5. landscape and visual
impact
5.5 Construction and
Operation Phase Audit
List of Tables
Table 5.1 Proposed Landscape and Visual Mitigation Measures in
Construction Phase
Table 5.2 Proposed Landscape and Visual Mitigation Measures in Operation
Phase
Appendix
Appendix A Implementation
Schedule of Proposed Mitigation Measures
Baseline Review
l
To check the status of the landscape
resources within, and immediately adjacent to, the works areas
l
To determine whether
amendments in the design of the landscape and visual mitigation measures are
required for those changes
l
To recommend any necessary
amendments to the design of the landscape and visual mitigation measures due to
the above changes, if any.
Design of Landscape
and Visual Mitigation Measures
Landscape and Visual Monitoring
Landscape and Visual Monitoring
Table
5.1 Proposed Landscape and Visual Mitigation Measures in Construction
Phase
ID No. |
Nature / Type |
Landscape and Visual Mitigation Measure |
CM1 |
Design / construction
Planning |
Temporary
Tree Nurseries Temporary
tree nurseries may be set up for the transplanted tree and proposed trees at
an early stage to allow small trees to grow during the construction periods.
By the time when planting area becomes available, trees mature and increase
in trunk & spread size. They will require minimal pruning and suffer much
less damage during transplanting when comparing the travel distance from an
on-site nursery to an off-site nursery. Besides,
these trees may also be positioned as visual mitigation during the
construction period. Potential
site and locations should sought agreement with relevant department in
advance and avoid doubling transplantation procedure.. |
CM2 |
Design / construction
Planning |
No-intrusion
Zone To
maximize protection to existing trees and ground vegetation, construction
contracts may designate “No-intrusion Zone” to various areas within the site
boundary with rigid and durable fencing for each individual no-intrusion
zone. The contractor should close monitor and restrict the site working staff
not to enter the “no-intrusion zone”, even for non-direct construction
activities and storage of equipment. |
CM3 |
Design / construction
Planning |
Hoarding
Hoarding
or boundary fencing for construction shall be considered. It should be
sensitively designed, subtle,
camouflaged and more ‘permeable’ so that they fit into the existing
environment when looking from outside. |
CM5 |
Site Practice |
Dust
and Erosion Control for Exposed Soil Excavation
works and demolition of existing building blocks and which will be highly
visible form surrounding areas should be well planned and with precautions to
suppress dust. Exposed soil shall be covered or ‘camouflaged’ and watered
often. Areas that are expected to be left with bare soil for a long period of
time after excavation shall be properly covered with suitable protective
fabric. Silt and erosion shall be controlled by ground barriers around the
slope cutting area. |
CM6 |
Site Supervision |
Existing
Tree Record Inventory All
retained trees should be record photographically at the commencement of the
Contract, and carefully protected during the construction period. Detailed
tree protection specification shall be allowed and included in the Contract
Specification, which specifying the tree protection requirement, submission
and approval system, and the tree monitoring system. |
CM7 |
Site Practice |
Construction
Light All
security floodlights for construction sites shall be equipped with adjustable
shield, frosted diffusers and reflective covers, and be carefully controlled
to minimize light pollution and night-time glare to nearby residences and GIC
users. The Contractor shall consider other security measures which shall
minimize the visual impacts. |
CM8 |
Design / construction
Planning |
Tree
Transplanting Apart from the 18 numbers of “Leucaena leucocephala”, which are proposed to be felled in accordance with ETWB TCW No.
3/2006, all the affected trees shall be transplanted. Where practicable, trees shall be directly transplanted to
permanent onsite locations. |
CM9 |
Design / construction
Planning |
Tree
Compensation Ratio The
total number of compensatory trees planted in the project area shall not be
less than 1:1 ratios by new trees. Required numbers and locations of
compensatory trees shall be determined and agreed with Government during the
tree felling application process under ETWCTC 3/2006. Compensatory
trees shall be at least heavy standard size to create “immediate” greening
effect. 81 numbers of “Cassia surattensis” will be provided
as the additional compensatory planting for loss of greenery in the area due
to removal of the affected trees. |
CM10 |
Design / construction
Planning |
Re-use of Existing Soil and
Formation of Planting Area in advance Existing topsoil shall be
re-used where possible for new planting areas within the project. Preparation
of planting area and early implementation of the planting works in advance can minimize adverse impact on
trees. The construction program shall consider using the soil removed from
one phase for backfilling another. Suitable storage ground, gathering ground
and mixing ground may be set up on-site as necessary. |
Table 5.2 Proposed Landscape and Visual Mitigation Measures in Operation Phase
ID No. |
Nature / Type |
Landscape and Visual Mitigation Measure |
OM1 |
Site Supervisions |
Establishment
Period 12
month establishment period for the soft landscape works will be allowed in
the main contract. Most construction contracts in |
OM2 |
Design / construction
Planning |
Re-instatement
of excavated Area All
excavated area and disturbed area for utilities diversion, temporary road diversion,
and pipeline woks will be reinstated to former conditions, subject to
applicable Government Standards. |
OM3 |
Design / construction
Planning |
Appearance
and Greening for the proposed structures Compatible
design, construction materials and surface finishes of the proposed structure
should match with the nearby existing external appearance of PPSTW buildings
for achieving visual uniformity.
Finishing materials shall have due consideration to form, basic color,
color/tone variation, micro- and macro-texture, and reflectivity/light
absorbance to avoid glare. Planting,
such as turf, low groundcovers and climbers, may also be planted on top of
these elements to provide greening and aesthetic effect. |