2          PROJECT DESCRIPTION

2.1        Site Location

2.2        EIA Study Area

2.3        Project Requirements, Scope and Benefits

2.4        Construction Methods and Engineering Requirements

2.5        Operation of the Project

2.6        Works Programme

2.7        Related Projects

 

 

 

2                    PROJECT DESCRIPTION

 

2.1              Site Location

 

2.1.1          Road P2 runs east-west from Central to connections with the existing road network in Wan Chai North.  The section of Road P2 to be implemented under the WDII project starts at the boundary of CRIII at the west and connects to the existing Hung Hing Road at the east.  Road P2 is a dual 2-lane primary distributor that serves both local east-west movements and the distribution of north-south traffic movements. The location of Road P2 and other roads which are classified as primary/district distributor roads under the WDII project is shown in Figure 1.2b.

 

2.2              EIA Study Area

 

2.2.1          The following definitions of the study areas have been adopted with reference to the EIA Study Brief registered under the EIAO:

 

·                     Air Quality Impact: the assessment area should include the area within 500 m from the boundary of the Project;

 

·                     Noise Impact Assessment: the assessment area should include the area within 300 m from the boundary of the Project;

 

·                     Water Quality Impact Assessment: the assessment area should include the areas within and 300m extended beyond the boundary of the Project, plus the Victoria Harbour Water Control Zone (WCZ), the Eastern Buffer WCZ and the Western Buffer WCZ as declared under the Water Pollution Control Ordinance;

 

·                     Waste Management: the assessment will focus on areas within the boundary of the Project;

 

·                     Land Contamination: the assessment area for land contamination impact will include any potentially contaminated sites identified in this EIA;

 

·                     Landscape and Visual Impact:  the area for landscape impact assessment should include all areas within 100 m extended from the boundary of the Project, while the assessment area for the visual impact assessment should be defined by the visual envelope from the Project and associated works;

 

·                     Marine Ecology: the assessment for marine ecological impact will focus on the area within the Project boundary; and

 

·                     Cultural Heritage Impact: the assessment for cultural heritage impact will focus on the area within the Project boundary.

 


2.3              Project Requirements, Scope and Benefits

 

Project Scope and Requirements

 

2.3.1          The major element of the future ground level road system is Road P2, which runs east-west from Central to connections with the existing road network in Wan Chai North.  Road P2 is a dual 2-lane primary distributor that serves both local east-west movements and the distribution of north-south traffic movements.

 

2.3.2          The Road P2 alignment has been planned to run over the top of the Trunk Road tunnel through CRIII and the HKCEC water channel, to the connection with Fleming Road, in order to minimize the overall road “footprint” and area of land sterilized by highway infrastructure. New junctions are formed along Road P2 with the north-south roads. 

 

2.3.3          Along the Wan Chai shoreline, the existing Hung Hing Road in front of the Wan Chai North PTI is realigned to connect with the new Road P2 / Fleming Road junction, but the current Hung Hing Road alignment in front of the Wan Chai Sports Ground is retained.  The retention further east of existing Hung Hing Road alignment and existing Hung Hing Road Flyover means there is no intrusion by new roads into the new Wan Chai waterfront area.

 

2.3.4          The at-grade road network also provides connections to slip roads of the Trunk Road at Wan Chai North area.

 

2.3.5          All existing road connections from Wan Chai North to the Wan Chai area south of Gloucester Road are maintained.

 

            Project Benefits          

2.3.6          The primary distributor serves both local east-west movements and the distribution of north-south traffic movements.  The new junction with Fleming Road / Hung Hing Road will improve traffic conditions along Fleming Road, by moving the critical bottleneck junctions (Fleming Road / Hung Hing Road and Fleming Road / Harbour Road) further apart to alleviate the current congestion caused by tailbacks along Fleming Road through Harbour Road.

2.3.7          The at-grade road network provides connections to slip roads of the Trunk Road at Wan Chai North area. The slip road connections are essential in meeting traffic demand and enabling the Trunk Road to adequately perform its function of relieving traffic from the overloaded Connaught Road Central / Harcourt Road / Gloucester Road corridor.

 

Consequences of Not Proceeding with the Project

            Not able to relieve traffic congestion

2.3.8          The primary distributor is important in serving both local east-west movements and the distribution of north-south traffic movements.  Without the primary distributor, most of the critical junctions in Wan Chai north area will have negative reserve capacities.  Most of the traffic from the Central waterfront heading east would access to Connaught Road Central causing the junction of Connaught Road and Connaught Place to operate over capacity.  The junction of Fleming Road and Harbour Road would operate over capacity during the AM peak which reveals that the traffic congestion problem along Fleming Road and Harbour Road would remain unresolved.

2.3.9          Without the slip road connections, the Trunk Road cannot adequately perform its function of relieving traffic from the overloaded Connaught Road Central / Harcourt Road / Gloucester Road corridor.  

Development Alternatives

2.3.10      Different scenarios for the road networks (e.g. with and without the Road P2 and Wan Chai slip road connections) have been examined in the Envisioning Stage - Expert Panel Forum on Sustainable Transport Planning and Central-Wan Chai Bypass in September 2005.  Details shall refer to the “Submission to the Expert Panel by Transport Department” and the “Supplementary Note to the Expert Panel by Transport Department”, which can be viewed at the HEC website: http://www.harbourfront.org.hk/eng/content_page/envis_stage.html?s=1. The Expert Panel recognizes the need for Road P2 and supports the provision of slip roads at the Wan Chai area to magnify the benefits of the CWB.  The Report of the Expert Panel can also be viewed on the
HEC website at: http://www.harbourfront.org.hk/eng/content_page/doc/report_of_the_expert_panel.pdf.

 

2.4              Construction Methods and Engineering Requirements

 

2.4.1          Road P2 in WDII is an at-grade road.  The construction method for Road P2 is similar to typical at-grade road works construction with sub-base, road drainages, road surfacing, traffic signs, road lightings, road markings, road junctions and central reserve etc.

 

2.5              Operation of the Project

 

2.5.1          Operational activities, on completion of the DP2, would comprise essentially traffic movements on the new roads. 

 

2.6              Works Programme

 

2.6.1          The Road P2 and other ground level roads construction works are anticipated to commence on site in 2014, with completion of the works by 2016.  A construction programme is presented in Appendix 2.5 for reference.

 

2.7              Related Projects

 

2.7.1          The following projects are related to the WDII and CWB project:

 

(i)                  Civil Engineering and Development Department's CRIII project, comprising reclamation along the Central waterfront for transport infrastructure needs (including CWB and NIL) and basic land use requirements.  A section of CWB tunnel will also be constructed under CRIII project.  Construction will take place from February 2003 to September 2012.

 

(ii)                Trade Development Council’s Atrium Link Extension project, comprising a link bridge spanning across the water channel between the Hong Kong Convention and Exhibition Centre (HKCEC) Phase I and HKCEC Extension.   Construction will take place from May 2006 to March 2009.