Proposed Comprehensive Development
at Wo Shang Wai, Yuen Long
Environmental Impact Assessment
March 2008
Mott Connell Ltd
7th Floor,
Tsim Sha Tsui,
Hong Kong
Tel: 2828 5757
Fax: 2827 1823
in association with
Urbis Limited
Master Plan Limited
Allied
Environmental Consultant Limited
"This
document has been prepared for the titled project or named part thereof and
should not be relied upon or used for any other project without an independent
check being carried out as to its suitability and prior written authority of
Mott Connell being obtained. Mott Connell accepts no responsibility or
liability for the consequences of this document being used for a purpose other
than the purposes for which it was commissioned. Any person using or relying on
the document for such other purpose agrees, and will by such use or reliance be
taken to confirm his agreement, to indemnify Mott Connell for all loss or
damage resulting therefrom. Mott Connell accepts no responsibility or liability
for this document to any party other than the person by whom it was
commissioned.
To the
extent that this document is based on information supplied by other parties,
Mott Connell
accepts
no liability for any loss or damage suffered by the client, whether contractual
or tortious, stemming from any conclusions based on data supplied by parties
other than Mott Connell and used by Mott Connell in preparing this document."
List of Contents Page
Chapters
Page
No.
1.3 EIAO
and Designated Projects
1.4 Continuous
Public Involvement
1.6 Objectives
of the EIA Study
1.9 Structure
of the EIA Report
2 CONSIDERATION OF ALTERNATIVES
2.4 Consideration
of Alternatives
2.5 Working
Up the Initial Options
2.6 Construction
Methods and Sequences of Works
3.2 Legislation,
Standards, Guidelines and Criteria
3.4 Baseline
Conditions/ Sensitive Receivers
3.5 Air
Quality Impact Assessment
3.8 Environmental
Monitoring and Audit
3.9 Conclusions
and Recommendations
4.2 Government
Legislation and Standards
4.4 Identification
of Potential Noise Impacts
4.5 Determination
of Noise Sensitive Receivers
4.7 Prediction
and Evaluation of Noise Impacts
5.2 Environmental
Legislation, Standards, Guidelines and Criteria
5.3 Existing
Environment and Sensitive Receivers
5.7 Environmental
Monitoring and Audit
6 Sewerage and Sewage Treatment Implications
6.3 Assessment
Approach and Methodology
6.4 Design
Assumptions, Parameters and Criteria
6.5 Existing
Sewerage Conditions
6.6 Estimated
Pollutant Loads to the Existing Water Body due to the Proposed Development
6.7 Proposed
Mitigation Measures
6.8 Short
Term Measures during Construction Stage
6.9 Conclusion
and Recommendations
7.2 Environmental
Legislation and Standards
7.8 Sediment
Quality and Potential Biogas
7.9 Environmental
Monitoring and Audit Requirements
8 Ecological Impact assessment
8.4 Sites
of Conservation Importance in the Area
8.7 Ecological
Value of habitats in the Project Area and within the Assessment Area
8.8 Potential
Ecological Impacts
8.9 Mitigation
Measures Adopted to Avoid, Minimise and Compensate for Ecological Impacts
8.10 Post-mitigation
Acceptability of the Project
9 Fisheries Impacts ASSESSMENT
9.8 Environmental
Monitoring and Audit Programme
10.2 Relevant
Legislation & Guidelines
10.4 Baseline
Conditions and Sensitive Receivers
11 Landscape and Visual Impact
11.2 Environmental
Legislation and Guidelines
11.3 Scope
and Content of the Study
11.4 Planning
and Development Control Framework
11.6 Landscape
Impact Assessment
13 SUMMARY OF ENVIRONMENTAL OUTCOMES
13.5 Sewerage
and Sewage Treatment
13.10 Landscape
and Visual Impact
14 ENVIRONMENTAL MONITORING AND AUDIT (EM&A) REQUIREMENTS
14.5 Sewerage
and Sewage Treatment Implications
14.10 Landscape
and Visual Impact
15 PROJECT IMPLEMENTATION SCHEDULE
List of Tables
Table 2‑1...... Development
Criteria
Table 2‑2...... Summary
of Alternative Options Considered
Table 3‑1...... Hong
Kong Air Quality Objectives (mg/m3)(i)
Table 3‑2...... Traffic
Forecast in Year 2027
Table 3‑3...... Air
Quality at Yuen Long Monitoring Station in Past Five Years
Table 3‑4...... Locations
of Representative Air Sensitive Receiver
Table 4‑1...... Relevant
Noise Standards for Planning Purposes.
Table 4‑2...... Noise
Standards for Daytime Construction Activities
Table 4‑3...... Area
Sensitivity Ratings (ASRs)
Table 4‑4...... Acceptable
Noise Levels (ANLs)
Table 4‑5...... Measured
Noise Levels
Table 4‑6...... Identified
Noise Sensitive Receivers within 300m from the Boundary of Project Area
Table 4‑8...... Assessment
Points of the Representative NSRs for Operational Stage
Table 4‑9...... Inventory
of Noise Sources at Each Phase – During Construction
Table 4‑10.... Summary
of Open Storage Site Noise Measurement Results at Point F
Table 4‑11.... Traffic
Flow Forecast of Existing and Future Road Networks (Year 2027)
Table 4‑12.... Maximum
Predicted Unmitigated Construction Noise Levels at Representative NSRs
Table 4‑13.... Predicted
Noise Levels at Representative NSRs
Table 4‑14.... QPME
to be used at the Construction Site
Table 5‑3...... Key
Water Quality Objectives for inland waters in Deep Bay Water Control Zones
Table 5‑5...... In-situ
Water Quality Testing Parameters
Table 5‑6...... Water
Quality Testing Parameters in Laboratory
Table 6‑1...... Design
Unit Load Factors
Table 6‑2...... Pollutant
Loads arising from the Raw Sewage of the Proposed Development
Table 7‑1...... Potential
contaminants
Table 7‑2...... General
hazardous effects of contaminants potentially present
Table 7‑3...... Ground
conditions encountered and depth of subsamples tested
Table 7‑4...... Summary
of chemical test results on soil samples
Table 7‑5...... Summary
of chemical test results on ground water samples
Table 7‑6...... Summary
of additional TPH test results on ground water samples
Table 7‑7...... Summary
of land contamination locations
Table 7‑8...... Criteria
for the chemical screening of sediment (from ETWB(W)TC 34/2002)
Table 7‑9...... Criteria
for classification of sediment (from ETWB(W)TC 34/2002)
Table 7‑10.... Criteria
for disposal of sediment at sea
Table 7‑11.... Depth
of marine sediment encountered and subsamples tested
Table 7‑12.... Samples
for Tier III biological testing
Table 7‑13.... Results
of Tier III Testing
Table 7‑14.... Results
of Tier III Testing
Table 7‑15.... Summary
of chemical screening results and sediment classification
Table 7‑16.... Depth
of pond deposit encountered and tested for TOC
Table 7‑17.... Results
of Gas Spike Test Survey
Table 7‑18.... Results
of TOC Testing on Pond Mud
Table 7‑19.... Assessment
of Biogas potential using TOC results.
Table 7‑20.... Percentage
% of methane emitted after June 2006
Table 7‑21.... Maximum
potential CH4
generation in June 2008
Table 7‑22.... Estimated
volume and classification of excavated sediment
Table 8‑1...... Habitats
present in Project Area and Assessment Area
Table 8‑4...... Heights
of ardeids flying over the Project Area, June 2006
Table 8‑5...... Summary
of birds using Flight paths 1, 2 and 3, May-June 2006
Table 8‑11.... Ecological
Evaluation of Grassland Habitats
Table 8‑12.... Ecological
Evaluation of Seasonal Marsh
Table 8‑13.... Ecological
Evaluation of Freshwater Marsh/Reedbed.
Table 8‑14.... Ecological
Evaluation of Fishponds.
Table 8‑15.... Ecological
Evaluation of Drainage Channels/ Ditches.
Table 8‑16.... Ecological
Evaluation of Woodland Habitats.
Table 8‑17.... Ecological
Evaluation of Plantation Habitats.
Table 8‑18.... Ecological
Evaluation of Active and Inactive Dry Agricultural Land.
Table 8‑19.... Ecological
Evaluation of Developed Area, Bare Ground and Wasteland.
Table 8‑28.... Summary
of Potential Ecological Impacts in the absence of Mitigation Measures.
Table 9‑1...... AFCD
Figures on HKSAR Pond Culture Fisheries
Table 9‑2...... Fishponds
Status and Area in the Project Area
Table 9‑3...... Evaluation
of Fisheries Impact
Table 11‑2.... Assessment
of Layout Options against Landscape / Visual Criteria
Table 11‑3.... Proposed
Construction Phase Landscape and Visual Mitigation Measures
Table 11‑4.... Proposed
Operation Phase Landscape and Visual Mitigation Measures
Table 12‑1.... Impacts
Summary
List of Plates
Plate 1.1 Aerial
Photo Showing the Proposed Development and the adjacent Environment
Plate 8.3 Freshwater
Marsh/ Reedbed
Plate 8.6 Drainage
Channel/ Ditch
Plate 8.9 Active
Dry Agricultural Land
Plate 8.10 Inactive
Dry Agricultural Land
Plate 9.1 Fishpond
in maintenance stage (not in the site, refer to Figure 9.1 for location)
Plate 9.2 Abandoned
fishpond with reeds growing (refer to Figure 9.1 for location)
Plate 9.3 Recreational
fishing ground at Wo Shang Wai Village
Plate 9.4 Wetland
dependent birds foraging in partially drained fishpond
Plate 9.5 Release of fish fingerlings into fishpond after
maintenance
Plate 9.6 Capturing
freshwater shrimps and Mosquito Fish in Mai Po fishpond
Plate 9.7 Mosquito
Fish captured in the fishponds
Plate 9.8 Brackish
fishponds in Mai Po
Plate 9.9 Brackish
fishes cultured in Mai Po fishponds
Plate 10.1 Ancestral
Hall (Hin Hing Tong) in Mai Po Village
Plate 10.2 Ancestral Hall in Wo Shang Wai Village
List of Figures
Figure 1.1 Locations and Assessment Area of the Proposed
Development Site
Figure 1.2 Location of Conservation Area and Buffer Area
Boundaries
Figure 1.3 Standing Water patches Observed
in Dry Season
Figure 1.4 Location of Gleyed Soil
Figure 1.5 Extract of Relevant OZP
Figure 2.1 Preliminary Development Concept
Figure 2.2 Generation of Options
Figure 2.3a Schematic “Rectangular”
Development
Figure 2.3b Concept Layout Rectangular
development (3 and 4 Storeys)
Figure 2.4a Schematic “Horse Shoe” Concept
Figure 2.4b Concept Layout Nucleated (Horse Shoe) (4 Storeys)
Figure 2.5 Sketch Master Layout Plan Option A – All 2.5/3-Storey
Houses
Figure 2.6 Sketch Master Layout Plan Option B – All 6-Storey
Apartments
Figure 2.7 Sketch Master Layout Plan Option C – Mixed Height
Scheme
Figure 2.8 Sketch Master Layout Plan Option D – 2.5/3-Storey
Houses with Duplex-on-Duplex
Figure 2.9 Sketch Master Layout Plan Option E – 2.5/3-Storey
Houses
Figure 2.10 Sketch Master Layout Plan Option F – 2.5/3-Storey
Houses with Duplex-on-Duplex
Figure 2.11 Phase Layout Plan for Construction
Figure 3.1 Location of the Air Sensitive Receivers
Figure 4.1 Assessment Area of the Proposed Development Site
Figure 4.2 Location of Representative Noise Sensitive Receivers
(NSRs) in Construction Phase
Figure 4.3 Locations of Representative Noise Sensitive Receivers
(NSRs) in Operational Phase
Figure 4.4 Alignment of Site Access Road and Haul Road
Figure 4.5 Location of Baseline Noise Measurement
Figure 4.6 Minimum Height Required for Proposed Noise Barriers
and Site Hoardings
Figure 4.7 Cross-section Diagram Showing Proposed Noise
Barriers
Figure 4.8 Cross–Sectional Diagrams of Four Types of Houses in
Residential Development
Figure 4.9 Computer Plot of Noise Model
Figure 5.1 Existing Drainage Pattern in Wo Shang Wai
Figure 5.2 Water Quality Sampling Locations
Figure 5.3 Tentative Drainage Discharge Arrangement
Figure 6.1 Planned Major Sewerage Works in Northwest New
Territories from DSD
Figure 6.2 Proposed Final Sewage Discharge Point
Figure 7.1 Current Land Use at the Project Area August 2006
Figure 7.2 Land Contamination Assessment Borehole Locations
Figure 7.3 Contaminated Land Excavation
Figure 7.4 Management Framework for Dredged/Excavated Sediment
Figure 7.5 Sediment Assessment Borehole Locations
Figure 7.6 Gas Spike Survey and Biogas Investigation Locations
Figure 7.7 Marine Sediment Excavation
Figure 8.1 Sites of known ecological value close to the Project
Area
Figure 8.2 Survey transects and sampling locations
Figure 8.3 Habitats present in Project Area and Assessment Area
Figure 8.4 Bird Flight Paths over the Project Area
Figure 9.1 Fishponds Status Around Wo Shang Wai on 18 November
2005
Figure 10.1 Potential Cultural Heritage
Resources
Figure 11.1A Extract of Relevant OZP
Figure 11.1B Plan of ZVI and VSRs
Figure 11.2 Landscape Resources (Plan)
Figure 11.3 Landscape Resources (Views)
(Sheet 1 of 12)
Figure 11.4 Landscape Resources (Views)
(Sheet 2 of 12)
Figure 11.5 Landscape Resources (Views)
(Sheet 3 of 12)
Figure 11.6 Landscape Resources (Views)
(Sheet 4 of 12)
Figure 11.7 Landscape Resources (Views)
(Sheet 5 of 12)
Figure 11.8 Landscape Resources (Views)
(Sheet 6 of 12)
Figure 11.9 Landscape Resources (Views)
(Sheet 7 of 12)
Figure 11.10 Landscape Resources (Views) (Sheet
8 of 12)
Figure 11.11 Landscape Resources (Views) (Sheet
9 of 12)
Figure 11.12 Landscape Resources (Views) (Sheet
10 of 12)
Figure 11.13 Landscape Resources (Views) (Sheet
11 of 12)
Figure 11.14 Landscape Resources (Views) (Sheet
12 of 12)
Figure 11.15 Landscape Character Areas (Plan)
Figure 11.16 Photo Views of Landscape Character
Areas (1 of 2)
Figure 11.17 Photo Views of Landscape Character
Areas (2 of 2)
Figure 11.18 Section Showing Derivation of ZVI
Figure 11.19 Photos of VSR Views (1 of 5)
Figure 11.20 Photos of VSR Views (2 of 5)
Figure 11.21 Photos of VSR Views (3 of 5)
Figure 11.22 Photos of VSR Views (4 of 5)
Figure 11.23 Photos of VSR Views (5 of 5)
Figure 11.24A Landscape and Visual Mitigation
Measures (1 of 7)
Figure 11.24B Landscape and Visual Mitigation
Measures (2 of 7)
Figure 11.25A Landscape and Visual Mitigation
Measures (3 of 7)
Figure 11.25B Landscape and Visual Mitigation
Measures (4 of 7)
Figure 11.25C Landscape and Visual Mitigation
Measures (5 of 7)
Figure 11.25D Landscape and Visual Mitigation Measures
(6 of 7)
Figure 11.26 Landscape and Visual Mitigation
Measures (7 of 7)
Figure 11.27 Landscape Resources Impacts in
Construction Phase
Figure 11.28 Residual Landscape Resources
Impacts in Operation Phase
Figure 11.29 Residual Landscape Character
Impacts in Construction Phase
Figure 11.30 Residual Landscape Character
Impacts in Operation Phase
Figure 11.31 Residual Visual Impacts in
Construction Phase
Figure 11.32 Residual Visual Impacts in Operation
Phase
Figure 11.33 Photomontage A – View from Palm
Springs Boulevard, Palm Springs
Figure 11.34 Photomontage B – View from Santa
Monica Avenue, Royal Palms
Figure 11.35 Photomontage C – View from Wo Shang
Wai Village
Figure 11.36 Photomontage D – View from Tam Kon
Chau Village
Figure 11.37 Photomontage E – View from Tam Kon
Chau Road
Figure 11.38
Photomontage F – View from Mai Po Lo Wai
Figure 11.39
Photomontage G – View from Mai Po Nature Reserve
List of Appendices
Appendix A EIA
Study Brief No. ESB - 131/2005
Appendix B-1 Application for Planning Permission at OU(CDWRA) Zoning
Appendix B-2 Construction Programme
Appendix
C Air Quality (Not used)
Appendix H Wetland
Restoration Plan
PREFACE
Wo Shang Wai to the north of Royal Palms and
The planning intention of this location is to provide
incentive for the restoration of degraded wetlands adjoining existing fish
ponds and to encourage the phasing out of sporadic open storage and port
back-up uses on degraded wetland. This
can be achieved through comprehensive residential and/or recreational
development to include wetland restoration area. Development or redevelopment schemes on the
degraded wetlands directly adjoining the existing continuous and contiguous
fish ponds should include wetland restoration and buffer proposals to separate
the development from and minimize its impact on the fish pond areas. Any new building should be located farthest
away from
1.1.1. In March 2005 the Project Proponent, Profit Point Enterprises Limited (Ltd), acquired a development site in Yuen Long at Wo Shang Wai, as shown on Figure 1.1. The site has evolved from tidal flats for fishponds to infilled fishponds during the 1980’s until 1991 almost 15 years before the Project Proponent obtained the site.
1.1.2.
The statutory planning intent
of the site at Wo Shang Wai is to provide an incentive for the restoration of
degraded land through comprehensive residential and/or recreational development
to include a wetland restoration area. It is also the intention of the zoning
plan to encourage the removal of existing sporadic open storage uses on
degraded land in the
1.1.3. The Project, and thus the EIA has also sought ways to minimise impacts to acceptable levels and to harmonise the apparently conflicting concepts of providing residential developments and the adjacent sensitive ecology in the Deep Bay Buffer Zone. In order to put the proposed development into context it is important to note that the site is bounded on three sides by existing residential development and is in an area which has already been disturbed by development as illustrated in Plate 1.1.
1.1.4.
In April 2005 Mott Connell
Ltd (MCL) was commissioned to undertake an EIA for this project. A Project Profile was prepared and submitted
to the Director of Environmental Protection (EPD), and in September 2005 a
Study Brief No. ESB – 131/2005 for the “Proposed Comprehensive Development at
Wo Shang Wai, Yuen Long” was issued. The
EIA has been conducted by MCL with Urbis providing the urban
planning and design, landscape and visual impact assessments. Masterplan and Allied Environmental
Consultant Limited were also engaged to provide statutory planning inputs
and noise impact assessment respectively to the EIA. In addition to the foregoing the Project has
also benefited from ecological inputs from Asia Ecological Consultants (AEC)
and Ecology and Environment, Inc. (E&E). AEC has principally been responsible for
input to the Ecological Assessments and developed the wetland restoration plans
as well as providing suggestions on the management and maintenance aspects. In addition to which, the Wetland Management arrangement have been reviewed by one of Hong Kong’s most experienced wetland
lawyers,
History and
Existing Condition of the Site
Definition of Wetland under the
“Ramsar Convention” is:
· presence of wetland hydrology;
· presence of hydric soil; and/or
· presence of predominantly wetland vegetation.
Rationale of a
Wetland Restoration Scheme with Residential Development
· compensate for the loss of habitat as a result of proposed development;
· provide flood protection to the surrounding developed area;
· provide life support by increasing habitat heterogeneity and thus increasing the biodiversity of the area;
· provide ecological linkages between the site and the CA; set a buffer between the residential development (set-back) and the existing fishponds area to the north of the Project Area; and
· increase the biodiversity of the site and encourage various forms of wildlife.
Statutory Planning
Intention of the Site
Purpose and
Objectives of the Proposed Project
Significance of
the Proposed Project
Scenario without
the Proposed Project
·
noise
impacts arising from construction and operation of the Project to the nearby
village and residential areas;
·
dust
impact arising from construction of the Project to the nearby air sensitive
receivers (ASRs), as there is no on-site sewage treatment plant there is no
sewage odour emanating from this development
·
landscape
and visual impacts during construction and operation of the Project;
·
the
potential water quality impacts caused by site formation, pond draining and
filling, drainage diversion, and any other works activities during
construction; the potential water quality impacts caused by the operation of
the Project;
·
potential
impacts on historical buildings/architectures and monuments;
·
terrestrial
and aquatic ecological impacts, in particular the potential impacts disturbance
and fragmentation to the adjacent recognized sites of conservation importance
including, for example, the Mai Po Nature Reserve, Mai Po Inner Deep Bay Ramsar
Site, Mai Po Village Site of Special Scientific Interest (SSSI), Mai Po Marshes
SSSI, Inner Deep Bay SSSI, Wetland Conservation Area and Wetland Buffer Area
(both were defined under Town Planning Board Guideline TPB PG-No. 12B) and
important habitats such as fishponds and egretries, due to the construction and
operation of the Project;
·
fisheries
impacts during construction and operation of the Project;
·
collection
and disposal of potentially contaminated dredged spoil arising from the
Project; and
·
the
short term and long term management of the proposed wetland restoration within
the site including trust and financial arrangement.
(i)
to
describe the Project and associated works together with the requirements for
carrying out the Project;
(ii)
to
identify and describe elements of community and environment likely to be
affected by the Project and/or likely to cause adverse impacts to the Project,
including both the natural and man-made environment;
(iii)
to
identify and quantify all environmental sensitive receivers, emission sources
and determine the significance of impacts on sensitive receivers and potential
affected uses;
(iv)
to
identify and quantify any potential losses or damage to flora, fauna and
wildlife habitats;
(v)
to
identify any negative impacts on sites of cultural heritage and to propose
measures to mitigate these impacts;
(vi)
to
identify and quantify any potential landscape and visual impacts and to propose
measures to mitigate these impacts;
(vii)
to
propose the provision of infrastructure or mitigation measures so as to
minimise pollution, environmental disturbance and nuisance during construction
and operation of the site;
(viii)
to
identify, predict and evaluate the residual (i.e. after practicable mitigation)
environmental impacts and the cumulative effects expected to arise during the
construction and operation phases of the Project in relation to the sensitive
receivers and potential affected uses;
(ix)
to
identify, assess and specify methods, measures and standards, to be included in
the detailed design, construction and operation of the Project which are
necessary to mitigate these environmental impacts and reducing them to
acceptable levels;
(x)
to
investigate the extent of secondary environmental impacts that may arise from
the proposed mitigation measures and to identify constraints associated with
the mitigation measures recommended in the EIA study, as well as the provision
of any necessary modification;
(xi)
to
identity, within the Assessment Area, any individual project(s) that fall under
Schedule 2 and/or Schedule 3 of the EIA Ordinance; to ascertain whether the
findings of this EIA study have adequately addressed the environmental impacts
of those projects; and where necessary, to identify the outstanding issues that
need to be addressed in any further detailed EIA study; and
(xii)
to
design and specify the environmental monitoring and audit requirements, if
required, to ensure the implementation and the effectiveness of the
environmental protection and pollution control measures adopted.
· Section 2 presents the consideration of alternative layout options and building height profiles as required under the Study Brief, construction methods and sequence works and describes selection of preferred scenario for the Project;
· Section 3 describes the Air Quality Impact Assessment;
· Section 4 describes the issues associated with Noise during and following construction, quantifies the impacts and recommends mitigation measures;
· Section 5 presents the Water Quality Impact Assessment which include the potential problem of biogas on reclamation (pond filling);
· Section 6 describes the Sewerage and Sewage Treatment Implications
· Section 7 presents the Waste Management Implications;
· Section 8 describes the Ecological Impact Assessment which is a combined report using the findings of the baseline survey and describing the development of the mitigation measures for the protection of the ecological resources and habitats. The management package for the wetland restoration in the Project Area is appended to this EIA report;
· Section 9 presents the Fisheries Impact Assessment;
· Section 10 describes the Impact on Cultural Heritage;
· Section 11 presents the Landscape and Visual Impact Assessment (LVIA) which is one of the components of the EIA;
· Section 12 describes the Impact Summary;
· Section 13 provides a summary of the Environmental Outcomes;
· Section 14 presents the Environmental Monitoring and Audit (EM&A) Requirements;
· Section 15 presents an Implementation Schedule; and
· Section 16 presents a summary of the Conclusions of the EIA.
PREFACE
Wo Shang Wai to the north of Royal Palms and
The planning intention of this location is to provide
incentive for the restoration of degraded wetlands adjoining existing fish
ponds and to encourage the phasing out of sporadic open storage and port
back-up uses on degraded wetland. This
can be achieved through comprehensive residential and/or recreational
development to include wetland restoration area. Development or redevelopment schemes on the
degraded wetlands directly adjoining the existing continuous and contiguous
fish ponds should include wetland restoration and buffer proposals to separate
the development from and minimize its impact on the fish pond areas. Any new building should be located farthest
away from
Background
“this zone is intended to
provide incentive for the restoration of degraded wetlands adjoining existing
fishponds through comprehensive residential and/or recreational development to
include wetland restoration area. It is also intended to phase out existing
sporadic open storage and port back up uses on degraded wetlands. Any new
buildings should be located farthest away from
“6.4 the intention of the
WBA is to protect the ecological integrity of the fishponds and wetlands within
the Wetland Conservation Area (WCA) and to prevent development that would have
a negative off-site disturbance impact on the ecological value of fishponds…….
As a substantial number of fishponds with the WBA have already been lost over
time through filling and certain areas have been degraded by the presence of
open storage use, these degraded areas may be considered as target areas to
allow an appropriate level of residential/recreational development so as to
provide an incentive to remove open storage use and/or to restore some of the
fishponds lost.
6.5 Within the WBA, for
development or redevelopment which requires planning permission from the Board,
an ecological impact assessment would also need to be submitted.
Development/redevelopment which may have negative impacts on the ecological
value of the WCA would not be supported by the Board, unless the ecological
impact assessment can demonstrate that the negative impacts could be mitigated
through positive measures. The assessment study should also demonstrate that
the development will not cause net increase in pollution load to
·
Visits to the Project Area and
adjacent areas to characterize the site and the Assessment Area. This included the definition of the Project
Area, its relationship with its nearest neighbours including the adjacent Royal
Palms and
· The history of the site was ascertained through examination of site records and aerial photographs.
· The planning status was confirmed.
· The constraints and opportunities for development were considered and compiled as a set of planning principles as illustrated in the “bubble diagram” (see Figure 2.1).
· Initial ecological baseline surveys were carried out.
· Initial environmental appraisals were conducted.
History
Statutory
Planning Intention for the Project Area
Plot Ratio |
0.4 |
|
6 storey including car park |
Layout Arrangement |
Building farthest away from |
Maximum GFA |
82,800m2 |
The Need for the
Project
“to allow an appropriate
level of residential/recreational development so as to provide an incentive to
remove the open storage use and/or to restore some of the fishponds lost.”
Purpose and
Objectives for the Proposed Project
“Development proposals to
restore lost fishponds or to replace existing undesirable uses by wetland
habitats are encouraged.”
(a)
To determine the function of the existing habitats,
assess the ecological impact of development and provide a comprehensive
proposal which will enhance the ecological function of the site and contribute
to the overall value of the Wetland Buffer Area and the Wetland Conservation
Area.
(b)
To provide a viable high quality residential
development in harmony with the conservation objectives of the zoning.
(c)
To provide for an increase in the wetland function
provided by the site over the existing degraded situation.
(d)
To provide a comprehensive residential development
with a plot ratio of 0.4 so as to provide support for the creation of a
sustainable managed wetland.
(e)
To ensure that the form and height of the residential
development is compatible with the general character of the area within the
flexibility provided by the 6 storey height limit.
(f)
To establish clear conservation objectives which are
compatible with the function that this wetland will provide in the
(g)
To provide an effective wetland and visual buffer to
separate the residential part of the development from the “CA” zone to the
north.
The Existing
Site Conditions
The Surrounding
Conditions
Introduction
Working Up the
Alternatives from Development Principles
Wetland Restoration
“Development proposals to
restore lost fishponds or to replace existing undesirable uses by wetland
habitats…”
and the definition of wetland habitat adopted by the TPB from Ramsar is :
“any area of marsh, fen, peatland or water whether natural or
artificial, permanent or temporary, with water that is static or flowing,
fresh, brackish or salt, including any area of marine water the depth of which
at low tide does not exceed 6 metres, in which plants and/or animals live.”
Buffering from Existing Ponds in the North
Building Form and Location
Access
to the Project Area
Parking Provision for Residential Development
No Community Facility Needed
Site Formation Level Relative to Water Level
Adjacent Site within the same OU(CDWRA)
No
Net Increase in Pollution Load to
Avoidance of Key Ecological Impact
Adjacent Ponds Wo
Water Supply to Wetland Features
Flight Path of Birds
Existing and Proposed Hydrology
Nuisance from Existing Open Storage in the Northeast
Sustainable Development
Continuous Public Involvement (CPI)
Consideration of
‘No-development’ Option
Compatible
Development
Development
Criteria for Option Consideration
Table 2‑1 Development Criteria
Alternative Factors Considered |
Reason for
Consideration |
Wetland Restoration
Area (WRA) |
The size, layout, form of the compensation differs between the
options (refer to Section 8). |
Buffering between
Development and Existing Ponds to the North |
Minimum distance between residential developments and CA vary (refer to Section 8) |
Building Form and
Location |
Different building heights or mixes or layouts vary and affect
performance of options (refer to Section 11) |
Continuous Public
Involvement (CPI) |
CPI was used in the development of layouts, or in the modification
of layouts following input from CPI
(refer to Section 1and 11) |
Avoidance of Key
Ecological Impacts |
Extent and variety of compensation is a key feature as is
mitigation during construction (refer to Section 8) |
Adjacent Ponds |
Factors include the continuity of water features |
Water Supply to
Wetland Features |
Source of water varies |
Flight Path of
Birds |
Use of flight path data to ascertain impacts of development on
avifauna (refer to Section 8 and Figure 8.4) |
Nuisance from
Existing Open Storage in the Northeast |
Interface issues |
Sustainable
Development |
Opportunities for sustainable development or green building designs |
Integrated
Wetland Concept Option
Transitional
Wetland Concept Options
Refined
Preferred Option
Summary of
Alternatives Considered
Summary of
Alternative Options Considered
Table 2‑2 Summary of Alternative Options Considered
Development Criteria |
Integrated Option |
Medium Rise Option |
Low Rise Option |
|||
A |
B |
C |
D |
E |
F |
|
Wetland
Restoration Area (WRA) (ha) |
3.4 |
3.4 |
4.3 |
4.0 |
4.0 |
4.7 |
Buffering
between Development and Existing Ponds to the North (m) |
little
buffer distance between residential developments and the CA. |
provided
by discrete WRA |
increased
buffer zone especially in the northwest of the Site |
|||
Building
Form and Location |
all
2.5/3 storeys |
all 6 storeys |
hybrid
up to 6 storeys |
hybrid 2 and 4 storeys |
all
2.5/3 storeys |
hybrid 2.5/3 and 4 storeys |
Continuous
Public Involvement (CPI) |
discussed
as part of CPI, not forward option |
discussed
as part of CPI |
discussed
as part of CPI |
discussed
as part of CPI used to develop option F |
discussed
as part of CPI |
discussed
as part of CPI process and subsequently
further refined following further CPI
process |
Avoidance
of Key Ecological Impact |
extensive
mitigation required during formation of wetland restoration area |
minimisation
and mitigation measures adopted |
avoidance,
minimisation and mitigation principles adopted |
|||
Adjacent
Pond |
fragmented development |
continuity
provided especially with the adjacent fishponds |
||||
Water
Supply to Waterscape |
initially
rainwater plus supplies of “top up” water such as tap water using fixed pumps
and a network of pipes |
rainwater
only with no fixed pumps |
||||
Flight
Path of Birds |
consideration
of birds with medium flight height but no buffer provided at the northern
portion |
some of
the frequent flight paths may be affected by the building heights and
increase disturbance |
buffer
zone provided but limited width at the northwest of the Site where there are
records of frequent flight paths |
consideration
of frequent birds flight path at low height with appropriate buffer width
especially increased at northwest part of the Site |
||
Nuisance
from Existing Open Storage in the Northeast |
reduced,
but interface with low-rise residential units |
impacts further
minimized by locating non-noisy private facilities in this area. |
||||
Sustainable
Development |
All have
opportunities to incorporate sustainable development and green building
design. However F has most sustainable
solution as the WRA is wholly sustained by rainwater and not fed by
alternative sources and requires no energy to maintain its functions. |
Forms of
construction
Site
Characteristics
Site Formation
Work
Building
Construction Work
Wetland
Restoration
Sequence of
Works
PREFACE
Wo Shang Wai to the north of Royal Palms and
The planning intention of this location is to provide incentive for
the restoration of degraded wetlands adjoining existing fish ponds and to
encourage the phasing out of sporadic open storage and port back-up uses on
degraded wetland. This can be achieved
through comprehensive residential and/or recreational development to include
wetland restoration area. Development or
redevelopment schemes on the degraded wetlands directly adjoining the existing
continuous and contiguous fish ponds should include wetland restoration and
buffer proposals to separate the development from and minimize its impact on
the fish pond areas. Any new building
should be located farthest away from
· Hong Kong Air Pollution Control Ordinance;
· Air Pollution Control (Construction Dust) Regulation; and
· Environmental Impact Assessment Ordinance and Technical Memorandum on Environmental Impact Assessment Process.
Hong Kong Air Pollution Control Ordinance
Table 3‑1 Hong Kong Air Quality Objectives (mg/m3)(i)
Pollutant |
1 Hour (ii) |
8 Hours (iii) |
24 Hours (iii) |
3 Months (iv) |
1 Year (iv) |
|
800 |
|
350 |
|
80 |
Total Suspended Particulates |
500(vii) |
|
260 |
|
80 |
Respirable Suspended Particulates (v) |
|
|
180 |
|
55 |
Carbon Monoxide |
30,000 |
10,000 |
|
|
|
Nitrogen Dioxide |
300 |
|
150 |
|
80 |
Photochemical Oxidants (as ozone) (vi) |
240 |
|
|
|
|
Lead |
|
|
|
1.5 |
|
|
|
|
|
|
|
Notes:
(i) Measured at 298K(25 oC) and 101.325 kPa (one atmosphere).
(ii) Not to be exceeded more than three times per year.
(iii) Not to be exceeded more than once per year.
(iv) Yearly and three monthly figures calculated as arithmetic means.
(v) Respirable suspended particulates means suspended particles in air with nominal aerodynamic diameter of 10 micrometres and smaller.
(vi) Photochemical oxidants are determined by measurement of ozone only.
(vii) This is not an AQO but a criterion for construction dust impact assessment under Annex 4 of the Technical Memorandum on Environmental Impact Assessment Process.
Air Pollution Control (Construction Dust) Regulation
Environmental Impact Assessment Ordinance and Technical Memorandum
on Environmental Impact Assessment Process
Construction Phase
Operational Phase
Traffic Forecast
Table 3‑2 Traffic Forecast in Year 2027
Peak
Hour Vehicle flows (veh/hr) |
|
|
Project
Access Road |
|
||||
AM |
PM |
AM |
PM |
AM |
PM |
AM |
PM |
|
Motor
cycles |
51 |
82 |
6 |
8 |
2 |
3 |
4 |
6 |
Private
Car |
2533 |
2631 |
226 |
240 |
88 |
89 |
162 |
213 |
Taxi |
243 |
212 |
20 |
18 |
8 |
7 |
15 |
16 |
Private
light buses |
30 |
35 |
16 |
21 |
0 |
0 |
19 |
29 |
Public
light buses |
148 |
114 |
81 |
68 |
0 |
0 |
95 |
96 |
LGV |
846 |
984 |
68 |
46 |
18 |
20 |
59 |
38 |
HGV |
1454 |
1482 |
105 |
88 |
2 |
1 |
121 |
122 |
Non-franchised
buses |
203 |
271 |
11 |
8 |
3 |
3 |
9 |
8 |
Single
Deck Franchised Buses |
13 |
15 |
0 |
0 |
0 |
0 |
0 |
0 |
Double
Deck Franchised Buses |
81 |
105 |
3 |
2 |
0 |
0 |
3 |
3 |
Total |
5602 |
5931 |
535 |
499 |
121 |
122 |
487 |
530 |
Table 3‑3 Air Quality at Yuen Long Monitoring Station in Past Five Years
Pollutant |
5-year Annual Average, mg/m3 |
Nitrogen Dioxide |
60 |
Total Suspended Particulates |
100 |
Respirable Suspended Particulates |
62 |
Source: Adapted from EPD’s
Air Quality in
Table 3‑4 Locations of Representative Air Sensitive Receiver
ID |
Receiver
Description |
Usage |
Construction
Phase |
Operational
Phase |
Distance to the nearest Emission Sources* (in
metres) |
ASR1 |
Royal Palms |
Residential |
ü |
ü |
approx
|
ASR2A & ASR 2B |
|
Residential |
ü |
ü |
approx
|
ASR3 |
Wo Shang Wai |
Residential |
ü |
ü |
approx
|
ASR4 |
Village House of |
Residential |
ü |
ü |
approx
15m |
ASR5 |
Proposed Comprehensive Development at Wo
Shang Wai (Project Area) |
Residential |
û |
ü |
approx 5m (local road) more
than 230m (major road) |
* Emission sources include construction activities in the construction phase and vehicular emissions from road traffic during operation
Construction Phase
Identification of Potential Impacts
Evaluation of Impacts
· all malodorous excavated material should be placed as far as possible from any ASRs;
· the stockpiled malodorous materials should be removed from site as soon as possible; and
· the stockpiled malodorous materials should be covered entirely by plastic tarpaulin sheets.
Operational Phase
Identification of Potential Impacts
Evaluation of Impacts
· use of effective dust screens, sheeting or netting to be provided to enclose dry scaffolding which may be provided from the ground floor level of the building or if a canopy is provided at the first floor level, from the first floor level, up to the highest level (maximum four floors for this Project) of the scaffolding where scaffolding is erected around the perimeter of a building under construction;
· dump trucks for material transport should be totally enclosed using impervious sheeting;
· any excavated dusty materials or stockpile of dusty materials should be covered entirely by impervious sheeting or sprayed with water so as to maintain the entire surface wet, and recovered or backfilled or reinstated within 24 hours of the excavation or unloading;
· dusty materials remaining after a stockpile is removed should be wetted with water;
· the area where vehicle washing takes place and the section of the road between the washing facilities and the exit point should be paved with e.g. concrete, bituminous materials or hardcore or similar;
·
the portion of road leading
only to a construction site that is within
· stockpile of dusty materials to be either covered entirely by impervious sheeting, placed in an area sheltered on the top and the 3 sides; or sprayed with water so as to maintain the entire surface wet;
· all dusty materials to be sprayed with water prior to any loading, unloading or transfer operation so as to maintain the dusty material wet;
· vehicle speed to be limited to 10 kph except on completed access roads;
· every vehicle should be washed to remove any dusty materials from its body and wheels before leaving the construction sites;
· the load of dusty materials carried by vehicle leaving a construction site should be covered entirely by clean impervious sheeting to ensure that the dusty materials do not leak from the vehicle;
· the working area of excavation should be sprayed with water immediately before, during and immediately after (as necessary) the operations so as to maintain the entire surface wet;
· all malodorous excavated material should be placed as far as possible from any ASRs;
· the stockpiled malodorous materials should be removed from site as soon as possible; and
· the stockpiled malodorous materials should be covered entirely by plastic tarpaulin sheets.
PREFACE
Wo Shang Wai to the north of Royal Palms and
The planning intention of this location is to provide
incentive for the restoration of degraded wetlands adjoining existing fish
ponds and to encourage the phasing out of sporadic open storage and port
back-up uses on degraded wetland. This
can be achieved through comprehensive residential and/or recreational
development to include wetland restoration area. Development or redevelopment schemes on the
degraded wetlands directly adjoining the existing continuous and contiguous
fish ponds should include wetland restoration and buffer proposals to separate
the development from and minimize its impact on the fish pond areas. Any new building should be located farthest
away from
Environmental Impact Assessment Ordinances, Cap. 499 S. 16
Table 4‑1 Relevant Noise Standards for Planning Purposes
Noise Sources Noise Standards Common
Uses |
Road
Traffic Noise Peak
Hour Traffic L10
(1hour) dB(A) |
Fixed
Noise Sources |
|
All
domestic premises including temporary housing accommodation |
70 |
(a)
5 dB(A) below the appropriate Acceptable Noise Levels (ANL) shown in Table 3
of the Technical Memorandum for the Assessment of Noise from Places Other
than Domestic Premises, Public Places or Construction Sites, or (b)
the prevailing background noise levels (For quiet areas with level 5 dB(A)
below the ANL) |
|
Educational
institutions including kindergartens, nurseries and all others where unaided
voice communication is required |
65 |
Notes: (i) The above standards apply to uses
which rely on opened windows for ventilation
(ii)
The
above standards should be viewed as the maximum permissible noise levels
assessed at 1m from the external façade
Table 4‑2 Noise Standards for Daytime Construction Activities
Noise Sources Noise Standards Uses |
0700 to 1900 hours on any day not being a Sunday or general holiday Leq (30 mins) dB(A) |
1900 to 0700 hours or any time on Sundays or general holiday |
·
All
domestic premises including temporary housing accommodation |
75 |
(See
Note iii) |
·
Educational
institutions including kindergartens, nurseries and all others where unaided
voice communication is required |
70 65 (During
examinations) |
Notes: (i) The above standards apply to uses which
rely on opened windows for ventilation.
(ii) The
above standards shall be viewed as the maximum permissible noise levels
assessed at
(iii) The
criteria laid down in the relevant technical memoranda under the Noise Control
Ordinance for designated areas and construction works other than percussive
piling may be used for planning purpose.
A Construction Noise Permit (CNP) shall be required for the carrying out
of the construction work during the period.
Noise Control Ordinance,
Cap. 400
Table 4‑3 Area Sensitivity Ratings (ASRs)
Type
of area containing the NSR |
Not Affected 1 |
Indirectly Affected 2 |
Directly Affected 3 |
(i) Rural area, including country parks
or village type developments |
A |
B |
B |
(ii) Low density residential area
consisting of low-rise or isolated high-rise developments |
A |
B |
C |
(iii) Urban area |
B |
C |
C |
(iv) Area other than those above |
B |
B |
C |
1 Not
Affected - NSR is located such that the noise generated by the influencing
factors (IF) 4 is not
noticeable.
2 Indirectly
Affected - NSR is located such that the noise generated by the influencing
factors while noticeable, is not a dominant feature of the noise environment.
3 Directly
Affected - NSR is located such that the noise generated by the IF is readily
noticeable and is a dominant feature of the noise environment.
4 IFs
are defined as industrial areas, major roads, or the area within the boundary
of
Table 4‑4 Acceptable Noise Levels (ANLs)
|
Area Sensitivity Rating |
||
Time
Period |
A |
B |
C |
Day (0700 to 1900 hours) |
60 |
65 |
70 |
Evening (1900 to 2300 hours) |
|||
Night (2300 to 0700 hours) |
50 |
55 |
60 |
Table 4‑5 Measured Noise Levels
ID |
Location
Description |
Date |
Time Period |
Measured Noise Level, Leq(15mins) dB(A) |
Corrected Façade Noise Level at planned
NSRs, Leq(15mins)
dB(A) |
A |
Northern side of the subject site –
dominant noise source is activities at fishpond and natural environment1 |
15 Feb
2006 |
1035 -
1050 |
44 |
47 |
B |
Western side of the subject site – dominant
noise source is from the domestic premises (which located approx. |
15 Feb
2006 |
1135 -
1150 |
46 |
49 |
C |
Southern side of the subject site –
dominant noise source is natural environment1 |
15 Feb
2006 |
1205 -
1220 |
43 |
46 |
D |
Near entrance of the subject site –
dominant noise sources are domestic premises, open storage area and vehicles1 |
15 Feb
2006 |
1250 -
1305 |
50 |
53 |
E |
Sewage Treatment Plant within Royal Palms1 |
19 Mar
2007 |
1030 -
1045 |
56 |
N/A |
F |
Entrance of the existing open storage site1 |
19 – 20
Apr 2007 |
24 hours |
46 – 63 |
N/A |
G |
Outside southern boundary of the site –
dominant noise source was insect2 |
19 – 20
Sep 2007 |
2345 -
0015 |
49 |
N/A |
1
Noise measurement undertaken by Mott Connell Ltd.
2
Noise measurement undertaken by Allied Environmental
Consultants Ltd.
Construction Phase
·
Phases
A and B – Wetland restoration
·
Phases
C, D, E and F – House construction
Operational Phase
-
A/YL-MP/061
– Application for “Temporary Car, Lorry and Container Trailer/Tractor Park for
a Period of 12 Months”
-
A/YL-MP/021
– Application for “Temporary Container Storage, Container Repair Workshop with
Ancillary Office and Canteen for a Period of 12 Months”
Table 4‑6 Identified Noise Sensitive Receivers within
Use |
Designation |
Residential |
|
Residential |
Royal Palms |
Residential |
Wo |
Educational Institute |
St |
Residential |
|
Residential |
|
Table 4‑7 Horizontal Distances between the Assessment Points of Representative NSRs and the Notional Centre of Each Phase for Construction Stage
NSR
ID |
Use |
Building
Name |
No.
of storeys |
Horizontal
distance between NSRs and the notional centre of each phase, m |
|||||
A |
B |
C |
D |
E |
F |
||||
1 |
Residential |
House No. 5, Camelia Path, |
3 |
104 |
364 |
220 |
442 |
66 |
338 |
1a |
Residential |
House No. 5, Cherry Path, |
3 |
76 |
338 |
214 |
424 |
96 |
358 |
2 |
Residential |
House No. 1, |
3 |
272 |
488 |
254 |
484 |
88 |
256 |
3 |
Residential |
House No. 17, Wo |
3 |
296 |
406 |
176 |
336 |
150 |
120 |
4 |
Residential |
House No. 25, Narcissus Path, Royal Palms |
3 |
330 |
364 |
180 |
282 |
234 |
58 |
4a |
Residential |
House No. 61, Narcissus Path, Royal Palms |
3 |
418 |
396 |
256 |
280 |
344 |
84 |
4b |
Residential |
House No. 1, Narcissus Path, Royal Palms |
3 |
278 |
366 |
148 |
294 |
156 |
76 |
5 |
Residential |
House No. 1, |
3 |
370 |
208 |
224 |
84 |
408 |
110 |
6 |
Residential |
House No. 1, |
3 |
400 |
288 |
226 |
180 |
398 |
94 |
7 |
Residential |
|
3 |
652 |
394 |
548 |
268 |
740 |
452 |
8 |
Residential |
House A1, |
3 |
800 |
608 |
644 |
414 |
816 |
514 |
9 |
Educational Institute |
St |
1 |
412 |
466 |
272 |
376 |
280 |
156 |
10 |
Residential (Planned) |
|
3 |
578 |
360 |
448 |
168 |
636 |
340 |
Table 4‑8 Assessment Points of the Representative NSRs for Operational Stage
NSR
ID |
Location |
No.
of storeys |
Height,
mPD |
A |
2.5/3 Storey house (near Project entrance, façade
facing |
3 |
1/F – 7.2mPD 2/F – 10.2mPD 3/F – 13.2mPD |
A |
2.5/3 Storey house (near Project entrance, façade
facing Project access road) |
3 |
|
B |
2.5/3 Storey house (façade facing Project access
road) |
3 |
|
C |
4 Storey duplex-on-duplex (façade facing |
4 |
1/F – 7.2mPD 2/F – 10.2mPD 3/F – 13.2mPD 4/F – 16.6mPD |
Construction
Phase
Table 4‑9 Inventory of Noise Sources at Each Phase – During Construction
Construction Stage |
Powered Mechanical Equipment |
TM Ref. |
Quantity |
SWL/unit, dB(A) |
Wetland Restoration
(only at Phases A and B) |
Breaker, excavator
mounted (pneumatic) |
CNP027 |
1 |
122 |
Excavator |
CNP081 |
2 |
112 |
|
Roller,
vibratory |
CNP186 |
2 |
108 |
|
Bulldozer |
CNP030 |
2 |
115 |
|
Generator,
standard |
CNP101 |
1 |
108 |
|
Dump
Truck |
CNP067 |
1 |
117 |
|
Lorry, with
crane, gross vehicle weight > 38 ton |
[1] |
1 |
112 |
|
Breaker,
hand-held, mass > 35 kg |
CNP026 |
1 |
114 |
|
Site Formation and Excavation |
Breaker, excavator mounted (pneumatic) |
CNP027 |
1 |
122 |
Excavator |
CNP081 |
2 |
112 |
|
Roller, vibratory |
CNP186 |
3 |
108 |
|
Bulldozer |
CNP030 |
3 |
115 |
|
Generator, standard |
CNP101 |
2 |
108 |
|
Dump
Truck |
CNP067 |
3 [2] |
117 |
|
Installation of
Band Drains |
Band drains
installation machine (Compactor, vibratory) |
CNP050 |
6 |
105 |
Piling |
Continuous flight
auger (CFA) piles (Piling, earth auger) |
CNP167 |
4 |
114 |
Generator, standard |
CNP101 |
2 |
108 |
|
Bar bender and
cutter (electric) |
CNP021 |
2 |
90 |
|
Concrete pump |
CNP047 |
2 |
109 |
|
Concrete lorry
mixer |
CNP044 |
3 |
109 |
|
Pile Cap |
Bar bender and
cutter (electric) |
CNP021 |
2 |
90 |
Generator, standard |
CNP101 |
2 |
108 |
|
Lorry |
CNP141 |
3 |
112 |
|
Concreting |
Crane, |
CNP048 |
1 |
112 |
Concrete lorry
mixer |
CNP044 |
3 |
109 |
|
Compactor,
vibratory |
CNP050 |
3 |
105 |
|
Superstructure |
Air Compressor, air
flow Air flow >10 m3/min and < = 30 m3/min |
CNP002 |
4 |
102 |
Bar bender and
cutter (electric) |
CNP021 |
3 |
90 |
|
Concrete lorry
mixer |
CNP044 |
5 |
109 |
|
Concrete pump |
CNP047 |
5 |
109 |
|
Crane, tower (electric) |
CNP049 |
2 |
95 |
|
Drill/ grinder,
hand-held (electric) |
CNP065 |
5 |
98 |
|
Excavator |
CNP081 |
3 |
112 |
|
Generator, standard |
CNP101 |
4 |
108 |
|
Lorry |
CNP141 |
4 |
112 |
|
Poker, vibratory,
hand-held |
CNP170 |
6 |
113 |
|
Saw, circular, wood |
CNP201 |
6 |
108 |
|
Water pump
(electric) |
CNP281 |
6 |
88 |
|
Water pump,
submersible (electric) |
CNP283 |
6 |
85 |
|
Haul Road |
Dump Truck (Moving
along |
CNP067 |
15 |
117 |
Note:
[1] Details extracted from EPD website: http://www.epd.gov.hk/epd/english/application_for_licences/guidance/files/OtherSWLe.pdf
[2] The number of dump trucks stationary at Phase F is
4 during site formation stage.
LAeq = SWL – 33 + 10Log10Q – 10Log10V –
10Log10d
Where,
SWL is the sound power level of dump truck (117dB(A))
Q is the number of vehicles per hour (15 veh/hr)
V is the average speed (
d is the distance of receiver
position from the centre of the site access road / haul road (m)
Operational
Phase
(a) Fixed Noise Sources
Table 4‑10 Summary of Open Storage Site Noise Measurement Results at Point F
Date |
Measurement
Duration |
Maximum
Measured Noise Level, Leq(30mins) |
Calculated
Sound Power Level, dB(A) |
19-20 April 2007 |
24 hours |
Day and Evening (0700-2300) : 63 |
81 |
Night (2300 – 0700) : 54* |
71 |
* Maximum measured noise level for night time period was recorded at 2300 – 2330
(b) Noise
from Road Traffic
Table 4‑11 Traffic Flow Forecast of Existing and Future Road Networks (Year 2027)
Road Name |
Peak Traffic Flow (Veh/hr) |
% of
Heavy vehicles |
Road Speed (km/hr) |
Road Surface Type |
||
AM |
PM |
AM |
PM |
|||
|
5602 |
5931 |
49.5 |
50.7 |
100 |
Pervious |
|
487 |
530 |
62.8 |
55.8 |
50 |
Bitumen |
|
535 |
499 |
53.1 |
46.7 |
50 |
Bitumen |
Project Access Road |
121 |
122 |
19.0 |
19.7 |
50 |
Bitumen |
Note:
The traffic flow of Project Access Road is for the planned site only.
1Department of
Construction
Phase
Table 4‑12 Maximum Predicted Unmitigated Construction Noise Levels at Representative NSRs
NSR |
Maximum
Predicted Unmitigated Construction Noise Level, Leq (30mins),
dB(A) |
1 |
87 |
1a |
86 |
2 |
85
|
3 |
85 |
4 |
88
|
|
85
|
4b |
87 |
5 |
87 |
6 |
85 |
7 |
77 |
8 |
75 |
9 |
81 |
10 |
82 |
Note:
Bold figures denote exceedance of
relevant noise criteria.
Operational
Phase
(a) Fixed
Noise Sources
(b) Noise
from Road Traffic
Table 4‑13 Predicted Noise Levels at Representative NSRs
NSR ID |
Description |
Floor |
Height, mPD |
Predicted Noise Levels, L10(1hour)
dB(A) |
A |
2.5/3
Storey house (near site entrance, façade facing |
1/F |
7.2 |
68 |
2/F |
10.2 |
68 |
||
3/F |
13.2 |
68 |
||
A |
2.5/3
Storey house (near site entrance, façade facing |
1/F |
7.2 |
69 |
2/F |
10.2 |
69 |
||
3/F |
13.2 |
69 |
||
B |
2.5/3
Storey house (façade facing Project Access Road) |
1/F |
7.2 |
69 |
2/F |
10.2 |
69 |
||
3/F |
13.2 |
68 |
||
C |
4
Storey duplex-on-duplex (façade facing |
1/F |
7.2 |
63 |
2/F |
10.2 |
63 |
||
3/F |
13.2 |
64 |
||
4/F |
16.6 |
65 |
Construction
Phase
Table 4‑14 QPME to be used at the Construction Site
QPME |
Reference |
SWL (dB(A)) |
Excavator |
Kato HD-512E |
104 |
Crane, |
|
101 |
Lorry |
BS 5228: C3/59 |
105 |
Pneumatic
Breaker |
BS 5228: C3/101 |
113 |
Dump Truck (5.5
tonne < Gross vehicle weight ≦ 38 tonne) |
Note [1] |
105 |
Roller,
vibratory |
Komatsu SW750, 77kW |
104 |
Bulldozer |
Komatsu modelled D |
102 |
Generator,
standard |
Atlas Copco QAS 300 |
99 |
Continuous
flight auger (CFA) piles (Piling, earth auger) |
BS 5228: C4/41 |
112 |
Concrete pump |
BS 5228: C6/36 |
106 |
Concrete lorry
mixer |
BS 5228: C6/35 |
100 |
Air Compressor,
air flow Air flow ≦ |
CNP001 |
100 |
Poker,
vibratory, hand-held |
BS 5228: C6/40 |
98 |
Saw, circular,
wood |
BS 5228: C7/78 |
106 |
Note [1] – Details extracted from EPD
website: http://www.epd.gov.hk/epd/english/application_for_licences/guidance/files/OtherSWLe.pdf
Table 4‑15 Maximum Predicted Mitigated Construction Noise Levels at Representative NSRs with the use of QPME
NSR |
Maximum
Predicted Mitigated Construction Noise Level, Leq (30mins), dB(A) |
1 |
81
|
1a |
78
|
2 |
79
|
3 |
78 |
4 |
83 |
|
80 |
4b |
81 |
5 |
81 |
6 |
79 |
7 |
70 |
8 |
68 |
9 |
75 |
10 |
74 |
Note:
Bold figures denote exceedance of
relevant noise criteria.
Table 4‑16 Maximum Predicted Mitigated Construction Noise Levels at Representative NSRs with the uses of QPME, Noise Barriers and Site Hoardings
NSR |
Maximum
Predicted Mitigated Construction Noise Level, Leq (30mins), dB(A) |
1 |
74 |
1a |
73 |
2 |
73 |
3 |
74 |
4 |
75 |
|
73 |
4b |
75 |
5 |
73 |
6 |
73 |
7 |
70 |
8 |
68 |
9 |
70 |
10 |
74 |
· Scheduling of work - The Contractor will be required to determine the number and type of construction equipment taking into account the use of quiet plant while devising a feasible work programme.
· Sitting of facilities - This includes avoiding simultaneous operation of noisy equipment; retaining existing features that can act as a noise barrier until the last phase; and erecting, as early as possible, any new structures which will have the effect of screening noise sources. Such screens can reduce noise levels by 15dB(A) or more. Noisy equipment should always be sited as far as possible from noise sensitive receivers. Consideration should also be given to the use of structures such as site offices and stores as noise barriers.
· Use of quiet Powered Mechanical Equipment (QPME) - The contractor should be requested, as far as possible, to use quiet PME, which has a lower SWL compared to one specified in GW–TM. This is one of the most effective measures to reduce noise emission at source and is increasingly practicable because of the availability of quiet equipment in the market.
· only well-maintained plant should be operated on-site and the plant should be serviced regularly during the construction programme;
· machines and plant that may be intermittent in use should be shut down between work periods or should be throttled back to a minimum;
· plant known to emit noise strongly in one direction, should, where possible, be oriented so that the noise is directed away from nearby NSRs;
· silencers or mufflers on construction equipment should be utilised and should be properly maintained during the construction period;
· mobile plant should be sited as far away from NSRs as possible;
· material stockpiles and other structures should be effectively utilised, where practicable, to screen noise from on-site construction activities; and
· The Contractor shall at all times comply with all current statutory environmental legislation.
Operational
Phase
Construction
Phase
Operational
Phase
PREFACE
Wo Shang Wai to the north of Royal Palms and
The planning intention of this location is to provide
incentive for the restoration of degraded wetlands adjoining existing fish
ponds and to encourage the phasing out of sporadic open storage and port back-up
uses on degraded wetland. This can be
achieved through comprehensive residential and/or recreational development to
include wetland restoration area.
Development or redevelopment schemes on the degraded wetlands directly
adjoining the existing continuous and contiguous fish ponds should include
wetland restoration and buffer proposals to separate the development from and
minimize its impact on the fish pond areas.
Any new building should be located farthest away from
·
Water Pollution Control Ordinance (WPCO) (Cap.
358);
·
Technical Memorandum for Effluents Discharged
into Drainage and Sewerage Systems, Inland and Coastal Waters (WPCO, Cap. 358,
S.21);
·
Town Planning Board Guidelines No. 12B;
·
Environmental Impact Assessment Ordinance (Cap.
499., S.16), Technical Memorandum on Environmental Impact Assessment Process
(EIAO-TM), Annexes 6 and 14;
·
Technical Memorandum for Effluent Discharges;
·
A Guide to Water Pollution Control Ordinance;
·
River Water Quality in
·
Water Pollution Control Ordinance
Technical Memorandum for Effluents Discharged into Drainage
and Sewerage Systems, Inland and Coastal Waters
Table 5‑1 Standards for effluents discharged into Group C inland waters (All units in mg/L unless otherwise stated; all figures are upper limits unless otherwise indicated)
Flow rate (m3/day) Determinand |
≤ 100 |
> 100 and ≤ 500 |
> 500 and ≤ 1000 |
> 1000 and ≤ 2000 |
pH (pH units) |
6-9 |
6-9 |
6-9 |
6-9 |
Temperature (°C) |
30 |
30 |
30 |
30 |
Colour (lovibond
units) ( |
1 |
1 |
1 |
1 |
Suspended solids |
20 |
10 |
10 |
5 |
BOD |
20 |
15 |
10 |
5 |
COD |
80 |
60 |
40 |
20 |
Oil & Grease |
1 |
1 |
1 |
1 |
Boron |
10 |
5 |
4 |
2 |
Barium |
1 |
1 |
1 |
0.5 |
Iron |
0.5 |
0.4 |
0.3 |
0.2 |
Mercury |
0.001 |
0.001 |
0.001 |
0.001 |
Cadmium |
0.001 |
0.001 |
0.001 |
0.001 |
Silver |
0.1 |
0.1 |
0.1 |
0.1 |
Copper |
0.1 |
0.1 |
0.05 |
0.05 |
Selenium |
0.1 |
0.1 |
0.05 |
0.05 |
Lead |
0.2 |
0.2 |
0.2 |
0.1 |
Nickel |
0.2 |
0.2 |
0.2 |
0.1 |
Other toxic metals
individually |
0.5 |
0.4 |
0.3 |
0.2 |
Total toxic metals |
0.5 |
0.4 |
0.3 |
0.2 |
Cyanide |
0.05 |
0.05 |
0.05 |
0.01 |
Phenols |
0.1 |
0.1 |
0.1 |
0.1 |
Sulphide |
0.2 |
0.2 |
0.2 |
0.1 |
Fluoride |
10 |
7 |
5 |
4 |
Sulphate |
800 |
600 |
400 |
200 |
Chloride |
1000 |
1000 |
1000 |
1000 |
Total phosphorus |
10 |
10 |
8 |
8 |
Ammonia nitrogen |
2 |
2 |
2 |
1 |
Nitrate + nitrite
nitrogen |
30 |
30 |
20 |
20 |
Surfactants (total) |
2 |
2 |
2 |
1 |
E. coli (count/100ml) |
1000 |
1000 |
1000 |
1000 |
Note: Table abstract from Technical
Memorandum on Effluent Standards (EPD, 1991).
Table 5‑2 Standards for effluents discharged into Group D inland waters (All units in mg/L unless otherwise stated; all figures are upper limits unless otherwise indicated)
Flow rate (m3/day) Determinand |
£ 200 |
> 200 and £ 400 |
> 400 and £ 600 |
> 600 and £ 800 |
> 800 and £ 1000 |
> 1000 and £ 1500 |
> 1500 and £ 2000 |
> 2000 and £ 3000 |
pH (pH units) |
6-10 |
6-10 |
6-10 |
6-10 |
6-10 |
6-10 |
6-10 |
6-10 |
Temperature (oC) |
30 |
30 |
30 |
30 |
30 |
30 |
30 |
30 |
Colour (lovibond units) ( |
1 |
1 |
1 |
1 |
1 |
1 |
1 |
1 |
Suspended solids |
30 |
30 |
30 |
30 |
30 |
30 |
30 |
30 |
BOD |
20 |
20 |
20 |
20 |
20 |
20 |
20 |
20 |
COD |
80 |
80 |
80 |
80 |
80 |
80 |
80 |
80 |
Oil & Grease |
10 |
10 |
10 |
10 |
10 |
10 |
10 |
10 |
Iron |
10 |
8 |
7 |
5 |
4 |
2.7 |
2 |
1.3 |
Boron |
5 |
4 |
3.5 |
2.5 |
2 |
1.5 |
1 |
0.7 |
Barium |
5 |
4 |
3.5 |
2.5 |
2 |
1.5 |
1 |
0.7 |
Mercury |
0.1 |
0.05 |
0.001 |
0.001 |
0.001 |
0.001 |
0.001 |
0.001 |
Cadmium |
0.1 |
0.05 |
0.001 |
0.001 |
0.001 |
0.001 |
0.001 |
0.001 |
Other toxic metals individually |
1 |
1 |
0.8 |
0.8 |
0.5 |
0.5 |
0.2 |
0.2 |
Total toxic metals |
2 |
2 |
1.6 |
1.6 |
1 |
1 |
0.5 |
0.4 |
Cyanide |
0.4 |
0.4 |
0.3 |
0.3 |
0.2 |
0.1 |
0.1 |
0.05 |
Phenols |
0.4 |
0.3 |
0.2 |
0.1 |
0.1 |
0.1 |
0.1 |
0.1 |
Sulphide |
1 |
1 |
1 |
1 |
1 |
1 |
1 |
1 |
Sulphate |
800 |
600 |
600 |
600 |
600 |
400 |
400 |
400 |
Chloride |
1000 |
800 |
800 |
800 |
600 |
600 |
400 |
400 |
Fluoride |
10 |
8 |
8 |
8 |
5 |
5 |
3 |
3 |
Total phosphorus |
10 |
10 |
10 |
8 |
8 |
8 |
5 |
5 |
Ammonia nitrogen |
20 |
20 |
20 |
20 |
20 |
20 |
20 |
10 |
Nitrate + nitrite nitrogen |
50 |
50 |
50 |
30 |
30 |
30 |
30 |
20 |
Surfactants (total) |
15 |
15 |
15 |
15 |
15 |
15 |
15 |
15 |
E. coli (count/100ml) |
1000 |
1000 |
1000 |
1000 |
1000 |
1000 |
1000 |
1000 |
Note: Table abstract from
Technical Memorandum on Effluent Standards (EPD, 1991).
Table 5‑3 Key Water Quality Objectives for inland waters in Deep Bay Water Control Zones
E.
coli (cfu)
per 100ml ≤ |
Min. DO (mg/L) ≥ |
pH range ≥ and
≤ |
Max. BOD5 (mg/L) ≤ |
Max. COD (mg/L) ≤ |
Max. Annual Median SS (mg/L) ≤ |
Ammoniacal nitrogen (mg/L) ≤
|
|
1000 |
4 |
6.0 |
9.0 |
5 |
30 |
20 |
0.021 |
Note: WQO follows River Water Quality in
No Net Increase Requirement
Environmental Impact
Assessment Ordinance (Cap. 499) Technical Memorandum on Environmental Impact
Assessment Process (EIAO-TM)
Technical Memorandum for
Effluent Discharges
A Guide to Water Pollution
Control Ordinance
River Water Quality in
Existing
Conditions
Table 5‑4 Summary of River Water Quality at Nearby
Parameters |
*WQO |
2002 |
2003 |
2004 |
2005 |
pH |
6.0 – 9.0 |
7.4 (6.8 – 8.7) |
7.6 (6.9 – 8.6) |
7.6 (7.3 – 9.1) |
7.6 (7.0 – 8.8) |
BOD5 (mg/L) |
≤ 5 |
12 (6 – 40) |
11 (6 – 21) |
13 (7 – 26) |
11 (4 – 28) |
COD (mg/L) |
≤ 30 |
29 (20 – 46) |
42 (28 – 59) |
51 (35 – 75) |
39 (10 – 85) |
SS (mg/L) |
≤ 20 |
49 (21 – 180) |
46 (18 – 110) |
46 (10 – 240) |
51 (10 – 170) |
DO (mg/L) |
≥ 4 |
5.3 (3.1 – 14.7) |
6.4 (3.1 – 11.9) |
7.2 (3.0 – 14.9) |
6.6 (1.9 – 13.6) |
E. coli (cfu/100mL) |
≤1000 |
29,000 (6,400 – 140,000) |
25,000 (5,600 – 90,000) |
31,000 (5,200 – 330,000) |
83,750 (14,000 – 150,000) |
Ammonia-nitrogen
(mg/L) |
Annual average ≤0.021 |
5.80 (2.50 – 14.00) |
5.65 (1.70 – 12.00) |
6.45 (1.70 – 11.00) |
5.39 (0.72 – 16.00) |
Nitrate-nitrogen
(mg/L) |
-- |
0.98 (0.54 – 2.20) |
0.89 (0.32 – 1.90) |
1.65 (0.23 – 3.20) |
0.73 (0.09 – 2.00) |
Aluminium (µg/L) |
(a) Waste discharges shall not cause the toxins in water to attain
such levels as to produce significant toxic carcinogenic, mutagenic or
teratogenic effects in humans, fish or any other aquatic organisms, with due
regard to biologically cumulative effects in food chains and to toxicant
interactions with each other. (b) Waste discharges shall not cause a risk to any beneficial uses
of the aquatic environment. |
165 (50 – 350) |
(60 – 580) |
240 (160 – 700) |
223 (90 – 460) |
Cadmium (µg/L) |
0.15 (0.10 – 0.50) |
0 |
0.1 (0.1 – 0.3) |
0.18 (<0.1 – 0.3) |
|
Chromium (µg/L) |
1.0 (1.0 – 4.0) |
(<1 – 5) |
2 (1 – 2) |
1.5 (<1 – 2) |
|
Copper (µg/L) |
11.5 (5.0 – 69.0) |
(2 – 21) |
7 (4 – 16) |
6.8 (2 – 25) |
|
Lead (µg/L) |
2.0 (1.0 – 6.0) |
(<1 – 11) |
4 (2 – 16) |
4.2 (2 – 11) |
|
Zinc (µg/L) |
50 (30 – 200) |
(10 – 80) |
35 (20 – 110) |
35 (10 – 80) |
*Note:
1. WQO follows WPCO Cap.358R.
2. Data presented are in
annual medians of monthly samples, except those for E. coli which are in annual geometric means.
3. Figures in brackets are
annual ranges.
4. Figures in bold show
non-compliance to WQO.
Water Quality
Sensitive Receivers
Water Quality
Monitoring at Sensitive Receivers
Table 5‑5 In-situ Water Quality Testing Parameters
Reference |
Parameters |
Frequency |
No.
of Depths |
WM1 to WM10 |
Dissolved Oxygen Saturation Water depth pH value Temperature Turbidity Salinity Dissolved Oxygen |
& |
Mid-depth |
*WM11 to WM13 |
Dissolved Oxygen Saturation Water depth pH value Temperature Turbidity Salinity Dissolved Oxygen |
2 in wet season |
Mid-depth for
WM11 & 12; |
*Note: WM11 to WM13 are control stations for estimation
of the water quality of the future restored wetland.
Table 5‑6 Water Quality Testing Parameters in Laboratory
Reference |
Sampling |
Laboratory
Testing Parameters |
WM1-WM7 |
|
Conductivity Copper (Cu) Chromium (Cr) Lead (Pb) Zinc (Zn) Aluminium Cadmium Suspended Solids Total Kjeldahl Nitrogen (SP) Ammonia-nitrogen Nitrate-nitrogen Ortho-phosphate Total Phosphorous (SP) Sulphide (SP) 5-day BOD COD Oil
& grease E. coli Faecal
coliforms |
WM11-WM13 |
2 in wet season |
*Note: WM11 to
WM13 are control stations for estimation of the water quality of the future
restored wetland.
Baseline Water
Quality
Table 5‑7 Summary of Water and Sediment Quality Monitoring Results in Dry Season (For Monitoring Stations WM1 to WM7)
Parameters |
WM1 |
WM2 |
WM3 |
WM4 |
WM5 |
WM6 |
WM7 |
pH value |
6.6 (6.2-6.9) |
5.3 (4.3-6.2) |
6.6 (6.4-6.8) |
6.4 (6.1-6.7) |
6.3 (5.9-6.6) |
6.2 |
6.2 (6.1-6.3) |
Conductivity
(ms/cm) |
407.5 (290-525) |
730.5 (592-869) |
1042 (994-1090) |
1011 (962-1060) |
1155 (1030-1280) |
2320 |
2470 (1330-3610) |
Temp.
(°C) |
26.4 (22.6-30.1) |
26.9 (23.4-30.3) |
25.9 (23.0-28.7) |
25.4 (21.4-29.4) |
27.5 (26.6-28.3) |
22.5 |
28.3 (26.9-29.6) |
Salinity
%o |
0.3 (0.2-0.4) |
0.4 |
0.5 |
0.55 (0.5-0.6) |
0.6 (0.5-0.7) |
1.2 |
1.3 (0.7-1.9) |
Suspended
Solids (mg/L) |
24 (11-37) |
71 (16-126) |
44.5 (24-65) |
28.5 (22-35) |
22 (10-34) |
28 |
215.5 (75-356) |
Turbidity
(NTU) |
29 (7-51) |
52.5 (4-101) |
34.5 (33-36) |
14 (9-19) |
24 (15-33) |
10 |
85.5 (31-140) |
Water
Depth (m) |
<0.5 |
<0.5 |
<0.5 |
<0.5 |
<0.5 |
<0.5 |
<0.5 |
Aluminium
(mg/L) |
23.5 (<10-37) |
193.5 (18-369) |
28 (<10-46) |
<10 |
11.5 (<10-13) |
25 |
11 (<10-12) |
Cadmium (mg/L) |
<0.2 |
0.3 (<0.2-0.4) |
<0.2 |
<0.2 |
<0.2 |
0.2 |
<0.2 |
Chromium
(mg/L) |
<1 |
<1 |
<1 |
<1 |
<1 |
<1 |
1.5 (<1-2) |
Copper (mg/L) |
2 (1-3) |
1 (<1-1) |
1.5 (<1-2) |
1.5 (<1-2) |
1 (<1-1) |
5 |
<1 |
Lead (mg/L) |
<1 |
<1 |
<1 |
<1 |
<1 |
3 |
<1 |
Zinc (mg/L) |
86.5 (32-141) |
124.5 (<10-239) |
<10 |
10 (<10-10) |
<10 |
29 |
13 (<10-16) |
Ammonia
as N (mg/L) |
0.65 (0.26-1.03) |
4.61 (3.91-5.30) |
4.46 (3.17-5.74) |
5.13 (4.74-5.51) |
7.24 (5.96-8.52) |
0.15 |
1.82 (1.81-1.83) |
Nitrate
as N (mg/L) |
0.08 |
0.41 (0.14-0.67) |
0.12 (0.02-0.22) |
0.07 (0.05-0.08) |
0.02 (0.01-0.02) |
0.01 |
2.68 (2.35-3.01) |
Total
Kjeldahl Nitrogen as N (mg/L) |
1.5 (0.9-2.0) |
6.9 (5.2-8.6) |
6.3 (4.9-7.6) |
6.8 (6.3-7.2) |
8.0 (6.9-9.0) |
3.1 |
4.2 (4.1-4.2) |
Total
Phosphorus (mg/L) |
0.15 (<0.1-0.2) |
0.25 (<0.1-0.4) |
1.1 (1.0-1.2) |
2.8 (1.1-4.5) |
2.2 (1.8-2.6) |
0.2 |
1.3 (1.1-1.4) |
Reactive
Phosphorus as P (mg/L) |
0.01 (<0.01-0.01) |
0.015 (<0.01-0.02) |
0.45 (0.43-0.46) |
1.06 (0.50-1.61) |
1.8 (1.20-2.40) |
0.02 |
0.44 (0.38-0.50) |
Sulphide
(mg/L) |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
0.55 (<0.1-1.0) |
Oil &
Grease (mg/L) |
<5 |
<5 |
<5 |
<5 |
<5 |
<5 |
<5 |
Dissolved
Oxygen Saturation (%) |
95.6 (93.8-97.4) |
76.0 (34.9-117) |
72.5 (69.7-75.3) |
65.1 (54.0-76.1) |
38.8 (23.1-54.4) |
107 |
71.7 (60.9-82.5) |
Chemical
Oxygen Demand (mg/L) |
24.5 (18-31) |
37.5 (19-56) |
44 (40-48) |
34 (28-40) |
43 (35-51) |
108 |
24.5 (14-35) |
Biochemical Oxygen Demand (mg/L) |
2 (<2-2) |
9.5 (<2-17) |
9 (<2-16) |
8 (<2-14) |
5 (<2-8) |
4 |
6 (<2-10) |
DO (mg/L) |
7.8 (7.1-8.4) |
5.9 (3.0-8.8) |
6.0 (5.9-6.0) |
5.2 (4.6-5.8) |
3.3 (1.8-4.8) |
8.5 |
5.8 (5.2-6.3) |
E. coli (cfu/100mL) |
230 (70-1.6*10²) |
8.1*10² (21-1.6*10³) |
99 (88-1.1*10²) |
96 (32-1.6*10²) |
1.5*104 (3.2*10³-1.2*104) |
1.0*10² |
5.9*10³ (3.7*10³-8.0*10³) |
Faecal
Coliform (cfu/100mL) |
125 (80-1.7*10²) |
1.1*10³ (22-2.2*10³) |
104 (88-1.2*10²) |
1.1*10² (35-1.8*10²) |
7.0*10³ (3.9*10³-1.0*104) |
10*10² |
6.6*10³ (4.4*10³-8.8*10³) |
Note: 1. Data presented are
average values and the ranges are shown in brackets.
2. Values at or below laboratory
reporting limits are presented as laboratory reporting limits (see Appendix E)
3. Figures in bold show
non-compliance to WQO.
4.
Water monitoring at WM6 was only performed on 29 Mar 06 due to no water could
be obtained.
Table 5‑8 Summary of Water Quality Monitoring Results in Wet Season (For Monitoring Stations WM1 to WM7 & WM11 to WM13)
Parameters |
WM1 |
WM2 |
WM3 |
WM4 |
WM5 |
WM6 |
WM7 |
WM 11 |
WM 12 |
WM 13S |
WM 13B |
pH value |
6.6 (6.2-6.9) |
6.7 (6.1-7.2) |
6.8 (6.2-7.3) |
6.7 (6.1-7.1) |
6.9 (6.3-7.5) |
6.6 (6.5-6.8) |
7.3 (7.1-7.4) |
6.6 (6.3-6.9) |
6.6 (6.3-6.8) |
7.2 |
7.2 (7.1-7.2) |
Conductivity (ms/cm) |
530 (352-780) |
561 (288-717) |
681 (515-991) |
674 (533-899) |
605 (440-719) |
564 (210-1180) |
2308 (952-4600) |
626 (561-691) |
581 (483-679) |
868 (716-1020) |
881 (731-1030) |
Temp. (°C) |
27.5 (24.3-28.9) |
27.6 (24.9-29.6) |
26.3 (23.1-28.5) |
26.3 (23.0-28.4) |
26.2 (22.7-28.6) |
28.1 (27.3-28.9) |
27.0 (25.2-27.9) |
27.6 (26.7-28.5) |
27.6 (26.6-28.6) |
28.0 (27.0-28.9) |
28.0 (27.2-28.8) |
Salinity % |
0.3 (0.2-0.4) |
0.3 (0.2-0.4) |
0.4 (0.2-0.4) |
0.4 |
0.3 (0.2-0.4) |
0.3 (0.2-0.6) |
1.3 (0.5-2.5) |
0.4 (0.3-0.4) |
0.3 |
0.5 |
0.5 |
Suspended Solids (mg/L) |
34.3 (8-87) |
24.0 (4-45) |
52.8 (20-104) |
53.3 (21-108) |
21.3 (12-32) |
17.3 (5-42) |
92.5 (14-253) |
72.5 (19-126) |
44 (17-71) |
63.5 (60-67) |
90.5 (68-113) |
Turbidity (NTU) |
51.8 (17-92) |
47.0 (9-83) |
54.5 (18-85) |
40.8 (15-70) |
17.3 (11-22) |
6.3 (4-8) |
72.5 (7-200) |
82.0 (24-140) |
90.5 (29-152) |
78.5 (77-80) |
122.0 (116-128) |
Water Depth (m) |
<0.5 |
<0.5 |
<0.5 |
<0.5 |
<0.5 |
<0.5 |
<0.5 |
<0.5 |
<0.5 |
1.0 |
1.5 |
Aluminium (mg/L) |
31 (<10-79) |
41.8 (<10-84) |
32.3 (<10-79) |
24 (<10-40) |
17.8 (<10-41) |
66 (55-81) |
15.3 (<10-21) |
29 (19-38) |
39 (29-152) |
16 (14-17) |
15 (14-16) |
Cadmium (mg/L) |
<0.2 |
<0.2 |
<0.2 |
<0.2 |
<0.2 |
<0.2 |
<0.2 |
<0.2 |
<0.2 |
<0.2 |
<0.2 |
Chromium (mg/L) |
1.3 (<1-2) |
1.5 (<1-3) |
1.5 (<1-2) |
1.8 (<1-4) |
1.5 (<1-3) |
1 (<1-1) |
1.5 (<1-3) |
2 (<1-3) |
1 (<1-1) |
<1 |
1.5 (<1-2) |
Copper (mg/L) |
1.8 (<1-2) |
1 (<1-1) |
1.3 (<1-2) |
1.3 (<1-2) |
1.3 (<1-2) |
1 (<1-1) |
1.5 (<1-3) |
1.5 (1.0-2.0) |
1.5 (1.0-2.0) |
<1 |
1 (<1-1) |
Lead (mg/L) |
1 (<1-1) |
<1 |
<1 |
<1 |
<1 |
1 (<1-1) |
<1 |
1 (<1-1) |
1.5 (<1-2) |
<1 |
<1 |
Zinc (mg/L) |
10.5 (<10-12) |
10.8 (<10-13) |
<10 |
<10 |
<10 |
<10 |
11.3 (<10-15) |
<10 |
<10 |
<10 |
<10 |
Ammonia as N (mg/L) |
0.69 (0.16-1.1) |
0.83 (0.04-2.2) |
4.11 (1.28-8.94) |
4.21 (1.92-8.67) |
5.17 (2.98-10.9) |
0.10 (0.09-0.1) |
2.35 (0.60-4.95) |
2.53 (1.85-3.2) |
2.29 (1.78-2.8) |
2.76 (2.6-2.91) |
2.75 (2.6-2.9) |
Nitrate as N (mg/L) |
0.08 (<0.01-0.16) |
0.03 (<0.01-0.07) |
0.06 (<0.01-0.19) |
0.02 (<0.01-0.04) |
0.02 (<0.01-0.03) |
0.01 (<0.01-0.01) |
1.68 (0.78-3.13) |
0.03 (0.01-0.04) |
0.03 (0.01-0.04) |
0.39 (0.23-0.55) |
0.39 (0.23-0.54) |
Total Kjeldahl
Nitrogen as N (mg/L) |
2.0 (0.9-2.4) |
2.7 (1.9-4.0) |
5.2 (2.6-10.3) |
6.9 (4.4-13.1) |
7.2 (3.8-16.6) |
2.4 (1.4-3.3) |
4.4 (2.2-7.8) |
4.1 (3.9-4.3) |
3.8 (3.5-4.0) |
3.1 (0.4-5.7) |
3.3 (0.5-6.0) |
Total Phosphorus
(mg/L) |
0.15 (<0.1-0.2) |
0.68 (<0.1-1.1) |
1.4 (0.5-2.1) |
1.4 (0.7-2.2) |
1.6 (0.6-2.8) |
0.7 (0.4-1.0) |
0.9 (0.7-1.3) |
1.0 (0.8-1.1) |
0.8 (0.6-1.0) |
3.4 (0.2-6.6) |
3.8 (0.3-7.3) |
Reactive Phosphorus
as P (mg/L) |
0.01 (<0.01-0.01) |
0.2 (0.03-0.55) |
0.8 (0.12-1.94) |
0.7 (0.09-1.68) |
1.0 (0.2-2.7) |
0.3 (0.21-0.37) |
0.7 (0.50-1.23) |
0.2 (0.09-0.4) |
0.2 (0.09-0.21) |
<0.01 |
<0.01 |
Sulphide (mg/L) |
<0.1 |
<0.1 |
0.28 (<0.1-0.8) |
0.45 (<0.1-1.1) |
0.1 (<0.1-0.1) |
<0.1 |
0.1 (<0.1-0.1) |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
Oil & Grease
(mg/L) |
<5 |
<5 |
<5 |
<5 |
<5 |
<5 |
<5 |
6.5 (<5-8) |
<5 |
<5 |
<5 |
Dissolved Oxygen
Saturation (%) |
61.2 (47-72) |
62.4 (43.6-108) |
59.0 (45.2-67.3) |
47.8 (25.2-68.2) |
45.9 (24.9-54.6) |
57.4 (55.3-58.4) |
75.5 (56.8-84.1) |
59.6 (54.4-64.7) |
64.0 (60.8-67.2) |
150.0 (143-157) |
125.0 (112-138) |
Chemical Oxygen
Demand (mg/L) |
48.0 (27-67) |
71.8 (38-105) |
50.5 (27-76) |
63.5 (38-84) |
29.0 (24-38) |
94.7 (76-112) |
37.0 (19-66) |
40.0 (34-46) |
44.5 (34-55) |
67.5 (63-72) |
81.5 (73-90) |
Biochemical Oxygen Demand (mg/L) |
5.25 (<2-12) |
12.75 (<2-40) |
6.75 (<2-10) |
12.25 (<2-26) |
6.5 (<2-15) |
7.67 (<2-16) |
8.25 (<2-17) |
12.0 (6-18) |
10.0 (4-16) |
16.0 (7-25) |
17.5 (12-23) |
DO (mg/L) |
4.7 (3.6-5.4) |
5.0 (3.3-8.9) |
4.7 (3.9-5.4) |
3.8 (2.2-5.4) |
3.6 (2.1-4.2) |
4.5 (4.3-4.6) |
5.9 (4.6-6.6) |
4.7 (4.2-5.2) |
5.1 (4.7-5.4) |
12.2 (11.8-12.5) |
10.1 (9.2-10.9) |
E. coli (cfu/100mL) |
2.9*10² (46-5.1*102) |
2.4*10² (39-5.3*102) |
1.1*103 (2.1*102-2.4*103) |
7.2*10² (2.4*102-1.2*103) |
4.1*103 (1.1*102-9.8*103) |
50 (2-1.2*102) |
7.2*103 (3.2*103-1.4*104) |
1.9*103 (2.2*102-3.6*103) |
2.0*103 (1.4*103-2.7*103) |
28 (26-29) |
40 (19-61) |
Faecal Coliform
(cfu/100mL) |
3.4*102 (49-5.6*102) |
2.8*102 (47-5.7*102) |
1.5*103 (2.4*102-3.1*103) |
1.1*103 (2.7*102-1.9*103) |
4.8*103 (1.9*102-1.0*104) |
55 (2-1.3*102) |
8.6*103 (4.3*103-1.7*104) |
2.2*103 (4.0*102-4.0*103) |
2.5*103 (1.9*103-3.0*103) |
31 (29-32) |
49 (27-70) |
Note:
1. Data presented are in average values and the ranges are shown in brackets.
2. Values at or below
laboratory reporting limits are presented as laboratory reporting limits
(see Appendix E)
3. Figures in bold show
non-compliance to WQO.
4. Water monitoring at WM6 was not performed on 26 Apr
06 due to no water could be obtained.
Table 5‑9 Summary of In-situ Water Quality Monitoring Results in Dry Season (For Monitoring Station WM8 to WM10)
Parameters |
WM8 |
WM9 |
WM10 |
Dissolved
Oxygen Saturation (%) |
11.7 |
20.0 |
121 (110-132) |
Dissolved
Oxygen (mg/L) |
<0.1 |
1.6 |
9.2 (8.2-10.1) |
Water
depth (m) |
<0.5 |
<0.5 |
<0.5 |
Temperature
(°C) |
27 |
28.7 |
32.2 |
Turbidity
(NTU) |
37 |
37 |
5.5 (5-6) |
Salinity
%o |
1.7 |
1.7 |
1.9 (1.5-2.3) |
pH value |
5.2 |
3.3 |
2.7 (2.5-2.9) |
Note:
1. Data presented are average values and the ranges are shown in brackets.
2. Water monitoring
at WM8 & 9 was only performed on 29 Mar 2006 due to no water sample could
be obtained.
3. Figures in bold
show non-compliance to WQO.
Table 5‑10 Summary of In-situ Water Quality Monitoring Results in Wet Season (For Monitoring Station WM8 to WM10)
Parameters |
WM8 |
WM9 |
WM10 |
Dissolved Oxygen Saturation (%) |
79 |
68.7 |
75.4 (49.8-101) |
Dissolved Oxygen (mg/L) |
6.0 |
5.2 |
5.8 (3.7-7.9) |
Water depth (m) |
<0.5 |
<0.5 |
<0.5 |
Temperature (°C) |
27.9 |
28.3 |
27.35 (26.3-28.4) |
Turbidity (NTU) |
26 |
71 |
78.5 (7-150) |
Salinity %o |
0.2 |
0.2 |
0.8 (0.3-1.3) |
pH value |
6.4 |
6.5 |
4.3 (2.4-6.2) |
Note: 1. Data presented are average values
and the ranges are shown in brackets.
2. Water monitoring at WM8 & 9 was only performed on 5 June 2006,
monitoring at WM10 were
performed on 26 April and 5 June 2006.
3. Figures in bold show non-compliance to WQO.
Table 5‑11 Summary of Key Water Quality Objectives Compliance for the Water Quality Monitoring Station WM1 to WM7 and WM11 to WM13
Parameters |
*WQO |
WM1 |
WM2 |
WM3 |
WM4 |
WM5 |
WM6 |
WM7 |
WM11 |
WM12 |
WM13 |
pH |
6.0 – 9.0 |
Ö |
Ö |
Ö |
Ö |
Ö |
Ö |
Ö |
Ö |
Ö |
Ö |
BOD5
(mg/L) |
≤ 5 |
Ö |
× |
× |
× |
× |
Ö |
× |
× |
× |
× |
COD
(mg/L) |
≤ 30 |
Ö |
× |
× |
× |
× |
× |
× |
× |
× |
× |
SS
(mg/L) |
≤ 20 |
× |
× |
× |
× |
× |
× |
× |
× |
× |
× |
DO
(mg/L) |
≥ 4 |
Ö |
Ö |
Ö |
× |
× |
Ö |
Ö |
Ö |
Ö |
Ö |
E. coli (cfu/100mL) |
≤1000 |
Ö |
Ö |
× |
Ö |
× |
Ö |
× |
× |
× |
Ö |
Ammonia-nitrogen
(mg/L) |
Annual average
≤0.021 |
× |
× |
× |
× |
× |
× |
× |
× |
× |
× |
*Note: WQO follows WPCO Cap.358R.
Water and Sediment Quality in the Drainage Channels and Water Ditches in the
Water Quality of Active Fishpond
Water Quality in the Ditches within the Project Area
In-situ Water Quality Monitoring Results at the Marsh
in the Project Area
Summary of Water Quality within the Assessment Area
Construction
Phase
Diversion of Existing Water Ditches and
Marsh
Draining of Existing Water Ditches
Soil Excavation
and Stockpiling
Release of
Contaminants during Excavation
Chemical Waste
from Plant and Equipment
Domestic
Effluent
Operational
Phase
Waste Water
Pollution
Diversion of existing water ditches and
marsh
Changes in hydrology
Construction
Phase
General Precautions
· The site should be confined to avoid silt runoff from the site;
· No discharge of silty water into the drainage channel within and in the vicinity of the site;
· Any soil contaminated with chemicals/oils shall be removed from site and the void created shall be filled with suitable materials;
· Stockpiles to be covered by tarpaulin to avoid spreading of materials during rainstorms;
· Suitable containers shall be used to hold the chemical wastes to avoid leakage or spillage during storage, handling and transport;
· Chemical waste containers shall be labelled with appropriate warning signs in English and Chinese to avoid accidents. There shall also be clear instructions showing what action to take in the event of an accidental;
· Storage areas shall be selected at safe locations on site and adequate space shall be allocated to the storage area;
· Any construction plant which causes pollution to the water system due to leakage of oil or fuel shall be removed off-site immediately;
· Spillage or leakage of chemical waste to be controlled using suitable absorbent materials;
· Chemicals will always be stored on drip trays or in bunded areas where the volume is 110% of the stored volume;
· Regular clearance of domestic waste generated in the temporary sanitary facilities to avoid waste water spillage; and
· Temporary sanitary facilities to be provided for on-site workers during construction.
Diversion of Existing Water Ditches and
Marsh
Draining of Existing Water Ditches
Soil Excavation and
Stockpiling
Operation Phase
Provisional Measures to
Emergency Sewage Discharges/Spillages
Diversion of Existing Water Ditches and Marsh
Provision of Soft-landscaping
Residual Impacts
Cumulative
Impacts
Binnie Black
& Veatch Hong Kong Limited, 2002. Sheung Shui to Lok Ma Chau Spur Line
Environmental Impact Assessment: Environmental Impact Assessment Report, Final
Report. Kowloon-Canton Railway Corporation,
Ove Arup &
Partners Hong Kong Limited, 2004. EIA & TIA Studies for the Stage 2 of PWP
Item No. 215DS – Yuen Long and Kam Tim Sewerage and Sewage Disposal, EIA
(Final). Drainage Services Department,
Planning
Department
Environmental
Protection Department, 2005. River Water
Quality in
Environmental
Protection Department, 2004. River Water
Quality in
Environmental
Protection Department, 2003. River Water
Quality in
Environmental
Protection Department, 1991. Technical Memorandum Standards for Effluents
Discharged into Drainage and Sewerage Systems, Inland and Coastal Waters. EPD
Water Policy Group. The Government Printer,
PREFACE
Wo Shang Wai to the north of Royal Palms and
The planning intention of this location is to provide
incentive for the restoration of degraded wetlands adjoining existing fish
ponds and to encourage the phasing out of sporadic open storage and port
back-up uses on degraded wetland. This
can be achieved through comprehensive residential and/or recreational
development to include wetland restoration area. Development or redevelopment schemes on the
degraded wetlands directly adjoining the existing continuous and contiguous
fish ponds should include wetland restoration and buffer proposals to separate
the development from and minimize its impact on the fish pond areas. Any new building should be located farthest
away from
· Carry out the desk study, water sampling, topography survey and site visit to collect the relevant information for the assessment.
· Investigate the existing/planning sewerage facilities in the vicinity of the development and determine the sewage flow and pollutant loading generated from the existing site.
· Determine the potential sewage and pollutant loading arising from the proposed development.
·
Study and assess the need and
impacts of discharging sewage to the existing/planning sewerage systems in
· Investigate and determine the need and the feasibility of having a separate sewage treatment plant within the Assessment Area.
· Formula options to mitigate the sewerage impacts identified and recommend the design, operation and maintenance requirements for the sewage disposal system.
Collected Information
·
The existing/planning sewerage facilities layout plan in
· The layout plan for the proposed residential development
· The proposed planning data of the development
·
Water sampling data at
· Topographic survey plan for the proposed development
Design Standards, Guidelines and Reference
· Sewerage Manual published by DSD
· Guidelines for the Design of Small Sewage Treatment Plant published by EPD
Design Average
Daily Sewage Flow
Design Pollutant
Loadings
Table 6‑1 Design Unit Load Factors
Loading Type |
Unit Load Factor |
SS (kg/d/person) |
0.055 |
BOD (kg/d/person) |
0.055 |
TN
(kg/d/person) |
0.0135 |
NH3N
(kg/d/person) |
0.005 |
E. coli (no./d/person) |
4.3x1010 |
Note:-
1. The
total nitrogen (TN) is equal to the sum of inorganic nitrogen (NH3N)
and the organic nitrogen (TKN). The TKN loading can be referred to Table 4 of
the Sewerage Manual which is about 0.0085 kg/d/person.
2. The
unit load factors for BOD and SS are based on Appendix 2 of the Guidelines for
the Design of Small Sewage Treatment Plants, for other parameters, the unit
load factors are based on Table 4 of the Sewerage Manual.
Assessment
Criteria for the Sewerage Facilities
Existing Land Uses of the Project Area to be Developed
Existing Sewerage and Sewage Treatment Facilities
Estimated Sewage
Flow and Pollutant Loading from the Existing Site
Planned Public Sewerage in
Description of the Proposed Development
Estimated Sewage
Flow from the Proposed Development
Estimated
Pollutant Loads from the Proposed Development
Table 6‑2 Pollutant Loads arising from the Raw Sewage of the Proposed Development
Parameters |
Loading from the
Proposed Development (kg/d) |
SS |
57.92 |
BOD |
57.92 |
TN |
14.22 |
NH3N |
5.27 |
E. coli (no./d) |
4.53 x
1013 |
PREFACE
Wo Shang Wai to the north of Royal Palms and
The planning intention of this location is to provide
incentive for the restoration of degraded wetlands adjoining existing fish
ponds and to encourage the phasing out of sporadic open storage and port
back-up uses on degraded wetland. This
can be achieved through comprehensive residential and/or recreational
development to include wetland restoration area. Development or redevelopment schemes on the
degraded wetlands directly adjoining the existing continuous and contiguous
fish ponds should include wetland restoration and buffer proposals to separate
the development from and minimize its impact on the fish pond areas. Any new building should be located farthest
away from
Legislation
·
Waste Disposal Ordinance (Cap 354);
·
Waste Disposal (Chemical Waste) (General) Regulation (Cap
354);
·
Land (Miscellaneous Provisions) Ordinance (Cap 28);
·
Public Health and Municipal Services Ordinance (Cap
132)-Public Cleansing and Prevention of Nuisances (Urban Council) and (Regional
Council) By-laws; and
·
Environment, Transport and Works Bureau (Works) Technical
Circular (ETWB(W)TC) No. 34/2002A Management of Dredged/Excavated Sediment and
Practice Note for Authorised Persons (PNAP) 252.
·
Waste Reduction Framework Plan, 1998 to 2007, Planning,
Environment and Lands Bureau, Government Secretariat (5 November 1998);
·
Environmental Guidelines for Planning in Hong Kong (1990),
Hong Kong Planning and Standards Guidelines,
·
New Disposal Arrangements for Construction Waste (1992);
Environmental Protection Department & Civil Engineering Department;
·
Code of Practice on the Packaging, Labelling and Storage of
Chemical Wastes (1992), Environmental Protection Department;
·
Works Branch Technical Circular No. 12/2000, Fill
Management;
·
Works Branch Technical Circular No. 2/93, Public Dumps;
·
Works Branch Technical Circular No. 16/96, Wet Soil in
Public Dumps; and
·
Environment, Transport and Works Bureau Technical Circular
(Works) No. 19/2005, Environmental Management on Construction Sites.
General
·
estimation of the types and quantities of the wastes to be
generated;
·
assessment of the secondary environmental impacts due to the
management of waste with respect to potential hazards, air and odour emissions,
noise, wastewater discharges and traffic; and
·
assessment of the potential impacts on the capacity of waste
collection, transfer and disposal facilities.
· residential development and associated infrastructure; and
· wetland restoration area and linear landscape area.
· site clearance waste;
· excavated materials;
·
construction and demolition
(C&D) materials;
· chemical waste; and
· general refuse.
Site Clearance
Waste
Excavated
Materials/Imported Filling Material
· Excavation of the Project Area to form the wetland restoration area.
Construction and
Demolition Waste
· wood from formwork and falsework;
· materials and equipment wrappings;
·
unusable/surplus
concrete/grouting mixes; and
· damaged /surplus construction materials.
Chemical Waste
· scrap batteries or spent acid/alkali from their maintenance;
· used engine oils hydraulic fluids and waste fuel;
· spent mineral oils/cleaning fluids from mechanical machinery; and
· spent solvents/solutions, some of which may be halogenated, from equipment clearing activities.
· toxic effects to workers;
· fire hazards; and
· possible disruption of sewage treatment works if chemical waste enters the sewerage system.
General Refuse
Site Clearance Waste
Excavated Material
topsoil material: 10,000m3 (see Paragraph 7.5.2 above)
sediment: 2,140m3 (see Table 7–22)
Imported Filling Material
Construction and Demolition
Material
Chemical Waste
General Refuse
Waste Management Hierarchy
·
avoidance and minimisation,
i.e. not generating waste through changing or improving practices and design;
· reuse of materials, thus avoiding disposal (generally with only limited reprocessing);
·
recovery and recycling, this
avoiding disposal (although reprocessing may be required); and
· treatment and disposal, according to relevant laws, guidelines and good practice.
Storage, Collection and
Transport of Waste
·
handle and store wastes in a manner which ensures that they
are held securely without loss or leakage, thereby minimising the potential for
pollution;
·
use waste haulers authorised or licensed to collect specific
category of waste;
·
remove wastes on a daily basis;
·
maintain and clean waste storage areas daily;
·
minimise windblown litter and dust during transportation by
either covering trucks or transporting wastes in enclosed containers;
·
obtain the necessary waste disposal permits from the
appropriate authorities, if they are required, in accordance with Waste
Disposal Ordinance (Cap 354), Waste Disposal (Chemical Waste) (General)
Regulation (Cap 354), the Land (Miscellaneous Provisions) Ordinance (Cap 28);
·
Dispose of waste at licensed waste disposal facilities;
·
Develop procedures such as ticketing system to facilities
tracking of loads, particularly for chemical waste, and to ensure that illegal
disposal of wastes does not occur; and
·
Maintain records of the quantities of wastes generated,
recycled and disposal.
Excavated Material/Imported Filling Material
Dust:
·
wetting the surface of the stockpiled soil with water when
necessary, especially during the dry season;
·
covering the stockpiled soil with sheets;
·
minimising disturbance of the stockpiled soil; and
·
enclosure of stockpiling area.
Water Quality:
·
installation of silt traps for the surface water drainage
system; and
·
covering stockpiled material with tarpaulin during heavy
rainstorm.
·
dropping heights for those materials should be controlled to
a practical height to minimise the fugitive dust arising from unloading;
·
materials should not be loaded to a level higher than the
side and tail boards, and should be dampened or covered before transport;
·
the travelling speed should be reduced to 10 km hr-1 to
reduce dust dispersion and re-suspension from the operating haul trucks; and
·
wheel washing facilities should be installed and used by all
vehicles leaving the Project Area.
Construction & Demolition Materials
Chemical Waste
Containers used for the
storage of chemical wastes should:
·
be suitable for the substance they are holding, resistant to
corrosion, maintained in a good condition, and securely closed:
·
have a capacity of less than 450 litres unless the
specification has been approved by the EPD; and
·
display a label in English and Chinese in accordance with
instructions prescribed in Schedule 2 of the Regulations.
The storage area for
chemical wastes should:
·
be clearly labelled and used solely for the storage of
chemical waste;
·
be enclosed on at least 3 sides;
·
have an impermeable floor and bunding, of capacity to
accommodate 110% of the volume of the largest container or 20% by volume of the
chemical waste stored in that area whichever is the greatest;
·
have adequate ventilation;
·
be covered to prevent rainfall entering (water collected
within the bund must be tested and disposed as chemical waste if necessary);
and
·
be arranged so that incompatible materials are adequately
separated.
Disposal of chemical waste
should:
·
be via a licensed waste collector;
·
be to a facility licensed to receive chemical waste, such as
the Chemical Waste Treatment Facility which also offers a chemical waste
collection service and can supply the necessary storage containers; or
·
be to a re-user of the waste, under approval from the EPD.
General Refuse
Construction Waste
Management Plan
Land contamination Environmental
Legislation and Standards
·
Technical Memorandum on
Environmental Impact Assessment Process (EIAO-TM);
·
Professional Persons
Environmental Consultative Committee Practice Note 3/94 - Contaminated Land
Assessment and Remediation (ProPECC PN 3/94); and
·
EPD Guidance Notes for
Investigation and Remediation of Contaminated Sites of: Petrol Filling
Stations; Boatyards; and Car Repair/Dismantling Workshops (1999).
Assessment Methodology
· provide a clear and detailed account of the present use of the land in question and the relevant past land use history, in relation to possible land contamination;
· identify those areas of potential contamination and associated impacts, risks or hazards; and
· if required, submit a plan to evaluate the actual soil contamination conditions.
(i) desk
study of past land uses and identification of potential contamination;
(ii) ground investigation and laboratory testing for possible contaminants (based on a contamination assessment plan (CAP) agreed with EPD);
(iii) assessment of the environmental impacts due to land contamination; and
(iv) presentation of appropriate remediation options.
Potential for land contamination
Potential
land contamination sources
Table 7‑1 Potential contaminants
Source |
Potential Contaminants |
Contaminant parameters to
be tested |
Lorry parking area |
Metals, solvents, hydraulic fluids,
fuels, lubricating oils, coolants |
·
Heavy
metals (Copper, Chromium, Lead and Zinc); ·
BTEX
(benzene, toluene, ethyl benzene, xylenes); ·
total
petroleum hydrocarbons (TPHs); ·
polyaromatic
hydrocarbons (PAHs); ·
Phenols ·
TCLP
& asbestos |
Filled ground |
Unknown |
As above |
Table 7‑2 General hazardous effects of contaminants potentially present
Contaminants |
Hazardous effect |
Heavy Metals (incl. Copper, Chromium,
Lead and Zinc) |
Can be toxic by ingestion and
contact. Toxic to fish, plants and
marine plants (especially copper). |
BTEX and TPH |
Can be toxic by inhalation, ingestion and
contact. May be flammable at high
concentrations. |
PAH’s |
Can be toxic by inhalation, ingestion and
contact. |
Ground
investigation and laboratory testing
Contamination
assessment plan (CAP)
Ground
investigation field work
Laboratory
testing
Table 7‑3 Ground conditions encountered and depth of subsamples tested
Drillhole Ref. |
Ground Level (mPD) |
Strata thickness (m) |
Depth of subsamples
tested (m) |
||
Fill |
Marine deposit |
Alluvium |
|||
BH-LC1 |
+4.43 |
2.00 |
2.00 |
1.00 |
0.75; 1.75; 3.25 |
BH-LC2 |
+4.13 |
1.50 |
3.00 |
3.90 |
0.75; 1.25; 3.0; 5.0 |
BH-LC3 |
+4.17 |
1.00 |
3.50 |
0.50 |
0.75; 1.25 |
BH-LC4 |
+3.52 |
0.50 |
3.50 |
1.00 |
0.9; 1.9; 2.9 |
BH-LC5 |
+3.18 |
0.50 |
4.00 |
0.50 |
0.9; 1.9; 2.9 |
BH-LC6 |
+2.48 |
1.50 |
2.50 |
1.00 |
0.9; 1.9; 2.9 |
BH-LC7 |
+2.87 |
1.50 |
2.00 |
1.50 |
0.75; 1.25; 2.9 |
BH-LC8 |
+2.89 |
1.50 |
2.50 |
1.00 |
0.75; 1.25; 2.9 |
BH-LC9 |
+2.91 |
1.50 |
3.50 |
- |
0.75; 1.25; 2.9 |
BH-LC10 |
+2.78 |
2.00 |
1.50 |
1.50 |
0.75; 1.25; 1.75; 2.9 |
BH-LC11 |
+3.29 |
2.00 |
2.90 |
0.10 |
0.5; 1.5; 2.9 |
BH-LC12 |
+3.44 |
2.00 |
1.00 |
2.00 |
0.75; 1.5; 3.5 |
BH-LC13 |
+3.93 |
3.00 |
0.50 |
4.80 |
0.75; 1.75; 2.75; 5.0 |
BH-LC14 |
+3.30 |
2.00 |
2.00 |
1.00 |
0.5; 1.5; 3.0 |
BH-LC15 |
+2.94 |
2.00 |
2.00 |
1.00 |
0.5; 1.5; 3.0 |
Results
of laboratory testing
Table 7‑4 Summary of chemical test results on soil samples
Analyse |
Chromium |
Copper |
Lead |
Zinc |
Total |
TPH |
BTEX |
Phenols |
PAH's |
TCLP |
Asbestos |
Classification |
||
Unit (In dry Wt basis) |
mg/kg |
mg/kg |
mg/kg |
mg/kg |
% |
mg/kg |
mg/kg |
mg/kg |
mg/kg |
Mg/L |
|
|
||
Reporting Limits |
1.0 |
1.0 |
1.0 |
1.0 |
0.05 |
various |
various |
0.1 |
various |
various |
|
|
||
Dutch 'A' |
100 |
20 |
50 |
200 |
2 |
100 |
0.1 |
0.02 |
1 |
|
|
|
||
Dutch 'B' |
250 |
100 |
150 |
500 |
20 |
1000 |
7 |
1 |
20 |
various |
|
|
||
Dutch 'C' |
800 |
500 |
600 |
3000 |
200 |
5000 |
70 |
10 |
200 |
|
|
|
||
Borehole |
Depth |
Material |
|
|
|
|
|
|
|
|
|
|
|
|
BHLC1 |
0.75 |
Fill |
15 |
33 |
182 |
832 |
0.06 |
All < reporting limits |
All BTEX are < reporting limits |
All Phenols are < reporting limits |
All polynuclear aromatics are <
reporting limits |
All TCLP are < landfill disposal
criteria limits [all TCLP < reporting limits, except lead and zinc) |
not detected |
Pb & Zn > Dutch B |
BHLC1 |
1.75 |
Fill |
7 |
6 |
104 |
433 |
0.25 |
not detected |
< Dutch 'A' |
|||||
BHLC1 |
3.25 |
Marine deposit |
28 |
13 |
58 |
193 |
0.54 |
- |
< Dutch 'A' |
|||||
BHLC2 |
0.75 |
Fill |
14 |
27 |
63 |
364 |
0.14 |
433 |
not detected |
<< Dutch 'B' |
||||
BHLC2 |
1.25 |
Fill |
10 |
35 |
170 |
179 |
0.05 |
|
not detected |
Pb > Dutch B |
||||
BHLC2 |
3.00 |
Marine deposit |
19 |
43 |
161 |
100 |
0.13 |
136 |
not detected |
Pb > Dutch B |
||||
BHLC2 |
5.00 |
Alluvium |
24 |
10 |
47 |
69 |
1.25 |
All TPHs are < reporting limits |
- |
< Dutch 'A' |
||||
BHLC3 |
0.75 |
Fill |
30 |
17 |
53 |
166 |
0.11 |
not detected |
< Dutch 'A' |
|||||
BHLC3 |
1.25 |
Marine deposit |
32 |
17 |
64 |
943 |
0.09 |
not detected |
Zn > Dutch B |
|||||
BHLC4 |
0.75 |
Marine deposit |
30 |
11 |
32 |
86 |
2.95 |
not detected |
< Dutch 'A' |
|||||
BHLC4 |
1.25 |
Marine deposit |
31 |
13 |
41 |
95 |
1.06 |
not detected |
< Dutch 'A' |
|||||
BHLC5 |
0.90 |
Marine deposit |
34 |
15 |
51 |
152 |
0.53 |
not detected |
< Dutch 'A' |
|||||
BHLC5 |
1.90 |
Marine deposit |
41 |
19 |
50 |
94 |
0.59 |
not detected |
< Dutch 'A' |
|||||
BHLC5 |
2.90 |
Marine deposit |
43 |
16 |
44 |
110 |
1.97 |
- |
< Dutch 'A' |
|||||
BHLC6 |
0.90 |
Fill |
8 |
8 |
138 |
103 |
0.11 |
not detected |
< Dutch 'A' |
|||||
BHLC6 |
1.90 |
Marine deposit |
29 |
14 |
72 |
182 |
0.97 |
not detected |
< Dutch 'A' |
|||||
BHLC6 |
2.90 |
Marine deposit |
31 |
12 |
43 |
76 |
1.12 |
0.3 |
- |
<< Dutch 'B' |
||||
BHLC7 |
0.75 |
Fill |
13 |
16 |
95 |
501 |
0.57 |
All BTEX are < reporting limits |
not detected |
Zn > Dutch B |
||||
BHLC7 |
1.25 |
Fill |
8 |
8 |
55 |
204 |
0.15 |
not detected |
< Dutch 'A' |
|||||
BHLC7 |
2.90 |
Marine deposit |
27 |
20 |
74 |
121 |
1.45 |
- |
< Dutch 'A' |
|||||
BHLC8 |
0.75 |
Fill |
17 |
48 |
59 |
177 |
0.28 |
not detected |
< Dutch 'A' |
|||||
BHLC8 |
1.25 |
Fill |
9 |
6 |
34 |
35 |
0.09 |
not detected |
< Dutch 'A' |
|||||
BHLC8 |
2.90 |
Marine deposit |
30 |
12 |
39 |
77 |
1.21 |
0.4 |
- |
<< Dutch 'B' |
||||
BHLC9 |
0.75 |
Fill |
11 |
23 |
88 |
590 |
0.34 |
All BTEX are < reporting limits |
not detected |
Zn > Dutch B |
||||
BHLC9 |
1.25 |
Fill |
10 |
43 |
275 |
538 |
0.22 |
not detected |
Pb & Zn > Dutch B |
|||||
BHLC9 |
2.90 |
Marine deposit |
32 |
13 |
44 |
84 |
1.56 |
- |
< Dutch 'A' |
|||||
BHLC10 |
0.75 |
Fill |
15 |
23 |
78 |
214 |
0.14 |
not detected |
< Dutch 'A' |
|||||
BHLC10 |
1.25 |
Fill |
13 |
21 |
76 |
88 |
0.06 |
not detected |
< Dutch 'A' |
|||||
BHLC10 |
1.75 |
Fill |
10 |
15 |
79 |
221 |
0.11 |
- |
< Dutch 'A' |
|||||
BHLC10 |
2.90 |
Marine deposit |
29 |
13 |
51 |
87 |
1.19 |
- |
< Dutch 'A' |
|||||
BHLC11 |
0.50 |
Fill |
9 |
56 |
214 |
322 |
0.25 |
not detected |
Pb > Dutch B |
|||||
BHLC11 |
1.50 |
Fill |
12 |
24 |
159 |
319 |
0.18 |
not detected |
Pb > Dutch B |
|||||
BHLC11 |
2.90 |
Marine deposit |
39 |
14 |
39 |
92 |
1.56 |
- |
< Dutch 'A' |
|||||
BHLC12 |
0.75 |
Fill |
11 |
16 |
101 |
221 |
0.29 |
not detected |
< Dutch 'A' |
|||||
BHLC12 |
1.50 |
Fill |
14 |
20 |
63 |
60 |
0.25 |
not detected |
< Dutch 'A' |
|||||
BHLC12 |
3.50 |
Marine deposit |
17 |
4 |
21 |
26 |
0.08 |
not detected |
< Dutch 'A' |
|||||
BHLC13 |
0.75 |
Fill |
32 |
45 |
36 |
862 |
0.12 |
not detected |
Zn > Dutch B |
|||||
BHLC13 |
1.75 |
Fill |
9 |
21 |
130 |
101 |
0.3 |
not detected |
< Dutch 'A' |
|||||
BHLC13 |
2.75 |
Fill |
9 |
36 |
173 |
114 |
0.07 |
not detected |
Pb > Dutch B |
|||||
BHLC13 |
5.00 |
Alluvium |
16 |
7 |
60 |
691 |
<0.05 |
- |
Zn > Dutch B |
|||||
BHLC14 |
0.50 |
Fill |
18 |
36 |
102 |
130 |
0.32 |
not detected |
< Dutch 'A' |
|||||
BHLC14 |
1.50 |
Fill |
8 |
26 |
306 |
218 |
0.14 |
not detected |
Pb > Dutch B |
|||||
BHLC14 |
3.00 |
Marine deposit |
25 |
11 |
59 |
72 |
1.1 |
- |
< Dutch 'A' |
|||||
BHLC15 |
0.50 |
Fill |
10 |
13 |
59 |
33 |
0.19 |
not detected |
< Dutch 'A' |
|||||
BHLC15 |
1.50 |
Fill |
9 |
25 |
140 |
122 |
0.1 |
not detected |
< Dutch 'A' |
|||||
BHLC15 |
3.00 |
Marine deposit |
26 |
16 |
65 |
89 |
1.1 |
- |
< Dutch 'A' |
Table 7‑5 Summary of chemical test results on ground water samples
Analyse |
Chromium |
Copper |
Lead |
Zinc |
TPH |
BTEX |
Phenols |
PAH's |
Classification |
Unit (In dry Wt basis) |
mg/kg |
mg/kg |
mg/kg |
mg/kg |
mg/kg |
mg/kg |
mg/kg |
mg/kg |
|
Reporting Limits |
1.0 |
1.0 |
1.0 |
10.0 |
various |
various |
0.1 |
various |
|
Dutch 'A' |
20 |
20 |
20 |
50 |
20 |
1 |
0.5 |
0.2 |
|
Dutch 'B' |
50 |
50 |
50 |
200 |
200 |
30 |
15 |
10 |
|
Dutch 'C' |
200 |
200 |
200 |
800 |
600 |
100 |
50 |
40 |
|
BHLC1 |
<1 |
<1 |
<1 |
<10 |
314 |
All BTEX are < reporting limits |
All Phenols are < reporting limits |
All polynuclear aromatics are <
reporting limits |
TPH above Dutch 'B' |
BHLC2 |
<1 |
1 |
<1 |
11 |
613 |
TPH above Dutch 'C' |
|||
BHLC3 |
<1 |
<1 |
<1 |
<10 |
310 |
TPH above Dutch 'B' |
|||
BHLC4 |
<1 |
<1 |
<1 |
<10 |
738 |
TPH above Dutch 'C' |
|||
BHLC5 |
2 |
10 |
<1 |
48 |
162 |
below Dutch 'B' |
|||
BHLC6 |
1 |
12 |
<1 |
24 |
389 |
TPH above Dutch 'B' |
|||
BHLC7 |
3 |
8 |
<1 |
38 |
391 |
TPH above Dutch 'B' |
|||
BHLC8 |
2 |
4 |
<1 |
<10 |
615 |
TPH above Dutch 'C' |
|||
BHLC9 |
2 |
9 |
<1 |
20 |
367 |
TPH above Dutch 'B' |
|||
BHLC10 |
3 |
6 |
<1 |
14 |
289 |
TPH above Dutch 'B' |
|||
BHLC11 |
<1 |
10 |
<1 |
<10 |
1568 |
TPH above Dutch 'C' |
|||
BHLC12 |
<1 |
2 |
<1 |
<10 |
399 |
TPH above Dutch 'B' |
|||
BHLC13 |
1 |
<1 |
<1 |
<10 |
510 |
TPH above Dutch 'B' |
|||
BHLC14 |
1 |
<1 |
<1 |
<10 |
206 |
TPH above Dutch 'B' |
|||
BHLC15 |
<1 |
<1 |
<1 |
<10 |
368 |
TPH above Dutch 'B' |
Table 7‑6 Summary of additional TPH test results on ground water samples
Analyse |
TPH |
Classification |
Unit (In dry Wt basis) |
mg/kg |
|
Reporting Limits |
various |
|
Dutch 'A' |
20 |
|
Dutch 'B' |
200 |
|
Dutch 'C' |
600 |
|
BHLC1 |
<LoR |
Below Dutch ‘A’ |
BHLC2 |
<LoR |
Below Dutch ‘A’ |
BHLC9 |
<LoR |
Below Dutch ‘A’ |
BHLC11 |
<LoR |
Below Dutch ‘A’ |
BHLC15 |
<LoR |
Below Dutch ‘A’ |
BHSQ6 |
<LoR |
Below Dutch ‘A’ |
BHSQ8 |
<LoR |
Below Dutch ‘A’ |
BHSQ10 |
<LoR |
Below Dutch ‘A’ |
LoR = Limit of
Reporting |
Results
of laboratory testing
Table 7‑7 Summary of land contamination locations
Location |
Depth |
Soil type |
Contaminant
exceeding Dutch ‘B’ criteria |
BHLC1 |
0.75 |
Fill |
Pb
& Zn |
BHLC2 |
1.25 |
Fill |
Pb |
BHLC2 |
3.00 |
Marine deposit |
Pb |
BHLC3 |
1.25 |
Marine deposit |
Zn |
BHLC7 |
0.75 |
Fill |
Zn |
BHLC9 |
0.75 |
Fill |
Zn |
BHLC9 |
1.25 |
Fill |
Pb
& Zn |
BHLC11 |
0.50 |
Fill |
Pb |
BHLC11 |
1.50 |
Fill |
Pb |
BHLC13 |
0.75 |
Fill |
Zn |
BHLC13 |
2.75 |
Fill |
Pb |
BHLC13 |
5.00 |
Alluvium |
Zn |
BHLC14 |
1.50 |
Fill |
Pb |
Assessment
of land contamination impacts
· health risks to site workers;
· disposal of contaminated soil, where encountered; and
· potential health risks to future users of the sites.
Health Risk to Site Workers
Disposal of Contaminated Soil
Potential Health Risks to
Future Users of the Site
Extent
and excavated volume of contaminated land
Remediation
of excavated contaminated material
Remediation
techniques
Immobilisation
- typical treatment process
Excavation/
landfilling - typical treatment process
Final
remediation option of contaminated material
Mitigation measures
·
Bulk
earth-moving equipment shall be used to minimise construction worker’s
potential contact with contaminated materials. Manual excavation shall be
avoided where possible.
·
Exposure to
any contaminated materials shall be minimised by use of appropriate clothing
and Personal Protective Equipment (PPE) such as gloves (when interacting
directly with contaminated material), preventing smoking and eating during such
activities, and providing adequate hygiene and washing facilities.
·
Vehicles
transporting contaminated materials shall be covered to limit potential dust
emissions, and truck bodies and tailgates shall be sealed to prevent any
discharge during transport or during wet conditions.
·
Only
reputable waste haulers shall be used to collect and transport any contaminated
material. Records of the quantities of
wastes generated and disposed of shall be maintained and procedures shall be
developed to ensure that illegal disposal of wastes does not occur.
·
The necessary
waste disposal permits shall be obtained from the appropriate authorities, in
accordance with the Waste Disposal Ordinance.
Wastewater shall be disposed of in accordance with the WPCO, and its
discharge license requirements.
Sediment Quality Environmental Legislation and Standards
Table 7‑8 Criteria for the chemical screening of sediment (from ETWB(W)TC 34/2002)
Contaminant |
Lower chemical exceedance level (LCEL) |
Upper chemical exceedance level (UCEL) |
Metals (mg/kg dry wt.) |
|
|
Cadmium (Cd) |
1.5 |
4 |
Chromium (Cr) |
80 |
160 |
Copper (Cu) |
65 |
110 |
Mercury (Hg) |
0.5 |
1 |
Nickel (Ni) |
40 |
40 |
Lead (Pb) |
75 |
110 |
Silver (Ag) |
1 |
2 |
Zinc (Zn) |
200 |
270 |
|
|
|
Metalloid
(mg/kg dry wt.) |
|
|
Arsenic (As) |
12 |
42 |
|
|
|
Organic-PAHs
(μg/kg dry wt.) |
|
|
Low molecular weight PAHs |
550 |
3060 |
High molecular weight PAHs |
1700 |
9600 |
|
|
|
Organic-non-PAHs
(μg/kg dry wt.) |
|
|
Total PCBs |
23 |
180 |
|
|
|
Organometallics
(TBT in interstitial water) |
|
|
Tributyltin (TBT) |
0.15 |
0.15 |
|
|
|
Table 7‑9 Criteria for classification of sediment (from ETWB(W)TC 34/2002)
Criteria |
Category |
All contaminant levels do not exceed the LCEL |
L |
One or more contaminant levels exceed the LCEL but none exceed the
UCEL |
M |
One or more contaminant levels exceed the UCEL |
H |
Table 7‑10 Criteria for disposal of sediment at sea
Results of
chemical screening |
Classification
category |
Results of
biological screening |
Disposal |
All
contaminant levels < LCEL |
L |
N/A |
Type 1 - open sea disposal |
One or more
contaminant levels > LCEL and < UCEL |
M |
Pass |
Type 1 - open sea disposal (dedicated
site) |
Fail |
Type 2 – confined marine disposal (e.g.
East Sha Chau mud pits) |
||
One or more
contaminant levels > UCEL |
H |
N/A |
Type 2 – confined marine disposal |
One or more
contaminant levels > 10 x LCEL |
H |
Pass |
Type 2 – confined marine disposal |
Fail |
Type 3 – special treatment / disposal to
be agreed with EPD |
Sediment Sampling and
Testing
Objectives of Sediment Sampling and Testing
(i) To
characterise the sediment quality (Study
Brief Section 3.9.3.4 (xx)).
(ii) To identify the categories of sediments which are to be disposed of in accordance with a permit issued under the Dumping at Sea Ordinance and to estimate their quantities (Study Brief Section 3.9.3.4 (xxi)).
Scope of Sediment Sampling
and Testing
Table 7‑11 Depth of marine sediment encountered and subsamples tested
Drilhole |
Ground
Level |
POND
DEPOSIT |
MARINE
DEPOSIT |
Depth of sub-sample tested (bgl) |
|||||
From |
To |
Thick |
From |
To |
Thick |
||||
(mPD) |
(mPD) |
(m) |
(mPD) |
(m) |
|||||
BH-SQ1 |
+2.69 |
- |
- |
- |
+0.69 |
-2.31 |
3.00 |
2.90 & 5.00 |
|
BH-SQ2 |
+2.69 |
- |
- |
- |
+2.69 |
-1.31 |
4.00 |
0.90, 1.90 &
2.90 |
|
BH-SQ3 |
+2.86 |
+1.86 |
+1.36 |
0.50 |
+1.36 |
-0.64 |
2.00 |
1.90 & 2.90 |
|
BH-SQ4 |
+2.94 |
- |
- |
- |
+0.94 |
-0.56 |
1.50 |
2.90 |
|
BH-SQ5 |
+3.29 |
- |
- |
- |
+1.79 |
-0.71 |
2.50 |
1.90 & 2.90 |
|
BH-SQ6 |
+3.22 |
- |
- |
- |
+2.22 |
-1.78 |
4.00 |
1.90, 2.90 &
5.00 |
|
BH-SQ7 |
+2.84 |
+0.84 |
+0.34 |
0.50 |
+0.34 |
-0.66 |
1.00 |
2.90 |
|
BH-SQ8 |
+3.15 |
+2.65 |
+2.15 |
0.50 |
+2.15 |
-0.85 |
3.00 |
0.90, 1.90 &
2.90 |
|
BH-SQ9 |
+2.78 |
+1.28 |
+0.78 |
0.50 |
+0.78 |
-1.22 |
2.00 |
1.90 & 2.90 |
|
BH-SQ10 |
+2.97 |
- |
- |
- |
+0.47 |
-1.53 |
2.00 |
2.90 |
|
BH-SQ11 |
+3.10 |
- |
- |
- |
+0.10 |
-0.90 |
1.00 |
3.50 |
|
BH-SQ12 |
+2.37 |
+2.37 |
+1.37 |
1.00 |
+1.37 |
-0.63 |
2.00 |
0.90 & 1.90 |
|
BH-LC3 |
+4.17 |
+3.17 |
+1.67 |
1.50 |
+1.67 |
-0.33 |
2.00 |
1.90 & 2.90 |
|
BH-LC4 |
+3.52 |
+3.02 |
+2.52 |
0.50 |
+2.52 |
-0.48 |
3.00 |
1.90 & 2.90 |
|
BH-LC5 |
+3.18 |
+2.68 |
+0.68 |
2.00 |
+0.68 |
-1.32 |
2.00 |
0.90, 1.90 &
2.90 |
|
BH-LC6 |
+2.48 |
+0.98 |
+0.48 |
0.50 |
+0.48 |
-1.52 |
2.00 |
0.90, 1.90 &
2.90 |
|
BH-LC7 |
+2.87 |
+1.37 |
+0.37 |
1.00 |
+0.37 |
-0.63 |
1.00 |
1.90 & 2.90 |
|
BH-LC8 |
+2.89 |
+1.39 |
+0.89 |
0.50 |
+0.89 |
-1.11 |
2.00 |
1.90 & 2.90 |
|
BH-LC9 |
+2.91 |
+1.41 |
+0.91 |
0.50 |
+0.91 |
-2.09 |
3.00 |
1.90, 2.90 &
5.00 |
|
BH-LC10 |
+2.78 |
+0.78 |
+0.28 |
0.50 |
+0.28 |
-0.72 |
1.00 |
1.90 & 2.90 |
|
BH-LC11 |
+3.29 |
+1.29 |
+0.29 |
1.00 |
+0.29 |
-1.61 |
1.90 |
2.90 & 5.00 |
|
BH-LC12 |
+3.44 |
+1.44 |
+0.44 |
1.00 |
- |
- |
- |
2.50 |
|
BH-LC13 |
+3.93 |
+0.93 |
+0.43 |
0.50 |
- |
- |
- |
3.25 |
|
Results of Chemical
Screening and Sediment Classification
Results of Biological
Screening
Table 7‑12 Samples for Tier III biological testing
Borehole Ref. |
Sample
depth (bgl) |
Classification
category |
LC5 |
1.9 |
M |
LC6 |
0.9 |
H * |
LC6 |
2.9 |
H * |
LC10 |
1.9 |
M |
LC12 |
2.5 |
H * |
LC13 |
3.25 |
M |
SQ12 |
0.9 |
M |
Table 7‑13 Results of Tier III Testing
Borehole
Ref. |
Sample depth (bgl) |
Pass/Fail |
||
10-day
amphipod1 |
20 day
polychaete2 |
48 hour
bivalve3 |
||
LC5 |
1.9 |
fail |
fail |
fail |
LC6 |
1.9 |
fail |
pass |
pass |
LC6 |
2.9 |
fail |
pass |
pass |
LC10 |
1.9 |
fail |
pass |
fail |
LC12 |
2.5 |
fail |
pass |
pass |
LC13 |
3.25 |
fail |
fail |
fail |
SQ12 |
0.9 |
fail |
fail |
fail |
1. Failure defined as mean survival in test sediment is
significantly different from reference sediment.
2. Failure defined as mean dry weight in test sediment is
significantly different from reference sediment.
3. Failure defined as mean survival in test sediment is
significantly different from reference sediment.
Table 7‑14 Results of Tier III Testing
Borehole Ref. |
Sample
depth (bgl) |
Tier
II Category |
Tier
III Test1 |
Disposal
route |
LC5 |
1.9 |
M |
Fail |
Type
2 (Confined Marine) |
LC6 |
0.9 |
H * |
Fail |
Type
3 (Special Treatment) |
LC6 |
2.9 |
H * |
Fail |
Type
3 (Special Treatment) |
LC10 |
1.9 |
M |
Fail |
Type
2 (Confined Marine) |
LC12 |
2.5 |
H * |
Fail |
Type
3 (Special Treatment) |
LC13 |
3.25 |
M |
Fail |
Type
2 (Confined Marine) |
SQ12 |
0.9 |
M |
Fail |
Type
2 (Confined Marine) |
1. Test
sample is classified as ‘fail’ if any Tier III test (see Table 7–13) fails.
Table 7‑15 Summary of chemical screening results and sediment classification
|
Silver |
Arsenic |
Cadmium |
Chromium |
Copper |
Nickel |
Lead |
Zinc |
Mercury |
Total PCB |
Low PAHs |
High PAHs |
Tributyltin |
Classification |
|
LCEL |
1 |
12 |
1.5 |
80 |
65 |
40 |
75 |
200 |
0.5 |
23 |
550 |
1700 |
0.15 |
||
UCEL |
2 |
42 |
4 |
160 |
110 |
40 |
110 |
270 |
1 |
180 |
3160 |
9600 |
0.15 |
||
10 x LCEL |
10 |
120 |
15 |
800 |
650 |
400 |
750 |
2000 |
5 |
230 |
5500 |
17000 |
|
||
BH-SQ1
|
2.90 |
0.3 |
48 |
<0.2 |
11 |
23 |
6 |
132 |
71 |
<0.05 |
All PCB congeners are <3 ug/kg limit of
reporting |
<550 |
<1700 |
N/A |
H |
BH-SQ1
|
5.00 |
0.2 |
21 |
<0.2 |
32 |
15 |
17 |
55 |
82 |
0.05 |
<550 |
<1700 |
N/A |
M |
|
BH-SQ2 |
0.90 |
0.2 |
15 |
<0.2 |
41 |
16 |
30 |
35 |
107 |
<0.05 |
<550 |
<1700 |
N/A |
M |
|
BH-SQ2
|
1.90 |
0.2 |
45 |
<0.2 |
36 |
17 |
21 |
54 |
93 |
<0.05 |
<550 |
<1700 |
N/A |
H |
|
BH-SQ2
|
2.90 |
0.2 |
15 |
<0.2 |
35 |
15 |
23 |
35 |
92 |
0.06 |
<550 |
<1700 |
N/A |
M |
|
BH-SQ3
|
1.90 |
0.2 |
17 |
<0.2 |
39 |
14 |
22 |
40 |
99 |
<0.05 |
<550 |
<1700 |
N/A |
M |
|
BH-SQ3
|
2.90 |
0.2 |
17 |
<0.2 |
35 |
13 |
18 |
43 |
87 |
<0.05 |
<550 |
<1700 |
N/A |
M |
|
BH-SQ4
|
2.90 |
0.2 |
31 |
<0.2 |
30 |
14 |
15 |
45 |
81 |
0.22 |
<550 |
<1700 |
N/A |
M |
|
BH-SQ5 |
1.90 |
0.2 |
21 |
<0.2 |
17 |
20 |
9 |
58 |
56 |
<0.05 |
<550 |
<1700 |
N/A |
M |
|
BH-SQ5 |
2.90 |
0.2 |
53 |
<0.2 |
53 |
17 |
18 |
113 |
84 |
<0.05 |
<550 |
<1700 |
N/A |
H |
|
BH-SQ6 |
1.90 |
0.3 |
99 |
<0.2 |
12 |
26 |
8 |
101 |
80 |
<0.05 |
<550 |
<1700 |
N/A |
H |
|
BH-SQ6 |
2.90 |
0.2 |
17 |
<0.2 |
27 |
12 |
15 |
49 |
74 |
0.06 |
<550 |
<1700 |
N/A |
M |
|
BH-SQ6 |
5.00 |
0.1 |
15 |
<0.2 |
81 |
12 |
40 |
39 |
68 |
0.06 |
<550 |
<1700 |
N/A |
M |
|
BH-SQ7 |
2.90 |
0.1 |
13 |
<0.2 |
27 |
12 |
17 |
38 |
75 |
<0.05 |
<550 |
<1700 |
N/A |
M |
|
BH-SQ8 |
0.90 |
0.2 |
48 |
<0.2 |
30 |
15 |
19 |
47 |
439 |
<0.05 |
<550 |
<1700 |
N/A |
H |
|
BH-SQ8 |
1.90 |
0.2 |
248 * |
<0.2 |
8 |
12 |
4 |
161 |
58 |
<0.05 |
<550 |
<1700 |
N/A |
H * |
|
BH-SQ8
|
2.90 |
0.2 |
55 |
<0.2 |
42 |
24 |
21 |
68 |
113 |
<0.05 |
<550 |
<1700 |
N/A |
H |
|
BH-SQ9 |
1.90 |
0.2 |
48 |
<0.2 |
26 |
14 |
17 |
47 |
80 |
<0.05 |
<550 |
<1700 |
N/A |
H |
|
BH-SQ9 |
2.90 |
0.1 |
13 |
<0.2 |
36 |
14 |
25 |
33 |
93 |
<0.05 |
<550 |
<1700 |
N/A |
M |
|
BH-SQ10
|
2.90 |
0.2 |
16 |
<0.2 |
29 |
11 |
14 |
41 |
73 |
<0.05 |
<550 |
<1700 |
N/A |
M |
|
BH-SQ11
|
3.50 |
0.2 |
16 |
<0.2 |
24 |
10 |
10 |
45 |
70 |
<0.05 |
<550 |
<1700 |
N/A |
M |
|
BH-SQ12 |
0.90 |
0.2 |
32 |
<0.2 |
36 |
19 |
20 |
47 |
106 |
<0.05 |
All PCB congeners are <3 ug/kg limit of
reporting |
<550 |
<1700 |
N/A |
M |
BH-SQ12 |
1.90 |
0.2 |
36 |
<0.2 |
37 |
20 |
24 |
53 |
89 |
<0.05 |
<550 |
<1700 |
N/A |
M |
|
BH-LC3 |
1.90 |
0.3 |
76 |
0.2 |
33 |
22 |
18 |
95 |
105 |
0.05 |
<550 |
<1700 |
N/A |
H |
|
BH-LC3 |
2.90 |
0.3 |
69 |
0.2 |
31 |
21 |
16 |
85 |
97 |
0.08 |
<550 |
<1700 |
N/A |
H |
|
BH-LC4 |
1.90 |
0.3 |
51 |
<0.2 |
34 |
17 |
15 |
53 |
88 |
<0.05 |
<550 |
<1700 |
N/A |
H |
|
BH-LC4 |
2.90 |
0.2 |
20 |
<0.2 |
31 |
13 |
18 |
45 |
86 |
<0.05 |
<550 |
<1700 |
N/A |
M |
|
BH-LC5 |
0.90 |
0.2 |
48 |
<0.2 |
23 |
23 |
13 |
82 |
184 |
0.07 |
<550 |
<1700 |
N/A |
H |
|
BH-LC5
|
1.90 |
0.2 |
36 |
0.3 |
37 |
16 |
21 |
61 |
115 |
0.08 |
<550 |
<1700 |
N/A |
M |
|
BH-LC5
|
2.90 |
0.2 |
32 |
<0.2 |
36 |
12 |
20 |
41 |
83 |
0.08 |
<550 |
<1700 |
N/A |
M |
|
BH-LC6 |
0.90 |
0.1 |
151 * |
<0.2 |
11 |
10 |
4 |
89 |
43 |
<0.05 |
<550 |
<1700 |
N/A |
H * |
|
BH-LC6 |
1.90 |
0.1 |
26 |
<0.2 |
25 |
13 |
14 |
42 |
358 |
<0.05 |
<550 |
<1700 |
N/A |
H |
|
BH-LC6 |
2.90 |
0.2 |
316 * |
<0.2 |
13 |
9 |
5 |
93 |
38 |
0.05 |
<550 |
<1700 |
N/A |
H * |
|
BH-LC7
|
1.90 |
0.3 |
77 |
0.3 |
19 |
15 |
12 |
73 |
118 |
0.07 |
<550 |
<1700 |
N/A |
H |
|
BH-LC7
|
2.90 |
0.2 |
60 |
0.3 |
33 |
23 |
20 |
62 |
140 |
0.1 |
<550 |
<1700 |
N/A |
H |
|
BH-LC8
|
1.90 |
0.3 |
175 * |
<0.2 |
18 |
28 |
6 |
58 |
639 |
0.05 |
<550 |
<1700 |
N/A |
H * |
|
BH-LC8
|
2.90 |
0.2 |
26 |
<0.2 |
28 |
14 |
16 |
42 |
83 |
<0.05 |
<550 |
<1700 |
N/A |
M |
|
BH-LC9
|
1.90 |
0.2 |
46 |
<0.2 |
9 |
37 |
3 |
154 |
448 |
<0.05 |
<550 |
<1700 |
N/A |
H |
|
BH-LC9 |
2.90 |
0.3 |
55 |
0.3 |
34 |
20 |
20 |
85 |
119 |
0.06 |
<550 |
<1700 |
N/A |
H |
|
BH-LC9 |
5.00 |
0.2 |
5 |
<0.2 |
24 |
19 |
8 |
85 |
39 |
0.06 |
<550 |
<1700 |
N/A |
M |
|
BH-LC10 |
1.90 |
0.2 |
25 |
<0.2 |
30 |
16 |
17 |
52 |
115 |
<0.05 |
<550 |
<1700 |
N/A |
M |
|
BH-LC10 |
2.90 |
0.2 |
23 |
<0.2 |
30 |
14 |
15 |
57 |
84 |
<0.05 |
<550 |
<1700 |
N/A |
M |
|
BH-LC11
|
2.90 |
0.2 |
35 |
<0.2 |
27 |
12 |
17 |
38 |
75 |
0.08 |
<550 |
<1700 |
N/A |
M |
|
BH-LC11
|
5.00 |
0.2 |
70 |
<0.2 |
26 |
16 |
14 |
50 |
74 |
0.06 |
<550 |
<1700 |
N/A |
H |
|
BH-LC12
|
2.50 |
0.2 |
186 |
<0.2 |
12 |
35 |
4 |
140 |
54 |
<0.05 |
All PCB < LoR |
<550 |
<1700 |
N/A |
H * |
BH-LC13
|
3.25 |
0.2 |
42 |
.2 |
8 |
23 |
3 |
104 |
103 |
<0.05 |
<550 |
<1700 |
N/A |
M |
|
Reference sediment |
0.2 |
8 |
<0.2 |
14 |
12 |
9 |
70 |
54 |
0.39 |
|
<550 |
<1700 |
<0.05 |
|
Sampling and Testing for
Potential Biogas
Objectives of Biogas
Sampling and Testing
Pond Deposit Sampling and Testing
Table 7‑16 Depth of pond deposit encountered and tested for TOC
Drillhole |
Ground Level |
POND DEPOSIT |
Depth of sub-sample tested for TOC (bgl) |
||
From |
To |
Thick |
|||
(mPD) |
(mPD) |
(m) |
|||
BH-SQ3 |
+2.86 |
+1.86 |
+1.36 |
0.50 |
1.25 |
BH-SQ7 |
+2.84 |
+0.84 |
+0.34 |
0.50 |
2.25 |
BH-SQ8 |
+3.15 |
+2.65 |
+2.15 |
0.50 |
0.90 |
BH-SQ9 |
+2.78 |
+1.28 |
+0.78 |
0.50 |
1.90 |
BH-SQ12 |
+2.37 |
+2.37 |
+1.37 |
1.00 |
0.25 & 0.90 |
BH-LC1 |
+4.43 |
+2.43 |
+1.43 |
1.00 |
2.50 |
BH-LC2 |
+4.13 |
+2.63 |
+2.13 |
0.50 |
1.75 |
BH-LC3 |
+4.17 |
+3.17 |
+1.67 |
1.50 |
1.25 & 1.90 |
BH-LC4 |
+3.52 |
+3.02 |
+2.52 |
0.50 |
0.75 |
BH-LC5 |
+3.18 |
+2.68 |
+0.68 |
2.00 |
0.90 & 1.90 |
BH-LC6 |
+2.48 |
+0.98 |
+0.48 |
0.50 |
0.90 & 1.90 |
BH-LC7 |
+2.87 |
+1.37 |
+0.37 |
1.00 |
1.90 |
BH-LC8 |
+2.89 |
+1.39 |
+0.89 |
0.50 |
1.90 |
BH-LC9 |
+2.91 |
+1.41 |
+0.91 |
0.50 |
1.90 |
BH-LC10 |
+2.78 |
+0.78 |
+0.28 |
0.50 |
1.90 |
BH-LC11 |
+3.29 |
+1.29 |
+0.29 |
1.00 |
2.90 |
BH-LC12 |
+3.44 |
+1.44 |
+0.44 |
1.00 |
2.50 |
BH-LC13 |
+3.93 |
+0.93 |
+0.43 |
0.50 |
3.25 |
BH-LC15 |
+2.94 |
+0.94 |
-0.06 |
1.00 |
2.25 |
|
|
Average
thickness (m) |
0.59 |
|
Results of Spike Survey and
TOC Testing
Table 7‑17 Results of Gas Spike Test Survey
Spike ref. |
Gas
reading (% v/v) |
Spike ref. |
Gas reading (% v/v) |
||||||
CH4 |
CO2 |
O2 |
ºC |
CH4 |
CO2 |
O2 |
ºC |
||
SS1 |
0.0 |
0.6 |
19.4 |
30.3 |
SS46 |
0.0 |
0.0 |
19.9 |
36.6 |
SS2 |
0.0 0.0 |
0.0 0.1 |
19.4 19.7 |
24.71 31.63 |
SS47 |
0.0 |
0.3 |
19.6 |
30.0 |
SS3 |
0.0 0.0 |
0.4 0.2 |
18.8 19.7 |
24.51 31.53 |
SS48 |
0.0 |
0.3 |
20.1 |
29.3 |
SS4 |
0.0 0.0 |
0.3 0.2 |
18.9 19.7 |
25.01 32.83 |
SS49 |
0.0 |
0.0 |
19.5 |
34.8 |
SS5 |
0.0 0.0 |
0.2 0.0 |
20.0 19.9 |
24.61 29.53 |
SS50 |
0.0 0.0 |
0.0 0.0 |
19.4 19.9 |
34.64 28.72 |
SS6 |
0.0 |
0.0 |
19.6 |
32.8 |
SS51 |
0.0 0.0 |
0.0 0.0 |
19.5 19.9 |
35.44 33.32 |
SS7 |
0.0 |
0.0 |
19.9 |
24.6 |
SS52 |
0.0 0.0 |
0.0 1.3 |
19.3 18.3 |
35.14 33.52 |
SS8 |
0.0 |
4.3 |
17.8 |
25.3 |
SS53 |
0.0 |
0.0 |
19.7 |
31.6 |
SS9 |
0.0 |
0.0 |
19.2 |
30.0 |
SS54 |
0.0 0.0 |
0.0 0.0 |
19.9 20.0 |
33.02 28.63 |
SS10 |
0.0 |
0.0 |
19.6 |
29.6 |
SS55 |
0.0 |
0.0 |
19.8 |
33.2 |
SS11 |
0.0 |
4.1 |
19.1 |
28.7 |
SS56 |
0.0 |
0.0 |
19.8 |
33.9 |
SS12 |
0.0 |
0.0 |
20.0 |
24.5 |
SS57 |
0.0 |
0.0 |
19.8 |
27.1 |
SS13 |
0.0 |
0.0 |
20.0 |
24.5 |
SS58 |
0.0 0.0 |
0.0 0.0 |
19.4 19.6 |
34.84 33.92 |
SS14 |
0.0 |
0.0 |
19.9 |
24.6 |
SS59 |
0.0 |
0.0 |
19.9 |
30.3 |
SS15 |
0.0 |
0.0 |
19.9 |
25.2 |
SS60 |
0.0 |
0.0 |
19.8 |
31.6 |
SS16 |
0.0 |
0.5 |
19.9 |
25.0 |
SS61 |
0.0 |
0.0 |
19.6 |
31.2 |
SS17 |
0.0 |
0.0 |
19.9 |
28.9 |
SS62 |
0.0 |
0.0 |
19.7 |
33.3 |
SS18 |
0.0 |
0.3 |
19.8 |
25.2 |
SS63 |
0.0 |
0.0 |
19.8 |
31.5 |
SS19 |
0.0 |
0.1 |
19.9 |
24.6 |
SS64 |
0.0 |
0.0 |
19.8 |
29.8 |
SS20 |
0.0 |
0.5 |
19.7 |
24.8 |
SS65 |
0.0 |
0.0 |
19.9 |
33.1 |
SS21 |
0.0 0.0 |
10.7 0.3 |
10.20 19.7 |
26.701 24.83 |
SS66 |
0.0 |
0.0 |
20.0 |
27.5 |
SS22 |
0.0 |
0.0 |
19.9 |
25.1 |
SS67 |
0.0 0.0 |
0.4 0.8 |
19.0 18.6 |
34.14 32.92 |
SS23 |
0.0 |
0.0 |
19.9 |
24.7 |
SS68 |
0.0 |
0.0 |
20.0 |
35.1 |
SS24 |
0.0 |
0.5 |
19.7 |
29.5 |
SS69 |
0.0 |
0.0 |
19.7 |
33.9 |
SS25 |
0.0 |
0.3 |
19.5 |
26.9 |
SS70 |
0.0 |
1.0 |
19.6 |
29.0 |
SS26 |
0.0 |
0.2 |
19.8 |
26.3 |
SS71 |
0.0 |
1.5 |
18.8 |
26.4 |
SS27 |
0.0 |
0.6 |
19.6 |
26.8 |
SS72 |
0.0 |
0.2 |
20.0 |
25.8 |
SS28 |
0.0 |
0.0 |
19.9 |
26.6 |
SS73 |
0.0 |
1.2 |
19.3 |
25.1 |
SS29 |
0.0 |
0.1 |
19.9 |
26.7 |
SS74 |
0.0 |
1.4 |
19.2 |
25.3 |
SS30 |
0.0 |
0.0 |
19.9 |
26.2 |
SS75 |
0.0 |
1.7 |
18.9 |
25.9 |
SS31 |
0.0 |
0.0 |
20.0 |
28.5 |
SS76 |
0.0 0.0 |
0.0 0.0 |
19.2 20.0 |
34.34 30.92 |
SS32 |
0.0 0.0 |
0.0 0.0 |
19.5 19.9 |
37.24 27.41 |
SS77 |
0.0 0.0 |
0.0 0.0 |
19.4 19.7 |
35.24 30.22 |
SS33 |
0.0 0.0 |
0.0 0.0 |
19.7 19.9 |
32.74 26.21 |
SS78 |
0.0 |
0.0 |
19.5 |
32.5 |
SS34 |
0.0 0.0 |
0.0 0.0 |
19.9 19.9 |
29.01 28.23 |
SS79 |
0.0 0.0 |
0.2 0.3 |
19.1 19.3 |
35.74 34.12 |
SS35 |
0.0 |
0.4 |
19.5 |
29.9 |
SS80 |
0.0 |
0.0 |
19.7 |
30.4 |
SS36 |
0.0 |
0.0 |
19.9 |
30.3 |
SS81 |
0.0 0.0 |
0.0 0.1 |
19.4 19.8 |
35.44 30.82 |
SS37 |
0.0 |
0.5 |
19.6 |
27.3 |
SS82 |
0.0 |
0.2 |
19.6 |
32.4 |
SS38 |
0.0 0.0 |
0.0 0.0 |
19.9 20.1 |
27.41 29.33 |
SS83 |
0.0 |
0.3 |
18.9 |
32.2 |
SS39 |
1.2 0.0 |
1.6 0.0 |
19.3 20.1 |
26.62 29.13 |
SS84 |
0.0 |
0.1 |
19.1 |
33.1 |
SS40 |
0.0 |
0.1 |
19.5 |
34.8 |
SS85 |
0.0 |
0.0 |
19.5 |
32.7 |
SS41 |
0.0 0.0 |
0.0 0.0 |
19.1 19.6 |
35.24 28.11 |
SS86 |
0.0 0.0 |
0.0 0.0 |
19.3 19.5 |
37.34 33.42 |
SS42 |
0.0 |
0.0 |
19.8 |
32.5 |
SS87 |
0.0 |
0.0 |
19.6 |
31.9 |
SS43 |
0.0 0.0 |
0.0 0.5 |
19.7 19.5 |
32.44 33.62 |
SS88 |
0.0 0.0 |
0.0 0.0 |
19.4 19.6 |
34.24 33.62 |
SS44 |
0.0 |
0.0 |
19.9 |
33.4 |
SS89 |
0.0 |
0.0 |
19.7 |
33.8 |
SS45 |
0.0 |
0.0 |
19.8 |
34.8 |
|
|
|
|
|
Notes:
1
2
3
4
Table 7‑18 Results of TOC Testing on Pond Mud
Drillhole |
Sample
depth (bgl) |
Laboratory test result |
|
Moisture content (%) |
Total organic content (TOC) (bgl) |
||
BH-SQ3 |
1.25 |
20.70 |
0.69 |
BH-SQ7 |
2.25 |
30.00 |
1.14 |
BH-SQ8 |
0.90 |
27.30 |
2.13 |
BH-SQ9 |
1.90 |
19.70 |
0.62 |
BH-SQ12 |
0.90 |
43.60 |
4.08 |
BH-SQ12 |
0.90 |
42.10 |
4.40 |
BH-LC1 |
2.50 |
19.40 |
1.05 |
BH-LC2 |
1.75 |
18.70 |
0.62 |
BH-LC3 |
1.25 |
26.10 |
1.08 |
BH-LC3 |
1.90 |
33.80 |
1.53 |
BH-LC4 |
0.75 |
22.50 |
1.48 |
BH-LC5 |
0.90 |
28.20 |
1.74 |
BH-LC5 |
1.90 |
30.70 |
2.09 |
BH-LC6 |
0.90 |
18.70 |
1.17 |
BH-LC6 |
1.90 |
37.80 |
2.17 |
BH-LC7 |
1.90 |
29.40 |
2.05 |
BH-LC8 |
1.90 |
27.70 |
1.80 |
BH-LC9 |
1.90 |
18.70 |
0.49 |
BH-LC10 |
1.90 |
36.60 |
2.05 |
BH-LC11 |
2.90 |
33.70 |
1.43 |
BH-LC12 |
2.50 |
20.30 |
0.64 |
BH-LC13 |
3.25 |
18.90 |
0.78 |
BH-LC15 |
2.25 |
13.40 |
0.52 |
Average (%): |
27.10% |
1.56% |
Assessment of Potential
Biogas Generation
Q T, x |
= |
K Rx Lo e-K(T-x) ,
where |
|
|
|
Q T, x |
= |
the amount of methane generated in
current time T by waste Rx |
x |
= |
year of waste input |
Rx |
= |
amount of waste input in year |
T |
= |
current year |
dQ |
= |
A e-bt , where |
dT |
||
|
|
|
Q |
= |
the amount of methane generated |
t |
= |
time in years since start of
emission of CH4 |
A & b |
= |
constants with respect to time |
b |
= |
Ln 2 |
T |
||
|
|
|
A |
= |
V |
b |
Peak annual CH4 potential
(kg) |
= |
V |
(1 - |
1 |
) |
(1) |
T √2 |
% of total methane after
t years |
= |
( |
1 |
- |
2 –t/T |
) |
(2) |
Volume of mud left in-situ = Total site area x depth of pond mud
= 21.36 ha x 0.6 m
= 128,160 m3
Table 7‑19 Assessment of Biogas potential using TOC results
|
Half-life of 5 years |
Half-life of 2 years |
Basis of calculation |
Volume (m3) |
128,200 |
128,200 |
Total Area x
thickness |
Density (Kg m-3) |
1,590 |
1,590 |
Assumed from
previous works |
Dry Matter (%
w/w) |
72.90 |
72.90 |
Calculated from
Laboratory Works |
Dry Matter (Kgm-3) |
1,159 |
1,159 |
Density x Dry
Matter (% w/w) |
TOC (%) |
1.56 |
1.56 |
From Laboratory
Tests |
TOC (kg m-3) |
18.08 |
18.08 |
Dry Matter
(Kgm-3) x TOC (%)/100 |
CH4
potential (Kg m-3) |
12.12 |
12.12 |
TOC x 0.67 ( 2C
-> CH4+CO2, so methane potential =(12+4)/(2x12)
=0.67 times TOC |
Peak annual CH4
potential (Kg) |
300,080.27 |
678,963.76 |
Equation (1)
above |
Total area (m2) |
213,600 |
213,600 |
Measured from
layout drawing |
Total potential
CH4 flux (kgm-2 per year) |
1.40 |
3.18 |
Peak Annual CH4
potential/ Total Area |
Total potential
CH4 flux (gm-2 per year) |
1,405 |
3,179 |
Total potential
CH4 flux (kgm-2 per year) x 1000 |
Total potential
CH4 flux (mol m-2 per year) |
87.8 |
198.7 |
Gm-2
per year/16 |
Total potential
CH4 flux (L m-2 per year) |
1,966.82 |
4,450.14 |
mol m-2
per year x 22.4 |
Total potential
CH4 flux (L m-2 per day) |
5.39 |
12.19 |
Lm-2
per year/365 |
Total potential
CH4 concentration (% v/v), assuming 100% of TOC biodegradable |
0.54 |
1.219 |
Lm-2
per day/10 |
Table 7‑20 Percentage % of methane emitted after June 2006
|
Year |
|||
Half-life (years) |
1 |
2 |
3 |
4 |
0.5 |
75% |
94% |
98% |
100% |
1 |
50% |
75% |
88% |
94% |
1.5 |
37% |
60% |
75% |
84% |
2 |
29% |
50% |
65% |
75% |
2.5 |
24% |
43% |
56% |
67% |
3 |
21% |
37% |
50% |
60% |
3.5 |
18% |
33% |
45% |
55% |
4 |
16% |
29% |
41% |
50% |
Table 7‑21 Maximum potential CH4 generation in June 2008
Half-life (years) |
0.5 |
1 |
1.5 |
2 |
2.5 |
3 |
4 |
5 |
Peak annual CH4 potential (kg) |
1,738,555 |
1,159,037 |
857,687 |
678,964 |
561,433 |
478,412 |
368,955 |
300,080 |
Total potential CH4 flux (L m-2
per day) |
31.21 |
20.81 |
15.40 |
12.19 |
10.08 |
8.59 |
6.62 |
5.39 |
Total potential CH4
concentration (% v/v) |
3.12 |
2.08 |
1.54 |
1.22 |
1.01 |
0.86 |
0.66 |
0.54 |
Potential CH4 concentration (%
v/v) after two years (June 2006 to June 2008) |
0.195 |
0.520 |
0.611 |
0.609 |
0.579 |
0.541 |
0.446 |
0.381 |
Assessment of Impacts
Sediment Excavation
Table 7‑22 Estimated volume and classification of excavated sediment
Location |
Area
|
Volume
of contaminated material to be excavated |
|
Category
M |
Category
H |
||
Wetland
restoration area |
1,200 m2 |
520 m3 |
0 |
Wetland
restoration area |
2,400 m2 |
0 |
1,620 m3 |
Total: |
2,140 m3 |
Release of Contaminants
during Excavation
Disposal of Excavated
Sediment at Sea
Reuse of Excavated
Sediment on Site
Cumulative Impacts
Potential Problem of
Biogas on Reclamation (Pond Filling)
Mitigation Measures
Soil excavation and
stockpiling
Disposal of Excavated
Sediment at Sea
· Bottom opening transport vessels should be fitted with tight fitting seals to prevent leakage of material. Excess material should be cleaned from the decks and exposed fittings of vessels before the vessel is moved.
· Monitoring of the vessel loading should be conducted to ensure that loss of material does not take place during transportation. Transport vessels should be equipped with automatic self-monitoring devices as specified by the DEP.
Sediment Quality and Potential Biogas
PREFACE
Wo Shang Wai to the north
of Royal Palms and
The planning intention of
this location is to provide incentive for the restoration of degraded wetlands
adjoining existing fish ponds and to encourage the phasing out of sporadic open
storage and port back-up uses on degraded wetland. This can be achieved through comprehensive
residential and/or recreational development to include wetland restoration
area. Development or redevelopment schemes
on the degraded wetlands directly adjoining the existing continuous and
contiguous fish ponds should include wetland restoration and buffer proposals
to separate the development from and minimize its impact on the fish pond
areas. Any new building should be
located farthest away from
Mai Po Inner Deep Bay Ramsar Site
Wetland Conservation Area
(WCA)
Wetland Buffer Area
Sites of Special Scientific
Interest and Mai Po Nature Reserve
Egretries
Habitats
Floral survey
Mammals
Birds
Transect counts
Egretries
On-site Flight path Counts
for non-breeding birds
Herpetofauna (Amphibians and Reptiles)
Fish
Butterflies / Dragonflies
Aquatic Invertebrates
Literature Review
Habitats/vegetation present within the Project Area
Grassland
Seasonal marsh
Freshwater marsh/reedbed
Drainage channels and
ditches
Developed area and Bare
ground
Habitats/vegetation present within the Assessment Area
Grassland
Seasonal marsh
Freshwater Marsh/Reedbed
Active and Abandoned
Fishponds
Drainage channels
Secondary
Active Dry Agricultural
Land
Inactive Dry Agricultural
Land
Wasteland
Developed Land
Table 8‑1 Habitats present in Project Area and Assessment Area
Habitat
type |
Project
Area |
Rest
of Assessment Area |
||
Area
(ha) |
% |
Area
(ha) |
% |
|
Grassland |
11.05 |
51.73 |
5.03 |
2.64 |
Seasonal
Marsh |
0.69 |
3.23 |
0.51 |
0.27 |
Freshwater
Marsh/Reedbed |
4.00 |
18.73 |
4.17 |
2.18 |
Active
Fishponds |
- |
- |
62.21 |
32.59 |
Abandoned
Fishponds |
- |
- |
18.71 |
9.80 |
Drainage
Channels/ Ditches |
0.81 |
3.79 |
4.46 |
2.34 |
Secondary
|
- |
- |
1.06 |
0.56 |
|
- |
- |
5.42 |
2.84 |
Active
Dry Agricultural Land |
- |
- |
0.79 |
0.41 |
Inactive
Dry Agricultural Land |
- |
- |
6.15 |
3.22 |
Wasteland |
- |
- |
1.03 |
0.54 |
Developed
Land & Bare Ground |
4.81 |
22.52 |
81.33 |
42.61 |
Total |
21.36 |
100 |
190.87 |
100 |
Mammals
Birds
Results of transect surveys
Table 8‑2 Mean and maximum number of individuals of bird species of conservation importance and wetland-dependent bird species recorded on morning transect counts in Project Area (PA) and in other parts of the Assessment Area (AA), April 2005-June 2006. (Level of Concern based on Fellowes et al. 2002)
Species |
Wetland-dependent |
Level of Concern |
Mean in PA† |
Max. in PA† |
Mean in other parts of AA† |
Max. in other parts of AA† |
Little Grebe Tachybaptus ruficollis |
Y |
LC |
- |
- |
0.5 |
3 |
Great Cormorant Phalacrocorax carbo |
Y |
PRC |
0.5 |
5 |
54.7 |
503 |
Grey Heron Ardea cinerea |
Y |
PRC |
0.1 |
2 |
2.8 |
11 |
Great Egret Egretta alba |
Y |
PRC (RC) |
X |
X |
3.4 |
22 |
Intermediate Egret Egretta intermedia |
Y |
RC |
- |
- |
0.4 |
4 |
Little Egret Egretta garzetta |
Y |
PRC (RC) |
5.5 |
48 |
31.5 |
123 |
Cattle Egret Bubulcus ibis |
Y |
(LC) |
1.3 |
14 |
6.4 |
60 |
Chinese Pond Heron Ardeola bacchus |
Y |
PRC (RC) |
1.3 |
4 |
5.4 |
13 |
Striated Heron Butorides striatus |
Y |
(LC) |
- |
- |
X |
X |
Black-crowned Night
Heron Nycticorax nycticorax |
Y |
(LC) |
0.2 |
4 |
0.2 |
1 |
Black-faced
Spoonbill Platalea minor |
Y |
PGC |
- |
- |
1.1 |
9 |
Northern Pintail Anas acuta |
Y |
RC |
- |
- |
1.7 |
21 |
Common Teal Anas crecca |
Y |
RC |
- |
- |
1.6 |
11 |
Eurasian Wigeon Anas penelope |
Y |
RC |
- |
- |
1.6 |
27 |
Osprey Pandion haliaetus |
Y |
RC |
- |
- |
0.1 |
1 |
Black Kite Milvus migrans |
N |
(RC) |
1.2 |
5 |
2.0 |
9 |
White-bellied Sea
Eagle Haliaeetus leucogaster |
Y |
(RC) |
- |
- |
X |
X |
Common Moorhen Gallinula chloropus |
Y |
- |
- |
- |
0.3 |
3 |
White-breasted
Waterhen Amaurornis phoenicurus |
Y |
- |
0.2 |
2 |
0.7 |
5 |
Oriental Pratincole Glareola maldivarum |
Y |
LC |
X |
X |
X |
X |
Little Ringed Plover Charadrius dubius |
Y |
(LC) |
0.1 |
1 |
0.1 |
1 |
Green Sandpiper Tringa ochropus |
Y |
- |
- |
- |
X |
X |
Common Sandpiper Actitis hypoleucos |
Y |
- |
0.2 |
1 |
1.4 |
6 |
Common Snipe Gallinago gallinago |
Y |
- |
0.1 |
1 |
0.1 |
1 |
Black-headed Gull Larus ridibundus |
Y |
PRC |
- |
- |
0.1 |
1 |
Pacific Swift Apus pacificus |
N |
(LC) |
X |
X |
X |
X |
Pied Kingfisher Ceryle rudis |
Y |
(LC) |
- |
- |
0.2 |
1 |
Common Kingfisher Alcedo atthis |
Y |
- |
- |
- |
0.5 |
5 |
White-throated
Kingfisher Halcyon smyrnensis |
Y |
(LC) |
- |
- |
0.4 |
2 |
White Wagtail Motacilla alba |
Y# |
- |
0.9 |
3 |
2.5 |
7 |
Grey Wagtail Motacilla cinerea |
Y |
- |
2.2 |
3 |
0.5 |
4 |
Yellow Wagtail Motacilla flava |
Y |
- |
10.0 |
151 |
0.3 |
2 |
Oriental Reed
Warbler Acrocephalus orientalis |
Y |
- |
0.1 |
1 |
- |
- |
Zitting Cisticola Cisticola juncidis |
Y# |
LC |
0.1 |
1 |
- |
- |
Red-billed Starling Sturnus sericeus |
Y# |
(RC)* |
0.9 |
15 |
119.3 |
821 |
White-shouldered
Starling Sturnus sinensis |
Y# |
(LC) |
0.1 |
2 |
X |
X |
Collared Crow Corvus torquatus |
Y# |
LC |
- |
- |
0.3 |
2 |
Y# - Species is not exclusively dependent on wetland habitats but is
usually found around wetlands in
X Species recorded in Project Area or Assessment Area, but not during
transect surveys.
† Mean values given are the mean number recorded on all transects; this
is included to indicate the relative importance of the site over the year,
reflecting the regularity of a species in the Project Area. Max. is the maximum
number of individuals recorded during any transects; this is included to
indicate whether single large flocks contribute towards the mean abundance.
* Red-billed Starling is considered by Fellowes et al. (2002) to
be of Global Concern. Since publication, however, the global population estimate
has been revised and the species is not now considered globally threatened
(BirdLife International 2007). A listing of Regional Concern (RC), based on the
importance of the large roosts present near
Monthly monitoring of waterbirds
by
Table 8‑3 Wetland-dependent bird species recorded in the Tam Kon Chau count area on monthly waterbird counts conducted by the Hong Kong Bird Watching Society, April 2005-March 2006 (data from Anon 2005, Anon 2006a)
Species |
Mean recorded |
Maximum |
Little Grebe Tachybaptus ruficollis |
10.8 |
24 |
Great Cormorant* Phalacrocorax carbo |
287.2 (5.5) |
3098 (32) |
Grey Heron Ardea cinerea |
2.7 |
10 |
Great Egret Egretta alba |
10.8 |
35 |
Intermediate Egret Egretta intermedia |
1.0 |
6 |
Little Egret Egretta garzetta |
74.7 |
229 |
Cattle Egret Bubulcus ibis |
5.5 |
61 |
Chinese Pond Heron Ardeola bacchus |
37.1 |
60 |
Black-crowned Night Heron Nycticorax nycticorax |
1.0 |
6 |
Eurasian Wigeon Anas penelope |
11.2 |
39 |
Northern Pintail Anas acuta |
0.5 |
6 |
Common Teal Anas crecca |
0.1 |
1 |
Osprey Pandion haliaetus |
0.2 |
1 |
Black Kite Milvus migrans |
0.5 |
4 |
Common Buzzard Buteo buteo |
0.1 |
1 |
White-breasted Waterhen Amaurornis phoenicurus |
2.1 |
6 |
Common Moorhen Gallinula chloropus |
10.0 |
29 |
Black-winged Stilt Himantopus himantopus |
0.5 |
6 |
Little Ringed Plover Charadrius dubius |
9.3 |
66 |
Marsh Sandpiper Tringa stagnatilis |
0.5 |
6 |
Green Sandpiper Tringa ochropus |
1.9 |
10 |
Wood Sandpiper Tringa glareola |
13.6 |
120 |
Common Sandpiper Actitis hypoleucos |
10.5 |
20 |
Common Snipe Gallinago gallinago |
0.1 |
1 |
Pied Kingfisher Ceryle rudis |
0.3 |
2 |
Common Kingfisher Alcedo atthis |
6.1 |
11 |
White-throated Kingfisher Halcyon smyrnensis |
2.0 |
8 |
Black-capped Kingfisher Halcyon pileata |
0.1 |
1 |
Red-billed Starling Sturnus sericeus |
6.2 |
57 |
Collared Crow Corvus torquatus |
0.8 |
4 |
* The Tam Kon Chau
count area includes ponds adjacent to the large roost of Great Cormorant at Mai
Po Nature Reserve; the exceptionally high count of 3098 Great Cormorants in
January 2006 undoubtedly included some roosting birds. Values in parentheses
discount the results of the count on that date.
Breeding Season
Observations of Foraging Egrets
Egretry flight path surveys
Table 8‑4 Heights of ardeids flying over the Project Area, June 2006
Species |
0-5 m |
6-10 m |
11-15 m |
16-20 m |
21-50 m |
Total |
Little Egret Egretta garzetta |
2 |
– |
– |
4 |
– |
6 |
Chinese Pond Heron Ardeola bacchus |
– |
2 |
– |
1 |
1 |
4 |
Total |
2 |
2 |
0 |
5 |
1 |
10 |
On-site Flight path Surveys
during the Wet Season
Table 8‑5 Summary of birds using Flight paths 1, 2 and 3, May-June 2006
Species |
Flight path 1 |
Flight path 2 |
Flight path 3 |
Total |
Little Egret Egretta garzetta |
2 |
5 |
1 |
8 |
Chinese Pond Heron Ardeola bacchus |
8 |
2 |
1 |
11 |
Total |
10 |
7 |
2 |
19 |
On-site Flight path Surveys during
the Dry Season
Herpetofauna
Table 8‑6 Relative abundance of herpetofauna species recorded in the Project Area and in other parts of the Assessment Area, April 2005 – June 2006
Species |
Project Area |
Other parts of Assessment Area |
Asian Common Toad Bufo melanostictus |
+ |
++ |
Brown Tree Frog Polypedates megacephalus |
+ |
|
Günther’s Frog Rana guentheri |
+ |
++ |
Paddy Frog Fejervarya limnocharis |
++ |
|
Ornate Pigmy Frog Microhyla ornata |
+ |
|
Chinese Striped
Terrapin* Ocadia sinensis |
+ |
|
Checkered Keelback Xenochrophis piscator |
|
+ |
Long-tailed Skink Mabuya
longicaudata |
|
+ |
+ 1-5 individuals,
++ 6-10 individuals
* The Chinese
Striped Terrapin recorded in the Project Area is considered to relate to an
escaped individual.
Fish
Table 8‑7 Relative abundance of fish species recorded in Project Area and in the drainage channel by Palm Springs, April 2005 – June 2006.
Species |
Project Area |
Channel by |
Tilapia
sp. Oreochromis sp. |
++++ |
+++++ |
Mosquito
Fish Gambusia affinis |
++++ |
++++ |
Snakehead
Murrel Channa striata |
++ |
|
Snakehead Channa sp. |
|
+ |
Swampy
Eel Monopterus albus |
+ |
|
Catfish
sp. Clarius sp. |
+ |
+ |
Common
Carp Cyprinus carpio |
|
+ |
+ 1-3 individuals,
++ 4-6 individuals, +++ 7-10 individuals, ++++ >10 individuals, +++++
>1000 individuals
Butterflies
Table 8‑8 Butterfly species recorded
in the Project Area (PA) and in other parts of the Assessment Area (AA) during
surveys, May 2005 – June 2006.
Species |
Level of concern |
Mean in PA |
Maximum in PA |
Mean in other parts of AA |
Maximum in other parts of AA |
Formosan Swift Borbo cinnara |
|
0.1 |
1 |
|
|
Skipper sp. Hesperiidae sp. |
|
|
|
0.1 |
1 |
Common Jay Graphium doson |
|
0.1 |
1 |
|
|
Common Mime Chilasa clytia |
|
0.1 |
1 |
|
|
Common Mormon Papilio polytes |
|
|
|
0.1 |
3 |
Great Mormon Papilio memnon |
|
0.1 |
1 |
|
|
Papilio paris |
|
0.2 |
1 |
0.2 |
2 |
Red-base Jezebel Delias pasithoe |
|
0.1 |
1 |
0.1 |
1 |
Indian Cabbage White Pieris canidia |
|
7.7 |
33 |
1.5 |
6 |
Yellow Ixias pyrene |
|
0.1 |
1 |
0.1 |
1 |
Mottled Emigrant Catopsilia pyranthe |
|
0.3 |
1 |
0.1 |
1 |
Lemon Emigrant Catopsilia |
|
0.2 |
2 |
|
|
Common Grass Yellow Eurema hecabe |
|
3.1 |
18 |
0.5 |
2 |
Pale Grass Blue Zizeeria maha |
|
0.3 |
3 |
0.1 |
1 |
Lime Blue Chilades lajus |
|
0.3 |
4 |
|
|
Dark-brand Bush Brown Mycalesis mineus |
|
0.2 |
2 |
|
|
Straight Five-ring Ypthima lisandra |
|
0.1 |
1 |
|
|
Large Faun Faunis eumeus |
|
0.2 |
1 |
|
|
Angled Castor Ariadne ariadne |
|
0.1 |
1 |
|
|
Rustic Cupha erymanthis |
|
|
|
0.1 |
1 |
Great Egg-fly Hypolimnas
bolina |
|
0.1 |
1 |
0.1 |
1 |
Danaid Egg-fly Hypolimnas
misippus |
LC |
0.1 |
1 |
0.1 |
1 |
Southern Sullied Sailer Neptis clinia |
|
|
|
0.1 |
1 |
White-edged Blue Baron Euthalia phemius |
|
0.1 |
1 |
|
|
Blue-spotted Crow Euploea midamus |
|
0.1 |
1 |
|
|
Dragonflies
Table 8‑9 Dragonfly species recorded in the Project Area (PA) and in other parts of the Assessment Area (AA) during surveys, May 2005 – June 2006.
Species |
Level of concern |
Mean in PA |
Maximum in PA |
Mean in other parts of AA |
Maximum in other parts of AA |
Orange-tailed Midget Agiocnemis femina |
|
0.7 |
4 |
0.2 |
2 |
Orange-tailed Sprite Ceriagrion auranticum |
|
0.4 |
3 |
0.2 |
2 |
Common Bluetail Ischnura senegalensis |
|
3.0 |
13 |
11.2 |
129 |
Black Threadtail Prodasineura autumnalis |
|
0.5 |
5 |
|
|
Lesser Emperor Anax parthenope |
|
0.2 |
2 |
|
|
Asian Widow Palpopleura sexmaculata |
|
0.2 |
1 |
|
|
Asian Amberwing Brachythemis contaminata |
|
4.5 |
41 |
5.7 |
57 |
Crimson Darter Crocothemis servilia |
|
1.1 |
7 |
0.5 |
4 |
Blue Percher Diplacodes trivialis |
|
0.3 |
3 |
|
|
Pied Percher Neurothemis tullia |
|
8.1 |
67 |
0.1 |
1 |
Blue Skimmer sp.* Orthetrum sp. |
|
1.4 |
12 |
0.3 |
3 |
Common Red Skimmer Orthetrum pruinosum |
|
1.5 |
6 |
0.4 |
5 |
Green Skimmer Orthetrum sabina |
|
4.5 |
15 |
0.6 |
4 |
Wandering Glider Pantala flavescens |
|
4.5 |
29 |
1.0 |
6 |
Variegated Flutterer Rhyothemis variegata |
|
5.5 |
17 |
3.8 |
43 |
Evening Skimmer Tholymis tillarga |
|
0.1 |
1 |
0.3 |
2 |
Saddlebag Glider Tramea virginia |
|
|
|
0.1 |
1 |
Crimson Dropwing Trithemis aurora |
|
0.9 |
6 |
|
|
Scarlet Basker Urothemis signata |
LC |
0.3 |
2 |
|
|
* Three species of blue skimmer may occur on
site: Common Blue Skimmer Orthetrum
glaucum, Lesser Blue Skimmer Orthetrum
triangulare and Marsh Skimmer Orthetrum
luzonicum.
Aquatic Invertebrates
Table 8‑10 Number of aquatic invertebrates recorded from sampling locations around the Project Area, 2005-2006.
Taxon |
Sampling Location D1 |
Sampling Location D2 |
Sampling Location D3 |
|||||||||
29
Nov |
19
Dec |
9
Apr |
23
May |
29
Nov |
19
Dec* |
9
Apr |
23
May |
29
Nov |
19
Dec |
9
Apr |
23
May |
|
Diptera |
|
|
|
|
|
|
|
|
|
|
|
|
Chironomus
sp. |
11 |
18 |
4 |
2 |
2 |
410 |
5 |
11 |
6 |
2 |
6 |
11 |
Other Chironominae sp. |
21 |
25 |
189 |
17 |
8 |
70 |
5 |
18 |
14 |
15 |
12 |
19 |
Tipula sp. |
2 |
|
|
|
|
|
|
|
|
|
|
|
Odonata |
|
|
|
|
|
|
|
|
|
|
|
|
Ischnura sp. |
19 |
1 |
3 |
|
1 |
|
|
|
5 |
1 |
|
|
Trithemis sp. |
|
|
|
2 |
|
|
12 |
3 |
1 |
|
4 |
2 |
Mollusca |
|
|
|
|
|
|
|
|
|
|
|
|
Melanoides tuberculata |
|
|
|
9 |
88 |
3 |
35 |
24 |
70 |
1 |
126 |
3 |
Pomacea lineata |
|
|
|
15 |
10 |
|
7 |
|
9 |
15 |
4 |
|
Sinotaia quadrata |
|
|
|
|
|
|
14 |
|
|
|
2 |
|
Radix plicatulus |
|
|
1 |
|
|
|
|
|
|
|
|
|
Biomphalaria straminea |
|
|
|
|
|
|
2 |
|
|
|
|
|
Hippeutis cantonensis |
|
|
|
|
|
|
1 |
|
|
|
2 |
|
Oligochaeta spp. |
|
68 |
|
23 |
4 |
7 |
13 |
13 |
5 |
73 |
2 |
5 |
Crustacea |
|
|
|
|
|
|
|
|
|
|
|
|
Caridina cantonensis |
|
|
|
|
3 |
|
|
|
2 |
|
|
|
Total
Invertebrates |
53 |
112 |
197 |
68 |
116 |
490 |
94 |
69 |
112 |
107 |
158 |
40 |
* Samples at
D2 collected from a slightly different location on 19th December,
because original location contained no water.
Grassland
Table 8‑11 Ecological Evaluation of Grassland Habitats
Criteria |
Grassland in Project Area |
Other Grassland in Assessment Area |
Naturalness |
Habitat derived from filling of fishponds and
disturbed by annual maintenance work. |
Mostly derived from succession on engineered slopes,
with some natural hillside grassland. |
Size |
Medium,
about 11.05 ha. |
Small,
about 5.03 ha. |
Diversity |
Low
plant species diversity, dominated by non-native species. Moderate faunal
diversity (33 bird species, 9 dragonfly species, 10 butterfly species). |
Plant
species diversity low and community structure simple. |
Rarity |
A fairly common habitat on filled land and fishpond
bunds. Small numbers of five bird species of conservation importance
recorded. |
A common habitat type in |
Re-creatability |
Easily
re-creatable. |
Easily
re-creatable. |
Fragmentation |
Not fragmented within the Project Area. Similar
habitat located on bunds around adjacent fishponds. |
Not fragmented within the Assessment Area. |
Ecological linkage |
Ecological linkage with adjacent wetland habitats,
especially fishponds. |
Ecologically linked to adjacent grassland and shrubland
outside the Assessment Area. |
Potential value |
Has the potential to be enhanced if vegetation was
suitably managed, although such a management regime is unlikely in practice. |
Potential to develop into more diverse shrubland if
left undisturbed though remoteness from seed sources is likely to reduce
potential shrub species diversity. |
Nursery/ breeding ground |
Not known to be a significant breeding ground. |
No significant breeding grounds known. |
Age |
14 years (based on aerial photos). |
Young. |
Abundance/ Richness of wildlife |
Moderate
abundance of wildlife. |
Low
richness/abundance of wildlife. |
Ecological value |
Low to Moderate |
Low |
Seasonal Marsh
Table 8‑12 Ecological Evaluation of Seasonal Marsh
Criteria |
Seasonal marsh in the Project Area |
Other Seasonal marsh in Assessment Area |
Naturalness |
Man-made habitat on land derived from filling of
fishponds. Disturbed by regular maintenance works. |
Artificial habitat comprising grasscrete area used
by DSD for floodwater storage. |
Size |
Small,
totally about 0.69 ha. |
Small,
around 0.51 ha. |
Diversity |
Low
plant species diversity but moderate diversity of common faunal species (20
bird species, 11 dragonfly species, 1 butterfly species). |
Low
diversity and simple plant community structure. |
Rarity |
A fairly common habitat in |
A fairly common habitat type in |
Re-creatability |
Easily
re-creatable under suitable hydrological conditions. |
Easily
re-creatable if hydrology is suitable, as substrate is artificial. |
Fragmentation |
Highly fragmented, consisting of five isolated
patches. |
Single small isolated area. |
Ecological linkage |
Ecologically linked to surrounding grassland and
nearby freshwater marsh. |
Some linkage to nearby wetlands, although this
fairly weak as habitat is surrounded by roads and fences. |
Potential value |
Could be enhanced or converted into freshwater marsh
with suitable hydrological conditions and vegetation management, although
value still limited by very small size although such a management regime is
unlikely in practice under current conditions. |
Limited because managed for flood prevention,
although may be improved with an increase in vegetative diversity. |
Nursery/ breeding ground |
Breeding ground for common dragonfly and amphibian
species. |
No breeding ground known but may support common
species of amphibian and dragonfly. |
Age |
Fishponds were filled about 14 years ago. |
Very recent, about 2-3 years. |
Abundance/ Richness of wildlife |
Moderate
abundance of wildlife. |
Low
abundance and richness of wildlife. |
Ecological value |
Low to moderate |
Low |
Freshwater Marsh/Reedbed
Table 8‑13 Ecological Evaluation of Freshwater Marsh/Reedbed
Criteria |
Freshwater marsh/reedbed in Project Area |
Other Freshwater marsh and reedbed in
Assessment Area |
Naturalness |
Artificially created by filling of fishponds.
Currently moderately disturbed by annual vegetation management works,
especially reed cutting. |
Derived from natural succession in wetland habitats (fishponds
and drainage channels). |
Size |
Moderately
large for this type of habitat (4.00 ha). |
Several
small patches; totally 4.17 ha. |
Diversity |
Plant
species diversity is relatively low. Faunal diversity is moderate due to
proximity to other wetland habitats and low levels of disturbance (35 bird
species, 3 amphibian species, 12 dragonfly species, 6 butterfly species). |
Low
plant species diversity and low faunal species diversity (8 bird species, 2
dragonfly species). |
Rarity |
Freshwater marsh is uncommon and declining in |
Similar areas of marsh are fairly common in the |
Re-creatability |
Can
be recreated under suitable hydrological conditions. |
Easily
re-creatable where hydrological conditions are suitable. |
Fragmentation |
Not fragmented within the Project Area. |
Several small, isolated patches, each with different
conditions. |
Ecological linkage |
Good ecological linkage to surrounding grassland and
nearby |
Patches in the north of the Assessment Area are
ecologically linked to nearby fishponds. |
Potential value |
Could be enhanced with management of water levels
and vegetation. Allowing reeds to mature would permit development of reedbed
habitat, potentially supporting a variety of uncommon species (especially
birds) although such a management regime is unlikely in practice under
current conditions. |
Could be improved by appropriate management,
although the small size of the habitat patches limits the potential value.
Also constrained by limited botanical diversity in the absence of
introductions. |
Nursery/ breeding ground |
Breeding ground for common amphibian and dragonfly
species. |
Not known as a significant breeding ground, but some
may support common amphibians and dragonflies. |
Age |
Evolved on land created by filling of fishponds
about 14 years ago. |
Fairly recently developed from other wetland
habitats. |
Abundance/ Richness of wildlife |
Reasonable
abundance of fauna, especially birds and dragonflies. Moderately diverse
dragonfly community, with 12 species recorded in the Project Area. |
Low
abundance of wildlife, largely due to small size of the habitat patches. |
Ecological value |
Moderate |
Low to moderate |
Fishponds
Table 8‑14 Ecological Evaluation of Fishponds.
Criteria |
Active fishponds in north and west of
Assessment Area |
Abandoned fishponds in south-west of
Assessment Area |
Naturalness |
Artificial habitat created for cultivation of fish
species, moderately disturbed by regular human activities related to fish
farming. |
Originally created for aquaculture, but have been
abandoned for a number of years and have undergone succession. |
Size |
A
large area in the Assessment Area (62.21 ha), contiguous with fishponds
throughout the |
Moderate
area in Assessment Area (18.71 ha). |
Diversity |
Plant
species diversity low due to regular disturbance to bunds. Faunal diversity
recorded during surveys moderate to high. |
Plant
species diversity low. Habitats present suggest faunal diversity is likely to
be fairly high, especially among birds. |
Rarity |
Fishpond habitats are common in the |
Although fishponds are common in this part of |
Re-creatability |
Easily
re-creatable if a large area of suitable habitat exists. |
Could
be re-created on abandoned fishponds. |
Fragmentation |
Mostly unfragmented and continuous with a large area
of similar habitat. A few fishponds in the Assessment Area are isolated by
residential development. |
Not fragmented. |
Ecological linkage |
Good ecological linkage to surrounding wetlands
throughout the |
Ecologically linked to |
Potential value |
High potential for enhancement with a suitable
management regime. |
High potential value with suitable management and
protection. |
Nursery/ breeding ground |
Breeding ground for widespread amphibians and
dragonflies. Foraging ground for egrets breeding in the nearby egretries. |
No significant nursery or breeding ground known. |
Age |
Over 30 years. |
Fishponds around 30 years old. Not known when these
were abandoned but probably fairly recent (10-15 years). |
Abundance/ Richness of wildlife |
Abundant
and diverse wetland community, especially for birds. |
Abandoned
fishponds and reedbeds support a relatively diverse faunal community,
especially birds including significant numbers of Black-faced Spoonbills. |
Ecological value |
Moderate to High |
High |
Drainage Channels/Ditches
Table 8‑15 Ecological Evaluation of Drainage Channels/ Ditches.
Criteria |
Drainage channels/ ditches in Project
Area |
Other Drainage channels/ ditches in
Assessment Area |
Naturalness |
Artificially created drainage ditches subject to
organic pollution from surrounding land-use. |
Man-made drainage ditches and water channels,
including concrete-lined channels. Polluted by surrounding land uses. |
Size |
Small
and narrow (total area 0.81 ha, length about 1.7 km). |
Some
channels are moderate in size, width and depth (total area 4.46 ha, length
about 3.0 km). |
Diversity |
Riparian
vegetation relatively low in diversity. Aquatic invertebrate community low in
diversity but riparian fauna moderately diverse (21 bird species, 3 amphibian
species, 1 reptile species (non-native), 16 dragonfly species, 13 butterfly
species). |
Moderately
diverse riparian vegetation where disturbance is low. Aquatic invertebrate
community low in diversity due to high levels of pollution. Other faunal
diversity moderate (27 bird species, 1 amphibian species, 1 reptile species,
7 dragonfly species, 3 butterfly species). |
Rarity |
A common habitat in |
A common habitat in |
Re-creatability |
Habitat
is easily re-creatable. |
Habitat
is easily re-creatable. |
Fragmentation |
Ditches within the Project Area are small but
connected. |
Not particularly fragmented. |
Ecological linkage |
Ecologically linked to nearby wetland habitats. |
Strong ecological links top surrounding wetland
habitats. |
Potential value |
Limited potential value, but could be enhanced if
pollution was reduced and riparian vegetation was improved. |
Ditches could be enhanced by suitable vegetation
management and reduction in pollution load. |
Nursery/ breeding ground |
Breeding ground for common amphibian and dragonfly
species, although low diversity of dragonfly larvae in samples of aquatic
fauna suggests most species do not breed in this habitat. |
Breeding ground for common amphibian and dragonfly
species. |
Age |
Fairly recent in their current form, created as part
of |
Over 30 years, more recent where modified for
residential developments. |
Abundance/ Richness of wildlife |
Moderate
abundance of common dragonfly species and exotic fish. Chinese Striped
Terrapin recorded in riparian vegetation, but considered to relate to an
escaped individual. |
Moderate
abundance of common dragonfly species and exotic fish. Some larger channels
are used by foraging birds. |
Ecological value |
Low |
Low to moderate |
Table 8‑16 Ecological Evaluation of
Criteria |
|
Naturalness |
Semi-natural woodland habitat, partly derived from fung shui wood and plantation. |
Size |
Small,
approximately 1.06 ha in Assessment Area. |
Diversity |
Moderate
floral diversity. Faunal diversity lower than in woodlands elsewhere in |
Rarity |
Secondary woodland is common in |
Re-creatability |
Could
be recreated in long-term if suitable resources are available. Fung shui wood would be difficult to
recreate. Recolonisation by egrets would be difficult to achieve. |
Fragmentation |
Not fragmented within the Assessment Area, but this
single block is isolated from similar habitats. |
Ecological linkage |
Some ecological linkage to |
Potential value |
Value could be enhanced by suitable management,
especially if the number of breeding egrets could be increased. |
Nursery/ breeding ground |
A small egretry at Mai Po Lung and a few pairs of
Chinese Pond Herons have recently colonised some trees on the edge of the
woodland at |
Age |
Fairly old due to fung shui functions. |
Abundance/ Richness of wildlife |
Moderate
abundance of wildlife, but lower than in other woodland areas. |
Ecological value |
Moderate |
Table 8‑17 Ecological Evaluation of
Criteria |
Plantation at
Mai Po Village |
Other |
Naturalness |
Artificial habitat created by planting of non-native
tree species (Eucalyptus citriodora). |
Habitat created by planting of various non-native
tree species, especially roadside planting. |
Size |
This
habitat patch is very small, around 0.43 ha. |
Moderate,
approximately 4.99 ha. |
Diversity |
Low
plant species diversity and low diversity of other wildlife. |
Fairly
low plant species diversity dominated by non-native species. |
Rarity |
A common habitat type in |
A common habitat type in |
Re-creatability |
Habitat
is re-creatable but recolonisation of the egretry would be difficult. |
Easily
recreated by planting of trees. |
Fragmentation |
One small isolated fragment. |
Fragmented by urban land uses (especially roads). |
Ecological linkage |
Ecologically linked to the |
Some linkage with woodland near Mai Po village and
grassland near Shek Wu Wai. |
Potential value |
High potential value if the egretry can be
maintained and increased. |
Moderate if understorey allowed to mature and native
woodland species colonise. |
Nursery/ breeding ground |
Important breeding colony of Little Egret (35 pairs
in 2006), although no birds bred here during 2007. |
No significant breeding ground recorded. |
Age |
Young. |
Variable but fairly young. |
Abundance/ Richness of wildlife |
High
abundance of egrets, low abundance of other wildlife. |
Abundance/Richness
of wildlife low. |
Ecological value |
Moderate to high due to presence of egretry; Low if egretry has relocated. |
Low to moderate |
Active and Inactive
Agricultural Land
Table 8‑18 Ecological Evaluation of Active and Inactive Dry Agricultural Land.
Criteria |
Active Dry Agricultural Land in
Assessment Area |
Inactive Dry Agricultural Land in
Assessment Area |
Naturalness |
Man-made habitat used for crops. |
Derived from natural succession on former cultivated
land. |
Size |
Two
small patches, totally 0.79 ha. |
Moderate,
about 6.15 ha. |
Diversity |
Species
diversity very low due to regular human disturbance (7 bird species, 2
dragonfly species). |
Low
diversity of plant species, dominated by exotic weeds. Low faunal diversity
(16 bird species, 3 dragonfly species, 7 butterfly species). |
Rarity |
Not a rare habitat in |
A common habitat in |
Re-creatability |
Easily
re-creatable. |
Easily
re-creatable. |
Fragmentation |
Two very small, isolated patches. |
Adjacent developed areas create irregular shape with
a degree of fragmentation. |
Ecological linkage |
Patch at |
Weak ecological linkage to adjacent plantation of
low ecological value. |
Potential value |
Low, especially due to small size. |
Could be enhanced with appropriate vegetation
management. |
Nursery/ breeding ground |
No significant breeding ground known. |
No significant breeding ground known. |
Age |
Not known, apparently fairly recent. |
Recently established since the abandonment of
agriculture on the land. |
Abundance/ Richness of wildlife |
Abundance/Richness
of wildlife low. |
Abundance/Richness
of wildlife low. |
Ecological value |
Low |
Low |
Developed Areas, Bare
Ground and Wasteland
Table 8‑19 Ecological Evaluation of Developed Area, Bare Ground and Wasteland.
Criteria |
Developed Area / Bare Ground in Project
Area |
Other Developed Area / Wasteland in
Assessment Area |
Naturalness |
Entirely man-made habitat, mostly open storage. |
Entirely man-made habitat, including villages,
residential developments and major roads. |
Size |
Medium,
4.79 ha. |
Large,
82.36 ha. |
Diversity |
Species
diversity low (13 bird species, 4 dragonfly species, 2 butterfly species). |
Species
diversity low (37 bird species, 1 dragonfly species, 1 butterfly species). |
Rarity |
Very common habitat in |
Very common habitat in |
Re-creatability |
Easily
re-creatable. |
Easily
re-creatable. |
Fragmentation |
Not fragmented. |
Slightly fragmented. |
Ecological linkage |
No significant linkage to other habitats. |
No significant linkage to other habitats. |
Potential value |
Potential value is very low. |
Potential value is very low. |
Nursery/ breeding ground |
No nursery or breeding ground known. |
No nursery or breeding ground known. |
Age |
Fairly recently created from other habitats. |
Variable, includes old villages and recent
residential developments. |
Abundance/ Richness of wildlife |
Low
diversity of wildlife. |
Low
diversity of wildlife. |
Ecological value |
Very Low |
Very Low |
· Direct impacts to habitats and species of conservation importance including habitat loss (both quantitative and qualitative) and reduction of species abundance and/or diversity. Such impacts may be permanent or temporary and may occur on-site and/or off-site.
· Indirect and secondary impacts to habitats and species of ecological significance including disturbance impacts, and loss of feeding, breeding and roosting habitats, loss or reduction of ecological linkages and functions and habitat fragmentation. Again, such impacts may occur on-site or off-site and may be temporary or permanent.
· Cumulative impacts are a form of indirect/secondary impact. However, because of the potential high ecological significance of cumulative impacts these are discussed separately below.
Direct Ecological Impacts
Habitat Loss
Table 8‑20 Potential Direct Ecological Impacts to habitats in Project Area without mitigation measures.
Criteria |
Impacts to Grassland |
Impacts to Seasonal Marsh |
Impacts to Freshwater Marsh/ Reedbed |
Impacts to Drainage Channels/ Ditches |
Habitat Quality |
Low to moderate. |
Low to moderate. |
Moderate. |
Low, due to high levels of organic pollution and
previous channelisation. |
Species |
Moderate
species diversity (33 bird species, 9 dragonfly species, 10 butterfly
species). The habitat does not appear
to be important for species of conservation importance, but small numbers of
some species (Black Kite, Oriental Pratincole, Pacific Swift, Zitting Cisticola
and White-shouldered Starling) were recorded. |
Moderate
diversity of fauna (20 bird species, 11 dragonfly species, 1 butterfly
species), including foraging Little Egret, Cattle Egret, Chinese Pond Heron,
Black Kite, Little Ringed Plover, Pacific Swift and Red-billed Starling. |
Moderate
to high species diversity (35 bird species, 3 amphibian species, 12 dragonfly
species, 6 butterfly species). Used by foraging ardeids, especially Little
Egret (maximum count 48) and Cattle Egret (maximum count 14), but also
Chinese Pond Heron and Black-crowned Night Heron. Other bird species of
conservation importance recorded, including Black Kite, Oriental Pratincole,
Little Ringed Plover, Pacific Swift and, Red-billed Starling. Moderately
diverse dragonfly community supported, although species are common. |
Moderate
faunal diversity (21 bird species, 3 amphibian species, 1 reptile species, 16
dragonfly species, 13 butterfly species). Great Cormorant, Grey Heron, Great
Egret, Little Egret, Chinese Pond Heron and Pacific Swift recording roosting
in riparian trees or foraging in/over the drainage ditches. Dragonflies
include Scarlet Basker of Local Concern. Chinese Striped Terrapin recorded
but considered to be an escaped individual. Aquatic invertebrate community
low in diversity. |
Size/Abundance |
Fairly
large area (11.05 ha) to be lost permanently. Fauna not particularly abundant
(no large flocks recorded). |
Five
separate fragmented patches, totalling 0.69 ha. Faunal abundance low due to
small size of habitat patches, and individuals must also be reliant on
surrounding habitats (grassland, freshwater marsh). |
Approximately
4.00 ha, a large area for this habitat type in |
Small
in size (area 0.81 ha, length 1.7 km). Stream invertebrates moderately
abundant but dominated by common, pollution-tolerant species. Some dragonfly species fairly numerous but
these are common species in |
Duration |
Permanent loss of existing habitat. |
Permanent loss of existing habitat. |
Permanent loss of existing habitat. |
Permanent loss of existing habitat. |
Reversibility |
Habitat
loss would be permanent. |
Habitat
loss would be permanent. |
Habitat
loss would be permanent. |
Habitat
loss would be permanent. |
Magnitude |
Existing habitat would be totally lost during
development of the scheme. |
Existing habitat would be totally lost during
development of the scheme. |
Existing habitat would be totally lost during
development of the scheme. |
Existing habitat would be totally lost during
development of the scheme. |
Overall Impact Severity |
Loss
of grassland habitats of Low
Significance despite permanent loss because habitat is of comparatively
low ecological value. |
Impacts
of Low to Moderate Significance.
Any loss of wetland in the |
Impacts
to freshwater marsh/reedbed of Moderate
Significance. Freshwater marsh of this size is of importance in a |
Impacts
to existing water ditches of Low
Significance despite permanent loss because ditches are small, polluted
and of low ecological value. |
Direct Impacts to Species of Conservation Importance
Vegetation
Mammals
Birds
Table 8‑21 Potential Ecological Impacts to bird species of conservation importance in Project Area, without mitigation measures.
Criteria |
Impacts to Roosting Water birds |
Impacts to Foraging Ardeids |
Impacts to Other Bird Species of
Conservation Importance |
Habitat Quality |
Riparian trees (Macaranga
tanarius and Melia azederach)
on northern perimeter of Project Area used as daytime roost by small numbers
of waterbirds foraging on nearby fishponds. |
Wetland habitats in Project Area used by small
numbers of foraging ardeids; the habitats present on site are not optimal
quality for ardeid species, however. |
Other bird species of conservation importance
recorded in Grassland, Seasonal Marsh and Freshwater Marsh/Reedbed. |
Species |
Species
recorded roosting in the Project Area include Great Cormorant (maximum 5),
Grey Heron (maximum 2), Great Egret (maximum 1), Black-crowned Night Heron
(maximum 4). Also used by Little
Egret, Cattle Egret and Chinese Pond Heron, including birds foraging on site. |
Species
recorded foraging in Project Area include Little Egret (maximum 48), Cattle
Egret (maximum 14) and Chinese Pond Heron (maximum 7). Little Egret and Chinese Pond Heron also
breed locally and some birds from these egretries probably forage in the
Project Area. |
Species
recorded include Black Kite (maximum 5), Oriental Pratincole (maximum 11,
only recorded during flight path surveys), Little Ringed Plover (maximum 1),
Pacific Swift (maximum 22), Zitting Cisticola (maximum 1), Red-billed
Starling (maximum 15) and White-shouldered Starling (maximum 2). |
Size/Abundance |
Numbers
present in Project Area very small in comparison to |
Numbers
present within Project Area are small in comparison to |
Numbers
of most species present in Project Area are small in comparison to |
Duration |
Impacts would be permanent if trees are removed,
otherwise temporary disturbance impacts during construction only. |
Impacts resulting from habitat loss would be
permanent. |
Impacts resulting from habitat loss would be
permanent. |
Reversibility |
Loss
of trees would be easily reversed in the long-term by replacement planting,
disturbance impacts would be temporary and reversible. |
Habitat
loss irreversible in absence of mitigation measures. |
Habitat
loss irreversible in absence of mitigation measures. |
Magnitude |
Magnitude would be low because alternative roost
sites for these species are available around nearby fishponds. |
Magnitude of impacts would be low due to relatively
small numbers of individuals present and large area of suitable habitat
nearby. Magnitude greater if the Project Area is also used for foraging by
egrets breeding nearby (see section 8.8.23). |
Magnitude of impacts would be low because number of
individuals for all species is small relative to |
Overall Impact Severity |
Impacts
are considered to be of Low
Significance due to presence nearby of alternative roost sites and low
number of individuals recorded roosting on site. |
Impacts
to foraging egrets, including birds from the nearby egretries, of Low to Moderate Significance given
the small numbers of individuals present relative to the |
Impacts
to Little Ringed Plover, Zitting Cisticola and White-shouldered Starling of Low Significance due to small numbers
present within the Project Area. Impacts to Pacific Swift of Low Significance because this highly
mobile, aerial species will not be significantly impacted by habitat changes
within the Project Area, and there are no local breeding colonies (Carey et al. 2001). Impacts to Oriental
Pratincole of Low Significance
because, despite reasonable numbers present on a single date, this is a
migratory species which is widespread in |
Herpetofauna
Dragonflies
Butterflies
Table 8‑22 Potential Ecological Impacts to Scarlet Basker and Danaid Egg-fly in Project Area, without mitigation measures.
Criteria |
Impacts to Scarlet Basker |
Impacts to Danaid Egg-fly |
Habitat Quality |
Scarlet Basker recorded in drainage ditches within
Project Area. Species is considered by
|
Danaid Egg-fly recorded within Freshwater Marsh in
Project Area; this is not typical habitat for the species, suggesting that it
was not breeding locally. The larval
foodplant (Portulaca oleracea) was
not recorded in the Project Area. |
Species |
Scarlet
Basker is listed by Fellowes et al.
(2002) as being of Local Concern, but the species has since increased in |
Danaid
Egg-fly is listed by Fellowes et al.
(2002) as being of Local Concern. |
Size/Abundance |
Very small
numbers recorded within the Project Area (totally 3 individuals recorded
during nine surveys). |
A single
individual recorded within the Project Area during the surveys. |
Duration |
Loss of wetland habitat would be permanent without
mitigation measures. |
Impacts would be permanent if habitat is lost. |
Reversibility |
Potential
impacts easily reversed by provision of suitable habitat. |
Impacts of
habitat loss could be reversed by provision of suitable plant species for
breeding. |
Magnitude |
Magnitude would be low because of small numbers
present in relation to total |
Species appears to be rare within the Project Area
(single individual recorded), so impacts considered to be of very low
magnitude. |
Overall Impact Severity |
Impacts are
considered to be of Low Significance
due to very small numbers of individuals present, suboptimal quality of
habitats presence and current |
Impacts
considered to be of No Significance
because a single individual was recorded in unusual habitat and the foodplant
was not found, suggesting the sole record may be an individual passing
through the Project Area. |
Indirect Ecological Impacts
Habitat Loss
Table 8‑23 Potential Indirect Ecological Impacts to habitats in the Assessment Area without mitigation measures.
Criteria |
Indirect Impacts to Fishponds |
Indirect Impacts to Drainage Channels |
Habitat Quality |
Moderate to High. |
Low to moderate. |
Species |
Used by a
number of disturbance-sensitive waterbirds, including 26 species of
conservation importance recorded during surveys. |
27 bird
species recorded, including 12 of conservation importance, but only Common
Teal recorded downstream of site.
Scarlet Basker (Local Concern) also recorded. Aquatic invertebrates low in diversity but
high abundance of pollution-tolerant species. |
Size/Abundance |
Drained
fishponds attract large numbers of waterbirds, with fairly large numbers
present on fishponds throughout the winter. |
Drainage
channels adjacent to the Project Area are fairly small and are used by
relatively small numbers of wetland-dependent species. These channels feed into |
Duration |
Disturbance to nearby fishponds would be greatest
during the construction phase of the project, especially while activities are
being carried out on the northern part of the sites, closest to the fishpond
area. After construction work finishes the presence of
residents close to these ecologically-important fishponds would cause ongoing
disturbance to sensitive waterbirds. |
Pollution impacts will occur during the construction
phase due to runoff of sediment and pollutants. In the absence of mitigation, pollution would
continue during the operation phase due to surface runoff. Ongoing but short-term impacts to hydrology due to
increased surface runoff from paved area during heavy rainfall. |
Reversibility |
Construction
phase disturbance would be temporary, finishing when construction activities
have ceased. Post-construction
disturbance would be permanent and on-going. |
Serious
pollution events would be costly to clean up.
Minor events would be more easily cleaned. |
Magnitude |
Degree of disturbance would be considerable during
construction phase of project, especially while construction activities are
being conducted at the northern edge of the Project Area, and during the
period of presence of large waterbirds (dry season). In the absence of mitigation, post-construction
disturbance would potentially also be quite high due to large numbers of
residents close to disturbance-sensitive waterbirds. |
Major pollution events, especially chemical
pollution, would have a large impact on water quality in watercourses. Minor
organic pollution and sediment runoff would have a lesser impact, especially
in comparison to existing pollution levels. Increase in surface runoff would be small in
comparison to existing water flow in |
Overall Impact Severity |
In the
absence of mitigation measures, disturbance to waterbirds in nearby fishponds
during the construction and operation phases is considered to be of Moderate to High Significance due to
the importance of these ponds to waterbirds and their proximity to the
northern edge of the Project Area. |
Impacts
from pollution of watercourses downstream of the site are considered to be of
Moderate Significance because the
areas to be impacted are currently of low ecological value and are polluted
from other sources. Changes in
surface runoff of Low Significance because
the increase in water flow would be small in comparison to existing flow in
the channel. |
Pollution of Watercourses
and
Table 8‑24 Potential Ecological Impacts
from pollution of watercourses and
Criteria |
Pollution Impacts to Watercourses and |
Habitat Quality |
Watercourses downstream of the Project Area are of
relatively low ecological value due to moderate levels of pollution. |
Species |
Watercourses
in Project Area contain a low diversity of fish and invertebrates but a high
abundance of pollution-tolerant species.
Similar conditions are present in other watercourses nearby. |
Size/Abundance |
Watercourses
draining the Project Area are small, only a few metres wide. |
Duration |
Construction phase impacts potentially include
sedimentation from soil runoff, release of contaminants during excavation,
chemical waste and domestic effluent. Sources of water pollution during the
operational phase would be from waste water discharge from residences. |
Reversibility |
Significant
pollution events could be cleaned up to some degree but this would be costly
and would have long-term impacts on ecosystems. |
Magnitude |
Pollution events would be large in watercourses
draining the Project Area, although these watercourses already suffer from
moderate levels of pollution. The
small size of the Project Area relative to |
Overall Impact Severity |
Impacts to
watercourses adjacent to and downstream of the site are considered to be of Moderate Significance because the
areas to be impacted are currently of low ecological value and are polluted
from other sources. Impacts to |
Habitat Fragmentation
Cumulative Ecological
Impacts of Habitat Loss
Indirect Impacts to Species of Conservation Importance in the
Assessment Area
Vegetation
Mammals
Birds
Disturbance of Water birds
Table 8‑25 Potential Disturbance Impacts to waterbirds of conservation importance in Assessment Area without mitigation measures.
Criteria |
Disturbance
Impacts to Water birds of Conservation Importance |
Habitat Quality |
A high diversity of disturbance-sensitive
waterbirds of conservation importance use fishpond habitats to the north of
the Project Area. |
Species |
22 bird
species of conservation importance recorded on the fishponds, including (with
maximum counts during transect surveys in parentheses): Little Grebe (3),
Great Cormorant (503), Grey Heron (11), Great Egret (22), Intermediate Egret
(4), Little Egret (123), Cattle Egret (60), Chinese Pond Heron (13),
Black-crowned Night Heron (1), Striated Heron (not on transects), Black-faced
Spoonbill (9), Northern Pintail (21), Common Teal (11), Eurasian Wigeon (27),
Osprey (1), Black Kite (9), Little Ringed Plover (1), Pied Kingfisher (1),
White-throated Kingfisher (2), Red-billed Starling (821), White-shouldered
Starling (not on transects) and Collared Crow (2). Also |
Size/Abundance |
High
abundance of some species, notably Red-billed Starling, Great Cormorant and
Little Egret. |
Duration |
Disturbance to nearby fishponds would be
greatest during the construction phase of the project, especially while
activities are being carried out on the northern part of the Project Area,
closest to the fishpond area. Disturbance would be reduced after construction
work finishes. Some permanent human disturbance may
occur where residential blocks are closest to existing fishponds. Possibility
of light disturbance impacts to roosting or night-time foraging waterbirds
during the operational phase. |
Reversibility |
Construction
phase disturbance would be temporary, finishing when construction activities
have ceased. Post-construction
disturbance would be permanent and on-going. |
Magnitude |
Degree of disturbance would be
considerable during construction phase of project, especially while
construction activities are being conducted at the northern edge of the
Project Area, and during winter when greater numbers of large waterbirds are
present. Post-construction disturbance would be small as human activity in
the vicinity of the fishponds would be small, and existence of the wetland
buffer would create a buffer between the existing fishponds and the source of
human disturbance. |
Overall Impact Severity |
In the
absence of mitigation measures, construction-phase disturbance to waterbirds
in nearby fishponds is considered to be of Moderate to High Significance due to the importance of these
ponds to waterbirds and their proximity to the northern edge of the Project
Area. Post-construction
disturbance impacts to fishponds are considered to be of Moderate Significance if human activity and night-time lighting
are present close to fishpond areas. |
Impacts to Egretries
Table 8‑26 Potential Ecological Impacts to egretries in Assessment Area without mitigation measures.
Criteria |
Impacts to |
Impacts to Other Egretries |
Habitat Quality |
Historically a high quality site, although Little
Egrets did not breed at the main site during 2007. |
Egretries at Mai Po Lung and Tam Kon Chau contain
reasonable numbers of pairs of Little Egret and Chinese Pond Heron. |
Species |
Egretry
used by Little Egret and Chinese Pond Heron. Formerly used by Cattle Egret
(2004), Great Egret (2003) and Black-crowned Night Heron (2002). |
Egretries
used by Chinese Pond Heron and Little Egret. |
Size/Abundance |
35
pairs of Little Egret and 50 of Chinese Pond Heron in 2006 (Anon. 2006c). |
Tam
Kon Chau: 37 pairs of Chinese Pond Heron in 2006 Mai
Po Lung: 12 pairs of Little Egret and 74 of Chinese Pond Heron in 2006 (Anon.
2006c). |
Duration |
Impacts would be restricted to the breeding season
of egrets, between March and July. Significant impacts, if they were to
occur, could cause permanent abandonment of the egretry. Noise disturbance at the egretry would be confined
to the construction phase. |
Impacts would be restricted to the breeding season
of egrets, between March and July. Significant impacts, if they were to
occur, could cause permanent abandonment of the egretry. Noise disturbance at the egretries would be confined
to the construction phase. |
Reversibility |
Abandonment
of the egretry would be difficult to reverse. |
Abandonment
of an egretry would be difficult to reverse. |
Magnitude |
Little Egrets forage in the Project Area during the
breeding season (March-July), with a peak count of 20 during this period.
Small numbers of Chinese Pond Heron also forage in the Project Area (peak
count seven birds). Both counts may
include birds from Major flight paths from the egretry to forage
grounds do not appear to pass through the Project Area, although small
numbers of egrets do fly through the Project Area during the breeding
season. Noise disturbance is not considered to be large as
birds in the egretry are tolerant of high levels of disturbance from nearby
San Tin highway. |
Some Chinese Pond Heron foraging in the Project Area
during the breeding season may come from the Tam Kon Chau egretry. Birds from Mai Po Lung are not thought to forage in
the Project Area because of the distance from the egretry and the presence of
hills on the flight path presenting an obstacle to egret movement. Noise disturbance may occur at Tam Kon Chau, but
egrets elsewhere seem to be tolerant of moderate noise levels. |
Overall Impact Severity |
Impact
considered to be of Low to Moderate
Significance, mostly due to loss of foraging habitat. There
appear to be no significant flight paths from the egretry over the Project
Area, and impacts to these are considered to be of Low Significance. No direct impact to egretry due to habitat loss or disturbance. Noise
disturbance considered to be of Low
Significance because of distance between egretry and Project Area, and
tolerance of egrets to moderate noise levels. |
Potential
impacts to Mai Po Lung egretry Not
Significant because there is no evidence of impacts to either foraging
birds or flight paths. Impacts
to Tam Kon Chau egretry of Low
Significance because small numbers of birds from this site may forage in
the Project Area, due to the proximity of the egretry. No Significant Impact to flight paths from Tam Kon Chau egretry
because there appear to be no important flight paths over the Project Area. Noise
disturbance to Tam Kon Chau considered to be of Low Significance because of distance between egretry and Project
Area, and tolerance of egrets to moderate noise levels. |
Impacts to Flight Paths of
Non-breeding and Migratory Birds
Table 8‑27 Potential Ecological Impacts to non-breeding bird flight paths without mitigation measures.
Criteria |
Impacts to Non-breeding Bird Flight
paths |
Habitat Quality |
Small numbers of birds were recorded flying over the
Project Area during the dry season surveys but flight paths through the area
are partly impeded by the presence of existing residential developments. |
Species |
42 bird
species recorded during flight path surveys, including 15 species of
conservation importance. |
Size/Abundance |
A few
wetland-dependent species recorded flying over the northern part of the
Project Area in reasonable numbers (e.g. total counts of 197 Great Cormorant,
128 Little Egret, 34 Chinese Pond Heron, 102 Black Kite); see Figure 8.4. Single large flocks of Black-headed Gull
(70) and Red-billed Starling (50) also recorded, but these apparently not
regular in Project Area. |
Duration |
Any obstruction to flight paths below the level of
buildings would be permanent; this applies particularly to Flight path 1,
where most birds were recorded below 20 m. All flight paths may be
temporarily disrupted by noise disturbance during construction. |
Reversibility |
Obstruction
of flight paths below the level of buildings would be permanent. Flight paths
above the level of buildings may be temporarily impacted during the
construction phase but this would subsequently be reversed. |
Magnitude |
No clearly-defined and regular flight paths exist
over the Project Area, suggesting that most birds passing over the Project
Area do so opportunistically. Most
individuals flying over the Project Area passed over the northern and west
edge of the Project Area, along Flight paths 1, 2, 4 or 5 (Figure
8.4);
impacts of development in this area would be of greater magnitude than
elsewhere within the Project Area.
Birds flying over the southern part of the Project Area are flying
higher to pass over existing residential developments. Any development in this area will have no
impact on flight paths, provided it does not significantly exceed the height
of the existing developments. |
Overall Impact Severity |
Impacts
considered of Low to Moderate
Significance for development in the south of the Project Area, where few
birds were recorded and these were usually relatively high. The magnitude of impacts in this area would
be dependent on the height of the buildings relative to the surrounding
residential estates. Impacts of Moderate Significance if development
occurs on the northern or northwestern part of the Project Area, particularly
along Flight paths 1, 2, 4 and 5, where more birds were recorded and these
were often flying below 20 m above the ground. No Significant Cumulative Impact predicted to flight paths as a result of loss
of undeveloped land adjacent to existing residential estates, because bird
species are also recorded flying over existing developments. |
Impacts to Other Fauna
Table 8‑28 Summary of Potential Ecological Impacts in the absence of Mitigation Measures.
Description of Potential Impact |
Significance of Impact |
Direct
loss of Habitats in Project Area |
|
Loss of Grassland Habitats |
Loss of habitat of Low Significance due to low value of habitat and low abundance of
species of conservation importance. |
Loss of Seasonal Marsh |
Impacts to
habitat of Low to Moderate
Significance due to small size, ephemeral nature and high fragmentation
of habitat. Impacts to species utilising the habitat of Low to Moderate Significance, mostly due to impacts to moderately
diverse dragonfly fauna. |
Loss of Freshwater Marsh/Reedbed |
Habitat
loss of Moderate Significance because
of importance of the habitat in a |
Loss of Drainage Channels/ Ditches |
Impacts of Low
Significance due to low existing value of the ditches in the Project
Area, and minimal impact to riparian trees used by roosting waterbirds. |
Direct
Impacts to Species of Conservation Importance |
|
Impacts to Vegetation |
No Significant Impact because no species of conservation importance
present in the Project Area. |
Impacts to Mammals |
No Significant Impact because no species of conservation importance
present in the Project Area. |
Impacts to Roosting Water birds |
Impacts to waterbirds
roosting at the northern edge of the Project Area of Low Significance due to small numbers of birds present and
existence of other suitable roosting sites. |
Impacts to Foraging Ardeids |
Impacts
from loss of foraging habitat of Low
to Moderate Significance due to the relatively small number of
individuals involved, the suboptimal quality of the habitat and the presence
of other suitable foraging locations nearby. |
Impacts to Other Bird Species |
Impacts to
other bird species of conservation importance (Black Kite, Oriental
Pratincole, Little Ringed Plover, Pacific Swift, Zitting Cisticola,
Red-billed Starling and White-shouldered Starling) of Low Significance because the Project Area does not provide
habitat for locally-important populations of any of these species. |
Impacts to Herpetofauna |
No Significant Impact because no species of conservation importance
present in the Project Area. |
Impacts to Scarlet Basker |
Impacts of Low Significance because of very
small numbers present in Project Area and current status of the species in |
Impacts to Danaid Egg-fly |
No Significant Impact because no evidence that the species breeds
within the Project Area. |
Indirect
Impacts to Habitats in Assessment Area (outside Project Area) |
|
Disturbance Impacts to Adjacent Fishponds |
Impacts of
disturbance to waterbirds in nearby fishponds of Moderate to High Significance due to the importance of these
ponds to waterbirds and their proximity to the northern edge of the Project
Area. |
Indirect Impacts to Off-site Drainage Channels |
Impacts
from pollution of watercourses downstream of the Project Area are considered
to be of Moderate Significance. Changes in surface runoff of Low Significance because magnitude small in comparison to
existing flow in the channel. |
Indirect Impacts to Other
Habitats in Assessment Area |
No Significant Impacts to other habitats because these are small
and/or show no ecological linkage to the Project Area. |
Pollution Impacts to
Watercourses and |
Impacts to
watercourses downstream of the Project Area are considered to be of Moderate Significance. Pollution
impacts to |
Impacts from Habitat
Fragmentation |
No Significant Impacts because Project Area is on the edge of the
wetland ecosystem and does not form a link between other habitats in the
area. |
Cumulative Impacts of
Wetland Loss |
Overall
impacts would be of High Significance if |
Indirect Impacts to Species of Conservation
Importance |
|
Indirect Impacts to
Vegetation |
No impacts to species of conservation importance because
none present in Assessment Area.
Impacts of Low Significance
to other vegetation during construction phase due to dust deposition. |
Indirect Impacts to
Mammals |
No Significant Impact because no species of conservation importance
recorded in Assessment Area, and low density mammal populations present. |
Disturbance to Water birds
of Conservation Importance |
Construction-phase
disturbance of Moderate to High
Significance due to the importance of fishponds to waterbirds and their
proximity to the northern edge of the Project Area. Post-construction
disturbance impacts of Moderate
Significance if human activity is present close to fishpond areas. |
Impacts to |
Impacts to |
Impacts to Other Egretries |
Impacts Not Significant at the Mai Po Lung
egretry, as there is no evidence that these birds forage in the Project Area
or fly over to reach other foraging sites.
No Significant Impact from
noise disturbance. Impacts to
Tam Kon Chau Egretry of Low
Significance because some birds may forage within the Project Area and a
few birds fly low over the north of the Project Area. Noise disturbance
considered to be of Low Significance. |
Impacts to Non-breeding
Bird Flight paths |
Impacts of Low to Moderate Significance for
development in the south of the Project Area.
Impacts of Moderate
Significance in the northern or northwestern part of the Project Area,
particularly along Flight paths 1, 2, 4 and 5. |
Impacts to Other Fauna |
Only
species of conservation importance recorded were Scarlet Basker and Danaid
Egg-fly, with only single individuals recorded of each. Overall No Significant Impact to herpetofauna, dragonflies, butterflies
or aquatic invertebrates. |
Mitigation for Loss of
Habitats in Project Area
· Creation of 4.74 ha of wetland habitats, including reedbeds, large open water bodies (for wetland birds) and small fish-free open water bodies (for dragonflies).
· Location of WRA at northern edge of the Project Area will allow integration with adjacent wetland habitats (fishponds and drainage channels), allowing the free movement of organisms. Wetland habitats currently present in the Project Area are found in small patches with a degree of fragmentation from each other and from surrounding wetlands.
· Maximisation of the interface between the WRA and adjacent wetlands along most of the length of the northern boundary of the Project Area, to encourage free movement of organisms (especially waterbirds) between the WRA and surrounding wetlands.
· Inclusion of wetland-dependent bird species as targets to ensure that habitats provided will mitigate for the species significantly impacted by the project.
· Creation of small water bodies free from fish, suitable for colonisation by dragonflies and amphibians, to enhance the diversity of habitats present for dragonfly and amphibian communities.
· Planting of trees and shrubs to enhance the site by provision of roosting sites for large waterbirds (cormorants and ardeids) using the WRA and adjacent fishponds.
· Inclusion of short grass habitats on bunds to provide habitat for foraging Cattle Egrets.
· Creation of a diversity of habitats on bunds and islands, including short grass, tall grass/shrubs, trees/shrubs and non-vegetated islands.
· Prevention of public access into the WRA to avoid disturbance of birds using the WRA and adjacent fishponds.
Mitigation for Loss of Ardeid Foraging Habitat
Mitigation for Direct
Impacts to Other Species
Mitigation for disturbance
to fishponds and disturbance-sensitive waterbirds
Mitigation for Pollution
Impacts to Watercourses and
Mitigation for Habitat
Fragmentation
Mitigation for Cumulative
Impacts of Habitat Loss
Mitigation for Impacts to
Egretries
Mitigation for Impacts to
Flight paths of Non-breeding Birds
Mitigation for Indirect
Impacts to Other Species outside the Project Area
Table 8‑29 Summary of Potential Ecological Impacts before and after adoption of Mitigation Measures.
Description of
Potential Impact |
Significance of
Impact without Mitigation |
Proposed
Mitigation |
Significance of
Impact after Adoption of Mitigation Measures |
Direct
Loss of Habitats in Project Area |
|
|
|
Loss of Grassland Habitats |
Loss of habitat of Low Significance due to low value of habitat and low abundance of
species of conservation importance. |
No mitigation required because impacts of
low significance but design of WRA includes 0.33 ha of grassland habitats on
bunds which will provide habitat for grassland species. |
Impact of Low Significance. |
Loss of Seasonal Marsh and Freshwater
Marsh/Reedbed |
Impacts
to habitat of Low to Moderate
Significance due to small size, ephemeral nature and high fragmentation
of habitat. Impacts to species utilising the habitat of Low to Moderate Significance, mostly due to impacts to moderately
diverse dragonfly fauna. Habitat
loss of Moderate Significance because
of importance of the habitat in a |
Loss
of wetland habitats to be compensated by provision of 4.74 ha of wetland in
the WRA (total area of seasonal marsh and freshwater marsh/reedbed currently
4.69 ha). This will include 1.12 ha of reedbed to compensate for reedbed loss
on site, as well as a variety of other habitats (open water, short grass,
trees and shrubs). |
Loss
of wetland area fully compensated, therefore No Significant Impact from wetland loss. No Significant Impacts to species using seasonal marsh and
freshwater marsh/reedbed. Temporary
wetland loss during construction of WRA of Low Significance but unavoidable and temporary. Management
of WRA for wildlife presents opportunity to enhance value of Project Area for
wildlife by habitat improvement, especially through provision of mature
reedbed habitat. |
Loss of Drainage Channels/ Ditches |
Impacts of Low Significance due to low existing value of the ditches on
site, and minimal impact to riparian trees used by roosting waterbirds. |
Any loss of habitats for dragonflies and
other fauna will be mitigated by provision of wetland habitats in WRA. |
Impacts of Low Significance. Wetland habitat to be provided in
WRA. |
Direct
Impacts to Species of Conservation Importance |
|
|
|
Impacts to Vegetation |
No Significant Impact because no species of conservation importance
present in the Project Area. |
No
mitigation required because no significant impacts predicted. |
No Significant Impact. |
Impacts to Mammals |
No Significant Impact because no species of conservation importance
present in the Project Area. |
No
mitigation required because no significant impacts predicted. |
No Significant Impact. |
Impacts to Roosting Waterbirds |
Impacts
to waterbirds roosting at the northern edge of the Project Area of Low Significance due to small numbers
of birds present and existence of other suitable roosting sites. |
Trees
and tall shrubs included in design for WRA to provide roosting sites for waterbirds. |
No Residual Impact because loss of trees fully compensated by
tree planting in WRA. |
Impacts to Foraging Ardeids |
Impacts
from loss of foraging habitat of Low
to Moderate Significance due to the relatively small number of
individuals involved, the suboptimal quality of the habitat and the presence
of other suitable foraging locations nearby. |
Habitat
suitable for foraging ardeids will be compensated in WRA. |
No
net loss of habitat, therefore No
Residual Impact during operation phase.
Unavoidable
Low Impact during construction
phase but this will be temporary, restricted to the first year of
construction. |
Impacts to Other Bird Species |
Impacts
to other bird species of conservation importance (Black Kite, Oriental
Pratincole, Little Ringed Plover, Pacific Swift, Zitting Cisticola,
Red-billed Starling and White-shouldered Starling) of Low Significance because the Project Area does not provide habitat
for locally-important populations of any of these species. |
Impacts
to these species considered to be of Low Significance due to low numbers of
individuals present, therefore further mitigation measures not required. Design of the WRA will, however, provide
habitat for these species which will compensate for habitat loss on site. |
Impacts
of Low Significance during
construction of the WRA but No
Significant Impacts to these bird species after construction completed. |
Impacts to Herpetofauna |
No Significant Impact because no species of conservation importance
present in the Project Area. |
None
required but WRA will compensate for any habitat loss. |
No Significant Impact. |
Impacts to Scarlet Basker |
Impacts
of Low Significance because of
very small numbers present in Project Area and current status of the species
in |
Mitigation
not required because impacts of Low Significance, but design of WRP should
provide suitable habitat to compensate for any habitat loss. |
Residual
impacts of Very Low Significance. |
Impacts to Danaid Egg-fly |
No Significant Impact because no evidence that the species breeds
within the Project Area. |
Mitigation
not required but inclusion of larval food plant (Portulaca oleracea) in
landscape planting will enhance value of Project Area for the species. |
No Significant Impact, planting of larval food plant may provide
net ecological benefit. |
Indirect Impacts to Habitats in
Assessment Area (outside Project Area) |
|
|
|
Disturbance
Impacts to Adjacent Fishponds |
Impacts of disturbance to waterbirds in nearby
fishponds of Moderate to High
Significance due to the importance of these ponds to waterbirds and their
proximity to the northern edge of the Project Area. |
Site layout designed to prevent human
disturbance at northern boundary and greatest human impacts furthest from
wetlands. No public access to WRA and
rest of Project Area to be screened from fishponds by landscape planting. |
Operation phase impacts outside Project Area
of Very Low Significance because
presence of WRA will distance human activity from fishpond areas. Operation
phase disturbance impacts to WRA of Low
Significance. |
|
|
Barriers during construction phase to block
noise and visual disturbance to fishponds. Timing of work in WRA during wet
season at the start of construction period; after completion WRA will provide
buffer from rest of construction work. |
Impacts during construction of WRA of Low Significance but temporary. Other
construction phase impacts of Very Low
Significance. |
Indirect
Impacts to Off-site Drainage Channels |
Impacts from pollution of watercourses
downstream of the Project Area are considered to be of Moderate Significance. Changes
in surface runoff of Low Significance because
magnitude small in comparison to existing flow in the channel. |
Good site practice during construction phase
to avoid pollution of watercourses. Connection
to trunk sewer during Operation phase to prevent discharge into watercourses
and |
Pollution
risks during construction and operation phase avoided, therefore No Significant Impact. Changes in
surface runoff of Low Significance because
magnitude small in comparison to existing flow in the channel. |
Indirect
Impacts to Other Habitats in Assessment Area |
No Significant Impacts
to other habitats
because these are small and/or show no ecological linkage to the Project
Area. |
No
mitigation measures necessary. |
No Significant
Impacts. |
Pollution
Impacts to Watercourses and |
Impacts
to watercourses downstream of the Project Area are considered to be of Moderate Significance. Pollution
impacts to |
Good
site practice during construction phase to avoid pollution of watercourses
and Connection
to trunk sewer during Operation phase to prevent discharge into watercourses
and |
Pollution
risks during construction and operation phase avoided, therefore No Significant Impact. |
Impacts from
Habitat Fragmentation |
No Significant Impacts
because Project Area
is on the edge of the wetland ecosystem and does not form a link between
other habitats in the area. |
Wetland
habitats present in Project Area will be incorporated into single WRA,
integrated with wetland habitats outside Project Area. |
No Significant Impacts
outside Project Area. Reduction
in habitat fragmentation within Project Area of Net Ecological Benefit. |
Cumulative
Impacts of Wetland Loss |
Overall
impacts would be of High Significance if |
Loss
of 4.69 ha of wetland habitats in Project Area mitigated by provision of 4.74
ha of wetland in WRA. |
Loss
of wetland habitat fully compensated, so No
Residual Impact. Potentially a small net ecological gain due to
protection of wetland habitats in WRA. |
Indirect Impacts to Species of Conservation
Importance |
|
|
|
Indirect
Impacts to Vegetation |
No impacts to species of conservation importance because
none present in Assessment Area.
Impacts of Low Significance
to other vegetation during construction phase due to dust deposition. |
Measures
to control dust emissions during construction phase. |
Impacts
to vegetation outside Project Area of Very
Low Significance. |
Indirect
Impacts to Mammals |
No Significant Impact because no species of conservation importance
recorded in Assessment Area, and low density mammal populations present. |
No
mitigation necessary. |
No Significant Impacts. |
Disturbance to Waterbirds
of Conservation Importance |
Construction-phase
disturbance of Moderate to High
Significance due to the importance of fishponds to waterbirds and their
proximity to the northern edge of the Project Area. Post-construction
disturbance impacts of Moderate
Significance if human activity is present close to fishpond areas. |
Site
layout designed to prevent human disturbance at northern boundary and
greatest human impacts furthest from wetlands. No public access to WRA and rest of the
Project Area to be screened from fishponds by landscape planting. Removal of
current potential disturbance from container storage adjacent to fishponds. |
Operation
phase impacts outside Project Area of Very
Low Significance because presence of WRA will distance human activity
from fishpond areas. Operation phase disturbance impacts to WRA of Low Significance. Impacts
during construction of WRA of Low
Significance but temporary. Other construction phase impacts of Low Significance. |
|
|
Barriers
during construction phase to block noise and visual disturbance to fishponds.
Timing of work in WRA during wet season at the start of construction period;
after completion WRA will provide buffer from rest of construction work. |
|
Impacts to |
Impacts
to |
Loss
of wetland foraging habitat to be compensated by provision of equal area of
suitable habitat in WRA. Impacts
to flight paths to be minimised by location of residential area on southern
side of Project Area and by MLP design involving building heights of 2.5/3
storeys and 4 storeys. Noise
disturbance to be minimised by adoption of appropriate site management
techniques. |
No Significant Impact from loss of habitat in operation phase, but
unavoidable Low Impact during
construction of WRA. Low Impact to flight paths. Very Low Impact to egretry due to noise disturbance during
construction phase. |
Impacts to
Other Egretries |
Impacts
of Not Significant at the Mai Po
Lung egretry, as there is no evidence that these birds forage in the Project
Area or fly over to reach other foraging sites. No
Significant Impact from noise disturbance. |
Loss
of wetland foraging habitat to be compensated by provision of equal area of
suitable habitat in WRA. |
No Impacts to Mai Po Lung egretry. Impacts
to Tam Kon Chau due to habitat loss of Low
Significance during construction of WRA, but No Net Impact during operation phase. |
|
Impacts
to Tam Kon Chau Egretry of Low
Significance because some birds may forage within the Project Area and a
few birds fly low over the north of the Project Area. Noise disturbance
considered to be of Low Significance. |
Impacts
to flight paths to be minimised by location of residential area on southern
side of Project Area and by MLP design involving building heights of 2.5/3
storeys and 4 storeys. Noise
disturbance to be minimised by adoption of appropriate site management
techniques. |
Low Impact to flight paths from Tam Kon Chau. Very Low Impact to Tam Kon Chau due to noise disturbance
during construction phase. |
Impacts to Bird
Flight Paths |
Impacts
of Low Significance for
development in the south of the Project Area.
Impacts of Moderate
Significance in the northern or northwestern part of the Project Area,
particularly along Flight paths 1, 2, 4 and 5. |
Layout
of the Project Area will restrict residential development to southern part of
Project Area, with tallest buildings closest to existing residential estates.
Building heights will be 2.5/3 storeys and 4 storeys and will therefore not
be significantly higher than in surrounding residential estates. |
Operation
phase impacts of Very Low Significance
because location and height of buildings will not obstruct existing
flight paths. Impacts
of Low Significance during
construction of WRA on northern part of the Project Area, but this will be
temporary at the start of construction phase. |
Impacts to
Other Fauna |
Only
species of conservation importance recorded were Scarlet Basker and Danaid
Egg-fly, with only single individuals recorded of each. Overall No Significant Impact to herpetofauna, dragonflies, butterflies
or aquatic invertebrates. |
No
mitigation measures required. |
No Significant
Impacts. |
Anon. 1997. Study on the Ecological Value of Fish Ponds
in
association with Wetlands International to Planning Department, Hong Kong SAR Government.
Anon. 2004a. Summer 2004 Report: Egretry Counts in Hong
Kong with particular reference to the
Anon. 2004b.
Focal Study of Black-faced
Spoonbills in
Anon. 2005. Summer 2005 Report on Waterbird Monitoring
at the
Anon. 2006a. Winter 2005-06 Report on Waterbird
Monitoring at the
Anon. 2006b. Summer 2006 Report: Egretry Counts in Hong
Kong with particular reference to the
BirdLife International. 2007. Species Factsheet: Sturnus sericeus. Downloaded fromhttp://www.birdlife.org.
Fellowes, J.R., Lau,
M.W.N., Dudgeon, D., Reels, G.T., Ades, G.W.J., Carey, G.J., Chan, B.P.L.,
Kendrick, R.C., Lee, K.S., Leven, M.R., Wilson, K.D.P and Yu, Y.T. 2002. Wild
Animals to Watch: Terrestrial and Freshwater Fauna of Conservation Concern in
Karsen, S.J., Lau, M.W.N.
and Bogadek, A. 1998.
Lee, V.L.F., Lam, S.K.S.,
Ng, F.K.Y., Chan, T.K.T. and Young, M.L.C. 2004. Field Guide to the Freshwater Fish of
Lo, P.Y.F. and Hui, W.l.
2004
Shek, C.T. 2006. A Field Guide to the Terrestrial Mammals of
Wilson, K.D.P. 2004. Field Guide to the Dragonflies of
Wong, C.L.C. 2002b. Summer 2002 Report on Egretry Counts in Hong
Kong, with particular reference to the
Wong, L.C. and Woo, C.K. 2003. Summer 2003 Report on Egretry Counts
in
PREFACE
Wo Shang Wai to the north of Royal Palms and
The planning intention of this location is to provide
incentive for the restoration of degraded wetlands adjoining existing fish
ponds and to encourage the phasing out of sporadic open storage and port
back-up uses on degraded wetland. This
can be achieved through comprehensive residential and/or recreational
development to include wetland restoration area. Development or redevelopment schemes on the
degraded wetlands directly adjoining the existing continuous and contiguous
fish ponds should include wetland restoration and buffer proposals to separate
the development from and minimize its impact on the fish pond areas. Any new building should be located farthest
away from
·
Environmental Impact Assessment Ordinance (Cap.
499., S.16), Technical Memorandum on Environmental Impact Assessment Process
(EIAO-TM), Annexes 9 and 17;
·
·
Town Planning Board Guidelines for Application
for Developments within
·
Fisheries Protection Ordinance (Cap. 171)
(i) The physical environmental background;
(ii) The existing level and pattern of pond culture activities and fisheries production;
(iii) The existing pond culture resources and composition of commercially important species;
(iv) Identification of parameters and area that are important to pond culture activities; and
(v) The status of the fishponds, the productivity and value of the fisheries resources of the actively used pond.
Literature
Review
Table 9‑1 AFCD Figures on HKSAR Pond Culture Fisheries
Year* |
Fish Pond Area (ha) |
Freshwater Fish Production (tonnes) |
1997 |
1,125 |
5,000 |
1998 |
1,110 |
4,900 |
1999 |
1,100 |
4,500 |
2000 |
1,060 |
2,820 |
2001 |
1,059 |
2,550 |
2002 |
1,030 |
1,989 |
2003 |
1,030 |
2,110 |
2004 |
1,030 |
1,980 |
2005 |
1,030 |
1,900 |
2006 |
1,024 |
1,943 |
*Data
from 1997 to 2000 are abstracted from Maunsell (2004).
Data from 2001 to 2006 are abstracted from
AFCD Annual Reports 2001-20052 and AFCD website1.
Field
Investigation Findings
Table 9‑2 Fishponds Status and Area in the Project Area
Status |
Size |
Activities |
Active
Freshwater Fishponds |
37.9 ha |
- Polyculture of Grass Carp, Tilapia, Big Head Carp and Grey
Mullet. - Trash fish capturing for aquarium sell. - Accredited Fish Farm Scheme providing
freshwater fish with quality assurance. |
Fishponds
in drying or maintenance stage |
5.4 ha |
- Draining around once a year for fish collection to the market. - Drying by direct sunlight to reduce the bacteria from fish
faeces. - Maintenance every 4 – 10 years to dredge the pond bottom and
adding lime to neutralize the acidity from long term rearing. |
Inactive
Fishponds |
18.7 ha |
- Abandoned from previous fishing ground. - Abandoned from previous aquaculture activities and forming reed
bed. |
Active
Brackish Fishponds |
17.9 ha |
- Culture of higher value estuarine fish species: Spotted Scat,
Giant Grouper and Grey Mullet. - Accredited Fish Farm Scheme providing brackish fishes with
quality assurance. |
Construction Phase
Operational Phase
Table 9‑3 Evaluation of Fisheries Impact
Criteria |
Increase suspended solids concentration in the adjacent fishponds
water column due to dust arises from the construction, water pollution due to
chemical waste release from mechanical equipment, silt runoff and sediment
release. |
Nature
of impact |
The impacts of silt runoff, sediment release and construction dust
will be temporary, localised and short term during the construction
period. However, the fisheries impacts
may not be recoverable/ reversible after the suspended solids have settled. The impacts of high dose of chemical waste pollution will be irreversible
and long term. |
Size of
affected area |
The adjoining fishponds will be potentially affected by water
pollution from chemicals as well as suspended solids arising from the works. |
Loss of
fisheries resources/production |
Insignificant for impacts of silt runoff, minor sediment release and
construction dust. Low proportion of total fisheries resources will be affected by high
dose of chemical waste pollution. Low impact from loss of culture fisheries resources due to both SS
and chemical |
Destruction
and disturbance of nursery and spawning grounds |
Not applicable. |
Impact
on fishing activity |
Not applicable. |
Impact
on aquaculture activity |
No aquaculture farms are affected by the insignificant impacts of silt
runoff, minor sediment release and construction dust. Low impacts for the effect of both SS and chemical waste pollution on
the aquaculture acitivity in the adjoining 4 fishponds with good site
practice and proper mitigation measures, as few aquaculturists will be
affected. |
1http://www.afcd.gov.hk/english/fisheries/fish_aqu/fish_aqu_mpo/fish_aqu_mpo.html (downloaded on 13 August 2007)
2http://www.afcd.gov.hk/english/publications/publications_dep/publications_dep.html
(downloaded on 13 August 2007)
3http://www.afcd.gov.hk/english/fisheries/fish_aqu/fish_aqu_good/fish_aqu_good.html
(downloaded on 13 August 2007)
AFCD, 2007. Agricultural, Fisheries and Conservation Department Annual Report 2005 – 2006. The Government of Hong Kong SAR.
AFCD, 2006. Agricultural, Fisheries and Conservation Department Annual Report 2003 – 2005. The Government of Hong Kong SAR.
AFCD, 2004. Agricultural, Fisheries and Conservation Department Annual Report 2002 – 2003. The Government of Hong Kong SAR.
AFCD, 2003. Agricultural, Fisheries and Conservation Department Annual Report 2001 – 2002. The Government of Hong Kong SAR.
Aspinwall &
Company, 1997. Study on the Ecological
Value of Fishponds in
Maunsell Consultants Asia Ltd., 2004. Improvements to San Tin Interchange EIA Report. Highways Department, HKSAR.
Planning
Department
Ove Arup & Partners Hong Kong Ltd., 2004. Agreement No. CE 66/2001 (EP) EIA and TIA Studies for the Stage 2 of PWP Item No. 215DS – Yuen Long and Kam Tin Sewerage and Sewage Disposal (YLKTSSD) Environmental Impact Assessment (Final). Drainage Services Department, HKSAR.
PREFACE
Wo Shang Wai to the north of Royal Palms and
The planning intention of this location is to provide
incentive for the restoration of degraded wetlands adjoining existing fish
ponds and to encourage the phasing out of sporadic open storage and port
back-up uses on degraded wetland. This
can be achieved through comprehensive residential and/or recreational
development to include wetland restoration area. Development or redevelopment schemes on the
degraded wetlands directly adjoining the existing continuous and contiguous
fish ponds should include wetland restoration and buffer proposals to separate
the development from and minimize its impact on the fish pond areas. Any new building should be located farthest
away from
· Antiquities and Monuments Ordinance (Cap. 53);
· Environmental Impact Assessment Ordinance (Cap. 499);
· Technical Memorandum on EIA Process (Annex 10 and 19, EIAO-TM); and
·
Antiquities and Monuments Ordinance (AM Ordinance)
Environmental Impact
Assessment Ordinance (EIAO) and Technical Memorandum on EIA Process (EIAO-TM)
Assessment Scope
Identification
of Baseline Cultural Heritage Conditions
· List of declared monuments protected by the AM Ordinance (Cap. 53);
· Deemed monuments, graded buildings and list of heritage sites identified by the AMO; and
· Published and unpublished papers, records, archival and historical documents through public libraries, archives and tertiary institutions.
Declared
Monuments
Graded Historical
Buildings
Historical
Villages
Other Cultural
Elements
Construction
Phase
Operational
Phase
Ove Arup & Partners Hong Kong Limited, 2004. EIA & TIA Studies for the Stage 2 of PWP
Item No. 215DS – Yuen Long and Kam Tim Sewerage and Sewage Disposal, EIA
(Final). Drainage Services Department,
PREFACE
Wo Shang Wai to the north of Royal Palms and
The planning intention of this location is to provide
incentive for the restoration of degraded wetlands adjoining existing fish
ponds and to encourage the phasing out of sporadic open storage and port
back-up uses on degraded wetland. This
can be achieved through comprehensive residential and/or recreational
development to include wetland restoration area. Development or redevelopment schemes on the
degraded wetlands directly adjoining the existing continuous and contiguous
fish ponds should include wetland restoration and buffer proposals to separate
the development from and minimize its impact on the fish pond areas. Any new building should be located farthest
away from
· a listing of the relevant environmental legislation and guidelines;
· a definition of the scope and contents of the study, including a description of the assessment methodology;
· a review of the relevant planning and development control framework;
· a review of comments on landscape and visual issues received during previous consultation with the public and/or advisory bodies and how these have been addressed in the design;
· a baseline study providing a comprehensive and accurate description of the baseline landscape and visual character;
· identification of the potential landscape and visual impacts and prediction of their magnitude and potential significance, before and after the mitigation measures; and
· recommendation of appropriate mitigation measures and associated implementation programmes.
· Environmental Impact Assessment Ordinance (Cap 499, section 16) and the Technical Memorandum on EIA Process (EIAO-TM), particularly Annexes 10, 11, 18, 20 and 21;
· EIAO Guidance Note (GN) 8/2002;
· Outline Zoning Plan No.S/YL-MP/6;
·
Town Planning Board Guidelines
for Application for Developments Within
·
· Town Planning Ordinance (Cap 131);
· Forests and Countryside Ordinance (Cap 96) and its subsidiary legislation the Forestry Regulations;
· Country Parks Ordinance (Cap 208);
· Marine Parks Ordinance (Cap 476) and associated subsidiary legislation;
· Animals And Plants (Protection of Endangered Species) Ordinance (Cap 187);
· WBTC No. 23/93 - Control of Visual Impact of Slopes;
·
SILTech Publication (1991) –
Tree Planting and Maintenance in
· WBTC No. 12/2000 – Improvement to the Appearance of slopes in connection with WBTC 23/93;
·
WBTC No. 30/2001 – Capital
Works or Maintenance Works (including Tree Planting) Within or Adjacent to the
Kowloon Canton Railway (
· WBTC No. 7/2002 – Tree Planting in Public Works
· ETWBTC No. 3/2006 - Tree Preservation;
· Land Administration Office Instruction (LAOI) Section D-12 – Tree Preservation
· GEO publication (1999) – Use of Vegetation as Surface Protection on Slopes;
· GEO 1/2000 – Technical Guidelines on Landscape Treatment and Bio-engineering of Man-made Slopes and Retaining Walls; and
·
Urban Council Publication
(1998) - Champion Trees in Urban
· Identification of the baseline landscape resources (physical and cultural) and landscape character found within the Assessment Area. This is achieved by site visits and desk-top study of topographical maps, information databases and photographs.
· Assessment of the degree of sensitivity to change of the landscape resources. This is influenced by a number of factors including whether the resource/character is common or rare, whether it is considered to be of local, regional, national or global importance, whether there are any statutory or regulatory limitations/ requirements relating to the resource, the quality of the resource/character, the maturity of the resource, and the ability of the resource / character to accommodate change. The sensitivity of each landscape feature and character area is classified as follows:
High: |
Important landscape or landscape resource of particularly distinctive character or high importance, sensitive to relatively small changes |
Medium: |
Landscape or landscape resource of moderately valued landscape characteristics reasonably tolerant to change |
Low: |
Landscape or landscape resource, the nature of which is largely tolerant to change |
· Identification of potential sources of landscape impacts. These are the various elements of the construction works and operational procedures that will generate landscape impacts.
· Identification of the magnitude of landscape impacts. The magnitude of the impact depends on a number of factors including the physical extent of the impact, the landscape and visual context of the impact, the compatibility of the project with the surrounding landscape; and the time-scale of the impact - i.e. whether it is temporary (short, medium or long term), permanent but potentially reversible, or permanent and irreversible. Landscape impacts have been quantified wherever possible. The magnitude of landscape impacts is classified as follows:
Large: |
The landscape or landscape
resource would suffer a major change |
Intermediate: |
The landscape or landscape
resource would suffer a moderate change |
Small: |
The landscape or landscape
resource would suffer slight or barely perceptible changes |
Negligible: |
The landscape or landscape
resource would suffer no discernible change. |
· Identification of potential landscape mitigation measures. These may take the form of adopting alternative designs or revisions to the basic engineering and architectural design to prevent and/or minimise negative impacts; remedial measures such as colour and textural treatment of building features; and compensatory measures such as the implementation of landscape design measures (e.g. tree planting, creation of new open space etc) to compensate for unavoidable negative impacts and to attempt to generate potentially positive long term impacts. A programme for the mitigation measures is provided. The agencies responsible for the funding, implementation, management and maintenance of the mitigation measures are identified and their approval-in-principle has been sought.
· Prediction of the significance of landscape impacts before and after the implementation of the mitigation measures. By synthesising the magnitude of the various impacts and the sensitivity of the various landscape resources it is possible to categorise impacts in a logical, well-reasoned and consistent fashion. Table 11–1 shows the rationale for dividing the degree of significance into four thresholds, namely insubstantial, slight, moderate, and substantial, depending on the combination of a negligible-small-intermediate-large magnitude of impact and a low-medium-high degree of sensitivity of landscape resource/character. The significant thresholds are defined as follows:
Substantial: |
Negative / positive impact where the proposal would cause significant deterioration or improvement in existing landscape quality |
Moderate: |
Negative / positive impact where the proposal would cause a noticeable deterioration or improvement in existing landscape quality |
Slight: |
Negative / positive impact where the proposal would cause a barely perceptible deterioration or improvement in existing landscape quality |
Insubstantial: |
No discernible change in the existing landscape quality |
· Prediction of Acceptability of Impacts. An overall assessment of the acceptability, or otherwise, of the impacts according to the five criteria set out in Annex 10 of the EIAO-TM.
Table 11‑1 Relationship between Receptor Sensitivity and Impact Magnitude in Defining Impact Significance
|
Large |
Moderate |
Moderate
/ Substantial |
Substantial |
Magnitude
of Impact |
Intermediate |
Slight
/ Moderate |
Moderate |
Moderate
/ Substantial |
|
Small |
Slight |
Slight
/ Moderate |
Moderate |
|
Negligible |
Insubstantial |
Insubstantial |
Insubstantial |
|
|
Low |
Medium |
High |
|
|
Receptor
Sensitivity (of
Landscape Resource, Landscape Character Area or VSR) |
· Identification of the Zones of Visual Influence during the construction and operational phases of the Wo Shang Wai Comprehensive Development project. This is achieved by site visit and desk-top study of topographic maps and photographs, and preparation of cross-sections to determine visibility of the Wo Shang Wai Comprehensive Development project from various locations.
· Identification of the Visually Sensitive Receivers (VSRs) within the ZVIs at construction and operational phases. These are the people who would reside within, work within, play within, or travel through, the ZVIs.
· Assessment of the degree of sensitivity to change of the VSRs and assessment of the potential magnitude of visual impacts. This includes consideration of the following factors:
· the type of VSRs, which is classified according to whether the person is at home, at work, at play, or travelling. Those who view the impact from their homes are considered to be highly sensitive as the attractiveness or otherwise of the outlook from their home will have a substantial effect on their perception of the quality and acceptability of their home environment and their general quality of life. Those who view the impact from their workplace are considered to be of low sensitivity as the attractiveness or otherwise of the outlook will have a less important, although still material, effect on their perception of their quality of life. Those who view the impact whilst taking part in an outdoor leisure activity may display varying sensitivity depending on the type of leisure activity. Those who view the impact whilst travelling on a public thoroughfare will also display varying sensitivity depending on the speed of travel.
· the approximate numbers of affected VSRs (very few, few, many, very many);
· the value and quality of existing views,
· the availability and amenity of alternative views;
· the duration or frequency of view;
the degree of visibility;
· the compatibility with the visual character of the surrounding landscape;
· the duration of the impact;
· scale of the development in the view;
· the reversibility of the impact;
· the distance of the source of impact from the viewer.
· the change / blockage to the character of existing views.
High: |
The VSR is highly sensitive to any change in their viewing experience |
Medium: |
The VSR is moderately sensitive to any change in their viewing experience |
Low: |
The VSR is only slightly sensitive to any change in their viewing experience |
Large: |
The VSRs would suffer a major change in the character of their viewing experience; |
Intermediate: |
The VSRs would suffer a moderate change in the character of their viewing experience; |
Small: |
The VSRs would suffer a small change in the character of their viewing experience; |
Negligible: |
The VSRs would suffer no discernible change in the character of their viewing experience. |
·
Identification of potential
sources of visual impacts. These are the various elements of the construction works and operational procedures that would
generate visual impacts.
· Identification of potential visual mitigation measures. These may take the form of adopting alternative designs or revisions to the basic engineering and architectural design to prevent and/or minimise negative impacts; remedial measures such as colour and textural treatment of building features; and compensatory measures such as the implementation of landscape design measures (e.g. tree planting, creation of new open space etc) to compensate for unavoidable negative impacts and to attempt to generate potentially positive long term impacts. A programme for the mitigation measures is provided. The agencies responsible for the funding, implementation, management and maintenance of the mitigation measures are identified and their approval-in-principle has been sought.
· Prediction of the significance of visual impacts before and after the implementation of the mitigation measures. By synthesising the magnitude of the various visual impacts and the sensitivity of the VSRs, and the numbers of VSRs that are affected, it is possible to categorise the degree of significance of the impacts in a logical, well-reasoned and consistent fashion. Table 11–1 shows the rationale for dividing the degree of significance into four thresholds, namely, insubstantial, slight, moderate and substantial, depending on the combination of a negligible-small-intermediate-large magnitude of impact and a low-medium-high degree of sensitivity of VSRs. Consideration is also given to the relative numbers of affected VSRs in predicting the final impact significance - exceptionally low or high numbers of VSRs may change the result that might otherwise be concluded from Table 11–1. The significance of the visual impacts is categorised as follows:
Substantial: |
Negative / positive impact where the proposal would cause significant deterioration or improvement in existing visual character; |
Moderate: |
Negative / positive impact where the proposal would cause a noticeable deterioration or improvement in existing visual character; |
Slight: |
Negative / positive impact where the proposal would cause a barely perceptible deterioration or improvement in existing visual character; |
Insubstantial: |
No discernible change in the existing visual character. |
· Prediction of Acceptability of Impacts. An overall assessment of the acceptability, or otherwise, of the impacts according to the five criteria set out in Annex 10 of the EIAOTM.
·
All mitigation proposals in
this report are practical and achievable within the known parameters of
funding, implementation, management and maintenance. The suggested agents for
the funding and implementation (and subsequent management and maintenance, if
applicable) are indicated in Table 11–3 and Table 11–4.
“The planning intention of this zone is to provide incentive for the
restoration of degraded wetlands adjoining existing fishponds and to encourage
the phasing out of sporadic open storage and port back-up uses on degraded
wetland. This can be achieved through
comprehensive residential and/or recreational development to include wetland
restoration area. Development or redevelopment
schemes on the degraded wetlands directly adjoining the existing continuous and
contiguous fishponds should include wetland restoration and buffer proposals to
separate the development from and minimize its impact on the fish pond
areas. Any new building should be
located farthest away from
“To be in line with the rural setting which is mainly village
houses, to minimize visual impact and to take into account the capacities of
local road network and infrastructure in this area, development or
redevelopment shall not result in a total development or redevelopment
intensity in excess of a total plot ratio of 0.4 and a maximum building height
of 6 storeys including car park. To
provide flexibility for innovative design adapted to the characteristics of
particular sites, minor relaxation of the above restrictions may be considered
by the Board through the planning permission system. Each proposal will be considered on its
individual planning merits. Full
justifications and illustration materials should be submitted to the Board for
consideration…
“An area at Wo Shang Wai to the north of Royal Palms and
“The intention of the WBA is to protect the ecological integrity of
the fishponds and wetland within the WCA and prevent development that would
have a negative off-site disturbance impact on the ecological value of
fishponds. A buffer area of about 500m
along the landward boundary of the WCA is thus designated as a WBA. As a substantial amount of the fishponds
within the WBA have already been lost over time through filling and certain
areas have been degraded by the presence of open storage use, these degraded
areas may be considered as target areas to allow an appropriate level of
residential/recreational development so as to provide an incentive to remove
the open storage use and/or to restore some of the fishponds lost.
Proposals for residential/recreational developments on degraded
sites to remove/replace existing open storage or container back-up uses and/or
to restore lost wetlands may be given sympathetic consideration by the Board
subject to satisfactory ecological and other impact assessments. For those disturbed areas directly abutting
the WCA, the development should provide a wetland and visual buffer to separate
the development from the WCA to minimise its impact on the wetland and to
restore some of the lost fishponds to an appropriate form of wetland adjoining
the WCA. Within these degraded areas
targeted for upgrading, the following types of activities may be considered:
Wetland Restoration
Development proposals to restore lost fishponds or to replace
existing undesirable uses by wetland habitats are encouraged…
Residential
Residential development projects which include replacement of
existing open storage and port back-up uses and/or proposals of detailed
wetland restoration may be given special consideration subject to satisfactory
ecological and other impact assessments.
These developments should be compatible with the surrounding land uses
and the rural setting of the area”
Physical, Human and Cultural Landscape Resources
On-Site Landscape Resources
LR29 – Drainage Channel at East of Site – A drainage channel 5m wide and around 120m long, flowing from the housing area towards a storage area and along the boundary fence. The water is clear and the embankment is covered with grass. The sensitivity of this landscape resource is Low.
LR30 – Freshwater Marsh – Approximately 4 ha area of marsh with patches of Phragmites sp reeds in wet depression near the centre of the Site. The sensitivity of this landscape resource is Medium.
LR32 – Grassland with
Seasonal Marsh Patches and Soils on Site – 11.74ha
(11.05ha of grassland and 0.69ha of seasonal marsh patches) of muddy grassland
comprising common grass species. The
sensitivity of this landscape resource is Low.
LR33 – Tree Group on Site – There are 4 nos. of
semi-mature trees comprising Dimocarpus
longan and Aleurites moluccana with a typical high of 5m. The sensitivity of this landscape resource is
Medium.
LR34 – Banana Trees on Site – A group of approximately 10 nos. of 4m high banana trees (Musa spp.). The sensitivity of this landscape resource is Low.
LR36 – Trees in Open Storage Area – There are approximately 74 semi-mature trees and about 119 young trees (less than 95mm dbh) with an average height of 5m comprising mainly Macaranga tanarius, Hibiscus tiliaceus, Bauhinia blakeana, Albizia lebbeck. The sensitivity of this landscape resource is Medium.
LR39 – Trees along
Off-Site Landscape Resources
LR1 – Trees Along
LR2 – Roadside Trees Surrounding Mai Po Substation – There are in this location, about 200 mature Eucalyptus citriodora with an average height of 10m. The sensitivity of this landscape resource is Medium.
LR3 – Trees Opposite Mai Po San Tsuen – There are about 40 mature trees in this location comprising mainly Dimocarpus longan, Celtis sinensis, Microcos paniculata generally approximately 6m high. The sensitivity of this landscape resource is Medium.
LR4 – Field East of
LR5 – Ponds in Field East
of
LR6 – Trees Behind Field
east of
LR7 – Stream Next to Field east of San Tam Road – This comprises a 220m long and 1m wide natural stream flowing from agricultural fields to a drainage channel along the east side of San Tam Road. Stream water is clear and the stream is about 100mm deep. Common riparian vegetation species are present along the natural embankment. The sensitivity of this landscape resource is Medium.
LR8 – Pond East of San Tam Road– A small pond approximately 3m2 besides village buildings. The water surface is covered with green algae. The sensitivity of this landscape resource is Low.
LR9 – Trees along
LR10 – Drainage Channel East of San Tam Road – This is a man made channel approximately 2m wide and 700m in length. The channel is made of concrete and common riparian vegetation species are present along the bank. The sensitivity of this landscape resource is Low.
LR11 – Grassland East of
LR12 – Trees around
Cottage Area east of
LR13 – Slope adjoining
LR14 – Trees North of
LR15 – Trees inside
LR16 – Fruit Trees North of Ki Lung Shan Foothills I – There are about 100 semi-mature fruit trees with an average height of 5m. They are mainly Dimocarpus longan, Litchi chinensis, Musa spp., Mangifera indica. The sensitivity of this landscape resource is Medium.
LR17 – Woodland North of Ki Lung Shan Foothills II – There are about 100 mature trees comprising mainly common woodland species with an average height of 5m (Microcos paniculata, Sapium sebiferum, Macaranga tanarius). The sensitivity of this landscape resource is Medium.
LR18 – Trees on Ki Lung Shan Foothills II – There are about 50 semi-mature trees comprising mainly Hibiscus tiliaceus, Michelia x alba, Acacia confuse. They have an average height of 4m. The sensitivity of this landscape resource is Medium.
LR19 – Trees on Ki Lung Shan Foothills I – There are about 50 ornamental trees with an average height of 5m comprising mainly Delonix regia, Michelia x alba, Juniperus chinensis var. kaizuca, Araucaria heterophylla, Mangifera indica. The sensitivity of this landscape resource is Medium.
LR20 – Trees in
LR21 – Grassland on Ki
Lung Shan Foothills – An area of grassland and small shrubs on hillsides. The sensitivity of this landscape resource is
Low.
LR22 – Trees between
LR23 – Chunk Kai Horticultural Nursery – There are approximately 10 semi-mature trees - about 5m high - comprising Mangifera indica, Ficus microcarpa. The Nursery also contains some young trees. The sensitivity of this landscape resource is Low.
LR24 – Trees along
LR25 – Pond east of Royal Palms – A small pond of 2m x 10m full of water. The sensitivity of this landscape resource is Low.
LR26 – Field east of Royal Palms – Agricultural field with common crop species. The sensitivity of this landscape resource is Medium.
LR27 – Trees east of Royal Palms – There are approximately 10 semi-mature trees with an average height of 5m, comprising mainly Musa spp, Dimocarpus longan, Clausena lansium. The sensitivity of this landscape resource is Medium.
LR28 – Trees outside Royal
Palms near
LR31 – Trees on northern
Boundary of Royal Palms – There are approximately 300 semi-mature trees of a typical height of
5-10m. Most are ornamental species
comprising mainly Mangifera
indica, Ficus microcarpa, Livistona chinensis, Aleurites moluccana. The sensitivity of this landscape resource is
Medium.
LR35 – Stream on northern Boundary of Site – A clear, slow running stream of approximately 10m wide, 2m deep and around 3000m long flowing from Tam Kon Chau through the fishponds to the site. Common riparian vegetations are present along the embankment. The sensitivity of this landscape resource is Medium.
LR37 – Not Used
LR38 – Trees inside Open
Storage Area – There are approximately 200 nos. of
wild grown semi-mature trees with a typical height of 5m comprising mainly Macaranga tanarius, Leucaena leucocephala. The sensitivity of this landscape resource is
Medium.
LR40 – Trees in Cottage
Area east of
LR41 – Pond behind Mai Po
San Tsuen – A small pond with an area of 60m x 80m
contains fully of water. The sensitivity
of this landscape resource is Low.
LR42 – Grassland besides DSD building – Artificial grassland besides a Drainage Services Department’s building. The sensitivity of this landscape resource is Low.
LR43 – Trees in Mai Po San
Tsuen – There are approximately 40 nos. of
semi-mature trees of typical height of 5m comprising mainly Macaranga tanarius, Michelia x alba,
Dimocarpus longan, Mangifera indic, Roystonea regia, Archontophoenix alexandrae, Juniperus chinensis var. kaizuca, Livistona
chinensis. The sensitivity of this
landscape resource is Medium.
LR44 – Trees behind Mai Po
San Tsuen – There are about 30 nos. of wild grown
semi-mature trees comprising mainly Leucaena
leucocephala, Melia azedarach. They have an average height of 6m. The sensitivity of this landscape resource is
Medium.
LR45 – Trees in Mai Po Lo
Wai – There are approximately 10 nos. of
semi-mature trees with a typical height of 5m comprising Celtis sinensis, Juniperus chinensis var. kaizuca, Clausena lansium,
Aglaia odorata. The sensitivity of
this landscape resource is Medium.
LR46 – Field west of Mai
Po Lo Wai – Agricultural field with an approximate
area of 2000m2 with a few common crop species cultivated. The sensitivity of this landscape resource is
Low.
LR47 – Pond west of Mai Po
San Tsuen – A
large pond of approximately 150m x 100m fully covered with fresh water plant Eichhornia
crassipes.
The sensitivity of this landscape resource is Low.
LR48 – Channel west of Mai
Po San Tsuen – A
man-made channel of 2m wide and 100m long with concert bank. Water is running
slow and sallow.
The sensitivity of this landscape resource is Low.
LR49 – Channel beside DSD building – A man-made channel of 2 m wide and 300m long with concert bank. The sensitivity of this landscape resource is Low.
LR50 – Woodland along
Castle Peak Road (Mai Po) – There are approximately
500 semi-mature to mature trees, comprising Macaranga
tanarius, Musa spp, Bambusa spp, Eucalyptus citriodora, Ficus
microcarpa. Their typical height is of 7m.
The sensitivity of this landscape resource is Medium.
LR51 – Fishponds along
LR52 – Trees north of Tam
Kon Chau Road –There are approximately 10 trees -
about 4m high - comprising mainly Macaranga
tanarius. The sensitivity of this landscape resource is Medium.
LR53 – Dry Pond north of
LR54 – Fishponds south of
LR55 – Trees beside
Fishponds south of
LR56 – Fishponds north-east of Site – A group of fishponds full of water, approximately 300m x 300m. The embankment is covered with grass and a few trees. The sensitivity of this landscape resource is Low.
LR57 – Trees beside
fishponds north-east of Site –There are about 2
semi-mature trees with a typical height of 5m, comprising mainly Melia azedarach. The sensitivity of this landscape resource is
Medium.
LR58 – Stream north of Tam
Kon Chau Road – Slow running stream 400m long and
10m wide with rubbish present. Reed and
grass present on the embankment. The
sensitivity of this landscape resource is Medium.
LR59 – Trees beside Stream
north of
LR60 – Fishponds north of
LR61 – Trees beside
Fishponds north of
LR62 – Fishponds
north-west of Site – A group of fishponds full of
water, approximately 400m x 400m. The embankment is covered with grass and a
few trees. The sensitivity of this
landscape resource is Low.
LR63 – Trees beside
Fishponds north-west of Site –There are about 60 4m
high semi-mature banana trees (Musa spp). The sensitivity of this landscape resource is
Medium.
LR64 – Fishponds north of
Tam Kon Chau – A group of fishponds full of water,
approximately 200m x 100m. The embankment is covered with grass and a few
trees. The sensitivity of this landscape
resource is Low.
LR65 – Trees beside
Fishponds north of Tam Kon Chau – There are about
30 nos. of 5m high semi-mature Dimocarpus
longan trees. The sensitivity of this landscape resource is
Medium.
LR66 – Trees in Tam Kon
Chau – There are about 40 semi-mature to mature
trees with a typical height of 6m, comprising mainly Dimocarpus longan, Ficus microcarpa, Casuarina equisetifolia. The sensitivity of this landscape resource is
Medium.
LR67 – Pond south of Tam
Kon Chau – A
pond full of water, about 40m x 40m. The embankment is covered with grass
and a few trees. The sensitivity of this
landscape resource is Low.
LR68 – Fishponds south of
Tam Kon Chau – A group of fishponds full of water,
approximately 200m x 300m. The embankment is covered with grass and a few
trees. The sensitivity of this landscape
resource is Low.
LR69 – Fishponds
south-west of Tam Kon Chau – A group of fishponds
full of water extending an area of 100m x 300m. The embankment is covered with
grass and a few trees. The sensitivity
of this landscape resource is Low.
LR70 – Fish Pond west of
LR71–Trees beside Fish
Pond west of
LR72 – Fishponds
north-west of
LR73 – Fishponds west of
LR74 – Trees beside
Fishponds west of
LR75 – Fishponds west of
LR76 – Fish Pond west of
Palm Springs – A long rectangular fish pond covered
with reeds, about 2000 m2. Grass is present on the embankment. The sensitivity of this landscape resource is
Low.
LR77 – Fishponds west of
LR78 – Trees beside
Fishponds west of
LR79 – Fishponds west of
LR80 – Trees beside
Fishponds west of
LR81 – Fishponds west of
LR82 – Trees beside
Fishponds west of
LR83 – Stream west of
LR84 – Fishponds west of
LR85 – Trees beside Fishponds
west of
LR86 – Trees in northern
LR87 – Trees in western
LR88 – Trees in southern
LR89 – Trees in Car Park
in
LR90 – Pond in Wo
LR91 – Trees in northern
LR92 – Trees at Shopping
Mall in
LR93 – Ponds in
LR94 – Trees beside Ponds
in
LR95 – Trees in southern Royal Palms – There are about 200 semi-mature trees comprising Livistona chinensis, Aleurites moluccana. Michelia x alba, Araucaria heterophylla. They have an average height of 6m. The sensitivity of this landscape resource is Medium.
LR96 – Trees around Sports
Facilities in Royal Palms – There are about 50 semi-mature trees with an average height of
6m, comprising Ficus mircocarpa,
Livistona chinensis. The sensitivity
of this landscape resource is Medium.
LR97 – Trees east of Royal Palms – There are about 200 semi-mature trees, comprising Eucalyptus robusta, Macaranga tanarius, Bombax ceiba, Cinnamomum camphora, Casuarina equisetifoli. They have an average height of 6m. The sensitivity of this landscape resource is Medium.
LR98 – Pond south of
LR99 – Ponds south of
LR100 – Trees surrounding
Ponds south of
LCA1 -
LCA2 - Tsing Lung Tsuen Plain
·
Tai Fu Tai Mansion is
considered as one of the most beautifully embellished traditional Chinese
buildings in
·
Man Lun Fung Ancestral Hall is
noted for the commemoration of one of the 'Five Major Clans' in
· Man Ancestral Hall
·
Mai Po
Village egretry is registered SSSI
LCA3 - San Tin Plain
LCA4 - Ki Lung Shan Uplands
Zone of Visual Influence (ZVI)
Visually Sensitive Receivers (VSRs)
Residential Visually Sensitive Receivers
R1 Residents in Royal Palms (those most affected are approximately 21 properties on Ventura Avenue and approximately 8 properties on Santa Monica Avenue which are the only properties which directly face the site)
R2 Residents in Palm Springs (those most affected are approximately 17properties in Camelia Path and approximately 32 properties on Narcissus Path which are the only properties which directly face the site)
R3 Residents in Wo Shang Wai
R4 Residents in Cottage Area South of Mai Po San Tsuen
R5 Residents
in Mai Po San Tsuen and Mai Po Lo Wai
R6 Residents in Tam Kon Chau
Occupational Visually Sensitive Receivers
O1 Workers in Fishponds in and around Mai Po
O2 Workers in Industrial / Storage Areas north of Royal Palms
O3 Workers in Industrial / Storage Areas east of Royal Palms
Travelling Visually Sensitive Receivers
T1 Motorists on
T2 Motorists on
T3 Motorists on
T4 Pedestrians on San Tin Highway Footbridge
Recreational Visually Sensitive Receivers
RE1 Visitors to Mai Po Nature Reserve
Potential Sources of Landscape and Visual Impact
· Site clearance works;
· Earth moving and regrading;
· Filling of existing marshes and channels;
· Removal of existing grass on Site;
· Removal of existing reeds on Site;
· Removal of existing trees on Site;
· Construction works on residential units, highways and club house;
· Presence of incomplete structures;
· Haulage off-site of excavated materials;
· Storage of existing topsoil for reinstatement works;
· Materials stockpiling;
· Importation and storage of construction equipment and plant;
· Laying down of utilities, including water, drainage and power;
· Construction of temporary parking areas, on site accommodation and working areas;
· Construction of temporary site hoarding (to entire site perimeter) and temporary noise barriers (9 and 10m high) to western and southern boundary of the site; and
· Night lighting.
· Presence of new residential structures in the landscape;
· Night-time domestic and street lighting; and
· Presence of associated features in the landscape (e.g. highways, club house, etc).
Nature and Magnitude of Landscape Impacts Before Mitigation in
Construction Phase
Impacts on Landscape Resources
Landscape Resources
Landscape Character
Nature and Magnitude of Landscape Impacts Before Mitigation in
Operation Phase
Landscape and Visual Mitigation Measures in Construction and
Operation Phases
Review of Comments on Landscape and Visual Issues During Continuous
Public Involvement (CPI)
Alternative Layout Options Considered During the Design Process
·
Reprovision of Landscape Area;
·
Building Height Variation;
·
Building Height;
·
Spacing Between Units;
·
Distance between Buildings and VSRs;
·
Consistency with CPI Comments; and
·
Compliance with OZP Layout Requirements vis-à-vis WRA.
Alternative Layouts
Compatible Development Option
Transitional Wetland Concept Options
Refined Preferred Option
· it scored as many ‘Good’ performances as any other option
· it did not score ‘Poor’ against any criterion and achieved at least a Moderate performance against every criterion. It was therefore preferable in this regard to Option C and E;
· it scored more ‘Good’ performances than Option D and was therefore preferable to Option D in this regard.
Table 11‑2 Assessment of Layout Options against Landscape / Visual Criteria
Landscape / Visual Factor |
Metrics (Good /
Medium / Poor) |
||||
|
Compatible Development Option
(refer to Fig. 2.3b) |
Transitional Wetland Concept
Options (refer to Figs. 2.7 – 2.10) |
|||
|
|
Option
C |
Option
D |
Option
E |
Option
F |
Reprovision of Landscape Area |
M |
M |
M |
P |
G |
Building Height Variation |
P |
G |
M |
P |
M |
Building Height |
G |
M |
M |
G |
M |
Spacing Between Units |
P |
G |
M |
P |
M |
Distance between Buildings and VSRs |
M |
M |
M |
M |
M |
Consistency with CPI Comments |
M |
P |
M |
M |
M |
Compliance with OZP Layout Requirements vis-à-vis
WRA |
G |
G |
G |
G |
G |
Other
Mitigation Measures
Table 11‑3 Proposed Construction Phase Landscape and Visual Mitigation Measures
ID No. |
Landscape and Visual
Mitigation Measure |
Funding Agency |
Implementation Agency |
CM1 |
The construction area and contractor’s
temporary works areas should be
minimised to avoid impacts on adjacent landscape. |
Developer |
Developer (via Contractor) |
CM2 |
Screening of construction works by hoardings/noise
barriers around Works area in visually unobtrusive colours, to screen Works. |
Developer |
Developer (via Contractor) |
CM3 |
Reduction of construction period to practical
minimum. |
Developer |
Developer (via Contractor) |
CM4 |
Topsoil, where identified, should be stripped and
stored for re-use in the construction of the soft landscape works, where the
soil material meets acceptable criteria and where practical. The Contract Specification shall include
storage and reuse of topsoil as appropriate. |
Developer |
Developer (via Contractor) |
CM5 |
Hydroseeding or sheeting of soil stockpiles with
visually unobtrusive material (in earth tone). |
Developer |
Developer (via Contractor) |
CM6 |
Advance screen planting to noise barriers. |
Developer |
Developer (via Contractor) |
CM7 |
Control night-time lighting and glare by hooding all
lights. |
Developer |
Developer (via Contractor) |
CM8 |
Ensure no run-off into streams adjacent to the
Project Area. |
Developer |
Developer (via Contractor) |
CM9 |
Protection of existing trees on boundary of the
Project Area shall be carefully protected during construction. Detailed Tree Protection Specification
shall be provided in the Contract Specification. Under this specification,
the Contractor shall be required to submit, for approval, a detailed working
method statement for the protection of trees prior to undertaking any works
adjacent to all retained trees, including trees in contractor’s works
areas. (Tree protection measures will be
detailed at S16 and Tree Removal Application stage). |
Developer |
Developer (via Contractor) |
CM10 |
Trees unavoidably affected by the works shall be
transplanted where practical. Trees
should be transplanted straight to their destinations and not held in a
nursery. A detailed Tree Transplanting
Specification shall be provided in the Contract Specification, if applicable.
Sufficient time for necessary tree root and crown preparation periods shall
be allowed in the project programme. |
Developer |
Developer (via Contractor) |
Table 11‑4 Proposed Operation Phase Landscape and Visual Mitigation Measures
ID
No. |
Landscape
Mitigation Measure |
Funding
Agency |
Implementation
Agency |
Manage-ment
Agency |
Mainten-ance
Agency |
OM1 |
Compensatory Tree Planting for all felled
trees shall be provided to the satisfaction of relevant Government
departments. Required numbers and
locations of compensatory trees shall be determined and agreed separately
with Government during the Tree Felling Application process under ETWBTC 3/2006. |
Developer |
Developer |
Incorporated Owners |
Management Co. |
OM2 |
A continuous belt of screen planting
along southern perimeter of site with fast growing tree species. At least 450 trees capable of reaching a
height > 10m within 10 years should be planted. Planting of
the belt of trees shall be carried out as advance works ahead of other site
formation and building works. These 450 trees are in addition to the 750
trees proposed under OM3. |
Developer |
Developer |
Incorporated Owners |
Management Co. |
OM3 |
Maximise soft landscape and amenity water
bodies in residential areas of the development. Approximately 750 of trees (of Heavy
Standard size) should be planted.
Where space permits, roadside berms should be created. Street trees should be of species that reach
a mature height of no less than 15m. |
Developer |
Developer |
Incorporated Owners |
Management Co. |
OM4 |
Maximise freshwater habitat wetland
creation consistent with achieving other parameters. Min 4.74 ha to be provided. Wetlands must have natural edge profiles
with >1m wide emergent zone. No
access to the wetland by residents and all wetlands must be screened from
residential development by a continuous tree screen at interface with
residential development or earth mounding such that disturbance is minimised.
Implementation of the wetland shall be carried out as advance works. |
Developer |
Developer |
Wetland Management Trust / Project
Proponent / Incorporated Owners |
Wetland Management Trust / Project
Proponent / Incorporated Owners |
OM5 |
Use appropriate (visually unobtrusive and
non-reflective) building materials and colours in built structures. |
Developer |
Developer |
Private Owners |
Private Owners |
OM6 |
During detailed
design, refine building layout to create a min 10m wide gap between buildings
north of Wo Shang Wai pond and also two min 10m wide gaps in the row of
buildings adjacent to Royal Palms. |
Developer |
Developer |
Incorporated Owners |
Management Co. |
OM7 |
Streetscape elements (e.g. paving,
signage, street furniture, lighting etc.) shall be sensitively designed in a
manner that responds to the local context, and minimises potential negative
landscape and visual impacts. Lighting
units should be directional and minimise unnecessary light spill. |
Developer |
Developer |
Incorporated Owners |
Management Co. |
Indicative Mitigation Planting Species for Different
Areas
Screen/Buffer Planting (Southern Boundary) Trees Acacia auriculiformis Casuarina equisetifolia Eucalyptus citriodora Palms / Bamboos Chrysalidocarpus
lutescens Bambusa textilis Bambusa vulgaris ‘Striata’ Shrubs Schefflera octophylla Ligustrum sinense Ficus microcarpa ‘Golden Leaves’ Murraya paniculata |
Street Trees Aleurites moluccana Bauhinia variegata Bischofia javanica Cassia siamea Grevillea robusta Melaleuca quinquenervia Peltophorum pterocarpum |
Garden and Park Trees Crataeva unilocularis Delonix regia Elaeocarpus hainanensis Michelia alba Melia azedarach Plumeria rubra var. acutifolia Bombax ceiba Magnolia grandiflora Spathodea campanulata Vernicia Montana Shrubs Prunus mume Prunus persica Breynia nivosa Buddleia asiatica Camellia japonica Camellia sasanqua Clerodendrum thomsonae Cuphea hyssopifolia Delphinium ajacis Gardenia jasminoides Hedychium coronarium Hibisus rosa-sinensis Hydrangea macrophylla Hypericum chinense Iris tectorum Ixora stricta Jasminum sambac Lagerstroemia indica Osmanthus fragrans Russelia equisetriformis Rhapis excelsa Rhododendron simsii Rhododendron purpurea Scheffloera aboricola Spathiphyllum sp. Groundcover Asclepias curassavica Hymenocallis Asparagus sprengeri Lantana montevidensis Liriope spicata Nephrolepis exaltata Portulaca oleracea Rhoeo discolor Setcreasea purpurea Syngonium sp. Tracheloepermum
jasminioides Zephyranthus grandiflora |
Riparian Plants (Including Screen Planting Along Residential
Boundaries) Riparian Trees and Shrubs Bambusa tuldoides Cleistocalyx operculatum Diaspyros vaccinoides Eurya chinensis Glyptostrobus pencilis Ficus superba Ficus virens Hibiscus
tiliaceus Litsea
glutinosa Litsea rotundifolia Macaranga atanarius Morus alba Glochidion hirsutum Saurarus chinensis Sapium sebiferum Symplocos laurina Viburnum oderatissimum Melicope pteleifolia Zanthoxylum nitidum Planting Within Wetland
Restoration Area Reedbed species Phragmites spp. (e.g. Phragmites australis) Tree/tall shrub mix Ficus hispida Ficus microcarpus Ficus variegata var. chlorocarpa
Macaranga tanarius Melia azedarach Syzygium jambos Bridelia tomentosa Trema orientalis Viburnum odoratissimum Grass and shrub mix Bridelia tomentosa Gardenia jasminoides Melastoma candidum Rhaphiolepis indica Cynodon dactylon Panicum maximum Paspalum paspaloides Short grass mix Commelina diffusa Cynodon dactylon Eleusine indica Marginal vegetation mix Polygonum barbatum Polygonum glabra Ludwigia octovalvis Ludwigia perennis Cyperus malaccensis Eleocharis spiralis |
Programme of
Implementation of Landscape and Visual Mitigation Measures
Prediction of Significance of Landscape Impacts
Construction Phase
·
Freshwater Marsh (LR30) – During construction, there will be a loss of around 4ha of grassy
marsh and reed marsh (Phragmites sp.). This is a relatively sensitive resource
(medium) in
· Grassland with Seasonal Marsh Patches and Soils on Site (LR32) – During construction approximately 11.7 ha of grassland with seasonal marsh patches and soil will be temporarily removed to allow for earthworks and construction. This kind of grassland is not a very sensitive resource and provided soils are stockpiled for re-use, resulting impacts on the resource will be Slight negative.
·
Tree Group on Site (LR33) - During
construction, around 4 trees will have to be removed from the Site to make way
for site formation. This is a relatively
sensitive resource (medium) in
·
Banana Trees on Site (LR34) - During construction, around 10 banana trees will have to be
removed from the Site to make way for site formation. This is a low sensitivity resource in
·
Trees in Open Storage Area (LR36) - During
construction, around 28 young trees (less than 95mm dbh) and around 21 semi
mature trees will have to be removed from the Site to make way for site
formation. This is a relatively
sensitive resource (medium) in
·
Trees along
·
Tsing Lung Tsuen Plain (LCA2) –
Construction works will introduce a variety of incoherent textures and colours
into the landscape of the Tsing Lung Plain.
An open site that is currently used as part open storage / parking and
part vacant / vegetated will be temporarily replaced by construction machinery,
stockpiles and partially completed structures which will contrast with the
existing character of the wider landscape of the LCA . However, given that the LCA covers many square kilometres, only part of it will be affected and
resulting impacts will be Slight negative.
Operation Phase
· Freshwater Marsh (LR30) – As part of mitigation, wet grassland and reeds removed from site will be compensated for by the creation of a new wetland. This will result in a slight increase in wetland area (around 0.05ha) and therefore in Slight positive landscape impacts.
· Trees on northern Boundary of Royal Palms (LR31) - As part of mitigation, this belt of trees will be augmented by additional planting of approximately 120 trees across the Site as a whole. This will result in a significant net gain of trees (+120) and therefore in Slight positive landscape impacts.
· Tree Group on Site (LR33) – As part of mitigation, trees removed from site will either be transplanted back to site or will be compensated for by additional planting of approximately 150 trees across the Site as a whole. This will result in a significant net gain of trees (+146) and therefore in Slight positive landscape impacts.
· Banana Trees on Site (LR34) - As part of mitigation, trees removed from site will be compensated for by additional planting of approximately 150 trees across the Site as a whole. This will result in a significant net gain of trees (+140) and therefore in Slight positive landscape impacts.
·
Trees in Open Storage Area (LR36) - As part of
mitigation, trees removed from site will be compensated for by additional
planting of approximately 250 trees across the Site as a whole and they may be
transplanted elsewhere on site. This
will result in a significant net gain of trees (+201) and therefore in Slight
positive landscape impacts.
· Trees along Castle Peak Road (Mai Po) (LR39) - As part of mitigation, trees removed from the area at the entrance of the Site will either be compensated for by additional planting of approximately 200 trees across the Site as a whole and may be transplanted elsewhere on site. This will result in a significant net gain of trees (+177) and therefore in Slight positive landscape impacts.
·
Trees in northern
·
Trees in western
·
Trees in northern
Table 11‑5 Significance of Landscape Impacts in Construction and Operation Phases (Negative Impacts unless otherwise stated)
Table 11.5 |
Landscape Resource / Landscape Character |
Sensitivity to Change (Low, Medium, High) |
Magnitude of Impact before Mitigation (Negligible, Small, Intermediate, Large) |
Impact Significance BEFORE Mitigation (Insubstantial, Slight, Moderate,
Substantial) |
Recommended Mitigation Measures |
Residual Impact
Significance AFTER Mitigation (Insubstantial,
Slight, Moderate, Substantial) |
|||||||||
|
|
|
|
|
|
Construction |
Operation |
||||||||
|
|
Construction |
Operation |
Construction |
Operation |
Construction |
Operation |
|
|
DAY 1 |
YEAR 10 |
||||
Part 1 – Physical Landscape Resources
(Topography, Vegetation, Soil, Open Space, Special Features, etc) |
|||||||||||||||
On-Site Landscape Resources |
|||||||||||||||
LR29 |
Drainage
channel at East of Site |
Low |
Low |
Negligible |
Negligible |
Insubstantial |
Insubstantial |
CM8 / OM4 |
Insubstantial |
Insubstantial |
Insubstantial |
||||
LR30 |
Freshwater
Marsh |
Medium |
Medium |
Intermediate |
Intermediate |
Moderate Negative |
Moderate
Negative |
CM4 / OM4 |
Moderate Negative |
Slight Positive |
Slight Positive |
||||
LR32 |
Grassland with Seasonal Marsh Patches and
Soils on Site |
Low |
Low |
Large |
Large |
Moderate
Negative |
Moderate
Negative |
CM4 / OM3 |
Slight Negative |
Insubstantial |
Insubstantial |
||||
LR33 |
Tree Group on
Site |
Medium |
Medium |
Small |
Small |
Slight
Negative |
Slight Negative |
CM10 / OM1 |
Slight Negative |
Slight Positive |
Slight Positive |
||||
LR34 |
Banana trees on
Site |
Low |
Low |
Small |
Small |
Slight
Negative |
Slight
Negative |
CM10 / OM1 |
Slight Negative |
Slight Positive |
Slight Positive |
||||
LR36 |
Trees in Open Storage Area |
Medium |
Medium |
Intermediate |
Intermediate |
Slight Negative |
Slight
Negative |
CM10 / OM1 |
Slight Negative |
Slight Positive |
Slight Positive |
||||
LR39 |
Trees along |
Medium |
Medium |
Small |
Small |
Slight Negative |
Slight Negative |
CM10 / OM1 |
Slight Negative |
Slight Positive |
Slight Positive |
||||
Off-Site Landscape Resources |
|||||||||||||||
LR1 |
Trees Along |
Medium |
Medium |
None |
None |
None |
None |
None |
None |
None |
None |
||||
LR2 |
Roadside Trees
Surrounding Mei Po Substation |
Medium |
Medium |
None |
None |
None |
None |
None |
None |
None |
None |
||||
LR3 |
Trees Opposite Mai Po San Tsuen |
Medium |
Medium |
None |
None |
None |
None |
None |
None |
None |
None |
||||
LR4 |
Field East of |
Low |
Low |
None |
None |
None |
None |
None |
None |
None |
None |
||||
LR5 |
Ponds in Field
East of |
Low |
Low |
None |
None |
None |
None |
None |
None |
None |
None |
||||
LR6 |
Trees Behind
Field east of |
Medium |
Medium |
None |
None |
None |
None |
None |
None |
None |
None |
||||
LR7 |
Stream Next to
Field east of |
Medium |
Medium |
None |
None |
None |
None |
None |
None |
None |
None |
||||
LR8 |
Pond East of |
Low |
Low |
None |
None |
None |
None |
None |
None |
None |
None |
||||
LR9 |
Trees along |
Medium |
Medium |
None |
None |
None |
None |
None |
None |
None |
None |
||||
LR10 |
Drainage
Channel East of |
Low |
Low |
None |
None |
None |
None |
None |
None |
None |
None |
||||
LR11 |
Grassland East
of |
Medium |
Medium |
None |
None |
None |
None |
None |
None |
None |
None |
||||
LR12 |
Trees around
Cottage Area east of |
Medium |
Medium |
None |
None |
None |
None |
None |
None |
None |
None |
||||
LR13 |
Slope adjoining
|
Medium |
Medium |
None |
None |
None |
None |
None |
None |
None |
None |
||||
LR14 |
Trees North of |
Medium |
Medium |
None |
None |
None |
None |
None |
None |
None |
None |
||||
LR15 |
Trees inside |
Medium |
Medium |
None |
None |
None |
None |
None |
None |
None |
None |
||||
LR16 |
Fruit Trees
North of Ki Lung Shan Foothills I |
Medium |
Medium |
None |
None |
None |
None |
None |
None |
None |
None |
||||
LR17 |
|
Medium |
Medium |
None |
None |
None |
None |
None |
None |
None |
None |
||||
LR18 |
Trees on Ki
Lung Shan Foothills II |
Medium |
Medium |
None |
None |
None |
None |
None |
None |
None |
None |
||||
LR19 |
Trees on Ki
Lung Shan Foothills I |
Medium |
Medium |
None |
None |
None |
None |
None |
None |
None |
None |
||||
LR20 |
Trees in |
Medium |
Medium |
None |
None |
None |
None |
None |
None |
None |
None |
||||
LR21 |
Grassland on Ki
Lung Shan Foothills |
Low |
Low |
None |
None |
None |
None |
None |
None |
None |
None |
||||
LR22 |
Trees between |
Medium |
Medium |
None |
None |
None |
None |
None |
None |
None |
None |
||||
LR23 |
Chunk Kai
Horticultural Nursery |
Low |
Low |
None |
None |
None |
None |
None |
None |
None |
None |
||||
LR24 |
Trees along |
Medium |
Medium |
None |
None |
None |
None |
None |
None |
None |
None |
||||
LR25 |
Pond east of
Royal Palms |
Low |
Low |
None |
None |
None |
None |
None |
None |
None |
None |
||||
LR26 |
Field east of
Royal Palms |
Medium |
Medium |
None |
None |
None |
None |
None |
None |
None |
None |
||||
LR27 |
Trees east of
Royal Palms |
Medium |
Medium |
None |
None |
None |
None |
None |
None |
None |
None |
||||
LR28 |
Trees outside
Royal Palms near |
Medium |
Medium |
None |
None |
None |
None |
None |
None |
None |
None |
||||
LR31 |
Trees on
northern Boundary of Royal Palms |
Medium |
Medium |
Small |
Small |
Slight |
Slight |
CM9/ OM2 |
Insubstantial |
Slight Positive |
Slight Positive |
||||
LR35 |
Stream flowing
from Tam Kon Chau to the site |
Medium |
Medium |
Small |
Small |
Slight
Negative |
Slight Negative |
CM8/OM4 |
Insubstantial |
Insubstantial |
Insubstantial |
||||
LR37 |
NOT USED |
|
|
|
|
|
|
|
|
|
|
||||
LR38 |
Trees inside
Open Storage Area |
Medium |
Medium |
None |
None |
None |
None |
None |
None |
None |
None |
||||
LR40 |
Trees in
Cottage Area east of |
Medium |
Medium |
None |
None |
None |
None |
None |
None |
None |
None |
||||
LR41 |
Pond behind Mai
Po San Tsuen |
Low |
Low |
None |
None |
None |
None |
None |
None |
None |
None |
||||
LR42 |
Grassland
besides DSD building |
Low |
Low |
None |
None |
None |
None |
None |
None |
None |
None |
||||
LR43 |
Trees in Mai Po San Tsuen |
Medium |
Medium |
None |
None |
None |
None |
None |
None |
None |
None |
||||
LR44 |
Trees behind
Mai Po San Tsuen |
Medium |
Medium |
None |
None |
None |
None |
None |
None |
None |
None |
||||
LR45 |
Trees in Mai Po Lo Wai |
Medium |
Medium |
None |
None |
None |
None |
None |
None |
None |
None |
||||
LR46 |
Field west of
Mai Po Lo Wai |
Low |
Low |
None |
None |
None |
None |
None |
None |
None |
None |
||||
LR47 |
Pond west of
Mai Po San Tsuen |
Low |
Low |
None |
None |
None |
None |
None |
None |
None |
None |
||||
LR48 |
Channel west of
Mai Po San Tsuen |
Low |
Low |
None |
None |
None |
None |
None |
None |
None |
None |
||||
LR49 |
Channel beside
DSD building |
Low |
Low |
None |
None |
None |
None |
None |
None |
None |
None |
||||
LR50 |
|
Medium |
Medium |
None |
None |
None |
None |
None |
None |
None |
None |
||||
LR51 |
Fishponds along
|
Low |
Low |
None |
None |
None |
None |
None |
None |
None |
None |
||||
LR52 |
Trees north of |
Medium |
Medium |
None |
None |
None |
None |
None |
None |
None |
None |
||||
LR53 |
Dry Pond north
of |
Low |
Low |
None |
None |
None |
None |
None |
None |
None |
None |
||||
LR54 |
Fishponds south
of |
Low |
Low |
None |
None |
None |
None |
None |
None |
None |
None |
||||
LR55 |
Trees beside
Fishponds south of |
Medium |
Medium |
None |
None |
None |
None |
None |
None |
None |
None |
||||
LR56 |
Fishponds
north-east of Site |
Low |
Low |
None |
None |
None |
None |
None |
None |
None |
None |
||||
LR57 |
Trees beside
fishponds north-east of Site |
Medium |
Medium |
None |
None |
None |
None |
None |
None |
None |
None |
||||
LR58 |
Stream north of
|
Medium |
Medium |
None |
None |
None |
None |
None |
None |
None |
None |
||||
LR59 |
Trees beside
Stream north of |
Medium |
Medium |
None |
None |
None |
None |
None |
None |
None |
None |
||||
LR60 |
Fishponds north
of |
Low |
Low |
None |
None |
None |
None |
None |
None |
None |
None |
||||
LR61 |
Trees beside
Fishponds north of |
Medium |
Medium |
None |
None |
None |
None |
None |
None |
None |
None |
||||
LR62 |
Fishponds
north-west of Site |
Low |
Low |
None |
None |
None |
None |
None |
None |
None |
None |
||||
LR63 |
Trees beside
Fishponds north-west of Site |
Medium |
Medium |
None |
None |
None |
None |
None |
None |
None |
None |
||||
LR64 |
Fishponds north
of Tam Kon Chau |
Low |
Low |
None |
None |
None |
None |
None |
None |
None |
None |
||||
LR65 |
Trees beside
Fishponds north of Tam Kon Chau |
Medium |
Medium |
None |
None |
None |
None |
None |
None |
None |
None |
||||
LR66 |
Trees in Tam
Kon Chau |
Medium |
Medium |
None |
None |
None |
None |
None |
None |
None |
None |
||||
LR67 |
Pond south of
Tam Kon Chau |
Low |
Low |
None |
None |
None |
None |
None |
None |
None |
None |
||||
LR68 |
Fishponds south
of Tam Kon Chau |
Low |
Low |
None |
None |
None |
None |
None |
None |
None |
None |
||||
LR69 |
Fishponds
south-west of Tam Kon Chau |
Low |
Low |
None |
None |
None |
None |
None |
None |
None |
None |
||||
LR70 |
Fish Pond west
of |
Low |
Low |
None |
None |
None |
None |
None |
None |
None |
None |
||||
LR71 |
Trees beside
Fish Pond west of |
Medium |
Medium |
None |
None |
None |
None |
None |
None |
None |
None |
||||
LR72 |
Fishponds
north-west of |
Low |
Low |
None |
None |
None |
None |
None |
None |
None |
None |
||||
LR73 |
Fishponds west
of |
Low |
Low |
None |
None |
None |
None |
None |
None |
None |
None |
||||
LR74 |
Trees beside
Fishponds west of |
Medium |
Medium |
None |
None |
None |
None |
None |
None |
None |
None |
||||
LR75 |
Fishponds west
of |
Low |
Low |
None |
None |
None |
None |
None |
None |
None |
None |
||||
LR76 |
Fish Pond west
of |
Low |
Low |
None |
None |
None |
None |
None |
None |
None |
None |
||||
LR77 |
Fishponds west
of |
Low |
Low |
None |
None |
None |
None |
None |
None |
None |
None |
||||
LR78 |
Trees beside
Fishponds west of |
Medium |
Medium |
None |
None |
None |
None |
None |
None |
None |
None |
||||
LR79 |
Fishponds west
of |
Low |
Low |
None |
None |
None |
None |
None |
None |
None |
None |
||||
LR80 |
Trees beside
Fishponds west of |
Medium |
Medium |
None |
None |
None |
None |
None |
None |
None |
None |
||||
LR81 |
Fishponds west
of |
Low |
Low |
None |
None |
None |
None |
None |
None |
None |
None |
||||
LR82 |
Trees beside
Fishponds west of |
Medium |
Medium |
None |
None |
None |
None |
None |
None |
None |
None |
||||
LR83 |
Stream west of |
Medium |
Medium |
None |
None |
None |
None |
None |
None |
None |
None |
||||
LR84 |
Fishponds west
of |
Low |
Low |
None |
None |
None |
None |
None |
None |
None |
None |
||||
LR85 |
Trees beside
Fishponds west of |
Medium |
Medium |
None |
None |
None |
None |
None |
None |
None |
None |
||||
LR86 |
Trees in
northern |
Medium |
Medium |
Small |
Small |
Slight |
Slight |
CM9 / OM2 |
Insubstantial |
Slight Positive |
Slight Positive |
||||
LR87 |
Trees in
western |
Medium |
Medium |
Small |
Small |
Slight |
Slight |
CM9 / OM2 |
Insubstantial |
Slight Positive |
Slight Positive |
||||
LR88 |
Trees in
southern |
Medium |
Medium |
None |
None |
None |
None |
None |
None |
None |
None |
||||
LR89 |
Trees in Car
Park in |
Medium |
Medium |
None |
None |
None |
None |
None |
None |
None |
None |
||||
LR90 |
Pond in Wo |
Low |
Low |
None |
None |
None |
None |
None |
None |
None |
None |
||||
LR91 |
Trees in
northern |
Medium |
Medium |
Small |
Small |
Slight |
Slight |
CM9 / OM2 |
Insubstantial |
Slight Positive |
Slight Positive |
||||
LR92 |
Trees at
Shopping Mall in |
Medium |
Medium |
None |
None |
None |
None |
None |
None |
None |
None |
||||
LR93 |
Ponds in |
Medium |
Medium |
None |
None |
None |
None |
None |
None |
None |
None |
||||
LR94 |
Trees beside
Ponds in |
Medium |
Medium |
None |
None |
None |
None |
None |
None |
None |
None |
||||
LR95 |
Trees in
southern Royal Palms |
Medium |
Medium |
None |
None |
None |
None |
None |
None |
None |
None |
||||
LR96 |
Trees around
Sports Facilities in Royal Palms |
Medium |
Medium |
None |
None |
None |
None |
None |
None |
None |
None |
||||
LR97 |
Trees east of
Royal Palms |
Medium |
Medium |
None |
None |
None |
None |
None |
None |
None |
None |
||||
LR98 |
Pond south of
Palm Springs Boulevard Entrance |
Low |
Low |
None |
None |
None |
None |
None |
None |
None |
None |
||||
LR99 |
Ponds south of |
Low |
Low |
None |
None |
None |
None |
None |
None |
None |
None |
||||
LR100 |
Trees
surrounding Ponds south of |
Medium |
Medium |
None |
None |
None |
None |
None |
None |
None |
None |
||||
Part 2 – Landscape Character
Areas |
|||||||||||||||
LCA1 |
|
Low |
Low |
Negligible |
Negligible |
Insubstantial |
Insubstantial |
None |
Insubstantial |
Insubstantial |
Insubstantial |
||||
LCA2 |
Tsing Lung
Tsuen Plain |
Medium |
Medium |
Small Negative |
Small Negative |
Moderate Negative |
Moderate Negative |
CM1 / CM3 / CM5-7 OM3-8 |
Slight Negative |
Slight Negative |
Insubstantial |
||||
LCA3 |
San Tin Plain |
High |
High |
Negligible |
Negligible |
Insubstantial |
Insubstantial |
None |
Insubstantial |
Insubstantial |
Insubstantial |
||||
LCA4 |
Ki Lung Shan
Uplands |
High |
High |
Negligible |
Negligible |
Insubstantial |
Insubstantial |
None |
Insubstantial |
Insubstantial |
Insubstantial |
||||
Landscape and Visual Mitigation Measures
Prediction of Significance of Visual Impacts
Construction Phase
·
Residents in Royal Palms,
Palm Springs and Wo Shang Wai (R1, R2 and R3) –
Residents in Palm Springs (approx 17 properties at the northern end of Camelia
Path and approx 32 properties on Narcissus Path) and Royal Palms (approx 21
properties on Ventura Avenue and approx 8 properties on Santa Monica Avenue)
will potentially experience views from short distances of site formation works,
noise barrier, construction machinery and partially completed 2.5/3-storey
structures. Other residents on the
northern sides of these developments may experience more distant, oblique views
of work on 2.5/3 and 4-storey structures.
Other affected residents will include users of peripheral roads in Royal
Palms and
Residents on the northern side of Wo Shang Wai will experience what are in some cases, uninterrupted views of site formation works, noise barrier, construction machinery and partially completed 2.5/3 and 4-storey structures. The upper portion of the noise barriers will be transparent while the remaining part will be of unobtrusive colours with design graphics. The views of these VSRs will be only partly screened by the existing belt of tall trees and some views are unscreened. Key issues determining the magnitude of change to these VSRs will be the relative proximity of some of these VSRs, the broken or interrupted nature of the views of many VSRs and changes to the character of existing views comprising a wide variety of rural fringe features. Rural fringe features include an agglomeration of visually unrelated structures and landscape elements such as village houses, residential development, utilities, tree clumps etc. This will constitute a small magnitude of impact to the existing views by introducing artificial construction features into them. Resulting impacts on this VSR group will be Moderate negative, during the construction period. Residents, who do not live on the northern edge of the village, will experience little or no impact on their views, due to the effects of intervening buildings.
· Residents in Mai Po San Tsuen and Mai Po Lo Wai (R5) – Residents in properties on the western edges of these villages which face directly towards the site, will experience distant views of site formation works, site hoardings, noise barrier, construction machinery and partially completed 2.5/3 and 4-storey structures across low-lying open land with a backdrop of trees. Key issues determining the magnitude of impact to these VSRs will be their moderate distance from the source of impacts, the panoramic quality of many views (a broad, expansive view within which several, distant features are observed and where the Project Area is only one element) and changes to the rural fringe character of existing views. Rural fringe features include an agglomeration of visually unrelated structures and landscape elements such as village houses, residential development, utilities, tree clumps etc. Although lower parts of the works will be hidden behind approx 4m high screen hoardings, this will nonetheless constitute a small magnitude of impact to the existing views, by introducing artificial and incoherent features into them. Resulting impacts on this small VSR group will be Slight negative.
·
Residents in Tam Kon Chau
(R6) – Residents in properties on the southern and
eastern side of Tam Kon Chau which face directly towards the site, will
experience distant views across fishponds of site formation works, site
hoardings, noise barrier, construction machinery and partially completed 2.5/3
and 4-storey structures. Key issues
determining the magnitude of impact to these VSRs will be their moderate
distance from the source of impacts, the panoramic quality of many views (a
broad, expansive view within which several, distant features are observed and
where the Project Area is only one element) and changes to the rural fringe
character of existing views. Rural fringe features include an agglomeration of
visually unrelated structures and landscape elements such as village houses,
residential development, utilities, tree clumps etc. Lower parts of the works
will be in part hidden behind approx 4m high screen hoardings, but this will
nonetheless constitute a small magnitude of impact to the existing views, by
introducing construction machinery and incoherent construction-related features
into the middle distance of them. The existing developments of
· Pedestrians on San Tin Highway Footbridge (T4) – Pedestrians crossing the footbridge across the San Tin Highway, south east of the Site will experience elevated broken and distant views across industrial / storage areas of site hoardings, noise barrier, construction machinery and traffic as well as partially completed 4-storey structures. Key issues determining the magnitude of impact to these VSRs will be their moderate distance from the source of impacts and limited changes to the indifferent character of existing views. This will constitute a small magnitude of impact to the existing views, by introducing brightly coloured construction machinery, and artificial features into the middle distance of views that are already fairly incoherent due to the presence of industrial and storage features. Resulting impacts on this very small VSR group will be Slight negative.
·
Workers in Fishponds in and
Around Mai Po (O1) – Those working at fishponds
north and north-west of the Site will experience views across fishponds of site
formation works, site hoardings, construction machinery and partially completed
structures. Key issues determining the
magnitude of impact to these VSRs will be their relative proximity to the
source of impacts, the panoramic quality of many views (a broad, expansive view within which
several, distant features are observed and where the Project Area is only one
element) and changes to the rural fringe character of existing views. Rural
fringe features include an agglomeration of visually unrelated structures and
landscape elements such as village houses, residential development, utilities,
tree clumps etc. Although lower parts of
the works will be hidden behind approx 4m high screen hoardings, this will
nonetheless constitute an intermediate magnitude of impact to the existing
views, by introducing construction machinery and incoherent
construction-related features into the middle distance of them. The existing developments of
· Workers in Industrial / Storage Areas north of Royal Palms (O2) – Those working in industrial / storage areas north-east of the Site (especially those in elevated machinery), may experience broken, close views across intervening fencing of site hoardings, construction machinery and partially completed structures. Additionally, the jumbled mass of incoherent elements (machinery, containers and equipment) within and surrounding these workers results in views of the site being significant interrupted. Key issues determining the magnitude of impact to these VSRs will be their relative proximity to the source of impacts and limited changes to the indifferent character of existing views. This will constitute a small magnitude of impact to the existing views, by introducing brightly coloured construction machinery and incoherent construction-related features into the foreground of them. Impacts will be partly offset by the fairly incoherent visual quality of existing views and resulting impacts on this very small VSR group will be Slight negative.
· Workers in Industrial / Storage Areas east of Royal Palms (O3) – Those working in industrial / storage areas east of the Site (especially those in elevated machinery), may experience close views across intervening fencing of construction traffic and partially complete structures close to the entrance of the site. Key issues determining the magnitude of impact to these VSRs will be their relative proximity to the source of impacts, limited changes to the indifferent character of existing views and the fact that many views are broken by storage yard features. This will constitute a small magnitude of impact to the existing views, by introducing brightly coloured construction machinery and incoherent construction-related features into the foreground of them. Impacts will be partly offset by the fairly incoherent visual quality of existing views and resulting impacts on this very small VSR group will be Slight negative.
·
Visitors to Mai Po Nature
Reserve (RE1) – Visitors to the eastern edge of the
WWF Mai Po Nature Reserve to the
· Motorists on Tam Kon Chau Road (T3) – Motorists on Tam Kon Chau Road will experience visual impacts of an intermediate magnitude due to their moderate distance from the source of impacts, the panoramic quality of views (a broad, expansive view within which several, distant features are observed and where the Project Area is only one element); and the fact that for the most part, motorists are travelling perpendicular to or away from the Site (rather than towards it). These factors, combined with the limited numbers of people using the road, the relatively low sensitivity of travelling VSRs generally, and the transient nature of views will mean that visual impacts on this VSR group will be slight.
· Residents in Cottage Area South of Mai Po San Tsuen (R4) – These residents will not experience visual impacts of significant magnitude due to the fact that their views are largely or entirely broken by intervening storage yard features, parked lorries or other structures such that views of the Project Area are not readily available. Even where glimpsed views might be possible, the visual character of the foreground is already so degraded by the features mentioned, that the relative effects of new features in these views would not be significant. This will mean that visual impacts on this VSR group will be Insubstantial.
· Motorists on San Tin Highway (T1) – Motorists on San Tin Highway will not experience visual impacts of significant magnitude due to their moderate distance from the source of impacts, the panoramic quality of views (a broad, expansive view within which several, distant features are observed and where the Project Area is only one element); and the fact that for the most part, motorists are travelling perpendicular to the Project Area entry. These factors, combined with the limited numbers of people using the road, the relatively low sensitivity of travelling VSRs generally, and the transient nature of views will mean that visual impacts on this VSR group will be Insubstantial.
· Motorists on Castle Peak Road (T2) – Motorists on Castle Peak Road will not experience visual impacts of significant magnitude due to their moderate distance from the source of impacts, the panoramic quality of views (a broad, expansive view within which several, distant features are observed and where the Project Area is only one element); and the fact that for the most part, motorists are travelling perpendicular to the Project Area entry. These factors, combined with the limited numbers of people using the road, the relatively low sensitivity of travelling VSRs generally, and the transient nature of views will mean that visual impacts on this VSR group will be Insubstantial.
Operation Phase
·
Residents in Royal Palms,
Palm Springs (R1 and R2) - Residents in Palm
Springs (approx 17 properties in Camelia Path and approx 32 properties on
Narcissus Path) and Royal Palms (approx 21 properties on Ventura Avenue and
approx 8 properties on Santa Monica Avenue) will potentially experience views
of completed 2.5/3 storey dwellings.
Other residents on the northern sides of these developments may
experience more distant, oblique views.
Residents using peripheral roads in Royal Palms and
·
Residents in Wo Shang Wai
(R3) - New 2.5/3 and 4-storey buildings will be
clearly visible in the middle distance
to a small number of Residents in Wo Shang Wai (R3) living on the
northern sides of the village, across the fishpond. Key issues determining the magnitude of
impact to these VSRs will be the relative proximity of some of the VSRs, the
broken or interrupted nature of the views of many VSRs, the screening effect of
proposed trees and changes to the character of existing views comprising a wide
variety of rural fringe features. Rural fringe features include an agglomeration
of visually unrelated structures and landscape elements such as village houses,
residential development, utilities, tree clumps etc. Views of new 2.5/3 and 4-storey
buildings will appear in views northward and will represent a further developed
feature in these views (which already feature views of houses in
·
Residents in Tam Kon Chau
(R6) - Residents in properties on the southern and
eastern side of Tam Kon Chau (R6) which face directly towards the site, will
experience distant views across fishponds of the new development with 2.5/3
storey buildings at the front and 4-storey buildings to the rear. Key issues determining the magnitude of
impact to these VSRs will be their moderate distance from the source of
impacts, the panoramic quality of many views (a broad, expansive view within
which several, distant features are observed and where the Project Area is only
one element) and changes to the rural fringe character of existing views. Rural
fringe features include an agglomeration of visually unrelated structures and
landscape elements such as village houses, residential development, utilities,
tree clumps etc. This will constitute a small magnitude of impact to the
existing views, by introducing new development features into the middle
distance of them, although the existing developments of
·
Pedestrians on San Tin
Highway Footbridge (T4) – Pedestrians crossing the
footbridge across the
·
Residents in Mai Po San
Tsuen and Mai Po Lo Wai (R5) – Residents in
properties on the northern and western edges of thee villages which face
directly towards the site, will experience views of completed 2.5/3 and
4-storey structures against a backdrop of trees. Key issues determining the magnitude of impact
to these VSRs will be their moderate distance from the source of impacts, the
panoramic quality of many views (a broad, expansive view within which several,
distant features are observed and where the Project Area is only one element)
and changes to the rural fringe character of existing views. Rural fringe
features include an agglomeration of visually unrelated structures and
landscape elements such as village houses, residential development, utilities,
tree clumps etc. This will introduce new development features into the distance
of views. At night, residential lighting
and street lighting may also be partly visible, but will not significantly
change views which are already characterised by residential lighting at
·
Workers in Fishponds in and
Around Mai Po (O1) – Those working at fishponds
north and north-west of the Site, will experience views across fishponds of the
new development with 2.5/3 storey buildings at the front and 4-storey buildings
to the rear. Key issues determining the
magnitude of impact to these VSRs will be their relative proximity to the
source of impacts, the panoramic quality of many views (a broad, expansive view
within which several, distant features are observed and where the Project Area
is only one element) and changes to the rural fringe character of existing
views. Rural fringe features include an agglomeration of visually unrelated
structures and landscape elements such as village houses, residential
development, utilities, tree clumps etc. This will constitute an intermediate
magnitude of impact to the existing views, by introducing new development
features into them although the existing developments of
· Workers in Industrial / Storage Areas north of Royal Palms (O2) – Those working in industrial / storage areas north-east of the Site (especially those in elevated machinery), may experience broken, close views across intervening fencing of construction machinery and of the completed development. Additionally, the jumbled mass of incoherent elements (machinery, containers and equipment) within and surrounding these workers results in views of the site being significant interrupted. Key issues determining the magnitude of impact to these VSRs will be their relative proximity to the source of impacts and limited changes to the indifferent character of existing views. This will constitute a small magnitude of impact to the existing views, by introducing new development features (2.5 / 3 and 4 storey buildings) into them. At night, residential lighting and street lighting may also be partly visible, but will not significantly change views of the general surroundings which are already characterised by residential and road lighting. Given the fairly incoherent visual quality of existing views, resulting impacts on this very small VSR group will be Slight negative (particularly on those working closer to the development) but will tend to diminish over time as planting in and around the development matures.
· Workers in Industrial / Storage Areas east of Royal Palms (O3) – Those working in industrial / storage areas east of the Site (especially those in elevated machinery), may experience close views across intervening fencing and storage areas of completed Project buildings. Key issues determining the magnitude of impact to these VSRs will be their relative proximity to the source of impacts, limited changes to the indifferent character of existing views and the fact that many views are broken by storage yard features. This will constitute a small magnitude of impact to the existing views, by introducing new development features (2.5 / 3 and 4 storey buildings) into them. At night, residential lighting and street lighting may also be partly visible, but will not significantly change views of the general surroundings which are already characterised by residential and road lighting. Given the fairly incoherent visual quality of existing views, resulting impacts on this very small VSR group will be Slight negative (particularly on those working closer to the development) but will tend to diminish over time as planting in and around the development matures.
·
Visitors to Mai Po Nature Reserve
(RE1) – Visitors to the eastern edge of the WWF Mai
Po Nature Reserve to the
· Motorists on Tam Kon Chau Road (T3) – Motorists on Tam Kon Chau Road will experience visual impacts of an intermediate magnitude due to their moderate distance from the source of impacts, the panoramic quality of views (a broad, expansive view within which several, distant features are observed and where the Project Area is only one element); and the fact that for the most part, motorists are travelling perpendicular to or away from the Site (rather than towards it). The Project will appear largely as an extension of existing housing at Royal Palms and Palms Springs and will therefore not appear out of place or incongruous in these views of the landscape. Mitigation planting will also help in blending buildings into the landscape. These factors, combined with the limited numbers of people using the road, the relatively low sensitivity of travelling VSRs generally, and the transient nature of views will mean that visual impacts on this VSR group will be slight.
· Residents in Cottage Area South of Mai Po San Tsuen (R4) – These residents will not experience visual impacts of significant magnitude due to the fact that their views are largely or entirely broken by intervening storage yard features, parked lorries or other structures such that views of the Project Area are not readily available. Even where glimpsed views might be possible, the visual character of the foreground is already so degraded by the features mentioned, that the relative effects of new features in these views would not be significant. This will mean that visual impacts on this VSR group will be Insubstantial.
· Motorists on San Tin Highway (T1) – Motorists on San Tin Highway will not experience visual impacts of significant magnitude due to their moderate distance from the source of impacts, the panoramic quality of views (a broad, expansive view within which several, distant features are observed and where the Project Area is only one element); and the fact that for the most part, motorists are travelling perpendicular to the Project Area entry. These factors, combined with the limited numbers of people using the road, the relatively low sensitivity of travelling VSRs generally, and the transient nature of views will mean that visual impacts on this VSR group will be Insubstantial.
· Motorists on Castle Peak Road (T2) – Motorists on Castle Peak Road will not experience visual impacts of significant magnitude due to their moderate distance from the source of impacts, the panoramic quality of views (a broad, expansive view within which several, distant features are observed and where the Project Area is only one element); and the fact that for the most part, motorists are travelling perpendicular to the Project Area entry. These factors, combined with the limited numbers of people using the road, the relatively low sensitivity of travelling VSRs generally, and the transient nature of views will mean that visual impacts on this VSR group will be Insubstantial.
·
Residents in Royal Palms,
Palm Springs (R1 and R2) – Residents in Palm
Springs (approx 17 properties at the northern end of Camelia Path and approx 32
properties on Narcissus Path) and Royal Palms (approx 21 properties on Ventura
Avenue and approx 8 properties on Santa Monica Avenue) will potentially
experience views of new 2.5/3 storey dwellings.
Other residents on the northern sides of these developments may
experience more distant, oblique views.
Residents using peripheral roads in Royal Palms and
·
Residents in Wo Shang Wai
(R3) – The effect of circa 10m high mitigation
screen planting will mean that to the small number of Residents in Wo Shang
Wai (R3) living on the northern sides of the village, views of new
buildings will be entirely, or almost entirely obscured. Key issues determining the magnitude of impact
to these VSRs will be the relative proximity of some of the VSRs, the broken or
interrupted nature of the views of many VSRs, the screening effect of proposed
trees and changes to the character of existing views comprising a wide variety
of rural fringe features. Rural fringe features include an agglomeration of
visually unrelated structures and landscape elements such as village houses,
residential development, utilities, tree clumps etc. In particular, the row of
mitigation planting will have matured by Year 10 and will at this time have a
fairly dramatic mitigation effect (as opposed to Day 1 when its effect will be
more limited), appearing in views northwards and will represent a further
natural feature in these views. At
night, residential lighting and street lighting is unlikely to be very visible
through belts of trees. In any case,
this will not represent a significant change to the night-time character of the
wider landscape which is already characterised by night-time lights from
existing houses in
· Residents in Cottage Area South of Mai Po San Tsuen (R4) – These residents will not experience visual impacts of significant magnitude due to the fact that their views are largely or entirely broken by intervening storage yard features, parked lorries or other structures such that views of the Project Area are not readily available. Even where glimpsed views might be possible, the visual character of the foreground is already so degraded by the features mentioned, that the relative effects of new features in these views would not be significant. This will mean that visual impacts on this VSR group will be Insubstantial.
·
Residents in Mai Po San
Tsuen and Mai Po Lo Wai (R5) - where the Project is
visible, it will appear largely as an extension of existing housing at Royal
Palms and Palms Springs and will not appear out of place or incongruous in
these views of the landscape. Key issues
determining the magnitude of impact to these VSRs will be their moderate
distance from the source of impacts, the panoramic quality of many views, the screening
effects of mitigation planting and changes to the rural fringe character of
existing views. Rural fringe features include an agglomeration of visually
unrelated structures and landscape elements such as village houses, residential
development, utilities, tree clumps etc. The maturing of mitigation planting at
the edges of the Site can be expected to have a significant effect on reducing
visual impacts at Year 10. At night,
residential lighting and street lighting is unlikely to be very visible. In any
case, this will not represent a significant change to the night-time character
of the wider landscape, which is already characterised by night-time lights
from various sources (highways, residential, etc). For this reason, residual visual impacts will
be Insubstantial in all cases (see Figure 11.38).
· Motorists on San Tin Highway (T1) – Motorists on San Tin Highway will not experience visual impacts of significant magnitude due to their moderate distance from the source of impacts, the panoramic quality of views (a broad, expansive view within which several, distant features are observed and where the Project Area is only one element); and the fact that for the most part, motorists are travelling perpendicular to the Project Area entry. These factors, combined with the limited numbers of people using the road, the relatively low sensitivity of travelling VSRs generally, and the transient nature of views will mean that visual impacts on this VSR group will be Insubstantial.
· Motorists on Castle Peak Road (T2) – Motorists on Castle Peak Road will not experience visual impacts of significant magnitude due to their moderate distance from the source of impacts, the panoramic quality of views (a broad, expansive view within which several, distant features are observed and where the Project Area is only one element); and the fact that for the most part, motorists are travelling perpendicular to the Project Area entry. These factors, combined with the limited numbers of people using the road, the relatively low sensitivity of travelling VSRs generally, and the transient nature of views will mean that visual impacts on this VSR group will be Insubstantial.
· Motorists on Tam Kon Chau Road (T3) – Motorists on Tam Kon Chau Road will not experience visual impacts of significant magnitude due to their moderate distance from the source of impacts, the panoramic quality of views (a broad, expansive view within which several, distant features are observed and where the Project Area is only one element); and the fact that for the most part, motorists are travelling perpendicular to or away from the Site (rather than towards it). The Project will appear largely as an extension of existing housing at Royal Palms and Palms Springs and will therefore not appear out of place or incongruous in these views of the landscape. Mitigation planting will also help in blending buildings into the landscape. These factors, combined with the limited numbers of people using the road, the relatively low sensitivity of travelling VSRs generally, and the transient nature of views will mean that visual impacts on this VSR group will be Insubstantial.
·
Visitors to Mai Po Nature
Reserve (RE1) – Visitors to the eastern edge of the
WWF Mai Po Nature Reserve to the
Table 11‑6 Significance of Visual Impacts in the
Construction and Operation Phases (Note: All impacts negative unless otherwise
noted)
|
Table 11.6 |
Key
Visually Sensitive Receiver (VSR) |
Degree of
Visibility of Source(s) of Visual Impact
(Full,
Partial, Glimpse) & Min Distance Between VSR & Nearest
Source(s) of Impact |
Magnitude
of Impact before Mitigation (Negligible, Small, Intermediate,
Large) |
Receptor
Sensitivity & Number
(Low, Medium, High) (Very Few, Few, Many, Very Many) |
Impact
Significance BEFORE Mitigation (Insubstantial, Slight, Moderate,
Substantial) |
Recommended
Mitigation Measures |
Residual
Impact Significance AFTER Mitigation (Insubstantial, Slight, Moderate,
Substantial) |
||||||
|
VSR Type |
Construction |
Operation |
|||||||||||
|
& ID. |
|
Construction |
Operation |
Construction |
Operation |
Construction |
Operation |
Construction |
Operation |
|
|
DAY 1 |
YEAR 10 |
|
R1 |
Residents in
Royal Palms |
Partial 20m |
Partial 20m |
Intermediate Negative |
Intermediate
Negative |
High Few |
High Few |
Moderate Negative |
Moderate Negative |
CM1-3 / CM5&7 / CM9 / OM1–7 |
Moderate Negative |
Moderate Negative |
Slight Negative |
|
R2 |
Residents in
|
Partial 10m |
Partial 10m |
Intermediate Negative |
Intermediate Negative |
High Few |
High Few |
Moderate Negative |
Moderate Negative |
CM1-3 / CM5&7 / CM9 /
OM1–7 |
Moderate Negative |
Moderate Negative |
Slight Negative |
|
R3 |
Residents in
Wo Shang Wai |
Partial 80m |
Partial 80m |
Small Negative |
Small Negative |
High Very Few |
High Very Few |
Moderate Negative |
Moderate Negative |
CM1-3 / CM5&7 / CM9 /
OM1–7 |
Moderate Negative |
Moderate Negative |
Insubstantial |
|
R4 |
Residents in
Cottage Area South of Mai Po San Tsuen |
Partial 100m |
Partial 100m |
Negligible |
Negligible |
High Very Few |
High Very Few |
Insubstantial |
Insubstantial |
CM1-3
/ CM5&7 / CM9 OM1 / OM3-7 |
Insubstantial |
Insubstantial |
Insubstantial |
|
R5 |
Residents in Mai Po San Tsuen and Mai Po Lo Wai |
Partial 300m |
Partial 300m |
Small Negative |
Small Negative |
High Few |
High Few |
Moderate Negative |
Moderate Negative |
CM1-3
/ CM5&7 / CM9 / OM1 / OM3-7 |
Slight Negative |
Slight
Negative |
Insubstantial |
|
R6 |
Residents in
Tam Kon Chau |
Full 400m |
Full 400m |
Small Negative |
Small Negative |
High Very Few |
High Very Few |
Moderate Negative |
Moderate Negative |
CM1-3
/ CM5&7 / CM9 / OM1 / OM3-7 |
Slight Negative |
Slight
Negative |
Insubstantial |
|
T1 |
Motorists on |
Glimpse 20m |
Glimpse 20m |
Negligible |
Negligible |
Low Very Many |
Low Very Many |
Insubstantial |
Insubstantial |
CM1-3
/ CM5&7 / CM9 / OM1 / OM3-7 |
Insubstantial |
Insubstantial |
Insubstantial |
|
T2 |
Motorists on |
Glimpse 5m |
Glimpse 5m |
Negligible |
Negligible |
Low Many |
Low Many |
Insubstantial |
Insubstantial |
CM1-3 /
CM5&7 / CM9 / OM1 / OM3-7 |
Insubstantial |
Insubstantial |
Insubstantial |
|
T3 |
Motorists on
|
Glimpse 400m |
Glimpse 400m |
Intermediate |
Intermediate |
Low Very Few |
Low Very Few |
Slight |
Slight |
CM1-3
/ CM5&7 / CM9 / OM1 / OM3-7 |
Slight |
Slight |
Insubstantial |
|
T4 |
Pedestrians
on San Tin Highway Footbridge |
Full 250m |
Full 250m |
Small Negative |
Small Negative |
Medium Very Few |
Medium Very Few |
Moderate Negative |
Moderate Negative |
CM1-3
/ CM5&7 / CM9 / OM1 / OM3-7 |
Slight Negative |
Slight Negative |
Insubstantial |
|
O1 |
Workers
in fishponds in and around Mai Po |
Full 10m |
Full 10m |
Intermediate Negative |
Intermediate Negative |
Low Very few |
Low Very few |
Slight Negative |
Slight Negative |
CM1-3
/ CM5&7 / CM9 / OM1 / OM3-7 |
Slight Negative |
Slight Negative |
Insubstantial |
|
O2 |
Workers in
Industrial / Storage Areas north of Royal Palms |
Partial 10m |
Partial 10m |
Small Negative |
Small Negative |
Low Very few |
Low Very few |
Slight Negative |
Slight Negative |
CM1-3
/ CM5&7 / CM9 / OM1 / OM3-7 |
Slight Negative |
Slight Negative |
Insubstantial |
|
O3 |
Workers in
Industrial / Storage Areas east of Royal Palms |
Partial 10m |
Partial 10m |
Small Negative |
Small Negative |
Low Very few |
Low Very few |
Slight Negative |
Slight Negative |
CM1-3
/ CM5&7 / CM9 / OM1 / OM3-7 |
Slight Negative |
Slight Negative |
Insubstantial |
|
RE1 |
Visitors to
Mai Po Nature Reserve |
Partial 620m |
Partial 620m |
Small Negative |
Small Negative |
High Few |
High Few |
Moderate Negative |
Moderate Negative |
CM1-3
/ CM5&7 / CM9 / OM1 / OM3-7 |
Slight Negative |
Slight Negative |
Insubstantial |
* O = Occupational; R = Residential; T =
Travelling; RE = Recreational #
Detailed description of the other key aspects of the project
contributing to the Magnitude of Impact are provided in the written
descriptions of impacts for each VSR %
Detailed description of the other key aspects of the project
contributing to VSR sensitivity are provided in the written descriptions of
impacts for each VSR |
||||||||||||||
Summary of Landscape and Visual Mitigation Measures
· CM1 - The construction area and contractor’s temporary works areas should be minimised.
· CM2 - Screening of construction works by hoardings/noise barriers around Works area in visually unobtrusive colours, to screen Works.
· CM3 - Reduction of construction period to practical minimum.
· CM4 - Topsoil, where identified, and where the soil material meets acceptable criteria, should be stripped and stored for re-use.
· CM5 - Hydroseeding or sheeting of soil stockpiles.
· CM6 – Advance Screen Planting to noise barriers.
· CM7 - Control night-time lighting and glare by hooding all lights.
· CM8 - Ensure no run-off into streams adjacent to Site.
· CM9 - Protection of existing trees on boundary of Site.
· CM10 - Trees unavoidably affected by the works shall be transplanted where practical.
· OM1 - Compensatory Tree Planting for all felled trees
· OM2 - A continuous belt of screen planting along southern perimeter of site with fast growing tree species. A minimum of 450 trees capable of reaching a height > 10m within 10 years should be planted. These quantities are separate from those tree quantities identified for OM3. Planting of the belt of trees shall be carried out as advance works ahead of other site formation and building works.
· OM3 - Maximise landscape planting and amenity water bodies in residential areas of the development. Approximately 750 Heavy Standard size trees should be planted.
· OM4 - Maximise freshwater habitat wetland creation consistent with achieving other parameters (4.74ha). Implementation of the wetland shall be carried out as advance works.
· OM5 - Use appropriate (visually unobtrusive) building materials and colours in built structures.
· OM6 - During detailed design, refine building layout to create a min 10m wider gap between buildings at Wo Shang Wai pond and also two min 10m wide gaps in the row of buildings adjacent to Royal Palms.
· OM7 - Streetscape elements (e.g. paving, signage, street furniture, lighting etc.) shall be sensitively designed in a manner that responds to the rural context. Lighting units should be directional and minimise unnecessary light spill.
Summary of Predicted Landscape and Visual Impacts in the
Construction Phase
Summary of Predicted Landscape and Visual Impacts in the Operation
Phase
PREFACE
Wo Shang Wai to the north of Royal Palms and
The planning intention of this location is to provide
incentive for the restoration of degraded wetlands adjoining existing fish
ponds and to encourage the phasing out of sporadic open storage and port
back-up uses on degraded wetland. This
can be achieved through comprehensive residential and/or recreational
development to include wetland restoration area. Development or redevelopment schemes on the
degraded wetlands directly adjoining the existing continuous and contiguous fish
ponds should include wetland restoration and buffer proposals to separate the
development from and minimize its impact on the fish pond areas. Any new building should be located farthest
away from
Table 12‑1 Impacts Summary
Environmental Aspects |
Construction Phase |
Operational Phase |
Air Quality |
Fugitive dust impacts
controllable through standard suppression measures. |
No unacceptable impact
envisaged. |
Noise |
Noise generated as
a result of construction activities can be controlled through standard
mitigation measures and noise barriers/ site hoardings. |
100% compliance with
noise criteria. No adverse impact
predicted. |
Water Quality |
Minor on-site water
quality issues associated with excavations and construction works, controllable
through standard mitigation measures. |
No impact predicted
off-site. On-site water
quality management at the wetland will be controlled through monitoring and
auditing programme. |
Sewerage and Sewage
Treatment Implications |
Temporary toilet
facilities provided on-site for workforce. |
Discharge of
domestic effluent to planned public sewer therefore no impact predicted. |
Waste Management |
2,140m3
of Category M and Category H sediment to be reused/disposed of. |
Waste arisings
relate to domestic wastes and “green”/landscaping wastes. |
Ecological Impact
Assessment |
Permanent loss of
11.05ha of grassland, 4ha of freshwater marsh/reedbed, 0.69 of seasonal
marsh, 0.81ha of drainage ditches/channels and 4.81ha of bare ground &
developed land; and disturbance to wildlife, mitigated through the early
establishment of the wetland restoration area in the Project Area and minimize
powered mechanical equipment on-site. |
Minor disturbance
from the development area to wildlife. Ecological enhancement of around 4.74ha
of wetland with a variety of habitats of enhanced quality. |
Cultural Heritage |
No impact
predicted. |
No impact
predicted. |
Fisheries Impact
Assessment |
No direct impact predicted and indirect impacts will be insignificant
with good site practices and implementation of dust and water quality control
measures as presented in Chapter 3 and 5 respectively. |
No impact
predicted. |
Landscape and
Visual Impact |
Moderate negative
Impacts on freshwater marsh (about 4 ha); slight negative residual landscape
impacts on grassland with seasonal marsh patches (about 11.7ha), tree groups
(including banana trees) on-site, in open storage and along Castle Peak Road
(Mai Po) (about 86 trees in total); and slight negative impacts on the
landscape character of the Tsing Lung Tsuen Plain. Mitigated through standard
measures and protection of trees. Moderate negative
visual impacts experienced by residents in Royal Palms, Palm Springs and Wo
Shang Wai; slight negative residual visual impacts experienced by residents,
pedestrians and workers in a further distance, mitigated through screens and
hoardings /noise barriers around works area. |
Insubstantial
change to the landscape character of the Tsing Lung Tsuen Plain and
insubstantial residual visual impacts for more distant VSRs. Landscape visual
enhancement through net gain of landscape resources. Slight negative
visual impacts on a small number of residents in Royal Palms and |
PREFACE
Wo Shang Wai to the north of Royal Palms and
The planning intention of this location is to provide
incentive for the restoration of degraded wetlands adjoining existing fish
ponds and to encourage the phasing out of sporadic open storage and port
back-up uses on degraded wetland. This
can be achieved through comprehensive residential and/or recreational
development to include wetland restoration area. Development or redevelopment schemes on the
degraded wetlands directly adjoining the existing continuous and contiguous
fish ponds should include wetland restoration and buffer proposals to separate
the development from and minimize its impact on the fish pond areas. Any new building should be located farthest
away from
PREFACE
Wo Shang Wai to the north of Royal Palms and
The planning intention of this location is to provide
incentive for the restoration of degraded wetlands adjoining existing fish
ponds and to encourage the phasing out of sporadic open storage and port
back-up uses on degraded wetland. This
can be achieved through comprehensive residential and/or recreational
development to include wetland restoration area. Development or redevelopment schemes on the
degraded wetlands directly adjoining the existing continuous and contiguous fish
ponds should include wetland restoration and buffer proposals to separate the
development from and minimize its impact on the fish pond areas. Any new building should be located farthest
away from
EIA
Ref. |
Recommended
Mitigation Measures |
Who to implement the measure? |
Location of the measure |
When to implement the measure? |
What requirements or standards for the
measure to achieve? |
|
||||
Air Quality |
|
|||||||||
3.6.1 |
During
Construction Dust which may be generated during the
construction of the proposed Comprehensive Development is expected to be
released as a result of construction activities such as material handling,
excavation, vehicle movement and erosion of unpaved area and stockpiles. The
potential air quality impact is however anticipated to be short-term and be
controlled through appropriate design and good site practice stipulated in the
Air Pollution Control (Construction
Dust) Regulation. |
Contractor |
Construction Work Sites |
During Construction |
Air Pollution Control (Construction Dust) Regulation |
|
||||
|
To ensure compliance with the guidelines
and AQOs at the ASRs all time, it is recommended to implement the Air
Pollution Control (Construction Dust) Regulation and include good site
practice in the contract clauses to minimize cumulative dust impact. In addition, a comprehensive dust
monitoring and audit programme is recommended to ensure proper implementation
of the identified mitigation measures.
Details of the monitoring and audit requirements are provided in a
separate EM&A Manual. |
|
|
|
|
|
||||
|
·
use
of effective dust screens, sheeting or netting to be provided to enclose dry
scaffolding which may be provided from the ground floor level of the building
or if a canopy is provided at the first floor level, from the first floor
level, up to the highest level (maximum four floors for this Project) of the
scaffolding where scaffolding is erected around the perimeter of a building
under construction; |
|
|
|
|
|
||||
|
·
dump
trucks for material transport should be totally enclosed using impervious
sheeting; |
|
|
|
|
|
||||
|
·
any
excavated dusty materials or stockpile of dusty materials should be covered
entirely by impervious sheeting or sprayed with water so as to maintain the
entire surface wet, and recovered or backfilled or reinstated within 24 hours
of the excavation or unloading; |
|
|
|
|
|
||||
|
·
dusty
materials remaining after a stockpile is removed should be wetted with water; |
|
|
|
|
|
||||
|
·
the
area where vehicle washing takes place and the section of the road between
the washing facilities and the exit point should be paved with e.g. concrete,
bituminous materials or hardcore or similar; |
|
|
|
|
|
||||
|
·
the
portion of road leading only to a construction site that is within |
|
|
|
|
|
||||
|
· stockpile of dusty materials to be either
covered entirely by impervious sheeting, placed in an area sheltered on the
top and the 3 sides; or sprayed with water so as to maintain the entire
surface wet; |
Contractor |
Construction Work Sites |
During Construction |
Air
Pollution Control (Construction
Dust) Regulation |
|
||||
|
·
all
dusty materials to be sprayed with water prior to any loading, unloading or
transfer operation so as to maintain the dusty material wet; |
|
|
|
|
|
||||
|
·
vehicle
speed to be limited to 10 kph except on completed access roads; |
|
|
|
|
|
||||
|
·
every
vehicle should be washed to remove any dusty materials from its body and
wheels before leaving the construction sites; |
|
|
|
|
|
||||
|
·
the
load of dusty materials carried by vehicle leaving a construction site should
be covered entirely by clean impervious sheeting to ensure that the dusty
materials do not leak from the vehicle; |
|
|
|
|
|
||||
|
·
the
working area of excavation should be sprayed with water immediately before,
during and immediately after (as necessary) the operations so as to maintain
the entire surface wet; |
|
|
|
|
|
||||
|
·
all
malodorous excavated material should be placed as far as possible from any
ASRs; |
|
|
|
|
|
||||
|
·
the
stockpiled malodorous materials should be removed from site as soon as
possible; and |
|
|
|
|
|
||||
|
·
the
stockpiled malodorous materials should be covered entirely by plastic
tarpaulin sheets. |
|
|
|
|
|
||||
|
In order to minimise the potential odour
nuisance arising from the excavation of pond deposit, the following control
measures shall be implemented: |
Contractor |
Construction Work Sites |
During excavation and dredging |
|
|
||||
|
·
all
malodorous excavated material should be placed as far as possible from any
ASRs; |
|
|
|
|
|
||||
|
·
the
stockpiled malodorous material should be removed from site as soon as
possible; and |
|
|
|
|
|
||||
|
·
the
stockpiled malodorous material should be covered entirely by plastic
tarpaulin sheets. |
|
|
|
|
|
||||
3.6.2 |
During
Operation |
N/A |
N/A |
N/A |
N/A |
|
||||
|
The potential impacts on air quality
during the operation phase are insignificant, therefore specific mitigation
measures are not required. |
|
|
|
|
|
||||
Noise |
|
|||||||||
4.8.1 |
During
Construction The noise impact of unmitigated
construction activities for Wo Shang Wai together with the wetland
restoration would cause exceedance of the daytime construction noise
criterion at all the representative NSRs except NSR8 during the normal
working hours. Mitigation measures for
construction site are proposed and should be incorporated into the Contract
Specifications. While it is recognised that the Contractor
may develop a different package of mitigation measures to meet the required
noise standards, the following suite of practical and implementable measures
demonstrate an approach that would be feasible to reduce noise to acceptable
levels. |
Contractor |
Construction Work Sites |
During Construction |
PN 2/93 Noise from Construction Activities
& EIAO |
|
||||
|
Good
Site Practice Good site practice and noise management
can significantly reduce the impact of construction site activities on nearby
NSRs. The following package of
measures should be followed during
construction: |
Contractor |
Construction Work Sites |
During Construction |
PN 2/93 Noise from Construction Activities
& EIAO |
|
||||
|
·
only
well-maintained plant should be operated on-site and plant should be serviced
regularly during the construction works; |
|
|
|
|
|
||||
|
·
machines
and plant that may be in intermittent use should be shut down between work
periods or should be throttled down to a minimum; |
|
|
|
|
|
||||
|
·
plant
known to emit noise strongly in one direction should, where possible, be
orientated to direct noise away from the NSRs; |
|
|
|
|
|
||||
|
·
silencers
or mufflers on construction equipment should be utilised and should be
properly maintained during the construction period; |
|
|
|
|
|
||||
|
·
mobile
plant should be sited as far away from NSRs as possible; |
|
|
|
|
|
||||
|
·
material
stockpiles and other structures should be effectively utilised, where
practicable, to screen noise from on-site construction activities; and |
|
|
|
|
|
||||
|
·
The
Contractor shall at all times comply with all current statutory environmental
legislation. |
|
|
|
|
|
||||
|
Selection
of quieter plant and working methods The Contractor shall obtain particular
models of plant that are quieter than standards given in GW-TM. The list of assumed quieter plants can be
found in the Table 4–14 of the EIA
report. The Contractor shall select
from the available models achieving the assumed sound levels while making
reference to the GW-TM and BS5228: Part 1: 1997 |
Contractor |
Construction Work Sites |
During Construction |
PN 2/93 Noise from Construction Activities
& EIAO |
|
||||
|
Use
of Noise Barriers/ Site Hoardings Noise barriers and site hoardings are
proposed along the site boundary to block the direct line of sight from the
most affected NSRs to the major noise contribution construction phases as
shown in Figures 4.6 and 4.7 of the EIA Report. The
height of the noise barriers ranged from 9-10m, while the height of the site
hoardings ranged from 2.4-3m. The
noise barriers and site hoardings shall be built before the commencement of
construction works in order to ensure protection to nearby NSRs. The noise barriers and site hoardings
should have a surface density of at least |
Contractor |
Construction Work Sites |
Before the commencement of construction
works |
PN 2/93 Noise from Construction Activities
& EIAO |
|
||||
4.7.5 |
During
Operation Fixed
Noise Sources Open storage site at the northeast corner
of the Project Area and the sewage treatment plant in Royal Palms are
potential fixed noise sources, the assessment result comply with both day and
night time noise criteria. No
mitigation measures are required. |
N/A |
N/A |
N/A |
N/A |
|
||||
4.7.6 |
Road
Traffic Noise During the operational phase, road traffic
noise will be the dominant noise source within the Study Area, and will
potentially affect the planned noise sensitive developments. |
N/A |
N/A |
N/A |
N/A |
|
||||
|
This assessment has predicted that the
traffic noise levels including the contribution from existing network at the
year 2027 will comply with the road traffic noise criterion of L10 (peak
hour) 70 dB(A). The increased noise
levels in 2028 are minimal and insignificant.
No mitigation measures are required. |
|
|
|
|
|
||||
Water Quality |
|
|||||||||
5.6.1 |
During
Construction Potential water quality impacts primarily
relate to the un-controlled discharge of sediments/ silts during construction.
Good site practices in addition to the implementation of mitigation measures
would minimize the impact to the surrounding environment. |
Contractor |
Construction Work Sites |
During Construction |
Practice Note for Professional Persons
with regard to site drainage (ProPECC PN 1/94) and WQO |
|
||||
|
General Precautions |
|
|
|
|
|
||||
|
·
The
site should be confined to avoid silt runoff to the site. |
|
|
|
|
|
||||
|
·
No
discharge of silty water into the storm drain and drainage channel within and
the vicinity of the site. |
|
|
|
|
|
||||
|
·
Any
soil contaminated with chemicals/oils shall be removed from site and the void
created shall be filled with suitable materials. |
|
|
|
|
|
||||
|
·
Stockpiles
to be covered by tarpaulin to avoid spreading of materials during rainstorms; |
|
|
|
|
|
||||
|
·
Suitable
containers shall be used to hold the chemical wastes to avoid leakage or
spillage during storage, handling and transport; |
|
|
|
|
|
||||
|
·
Chemical
waste containers shall be labelled with appropriate warning signs in English
and Chinese to avoid accidents. there
shall also be clear instructions showing what action to take in the event of
an accidental; |
Contractor |
Construction Work Sites |
During Construction |
Practice Note for Professional Persons
with regard to site drainage (ProPECC PN 1/94) and WQO |
|
||||
|
·
Storage
areas shall be selected at safe locations on site and adequate space shall be
allocated to the storage area; |
|
|
|
|
|||||
|
·
Any
construction plant which causes pollution to the water system due to leakage
of oil or fuel shall be removed off-site immediately; |
|
|
|
|
|
||||
|
·
Spillage
or leakage of chemical waste to be controlled by using suitable absorbent
materials; |
|
|
|
|
|
||||
|
·
Chemicals
will always be stored on drip trays or in bunded areas where the volume is
110% of the stored volume; |
|
|
|
|
|
||||
|
·
Regular
clearance of domestic waste generated in the temporary sanitary facilities to
avoid waste water spillage. |
|
|
|
|
|
||||
|
·
Temporary
sanitary facilities to be provided for on-site workers during
construction. |
|
|
|
|
|
||||
|
Diversion of Existing Water Ditches and Marsh |
|
|
|
|
|
||||
|
Temporary drainage channel and associated facilities will be provided
to collect the surface runoff generated within the Project Area during the
construction phase. |
Contractor |
Construction
Work Sites |
During
Construction |
Practice
Note for Professional Persons with regard to site drainage (ProPECC PN 1/94)
and WQO |
|
||||
|
Draining of
Existing Water Ditches |
|
|
|
|
|
||||
|
Sandbags or
silt traps will need to be placed to avoid silt runoff to the drainage
channel draining the water in the northern ditch. Draining of the ditches should avoid rainy
weather. |
Contractor |
Construction Work Sites |
During Construction |
Practice Note for Professional Persons
with regard to site drainage (ProPECC PN 1/94) and WQO |
|
||||
|
Soil Excavation and Stockpiling |
|
|
|
|
|
||||
|
Excavated soil which needs to be temporarily stockpiled should be
stored in a specially designated area and provided with a tarpaulin cover to
avoid runoff into the drainage channels. |
Contractor |
Construction
Work Sites |
During
Construction |
Practice
Note for Professional Persons with regard to site drainage (ProPECC PN 1/94)
and WQO |
|
||||
|
|
|
|
|
|
|
||||
|
|
|
|
|
|
|
||||
|
|
|
|
|
|
|
||||
5.6.2 |
During
Operation |
|
|
|
|
|
||||
|
Provisional
Measures to Emergency Sewage Discharges/Spillages |
|
|
|
|
|
||||
|
As described in Section 6, the sewage
generated from the residents of this development will be discharged to the
planned public sewer. For discharging
the sewage to the public sewers in the permanent case, no special mitigation
measures are required. In order to minimize the potential impacts arising
from sewer bursting, concrete surround to the sewers is proposed within the
proposed development as an additional protection measures for the pipelines.
(Study Brief Section 3.9.3.4 (xxviii)) |
Residential Management Contractor |
Project Area |
During Operation |
WPCO WQO |
|
||||
|
Diversion of Existing Water Ditches and Marsh |
|
|
|
|
|
||||
|
Future internal drainage network will have
sufficient capacity to cater for the runoff generated from the proposed
development, to replace the existing water ditches and marsh. The tentative drainage scheme is shown on Figure 5.3. (Study
Brief Section 3.9.3.4 (iv)). |
N/A |
N/A |
N/A |
N/A |
|
||||
|
Provision of Soft-landscaping |
|
|
|
|
|
||||
|
An internal drainage network will be
provided to collect runoff from the residential development. Runoff from the developed areas will be
diverted into the internal drainage system during storm and adverse weather
conditions. Soft landscaping in
between the boundary of the wetland and the residential area will be provided
to act as a buffer zone to absorb any overflow or flood waters before enters
into wetland area. |
Residential Management Contractor |
Interface of
Residential Development and Restored Wetland |
During Operation |
N/A |
|
||||
Waste Management |
|
|||||||||
7.5.1 |
During
Construction Site
Clearance Waste The major construction works of Wo Shang
Wai is in the development of residential buildings and other associated
facilities (club house, tennis courts, etc). The amount of site clearance
works will be limited with the exception of the excavated materials. The thin
layer of vegetation removed can be stored and reused for landscaping. |
Contractor |
Construction Work Sites |
During Construction |
Waste Disposal Ordinance (Cap.354); Waste
Disposal (Chemical Wastes) (General) Regulation (Cap 354) and ETWBTC No.
15/2003, Waste Management on Construction Site |
|
||||
7.5.2 |
Excavated
Materials The intention is to maximize the reuse of
the excavated materials on-site as fill materials. |
|
|
|
|
|||||
7.5.3 |
Imported Filling Material The
excavated/imported filling material may have to be temporarily stockpiled
on-site for the construction of road embankment and foundation of viaduct
substructure. Control measures should
be taken at the stockpiling area to prevent the generation of dust and
pollution of stormwater channels.
However, to eliminate the risk of blocking drains in the wet season,
it is recommended that stockpiling of excavated materials at during wet
season should be avoided as far as practicable. |
|
|
|
|
|||||
7.5.4 |
Construction and Demolition Materials Careful design, planning and good site
management can minimise over-ordering and generation of waste materials such as
concrete, mortars and cement grouts.
The design of formwork should maximise the use of standard wooden
panels so that high reuse levels can be achieved. Alternatives such as steel formwork of
plastic facing should be considered to increase the potential for reuse. |
Contractor |
Construction Work Sites |
During Construction Planning |
Waste Disposal Ordinance (Cap.354); Waste
Disposal (Chemical Wastes) (General) Regulation (Cap 354) and ETWBTC No.
15/2003, Waste Management on Construction Site |
|
||||
The Contractor should reuse any C&D
material on-site. C&D waste should be segregated and stored in different
containers to other wastes to encourage the re-use or recycling of materials
and their proper disposal. |
Contractor |
Construction Work Sites |
During Construction |
|
||||||
7.5.5 |
Chemical Waste For those processes which generate chemical waste, it may be possible
to find alternatives which generate reduced quantities or even no chemical
waste, or less dangerous types of chemical waste. |
|
|
|
|
|
||||
|
Chemical waste that is produced, as defined by Schedule 1 of the Waste
Disposal (Chemical Waste) (General) Regulation, should be handed in
accordance with the Code of Practice on the Packaging, Handling and Storage
of Chemical Waste as follows: |
|
|
|
|
|||||
|
Containers used for the storage of chemical wastes should: |
|
|
|
|
|
||||
|
·
be
suitable for the substance they are holding, resistant to corrosion,
maintained in a good condition, and securely closed: |
|
|
|
|
|
||||
|
·
have
a capacity of less than 450 litres unless the specification have been
approved by the EPD; and |
|
|
|
|
|
||||
|
·
display
a label in English and Chinese in accordance with instructions prescribed in
Schedule 2 of the Regulations, |
|
||||||||
|
The storage area for chemical wastes should: |
|
||||||||
|
·
be
clearly labelled and used solely for the storage of chemical waste; |
|
||||||||
|
·
be
enclosed on at least 3 sides; |
|
|
|
|
|||||
|
·
have
an impermeable floor and bunding, of capacity to accommodate 110% of the
volume of the largest container or 20% by volume of the chemical waste stored
in that area whichever is the greatest; |
|
|
|
|
|||||
|
·
have
adequate ventilation; |
|
|
|
|
|
||||
|
·
be
covered to prevent rainfall entering (water collected within the bund must be
tested and disposed as chemical waste if necessary); and |
|
|
|
|
|
||||
|
·
be
arranged so that incompatible materials are adequately separated. |
|
|
|
|
|
||||
|
Disposal of chemical waste should: |
|
|
|
|
|
||||
|
·
be
via a licensed waste collector; and |
|
|
|
|
|
||||
|
·
be to
a facility licensed to receive chemical waste, such as the Chemical Waste
Treatment Facility which also offers a chemical waste collection service and
can supply the necessary storage containers, or |
|
|
|
|
|
||||
|
·
to be
re-user of the waste, under approval from the EPD. |
|
|
|
|
|
||||
7.5.6 |
General Refuse Should be stored in enclosed bins or
compaction units separate from C&D and chemical wastes. The Contractor should employ a reputable
waste collector to remove general refuse from the site, separate from C&D
and chemical wastes, on a regular basis to minimise odour, pest and litter
impacts. Burning of refuse on
construction sites is prohibited by law. |
Contractor |
Construction Work Sites |
During Construction |
WDO (Cap.354) and ETWBTC No. 15/2003 |
|
||||
7.8.13 |
Disposal of Excavated Sediment at Sea |
|
|
|
|
|
||||
|
The requirements and procedures for
excavated sediment disposal are specified under the ETWB TCW No. 34/2002 and
PNAP 252. The management of the
excavation, use and disposal of sediment is monitored by Fill Management
Committee, whilst the licensing of marine dumping is the responsibility of
the Director of Environmental Protection (DEP). |
Contractor |
Project Area |
Construction |
ETWB TCW No. 34/2002 and PNAP 252 |
|
||||
|
The excavated sediment would be loaded
onto barges or other appropriate vessel and transported to the designated
marine disposal site. Category L
sediment and Category M sediment passing the biological test would be
suitable for disposal at a gazetted open sea disposal ground. Category M sediment failing the biological
test and Category H sediment passing the biological test would require
confined marine disposal. |
Contractor |
Project Area |
Construction |
Practice Note for Professional Persons
with regard to site drainage (ProPECC PN 1/94) and WQO |
|
||||
|
During transportation and disposal of the
dredged sediment, the following measures should be taken to minimize
potential impacts on water quality: - |
|
|
|
|
|
||||
|
·
Bottom
opening transport vessels should be fitted with tight fitting seals to
prevent leakage of material. Excess material should be cleaned from the decks
and exposed fittings of vessels before the vessel is moved. |
|
|
|
|
|
||||
|
·
Monitoring
of the barge loading should be conducted to ensure that loss of material does
not take place during transportation. Transport barges or vessels should be
equipped with automatic self-monitoring devices as specified by the DEP. |
|
|
|
|
|
||||
Ecology |
|
|||||||||
8.9.2 |
During
Construction Major potential impacts on ecology during
the construction phase include habitat loss and disturbances to wildlife.
These impacts were assessed in section 8.8. |
|
|
|
|
|
||||
|
The following specific mitigation measures
to minimise impacts and disturbance to the surrounding habitats, are
recommended. |
|
|
|
|
|
||||
|
Clear Definition of Site Limit |
|
|
|
|
|
||||
8.9.20-8.9.21 |
Clear definition of
the site limit should be provided in order to minimize and confine the
disturbance during the construction period, especially the northern limit of
the Site which is adjacent to fishponds within the Conservation Area (CA)
zone and are considered to be ecological sensitive receivers. During wetland construction stage the WRA
boundary will be delineated using a temporary hoarding in order to reduce
disturbance to off-site habitats and wildlife. During the establishment phase this
hoarding will be replaced with a 1 m high chain-link fence in order to reduce
disturbance to the WRA through access by humans and dogs, and a hoarding will
be established around the residential construction site. |
Contractor |
Construction Work Sites |
During Construction |
EIAO |
|
||||
|
Dust and Noise Suppression and Avoidance
of Water Pollution |
|
|
|
|
|
||||
8.9.20-8.9.21 |
Good site practices
of dust and noise suppression should be strictly implemented to ensure that
disturbance is minimized to acceptable levels. Mitigation measures for the
off-site disturbance impacts on the fishponds in the CA include hoarding at
the northern site boundary during construction of the WRA to reduce noise and
dust impacts to the adjacent habitats. Through the use of quieter plant and
temporary/movable noise barriers, the noise level would be reduced
significantly to an acceptable level. Hoarding at the northern boundary
should be replaced with a 1 m high chain-link fence following construction
and the WRA will then act as a buffer between the existing wetland areas and
the residential part of the site until construction is completed. Hoarding will be retained between the WRA
and ongoing construction work to avoid visual disturbance and reduce noise
and dust emissions. Pollution of watercourses
and sedimentary runoff will be minimized by good site practice, especially
the containment of water and sediment within the site for removal. These
standard noise and air and water quality site practices are considered to be
effective measures for minimizing the disturbance impact during the
construction period. |
Contractor |
Construction Work Sites |
During
Construction |
EIAO and |
|
||||
|
Planning of Construction Schedule The
construction of the proposed project should be scheduled in phases. Because
mitigation is preferably carried out in advance of the main works rather than
after the completion of works, the construction of the WRA will commence at
the start of the project. Construction
work within the WRA is scheduled to take place in a single wet season,
followed by 1.5 years of wetland establishment. During the wetland
establishment period no noisy work will be undertaken within the WRA to
minimize the disturbance to off-site habitats and wildlife. |
Contractor |
Construction
Work Sites |
During
Construction |
EIAO and |
|
||||
|
Reusing Onsite Materials |
|
|
|
|
|
||||
|
Soil and plants
on-site should be reused (e.g. used as fill material) as far as practical.
Stock piles of these reusable materials should be stored in an appropriate
area on-site. In particular, the re-use of the wetland soils and topsoil
should be considered. |
Contractor |
Construction
Work Sites |
During
Construction |
Waste
Disposal Ordinance (Cap.354); Waste Disposal (Chemical Wastes) (General)
Regulation (Cap 354) and ETWBTC No. 15/2003, Waste Management on Construction
Site |
|
||||
|
Construction of the Wetland Restoration Area The WRA will be operational within 2.5 yrs from the
commencement of construction (1 year for site formation and1.5 years for
establishment) and will compensate for the predicted ecological impacts of
the proposed development. |
Contractor
to construct and Wetland Manager to manage |
The defined area for the proposed Wetland
Restoration Area |
During construction phase prior to the
construction of the residential area |
EIAO and the proposed Wetland Restoration
Plan (WRP) |
|
||||
8.9.3 |
During Operation The major impact would be the habitat change
resulting from the proposed project and disturbance from the proposed
residential area. |
|
|
|
|
|
||||
|
Operational Phase |
|
|
|
|
|
||||
|
Operational impacts include disturbance to wildlife
and loss of habitat. Species that potentially receive significant impacts
from the proposed development are Little Egret, Cattle Egret and Chinese Pond
Heron. |
Contractor
to construct and Wetland Manager to manage |
The defined area for the proposed Wetland
Restoration Area |
During construction phase prior to the
construction of the residential area |
EIAO and the proposed Wetland Restoration
Plan (WRP) |
|
||||
|
The recommended mitigation measure to
reduce/eliminate the impacts on these species is the provision of the WRA.
The location of the WRA at the northern portion of the Site is selected to
minimise impacts on bird flight paths, to buffer the existing wetland areas
from the proposed residential areas and to enhance integration with existing
wetland habitats outside the Project Area. |
|
|
|
|
|
||||
|
Protect the Offsite Fishpond Habitats
& Perform Buffer Function These objectives can best be achieved by
locating the WRA between the WCA/CA and residential areas to separate the two
types of land use. In addition, the area of the existing lorry park site will
be incorporated into the WRA to further enhance the buffer function. |
|
|
|
|
|
||||
|
Provide
Suitable Habitats of Enhanced Quality for the Target Species The Wetland Restoration Area of a minimum
size of 4.74 ha will be established, to mitigate the loss of 4.69 ha of
wetland habitats. In addition to the
habitat loss, the WRA is designed to mitigate for on-site and/or off-site
disturbance during construction and operational phases as identified in
Section 8.8 of the final EIA report. The habitats in the WRA will be designed
specifically to meet the habitat requirements of the target species rather
than simply restore specific habitats of ecological value. |
Contractor
to construct and Wetland Manager to manage |
The defined area for the proposed Wetland
Restoration Area |
During construction phase prior to the
construction of the residential area |
EIAO and the proposed Wetland Restoration
Plan (WRP) |
|
||||
|
The following
micro-habitats will be provided within the wetland restoration area to meet
the requirements for the target species: ·
Open
water up to 2.5 m in depth with shallow water margins (0-20 cm depth); ·
reedbed
with shallow water margins (0-20 cm depth) and deeper water areas up (to 1 m
depth); ·
vegetated
and non-vegetated islands and shallow water margins (0-20 cm depth); ·
trees/tall
shrubs overhanging parts of the main water body; ·
short
grass; and ·
a
mixture of tall grass and shrubs. |
|
|
|
|
|
||||
|
Building
Height with Consideration of Bird Flight Path Under the OZP for the area (OZP No. S/YL-MP/6) the
maximum permitted height for buildings within the Project Area is six
storeys. This is considerably higher
than the buildings at There will be some residual impact to
flight paths in the northern part of the Project Area during the construction
phase of the WRA, resulting from the presence of construction machinery and
from site fencing (required to avoid visual disturbance impacts to foraging waterbirds)
and potentially also from noise disturbance.
These impacts will be limited in duration to the construction period
of the WRA (scheduled to take place in a single wet season), and the timing
of the WRA formation at the start of the construction period will ensure that
the duration of these construction-phase impacts to flight paths will be
minimised |
Developer |
The defined area for the proposed Wetland
Restoration Area |
During planning stage |
Mai Po and |
|
||||
Fisheries |
|
|||||||||
9.7 |
With good site practices and
implementation of dust and water quality control measures addressed in S.3.6 and
S.5.6 of this EIA report (including site confinement with scaffolding
erection around the perimeter of the construction site, covering of stockpile
by impervious sheeting to avoid spread of dusty materials and proper storage
and disposal of chemical waste to avoid discharge to the existing water
system, etc.), the dust and water quality impacts on the adjacent fishponds
are expected be controlled to within acceptable levels, which will also
protect the fisheries resources from being impacted. The moderate-low impacts
for the event of high dose chemical waste pollution would also be avoided by
the proper handling and disposal of chemical waste released from mechanical
equipment during construction phase. All indirect off-site impacts on pond
culture activities are expected to be insignificant. Thus, no specific mitigation measure for
fisheries impacts is required during the construction and operation phases. |
Contractor |
Construction Work Sites |
During Construction |
EIAO |
|
||||
Cultural Heritage |
|
|||||||||
10.5 |
As no impacts on recorded archaeological
sites or area with archaeological potential were identified within the Study
Area, no mitigation measure for archaeological resources is considered
necessary. The assessment results showed that neither
declared / deemed monuments nor graded historical buildings were located
within the study area. No impact on cultural heritage elements was
anticipated and no associated mitigation measures therefore were considered
necessary. |
|
|
|
|
|
||||
Landscape & Visual Impact |
||||||||||
|
Overall, it is considered that, in the
terms of Annex 10 of the EIAO-TM, the landscape and visual impacts are
acceptable with the mitigation measures outlined below. |
|
|
|
|
|||||
|
During
Construction |
|
|
|
|
|||||
11.6 |
Mitigation measures will comprise the
following: |
|
|
|
|
|||||
Table 11-3 |
CM1- The construction area and
contractor’s temporary works areas should be minimised to avoid impacts on
adjacent landscape. |
Developer via Contractor |
Construction Work Sites |
During Construction |
EIAO |
|||||
|
CM2 - Screening of construction works by
hoarding / noise barriers. |
Developer via Contractor |
Construction Work Sites |
During Construction |
EIAO |
|||||
|
CM3 - Reduction of construction period to
practical minimum. |
Developer via Contractor |
Construction Work Sites |
During Construction |
EIAO |
|||||
|
CM4 - Topsoil, where identified, should be
stripped and stored for re-use in the construction of the soft landscape
works, where the soil material meets acceptable criteria and where
practical. The Contract Specification
shall include storage and reuse of topsoil as appropriate. |
Developer via Contractor |
Construction Work Sites |
During Construction |
EIAO |
|||||
|
CM5 - Hydroseeding or sheeting of soil
stockpiles with visually unobtrusive material (in earth tone). |
Developer via Contractor |
Construction Work Sites |
During Construction |
EIAO |
|||||
|
CM6 – Advance screen planting of noise
barriers |
Developer via Contractor |
Construction Work Sites |
During Construction |
EIAO |
|||||
|
CM7 - Control night-time lighting and
glare by hooding all lights. |
Developer via Contractor |
Construction Work Sites |
During Construction |
EIAO |
|||||
|
CM8 - Ensure no run-off into streams
adjacent to the Project Area. |
Developer via Contractor |
Construction Work Sites |
During Construction |
EIAO |
|||||
|
CM9 - Protection of existing trees on
boundary of site shall be carefully protected during construction. Detailed Tree Protection Specification
shall be provided in the Contract Specification. Under this specification,
the Contractor shall be required to submit, for approval, a detailed working
method statement for the protection of trees prior to undertaking any works
adjacent to all retained trees, including trees in contractor’s works
areas. (Tree protection measures will
be detailed at S16 and Tree Removal Application stage). |
Developer via Contractor |
Construction Work Sites |
During Construction |
EIAO |
|||||
|
CM10 - Trees unavoidably affected by the
works shall be transplanted where practical.
Trees should be transplanted straight to their destinations and not
held in a nursery. A detailed Tree
Transplanting Specification shall be provided in the Contract Specification, if
applicable. Sufficient time for necessary tree root and crown preparation
periods shall be allowed in the project programme. |
Developer via Contractor |
Construction Work Sites |
During Construction |
EIAO |
|||||
|
During
Operation |
|
|
|
|
|||||
11.6 |
Mitigation measures will comprise the
following: |
|
|
|
|
|||||
Table 11-4 |
OM1 - Compensatory Tree Planting for all
felled trees shall be provided to the satisfaction of relevant Government
departments. Required numbers and locations of compensatory trees shall be
determined and agreed separately with Government during the Tree Felling
Application process under ETWBTC 3/2006. |
Developer / Detailed Designer |
Across Project Site |
Before Day
1 of Opening |
EIAO & ETWBTC 3/2006 |
|||||
|
OM2 - A continuous belt of screen planting
along southern perimeter of site with fast growing tree species. At least 450
trees capable of reaching a height > 10m within 10 years should be
planted. Planting of the belt of trees
shall be carried out as advance works ahead of other site formation and
building works. |
Contractor / Developer |
Southern perimeter of Project Site |
Immediately on completion of Site
Formation Works |
EIAO |
|||||
|
OM3 - Maximise soft landscape and amenity
water bodies in residential areas of the development. Approximately 750 trees of Heavy Standard
size should be planted. Where space permits, roadside berms should be
created. Street trees should be of species that reach a mature height of no
less than 15m. |
Developer / Detailed Designer |
Across Project Site |
Before Day
1 of Opening |
EIAO |
|||||
|
OM4 - Maximise wetland creation consistent
with achieving other parameters. Minimum 4.74 ha will be provided.
Implementation of the wetland shall be carried out as advance works. |
Developer |
Wetland areas, other than wetland purely
for visual amenity. |
Before Day
1 of Opening |
EIAO |
|||||
|
OM5 - Use appropriate (visually
unobtrusive and non-reflective) building materials and colours in built
structures. |
Developer / Detailed Designer |
Across Project Site |
Before Day
1 of Opening |
EIAO |
|||||
|
OM6 - During detailed design,
refine building layout to create a min 10m
wider gap between buildings at Wo Shang Wai pond and also two min 10m
wide gaps in the row of buildings adjacent to Royal Palms. |
Developer / Detailed Designer |
Across Project Site |
Before Day
1 of Opening |
EIAO |
|||||
|
OM7 - Streetscape elements (e.g. paving,
signage, street furniture, lighting etc.) shall be sensitively designed in a
manner that responds to the rural context. Lighting units should be
directional and minimise unnecessary light spill. |
Developer / Detailed Designer |
Across Project Site |
Before Day
1 of Opening |
EIAO |
|||||
PREFACE
Wo Shang Wai to the north of Royal Palms and
The planning intention of this location is to provide
incentive for the restoration of degraded wetlands adjoining existing fish
ponds and to encourage the phasing out of sporadic open storage and port
back-up uses on degraded wetland. This
can be achieved through comprehensive residential and/or recreational
development to include wetland restoration area. Development or redevelopment schemes on the
degraded wetlands directly adjoining the existing continuous and contiguous
fish ponds should include wetland restoration and buffer proposals to separate
the development from and minimize its impact on the fish pond areas. Any new building should be located farthest
away from
Air Quality
Noise Impact
Water Quality Impact
Sewerage and Sewage Treatment Implications
Waste Management
Ecological Impact Assessment
Fisheries Impact Assessment
Cultural Heritage
Landscape and Visual Impact