4                         NOISE

4.1                   Introduction

4.1.1             Potential noise impact arising from the Project would be construction noise and operational traffic noise. This section presents the assessment on noise impact during construction and operation phases of the Project. The representative noise assessment points to be affected by the Project and potential noise impacts are identified and assessed. Appropriate noise mitigation measures are recommended under the study where necessary.

4.2                   Environmental Legislation, Policies, Plans, Standards and Criteria

General

4.2.1             Noise impacts have been assessed in accordance with the criteria and methodology given in the Technical Memoranda (TMs) under the Noise Control Ordinance (NCO), and the Technical Memorandum on Environmental Impact Assessment Process (EIAO-TM).

4.2.2             The NCO and EIAO provide the statutory framework for noise control.  Assessment procedures and standards relevant to this study are set out in four TMs listed below:

l            EIAO-TM

l            TM on Noise from Construction Work other than Percussive Piling (GW-TM)

l            TM on Noise from Percussive Piling (PP-TM)

l            TM on Noise from Construction Work in Designated Areas (DA-TM) 

Construction Noise – General Construction

4.2.3             The NCO provides the statutory framework for noise control of construction work, other than percussive piling, using powered mechanical equipment (PME) between the hours of 1900 and 0700 hours or at any time on Sundays and general holiday (that is, restricted hours).  Noise control on construction activities taking place at other times is subject to the Criteria for Evaluating Noise Impact stated in Table 1B of Annex 5 in the EIAO-TM.  The noise limit is Leq (30 minutes) 75 dB(A) at the façades of dwellings and 70 dB(A) at the façade of schools (65 dB(A) during examinations).  The standards apply to uses which rely on opened windows for ventilation.

4.2.4             Between 1900 and 0700 hours and all day on Sundays and public holidays, activities involving the use of powered mechanical equipment (PME) for the purpose of carrying out construction work is prohibited unless a Construction Noise Permit (CNP) has been obtained.  A CNP may be granted in cases where the noise can be contained within the Acceptable Noise Level (ANL) at the NSRs.  ANLs are assigned depending upon the Area Sensitivity Ratings (ASRs).  The corresponding basic noise levels (BNLs) for evening and nighttime periods are given in Table 4.1.

Table 4.1     Construction Noise Criteria for Activity other than Percussive Piling

Time Period

Basic Noise Level (BNLs)

ASR A

ASR B

ASR C

Evening (1900 to 2300 hours) (1)

60

65

70

Night (2300 to 0700 hours)

45

50

55

Notes:      (1)      Includes Sundays and Public Holidays during daytime and evening

4.2.5             Despite any description or assessment made in this EIA Report on construction noise aspects, there is no guarantee that a Construction Noise Permit (CNP) will be issued for the project construction. The Noise Control Authority will consider a well-justified CNP application, once filed, for construction works within restricted hours as guided by the relevant Technical Memoranda issued under the Noise Control Ordinance. The Noise Control Authority will take into account contemporary conditions/ situations of adjoining land uses and any previous complaints against construction activities at the site before deciding whether to grant a CNP.  Nothing in this EIA Report should bind the Noise Control Authority in making its decision.  If a CNP is to be issued, the Noise Control Authority should include in the permit any condition it thinks fit.  Failure to comply with any such conditions will lead to cancellation of the CNP and prosecution under the NCO.

4.2.6             Percussive piling is prohibited between 1900 and 0700 hours on any weekday not being a general holiday and at any time on Sunday or general holiday.  A CNP is required for carrying out of percussive piling between 0700 and 1900 hours on any day not being a general holiday.  PP-TM sets out the requirements for working and determination of the permitted hours of operations.  ANLs for percussive piling for different type of NSRs are shown in Table 4.2.

Table 4.2     Acceptable Noise Levels for Percussive Piling

NSR Window Type or Means of Ventilation

ANL, dB(A)

(i) NSR (or part of NSR) with no windows or other opening

100

(ii) NSR with central air conditioning system

90

(iii) NSR with windows or other openings but without central air conditioning system

85

Note:   10 dB(A) should be subtracted from the ANLs shown above for NSRs which are hospitals, medical clinics, educational institutes, courts of law or other NSRs which are considered by the Authority to be particularly sensitive to noise.

 

4.2.7             Effective from 1 October 1999, diesel, pneumatic and / or steam hammers are not allowed to be used in Hong Kong.  The permitted hours of operation for carrying out of percussive piling work, subject to the issuance of a CNP, are listed in Table 4.3.


Table 4.3     Permitted Hours of Operation for Percussive Piling

Amount by which Corrected Noise Level (CNL) exceeds Acceptable Noise Level (ANL), CNL-ANL

Permitted hours of operation on any day not being a general holiday

10 dB(A) < CNL-ANL

0800 to 0900 AND 1230 to 1330 AND 1700 to 1800

0 dB(A) < CNL-ANL £ 10 dB(A)

0800 to 0930 AND 1200 to 1400 AND 1630 to 1800

CNL-ANL £ 0 dB(A)

0700 to 1900

 

4.2.8             Under the TM on Noise from Construction Work in Designated Areas, the use of five types of Specified Powered Mechanical Equipment (SPME) and three types of Prescribed Construction Work (PCW) within a designated area during restricted hours would require a valid CNP.  The SPME includes hand-held breaker, bulldozer, concrete lorry mixer, dump truck and hand-held vibratory poker.  The PCW are:

·         Erecting or dismantling of formwork or scaffolding.

·         Loading, unloading or handling of rubble, wooden boards, steel bars, wood or scaffolding material.

·         Hammering.

4.2.9             In general, it should not be presumed that a CNP would be granted for carrying out PCW within a designated area during restricted hours.  The CNP may be granted for the execution of construction works during restricted hours involving the use of PME and/ or SPME if the relevant Acceptable Noise Levels and criteria stipulated in the GW-TM and DA-TM can be met.

 

Operational Noise - Traffic Noise

4.2.10         Annex 5 “Criteria for Evaluating Noise Impact” of the EIAO-TM defines the criteria L10 (1 hour) for road traffic noise at various NSRs which rely on openable window for ventilation:

·        70 dB(A) at the façades of dwellings, hotels, offices.

·        65 dB(A) at the façades of schools, places of public worship, courts of law, place where unaided voice communication is required.

·        55 dB(A) at the façades of hospital.

4.2.11         For traffic noise assessment, the roads within 300 m of the Project boundary have been included in the assessment.  The roads are classified into one of the following categories:

·        ‘Existing’ Roads - that is, roads that are unchanged or subject to minor changes by the Project.

·        ‘New’ Roads - roads that are completely new or major modification to an existing road section that will result in 25% increase in lanes or substantial changes in alignment or characters of the existing road due to the proposed Project.

4.2.12          The ‘New’ roads defined for the assessment are shown in Appendix 4.1. 

4.2.13          The noise contribution from “New” roads should be less than 70 dB(A) at any dwelling (less than 65 dB(A) for educational institutions), so as to satisfy the relevant noise criteria, and there should not be any increase in traffic noise impact.  In the case of an NSR where existing noise levels already exceed the relevant criteria, any increase in noise level contributed by the “New” roads should not be greater than 1 dB(A).

4.2.14          If any façades of NSRs are still exposed to predicted noise levels exceeding the relevant noise criteria after the implementation of all direct mitigation measures, provision of indirect technical remedies in the form of acoustic insulation and air conditioning should be considered under the EIAO-TM and the ExCo Directive “Equitable Redress for Persons Exposed to Increased Noise Resulting from the Use of New Roads”.  The eligibility for indirect technical remedies will be tested against the following three criteria:

·         The predicted overall noise level from the “New” road, together with other traffic noise in the vicinity must be above a specified noise level (for example, 70 dB(A) for domestic premises and 65 dB(A) for educational institutions, all in L10 (1 hour));

·         The predicted overall noise level is at least 1.0 dB(A) more than the prevailing traffic noise level, that is, the total traffic noise level existing before the works to construct the road were commenced; and

·         The contribution to the increase in the predicted overall noise level from the “New” road must be at least 1.0 dB(A).

 

4.3                   Description of the Environment

4.3.1             The existing land uses in the vicinity of the Project site are commercial, GIC, educational, residential and recreational uses. The dominant existing noise source comes from the road traffic on busy TMR and Castle Peak Road.  No major industrial noise source is found within the Project boundary. 

4.4                   Noise Sensitive Receivers

4.4.1             Existing and planned NSRs including domestic premises and educational institutions within 300m from the project boundary were identified in accordance with Section 3 of Annex 13 of the EIAO-TM.  For the purpose of the noise assessment, a number of representative NSRs which were considered to be potentially worst-affected NSRs were selected for the assessment and has been agreed with EPD (The relevant correspondence letter is attached in Appendix 4.2).  Photographs of all the identified existing NSRs are provided in Appendix 4.3.  Tuen Mun Hospital, one of identified existing NSR, is provided with central air conditioners and do not rely on openable window for ventilation, therefore, it has been excluded in the assessment.  The representative NSRs for construction and traffic noise assessments are summarised in Tables 4.4 below and their locations are illustrated in Figure 4.1.

 

Table 4.4     Summary of Representative Noise Assessment Point

NSR

Description

Use

No. of Storey

TMHQ

Block F, Tuen Mun Hospital Quarter

Residential

20

TLLF

The Church of Christ in China Tam Lee Lai Fun Memorial Secondary School

Educational Institution

6

LB1

Lakeshore Building

Residential

20

MYS

SKH Mung Yan Primary School

Educational Institution

7

BG1

Block A, Brilliant Garden

Residential

11

VB

Victory Building

Residential

25

KF

Kam Fat Building

Residential

18

 

 

4.5                   Assessment Methodology

Construction Noise

4.5.1              The Project is scheduled to commence in early 2008 and to be completed in late 2009.  All construction tasks would be carried out during unrestricted hours (0700 to 1900 hours Monday to Saturday excluding general holidays).  Details of construction tasks are as follows:

 

·         Tree felling (in the vicinity of widen road section);

·         At grade road widening, i.e. excavation and slope works, realign the kerb;

·         Road paving and road marking;

·         Construction of noise barrier; and

·         Installation of high mast lighting.

 

4.5.2             In view of limited work site, the above construction activities would not take place concurrently. 

4.5.3             The programme of the Project would have about three months overlapping with the project of “Traffic Improvement to Tuen Mun Road Town Centre Section” which would be commenced in the third quarter of September 2008 and be completed in the second quarter of 2010.  However, separate distance between these two sites would be more than 300m, therefore, cumulative noise impacts are therefore not expected.  There is no any other concurrent project undertaken within 300m of the study area during construction period of the Project.  Noise sources from the areas greater than 300m of a given NSR are excluded from the assessment

4.5.4             In accordance with the EIAO-TM, the methodology outlined in the GW-TM has been used for the assessment of construction noise (excluding percussive piling).  Sound Power Levels (SWLs) of the equipment were taken from Table 3 of this TM.  Schedules of powered mechanical equipment (PME) for different construction tasks of the Project and other concurrent construction activities of other projects during normal daytime working hours are presented in Appendix 4.4.  As the worst case scenario, on-time percentage for all PME of each construction activity is assumed to be 100%.  The Project Proponent has confirmed that the plant inventory is valid for the Project works.

4.5.5             It is assumed that all PME items required for a particular construction activity would be located at the notional or probable source position of the segment where such activity is to be performed.  The assessment is based on the cumulative SWL of PME likely to be used for each location, taking into account the construction period in the vicinity of the receiver location.  To predict the noise level, PME is divided into groups required for each discrete construction task.  The objective is to identify the worst case scenario representing those items of PME that would be in use concurrently at any given time.  The sound pressure level of each construction task is calculated, depending on the number of plant and distance from receivers.  The noise levels at NSRs are then predicted by adding up the SWLs of all concurrent construction tasks.

4.5.6             A positive 3 dB(A) façade correction is added to the predicted noise levels in order to account for the facade effect at each NSR.

Operation Noise

4.5.7             Traffic noise was predicted using the methodology provided in the UK Department of Transport Calculation of Road Traffic Noise (CRTN) 1988.  The assessment was based on projected peak hour flows for the worst year within 15 years after opening of the road. The roads proposed under the Project are scheduled to open in 2009. Therefore, the traffic data for year 2024, which has been endorsed by Transport Department (see Appendix 4.5), was adopted for the assessment.  The projected 2024 peak hour traffic flows are presented in Appendix 4.5.

4.5.8             Traffic speeds for the roads adopted in the noise model are summarised as follows:

Road                            Speed Limit

Tuen Mun Road           70 km per hour

Castle Peak Road         50 km per hour

Other Roads                 50 km per hour

 

4.5.9             The traffic speed for all existing roads has been made reference to the Traffic Aids provided by Transport Department. 

4.5.10         The road network, proposed building layout and all other features that could have noise screening or reflective effects were digitised in the road traffic noise model. The roads were divided into segments, each of which was assigned a road layout number.  A road layout defined the road width, opposing traffic lane separation, road surface type and traffic mix, flow and road design speed.  There is only one lane of six lanes at existing road section of TMR within the study area is provided with low noise surfacing material, as a conservative approach, impervious road surface was assumed for TMR main alignment as well as other roads within the study area in the assessment.  Noise levels were calculated at each receiver point at various elevations.

4.5.11         It is noted that NSR TLLF is located at about 3.9m from the road kerb of TMR.  In accordance with CRTN, if the assessment is less than 4m from the carriageway edge, there may be an uncertainty in the distance attenuation correction.  Therefore, the predicted noise levels at NSR TLLF was based on site noise measurement data and then normalized with 2024 peak traffic flow.    

 

4.6                   Identification of Environmental Impacts

Construction Phase

4.6.1             Potential construction noise impacts may arise from road works, slope works, and construction of noise mitigation measures. 

Operation Phase

4.6.2             Road traffic noise impact would be caused by vehicular traffic from widened TMR section and the existing roads.

 

4.7                   Prediction and Evaluation of Environmental Impacts

Construction Phase

4.7.1             Except NSR MYS, the NSRs as mentioned in Table 4.4 in the vicinity of the Project site are selected for construction noise impact assessment.  The exclusion of NSR MYS in the assessment is due to a large separate distance between the NSR and work site (about 113 m). If the predicted construction noise levels at other representative NSRs which are located closest to the work site (less than 113 m from the work site) would comply with the noise criterion, the predicted noise levels at NSR MYS should also comply with the criterion. During normal daytime working hours, exceedance of the construction noise criteria were predicted at residential NSR LB1 and educational NSR TLLF in the absence of mitigation measures.  The predicted noise levels at representative NSRs are in the range of 63 to 85 dB(A).  Mitigation measures are considered necessary.  A summary of the unmitigated construction noise levels of the representative NSRs during normal daytime working hours within the construction period of the Project is listed in Table 4.5.  Details of construction noise calculations and results are presented in Appendix 4.4.

Table 4.5     Summary of Unmitigated Construction Noise Levels at Representative NSRs During Normal Daytime Working Hours

Representative NSRs

Use

Criteria

dB(A)

Predicted Unmitigated Construction Noise Levels during Normal Daytime Working Hour (dB(A))

TMHQ

Residential

75

63 - 71

TLLF

Educational Institution

70/65#

73 – 85

LB1

Residential

75

74 – 82

BG1

Residential

75

64 – 69

VB

Residential

75

66 – 74

KF

Residential

75

73 – 74

Note: #      For normal daytime working hours, the noise criteria are 70 dB(A) and 65 dB(A) for normal teaching periods and examination periods, respectively.

 

Operation Phase

4.7.2             Traffic noise levels have been predicted at a total of 8 representative noise assessment points including existing residential dwellings and educational institutions. Appendix 4.6 gives the breakdown of the noise contributions from the “New” roads and existing roads at the representative NSRs.

4.7.3             Without the noise mitigation measures in place, the predicted noise levels at the identified NSRs are in the range of 65 dB(A) to 85 dB(A). Results indicated that NSR TMHQ, VB, MYS and LB1 would exceed the traffic noise criteria due to both ‘New’ roads and existing roads; while exceedance predicted at other NSRs would be due to existing roads only.  Noise mitigation measures on ‘New’ roads are required to alleviate the adverse traffic noise impact.

 

4.8                   Mitigation of Adverse Environmental Impacts

Construction Noise

4.8.1             In order to reduce the excessive noise impacts at the affected NSRs during normal daytime working hours, mitigation measures such as adopting quiet powered mechanical equipment, is recommended.  The above mitigation measures have been vetted and confirmed by the Engineer as being practicable in completing the works within scheduled timeframe. The Contractor may be able to obtain particular models of plant that are quieter than the PMEs given in GW-TM. It is considered too restrictive to specify that a Contractor has to use specific items of plant for the construction operations. It is practical to specify the total SWL of all plant to be used on site so that the Contractor is allowed some flexibility to select plant to suit his needs. 

4.8.2             In this assessment, the recommended quiet PME are taken from the BS 5228: Part 1: 1997 and the PME are known to be available in Hong Kong.

4.8.3             The lists of quiet PME adopted in the construction tasks of the Project during normal daytime working hours are presented in Appendix 4.4.

4.8.4             With the use of quiet PMEs, the predicted noise levels at all residential NSR would comply with construction noise criteria.  However, noise exceedance was predicted at educational NSR TTLF for following construction activities.

Road Paving – exceedance by 8 dB(A) in the normal teaching period and 13 dB(A) in the examination period;

Road Marking – exceedance by 4 dB(A) in the normal teaching period and 9 dB(A) in the examination period;

Construction of Noise Barriers – exceedance by 4 dB(A) in the examination period;

4.8.5             In order to further alleviate construction noise impact, it is proposed to adopt movable noise barrier (3m high) for the PMEs during road paving and road marking in the vicinity of NSR TLLF.  It is anticipated that a movable noise barrier located within 5m from mobile plant can provide at least 5 dB(A) noise reduction.  The barrier material shall have a surface mass of not less than 14 kg/m2 on skid footing with 25mm thick internal sound absorptive lining to achieve the maximum screening effect.  Use of barrier has been confirmed by the Engineer as being practical from engineering and programming point of view.

4.8.6             In view of the limited buffer distance between NSR TLLF and the nearest work area (road paving) is around 12m, the predicted noise level would still exceed the noise criteria by 3 dB(A) in normal teaching period and 8 dB(A) in examination period during road paving.  Practical mitigation measures (i.e. use of quiet PMEs and movable noise barriers) have been exhausted, taking into account the engineering and programming point of view.  In order to further alleviate the construction noise impacts, only one PME (asphalt paver or vibratory roller) is allowed to be operated.  The predicted noise level at NSR TLLF would comply with the criterion of 70 dB(A) in normal teaching period.  In the examination period, it is recommended to cease paving activity if the paving work area is less than 30m from the NSR TLLF or only one PME (asphalt paver or vibratory roller) is allowed to be operated if the work area is not less than 22m from NSR TLLF.  

4.8.7             With the implementation of movable noise barrier for PMEs during road marking, the predicted noise levels at NSR TLLF would comply with the criteria of 70 dB(A) in the normal teaching period.  In order to comply with the criterion of 65 dB(A) in the examination period, the road marking activity should be carried out at least 18m from the NSR TLLF.

4.8.8             Movable noise barrier is also proposed for excavator and compressor during construction of noise barrier in the vicinity of NSR TLLF in the examination period.  As noise screening effect from movable noise barrier is not effective for piling, it is proposed to avoid the piling operation for construction of noise barriers or implemented by other quiet construction method during examination period.  Movable noise barrier would be provided for excavator and compressor.  The predicted noise levels at NSR TLFF would comply with the criteria of 65 dB(A).  

4.8.9              A summary for mitigated noise levels during normal daytime working hours at representative NSRs is presented in Table 4.6.

Table 4.6     Summary of Mitigated Construction Noise Levels at Representative NSRs During Normal Daytime Working Hours 

Representative NSRs

Use

Criteria

dB(A)

Predicted Mitigated Construction Noise Levels during Normal Daytime Working Hour (dB(A))

TMHQ

Residential

75

52 – 64 (1)

TLLF

Educational Institution

70/65#

64 – 70 (2) (3) (4)

LB1

Residential

75

63 – 75 (1)

BG1

Residential

75

53 – 62 (1)

VB

Residential

75

54 – 67 (1)

KF

Residential

75

63 – 67 (1)

Note: #      For normal daytime working hours, the noise criteria are 70 dB(A) and 65 dB(A) for normal teaching periods and examination periods, respectively.

(1)     Adoption of quiet PMEs

(2)     Road marking - Adoption of quiet PMEs and movable noise barrier during normal teaching period and examination period.  The work area should be located not less than 18m from NSR TLLF during examination period. 

(3)     Construction of noise barrier - Adoption of quiet PMEs and movable noise barrier during examination period, piling operation for construction of noise barrier would also be ceased during examination period

(4)     Road paving - Adoption of quiet PMEs, movable noise barrier and scheduling of PMEs during normal teaching period, only one PME to be operated and the work area not less than 22m from NSR TLLF or cease operation of PMEs if work area less than 30m from NSR TLLF during examination period.

 

Operation Noise

4.8.10         Direct mitigation measures would be proposed for ‘New’ roads (i.e. within the meaning of Item A.1 of Schedule 2 of EIAO-TM) if there would be adverse environmental impact. If the NSRs are affected by noise from other existing roads, direct mitigation measures are required to reduce the noise from the ‘New’ roads to a level that it

(i)                  is not higher than the noise standard; and

(ii)                has no significant contribution to the overall noise from other existing roads, if the cumulative noise level (i.e. noise from the “New” road together with other existing roads) exceeds the noise standard.

 

4.8.11         The proposed noise mitigation measures as shown in Figure 4.2 are summarised as follows:

·         A section of a 100m long 6m high cantilevered barrier with 3.5m cantilever inclined at 23° on the Kowloon bound of TMR

·         A section of 80m long 6m high cantilevered barrier with 2.5m cantilever inclined at 23° on the Yuen Long bound of TMR

·         Low noise material surfacing on the ‘New’ road section (185m for Kowloon bound and 195m for Yuen Long bound)

4.8.12         Appendix 4.6 presents the breakdown of noise contribution from the “New” roads and existing roads at all representative NSRs with the proposed cantilevered noise barriers and low noise material road surfacing in place.

4.8.13         With the proposed direct mitigation measures in place, the predicted overall noise levels at most of the NSRs would still exceed the relevant noise limits due to the noise contributions from existing roads. However, the ‘New’ road noise contributions to the overall noise levels would be less than 1.0 dB(A) and the ‘New’ road noise levels at these NSRs would all be below the relevant noise limits.  Hence, no further direct mitigation measures are considered effective in mitigating the noise impact. 

 

4.9                   Evaluation of Residual Environmental Impacts

Construction Noise

4.9.1             With the implementation of the above-mentioned mitigation measures, the construction noise levels at all representative residential and educational NSRs are predicted to comply with the noise standards stipulated in the EIAO-TM.

4.9.2             In order to further ameliorate the construction noise impacts, the good site practices listed below should be adopted by all the Contractors.  Although the noise mitigating effects are not easily quantifiable and the benefits may vary with the site conditions and operating conditions, good site practices are easy to implement and do not impact upon the works schedule.

l            Only well-maintained plant should be operated on-site and plant should be serviced regularly during the construction program.

l            Silencers or mufflers on construction equipment should be utilized and should be properly maintained during the construction program.

l            Mobile plant, if any, should be sited as far away from NSRs as possible.

l            Machines and plant (such as trucks) that may be in intermittent use should be shut down between works periods or should be throttled down to a minimum.

l            Plant known to emit noise strongly in one direction should, wherever possible, be orientated so that the noise is directed away from the nearby NSRs.

l            Material stockpiles and other structures should be effectively utilised, wherever practicable, in screening noise from on-site construction activities.

l            Noisy work to be conducted in non-school hours or long holiday such as summer vacation as possible.

Operation Noise

4.9.3             With the proposed direct noise mitigation measures in place, the ‘New’ road noise contributions to the overall noise levels at all representative NSRs would be less than 1.0 dB(A) and the ‘New’ road noise levels would all be below the relevant noise criteria.  No adverse noise impacts arising from the ‘New’ roads are predicted at any of the representative NSRs. Noise exceedances at the representative NSRs, if any, would be due to the existing roads.

4.9.4             The contribution to the increase in predicted overall noise level from the ‘New’ roads is below 1.0 dB(A), therefore none of the representative NSRs is eligible for consideration for indirect technical remedies in the form of acoustic insulation and air conditioning under the EIAO-TM and the ExCo Directive “Equitable Redress for Persons Exposed to Increased Noise Resulting from the Use of New Roads”.

 

4.10               Environmental Monitoring and Audit

Construction Noise

4.10.1         An EM&A programme is recommended to be established according to the predicted occurrence of noisy activities. All the recommended mitigation measures for daytime normal working activities should be incorporated into the EM&A programme for implementation during construction.  Details of the programme are provided in the stand-alone EM&A Manual.

Operation Noise

4.10.1         Road traffic noise levels should be monitored at representative NSRs, which are in the vicinity of the recommended direct noise mitigation measures, during the first year after road opening. Details of the programme are provided in the stand-alone EM&A Manual.

 

4.11               Summary

Construction Noise

4.11.1         This assessment has predicted the construction noise impacts of the Project during normal daytime working hours. With the use of quiet PME, movable barriers and scheduling of PMEs/construction activities, the noise levels at all representative NSRs would comply with the construction noise standard.

Operation Noise

4.11.2         The potential road traffic noise impacts have been assessed based on the worst case traffic flows in 2024. The noise levels at some NSRs are predicted to exceed the EIAO-TM traffic noise criteria due to both ‘New’ road and existing roads. As a result, direct mitigation measures have been proposed to mitigate the noise impacts at NSRs TMHQ, VB, MYS and LB1 where ‘New’ road noise contributions to the overall noise levels would be more than 1.0 dB(A).

4.11.3         With two sections of 6m high cantilevered noise barrier and low noise material surfacing on ‘New’ road in place, the ‘New’ road noise contributions to the overall noise levels at all representative NSRs would be less than 1.0 dB(A) and the ‘New’ road noise levels would all be below the relevant noise criteria, though the overall noise levels at most of the NSRs would still exceed the relevant noise criteria. However, it should be noted that such noise exceedances at the representative NSRs are due to the existing roads.

4.11.4         Monitoring of road traffic noise is recommended to verify the effectiveness of the mitigation scheme during the first year after road opening.