3.2 Environmental
Legislation, Policies, Plans, Standards and Criteria
3.3 Description
of the Environment
3.5 Identification
of Environmental Impacts
3.6 Mitigation
of Adverse Environmental Impacts
3.7 Evaluation
of Residual Impacts
3.8 Environmental
Monitoring and Audit
3.1.1 This section presents an air quality impact assessment during the dredging for the cross-harbour water mains from Wan Chai to Tsim Sha Tsui (DP6) of the Wan Chai Development Phase II project. In view of the project nature, no adverse air quality impact during the operation phase would be anticipated. Thus, this section would only focus on construction air quality impact assessment.
3.2
Environmental Legislation, Policies, Plans, Standards and Criteria
Air
Quality Objective & EIAO-TM
3.2.2 The Air Pollution Control Ordinance (APCO) provides the statutory authority for controlling air pollutants from a variety of sources. The Hong Kong Air Quality Objectives (AQOs), which must be satisfied, stipulate the maximum allowable concentrations of certain pollutants over specific periods. The relevant AQOs are listed in Table 3.1.
Table 3.1
Notes:
(1)
Measured
at 298 K and 101.325 kPa.
(2)
Not to
be exceeded more than three times per year.
(3)
Not to
be exceeded more than once per year.
(4)
Arithmetic
mean.
(5)
Suspended
particulates in air with a nominal aerodynamic diameter of
(6)
Photochemical
oxidants are determined by measurement of ozone only.
3.2.3
The EIAO-TM stipulates that the
hourly TSP level should not exceed
3.2.4 In accordance with the EIAO-TM, odour level at an air sensitive receiver should meet 5 odour units based on an averaging time of 5 seconds for odour prediction assessment.
3.3
Description of the Environment
3.3.1
The dredging area for proposed cross-harbour
water mains is between Wan Chai and Tsim Sha Tsui, the study area is in
Table 3.2 Annual
Average Concentrations of Pollutants in 2006
Pollutant |
Annual Average Concentration in 2006 (mg m-3) |
Monitoring Stations |
CO |
862 |
Central |
NO2 |
54 |
Central / Western |
RSP |
53 |
Central / Western |
TSP |
78 |
Central / Western |
3.4.1
The study area is within
3.4.2 The identified nearest ASRs to the work site of DP6 are Hong Kong Convention & Exhibition Centre Extension in Wah Chai and Art Centre in Tsim Sha Tsui.
3.5
Identification of
Environmental Impacts
3.5.1 The dredging activities would be commenced in January 2009. One dredger would be used and the duration would be last for 16 days. As dredging is marine based activity, dust nuisance from this construction activity is not anticipated.
3.5.2 Insignificant marine traffic emission impact from the dredger is expected as only one dredger to be operated at the work site. Under normal operation, equipment with proper maintenance is unlikely to cause significant dark smoke emissions and gaseous emissions are expected to be minor. Thus, the AQOs are not expected to be exceeded. Notwithstanding, plant should be regularly maintained to minimise emissions.
3.5.3 In accordance with the construction programme, there is no other construction activity to be operated concurrently within 500m study area of DP6, no cumulative air quality impact is anticipated.
3.5.4
The dredging area is not a
stagnant or low water flow area in
3.6
Mitigation of Adverse Environmental Impacts
3.6.1 No adverse air quality impacts at the ASRs are expected during dredging. However, the operated dredger should be regularly maintained to minimise emissions.
3.7
Evaluation of Residual Impacts
3.7.1 No adverse residual air quality impact arsing from the DP6 would be expected.
3.8
Environmental
Monitoring and Audit
3.8.1 No adverse air quality impact would be expected arsing from the DP6, air quality monitoring and audit is considered unnecessary.
3.9.1 Negligible dust impact and emission impact from the DP6 would be expected at the nearest ASRs. Air quality monitoring and audit is therefore not required.