5                                            Noise

5.1                                      Introduction

This Section assesses the potential noise impacts associated with the construction, operation, restoration and aftercare of the Extension.

5.2                                      Relevant Legislation and Guidelines

5.2.1                                Construction, Restoration & Aftercare Noise

The principal legislation relating to the control of construction, restoration and aftercare noise is the Environmental Impact Assessment Ordinance (EIAO) (Cap. 499).  The Technical Memorandum on Environmental Impact Assessment Process (EIAO-TM), issued under the EIAO, provides guidelines and noise criteria for evaluating the noise impacts.

The Noise Control Ordinance (Cap. 400) (NCO) also provides means to assess construction, restoration and aftercare noise impacts.  Various Technical Memoranda (TMs), which stipulate control approaches and criteria, have been issued under the NCO.  The following TMs are applicable to the control of noise impacts from construction activities:

·           Technical Memorandum on Noise from Construction Work other than Percussive Piling (GW-TM); and

·           Technical Memorandum on Noise from Construction Work in Designated Areas (DA-TM).

General Construction Works

Under the EIAO, potential noise impact arising from general construction works during normal working hours (ie 07:00 to 19:00 hrs on any day not being a Sunday or public holiday) at the openable windows of buildings, which rely on opened windows for ventilation, is to be assessed in accordance with the noise criteria specified in the EIAO-TM.  The EIAO-TM noise standards are presented in Table 5.2a.

Table 5.2a      EIAO-TM Day-time Construction Noise Standards (Leq, 30 min dB(A))

Use

Noise Standard (dB(A))

Domestic Premises

75

Educational Institutions (normal periods)

Educational Institutions (during examination periods)

70

65

Notes:

(1)  The above standards apply to uses which reply on opened windows for ventilation.

(2)  The above standards shall be viewed as the maximum permissible noise levels assessed at 1m from the external façade.

When assessing a Construction Noise Permit (CNP) application for the use of Powered Mechanical Equipment (PME) during the restricted hours, the Noise Control Authority will compare the Acceptable Noise Levels (ANLs), as promulgated in GW-TM, and the Corrected Noise Levels (CNLs) (ie after accounting for factors such as barrier effects and reflections) associated with the proposed PME operations.  The ANLs are related to the noise sensitivity of the area in question and different Area Sensitivity Ratings (ASR) have been established to reflect the background characteristics of different areas.  The appropriate ASR for the Noise Sensitive Receiver (NSR) is determined with reference to Table 5.2b.

Table 5.2b      Area Sensitivity Ratings

Types of Area Containing NSR

Degree to which NSR is affected by Influencing Factor (IF)

 

Not Affected

Indirectly Affected

Directly Affected

Rural area, including Country Parks or village type developments

A

B

B

Low density residential area consisting of low-rise or isolated high-rise developments

A

B

C

Urban area

B

C

C

Area other than those above

B

B

C

Notes:

The following definitions apply:

(a)       "Country Park" means an area that is designated as a country park pursuant to section 14 of the Country Parks Ordinance;

(b)       "directly affected" means that the NSR is at such a location that noise generated by the IF is readily noticeable at the NSR and is a dominant feature of the noise climate of the NSR;

(c)       "indirectly affected" means that the NSR is at such a location that noise generated by the IF, whilst noticeable at the NSR, is not a dominant feature of the noise climate of the NSR;

(d)       "not affected" means that the NSR is at such a location that noise generated by the IF is not noticeable at the NSR; and

(e)       "urban area" means an area of high density, diverse development including a mixture of such elements as industrial activities, major trade or commercial activities and residential premises.

The relevant ANLs are shown in Table 5.2c.

Table 5.2c      Acceptable Noise Levels for General Construction Works (ANL, Leq, 5 min dB(A))

Time period

Area Sensitivity Rating (dB(A))

 

A

B

C

All days during the evening (ie 19:00-23:00 hrs) and general holidays (including Sundays) during the day and evening (ie 07:00-23:00 hrs)

60

65

70

All days during the night-time (ie 23:00-07:00 hrs)

45

50

55

The Noise Control Authority will consider a well-justified CNP application, for construction works within restricted hours as guided by the relevant Technical Memorandum issued under the NCO.  The Noise Control Authority will take into account adjoining land uses and any previous complaints against construction activities at the site before making a decision.  Nothing in this EIA Report shall bind the Noise Control Authority in making its decision.  The Noise Control Authority may include any conditions in a CNP that it considers appropriate.  Failure to comply with any such conditions may lead to cancellation of the CNP and prosecution action under the NCO.

5.2.2                                Operational Noise

On-site Operational Noise

The EIAO-TM and Technical Memorandum on Noise From Places Other than Domestic Premises, Public Places or Construction Sites (IND-TM) specifies the applicable ANLs for the operation of the Extension.  The ANLs are dependent on the ASR and the time of the day and are presented in Table 5.2d.

Table 5.2d      ANLs to be used as Fixed Plant Noise Criteria

Time Period

Leq 30min (dB(A))

 

ASR “A”

ASR “B”

ASR “C”

Day-time (ie 07:00-19:00 hrs)

60

65

70

Evening (ie 19:00-23:00 hrs)

60

65

70

Night-time (ie 23:00-07:00 hrs)

50

55

60

Fixed plant noise is controlled under Section 13 of the NCO and the predictions will be undertaken in accordance with the IND-TM.  The noise criteria for planning and design of Designated Projects are set out in the EIAO-TM as follows:

·           the noise level at the facade of the nearest NSR is at least 5 dB(A) lower than the appropriate ANL (as shown in Table 5.2d) as specified in the IND-TM; or,

·           the prevailing background noise level (for quiet areas with a noise level 5 dB(A) below the appropriate ANL). 

 

The noise criteria stipulated in the IND-TM are also dependent on the ASR of the NSR, as shown in Table 5.2d.  For this assessment, the ASR assumed for the NSR and the associated ANL are discussed in Section 5.3.2.

Road Traffic Noise

The traffic noise standards for planning purposes specified in Table 1 under Annex 5 of the EIAO-TM was employed as the noise limits for the road traffic noise impact assessment.  The applicable road traffic noise standards are 70dB(A) L10, 1hr for domestic premises and 65dB(A) L10, 1hr for education institutions and church, respectively.  These noise limits were applied for the peak hour traffic flows and for uses that rely on opened windows for ventilation.

5.3                                      Baseline Environmental Conditions and Noise Sensitive Receivers

5.3.1                                Baseline Environmental Conditions

The Extension Site is located near the southern end of Wan Po Road.  The nearest existing high-rise residential developments are located at more than 2.4km and 3.5km away in the Eastern District of Hong Kong Island and Tseung Kwan O (TKO), respectively.  Background noise levels are typical of a general rural environment and there are limited numbers of vehicles or noisy plant items operating during evening and night-time periods.  The major existing noise sources were identified as the general noise from the existing SENT Landfill, Tseung Kwan O Industrial Estate and the traffic noise in the vicinity.

5.3.2                                Noise Sensitive Receivers

In accordance with the requirements given in Section 3.4.2.2 of the EIA Study Brief, the Study Area for the noise impact assessment covered a distance of 300m from the roads with traffic generated by the Extension.  Only the first layer of the NSRs located along Wan Po Road and Chiu Shun Road were included in the assessment as the NSRs behind were located further away from the road and were screened.  The area considered in the assessment is shown in Figure 5.3a.

Existing NSRs that would potentially affected by the Extension are identified as the Island Resort at Siu Sai Wan which is located at more than 2.4km to the south-west of the Extension Site boundary, and Oscar By the Sea in Tseung Kwan O which is located at more than 3.2km to the north of the Extension Site.  Other existing NSRs, including residential developments and schools, are located at a further distance away to the north.  Planned residential developments and schools in TKO Area 85 and Area 86 are located at more than 1.5km to the north of the Extension Site boundary.  The locations of the identified representative NSRs and photographs showing the existing representative NSRs are presented in Figures 5.3b to 5.3e.  The locations of the identified representative planned NSRs for assessment are presented in Figure 5.3f.   

As the NSRs are located in an isolated high-rise development area and are indirectly affected by Wan Po Road or the Tseung Kwan O Industrial Estate, an ASR of “B” was assigned.  Background noise measurements were conducted to investigate the prevailing noise level in the Study Area.  With the inclusion of façade correction, the measured prevailing noise levels were 60 dB(A) Leq, 30min and 55 dB(A) Leq, 30min during day-time and night-time respectively.  Therefore, the (ANL – 5) criteria of 60 dB(A) Leq, 30min and 50 dB(A) Leq, 30min for day-time and night-time periods, respectively were considered as the stipulated noise limits for the assessment of operational noise impact.  Details of the background noise measurements are provided in Section 5.3.3.

The representative NSRs located along Wan Po Road, and the separation distances between the representative NSRs and the Extension Site are listed in Table 5.3a.  Potential construction noise impact, on-site operational noise and traffic noise impact generated by the operation of the Extension at the representative existing and planned NSRs were assessed according to the matrix in Table 5.3a. 

Table 5.3a      Representative Noise Sensitive Receivers Selected for Assessment

NSR

Location

Use

No. of Floors

Distance to the Extension Site (km) (Approx.)

Selected for Noise Impact Assessment

 

Construction

On-site Operational

Road Traffic

NFP1

Nan Fung Plaza

Residential

39 – 43

4.0

 

 

ü

LCN1

La Cite Noble

Residential

44 – 47

3.9

 

 

ü

YUKMC1

Yuk Ming Court

Residential

38

4.1

 

 

ü

THWV1

Tin Ha Wan Village

Residential

3

4.0

 

 

ü

MTE1

Ming Tak Estate

Residential

38

4.0

 

 

ü

OS1

Oscar By the Sea

Residential

32 - 49

3.2

 

 

ü

IR1

Island Resort

Residential

50 - 51

2.4

ü

ü

 

A86R1(a)

Planned Residential Development in Area 86

Residential

40 – 50

1.5

ü

ü

ü

A86R2(a, b)

Planned Residential Development in Area 86

Residential

40 – 50

1.7

 

 

ü

Notes:

(a)       Under construction

(b)       Only applicable to road traffic noise assessment with Cross Bay Link.

5.3.3                                Prevailing Noise Measurement

To investigate the prevailing noise levels in the Extension Site, noise measurements were made from 23 to 24 August 2006 near the office of Green Valley Landfill Limited at the existing SENT Landfill.  The noise measurements were conducted using a 01dB Sound Level Meter (Type 1), which had been calibrated using a SVAN Sound Level Calibrator Type 4231 with a calibration signal of 94.0 dB(A) at 1kHz.  The measurements were conducted with reference to the calibration and measurement procedures stated in the IND-TM. 

As the background noise in the Extension Site is generally low, especially during night-time, the prevailing noise measurement represents the quietest acoustic environment in the vicinity of the NSRs.  Since the microphone was set in the free field measurement mode, a façade correction of 3dB(A) was applied to the noise measurement results.  The measured prevailing background noise levels including façade correction were in the range of 60 – 75 dB(A) Leq, 30min and 55 – 64 dB(A) Leq, 30min during 13:00 to 20:00 hrs and 23:00 to 07:00 hrs, respectively.  

5.4                                      Potential Sources of Impact

5.4.1                                Construction/Restoration Phase

The major activities associated with the construction phase will involve the use of PME and they are summarised as follows:

·           Foundation and building structure construction for the infrastructure area – transportation of plant and equipment, excavation, installation of formwork and reinforcement, concreting, and construction of monitoring wells;

·           Demolition of existing structures at the infrastructure area – concrete breaking and crushing;

·           Site formation and installation of liner – site formation, installation of liner, provision of leachate and landfill gas collection system, construction of drainage channels and sumps, construction of drainage tunnel and road construction;

·           Construction activities associated with the construction/operation in the Extension - construction of drainage channels and sumps, construction of drainage tunnel and road construction during each phase of the Extension;

·           Capping and Landscaping (progressive restoration) – the use of excavator, bulldozer, dump truck, vibratory roller, loader and mobile crane; and

·           Construction of permanent gas wells – the use of drilling rig, mobile crane and small excavator.

 

The construction noise assessment was undertaken based on the proposed construction works programme (see Figure 3.4a), phasing plans (see Figure 3.6a to 3.6k) and plant inventory presented in Annex B1.  The plant inventory was reviewed by the Design Engineer and was confirmed to be suitable for completing the Assignment within the scheduled timeframe.

The normal working hours of the Contractor will be between 07:00 and 19:00 hrs from Monday to Saturday (except public holidays).  Construction activities during restricted hours are not expected.  Should evening and night works between 19:00 and 07:00 hrs or on public holidays (including Sundays) be required, the Contractor will submit a CNP application which will be assessed by the Noise Control Authority. 

5.4.2                                Operational Phase

Landfilling Operation

The Extension will be operated from Year 2013 to Year 2018 and will involve deposition and compaction of waste, placement of intermediate cover, removal of intermediate cover, capping and landscaping.   The Extension will be operated in six phases starting from the south and filling progressively to the north as shown in Annexes B1 and B4.  The major activities associated with the operational phase will involve the use of PME and they are summarised as follows:

·           Deposition and compaction of waste – transportation and deposition of waste, and compaction; and

·           Placement and removal of daily and intermediate cover – with the use of excavator, bulldozer, dump truck, vibratory roller and loader.

The landfill operates daily from 08:00 to 23:00 hrs.  However, the placement of daily cover will be undertaken for about 25 minutes after 23:00 hrs.  The noise levels due to the use of PME were predicted and compared with the day-time and night-time noise criteria as per the EIAO-TM.

Fixed Plant Operation

The Extension also involves the operation of a new leachate treatment plant (LTP) and a landfill gas treatment plant on-site.  The new LTP and landfill gas treatment plant will be constructed at the new infrastructure area as shown in Figure 5.3g.  The Design Engineer has confirmed that the type and power of the new LTP will be of a scale similar to that of the Bioplant at the existing SENT Landfill and similar building envelopes currently provided for the fixed equipment will also be provided for the LTP and landfill gas treatment plant at the new infrastructure (Annex B4).  Additional number of equipment will not be required for the operation of the Extension.

Reference was made to the GW-TM for the sound power levels (SWLs) of the fixed plant items that were similar in nature to certain PME in the aforementioned GW-TM.  Comparing with the sound data provided by the operator of the existing SENT Landfill for the equipment currently being used (Annex B4), the noise assessment based on the SWLs from the GW-TM would have represented the worst scenario as the sound data for the equipment currently being used is far lower than that from the GW-TM.  Similarly, reference was made to the EIA Report for North East New Territories (NENT) Landfill Extension ([1]).

A survey was undertaken on 23 August 2006 to identify the major noise sources of the Bioplant and landfill gas treatment plant.  The new LTP and landfill gas treatment plant will operate on a 24-hour basis. 

Road Traffic Noise

The Extension peak operating hour (ie the hour with the maximum number of trucks associated with the operation of the Extension) is expected to be 14:00 to 15:00 hrs (SENT Peak) and 17:15 to 18:15 hrs (PM Peak) based on the traffic survey conducted for the operation of the existing SENT Landfill.  There will not be any potential traffic noise impact during the night-time period as the landfill will be closed after 23:00 hrs. 

According to the Civil Engineering and Development Department (CEDD), the Cross Bay Link (CBL) connecting Tiu Keng Leng and Wan O Road is currently scheduled for completion in Year 2016, ie before the anticipated date of completion and closure of the Extension.

To enable identification of the traffic noise contribution from the operation of the Extension and the prevailing situation, traffic noise impact assessment was undertaken for the scenarios shown in Table 5.4b.

Table 5.4b     Scenarios of Traffic Noise Impact Assessment

Peak Hour Scenario

Traffic Noise Impact Assessment Scenario

2006 AM peak hour

With Existing SENT Landfill

Without Existing SENT Landfill

2006 PM peak hour

With Existing SENT Landfill

Without Existing SENT Landfill

2006 SENT peak hour

With Existing SENT Landfill

Without Existing SENT Landfill

Without Cross Bay Link

 

 

2018 AM peak hour

With the Extension

Without the Extension

2018 PM peak hour

With the Extension

Without the Extension

2018 SENT peak hour

With the Extension

Without the Extension

With Cross Bay Link

 

 

2018 AM peak hour

With the Extension

Without the Extension

2018 PM peak hour

With the Extension

Without the Extension

2018 SENT peak hour

With the Extension

Without the Extension

Traffic forecasts for each of the scenarios shown in Table 5.4b were prepared by the Traffic Consultant for the worst case representative assessments (Annex B2).  The maximum estimated traffic flows in/out of the existing SENT Landfill during AM, PM and SENT peak hours for the “with existing SENT Landfill” scenarios for Year 2006 were 105/105, 110/110 and 110/110 vehicles, respectively([2]).  The maximum hourly traffic forecast for the “with the Extension” scenarios in/out of the Extension during AM, PM and SENT peak hours for Year 2018 was 136/136, 143/143 and 143/143 vehicles (1), respectively.  The traffic flows in/out of the Landfill Extension generated by the scenarios with and without CBL would be the same. 

The traffic forecast employed for this assessment has been submitted to the Transport Department (TD) and it was confirmed that TD had no comment on the data set.

5.4.3                                Aftercare Phase

From the Year 2018 when the Extension is full, it will be restored.  The Contractor will be responsible for the aftercare of the restored Extension for a period of 30 years.  The aftercare of the restored Extension will involve limited construction works and is expected to have insignificant noise impact compared with the construction and operation/restoration of the Extension.  The LTP and landfill gas treatment plant will continue to operate during the aftercare period. 

The restored Extension (and together with the restored SENT Landfill) may be developed into various beneficial uses (eg as open space, education/ecological park, hiking track, or passive recreational uses (which are referred to as the afteruses) subject to future planning.  It should be noted that the afteruse of the restored Extension did not form part of the Extension contract.  The potential environmental impacts associated with the development and operation of the afteruse(s) will be subject to a separate EIA Study, where appropriate. 

5.5                                      Assessment Methodology

5.5.1                                Construction/Restoration Phase

The construction noise impact assessment was undertaken in accordance with the procedures outlined in the GW-TM, which is issued under the NCO and the EIAO-TM.  The assessment methodology is summarised as follows:

·           Locate representative NSRs that may be affected by the Extension;

·           Determine the plant teams for corresponding activities, based on the agreed plant inventory;

·           Assign sound power levels (SWLs) to the PME proposed based on the GW-TM, British Standard BS 5228([3]) and list of SWLs of other commonly used PME([4]);

·           Calculate the correction factors based on the distance between the NSRs and the notional noise source position of the work sites;

·           Apply corrections in the calculations, such as potential screening effects and acoustic reflection, if any; and

·           Predict the construction noise levels at NSRs in the absence of any mitigation measures.

The total SWL associated with each construction activity was established based on an assumed plant inventory.  The notional source position was established in accordance with the procedures stated in the GW-TM.  The potential noise impacts at NSRs were subsequently evaluated by comparing the predicted noise levels with the EIAO-TM day-time construction noise limits (Leq, 30min dB(A)), as outlined in Section 5.2.1.

5.5.2                                Operational Phase

The potential sources of noise impacts that may arise from the operation of the Extension include the use of PME for waste placement, operation of the LTP and landfill gas treatment plant and the noise impact due to the traffic generated by the Extension.  The assessment methodologies employed for the on-site operational noise impact assessment are summarised below.

On-site Operational Noise

Noise impact assessment due to the on-site operation of the Extension was undertaken based on standard acoustic principles as per the requirements of the EIAO-TM.  The assessment took into account typical SWLs for the plant items, including the EIA Report for North East New Territories (NENT) Landfill Extension ([5]), distance attenuation, topography attenuation and façade reflection.  Based on the site survey conducted on 23 August 2006, it was indicated that except two small compressors placed outdoors, all noisy equipment was fully enclosed within the concrete building structures of two blower rooms and a landfill gas power plant room.  Noise was emitted to the external environment through lourves or openings for exhaust fans only.  The Design Engineer has confirmed that the type and power of the new LTP will be of a scale similar to that of the existing SENT Landfill and similar building envelopes currently provided for the fixed equipment will also be provided for the LTP and landfill gas treatment plant at the new infrastructure area.

The noise impact due to the waste filling and the operation of the LTP and the landfill gas treatment plant was assessed and compared with the noise criteria as outlined in Section 5.2.2. 

Road Traffic Noise

The noise impact assessment due the truck movements at Wan Po Road and Chiu Shun Road during the peak hours, was based on the procedures given in The Calculation of Road Traffic Noise (CRTN) prepared by the UK Department of Transport.  The assessment has been undertaken for the scenarios of with and without the existing SENT Landfill during AM, PM and SENT peak hours at the prevailing Year 2006 and with and without the Extension during AM, PM and SENT peak hours at the worst assessment Year 2018 (for both scenarios with and without Cross Bay Link).  The traffic forecast provided by the Traffic Consultant is given in Annex B2.

In accordance with the Environmental Permit (EP-073/2000/D) issued by the EPD based on the Tseung Kwan O Development Contract F - Grade Separated Interchange T1/P1/P2, Environmental Impact Assessment (EIA) Study (Register No. AEIAR – 017/1999), an absorptive 5.5m inverted L-shaped barrier of about 175m length along the central divider and an absorptive 5.5m inverted L-shaped barrier of about 450m length alongside the southbound verge of Wan Po Road (referred as Road P1 in the above EP) near On Ning Garden and Nan Fung Plaza have been constructed.  The noise barriers were taken into account in the traffic noise impact assessment.

Other existing noise mitigation measures, including a cantilevered noise barrier near the junction of Wan Po Road and Chiu Shun Road, and two sections of concrete noise barriers in front of Tin Ha Wan Village facing Chiu Shun Road, were also taken into account in the traffic noise impact assessment.

With reference to the EIA Report for Further Development of Tseung Kwan O – Feasibility Study ([6]), a 120 m long cantilevered barrier (5.5 m high vertical barrier with 3 m cantilever) located at the kerb of the eastbound carriageway, three sections of 100 m, 200 m and 168m long cantilevered barriers (5.5 m high vertical barriers with 5m, 4.5m and 5m cantilevers) located at the central divider, have been proposed for CBL to protect the NSRs at Area 86.  The above-mentioned noise barriers have been included in the traffic noise impact assessment for the scenarios with CBL.

Information on low noise surfacing for the roads within the Study Area has been reviewed.  Low noise surfacing has been included in the traffic noise impact assessment for the roads, including sections of Wan Po Road between Po Shun Road and Chiu Shun Road, Chiu Shun Road and Pak Shing Kok, and between Road D10 and Wan O Road, and Chiu Shun Road between Ngan O Road and Po Ning Road.

The predicted noise levels due to the traffic generated on Wan Po Road and Chiu Shun Road were evaluated by comparing with the EIAO-TM traffic noise limits (L10, 1hr dB(A)), as outlined in Section 5.2.2.

5.6                                      Evaluation of Impacts

5.6.1                                Construction/Restoration Phase

As the representative NSRs are located at more than 1.6km away from the Notional Source Position, the predicted noise levels at the representative NSRs would comply with the stipulated construction noise criteria.  A summary of the predicted construction noise levels is presented in Table 5.6a.  Details of the noise calculations are presented in Annex B3. 

Table 5.6a      Predicted Construction Noise Levels at Representative NSRs

NSR

Description

Approx. Horizontal Distance to Notional Source Position(a) (km)

Predicted Construction Noise Levels(b), Leq, 30 min dB(A)

A86R1

Planned Residential Development in Area 86

1.6

41 - 59

IR1

Island Resort

2.6

37 - 55

Notes:

(a)    According to the GW-TM, notional source position refers to the position mid-way between the approximate geographical centre of the construction site and its boundary nearest to the NSR.

(b)    All predicted noise levels were corrected with 3dB(A) for façade reflection.

(c)    Assessment criterion for construction noise impact is 75 dB(A) for domestic premises.

The predicted construction noise levels at the representative NSRs are well below the noise criteria, the NSRs will not be adversely affected by the construction of the Extension.

5.6.2                                Operational Phase

On-site Operational Noise

The noise levels due to the operation of the landfilling works, new LTP and the landfill gas treatment plant at the representative NSRs were predicted and are summarised in Table 5.6b.  The predicted noise levels are well within both the stipulated day-time and night-time (ANL-5) noise criteria.  Details of the noise calculations are presented in Annex B5.

Table 5.6b      Predicted Operational Noise Levels at Representative NSRs

NSR

Description

Predicted Facade Noise Level(a), Leq, 30 min dB(A)

Day-time        (07:00 – 23:00hrs)

Night-time     (23:00 – 07:00hrs)

A86R1

Planned Residential Development in Area 86

41 – 53

33 - 47

IR1

Island Resort

44 - 50

43 - 46

Notes:

(a)    All predicted noise levels were corrected with 3dB(A) for façade reflection..

(b)       According to EIAO-TM, day-time and night-time (ANL-5) noise criteria are 60 dB(A) and 50 dB(A), respectively. 

As NSR A86R1 will be screened from the LTP and landfill gas treatment plant by the buildings in Tseung Kwan O Industrial Estate and the existing topography near the SENT Landfill, a 10dB(A) attenuation was included in the assessment. 

The noise assessment for landfilling and fixed plant operation did not account for the atmospheric absorption and the realistic utilisation rates of the PME (ie not operating for 100% of the time).  Screening by building envelopes and attenuation by acoustic treatment for the fixed plant items were not included in the assessment.  The Design Engineer has confirmed that building envelopes and acoustic treatment similar to the existing SENT Landfill will be provided for the new equipment.  Therefore, the noise levels at the NSRs in real situation will be less than the predicted noise levels presented in Table 5.6b.

Road Traffic Noise

The predicted façade noise levels at the representative NSRs for the Years 2006 and 2018 (with and without CBL in operation) are presented in Annex B6.  The noise levels are predicted for the purpose of assessing the road traffic noise impact due to the Extension, and therefore, the predicted noise levels are for indicative uses only.  Detailed road traffic noise impact assessments should be referred to corresponding EIA Reports or Planning Submissions for individual developments. Results indicate that the predicted façade noise levels complied the stipulated noise limit of 70dB(A) for domestic premises at all NSR locations, except A86R1.  This exceedance would mainly be due to the background traffic at Wan Po Road, as indicated by the predictions for the scenario of “without the Extension” for Year 2018.  It was noted that A86R1 is a planned NSR.  Planned noise mitigation measures at the NSR, if any, eg fins, window insulation, etc, were not included in this assessment.  The noise levels predicted for A86R1 are indicative only for the purpose of estimating the noise contributions due to the Extension.

The noise contributions due to the traffic generated by the Extension were predicted to be less than 0.4dB(A).  In view of the fact that the noise contributions due to the Extension are less than 1.0dB(A) for Year 2018 with and without CBL in operation, the traffic noise impact is considered insignificant.  Detailed results of the road traffic noise impact assessment are given in Annex B6.  The computer road plots and input files of the model are provided in Annexes B7 and B8, respectively.

5.7                                      Mitigation Measures

5.7.1                                Construction /Restoration Phase

While adverse noise impact is not expected during the construction/restoration phase of the Extension, good site practices should be implemented by the Contractor to minimise the construction noise impact.  The site practices listed below should be adopted during the construction phase:

·            Only well-maintained plant should be operated on-site and plant should be serviced regularly during the construction program;

·            Silencers or mufflers on construction equipment should be utilized and should be properly maintained during the construction program;

·            Mobile plant, if any, should be sited as far from NSRs as possible;

·            Machines and plant (such as trucks) that may be in intermittent use should be shut down between work periods or should be throttled down to a minimum;

·            Plant known to emit noise strongly in one direction should, wherever possible, be orientated so that the noise is directed away from the nearby NSRs; and

·            Material stockpiles and other structures should be effectively utilised, wherever practicable, in screening noise from on-site construction activities.

5.7.2                                Operational Phase

While no adverse noise impact is expected during the operational phase of the Extension, it is still recommended that the following measures be implemented as far as practicable:

·            Choose quieter PME; 

·            Include noise levels specification when ordering new plant items;

·            Locate fixed plant items or noise emission points away from the NSRs as far as practicable;

·            Locate noisy machines in completely enclosed plant rooms or buildings; and

·            Develop and implement a regularly scheduled plant maintenance programme so that plant items are properly operated and serviced.  The programme should be implemented by properly trained personnel.

5.8                                      Environmental Monitoring and Audit

Notwithstanding the prediction that the NSRs will not be subject to adverse noise impact during the construction and operational phases, noise monitoring is recommended to be carried out during the construction, operational and restoration stages of the Extension to ensure noise compliance.  In addition, site audits are recommended to be undertaken regularly during the construction, operation/restoration and aftercare phases to ensure that appropriate environmental protection and pollution control mitigation measures are properly implemented.  Details of the EM&A requirements are provided in Section 11 and the EM&A Manual.

5.9                                      Conclusions

No adverse noise impacts are anticipated at the representative NSRs during the construction, operational, restoration and aftercare phases due to the Extension because of the large horizontal separation.  To further minimise the noise impacts, good site practices and noise reduction measures are recommended during the construction and operational/restoration phases of the Extension.


 



([1])      EIA Report for North East New Territories (NENT) Landfill Extension (Register No.: AEIAR-111/2007).

([2])   Traffic flow estimated based on the number of vehicles required during peak hour for the quantity of waste estimated in the Final Technical Note 1 - Waste Arisings Forecast, August 2006.

([3])     British Standard “Noise and Vibration Control on Construction and Open Sites – Part I”, BS 5228: Part I

([4])     “Sound power levels of other commonly used PME” prepared by the Noise Control Authority (http://www.epd.gov.hk/epd/english/application_for_licences/guidance/files/OtherSWLe.pdf )

([5])     EIA Report for North East New Territories (NENT) Landfill Extension (Register No.: AEIAR-111/2007)

([6])      EIA Report for Further Development of Tseung Kwan O – Feasibility Study (Register No.: AEIAR-092/2005).