14.6 Waste
Management Implications
14.7 Land Contamination
Impact
14.9 Landscape and
Visual Impact
14.10 Cultural Heritage
Impact
14.11 Environmental
Monitoring and Audit
Table 14.1 Summary
of Environmental Impacts Associated with the Project
Environmental Issue |
Sensitive
Receivers/ Assessment Points |
Impact Prediction
Results |
Relevant Standards/
Criteria |
Extents of
Exceedances |
Impact Avoidance
Measures/ Mitigation Measures |
Residual Impacts |
Air Quality |
|
|
|
|
|
|
Construction Phase |
48 assessment points |
1-hour Average TSP
Conc.: 88-434 mg/m3 24-hour Average TSP
Conc.: 82-241mg/m3 |
EIAO-TM and Air
Quality Objective |
Nil |
Four times daily watering with complete coverage of active construction area Requirements of the Air Pollution Control (Construction Dust) Regulation The following mitigation measures, good site practices and a comprehensive dust monitoring and audit programme are recommended to minimise cumulative dust impacts. ·
Strictly
limit the truck speed on site to below |
Nil |
|
|
|
|
|
·
Watering
during excavation and material handling; |
|
|
|
|
|
|
·
Provision
of vehicle wheel and body washing facilities at the exit points of the site,
combined with cleaning of public roads where necessary; and |
|
|
|
|
|
|
·
Tarpaulin
covering of all dusty vehicle loads transported to, from and between site
locations. |
|
Operational Phase |
56 assessment points |
1-hour Average NO2 Conc.: 73-254 mg/m3 24-hour Average NO2 Conc.: 62-135 mg/m3 24-hour Average RSP Conc.: 56 |
Air Quality Objective |
Nil |
Not Applicable |
Nil |
|
Air quality inside CWB Tunnel & deckover for planned HKCEC Atrium Link |
CWB Tunnel – achieve
EPD recommended standard of 1 ppm NO2 concentration |
EPD Tunnel Air Quality
Guidelines |
Nil |
Not Applicable |
Nil |
|
Deckover on Atrium
Link – the
predicted maximum NO2 concentrations (5 minutes average) under
normal traffic flow and congested traffic flow would be 114mg/m3 and 130mg/m3
respectively, |
|
|
|
|
|
Noise |
|
|
|
|
|
|
Construction Phase |
N1, N2, N3, N6, N8,
N11, N13, N15, N17, N18, N20 and N22 |
Predicted noise levels
would be in the range of 57 to 101 dB(A) |
Domestic premises:
75dB(A) Educational
institutions: 70 dB (A) during normal teaching periods & 65 dB(A) during
examinations |
Domestic premises:
Exceed the noise standard by up to 26dB(A). Educational
institutions: Exceed the noise standard by 20 dB(A) during normal teaching
period and up to 25 dB(A) during examination period. |
Use of quiet
equipment, movable/temporary noise barriers and PME grouping to mininise
construction noise impact |
For N11 (i.e. For N17 ( |
|
|
|
|
|
|
For N18 (i.e. For N20 (i.e. |
Operational Phase |
N1 to N23 and P1 to P3 |
NSRs N1 – N5: 60 – 87 dB(A) NSRs N6 - N8: 78 – 85 dB(A) NSRs N9 – N17 and P1: 65 – 81 dB(A) NSRs N18 – N23, P2 and P3: 65 – 81 dB(A)
|
Domestic premises: 70 dB(A) |
Domestic premises: Exceed the noise standard by up to 17dB(A). |
1.
About
|
With the proposed noise mitigation measures in place, the ‘New’ road noise contributions to the overall noise levels at all representative NSRs would be less than 1.0 dB(A) and the ‘New’ road noise levels would all be below the relevant noise criteria. No adverse noise impacts arising from the ‘New’ roads are predicted at representative NSRs. Noise exceedances at the representative NSRs, if any, would be due to the existing roads. |
|
|
Educational institutions and all others where unaided voice communication is required: 65dB(A) |
Education institution: Exceed the noise standard by up to 12dB(A) |
|||
|
|
Places of public worship: 65 dB(A) |
Places of public worship: Exceed the noise standard by 7dB(A). |
|||
|
|
|
|
|||
|
||||||
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Water Quality |
|
|
|
|
|
|
Construction Phase |
Seawater intakes at or
near the Project site |
It is anticipated that
the water quality impacts will generally be localised during
construction. Unacceptable impact
on the identified sensitive receivers is not expected. |
Water Pollution
Control Ordinance (WPCO) Water Supplies
Department (WSD) Water Quality Criteria: for flushing intake |
Not applicable |
Good housekeeping and stormwater best management practices for control of construction site runoff, stormwater discharges, sewage effluent, drainage and general refuse |
Nil |
|
|
|
Technical Memorandum on Standards for Effluents
Discharged into Drainage and Sewerage Systems, Inland and Coastal Waters (TM-DSS) ProPECC PN 1/94 “Construction Site Drainage” |
|
|
|
Operational Phase |
Seawater intakes at or
near the Project site |
It is anticipated that
the water quality impacts will generally be localised during operation. Unacceptable impact on the identified
sensitive receivers is not expected. |
WPCO WSD Water Quality
Criteria: for flushing intake TM-DSS ProPECC PN 1/94 “Construction Site Drainage” |
Not applicable |
Provision of adequately designed silt trap and oil
interceptors, as necessary |
Nil |
Waste Management Implications |
|
|
|
|
|
|
Construction Phase |
Not applicable |
General refuse from the workforce; chemical waste from plant and
equipment maintenance; and C&D material from excavation works and the
demolition of existing structures. |
1. Waste Disposal Ordinance (Cap.
354) |
Not applicable |
Refer to Table 13.4 |
Nil |
|
|
2. Waste Disposal (Chemical Waste)
(General) Regulation (Cap. 354) |
|
|
|
|
|
|
3. Land (Miscellaneous Provisions)
Ordinance (Cap. 28) |
|
|
|
|
|
|
4. Public Health and Municipal
Services Ordinance (Cap. 132) - Public Cleansing and Prevention of Nuisances
Regulation |
|
|
|
|
|
|
|
5. Annexes 7 & 15 of EIAO TM |
|
|
|
Land Contamination Impact |
|
|
|
|
|
|
Construction Phase |
Construction Workers
via direct ingestion of and dermal contact with contaminated soils. |
No land contamination
impact is expected. |
ProPECC PN3/94 - “Contaminated Land Assessment and
Remediation” “Guidance Notes for Investigation and
Remediation of Contaminated Sites of: Petrol Filling Stations, Boatyards, and
Car Repair /Dismantling Workshops |
None |
None |
Nil |
|
||||||
Marine Ecological Impacts |
|
|
|
|
|
|
Construction Phase |
Marine ecological
resources in the assessment area. |
No adverse ecological impact is expected. Only negligible indirect
impact on subtidal and intertidal habitats and associated marine wildlife
caused from change of water quality due to potential site run-off from
land-based construction sites. |
(See water quality
assessment) |
(See water quality
assessment) |
-
As no adverse ecological impact on marine habitats and associated
wildlife is identified, no necessary mitigation measure specific for marine
ecology is required. |
Not expected |
Landscape and Visual Impact |
|
|
|
|
|
|
Construction Phase |
All Landscape Resources /
Landscape Character Areas and Visual Sensitive Receivers within the study
area |
- Approximately 300 trees will be affected. None of these are LCSD Champion Trees or Registered Old and Valuable Trees. There are no rare species or endangered specie but common species. |
1. ETWB TCW No. 29/2004 - Registration of Old and Valuable Trees, and Guidelines for their Preservation, 2. ETWB TCW No. 3/2006 - Tree Preservation |
Not applicable |
-
Existing trees to be retained
on site should be carefully protected during construction. - Trees unavoidably affected by the works should be transplanted where practical. -
Compensatory tree planting
should be provided to compensate for felled trees. |
Landscape Impacts
Approximately 300 trees
will be affected.
There
will be substantial negative impacts on the CBTS landscape character and
moderate residual impact on
|
|
|
|
·
|
|
- Control of night-time lighting. - Erection of decorative screen hoarding compatible with the surrounding setting. |
Visual Impacts
With implementation of mitigation measures, there will
still be some moderate negative visual impact on the VSRs in the front row of
high rise buildings along the waterfront from Central to North Point. Residual impacts VSRs further away the
|
Operational Phase |
All Landscape
Resources / Landscape Character Areas and Visual Sensitive Receivers within
the study area |
Not applicable |
1. EIAO and TM, particularly Annexes 10 and 18, 2. EIAO Guidance Note 8/2002, 3. Town Planning Ordinance (Cap 131), |
Not applicable |
-
Aesthetic design of buildings and road-related structures, including
viaducts, vent buildings, subways, footbridges and noise barriers and
enclosure. -
Shrub and Climbing Plants to soften proposed structures. |
Landscape Impacts
There
are slight negative impacts on
|
|
|
|
4. ETWB TCW No. 2/2004 - Maintenance of Vegetation and Hard Landscape Features, 5. ETWB TCW No. 29/2004 - Registration of Old and Valuable Trees, and Guidelines for their Preservation |
|
-
Buffer Tree and Shrub Planting to screen proposed roads and associated
structures. -
Aesthetic streetscape design. -
Aesthetic design of roadside amenity areas. |
Visual Impacts There will be substantial to moderate positive visual impact on
VSRs along the new waterfront as the landscape and visual amenity are
generally enhanced and strengthen by the proposed project. |
|
|
6. ETWB TCW No. 3/2006 - Tree Preservation |
|
|
|
|
Cultural Heritage Impact |
|
|
|
|
|
|
Construction Phase |
Cultural heritage
resources within the project boundary |
No adverse cultural
heritage impact is expected. |
1.
Antiquities and Monuments Ordinance (Cap.53) 2.
Environmental Impact Assessment Ordinance (EIAO) (Cap. 499,
S.16) |
Not applicable |
None |
Nil |
|
|
|
3.
Technical Memorandum on the Environmental Impact Assessment
Process (EIAO-TM) |
|
|
|
|
|
|
4.
Guidance Notes on Assessment of Impact on Sites of Cultural
Heritage in Environmental Impact Assessment Studies (GN-CH) |
|
|
|
|
|
|
5.
6.
Marine Archaeological Investigation Guidelines. |
|
|
|
Table 14.2 Summary
of Key Environmental Outcomes/ Benefits
Issue |
Environmental Outcomes/Benefits |
The Project |
Requirements: The Trunk Road is defined as the section of road extending from Rumsey
Street Flyover Extension to the IEC, comprising the CWB and the IECL. The Trunk Road will form an east-west
strategic route through Central and Wan Chai and is an essential element of
Government’s strategic transportation planning for |
|
Benefits: The Project provides key transport infrastructure so as to relieve
congestion on the strategic east-west routes through Central, Wan Chai and |
|
Potential
consequences without the Project:
(i)
Not able to relieve traffic congestion · Without the Trunk Road, the east-west strategic corridors of the
hinterland such as |
|
· From traffic point of view, given that the existing east-west corridor along the north shore is already overloaded at present, the future increase in general traffic growth on the Island due to territory-wide population and employment growth will exert additional pressure on the existing road network, thus causing further congestion and likely ‘gridlock’ situations to the north shore of Hong Kong Island, which may also have far reaching impacts to the harbour crossings. |
|
· A district traffic study has confirmed that a dual 3-lane Trunk Road (or Central-Wan Chai Bypass), together with intermediate slip roads, is required to divert traffic away from the existing east-west corridor and to provide adequate relief to the corridor and the local road network. The need for the Trunk Road has also been confirmed by the Expert Panel on Sustainable Transport Planning and Central-Wan Chai Bypass (‘Expert Panel’), which consists of independent local and overseas experts in the relevant fields. (ii)
Likely environmental conditions · In the absence of project,
similar air quality conditions along the northshore areas of Wan Chai, · In the absence of the project,
the noise environment of the project area would be increased due to the
natural growth of traffic. In the presence of the project, it would help
lessen the traffic burden on · Water quality at |
Development Alternatives |
Factors
such as engineering, social, and environmental aspects have been considered
in the light of different alternatives and construction methods. The following outcomes are found:
·
A “foreshore” alignment of Trunk Road is considered the most
reasonable and practical Trunk Road routeing, while “offshore” and “inland”
alignments are found not feasible due to conflict with existing development
and infrastructure. ·
Tunnel Option is selected in preference to Flyover Option, as it would
serve better to protect and preserve the Harbour. ·
Trunk Road Tunnel Variation 1 scheme is selected as the preferred
scheme in that it provides the necessary functional requirements of the Trunk
Road in meeting the overriding need and results in the least affected area of
the Harbour in conformance with the PHO. |
Environmentally Friendly Designs Recommended |
The
following environmental-friendly designs have been incorporated into the current project designs: |
|
l
The length of elevated road section
from east portal ramp of Trunk Road to existing IEC is approximately |
|
l A landscaped deck has been proposed over the east tunnel portal area of the Trunk Road. This landscaped deck provides visual and noise screening effect to the nearby sensitive receivers. |
|
l The current ventilation system proposed for the Trunk Road consists of three extraction fans for the East Tunnel Portal. Two fans will be adequate to extract all polluted air from the upstream tunnel section of the exit portal. The third fan will be used as standby in case one fan is under maintenance or out of order. Airflow direction sensors will be installed at the location of the exit portal to monitor the airflow direction of the tunnel. This sensor will be used to control the operation of tunnel portal extraction system to ensure that the target of “zero portal emission” will be met. |
|
l
The polluted tunnel air
extracted from the East Tunnel Portal will be filtered by electrostatic
precipitator installed at the |
Environmental Problems Avoided |
The
environmental problems avoided/minimized due to the current scheme include: ·
As a result of the tunnel design of the
Trunk Road, potential vehicle emissions and road traffic noise impacts from
the proposed Trunk Road on the air and noise sensitive receivers at Wan Chai and ·
Noonday Gun at CBTS would not be
affected and would be retained at the same location. ·
Kellett Island
Archaeological Site at RHKYC would not be affected. ·
Since the section of Trunk Road across RHKYC
under the current scheme is more than 20m below ground level, land
contamination impact associated with the construction of Trunk Road section
at RHKYC would be avoided. ·
With the zero portal emission design of the
East Tunnel Portal, potential air quality impact from the portal emission
would be avoided. In addition, the air quality of the East Tunnel Portal area
would be enhanced by locating the exhaust vent shaft
proposed at the East Breakwater of the CBTS and the electrostatic precipitator system at the |
Construction Air Quality Impact |
Environmental benefits of
environmental protection measures recommended: During
construction phase, potential air quality impacts include dust nuisance and
gaseous emissions from the construction plant and vehicles.. Mitigation
measures for dust impact include four times watering a day on the active work
areas and implementation of the Air Pollution Control (Construction Dust)
Regulation and good site practices. With the
implementation of the recommended control and mitigation measures, no adverse
air quality impacts are anticipated. Compensation areas included: Not required Population and environmental
sensitive receivers protected: Existing
air sensitive receivers within |
Operational Air Quality Impact |
Environmental benefits of environmental protection measures recommended: No unacceptable residual traffic emission impacts are anticipated at the existing and future ASRs. |
|
Air quality inside CWB Tunnel and deckover for planned HKCEC Atrium Link would comply with standards of EPD Tunnel Air Quality Guidelines. Air
quality monitoring for the operation performance of the Compensation areas included: Not
required Population and environmental sensitive receivers protected: Existing and planned air sensitive receivers within |
Construction Noise Impact |
Environmental benefits of
environmental protection measures recommended: The predicted mitigated noise levels
would range from 44 to 85
dB(A) at the representative NSRs. With
the implementation of quiet PME, movable barriers, temporary barriers, PME grouping
and good site practices for construction tasks under the Project and
implementation of the noise mitigation measures proposed in the CRIII
Reports, the noise levels at the NSRs selected for construction noise impact
assessment except N11,
N17, N18 and N20 would comply with the construction noise standard. |
|
Compensation areas included: Not required. |
|
Population and environmental
sensitive receivers protected: Noise sensitive receivers within |
Road Traffic Noise Impact |
Environmental benefits of
environmental protection measures recommended: The
following mitigation measures would be recommended: ·
about ·
about ·
about ·
about ·
about ·
low noise road surfacing for
the trunk road (except tunnel section and beneath the landscaped deck at the
eastern portal area) with speed limit of 70 km/hour; and ·
the openable windows of the
re-provisioned Predicted mitigated noise levels would be in the range of 60 dB(A) to 87 dB(A). Noise exceedances at the representative NSRs are due to the existing roads. The ‘new’ road noise contributions to the overall noise levels at all representative NSRs would be less than 1.0 dB(A) and the ‘new’ road noise levels would all be below the relevant noise criteria. No adverse noise impacts arising from the ‘new’ roads are predicted at any of the representative NSRs. |
|
In general, the noise environment for the NSRs would be improved by the Project and the direct noise mitigation measures. As compared with the prevailing noise environment, the predicted road traffic noise levels at the existing NSRs in year 2031 would be reduced by: · 1-10 dB(A) at N2 to N5 (Wan Chai area) · 1-3 dB(A) at N6 to N8 ( · 1-27 dB(A) at N12 to N17 (Tin Hau area) ·
1-27 dB(A) at N18 to N21
(North Point area) |
|
Compensation areas included: Not required. |
|
Population and environmental
sensitive receivers protected: Existing and planned NSRs within |
Fixed Plant Noise Impact |
Environmental benefits of environmental protection measures recommended: Operation of the proposed ventilation buildings would not impose adverse noise impacts on the existing and planned NSRs. Compensation areas included: Not required. Population and environmental
sensitive receivers protected: Noise sensitive
receivers within |
Water Quality Impact |
Environmental benefits of environmental protection measures recommended: Water quality impacts from land-based construction are associated with the surface runoff, effluent discharge from the site, and sewage from on-site construction workers. Impacts can be controlled to comply with the WPCO standards by implementing the recommended mitigation measures. No unacceptable residual impacts on water quality are anticipated. |
|
Compensation areas included: Not required. |
|
Population and environmental
sensitive receivers protected: Seawater intakes along the waterfront of |
Waste Management Implications |
Environmental benefits of environmental protection measures recommended: With the implementation of the recommended mitigation measures and practices, potential air, odour, noise, water quality for the handling, transportation and disposal of the identified waste arisings, no adverse environmental impacts are expected. Limited
amount of refuse and debris may be unintentionally brought from the site into
the harbour during heavy rains or typhoons. Given that the Project would not
worsen the shoreline configuration and the implementation of appropriate
control measures during construction phase, it is considered that the future
quantity of refuse to be found along the shoreline would be similar if not
better than the existing situation. With the implementation of a refuse
collection system within the project area, no insurmountable environmental
impact with regard to floating refuse would be anticipated during the
construction phase, or after completion of the Project. Compensation areas included: Not required. |
|
Population and environmental sensitive receivers protected: Water quality, air, and noise sensitive receivers at or near the
Project site, the waste transportation routes and the waste disposal site. |
Land Contamination Impact |
Environmental benefits of environmental protection measures recommended: No potential contaminative land uses were identified within the Study Area. As such, adverse land contamination impacts associated with the construction and operation of the Project is not expected. Compensation areas included: Not required. Population and
environmental sensitive receivers protected: No construction worker would be affected. |
Marine Ecological Impact |
Environmental
benefits of environmental protection measures recommended: No adverse ecological impact on marine ecology is expected. Compensation areas included: Not required. Population and
environmental sensitive receivers protected: No marine resources
would be adversely affected. |
Landscape and Visual Impact |
Environmental benefits of environmental protection measures recommended: · Under
the proposed development, approximately · The bowling greens will be temporarily affected by the construction of Slip Road 8 and will be reprovisioned within the Victoria Park during the operation phase. |
|
·
Approximately 300 trees will be
affected. None of these are LCSD
Champion Trees, Registered Old and Valuable Trees, rare or
endangered specie, all trees are common species. Approximately 1500 new trees and other
proposed planting will be planted in the new waterfront and along roadside
amenity areas after the new open space is built to compensate the felled
trees. |
|
·
During construction,
substantial negative impacts on the Fenwick Pier Street Public Open Space
landscape character and the CBTS landscape character, and moderate residual
impact on |
|
·
During operation, slight
negative impacts on ·
There will still be slight residual visual impact due to the provision
of noise barriers/screening/semi-enclosures in North Point. However, there will be significant
area of new waterfront open space from Tin Hau to |
|
·
With implementation of
mitigation measures during construction, there will still be some
moderate negative visual impact on the VSRs in the front row of high rise
buildings along the waterfront from Central to North Point. Residual impacts on VSRs further away
the ·
During operation, there will
be substantial to moderate positive visual impact on VSRs along the new
waterfront as the landscape and visual amenity are generally enhanced and
strengthened by the Project. Compensation areas included: Approximately Population and environmental
sensitive receivers protected: Existing and planned Landscape Resources ,
Landscape Character Area and VSR at and near the project site. |
Cultural Heritage Impact |
Environmental benefits of environmental protection measures recommended: No archaeological impact due to the construction activities is not expected. Compensation areas included: Not required. Population and
environmental sensitive receivers protected: No archaeological resources would
be affected. |
Construction
Phase
Operational Phase