Annex B4-2
Programme for Construction, Operation and Restoration of Landfill Extension
                                                                       
    2012 2013 2014 2015 2016 2017 2018 2019
Activity No. Activity Description   Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
                                                                       
                                                                       
                                                                       
                                                                       
                                                                       
                                                                       
Phase 1 6a Deposition and compaction of waste                                                                  
  6b Placement of intermediate cover                                                                  
  6c Removal of intermediate cover                                                                  
Phase 2 6a Deposition and compaction of waste                                                                  
  6b Placement of intermediate cover                                                                  
  6c Removal of intermediate cover                                                                  
Phase 3 6a Deposition and compaction of waste                                                                  
  6b Placement of intermediate cover                                                                  
  6c Removal of intermediate cover                                                                  
Phase 4 6a Deposition and compaction of waste                                                                  
  6b Placement of intermediate cover                                                                  
  6c Removal of intermediate cover                                                                  
Phase 5 6a Deposition and compaction of waste                                                                  
  6b Placement of intermediate cover                                                                  
  6c Removal of intermediate cover                                                                  
Phase 6 6a Deposition and compaction of waste                                                                  
  6b Placement of intermediate cover                                                                  
  6c Removal of intermediate cover                                                                  
All over construction, operation & restoration 7a Site housekeeping                                                                  
7b Vehicle maintenance                                                                  
Phase 1 8 Placement of daily cover after 2300 hours                                                                  
Phase 2 8 Placement of daily cover after 2300 hours                                                                  
Phase 3 8 Placement of daily cover after 2300 hours                                                                  
Phase 4 8 Placement of daily cover after 2300 hours                                                                  
Phase 5 8 Placement of daily cover after 2300 hours                                                                  
Phase 6 8 Placement of daily cover after 2300 hours