|
-
Lay new submarine pipeline |
|
|
|
-
Connection to TST watermains |
|
|
|
-
Connection to Wan Chai watermains |
|
|
|
-
Installation of a new pipeline (land section) |
|
|
No road traffic and fixed noise impact is expected. |
|
Not expected
|
Water Quality Impact |
The major water quality impact associated with dredging activities for construction of the water mains is the elevation of SS within the marine water column. Provided the recommended mitigation measures are implemented, including limiting maximum dredging rates, and installation of silt screens at selected seawater intakes, there will be no unacceptable residual water quality impact due to the proposed works. |
All mitigation measures should
control the following items:
·
Construction runoff and drainage ·
Sewage from construction work force ·
Floating debris and refuse · Storm water discharges |
Not expected
|
|
Adverse water quality impacts
associated with the operation of water mains are not expected. Thus, there will be no residual impact
associated with the operation of the water mains.
|
|
Not expected |
Waste Management Implications |
Wastes generated by construction
activities: general refuse from the workforce, chemical waste from plant and equipment
maintenance, and dredged marine sediment.
|
The Contractor should implement the
following mitigation measures: good site practices and waste reduction
measures, good practices to handle general refuse, chemical waste and C&D
material. |
Not expected
|
Land Contamination Impact |
No land contamination impacts are expected. |
N/A |
Not expected |
Marine Ecological Impact |
No adverse ecological impact would be expected |
N/A |
Not expected |
Landscape and Visual Impact |
Since DP6 is under sea/underground, landscape and visual impact is not expected. |
The Contractor should implement the following mitigation measures during construction phase · Minimisation of works areas · Erection of decorative hoardings. · Control night-time lighting. ·
Minimisation
of disruption to public by effective programming of the works. |
Not expected |
Cultural Heritage Impact |
There are no archaeological resources within the study area . |
N/A |
Not expected |