(a)
Widening
of the 240 metre-long dual 2-lane section of TMR at Tsing Tin Interchange to a
(b)
Construction
of associated earth retaining structures, slope works, geotechnical works, and
works on environmental mitigation, landscape, drainage, road lightings, water
mains and traffic aids.
(a) Option 2 -
Tunnel/Under-pass
It is apparent that this
option will induce less noise and air quality impacts arising from road traffic
during the operation stage.
However, this option is considered not viable due to the following
reasons:
·
Higher impact on land use;
·
Higher impact on trees;
·
Longer construction period resulting
prolonged construction impacts;
·
More C&D materials to be
generated;
·
Higher energy consumption during the
operation of the tunnel/under-pass, e.g. tunnel lighting, ventilation etc.;
·
Additional impacts on noise and air
quality arising from the tunnel ventilation system, e.g. air and noise
emissions from ventilation shafts at road side, portal emissions; and
·
Higher construction cost.
Due to the poor soil
properties in Tuen Mun area and the shallow nature of the road tunnel, only
cut-and-cover method can be engaged for the construction of the road tunnel.
The trees along the existing central divider of
(b) Option 3 - By-pass
The introduction of
additional traffic lanes by means of an elevated by-pass has been
considered. The
environmental impacts arising from this option are considered far more worse,
details of which are elaborated below:
·
Higher impact on land use;
·
Higher impact on trees;
·
Higher visual impacts;
·
Longer construction period resulting
prolonged construction impacts;
·
Higher noise impact as resulted from
the elevated structures;
·
More C&D materials to be
generated; and
·
Higher construction cost.
Due to site constraints
and the presence of elevated structures, additional traffic lanes in the form
of a by-pass can only be fixed as shown in
Appendix 2.1 which is through an existing park. Part of the trees in
the park and along the existing central divider of
Comparison of Visual Impacts
·
Option 1 - Widening of Roads:
The widening of the existing
·
Option 2 - Tunnel/Underpass:
The tunnel/underpass will be constructed using cut-and-cover method and
two tunnel portal structures will be constructed at the two ends of the
tunnels. More trees along the central divider of the concerned road
section than Option 1 will be affected. The visual impact arising from
this option is considered larger than Option 1.
·
Option 3 - Bypass: The bypass
will be in the form of an elevated viaduct routing through
Table
2.1 Unmitigated
Landscape Impacts of Different Alignment Options on Landscape Resources and
Landscape Character Areas
Landscape
Resources 1(LR)/ Landscape
Character Area (LCA) |
Option
1 – Widening of Road |
Option
2 – Tunnel/Underpass |
Option
3 - Bypass |
LR1 – Roadside Planting |
s
34 trees will be affected. |
s
114 trees will be affected |
s
63 trees will be affected. |
LR |
s
13 trees will be affected. |
s
13 trees will be affected. |
s
90 trees will be affected. |
LCA1 –
Transportation Corridor |
Magnitude
of Impacts: Large s
34 trees will be affected. |
Magnitude
of Impacts: Large s
114 trees will be affected |
Magnitude
of Impacts: Large s
63 trees will be affected. |
LCA2-
Park Urban |
Magnitude
of Impacts: Large s
A portion of s
13 trees inside |
Magnitude
of Impacts: Large s
A portion of s
13 trees inside |
Magnitude
of Impacts: Very Large s
A substantial portion of s
90 trees inside |
LCA3-
Tuen Mun Urban |
Magnitude
of Impacts: Large s
Change of an existing car park to a temporary works
area. |
Magnitude
of Impacts: Large s
Change of an existing car park to a temporary works
area. |
Magnitude
of Impacts: Large s
Change of an existing car park to a temporary works
area. |
LCA4- |
Magnitude of
Impacts: Small s
No noticeable off-site water quality impact will be
expected as the work site is about |
Magnitude of
Impacts: Small s
No noticeable off-site water quality impact will be
expected as the works site is about |
Magnitude of
Impacts: Medium s
The water quality of |
Note 1:
Please refer to Figures
(a) Widening and
re-construction of both bounds of
The most distinct
advantage of this construction method is that a shorter construction period can
be achieved thus resulting construction impacts of shorter term. However, there are drawbacks as
follows:
·
Higher impacts on noise and air
quality during construction period;
·
Complicated diversion schemes for
traffic and utilities; and
·
Higher risks to road users;
(b) Widening and
re-construction of
Under this option, the
concerned section of
·
Less noise and air quality impacts
during construction period thus more manageable;
·
Less complicated diversion schemes
for traffic and utilities; and
·
More flexibility for tree
transplanting which is a time consuming process (certain trees should be
transplanted prior to any road widening work).