8                                            Landfill Gas Hazards

8.1                                      Background to the Study

The Extension will be located adjacent to the SENT Landfill with a portion piggybacking onto the south slope of the SENT Landfill.  Figure 3.1a shows the location of the SENT Landfill and the Extension.  The Extension will be a new source of landfill gas generation. 

There are potential risks associated with developments close to a landfill site due to sub-surface migration of landfill gas.  This Section describes the methodology and presents the findings of a qualitative landfill gas hazard assessment of the Extension.

8.2                                      Procedures and Guidelines

Under Annex 7 of the EIAO-TM, an evaluation of the potential risk posed by landfill gas is required for any development which is proposed within 250m of the edge of waste, known as Landfill Consultation Zone.  As the Extension Site falls within the SENT Landfill Consultation Zone (see Figure 8.2a), a Qualitative Landfill Gas Hazards Assessment (QLFGHA) is required to assess the potential risk due to landfill gas migration from the SENT Landfill to the Extension. 

 

A Practice Note for Professional Person (ProPECC PN 3/96) ([1]) and Guidance Note([2]) for the assessment of the hazards which landfill gas may present to developments close to landfills have been issued by the EPD.  These documents provide an assessment framework to be followed when evaluating the risks related to developments described under Section 6.5, Chapter 9 of the Hong Kong Planning Standards and Guidelines.  The ProPECC PN 3/96 and Guidance Note apply to all developments proposed within 250m of the edge of the waste boundary, known as the Landfill Consultation Zone.

 

As the Extension is located adjacent to the existing development in the TKOIE and future industrial development in TKO Area 137, a QLFGHA will be required for developments within 250m of the Extension (see Figure 8.2a).

8.3                                      Scope of this Study

The following tasks have been undertaken as part of this study:

·            review of background information (including landfill gas monitoring data) and studies related to the SENT Landfill and the Extension;

·            identification of the nature and extent of the sources, including the likely concentrations and/or amounts of landfill gas emissions which might have the potential for impacts on the Extension and impacts from the Extension to the potential receivers;

·            identification of possible pathways through the ground, underground cavities, utilities or groundwater, and the nature of these pathways through which the landfill gas must traverse if they were to reach the Extension and the new consultation zone;

·            identification of the potential receivers associated with the Extension which are sensitive to the impacts of landfill gas emissions;

·            qualitative assessment on the degree of risk which the landfill gas emissions may impose on the receivers for each of the source-pathway-receiver combinations; and

·            design of suitable level of precautionary measures and contingency plan for the Extension and the potential receivers, if needed.

 

8.4                                      Landfill Gas Assessment Criteria and Methodology

In accordance with the Guidance Note on Landfill Gas Hazard Assessment, the risk due to landfill gas may be evaluated based upon the following three criteria:

 

·       Source - the rate and concentration of gas generation by the landfill;

 

·       Pathway - the nature of and length of potential pathways through which landfill gas can migrate and leachate flow, such as geological strata, utility services; and

 

·       Target - the level of vulnerability of various elements of the development to landfill gas.

 

Each of these criteria is further described in the sub-sections below.

 

8.4.1                                Source

The classification of the Source (ie the landfill) is determined as follows:

 

Major                 Recently filled landfill site at which there is little or no control to prevent migration of gas or at which the efficacy of the gas control measures has not been assessed; or

 

Any landfill site at which monitoring has demonstrated that there is significant migration of gas beyond the site boundary.

 

Medium              Landfill site at which some form of gas control has been installed (eg lined site or one where vents or barriers have been retrospectively installed) but where there are only limited monitoring data to demonstrate its efficacy to prevent migration of gas; or

 

Landfill site where comprehensive monitoring has demonstrated that there is no migration of gas beyond the landfill boundary but where the control of gas relies solely on an active gas extraction system or any other single control system which is vulnerable to failure.

 

Minor                  Landfill sites at which gas controls have been installed and proven to be effective by comprehensive monitoring which has demonstrated that there is no migration of gas beyond the landfill boundary (or any specific control measures) and at which control of gas does not rely solely on an active gas extraction system or any other single control measure which is vulnerable to failure; or

 

Old landfill sites where the maximum concentration of methane within the waste, as measured at several locations across the landfill and on at least four occasions over a period of at least 6 months, is less than 5% (v/v).

 

8.4.2                                Pathway

Generally, three types of pathway are considered for the transmission of landfill gas.  They are:

 

·       Man-made pathways, eg utility connections, stormwater channels, etc,

 

·       Natural pathways such as rock jointing planes, fissures and other naturally occurring phenomena which may promote or give rise to the transmission of gas over distances; and

 

·       A combination of the previous two categories.  An example of the latter may be, for instance, where a specific geological feature promotes gas transmission but which stops short of directly linking the landfill and target.  A man made connection, however may also co-exist near the edge of the geological feature, which in combination with the former, may act to link the two sites.  In this instance, careful assessment of the likelihood of the mechanism acting to link the two pathways needs to be undertaken before assigning an appropriate pathway classification.

 

The broad classification of a Pathway is as follows:

 

Very short/direct

Path length of less than 50m for unsaturated permeable strata and fissured rock or less than 100m for man-made conduits

 

Moderately short/direct

Path length of 50 to 100m for unsaturated permeable soil or fissured rock or 100 to 250 m for man-made conduits

 

Long/indirect

Path length of 100 to 250m for unsaturated permeable soils and fissured rock

 

In classifying the pathway, however, adjustment to the above general guidelines will often be required to take account of other factors which will affect the extent of gas migration including the following:

 

·       a broad assessment of the specific permeability of the soil;

 

·       spacing, tightness and direction of the fissures/joints;

 

·       topography;

 

·       depth and thickness of the medium through which the gas may migrate (which may be affected by groundwater level);

 

·       the nature of the strata over the potential pathway;

 

·       the number of different media involved; and

 

·       depth to groundwater table and groundwater flow patterns.

 

8.4.3                                Target

Different levels of vulnerability or sensitivity of potential targets for landfill gas have been classified as follows:

 

High Sensitivity

·       Buildings and structures with ground level or below ground rooms/voids or into which services enter directly from the ground and to which members of the general public have unrestricted access or which contain sources of ignition.

·       This would include any developments where there is a possibility of additional structures being erected directly on the ground on an ad hoc basis and thereby without due regard to the potential risks.

 

Medium Sensitivity

·       Other buildings, structures or service voids where there is access only by authorised, well trained personnel, such as the staff of utility companies, who have been briefed on the potential hazards relating to landfill gas and the specific safety procedures to be followed.

·       Deep excavations.

 

Low Sensitivity

·       Buildings/structures which are less prone to gas ingress by virtue of their design (such as those with a raised floor slab).

·       Shallow excavations.

·       Developments which involve essentially outdoor activities but where evolution of gas could pose potential problems.

 

The above examples of different categories within each criterion are to be used as a general guide only and specific aspects of a development may render it more or less sensitive than indicated.  Account needs to be taken of any particular circumstances when assigning a target to one of the three indicated categories.

 

8.4.4                                Assessment of Risk Criteria

Following the determination of the categories for the source, pathway and target in which the landfill, pathway and development fall, a qualitative assessment of the overall risk may be made by reference to Table 8.4a which is extracted from the EPD’s Guidance Note on Landfill Gas Hazard Assessment.  The potential implications associated with the various qualitative risk categories are summarised in Table 8.4b.  It should be noted that the different levels of risk determine the likely extent of the protection measures required to ensure the safety of a development, but with the possible exception of the very high risk category, development is not precluded for any of the assessed levels of risk.

 

Table 8.4a      Classification of Risk Category

 

Source

Pathway

Target Sensitivity

Risk Category

Major

Very short/direct

High

Very high

 

 

Medium

High

 

 

Low

 

Medium

 

Moderately Short/direct

High

High

 

 

Medium

Medium

 

 

Low

 

Low

 

Long/indirect

High

High

 

 

Medium

Medium

 

 

Low

 

Low

Medium

Very short/direct

High

High

 

 

Medium

Medium

 

 

Low

 

Low

 

Moderately Short/direct

High

High

 

 

Medium

Medium

 

 

Low

 

Low

 

Long/indirect

High

Medium

 

 

Medium

Low

 

 

Low

 

Very low

Minor

Very short/direct

High

High

 

 

Medium

Medium

 

 

Low

 

Low

 

Moderately Short/direct

High

Medium

 

 

Medium

Low

 

 

Low

 

Very low

 

Long/indirect

High

Medium

 

 

Medium

Low

 

 

Low

Very low

 

Table 8.4b      Summary of General Categorisations of Risk

 

Level of Risk

Implication

Very high

At the very least, extensive engineering measures and alarm systems are likely to be required.  An emergency actions plan should also be developed so that appropriate actions may be immediately taken in the event of high gas concentrations being detected within the development.

 

High

Significant engineering measures will be required to protect the planned development.

 

Medium

Engineering measures required to protect the development.

 

Low

Some precautionary measures will be required to ensure that the planned development is safe.

 

Very low

No protection or precautionary measures are required.

8.5                                     Assessment of Potential Risk

8.5.1                                The Source

SENT Landfill - History

SENT landfill is located on the western edge of Clear Water Bay Peninsula in the south-eastern corner of the New Territories.  The site covers an area of about 100 ha, half of which has been reclaimed from Shek Biu Wan (Junk Bay).   To the north and east of the site lies Clear Water Bay Country Park; to the west lies land reclaimed as industrial estate and to the south a reclamation (TKO Area 137) intended for industrial uses. 

The landfill is one of the three strategic landfills in operation in the SAR and was designed to receive approximately 43 Mm3 of waste over a period initially projected as 15 to 17 years.    The landfill commenced operation in 1994 and accepts domestic, commercial & industrial (C&I), construction, and clinical wastes, sewage sludge and stablised incineration residues.  However, the landfill is filling faster than originally projected and the latest forecast shows that the landfill will be full by around 2012.

In the landfill gas generation forecast undertaken as part of this Study, it has been estimated that the landfill will typically generate between 100 and 140 Mm3 of gas per year throughout its operational life.  Gas generation was predicted to peak at about 150 Mm3 per year in 2014, approximately 2 years after the landfill is closed.

 

SENT Landfill - Landfill Gas Control

The landfill has been designed to incorporate extensive measures to contain, collect, and treat/utilise landfill gas.  Such measures include the state-of-the-art technologies (including a composite liner systems, active landfill gas extraction and landfill gas treatment and utilisation) in accordance with international best practices for landfill operations.  The landfill gas extraction system contains two skids, each with spare parts.  While only one skid is in operation at one time, the other skid serves as an emergency backup.  The landfill contractor is undertaking routine maintenance and checking of the landfill gas extraction system to ensure it is operating satisfactorily.  As the site is lined and landfill gas is collected and treated, it effectively controls sub-surface off-site migration of landfill gas.  Typical details of the composite liner system (including an impermeable liner) installed at the SENT Landfill are presented in Figure 8.5a.

 

A comprehensive environmental monitoring programme has been implemented to monitor landfill gas generated within the landfill and at the perimeter boreholes around the landfill.  Under the existing contract, the landfill contractor will be required to continue the control and monitoring of landfill gas following closure of the landfill for a period of 30 years.  Recent monitoring results from the boreholes located along the southern boundary of SENT Landfill have been reviewed.  Figure 8.5b shows the locations of these boreholes and the monitoring results are summarised in Table 8.5a (see Annex C for details).  The monitoring results indicate that there is no sub-surface off-site migration of methane at the southern part of the landfill.  Elevated carbon dioxide concentrations (over 15% v/v) were recorded in GP-4 (deep), GP-9, GP-10, GP-11, P-1, P-2, P-3, P-4 and P-5. 

Table 8.5a      Landfill Gas Monitoring Results at SENT Landfill (Jan 2006 – Jul 2007)

Location

Methane (% gas)

Carbon Dioxide (% gas)

 

Range

Average

Range

Average

GP-1

0.0 – 0.0

0.0

0.0 – 3.1

0.9

GP-2 (deep)

0.0 – 0.0

0.0

0.0 – 2.4

1.0

GP-2 (shallow)

0.0 – 0.1

0.0

0.0 – 3.5

2.2

GP-3 (deep)

0.0 – 0.0

0.0

0.0 – 0.3

0.0

GP-3 (shallow)

0.0 – 0.0

0.0

0.0 – 3.3

0.2

GP-4 (deep)

0.0 – 0.0

0.0

0.0 – 12.6

1.8

GP-4 (shallow)

0.0 – 0.1

0.0

0.0 – 5.2

1.6

GP-5 (deep)

0.0 – 0.0

0.0

0.0 – 0.1

0.0

GP-5 (shallow)

0.0 – 0.1

0.0

0.0 – 1.9

0.5

GP-6

0.0 – 0.0

0.0

0.0 – 2.6

1.1

GP-7

0.0 – 0.1

0.0

0.0 – 0.9

0.2

GP-8

0.0 – 0.0

0.0

0.0 – 5.2

1.2

GP-9

0.0 – 0.0

0.0

0.0 – 12.3

4.5

GP-10

0.0 – 0.1

0.0

0.0 – 21.1

7.1

GP-11

0.0 – 0.1

0.0

0.0 – 16.0

7.7

GP-15

0.0 – 0.0

0.0

0.0 – 0.2

0.0

P-1

0.0 – 0.1

0.0

0.0 – 15.0

8.0

P-2

0.0 – 0.1

0.0

0.0 – 10.2

5.2

P-3

0.0 – 0.0

0.0

0.0 – 16.8

6.8

P-4

0.0 – 0.1

0.0

6.2 – 19.2

15.0

P-5

0.0 – 0.0

0.0

0.0 – 13.8

4.3

P-6

0.0 – 0.1

0.0

0.0 – 1.7

0.5

P-7

0.0 – 0.1

0.0

0.0 – 0.0

0.0

P-8

0.0 – 0.0

0.0

0.0 – 0.0

0.0

P-9

0.0 – 0.0

0.0

0.0 – 0.2

0.0

 

SENT Landfill - Classification of Source

As SENT Landfill is a large operating landfill, the facility must be acknowledged as a significant potential source of landfill gas.  SENT Landfill was designed and constructed to incorporate international best practices to contain, manage and control waste, leachate, and landfill gas.   It is operated by an experienced international reputable waste management contractor.

 

The potential off-site migration of landfill gas should be assessed taking into account the comprehensive and highly effective collection and management system installed and operated.   The regular landfill gas monitoring results at the perimeter boreholes undertaken by the landfill contractor indicate that an insignificant amount of methane was recorded in the perimeter boreholes along the southern boundary.  However, according to the Guidance Note, a carbon dioxide concentration greater than 5% v/v above background levels in any monitoring well indicates significant migration.  Hence the potential of off-site migration of landfill gas cannot be eliminated.    

 

Given the size of the SENT Landfill, the multiple landfill gas controls and the recent landfill gas monitoring data, it would be reasonable to classify it as a “medium” source.

 

The Extension

The Extension will occupy 15 ha in TKO Area 137 located immediately south of the existing infrastructure area of SENT Landfill.  The Extension will piggyback onto the southern slope of the existing SENT Landfill and will occupy approximately 5 ha of the natural slope at the edge of the Clear Water Bay Country Park (CWBCP).  The two landfills will be separated by the cap of the SENT Landfill and the liner of the Extension.

The Extension is designed to receive approximately 17 Mm3 of waste over a period of approximately 6 years.  It is anticipated that the Extension will commence operation in 2013 and will accept similar waste types to those currently disposed of at SENT Landfill.

 

It has been estimated that the landfill will typically generate between 14 and 52 Mm3 of gas per year throughout its operational life.  Gas generation is predicted to peak at 73 Mm3 per year in 2020, around two years after the Extension is closed.

 

The Extension – Landfill Gas Control

Similar to the SENT Landfill, the Extension will be designed to incorporate extensive measures to contain, collect, and treat/utilise landfill gas.  These measures include a composite liner systems, active landfill gas extraction and landfill gas treatment and utilisation system in accordance with international best practices for landfill operation.  These measures can effectively control sub-surface off-site migration of landfill gas, as demonstrated by the monitoring data at the SENT Landfill.  The design of the composite liner system for the Extension will be similar to those currently being used in the SENT Landfill.  Details of the composite liner system designed for the Extension is shown in Figure 3.3c.

 

A comprehensive environmental monitoring programme will be implemented during the construction, operation, restoration and aftercare of the Extension to monitor landfill gas generated within the Extension and at the perimeter boreholes around the Extension.  With reference to the performance standard stipulated in the SENT Landfill contract, the landfill contractor is required to control the migration of landfill gas such that the concentration of methane and carbon dioxide at the perimeter boreholes shall not exceed 1% v/v and 1.5% v/v, respectively.  The Extension contract will adopt the same standard.  Since the Extension Site is formed by reclamation of public fill, carbon dioxide may occur naturally in the fill material.  It is thus more reasonable to adopt 1.5% v/v above the background concentration as the standard.  The Extension contractor will be required to continue the control and monitoring of landfill gas following closure of the landfill for a period of 30 years.

 

The Extension – Classification of Source

Although the Extension is not as large as the SENT Landfill, the facility should still be acknowledged as a potential source of landfill gas.  Similar to the SENT Landfill, the Extension will be designed and constructed to incorporate international best practices to contain, manage and control waste, leachate, and landfill gas.   It will be operated by an experienced waste management contractor.

 

Under the Extension contract requirement, the Extension contractor will be required to control off-site landfill gas migration such that the methane and carbon dioxide concentration at the perimeter wells will not exceed 1% v/v and 1.5% v/v above background level, respectively.  The potential off-site migration of landfill gas should be assessed taking into account the comprehensive and highly effective collection and management system to be installed and operated.

 

Taking into account the multiple landfill gas control measures to be installed, the recent landfill gas monitoring data of the SENT Landfill, and stringent contract requirements for controlling off-site landfill gas migration, it would be reasonably conservative to classify the Extension as a “medium” source. 

 

8.5.2                                The Pathways

General

The potential pathways through which landfill gas may enter the Extension Site and the developments adjacent to the Extension are threefold; namely:

·            through transmission along natural pathways such as fissures or joints in rock;

·            man-made pathways such as through permeable backfill in utilities trenches; or

·            a combination of both. 

The likely potential for each mode of transmission are clearly dependent on the geological and hydrogeological conditions, which are discussed below.

 

Geology and Hydrogeology

The Extension is located partly on reclaimed land in TKO Area 137, partly on the southern slope of the SENT Landfill and partly on the natural slope of CWBCP. 

 

It is understood that TKO Area 137 was formed by public fill generated from construction projects in Hong Kong as it has been operating as a fill bank since 2002.  The future final level of TKO Area 137 is at approximately +5.5mPD.  Based on records of the ground investigation undertaken as part of this Study, the level of groundwater table is approximately at +2.8mPD, leaving an unsaturated layer of 2.7m.   It is considered that this permeable layer between the SENT Landfill, the Extension and the adjacent existing and future development must be conservatively considered as conducive to landfill gas migration.  Sections through the SENT Landfill and the Extension site is presented in Figures 8.5c and 8.5d. 

 

Utilities

It is known that underground utilities (leachate and landfill gas collection pipes, electricity, telecommunications and Towngas) exist in the existing infrastructure area of SENT Landfill.  However, these underground utilities do not connect to TKO Area 137 or the TKOIE.  It is also understood that there are no man-made underground utilities in TKO Area 137, except a box culvert connect the existing SENT Landfill and the berthing area in TKO Area 137.  A layout plan for the utility services in the infrastructure area is presented in Figure 8.5e.

 

It is known that services (electricity, telecommunications and Towngas) exist running parallel to Wan Po Road near TKOIE and there are no man-made underground service channels, tunnels or culverts run contiguously between the Extension and the TKOIE.  

 

In future, leachate and landfill gas pipes at the existing SENT Landfill will be connected to the infrastructure area of the Extension.

 

Classification of Pathways – from SENT Landfill to the Extension

At present, the potential pathways for migration of landfill gas from the SENT Landfill to the Extension Site in TKO Area 137 are considered to comprise only natural features and reclamation fill.  No direct anthropogenic migration pathways (man-made underground utilities) have been identified as connecting the SENT Landfill to the Extension site in TKO Area 137.  As the design of the Extension will piggyback onto the southern slope of the SENT Landfill, gaps in the SENT Landfill capping system, if any, and the underground utilities at the infrastructure area may form migration pathways for landfill gas to migrate to the portion of Extension directly over the infrastructure area and the southern slope of the SENT Landfill.  Taking into account the distance between the SENT Landfill and the Extension and the presence of possible migration pathways between the two landfills, the pathway for landfill gas migration from the SENT Landfill to the Extension should be classified as “very short/direct”.

 

Classification of Pathways – from the Extension to the Future Infrastructure Area

The potential pathways for sub-surface migration of landfill gas from the Extension to the future infrastructure area are considered to comprise both reclamation fill and the future utilities connecting the infrastructure area.  At present, no direct anthropogenic migration pathways (man-made underground utilities) have been identified as connecting the Extension to the adjacent existing and future development in TKO Area 137.  Taking into account the distance and the presence of possible migration pathways between the Extension and the future infrastructure area, the pathway for landfill gas migration from the Extension to the future infrastructure area should be classified as “very short/direct”.

 

Classification of Pathways – from the Extension to the Adjacent Developments

The potential pathways for sub-surface migration of landfill gas from the Extension to the adjacent existing and future developments in TKO Area 137 are considered to comprise only natural features and reclamation fill.  At present, no direct anthropogenic migration pathways (man-made underground utilities) have been identified as connecting the Extension to the adjacent existing and future development in TKO Area 137.  Taking into account the distance between the Extension and the adjacent existing and future development, and the presence of possible migration pathways, the pathway for landfill gas migration from the Extension to the adjacent existing and future developments in Area 137 should be classified as according to the distance between the development and the Extension: <50m as very short/direct, 50-100m as moderately short/indirect, 100-250m as long/indirect.

 

8.5.3                                The Targets

Landfill gas related impacts may occur in areas at or below ground, at the Extension and the adjacent existing and future development in TKO Area 137.

 

Target 1 - Construction Site of the Extension

As shown in Figure 8.2a, the majority of the Extension Site falls within the 250m Landfill Consultation Zone of the SENT Landfill.  Demolition and minor excavation at the existing infrastructure area are expected.  The excavation area and the areas of confined space and trenches, if any, are at a higher risk of exposure to landfill gas.  However, in general, any excavation work or work involving the construction of trenches will use the open cut method, although there may be deep excavations.  Any migration of landfill gas will easily be dispersed and diluted upon contact with the atmosphere.  Tunnel construction will involve working in confined spaces by trained workers.  This target is thus classified as “medium sensitivity”.

 

Target 2 - Operation of the Extension (Tipping Face)

As discussed earlier, the SENT Landfill and the Extension are separated by the capping system of the SENT Landfill and the liner system of the Extension.  It is not expected that there will be landfill gas migration from the SENT Landfill to the tipping face.  In addition, all landfill equipment is designed to work under conditions where flammable gas may present.

 

The majority the waste tipping face will be carried out within the 250m Landfill Consultation Zone of the SENT Landfill.  Waste tipping will be in the open air which will not involve working at confined spaces and by definition, the Extension is also a source of landfill gas, thus any migration of landfill gas to the Extension will either be dispersed and diluted upon contact with the atmosphere or be captured in the landfill gas collection system of the Extension.  However, it is also noted that drivers/operators of waste collection vehicles will have access to the waste tipping face for disposal of waste and they may not have knowledge on landfill gas hazards.  In view of the above, this target is thus classified as “medium sensitivity”. 

 

Target 3 – Operation of the Extension (Infrastructure Area)

The proposed infrastructure area of the Extension will be outside the 250m Landfill Consultation Zone of the SENT Landfill but within the 250m Landfill Consultation Zone of the Extension.  Underground confined spaces (such as manhole and utility pits) and ground level offices and pump rooms with underground utility connections are places where landfill gas can potentially accumulate and may have sources of ignition (e.g. electrical or other equipment).  Restricted access to the manhole, utility pits and pump rooms by authorised and well trained personnel is expected.  These rooms/voids are thus considered to have “medium” sensitivity.   Ground level offices and some ground level rooms are generally of unrestricted staff access or public access accompanied by site staff.  These rooms/voids are thus considered to have “high” sensitivity.  Nevertheless, the landfill will be operated by an experienced landfill contractor who is fully aware of the potential landfill gas hazards and with their staff well trained on the potential hazards relating to landfill gas and the specific safety procedures.  All ground floor rooms of the buildings on-site will be equipped with a gas detection and alarm system.  This target is classified as “medium to high sensitivity”.

 

Target 4 – Adjacent Existing and New Development in TKOIE and TKO Area 137

Parts of the TKOIE and TKO Area 137 are within the existing Landfill Consultation Zone of the SENT Landfill and the new Landfill Consultation Zone of the Extension.  The additional Landfill Consultation Zone, not covered by the existing one, is shown in Figure 8.2a.  The area within this additional consultation zone is located at TKO Area 137, which is planned for industrial uses.

 

The potential hazards posed by landfill gas migration and the need for protection measures for developments close to landfill sites are outlined in Chapter 9 of the HKPSG.  It is a requirement that project proponents of developments adjacent to landfills undertake a landfill gas hazard assessment and submit the findings to EPD for vetting.  As recommended in ProPECC PN 3/96, the project proponents and professionals (Authorised Persons) responsible for the developments adjacent to landfills should:

(i)        carry out a landfill gas hazard assessment to evaluate the degree of risk associated with the proposed development;

(ii)       design suitable precautionary/protection measures to render the proposed development as safe as reasonably practicable;

(iii)     ensure that the precautionary/protection measures will be implemented and constructed in accordance with the design; and

(iv)     establish a maintenance and monitoring programme for ensuring the continued performance of the implemented protection measures.

 

Design information for the uses located within the 250m Landfill Consultation Zone of the Extension is not available at this stage.  The Extension will impose constraints on the landuse and suitable landfill gas protection measures will/may be required depending on the landuse. 

 

With consideration of these above requirements, this target is classified as “low sensitivity”.

 

8.5.4                                Source-Pathway-Target Analysis

On the basis of the source, pathways and targets identified above, a source-pathway-target analysis has been undertaken and is presented in Table 8.5b according to EPD’s assessment framework.  Different combination of source, pathway and target result in a range of overall potential hazards.

 

Table 8.5b            Qualitative Assessment of Landfill Gas Hazard Associated with the Extension

 

Source

Pathway

Target

Qualitative Risk

SENT landfill - potential for gas generation over time, but comprehensive and proven mitigation installed 

(category: medium)

Surface soil, reclamation fill materials, part of the work site piggyback onto the waste slope of SENT Landfill and the existing infrastructure area with potential direct anthropogenic conducts, distance to waste boundary  <50m

(category: very short/direct)

Target 1 (Construction site of the Extension) – Open cut construction method, may have deep excavation, working in confined space by trained workers

(category: medium sensitivity target)

Medium

SENT landfill - potential for gas generation over time, but comprehensive and proven mitigation installed 

 

The Extension - potential for gas generation over time, comprehensive and proven mitigation to be installed 

 

(category: medium)

 

Surface soil, reclamation fill materials, part of the tipping face piggyback onto the waste slope of SENT Landfill and the existing infrastructure area with potential direct anthropogenic conducts, distance to waste boundary <50m

(category: very short/direct)

Target 2 (Tipping face of the Extension) –  waste tipping in the open air, absence of confined space, access by drivers/operators of waste collection vehicles who may not have knowledge on landfill gas hazards

(category: medium sensitivity)

Medium

The Extension - potential for gas generation over time, comprehensive and proven mitigation to be installed 

(category: medium)

Surface soil, reclamation fill materials, potential direct anthropogenic conducts, distance to waste boundary  <50m

(category: very short/direct)

Target 3 (Infrastructure area of the Extension) – Ground level offices and pump rooms of unrestricted staff access, underground confined spaces with restricted access, some with source of ignition

(category: medium to high sensitivity)

 

Medium to High

Surface soil, reclamation fill materials, no direct anthropogenic conducts

-                                             Distance to waste boundary <50m (category: very short/direct)

-                                             Distance to waste boundary between 50m to 100m (category: moderate short/direct)

-                                             Distance to waste boundary >100m (category: long/indirect)

Target 4 (Adjacent existing and new development) –according to ProPECC PN 3/96, project proponents and are required to carry out landfill gas hazard assessment and implement suitable landfill gas protection measures

(category: low sensitivity)

Very Low to Low

 

8.6                                      Recommendations

The source-pathway-target analysis shows that landfill gas risk posed by the SENT Landfill and the Extension is medium to high within the Extension Site boundary during both the construction and operation phases.  Whereas the risk posed by the Extension to the adjacent developments ranges from very low to low depending on the nature and location of the adjacent developments.

 

This section of the report provides general advice and recommendations for the avoidance of environmental impacts related to landfill gas during the construction and operation of the Extension.  It is recommended that the project proponent of any development within the 250m Landfill Consultation Zone of the Extension should strictly follow the requirements for landfill gas hazard assessment stipulated in the ProPECC 3/96 and the Guidance Note and undertake a detailed QLFGHA to assess the hazard potential and to identify the precautionary measures.

 

Implementation of the landfill gas control measures, and restoration works undertaken will also significantly reduce the potential for off-site migration of landfill gas to the adjacent developments.

 

8.6.1                                General Hazards Related to Landfill Gas

Landfill Gas

All contractors participating in the works and operational staff should be aware that potential of methane and carbon dioxide present in the soil and all works should be undertaken on the basis of an "assumed presence of landfill gas".  In addition the following properties of landfill gas should be noted.

 

·           Methane is odourless and colourless, although in landfill gas it is typically associated with numerous highly odoriferous compounds which gives some warning of its presence.  However, the absence of odour should not be taken to mean that there is no methane.  Methane levels can only be reliably confirmed by using appropriately calibrated portable methane detectors.

 

·           Methane is a flammable gas and will burn when mixed with air between approximately 5 and 15% (v/v).  If a mixture of methane and air with a composition between these two values is ignited in a confined space, the resulting combustion may give rise to an explosion.  Methane is also an asphyxiant.

 

·           Carbon dioxide, the other major component of landfill gas is an asphyxiating gas and causes adverse health effects at relatively low concentrations.  The long-term Occupational Exposure Limit (OEL) is 0.5% (v/v).  Like methane, it is odourless and colourless and its presence (or absence) can only be confirmed by using appropriately calibrated portable detectors.

 

·           Gas density.  Methane is lighter than air whereas carbon dioxide is heavier than air.  Typical mixtures of landfill gas are likely to have a density close to or equal to that of air.  However, site conditions may result in a ratio of methane to carbon dioxide which may make the gas mixture lighter or heavier than air.  As a result, landfill gas may accumulate in either the base or top of any voids or confined spaces.

 

8.6.2                                General Recommended Precautionary and Protection Measures – Construction Phase

The construction works to be undertaken at the Extension Site and the adjacent developments present construction workers and others with risks resulting from contact with landfill gas.  For example, when laying of underground pipes/utilities in trenches or other situations, personnel may have to enter confined spaces.  Precautionary measures to be adopted by the contractors at the Extension Site and the adjacent development site within the landfill consultation zone are outlined in Paragraphs 8.3 to 8.49 of EPD’s Guidance Note.  The following guidance has been extracted from and appended to this and to ensure a robust and comprehensive set of measures to protect workers are provided.

 

·           During all works, safety procedures will be implemented to minimise the risks of fires and explosions and asphyxiation of workers (especially in confined space).

 

·           Safety officers, specifically trained with regard to landfill gas related hazards and the appropriate actions to take in adverse circumstances, will be present on all worksites throughout the works.

 

·           All personnel who work on site and all visitors to the site will be made aware of the possibility of ignition of gas in the vicinity of the works.

 

·           Those staff who work in, or have responsibility for 'at risk' areas, including bore piling and excavation works, will receive appropriate training on working in areas susceptible to landfill gas.

 

·           Any offices/quarters set up on site will take precautions against landfill gas ingress, such as being raised off the ground.  Other storage premises, e.g. shipping containers, where this is not possible will be well ventilated prior to entry.

 

·           Adequate precautions to prevent the accumulation of landfill gas under site buildings and within storage shed will be taken by raising buildings off the ground where appropriate and 'airing' storage containers prior to entry by personnel and ensuring adequate ventilation at all times.

 

·           Smoking and naked flames will be prohibited within confined spaces.  'No Smoking' and 'No Naked Flame' notices in Chinese and English will be posted prominently around the construction site.  Safety notices should be posted warning of the potential hazards.

 

·           Welding, flame-cutting or other hot works may only be carried out in confined spaces when controlled by a 'permit to work' procedure, properly authorised by the Safety Officer.  The permit to work procedure will set down clearly the requirements for continuous monitoring of methane, carbon dioxide and oxygen throughout the period during which the hot works are in progress.  The procedure will also require the presence of an appropriately qualified person who shall be responsible for reviewing the gas measurements as they are made, and who shall have executive responsibility for suspending the work in the event of unacceptable or hazardous conditions.  Only those workers who are appropriately trained and fully aware of the potentially hazardous conditions which may arise will be permitted to carry out hot works in confined areas.

 

·           During the construction works, adequate fire extinguishers and breathing apparatus sets will be made available on site and appropriate training given in their use. 

 

Monitoring

Monitoring will be undertaken when construction works are carried out in confined space within the consultation zone.  The monitoring requirements and procedures specified in Paragraphs 8.23 to 8.28 of EPD’s Guidance Note are highlighted below: 

 

·           The monitoring equipment used will be capable of measuring methane, carbon dioxide and oxygen concentrations.  The equipment will be intrinsically safe and calibrated according to the manufacturers instructions.

 

·           When portable monitoring equipment is to be used, the frequency and areas to be monitored will be set down prior to commencement of the works either by the Safety Officer or by an appropriately qualified person. 

 

·           All measurements will be made with the monitoring tube located not more than 10 mm from the surface.

 

·           A standard form, detailing the location, time of monitoring and equipment used together with the gas concentrations measured, will be used when undertaking manual monitoring to ensure that all relevant data are recorded.

 

·           Monitoring of excavations will be undertaken as follows:

 

For excavations deeper than 1m, measurements will be made:

(i)        At the ground surface before excavation commences;

(ii)      Immediately before any worker enters the excavation;

(iii)     At the beginning of each working day for the entire period the excavation remains open; and

(iv)    Periodically through the working day whilst workers are in the excavation.

 

For excavations between 300mm and 1m deep, measurements will be made:

 

(i)        Directly after the excavation has been completed; and

(ii)      Periodically whilst the excavation remains open.

 

For excavations less than 300mm deep, monitoring may be omitted, at the discretion of the Safety Officer or other appropriately qualified person.

 

·         If methane (flammable gas) or carbon dioxide concentrations are in excess of the trigger levels or that of oxygen is below the level specified in the Emergency Management in the following section, then evacuation will be initiated.

 

Actions in the Event of Gas Being Detected

Depending on the results of the measurements, actions required will vary and will be set down by the Safety Officer or another appropriately qualified person.  As a minimum these should encompass those actions specified in Table 8.6a.

Table 8.6a   Actions in the Event of Gas Being Detected

Parameter

Measurement

Action

O2

< 19% v/v

Increase underground ventilation to restore O2 to >19% v/v

 

 

< 18% v/v

Stop works

Evacuate all personnel

Increase ventilation further to restore O2 to >19% v/v

CH4

> 10% LEL

Prohibit hot works

Increase ventilation to restore CH4 to <10% LEL

 

 

>20% LEL

Stop works

Evacuate all personnel

Increase ventilation further to restore CH4 to <10% LEL

CO2

>0.5% v/v

Increase ventilation  to restore CO2 to <0.5% v/v

 

 

> 1.5% v/v

Stop works

Evacuate all personnel

Increase ventilation further to restore CO2 to <0.5%

Emergency Management

In order to ensure that evacuation procedures are implemented in the event of the trigger levels specified in Table 8.6a above being exceeded, it is recommended that a person, such as the Safety Officer, is nominated, with deputies, to be responsible for dealing with any emergency which may occur due to landfill gas.

 

In an emergency situation the nominated person, or his deputies, shall have the necessary authority and shall ensure that the confined space is evacuated and the necessary works implemented for reducing the concentrations of gas.  The following organisations shall also be contacted as appropriate:

 

·       Hong Kong Police Force;

·       Fire Services Department; and

·       Environmental Protection Department.

 

8.6.3                                General Recommended Precautionary and Protection Measures - Design Phase

The design of the landfill gas management system and the landfill gas precautionary measures to be adopted on-site will be performed by a landfill gas specialist consultant appointed by the Extension contractor, who has comprehensive knowledge on landfill characteristics, potential landfill gas hazards and appropriate precautionary measures to minimise hazards.  Moreover, the landfill gas management system and landfill gas precautionary measures will be checked and certified by a qualified independent consultant The potential implications associated with the various qualitative risk categories are summarised in Table 8.4b.  During the detailed design stage, a review of this preliminary qualitative risk assessment will be carried out, a detailed qualitative landfill gas risk assessment will be prepared and the report together with the detailed design of gas protection measures will be submitted to EPD for vetting.

 

For the Construction and Operation of the Extension

According to the source-path-target analysis in Section 8.5, the risk category at the Extension during construction and operation (waste tipping) is medium.  This implies that engineering measures will be required during the design stage to ensure that the construction and waste tipping at the Extension is safe.  As the Extension will be designed, built and operated by an experienced landfill contractor, it is anticipated that relevant engineering measures will be identified and implemented in accordance with the Extension Contract Specification requirements.  These measures will include the placement of liner and installation of landfill gas management system to contain, manage and control landfill gas.  Migration of landfill gas from the SENT Landfill to the Extension, if any, will be captured by the landfill gas management system at the Extension.

 

For the Operation of the Infrastructure Area at the Extension

The infrastructure area at the Extension is considered to have medium to high risk.  According to Table 8.4b, engineering measures to significant engineering measures will be required to protect the staff working in the infrastructure area.   These measures include a combination of passive and active systems.  Examples of these measures as recommended in EPD’s Guidance Notes are listed below for reference.

 

·       Passive control measures:

·       Gas-resistant polymeric membranes which can be incorporated into floor or wall construction as continuous sealed layer (see Figure 8.6a).  Membranes should be able to demonstrate low gas permeability and resistance to possible chemical attack, and may incorporate aluminium wafers to improve performance.

·       Other building materials such as dense well-compacted concrete or steel shuttering which provide a measure of resistance to gas permeation.

·       Creation of a clear void under the structure which is ventilated by natural air movements such that any emissions of gas from the ground are mixed and diluted by air (see Figure 8.6b).

·       Synthetic composite geotextiles which provide a free-venting cellular structure and provide preferential pathways for release of gas

 

·       Active control measures:

·       A void under the structure, as discussed for passive control, but which is continuously ventilated by a fan, such that any emissions of gas from the ground are mixed and diluted in the air flow before discharge to atmosphere (see Figure 8.6b).  The rate of ventilation is usually expressed in terms of the number of air changes (volume of the void) per hour and is designed to ensure that, based on the estimated rate at which gas will enter the void, the landfill gas will be diluted to safe concentrations.  Discharge to atmosphere usually takes place above the eaves level of the building or, in the case of high rise structures, at a minimum height of 10 m above ground and away from air intakes to the building.

·       Construction of a granular layer incorporating perforated collector pipes which is continually ventilated by a fan, such that any emissions of gas from the ground are drawn towards the end of the pipes and diluted in the air flow before discharge to atmosphere above the eaves level of the building, or in the case of high rise structures, at a minimum height of 10 m above ground and away from air intakes to the building.

·       Creation of a positive pressure zone below the building structure by injection of air from a blower into the granular layer.

·       Creation of a positive air pressure zones within building structures to counteract possible leakage of gas into the building from the ground.

 

Active control should always be used in conjunction with passive barriers such as membranes in floors, in order that there is no leakage of air/gas flow through a floor or wall into a structure.  Gas detection systems should also be used to monitor gas in extracted air flow, and to monitor internal spaces inside buildings.  Active systems are normally required for high risk sites where landfill gas has been measured in the ground at or close to the development site, and where buildings are close to the source of landfill gas.

 

Landfill gas may also enter the building/void via service entries.  Measures to prevent gas migration through service entries are listed below:

 

·       Gas Barriers

·       Barriers used to prevent movement of landfill gas through service entries may be made of clay (or clay-rich soils), bentonite or polymeric membranes (such as HDPE).  The design detail at the point where the service penetrates the membrane is important and, in the case of HDPE membranes, pre-formed shrouds are available.  The design detail at the point where the service penetrates the membrane is important and use should be made of pre-formed shrounds (orr cloaks), skirts and fillets.  A schematic for an HDPE flexible membrane cut-off is shown in Figure 8.6c.

·       It may be appropriate to consider routing all services through a sealed culvert or duct which is either completely lined in naturally gas-resistant material (e.g. clay) or which is lined with an HDPE membrane.

·       In the case of water pipes and sewers which are not always fully filled, water traps, such as U-bends, should be provided to effectively seal off the conduit and prevent gas-phase transport.

·       In order to prevent the ingress of landfill gas into a building via the interface between the service pipe and the backfilled soil, it is important that the annulus around any service entry points is effectively blocked by means of sealant, collars or puddle flanges as appropriate (see Figure 8.6d)

·       Gas Vents

·       Vent pipes or griddled manhole covers may be used to avoid build-up of landfill gas in underground utilities manholes.  Venting stacks may be built into inspection chambers or connected to collection pipes within high permeability drainage layers adjacent to landfill gas barriers.  A typical vented manhole arrangement is shown in Figure 8.6e.

·       A further type of venting arrangement, which may be appropriate to multiple service entries, comprises a vented gas interceptor cavity through which service pipes pass, as shown in Figure 8.6f.  The aim of this protection measure is to locate the barrier component within the building sub-structure in a sealed entry box which is fitted with a vent stack.

 

In addition to the above precautionary measures, landfill gas monitoring boreholes will be installed at the edge of the waste slope between the waste and the new infrastructure area to monitor the migration of landfill gas, if any.

 

For Future Developments in TKO Industrial Estate and TKO Area 137

For future developments in TKOIE and TKO Area 137 which fall into the Landfill Consultation Zone of the Extension as shown in Figure 8.2a, the project proponents should strictly follow the recommendations in the HKPSG and the ProPECC PN 3/96 to carry out landfill gas hazard assessment for the developments and design/implement suitable precautionary and protection measures to render the development as safe as practicable.  These adjacent developments are considered to have very low to low risk. 

 

8.6.4                                General Recommended Precautionary and Protection Measures - Operational, Restoration and Aftercare Phases

The Extension Contractor

The Extension Contractor will have a responsibility to train and to ensure that their staff take appropriate precautions at all times when entering enclosed spaces or plant rooms.  The Extension Contractor will also undertake regular monitoring of landfill gas at the perimeter boreholes to detect if there are any signs of off-site landfill gas migration.  The Extension Contractor will be responsible to prepare and implement emergency plan in case off-site landfill gas migration is detected.

 

A permanent gas monitoring system with alarms will be installed and operated in all occupied on-site buildings.

 

Utility Companies

All utility companies should be made aware of the location and features of the development site within the Extension Landfill Consultation Zone by the future developers of the site during the respective detailed design stage as part of the QLFGHA.  The utilities companies should have a responsibility to train and ensure their staff to take appropriate precautions at all times when entering enclosed spaces or plant rooms. 

8.7                                      Environmental Monitoring and Audit

The Extension Contractor will be required to undertake regular monitoring of landfill gas within the Extension and the Extension boundary as required by the Extension Contract Specification. 

 

Similar to the Contract Specification of the existing SENT Landfill, monitoring of landfill gas at the perimeter landfill gas monitoring wells will be required at weekly (where there is development within 250m of the Extension Site Boundary) or monthly intervals (for the other monitoring wells) during the operation and restoration of the Extension.  During the aftercare phase, monitoring at all perimeter wells will be at monthly intervals.  Bulk gas analysis for at least 2 of the perimeter wells will be required at quarterly intervals throughout the operation, restoration and aftercare of the Extension.  In addition, monitoring of service voids along the Site boundary and within the Extension Site will be required at monthly intervals throughout the operation, restoration and aftercare of the Extension.  The Extension Contractor will also be required to undertake surface emission monitoring of methane gas (or flammable gas) in areas between the waste boundary and the Extension Site boundary at quarterly intervals throughout the operation, restoration and aftercare phases.  Actions will be taken if an abnormal level of landfill gas is detected.

 

8.8                                      Summary and Conclusions

This section has provided a qualitative assessment on potential hazards associated with landfill gas migration from the SENT Landfill to the Extension and from the Extension to the adjacent existing and future developments.  Both landfills are considered as a “medium” source of gas migration due to the comprehensive and proven landfill gas control measures installed or to be installed.  The source-pathway-target analysis shows that landfill gas risk posed by the SENT Landfill and the Extension is medium to high during both construction and operation phases within the Extension Site.  Whereas the risk posed by the Extension to the adjacent developments ranges from very low to low depending on the nature and location of the these developments.

 

In general, underground rooms or void spaces should be avoided as far as practicable at the infrastructure area of the Extension site.  Other precautionary and protection measures during construction, design and operation/restoration phases of the Extension have been recommended.  It is expected that with the proposed precautionary measures in place, the potential risk of landfill gas migration to the respective targets will be minimal. 



 



([1])    ProPECC PN3/96 Landfill Gas Hazard Assessment for Developments adjacent to Landfills, Dec 1996, EPD.

([2])    Landfill Gas Hazard Assessment Guidance Note, 1997, EPD.