15.6 Waste Management Implications
15.7 Land Contamination Impact
15.9 Landscape and Visual Impact
15.10 Cultural Heritage Impact
15.11 Environmental Monitoring and Audit
List of Tables
Table 15.1 Summary of Environmental Impacts Associated
with the Project
Table 15.2 Summary
of Key Environmental Outcomes/ Benefits
·
DP1 - Central-Wanchai Bypass including its road
tunnel (Items A.1 and A.7 of Part I of Schedule 2 of the EIAO)
·
DP2 -
WDII major roads (including Road P2) (Item A.1 of Part I of Schedule 2 of the
EIAO)
·
DP3 -
Reclamation works including associated dredging works (Item C.1 of Part I of
Schedule 2 of the EIAO)
·
DP4 -
Temporary typhoon shelter (Item C.5 of Part I, Schedule 2 of the EIAO)
·
DP5 -
Wan Chai East Sewage Outfall (Item F
·
DP6 -
Cross-harbour Water Mains from Wan Chai to Tsim Sha Tsui (Item C.12 of Part I of Schedule 2 of
the EIAO); and
Table 15.1 Summary
of Environmental Impacts Associated with the Project
Environmental Issue |
Sensitive
Receivers/ Assessment Points |
Impact Prediction
Results |
Relevant Standards/
Criteria |
Extents of
Exceedances |
Impact Avoidance
Measures/ Mitigation Measures |
Residual Impacts |
Air Quality |
|
|
|
|
|
|
Construction Phase |
48 assessment points |
1-hour Average TSP
Conc.: 88 24-hour Average TSP
Conc.: 82 |
EIAO-TM and Air
Quality Objective |
Nil |
Four times daily watering with complete coverage of active construction area Requirements of the Air Pollution Control (Construction Dust) Regulation The following mitigation measures, good site practices and a comprehensive dust monitoring and audit programme are recommended to minimise cumulative dust impacts. ·
Strictly
limit the truck speed on site to below |
Nil |
|
|
|
|
|
·
Watering during
excavation and material handling; |
|
|
|
|
|
|
·
Provision
of vehicle wheel and body washing facilities at the exit points of the site,
combined with cleaning of public roads where necessary; and |
|
|
|
|
|
|
·
Tarpaulin
covering of all dusty vehicle loads transported to, from and between site
locations. |
|
Operational Phase |
56 assessment points |
1-hour Average NO2 Conc.: 73 24-hour Average NO2 Conc.: 62 24-hour Average RSP Conc.: 56 |
Air Quality Objective |
Nil |
Not Applicable |
Nil |
|
Air quality inside CWB Tunnel & deckover for planned HKCEC Atrium Link |
CWB Tunnel – achieve
EPD recommended standard of 1 ppm NO2 concentration |
EPD Tunnel Air Quality
Guidelines |
Nil |
Not Applicable |
Nil |
Deckover on Atrium
Link – the
predicted maximum NO2 concentrations (5 minutes average) under
normal traffic flow and congested traffic flow would be |
|
|
|
|
||
Planned ASR – Open space with sensitive use at the west of HKCEC and Northern Breakwater of CBTS breakwater, and waterfront related commercial and leisure uses and Water Sports Centre at Wanchai |
The predicted odour
concentrations range from 1.5 to 29 ou/m3 over averaging time of 5
seconds under worst case condition. |
EIAO-TM |
Exceed the odour criterion up to 29 ou/m3 |
The Project itself would not introduce any additional odour emission sources within the study area. Odour nuisance associated with the Causeway Bay Typhoon Shelter is an existing environmental problem and adverse odour impacts in the vicinity of CBTS would be expected during worst case conditions. The potential odour impact would likely be minimized by the following mitigation measures: l Implementation of enhancement package for existing odour sources identified at CBTS as details in Appendix 15.1 |
Residual odour impact is predicted at the planned ASRs for around 0.1% to 0.2% of time in a year, under worst case meteorological and tidal conditions. For the other ASRs, there is also a 0.1% probability that the actual odour levels as perceived at the ASRs would exceed the predicted odour concentration (taking into account of 0.1% probability of exceeding the predicted odour concentration inherent in the calculation method).This situation is not expected to result in unacceptably adverse odour impact. |
|
Noise |
|
|
|
|
|
|
Construction Phase |
N1, N2, N3, N6, N8,
N11, N13, N15, N17, N18, N20 and N22 |
Predicted noise levels
would be in the range of 57 to 101 dB(A). |
Domestic premises:
75dB(A) |
Domestic premises:
Exceed the noise standard by up to 26dB(A). |
Use of quiet
equipment, movable/temporary noise barriers and PME grouping to mininise
construction noise impact |
For N11 ( For N17 ( |
Educational
institutions: 70 dB (A) during normal teaching periods & 65 dB(A) during
examinations |
Educational
institutions: Exceed the noise standard by 20 dB(A) during normal teaching period
and up to 25 dB(A) during examination period. |
|||||
|
|
|
|
|
|
For N18 ( |
|
|
|
|
|
|
For N20 ( |
Operational Phase |
N1 to N23 and P1 to P3 |
NSRs N1 – N5: 60 – 87 dB(A) NSRs N6 - N8: 78 – 85 dB(A) NSRs N9 – N17 and P1: 65 – 81 dB(A) NSRs N18 – N23, P2 and P3: 65 – 81 dB(A)
|
Domestic premises: 70 dB(A) Educational institutions and all others where unaided
voice communication is required: 65dB(A) |
Domestic premises: Exceed the noise standard by up to
17dB(A). Education institution: Exceed the noise standard by up
to 12dB(A) |
1.
About
|
With the proposed noise mitigation measures in place, the ‘New’ road noise contributions to the overall noise levels at all representative NSRs would be less than 1.0 dB(A) and the ‘New’ road noise levels would all be below the relevant noise criteria. No adverse noise impacts arising from the ‘New’ roads are predicted at representative NSRs. Noise exceedances at the representative NSRs, if any, would be due to the existing roads. |
|
|
Places of public worship: 65 dB(A) |
Places of public worship: Exceed the noise standard by 7dB(A). |
|||
|
|
|
|
|||
|
|
|
|
|
4.
About
|
|
|
|
|
|
|
5.
About
|
|
|
|
|
|
|
6.
low noise road
surfacing for the trunk road (except tunnel section and beneath the
landscaped deck at the eastern portal area) with speed limit of
|
|
|
|
|
|
|
7.
The openable
windows of the re-provisioned
|
|
Water Quality |
|
|
|
|
|
|
Construction Phase |
All water sensitivity
receivers in |
The model results indicate
exceedances of WSD water quality (SS) criterion for flushing water intakes
(at |
WSD water quality
criterion for SS: < 10 mg/l |
Full compliance with
the assessment criteria with the implementation of mitigation measures. |
Restriction on the
maximum dredging rates at the sewage pipelines zone, water mains zone, TWB,
TPCWA, HKCEC Stage 1 & 3 as well as the western
seawall of WCR1 which is close to the WSD intake at Wan Chai; |
Nil |
Full compliance with
the assessment criterion for sedimentation rate |
Target SS level at
Admiralty Centre and MTRC cooling water intakes: < 40 mg/l |
Deployment of silt
curtains around seawall dredging and seawall trench filling in NPR, TCBR, WCR
and HKCEC areas. |
||||
Sedimentation rate at
corals: < |
Deployment of silt screens at selected seawater
intakes |
|||||
Operational Phase |
All water sensitivity
receivers in |
Operation of WDII and
CWB would not cause unacceptable impacts upon the water quality in |
Relevant WQO for
marine water: |
No WQO
exceedance is induced by
the Project |
No mitigation measures
are considered necessary. |
Nil |
TIN level: <0.4
mg/l for annual mean |
||||||
UIA level: <0.021
mg/l for annual mean |
||||||
Depth-averaged DO
level: > 4 mg/l for 10th percentile |
||||||
Bottom DO level: |
||||||
Temperature increase:
< 2oC from background |
||||||
Waste Management Implications |
|
|
|
|
|
|
Construction Phase |
Not applicable |
Main waste: dredged marine sediment with a total volume of approx. |
1. Waste Disposal Ordinance (Cap.
354) |
Not applicable |
Refer to Table 14.4 |
Nil |
|
|
Other wastes: general refuse from the
workforce; chemical waste from plant and equipment maintenance; and C&D
material from excavation works and the demolition of existing structures. |
2. Waste Disposal (Chemical Waste)
(General) Regulation (Cap. 354) |
|
|
|
|
|
3. Land (Miscellaneous Provisions)
Ordinance (Cap. 28) |
|
|
|
|
|
|
4. Public Health and Municipal
Services Ordinance (Cap. 132) - Public Cleansing and Prevention of Nuisances
Regulation |
|
|
|
|
|
|
|
5. Annexes 7 & 15 of EIAO TM |
|
|
|
Land Contamination Impact |
|
|
|
|
|
|
Construction Phase |
Construction Workers
via direct ingestion of and dermal contact with contaminated soils. |
Source of land
contamination from past land uses of A King Marine Shipyard. Potential land contamination impacts
might occur as a result of handling contaminated soil by construction workers
during the remediation works at A King Marine. |
ProPECC PN3/94 - “Contaminated Land Assessment and
Remediation” “Guidance Notes for Investigation and
Remediation of Contaminated Sites of: Petrol Filling Stations, Boatyards, and
Car Repair /Dismantling Workshops |
Five contaminated
areas (One area with heavy metals and TPH and 4 areas with heavy areas only)
were identified. The estimated
quantity of soil contamination is |
Refer to Table 14.5 |
After appropriate
remediation actions (if required) have been completed, A King Marine will be
cleaned up to acceptable standards and no adverse impact would be envisaged. |
It is expected that land
contamination impacts would be minimal if the proposed mitigation measures
were properly implemented. |
||||||
Marine Ecological Impacts |
|
|
|
|
|
|
Construction Phase |
Ecological resources
in the assessment area |
Habitat loss -
Permanent: |
Not applicable |
Not applicable |
Avoidance -
Revised design of alternative Trunk Road constructed in tunnel to
avoid permanent loss of large area of marine habitats |
No adverse residual impact as loss of approximately |
|
|
-
Temporary: |
|
|
Minimization |
|
|
|
|
|
-
Translocation of all coral
colonies found within the reclamation areas |
|
|
|
|
|
|
-
Mitigation measures to control water quality |
|
|
|
|
Changes in water
quality -
More than 30% increase of SS at the immediate vicinity outside
reclamation area -
Insignificant elevation of SS at far-field sensitive receivers -
Level of TIN is predicted to be slightly higher than WQO standard at
several locations immediately outside reclamation area -
Minimum depth-averaged DO at HKCEC is predicted to be slightly lower
than 4.0 mg/L |
(See water quality
assessment) |
(See water quality
assessment) |
-
Mitigation measures to avoid disturbance impact to nearby waterbird
population Other Measures -
Construction of about |
|
|
|
Disturbance impact |
Not applicable |
Not applicable |
|
|
Operational Phase |
Ecological resources in
the assessment area |
Disturbance impact |
Not applicable |
Not applicable |
Mitigation measures are not required as no adverse impact is predicted. |
Nil |
Potential change in water quality in |
(See water quality assessment) |
(See water quality assessment) |
||||
Landscape and Visual Impact |
|
|
|
|
|
|
Construction Phase |
All Landscape Resources /
Landscape Character Areas and Visual Sensitive Receivers within the study
area |
Approximately 571 trees will be
affected. None of these are LCSD Champion Trees or Registered Old and
Valuable Trees. There are no rare
species or endangered specie but common species. |
1. ETWB TCW No. 29/2004 - Registration of Old and Valuable Trees, and Guidelines for their Preservation 2.
ETWB TCW No. 3/2006 - Tree Preservation |
Not applicable |
-
Existing trees to be retained
on site should be carefully protected during construction. - Trees unavoidably affected by the works should be transplanted where practical. - Compensatory tree planting should be provided to compensate for felled trees. |
Landscape Impacts
With mitigation measures, the project will not create adverse impact to
open space framework but have positive substantial impact to the waterfront
from Central to North Point.
Approximately
571 trees will be affected. There will be moderate residual
impact on |
|
|
|
|
|
- Control of night-time lighting. |
|
|
|
|
|
|
-
Erection of decorative screen
hoarding compatible with the surrounding setting. |
Visual Impacts
With implementation of mitigation measures, there will still be some
moderate negative visual impact on the VSRs in the front row of high rise
buildings along the waterfront from Central to North Point. Residual impacts VSRs further away the
|
Operational Phase |
All Landscape
Resources / Landscape Character Areas and Visual Sensitive Receivers within
the study area |
|
1. EIAO and TM, particularly Annexes 10 and 18 2. EIAO Guidance Note 8/2002 |
Not applicable |
-
Aesthetic design of buildings and road-related structures, including
viaducts, vent buildings, subways, footbridges and noise barriers and
enclosure. |
Landscape Impacts
With implementation
of mitigation measures, the residual impacts on
|
|
|
|
3. Town Planning Ordinance (Cap 131) 4. ETWB TCW No. 2/2004 - Maintenance of Vegetation and Hard Landscape Features 5. ETWB TCW No. 29/2004 - Registration of Old and Valuable Trees, and Guidelines for their Preservation 6. ETWB TCW No. 3/2006 - Tree Preservation |
|
-
Shrub and Climbing Plants to soften proposed structures -
Buffer Tree and Shrub Planting to screen proposed roads and associated
structures. -
Aesthetic design of proposed waterfront promenade. -
Aesthetic streetscape design. -
Aesthetic design of roadside amenity areas. |
There
are slight negative impacts on
|
|
|
|
|
Visual Impacts There will be substantial to moderate positive visual impact on VSRs
along the new waterfront as the landscape and visual amenity are generally
enhanced and strengthen by the proposed project. |
||
Cultural Heritage Impact |
|
|
|
|
|
|
Construction Phase |
Marine archaeological
resources in |
Since there is no
archaeological material present within the study area, no adverse cultural
heritage impact is expected. |
1.
Antiquities and Monuments Ordinance (Cap.53) 2.
Environmental Impact Assessment Ordinance (EIAO) (Cap. 499,
S.16) |
Not applicable |
No further
archaeological investigation or mitigation measures is required |
Nil |
|
|
|
3.
Technical Memorandum on the Environmental Impact Assessment
Process (EIAO-TM) |
|
|
|
|
|
|
4.
Guidance Notes on Assessment of Impact on Sites of Cultural Heritage
in Environmental Impact Assessment Studies (GN-CH) |
|
|
|
|
|
|
5.
|
|
|
|
|
|
|
6.
Marine Archaeological Investigation Guidelines. |
|
|
|
Table 15.2 Summary
of Key Environmental Outcomes/ Benefits
Issue |
Environmental Outcomes/Benefits |
The Project |
Requirements: · The Project is driven by the need for the implementation of the
Trunk Road, which is defined as the section of road extending from Rumsey
Street Flyover Extension to the IEC, comprising the CWB and the IECL. The Trunk Road will form an east-west
strategic route through Central and Wan Chai and is an essential element of
Government’s strategic transportation planning for · The Project can create a coherent pattern of land use and for the development of an appropriate waterfront ‘edge’ to the existing urban area. The Project will therefore consider imaginative measures to develop a high quality waterfront for the enjoyment of the public and tourists. |
|
Benefits: · The Project provides essential land for the construction of the
Trunk Road, the NIL, the SCL and other key transport infrastructure so as to
relieve congestion on the strategic east-west routes through Central, Wan
Chai and · The Project provides opportunity to create an attractive waterfront for the enjoyment of the public. The land formed through this Project will be used to regenerate the waterfront into an attractive public resource that could be used for a wide range of recreational and tourism-related uses and functions, with easy access from the urban hinterland. In so doing, the waterfront will become, as it should, an integral element of the public asset currently provided by the harbour. |
|
Potential
consequences without the Project:
(i) Not able to relieve traffic
congestion |
|
· Without the Trunk Road, the east-west strategic corridors of the
hinterland such as |
|
· From traffic point of view, given that the existing east-west corridor along the north shore is already overloaded at present, the future increase in general traffic growth on the Island due to territory-wide population and employment growth will exert additional pressure on the existing road network, thus causing further congestion and likely ‘gridlock’ situations to the north shore of Hong Kong Island, which may also have far reaching impacts to the harbour crossings. · A district traffic study has confirmed that a dual 3-lane Trunk Road (or Central-Wan Chai Bypass), together with intermediate slip roads, is required to divert traffic away from the existing east-west corridor and to provide adequate relief to the corridor and the local road network. The need for the Trunk Road has also been confirmed by the Expert Panel on Sustainable Transport Planning and Central-Wan Chai Bypass (‘Expert Panel’), which consists of independent local and overseas experts in the relevant fields. (ii) Not able to provide land for NIL and
SCL · Land formed under the Project, in addition to providing for the construction of the Trunk Road, also provides for the construction of the NIL and the SCL. Should the Project not proceed, implementation of these rail routes will be severely constrained. This will have consequential adverse impacts on the planning and provision of public transport infrastructure. (iii) No improvement of the waterfront ·
Should the Trunk Road not be
implemented the requirement for land formation is likely to fall away and
opportunities to improve the existing waterfront would be limited. (iv)
Likely environmental conditions · The existing odour nuisance at
the CBTS would persist and no improvement of the situation would be
expected. The Project will provide
opportunities to remove the potential sources of odour nuisance within the
CBTS so as to alleviate this existing environmental problem as well as to
provide an acceptable environment for the future land uses within the project
area. · In the absence of project,
similar air quality conditions along the northshore areas of Wan Chai, |
|
· In the absence of the project,
the noise environment of the project area would be increased due to the
natural growth of traffic. In the presence of the project, it would help
lessen the traffic burden on |
|
· No improvement of the existing
landscape and visual conditions of the waterfront would be expected. With the
implementation of the Project, there will be substantial to moderate positive
landscape and visual impact along the new waterfront as the landscape and
visual amenity are generally enhanced and strengthened. |
|
· Water quality at |
Development
Alternatives |
Factors such as engineering, social, and environmental
aspects have been considered in the light of different alternatives and
construction methods. The
following outcomes are found:
·
A “foreshore” alignment of Trunk Road is considered the most
reasonable and practical Trunk Road routeing, while “offshore” and “inland”
alignments are found not feasible due to conflict with existing development
and infrastructure. ·
Tunnel Option is selected in preference to Flyover Option, as it would
serve better to protect and preserve the Harbour. ·
Trunk Road Tunnel Variation 1 scheme is selected as the preferred
scheme in that it provides the necessary functional requirements of the Trunk
Road in meeting the overriding need and results in the least affected area of
the Harbour in conformance with the PHO. |
Environmentally
Friendly Designs Recommended |
The following environmental-friendly designs have been incorporated
into the current project designs: |
|
l
The extent of reclamation under the current
scheme has been minimized. Compared to original scheme in the previous
approved EIA report, the reclamation area is substantially reduced by
approximately |
|
l
The length of elevated road section from
east portal ramp of Trunk Road to existing IEC is approximately l
The section of Trunk Road passing across
RHKYC will be in the form of tunnel. Hence, RHKYC will not be affected. |
|
l A landscaped deck has been proposed over the east tunnel portal area of the Trunk Road. This landscaped deck provides visual and noise screening effect to the nearby sensitive receivers. |
|
l Smooth curves have been adopted at indented areas rather than sharp corners along the shoreline. This smoothing of the shoreline will enhance flows and prevent accumulation of pollutants or floating refuse. |
|
l
The current ventilation system proposed for
the Trunk Road consists of three extraction fans for the East Tunnel
Portal. Two fans will be adequate
to extract all polluted air from the upstream tunnel section of the exit
portal. The third fan will be
used as standby in case one fan is under maintenance or out of order. Airflow direction sensors will be
installed at the location of the exit portal to monitor the airflow direction
of the tunnel. This sensor will be
used to control the operation of tunnel portal extraction system to ensure
that the target of “zero portal emission” will be met. |
|
l
The polluted tunnel air extracted from the
East Tunnel Portal will be filtered by electrostatic precipitator installed
at the |
Environmental
Problems Avoided |
The environmental problems avoided/minimized due to the current scheme
include: ·
As a result of the tunnel design of the
Trunk Road, potential vehicle emissions and road traffic noise impacts from
the proposed Trunk Road on the air and noise sensitive receivers at Wan Chai and ·
Noonday Gun at CBTS would not be
affected and would be retained at the same location. ·
Kellett Island
Archaeological Site at RHKYC would not be affected. ·
Potential environmental impacts including
construction dust, water quality and marine ecology would be reduced compared
to the original scheme in the approved EIA report due to the decrease in the
extent of reclamation. ·
As there is no longer any development on
reclaimed land formed with marine sediments in place within CBTS, potential
biogas problem would be avoided in the current scheme. |
|
·
Since the section of Trunk Road across RHKYC
under the current scheme is more than |
|
·
With the zero portal emission design of the
East Tunnel Portal, potential air quality impact from the portal emission
would be avoided. In addition, the air quality of the East Tunnel Portal area
would be enhanced by locating the exhaust vent shaft proposed at the East
Breakwater of the CBTS and the electrostatic precipitator system at the |
Population and
Environmentally Sensitive Areas Protected |
The major environmentally sensitive areas within
the study area include residential buildings, commercial buildings, hotels,
recreational areas, and educational institutions at Wan Chai, |
Construction Air
Quality Impact |
Environmental
benefits of environmental protection measures recommended: During construction phase, potential air quality impacts include dust
nuisance and gaseous emissions from the construction plant and vehicles and
dredgers and odour impact from contaminated sediment during dredging in the
vicinity of Police Officers’ Club. Mitigation measures for dust impact include four times watering a day
on the active work areas and implementation of the Air Pollution Control
(Construction Dust) Regulation and good site practices. For the dredging activities carried out in the vicinity of Police
Officers’ Club, the dredging operation will be restricted to only 1 small
close grab dredger to minimise the odour impact during the dredging
activity. The dredging rate
should be reduced as much as practicable for area in close proximity to the
Police Officers’ Club. With the implementation of the recommended control and mitigation
measures, no adverse air quality impacts are anticipated. Compensation
areas included: Not
required |
|
Population
and environmental sensitive receivers protected: Existing air sensitive receivers within |
Operational Air
Quality Impact |
Environmental benefits of environmental protection measures recommended: No unacceptable residual traffic emission impacts are anticipated at the existing and future ASRs. |
|
Air quality inside CWB Tunnel and deckover for planned HKCEC Atrium Link would comply with standards of EPD Tunnel Air Quality Guidelines. |
|
Potential odour impacts are identified at the corner of CBTS near the Police Officers’ Club and the area in the vicinity of Outfall Q. With the removal of seabed sediments at the corner of CBTS and removal of slime attached on the CBTS seawall during construction phase, as well as rectification of expedient connections to CBTS and the implementation of Enhancement Package for existing identified odour sources at CBTS, odour impact will be significantly reduced. Although modelling results indicate that some residual impact is still predicted at the nearest planned ASRs (open space at CBTS Breakwater and Water Sports Centre), this impact would occur infrequently and mainly under a combination of extreme weather and tidal conditions. Monthly monitoring (from July to September) of odour impacts, for a period of 5 years, is proposed during the operational phase of the Project to ascertain the effectiveness of the Enhancement Package over time, and to monitor any on-going odour impacts at the ASRs. Air quality monitoring for the operation performance of the Compensation
areas included: Not
required Population
and environmental sensitive receivers protected: Existing and planned air sensitive receivers within |
Construction Noise
Impact |
Environmental
benefits of environmental protection measures recommended: The predicted mitigated noise levels would range from 44 to 85 dB(A) at the representative NSRs. With the implementation of quiet PME, movable barriers, temporary barriers, PME grouping and good site practices for construction tasks under the Project and implementation of the noise mitigation measures proposed in the CRIII Reports, the predicted noise levels at the NSRs selected for construction noise impact assessment except N11, N17, N18 and N20 would comply with the construction noise standard. |
|
Compensation
areas included: Not required. |
|
Population
and environmental sensitive receivers protected: Noise
sensitive receivers within |
Road Traffic Noise
Impact |
Environmental
benefits of environmental protection measures recommended: The following mitigation measures would be recommended: ·
about ·
about ·
about ·
about ·
about ·
low noise road surfacing for
the trunk road (except tunnel section and beneath the landscaped deck at the
eastern portal area) with speed limit of 70 km/hour; and ·
the openable windows of the
re-provisioned Predicted mitigated noise levels would be in the range of 60 dB(A) to 87 dB(A). Noise exceedances at the representative NSRs are due to the existing roads. The ‘new’ road noise contributions to the overall noise levels at all representative NSRs would be less than 1.0 dB(A) and the ‘new’ road noise levels would all be below the relevant noise criteria. No adverse noise impacts arising from the ‘new’ roads are predicted at any of the representative NSRs. In general, the noise environment for the NSRs would be improved by the Project and the direct noise mitigation measures. As compared with the prevailing noise environment, the predicted road traffic noise levels at the existing NSRs in year 2031 would be reduced by: · 1-10 dB(A) at N2 to N5 (Wan Chai area) · 1-3 dB(A) at N6 to N8 ( · 1-27 dB(A) at N12 to N17 (Tin Hau area) ·
1-27 dB(A) at N18 to N21
(North Point area) |
|
Compensation
areas included: Not required. |
|
Population
and environmental sensitive receivers protected: Existing
and planned NSRs within |
Fixed Plant Noise
Impact |
Environmental benefits of environmental protection measures recommended: Operation of the proposed permanent
helipad, ventilation buildings and PTI will not impose adverse noise impacts
on the existing and planned NSRs. |
|
Compensation
areas included: Not
required. Population
and environmental sensitive receivers protected: Noise sensitive receivers within |
Water Quality Impact |
Environmental benefits of environmental protection measures recommended: Implementation of the proposed mitigation
measures including use of closed grab dredging, the deployment of silt
curtains at appropriate dredging areas, and installation of silt screens at
selected seawater intakes along the water front of Compensation
areas included: Not required. Population
and environmental sensitive receivers protected: Seawater intakes along the waterfront of |
Waste Management
Implications |
Environmental benefits of environmental protection measures
recommended: |
|
With
the implementation of the recommended mitigation measures and practices
(refer to Section 6.7 for details), potential air, odour, noise, water
quality for the handling, transportation and disposal of the identified waste
arisings, no adverse environmental impacts are expected. |
|
Limited amount of refuse and debris may be
unintentionally brought from the site into the harbour during heavy rains or
typhoons. Given that the Project would not worsen the shoreline configuration
and the implementation of appropriate control measures during construction
phase, it is considered that the future quantity of refuse to be found along
the shoreline would be similar if not better than the existing situation.
With the implementation of a refuse collection system within the project
area, no insurmountable environmental impact with regard to floating refuse
would be anticipated during the construction phase, or after completion of
the Project. |
|
Compensation
areas included: Not required. Population and environmental sensitive
receivers protected: Water quality, air, and noise sensitive
receivers at or near the Project site, the waste transportation routes and
the waste disposal site. |
|
|
Land Contamination
Impact |
Environmental benefits of environmental protection measures recommended: Based on the review of the
previous WDIICFS EIA Report and investigation on the historical/current land
uses, the proposed re-development of A King Marine might pose potential land
contamination impacts during the construction phase of the Project. Site
investigation (SI) was carried out in accordance with the endorsed CAP. Based on the analytical results,
exceedances in relevant criteria of heavy metals and total petroleum
hydrocarbons (TPH) were identified and an estimated The land contamination impacts associated with A King Marine would be the handling of contaminated soil by construction works during the remediation works. If the proposed mitigation measures (refer to Section 7.10 for details) were properly implemented, adverse land contamination impacts are not anticipated. Compensation
areas included: Not
required. Population
and environmental sensitive receivers protected: Construction workers at A
King Marine Shipyard. |
Marine Ecological
Impact |
Environmental benefits of environmental protection measures
recommended: The
benthic, intertidal and subtidal habitats within the affected area are of
very low ecological value and direct impact on some small and isolated coral
colonies attached to movable boulders at the coastlines within
|
|
Population
and environmental sensitive receivers protected: Ecological resources in the assessment area. |
Landscape and Visual
Impact |
· Environmental benefits of
environmental protection measures recommended: · Under the proposed development,
approximately · Approximately · The bowling greens will be
temporarily affected by the construction of Slip Road 8 and will be
reprovisioned within the Victoria Park during the operation phase. |
|
· Under the proposed development,
Fenwick Pier Street Public Open Space will be temporarily affected during the
construction stage. However, this
open space will be replaced by the new district open space at the site of the
Hong Kong Academy of Performing Arts Extension in the future. |
|
· Approximately 571 trees will be affected. None of these are LCSD Champion Trees, Registered Old and Valuable Trees, rare or endangered specie, all trees are common species. Approximately 1500 new trees and other proposed planting will be planted in the new waterfront and along roadside amenity areas after the new open space is built to compensate the felled trees. |
|
·
During construction,
substantial negative impacts on the Fenwick Pier Street Public Open Space
landscape character and the CBTS landscape character, and moderate residual
impact on |
|
· During operation, slight negative impacts on · There will still be slight
residual visual impact due to the provision of noise
barriers/screening/semi-enclosures in North Point. However, there will be significant
area of new waterfront open space from Tin Hau to |
|
·
With implementation of
mitigation measures during construction, there will still be some moderate
negative visual impact on the VSRs in the front row of high rise buildings
along the waterfront from Central to North Point. Residual impacts on VSRs further away
the |
|
· During operation, there will be substantial to moderate positive visual impact on VSRs along the new waterfront as the landscape and visual amenity are generally enhanced and strengthened by the Project. |
|
Compensation
areas included: Approximately Population
and environmental sensitive receivers protected: Existing and
planned Landscape Resources , Landscape Character Area and VSR at and near
the project site. |
Cultural Heritage
Impact |
Environmental
benefits of environmental protection measures recommended: Since there are no marine archaeological
resources within the study area that would be affected by the project, marine
archaeological impact due to the construction activities is not expected. The
current project design would avoid the potential impact on the Kellett Island
Archaeological Site at RHKYC and Noonday Gun at CBTS. No environmental protection measure is
required. Compensation
areas included: Not required. Population
and environmental sensitive receivers protected: Potential archaeological resources, and
historical buildings and structures within the project area. |
Marine-based
Impact
Land-based
Impact