10. CONCLUSIONS & SUMMARY OF ENVIRONMENTAL OUTCOMES
10.5 Waste Management
Implications
10.6 Landscape and Visual Impact
Table 10.1 Summary of Key Environmental Outcomes / Benefits
n
Air Quality
Impact
n
Water Quality
Impact
n
Ecological Impact
n
Waste Management
Implications
n
Landscape and
Visual Impact
Construction Phase
Operation Phase
Table
10.1 Summary of Key Environmental Outcomes / Benefits
Area/Issue |
Environmental Outcomes / Benefits and
Mitigation Measures |
Purpose and Scope of the Project |
Under the
Review of the Tuen Mun and Tsing Yi Sewerage Master Plan (RTMTYSMP) commissioned
in February 1999, the existing Pillar Point STW was recommended to be
upgraded from preliminary treatment to chemical treatment with disinfection.
The aim of the PPSTW upgrading works is to improve the effluent quality, and
to meet the demand of future population and pollutant loads at ultimate
development scenario (UDS). The
RTMYSMP recommended the viability of the upgrading works to the STW, which
comprised the following: ·
expanding the treatment capacity of the existing STW to
cope with the increased peak wet weather sewage flow under the UDS to cater
for the increase in population arising from the planned development in Tuen
Mun area; ·
upgrading the sewage treatment level of the existing STW
to incorporate chemical treatment (subject to EIA Study under the Assignment)
with disinfection at minimum removal rates of 70%, 55% and 99.9% for
suspended solids, biochemical oxygen demand and E. coli respectively; ·
upgrading existing septic waste reception facilities at
PPSTW; and ·
providing and upgrading ancillary facilities including the
administration building, workshop, laboratory, odour control facilities,
sludge handling and dewatering facilities, access roads and minor landscaping
works within the STW for the operation and maintenance of the upgraded STW. A
preliminary design taking into account all the Project requirements is
carried out. In the preparation of the
preliminary design, the sewage flows and loads are to be estimated in order to
determine the treatment capacity and effluent standards of the upgraded
PPSTW. Moreover, an appropriate
treatment process is to be selected for the upgraded PPSTW. The EIA Study is
conducted based on the preliminary design
is to provide information on the nature and extent of environmental
impacts arising from the construction and operation of the Project and
related activities that take place concurrently. |
Selection of Preferred Treatment Processes |
The
technical review and evaluation of different treatment processes conducted
for the Project recommended the following processes and these recommendations
were adopted for development of the preliminary design : ·
CEPT with
conventional single-deck clarifier ·
UV irradiation
for disinfection ·
Compact septic
waste reception station and discharging septic waste into sludge holding
tanks ·
Sludge
dewatering by using centrifuges |
Key Environmental friendly designs recommended |
·
All the exposed
areas of the upgraded PPSTW would be covered with providing deodourizing
facility. All vented air would be
treated in the deodourizing units with 90% odour removal efficiency, which is
considered common and practically achievable, before discharging into the
atmosphere. ·
Dual power
supply should be provided to prevent the occurrence of power failure. The main treatment units include the sedimentation
tanks, sludge treatment facilities including the sludge holding tanks and
sludge dewatering building and the UV disinfection facility. There are in
total 9 nos. of sedimentation tanks in which 8 nos. are duty, which are
capable for the treatment during peak design flow and 1 no. of sedimentation
tank is reserved for standby. There are in total 3 nos. of sludge holding
tanks in which one tank is in use normally and the second tank is for in use
over weekend due to weekend stopage and the third tank retained for emergency
storage. There are in total 4 nos. of centrifuges installed in the sludge
dewatering building, with 3 in duty and 1 in standby mode for sludge
dewatering. There are spare UV lamps and accessories, like ballasts etc., for
the UV disinfection facility. They
will be stored in the spares storage areas as shown in Figure 2.3 for replacement of worn parts/accessories in the UV
tanks during non-peak period. At least one standby pump will be provided for
each pumping station for maintenance purpose. ·
Trees affected
by the upgrading works will be mitigated through the transplanting of
existing trees and planting of new stock. All excavated area and disturbed
area for utilities diversion, temporary road diversion, and pipeline woks
will be reinstated to former conditions, subject to applicable Government
Standards. Existing topsoil shall be re-used where possible for
new planting areas within the project. The construction program shall
consider using the soil removed from one phase for backfilling another.
Suitable storage ground, gathering ground and mixing ground may be set up
on-site as necessary. ·
Compatible
design, construction materials and surface finishes of the proposed structure
should match with the nearby existing external appearance of PPSTW buildings
for achieving visual uniformity.
Finishing materials shall have due consideration to form, basic color,
color/tone variation, micro- and macro-texture, and reflectivity/light
absorbance to avoid glare. Planting,
such as turf, low groundcovers and climbers, may also be planted on top of
these elements to provide greening and aesthetic effect. |
Key environmental problems avoided |
The aim of
the upgrading works is to expand the sewage treatment capacity and to upgrade
the treatment level of the PPSTW in order to cater for the projected ultimate
population and planned developments in the Tuen Mun area. |
Air Quality Impact |
Population and environmental sensitive
receivers protected: (Refer to
Figure 3.1) ·
River Trade
Terminal Office (Commercial) ·
·
·
Sawmill
(Factory) ·
Sunhing Hung
Kai Tuen Mun Godown (Factory) ·
Tuen Mun EMSD
Servicing Vehicle Station ·
Pillar Point
Fire Station Compensation areas included: Not
required (no adverse air impact is predicted from the Project after
implementation of the mitigation measures). Environmental benefits of environmental
protection measures recommended: The odour
level predicted at the air sensitive receivers would be reduced to an
acceptable level. |
Water Quality Impact |
Population and environmental sensitive
receivers protected: (Refer to
Figure 4.1) ·
Cooling Water
Intakes ·
Fish Culture
Zone ·
Beaches ·
Secondary
Contact Recreation Subzones ·
Site of Special
Scientific Interest (SSSIs) ·
Ramsar Site ·
·
WSD ·
Corals ·
Artificial
Reefs ·
Horseshoe Crab ·
Seagrass ·
Mangrove
Communities ·
Chinese White
Dolphins ·
Mai Po Nature
Reserve Area Compensation areas included: Not
required (no adverse water impact would be resulted from this upgrading
project). Environmental benefits of environmental
protection measures recommended: With dual
power supply and standby facilities as proposed, occurrence of emergency
discharge and the associated water quality impact would be minimized. |
Ecological Impact |
Population and environmental sensitive
receivers protected: Ecological
resources at and near the Project site (refer to Figure 6.1) Compensation areas included: Not
required (no adverse ecological impact would be resulted from this upgrading
project). Environmental benefits of environmental
protection measures recommended: With dual
power supply and standby facilities as proposed, occurrence of emergency
discharge and the associated ecological impact would be minimized. |
Waste Management Implications |
Population and environmental sensitive
receivers protected: Water
quality and air sensitive receivers at or near the Project site, the waste
transportation routes and the waste disposal site. Compensation areas included: Not
required (no adverse waste impact is predicted after implementation of the
mitigation measure). Environmental benefits of environmental
protection measures recommended: Implementation
of the proposed waste control and mitigation measures (refer to Section 7.5 for
details) would avoid the potential water quality, dust and odour impacts
associated with handling, transportation and disposal of the identified
wastes arising from the Project. |
Landscape and Visual Impact |
Population and environmental sensitive
receivers protected: Landscape
resources and visual sensitive receivers near the Project site. Compensation areas included: Trees affected by the
upgrading works will be mitigated through the transplanting of existing trees
and planting of new stock. 81 numbers of “Cassia
surattensis” will be provided as the additional compensatory planting for
loss of greenery in the area due to removal of the affected trees. Environmental benefits of environmental
protection measures recommended: After the proposed mitigation measures have been
implemented and the proposed tree planting has matured over 10 years, it is
anticipated that all residual adverse landscape and visual impacts will be of
insubstantial significance. |