3                    aIR qUALITY

3.1              Introduction

3.1.1          This section presents an assessment of air quality impact due to proposed Wan Chai East sewage outfall submarine pipelines (DP5). Potential air quality impacts arising from the DP5 and appropriate mitigation measures if necessary are identified under this Study.       

3.2              Environmental Legislation, Policies, Plans, Standards and Criteria

3.2.1          The criteria for evaluating air quality impacts and the guidelines for air quality assessment are set out in Annex 4 and Annex 12 of the Technical Memorandum on Environmental Impact Assessment Process (EIAO-TM).

Air Quality Objective & EIAO-TM

 

3.2.2          The Air Pollution Control Ordinance (APCO) provides the statutory authority for controlling air pollutants from a variety of sources.  The Hong Kong Air Quality Objectives (AQOs), which must be satisfied, stipulate the maximum allowable concentrations of certain pollutants over specific periods.  The relevant AQOs are listed in Table 3.1.

Table 3.1     Hong Kong Air Quality Objectives

Notes:

(1)              Measured at 298 K and 101.325 kPa.

(2)              Not to be exceeded more than three times per year.

(3)              Not to be exceeded more than once per year.

(4)              Arithmetic mean.

(5)              Suspended particulates in air with a nominal aerodynamic diameter of 10 mm or smaller.

(6)              Photochemical oxidants are determined by measurement of ozone only.

 


3.2.3          The EIAO-TM stipulates that the hourly TSP level should not exceed 500 mgm-3 (measured at 25oC and one atmosphere) for construction dust impact assessment.  Standard mitigation measures for construction sites are specified in the Air Pollution Control (Construction Dust) Regulations.

3.2.4          In accordance with the EIAO-TM, odour level at an air sensitive receiver should meet 5 odour units based on an averaging time of 5 seconds for odour prediction assessment.

3.3              Description of the Environment

Baseline Conditions

3.3.1          The study area is in the vicinity of Wan Chai Waterfront (near Wan Chai Sports Ground).  The nearest EPD air quality monitoring stations are in Central and Central/Western.  The annual average concentrations of the pollutants measured at EPD’s Central / Western and Central air quality monitoring stations in 2006 adjacent to the WDII development area are summarised in Table 3.2.

Table 3.2     Annual Average Concentrations of Pollutants in 2006

Pollutant

Annual Average Concentration in 2006 (mg m-3)

Monitoring Stations

CO

862

Central

NO2

54

Central / Western

RSP

53

Central / Western

TSP

78

Central / Western

 

3.4              Sensitive Receivers

3.4.1          The study area is within 500m from the project boundary.  The study area of air quality assessment is shown in Figure 3.1.  The Air Sensitive Receivers (ASRs) including domestic premises, commercial buildings, educational institutions, and recreational and leisure facilities have been identified for air quality impact assessment.

3.4.2          The identified nearest ASRs to the work site of DP5 are Wan Chai Sports Ground, SPCA, Wan Chai Swimming Pool and Great Eagle Centre.  

3.5              Identification of Environmental Impacts

Construction Phase

3.5.1          The major activities would be dredging and laying submarine pipelines which would be commenced in October 2009.  One dredger would be used and the duration would be last for a month.  As dredging and laying submarine pipelines are marine based activities, dust nuisance from these construction activities is not anticipated.   

3.5.2          Insignificant marine traffic emission impact from the dredger is expected as only one dredger to be operated at the work site.  Under normal operation, equipment with proper maintenance is unlikely to cause significant dark smoke emissions and gaseous emissions are expected to be minor. Thus, the AQOs are not expected to be exceeded.  Notwithstanding, plant should be regularly maintained to minimise emissions. 


3.5.3          In accordance with the construction programme, one dredger at TCBR1W area would be operated concurrently within 500m study area of DP5.  In view of limited emissions from two dredgers in the study area, adverse cumulative air quality impact is not anticipated.

3.5.4          The dredging area is not a stagnant or low water flow area in Victoria Harbour.  The sediment is not expected to be highly contaminated.  Hence, generation of adverse odour impact from dredging is not anticipated.

Operational Phase

3.5.5          Effluent from Wan Chai East Sewage Screening Plant would be discharged to Victoria Harbour via the proposed sewage outfall.  As the distance between the discharge location and the nearest ASR is more than 620 m, no adverse odour impact from the effluent is anticipated. 

 

3.6              Mitigation of Adverse Environmental Impacts

3.6.1          No adverse air quality impacts at the ASRs are expected during the construction and operation of DP5.  However, the operated dredgers and equipments should be regularly maintained to minimise emissions during construction phase. 

 

3.7              Evaluation of Residual Impacts

3.7.1          No adverse residual air quality impact arsing from the DP5 would be expected.

3.8              Environmental Monitoring and Audit

3.8.1          No adverse air quality impact would be expected arsing from the construction and operation of DP5, air quality monitoring and audit is considered unnecessary. 

3.9              Conclusion

3.9.1          Negligible air quality impact from the construction and operation of DP5 would be expected at the nearest ASRs.  Air quality monitoring and audit is therefore not required.