4.2 Environmental Legislation, Policies, Plans, Standards
and Criteria
4.3 Description of the Environment
4.6 Identification of Environmental Impacts
4.7 Prediction and Evaluation of Environmental Impacts
4.8 Mitigation of Adverse Environmental Impacts
4.9 Evaluation of Residual Impacts
4.10 Environmental Monitoring and Audit
·
EIAO-TM
·
TM
on Noise from Construction Work other than Percussive Piling (GW-TM)
·
TM
on Noise from Percussive Piling (PP-TM)
·
TM
on Noise from Construction Work in Designated Areas (DA-TM)
·
TM
on Noise from Places other than Domestic Premises, Public Places or
Construction Sites (IND-TM)
Table 4.1 Construction Noise Criteria for Activity other than Percussive Piling
Time Period |
Basic Noise Level (BNLs), Leq (30-min) dB(A) |
||
ASR A |
ASR B |
ASR C |
|
Evening
(1900 to 2300 hours) (1) |
60 |
65 |
70 |
Night (2300 to 0700 hours) |
45 |
50 |
55 |
Notes: (1) Includes
Sundays and Public Holidays during daytime and evening
Table 4.2 Acceptable Noise Levels for Percussive Piling
NSR Window Type or Means of Ventilation |
ANL, Leq (30-min) dB(A) |
NSR (or part of NSR) with no
windows or other opening |
100 |
NSR
with central air conditioning system |
90 |
NSR
with windows or other openings but without central air conditioning system |
85 |
Note: 10
dB(A) shall be subtracted from the ANLs shown above for NSRs which are
hospitals, medical clinics, educational institutes, courts of law or other NSRs
which are considered by the Authority to be particularly sensitive to noise.
Table 4.3 Permitted Hours of Operation for Percussive Piling
Amount by which
Corrected Noise Level (CNL) exceeds Acceptable Noise Level (ANL), CNL-ANL |
Permitted hours of operation
on any day not being a general holiday |
-10 dB(A) <
CNL-ANL |
Nil |
CNL-ANL £
-10 dB(A) |
0700 to 1900 |
·
erecting
or dismantling of formwork or scaffolding
·
loading,
unloading or handling of rubble, wooden boards, steel bars, wood or scaffolding
material
·
hammering
·
70
dB(A) at the façades of dwellings, hotels, offices
·
65
dB(A) at the façades of schools, places of public worship, courts of law,
places where unaided voice communication is required
·
55
dB(A) at the façades of hospital
·
the
predicted overall noise level from the new road, together with other traffic
noise in the vicinity must be above a specified noise level (for example, 70
dB(A) for domestic premises and 65 dB(A) for educational institutions, all in L10
(1 hour)); and
·
the
predicted overall noise level is at least 1.0 dB(A) more than the prevailing
traffic noise level, that is, the total traffic noise level existing before the
works to construct the road commence; and
·
the
contribution to the increase in the predicted overall noise level from the new
road must be at least 1.0 dB(A).
·
‘Existing’
Roads are the roads that are unchanged or subject to minor changes by the
Project.
·
‘New’
Roads are the roads that are completely new or existing road sections that
undergo major modifications that would cause significant traffic noise impact
(i.e. road sections within the meaning of Item A.1 of Schedule 2 of EIAO).
Modifications to
Table 4.4 Representative Existing Noise Sensitive Receivers
NSR |
Section |
Location |
Use |
Ground elevation (mPD) |
No. of Floors |
N1 |
Wanchai |
HKAPA
(Open Arena) |
Performing
Arts Centre |
5.0 |
G/F |
N2 |
Wanchai |
Causeway
Centre |
Residential |
4.0 |
42 |
N3 |
Wanchai |
|
Residential |
3.7 |
12 |
N4 |
Wanchai |
|
Residential
|
3.7 |
18 |
N5 |
Wanchai |
Hyde
Centre |
Residential |
3.7 |
22 |
N6 |
|
Elizabeth
House |
Residential |
3.7 |
21 |
Table 4.5 Summary of Construction Tasks and Stages
Item |
Tasks and Stages |
Construction Period |
Main Construction Elements |
1
|
|||
1.1 |
|
January 2009 to February 2016 |
Temporary Breakwater Relocation Mooring to Temporary CBTS Relocation Mooring back to CBTS |
1.2 |
CBTS Temporary Reclamation Stage 1 |
August 2009 to May 2012 |
Dredging, temp seawalls and filling (TCBR1) CWB Tunnel (TCBR1) CWB Tunnel ( |
1.3 |
CBTS Temporary Reclamation Stage 2 |
November 2009 to May 2012 |
Dredging, temp seawalls and filling (TCBR2) CWB Tunnel (TCBR2) |
1.4 |
CBTS Temporary Reclamation Stage 3 |
January 2011 to April 2014 |
Dredging, temp seawalls and filling (TCBR3) CWB Tunnel (TCBR3) |
1.5 |
CBTS Temporary Reclamation Stage 4 |
May 2012 to November 2015 |
Dredging, temp seawalls and filling (TCBR4) CWB Tunnel (TCBR4) |
1.6 |
Temp Diversion of Cooling Water System |
October 2010 to January 2016 |
|
1.7 |
Promenade along CBTS |
November 2015 to March 2016 |
|
1.9 |
|
August 2013 to March 2015 |
Slip Road 8 &Tunnel Transplant Trees in Victoria Park At-grade Road, Landscaped deck Reinstate Landscape work in VP |
2
Ex-PCWA Temporary Reclamation |
|||
2.1 |
Temporary Reclamation PCWA Stage 1 |
February 2009 to May 2012 |
Dredging, Filing and Seawall (PCWAE) CWB Tunnel (PCWAE) |
2.2 |
Temporary Reclamation PCWA Stage 2 |
March 2012 to May 2015 |
Dredging, Filing and Seawall (PCWAW) CWB Tunnel (PCWAW) |
3
Wan Chai Reclamation |
|||
3.1 |
Wan Chai Reclamation Stage 1 |
January 2009 to February 2011 |
Dredging, Seawalls and Filling Drainage Culverts Cooling Water Syetem CWB Tunnel(WCR1) |
3.2 |
Wan Chai Reclamation Stage 2 |
January 2011 to May 2013 |
Dredging, Seawalls and Filling CWB Tunnel Promenade |
3.3 |
Wan Chai Reclamation Stage 3 |
April 2011 to March 2015 |
Dredging, Seawalls and Filling CWB Tunnel Promenade |
3.4 |
Wan Chai Reclamation Stage 4 |
October 2012 to March 2015 |
Dredging, Seawalls and Filling Drainage Culverts CWB Tunnel Promenade |
3.6 |
Ferry Pier Reprovisioning |
February 2009 to May 2011 |
Temporary Ferry Piers New Ferry Piers |
3.7 |
Helipad Reprovisioning |
January 2009 to June 2010 |
Reprovisioning at HKCEC |
3.8 |
Sewage Outfall |
October 2009 to April 2011 |
Marine Section – Submarine Pipelines Land Section – New Pipeline |
3.9 |
WSD’s Salt Water Pumping Station |
February 2009 to October 2010 |
Construct New Pumping Station |
3.10 |
Roads |
October 2014 to September 2015 |
Road P2 |
4
HKCEC Reclamation |
|||
4.1 |
HKCEC Reclamation Stage 1 (Water Channel) |
January 2009 to April 2016 |
Dredging, Seawalls and Filling Cooling Water Systems CWB Tunnel |
4.2 |
HKCEC Reclamation Stage 2 |
January 2009 to March 2014 |
Dredging, Seawalls and Filling Drainage Culverts CWB Tunnel |
4.3 |
MTR Tunnel Crossing |
October 2010 to February 2012 |
Piling for Tunnel Units and Deck Tunnel and Deck Construction |
4.4 |
HKCEC Reclamation Stage 3 |
March 2011 to October 2013 |
Dredging, Seawalls and Filling Drainage Culverts CWB Tunnel |
4.5 |
Roads |
March 2014 to November 2015 |
Road P2 |
5
Cross Harbour Watermains |
|||
5.1 |
Submarine Pipeline |
January 2009 to September 2010 |
Lay New Submarine Pipeline |
5.2 |
Lands Sections |
September 2009 to May 2010 |
|
6.0
North Point Reclamation |
|||
6.1 |
North Point Reclamation Stage 1 |
January 2009 to October 2010 |
Dredging, Seawalls and Filling CWB Tunnel (NPR1) |
6.2 |
North Point Reclamation Stage 2 |
April 2009 to November 2012 |
Dredging, Seawalls and Filling (NPR2E, NPR2W) CWB Tunnel (NPR2W) |
6.3 |
Promenade |
August 2016 to December 2016 |
Promenade (NP) Final |
7.0
Construction of |
|||
7.2 |
IEC Connection Work |
October 2010 to May 2016 |
IEC East Bound (E/B) (HFS to Mainline) IEC E/B Traffic Diversion Reconstruction IEC West Bound(W/B) IEC W/B Traffic Diversion Mainline Connection to IEC |
7.3 |
East Portal and IEC Connection |
May 2015 to August 2016 |
Portal Construction Traffic Diversion IEC E/B |
10 |
|
November 2011 to May 2016 |
|
10.1 |
|
November 2012 to September 2013 |
Superstructure of the Building E&M Work |
10.2 |
|
February 2015 to November 2015 |
Substructure of the Building Superstructure of the Building E&M Work |
10.3 |
|
January 2014 to January 2015 |
Substructure of the Building Superstructure of the Building E&M Work |
Road Traffic Noise
Road
Speed
Limit
Trunk Road (Open Section & Underneath Landscaped deck)
Trunk Road in Tunnel
Road P2
Slip Roads
Operation Roads
·
Road P2 from
·
Road P2 from CRIII to
· DP1 - Central-Wanchai Bypass (CWB) including its road tunnel and slip roads
Table 4.6 Summary of
Unmitigated Construction Noise Levels at Representative NSRs During
Representative NSRs |
Predicted Unmitigated Construction Noise Levels during |
N1 |
76 - 81 |
N2 |
72 - 80 |
N3 |
71 |
Wan Chai Area (NSRs N1 – N5)
Table 4.7 Summary of
Mitigated Construction Noise Levels at Representative NSRs during
Representative NSRs |
Predicted Mitigated Construction Noise Levels during |
N1 |
69 - 72 |
N2 |
65 - 72 |
N3 |
64 |
(i) is not higher than the noise standard; and
(ii) has no significant contribution to the overall noise from other existing roads, if the cumulative noise level (i.e. noise from the new road together with other existing roads) exceeds the noise standard.
· Only well-maintained plant shall be operated on-site and plant shall be serviced regularly during the construction program.
· Silencers or mufflers on construction equipment shall be utilised and shall be properly maintained during the construction program.
· Mobile plant, if any, shall be sited as far away from NSRs as possible.
· Machines and plant (such as trucks) that may be in intermittent use shall be shut down between works periods or shall be throttled down to a minimum.
· Plant known to emit noise strongly in one direction shall, wherever possible, be orientated so that the noise is directed away from the nearby NSRs.
· Material stockpiles and other structures shall be effectively utilised, wherever practicable, in screening noise from on-site construction activities.