14   CONCLUSION

14.1      Introduction

14.2      Environmental Outcomes

14.3      Air Quality Impact

14.4      Noise Impact

14.5      Water Quality Impacts

14.6      Waste Management Implications

14.7      Land Contamination Impact

14.8      Marine Ecological Impact

14.9      Landscape and Visual Impact

14.10    Cultural Heritage Impact

14.11    Environmental Monitoring and Audit

14.12    Overall Conclusion

 

 

 

 

14                CONCLUSION

14.1          Introduction

The Project is a designated project in accordance with Item C.12 of Part I of Schedule 2 of the EIAO, which specifies “A dredging operation which is less than 100m from a seawater intake point”.

14.1.1     This EIA Report has provided an assessment of the potential environmental impacts associated with the construction and operation of the Project, with the consideration of the potential cumulative impact from other projects including the Central Reclamation Phase III (CRIII) and Hong Kong Convention and Exhibition Centre Atrium Link Extension projects. Since the details of the potential future railway projects, i.e. Shatin to Central Link (SCL) and North Hong Kong Island Line (NIL) were not available at the time of this EIA study, the cumulative impacts from these two railway projects could not be addressed. Specific mitigation measures requirements for the Project, as well as an environmental monitoring and auditing programme, have been developed during the assessment of the proposed developments.  The Implementation Schedule of the recommendations is presented in Section 13.  A summary of the environmental impacts associated with the Project are present in Table 14.1. The key assessment assumptions, limitation of assessment methodologies and all obtained relevant prior agreements with the EPD or other authorities on individual environmental media assessment components are given in Appendix 15.1. The key environmental outcomes arising from the EIA study and the principal findings of the study are summarized in Section 14.2.


Table 14.1       Summary of Environmental Impacts Associated with the Project

 

Environmental Issue

Sensitive Receivers/ Assessment Points

Impact Prediction Results

Relevant Standards/ Criteria

Extents of Exceedances

Impact Avoidance Measures/ Mitigation Measures

Residual Impacts

Air Quality

 

 

 

 

 

 

Construction Phase

2 assessment points

Negligible dust impact, marine emission and odour impact from the DP6 would be expected.

EIAO-TM and Air Quality Objective

Nil

The dredger should be regularly maintained to minimise emissions.

 

Nil

Operation Phase

Not Applicable

In view of the project nature, no adverse air quality impact during the operation phase would be anticipated. 

Not Applicable

Nil

Nil

Nil

Noise

 

 

 

 

 

 

Construction Phase and Operation Phase

Not Applicable

The proposed cross harbour water mains will extend from Wan Chai near the HKCEC Extension to connect to the existing system near the Museum of Arts at the Tsim Sha Tsui promenade. The noise sensitive receivers located within 300m of construction sites at Wan Chai and Tsim Sha Tsui are basically the buildings equipped with central air-conditioning system. The first layer of NSRs near Tsim Sha Tsui site, which are centrally air-conditioned, would provide considerable acoustic shielding to those receivers at further distance behind. Thus, no adverse noise impacts on the indoor environment of these NSRs would be anticipated.

Not Applicable

 

 

Nil

 

 

Implementation of good site practices.

Nil

 

 

 

 

Water Quality

 

 

 

 

 

 

Potential SS elevations from dredging for construction of the water mains

All water sensitivity receivers in Victoria Harbour, Western Buffer and Eastern Buffer WCZs

The model results indicate exceedances of WSD water quality (SS) criterion for flushing water intakes (at Kennedy Town, Quarry Bay, Sai Wan Ho, Sheung Wan, and Wan Chai) and target SS level at Admiralty Centre and MTRC South cooling water intakes. 

Full compliance with the assessment criterion for sedimentation rate

WSD water quality criterion for SS: < 10 mg/l

Target SS level at Admiralty Centre and MTRC cooling water intakes: < 40 mg/l

Sedimentation rate at corals: <100g/m2/day

Maximum SS levels predicted at the WSD flushing water intakes ranged from 12.5 mg/l to 51.1 mg/l.

Maximum SS levels predicted at Admiralty Centre and MTRC cooling water intakes ranged from 40.4 mg/l to 100.8 mg/l.

No exceedance for the sedimentation rate was predicted

Restriction on the maximum dredging rates at the sewage pipelines zone, water mains zone, TWB, HKCEC Stage 1 & 3 as well as the western seawall of WCR1 which is close to the WSD intake at Wan Chai;

Deployment of silt curtains around seawall dredging and seawall trench filling in NPR, TCBR, WCR and HKCEC areas.

Deployment of silt screens at selected seawater intakes

Nil

Waste Management Implications

 

 

 

 

 

Construction Phase

Not applicable

Main waste: dredged marine sediment with a total volume of approx. 0.06Mm3. 

1.    Waste Disposal Ordinance (Cap. 354)

Not applicable

Refer to Table 13.4

Nil

 

 

Other wastes: general refuse from the workforce; chemical waste from plant and equipment maintenance; and C&D material from excavation works and the demolition of existing structures.

2.    Waste Disposal (Chemical Waste) (General) Regulation (Cap. 354)

 

 

 

 

 

3.    Land (Miscellaneous Provisions) Ordinance (Cap. 28)

 

 

 

 

 

4.    Public Health and Municipal Services Ordinance (Cap. 132) - Public Cleansing and Prevention of Nuisances Regulation

 

 

 

 

 

 

5.    Annexes 7 & 15 of EIAO TM

 

 

 

Marine Ecological Impacts

 

 

 

 

 

Construction Phase

Ecological resources in the assessment area

Temporary loss of less than 0.5 ha soft bottom benthic & subtidal habitats

Not applicable

Not applicable

-          As no adverse ecological impact on marine habitats and associated wildlife is predicted, no necessary mitigation measure specific for marine ecology is considered as required in this assessment.  The mitigation measures recommended in the water quality impact assessment to control water quality would also serve to protect marine ecological resources from indirect impacts and ensure no adverse impact on marine life would be resulted from this designated project.

Not expected

Changes in water quality

-          More than 30% increase of SS at the immediate vicinity outside reclamation area

-          Insignificant elevation of SS at far-field sensitive receivers

-          Level of TIN is predicted to be slightly higher than WQO standard at several locations immediately outside reclamation area

-          Minimum depth-averaged DO at HKCEC is predicted to be slightly lower than 4.0 mg/L

(See water quality assessment)

 

(See water quality assessment)

 

 

 

Disturbance impact

Not applicable

Not applicable

 

 

Operational Phase

Ecological resources in the assessment area

No direct or indirect impact on marine ecological resources is predicted

 

 

 

 

Landscape and Visual Impact

 

 

 

 

 

Construction Phase

All Landscape Resources / Landscape Character Areas and Visual Sensitive Receivers within the study area

-          There will still be some slight negative visual impact on the VSRs in the front row of high rise buildings along the waterfront from Central to North Point. 

 

-          The impact on the Victoria Harbour is primary due to the construction of the submarine section of the cross-harbour watermains.

1.        EIAO and TM, particularly Annexes 10 and 18,

2.        EIAO Guidance Note 8/2002,

 

Not applicable

-          Control of night-time lighting.

-          Erection of decorative screen hoarding compatible with the surrounding setting.

 

Landscape Impacts

There will be no landscape impact during construction.

It is considered that the residual impacts on Victoria Harbour are slight with implementation of mitigation measures.

Visual Impacts

With implementation of mitigation measures during construction, there will be some slight negative visual impact on the VSRs in the front row of high rise buildings along the waterfront from Central to North Point.  Residual impacts VSRs further away the Victoria Harbour and from the hinterland will become slight or insubstantial.  

Operational Phase

All Landscape Resources / Landscape Character Areas and Visual Sensitive Receivers within the study area

There will be no landscape and visual impacts during operation.

1.                    EIAO and TM, particularly Annexes 10 and 18,

2.                    EIAO Guidance Note 8/2002,

3.                    Town Planning Ordinance (Cap 131),

Not applicable

Not applicable

Landscape Impacts

There will be no landscape impact during operation.

 

Visual Impacts

There will be no visual impact during operation.

 

 

 

4.                    ETWB TCW No. 2/2004 - Maintenance of Vegetation and Hard Landscape Features.

 

 

 

Cultural Heritage Impact

 

 

 

 

 

Construction Phase

Marine archaeological resources in Victoria Harbour

Since there is no archaeological material present within the study area, no adverse cultural heritage impact is expected.

1.  Antiquities and Monuments Ordinance (Cap.53)

2.  Environmental Impact Assessment Ordinance (EIAO) (Cap. 499, S.16)

Not applicable

No further archaeological investigation or mitigation measures is required

Nil

 

 

 

3.  Technical Memorandum on the Environmental Impact Assessment Process (EIAO-TM)

 

 

 

 

 

 

4.  Guidance Notes on Assessment of Impact on Sites of Cultural Heritage in Environmental Impact Assessment Studies (GN-CH)

 

 

 

 

 

 

5.  Hong Kong Planning Standards and Guidelines (HKPSG)

6.  Marine Archaeological Investigation Guidelines.

 

 

 


14.2          Environmental Outcomes

14.2.1      The major environmentally sensitive areas within the study area include residential buildings, commercial buildings, hotels, recreational areas, educational institutions, and WSD flushing water intakes and cooling water intakes at the waterfront of Victoria Harbour.  The population within the study area is approximately 125,000.  With the implementation of the proposed control and mitigation measures, the air, noise and water quality sensitive receivers within the study area would be protected from adverse environmental impacts arising from the Project during both construction and operational phases.  A summary of the key environmental outcomes arising from the EIA study and environmental benefits of the environmental protection measures recommended are presented in Table 14.2 below.

 

           Table 14.2       Summary of Key Environmental Outcomes/ Benefits

 

Issue

Environmental Outcomes/Benefits

 

The Project

Requirements:

An existing cross harbour fresh water mains, comprising twin 1,000 mm diameter steel submarine pipelines from Tsim Sha Tsui, runs along the west of the MTR Tsuen Wan Line to a landfall at the seafrontage north of the Wan Chai West Sewage Screening Plant, near Lung King Street.  As the reclamation works could potentially damage the watermains, diversion of these mains prior to construction will be necessary.  It is an essential requirement by WSD that the operation of the cross harbour water mains should be maintained at all times with no interruption to the water supply.

 

 

Benefits:   

The Project provides opportunity to lay new cross harbour water mains to replace the existing ones, to avoid damage to the existing mains and disruption to essential water supply to Hong Kong Island.

In environmental terms, water quality at Victoria Harbour would be similar for both the situations with and without the Project.

 

 

Potential consequences without the Project:

Should the existing cross harbour water mains not be reprovisioned under the Project, the existing cross harbour water mains will potentially be damaged by the reclamation works and the construction of the Trunk Road tunnel.  Without the cross harbour watermains, the fresh water supply to Hong Kong Island will be seriously affected, which cannot be tolerated.

 

Development Alternatives

The alternative to constructing new cross harbour watermains to reprovision the existing one is to construct a deck over structure above the existing pipelines.  However, this alternative option is considered not feasible as the Trunk Road tunnel will be crossing the existing pipelines at a similar level and there will be problems for future maintenance of the pipelines below the deck structure.  Construction of new cross-harbour water mains is considered a reasonable and practicable solution.

 

Construction Air Quality Impact

Environmental benefits of environmental protection measures recommended:

Dust nuisance is not expected as dredging is a marine based activity

Adverse marine emission from the dredging activities is not anticipated as only one dredger to be operated for 16 days in accordance with the construction programme.  The dredger should be regularly maintained.

Potential odour impact from contaminated sediment during dredging in the work site is not expected as the work area is not a stagnant or low water flow area in Victoria Harbour.

 

Compensation areas included:

Not required.

 

Population and environmental sensitive receivers protected:

Existing air sensitive receivers within 500m of the project boundary.

 

Operation Air Quality Impact

Environmental benefits of environmental protection measures recommended:

In view of the project nature, no adverse air quality impact during the operation phase would be anticipated.

 

Compensation areas included:

Not required

 

Population and environmental sensitive receivers protected:

No air sensitive receiver would be affected.

 

Construction Noise Impact

Environmental benefits of environmental protection measures recommended:

The proposed cross harbour water mains will extend from Wan Chai near the HKCEC Extension to connect to the existing system near the Museum of Arts at the Tsim Sha Tsui promenade. The noise sensitive receivers located within 300m of construction sites at Wan Chai and Tsim Sha Tsui are basically the buildings equipped with central air-conditioning system. The first layer of NSRs near Tsim Sha Tsui site, which are centrally air-conditioned, would provide considerable acoustic shielding to those receivers at further distance behind. Thus, no adverse noise impacts on the indoor environment of these NSRs would be anticipated. Nevertheless, the Contractor shall implement good site practices during construction work.

 

 

Compensation areas included:

Not required.

 

 

Population and environmental sensitive receivers protected:

Noise sensitive receivers within 300m of the project boundary.

 

Operation Noise Impact

Environmental benefits of environmental protection measures recommended:

In view of the project nature, no adverse noise impact during the operation phase would be anticipated

 

Compensation areas included:

Not required

 

Population and environmental sensitive receivers protected:

No noise sensitive receiver would be affected.

 

Water Quality Impact

Environmental benefits of environmental protection measures recommended:

The major water quality impact associated with the new water mains would be the potential SS elevations within the water column from the dredging works during the construction phase.  Provided the recommended mitigation measures are implemented, including restriction on the maximum dredging rates, the deployment of silt curtains at the other specified current dredging and filling areas activities within the WDII work site, and installation of silt screens at seawater intakes, there will be no unacceptable residual water quality impact due to the proposed dredging works.

 

Compensation areas included:

Not required.

 

Population and environmental sensitive receivers protected:

Seawater intakes along the waterfront of Victoria Harbour and corals identified in Junk Bay, Green Island and Cape Collinson.

 

Waste Management Implications

Environmental benefits of environmental protection measures recommended:

With the implementation of the recommended mitigation measures and practices, potential air, odour, noise, water quality for the handling, transportation and disposal of the identified waste arisings, no adverse environmental impacts are expected.

 

Compensation areas included:

Not required.

Population and environmental sensitive receivers protected:

Water quality, air, and noise sensitive receivers at or near the Project site, the waste transportation routes and the waste disposal site.

 

 

Land Contamination Impact

Environmental benefits of environmental protection measures recommended:

No potential contaminative land uses were identified within the Study Area.  As such, adverse land contamination impacts associated with the construction and operation of the Project  is not expected.

 

Compensation areas included:

Not required.

 

Population and environmental sensitive receivers protected:

No construction worker would be affected.

 

Marine Ecological Impact

Environmental benefits of environmental protection measures recommended:

The benthic, intertidal and subtidal habitats within the affected area are of very low ecological value. Hence, adverse direct ecological impact is not expected. Water quality and noise control measures (as described above) would minimise indirect impact on marine habitats and associated flora and fauna due to change in water quality and noise environment during the construction phase.   

 

Compensation areas included:

Not required.

 

Population and environmental sensitive receivers protected:

No ecological sensitive receiver would be affected.

 

Landscape and Visual Impact

Environmental benefits of environmental protection measures recommended:

·       A twin submarine cross-harbour water mains will be constructed in Victoria Harbour.  It is considered that the residual impacts on Victoria Harbour are slight with implementation of mitigation measures and insubstantial during operation.

 

 

·       With implementation of mitigation measures during construction, there will still be some slight negative visual impact on the VSRs in the front row of high rise buildings along the waterfront from Central to North Point.  Residual impacts VSRs further away the Victoria Harbour and from the hinterland will become slight or insubstantial.  During operation, there will be no visual impact as the cross harbour water mains will be underneath the harbour.

 

 

 

Compensation areas included:

Approximately 13.8 ha of new waterfront open space and nine new pedestrian links to the new harbour-front will be provided

 

Population and environmental sensitive receivers protected:

Existing and planned Landscape Resources , Landscape Character Area and VSR at and near the project site.

 

Cultural Heritage Impact

Environmental benefits of environmental protection measures recommended:

Since there are no marine archaeological resources within the study area that would be affected by the project, marine archaeological impact due to the construction activities is not expected. No environmental protection measure is required.

 

Compensation areas included:

Not required.

 

Population and environmental sensitive receivers protected:

No archaeological resources would be affected.

 

 

14.3          Air Quality Impact

14.3.1      Dredging is marine based activity, dust nuisance from this construction activity is not anticipated.  Under normal operation, the dredger with proper maintenance is unlikely to cause significant dark smoke emissions and gaseous emissions are expected to be minor.  The dredging area is not a water stagnant or low water flow area in Victoria Harbour.  Hence, the sediment is not expected to be highly contaminated and generation of adverse odour impact from dredging is not anticipated.

14.3.2      Negligible dust impact, marine emission and odour impact from the DP6 would be expected, air quality monitoring and audit is therefore not required.

 

14.4          Noise Impact

Construction Phase

14.4.1      The proposed cross harbour water mains will extend from Wan Chai near the HKCEC Extension to connect to the existing system near the Museum of Arts at the Tsim Sha Tsui promenade. The noise sensitive receivers located within 300m of construction sites at Wan Chai and Tsim Sha Tsui are basically the buildings equipped with central air-conditioning system. The first layer of NSRs near Tsim Sha Tsui site, which are centrally air-conditioned, would provide considerable acoustic shielding to those receivers at further distance behind. Thus, no adverse noise impacts on the indoor environment of these NSRs would be anticipated. 

14.4.2      While construction noise monitoring would not be considered required for this DP, a weekly site inspection shall be carried out throughout the construction phase to ensure that appropriate noise control measures would be properly implemented with a view to minimizing the construction noise impact.

 

Operational Phase

14.4.3      In view of the project nature, no adverse noise impact during the operation phase would be anticipated.

 

14.5          Water Quality Impacts

14.5.1      The major water quality impact associated with the new water mains would be the potential SS elevations within the water column from the dredging works during the construction phase.  Provided the recommended mitigation measures are implemented, including restriction on the maximum dredging rates, the deployment of silt curtains at the other specified current dredging and filling areas activities within the WDII work site, and installation of silt screens at seawater intakes, there will be no unacceptable residual water quality impact due to the proposed dredging works.

14.6          Waste Management Implications

14.6.1      A review of the sediment quality data from the marine ground investigation indicated that the majority of marine sediments to be dredged for the project are classified as contaminated.  The total dredged volume during the construction of the Cross-harbour water mains is estimated as approximately 0.06 Mm3, of which 0.024 Mm3 is classified as contaminated (Category M and H) requiring Type 2 confined marine disposal, and 0.036 Mm3  is classified as Category L and would be suitable for Type 1 open sea disposal.  With the implementation of the recommended mitigation measures in accordance with the requirements of ETWB TCW No. 34/2002, no adverse residual impact is predicted.

14.6.2      Wastes generated by the construction activities will include C&D material, general refuse from the workforce and chemical waste from the maintenance of construction plant and equipment.  C&D material with suitable characteristics would be reused on-site as far as practicable.  Surplus material would require disposal to designed public filling facilities.  Provided that these identified waste arisings are handled, transported and disposed of using approved methods and that recommended good site practice are strictly followed, adverse environmental impacts would not be expected during the construction phase.

14.7          Land Contamination Impact

14.7.1      No potential contaminative land uses were identified within the Study Area.  As such, no adverse land contamination impacts associated with the construction and operation of the Project is expected.

14.8          Marine Ecological Impact

14.8.1      Literature reviews of existing information supplemented with the results of recently undertaken field surveys on marine ecological resources indicated that identified marine habitats within the Assessment Area are of low ecological value.  There are no ecological sensitive receivers, such as SSSIs, Marine Parks and / or Reserves and other areas of ecological importance or conservation interest, in and within the immediate vicinity of the Assessment Area.


14.8.2      Direct and indirect ecological impacts arising from this designated project during construction phase were identified and evaluated. The designated project would result in the temporary loss of less than 0.5 hectare of soft bottom benthic and subtidal habitats in the coastal area of the Victoria Harbour. Considering that the benthic and subtidal habitats within the Assessment Area are of very low ecological value, no adverse direct ecological impact is expected. 

14.8.3                                               Indirect disturbance impact on the associated waterbirds and other avifaunal species of conservation interest foraging in the Victoria Harbour and the CBTS was expected to occur during the construction phase of this project. Considering the existing background of intense human activities in these areas, the affected wildlife are considered already well adapted to human disturbance and therefore no adverse indirect impact is expected to occur.

14.8.4      Other impacts arsing from this project would be temporary and minimised with implementation of proper mitigation measures. Overall, no adverse ecological impacts on marine resources are anticipated. 

 

14.9          Landscape and Visual Impact

14.9.1      The proposed development and associated works follow in principle the planning intentions from the Metroplan, Visions and Goals for Victoria Harbour prepared by Town Planning Board and the views of the public received during the engagement exercises of the HER that was carried out under the steer of HEC Sub-committee on WDII Review.  In respond to the CFA judgment on the PHO, the extent of reclamation has been reduced to the minimum.  With the new waterfront development proposals together with enhanced connectivity to the waterfront from the hinterland and east-west linkages along the northshore, the landscape planning framework of the waterfront from Wan Chai to North Point is strengthened and reinforced by the proposed project.

14.9.2      A twin submarine cross-harbour watermains from Wan Chai to Tsim Sha Tsui will be constructed in Victoria Harbour.  It is considered that the residual impacts on Victoria Harbour are slight during construction with mitigation measures and insubstantial during operation phase.

14.9.3      With implementation of mitigation measures during construction, there will still be some slight negative visual impact on the VSRs in the front row of high rise buildings along the waterfront from Central to North Point.  Residual impacts on VSRs further away the Victoria Harbour and in the hinterland will become slight or insubstantial.  During operation, there will be no visual impact as the cross harbour water mains will be underneath the harbour.

14.10      Cultural Heritage Impact

14.10.1   The results of the MAI in 2001 (Report No. SDA8827) are applicable to the current study since they cover the same seabed area.  There have not been any significant changes to the seabed since 2001 which would have affected its archaeological potential. According to the MAI in 2001, it was concluded there were no archaeological resources within the project area of the Cross-harbour water mains.


14.11      Environmental Monitoring and Audit

14.11.1  Environmental monitoring and audit (EM&A) are recommended for construction dust monitoring, construction and operation noise, and water quality.  Site inspection / audit is also recommended for waste management during construction and also for implementation of landscaping measures during operation.  Details of the recommended mitigation measures, monitoring procedures and locations will be presented in a stand-alone EM&A Manual.  This will enable the Contractor to have early warning and provide necessary action to reduce impacts at specific areas if the assessment criteria are approached.  The effectiveness of on-site control measures could also be evaluated through the monitoring exercise.  All the recommended mitigation measures should be incorporated into the EM&A programme for implementation.

 

14.12      Overall Conclusion

14.12.1  The EIA has been conducted based on currently available information and has been adequately addressed the environmental impacts of this Schedule 2 designated project. No outstanding issues were identified and hence further detailed EIA study was considered not necessary.  The findings of this EIA have provided information on the nature and extent of environmental impacts arising from the construction and operation of the Project.  The EIA has, where appropriate, identified mitigation measures to ensure compliance with environmental legislation and standards.

14.12.2  Overall, the EIA Report for this DP has predicted that the Project will generally comply with the environmental standards and legislation after the proposed construction and operational stage mitigation measures are implemented.  This EIA has also demonstrated the general acceptability of the residual impacts from the Project and the protection of the population and environmentally sensitive resources.  Environmental monitoring and audit mechanisms have been recommended before and during construction and operation, where necessary, to verify the accuracy of the EIA predictions and the effectiveness of recommended mitigation measures.