1.4 ENVIRONMENTAL
PARAMETERS TO BE MONITORED
§
responsibilities of the ContractorNote 1 , the Supervising
Officer (SO)Note 2, the Supervising Officer’s Representative (SOR)Note
2, Environmental Team (ET)Note 3, the Independent
Environmental Checker (IEC) and Drainage Services Department (DSD)Note 4
with respect to the environmental monitoring and audit requirements during the
course of the Project.
§
project organisation for the Project
§
the basis for, and description of the broad
approach underlying the EM&A programme
§
requirements with respect to the construction
programme schedule and the necessary environmental monitoring and audit
programme to track the varying environmental impact
§
details of the methodologies to be adopted,
including all field, laboratories and analytical procedures, and details on
quality assurance and quality control programme (e.g. calibration of monitoring
equipment)
§
definition of Action and Limit levels
§
establishment of Event and Action plans
§
procedures for environmental complaints handling
§
requirements for reviewing pollution sources and
working procedures required in the event of non-compliance with the environmental
criteria and complaints
§
requirements for presentation of environmental
monitoring and audit data and appropriate reporting procedures
§
requirements for review of EIA predictions and the effectiveness
of the mitigation measures / environmental management systems and the EM&A
programme
Note 1: The
PPSTW Upgrading Works will be procured using a design-build-operation (DBO)
contract form. Under such type of contract, the Contractor is required to
design, build and operate the PPSTW. As such, the Contractor will be the
constructor in the construction stage and will be the PPSTW operator in the
operation stage.
Note 2: The
PPSTW Upgrading Works will be procured using a design-build-operation (DBO)
contract form. Under such type of
contract, the contract administration and site supervision works are to be
undertaken by the Supervising Officer (SO) and the Supervising Officer’s
Representative (SOR), which are equivalent to the roles of the Engineer and the
Engineer’s Representative respectively in traditional form of construction
contracts.
Note 3: The
Environmental Team, i.e. the Team Leader and his supporting staff, will be
employed by the Contractor.
Note 4: The
Employer of the contract will be the Government of HKSAR and DSD will be act on
behalf of the Employer.
Project
Background
expanding the treatment capacity of the existing PPSTW to cope with the increased peak wet weather sewage flow under the ultimate development scenario to cater for the increase in population arising from the planned development in Tuen Mun area;
upgrading the sewage treatment level of the existing PPSTW to incorporate chemical treatment with disinfection at minimum removal rates of 70%, 55% and 99.9% for suspended solids (SS), biochemical oxygen demand (BOD) and E. coli respectively;
upgrading existing septic waste reception facilities at PPSTW; and
providing and upgrading ancillary facilities including the administration building, workshop, laboratory, odour control facilities, sludge handling and dewatering facilities, access roads and minor landscaping works within the STW for the operation and maintenance of the upgraded STW.
Project
Location
Project
Description
Chemically Enhanced Treatment Process (CEPT)
Disinfection by UV irradiation
· ADWF = 230,000 m3/day
· PWWF = 525,000 m3/day (6.08 m3/s)
· Average Influent Loads:
- TSS = 270 mg/l
- BOD = 280 mg/l
- COD = 940 mg/l
- TKN = 47 mg/l
- NH3-N = 22 mg/l
- E. coli = 3 x 107 no/100 ml
Table 1.1 Recommended Effluent Standards for Upgraded PPSTW
Parameters |
Concentrations |
Remarks |
Concentrations |
Remarks |
Sampling Method |
Sampling Frequency |
TSS |
80 mg/L |
average |
120 mg/L |
95%ile |
24-hour Composite |
2 times a week |
BOD5 |
120 mg/L |
average |
180 mg/L |
95%ile |
24-hour Composite |
2 times a week |
E.coli |
20,000 counts/100ml |
geometric mean |
300,000 counts/100ml |
95%ile |
Grab Sample |
3 times a week |
Remarks:
(a) The recommended sampling method and sampling frequency will be
incorporated into the discharged license to be issued by EPD.
Construction Phase
l Air quality (dust) impact monitoring
Operation Phase
l Air quality (odour) impact monitoring
l Water quality impact monitoring (for
emergency discharge)
Construction
Phase
Supervising Officer (SO) and Supervising
Officer’s Representative (SOR)
· Monitor the Contractor’s compliance with contract specifications, including the implementation and operation of the environmental mitigation measures and ensure their effectiveness, and other aspects of the EM&A programme
· Monitor the compliance of the Contractor, the ET and the IEC and ensure that the requirements in the Environmental Permit (EP) and EM&A Manual are fully complied with
· Provide assistance to the ET as necessary in the implementation of the EM&A programme
· Participate in joint site inspection undertaken by the ET and the IEC
· Comply with the agreed Event / Action Plan in the event of any exceedance
· Adhere to the procedures for carrying out complaint investigation
The Contractor
· Work within the scope of the relevant contract and other tender conditions
· Provide assistance to the ET in carrying out monitoring
· Participate in the site inspections undertaken by the ET as required, and undertake any corrective actions
· Provide information / advice to the ET regarding works activities which may contribute, or be continuing to the generation of adverse environmental conditions
· Submit proposals on mitigation measures in case of exceedances of Action and Limit levels in accordance with the Event / Action Plans
· Implement measures to reduce impact where Action and Limit levels are exceeded
· Adhere to the procedures for carrying out complaint investigation
Independent Environmental Checker (IEC)
· Advise the SOR on environmental issues related to the Project, independent from the management of construction works, but empowered to audit the environmental performance of construction
· Provide proactive advice to the SOR and the Employer of the Project on environmental matters.
· Review and audit all aspects of the EM&A programme, including the implementation of environmental mitigation measures, submission relating to the EP and EM&A, and any other submission required under the EP and EM&A Manual
· Review and verify the monitoring data and all submissions relating to or under the EP and EM&A Manual submitted by the ET, including but not limited to the EM&A reports
· Monitor the implementation of the EM&A programme and the overall level of environmental performance being achieved
· Arrange and conduct regular, at least monthly site inspections of the works during construction phase, and ad hoc inspections if significant environmental problems are identified
· Comply with the agreed Event / Action Plan in the event of any exceedance
· Check and ensure the procedures for carrying out complaint investigation being followed and check the effectiveness of corrective measures
· Feedback audit results to ET by signing off relevant EM&A proforma
· Ensure the impact monitoring is conducted at the correct locations at the frequency identified in the EM&A Manual
· Check that the mitigation measures are effectively implemented
· Report the works conducted, the findings, recommendation and improvement of the site inspections, the findings, recommendation, and improvement after reviewing the ET’s and the Contractor’s works, and any advices to the SOR and the Employer of the Project on a monthly basis
Environmental Team (ET)
· Monitor and audit various environmental parameters as required in this EM&A Manual
· Analyse the environmental monitoring and audit data and review the success of EM&A programme to cost-effectively confirm the adequacy of mitigation measures implemented and the validity of the EIA predictions and to identify any adverse environmental impacts arising
· Carry out regular site inspection to investigate and audit the Contractor’s site practice, equipment and work methodologies with respect to pollution control and environmental mitigation, and effect proactive action to pre-empt problems
· Monitor compliance with conditions in the EP, environmental protection, pollution prevention and control regulations and contract specifications
· Audit environmental monitoring data and site environmental conditions
· Report on the environmental monitoring and audit results to EPD, DSD, the SOR, the IEC and Contractor or their delegated representative
· Recommend suitable mitigation measures to the Contractor in the case of exceedance of Action and Limit levels in accordance with the Event and Action Plans
· Liaise with the IEC on all environmental performance matters and timely submit all relevant EM&A proforma for approval by the IEC
· Advise the Contractor on environmental improvement, awareness, enhancement matters, etc., on site
· Adhere to the procedures for carrying out complaint investigation
· Timely submit the EM&A Reports to the EPD, DSD, SOR and IEC.
Operation
Phase
· Monitor various environmental parameters as required in this EM&A Manual
·
Report on the environmental
monitoring results to the Contractor, the SOR, the IEC and DSD
· Analyze monitoring results collected from the monitoring works
· Prepare Water Quality Monitoring Report to provide the water quality impact evaluation results to the Contractor, the SOR, the IEC and DSD
· Prepare Odour Monitoring Report to provide the odour impact evaluation results to the Contractor, the SOR, the IEC and DSD
· Recommend suitable actions to the Contractor, the IEC and the SOR in case of exceedance of any assessment criteria for water quality and odour.
·
Section 2 details
the requirements for impact monitoring for dust during the construction phase
and for odour during the operation phase.
·
Section 3 details
the requirements for baseline and impact monitoring for water quality during
the operation phase.
·
Section 4 details
the audit requirements with regard to waste management issues during the
construction phase.
·
Section 5 details the
requirements with regard to landscape and visual issues.
·
Section 6
describes the scope of environmental auditing and the complaints handling procedure.
·
Section 7 details
the EM&A reporting requirements.