14.6 Waste
Management Implications
14.7 Land
Contamination Impact
14.9 Landscape
and Visual Impact
14.10 Cultural
Heritage Impact
14.11 Environmental
Monitoring and Audit
The Project is a designated project in
accordance with Item C.12 of Part I of Schedule 2 of the EIAO, which specifies
“A dredging operation which is less than 100m from a seawater intake point”.
14.1.1
This
EIA Report has provided an assessment of the potential environmental impacts
associated with the construction and operation of the Project, with the
consideration of the potential cumulative impact from other projects including
the Central Reclamation Phase III (CRIII) and Hong Kong Convention and
Exhibition Centre Atrium Link Extension projects. Since the details of the
potential future railway projects, i.e. Shatin to Central Link (SCL) and North
Hong Kong Island Line (NIL) were not available at the time of this EIA study,
the cumulative impacts from these two railway projects could not be addressed.
Specific mitigation measures requirements for the Project, as well as an
environmental monitoring and auditing programme, have been developed during the
assessment of the proposed developments.
The Implementation Schedule of the recommendations is presented in
Section 13. A summary of the
environmental impacts associated with the Project are present in Table 14.1. The key assessment
assumptions, limitation of assessment methodologies and all obtained relevant
prior agreements with the EPD or other authorities on individual environmental
media assessment components are given in Appendix
15.1. The key
environmental outcomes arising from the EIA study and the principal findings of
the study are summarized in Section 14.2.
Table 14.1 Summary
of Environmental Impacts Associated with the Project
Environmental Issue |
Sensitive
Receivers/ Assessment Points |
Impact Prediction
Results |
Relevant Standards/
Criteria |
Extents of
Exceedances |
Impact Avoidance
Measures/ Mitigation Measures |
Residual Impacts |
|
Air Quality |
|
|
|
|
|
|
|
Construction Phase |
2 assessment
points |
Negligible dust impact,
marine emission and
odour impact from the
DP6 would be expected. |
EIAO-TM and Air
Quality Objective |
Nil |
The dredger should be regularly maintained to minimise emissions. |
Nil |
|
Operation Phase |
Not Applicable |
In view of the project nature, no adverse air quality
impact during the operation phase would be anticipated. |
Not Applicable |
Nil |
Nil |
Nil |
|
Noise |
|
|
|
|
|
|
|
Construction Phase and
Operation Phase |
Not Applicable |
The
proposed cross harbour water mains will extend from Wan Chai near the HKCEC
Extension to connect to the existing system near the |
Not Applicable |
Nil |
Implementation of good
site practices. |
Nil |
|
|
|
|
|
||||
Water Quality |
|
|
|
|
|
|
|
Potential SS elevations from dredging for construction of the water
mains |
All water sensitivity
receivers in |
The model results indicate
exceedances of WSD water quality (SS) criterion for flushing water intakes
(at Full compliance with
the assessment criterion for sedimentation rate |
WSD water quality
criterion for SS: < 10 mg/l Target SS level at
Admiralty Centre and MTRC cooling water intakes: < 40 mg/l Sedimentation rate at
corals: <100g/m2/day |
Maximum SS levels
predicted at the WSD flushing water intakes ranged from 12.5 mg/l to 51.1 mg/l. Maximum SS levels
predicted at Admiralty Centre and MTRC cooling water intakes ranged from 40.4 mg/l to 100.8 mg/l. No exceedance for the
sedimentation rate was predicted |
Restriction on the
maximum dredging rates at the sewage pipelines zone, water mains zone, TWB,
HKCEC Stage 1 & 3 as well as the western seawall
of WCR1 which is close to the WSD intake at Wan Chai; Deployment of silt
curtains around seawall dredging and seawall trench filling in NPR, TCBR, WCR
and HKCEC areas. Deployment of silt screens at selected seawater
intakes |
Nil |
|
Waste Management Implications |
|
|
|
|
|
||
Construction Phase |
Not applicable |
Main waste: dredged marine sediment with a total volume of approx. 0.06Mm3. |
1. Waste Disposal Ordinance (Cap.
354) |
Not applicable |
Refer to Table 13.4 |
Nil |
|
|
|
Other wastes: general refuse from
the workforce; chemical waste from plant and equipment maintenance; and
C&D material from excavation works and the demolition of existing
structures. |
2. Waste Disposal (Chemical Waste)
(General) Regulation (Cap. 354) |
|
|
|
|
|
|
3. Land (Miscellaneous Provisions)
Ordinance (Cap. 28) |
|
|
|
||
|
|
4. Public Health and Municipal
Services Ordinance (Cap. 132) - Public Cleansing and Prevention of Nuisances
Regulation |
|
|
|
||
|
|
|
5. Annexes 7 & 15 of EIAO TM |
|
|
|
|
Marine Ecological Impacts |
|
|
|
|
|
||
Construction Phase |
Ecological resources
in the assessment area |
Temporary loss of less than |
Not applicable |
Not applicable |
- As no adverse ecological impact on marine habitats and associated wildlife is predicted, no necessary mitigation measure specific for marine ecology is considered as required in this assessment. The mitigation measures recommended in the water quality impact assessment to control water quality would also serve to protect marine ecological resources from indirect impacts and ensure no adverse impact on marine life would be resulted from this designated project. |
Not
expected |
|
Changes in water
quality -
More than 30% increase of SS at the immediate vicinity outside
reclamation area -
Insignificant elevation of SS at far-field sensitive receivers -
Level of TIN is predicted to be slightly higher than WQO standard at
several locations immediately outside reclamation area -
Minimum depth-averaged DO at HKCEC is predicted to be slightly lower than
4.0 mg/L |
(See water quality
assessment) |
(See water quality
assessment) |
|||||
|
|
Disturbance impact |
Not applicable |
Not applicable |
|
|
|
Operational Phase |
Ecological resources
in the assessment area |
No direct or indirect impact on marine ecological resources is predicted |
|
|
|
|
|
Landscape and Visual Impact |
|
|
|
|
|
||
Construction Phase |
All Landscape Resources /
Landscape Character Areas and Visual Sensitive Receivers within the study
area |
- There will still be some slight negative visual impact on the VSRs in the front row of high rise buildings along the waterfront from Central to North Point. -
The impact on the |
1. EIAO and TM, particularly Annexes 10 and 18, 2. EIAO Guidance Note 8/2002, |
Not applicable |
- Control of night-time lighting. - Erection of decorative screen hoarding compatible with the surrounding setting. |
Landscape
Impacts There
will be no landscape impact during construction. It is considered that the residual impacts on Visual
Impacts With implementation of mitigation measures during
construction, there will be some slight negative visual impact on the VSRs in
the front row of high rise buildings along the waterfront from Central to
North Point. Residual impacts
VSRs further away the |
|
Operational Phase |
All Landscape Resources / Landscape Character Areas and Visual Sensitive Receivers within the study area |
There will be no landscape
and visual impacts during operation. |
1. EIAO and TM, particularly Annexes 10 and 18, 2. EIAO Guidance Note 8/2002, 3. Town Planning Ordinance (Cap 131), |
Not applicable |
Not applicable |
Landscape
Impacts There will be no landscape impact during operation. Visual Impacts There will be no visual impact during operation. |
|
|
|
|
4. ETWB TCW No. 2/2004 - Maintenance of Vegetation and Hard Landscape Features. |
|
|
|
|
Cultural Heritage Impact |
|
|
|
|
|
||
Construction Phase |
Marine archaeological
resources in |
Since there is no
archaeological material present within the study area, no adverse cultural
heritage impact is expected. |
1.
Antiquities and Monuments Ordinance (Cap.53) 2.
Environmental Impact Assessment Ordinance (EIAO) (Cap. 499,
S.16) |
Not applicable |
No further
archaeological investigation or mitigation measures is required |
Nil |
|
|
|
|
3.
Technical Memorandum on the Environmental Impact Assessment
Process (EIAO-TM) |
|
|
|
|
|
|
|
4.
Guidance Notes on Assessment of Impact on Sites of Cultural
Heritage in Environmental Impact Assessment Studies (GN-CH) |
|
|
|
|
|
|
|
5.
6.
Marine Archaeological Investigation Guidelines. |
|
|
|
|
14.2.1
The
major environmentally sensitive areas within the study area include residential
buildings, commercial buildings, hotels, recreational areas, educational
institutions, and WSD flushing water intakes and cooling water intakes at the
waterfront of
Table
14.2 Summary
of Key Environmental Outcomes/ Benefits
Issue |
Environmental Outcomes/Benefits |
The Project |
Requirements: An existing cross harbour fresh water mains, comprising twin |
|
Benefits: The Project provides opportunity to lay new cross harbour water
mains to replace the existing ones, to avoid damage to the existing mains and
disruption to essential water supply to In environmental terms, water quality at |
|
Potential consequences
without the Project: Should the existing cross harbour water mains not be reprovisioned
under the Project, the existing cross harbour water mains will potentially be
damaged by the reclamation works and the construction of the Trunk Road
tunnel. Without the cross harbour
watermains, the fresh water supply to |
Development
Alternatives |
The alternative to constructing new cross harbour watermains to reprovision the existing one is to construct a deck over structure above the existing pipelines. However, this alternative option is considered not feasible as the Trunk Road tunnel will be crossing the existing pipelines at a similar level and there will be problems for future maintenance of the pipelines below the deck structure. Construction of new cross-harbour water mains is considered a reasonable and practicable solution. |
Construction Air
Quality Impact |
Environmental
benefits of environmental protection measures recommended: Dust nuisance is not expected as dredging is a marine based activity Adverse marine emission from the dredging
activities is not anticipated as only one dredger to be operated for 16 days
in accordance with the construction programme. The dredger should be regularly
maintained. Potential odour impact from contaminated sediment during dredging in the work site is not expected as the work area
is not a stagnant or low water flow area in Compensation
areas included: Not
required. Population
and environmental sensitive receivers protected: Existing air sensitive receivers within 500m of the project boundary. |
Operation Air
Quality Impact |
Environmental
benefits of environmental protection measures recommended: In view of the project nature, no adverse air quality impact during the
operation phase would be anticipated. Compensation
areas included: Not
required Population
and environmental sensitive receivers protected: No air sensitive receiver would be affected. |
Construction Noise
Impact |
Environmental benefits of environmental protection measures recommended: The proposed cross harbour water mains will
extend from Wan Chai near the HKCEC Extension to connect to the existing
system near the |
|
Compensation
areas included: Not required. |
|
Population
and environmental sensitive receivers protected: Noise
sensitive receivers within 300m of the project boundary. |
Operation Noise Impact |
Environmental
benefits of environmental protection measures recommended: In view of the project nature, no adverse noise
impact during the operation phase would be anticipated Compensation
areas included: Not
required Population
and environmental sensitive receivers protected: No noise sensitive receiver would be affected. |
Water Quality Impact |
Environmental
benefits of environmental protection measures recommended: The major water quality impact associated
with the new water mains would be the potential SS elevations within the
water column from the dredging works during the construction phase. Provided the recommended mitigation
measures are implemented, including restriction on the maximum dredging
rates, the deployment of silt curtains at the other specified current
dredging and filling areas activities within the WDII work site, and
installation of silt screens at seawater intakes, there will be no
unacceptable residual water quality impact due to the proposed dredging
works. Compensation
areas included: Not required. Population
and environmental sensitive receivers protected: Seawater intakes along the waterfront of |
Waste Management
Implications |
Environmental benefits of environmental protection measures recommended: With the implementation of the recommended mitigation measures and practices, potential air, odour, noise, water quality for the handling, transportation and disposal of the identified waste arisings, no adverse environmental impacts are expected. Compensation
areas included: Not required. Population and environmental sensitive
receivers protected: Water quality, air, and noise sensitive receivers at or near the Project site, the waste transportation routes and the waste disposal site. |
|
|
Land Contamination
Impact |
Environmental benefits of environmental protection measures recommended: No potential contaminative land uses were identified within the Study Area. As such, adverse land contamination impacts associated with the construction and operation of the Project is not expected. Compensation
areas included: Not
required. Population and environmental sensitive receivers protected: No construction worker would be affected. |
Marine Ecological
Impact |
Environmental benefits of environmental protection measures recommended: The benthic,
intertidal and subtidal habitats within the affected area are of very low
ecological value. Hence, adverse direct ecological impact is not expected.
Water quality and noise control measures (as described above) would minimise
indirect impact on marine habitats and associated flora and fauna due to
change in water quality and noise environment during the construction
phase. Compensation
areas included: Not
required. Population
and environmental sensitive receivers protected: No ecological sensitive receiver would be affected. |
Landscape and Visual
Impact |
Environmental benefits of environmental protection measures recommended: · A twin submarine cross-harbour
water mains will be constructed in |
|
·
With implementation of
mitigation measures during construction, there will still be some slight
negative visual impact on the VSRs in the front row of high rise buildings
along the waterfront from Central to North Point. Residual impacts VSRs further away the
|
|
Compensation
areas included: Approximately
Population
and environmental sensitive receivers protected: Existing and
planned Landscape Resources , Landscape Character Area and VSR at and near
the project site. |
Cultural Heritage
Impact |
Environmental
benefits of environmental protection measures recommended: Since there are no marine archaeological
resources within the study area that would be affected by the project, marine
archaeological impact due to the construction activities is not expected. No
environmental protection measure is required. Compensation
areas included: Not required. Population
and environmental sensitive receivers protected: No archaeological resources would be
affected. |
14.3.1 Dredging is marine based
activity, dust nuisance from this construction activity is not
anticipated. Under normal
operation, the dredger with proper maintenance is unlikely to cause significant
dark smoke emissions and gaseous emissions are expected to be minor. The dredging area is not a water
stagnant or low water flow area in
14.3.2 Negligible dust impact,
marine emission and odour impact from the DP6 would be expected, air quality
monitoring and audit is therefore not required.
Construction Phase
14.4.1
The
proposed cross harbour water mains will extend from Wan Chai near the HKCEC
Extension to connect to the existing system near the
14.4.2
While
construction noise monitoring would not be considered required for this DP, a weekly site inspection shall be carried
out throughout the construction phase to ensure that appropriate noise control
measures would be properly implemented with a view to minimizing the
construction noise impact.
Operational Phase
14.4.3
In
view of the project nature, no adverse noise impact during the operation phase
would be anticipated.
14.5.1
The
major water quality impact associated with the new water mains would be the
potential SS elevations within the water column from the dredging works during
the construction phase. Provided
the recommended mitigation measures are implemented, including restriction on
the maximum dredging rates, the deployment of silt curtains at the other
specified current dredging and filling areas activities within the WDII work
site, and installation of silt screens at seawater intakes, there will be no
unacceptable residual water quality impact due to the proposed dredging works.
14.6
Waste Management
Implications
14.6.1
A
review of the sediment quality data from the marine ground investigation
indicated that the majority of marine sediments to be dredged for the project are classified as
contaminated. The total dredged
volume during the construction of the Cross-harbour water mains is estimated as
approximately
14.6.2 Wastes generated by the construction
activities will include C&D
material, general refuse from the workforce and chemical waste from the
maintenance of construction plant and equipment. C&D material with suitable
characteristics would be reused on-site as far as practicable. Surplus material would require disposal
to designed public filling facilities.
Provided that these identified waste arisings are handled, transported
and disposed of using approved methods and that recommended good site practice
are strictly followed, adverse environmental impacts would not be expected
during the construction phase.
14.7
Land Contamination
Impact
14.7.1
No
potential contaminative land uses were identified within the Study Area. As such, no adverse land contamination
impacts associated with the construction and operation of the Project is
expected.
14.8.1
Literature
reviews of existing information supplemented with the results of recently
undertaken field surveys on marine ecological resources indicated that
identified marine habitats within the Assessment Area are of low ecological
value. There are no ecological
sensitive receivers, such as SSSIs,
14.8.2
Direct
and indirect ecological impacts arising from this designated project during
construction phase were identified and evaluated. The designated project would
result in the temporary loss of less than 0.5 hectare of soft bottom benthic
and subtidal habitats in the coastal area of the
14.8.3
Indirect
disturbance impact on the associated waterbirds and other avifaunal species of
conservation interest foraging in the
14.8.4
Other
impacts arsing from this project would be temporary and minimised with
implementation of proper mitigation measures. Overall, no adverse ecological
impacts on marine resources are anticipated.
14.9
Landscape and
Visual Impact
14.9.1 The proposed
development and associated works follow in principle the planning intentions
from the Metroplan, Visions and Goals for
14.9.2 A twin submarine
cross-harbour watermains from Wan Chai to Tsim Sha Tsui will be constructed in
14.9.3 With
implementation of mitigation measures during construction, there will still be
some slight negative visual impact on the VSRs in the front row of high rise
buildings along the waterfront from Central to North Point. Residual impacts on VSRs further away
the
14.10 Cultural Heritage Impact
14.10.1 The results of
the MAI in 2001 (Report No. SDA8827) are applicable to the current study since
they cover the same seabed area.
There have not been any significant changes to the seabed since 2001
which would have affected its archaeological potential. According to the MAI in
2001, it was concluded there were no archaeological resources within the
project area of the Cross-harbour water mains.
14.11 Environmental Monitoring and Audit
14.11.1
Environmental
monitoring and audit (EM&A) are recommended for construction dust
monitoring, construction and operation noise, and water quality. Site inspection / audit is also
recommended for waste management during construction and also for
implementation of landscaping measures during operation. Details of the recommended mitigation
measures, monitoring procedures and locations will be presented in a
stand-alone EM&A Manual. This
will enable the Contractor to have early warning and provide necessary action
to reduce impacts at specific areas if the assessment criteria are
approached. The effectiveness of
on-site control measures could also be evaluated through the monitoring
exercise. All the recommended
mitigation measures should be incorporated into the EM&A programme for
implementation.
14.12.1
The
EIA has been conducted based on currently available information and has been
adequately addressed the environmental impacts of this Schedule 2 designated
project. No outstanding issues were identified and hence further detailed EIA
study was considered not necessary.
The findings of this EIA have provided information on the nature and
extent of environmental impacts arising from the construction and operation of
the Project. The EIA has, where
appropriate, identified mitigation measures to ensure compliance with
environmental legislation and standards.
14.12.2
Overall,
the EIA Report for this DP has predicted that the Project will generally comply
with the environmental standards and legislation after the proposed
construction and operational stage mitigation measures are implemented. This EIA has also demonstrated the general
acceptability of the residual impacts from the Project and the protection of
the population and environmentally sensitive resources. Environmental monitoring and audit
mechanisms have been recommended before and during construction and operation,
where necessary, to verify the accuracy of the EIA predictions and the
effectiveness of recommended mitigation measures.