Table 13.1 Summary of Key Environmental Outcomes/Benefits
Issue |
Environmental Outcomes/Benefits |
The Project |
Requirements: ·
Widening of the 240m long dual 2-lane section of · Construction of associated earth retaining structures, slope works, geotechnical works and works on environmental mitigation, landscape, drainage, road lightings, water mains and traffic aids. Benefits: ·
The Project can relieve the traffic congestion
at the Tsing Tin Interchange road section of Potential consequences without the Project: ·
Without the Project,
· As severe traffic congestion at both ends of Tsing Tin Interchange, there would have consequential adverse air quality impacts to the nearby ASRs as the vehicles are in idling condition in traffic congestion. |
Development Alternatives |
The
widening of In
view of environmental aspects, the widening of existing road section would
pose the least environmental impacts to the surrounding environment as it
would involve the least construction area. |
Construction Air Quality Impact |
Impact/Problem · Potential
air quality impacts are dust nuisance. Environmental benefits of environmental
protection measures recommended: · Mitigation
measures: implement the Air Pollution Control (Construction Dust)
Regulation and good site practices. · No
adverse air quality impacts are anticipated. |
Operational Air Quality Impact |
Impact/Problem ·
No adverse traffic emission
impacts are anticipated at the existing and future ASRs. |
Construction Noise Impact |
Impact/Problem · Unmitigated cumulative construction noise levels: 63 dB(A) to 85 dB(A). Environmental benefits of environmental
protection measures recommended & Environmentally sensitive areas
protected: · Recommended mitigation measures: adopting quiet construction plant, movable noise barriers and scheduling of PMEs/construction activities; and implementing good site practices. ·
Under mitigated scenario, the predicted noise levels at all representative NSRs would comply with the daytime construction noise standard as
set out in the EIAO-TM. |
Road Traffic Noise Impact |
Impact/Problem · Unmitigated noise levels: 65 dB(A) to 85 dB(A). Environmental benefits of environmental
protection measures recommended & Environmentally sensitive areas
protected: ·
Recommended mitigation
measures include: (1) about ·
Mitigated noise levels: 64 dB(A)
to 85 dB(A). Noise exceedances at all the representative NSRs are due
to the existing roads. The ‘new’
road noise contri ·
The proposed noise barriers
would alleviate the traffic noise impacts from ‘new’ road on the NSRs
including Tuen Mun Hospital Quarter, · |
Construction Water Quality Impact |
Impact/Problem · General construction activities associated with the construction of the Project could lead to site runoff. Environmental benefits of environmental
protection measures recommended: · All of the recommended mitigation measures are implemented and all construction site / work area discharges comply with the TM-DSS standards. ·
No unacceptable residual water
quality impacts are expected during the construction of the proposed
infrastructure. |
Operational Water Quality Impact |
Impact/Problem · Adverse water quality impacts associated with the operation of the Project are not expected at the water sensitive receivers within the study area. Thus, there will be no residual impact associated with the operation of the Project. |
Waste Management Implications |
Impact/Problem ·
Wastes generated by construction activities: general
refuse from the workforce, chemical waste from plant and equipment
maintenance, and C&D material from excavation works and the demolition of
existing structures. Environmentally friendly
designs recommended: ·
C&D material with
suitable characteristics should be reused on-site as far as practicable
(approx Environmental benefits of environmental protection measures recommended: ·
With the implementation of the recommended mitigation
measures and practices for the handling, transportation and disposal of the
identified waste arisings, no adverse environmental impacts are expected. |
Land Contamination Impact |
· Based on the finding from the desktop studies and site inspection, no contaminated sites were identified within/in vicinity of the Project boundary. ·
Although a petrol filling
station was found approximately · No adverse environmental impacts on land contamination for the Project are anticipated. |
Hazard to Life Impact |
Impact/Problem & Environmentally friendly designs
recommended · No construction hazard was identified that would affect the storage, use or on-site transport of chlorine in the TMWTW. · Individual Risk at the construction site is acceptable. · No significant change in the Societal Risk during construction stage (Year 2009) and Operation Stage (Year 2024) of the project. |
Ecological Impact |
Impact/Problem & Environmentally friendly designs
recommended ·
The proposed construction works would only
be conducted in the developed area. No direct impact on ecological important
habitats, such as woodland habitat, would be resulted from the proposed
works. ·
Approximately 47 roadside trees located
within the proposed works area would be removed. All of the affected species
are widespread and are not protected or threatened in ·
Disturbance impacts to habitats and
associated communities adjacent to the proposed works area would be resulted
due to the construction works. Wildlife within the proposed works area and
the adjacent woodland also adapted to high levels of human disturbance, heavy
traffic flow and traffic noise, thus the disturbance impact is considered
low. ·
Impacts resulting from improper dumping of
construction materials/wastes and deposition of dust on vegetation adjacent
to works areas would be resulted in the construction phase. The potential
impacts can be avoided and minimized to acceptable levels through the
implementation of standard good site practice. ·
Sediment and runoff if uncontrolled, would
carry pollutants into Tuen Mun River Channel. With the implementation of
adequate construction site drainage and provision of sediment removal
facilities, it is anticipated that unacceptable water quality impacts on the
River Channel would not arise. ·
Potential disturbance on Little Egret found
at Tuen Mun egretry and Tuen Mun River Channel as well as water quality
impact on its feeding habitat would be resulted. With the implementation of
effective noise and water quality control mitigation measures, such construction
phase disturbance would be minimised. In addition, in view of the already
highly disturbed nature of the egretry and availability of alternative
similar foraging area along the Tuen Mun River Channel, potential impact to breeding
and feeding activities of Little Egret is considered as low. Environmentally friendly
designs recommended: ·
Noise barrier with transparent panels
implemented in the operation phase would cause potential bird mortality. As
the transparent panels would appear invisible to birds or mirrors the facing
landscape, birds are unable to recognize them as physical barriers. With
bird-friendly design of noise barriers, such as using non-glaring and tinted
materials, putting falcon stickers on the transparent panels. Environmental benefits of environmental protection measures recommended: ·
the bird collision due to the noise barrier
would be minimized. |
Landscape and Visual Impact |
Impact/Problem & Environmentally friendly designs recommended ·
Under the proposed
development, approximately ·
Based on broad brush survey,
approximately 47 trees will be affected by the construction of noise barrier, road
widening and associated slope works.
None of these are LCSD Champion Trees or Registered Old and Valuable
Trees. There are no rare species
or endangered specie · Impact on Landscape Character Areas during construction will be primarily due to the construction activities including associated temporary works for the road widening works and construction of noise barrier. After implementation of mitigation measures, there will be moderate residual impacts on Transportation Corridor LCA and Park Urban LCA. During Operation, all the LCAs will have insubstantial impacts with the implementation of mitigation measures. · With implementation of mitigation measures during construction, there will still be some moderate negative visual impact on the VSRs adjacent or close to the works area. Residual impacts on VSRs further away the works area will become slight to insubstantial. During operation, residual visual impacts on all VSRs are insubstantial after the implementation of proposed mitigation measures. |
Cultural Heritage Impact |
Impact/Problem · Since there are no archaeological resources within the study area, cultural heritage impact due to the construction activities is not expected. |