3.         air Quality.. 3-1

3.1       Introduction. 3-1

3.2       Environmental Legislations, Policies, Plans, Standards and Criteria. 3-1

3.3       Description of the Environment 3-2

3.4       Air Sensitive Receivers. 3-2

3.5       Initial Assessment and Control Measures. 3-3

3.6       Prediction and Evaluation of Environmental Impacts. 3-16

3.7       Mitigation of Adverse Environmental Impacts. 3-17

3.8       Evaluation of Residual Impact 3-21

3.9       Environmental Monitoring and Audit 3-21

3.10     Conclusions. 3-21

 

 

List of Tables

 

Table 3.1          Hong Kong Air Quality Objectives

Table 3.2          Background Air Quality

Table 3.3          Details of Representative Air Sensitive Receivers

Table 3.4          Potential Odour Sources of Existing Treatment Facilities

Table 3.5          Potential Odour Sources of New Sewage Treatment Facilities after Upgrading

Table 3.6          Odour Emission Rate of Upgraded PPSTW (Unmitigated)

Table 3.7          Conversion Factors to 5-second Mean Concentration

Table 3.8          Predicted Unmitigated Odour Levels at ASRs after PPSTW Upgrading

Table 3.9          Odour Emission Rate of Upgraded PPSTW (Mitigated)

Table 3.10        Predicted Mitigated Odour levels at ASRs after PPSTW Upgrading

 

 

List of Figures

 

Figure 3.1         Locations of Representative Air Quality Sensitive Receivers

Figure 3.2         Locations of Potential Odour Emission Sources of Pillar Point Sewage Treatment Works

Figure 3.3         Recommended Odour Mitigation Measures

Figure 3.4         Contours of Mitigated Odour Concentration at 25m above ground level

 

 

Appendices

 

Appendix 3-1     Calculation of Odour Emission Rate

 


3.                              air Quality

 

3.1                          Introduction

 

3.1.1.1              This section evaluates the potential air quality and odour impacts that are likely to be generated during the construction and operation phases of the proposed Project. Appropriate mitigation measures were identified, where necessary, to mitigate the potential air quality and odour impacts to acceptable levels.

 

3.2                          Environmental Legislations, Policies, Plans, Standards and Criteria

 

3.2.1.1              The criteria for evaluating air quality impacts and the guidelines for air quality assessment are laid out in Annex 4 and Annex 12 of the EIAO-TM, respectively.

 

3.2.1.2              The Air Pollution Control Ordinance (APCO) provides the statutory authority for controlling air pollutants from a variety of sources.  The Hong Kong Air Quality Objectives (AQOs) should be satisfied at the Hong Kong Special Administrative Region (HKSAR). The AQOs stipulate the maximum allowable concentrations over specific period for typical pollutants.  The relevant AQOs are listed in Table 3.1.

 

Table 3.1               Hong Kong Air Quality Objectives

Pollutant

Maximum Average Concentration (µg m-3) (1)

 

1-Hour (2)

8-Hour (3)

24-Hour (3)

Annual (4)

TSP

-

-

260

80

RSP (5)

-

-

180

55

SO2

800

-

350

80

NO2

300

-

150

80

CO

30,000

10,000

-

-

Note:          (1)     Measured at 298 K and 101.325 kPa.

(2)       Not to be exceeded more than three times per year.

(3)       Not to be exceeded more than once per year.

(4)       Arithmetic mean.

(5)       Suspended particulates in air with a nominal aerodynamic diameter of 10 mm or smaller.

 

3.2.1.3              The EIAO-TM also stipulates that the hourly TSP level should not exceed 500 µgm-3 (measured at 25°C and one atmosphere) for construction dust impact assessment.  Mitigation measures for construction sites have been specified in the Air Pollution Control (Construction Dust) Regulations.

 

3.2.1.4              In accordance with the EIAO-TM, an odour prediction limit of 5 odour units based on an averaging time of 5 seconds at an air sensitive receiver should be met.

 

3.3                          Description of the Environment

 

3.3.1.1              The existing PPSTW is located at the southern coast of the western New Territories.  To the south of the site is the River Trade Terminal at Tuen Mun Area 38. To the west of the site are Green Island Cement Plant and Castle Peak Power Station.   Most of the area surrounding Pillar Point STW is unpopulated.  The proposed site of the upgrading facilities is located within a reserved area next to the existing STW compound, and the surrounding area comprises various government agencies and industrial buildings.  

 

3.3.1.2              The ambient air quality of the site is mainly affected by the emissions from Castle Peak Power Station.  Vehicle exhaust emissions from the local road network also contribute to the ambient air quality of the assessment area.

 

3.3.1.3              As there are no EPD air quality monitoring stations located in the Tuen Mun area, reference has been made to representative data from other monitoring stations.  According to EPD's Guidelines on Assessing the 'Total' Air Quality Impacts, Tuen Mun has an air quality category of "Rural / New Development", which is the same as Yuen Long area.  The background air quality for the assessment area has thus been estimated with reference to five years of monitoring data at EPD’s Yuen Long ambient air quality monitoring station as stated in Air Quality in Hong Kong” (2002 – 2006) as published by EPD.  The background levels of the major air pollutants are summarised in Table 3.2.

 

Table 3.2               Background Air Quality

Pollutants

5-year Annual Average (mg m-3)

Total Suspended Particulates

100

Respirable Suspended Particulates

62

Sulphur Dioxide

24

Nitrogen Dioxide

60

 

 

3.4                          Air Sensitive Receivers

 

3.4.1.1              The assessment area for air quality impact is defined by a distance of 500 m from the boundary of the project as shown in Figure 3.1.  Within the assessment area, representative worst affected Air Sensitive Receivers (ASRs) have been identified for this assessment, in accordance with the criteria stipulated in the EIAO-TM.  Domestic premises, hotel, hostel, hospital, clinic, nursery, temporary housing accommodation, school, educational institution, office, factory, shop, shopping centre, home for the aged and active recreational activity areas are classified as ASRs.  The nearest ASRs in the vicinity of the proposed site within 500m from the site boundary are identified and the locations of these ASRs and their horizontal separation from the site boundary are listed in Table 3.3.  Figure 3.1 shows the locations of the ASRs.

 

3.4.1.2              The air quality impact at 1.5m above local ground level of representative ASRs, which is the average height of the human breathing zone, will be assessed in the study.  Higher assessment levels are also selected for elevated ASRs to show the vertical variation of the pollutant concentrations.  The maximum building heights of the ASRs within 500m from the site boundary are 25m above ground level and therefore it is the maximum assessment height for this study.

 

Table 3.3               Details of Representative Air Sensitive Receivers

ASR I.D.

Description

No. of Floor

Uses

Assessment Height (above ground)

Distance between ASR and plant boundary (1)

A1

River Trade Terminal Office

 

5

Commercial

1.5m, 5m, 10m, 15m, 20m & 25m

80m

A2

Chu Kong Warehouse 1

5

Factory

1.5m, 5m, 10m, 15m, 20m & 25m

180m

A3

Chu Kong Warehouse 2

3

Factory

1.5m, 5m, 10m, 15m, & 20m

150m

A4

Sawmill

1

Factory

1.5m, 5m & 10m

250m

A5

Pillar Point Fire Station

3

GIC

1.5m, 5m, 10m, 15m, & 20m

250m

A6

Sunhing Hung Kai Tuen Mun Godown

3

Factory

1.5m, 5m, 10m, 15m, & 20m

370m

A7

Tuen Mun EMSD Servicing Vehicle Station

1

GIC

1.5m, 5m & 10m

120m

Note :              1.  Distances are measured between ASRs and the nearest boundary of Pillar Point STW.

                        2. The assessment height of each ASR is based on its maximum height.

 

 

3.5                          Initial Assessment and Control Measures

 

3.5.1                    Construction Phase

 

3.5.1.1              Potential dust impacts would be generated from site clearance, excavation, materials handling, concreting operation and wind erosion.  All the construction works would be limited to within the boundary of PPSTW.  The construction works are mainly carried out in the open area (about 32,800 m2) adjacent to the existing PPSTW. There are also new buildings to be constructed inside the existing PPSTW and the total area required for the new buildings would be about 3,710 m2.  Based on the preliminary design, the construction works would create about 61,489 m3 excavated material in total, and the number of trucks hauling on-site depends on the schedule of construction activities.  In accordance with the tentative construction programme, the excavation activities are to be completed within 213 days.  The average volume of excavated materials per day during construction period would be 288 m3.  The average number of trucks (carrying 5m3 excavated materials) required on-site would be about 6 trucks per hour.  As all the trucks would be well covered and the dust suppression measures stipulated in the Air Pollution Control (Construction Dust) Regulation would be applied, and the nearest ASRs is located at least 80m away from the site boundary, it is expected there would be no adverse construction dust impacts on the nearby ASRs.  Qualitative assessment was therefore conducted for the construction of the Project and mitigation measures are recommended to protect ASRs. 

 

3.5.1.2              According to the latest programme and preliminary design, the upgraded PPSTW is scheduled to start commissioning in May 2012.   Phased construction of PPSTW would not be required. During construction of the Project, the existing sewage treatment facilities would not be affected and provision of temporary sewage treatment units would be unnecessary.  Therefore, no additional odour sources would be expected during the construction phase of the Project.

3.5.1.3              It is noted that there are planned developments in the Tuen Mun Area 38, which include Permanent Aviation Fuel Facility and EcoPark.  However, all of the developments are located outside 500m from the PPSTW site boundary.  No other major project is identified to be carried out concurrently in the vicinity of the Project site and within the 500m assessment area.  Cumulative construction dust impacts would not be expected.

 

3.5.2                    Operational Phase

 

Potential Source of Pollutants

 

Existing Pillar Point Sewage Treatment Facilities

 

3.5.2.1              The existing PPSTW was built in the early 1980’s as part of the development planning for the new town population increasing in the Tuen Mun area. The existing works comprises plant provided under two stages of construction – Stage I in 1980 and Stage II (Phase I) in 1988. The works was originally designed to treat dry weather flows to 192,000 m3/day in Stage I. In the late 1980’s the works was subsequently designed and extended to treat dry weather flows of 246,000 m3/day under the Stage II (Phase I) Programme.

 

3.5.2.2              The existing PPSTW is a preliminary treatment plant. Existing major facilities comprise inlet screw pumps, coarse screens, aerated grit channels, fine screens, and outfall screw pumps. The preliminary treated effluent is discharged into the Urmston Road tidal stream through a 2,000m long twin 1,500mm diameter outfall with an approximate capacity of 6.66 m3/s. There is also a 700m long 2,100mm diameter emergency outfall next to the twin outfall. Figures 2.3 and 2.4 show the preliminary layout plan of the upgraded PPSTW and the process flow diagram.  In accordance with the preliminary design, the design sewage flow of the upgraded PPSTW is 6.04m3/s. The individual treatment facilities are described as follows. 

 

Inlet Pumping Station

 

3.5.2.3              A 2,100 mm diameter pipe delivers sewage flows to inlet / bypass chamber. The flows then divert into the Stage I and Stage II screw pumping station (or the emergency bypass outfall).  Three 2.9 m diameter screw pumps (2 duty + 1 standby), each with a maximum capacity of 143,856 m3/d were installed and commissioned under the Stage I Works in 1982. Two with identical capacity to those installed under Stage II Works.  The existing capacity should be able to handle the ultimate flow of 6.04 m3/s.  In total, there are five 2.9 m diameter screw pumps (4 duty + 1 standby), which provide a total capacity of 575,425 m3/d (6.66 m3/s). The existing capacity should be able to handle the ultimate flow of 6.04 m3/s.

 

3.5.2.4              According to the site observation, all five existing screw pumps have been covered.  The odour emission sources include the exposed areas with sewage or sludge of the inlet chambers / influent channel to coarse screens.  All the exposed area with sewage or sludge of the inlet chambers / influent channel would be covered in the preliminary design.  The vented air from the inlet chambers / influent channel, screw pumps and wet wells of the inlet pumping station would be discharged into the atmosphere via two deodourizing units (OD1 and OD2). 

 

 

 

Coarse Screens

 

3.5.2.5              Outlet channels from both Stage I and Stage II pumping stations are connected such that flow can be directed to both Stage I Screens and Stage II Screens. Stage I and Stage II screens are installed mechanical raked 2.5m wide coarse screens with 18mm bar spaces. At present, all four mechanical screens are configured to duty unit with one screen acting as standby. The design capacity of 6.66 m3/s is adequate to handle the ultimate flow of 6.04 m3/s. All screenings from all five screens are currently directed to the solids handling building.

 

3.5.2.6              The existing coarse screens are partially enclosed.  Potential odour emissions would be expected from some exposed area with sewage or screens of coarse screen. Based on the preliminary design, all the coarse screens would be completely enclosed and the vented air from the coarse screens would be discharged into the atmosphere via two deodourizing units (OD1 and OD2).

 

Aerated Grit Channels

 

3.5.2.7              There are four aerated grit channels (3 duty + 1 standby) at the existing PPSTW.  Two units were installed under the Stage I while two units were installed under the Stage II.  A common flow channel connects the coarse screens and the two pairs of aerated grit channels. The size of each grit channel is 14m x 5.7m wide x 3.8m depth.  A common main transfers grit from each of the air lift pumps to the solids handling building.

 

3.5.2.8              Each aerated grit channel has capacity of 1.94 m3/s. They are installed and operated as 3 duty and 1 standby which provide a total capacity of 502,848 m3/d (5.82 m3/s). As such, additional one unit of aerated grit channel would be constructed to cater for the projected flow of 6.04m3/s.

 

3.5.2.9              Two air lift pumps are installed in each aerated grit channel nos. 1 and 2, and three air lift pumps are installed in each aerated grit channel nos. 3 and 4. Air lift pumps, with each design capacity of 24 L/s, are used to remove grits from the grit channels.  All air lift pumps are enclosed.

 

3.5.2.10          As all aerated grit channels as well as the common flow channel are not covered, they would be potential odour sources in the STW. Therefore, all the exposed area with sewage or grits of the aerated grit channels and the common flow channel would be covered in the preliminary design. The vented air from all aerated grit channels and the common flow channel would be discharged into the atmosphere via two deodourizing units (OD1 and OD2). 

 

Fine Screens

 

3.5.2.11          There are four bar screens (3 duty + 1 standby) with a total capacity up to 5.79 m3/s (1.93 m3/s each) at the existing PPSTW.  The extension of existing fine screens is found to be not necessary by increasing the velocity across the screens from 1.0m/s to 1.04m/s. The bars are mechanically raked and the screenings are fed into a hopper and then into a screening press for dewatering. The screenings are then transferred to the sludge holding building through a series of screw conveyors.

 

3.5.2.12          All existing fine screens, the hopper and screening press have been enclosed except minor exposed area with sewage or screens at fine screens.  The possible emission sources would be the exposed areas with sewage or screens at fine screens and also the common flow channel after the fine screens. Therefore, all the exposed area with sewage or screens of fine screens and common flow channel would be covered in the preliminary design. The vented air from the covered areas of these facilities would be discharged into the atmosphere via two deodourizing units (OD1 and OD2). 

 

Solids Handling Building

 

3.5.2.13          The solids handling building (SHB) houses the main control panel for sewage solids removal processes. There are 4 nos. (3 duty and 1 standby) grit classifiers inside the SHB for dewatering grit removed from the aerated grit channels. Grit is fed to each classifier through a ductile iron main. A series of screw conveyors are also located within the SHB.  All the screw conveyors are fed separately from the coarse and fine screenings removal processes. The screenings and grit are fed into a skip for disposal.

 

3.5.2.14          The storage area of grits/screening and dewatering facilities including grit classifiers are located inside the SHB.  Deodourizing chemical is currently used in the SHB as a odour control measure, which is found to be effective.  Nevertheless, this existing odour control measure would not be taken into account in the air quality modelling in order to assess the need of odour control measures for SHB and/or to provide flexibility for the future DBO Contractor to consider their own odour control measures. In this assessment, the odour emission from the screenings and grits and dewatering facilities inside the SHB would be assumed to be released into the atmosphere via two deodourizing units (OD1 and OD2).   

 

Outfall Pumping Station

 

3.5.2.15          In the existing operation, the treated sewage from the fine screen is diverted into the outfall pumping station.  After upgrading, the treated sewage from UV contact tank would be diverted into the outfall pumping station.  The outfall pumping station is equipped with four fully covered Archimedean screw pumps actuated penstocks, level control, control panel and switchgear together with a separate power supply to that of the PPSTW.  The Archimedean screw pumps are operated at 3 duty and 1 standby mode with the maximum capacity of 6.66 m3/s.  All screw pumps have been covered.  Based on the preliminary design, the inlet chamber before outfall pumping station would be covered and the vented air from the inlet chamber, screw pumps and wet wells of outfall pumping stations would be discharged to the atmosphere via two deodourizing units (OD1 and OD2).

 

Septic Waste Reception Facility

 

3.5.2.16          Currently, there is septic waste reception facility at the inlet chamber of the Inlet Pumping Station of the PPSTW. The septic waste is delivered by road tankers and discharged into the inlet chamber.  The existing septic waste reception facility will be decommissioned and another new septic waste reception facility would be provided and located next to the UV contact tanks in accordance with the preliminary design.  During the operation, the septic waste is to be unloaded via a duct connecting the road tanker and the septic waste receiving equipment, which is installed inside a confined area.  Air inside the confined area would be extracted to centralized odour control plants.  The tank for containing septic waste is well isolated from the environment even in the unloading process, as such, the potential odour impact arising from the septic waste facility as well as the road tankers would be remote.  

 

New Sewage Treatment Facilities after Upgrading Pillar Point STW

 

3.5.2.17          Based on the preliminary design, a chemical enhanced primary treatment (CEPT) process and disinfection would be provided for sewage treatment in the upgraded PPSTW. 

 

3.5.2.18          The individual new treatment facilities proposed in the upgraded STW are described as follows.

 

Low Lift & Returns Pumping Station, Flash Mixing Tanks and Flocculation Tanks

 

3.5.2.19          After the upstream existing preliminary treatment (screening processes), the flow would be distributed to the flash mixing tanks after the addition of coagulant and then the flow would be distributed to the flocculation tanks after the addition of polymer.  There are four flash mixing tanks and two flocculation tanks to be provided and operated in the upgraded PPSTW.  The turbulence created by the coagulation and flocculation systems would lead to odour emissions.  Therefore, all the tanks would be covered in the preliminary design.  The vented air from these tanks as well as low lift and returns pumping station would be discharged into the atmosphere via two deodourizing units (OD1 and OD2). 

 

Sedimentation Tanks

 

3.5.2.20          After flocculation process, the sewage would divert into the sedimentation tanks.  There would be nine sedimentation tanks. In the primary sedimentation tanks, the turbulence resulting from the flow over weirs and evaporative losses from quiescent liquid surfaces of the tanks would be the main source of odour emission.  Based on the preliminary design, the weir areas and effluent channel of sedimentation tanks would be enclosed and the vented air would be treated in the two deodourizing units (OD1 & OD2).  

 

UV Contact Tanks

 

3.5.2.21          After the CEPT process, the effluent would flow to the UV disinfection facilities for disinfection.  The UV disinfection facilities would include one fine screen influent channel, four fine screens, two UV contact tank influent channels, ten UV contact tanks and one UV contact tank effluent channel.  Based on the preliminary design, the exposed area with sewage of UV contact tanks and fine screens (including all influent & effluent channels) of UV disinfection facilities would be enclosed and the vented air would be treated in two deodourizing units (OD3 & OD4). 

  

Sludge Pumping Station and Sludge Holding Tanks

 

3.5.2.22          The sludge and scrum removed from the sedimentation tanks would be pumped into the sludge holding tanks via sludge pumping station. There are three sludge holding tanks to be operated in the upgraded PPSTW.  Based on the preliminary design, the sludge pumping station and all the sludge holding tanks would be enclosed and the ventilated air would be treated in the two deodourizing units (OD3 & OD4) before releasing into the atmosphere.

 

Sludge Dewatering Building and Return Liquor Pumping Station

 

3.5.2.23          At the sludge dewatering building, sludge materials are fed into the centrifuges in enclosed pipes and then fed into the hopper after dewatering.  The extracted liquor would be pumped into the intermediate low lift and returns pumping station via the return liquor pumping station.  The dewatered sludge would be stored temporarily in the sludge containers and would be disposed at landfill site everyday.  Both the centrifuge feed pumps and the sludge containers would be enclosed with sealed covers.  The odour generated from the hopper would be a potential odour source.  The vented air would release to the atmosphere via two deodourizing units (OD3 and OD4) in accordance with preliminary design. 

 

Sludge/Septic Waste Reception Area

 

3.5.2.24          In the preliminary design of the upgraded PPSTW, pre-treatment of septic waste is recommended. The function of the pre-treatment is mainly for suspended solids and grits removal. In the preliminary design, there would be some automatic, self-operating septage receiving station for receiving septic waste. After the grit removal, the liquid fraction of septic waste would be discharged into the sludge pumping station for well mixing prior to discharging into the sludge holding tanks. Basically, the septic waste receiving station is an enclosed system.  The vented air would release to the atmosphere via two deodourizing units (OD3 and OD4).

 

Odour Control Units

 

3.5.2.25          In the preliminary design, the two deodourizing units (OD1 and OD2) provided for the solids handling building (SHB) would also be used to treat the vented air from the covered odour source areas of the inlet pumping station, coarse screens, aerated grit channels, fine screens, common flow channels, outfall pumping station, flash mixing tanks, flocculation tanks, low lift and returns pumping station, weir area and effluent channel of sedimentation tanks.  Another deodourizing units would be provided for treatment of vented air from the sludge pumping station, raw sludge holding tanks, sludge dewatering building, return liquor pumping station, centrifuge, septic waste reception facility, UV contact tanks and fine screens (including all influent & effluent channels) of UV disinfection facilities.  The treated air will be discharged into the atmosphere via two deodourizing units (OD3 & OD4).  The odour removal efficiency of all the deodourizing units is 90%, which is considered common and practically achievable. 

 

3.5.2.26          Potential sources of odour for different sewage treatment facilities at the PPSTW were identified.  With reference to Sections 3.5.2.3 to 3.5.2.25 above, apart from the exposed quiescent zone of the sedimentation tanks, all the exposed areas ([1]) with sewage or sludge of the upgraded PPSTW would be covered with providing deodourizing units in the preliminary design.  The identified potential odour sources for existing and planned sewage treatment facilities are summarized in Tables 3.4 and 3.5, respectively.    Layouts of the existing and upgraded treatment facilities are shown in Figures 2.3 and 3.2, respectively.  The odour sources considered in the model would represent the worst-case scenario in view of the operation process of the STW.

 

Table 3.4               Potential Odour Sources of Existing Treatment Facilities

Process

Potential Odour Source

Source ID

Odour Control Measures in the Design

Odour Source considered in the assessment

Inlet Pumping Station

·         Inlet Chambers/Influent Channel

·         Screw Pumps

·         Wet Wells

 

-

Fully enclosed, foul air would release to atmosphere via the deodourizing units

Outlet of vent pipes from the deodourizing units (OD1&OD2)

 

Coarse Screens

·         Coarse Screens

·         Common Flow Channel

-

Aerated Grit Channels

·         Aerated Grit Channels

·         Common Flow Channel

-

Fine Screens

·         Fine Screens

·         Common Flow Channel after Fine Screens

-

Solid Handling Building (a)

·         Solid Handling Building

 

-

Outfall Pumping Station

·         Inlet Chambers

·         Screw Pumps

·         Wet Wells

 

-

Remarks (a) : The existing odour control measure by adding chemicals would not be taken into account in the air quality modeling.

 

 

 

Table 3.5               Potential Odour Sources of New Sewage Treatment Facilities after Upgrading

Process

Potential Odour Source

Source ID

Odour Control Measures in the Design

Odour Source considered in the assessment

Coagulation  & Flocculation

4 nos. Flash Mixing Tanks and 2 nos. Flocculation Tanks

 

-

Fully enclosed, foul air would release to atmosphere via the deodourizing units

 

Outlet of vent pipes from the deodourizing units (OD1&OD2)

Low Lift and Returns Pumping Station

Wet well

-

Sedimentation

9 nos. Sedimentation tanks (Weir Area) and effluent channel for sedimentation tank

-

Sedimentation

9 nos. Sedimentation tanks (Quiescent Zone)

PR02

None

Open area of the operated tanks

Disinfection Facilities

1 no. Fine Screen Influent Channel

-

 

 

 

 

 

Fully enclosed, and foul air via deodourizing units release to atmosphere

 

 

 

 

 

Emission source from the outlet of vent pipes of the deodourizing units (OD3 & OD4)

4 nos. Fine Screens

-

2 nos. UV Contact Tank Influent Channel

-

10 nos. UV Contact Tanks

-

1 nos. UV Contact Tank Effluent Channel

-

Sludge Treatment

Sludge Pumping Station

-

3 nos. Sludge Holding Tanks

-

Sludge Dewatering Building

 

Return Liquor Pumping Station

-

Sludge/Septic Waste Reception Area

 

Sludge/Septic Waste Reception Area

-

 

 


Deviation of Odour Emission Rates

 

Inlet Chambers/Influent Channel, Screw Pumps & Wet Wells of Inlet Pumping Station

 

3.5.2.27          The odour emission rates of raw sewage at inlet works including inlet chamber/inlet channel, screw pumps and wet wells of inlet pumping station in the study were derived from empirical equation developed by Shahalem([2]).  This equation was established from the laboratory results which indicated that the odour intensity of raw sewage at wet well was found to be a function of sewage temperature and oxidation-reduction potential (ORP).  Therefore, it is appropriate to use this equation to determine the odour emission rates of the facilities at inlet works.  The equation has been employed under various approved EIA Studies of STW in Hong Kong, such as EIA of the Tung Chung Main Sewage Pumping Station, Outlying Islands Sewerage Stage 1 Phase I - EIA Study, and Sha Tin Sewage Treatment Works, Stage III Extension, EIA Study.

DF = 1.6 x (T/10) 4.9 x (ORP + 200) –0.59

E = DF x A x (V/3600)

where               DF       =          odour concentration, ou m-3

                        T          =          temperature of sewage, oF

                        ORP     =          oxidation-reduction potential of sewage, mV

                        E          =          odour emission rate, ou s-1

                        A          =          air volume of the emission source, m3

                        V          =          ventilation rate, air changes per hour

                       

3.5.2.28          The ORP depends on the strength and retention time of sewage, and varies from 50 mV for septic sewage to 200 mV for fresh sewage.  The sewage leading to the PPSTW is located close to the pumping station with short retention time (less than 2 hours).  Anaerobic conditions would not be expected, and ORP of semi-fresh sewage 150 mV, was assumed in the model.  Referring to the measurement data at the STWs in summer season, the temperature of sewage was not higher than 30 oC, therefore, the temperature of sewage was assumed to be 30 oC (86 oF) as a worst case scenario in the assessment. In addition, the following parameters, which were adopted in the Outlying Islands Sewerage Stage 1 Phase 1 EIA Study for similar facilities, was employed for this odour assessment.

A          =          1.0 m x surface area of tanks, (for sources confined in cover areas/buildings)

V          =          5 air changes per hour

 

Coarse Screens & Fine Screens

 

3.5.2.29          The large particles in sewage would be removed in the coarse screen and fine screen facilities.  It is expected that the strength of the sewage at coarse screen and fine screen facilities would be similar to or less than that at inlet works.  The equation (Section 3.5.2.27) developed by Shahalem is still applicable for determination of odour emission rates of sewage at coarse screens and fine screens.

 

Aerated Grit Channel, Wet Well of Low Lift and Returns Pumping Station, Flash Mixing and Flocculation Tanks

 

3.5.2.30          It is expected that the sewage after passing the screening facilities would have a lower odour strength comparing with that at inlet works.  As a conservative approach, the Shahalem’s equation (Section 3.5.2.27) was still adopted for the determination of the odour emission rates of sewage in Aeration Grit Channel, Wet Well of Low Lift and Returns Pumping Station, Flash Mixing Tanks and Flocculation Tanks. As the time for screening processes is short, the ORP of sewage at these facilities are assumed to be similar to the condition of sewage at inlet works.

 

Solid Handling Building

 

3.5.2.31          The potential odour sources in Solid Handling Building are temporary storage area of the grits/screens.  There is no empirical formula appropriate to estimate odour concentration of grits/screens.  To determine the odour emission of grits/screens, measured odour concentration of grits/screens produced at similar process of STWs was adopted in the assessment.  Regarding the adoption of appropriate odour concentration of grits/screens in the assessment, the characteristics of influent, the treatment method and the availability of measured odour concentration have been taken into consideration.  It is considered that the influent to both the PPSTW and the SCISTW is mainly domestic, and the flow process and treatment method to be adopted for the proposed upgraded PPSTW and the SCISTW are identical.  The odour characteristics of the screens/grits are also considered similar.  As such, the odour concentration of the grits/screens measured at SCISTW, which is 6,595 oum-3 (This is the maximum value measured in a four-day grits/screens odour measurement exercise at SCISTW. 

 

3.5.2.32          The average daytime temperature in the odour surveys at SCISTW was 29°C.  In accordance with Year 2005 to 2007 meteorological data from the Hong Kong Observatory, the mean daily maximum ambient temperature in the summer (June – September) were in the range of 29 to 33°C.   With reference to the Hydrogen Sulphide Control Manual (Technological Standing Committee on Hydrogen Sulphide Corrosion in Sewage Works, 1989), the equation below presented by Pomeroy and Parkurst was taken to estimate the variation of odour emissions due to temperature changes:

 

G = M[BOD5]1.07T-20

where               G                     =          sulphide flux

                        [BOD5]           =          5-day biochemical oxygen demand

                        T                      =          Temperature °C

                        M                     =          coefficient, m/h

 

3.5.2.33          Based on the above equation, .the sulphide flux increased by about 31% when temperature increased from 29 to 33°C.  Therefore, 31% increase or a 1.31 correction factor was applied in the odour emission rate which was calculated based on the measurement data from the SCISTW to estimate the worst case odour emission.  In accordance with the detailed design, the air exchange rate of solid handling house is 15 air change/hr.

    

Primary Sedimentation Tanks

 

3.5.2.34          The emission of odorous gas from the primary sedimentation tank is highly dependent on the turbulence at the water’s surface. Odour release at rectangular sedimentation tank occurs mostly at the settled sewage overflow weir and channels.  Odour emission from the top-water horizontal surface, quiescent zone, is also expected but with a lesser odour strength.   The equations below were adopted for calculation of odour emission rates for the weir area and quiescent zone developed by Stuetz & Frechen([3]) and  J Hobson([4]).  The OP value for primary sedimentation tank is 3305 ou/m3 based on the Sewage Treatment Odour Production (STOP) Model.

 

E weir = 7.16 x 10-4 x OP x Fweir x h x KpH

where               E weir     = odour emission rate per unit length of weir, ou/s/m

                        OP       = odour potential of the liquid flowing over the weir, ou/m3

                        Fweir     = weir loading rate, m2/h

                        h          = height of drop of liquid flow at weir, m

                        KpH      = pH correction coefficient, take a value of 1.17 at pH7.

 

Eton = 4 x 10-3 (0.0103 V wind1.42 +2.93 Vliquid) OP

where   Eton      = surface emissions of quiescent zone, ou m-2 s-1

            OP       = odour potential, ou m-3

            Vwind     = wind speed on surface of tank, m s-1

            Vliquid    = velocity of liquid across the tank, m s-1

 

Sedimentation Tank Effluent Channel, Fine Screen of UV Disinfection Facilities, UV Contact Tank Influent Channel, UV Contact Tanks, UV Contact Tank Effluent Channel, Inlet Chamber & Screw Pumps & Wet Wells of Outfall Pumping Station  

 

3.5.2.35          In view of the top-water surface of the above facilities is quiescent condition, the odour emission from the above sewage treatment facilities of PPSTW were therefore calculated based on the empirical formula developed by J Hobson.  

Eton = 4 x 10-3 (0.0103 V wind1.42 +2.93 Vliquid) OP

where   Eton      =          surface emissions (ou m-2s-1)

            OP       =          odour potential (ou m-3)

            Vwind     =          wind speed on surface of tank (m s-1)

            Vliquid    =          velocity of liquid across the tank (m s-1)

3.5.2.36          After the sedimentation process, the odour potential of the effluent in the sedimentation tank effluent  channel, fine screen of UV disinfection facilities, UV contact tank influent channel, UV contact tank, UV contact tank effluent channel and inlet chamber, screw pumps and wet wells of outfall pumping station would decrease. However, the exact odour potential values of these treatment facilities are not available, as a conservative approach, the odour potential of sewage of these facilities was still assumed to be 3305 ou m-3, similar to the odour potential of sewage at primary sedimentation tank.

 

Sludge Pumping Station, Raw Sludge Holding Tanks, Return Liquor Pumping Station, Sludge Dewatering Building, Centrifuge & Sludge/Septic Waste Reception Area

 

3.5.2.37          There is no empirical formula appropriate to estimate odour concentration of fresh dewatered sludge.  To determine the odour emission of sludge handling facilities, including sludge pumping station, raw sludge holding tanks, return liquor pumping station, sludge dewatering building, and centrifuge and sludge/septic waste reception area, it considered appropriate to adopt measured odour concentration of fresh dewatered sludge produced at sewage treatment works using CEPT process. Currently, there are several existing sewage treatment works using CEPT process, including Siu Ho Wan STW, Sham Tseng STW, Cyperport STW and SCISTW.  Regarding the adoption of appropriate odour concentration of fresh dewatered sludge in the assessment, the characteristics of influent, the treatment method and the availability of measured odour concentration have been taken into consideration.  It is considered that the influent to both the PPSTW and the SCISTW is mainly domestic, and the operation of the SCISTW is in full swing.  In addition, the sludge treatment method to be adopted for the proposed upgraded PPSTW and the SCISTW is identical, i.e. temporary stored in sludge holding tanks and then dewatered by centrifuge, the odour emitted during the sludge treatment process and the odour characteristics of the dewatered sludge are also considered similar.  As such, the odour concentration of the fresh dewatered sludge measured at SCISTW, which is 7,603 ou m-3 (This is the maximum value measured in a four-day sludge odour measurement exercise at SCISTW. The ambient temperature with this measured value is 31oC.), is considered appropriate to be assumed as the odour concentration of the fresh dewatered sludge at the upgraded PPSTW.

 

For the odour emission rate of the Sludge Pumping Station, Raw Sludge Holding Tanks, Return Liquor Pumping Station, Sludge Dewatering Building, Centrifuge and Sludge/Septic Waste Reception Area of the upgraded PPSTW, the following theoretical formula is used in the assessment:

 

E = DF x A x (V/3600)

where DF    =    measured odour concentration, ou m-3 of fresh dewatered sludge  (i.e. 7,603 ou m-3)

              E    =    odour emission rate, ou s-1

              A    =    air volume of the emission source, m3

              V    =    ventilation rate, air changes per hour

        

3.5.2.38          As the odour emission rate is calculated based on the measurement data from SCISTW, a correction factor for temperature change as mentioned in Section 3.5.2.32 - 3.5.2.33 was applied to estimate the worst case odour emission rate.

 

3.5.2.39          The odour emission parameters for the upgraded PPSTW to be considered in the model, which would be the worst-case scenario, are summarised in Table 3.6.  Detailed calculations of the emission rates are shown in Appendix 3.1.  The locations of emission sources at upgraded PPSTW are indicated in Figure 3.2.

 

Table 3.6               Odour Emission Rate of Upgraded PPSTW (Unmitigated)

Emission Source

Source ID

No. of unit operated

Exposed Surface Area (m2) (a)

Stack Height above ground (m)

Odour Emission Rate

Two deodourizing units with two vent pipes next to low lift and returns pumping station (The vented air from the inlet  chambers/influent channel & screw pumps & wet wells of inlet pumping station, coarse screens, aerated grit channels, fine screens, common flow channels, inlet chamber & screw pumps & wet wells of outfall pumping station, solid handling building, wet well of the low lift and returns pumping station, flash mixing tanks, flocculation tanks, weir zone of sedimentation tank and sedimentation tank effluent channel would be treated before release to the atmosphere. )

OD1 & OD2 (b)

-

-

6.58

1787.95ou s-1

(total emission from both vent pipes)

Sedimentation

Tanks -

(Quiescent Zone)

PR02

9

6210

1.8

2.065x10-2 ou m-2 s-1  (c)

Two deodourizing units with two vent pipes next to septic waste reception area (The vented air from sludge/septic waste reception area, sludge holding tanks, sludge pumping station, return liquor pumping station, sludge dewatering building, centrifuge, UV disinfection facilities would be treated before release to the atmosphere)

OD3 & OD4 (b)

-

-

6.81

1879.05 ou s-1

(total emission from both vent pipes)

(a)     Exposed area with sewage or sludge of all units

(b)     Point source

(c)     Maximum odour emission rate is selected for assessment, details refer to Appendix 3.1

Dispersion Model

 

3.5.2.40          Air quality impacts of odour on ASRs would be modelled with the air dispersion model, AUSPLUME.  Hourly meteorological data for the year 2005 (including wind speed, wind direction, air temperature, Pasquill stability class and mixing height) of the Tuen Mun Weather Station would be employed for the model run.

 

3.5.2.41          The modelled hourly odour concentrations at the ASRs would be converted into the 5-second odour concentration by the methodology proposed by Duffee et al.([5]) and Keddie([6]).  In addition, Turner([7]) has identified that the Pasquill-Gifford vertical dispersion parameter used in the ISC3 model is around 3 to 10 minutes.  As a conservative assumption, the hourly average estimated by AUSPLUME model is assumed as 15 minutes, and the conversion factors for the predicted 1-hour averaged concentration of odour at the receivers would be adjusted to 5-second averaging time by the values shown in Table 3.7.

 

Table 3.7               Conversion Factors to 5-second Mean Concentration

Pasquill Stability Class

Conversion Factor

15 min to 3 min

3 min to 5 sec

Overall

A

2.23

10

22.3

B

2.23

10

22.3

C

1.7

5

8.5

D

1.38

5

6.9

E

1.31

5

6.55

F

1.31

5

6.55

 

3.5.2.42          Higher topographical relief (50m – 100m above ground) is found to the north of the Pillar Point STW.  Mid-rise developments are found to the east, south and west of the STW. Surface roughness of the study is estimated to be 100 cm.  

 

3.6                          Prediction and Evaluation of Environmental Impacts

 

3.6.1                    Construction Phase

 

3.6.1.1              Given that construction works are controlled by the Air Pollution Control (Construction Dust) Regulation and mitigation measures such as watering are required under the regulation to limit dust emission, no adverse construction dust impacts at the ASRs is expected.  Typical dust control measures are presented in Section 3.7.   

 

3.6.2                    Operational Phase

 

3.6.2.1              Odour levels at the ASRs have been predicted based on the preliminary upgrading design of PPSTW.  The unmitigated results are shown in Table 3.8.


Table 3.8               Predicted Unmitigated Odour Levels at ASRs after PPSTW Upgrading

  ASR

Description

Odour level (5 seconds average) (ou) at different height

1.5 m

5m

10 m

15m

20 m

25 m

A1

River Trade Terminal Office

2.7

2.7

2.7

2.9

5.2

8.5

A2

Chu Kong Warehouse 1

1.8

1.8

1.8

1.9

3.5

5.4

A3

Chu Kong Warehouse 2

1.9

1.9

1.9

1.9

3.1

-

A4

Sawmill

1.4

1.4

1.4

-

-

-

A5

Pillar Point Fire Station

1.4

1.3

1.3

1.7

2.6

-

A6

Sunhing Hung Kai Tuen Mun Godown

 

0.9

0.9

1.1

1.5

2.2

-

A7

Tuen Mun EMSD Servicing Vehicle Station

 

3.2

2.6

2.6

-

-

-

(1)                 The odour criterion is 5 ou over five second averaging.

 

3.6.2.2              Modelling results indicated that unmitigated odour levels at some ASRs would exceed the odour criterion of 5 odour units.  Highest odour concentration of 8.5 odour units would be predicted at A1 under the worst-case scenario.  Mitigation measures would be required to protect receivers in the vicinity of the PPSTW.  No other concurrent odour emission is identified within 500m from the project site boundary, therefore, no cumulative odour impact is expected at the ASRs.

 

3.7                          Mitigation of Adverse Environmental Impacts

 

3.7.1                    Construction Phase

 

3.7.1.1              Dust mitigation measures stipulated in the Air Pollution Control (Construction Dust) Regulation should be incorporated to control dust emission from the site.  Control measures relevant to this Project are listed below:

·            skip hoist for material transport should be totally enclosed by impervious sheeting;

·            vehicle washing facilities should be provided at every vehicle exit point;

·            the area where vehicle washing takes place and the section of the road between the washing facilities and the exit point should be paved with concrete, bituminous materials or hardcore;

·            where a site boundary adjoins a road, streets or other areas accessible to the public, hoarding of not less than 2.4 m high from ground level should be provided along the entire length except for a site entrance or exit;

·            every main haul road should be paved with concrete and kept clear of dusty materials or sprayed with water so as to maintain the entire road surface wet;

·            the portion of road leading only to a construction site that is within 30 m of a designated vehicle entrance or exit should be kept clear of dusty materials;

·            every stock of more than 20 bags of cement should be covered entirely by impervious sheeting placed in an area sheltered on the top and the 3 sides;

·            all dusty materials should be sprayed with water prior to any loading, unloading or transfer operation so as to maintain the dusty materials wet;

·            every vehicle should be washed to remove any dusty materials from its body and wheels before leaving the construction sites;

·            the load of dusty materials carried by vehicles leaving a construction site should be covered entirely by clean impervious sheeting to ensure dusty materials do not leak from the vehicle.

 

3.7.2                    Operation Phase

 

3.7.2.1              The predicted results indicated that the nearest two ASRs would exceed the odour criterion under the worst-case scenario and no other ASRs within the study area would exceed the criterion.  Mitigation measures are required to protect the affected ASRs against odour nuisance. 

 

3.7.2.2              In order to alleviate the odour impact, it is considered to cover the exposed area with sewage or sludge of the quiescent zone of the sedimentation tanks and the vented air would be treated in the deodourizing units located next to the low lift and returns pumping station before discharging into the atmosphere. In view of the increase in the air flow rate of the deodourizing units, the number of deodourizing units increases from two (OD1 & OD2) to three (OD1, OD2 & OD5). The odour removal efficiency of all the deodourizing units would be 90%, which is considered common and practically achievable. 

 

3.7.2.3              With the implementation of the mitigation measure as stated in Section 3.7.2.2 above, all the exposed areas(1) with sewage or sludge of the upgraded PPSTW would be covered with providing deodourizing units in the preliminary design (See Figure 3.3).  The vented air from the inlet pumping station, coarse screens, aerated grit channels, fine screens, common flow channels, outfall pumping station, flash mixing tanks, flocculation tanks, low lift and returns pumping station, weir area and effluent channel of the sedimentation tanks, quiescent zone of the sedimentation tanks and the solids handling building (SHB) would be treated at the three deodourizing units (OD1, OD2 & OD5) next to low lift and returns pumping station before discharging into the atmosphere.  While the vented air from the sludge pumping station, raw sludge holding tanks, sludge dewatering building, return liquor pumping station, sludge/septic waste reception area, UV contact tanks and fine screens (including all influent & effluent channels) of UV disinfection facilities would be treated in the two deodourizing units (OD3 & OD4).  The emission rates for mitigated scenario are summarized in Table 3.9 and the detailed calculation is presented in Appendix 3.1.

 

Table 3.9               Odour Emission Rate of Upgraded PPSTW (Mitigated)

Emission Source

Source ID

Stack Height above ground (m)

Exit Velocity (m/s)

Diameter of the Stack (m)

Odour Emission Rate

 

Three deodourizing unit with three vent pipes next to low lift and returns pumping station.  The vented air from the following covered facilities(1) would be treated before release to the atmosphere.

·      inlet chambers / influent channel, wet wells of inlet pumping station  (IN01-IN04)

·      inlet screw pumps (2)

·      coarse screens (SC01 – SC04)

·      Aerated grit channel (GR01)

·      fine screens (FSC01-FSC05), common flow channels (FSC06)

·      solids handling house,

·      wet well of the low lift and returns pumping station

·      flash mixing tanks including No.1 – No. 4

·      flocculation tanks No 1 & 2

·      weir zone of sedimentation tank and effluent channel (PR01)

·      sedimentation tank (quiescent zone) (PR02)

·      inlet chamber & wet wells of outfall pumping station (OUT01) & screw pumps (2)

OD1, OD2 & OD5

6.81

13.82

1.0

1800.78 ous-1

(total emission from all vent pipes)

Two deodourizing unit with two vent pipes next to septic waste reception area.  The vented air from the following covered facilities(1) would be treated before release to the atmosphere.

·      sludge holding tanks No.1, No2, No3

·      sludge pumping station

·      return liquor pumping station

·      sludge dewatering building & centrifuge

·      sludge/septic waste reception area

·      UV disinfection facilities (FIS01, FIS02, FIS03, UV01, UV02, UV03, UV04, UV05 & UV06)

OD3 & OD4

6.81

14.36

1.0

1879.05ou s-1

(total emission from both vent pipes)

(1)     The locations of covered sewage facilities are indicated in Figure 3.3.

(2)     Existing facility has been covered.

 

3.7.2.4              The predicted odour level at representative ASRs with implementing the mitigation measures as stated in Section 3.7.2.3 above would comply with the EPD criterion of 5 odour units.  The mitigated results are summarized in Table 3.10.  Details of the emission calculation are presented in Appendix 3.1.  Contours of mitigated odour concentration at 25 m above ground (the highest assessment height of the representative ASRs), have been plotted and presented in Figure 3.4.

 

 

Table 3.10             Predicted Mitigated Odour levels at ASRs after PPSTW Upgrading

ASR

Description

Odour level (5 seconds average) (ou) at different height

1.5 m

5m

10 m

15m

20 m

25 m

A1

River Trade Terminal Office

2.0

2.0

2.0

2.1

2.4

4.8

A2

Chu Kong Warehouse 1

1.5

1.5

1.5

1.5

1.6

2.9

A3

Chu Kong Warehouse 2

1.6

1.6

1.6

1.6

1.7

-

A4

Sawmill

1.2

1.2

1.2

-

-

-

A5

Pillar Point Fire Station

1.2

1.2

1.2

1.2

1.6

-

A6

Sunhing Hung Kai Tuen Mun Godown

0.8

0.8

0.8

1.0

1.4

-

A7

Tuen Mun EMSD Servicing Vehicle Station

2.1

2.1

2.1

-

-

-

(1)                 The odour criterion is 5 ou over five second averaging.

 

3.7.2.5              For each odour control plants, there will be one standby deodourizing unit to provide buffer for maintenance or breakdown of one of the duty deodourizing units.  In addition, the practices of good housekeeping for PPSTW listed below should be followed to ameliorate any odour impact from the plant and these standard practices should be included in the PPSTW operator manual.

 

·        Screens should be cleaned regularly to remove any accumulated organic debris

·        Grit and screening transfer systems should be flushed regularly with water to remove organic debris and grit

·        Grit and screened materials should be transferred to closed containers to minimise odour escape

·        Scum and grease collection wells and troughs should be emptied and flushed regularly to prevent putrefaction of accumulated organics

·        Skim and remove floating solids and grease from primary clarifiers regularly

·        Frequent sludge withdrawal from tanks is necessary to prevent the production of gases

·        Sludge cake should be transferred to closed containers

·        Sludge containers should be flushed with water regularly

 

 

3.8                          Evaluation of Residual Impact

 

3.8.1                    Construction Phase

 

3.8.1.1              With the incorporation of Air Pollution Control (Construction Dust) Regulation and EM&A programme, adverse residual dust impact during construction phase is not expected.

 

3.8.2                    Operation Phase

 

3.8.2.1              Air quality at the ASRs has been predicted to satisfy with the odour criteria with the proposed mitigation measures, and adverse residual impact is not expected.  There is no ASR within the area out of the project boundary with exceedance of EIAO-TM odour criterion.

 

3.9                          Environmental Monitoring and Audit

 

3.9.1                    Construction Phase

 

3.9.1.1              With the implementation of mitigation measures stipulated in the Air Pollution Control (Construction Dust) Regulation, dust levels at all ASRs would comply with the dust criteria.  It is recommended that a dust monitoring programme should be implemented during the construction phase to ensure that the dust criteria would be satisfied at the ASRs.  Details of the EM&A requirements are given in the stand-alone EM&A Manual.

 

3.9.2                    Operation Phase

 

3.9.2.1              The predicted air quality at the ASRs would comply with the criteria with the implementation of proposed mitigation measures.  It is recommended that odour patrol should be carried out during the operation phase to ensure that the proposed mitigation measures would be effectively implemented.  Details of monitoring programme are presented in the EM&A Manual.

 

3.10                      Conclusions

 

3.10.1                Construction Phase

 

3.10.1.1          Air quality impact from the construction of the Project has been assessed.  With the implementation of mitigation measures specified in the Air Pollution Control (Construction Dust) Regulation, dust nuisance at ASRs would not be expected.  An EM&A programme is recommended for the construction phase to ensure that the dust criteria would be satisfied at the ASRs.

 

3.10.2                Operation Phase

 

3.10.2.1          Odour emission from the Upgraded PPSTW would be the main concern during the operation phase.  Air dispersion modelling was conducted to simulate the potential odour impacts of the proposed preliminary layout of the Upgraded PPSTW on the ASRs.  With reference to the modelling results as shown in Table 3.8, it is noted that only providing deodourizing units for the treatment of vented air from the covered sewage/sludge treatment facilities (as mentioned in Table 3.4 and Table 3.5) of the upgraded PPSTW except the quiescent zone of sedimentation tanks is not sufficient to make all ASRs below the odour criterion of 5 odour units.  Highest odour concentration of 8.5 odour units is predicted at A1 under the worst-case scenario.  With the implementing the recommended mitigation measure, covering the quiescent zone of sedimentation tanks and providing an additional  deodourizing unit for the treatment of vented air as stated in Section 3.7.2.3, the predicted odour level at representative ASRs would comply with the EPD criterion of 5 odour units. 

 

3.10.2.2          Based on the preliminary design with implementing the mitigation measure, all the exposed areas with sewage or sludge of the upgraded PPSTW would be covered (See Figure 3.3).  The vented air from the inlet pumping station, coarse screens, aerated grit channels, fine screens, common flow channels, outfall pumping station, flash mixing tanks, flocculation tanks, low lift and returns pumping station, weir area and effluent channel of the sedimentation tanks, quiescent zone of the sedimentation tanks and the solids handling building (SHB) would be treated at the three deodourizing units (OD1,OD2 & OD5) next to low lift and returns pumping station before discharging into the atmosphere.  While the vented air from the sludge pumping station, raw sludge holding tanks, sludge dewatering building, return liquor pumping station, septic waste reception area, exposed area with sewage or sludge of UV contact tanks and fine screens (including all influent & effluent channels) of UV disinfection facilities would be treated in the two deodourizing units (OD3 & OD4).  All the deodourizing units are with 90% odour removal efficiency, which is considered common and practically achievable.  Operational odour monitoring is proposed to monitor the effectiveness of recommended mitigation measures.

 



([1]) The exposed areas of sewage treatment facilities include inlet chambers/influent channel of the inlet pumping station, coarse screens, aerated grit channels, fine screens, common flow channels, solid handling house, wet well of the low lift and returns pumping station, rapid mixing tanks, flocculation tanks, weir zone of sedimentation tanks, sedimentation tanks (quiescent zone),  sedimentation tank effluent channel, fine screens of UV disinfection facilities, UV contact tanks, UV contact tank influent and effluent channels, sludge holding tanks, sludge dewatering building, sludge/septic waste reception area, sludge pumping station, return liquor pumping station and inlet chamber of the outfall pumping station of the upgraded PPSTW.

([2])       Shahalam, A. (1982), Scrubbing Odors from Wastewater Treatment, Journal of the Environmental Engineering Division, Proceedings of the ASME, Vol. 108, No. EE4.

([3])    Richard Stuetz and Franz-Bernd Frechen (2001), Odours in Wastewater Treatment Measurement, Modelling and Control, IWA Publishing. 

([4])    Hobson, J. (1995), Emission Rate from Sewage Works, WRc Report PT 1048, Water Research Centre, (unpublished report).

([5])    Richard A. Duffee, Martha A. O”Brien and Ned Ostojic (1991).  Odor Modeling – Why and How, Recent Developments and Current Practices in Odor Regulation, Controls and Technology, Air & Waste Management Association.

([6])     Keddie, A. W. C (1980).  Dispersion of Odours, Odour Control – A Concise Guide, Warren Spring Laboratory.

([7])     Turner, D. (1994).  Workbook of Atmosphere Dispersion Estimates, 2nd Edition, Lewis Publishers.