2.3 Project Requirements, Scope and Benefits
2.4 Consideration of Alternatives
2.5 Construction Methods and Engineering Requirements
2.1.1
The
temporary typhoon shelter (DP4) is located to the north of the existing
Causeway Bay Typhoon Shelter (CBTS). Figure 1.2d shows the
location of the temporary typhoon shelter.
2.2.1
The
following definitions of the study areas have been adopted with reference to
the EIA Study Brief registered under the EIAO:
·
Air
Quality Impact: the assessment area should include the area within
·
Noise
Impact Assessment: the assessment area should include the area within
·
Water
Quality Impact Assessment: the assessment area should include the areas within
and
·
Waste
Management: the assessment will focus on areas within the boundary of the
Project;
·
Land
Contamination: the assessment area for land contamination impact will include
any potentially contaminated sites identified in this EIA;
·
Landscape
and Visual Impact: the area for
landscape impact assessment should include all areas within
·
Marine
Ecology: the assessment for marine ecological impact will focus on the area
within the Project boundary; and
·
Cultural
Heritage Impact: the assessment for cultural heritage impact will focus on the
area within the Project boundary.
Project Scope and Requirements
2.3.1
The
construction of the Trunk Road tunnel beneath the existing CBTS will
temporarily affect the existing moorings.
To maintain the operation of the CBTS during the construction period, it
is necessary to reprovision a temporary typhoon shelter in the vicinity of the
existing one. The Project includes
a temporary typhoon shelter at the north of the existing typhoon shelter with
around
Project
Benefits
2.3.2
The
temporary reprovisioning of the affected CBTS to the temporary typhoon shelter
at the north of the existing one maintains the current provision of mooring
area at
Consequences of Not Proceeding with the
Project
2.3.3
Should
the temporary typhoon shelter not be temporarily reprovisioned, the existing
mooring area at the CBTS will be temporarily lost during construction of the
Trunk Road.
2.4.1
As
alternative to temporarily reprovisioning the typhoon shelter to the north of
the existing one, which is the nearby available location, affected vessels
sheltered at CBTS could be temporarily relocated to other off-site typhoon
shelters. These are very far away from the
2.5.1
The
proposed temporary moorings will require construction of a
2.5.2
The
primary wave and physical protection will be provided by the conventional
rubble mound breakwater, which will be of similar construction to existing
breakwater. The piled wave walls
will comprise vertical concrete downstands, supported on tubular steel
piles. The downstands will extend
down below the surface of the water to reduce wave transmission through the
typhoon shelter entrances from the north-easterly and north-westerly
directions.
2.5.3
Typical
details of the breakwater and the piled wave walls are shown in Figure 5.5.
2.5.4
Dredging
for the rubble mound breakwater construction will be carried out by a closed
grab dredger. Rock fill for the
breakwater will be placed by bottom dumping (below water) and by grab (above
water).
2.5.5
No
dredging will be required for the construction of the wave walls. The concrete wave wall downstands will
be precast units constructed off-site.
They will be delivered to site for installation upon completion of
piling works.
2.5.6
Upon
relocation of the moorings back to their original locations in the CBTS, the
temporary typhoon shelter will be demolished by extraction of the wave wall
piles and removal of the breakwater rock fill down to seabed level.
2.6.1 During the operation phase of the Project, the moorings will be relocated back to the existing typhoon shelter and the temporary typhoon shelter will be demolished.
2.7.1 The temporary relocation of CBTS is anticipated to commence on site in early 2009 and will be demolished in 2016. A construction programme is presented in Appendix 2.5 for reference.
2.8.1 The following projects are related to this DP4:
(i) Civil Engineering and Development Department's CRIII project, comprising reclamation along the Central waterfront for transport infrastructure needs (including CWB and NIL) and basic land use requirements. A section of CWB tunnel will also be constructed under CRIII project. Construction will take place from February 2003 to September 2012.
(ii) Trade Development Council’s Atrium Link Extension project, comprising a link bridge spanning across the water channel between the Hong Kong Convention and Exhibition Centre (HKCEC) Phase I and HKCEC Extension. Construction will take place from May 2006 to March 2009.