2                   PROJECT DESCRIPTION.. 1

2.1                Site Location. 1

2.2                EIA Study Area. 1

2.3                Project Requirements, Scope and Benefits. 2

 

 

2                    PROJECT DESCRIPTION

 

2.1              Site Location

 

2.1.1          A new sewage outfall will be constructed under the project at the Wan Chai North waterfront to replace and upgrade the existing Wan Chai East sewage outfall.  The location of the Wan Chai East sewage outfall is shown in Figure 1.2e.

 

2.2              EIA Study Area

 

2.2.1          The following definitions of the study areas have been adopted with reference to the EIA Study Brief registered under the EIAO:

 

·                     Air Quality Impact: the assessment area should include the area within 500 m from the boundary of the Project;

 

·                     Noise Impact Assessment: the assessment area should include the area within 300 m from the boundary of the Project;

 

·                     Water Quality Impact Assessment: the assessment area should include the areas within and 300m extended beyond the boundary of the Project, plus the Victoria Harbour Water Control Zone (WCZ), the Eastern Buffer WCZ and the Western Buffer WCZ as declared under the Water Pollution Control Ordinance;

 

·                     Waste Management: the assessment will focus on areas within the boundary of the Project;

 

·                     Land Contamination: the assessment area for land contamination impact will include any potentially contaminated sites identified in this EIA;

 

·                     Landscape and Visual Impact:  the area for landscape impact assessment should include all areas within 100 m extended from the boundary of the Project, while the assessment area for the visual impact assessment should be defined by the visual envelope from the Project and associated works;

 

·                     Marine Ecology: the assessment for marine ecological impact will focus on the area within the Project boundary; and

 

·                     Cultural Heritage Impact: the assessment for cultural heritage impact will focus on the area within the Project boundary.

 

2.3              Project Requirements, Scope and Benefits

 

Project Scope and Requirements

2.3.1          The Wan Chai West Sewage Screening Plant will be decommissioned once flows have been diverted to the Wan Chai East Sewage Screening Plant.  The Wan Chai East Sewage Screening Plant will have adequate capacity to handle these flows.  However, in the longer term, the existing sewage outfall will need to be upgraded to handle the future design flows.  A new sewage outfall will be constructed under the project to replace and upgrade the existing Wan Chai East sewage outfall.  The configuration of the new sewage outfall will comprise a landfall section of 2,250mm diameter pipe with approximate length of 180m, and a marine section of twin 1,600mm diameter submarine pipelines of about 550m length. 

 

            Project Benefits

           

2.3.2          The existing sewage outfall has to be reprovisioned to enable the construction of the reclamation and Trunk Road.  The project provides opportunity to upgrade the sewage outfall to handle the future design flows.

 

Consequences of Not Proceeding with the Project

           

2.3.3          Should the existing sewage outfall not be reprovisioned under the Project, the existing sewage outfall will be damaged by the reclamation works and the construction of the Trunk Road.  Without a sewage outfall, the Wan Chai East Sewage Screening Plant cannot operate.

2.4              Development Alternatives

2.4.1          The alternative to constructing a new sewage outfall to reprovision the existing one is to construct a deck-over structure above the existing sewage outfall.  However, this alternative option is considered not feasible as the Trunk Road tunnel will be crossing the existing pipeline at the same level and there will be problems for future maintenance of the pipeline below the deck structure.  Construction of a new sewage outfall is considered a reasonable and practicable solution.

2.5              Construction Methods and Engineering Requirements

2.5.1          The configuration of the new sewage outfall will comprise a landfall section of 2,250mm diameter pipe with approximate length of 180m, and a marine section of twin 1,600mm diameter submarine pipelines of about 550m length.  Based on preliminary assessment, this configuration will have capacity to cater for a design peak flow of 4,613 l/s.

2.5.2          The preliminary analysis has been based on the new outfall having similar configuration to the existing, with similar diffuser arrangements.  The hydraulic performance of the new outfall, and the efficiency of the diffusers will be assessed more thoroughly in the detailed design stage.

2.5.3          The construction method for the submarine pipelines involves dredging for a pipe trench and laying of bedding materials, pipelines and covering materials by marine plants.  The construction of land section of the outfall is similar to typical pipe laying work with excavation and installation of shoring, bedding pipe laying, back filling and construction of chambers.

2.6              Operation of the Project

2.6.1          Operational activities, on completion of the Project, would comprise essentially the operation of the new sewage outfall, which will replace and upgrade the existing Wan Chai East sewage outfall.

2.7              Works Programme

2.7.1          The construction works of the sewage outfall are anticipated to commence on site in late 2009, with completion by 2011.  A construction programme is presented in Appendix 2.5 for reference.


2.8              Related Projects

2.8.1          The following projects are related to the DP5:

(i)                  Civil Engineering and Development Department's CRIII project, comprising reclamation along the Central waterfront for transport infrastructure needs (including CWB and NIL) and basic land use requirements. A section of CWB tunnel will also be constructed under CRIII project.  Construction will take place from February 2003 to September 2012.

 

(ii)                Trade Development Council’s Atrium Link Extension project, comprising a link bridge spanning across the water channel between the Hong Kong Convention and Exhibition Centre (HKCEC) Phase I and HKCEC Extension.   Construction will take place from May 2006 to March 2009.