14.6 Waste
Management Implications
14.7 Land
Contamination Impact
14.9 Landscape
and Visual Impact
14.10 Cultural
Heritage Impact
14.11 Environmental
Monitoring and Audit
The Project is a designated project in
accordance with Item C1 of Part 1 of Schedule 2 of the EIAO, which specifies
“Reclamation works including associated dredging works”.
Table 14.1 Summary
of Environmental Impacts Associated with the Project
Environmental Issue |
Sensitive
Receivers/ Assessment Points |
Impact Prediction
Results |
Relevant Standards/
Criteria |
Extents of
Exceedances |
Impact Avoidance
Measures/ Mitigation Measures |
Residual Impacts |
Air Quality |
|
|
|
|
|
|
Construction Phase |
48 assessment points |
1-hour Average TSP
Conc.: 95 24-hour Average TSP
Conc.: 86 |
EIAO-TM and Air
Quality Objective |
Nil |
Four times daily watering with complete coverage of active construction area Requirements of the Air Pollution Control (Construction Dust) Regulation The following mitigation measures, good site practices and a comprehensive dust monitoring and audit programme are recommended to minimise cumulative dust impacts. ·
Strictly
limit the truck speed on site to below |
Nil |
|
|
|
|
|
·
Watering
during excavation and material handling; |
|
|
|
|
|
|
·
Provision
of vehicle wheel and body washing facilities at the exit points of the site,
combined with cleaning of public roads where necessary; and |
|
|
|
|
|
|
·
Tarpaulin
covering of all dusty vehicle loads transported to, from and between site
locations. |
|
Operational Phase |
In view of the project nature, no adverse air quality impact during the operation phase would be anticipated. |
|
Not Applicable |
Nil |
Not Applicable |
Nil |
Noise |
|
|
|
|
|
|
Construction Phase |
N1, N2, N3, N6, N8,
N13, N15, N17, N18 and N20 |
Predicted noise levels
would be in the range of 61 to 86 dB(A). |
Domestic premises:
75dB(A) Educational
institutions: 70 dB (A) during normal teaching periods & 65 dB(A) during
examinations |
Domestic premises:
Exceed the noise standard by up to 26dB(A). Educational
institutions: Exceed the noise standard by 1 dB(A) during normal teaching
period and up to 6 dB(A) during examination period. |
Use of quiet equipment
to mininise construction noise impact. |
With the use of quiet PME for the Project and
implementation of the noise mitigation measures for other Schedule 2 DPs and
CRIII project, the predicted cumulative noise levels at the NSRs selected for construction noise impact
assessment except N20 during examination period
would comply with the construction noise standard. For N20 (i.e. |
Water Quality |
|
|
|
|
|
|
Construction Phase |
All water sensitivity
receivers in |
The model results
indicate exceedances of WSD water quality (SS) criterion for flushing water
intakes (at |
WSD water quality
criterion for SS: < 10 mg/l |
Full compliance with
the assessment criteria with implementation of the recommended measures. |
Restriction on the
maximum dredging rates at the sewage pipelines zone, water mains zone, TWB,
TPCWA, HKCEC Stage 1 & 3 as well as the western
seawall of WCR1 which is close to the WSD intake at Wan Chai; |
Nil |
Full compliance with
the assessment criterion for sedimentation rate |
Target SS level at
Admiralty Centre and MTRC cooling water intakes: < 40 mg/l |
Deployment of silt
curtains around seawall dredging and seawall trench filling in NPR, TCBR, WCR
and HKCEC areas. |
||||
|
Sedimentation rate at
corals: < |
Deployment of silt screens at selected seawater
intakes |
||||
Operational Phase |
All water sensitivity
receivers in |
Operation of WDII
reclamation would not cause unacceptable impacts upon the water quality in |
Relevant WQO for
marine water: |
No WQO exceedance is
induced by the Project |
Existing practices
currently adopted by Marine Department for collection of floating refuse at
the Project site should be continued during the operational
phase of this Project. |
Nil |
TIN level: <0.4
mg/l for annual mean |
||||||
UIA level: <0.021
mg/l for annual mean |
||||||
Depth-averaged DO
level: > 4 mg/l for 10th percentile |
||||||
Bottom DO level: |
||||||
Temperature increase:
< 2oC from background |
||||||
Waste Management Implications |
|
|
|
|
|
|
Construction Phase |
Not applicable |
Main waste: dredged marine sediment with a total volume of approx. |
1. Waste Disposal Ordinance (Cap.
354) |
Not applicable |
Refer to Table 13.4 |
Nil |
|
|
Other wastes: general refuse from
the workforce; chemical waste from plant and equipment maintenance; and
C&D material from excavation works and the demolition of existing
structures. |
2. Waste Disposal (Chemical Waste)
(General) Regulation (Cap. 354) |
|
|
|
|
|
3. Land (Miscellaneous Provisions)
Ordinance (Cap. 28) |
|
|
|
|
|
|
4. Public Health and Municipal
Services Ordinance (Cap. 132) - Public Cleansing and Prevention of Nuisances
Regulation |
|
|
|
|
|
|
|
5. Annexes 7 & 15 of EIAO TM |
|
|
|
Land Contamination Impact |
|
|
|
|
|
|
Construction Phase |
Construction Workers
via direct ingestion of and dermal contact with contaminated soils. |
No land contamination
impact is expected. |
ProPECC PN3/94 - “Contaminated Land Assessment and
Remediation” “Guidance Notes for Investigation and
Remediation of Contaminated Sites of: Petrol Filling Stations, Boatyards, and
Car Repair /Dismantling Workshops |
None |
None |
None |
Marine Ecological Impacts |
|
|
|
|
|
|
Construction Phase |
Ecological resources
in the assessment area |
Habitat loss -
Permanent: |
Not applicable |
Not applicable |
Avoidance - Revised design of alternative Trunk Road constructed in tunnel to avoid permanent loss of large area of marine habitats Minimization -
Translocation of all the coral colonies found at
coastlines within -
Mitigation measures to control water quality |
No adverse residual impact as loss of approximately |
|
|
-
Temporary: |
|
|
||
|
|
Changes in water
quality -
More than 30% increase of SS at the immediate vicinity outside
reclamation area -
Insignificant elevation of SS at far-field sensitive receivers -
Level of TIN is predicted to be slightly higher than WQO standard at
several locations immediately outside reclamation area |
(See water quality
assessment) |
(See water quality
assessment) |
-
Mitigation measures to avoid disturbance impact to nearby waterbird
population Other Measures -
Construction of about |
|
|
|
-
Minimum depth-averaged DO at HKCEC is predicted to be slightly lower
than 4.0 mg/L |
|
|
|
|
|
|
Disturbance impact |
Not applicable |
Not applicable |
|
|
Operational Phase |
Ecological resources
in the assessment area |
Disturbance impact |
Not applicable |
Not applicable |
Mitigation measures are not required as no adverse impact are predicted. |
Nil |
Potential change in water quality in |
(See water quality assessment) |
(See water quality assessment) |
||||
Landscape and Visual Impact |
|
|
|
|
|
|
Construction Phase |
All Landscape Resources / Landscape
Character Areas and Visual Sensitive Receivers within the study area |
-
During construction, there
will be moderate residual impact on the |
Not applicable |
Not applicable |
-
Control of night-time
lighting. - Erection of decorative screen hoarding compatible with the surrounding setting. |
Landscape Impacts
The reclamation work will not
affect any existing trees.
The impact on the |
|
|
|
|
|
|
Visual Impacts
With implementation of mitigation
measures during construction, there will still be some moderate negative
visual impact on the VSRs in the front row of high rise buildings along the
waterfront from Central to North Point.
Residual impacts on VSRs further away the |
Operational Phase |
All Landscape Resources / Landscape Character Areas and Visual Sensitive Receivers within the study area |
-
During operation, slight
negative impacts on the |
1. EIAO and TM, particularly Annexes 10 and 18, 2. EIAO Guidance Note 8/2002, 3. Town Planning Ordinance (Cap 131), 4. ETWB TCW No. 2/2004 - Maintenance of Vegetation and Hard Landscape Features, 5. ETWB TCW No. 29/2004 - Registration of Old and Valuable Trees, and Guidelines for their Preservation, 6. ETWB TCW No. 3/2006 - Tree Preservation |
Not applicable |
-
Aesthetic design of proposed waterfront promenade. |
Landscape Impacts
The reclamation work will not
affect any existing trees.
The impact on Visual Impacts During operation, there will be substantial to moderate positive visual impact on
VSRs along the new waterfront as the landscape and visual amenity are
generally enhanced and strengthen by the proposed project. Visual impacts from the hinterland and
harbour will be insubstantial |
Cultural Heritage Impact |
|
|
|
|
|
|
Construction Phase |
Marine archaeological
resources in |
Since there is no
archaeological material present within the study area, no adverse cultural
heritage impact is expected. |
1.
Antiquities and Monuments Ordinance (Cap.53) 2.
Environmental Impact Assessment Ordinance (EIAO) (Cap. 499,
S.16) |
Not applicable |
No further
archaeological investigation or mitigation measures is required |
Nil |
|
|
|
3.
Technical Memorandum on the Environmental Impact Assessment
Process (EIAO-TM) |
|
|
|
|
|
|
4.
Guidance Notes on Assessment of Impact on Sites of Cultural
Heritage in Environmental Impact Assessment Studies (GN-CH) |
|
|
|
|
|
|
5.
6.
Marine Archaeological Investigation Guidelines. |
|
|
|
Table
14.2 Summary
of Key Environmental Outcomes/ Benefits
Issue |
Environmental Outcomes/Benefits |
The Project |
Requirements: The Project is driven by the need for the
implementation of the Trunk Road, which is defined as the section of road
extending from Rumsey Street Flyover Extension to the IEC, comprising the CWB
and the IECL. The Trunk Road will
form an east-west strategic route through Central and Wan Chai and is an
essential element of Government’s strategic transportation planning for The Project can create a coherent pattern of land use and for the development of an appropriate waterfront ‘edge’ to the existing urban area. The Project will therefore consider imaginative measures to develop a high quality waterfront for the enjoyment of the public and tourists. |
1.
|
Benefits: The reclamation provides essential land for the construction of
key transport infrastructure including the Trunk Road and the NIL and
SCL. The road and rail routes are
required to relieve congestion on the strategic east-west routes through
Central, Wan Chai and The land formed also provides opportunity to create an attractive
waterfront for the enjoyment of the public. At present, large parts of the Wan
Chai, The project also provides opportunity to enhance the existing odour at the south-west corner of the CBTS by removal of the polluted sediments which will be carried out in conjunction with the dredging for the Trunk Road reclamation. |
|
Potential
consequences without the Project:
(i) Not able to relieve traffic
congestion · Without the Trunk Road, the east-west strategic corridors of the
hinterland such as · From traffic point of view, given that the existing east-west corridor along the north shore is already overloaded at present, the future increase in general traffic growth on the Island due to territory-wide population and employment growth will exert additional pressure on the existing road network, thus causing further congestion and likely ‘gridlock’ situations to the north shore of Hong Kong Island, which may also have far reaching impacts to the harbour crossings. · A district traffic study has confirmed that a dual 3-lane Trunk Road (or Central-Wan Chai Bypass), together with intermediate slip roads, is required to divert traffic away from the existing east-west corridor and to provide adequate relief to the corridor and the local road network. The need for the Trunk Road has also been confirmed by the Expert Panel on Sustainable Transport Planning and Central-Wan Chai Bypass (‘Expert Panel’), which consists of independent local and overseas experts in the relevant fields. (ii) Not able to provide land for NIL and
SCL · Land formed under the Project, in addition to providing for the construction of the Trunk Road, also provides for the construction of the NIL and the SCL. Should the Project not proceed, implementation of these rail routes will be severely constrained. This will have consequential adverse impacts on the planning and provision of public transport infrastructure. (iii) No improvement of the waterfront ·
Should the Trunk Road not be
implemented the requirement for land formation is likely to fall away and
opportunities to improve the existing waterfront would be limited. (iv) Likely environmental conditions · Water quality at |
Development
Alternatives |
The size of reclamation, and the corresponding shoreline configuration, is determined based on the minimum extent of reclamation that is needed to meet the essential engineering requirements for the construction of the Trunk Road. It is the minimum reclamation required to meet the overriding need for the Trunk Road. A step by step approach is taken to ensure the reclamation is the minimum extent required. The first step is to confirm that there is an overriding and present need for the Trunk Road. The next step is to identify any “no-reclamation options”. If there is no reasonable alternative to reclamation, the third step is to ensure that the reclamation is restricted to only the minimum amount necessary to meet the overriding public need. |
Environmentally
Friendly Designs Recommended |
The following environmental-friendly designs have been incorporated
into the current project designs: l
The extent of reclamation under the current
scheme has been minimized. Compared to original scheme in the previous
approved EIA report, the reclamation area is substantially reduced by
approximately l
Smooth curves have been adopted at indented
areas rather than sharp corners along the shoreline. This smoothing of the shoreline will
enhance flows and prevent accumulation of pollutants or floating refuse. |
Environmental
Problems Avoided |
The environmental problems avoided/minimized due to the current scheme
include: ·
Potential environmental impacts including
construction dust, water quality and marine ecology would be reduced compared
to the original scheme in the approved EIA report due to the decrease in the
extent of reclamation. ·
As there is no longer any development on
reclaimed land formed with marine sediments in place within CBTS, potential
biogas problem would be avoided in the current scheme. |
Construction Air
Quality Impact |
Environmental
benefits of environmental protection measures recommended: |
|
During construction phase, potential air quality impacts include dust
nuisance and gaseous emissions from the construction plant and vehicles and dredgers
and odour impact from contaminated sediment during dredging in the vicinity
of Police Officers’ Club. |
|
Mitigation measures for dust impact include four times watering a day
on the active work areas and implementation of the Air Pollution Control
(Construction Dust) Regulation and good site practices. |
|
For the dredging activities carried out in the vicinity of Police
Officers’ Club, the dredging operation will be restricted to only 1 small close
grab dredger to minimise the odour impact during the dredging activity. The dredging rate should be reduced as
much as practicable for area in close proximity to the Police Officers’ Club.
|
|
With the implementation of the recommended control and mitigation
measures, no adverse air quality impacts are anticipated. Compensation
areas included: Not
required Population
and environmental sensitive receivers protected: Existing air sensitive receivers within |
Operational Air
Quality Impact |
Environmental
benefits of environmental protection measures recommended: In view of the project nature, no adverse air quality impact during the
operation phase would be anticipated. Compensation
areas included: Not
required Population
and environmental sensitive receivers protected: Existing and planned air sensitive receivers within |
Construction Noise
Impact |
Environmental
benefits of environmental protection measures recommended: · The predicted mitigated noise levels would range from 57 to 74 dB(A) at the representative NSRs. With the implementation of quiet PME under the Project and the noise mitigation measures under other concurrent Schedule 2 DPs, the noise levels at the NSRs selected for construction noise impact assessment except N20 during examination periods would comply with the construction noise standard. |
|
Compensation
areas included: Not required. |
|
Population
and environmental sensitive receivers protected: Noise
sensitive receivers within |
Operation Noise Impact |
Environmental
benefits of environmental protection measures recommended: In view of the project nature, no adverse
noise impact during the operation phase would be anticipated |
|
Compensation
areas included: Not
required Population
and environmental sensitive receivers protected: Not applicable. |
Water Quality Impact |
Environmental
benefits of environmental protection measures recommended: · The major water quality impact associated with dredging activities is the elevation of SS within the marine water column. Provided the recommended mitigation measures are implemented, including restriction on the maximum dredging rates, the deployment of silt curtains at the dredging and filling areas, and installation of silt screens at selected seawater intakes, there will be no unacceptable residual water quality impact due to the proposed reclamation works. · General construction activities associated with the construction of WDII reclamation could lead to site runoff containing elevated concentrations of SS and associated contaminants that may enter into the marine water. However, it is anticipated that the water quality impacts will generally be temporary and localised during construction. Therefore, no unacceptable residual water quality impacts are expected during the construction of the proposed infrastructure, provided all of the recommended mitigation measures are implemented and all construction site / works area discharges comply with the TM-DSS standards. · Adverse water quality impacts associated with the operation of WDII reclamation are not expected. Thus, there will be no residual impact associated with the operation of the Project. Compensation
areas included: Not required. Population
and environmental sensitive receivers protected: Seawater intakes along the waterfront of |
Waste Management
Implications |
Environmental benefits of environmental protection measures recommended: With the implementation of the recommended mitigation measures and practices, potential air, odour, noise, water quality for the handling, transportation and disposal of the identified waste arisings, no adverse environmental impacts are expected. |
|
Limited amount of refuse and debris may be
unintentionally brought from the site into the harbour during heavy rains or
typhoons. Given that the Project would not worsen the shoreline configuration
and the implementation of appropriate control measures during construction
phase, it is considered that the future quantity of refuse to be found along
the shoreline would be similar if not better than the existing situation.
With the implementation of a refuse collection system within the project
area, no insurmountable environmental impact with regard to floating refuse
would be anticipated during the construction phase, or after completion of
the Project. |
|
Compensation
areas included: Not required. |
|
Population and environmental sensitive
receivers protected: Water quality, air, and noise sensitive
receivers at or near the Project site, the waste transportation routes and
the waste disposal site. |
Land Contamination
Impact |
Environmental benefits of environmental protection measures recommended: No potential contaminative land uses were identified within the Study Area. As such, adverse land contamination impacts associated with the construction and operation of the Project is not expected. Compensation
areas included: Not
required. Population and environmental sensitive receivers protected: No construction worker would be affected. |
Marine Ecological
Impact |
Environmental benefits of environmental protection measures
recommended: The
benthic, intertidal and subtidal habitats within the affected area are of
very low ecological value and direct impact on some small and isolated coral
colonies attached to movable boulders at the coastlines within
|
|
Population
and environmental sensitive receivers protected: Ecological resources in the assessment area. |
Landscape and Visual
Impact |
Environmental benefits of
environmental protection measures recommended: |
|
·
Approximately |
|
·
Under the proposed development, approximately · With implementation of mitigation
measures during construction, there will still be some moderate negative
visual impact on the VSRs in the front row of high rise buildings along the
waterfront from Central to North Point.
Residual impacts VSRs further away the Compensation areas included: Approximately Population
and environmental sensitive receivers protected: Existing and
planned Landscape Resources , Landscape Character Area and VSR at and near
the project site. |
Cultural Heritage
Impact |
Environmental
benefits of environmental protection measures recommended: Since there are no marine archaeological
resources within the study area that would be affected by the project, marine
archaeological impact due to the construction activities is not expected. The
current project design would avoid the potential impact on the Kellett Island
Archaeological Site at RHKYC and Noonday Gun at CBTS. No environmental protection measure is
required. Compensation
areas included: Not required. Population
and environmental sensitive receivers protected: No archaeological resources would be
affected. |
Operational Phase
Construction Phase
Operational
Phase