7.2 Environmental Legislation,
Policies, Plans, Standards and Criteria
7.4 Review of Previous WDIICFS
EIA Study
7.5 Potential
Contaminative Land Uses
7.7 Identification of
Environmental Impacts
7.8 Land
Contamination Assessment
7.9 Evaluation and Prediction
of Impacts
7.11 Residual Environmental
Impact
7.12 Environmental Monitoring
and Audit (EM&A) Requirements
List of Tables
Table
7.1 Potential
Contaminative Land Use within the Study Area
Table 7.2 List
of Aerial Photographs Reviewed (A King Marine)
Table 7.3 Details
of Existing Potential Contaminative Land Use
Table 7.4 Estimated
Quantity of Contaminated Soil
Table 7.5 Findings
of Site Reconnaissance
Table
7.1 Potential
Contaminative Land Use within the Study Area
Site
ID |
Potential
Contaminative Land Uses |
Location |
Site 1 |
A King Marine (abandoned shipyard) |
Eastern corner of Causeway Bay Typhoon
Shelter (CWBTS). |
Table
7.2 List
of Aerial Photographs Reviewed (A King Marine)
Date |
Reference No. |
Height (ft) |
Key Issues |
13.11.1924 |
11 |
11100 |
The site was yet reclaimed. The coastline
extended along current |
8.5.1949 |
6028 |
8000 |
Ditto |
5.10.1959 |
0291 |
40000 |
Reclamation
completed and the site was formed. The shipyard started to operate in
small-scale with less than 10 workshops/buildings. |
1.2.1963 |
7223 |
2700 |
Shipyard
expanding its operation to its West. |
16.5.1967 |
5612 |
6250 |
Western
portion of the site established. |
1968 |
842 |
2000 |
Full-scale Operations underway (at least
10 workshops / buildings). |
5.11.1980 |
32259 |
4000 |
Decreased number of workshops and
buildings (about 6). |
19.3.1990 |
A20665 |
2000 |
Not much change from 1980. |
5.12.1993 |
A36934 |
4000 |
Decommissioning / Site formation at east
portion of the site. |
7.12.1995 |
CN12608 |
3500 |
Operation of Fire Station in the “former”
decommissioning / site formation area.
|
3.2.2000 |
A50906 |
2000 |
Not much change from 1995. Only 2 workshops / buildings
noted. |
15.3.2001 |
CN30244 |
4000 |
Not much
change from 2000. The remaining portion of shipyard was still in operation. |
7.10.2002 |
CW44335 |
4000 |
The shipyard had
ceased operation and was abandoned. |
19.5.2006 |
CW71907 |
4000 |
Not much
change from 2002. The shipyard was abandoned. |
Source: Survey and Mapping Office, Lands Department.
·
Direct ingestion of contaminated soils through
eating or drinking/smoking on site; and
·
Dermal contact with contaminated soils.
Table 7.3 Details
of Existing Potential Contaminative Land Use
Site ID |
Potential Contaminative Use/Activity |
Site Descriptions |
|
Necessity for Further Investigation |
1 |
A King Marine (abandoned
shipyard) |
-
Located at eastern corner of CWBTS. -
Ceased operation and was abandoned around 2001 to 2002. -
Approximately 1,500 m2 in land area. -
Based on previous WDIICFS EIA Study and site reconnaissance
carried out in December 2006 under this Study, the site consisted of winches,
slipway, aboveground storage tank, workshops, open boat storage area and
chemical / dangerous goods storage area. |
In the current RODP, the area is
proposed for the re-provision of the floating |
Yes if excavations, foundation
works or other construction activities requiring handling of underlying soil. |
Table
7.4 Estimated
Quantity of Contaminated Soil
Area ID |
Corresponding Sampling
Location |
Contaminants |
Estimated Vertical Contamination Extent |
Estimated Horizontal Contamination Extent (m2) |
Estimated Volume of
Contaminated Soil * (m3) |
Area B1 |
BH-3 |
TPH, copper, lead, zinc and barium |
0.0-0.8 |
49 |
39.2 |
Area B2 |
BH-3 & BH-4 |
Copper and lead |
0.0-0.8 |
570.5 |
456.4 |
Area B3 |
BH-4 |
Copper |
1.2-2.0 |
49 |
39.2 |
Area C1 |
BH-5 |
Lead |
2.5-3.5 |
49 |
49 |
Area C2 |
BH-8 |
Lead |
1.0-2.0 |
49 |
49 |
Total Estimated Volume of Contaminated Soil: |
632.8 |
||||
(TPH and Heavy
Metals: |
Notes: * The soil volume may vary subject to the testing of confirmatory samples collected at the defined contaminated zone boundary as well as the site specific conditions (e.g. encountering of boulders).
Ù Based on the RAP (Appendix 7.2), heavy metals only
contaminated soil (estimated volume of
Table 7.5 Findings
of Site Reconnaissance
Area |
Facilities Identified1 |
Area (m²) |
Site Observation |
SI Proposed |
A |
2 Winches Site Office |
326 |
l
The whole
area was located on elevated seawall and paved with thick intact
concrete. In general, no stains
were observed. l
No
evidence of open burning was observed in the area. l
Two
winches were observed near the edge of the seawall, paved with thick intact
concrete. It is possible that the
area is for loading ships for maintenance. l
Site
office was paved with intact concrete without stains. l
Potential
contamination is possible near the two winches. |
Yes |
B |
Slipways Open Boat Storage Area |
570.5 |
l
The ground
is made up of permeable sandy materials.
No obvious stains were observed. l
No
evidence of open burning was observed in the area. l
According
to 2001 EIA, the area is identified as slipways and open boat storage area. l
Remains
of the slipways were observed at the western portion of Area B. l
Only
vegetation and substantial amount of general refuse were observed at the
eastern portion of the site. l
Based
on the permeable nature of the ground and possible past activities in the area,
contamination at Area B is possible. |
Yes |
C |
2 Workshops 1 Winch Aboveground Storage Tank. (AGT) Storage Facility Site Office |
703 |
l
The
whole area was located on elevated seawall and paved with thick intact
concrete. l
No evidence
of open burning was observed in the area. l
Only
a container was observed at the location of borehole ‘BH-4’ as proposed in
the 2001 EIA. Based on the site
reconnaissance, the area was elevated and constructed on intact concrete. No stains were observed. Potential contamination in the area is
therefore unlikely. l
A
storage facility (possibly for chemicals), made up of small compartments,
were observed at the southern portion of the Site. Minor stains were observed in one of
the compartment. The switch and
meter room was also located in one of compartment. The storage area was paved with intact
concrete and no stains were observed near the facility l
One
winch and a workshop (Workshop A) was observed near the edge of the seawall,
at the northern portion of Area C.
The facilities are located on top of the seawalls and paved with thick
intact concrete. Some stains were
observed just west of the workshop. l
A 9
ton aboveground diesel storage tank (AGT) was observed near the storage
facility. The tank was
semi-enclosed by concrete walls at four sides. The floor was paved with intact
concrete. No stains were observed
within / near the AGT. l
A
shaded workshop (Workshop B) was identified at the western end of the
shipyard. The workshop was
constructed on the edge of the seawall and paved with thick intact
concrete. l
A
site office was located just west of the workshop, constructed on the seawall
and thick concrete. The office
was tiled and no stains were observed. l
Potential
contamination is expected to be minimized as the area is paved with thick
intact concrete. However, due to
length of operation of the shipyard and potential contamination of the
workshops, AGT and Storage Facility, SI is proposed near the facilities. |
Yes |
1: Please refer to Figure 7.2 for location.
·
Excavation
profiles must be properly designed and executed;
·
In
case the soil to be excavated is situated beneath the groundwater table, it may
be necessary to lower the groundwater table by installing well points or
similar means;
·
Quantities
of soil to be excavated must be estimated;
·
It
maybe necessary to split quantities of soil according to soil type, degree and
nature of contamination.
·
Temporary
storage of soil at intermediate depot or on-site maybe required. The storage site should include
protection facilities for leaching into the ground. eg. Liner maybe required.
·
Supply
of suitable clean backfill materials is needed after excavation.
·
Care
must be taken of existing buildings and utilities.
·
Precautions
must be taken to control of ground settlement
·
Speed
controls for vehicles should be imposed on dusty site areas.
·
Vehicle
wheel and body washing facilities at the site’s exit points should be
established and used.
Air
Quality Mitigation Measures
·
The
loading, unloading, handling, transfer or storage of cement should be carried
out in an enclosed system.
·
The
loading, unloading, handling, transfer or storage of other materials which may
generate airborne dust emissions such as untreated soil and oversize materials
sorted out from the screening plant and stabilized soil stockpiled in the
designated handling area, should be carried out in such a manner to prevent or
minimise dust emissions. These materials should be adequately wetted prior to
and during the loading, unloading and handling operations.
·
All
practicable measures, including speed controls for vehicles, should be taken to
prevent or minimize the dust emission caused by vehicle movement.
·
Tarpaulin
or low permeable sheet should be put on dusty vehicle loads transported between
site locations.
Noise
Mitigation Measures
·
The
mixing facilities should be sited as far as practicable to the nearby noise
sensitive receivers.
·
Simultaneous
operation of mixing facilities and other equipment should be avoided.
·
Mixing
process and other associated material handling activities should be properly scheduled
to minimise potential cumulative noise impact on the nearby noise sensitive
receivers.
· Construction Noise Permit should be applied for the operation of powered mechanical equipment during restricted hours (if any).
Water
Quality Mitigation Measures
·
Stockpile
of untreated soil should be covered as far as practicable to prevent the
contaminated material from leaching out.
The leachate should be discharged following the requirements of WPCO.
Waste
Mitigation Measures
·
Treated
oversize materials will be used as filling material for backfilling within the
site. Sorted materials of size
smaller than 5 cm will be collected and transferred to the mixing plant for
further decontamination treatment.
·
Stabilized
soils should be broken into suitable size for backfilling or reuse on site.
·
A high
standard of housekeeping should be maintained within the mixing plant area.
·
If
necessary, there should be clear and separated areas for stockpiling of
untreated and treated materials.