8. LANDSCAPE AND VISUAL IMPACT
8.3 Review of Planning and Development
Control Framework
8.4 Environmental Legislation and Standards
8.7 Landscape Impact Assessment (LIA)
8.8 Visual Impact Assessment (VIA)
8.9 Recommendation on Landscape and Visual
Mitigation Measures
Table 8.1 Illustration of the Sensitivity of
LRs in Study area
Table 8.2 Identity of key Visual Sensitive
Receivers (VSRs) and Their Sensitivity to Change
Table 8.3 Visual Sensitive Receivers (VSRs) and
Their Magnitude of Impacts
Table 8.6 Proposed Landscape and Visual
Mitigation Measures in Construction Phase
Table 8.7 Proposed Landscape and Visual
Mitigation Measures in Operation Phase
Figure 8.1.1 Existing Aerial Photo
Figure 8.1.2 Planning & Development Framework (OZP)
Figure 8.2.1 Landscape Resource
Figure 8.2.2 Photos of Landscape Resource (sheet 1 of 2)
Figure 8.2.3 Photos of Landscape Resource (sheet 2 of 2)
Figure 8.3.1 Landscape Character Area
Figure 8.3.2 Photos of Landscape Character Area
Figure 8.4.1 Zone of Visual Influence & Visual Sensitive Receivers
Figure 8.4.2 Photos of Visual Sensitive Receivers Group
Figure 8.4.3 View for Visual Sensitive Receivers (sheet 1 of 2)
Figure 8.4.4 View for Visual Sensitive Receivers (sheet 2 of 2)
Figure 8.5.1 Residual Landscape Resource Impacts in Construction Phase
Figure 8.5.2 Residual Landscape Resource Impacts in Operation Phase
Figure 8.5.3 Residual Landscape Character Area Impacts in Operation Phase
Figure 8.5.4 Residual Landscape Character Area Impacts in Construction Phase
Figure 8.5.5 Residual Visual Impacts in Operation Phase
Figure 8.5.6 Residual Visual Impacts in Construction Phase
Figure 8.6.1 Landscape and Visual Mitigation Measures in Operation Phase
Figure 8.7.1 Photomontage – Residual Visual Impact for GIC1
Figure 8.7.2 Photomontage – Residual Visual Impact for OU1
Figure 8.9.1 Location of Transplanted Trees and Additional Compensatory Planting
Figure 8.9.2 Approximate Location of Existing Trees
Figure 8.9.3 Location of Affected Trees and Tree Assessment Schedule
n
Modify and expand the existing aerated grit
channel;
n
Construct chemically enhanced primary treatment
units;
n
Construct sludge treatment units which include sludge
dewatering facilities and sludge holding facilities;
n
Construct UV irradiation disinfection units;
n
Modify and expand the existing septic waste
reception facilities;
n
Provide odour control facilities; and
n
Modify and upgrade the existing ancillary facilities
including administration building, workshop, laboratory and landscaping works.
The dimensions of
all the above-ground structures as listed above are:
New
structures for upgraded PPSTW (Figure 2.3
refers) |
Approximate
dimensions of above-ground structures |
||
Width (m) |
Length
(m) |
Height
(m) |
|
New Transformer Room |
6 |
12 |
5 |
Extension of Air Compressor
House |
5.5 |
5.5 |
4.8 |
New Aerated Grit Channel |
5.5 |
13 |
1.5 |
New Workshop, New Admin.
Building & Lab and Control Room |
14 |
46 |
9 |
New Rapid Mixing Tanks, New
Flocculation Tanks and New Sedimentation Tanks |
85 |
95.5 |
2.5 |
New Odour Control Plant I |
24 |
27 |
7 |
New Low Lift and Pumping
Station |
23.5 |
25 |
7 |
New |
18 |
45.5 |
8 |
Sludge Holding Tank No. 1,
2, 3 |
29 |
38.2 |
17.5 |
New Odour Control Plant II |
16.5 |
27 |
7 |
New Sludge Dewatering
Building |
30 |
31 |
13.5 |
New Sludge / Septic Waste
Reception Area |
15.2 |
29.7 |
6 |
New Return Liquor Pumping
Station |
6.2 |
6.7 |
0.5 |
New Sludge Pumping Station |
7 |
7 |
0.5 |
UV Spares Storage Area |
6 |
16 |
5 |
UV Spares Storage Area |
12 |
13 |
5 |
UV Switchgear and |
6 |
18 |
5 |
|
6 |
18 |
5 |
UV disinfection Facility |
35.3 |
39.4 |
0.5 |
Payment Flowmeter Chamber |
13.4 |
22.3 |
2 |
· Natural and secondary woodland
· Amenity planting
· Scrubland and grassland
· Natural topography
·
Significant planning
designation, e.g.
· Heritage or cultural features
· Land use
· Public use of land
· Extent of vegetation
· Age of landscape
· Cultural, heritage and religious elements
· Scale and type of buildings
· Pattern of settlement
· Location and topography
· Extent of natural vs manmade
Sensitivity |
Definition |
High |
Important components of landscape of particularly
distinctive character susceptible to relatively small changes |
Medium |
A landscape of moderately valued characteristics
reasonably tolerant of change |
Low |
A relatively unimportant landscape, the nature of
which is largely tolerant to change |
Visual Resources
Zone
of Visual Influence/ Visual Envelope(ZVI)
Visually
Sensitive Receivers (VSRs)
·
Value
and quality of existing views, e.g. urban high-rise, natural hills, sea view
·
Presence
and amenity of alternative views
·
Type
and estimated number of receiver population
·
Duration
or frequency of view
·
Degree
of visibility of the proposed project, e.g. no view, glimpse, partial view,
vista, open view, and panorama view)
·
Identification
of the source of impact, their magnitude, that would be generated during
construction and operation of the project; and
·
Identification
of principal impacts, primarily in consideration of the degree of change to the
baseline conditions.
·
Compatibility
of the project with the surrounding landscape
·
Duration
of impacts under construction and operation phases
·
Scale
of the impact
·
Reversibility
of change
Magnitude of Change |
Definition |
Large |
Notable permanent change in
the landscape characteristics over an extensive area ranging to very
intensive changes over a more limited area |
Intermediate |
Moderate changes in a
localised area |
Small |
Virtually imperceptible
change or temporary change |
Negligible |
Virtually no changes in
the area |
·
The
landscape character and its quality
·
The
sensitivity of the landscape in accommodating change
·
Source,
nature and magnitude of potential impacts
·
Construction
and operation phases impacts
·
Degree
of change caused by each of the impacts to the existing LCAs
·
Significance
of this change in the local and regional context and in relation to other
developments
·
Cumulative
effects on the landscape of this and neighbouring projects
|
|
Sensitivity / Quality of the landscape |
||
|
|
Low |
Medium |
High |
Magnitude of Change |
Large |
Slight /
moderate |
Moderate / Substantial |
Substantial |
Intermediate |
Slight /
Moderate |
Moderate |
Moderate / Substantial |
|
Small |
Insubstantial /
Slight |
Slight /
Moderate |
Moderate /
slight |
|
Negligible |
Insubstantial |
Insubstantial |
Insubstantial |
Identification of the Landscape Impact |
Definition |
Adverse |
An impact which will be detrimental to the existing landscape
context |
Beneficial |
An impact which will improve the existing landscape
context |
Neutral |
An impact which will alter the existing landscape
context but not to improve or destroy it |
Impacts |
|
Substantial |
Adverse/beneficial impact where the proposal would
cause significant deterioration or improvement in existing landscape quality |
Moderate |
Adverse/beneficial impact where the proposal would
cause a noticeable deterioration or improvement in existing landscape quality |
Slight |
Adverse/beneficial impact where the proposal would
cause a barely perceptible deterioration or improvement in the existing
landscape quality |
Insubstantial |
No discernible change in the existing landscape
quality |
·
Identification
of the source of visual impacts, their magnitude of change and sensitivity of
the receivers, that would be generated during construction and operation of the
project, and;
·
Identification
of principal visual impacts, primarily in consideration of the degree of change
to the baseline conditions
·
Compatibility
of the proposed project with the surrounding landscape
·
Duration of
impacts during construction and operation stages
·
Scale of
impact and distance of the source of impact from the viewer
·
Reversibility
of impact
·
Potential
blockage of the view
|
|
Sensitivity /
Quality of the Visual Receivers |
||
|
|
Low |
Medium |
High |
Magnitude of Change |
Large |
Moderate |
Moderate / Substantial |
Substantial |
Intermediate |
Slight /
moderate |
Moderate |
Moderate / Substantial |
|
Small |
Slight |
Slight /
Moderate |
Moderate |
|
Negligible |
Insubstantial |
Insubstantial |
Insubstantial |
Identification of
the Visual Impact |
Definition |
Adverse |
An impact which will
be detrimental to the existing views |
Beneficial |
An impact which
will improve the existing views |
Neutral |
An impact which
will alter the existing views but not to improve or destroy it |
Impacts |
|
Substantial |
Adverse/beneficial impact where the proposal would
cause significant deterioration or improvement in existing views |
Moderate |
Adverse/beneficial impact where the proposal would
cause a noticeable deterioration or improvement in existing views |
Slight |
Adverse/beneficial impact where the proposal would
cause a barely perceptible deterioration or improvement in the existing views |
insubstantial |
No discernible change in the existing views |
Identification of Potential Landscape and Visual
Impact Mitigation Measures
Identification of Residual Impacts
LR2 -
Stream Course
LR3 -
Disturbed Hillside
LR4 - Scrubland/
LR5 -
Roadside Planting
LR6 -
Vegetation within existing DSD Sewage Treatment Works
LR7 -
Vegetation within Industrial
Area
LR8 -
Golf Course
Table 8.1 Illustration of the Sensitivity of LRs in Study area
|
Vegetation Feature |
Dominant Tree Species |
Function |
Sensitivity |
LR 1 |
Water Body |
N.A. |
As habitat purpose |
Low |
LR 2 |
Stream course (natural / artificial
channel) |
N.A. |
As habitat purpose |
Medium |
LR 3 |
Disturbed hillside
plantation area |
Casuarina equisetifolia |
As habitat purpose |
Medium |
LR 4 |
Scrubland/ |
- Acacia confusa, Ficus microcarpa, Sapium discolor,
Sapium sebiferum, Mallotus paniculatus, Litsea glutinosa, Celtis sinensis,
Sterculia lanceolata, Casuarina equisetifolia, Musa paradisiaca, Macaranga
tanarius, and other native tree species, etc. |
Public usage |
High |
LR 5 |
Roadside planting |
Delonix regia, Cassia siamea |
Public usage |
medium |
LR 6 |
Vegetation within existing
DSD sewage treatment Works |
343 no of exsting trees are
recorded in general height from 4m to 13m, trunk diameter from 95mm to 300mm
and a spread from 2 to 13; they are mainly Casuarina equisetifolia, Hibiscus trifolia, Ficus elastica, Leucaena
leucocephala |
Public usage |
medium |
LR 7 |
Vegetation within industrial area |
Casuarina equisetifolia, Hibiscus trifolia, Cassia
siamea |
Public usage |
Medium |
LR 8 |
Golf course |
N.A. |
Recreational purpose |
Low |
·
LCA 1 – Transport Corridor Landscape Character Area, which represents
vehicular roads such as Lung Mun Road Highway.
·
LCA 2 – Upland & Hillside Landscape Character Area, which represents all
hillside plantation area, including roadside amenity areas along Lung Mun Road
Highway. It also contains woodlands, scrubland and fresh water body, which
represent the major character of the area.
·
LCA 3 – Inshore Water Landscape Character Area, which represents seawater
body and waterfront character such as breakwaters and seashore at the south of
the River Trade Terminal.
·
LCA 4 – Institutional Landscape Character Area, which represents all
government institutions and public utilities such as existing Pillar Point STW,
EMSD Tuen Mun Vehicular Servicing Station, Harbor Hydraulics Laboratory,
Physical Model Lab Sub-station, Pillar
Point Fire Station and WSD Tuen Mun West Fresh Water Service Reservoir.
·
LCA 5 – Industrial Urban Landscape Character Area, which represents all
industrial zone in the reclaimed area of Ho Fuk Street and Ho Yeung Street such
as River Trade Terminal & cargo handling area.
Table 8.2 Identity of key Visual Sensitive Receivers (VSRs) and Their Sensitivity to Change
|
Key Visual Sensitive Receivers (VSRs) |
Type of VSRs |
Number of Individuals (Many/ Medium/ Few/ Very
Few) |
Quality of Existing View (Good/ Fair/ Poor) |
Availability of Alternative Views (Yes/ No) |
Amenity of Alternative Views (Good/Fair/Poor) |
Degree of Visibility (Full/ Partial/ Glimpse) |
Frequency of View (Very Frequent/ Frequent/
Occasional/ Rare) |
Sensitivity to Change (Low, Medium, High) |
OU1 |
River Trade Terminal &
Cargo Handling Area |
Occupational |
Many |
Fair |
Yes |
Fair |
Full |
Occasional |
Low |
OU2 |
River Trade Golf Course |
Recreational |
Many |
Fair |
Yes |
Fair |
Glimpse |
Rare |
Medium |
OU3 |
Planned Development in Tuen
Mun Area 38 – |
Occupational |
Medium |
Fair |
Yes |
Fair |
Glimpse |
Rare |
Low |
GIC1 |
EMSD Tuen Mun Vehicle
Servicing Station, Harbour Hydraulics Laboratory and Physical Model Lab
Sub-station |
Occupational |
Medium |
Fair |
Yes |
Fair |
Partial |
Rare |
Low |
|
|
|
|
|
|
|
|
|
|
GB1 |
|
Recreational |
Few |
Good |
Yes |
Fair |
Partial |
Rare |
Low |
T1 |
Lung |
Transportation |
Medium |
Fair |
Yes |
Fair |
partial |
Frequent |
Low |
R =
Residential; C = Commercial, GIC = Government/Institution/Community, O = Open space,
OU = Others use; T = Transport related
Table 8.3 Visual Sensitive Receivers (VSRs) and Their Magnitude of Impacts
Id No. |
Key Visual Sensitive Receiver (VSR) |
Blockage of View (Full/ Partial/ Glimpse |
Viewing Distance (M) |
Scale of Development (Large/ Medium/ Small) |
Compatibility (Good/ Fair/ Poor) |
Reversibility of Change (Yes/ No) |
Magnitude of Impacts (Large/ Intermediate/ Small/ Negligible |
|
Construction |
Operation |
|||||||
OU1 |
River Trade Terminal & Cargo
Handling Area |
Partial |
10 |
Large |
Good |
No |
Intermediate |
Intermediate |
OU2 |
River Trade Golf Course |
Glimpse |
150 |
Medium |
Good |
No |
Small |
Small |
OU3 |
Planned Development in Tuen
Mun Area 38 – |
Glimpse |
650 |
Small |
Good |
No |
Negligible |
Negligible |
GIC1 |
EMSD Tuen Mun Vehicle
Servicing Station, Harbour Hydraulics Laboratory and Physical Model Lab
Sub-station |
Glimpse |
25 |
Large |
Good |
No |
Intermediate |
Intermediate |
|
|
|
|
|
|
|
|
|
GB1 |
|
Glimpse |
25 |
Large |
Good |
No |
Intermediate |
Intermediate |
T1 |
Lung |
Glimpse |
10 |
Large |
Good |
No |
Small |
Small |
R = Residential;
C = Commercial, GIC = Government/Institution/Community, O = Open space, OU =
Others use; T = Transport related
Sources
of Landscape and Visual Impacts
§
construction
works involving the removal of existing vegetation;
§
construction
of site access;
§
excavation
works for the sedimentation tank and sludge holding tank;
§
stockpiling
of excavated materials;
§
haulage
off-site of excavated materials
§
stockpiling
of construction materials;
§
importation
and storage of construction equipment and plant;
§
contractor’s
temporary works areas, including site accommodation and parking area;
§
construction
of above ground features such as new administration building, laboratory, and
control room; and
§
night
lighting;
§
new
administration building, laboratory and control room (approximately 8m
height);
§
chemical
storage building and chemical dosing area (approximately 8m height);
§
low lift and returns pumping station / odour
control units (approximately 7m height);
§
rapid mixing tanks, flocculation tanks and
sedimentation tanks (approximately 2.5m height);
§
UV disinfection facilities (approximately 0.5-5m
height);
§
sludge holding tanks (approximately 17.5m height);
§
sludge
dewatering building (approximately 13.5m height);
§
septic waste reception area (approximately 6m height)
Landscape
Impact Assessment
Nature and Magnitude of Landscape Change
Before Mitigation in Construction Phase
LR6-Vegetation within existing sewage treatment plant
There would be a
large change to the existing Pillar Point STW due to the excavation works of the
sedimentation tanks and associated structures, and site access. There are a total approx.
343 trees within the Pillar Point STW. The approximate location of the existing
trees and the broadbrush tree survey results (including the general species
name) are shown in Figure 8.9.2. There would be impacts on approximately 90 numbers of trees,
of which all have a high to low amenity value.
The locations as well as the assessment schedule for the 90 numbers of
the affected trees are shown in Figure 8.9.3. Those affected trees have a height
from 4m to 13m, trunk diameter from 95mm to 300mm and a spread from 2 to 13.
Apart from the 18 numbers of “Leucaena
leucocephala”, which are proposed to be felled in accordance with ETWB TCW
No. 3/2006, all the affected trees are capable of transplanting, although the
largest trees would suffer some loss of form and amenity value during
transplanting process.
Predication of Significance of Landscape Impacts
Operational Phase Landscape Impacts
Table 8.4 Significance of landscape impacts in the construction and operation phases (Note: All impacts adverse unless otherwise noted. Only those resources or character areas that are impacted are listed in the table – resources not impacted are not listed. )
Part 1 – Physical Landscape Resources (Topography, Vegetation, Soil, Open Space, Special Features, etc)
|
Landscape
Resources (LR) |
Sensitivity
to Change (Low,
Medium, High) |
Magnitude
of Change before Mitigation (Negligible,
Small, Intermediate, Large) |
Impact
significance Threshold Before Mitigation (Insubstantial,
Slight, Moderate, Substantial) |
Recommended
Mitigation Measures* |
Residual
Impact Significance Threshold After Mitigation (Insubstantial,
Slight, Moderate, Substantial) |
||||
Construction |
Operation |
Construction |
Operation |
Construction |
Operation |
|||||
DAY 1 |
YEAR 10 |
|||||||||
LR1 |
Water Body |
High |
Negligible |
Negligible |
Insubstantial |
Insubstantial |
N/A |
Insubstantial |
Insubstantial |
Insubstantial |
LR2 |
Stream Course (natural
artificial channel) |
Medium |
Negligible |
Negligible |
Insubstantial |
Insubstantial |
N/A |
Insubstantial |
Insubstantial |
Insubstantial |
LR3 |
Disturbed Hillside |
Medium |
Negligible |
Negligible |
Insubstantial |
Insubstantial |
N/A |
Insubstantial |
Insubstantial |
Insubstantial |
LR4 |
Scrubland / |
High |
Negligible |
Negligible |
Insubstantial |
Insubstantial |
N/A |
Insubstantial |
Insubstantial |
Insubstantial |
LR5 |
Roadside Planting |
Medium |
Negligible |
Negligible |
Insubstantial |
Insubstantial |
N/A |
Insubstantial |
Insubstantial |
Insubstantial |
LR6 |
Vegetation within Existing
DSD Sewage Treatment Works |
Medium |
Intermediate |
Intermediate |
Moderate |
Moderate |
CM1, CM2, CM5, CM6 OM1, OM2, OM3 |
Moderate |
Slight |
Insubstantial |
LR7 |
Vegetation within Industrial
Area |
Medium |
Negligible |
Negligible |
Insubstantial |
Insubstantial |
N/A |
Insubstantial |
Insubstantial |
Insubstantial |
LR8 |
Golf Course |
Low |
Negligible |
Negligible |
Insubstantial |
Insubstantial |
N/A |
Insubstantial |
Insubstantial |
Insubstantial |
* Recommendation on landscape
and visual mitigation measures are described in Section 8.9.
Part 2 – Landscape Character Areas
|
Landscape
Character Area (LCA) |
Sensitivity
to Change (Low,
Medium, High) |
Magnitude
of Change before Mitigation (Negligible,
Small, Intermediate, Large) |
Impact
significance Threshold Before Mitigation (Insubstantial,
Slight, Moderate, Substantial) |
Recommended
Mitigation Measures* |
Residual
Impact Significance Threshold After Mitigation (Insubstantial,
Slight, Moderate, Substantial) |
||||
Construction |
Operation |
Construction |
Operation |
Construction |
Operation |
|||||
DAY 1 |
YEAR 10 |
|||||||||
LCA1 |
Transport Corridor Landscape
Character Area |
Medium |
Negligible |
Negligible |
Insubstantial |
Insubstantial |
N/A |
Insubstantial |
Insubstantial |
Insubstantial |
LCA2 |
Upland & Hillside
Landscape Character Area |
High |
Negligible |
Negligible |
Insubstantial |
Insubstantial |
N/A |
Insubstantial |
Insubstantial |
Insubstantial |
LCA3 |
Inshore Water Landscape
Character Area |
Low |
Negligible |
Negligible |
Insubstantial |
Insubstantial |
N/A |
Insubstantial |
Insubstantial |
Insubstantial |
LCA4 |
Institutional Landscape Character
Area |
Medium |
Negligible |
Negligible |
Insubstantial |
Insubstantial |
CM1, CM2, CM5, CM6 OM1, OM2, OM3 |
Moderate |
Slight |
Insubstantial |
LCA5 |
Industrial Urban Landscape
Character Area |
Low |
Negligible |
Negligible |
Insubstantial |
Insubstantial |
N/A |
Insubstantial |
Insubstantial |
Insubstantial |
* Recommendation on landscape
and visual mitigation measures are described in Section 8.9.
Table 8.5 Significance of visual impacts in the construction and operational phases (Note: All impacts adverse unless otherwise noted. Only those VSRs that are impacted are listed in the table – VSRs not impacted are not listed.)
VSR Type & ID |
Key Visually Sensitive Receiver (VSR) |
Magnitude of Change in View before Mitigation
(negligible, small, intermediate, large) |
Receptor Sensitivity (Low, medium, High) |
Impact significance threshold before mitigation (insubstantial, slight, moderate, substantial) |
Recommended Mitigation Measures* |
Residual Impact Significance Threshold after
Mitigation (insubstantial, slight, moderate, substantial) |
|||||
Construction |
Operation |
Construction |
Operation |
Construction |
Operation |
Construction |
Operation |
||||
DAY 1 |
YEAR 10 |
||||||||||
OU1 |
River
Trade Terminal & Cargo Handling Area |
Intermediate |
Intermediate |
Low |
Low |
Moderate |
Moderate |
CM1, CM3, CM5, CM7, OM2, Om3 |
Moderate |
Slight |
Insubstantial |
OU2 |
River
Trade Golf Course |
Small |
Small |
Medium |
Medium |
Slight |
Slight |
CM1, CM3, CM5, CM7, OM2, Om3 |
Slight |
Insubstantial |
Insubstantial |
OU3 |
Planned Development in Tuen Mun Area 38 – |
Negligible |
Negligible |
Low |
Low |
Insubstantial |
Insubstantial |
CM1, CM3, CM5, CM7, OM2, Om3 |
Insubstantial |
Insubstantial |
Insubstantial |
GIC1 |
EMSD Tuen Mun Vehicle Servicing Station, Harbour
Hydraulics Laboratory and Physical Model Lab Sub-station |
Intermediate |
Intermediate |
Low |
Low |
Moderate |
Moderate |
CM1, CM3, CM5, CM7, OM2, Om3 |
Slight |
Insubstantial |
Insubstantial |
GB1 |
|
Intermediate |
Intermediate |
Low |
Low |
Moderate |
Moderate |
CM1, CM3, CM5, CM7, OM2, Om3 |
Slight |
Insubstantial |
Insubstantial |
T1 |
Lung |
Small |
Small |
Low |
Low |
Slight |
Slight |
CM1, CM3, CM5, CM7, OM2, Om3 |
Slight |
Insubstantial |
Insubstantial |
R =
Residential; C = Commerciall, GIC = Government/Institution/Community, O = Open
space, OU = Others use; T = Transport related
* Recommendation on landscape
and visual mitigation measures are described in Section 8.9.
Table
8.6 Proposed Landscape
and Visual Mitigation Measures in Construction Phase
ID No. |
Nature / Type |
Landscape and Visual Mitigation Measure |
Implementation Agent |
Management/ Maintenance |
CM1 |
Design / construction
Planning |
Temporary
Tree Nurseries Temporary
tree nurseries may be set up for the transplanted tree and proposed trees at
an early stage to allow small trees to grow during the construction periods.
By the time when planting area becomes available, trees mature and increase
in trunk & spread size. They will require minimal pruning and suffer much
less damage during transplanting when comparing the travel distance from an
on-site nursery to an off-site nursery. Besides,
these trees may also be positioned as visual mitigation during the
construction period. Potential
site and locations should sought agreement with relevant department in
advance and avoid doubling transplantation procedure. |
Contractor |
Contractor |
CM2 |
Design / construction
Planning |
No-intrusion
Zone To
maximize protection to existing trees and ground vegetation, construction
contracts may designate “No-intrusion Zone” to various areas within the site
boundary with rigid and durable fencing for each individual no-intrusion
zone. The contractor should close monitor and restrict the site working staff
not to enter the “no-intrusion zone”, even for non-direct construction
activities and storage of equipment. |
Contractor |
Contractor |
CM3 |
Design / construction
Planning |
Hoarding
Hoarding
or boundary fencing for construction shall be considered. It should be
sensitively designed, subtle, camouflaged and more ‘permeable’ so that they
fit into the existing environment when looking from outside. |
Contractor |
Contractor |
CM5 |
Site Practice |
Dust
and Erosion Control for Exposed Soil Excavation
works and demolition of existing building blocks and which will be highly
visible form surrounding areas should be well planned and with precautions to
suppress dust. Exposed soil shall be covered or ‘camouflaged’ and watered
often. Areas that are expected to be left with bare soil for a long period of
time after excavation shall be properly covered with suitable protective
fabric. Silt and erosion shall be controlled by ground barriers around the
slope cutting area. |
Contractor |
Contractor |
CM6 |
Site Supervision |
Existing
Tree Record Inventory All
retained trees should be record photographically at the commencement of the
Contract, and carefully protected during the construction period. Detailed
tree protection specification shall be allowed and included in the Contract
Specification, which specifying the tree protection requirement, submission
and approval system, and the tree monitoring system. |
Contractor |
Contractor |
CM7 |
Site Practice |
Construction
Light All
security floodlights for construction sites shall be equipped with adjustable
shield, frosted diffusers and reflective covers, and be carefully controlled to
minimize light pollution and night-time glare to nearby residences and GIC
users. The Contractor shall consider other security measures which shall
minimize the visual impacts. |
Contractor |
Contractor |
CM8 |
Design / construction
Planning |
Tree
Transplanting Apart
from the 18 numbers of “Leucaena leucocephala”, which are
proposed to be felled in accordance with ETWB TCW No. 3/2006, all the
affected trees shall
be transplanted. Where practicable, trees shall be directly transplanted to
permanent on-site locations. The location of the transplanted tree is shown
in Figure
8.9.1. |
Contractor |
Contractor |
CM9 |
Design / construction
Planning |
Tree
Compensation Ratio The
total number of compensatory trees planted in the project area shall not be
less than 1:1 ratios by new trees. Required numbers and locations of
compensatory trees shall be determined and agreed with Government during the
tree felling application process under ETWCTC 3/2006. Compensatory
trees shall be at least heavy standard size to create “immediate” greening
effect. 81 numbers of “Cassia surattensis” will be provided
as the additional compensatory planting for loss of greenery in the area due
to removal of the affected trees. The location of the additional compensatory
planting is shown in Figure 8.9.1. |
Contractor |
Contractor |
CM10 |
Design / construction
Planning |
Re-use of Existing Soil
and Advance formation of Planting Area Existing topsoil shall be
re-used where possible for new planting areas within the project. Advance
formation of planting area and early implementation of the plating works
can minimize adverse impact on trees. The construction program shall consider
using the soil removed from one phase for backfilling another. Suitable
storage ground, gathering ground and mixing ground may be set up on-site as
necessary. |
Contractor |
Contractor |
Table 8.7 Proposed Landscape and Visual Mitigation Measures in Operation Phase
ID No. |
Nature / Type |
Landscape and Visual Mitigation Measure |
Implementation Agent |
Management/ Maintenance |
OM1 |
Site Supervisions |
Establishment
Period 12
month establishment period for the soft landscape works will be allowed in
the main contract. Most construction contracts in |
PPSTW Operator |
PPSTW Operator |
OM2 |
Design / construction
Planning |
Re-instatement
of excavated Area All
excavated area and disturbed area for utilities diversion, temporary road
diversion, and pipeline woks will be reinstated to former conditions, subject
to applicable Government Standards. |
PPSTW Operator |
PPSTW Operator |
OM3 |
Design / construction Planning
|
Appearance
and Greening for the proposed structures Compatible
design, construction materials and surface finishes of the proposed structure
should match with the nearby existing external appearance of PPSTW buildings
for achieving visual uniformity.
Finishing materials shall have due consideration to form, basic color,
color/tone variation, micro- and macro-texture, and reflectivity/light
absorbance to avoid glare. Planting,
such as turf, low groundcovers and climbers, may also be planted on top of
these elements to provide greening and aesthetic effect. |
PPSTW Operator |
PPSTW Operator |
Summary of
Predicated Residual Landscape and Visual Impacts in the Construction Phase
Summary of
Predicated Residual Landscape and Visual Impacts in the Operational Phase