14.6 Waste Management
Implications
14.7 Land
Contamination Impact
14.9 Landscape and
Visual Impact
14.10 Cultural Heritage
Impact
14.11 Environmental
Monitoring and Audit
Table 14.1 Summary
of Environmental Impacts Associated with the Project
Environmental Issue |
Sensitive
Receivers/ Assessment Points |
Impact Prediction
Results |
Relevant Standards/
Criteria |
Extents of
Exceedances |
Impact Avoidance
Measures/ Mitigation Measures |
Residual Impacts |
Air Quality |
|
|
|
|
|
|
Construction Phase |
4 assessment points |
No adverse dust and
emission impacts would be expected during dredging activities as dredging is a
marine-based activity; and limited emissions from one operated dredgers last
for one month (taking into account of concurrent activities). . |
EIAO-TM and Air
Quality Objective |
Nil |
The operated dredgers and equipments should
be regularly maintained to minimise emissions during construction phase |
Nil |
Operational Phase |
4 assessment points |
Effluent from Wan Chai
East Preliminary Treatment Works would be discharged to |
EIAO-TM |
Nil |
Not Applicable |
Nil |
Noise |
|
|
|
|
|
|
Construction Phase |
N2 and N3 |
Predicted noise levels
would be in the range of 69 to 81 dB(A). |
Domestic premises:
75dB(A) |
Domestic premises:
Exceed the noise standard by up to 6dB(A). |
Use of quiet equipment
and movable noise barriers to mininise construction noise impact |
Nil |
Operational Phase |
Not Applicable |
In view of the project nature, no adverse noise impact during the operation phase would be anticipated. |
Nil |
Not Applicable |
Not Applicable
|
Nil |
Water Quality |
|
|
|
|
|
|
Potential SS elevations from dredging for construction of the sewage
pipeline |
All water sensitivity
receivers in |
The model results
indicate exceedances of WSD water quality (SS) criterion for flushing water
intakes (at Full compliance with
the assessment criterion for sedimentation rate |
WSD water quality
criterion for SS: < 10 mg/l Target SS level at
Admiralty Centre and MTRC cooling water intakes: < 40 mg/l Sedimentation rate at
corals: < |
Maximum SS levels
predicted at the WSD flushing water intakes ranged from 15.9 mg/l to 33.1 mg/l. Maximum SS levels
predicted at Admiralty Centre and MTRC cooling water intakes ranged from 26mg/l to 58.5 mg/l. No exceedance for the
sedimentation rate was predicted |
Restriction on the
maximum dredging rates at the sewage pipelines zone, water mains zone, TWB,
HKCEC Stage 1 & 3 as well as the western seawall
of WCR1 which is close to the WSD intake at Wan Chai; Deployment of silt
curtains around seawall dredging and seawall trench filling in NPR, TCBR, WCR
and HKCEC areas. Deployment of silt screens at selected seawater
intakes |
Nil |
Waste Management Implications |
|
|
|
|
|
|
Construction Phase |
Not applicable |
Main waste: dredged marine sediment with a total volume of approx. |
1. Waste Disposal Ordinance (Cap.
354) |
Not applicable |
Refer to Table 13.4 |
Nil |
|
|
Other wastes: general refuse from
the workforce; chemical waste from plant and equipment maintenance; and
C&D material from excavation works and the demolition of existing
structures. |
2. Waste Disposal (Chemical Waste)
(General) Regulation (Cap. 354) |
|
|
|
|
|
3. Land (Miscellaneous Provisions)
Ordinance (Cap. 28) |
|
|
|
|
|
|
4. Public Health and Municipal
Services Ordinance (Cap. 132) - Public Cleansing and Prevention of Nuisances
Regulation |
|
|
|
|
|
|
|
5. Annexes 7 & 15 of EIAO TM |
|
|
|
Marine Ecological Impacts |
|
|
|
|
|
|
Construction Phase |
Ecological resources
in the assessment area |
-
Temporary loss of less than |
Not applicable |
Not applicable |
-
As no adverse ecological impact on marine habitats and associated
wildlife is predicted, no necessary mitigation measure specific for marine
ecology is considered as required in this assessment. The mitigation measures recommended in
the water quality impact assessment to control water quality would also serve
to protect marine ecological resources from indirect impacts and ensure no
adverse impact on marine life would be resulted from this designated project. |
Not expected |
|
|
-
Changes in water quality -
More than 30% increase of SS at the immediate vicinity outside
reclamation area -
Insignificant elevation of SS at far-field sensitive receivers -
Level of TIN is predicted to be slightly higher than WQO standard at
several locations immediately outside reclamation area -
Minimum depth-averaged DO at HKCEC is predicted to be slightly lower
than 4.0mg/L |
(See water quality
assessment) |
(See water quality
assessment) |
||
|
|
Disturbance impact |
Not applicable |
Not applicable |
|
|
Operational Phase |
Ecological resources
in the assessment area |
-
No direct or indirect impact
on marine ecological resources is predicted |
|
|
|
|
Landscape and Visual Impact |
|
|
|
|
|
|
Construction Phase |
All Landscape Resources /
Landscape Character Areas and Visual Sensitive Receivers within the study
area |
- There will still be some slight negative visual impact on the VSRs in the front row of high rise buildings along the waterfront from Central to North Point. |
1. EIAO and TM, particularly Annexes 10 and 18, |
Not applicable |
- Control of night-time lighting. |
Landscape Impacts
There
will be no landscape impact during construction.
|
|
-
The impact on the |
2. EIAO Guidance Note 8/2002, |
|
-
Erection of decorative screen hoarding compatible with the surrounding
setting. |
It is considered that the
residual impacts on
|
|
|
|
|
|
|
|
Visual Impacts
With implementation of mitigation measures during
construction, there will be some slight negative visual impact on the VSRs in
the front row of high rise buildings along the waterfront from Central to
North Point. Residual impacts
VSRs further away the
|
|
|
|||||
Operational Phase |
All Landscape Resources / Landscape Character Areas and Visual Sensitive Receivers within the study area |
There will be no
landscape and visual impact during operation. |
1. EIAO and TM, particularly Annexes 10 and 18, 2. EIAO Guidance Note 8/2002, 3.
Town Planning Ordinance (Cap
131), |
Not applicable |
Not applicable |
Landscape Impacts
There will be no landscape impact
during operation.
Visual Impacts During operation, the visual impact will be insubstantial. |
|
|
|
4. ETWB TCW No. 2/2004 - Maintenance of Vegetation and Hard Landscape Features. |
|
|
|
Cultural Heritage Impact |
|
|
|
|
|
|
Construction Phase |
Marine archaeological
resources in |
Since there is no
archaeological material present within the study area, no adverse cultural
heritage impact is expected. |
1.
Antiquities and Monuments Ordinance (Cap.53) 2.
Environmental Impact Assessment Ordinance (EIAO) (Cap. 499,
S.16) |
Not applicable |
No further
archaeological investigation or mitigation measures is required |
Nil |
|
|
|
3.
Technical Memorandum on the Environmental Impact Assessment
Process (EIAO-TM) |
|
|
|
|
|
|
4.
Guidance Notes on Assessment of Impact on Sites of Cultural
Heritage in Environmental Impact Assessment Studies (GN-CH) |
|
|
|
|
|
|
5.
6.
Marine Archaeological Investigation Guidelines. |
|
|
|
Table
14.2 Summary
of Key Environmental Outcomes/ Benefits
Issue |
Environmental Outcomes/Benefits |
The Project |
Requirements: The Wan Chai West Sewage Screening Plant
will be decommissioned once flows have been diverted to the Wan Chai East
Sewage Screening Plant. The Wan
Chai East Sewage Screening Plant will have adequate capacity to handle these
flows. However, in the longer
term, the existing sewage outfall will need to be upgraded to handle the
future design flows. A new sewage
outfall will be constructed under the project to replace and upgrade the
existing Wan Chai East sewage outfall.
The configuration of the new sewage outfall will comprise a landfall
section of |
|
Benefits: The
existing sewage outfall has to be reprovisioned to enable the construction of
the reclamation and Trunk Road.
The project provides opportunity to upgrade the sewage outfall to
handle the future design flows.
In environmental terms, water quality at |
|
Potential
consequences without the Project:
Should
the existing sewage outfall not be reprovisioned under the Project, the
existing sewage outfall will be damaged by the reclamation works and the
construction of the Trunk Road.
Without a sewage outfall, the Wan Chai East Sewage Screening Plant
cannot operate.
|
Development
Alternatives |
The
alternative to constructing a new sewage outfall to reprovision the existing
one is to construct a deck-over structure above the existing sewage
outfall. However, this
alternative option is considered not feasible as the Trunk Road tunnel will
be crossing the existing pipeline at the same level and there will be
problems for future maintenance of the pipeline below the deck
structure. Construction of a new
sewage outfall is considered a reasonable and practicable solution.
|
Construction Air
Quality Impact |
Environmental
benefits of environmental protection measures recommended: Negligible air quality impact from the DP5 would be expected at the
nearest ASRs. The operated dredgers and equipments should be regularly maintained to
minimise emissions during construction phase. Compensation
areas included: Not
required. Population
and environmental sensitive receivers protected: Existing air sensitive receivers within 500m of the project boundary. |
Operational Air
Quality Impact |
Environmental
benefits of environmental protection measures recommended: Effluent from Wan Chai East Preliminary Treatment Works would be
discharged to Compensation
areas included: Not
required Population
and environmental sensitive receivers protected: Existing and planned air sensitive receivers within 500m of the project boundary. |
Construction Noise
Impact |
Environmental
benefits of environmental protection measures recommended: The predicted mitigated noise levels would range from 62 to 71 dB(A) at the representative NSRs. With the implementation of quiet PME and movable noise barriers under the Project and the noise mitigation measures under other concurrent Schedule 2 DPs, the noise levels at all representative NSRs would comply with the construction noise standard. |
|
Compensation
areas included: Not required. |
|
Population
and environmental sensitive receivers protected: Noise
sensitive receivers within 300m of the project boundary. |
Operation Noise
Impact |
Environmental
benefits of environmental protection measures recommended: In view of the project nature, no adverse
noise impact during the operation phase would be anticipated |
|
Compensation
areas included: Not
required Population
and environmental sensitive receivers protected: No noise sensitive receiver would be affected. |
Water Quality Impact |
Environmental
benefits of environmental protection measures recommended: The major water quality impact associated with the new sewage outfall would be the potential SS elevations within the water column from the dredging works during the construction phase. Provided the recommended mitigation measures are implemented, including restriction on the maximum dredging rates, the deployment of silt curtains at the other specified current dredging and filling areas activities within the WDII work site, and installation of silt screens at seawater intakes, there will be no unacceptable residual water quality impact due to the proposed dredging works. During the operational phase, the screened
sewage currently discharged from the existing Wan Chai East (WCE) and Wan
Chai West (WCW) submarine outfalls would be diverted to the new WCE submarine
outfall to be constructed under the WDII. It is not expected that there would
be any adverse impacts on the overall water quality in the Compensation
areas included: Not required. Population
and environmental sensitive receivers protected: Seawater intakes along the waterfront of |
Waste Management Implications |
Environmental benefits of environmental protection measures recommended: With the implementation of the recommended mitigation measures and practices, potential air, odour, noise, water quality for the handling, transportation and disposal of the identified waste arisings, no adverse environmental impacts are expected. |
|
Compensation
areas included: Not required. |
|
Population and environmental sensitive
receivers protected: Water quality, air, and noise sensitive receivers
at or near the Project site, the waste transportation routes and the waste
disposal site. |
Land Contamination
Impact |
Environmental benefits of environmental protection measures recommended: No potential contaminative land uses were identified within the Study Area. As such, adverse land contamination impacts associated with the construction and operation of the Project is not expected. Compensation
areas included: Not
required. Population and environmental sensitive receivers protected: ·
No construction worker would be affected. |
Marine Ecological
Impact |
Environmental benefits of environmental protection measures
recommended: The
benthic, intertidal and subtidal habitats within the affected area are of
very low ecological value. Hence, adverse direct ecological impact is not
expected. Water quality and noise control measures (as described above) would
minimise indirect impact on marine habitats and associated flora and fauna
due to change in water quality and noise environment during the construction
phase.
Compensation
areas included: Not
required. Population
and environmental sensitive receivers protected: No ecological sensitive receiver would be affected. |
Landscape and Visual
Impact |
Environmental benefits of environmental protection measures recommended: · A submarine sewage outfall will
be constructed in |
|
· It is considered that the
residual impacts on |
|
· With implementation of mitigation measures during construction,
there will still be some slight negative visual impact on the VSRs in the front
row of high rise buildings along the waterfront from Central to North
Point. Residual impacts VSRs
further away the |
|
Compensation
areas included: Approximately
Population
and environmental sensitive receivers protected: Existing and
planned Landscape Resources , Landscape Character Area and VSR at and near
the project site. |
Cultural Heritage
Impact |
Environmental
benefits of environmental protection measures recommended: Since there are no marine archaeological
resources within the study area that would be affected by the project, marine
archaeological impact due to the construction activities is not expected. No environmental
protection measure is required. Compensation
areas included: Not required. Population
and environmental sensitive receivers protected: No archaeological resources would be
affected. |