12                     Environmental Monitoring And Audit

12.1                Introduction

12.1.1          This section further elaborates the requirements of EM&A for the construction and operation of the Project, based on the assessment results of various environmental issues.

12.1.2          The objectives of carrying out EM&A for the Project include the following:

Ÿ                      to provide a database against which any short or long term environmental impacts of the Project can be determined;

Ÿ                      to provide an early indication should any of the environmental control measures or practices fail to achieve the acceptable standards;

Ÿ                      to monitor the performance of the Project and the effectiveness of mitigation measures;

Ÿ                      to verify the environmental impacts predicted in this EIA;

Ÿ                      to determine project compliance with regulatory requirements, standards and government policies;

Ÿ                      to take remedial action if unexpected problems or unacceptable impacts arise; and

Ÿ                      to provide data to enable an environmental audit.

12.1.3          The following sections summarise the recommended EM&A requirements.  Details of EM&A are provided in a stand-alone EM&A Manual.

 

12.2                Air Quality

Construction Phase

12.2.1          With implementation of the proposed dust suppression measures stipulated in the Air Pollution Control (Construction Dust) Regulation, good site practices and comprehensive dust monitoring and audit, the dust impact would be further diminished.

12.2.2          Dust monitoring and auditing is recommended in the EM&A Manual to ensure the efficacy of the control measures.

Operation Phase

12.2.3          There will be no exceedance of AQOs at the sensitive receivers.  No mitigation measures or environmental monitoring are considered necessary during the operation phase of the Project.


12.3                Noise

Construction Phase

12.3.1          Construction noise impacts from the Project would be expected at the NSRs identified in this EIA.  Appropriate mitigation measures such as adoption of quiet PMEs, movable noise barrier and scheduling of PMEs/construction activities are required in order to alleviate the impacts to meet the EIAO-TM criteria.  Noise monitoring during construction phase will be carried out to ensure that such mitigation measures are implemented properly.

Operation Phase

12.3.2          After completion of the Project, traffic noise monitoring should be carried out at the NSRs in the vicinity of the recommended direct mitigation measures. The purpose of this monitoring is to ensure that the proposed mitigation measures are effective to alleviate traffic noise impact. Highways Department will be responsible for the operational phase monitoring. Qualified environmental team should be employed to carry out the proposed monitoring. The parameters, monitoring equipment, locations and procedures are presented in detail in the EM&A Manual.

 

12.4                Water Quality

Construction Phase

12.4.1          The water quality assessment has concluded that the identified water quality impacts could be minimized by implementing the recommended mitigation measures for the construction works, such as control measures on runoff and drainage from the work areas to minimise construction run-off and proper site management and good housekeeping practices.  No unacceptable residual water quality impact would be expected.  Any effluent discharges from the site would be required to comply with the terms and conditions of a discharge licence, issued by EPD, under the WPCO. 

12.4.2           It is recommended that regular site inspections be undertaken to inspect the construction activities and works areas in order to ensure the recommended mitigation measures are properly implemented.   

Operation Phase

12.4.3          No residual impact is anticipated during operation stage of the Project, EM&A requirement is considered not necessary.

 


12.5                Waste Management

12.5.1          Waste management will be the contractor’s responsibility to ensure that all wastes produced during the construction of the Project are handled, stored, reused and disposed of in accordance with the recommended good waste management practices and EPD’s regulations and requirements.  The mitigation measures recommended in Section 6 should form the basis of the site Waste Management Plan to be developed by the Contractor at the construction stage.

12.5.2          It is recommended that the waste arisings generated during the construction activities should be audited periodically to determine if wastes are being managed in accordance with approved procedures and the site Waste Management Plan.  The audits should look at all aspects of waste management including waste generation, storage, reuse, transport and disposal.  An appropriate audit programme would be to undertake a first audit near the commencement of the construction works, and then to audit on a quarterly basis thereafter.  In addition, the routine site inspections should check the implementation of the recommended good site practices and other waste management mitigation measures.

 

12.6                Land Contamination

12.6.1          Based on the findings from the desktop studies and site inspection, no contaminated sites were identified within/in vicinity of the Project boundary. No adverse environmental impacts on land contamination for the widening of Tuen Mun Road at Tsing Tin Interchange are anticipated. As a result, no monitoring programme specific for land contamination would be required.

 

12.7                Ecology

12.7.1          The ecological assessment concluded that only minor impacts would be resulted from the proposed works and these impacts would be further mitigated by proposed measures. Therefore, apart from regular environmental site auditing of the implementation of mitigation measures as recommended in Section 9 of this EIA, no specific ecological monitoring programme would be required under this project.

 

12.8                Hazard to Life

12.8.1          There is no substantial increase of risk to construction workers, nearby population and transient population due to widening of the TMR during construction and operation stages. Mitigation measures to reduce risk induce by the project is considered not required.  However, the number of construction workers should be kept at the same level as the assessment.

12.8.2          In addition, development of an evacuation plan and procedures, conducting induction training for construction workers together with performing periodic drill during construction phase are recommended as a good practice. 


12.9                Landscape and Visual

12.9.1          The EIA has recommended landscape and visual mitigation measures to be implemented during construction and operation phases of the Project.  The EM&A is required to ensure that the proposed mitigation measures are effectively implemented.

12.9.2          Baseline monitoring is required to record baseline conditions of the site, in particular, changes of each landscape resource, landscape character area and the view conditions of each visually sensitive receiver.  Parameters used to describe changes in each of the above should be the same as in Section 10 of EIA.

12.9.3          The baseline monitoring should be conducted as a one-off site survey prior to commencement of any construction works.

12.9.4          During construction phase, all mitigation measures proposed in the EIA should be implemented by the Contractor and would be audited by a landscape auditor of the Environment Team, on a regular basis to ensure compliance with the intended aims of the measures.  Site inspection should be undertaken at least once every two weeks throughout the construction period.

12.9.5          The landscape auditor should also audit the operation phase mitigation measures proposed in the EIA report and as depicted in the Landscape Mitigation Plan to ensure that they are fully implemented within the Project design and construction.

12.9.6          The detail monitoring and audit requirements are presented in detail in the EM&A Manual.

 

12.10            Cultural Heritage

12.10.1      There is no cultural heritage impact arising from the construction and operation of the Project, therefore, monitoring and audit requirement is considered not necessary.