2 PROJECT DESCRIPTION.. 5
2.1 Site Location. 5
2.2 EIA Study Area. 6
2.3 Project Requirements,
Scope and Benefits. 6
2.4 Consideration of
Alternatives and Development of Preferred Option. 9
2.5 Construction Methods and
Engineering Requirements. 11
2.6 Operation of the Project 12
2.7 Works Programme. 12
2.8 Related Projects. 14
2
PROJECT DESCRIPTION
2.1
Site Location
2.1.1
The
reclamation works (including the dredging works) sites are located along the
Wan Chai, Causeway Bay and North Point shorelines.
The location of reclamation is shown in Figure 1.2c
2.2
EIA Study Area
2.2.1
The
following definitions of the study areas have been adopted with reference to
the EIA Study Brief registered under the EIAO:
·
Air
Quality Impact: the assessment area should include the area within 500 m from the boundary of the Project;
·
Noise
Impact Assessment: the assessment area should include the area within 300 m from the boundary of the Project;
·
Water
Quality Impact Assessment: the assessment area should include the areas within
and 300m extended beyond the boundary of the Project, plus the Victoria Harbour
Water Control Zone (WCZ), the Eastern Buffer WCZ and the Western Buffer WCZ as
declared under the Water Pollution Control Ordinance;
·
Waste
Management: the assessment will focus on areas within the boundary of the
Project;
·
Land
Contamination: the assessment area for land contamination impact will include
any potentially contaminated sites identified in this EIA;
·
Landscape
and Visual Impact: the area for
landscape impact assessment should include all areas within 100 m extended from the boundary of the Project, while the assessment area
for the visual impact assessment should be defined by the visual envelope from
the Project and associated works;
·
Marine
Ecology: the assessment for marine ecological impact will focus on the area
within the Project boundary; and
·
Cultural
Heritage Impact: the assessment for cultural heritage impact will focus on the
area within the Project boundary.
2.3
Project Requirements, Scope and
Benefits
Project Scope and Requirements
2.3.1
The
reclamation works including associated dredging works (DP3) is driven by the
need for the implementation of the Trunk Road, which will form an east-west
strategic route through Central and Wan Chai to existing IEC. Construction of this Trunk Road will,
though, require permanent reclamation in the areas to the west of HKCEC,
through the HKCEC water channel, along the Wan Chai shoreline and along the
North Point shoreline. Permanent
reclamation is not required in the ex-Public Cargo working Area (PCWA) basin or in the CBTS.
2.3.2
During
the Trunk Road construction, temporary reclamation will be required in the
ex-PCWA basin and the CBTS to facilitate cut-and-cover tunnel construction of
the Trunk Road. After construction
of the Trunk Road, the temporary reclamation will be removed and the ex-PCWA
basin and the CBTS will be reinstated.
2.3.3
The
reclamation can create a coherent pattern of land use and provide for the
development of an appropriate waterfront ‘edge’ to the existing urban
area. The reclamation will
therefore consider imaginative measures to develop a high quality waterfront
for the enjoyment of the public and tourists.
2.3.4
The
total volume of sediments to be dredged and disposed is estimated to be
approximately
1.15 Mm3.
2.3.5
The
minimum area of permanent reclamation required is summarised as follows:
(i) HKCEC West: 3.7 ha
(ii) HKCEC Water Channel: 1.6 ha
(iii) Wan Chai Shoreline: 4.1 ha
(iv) North Point Shoreline: 3.3 ha
2.3.6
The
total reclamation area is 12.7 ha.
2.3.7
For
the mitigation of odour, dredging to remove the polluted sediments at the
south-west corner of the CBTS will be carried out in conjunction with the
dredging for the Trunk Road reclamation.
Project Benefits
2.3.8
The
reclamation provides essential land for the construction of key transport
infrastructure including the Trunk Road and the NIL and SCL. The road and rail routes are required to
relieve congestion on the strategic east-west routes through Central, Wan Chai
and Causeway Bay and on the public transport system, and their implementation is a core
element of Government's transport planning strategy.
2.3.9
The
land formed also provides opportunity to create an attractive waterfront for
the enjoyment of the public. At
present, large parts of the Wan Chai, Causeway Bay and North Point waterfront are inaccessible to the public or are
difficult to access. The land
formed through this Project will be used to regenerate the waterfront into an
attractive public resource that could be used for a wide range of recreational
and tourism-related uses and functions, with easy access from the urban
hinterland. In so doing, the
waterfront will become, as it should, an integral element of the public asset
currently provided by the harbour.
2.3.10
The
project also provides opportunity to enhance the existing odour at the
south-west corner of the CBTS by removal of the polluted sediments which will
be carried out in conjunction with the dredging for the Trunk Road reclamation.
Consequences of Not Proceeding
with the Project
(i) Not
able to meet the need for the Trunk Road
2.3.11
The
need to provide a strategic trunk road along the northern shore of Hong Kong Island has long been identified.
The Trunk Road is the missing link required to complete this strategic
route. The Trunk Road is needed to
divert through traffic away from the Central Business District and from the
existing east-west traffic corridor of Connaught Road Central – Harcourt Road – Gloucester Road. It is also needed to cater for the
anticipated natural growth of traffic and to alleviate the already existing
congestion on the road networks.
Without the Trunk Road, there will not be sufficient capacity to serve
the heavy demands at both the strategic and local levels.
2.3.12
The
existing east-west corridor (Connaught Road Central – Harcourt Road – Gloucester Road)
serving the CBD on Hong Kong
Island is already
operating beyond its capacity, as can be observed on site. Previous and recent strategic transport
studies have predicted further increase in traffic demand along the east-west
corridor, and confirmed the need for a parallel east-west Trunk Road to avoid
more extensive and frequent traffic congestion, and even gridlock, on the road
network.
2.3.13
A
district traffic study has confirmed that a dual 3-lane Trunk Road (or
Central-Wan Chai Bypass), together with intermediate slip roads, is required to
divert traffic away from the existing east-west corridor and to provide
adequate relief to the corridor and the local road network.
2.3.14
Traffic
management and fiscal measures are already in place to maximise the capacity of
the existing road network and suppress traffic demand. Further measures including ERP have also
been considered. However, all these
existing and proposed measures, alone, cannot resolve the traffic congestion
problem along the east-west corridor.
In other words, the Trunk Road is essential, and ERP can complement the
Trunk Road but cannot replace it.
2.3.15
The
need for the Trunk Road has also been confirmed by the Expert Panel on
Sustainable Transport Planning and Central-Wan Chai Bypass, comprising leading
independent local and overseas transport planning experts. The Expert Panel supports the construction
of the CWB to improve the reliability of the road network and to enhance
multi-modal public transportation in the Connaught Road Central – Harcourt Road – Gloucester Road
corridor. The Expert Panel agrees
that the inability of the present infrastructure capacity to cope with the
present and future travel demand would persist even if development in the
Central reclamation area were stopped and territory-wide car ownership held
unchanged from now until 2016, and therefore recommends the construction of the
Trunk Road as a medium term solution to tackle the problem of deteriorating
traffic congestion in the Central and Wan Chai area. The Expert Panel further supports the
provision of the planned slip roads at the HKCEC area and at the Victoria Park Road
/ Gloucester Road
/ Hing Fat Street
passageway, to magnify the benefits of the CWB. The Expert Panel also recognises the
need for Road P2 both in the longer term and as an important ad interim measure
in addressing traffic congestion in the Central reclamation area even before
the CWB is implemented.
(ii) NIL and SCL
2.3.16
Land
formed under the Project, in addition to providing for the construction of the
Trunk Road, also provides for the construction of the NIL and the SCL. Should the Project not proceed,
implementation of these rail routes will be severely constrained. This will have consequential adverse
impacts on the planning and provision of public transport infrastructure.
(iii) No improvement of the waterfront
2.3.17
Should
the Trunk Road not be implemented the requirement for land formation will fall
away and opportunities to improve the existing waterfront would be
limited. The following scenarios
are likely:
·
no
new land will be available to upgrade and improve the waterfront;
·
it
will be difficult to realise the Town Planning Board's objectives stipulated in
the Vision and Goals for Victoria Harbour
to make the harbour attractive, vibrant, accessible and symbolic of Hong Kong;
·
it
will also be difficult to achieve the harbour-planning principles established
by the HEC, including, amongst others, sustainable development, proactive
harbour enhancement, vibrant harbour, accessible harbour and public enjoyment.
2.4
Consideration of Alternatives and
Development of Preferred Option
Introduction
2.4.1
Having
established the need for the Trunk Road, any reasonable alternative to
reclamation that may meet this overriding need must be determined. In other words, can an alternative
alignment or form of construction for the Trunk Road be adopted that will
obviate the need for reclamation?
If there is a feasible “no reclamation” option, then it should be
pursued. Only if the need for
reclamation can be demonstrated to be necessary will scenarios involving
minimum reclamation be contemplated.
2.4.2
A
detailed examination of Trunk Road needs and constraints, including an
exhaustive investigation into the need for reclamation for the Trunk Road
construction and of alternative schemes that might do away with reclamation or,
at least, minimise reclamation, has been carried out. A “Report on Trunk Road Alignments and Harbour-front
Enhancement, April 2006” was submitted to the HEC
Sub-committee on WDII Review, which set out the findings of these
investigations and the conclusions regarding the need for reclamation and the
minimum extent of reclamation. A
copy of the report is given in Annex G of the CCM Report which can be viewed at
the website:
http://www.harbourfront.org.hk/eng/content_page/reportTRA.html?s=1.
Alternative Reclamation Options and
Shoreline Configurations
2.4.3
The
size of reclamation, and the corresponding shoreline configuration, is
determined based on the minimum extent of reclamation that is needed to meet
the essential engineering requirements for the construction of the Trunk Road. It is the minimum reclamation required
to meet the overriding need for the Trunk Road. A step by step
approach is taken to ensure the reclamation is the minimum extent
required. The first step is to
confirm that there is an overriding and present need for the Trunk Road. The next step is to identify any
“no-reclamation options”. If there
is no reasonable alternative to reclamation, the third step is to ensure that
the reclamation is restricted to only the minimum amount necessary to meet the
overriding public need.
2.4.4
The
compelling and present need for the Trunk Road has been confirmed and reference
can be made to the CCM Report. The
need for the Trunk Road is explained in Section 2 of the CCM Report and also
mentioned in paragraphs 2.4.10 to 2.4.17 of Volume 1 of this EIA
Report. The Trunk Road is the
“missing link” in the strategic road network of Hong Kong and will provide the
essential east-west linkage between Rumsey Street Flyover in Central and the
IEC in Causeway Bay. The implementation of the Trunk Road
will relieve the existing congested east-west corridor of Hong Kong Island
North. The need for the Trunk Road
has been clearly established through traffic and transport studies. The Expert Panel has confirmed the need
for the Trunk Road and intermediate slip roads. The Expert Panel considers that the
Trunk Road is essential for improving the reliability of the road network. The findings of the traffic and
transport studies, and of the Expert Panel, demonstrate conclusively the
compelling and present need for the Trunk Road.
2.4.5
The
“no-reclamation” options are given in Section 3 of CCM Report. All possible alignments for the Trunk
Road, including suggestions from the public, have been examined, taking into
account land use and infrastructural constraints, with a view to determining if
there are any that do not require any reclamation for the Trunk Road
construction. It is found that the
feasible Trunk Road routeing is along the foreshore of Wan Chai and Causeway Bay. However, foreshore
alignments do require reclamation for Trunk Road tunnel construction at the
western end of WDII where the Trunk Road tunnel crosses over the MTR Tsuen Wan
Line, and at the eastern end of WDII where the Trunk Road tunnel must rise to
ground level for the connection with the elevated IEC, at least. There is no feasible “no-reclamation”
alignment for the Trunk Road, and at least some reclamation will be required
for the Trunk Road construction.
2.4.6
The
“Report on Trunk Road Alignments and Harbour-front Enhancement, April 2006” sets out the findings of the investigations on the alternative schemes
of the Trunk Road and the conclusions regarding the need for reclamation and
the minimum extent of reclamation.
Reference is made to Annex G of the CCM Report which can be viewed at
the website: http://www.harbourfront.org.hk/eng/content_page/reportTRA.html?s=1. As given in the paragraphs 2.5.1
to 2.5.41 of Volume 1 of this EIA Report, the preferred Trunk Road option,
Trunk Road Tunnel Variation 1, has been derived with a detailed examination of
Trunk Road needs and constraints, including an exhaustive investigation into
the need for reclamation for the Trunk Road construction and of alternative
schemes that might do away with reclamation or, at least, minimise reclamation. Trunk Road Tunnel Variation 1 affects
the minimum area of the Harbour and serves best to protect and preserve the
Harbour, among all the options that have been assessed. This option has clearly expressed
support as the preferred Trunk Road scheme, following extensive consultations
with various public, advisory and relevant statutory bodies.
2.4.7
Details
of the extent of reclamation, in respect of the engineering requirements for
the construction of the Trunk Road tunnel, reclamation and seawalls, are
presented in a “Minimum Reclamation Report”, a copy of which is appended at
Annex O of the CCM Report which can be viewed at the web site:
http://www.devb.gov.hk/reclamation/filemanager/en/content_19/annexO_e.pdf. Detailed examination of the
engineering requirements in respect of highway geometric design and
construction of the Trunk Road tunnel, reclamation and seawalls, and
reprovisioning requirements, has been carried out to accurately determine the
minimum extent of reclamation. In
total, an area of 12.7ha of reclamation (in addition to an
area of 0.4ha of
affected water area by flyover structures) is needed to meet essential
engineering requirements for construction of the Trunk Road. This is the minimum reclamation required
to meet the overriding public need for the Trunk Road.
2.4.8
With
the size of reclamation being minimised to the minimum extent to meet the
overriding need for the Trunk Road, the affected area of the harbour, the
foreshore and seabed is minimised, and the corresponding environmental impacts,
such as marine ecological and cultural heritage impacts, on the foreshore and
seabed are also minimised. Details
of the marine ecology and cultural heritage impact assessment for the proposed
scheme shall refer to the respective sections in this WDII&CWB EIA Report.
2.4.9
As
presented in the “Minimum Reclamation Report”, as appended at Annex O of the
CCM Report, the shoreline (ie the seawall copeline) is set at the minimum
separation from the Trunk Road tunnel and it follows the curvature of the Trunk
Road tunnel edge. Smooth curves
have been adopted at indented areas rather than sharp corners along the
shoreline, and a curved splay in the seawall is incorporated at the corner with
Expo Drive
East, where there is a drainage
culvert. This smoothing of the
shoreline will enhance flows and prevent accumulation of pollutants or floating
refuse.
2.5
Construction Methods and Engineering Requirements
2.5.1
A number of existing waterfront
facilities (ferry piers, drainage culverts, cooling water intakes, sewage outfall,
etc.) will be affected by the WDII reclamation. Although these facilities will be
reprovisioned under the Project, they should be kept functional and operational
during reclamation until the reprovisioned facilities are constructed and
available for use. There is
therefore a requirement for reclamation to be carried out in stages, with
careful planning of construction sequence for both the reclamation and
reprovisioning works.
2.5.2
The resultant reclamation
staging creates a number of relatively small and confined areas of land
formation. Containment of fill
within each of these areas by seawalls is proposed, with the seawalls
constructed first and filling being carried out behind the seawalls. This method will allow the land area
formed in each stage to be maximised and also has significant benefits in terms
of water quality; by containing all filling behind seawalls, the release of
suspended sediments during the filling operations will not impact the open
water areas of the harbour.
2.5.3
Seawall construction will, in
general, comprise wave energy absorbing caisson seawall units, where exposed to
harbour waves, constructed on dredged foundations for stability reasons. These
caisson seawall units will be in the form of precast caisson units. In lieu of casting the precast units at
the works site, off-site precast yard in mainland for casting of these precast
units and transportation to the seawall construction site by sea will be the
common alternative adopted for precast works.
2.5.4
Dredging of marine mud is
required for the foundations of the seawalls, culverts, at-grade roads, and
associated with the construction of the CWB tunnel. The minimum extent of dredging required
for foundations of the seawalls, roads and drainage culverts, and for practical
engineering and construction reasons due mainly to the narrow configuration of
the reclamation, effectively results in a fully dredged approach over the
length of the site. Figure
2.6 indicates the proposed
extent of dredging for the WDII project.
2.5.5
The use of marine sand fill is
proposed, with fill placed behind the enclosing seawalls of each reclamation
stage. The use of marine sand fill
will enable the formed land to comply with required engineering and settlement
performance criteria, with the fill placed within a very tight programme in
order to meet critical project completion dates. Transportation of marine sand
fill will mainly by barges to achieve the filling rate to meet the construction
programme.
2.5.6
While marine sand is proposed
to be used generally for filling, detailed investigations have been conducted
to explore the possibility of using public fill and surplus rock fill from appropriate
sources that may be identified during the detailed implementation stages of the
project, where engineering, programme and implementation constraints
permit. The investigations indicate
that it is possible to use public fill from Penny’s Bay Reclamation Stage 2
(PBR2) in the upper formation layers, above +2.5 mPD. For the temporary reclamation where
settlement is not a major concern, public fill from PBR2 for the full depth of
reclamation is proposed, to maximise the use of public fill materials.
Transportation of public fill from PBR2 to the works site will mainly by barges
as both the supply and demand locations are at their respective
shorelines. Delivery of reused
construction and demolition materials within the site and/or surplus materials
to the public fill reception facilities will be by barges for large quantities
and by truck for local and small quantities.
2.5.7
The reprovisioned Wan Chai East
ferry pier will be a piled structure, similar to the existing pier structure.
Some concrete members or panels of the ferry pier structure may be in the form
of precast units. Similar to the
precast caisson units, besides casting the precast units at the works site,
off-site precast yard in Mainland for casting of these precast units and
transportation to the seawall construction site by sea will be the common
alternative adopted for precast works.
2.6
Operation of the Project
2.6.1
Operational activities, on
completion of the DP3, would comprise essentially traffic movements on the new
roads and public use of the waterfront.
Other than the new waterfront leisure uses, there are no major changes
of land uses which will result in new operations not already taking place along
this shoreline.
2.7
Works Programme
2.7.1
The reclamation and associated
works are anticipated to commence on site in early 2009, with completion of the
project by 2016. A construction
programme is presented in Appendix 2.5
for reference.
2.7.2
As noted in Section 2.5 above,
construction needs to be carried out in stages in order to meet the services
and utilities reprovisioning requirements and construction sequencing
constraints. A staged construction
programme, with works in each area being carried out sequentially has been
developed to meet the objectives of the Project. The staging of the reclamation works,
with respect to the above issues and constraints, is shown indicatively in Figures
2.7 to 2.19. A brief description of
the proposed works, with reference to the staging requirements, is given in the
following paragraphs.
Implementation Staging
2.7.3
The construction works can be
considered in terms of three mains works areas being, from east to west, the
North Point and Causeway Bay Reclamation, the Wan Chai Reclamation and the
HKCEC Reclamation.
North Point & Causeway Bay Reclamation
2.7.4
The reclamation at North Point
will be in a two stages. The
central area of reclamation will commence first to provide land for temporary
reprovisioning of the FEHD Depot while the new Depot is under
construction. The reclamation on
either side will follow subsequently but the construction of the Trunk Road
tunnel structure, which is partly on existing land, will commence after the
temporary relocation of the existing FEHD Depot. The land formation at the eastern end of
this reclamation area will be handed over for the construction of the tunnel
approach ramp and connecting to the existing IEC.
2.7.5
The temporary reclamation in
the typhoon shelter is divided into four stages to avoid creating an embayed
water area with a pond of stagnant water between the temporary reclamation and
the existing seawall during construction, and to allow the reuse of filling and
surcharge materials between reclamation stages.
2.7.6
Works for the North Point &
Causeway Bay Reclamation will commence in early 2009. The permanent land formation at North
Point will be completed by late 2010 for handing over of works area for
construction of tunnel approach ramps.
The Trunk Road tunnel structure will be completed by early 2015 for
tunnel installations and fitting out.
Operational completion of the Trunk Road will be in 2016.
Wan Chai Reclamation
2.7.7
Four stages have been proposed for
Wan Chai Reclamation, in addition to the temporary reclamation of the ex-PCWA
basin. The first stage is
constructed between the existing Wan Chai East sewage outfall and the existing
seawater intakes for WSD and Sun Hung Kai.
This land needs to be formed in advance to allow the diversions of the
sewage outfall and seawater intake pipelines.
2.7.8
The following stages, on either
side of this advance reclamation area, are constructed subsequent to the
diversion of the sewage outfall and the seawater intakes. The construction sequencing of these
stages also makes provision for the drainage outfalls from Marsh Road and Canal Road and caters for the temporary
relocation of the Wan Chai to Hung Hom ferry services to temporary berthing
facilities.
2.7.9
Works in this area also
commence in early 2009, with land formation being completed by mid 2013 and the
Trunk Road tunnel structure completed by mid 2014 for tunnel installations and
fitting out. Operational completion
of the Trunk Road will be in 2016.
HKCEC Reclamation
2.7.10
Reclamation in this area takes
place after diversion of the existing cooling water intakes to the intake
chambers already provided on the north side of the HKCEC. Reclamation on either side of the MTR
Tsuen Wan line will follow the bored pile wall construction on either side for
the Trunk Road crossing over the MTR line.
Reclamation of the HKCEC water channel takes place before adjacent
reclamation to either the east or west of the HKCEC Extension so as to avoid
embayment of this confined water area.
2.7.11
Reclamation in this area would
commence in early 2009 and would be completed by mid 2012. The Trunk Road tunnel works would be
completed by early 2014 for tunnel installations and fitting out. Operational completion of the Trunk Road
will be in 2016.
2.8
Related Projects
2.8.1
The following projects are
related to the DP3:
(i)
Civil Engineering and
Development Department's CRIII project, comprising reclamation along the
Central waterfront for transport infrastructure needs (including CWB and NIL)
and basic land use requirements. A
section of CWB tunnel will also be constructed under CRIII project. Construction will take place from
February 2003 to September 2012.
(ii)
Trade Development Council’s
Atrium Link Extension project, comprising a link bridge spanning across the
water channel between the Hong Kong Convention and Exhibition Centre (HKCEC)
Phase I and HKCEC Extension.
Construction will take place from May 2006 to March 2009.