3.2 Environmental Legislation, Policies, Plans,
Standards and Criteria
3.3 Description of the Environment
3.5 Identification of Environmental Impacts
3.7 Prediction and Evaluation of Environmental
Impacts
3.8 Mitigation of Adverse Environmental Impacts
3.9 Evaluation of Residual Impacts
3.10 Environmental Monitoring and Audit
3.1.1 This section presents an air quality impact assessment of air quality during the reclamation works including associated dredging works (DP3) of the Wan Chai Development Phase II project. Compared to the previous scheme, the size of reclamation has been decreased in the latest scheme. Potential construction dust impact is expected to be less. Potential odour impacts from contaminated sediment during dredging at Causeway Bay Typhoon Shelter (CBTS) would also be another issue. Appropriate mitigation measures for the proposed works are identified under this Study where necessary.
3.1.2 In view of the project nature, no adverse air quality impact during the operation phase would be anticipated. Thus, this section would only focus on construction air quality impact assessment.
3.2
Environmental Legislation,
Policies, Plans, Standards and Criteria
Air
Quality Objective & EIAO-TM
3.2.2 The Air Pollution Control Ordinance (APCO) provides the statutory authority for controlling air pollutants from a variety of sources. The Hong Kong Air Quality Objectives (AQOs), which must be satisfied, stipulate the maximum allowable concentrations of certain pollutants over specific periods. The relevant AQOs are listed in Table 3.1.
Table 3.1
Notes:
(1)
Measured
at 298 K and 101.325 kPa.
(2)
Not to
be exceeded more than three times per year.
(3)
Not to
be exceeded more than once per year.
(4)
Arithmetic
mean.
(5)
Suspended
particulates in air with a nominal aerodynamic diameter of
(6)
Photochemical
oxidants are determined by measurement of ozone only.
3.2.3
The EIAO-TM stipulates that the
hourly TSP level should not exceed
3.2.4 In accordance with the EIAO-TM, odour level at an air sensitive receiver should meet 5 odour units based on an averaging time of 5 seconds for odour prediction assessment.
Air Pollution Control (Construction Dust) Regulation
3.2.5 Notifiable and regulatory works are under the control of the Air Pollution Control (Construction Dust) Regulation. Notifiable works are site formation, reclamation, demolition, foundation and superstructure construction for buildings and road construction. Regulatory works are building renovation, road opening and resurfacing slope stabilisation, and other activities including stockpiling, dusty material handling, excavation, concrete production etc. This Project is expected to include both notifiable and regulatory works. Contractors and site agents are required to inform the Environmental Protection Department (EPD) on carrying out construction works and to adopt dust reduction measures to reduce dust emission to the acceptable level.
3.3
Description of
the Environment
3.3.1
The study area is in Wan Chai,
Table 3.2 Annual
Average Concentrations of Pollutants in 2006
Pollutant |
Annual Average Concentration in 2006 (mg m-3) |
Monitoring Stations |
CO |
862 |
Central |
NO2 |
54 |
Central / Western |
RSP |
53 |
Central / Western |
TSP |
78 |
Central / Western |
3.4
Sensitive
Receivers
3.4.1
The study area is within
3.4.2 The identified representative ASRs are listed in Table 3.3 and the corresponding locations are shown in Figures 3.2 and 3.3.
Table 3.3 Details
of Air Sensitive Receivers
|
||||
A25 |
Wanchai |
Police Headquarters |
G/IC |
7 |
A26 |
Wanchai |
HK Academy for Performing Arts (Office/Performance Hall) |
G/IC |
9 |
A27 |
Wanchai |
Arts Centre |
G/IC |
10 |
A28 |
Wanchai |
Citic Tower |
Commercial |
42 |
A29 |
Wanchai |
Servicemen's Guides Association |
Commercial |
3 |
A30 |
Wanchai |
HK Academy for Performing Arts (Open Space) |
G/IC |
9 |
A31 |
Wanchai |
Shui On Centre |
Commercial |
34 |
A32 |
Wanchai |
|
Commercial |
46 |
A33 |
Wanchai |
Pedestrian plaza |
Recreation |
0 |
A34 |
Wanchai |
HKCEC Extension |
Commercial |
8 |
A35 |
Wanchai |
Great Eagle Centre |
Commercial |
27 |
A36 |
Wanchai |
Causeway Centre |
Residential |
42 |
A37 |
Wanchai |
Wanchai Swimming Pool |
Recreation |
3 |
A38 |
Wanchai |
Wanchai Sports Ground |
Recreation |
0 |
A39 |
Wanchai |
SPCA |
G/IC |
6 |
A40 |
Wanchai |
|
Residential |
12 |
A41 |
Wanchai |
|
Residential |
18 |
A42 |
Wanchai |
|
Residential |
22 |
A43 |
|
Elizabeth House |
Residential |
21 |
A44 |
|
|
Commercial |
33 |
A45 |
|
World Trade Centre |
Commercial |
34 |
A46 |
|
Excelsior Hotel |
Commercial |
28 |
A47 |
|
|
Residential |
15 |
A48 |
|
|
Residential |
15 |
A49 |
|
|
Residential |
15 |
A50 |
|
Royal |
Recreation |
3 |
A51 |
|
Police Officers Club (Tennis Courts) |
Recreation |
0 |
A52 |
|
Police Officers Club ( |
Recreation |
0 |
A53 |
|
Police Officers Club |
Recreation |
3 |
A54 |
|
|
Recreation |
0 |
A55 |
|
Victoria Park Public Swimming Pool |
Recreation |
0 |
A56 |
|
|
Residential |
25 |
A57 |
|
|
Residential |
18 |
A58 |
|
|
Residential |
24 |
A59 |
|
Gorden House |
Residential |
15 |
A60 |
|
Belle House |
Residential |
24 |
A61 |
|
Citicorp Centre |
Commercial |
36 |
A62 |
|
|
Residential |
30 |
A63 |
|
Victoria Centre |
Residential |
30 |
A64 |
|
Seaview Estate |
Industrial/ commercial |
13 |
A65 |
|
|
Residential |
44 |
A66 |
|
|
Recreation |
0 |
A93 |
North Point |
|
Residential |
27 |
A94 |
North Point |
|
Residential |
27 |
A95 |
North Point |
|
Educational |
N/a |
A96 |
North Point |
Provident Centre (Block 1) |
Residential |
25 |
A97 |
North Point |
Provident Centre (Block 6) |
Residential |
25 |
A98 |
North Point |
Provident Centre (Block 17) |
Residential |
25 |
Future |
||||
A70 |
Central |
Central Government Complex |
G/IC |
N/a |
3.4.3 The planned ASR A70 is Central Government Complex which may be occupied during the construction period of WDII Project. As a conservative approach, ASR A70 was considered in the construction dust impact assessment.
3.5
Identification of
Environmental Impacts
Air Quality Impact from Construction Activities
3.5.1 Construction of seawall and filling works are the major construction works during reclamation. Materials handling, wind erosion, truck haulage on unpaved roads are other major sources of dust impact. SO2, NO2 and smoke emitted from diesel-powered equipment may also affect the air quality of the study area.
3.5.2
Potential marine traffic
emissions from the dredgers would be expected. However, given that only a maximum of 10
dredgers would be concurrently operated at CBTS and Wan Chai waterfront, the
associated emissions should be limited.
In addition, the nearest distance between the dredgers and ASR (A50) at
CBTS is
3.5.3 The concurrent works for the CRIII project has also been taken into account in assessing the impacts.
Odour Impact from Dredging Activities
3.5.4 The water quality in the typhoon shelter has been polluted by sewage discharges in the past and sediments deposited on the seabed in the vicinity of storm outfalls. These sediments may contain high concentrations of organic matter and heavy metals. The sediments in CBTS would be dredged away when carrying out the temporary reclamation.
3.5.5 For the dredging activities carried out in the vicinity of Police Officers’ Club, the dredging operation will be restricted to only 1 small close grab dredger to minimise the odour impact during the dredging activity. The dredging rate should be reduced as much as practicable for the area in close proximity to the Police Officers’ Club. As the sediments may contain highly contaminated mud which may be disposed with the use of geosynthetic containers (details shall refer to Section 6), grab dredger has to be used for filling up the geosynthetic containers on barges. As there is no programme constraint for the removal of the sediments at the south-west corner of the typhoon shelter in the vicinity of Police Officers’ Club for mitigating the existing odour problem, the dredging rate can be slowed down or restricted to specific non-popular hours in weekdays when it is necessary during construction.
3.6.1 There is potential for SO2, NO2 and smoke to be emitted from the diesel-powered equipment and dredgers being used during the construction phase. However, the number of such plant required on-site (land based and water based) will be limited and under normal operation, equipment with proper maintenance is unlikely to cause significant dark smoke emissions and gaseous emissions are expected to be minor. Thus, the AQOs are not expected to be exceeded. Notwithstanding, plant should be regularly maintained to minimise emissions.
3.6.2
The principal source of air
pollution during the construction phase will be dust from the dusty activities
as mentioned in Section
3.6.3
According to the USEPA AP-42,
construction dust particles may be grouped into nine particle size
classes. Their size ranges are 0 -
3.6.4
The emission rates adopted in the
WDII project assessment for different construction activities were based on the
USEPA Compilation of Air Pollutant Emission Factors (AP-42), 5th edition. Table
3.4 gives the relevant clauses for emission factors used in this assessment
in AP-42. Detailed calculation of
emission rate is presented in Appendix 3.1.
Table 3.4 Emission
Factors for Construction Activities
Construction Activities |
Emission Rate (g/m2/s) |
Remark |
Road Construction, Building Construction and Material
Handling (as Heavy Construction) |
E = 3.113426E-05 |
- 50% work area - 75% reduction by water suppression (watering four times a day) -USEPA AP-42 5th
ED., S. |
Wind Erosion |
E = 1.347666E-06 |
- 50% work area - AP-42 5th ED., S.11.9 Table |
3.6.5 The Air Pollution Control (Construction Dust) Regulation specifies that dust suppression measures such as watering should be applied for the construction site. Dust emission from the site would be reduced by 75% if watering with complete coverage of active construction area four times a day. This assumption was adopted in the construction dust impact assessment.
3.6.6 As confirmed with the Project Proponent, 10 working hours per day (08:00-18:00) was assumed for the dusty construction works in the assessment. Wind erosion of open work sites would take place over the whole day.
3.6.7 The following summarises the construction activities during the construction stage of the DP3 Project and other construction activities under WDII Project. The locations of the different reclamation sites are shown in Figure 3.4.
·
·
CBTS Temporary Reclamation
Stage 1 (TCBR1W & TCBR1E)
·
CBTS Temporary Reclamation
Stage 2 (TCBR2)
·
CBTS Temporary Reclamation
Stage 3 (TCBR3)
·
CBTS Temporary Reclamation
Stage 4 (TCBR4)
·
Slip Road 8 & Victoria
Park Reprovisioning
Ex-PCWA Temporary Reclamation
·
Temporary Reclamation PCWA
Stage 1 (TPCWAE)
·
Temporary Reclamation PCWA
Stage 2 (TPCWAW)
Wan Chai Reclamation (WCR)
·
Wan Chai Reclamation Stage 1
(WCR1)
·
Wan Chai Reclamation Stage 2
(WCR2)
·
Wan Chai Reclamation Stage 3
(WCR3)
·
Wan Chai Reclamation Stage 4
(WCR4)
·
New Ferry Pier
Reprovisioning & Demolish Existing Pier
·
Helipad Reprovisioning at
HKCEC
·
Roads
HKCEC Reclamation
·
HKCEC Reclamation Stage 1
(Water Channel) (HKCEC1)
·
HKCEC Reclamation Stage 2
(HKCEC2E & HKCEC2W)
·
MTR Tunnel Crossing
·
HKCEC Reclamation Stage 3
(HKCEC3E & HKCEC3W)
·
Roads
Cross Harbour Watermains
·
Submarine Pipeline
·
Land Section
North Point Reclamation (NPR)
·
North Point Reclamation
Stage 1 (NPR1)
·
North Point Reclamation
Stage 2 (NPR2E & NPR2W)
Construction of IECL
·
IECL Connection Work
·
East Portal and IEC
Connection
Construction of Central
Interchange
·
·
·
3.6.8
Beside the Wan Chai
development, some construction activities would be undertaken within
Construction of CWB Tunnel
Under CRIII Project
·
CWB Tunnel at Initial
Reclamation Area East
·
CWB Tunnel at Final
Reclamation Area East
3.6.9
Based on the construction
programme (Appendix 2.5) and the
number of dusty activities on site, four worst-case scenarios for the DP3
Project have been identified throughout the construction period and are shown
in Table 3.5. Overall, the scenarios presented can be
considered to be representative of the worst case. The figures showing locations of dusty
construction site areas for each scenario are presented in Figure A3.1 to A
Table 3.5 Different
Major Dust Generating Activities in the Worst Case Scenarios during
Construction Phase
Period |
2009 – Early 2010 |
Mid 2010 – Early 2011 |
Mid 2011 – Early 2012 |
Mid 2012 – Early 2013 |
Worst month |
Jan 2010 |
Aug 2010 |
April 2012 |
Feb 2013 |
Activities |
Scenario 1 |
Scenario 2 |
Scenario 3 |
Scenario 4 |
1 |
TCBRIE– Filling |
TCBR1E
– CWB Tunnel |
TCBR1W – CWB Tunnel |
TCBR3 – CWB Tunnel |
2 |
TCBRIW
– Filling |
TCBR1W
– CWB Tunnel |
TCBR2 – CWB Tunnel |
TCBR4 – Filling |
3 |
TCBRIE
– CWB
Tunnel |
TCBR2
– CWB Tunnel |
TCBR3 – CWB Tunnel |
TPCWAW – CWB Tunnel |
4 |
TCBR2
– Filling |
TPCWAE
– CWB Tunnel |
TPCWAE – CWB Tunnel |
WCR2 – Promenade |
5 |
TPCWAE
– CWB Tunnel |
WCR1
- Drainage |
WCR2 – CWB Tunnel |
WCR3 – Filling |
6 |
WCR1 – Filling |
WCR1
– Cooling Water |
HKCEC2E – Filling |
WCR4 – Filling |
7 |
WCR1 – CWB Tunnel |
WCR1
– CWB Tunnel |
HKCEC2W – Filling |
WCR4 – Drainage |
8 |
New Ferry Piers |
HKCEC1 – Cooling Water |
HKCEC3E – Filling |
HKCEC2W – CWB Tunnel |
9 |
HKCEC1 – Cooling Water |
MTR - Piling |
HKCEC3E – Drainage |
HKCEC3W – CWB Tunnel |
10 |
HKCEC2E - Filling |
NPR1 – CWB Tunnel |
HKCEC3W – Drainage |
HKCEC3E – CWB Tunnel |
11 |
Cross Harbour Watermains –
Land Sections |
NPR2E – Filling |
HKCEC3E – CWB Tunnel |
IEC Connection Work |
12 |
NPR1 – CWB Tunnel |
CRIII – CWB Tunnel at
Initial Area East |
NPR2W – CWB Tunnel |
|
13 |
NPR2E – Filling |
CRIII – CWB Tunnel at Final Area
West |
|
|
14 |
NPR2W – CWB Tunnel |
CRIII – CWB Tunnel at Final
Area East |
|
|
15 |
CRIII – CWB Tunnel at
Initial Area East |
|
|
|
16 |
CRIII-CWB Tunnel at Final
East |
|
|
|
3.6.10
Fugitive Dust Model (FDM) (1993
version) was used to assess potential dust impact from the construction
works. The worst case
meteorological data was used to predict the 1-hour and 24-hour average TSP
concentrations at representative discrete ASRs close to the construction
works. Since the construction
activities would be undertaken at ground level and underground level, the worst
dust impact on the ASRs would be at the ground floor of the ASRs. The height of
·
Wind
speed:
·
Wind
direction: 360
wind direction
·
Stability
class: D (daytime) & F (night time)
·
Surface
roughness:
·
Mixing
height:
3.6.11 Daily TSP concentrations were calculated as follows:
Daily TSP concentration = (number of working hour)/24 ´ (1-hour average maximum TSP
concentration during working hours) + (number of non-working hour)/24 ´ (1-hour average maximum TSP
concentration during non-working hours) + Background
3.6.12
The background TSP concentration of
3.6.13 The emission rates adopted in the construction dust impact assessment are in accordance with the USEPA Compilation of Air Pollutant Emission Factors (AP-42), which had previously been applied in similar situations in other EIA studies.
3.6.14 The Fugitive Dust Model (FDM) for construction dust impact assessment is generally accepted models for use in assessing construction dust impacts.
3.6.15 There would be some limitations such as the accuracy of the predictive base data for future conditions e.g. plant inventory for the proposed construction works and sequences of construction activities. Uncertainties in the assessment of impacts have been considered when drawing conclusions from the assessment.
3.7
Prediction and Evaluation of Environmental Impacts
3.7.1 Dredging and reclamation activities would overlap some construction activities of WDII, Trunk Road and CRIII Project will cause a cumulative dust impact on the nearby sensitive receivers.
3.7.2
Since most of the construction
activities are at ground level, the likely cumulative dust impacts of the WDII
on the ASRs at
3.7.3 The predicted cumulative maximum 1-hour average TSP and 24-hour average TSP during construction are shown in Tables 3.6 - 3.7.
Table 3.6 Predicted
Cumulative Maximum 1-hour Average TSP Concentrations at
ASR |
Predicted Concentration (mg m-3) * |
||||
Scen. 1 |
Scen. 2 |
Scen. 3 |
Scen. 4 |
Max. |
|
A25 |
123
|
107
|
172
|
162
|
172
|
A26 |
151
|
130
|
252
|
247
|
252
|
A27 |
195
|
135
|
199
|
196
|
199
|
A28 |
132
|
120
|
222
|
204
|
226
|
A29 |
170
|
154
|
409
|
402
|
409
|
A30 |
216
|
175
|
277
|
276
|
277
|
A31 |
208
|
138
|
193
|
192
|
208
|
A32 |
221
|
186
|
394
|
434
|
434
|
A33 |
378
|
232
|
367
|
269
|
378
|
A34 |
246
|
173
|
328
|
224
|
328
|
A35 |
141
|
126
|
240
|
278
|
278
|
A36 |
124
|
121
|
175
|
205
|
205
|
A37 |
214
|
213
|
329
|
414
|
414
|
A38 |
241
|
228
|
235
|
292
|
292
|
A39 |
225
|
206
|
199
|
238
|
238
|
A40 |
113
|
112
|
131
|
152
|
152
|
A41 |
120
|
118
|
129
|
150
|
150
|
A42 |
121
|
120
|
129
|
147
|
147
|
A43 |
127
|
125
|
125
|
138
|
138
|
A44 |
150
|
149
|
149
|
163
|
163
|
A45 |
189
|
189
|
189
|
218
|
218
|
A46 |
193
|
193
|
193
|
230
|
230
|
A47 |
180
|
180
|
180
|
226
|
226
|
A48 |
158
|
158
|
158
|
224
|
224
|
A49 |
151
|
150
|
151
|
219
|
219
|
A50 |
306
|
306
|
306
|
193
|
306
|
A51 |
212
|
212
|
212
|
210
|
212
|
A52 |
201
|
199
|
200
|
191
|
201
|
A53 |
280
|
277
|
277
|
216
|
280
|
A54 |
147
|
145
|
156
|
185
|
320
|
A55 |
125
|
123
|
129
|
153
|
237
|
A56 |
111
|
108
|
113
|
133
|
148
|
A57 |
116
|
114
|
119
|
141
|
194
|
A58 |
123
|
121
|
128
|
148
|
277
|
A59 |
129
|
128
|
137
|
154
|
183
|
A60 |
148
|
147
|
160
|
166
|
167
|
A61 |
183
|
182
|
193
|
181
|
193
|
A62 |
166
|
162
|
162
|
155
|
166
|
A63 |
221
|
212
|
174
|
195
|
221
|
A64 |
194
|
175
|
165
|
223
|
223
|
A65 |
185
|
172
|
166
|
254
|
254
|
A66 |
170
|
170
|
184
|
184
|
184
|
A70 |
217
|
210
|
168
|
162
|
217
|
A95 |
225
|
220
|
102
|
238
|
238
|
A96 |
167
|
162
|
99
|
185
|
185
|
A97 |
149
|
145
|
98
|
167
|
167
|
A98 |
121
|
117
|
95
|
132
|
132
|
Note: * Background
concentration is included.
Hourly TSP criteria (EIAO-TM):
Table 3.7 Predicted
Cumulative Maximum 24-hour Average TSP Concentrations for at
ASR |
Predicted Concentration (mg m-3) * |
||||
Scen. 1 |
Scen. 2 |
Scen. 3 |
Scen. 4 |
Max. |
|
A25 |
98
|
91
|
122
|
117
|
122
|
A26 |
111
|
102
|
158
|
156
|
158
|
A27 |
131
|
105
|
134
|
133
|
134
|
A28 |
102
|
98
|
145
|
136
|
147
|
A29 |
119
|
113
|
229
|
226
|
229
|
A30 |
141
|
124
|
169
|
169
|
169
|
A31 |
137
|
106
|
131
|
130
|
137
|
A32 |
143
|
129
|
221
|
241
|
241
|
A33 |
213
|
149
|
210
|
168
|
213
|
A34 |
154
|
122
|
193
|
145
|
193
|
A35 |
106
|
101
|
152
|
169
|
169
|
A36 |
99
|
98
|
122
|
136
|
136
|
A37 |
140
|
140
|
192
|
231
|
231
|
A38 |
152
|
146
|
151
|
178
|
178
|
A39 |
145
|
137
|
136
|
154
|
154
|
A40 |
94
|
94
|
103
|
112
|
112
|
A41 |
97
|
97
|
102
|
111
|
111
|
A42 |
97
|
98
|
102
|
110
|
110
|
A43 |
100
|
100
|
100
|
107
|
107
|
A44 |
111
|
111
|
111
|
119
|
119
|
A45 |
129
|
129
|
129
|
143
|
143
|
A46 |
130
|
130
|
130
|
148
|
148
|
A47 |
124
|
124
|
124
|
146
|
146
|
A48 |
114
|
115
|
115
|
144
|
144
|
A49 |
111
|
111
|
112
|
142
|
142
|
A50 |
180
|
183
|
183
|
132
|
183
|
A51 |
139
|
141
|
141
|
139
|
141
|
A52 |
134
|
134
|
135
|
132
|
135
|
A53 |
171
|
170
|
170
|
144
|
171
|
A54 |
109
|
108
|
113
|
127
|
187
|
A55 |
99
|
99
|
101
|
113
|
151
|
A56 |
92
|
92
|
94
|
103
|
110
|
A57 |
95
|
94
|
97
|
107
|
132
|
A58 |
98
|
97
|
101
|
111
|
170
|
A59 |
101
|
100
|
105
|
114
|
126
|
A60 |
109
|
109
|
116
|
120
|
120
|
A61 |
125
|
125
|
132
|
127
|
132
|
A62 |
118
|
117
|
118
|
115
|
118
|
A63 |
142
|
142
|
124
|
132
|
142
|
A64 |
130
|
124
|
119
|
145
|
145
|
A65 |
126
|
122
|
118
|
159
|
159
|
A66 |
120
|
120
|
127
|
129
|
129
|
A70 |
141
|
139
|
121
|
118
|
141
|
A95 |
144
|
145
|
89
|
153
|
153
|
A96 |
117
|
118
|
88
|
128
|
128
|
A97 |
109
|
110
|
87
|
119
|
119
|
A98 |
97
|
97
|
86
|
103
|
103
|
Note: * Background
concentration is included.
24-hour TSP criteria (AQO):
Table 3.8 Predicted
Cumulative Maximum 1-hour Average TSP Concentrations at
ASR |
Predicted Concentration (mg m-3) * |
||||
Scen. 1 |
Scen. 2 |
Scen. 3 |
Scen. 4 |
Max. |
|
A25 |
125 |
104 |
175 |
163 |
175 |
A26 |
153 |
122 |
248 |
242 |
248 |
A27 |
194 |
125 |
199 |
196 |
199 |
A28 |
135 |
115 |
226 |
207 |
230 |
A29 |
173 |
142 |
364 |
354 |
364 |
A30 |
213 |
155 |
266 |
266 |
266 |
A31 |
206 |
127 |
192 |
195 |
206 |
A32 |
219 |
167 |
318 |
390 |
390 |
A33 |
323 |
187 |
312 |
270 |
323 |
A34 |
229 |
151 |
308 |
224 |
308 |
A35 |
143 |
120 |
234 |
259 |
259 |
A36 |
125 |
114 |
178 |
203 |
203 |
A37 |
203 |
182 |
258 |
371 |
371 |
A38 |
222 |
186 |
234 |
291 |
291 |
A39 |
214 |
176 |
202 |
241 |
241 |
A40 |
115 |
108 |
134 |
155 |
155 |
A41 |
122 |
114 |
132 |
153 |
153 |
A42 |
124 |
115 |
132 |
150 |
150 |
A43 |
130 |
120 |
128 |
141 |
141 |
A44 |
152 |
138 |
151 |
167 |
167 |
A45 |
185 |
167 |
185 |
221 |
221 |
A46 |
188 |
170 |
188 |
231 |
231 |
A47 |
176 |
160 |
176 |
226 |
226 |
A48 |
158 |
145 |
157 |
221 |
221 |
A49 |
152 |
139 |
152 |
216 |
216 |
A50 |
259 |
230 |
259 |
195 |
259 |
A51 |
202 |
179 |
200 |
208 |
208 |
A52 |
199 |
178 |
197 |
196 |
199 |
A53 |
265 |
233 |
263 |
220 |
265 |
A54 |
148 |
134 |
156 |
188 |
209 |
A55 |
127 |
117 |
130 |
157 |
216 |
A56 |
113 |
105 |
115 |
136 |
151 |
A57 |
118 |
109 |
121 |
144 |
191 |
A58 |
124 |
115 |
131 |
152 |
223 |
A59 |
130 |
121 |
140 |
159 |
179 |
A60 |
148 |
136 |
163 |
171 |
171 |
A61 |
180 |
163 |
196 |
186 |
196 |
A62 |
168 |
150 |
166 |
158 |
168 |
A63 |
219 |
190 |
177 |
196 |
219 |
A64 |
194 |
161 |
167 |
222 |
222 |
A65 |
186 |
157 |
167 |
248 |
248 |
A66 |
169 |
154 |
186 |
189 |
189 |
A70 |
201 |
174 |
173 |
167 |
201 |
A93 |
410 |
354 |
115 |
432 |
432 |
A94 |
301 |
258 |
106 |
299 |
301 |
A95 |
228 |
199 |
104 |
239 |
239 |
A96 |
171 |
152 |
101 |
189 |
189 |
A97 |
152 |
137 |
99 |
171 |
171 |
A98 |
124 |
113 |
96 |
135 |
135 |
Note: * Background
concentration is included.
Hourly TSP criteria (EIAO-TM):
Table 3.9 Predicted
Cumulative Maximum 24-hour Average TSP Concentrations at
ASR |
Predicted Concentration (mg m-3) * |
||||
Scen. 1 |
Scen. 2 |
Scen. 3 |
Scen. 4 |
Max. |
|
A25 |
100
|
90
|
122
|
117
|
122
|
A26 |
112
|
98
|
154
|
152
|
154
|
A27 |
131
|
100
|
133
|
132
|
133
|
A28 |
105
|
95
|
146
|
137
|
147
|
A29 |
122
|
108
|
205
|
200
|
205
|
A30 |
140
|
114
|
162
|
162
|
162
|
A31 |
136
|
100
|
129
|
132
|
136
|
A32 |
142
|
119
|
185
|
219
|
219
|
A33 |
186
|
126
|
182
|
167
|
186
|
A34 |
145
|
111
|
181
|
144
|
181
|
A35 |
108
|
98
|
148
|
158
|
158
|
A36 |
99
|
95
|
123
|
134
|
134
|
A37 |
134
|
125
|
160
|
209
|
209
|
A38 |
142
|
126
|
149
|
176
|
176
|
A39 |
139
|
123
|
136
|
155
|
155
|
A40 |
95
|
92
|
104
|
113
|
113
|
A41 |
99
|
95
|
103
|
112
|
112
|
A42 |
100
|
96
|
103
|
111
|
111
|
A43 |
103
|
98
|
101
|
108
|
108
|
A44 |
112
|
106
|
111
|
120
|
120
|
A45 |
126
|
119
|
126
|
144
|
144
|
A46 |
127
|
119
|
127
|
148
|
148
|
A47 |
122
|
115
|
122
|
145
|
145
|
A48 |
114
|
109
|
114
|
142
|
142
|
A49 |
112
|
106
|
112
|
140
|
140
|
A50 |
158
|
145
|
157
|
132
|
158
|
A51 |
136
|
126
|
135
|
138
|
138
|
A52 |
133
|
124
|
132
|
134
|
134
|
A53 |
163
|
149
|
161
|
145
|
163
|
A54 |
110
|
104
|
113
|
128
|
137
|
A55 |
100
|
96
|
102
|
115
|
140
|
A56 |
94
|
90
|
95
|
104
|
111
|
A57 |
96
|
92
|
98
|
109
|
129
|
A58 |
99
|
95
|
102
|
113
|
144
|
A59 |
101
|
97
|
106
|
116
|
125
|
A60 |
110
|
104
|
117
|
122
|
122
|
A61 |
124
|
117
|
132
|
129
|
132
|
A62 |
119
|
111
|
119
|
116
|
119
|
A63 |
143
|
131
|
125
|
132
|
143
|
A64 |
132
|
118
|
119
|
143
|
143
|
A65 |
128
|
115
|
119
|
155
|
155
|
A66 |
118
|
112
|
128
|
131
|
131
|
A70 |
134
|
122
|
123
|
120
|
134
|
A93 |
224
|
200
|
95
|
235
|
235
|
A94 |
181
|
162
|
91
|
179
|
181
|
A95 |
148
|
135
|
90
|
152
|
152
|
A96 |
122
|
114
|
89
|
129
|
129
|
A97 |
113
|
106
|
88
|
121
|
121
|
A98 |
99
|
95
|
86
|
105
|
105
|
Note: * Background
concentration is included.
24-hour TSP criteria (AQO):
3.7.4
Based on results indicated in Tables 3.6 and 3.7, no exceedance of 1-hour average and 24-hour average TSP
guideline and AQO is predicted at the ASRs
Exceedance of the 1-hour
average TSP guideline of
Scenario 1 – sea area, area next
to Cross Harbour Tunnel and area next to HKCEC, IEC;
Scenario 2 – sea area and IEC
Scenario 3 – sea
area, area next to Cross Harbour Tunnel, area next to HKCEC, area underneath
New Atrium Link (Extension of HKCEC)
Scenario 4 -
sea area, IEC, part of waterfront in the vicinity of Causeway Bay
Flyover, area underneath New Atrium Link (Extension of HKCEC), area in the
vicinity of existing Wan Chai Pier and nearby PTI, area next to Servicemen’s
Guides Association
Exceedance of the 24-hour
average TSP AQO of
Scenario 1 – sea area, area
next to Cross Harbour Tunnel and area next to HKCEC, IEC;
Scenario 2 – sea area, IEC
and area next to Cross Harbour Tunnel
Scenario 3 – sea
area, area next to Cross Harbour Tunnel, areas next to Servicemen’s Guides
Association and HKCEC, area underneath New Atrium Link (Extension of HKCEC)
Scenario 4 -
sea area, IEC, part of waterfront in the vicinity of Causeway Bay
Flyover, GFS Helipad, area underneath New Atrium Link (Extension of HKCEC),
area in the vicinity of existing Wan Chai Pier and nearby PTI, area next to
Servicemen’s Guides Association
3.7.5
Exceedances were noted at the
above identified areas
3.8
Mitigation of
Adverse Environmental Impacts
3.8.1 As shown in Tables 3.10 to 3.12, the cumulative maximum 1-hour average and 24-hour average TSP concentrations are predicted to comply with the TSP criteria at all representative ASRs with watering on the active works area four times a day. The area within study area of WDII Project would also meet the TSP criteria. In order to further ensure compliance with the AQOs at the ASRs at all time, requirements of the Air Pollution Control (Construction Dust) Regulation shall be adhered to during the construction period. In addition, the following mitigation measures, good site practices and a comprehensive dust monitoring and audit programme are recommended to minimise cumulative dust impacts.
·
Strictly limit the truck speed on site to
below
·
Watering during excavation and material
handling;
·
Provision of vehicle wheel and body washing
facilities at the exit points of the site, combined with cleaning of public
roads where necessary; and
·
Tarpaulin covering of all dusty vehicle loads
transported to, from and between site locations.
3.9
Evaluation of
Residual Impacts
3.9.1 With the implementation of the proposed mitigation measures and the dust suppression measures stipulated in Air Pollution Control (Construction Dust) Regulation during the construction phase, no adverse residual air quality impact would be expected.
3.9.2 No adverse odour impact from contaminated sediment during dredging would be anticipated with the implementation of proposed mitigation measures.
3.10
Environmental
Monitoring and Audit
3.10.1 With the implementation of the proposed dust suppression measures, good site practices and dust monitoring and audit programme, acceptable dust impact would be expected at the ASRs. Details of the monitoring requirements such as monitoring locations, frequency of baseline and impact monitoring are presented in the stand-alone EM&A Manual.
3.11.1
During construction, reclamation,
filling and surcharging were identified as the major dust sources. Trunk Road tunnel works would also
generate dust and contri
3.11.2 Potential odour impacts from contaminated sediment would be expected when the dredging activities carrying out in the vicinity of Police Officers’ Club. As the dredging operation will be restricted to only 1 small close grab dredger, the odour impact during the dredging activity would be minimised. With the implementation of proposed mitigation measures, no adverse odour impacts from contaminated sediment would be anticipated.