4.2 Environmental Legislation, Policies, Plans, Standards
and Criteria
4.3 Description of the Environment
4.6 Identification of Environmental Impacts
4.7 Prediction and Evaluation of Environmental Impacts
4.8 Mitigation of Adverse Environmental Impacts
4.9 Evaluation of Residual Impacts
4.10 Environmental Monitoring and Audit
·
EIAO-TM
·
TM
on Noise from Construction Work other than Percussive Piling (GW-TM)
·
TM
on Noise from Percussive Piling (PP-TM)
·
TM
on Noise from Construction Work in Designated Areas (DA-TM)
·
TM
on Noise from Places other than Domestic Premises, Public Places or Construction
Sites (IND-TM)
Table 4.1 Construction Noise Criteria for Activity other than Percussive Piling
Time Period |
Basic Noise Level (BNLs), Leq (30-min) dB(A) |
||
ASR A |
ASR B |
ASR C |
|
Evening
(1900 to 2300 hours) (1) |
60 |
65 |
70 |
Night (2300 to 0700 hours) |
45 |
50 |
55 |
Notes: (1) Includes
Sundays and Public Holidays during daytime and evening
Table 4.2 Acceptable Noise Levels for Percussive Piling
NSR Window Type or Means of Ventilation |
ANL, Leq (30-min) dB(A) |
NSR (or part of NSR) with no
windows or other opening |
100 |
NSR
with central air conditioning system |
90 |
NSR
with windows or other openings but without central air conditioning system |
85 |
Note: 10
dB(A) shall be subtracted from the ANLs shown above for NSRs which are
hospitals, medical clinics, educational institutes, courts of law or other NSRs
which are considered by the Authority to be particularly sensitive to noise.
Table 4.3 Permitted Hours of Operation for Percussive Piling
Amount by which
Corrected Noise Level (CNL) exceeds Acceptable Noise Level (ANL), CNL-ANL |
Permitted hours of
operation on any day not being a general holiday |
-10 dB(A) <
CNL-ANL |
Nil |
CNL-ANL £
-10 dB(A) |
0700 to 1900 |
·
erecting
or dismantling of formwork or scaffolding
·
loading,
unloading or handling of rubble, wooden boards, steel bars, wood or scaffolding
material
·
hammering
Table 4.4 Representative Existing Noise Sensitive Receivers
NSR |
Section |
Location |
Use |
Ground
elevation (mPD) |
No.
of Floors |
N2 |
Wanchai |
Causeway
Centre |
Residential |
4.0 |
42 |
N3 |
Wanchai |
|
Residential |
3.7 |
12 |
Table 4.5 Summary of Construction Tasks and Stages
Item |
Tasks and Stages |
Construction Period |
Main Construction Elements |
1
|
|||
1.1 |
|
January 2009 to February 2016 |
Temporary Breakwater Relocation Mooring to
Temporary CBTS Relocation Mooring back to CBTS |
1.2 |
CBTS Temporary Reclamation Stage 1 |
August 2009 to May 2012 |
Dredging, temp seawalls
and filling (TCBR1) CWB Tunnel (TCBR1) CWB Tunnel ( |
1.3 |
CBTS Temporary Reclamation Stage 2 |
November 2009 to May 2012 |
Dredging, temp seawalls and filling (TCBR2) CWB Tunnel (TCBR2) |
1.4 |
CBTS Temporary Reclamation Stage 3 |
January 2011 to April 2014 |
Dredging, temp seawalls and filling (TCBR3) CWB Tunnel (TCBR3) |
1.5 |
CBTS Temporary Reclamation Stage 4 |
May 2012 to November 2015 |
Dredging, temp seawalls and filling (TCBR4) CWB Tunnel (TCBR4) |
1.6 |
Temp Diversion of Cooling Water System |
October 2010 to January 2016 |
|
1.7 |
Promenade along CBTS |
November 2015 to March 2016 |
|
1.9 |
|
August 2013 to
March 2015 |
Slip Road 8 &Tunnel Transplant Trees in Victoria Park At-grade Road, Landscaped deck Reinstate Landscape work in VP
|
2
Ex-PCWA Temporary Reclamation |
|||
2.1 |
Temporary Reclamation PCWA Stage 1 |
February 2009 to
May 2012 |
Dredging, Filing
and Seawall (PCWAE) CWB Tunnel (PCWAE) |
2.2 |
Temporary Reclamation PCWA Stage 2 |
March 2012 to
May 2015 |
Dredging, Filing
and Seawall (PCWAW) CWB Tunnel (PCWAW) |
3
Wan Chai Reclamation |
|||
3.1 |
Wan Chai Reclamation Stage 1 |
January 2009 to February 2011 |
Dredging, Seawalls and Filling Drainage Culverts Cooling Water Syetem CWB Tunnel(WCR1) |
3.2 |
Wan Chai Reclamation Stage 2 |
January 2011 to May 2013 |
Dredging, Seawalls and Filling CWB Tunnel Promenade |
3.3 |
Wan Chai Reclamation Stage 3 |
April 2011 to March 2015 |
Dredging, Seawalls and Filling CWB Tunnel Promenade |
3.4 |
Wan Chai Reclamation Stage 4 |
October 2012 to March 2015 |
Dredging, Seawalls and Filling Drainage Culverts CWB Tunnel Promenade |
3.6 |
Ferry Pier Reprovisioning |
February 2009 to May 2011 |
Temporary Ferry Piers New Ferry Piers |
3.7 |
Helipad Reprovisioning |
January 2009 to June 2010 |
Reprovisioning at HKCEC |
3.8 |
Sewage Outfall |
October 2009 to April 2011 |
Marine Section – Submarine Pipelines Land Section – New Pipeline |
3.9 |
WSD’s Salt Water Pumping Station |
February 2009 to October 2010 |
Construct New Pumping Station |
3.10 |
Roads |
October 2014 to September 2015 |
Road P2 |
4
HKCEC Reclamation |
|||
4.1 |
HKCEC Reclamation Stage 1 (Water Channel) |
January 2009 to April 2016 |
Dredging, Seawalls and Filling Cooling Water Systems CWB Tunnel |
4.2 |
HKCEC Reclamation Stage 2 |
January 2009 to March 2014 |
Dredging, Seawalls and Filling Drainage Culverts CWB Tunnel |
4.3 |
MTR Tunnel Crossing |
October 2010 to February 2012 |
Piling for Tunnel Units and Deck Tunnel and Deck Construction |
4.4 |
HKCEC Reclamation Stage 3 |
March 2011 to October 2013 |
Dredging, Seawalls and Filling Drainage Culverts CWB Tunnel |
4.5 |
Roads |
March 2014 to November 2015 |
Road P2 |
5 Cross
Harbour Watermains |
|||
5.1 |
Submarine Pipeline |
January 2009 to September 2010 |
Lay New Submarine Pipeline |
5.2 |
Lands Sections |
September 2009 to May 2010 |
|
6.0
North Point Reclamation |
|||
6.1 |
North Point Reclamation Stage 1 |
January 2009 to October 2010 |
Dredging, Seawalls and Filling CWB Tunnel (NPR1) |
6.2 |
North Point Reclamation Stage 2 |
April 2009 to November 2012 |
Dredging, Seawalls and Filling (NPR2E, NPR2W) CWB Tunnel (NPR2W) |
6.3 |
Promenade |
August 2016 to December 2016 |
Promenade (NP) Final |
7.0
Construction of |
|||
7.2 |
IEC Connection Work |
October 2010 to May 2016 |
IEC East Bound (E/B) (HFS to Mainline) IEC E/B Traffic Diversion Reconstruction IEC West Bound(W/B) IEC W/B Traffic Diversion Mainline Connection to IEC |
7.3 |
East Portal and IEC Connection |
May 2015 to August 2016 |
Portal Construction Traffic Diversion IEC E/B |
10 |
|
November 2011 to May 2016 |
|
10.1 |
|
November 2012 to September 2013 |
Superstructure of the Building E&M Work |
10.2 |
|
February 2015 to November 2015 |
Substructure of the Building Superstructure of the Building E&M Work |
10.3 |
|
January 2014 to January 2015 |
Substructure of the Building Superstructure of the Building E&M Work |
· Construction of Wan Chai Sewage Outfall
· DP1 - Central-Wanchai Bypass (CWB) including its road tunnel and slip roads
· DP3 - reclamation works including associated dredging works
Table 4.6 Summary of
Unmitigated Construction Noise Levels at Representative NSRs During
Representative NSRs |
Predicted Unmitigated Construction Noise Levels during |
N2 |
69 –
81 |
N3 |
72 – 79 |
Table 4.7 Summary of Mitigated
Construction Noise Levels at Representative NSRs during
Representative NSRs |
Predicted Mitigated Construction Noise Levels during |
N2 |
64 - 71 |
N3 |
62 - 67 |
Only well-maintained plant shall be operated on-site and
plant shall be serviced regularly during the construction program.
Silencers or mufflers on construction equipment shall be
utilised and shall be properly maintained during the construction program.
Mobile plant, if any, shall be sited as far away from
NSRs as possible.
Machines and plant (such as trucks) that may be in
intermittent use shall be shut down between works periods or shall be throttled
down to a minimum.
Plant known to emit noise strongly in one direction
shall, wherever possible, be orientated so that the noise is directed away from
the nearby NSRs.
Material stockpiles and other structures shall be
effectively utilised, wherever practicable, in screening noise from on-site
construction activities.